You are on page 1of 420

 

PATWADH GOV DETAIL PROJECT REPORT    


REV.NO. DESCRIPTION DATE CHECKED APPROVED

DETAIL PROJECT REPORT

NCC LIMITED, HYDERABAD

Construction of Patwdh group of Villages Water Supply Scheme, District - Sonbhadra


Project

PMC
Consultants CEINSYS TECH LTD.

Executive Director,

Client State Water & Sanitation Mission


U.P. Jal Nigam Compound Rana Pratap Marg, Lucknow - 226001

DETAIL PROJECT REPORT@55LPCD


DOCUMENT
Rev. No. 0 Date: 15/12/2021
NO.

This Document is the Property of NCC Limited and must not be passed Prepared By
on to any person or body not authorized by us to receive it nor be copied Reviewed By
or otherwise made use either in full or in part by such person or body
Approved By
without our prior permission in writing.

  1 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

1. PROJECTBACKGROUND ……………………………………………………………
NEED OF THE PROJECT ………………..……………………………………………………
OBJECTIVE OF THE.………………………………………………………………………...
SCOPE OF WORK ………………….…………………………………………………………
BENEFIT OF PROJECT ……………………………………………………………………….
ABOUT STATE WATER AND SANITATION MISSION……………………………………
2. PROJECT AT A GLANCE ……………………………………………………………
Introduction to Sonbhadra District ……………………………………………………………….
History …………………………………………………………………………………………..
Location and Geographical Area ………………………………………………………………..
Accessibility …………………………………………………………………………………….
Demography …………………………………………………………………………………….
Topography …………………………….………………………………………………………..
Climate and Rainfall...…………………………………………………………………………...
Geography …………………………..…………………………………………………………..
Land use in Sonbhadra District……………………………………………………………………
3. ADMINISTRATIVE SETUP……………………………………………………………
Tehsil in Sonbhadra District ………………………………………………………………………
Blocks in Sonbhadra District ………………………………………………………………………
INTRODUCTION TO PROJECT AREA …….. ………………………………………………
Location of the Project Area ……………………………………………. ……………………...
4. EXECUTIVE SUMMARY……………………………………………………………..
OBJECTIVE …………………………………………………………………………………..
Proposed Water Supply Scheme Components………………………………………………….
Source of Water Supply Scheme …..……………………………………………………………
Raw Water Intake Arrangement………………………… ……………………………………..
Raw Water pumping machinery ……….………………………………………………………
Raw water rising main ..………………………………………………………………………..
Water Treatment Plant ……………………….………………………………………………….
Clear water pumping machinery…………………………………………………………………
Clear water transmission ……..…………………………………………………………………

  2 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Elevated Service reservoirs…….…………………………………………………………………
Proposed Distribution Network…………………………………………………………………
FITTING AND APPURTENANT WORKS ……………………………………………………
BOUNDARY WALL …………………………………………………………………………...
HOUSE SERVICE CONNECTION ……………………………………………………………
STAND POST …………………………………………………………………………………..
LAND ACQUISITION …………………………………………………………………………
8. Operation & Maintenance ……………………………………………………………
NEED FOR O&M……………………………………………………………………………….
OPERATION AND MAINTENANCE PLAN ………………………………………………..
COMMON FEATURES OF OPERATION AND MAINTENANCE ………………………..
Availability of Detailed Plans, Drawing, O&M Manual …………………………………….
Schedule of Daily Operation ………………………………………………………………….
Schedule of Inspection of Machinery ………………………………………………………..
Records ………………………………………………………………………………………...
Records of Key Activities of O&M …………………………………………………………..
Staff Positions …………………………………………………………………………………
Inventory of Stores ……………………………………………………………………………
O&M OF INDIVIDUAL COMPONENTS ……………………………………………………
Maintenance of Intakes (Intake Tower) ………………………………………………………
Maintenance of Pumps & Pumping Machinery ………………………………………………
DUTIES OF PUMP OPERATOR & MAINTENANCE OF RECORDS ……………………...
Log Book ………………………………………………………………………………………..
Complaint Register ……………………………………………………………………………..
Movement Register …………………………………………………………………………….
Meeting Register with Corporation ……………………………………………………………
MAINTENANCE OF WATER TREATMENT PLANT ……………………………………..
Preventive Maintenance for Cleaning …………………………………………………………
Chlorination Register …………………………………………………………………………..
Maintenance of Pumping Main ……………………………………………………………….
MAINTENANCE OF OVERHEAD TANK (STORAGE RESERVOIR) ……………………
CLEANING OPERATION ……………………………………………………………………
SAFETY PRECAUTIONS
MAINTENANCE OF DISTRIBUTION SYSTEM

