Professional Documents
Culture Documents
5 5 2
4 4 3 0 0 0 0 0 9
9 9 2
2
5
-
O
c
t
-
2
2
2
5
-
A
p
r
-
2
4
CP28-B Design & Build of Infras
Infrastructure and Landscape Works for Huzoom Lusail-Phase 1_R00
2
5
-
O
c
t
-
2
2
2
5
-
A
p
r
-
2
4
General
2
5
-
O
c
t
-
2
2
1
3
-
J
u
n
-
2
3
Design
2
5
-
O
c
t
-
2
2
2
5
-
O
c
t
-
2
2
Schematic Design-Inputs from Client/Authorities
Client/
2
5
-
O
c
t
-
2
2
2
5
-
O
c
t
-
2
2
Wet Utility Network
2
5
-
O
c
t
-
2
2
2
5
-
O
c
t
-
2
2
Dry Utility Network
2
5
-
O
c
t
-
2
2
2
5
-
O
c
t
-
2
2
Road Network
2
5
-
O
c
t
-
2
2
2
5
-
O
c
t
-
2
2
Buildings
7 0 2 2 5 2 9
2
5
-
O
c
t
-
2
2
2
9
-
J
a
n
-
2
3
Detailed Design
2
5
-
O
c
t
-
2
2
2
3
-
N
o
v
-
2
2
Utilities
7
-
N
o
v
-
2
2
8
-
N
o
v
-
2
2
Roads and Paving
3
-
N
o
v
-
2
2
1
4
-
D
e
c
-
2
2
Buildings
1
7
-
N
o
v
-
2
2
2
1
-
N
o
v
-
2
2
Substations
6 1 6 1
2
9
-
N
o
v
-
2
2
2
9
-
J
a
n
-
2
3
Landscape Works
5 8 1 5 7 6 9 0 1 3 5 4 4 6 5 4 6 5 5 4 8 9 9 9 9 7 9 8 8 7 8
3
-
N
o
v
-
2
2
1
6
-
M
a
y
-
2
3
Authority Approvals
3
-
N
o
v
-
2
2
9
-
J
a
n
-
2
3
Utilities and Asphalt Works
9 4 9 8 9 7 5 4 7 9 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
6
-
N
o
v
-
2
2
1
6
-
M
a
y
-
2
3
Buildings- DC1 and DC2
3
0
-
J
a
n
-
2
3
1
5
-
M
a
r
-
2
3
Landscape Works
2
9
-
N
o
v
-
2
2
1
3
-
J
u
n
-
2
3
IFC Drawings
2
9
-
N
o
v
-
2
2
2
2
-
F
e
b
-
2
3
Utilities
2
1
-
D
e
c
-
2
2
2
9
-
M
a
r
-
2
3
Roads and Paving
1
2
-
D
e
c
-
2
2
3
0
-
M
a
y
-
2
3
Buildings and Substations
2
7
-
D
e
c
-
2
2
1
5
-
F
e
b
-
2
3
Substations
1 3
2
2
-
J
a
n
-
2
3
1
3
-
J
u
n
-
2
3
Landscape Works
2
7
-
O
c
t
-
2
2
5
-
N
o
v
-
2
3
Engineering
1
-
N
o
v
-
2
2
2
-
F
e
b
-
2
3
Pre-Qualification
1
-
N
o
v
-
2
2
2
4
-
N
o
v
-
2
2
Trench Excavation
3
-
N
o
v
-
2
2
2
8
-
N
o
v
-
2
2
Geotechnical & Geophysical Survey
6
-
N
o
v
-
2
2
3
0
-
N
o
v
-
2
2
Lab Testing
8
-
N
o
v
-
2
2
1
-
D
e
c
-
2
2
BIM Works
1
0
-
N
o
v
-
2
2
5
-
D
e
c
-
2
2
GSAS Works
1
3
-
N
o
v
-
2
2
7
-
D
e
c
-
2
2
Asphalt Works
1
3
-
N
o
v
-
2
2
7
-
D
e
c
-
2
2
Road Marking Works
1
5
-
N
o
v
-
2
2
8
-
D
e
c
-
2
2
Dewatering Works
1
7
-
N
o
v
-
2
2
1
4
-
D
e
c
-
2
2
Microtunneling
2
3
-
N
o
v
-
2
2
2
1
-
D
e
c
-
2
2
Landscaping Works
2
9
-
N
o
v
-
2
2
2
7
-
D
e
c
-
2
2
Fabric Shades
1
