Government of Odisha
Housing & Urban Development Department
3rd floor, Kharavel Bhavan, Unit-V, Bhubaneswar, PIN:751001
Letter No. HUD-UT-SCH-0003-2022/ 60 36? jHup, Bhubaneswar, Dated.
Sub: Accordance of Administrative Approval (2°4 Stage) for “In-situ up-gradation
of Bus Terminal at Jagatsingpur Municipality “as Model Bus Stand in the
District Headquarter ULB of Jagatsingpur District.
ORDER: Administrative Approval of the Governor is hereby accorded to the
work, “In-situ Development of Municipal Bus Stand at Jagatsinghpur" as in-situ
development of existing bus stand in the District Headquarter ULB of
Jagatsingpur district at an estimated cost of Rs-1594.15 lakh (Rupees fifteen e Crore
ninety four Lakh and fifteen thousand) only inclusive of Contingency, Consultancy
Charges and GST etc., as detailed below:
sl. Description of works Amount in Rs.
A_ | Building Works
I Civil Work
i) | Bus Bay “Rs.2,10,89,069.66
ii) | Terminal Building -A Rs.1,18,08,158.93.
iii) | Terminal Building -B
Rs.1,18,08,158.93,
iv) | Terminal Building -C
Rs.1,18,08,158.93
Total (I) Rs.5,65,13,546.45
1 Internal PH Works@10% of Civil Work Rs .56,51,354.65
I | External PH Works @5% of Civil Work including | Rs.28,25,677.32
source
IV_| Internal Electrical Work Rs.60,07,250.00
v External Electrical Work Rs.17,53,605.70
Sub Total (A) Rs.7,27,51,434.12
B Other Specialized Items & Servicei) _| Site Grading Work
ii) | Parking Facilities
iii) | Security Guard Room & Building, Rs.29,00,000.00
iv) | Post Tensioning roofing arrangement Rs.60,00,000.00
v) _ | Boundary wall, Landscaping & Sculpture Rs.56,00,000.00
vi) | Internal road & Pathways & Internal Drain Rs.49,75,000.00
Vii) _| Fire Protection & Detection Work Rs.38,52,630.00
Vii) | HVAC, Diesel Generator, CCTV System, wich, | Rs.2,80,83,308.00
Boom Barrier, lift STP, Specialised Landscaping
lighting ete
Total = B Rs.5,84,10,938,00
C_ | Total= (A+B) Rs.13,11,62,372.12
‘Add consultancy Charges @ 1.5% on Total C Rs.19,67,435.58
E | Add Quality Control @0.5% on civil work on | Rs.6,55,811.86
Total C
F | Add contingencies @1% on Total C Rs.13,11,623.72
G_| Sub Total Rs.13,50,97,243.28
Add GST @18% on Total G Rs.2,43,17,503.79
Grand Total Rs.15,94,14,747.07
Rs.15,94,15,000.00
Or Say Rs.1594.15 lakh
1. The charge is debitable to Demand No.13 - 2217-Urban Development -
Programme Expenditure-State Sector Scheme-State Sector-05-Other UD
Scheme-051-(Construction)/ 789-SCP for SC/ 796:TASP — -3256-Urban
Transformation Initiative(UNNATI)-22028-Infrastructure Development-908-
Grants for Creation of Capital Assets(Voted) .
2. Funds would be released in two equal installments @50% each of the project
cost approved herewith. 50% of the approved Project Cost towards Fig
installment shall be released after accordance of Administrative Approval and
the balance 30% towards 2" installment would be released on receipt of the
Utilization Certificate towards at least 70% of Ist installment of funds in
proper format of OGER along with a report on progress of the work.