  3 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Preventive maintenance Schedule ………………………………………………………………
Leakage Control …………………………………………………………………………………
Cross Connections……………………………………………………………………………….
PLUMBING PRACTICES FOR DRINKING WATER SUPPLY
QUALITY OF PIPE MATERIAL FOR HOUSE CONNECTION
CONTAMINATION THROUGH HOUSE CONNECTION
RULES FOR CONSUMER CONNECTIONS
CHLORINE RESIDUAL TESTING AT CONSUMER END
WATER QUALITY
CHEMICAL AND BACTERIOLOGICAL EXAMINATION OF SOURCE
CONSUMER GRIEVANCES REDRESSAL PLAN
Complaint Communication ……………………………………………………………………
Redressal System
Remedial Measures for improving Efficiencies ……………………………………………..
Public Awareness and Participation ……………………………………………………….....
Water Saving Techniques …………………………………………………………………….
REDUCTION IN NON REVENUE WATER (NRW)
OPERATING RECOMMENDATIONS
DAILY MAINTENANCE
ROUTINE OBSERVATIONS OF IRREGULARITIES
OVERHAUL A PUMP
TOOLS AND TESTING EQUIMPMENTS
9. Cost Abstract ……………………………………………………………………….

  4 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

ABBREVIATIONS
AC Asbestos Cement
BHP Brake Horse Power
CI Cast Iron
CWTM Clear Water Transmission Main
CWRM Clear Water Rising Main
CPHEEO Central Public health Engineering and Environmental Organization
DI Ductile Iron
DMA District Metering Area
ESR Elevated Service Reservoir
DPR Detailed Project Report
GI Galvanised Iron
GIS Geographic Information system
GP Gram Panchayat
GSR Ground Service Reservoir
HDPE High Density Polyethylene
HM Hydraulic Model
HP Horse Power
IIT Indian Institute of Technology
LPCD Liter Per Capita Per Day
LPM Liter per minute
LPS Liter per second
LSL Low Sump Level
MCFT Million cubic feet
ML Million Liter
MLD Million Liters Per Day
Mm3 Million Cubic Meter
MoUD Ministry of Urban Development
NRW Non-Revenue Water
NH National Highway
O&M Operation and Maintenance
PFR Pre-feasibility Report
PW Pure Water
PWD Public Works Department
RFP Request for Proposal
RWTM Raw Water Transmission Main
RWRM Raw Water Rising Main
SWSM UP State Water & Sanitation Mission, Uttar Pradesh
TOD Time of Day
TOR Terms of Reference
TS Technical Sanction
UA Urban Agglomerates
  5 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
UPJN Uttar Pradesh Jal Nigam
VT Vertical Turbine
VWSC Village Water and Sanitation committee
WTP Water Treatment Plant
WHO World Health Organization
WSSO Water and Sanitation Support Organization