-
D
e
c
-
2
2
2
9
-
D
e
c
-
2
2
GRC Works
4
-
D
e
c
-
2
2
1
-
J
a
n
-
2
3
Metal Works
1
0
-
D
e
c
-
2
2
5
-
J
a
n
-
2
3
Waterproofing
1
5
-
D
e
c
-
2
2
1
2
-
J
a
n
-
2
3
Play & Fitness Equipment
1
9
-
D
e
c
-
2
2
1
5
-
J
a
n
-
2
3
Gypsum Ceiling 2
1
-
D
e
c
-
2
2
1
7
-
J
a
n
-
2
3
LV Network
2
4
-
D
e
c
-
2
2
1
9
-
J
a
n
-
2
3
MV Network
2
6
-
D
e
c
-
2
2
2
2
-
J
a
n
-
2
3
Substation Works
2 2
7 2
7
-
J
a
n
-
2
3
2
-
F
e
b
-
2
3
Traffic Signal Control System
9 6 3 4 8 2 3 6 0 0 7 7 3 0 6 9 3 1 7 4 9 1 8 0 7 9 9 8 9 8 8 8 8 8 0 6 7 8 8 7 4 7 9 9
2
7
-
O
c
t
-
2
2
1
2
-
J
u
n
-
2
3
Material Submittal
1 2 2 2 2 1 3 1 5 1 1 2 2 1 2 3 2 1 1 1 3 2 3 2 2 2 2 2 2 2 2 2 2 3 2 2 2 2 2 3 2 2 2
7 1 2
2
7
-
O
c
t
-
2
2
2
0
-
A
p
r
-
2
3
Utilities
1
-
N
o
v
-
2
2
1
-
J
u
n
-
2
3
Roads and Paving
1
-
N
o
v
-
2
2
1
2
-
J
u
n
-
2
3
Buildings
1
-
N
o
v
-
2
2
2
8
-
N
o
v
-
2
2
Enabling Works
0 8 2 6
1
-
N
o
v
-
2
2
2
1
-
M
a
y
-
2
3
Landscape
5
-
D
e
c
-
2
2
5
-
J
u
n
-
2
3
Authority Approvals (Kahramaa)
1
5
-
D
e
c
-
2
2
5
-
N
o
v
-
2
3
Shop Drawing
1
5
-
D
e
c
-
2
2
2
3
-
M
a
y
-
2
3
Utilities
2
0
-
A
p
r
-
2
3
8
-
J
u
n
-
2
3
Roads and Paving
5 4 3 0 8 1 0 0 2 3 0 0
2
4
-
J
a
n
-
2
3
2
9
-
J
u
n
-
2
3
Substations
3
1
-
J
a
n
-
2
3
2
6
-
J
u
n
-
2
3
Utility Hub Substation
7
-
J
a
n
-
2
3
2
7
-
A
u
g
-
2
3
Terminal Sewage Pumping Station
7
-
J
a
n
-
2
3
2
5
-
J
u
l
-
2
3
Potable and Fire Water Pumping Station
Sta
1
4
-
J
a
n
-
2
3
1
8
-
J
u
l
-
2
3
TSE Tank and Pumping Station
2
5
-
D
e
c
-
2
2
3
1
-
J
u
l
-
2
3
Potable Water Reservoir
7
-
J
a
n
-
2
3
5
-
N
o
v
-
2
3
Storm Water Attenuation Tanks
2
8
-
J
a
n
-
2
3
1
6
-
A
u
g
-
2
3
Chlorination Room
8
-
F
e
b
-
2
3
1
4
-
J
u
n
-
2
3
Guard Room
1
0
-
J
a
n
-
2
3
2
3
-
M
a
y
-
2
3
Foul Water Lift Station
8
-
M
a
y
-
2
3
2
4
-
A
u
g
-
2
3
Landscape
1
-
N
o
v
-
2
2
2
8
-
A
u
g
-
2
3
Method Statement
1
-
N
o
v
-
2
2
2
8
-
N
o
v
-
2
2
Mobilization of Temporary Site Facilities
Facili
2
6
-
N
o
v
-
2
2
2
5
-
D
e
c
-
2
2
Trial Pits Excavation
1
0
-
D
e
c
-
2
2
5
-
J
a
n
-
2
3
Dewatering Works
1
2
-
D
e
c
-
2
2
9
-
J
a
n
-
2
3
Survey Works
1
4
-
D
e
c
-
2
2
1
1
-
J
a
n
-
2
3
Night Works
1
9
-
D
e
c
-
2
2
1
5
-
J
a
n
-
2
3
Micro-Tunneling
2
8
-
N
o
v
-
2
2
2
6
-
D
e
c
-
2
2
