TAREFAS TEMPO
0h 1h 2h 3h 4h 5h 6h
A lllllllllllllllllllllllllll
B lllllllllllllllllllllllllllllllllllllllllllllll
C lllllllllllllllllllllllllllllllllllllllllllllll
D lllllllllllllllllllllllllllllllllllllllllllllll
E lllllllllllllllllllllllllllllllllllllllllllllllllllllllllllll
F lllllllllllllllllllllllllllllll
G lllllllllllllllllllllllllllllllllllllllllllllll
H lllllllllllllllllllllllllllllllllllllllllllllll
CONSTRUÇÃO DIAGRAMA CPM
A Visualização - 2h
B Desmontagem A 3h
C Limpeza B 3h
D Soldagem B 4h
E Usinagem E 4h
F Lubrificação C 2h
G Remontagem D 3h
H Teste G 3h
MÉTODO CPM
2
B D
A 3h 4h F
01 1 4 5
2h C E 2h
3h 4h
3
CAMINHOS CRITICO
1. A – B – D – F – G – H, = 17 HORAS
2. A – C – E – F – G – H, = 17 HORAS
3. A – B – IMAGINANARIA E – F – G – H, = 17 HORAS
G H
5 6 7
3h 3h