  6 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

1. PROJECT BACKGROUND
1.1 NEED OF THE PROJECT

As per Government of India strategic plan (2011‐2022), the 90% of the rural population in the country has 
benefited with the pipe water supply. However as on date approximately only 19% rural population of Uttar 
Pradesh  is  covered  with  Pipe  Water  Supply  Schemes  in  water  scarce  areas  of  Bundelkhand  and  Vindhya 
region and Arsenic, Fluoride and AES/JE affected areas in the state, under the direction of Executive Director 
of  State  Water  and  Sanitation  Mission  (SWSM)  appointed  a  consultant  to  provide  Consultancy  Services  to 
State  Water  and  Sanitation  Mission,  Department  of  Rural  Development,  GOUP  for  planning,  designing  and 
DPR  Preparation  of  drinking  water  supply  schemes  in  Bundelkhand,  Vindhya  Region  and  Arsenic/  Fluoride 
and AES/JE affected areas of state of Uttar Pradesh. 

1.2 OBJECTIVE OF THE PROJECT

The objective of the project is planning and designing of a methodical and efficient water supply scheme for 
the villages of Roberts Ganj & Ghorawal and Chopan block of Sonbhadra District. The project objective is the 
coverage of the entire block by precisely planning and hydraulic designing for the water supply system and 
selection of a sustainable source. It aims to provide tapped water to every household at the rate of 55 LPCD 
up to its ultimate design stage at an equitable and optimum cost. 

SMEC  LTD  has  appointed  as  a  consultant  for  Sonbhadra  District  in  Vindhya  region  and  vide  letter  1708/W‐
409/2018‐2019 dated 01.01.2019  to SMEC  & Contract agreement signed on 5th Jan 2019)". As per the direction of 
SWSM  the  objective  of  the  assignment  is  to  provide  consultancy  Services  to  State  Water  and  Sanitation 
Mission,  Department  of  Rural  Development,  GOUP  for  planning,  designing  and  preparation  of  DPRs  of 
drinking water supply schemes (Pipe water supply ) in Jhansi district of Bundelkhand, Sonbhadra district of 
Vindhya Region of Uttar Pradesh. 

1.3 SCOPE OF WORK

The  scope  of  the  project  included  the  coverage  of  villages  of  the  block  to  100%  piped  water  supply.  The 
primary  objective  is  to  identify  a  sustainable  and  suitable  source  of  raw  water  which  shall  assure  the 
availability of water up to the ultimate stage of the proposed scheme. 

Other major contents of the report include the topographical and geographical details as mentioned earlier 
which include the village boundaries of the block on the GIS based map. The population projected in a span 
of 15 and 30 years according to the design stages of the project with are the immediate, intermediate and 
ultimate  design  stages.  An  optimum  hydraulic  design  shall  be  done  after  appropriate  projection  of  the 
population and exact estimation of the water demand for the water supply scheme of the block. The entire 
designed  water  supply  scheme  represented  in  the  form  of  a  flow  diagram,  index  map  and  key  plan.  The 
designed scheme analysed for its cost estimation and rough cost estimation attached in a way that there is 
minimum variation. The per capita cost of the project then evaluated with respect to the base, intermediate 
and  ultimate  stage  of  the  project.  The  overall  cost  of  the  project  includes  the  cost  of  operation  and 
maintenance which shall get incurred year on up till the ultimate design stage of the proposed water supply 
scheme. 

  7 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
1.4 BENEFIT OF PROJECT

Proposed water supply scheme for Roberts Ganj & Ghorawal and Chopan Block will have several benefits like 
increase in revenue of the block, improved water quality leading improved health, sufficient water quantity, 
rising  employment,  rising  employment,  rising  living  standards  of  the  people,  etc.  Some  of  the  benefits  are 
briefed below. The fore most benefit of the water supply system is that there will be access to tapped water 
to the people of the villages of the Roberts Ganj & Ghorawal and Chopan block. The coverage of water supply 
will increase the living standard of the people. The quality and quantity of the water supply will improve as 
scheme will be designed for 55 LPCD and all the underground sources shall be proposed to be discarded. The 
main benefit will be reduction of water borne diseases due to contaminated water supply. Children are most 
vulnerable  to  the  preventable  diseases  which  result  from  lack  of  clear  water.  Coverage  of  water  supply  is 
targeted  to  be  100%.  Block  level  governance  will  also  be  improved  through  the  proposed  water  supply 
scheme. Proposed water supply scheme will also be improved through the proposed water supply scheme. 
Proposed  water  supply  scheme  will  increase  growth  opportunities  thereby  help  in  increasing  employment 
among the villagers. 