Remaining Works at Tree Nursery A
Area
2
1
-
D
e
c
-
2
2
1
7
-
J
a
n
-
2
3
Foul Water Network
2
1
-
D
e
c
-
2
2
1
7
-
J
a
n
-
2
3
Storm Water Network
4
-
J
a
n
-
2
3
3
1
-
J
a
n
-
2
3
Potable Water Network
2
-
J
a
n
-
2
3
2
9
-
J
a
n
-
2
3
TSE/Irrigation Network
2
7
-
D
e
c
-
2
2
2
3
-
J
a
n
-
2
3
Polymer Concrete Manhole
2
1
-
J
a
n
-
2
3
1
9
-
F
e
b
-
2
3
MV/LV Network
8
-
J
a
n
-
2
3
2
-
F
e
b
-
2
3
Telecom Network
4
-
F
e
b
-
2
3
2
-
M
a
r
-
2
3
ELV/MOI-SSD Network
2
-
J
a
n
-
2
3
2
9
-
J
a
n
-
2
3
Anti-Termite Treatment
4
-
J
a
n
-
2
3
3
1
-
J
a
n
-
2
3
Concrete Works
4
-
M
a
r
-
2
3
3
0
-
M
a
r
-
2
3
Wall, Floor and Ceiling Works
1
-
A
p
r
-
2
3
4
-
M
a
y
-
2
3
GRC Works
6
-
M
a
y
-
2
3
1
-
J
u
n
-
2
3
Doors and Windows 1
8
-
J
a
n
-
2
3
1
5
-
F
e
b
-
2
3
Waterproofing Works
1
-
F
e
b
-
2
3
1
-
M
a
r
-
2
3
Asphalt Works
Page 3 of 5
3 3 3 3 3 3 3 3 3 3 3 4 4 4 3 3 3 3 3 3 3 3 3 3 3 3 3 3
2 2 3 2 2 3 2 2 2 3 2 2 3 3 3 3 3 2 3 3 3 3 2 2 2 2 2 2 2 2 3 2 3 3 2 2 2 2 2 3 2 2 2 3 2
- -
r 2 - - 2 - - - 2 - - 2 2 2 2 2 -
r 2 2 2 2 - - - - - - - - 2 -
v 2 2 -
v - - - - 2 -
v -
v -
v 2 -
n a -
l g r - p p p - n r - - - - - a - - - - p b n n c c c c - - - c c c t - - c
u u u p v e e e p u p g p n n v v t t t e e a a e e e e c o c c o e e e c c o o o c e
J M J A A o S S S e J A u e o M o c c c S F J J D D D D e N e e N D D D O e N N N e D
- - - - - N - - - S - - A S a
J a
J N - N O O O - - - - - - - - D - D D - - - - - D - - - D -
Finish
9 9 1 8 0 - 7 7 5 - 8 0 - - - - - 6 - - - - 1 3 5 5 3 6 7 2 - 7 - - 5 3 0 6 5 - 9 5 0 - 9
2 2 3 2 1 3 2 2 2 1 2 3 5 1 9 9 3 2 3 5 6 6 2 1 1 1 1 1 1 1 5 2 3 9 2 1 2 2 2 6 1 2 3 6 1
CP28B – Design and Build of Infrastructure and
Landscape Works for Huzoom Lusail – Phase 1
3 3 3 2 2 2 2 3 3 2 2 2 2 2 2 2 2 3 2 2 2 2 2 2 2 2 3 3 3 3 3 3 3 3 3 3 3 3
3 2 3 2 2 2 2 2 2 3 3 3 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 3 2 3 2 2 2 2 2 2 2 2
2 - - 2 2 2 2 2 - - - - - - 2 - - - - - - - 2 2 2 2 2
Actual Start
- - 2
- - r - - - v - - - - - v v v v v v - - - t t v v - c c c - - - - - - - - - - - - - -
r
7 8 8 8 8 6 2 2 0 3 7 2 4 1 4 1 1 1 7 7 7 4 2 1 0 0 8 7 5 5 7 8 8 8 2 6 4 5 5 5 7
2 2 2 2 2 3 3 3 3 2 1 8 1 9 4 4 3 1 3 3 3 3 1 4 3 3 3 3 3 3 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Milestone
