Fy = 390 Mpa
Fy = 240 Mpa
d = 400 – 40 – 12 – 8 = 340 mm
Asmin1 =
√ Fc xbxd=
√ 35 x 250 x 340 = 3,223 cm2
4 x Fy 4 x 390
1,4 1,4
Asmin2 = xbxd= x 250 x 340 = 3,051 cm2
Fy 390
e) Tulangan Sengkang
Asmin dari SAP = 0,15 cm2
Tulangan Pakai = 12 mm
As Tulangan = 0,25 x 3,14 x 122 x 2= 2,2608 cm2
As Min SAP 0,15
Jarak = = = 150,72 mm
As Tulangan 2,2608
Digunakan Jarak 150 mm
dt = 340 mm
a 73,7641
= = 0.216
dt 340
atcl
= 0,375 x β = 0,31875
dt
a atcl
Karena < maka (OK)
dt dt
dt = 340 mm
a 73,7641
= = 0.216
dt 340
atcl
= 0,375 x β = 0,31875
dt
a atcl
Karena < maka (OK)
dt dt
dt = 340 mm
a 73,7641
= = 0.216
dt 340
atcl
= 0,375 x β = 0,31875
dt
a atcl
Karena < maka (OK)
dt dt
dt = 340 mm
a 73,7641
= = 0.216
dt 340
atcl
= 0,375 x β = 0,31875
dt
a atcl
Karena < maka (OK)
dt dt
dt = 340 mm
a 73,7641
= = 0.216
dt 340
atcl
= 0,375 x β = 0,31875
dt
a atcl
Karena < maka (OK)
dt dt
Vkiri = -109,816 kN
Vkanan = 107,126 kN
Vkiri = -0.79 kN
Vkanan = -73.493 kN
Fy = 390 Mpa
Fy = 240 Mpa
d = 400 – 40 – 12 – 8 = 340 mm
Asmin1 =
√ Fc x b x d = √ 35 x 250 x 340 = 3,223 cm2
4 x Fy 4 x 390
1,4 1,4
Asmin2 = xbxd= x 250 x 340 = 3,051 cm2
Fy 390
e) Tulangan Sengkang
Asmin dari SAP = 0,15 cm2
Tulangan Pakai = 12 mm
As Tulangan = 0,25 x 3,14 x 122 x 2= 2,2608 cm2
As Min SAP 0,15
Jarak = = = 150,72 mm
As Tulangan 2,2608
Digunakan Jarak 150 mm
2. Detailing SRPMK
dt = 340 mm
a 73,7641
= = 0.216
dt 340
atcl
= 0,375 x β = 0,31875
dt
a atcl
Karena < maka (OK)
dt dt
dt = 340 mm
a 73,7641
= = 0.216
dt 340
atcl
= 0,375 x β = 0,31875
dt
a atcl
Karena < maka (OK)
dt dt
dt = 340 mm
a 73,7641
= = 0.216
dt 340
atcl
= 0,375 x β = 0,31875
dt
a atcl
Karena < maka (OK)
dt dt
dt = 340 mm
a 73,7641
= = 0.216
dt 340
atcl
= 0,375 x β = 0,31875
dt
a atcl
Karena < maka (OK)
dt dt
dt = 340 mm
a 21,0754
= = 0,06198
dt 340
atcl
= 0,375 x β = 0,31875
dt
a atcl
Karena < maka (OK)
dt dt
Vkiri = -73,202 kN
Vkanan = 70,419 kN
Vkiri = -30,976 kN
Vkanan = -30,976 kN
- Struktur Bergoyang ke kanan
Mpr−2+ Mpr −4 201,547+122,9128
Vsway Ka = = = 64,8921 kN
ln 5
Total Reaksi Geser diujung kiri balok
= Vkiri + Vswayka = -30,976 + 64,8921 = 37,3559 kN
Total Rekasi Geser diujung kanan balok
= Vkanan + Vswayka = -30,976 + 64,8921 = 37,3559 kN
Fy = 390 Mpa
Fy = 240 Mpa
d = 300 – 40 – 10 – 8 = 242 mm
1. Menentukan Tulangan Melalu Longitudinal Reinforcing
Asmin1 =
√ Fc x b x d = √ 35 x 250 x 242 = 2,2943 cm2
4 x Fy 4 x 390
1,4 1,4
Asmin2 = xbxd= x 250 x 242 = 2,1717 cm2
Fy 390
e) Tulangan Sengkang
Asmin dari SAP = 0,15 cm2
Tulangan Pakai = 12 mm
As Tulangan = 0,25 x 3,14 x 122 x 2= 2,2608 cm2
As Min SAP 0,15
Jarak = = = 150,72 mm
As Tulangan 2,2608
Digunakan Jarak 150 mm
2. Detailing SRPMK
Kondisi Lokasi Arah Goyang Momen Mu (kN.m)
1 Ujung Kanan (-) Kanan -7,3006
2 Ujung Kiri (-) Kiri -7,1312
3 Ujung Kiri (+) Kanan 3,1579
4 Ujung Kanan (+) Kiri 1,5023
5 Tengah (+) Kanan dan Kiri 12,7541
dt = 242 mm
a 21,075
= = 0,087
dt 242
atcl
= 0,375 x β = 0,31875
dt
a atcl
Karena < maka (OK)
dt dt
dt = 242 mm
a 21,075
= = 0,087
dt 242
atcl
= 0,375 x β = 0,31875
dt
a atcl
Karena < maka (OK)
dt dt
dt = 242 mm
a 21,075
= = 0,087
dt 242
atcl
= 0,375 x β = 0,31875
dt
a atcl
Karena < maka (OK)
dt dt
dt = 242 mm
a 21,075
= = 0,087
dt 242
atcl
= 0,375 x β = 0,31875
dt
a atcl
Karena < maka (OK)
dt dt
dt = 242 mm
a 21,075
= = 0,087
dt 242
atcl
= 0,375 x β = 0,31875
dt
a atcl
Karena < maka (OK)
dt dt
Vkiri = -8,984 kN
Vkanan = 10,525 kN
- Struktur Bergoyang ke kanan
SNI 18.4.2.4 menerangkan bahwa dierlukan hoops disepanjang jarak 2h dari sisi
(muka kolom)
2 x h = 2 x 400 = 800 mm
Dengan pemasangan hoop pertama berjarak 50 mm dari muka kolom