1.5 ABOUT STATE WATER AND SANITATION MISSION

The  Government  of  India  launched  reform  initiatives  in  the  rural  water  and  sanitation  sector  in  1999  by 
introducing a high esteemed State Water Sanitation Mission. The Mission has the overall goal to improve the 
quality of the life by enhancing access to better water supply & sanitation facilities in the rural areas ensuring 
sustainability.  In  this  regard,  “State  Misson”  (State  Water  &  Sanitation  Mission)  has  been  constituted  and 
established  in  Rural  Development  Department,  Government  of  Uttar  Pradesh,  for  providing  overall  policy 
guidance for community led and participatory projects. 

Uttar Pradesh  is the  4th largest state of our  country  with the area of 294411  Square Kilometers. There are 


112804 inhabited villages & 822 blocks in 75 districts. To provide access to safe drinking water and sanitation 
facility to a population of approximately 195989768 (2010), is a big challenge/task, especially in rural areas of 
our  State.  To  support  the  existing  State  rural  water  supply  and  sanitation  agencies,  Water  and  Sanitation 
Support Organization, UP (WSSO, UP) has been set up in the State under the UP State Water & Sanitation 
Mission with the effect from June 04, 2010. 

1.6 PROJECT AT A GLANCE

The  objective  of  this  document  is  to  present  the  detailed  designs,  and  estimates  for  the  proposed  water 
supply scheme for the practical implementation and execution of the scheme on the ground with an insight 
of  achievement  of  service  level  delivery  and  performance  indicators  set  by  the  government  by 
implementation of standard practices of operation and maintenance. The approach for Consultancy services 
included  overall  planning,  engineering  survey  designing  and  preparation  of  DPR  of  drinking  water  supply 
scheme. This document is organized to provide execution road map for Project Execution with schedule of 
activities for the proposed Water Supply systems. 

The  objective  of  the  project  is  ensuring safe, sustainable  and  adequate drinking  water  cost effectively  and 
contributing  towards  a  healthy  and  dignified  life  through  good  sanitation  and  hygiene  practices  with 
community  involvement  for  the  people  of  Uttar  Pradesh  from  seven  district  of  Bundelkhand,  2  districts  of 
Vindhyanchal and about 7300 quality affected villages from different districts of state. 

Initially  one  separate  proposals  were  made  considering  the  Roberts  Ganj  &  Ghorawal  and  Chopan  Block 
considering lifting of water from Son River. Later as per the recommendation given by SWSM. This proposal 
is now focuses on the combined area of Roberts Ganj & Ghorawal and Chopan block considering Son River as
  8 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
a source of water supply. Now, we are focusing our study for 663 villages water supply scheme to be covered
with piped water supply scheme in this report.

As per DPR provided by SWSM, this project report consists of Roberts Ganj & Ghorawal and Chopan Block of 
Sonbhadra district. Sonbhadra district includes 3 blocks and their villages. There are 663 villages in Roberts 
Ganj & Ghorawal and Chopan Block. 

This  report  consists  Methodology  of  work.  As  per  this  methodology,  initially  we  started  reconnaissance 
survey  for  assessment  of  existing  water  supply  status  and  find  out  their  problems.  We  collected  the  data 
through  this  survey  which  is  useful  for  preparing  planning  of  proposed  water  supply  scheme.  As  per  this 
information, we have proposed water supply scheme for improvement of service levels for water supply in 
the above‐mentioned villages of the selected block. 