summary
Critical Remaining Work
Activity Name
Remaining Work
Installation of Traffic Signs and Gantry
Gant
Landscaping - Hardscape Works
Landscaping - Softscape Works
Road S10-R27A
Road S10-R28A
Road S8-R25A
Road S9-R26A
Road S20-R9A
Road S21-R10
Road S24-R12
Road S25-R13
Road S10-R57
Road Markings
Road S23-R11
Asphalt Paving
Enabling Works
Road S7-R8A
Road S9-R58
Road S4-R59
Construction
Procurement
Road S5-R6
Road S4-R5
Road S3-R3
Road S4-R4
Road S2-R2
Road S6-R7
Traffic Signs
Wet Utilities
Actual Work
Dry Utilities
Hardscape
Landscape
Softscape
Buildings
Finishes
Zone 1A
Utilities
Utilities
MEP
Civil
Activity ID
S O N D J FM A M J J A S O N D J F M A M J J
2024
2023
Page 4 of 5
3 4 3 3 3 3 3 3 3 3 3 4 3 3 3 3 3 3 3 3 3 3 3 3 4 3 3 3 3 3 3 3 3 3 3 3
2 2 4 2 2 2 2 4 2 2 2 2 2 2 2 2 2 2 3 2 2 3 3 2 2 2 2 2 2 3 2 2 2 3 2 2 2 2 2 2 2 3 3 2 2
- - 2 - - - - 2 - - -
v -
v - - - - -
v - 2 - - 2 2 - -
v -
v -
v -
v - 2 - - -
v 2 - -
v -
v -
v - - - 2 2 - -
c n - c c c c - t t c n c c c - c t - -
v c c -
v n c - c c t c - - t t
e a n e e e e n c c o o e a e e o e c e c c e o o o o e a e o c e o o o e c e c c c c
D J D D D D O O N N D J D D N D e D O e o D N N N N D o J D N e D N N N D O D e e O O
- - a
J - - - - a
J - - - - - - - - - - D - - D N - - - - - - N - - - D - - - - - - - D D - -
Finish
5 5 - 7 4 3 7 - 1 1 1 6 4 1 1 0 5 1 - 3 1 - - 0 0 9 5 0 7 - 1 3 7 - 0 6 9 2 3 6 1 - - 5 5
2 1 2 1 1 2 1 2 3 3 1 1 2 1 1 1 2 1 7 1 1 7 8 2 2 1 2 3 1 4 1 1 2 3 1 2 2 2 1 2 1 7 4 2 2
CP28B – Design and Build of Infrastructure and
Landscape Works for Huzoom Lusail – Phase 1
3 3 2 2 2 2 2 2 2 3 3 3 3 2 2 2 2 2 2 2 2 2 2 3 3 3 3 3 3 2 2 2 2 2 2 2 2 2 2 2 2 2 2
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 3 3 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
2 - - - - - - - - - - - - - 2 2 2 2 - - - - - - - - -
Actual Start
- - v v v - c c c - - - - t t - v v - - c c c - - - - - - - - t t t - - - - v v v - c c c
b b
6 4 4 2 2 2 1 2 6 4 5 5 7 7 4 3 1 1 1 1 5 0 7 9 6 5 5 5 6 1 3 4 3 3 3 2 2 1 3 9 2 0 9 5 5
2 2 3 3 3 3 3 3 2 2 2 2 2 3 3 3 3 3 3 3 2 3 2 2 2 2 2 2 2 2 2 3 3 3 3 3 3 3 3 2 3 3 2 2 2
Milestone
summary
Critical Remaining Work
Activity Name
Remaining Work