3, Since the required fund is decided to be met out of UNNATI, funds would be
sanctioned & released in favour of the concerned ULBs through a separate
UNNATI Account as grant which would subsequently be transferred to the
Executing Agency of R & B ie Local Executive Engineer of R & B Division
within 7 days of receipt of fund by the Executive Officer, Jagatsinghpur
Municipality. Hence, Executive Officer, Jagatsinghpur Municipality would
take immediate step to provide the Bank Account Details soon after the A/A
is accorded for the work, in order to release the 1st instalment.
4, Except passenger amenities no shopping/market complex is allowed under
the scheme5, District Collector, Jagatsinghpur need to take periodical review of the
construction activities of the Model Bus Terminal, in order to complete the
same in scheduled time and to avoid Cost & Time overrun.
6. The District Collector to take appropriate decision and pass necessary orders
50 that the bus terminal to be developed by the H&UD Department need to be
under the possession of the ULB concerned for Operation & Maintenance
(O&M) as a Civic Facility.
7. The Principal AG. (A & E), Odisha and Senior D.A.G.(Works),Odisha are
being informed,
8, The DPR with Plan & Cost Estimates (In Original) is returned herewith for
further action by the Executing Agency. ;
Seton Dbewratl
aut
F.A-cum-Additional Secretary to Government
Memo No. YO3sY /HUD., Date. OL 1A ROLL
Copy forwarded to the Principal A.G. (A & E), Odisha / Senior D.A.G
(Works), Odisha, Puri/ R.D.C(Central Division), Cuttack for information and
necessary action. c w
F.A-cum-Additional Seététary to Government
MemoNo_ 20255 /HUD, Dated 02: 12" 2022
Copy forwarded to the Principal Secretary to Govt., Commerce & Transport
(Transport) Department/ Principal Secretary to Govt, Works Department for kind
information. oe ,
. J
F.A-cum-Additional aes to Government
Memo No. d03G6 /HUD., Dated 02-12-2022
Copy forwarded to PS to Principal Secretary to Govt., H & UD Department
for kind information. Cae
F.A-cum-Additional Betis Government
MemoNo.202¢F /HUD., Dated 02 12. JO2D
Copy forwarded to PS to Special Secretary to Govt (UT)., H&UD Department /
CE-cum-Additional Secretary to Government, H & UD Department/FA-cum-
‘Additional Secretary to Government, H & UD Department _for-kind information.
F.A-cum-Additional Secretary to/ Government
Memo No._2036% /HUD, Dated O 212.2022
Copy forwarded to the Collector & D.M Jagatsinghpur for kind information.
F-A-cum-Additional Secretahy/t5 Government
Memo No._g)03E4 /HUD, Dated 6212 - 2022
Copy forwarded to the OSD (Buildings), Odisha, Bhubaneswar, Office of the
Engineer-in-Chief (Civil), Odisha, Nirmana Soudha, Unit-V, Bhubaneswar forinformation.
He is requested to go ahead with execution of the work as per the
Administrative Approval accorded herewith. The DPR with Plan & Cost Estimates
(In Original) is returned herewith for further action at his end
Ca se
F.A-cum-Additional eatetUeaieinment
Memo No._2D.3GQ /HUD., Date. 02:12. 2022
Copy forwarded to the Chief Construction Engineer, Cuttack (R é& B) Circle,
Cuttack/ Superintending Engineer, Jagatsinghpur(R & B) Division, Jagatsinghpur
for information & necessary action. ener
as ai at
F.A-cum-Additional Secretary to Government
Memo No. 2026} /HUD., Date. O2- 12-2022,
Copy forwarded to Executive Officer, Jagatsinghpur Municipality for
information & necessary action.
He/She is requested to submiit the Bank Account details immediately for
release of funds by H & UD Department ic eee:
242
F.A-cum-Additional Sectetary to Government
Memo No._2.0. 36 2,/HUD., Date. 02+ (2: 2022
Copy forwarded to Fund Section/ Budget Section / Finance Section/ Audit
Section for information ahd necessary action. ;
a SHidfra
F.A-cum-Additional Secretary to Government