1.6.1 Introduction of Sonbhadra District

Sonbhadra or Sonebhadra is  the second  largest  district  by area  of Uttar  Pradesh after Lakhimpur  Kheri.  It  is 
the only district in India which borders four states, namely Madhya Pradesh to the west, Chhattishgarh to the 
south, Jharkhand in  the  south‐east  and Bihar to  the  north‐east.  The  district  has  an  area  of 
6,788 km2 (2,621 sq mi)  and  a  population  of  1,862,559  (2011  census),  with  a  population  density  of  270 
inhabitants per square kilometre (700/sq mi). It lies in the extreme south‐east of the state, and is bounded 
by Sonbhadra District to the northwest, Chandauli District to the north, Kaimur and Rohtas districts of Bihar 
state  to  the  north‐east, Garhwa  district of Jharkhand state  to  the  east, Balrampur 
District of Chhattisgarh state  to  the  south,  and Singrauli  district of Madhya  Pradesh state  to  the  west.  The 
district headquarters is in the town of Robertsganj. Sonbhadra district is an industrial zone and it has much 
bauxite, limestone, coal, gold, etc. It is called the "Energy Capital of India" because there are multiple power 
plants.  

Sonbhadra lies between Vindhya and Kaimur hills, and its topology and natural environment prompted First 
Prime Minister of India Jawaharlal Nehru to refer to Sonbhadra as the "Switzerland of India. 

Jawaharlal Nehru at inauguration of Rihand Dam 

In 2018 Uttar Pradesh's chief minister Yogi Adityanath recognised Sonbhadra as a tourist hub in Purvanchal 
region and further promoted by Uttar Pradesh Tourism Department.  

In  February  2020,  a Press  Trust  of  India (PTI)  news  report  incorrectly  claimed  that Geological  Survey  of 
India (GSI) has found 3,000 tonnes (3,300 tons) of gold deposits in Sonbhadra district. PTI later clarified on 
Twitter that the GSI had told PTI that there had been no such discovery of large gold deposits in the district.

  9 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

1.6.2 History

The  Valley  of Son and Belan Rivers  abounds  in  caves  which  were  the  earliest  dwellings  of  the  primeval 
inhabitants.  This  area  had  been  the  centre  of  activities  of  pre‐historic  man  which  is  evident  from  the  rock 
paintings (pre‐historic cave art) found in abundance in this region. These paintings are of the periods ranging 
from Mesolithic to Paleolithic ages. 
Based on evidence from religious and cultural perspectives of Ramayana and the Mahabharat, Huyen found 
here  is  the  cultural  symbol.  By Jarasandh many  rulers  in  the  Mahabharat  were  maintained  prisoner 
here. Sonbhadra, whose ancient name was Gramputra or Gupt Kashi, was built by the ancient king Putrak for 
his queen Paatali. It is said that 'Bhars' had settlements along with Chero, Searis and Kharwar communities in 
the  district up  to  fifth  century  there  was  the  rule  of  ''Chandel  Rajput''  kings  on Vijaygarh  Fort.  This  district 
was famous as second Kashi during 11th to 13th centuries. In the 9th century B.C., the Brahmadutt dynasty 
was  subdivided  by  Nagas. Kushan and Nagas also  held  supremacy  over  this  region  before  the  advent  of 
the Gupta period. After the death of Harshvardhan in the latter half of the 7th century, it remained under the 
control of the Gurjara‐Pratihars till 1025 before they were driven out by Mahmud of Ghazni. This area was 
under  the  administration  of  various  Governors  of Mughal  emperors.  Some  of  the  forts  such  as Agori 
Fort were under the control of Madan Shah. 
During  the  18th  century,  the  district  came  under  the  control  of  the Narayan rulers  of Benares  State,  who 
built  or  occupied  several  fortresses  in  the  district.  In  the  decade  after  1775,  the British took  over 
administrative  control  of  most  of  the  territory  of  the  rajas  of  Benares.  The  British  district 
of Sonbhadra included  present‐day  Sonbhadra  and  Sonbhadra  districts,  with  all  of  present‐day  Sonbhadra 
district  included  in  Robertsganj  tehsil.  On  4  March  1989,  Sonbhadra  district  was  divided  from  Sonbhadra 
district. 
 
