0% found this document useful (0 votes)
412 views2 pages

PMP Formulas Cheat Sheet

Uploaded by

Ravikanth L
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
412 views2 pages

PMP Formulas Cheat Sheet

Uploaded by

Ravikanth L
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

kamal84.4u@gmail.

com 02 Apr 2018

PMP® CAPM® Formulas Cheat Sheet


Earned Value Management
BAC No Formula. Project % Σ𝐸𝑉
𝑋100
No Formula. It is sometimes expressed Complete 𝐵𝐴𝐶
PV as a %age of BAC. ETC = (BAC – EV) / CPI
No Formula. It is sometimes shown as ETC = (BAC – EV)
EV a %age of BAC or PV. ETC ETC = (BAC – EV) / CPIp
AC No Formula. EAC = AC + ETC
SV SV = EV – PV EAC = AC + (BAC – EV)
CV CV = EV – AC EAC = AC + (BAC – EV) / CPI
SPI SPI = EV / PV EAC = BAC / CPI
SPIC SPIC =∑EV / ∑PV EAC EAC = AC + [(BAC – EV) / (CPI * SPI)]
CPI CPI = EV / AC VAC VAC = BAC – EAC
CPIC CPIC = ∑EV / ∑AC TCPI = (BAC – EV) / (BAC – AC)
Budget % Σ𝐴𝐶 TCPI TCPI = (BAC – EV) / (EAC – AC)
𝑋100
Spent 𝐵𝐴𝐶
Estimation
Earned Schedule Management E = (O + P + M) / 3
SVT ES - AT Triangular 𝑃−𝑂 2+ 𝑀−𝑃 𝑀−𝑂
SPIT ES / AT Dist. 𝜎= √
18
PERT E = (O + P + 4*M) / 6
Network Diagram σ = (P – O) / 6
TF = LS – ES Range Est. R = E ± (n * σ)
Activity
2
Total Float TF = LF – EF Var. Var = σ
Free Float FF = ESSuccessor – ESPresent – DurPresent Path Var. VarPath = ∑(Var)
Path St.
𝜎𝑃𝑎𝑡ℎ = √𝑉𝑎𝑟𝑃𝑎𝑡ℎ
Project Selection Methods Deviation
PV = FV / (1 + r)n 1σ = 68.27%
PV / DCF PV = FV * DF 2σ = 95.45%
NPV NPV = ∑PV Sigma 3σ = 99.73%
ROI ROI = Return / Investment Values 4σ - 99.994%
BCR BCR = Benefits / Costs 5σ = 99.99994%
CBR CBR = Costs / Benefits 6σ = 99.999999%
IRR Formula not needed. Higher is better.
PP No formula. Lesser the better. Communication Channels
Opp Cost No formula. C = n*(n – 1) / 2

Expected Monetary Value Procurement


EMVR EMVR = P * I Pt. of Total 𝐶𝑃 − 𝑇𝑃
𝑃𝑇𝐴 = + 𝑇𝐶
EMVP EMVP = ∑EMVR Assumption 𝐵𝑢𝑦𝑒𝑟 ′ 𝑠 𝑆ℎ𝑎𝑟𝑒 𝑅𝑎𝑡𝑖𝑜
Net Benefit Net Benefit = EMVP – Cost
4 Ways to Use this Guide
About PMP® Formulas Pocket Guide Pg. 1 - PMP Formulas
This guide is based on PMBOK® Guide 6th Edition. It Pg. 2 - Abbreviations & brief explnations.
can be used for CAPM® PMP® exam preparation. You can print just Pg.1 or print it as a 2-sided sheet.
The guide has been compiled with great care but it - Fold & carry it in your pocket to memorize
has not been independently verified. You can use it formulas
for reference but it should not replace your primary - Pin it beside your study table for quick reference
study material. The usage of this guide does not - Save it as an image on your PC Desktop
gurantee success in the certification exams. - Save it on your mobile for any time viewing
Copyright 2016-18 Version: 2.0a
https://www.pmbypm.com Release Date: March 28, 2018 1
kamal84.4u@gmail.com 02 Apr 2018

PMP® CAPM® Formulas Cheat Sheet


Earned Value Management
BAC Budget At Completion SPIC Cumulative Schedule Performance Index
PV Planned Value CPI Cost Performance Index
EV Earned Value CPIC Cumulative Cost Performance Index
AC Actual Cost ETC Estimate To Complete
SV Schedule Variance EAC Estimate At Completion
CV Cost Variance VAC Variance At Completion
SPI Schedule Performance Index TCPI To Complete Performance Index

Earned Schedule Management Network Diagram


SVT Schedule Variance (Time) TF Total Float
SPIT Schedule Performance Index (Time) FF Free Float
ES Earned Schedule ES Early Start
AT Actual Time LS Late Start
EF Early Finish
Estimation LF Late Finish
E Expected Value Dur Duration
O Optimistic Value
P Pessimistic Value Project Selection Methods
M Most Likely Value PV Present Value
SD or σ Standard Deviation or Sigma DCF Discounted Cash Flow
Var Variance of an Activity FV Future Value
VarPath Variance of a Network Path r Discount Rate
n Sigma multiplication Factor n Number of years
DF Discount Factor
Expected Monetary Value NPV Net Present Value
EMVR Expected Monetary Value for Risk ROI Return on Investment
P Probability BCR Benefit Cost Ratio
I Impact (Monetary Value) CBR Cost Benefit Ratio
EMVP Expected Monetary Value for Project IRR Internal Rate of Return
PP Payback Period
Procurement Opp. Cost Opportunity Cost
PTA Point of Total Assumption
CP Ceiling Price Communication Channels
TP Target Price C Number of Communication Channels
TC Target Cost n Number of Stakeholders

Follow Us for Certification Exam Tips, Updates, Articles, & latest Discounts/Offers on PMP®
PMbyPM On Facebook PMbyPM On LinkedIn
PMbyPM On Twitter PMbyPM On Google+
PMbyPM On Quora PMbyPM On PMI's projectmanagement.com
PMbyPM On Pinterest PMbyPM On Slideshare
Free PMP Exam Prep Guide http://www.pmbypm.com/how-to-get-pmp-certification/

Copyright
This sheet is compiled by Praveen Malik & is available without any cost. It can be freely downloaded by joining
https://www.linkedin.com/groups/4456858 or by visiting http://payhip.com/b/VQil. You can use it for your own exam
prep but not for any other purpose. Unathorized copying, modification, or distribution is strictly prohibited.

Copyright 2016-18 Version: 2.0a


https://www.pmbypm.com Release Date: March 28, 2018 2