Actual Level of Effort
Road S12-R32A
Road S31-R39B
Road S30-R39A
Road S11-R30A
Road S11-R31A
Road M2-R29A
Road S27-R21
Road S29-R23
Road S28-R22
Road S26-R14
Road S13-R17
Road S14-R18
Road S15-R16
Road S16-R19
Road S26-R36
Road S27-R37
Road S19-R35
Road S17-R33
Road S18-R34
Road S33-R40
Road S28-R38
Road S43-R55
Road S36-R43
Road S39-R47
Road S40-R48
Road S40-R49
Road S38-R46
Road S46-R50
Road S38-R45
Road S47-R51
Road S33-R54
Road S40-R63
Road S36-R61
Road S50-R52
Road S37-R44
Road S11-R60
Nursery Area
Nursery Area
Road M1-R20
Road S1-R24
Road S1-R15
Road S1-R1
Actual Work
Zone 1B
Zone 1C
Zone 1D
Activity ID
S O N D J FM A M J J A S O N D J F M A M J J
2024
2023
Page 5 of 5
3 3 3 4 3 4 3 4 3 4 3 3 3 3 4 4 3 3 3 4 4 4 4 4 4 4 4 4
3 2 2 2 2 2 3 2 2 2 2 2 3 2 3 2 2 2 3 2 2 2 2 2 2 4 2 4 2 2 2 2 2 2 2 4
2 -
v -
v -
v - - 2 - - - - - 2 - 2 - - - 2 - - - - - - 2 - 2 - - - - - - - 2
- o o o b c - b c n c n - r - r c c - n n c c c r - n - n n r r r r r -
r
c e e c e e a e a c p r p e e c a a e e e p b a b a a p p p p p a
e N N N F D e F D J D J e A p A D D e J J D D D A e J e J J A A A A A
D - - - - - D - - - - - D - A - - - D - - - - - - F - F - - - - - - - M
Finish
- 3 5 9 3 0 - 3 1 0 0 0 - 7 - 7 3 3 - 6 6 3 7 7 5 - 8 - 6 6 5 5 4 4 4 -
2 2 2 2 1 3 7 1 1 1 1 1 5 1 9 1 2 2 9 1 1 2 2 2 2 6 1 6 1 1 2 2 2 2 2 7
CP28B – Design and Build of Infrastructure and
Landscape Works for Huzoom Lusail – Phase 1
3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 4 4
2 2 2 2 2 2 2 2 2 3 3 2 2 2 2 2 2 2 3 2 3 3 3 2 2 2 2 2 2 2 2 2 2 2 2
- - - - 2 2 2 2 2 2 2 - - - - -
Actual Start
- - - - y - y y y - - - - - - - - - - - - - - - - - - - - t t t t c - -
n r r r b r b n l l l
7 5 5 5 6 7 6 6 7 6 3 9 0 1 4 6 5 4 4 9 8 6 7 7 7 9 1 9 3 7 8 7 8 1 9 6
2 2 2 2 2 1 1 2 1 3 3 2 3 4 3 3 2 2 2 1 1 1 1 1 2 1 1 1 3 7 1 1 1 1 9 3
Milestone
summary
Over
Remaining Work
Testing, Commissioning and Handing
Ha
Utility Hub Buildings and Substation
Storm Water Attenuation Tanks
Handover Documents
Enabling Works
Roads Works
Handing Over
Road Works
Road Works
Actual Work
Substations
Landscape
Landscape
Landscape
Buildings
Buildings
Buildings
Zone 1A
Zone 1B
Zone 1C
Zone 1D
Zone 1A
Zone 1C
Zone 1A
Zone 1B
Zone 1C
Zone 1D
Utilities
Utilities
Activity ID