 

  10 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
1.6.3 Geography

The northern part of the district lies on a plateau of the Vindhya Range, and is drained by tributaries of the 
Ganges including the Belan and Karmanasha rivers. South of the steep escarpment of the Kaimur Range is the 
valley  of  the Son  River,  which  flows  through  the  district  from  west  to  east.  The  southern  portion  of  the 
district  is  hilly,  interspersed  with  fertile  stream  valleys.  The Rihand  River,  which  rises  to  the  south  in  the 
highlands  of Surguja  district of Chhattisgarh,  flows  north  to  join  the  Son  in  the  center  of  the  district. 
The Govind  Ballabh  Pant  Sagar,  a  reservoir  on  the Rihand,  lies  partly  in  the  district  and  partly  in Madhya 
Pradesh. East of the Rihand, the Kanhar River, which originates in Chhattisgarh, flows north to join the Son. 

The  district  has  historic,  cultural,  and  ecological  affinities  with  the Bagelkhand region. Robertsganj is  the 
district headquarters 

 
1.6.4 Climate and Rainfall

Sonbhadra  has  a  relatively  subtropical  climate  with  high  variation  between  summer  and  winter 
temperatures.  The  average  temperature  is  30  to  46 °C  (86  to  115 °F)  in  the  summer  and  2  to  15 °C  (36  to 
59 °F) in the winter. The weather is pleasant in rainy season from July to October. 
 
1.6.5 LOCATION, TOPOGRAPHY AND DEMOGRAPHY
 

Overall  topography  of  the  Project  area  varies  between  90  m  above  MSL  to  403  m  above  MSL  with  663 
villages  in  this  cluster.  Geographically,  the  district  lies  between  24°37'N  latitude,  82°52'E  longitude  and 
24°27'N  latitude,  83°09'E  longitude.  Robertsganj  is  well  connected  to  Lucknow,  Allahabad,  Varanasi  and 
Sonbhadra by road. Buses are available at all hours of the day from Varanasi, and it normally takes 2.5 hours 
to cover the distance. 
The highway connecting Varanasi and Waidhan passes through the city. Though this is not a national highway 
it  is  a  very  busy  road  because  of  the  towns  Dalla,  Renukoot,  Anpara,  Shakti  nagar  which  are  sufficiently 
commercialized areas. Churk a nearby town is situated around 10 km, where Jaypee Group is establishing a 
thermal power project.The village and hamlets are approachable through motorable roads from the highway 
and is situated at a distance of about 17 Kms from Sonbhadra District Headquarters 

The  topography  of  Project  area  is  undulating.  As  per  reconnaissance  survey  of  the  Project  area,  the 
difference between highest and lowest ground levels in the hamlets and village is about 403 & 167 meters 
above mean sea level. 

For detailed land survey report refer to Annexure 1.1. A CD of digital record is appended herewith. 

 
1.7 ADMINISTRATIVE SETUP

The district falls under the Vindhyachal mandal and the headquarter is Sonbhadra town. The district has four 
Tehsils namely Robertsganj, Ghorawal, Duddhi, and Obra. The district is divided into 10 blocks. 
 
 
 
 
 

  11 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Tehsil Blocks

Robertsganj
Robertsganj
Chopan

Gorawal Gorawal

1.7.1 Tehsil in Sonbhadra District


The district has 4 legislative Assembly constituencies i.e. Robertsganj,Ghorawal,Duddhi, and , Obra. 

1.7.2 Blocks in Sonbhadra District


The  district  is  divided  into  10  blocks  such  as  Robatsgan,  Ghorawal,  Chatra,  Nagwa,  Chopan,  Babhani, 
Myorpur, Duddhi, Karma, & Kone. 

  12 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

1.8 Robertsganj -Block

 Robertsganj is located in the southeastern corner of the state. Robertsganj is the administrative headquarter 
of Sonbhadra District.  The  district Sonbhadra and  Robertsganj  as  its  district  headquarter  were  created  by 
carving  off  the  southern  part  of  the Sonbhadra district  on  4  March  1989. Son, Karmnasha,  Chandra 
Prabha, Rihand,  Kanhar,  Renu,  Ghagar  and  Belan  Rivers  drain  this  area.  The  city  is  named  after Frederick 
Roberts, 1st Earl Roberts. 
Located  between Vindhyan Range  and Kaimur  Range,  this  area  had  been  the  centre  of  activities  of  pre‐
historic  man  which  is  evident  from  the  rock  paintings  (pre‐historic  cave  art)  found  in  abundance  in  this 
region. 

1.9 Chopan -Block

Chopan is  a  town  and  a nagar  panchayat in Sonbhadra  district in  the  state  of Uttar  Pradesh, India.  It  is 
situated  on  the Sone  River.  Chopan  Railway  station  is  a  junction  in Sonbhadra  district.  Chopan  is  located 
at 24.52°N  83.03°E.[1] It  has  an  average  elevation  of  159 metres  (521 feet).  As  of 
2011 India census,[2] Chopan had total population of 14,302. The male population was 7,710, and the female 
population was 6,592. Chopan has an average literacy rate of 85.1%, higher than the national literacy rate 
with male literacy of 90% and female literacy of 79%. 14% of the population is under 6 years of age. 

2.0 Gorawal -Block

Ghorawal  is  located  at 24.77°N  82.78°E. It  has  an  average  elevation  of  303 metres  (994 feet).  As  of 
2001 India census,[2] Ghorawal  had  a  population  of  6,478.  Males  constitute  54%  of  the  population  and 
females 46%. Ghorawal has an average literacy rate of 59%, lower than the national average of 59.5%: male 
literacy is 69%, and female literacy is 47%. In Ghorawal, 18% of the population is under 6 years of age. 

  13 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

EXECUTIVE SUMMARY

  14 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
 

EXECUTIVE SUMMARY 

1. OBJECTIVE 

As per Strategic plan (2011-2023) of Government of India, the 90% of the Rural population in the
country has to be benefited with the pipe water supply. However, only 19% Rural population of Uttar
Pradesh is covered with pipe water supply schemes. In order to achieve the objective of project, it has
been decided to provide the pipe water supply schemes particularly in water scarce area of
Bundelkhand and Vindhaya region and Arsenic, Fluoride and AES/JE affected areas in the State. It
has been decided to appoint a consultant to provide consultancy services to State Water and
Sanitation Mission (SWM), Department of Rural Development.

Under this mission, 9 District are identified in Uttar Pradesh, which are as follows;

Table 0‐1: List of District of UP to be covered under Indian Strategic Plan (2011‐22) 

S. No. Name of District Area/Region


1 Jhansi
2 Lalitpur  

3 Jalaun
4 Banda Bundelkhand
5 Hamirpur
6 Chitrakoot
7 Mahoba
8 Mirzapur
Vindyanchal
9 Sonbhadra
 

Under these proposals, infrastructure for water supply is proposed to be provided / augmented to
achieve equitable and potable water supply to each & every household in water scared villages of
Bundelkhand and Vindhaya region in Uttar Pradesh.

1.8     DETAIL OF (EXISTING WATER SUPPLY ARRANGEMENT) 
 

In  Patwdh  Group  of  village’s  water  supply  scheme,  663  villages  are  included  under  this  Detailed 
Project  Report.  Piped  water  supply  system  does  not  exist.  Residents  of  villages  meet their  daily 
drinking  water  Requirements  from  the  Installed  India  mark‐II  Hand  pumps/Shallow Hand  pumps 
and  open  wells.  Installed  India  mark‐II  Hand  pumps  are  inadequate  to  meet  the Drinking Water 
demand of the villages, also shallow Hand pumps and open wells dry up during summer season. 

In view of the position given above under para 4 and sub para 4.1, it is necessary that piped water 
supply system is provided in all the 663 Villages covered under this Detailed Project Report. 

  15 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
List of Villages Covered Under Project Area (Robatgang, Chopan and Gorawal Block) 

Sl No.  Name of Revenue Villages  Sl No.  Name of Revenue Villages  Sl No.  Name of Revenue Villages 

1  Karia  33  Majurahi  65  Koladiha 

2  Tendua  34  Kanhari  66  Bharkana 

3  Barbaspur  35  Siwadar  67  Bhagahi 

4  Ghuwas  36  Bantara  68  Baidawar 

5  Basahi  37  Deogarha  69  Jamua 

6  Lali  38  Hinauti  70  Sonabarsa 

7  Mukkha  39  Parwania  71  Khagia 

8  Amilia  40  Bardiya  72  Musha 

9  Amilaudha  41  Rumma  73  Mandha 

10  Karsoata  42  Manhwa  74  Snihawal 

11  Lahas  43  Khajuari  75  Janar 

12  Sirsain  44  Harankhuri  76  Beerkala 

13  Fulwary  45  Meejhun  77  Dorihar 

14  Madhaka  46  Chandwa  78  Khardeur 

15  Samerwar  47  Bhainshi  79  Mohani 

16  Mahokhar  48  Sonhati  80  Beerkhurd 

17  Ubha  49  Dulahatha  81  Baraudhi 

18  Pathartal  50  Bar  82  Beheri 

19  Karry  51  Seegra  83  Majhgawan Chauhan 

20  Rahi  52  Baijanath  84  Kanhi 

21  Purana  53  Gawnkunda  85  Dharmauli 

22  Ghoria  54  Satdwari  86  Keweta 

23  Semera Kala  55  Chigori  87  Khakh 

24  Semera Khurd  56  Domakhri  88  Mahvarioa 

25  Babhari  57  Dhura Kund  89  Kewali 

26  Marni  58  Amadhi  90  Khadaha 

27  Murtiya  59  Manjhiganwa Mishra  91  Munghri 

  16 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Sl No.  Name of Revenue Villages  Sl No.  Name of Revenue Villages  Sl No.  Name of Revenue Villages 

28  Dholo  60  Kon  92  Khutaha 

29  Amli Pokhar  61  Bauradih  93  Samara 

30  Sapahi  62  Jurauli Kolani  94  Hinauti 

31  Tenthuhar  63  Lilwahi  95  Parsauna Khurd 

32  Parsauna  64  Koharatha  96  Junia 

97  Pidaria  144  Bahorika  191  Deori Kalan 

98  Parhi  145  Sahpurwa Kalan  192  Kushai 

99  Satohan  146  Pagia  193  Burar Kalan 

100  Newari  147  Bharawah  194  Nauganwa Kalan 

101  Nakawai  148  Khairwa  195  Kewati 

102  Visundhary  149  Birmaua  196  Dehra 

103  Amilia  150  Chakahi  197  Theru 

104  Tilauli Kalana  151  Mukasim  198  Babura 

105  Khuthnia  152  Uachka  199  Pursotampur 

106  Geduri  153  Pandepokhar  200  Nauganwa Khurd 

107  Sahpurwa Khurd  154  Ranitara  201  Organai 

108  Kamhria  155  Barimahewa  202  Durha 

109  Bnardewa  156  Dudhia  203  Deora Raja 

110  Kathapura  157  Bhulahi  204  Bagaura 

111  Silahta  158  Teprasivadati  205  Belatand 

112  Jogani  159  Salaia  206  Khajurikhurd 

113  Naudiha  160  Jorwria  207  Usarikalan 

114  Khodaichak  161  Asana  208  Ushrikhurd 

115  Bisun Pur  162  Patehara  209  Lasari Kalan 

116  Atarwa  163  Khairawa Raja  210  Khajurikala 

117  Teti  164  Rajkhar  211  Bhurkura 

118  Gotauli  165  Pateri  212  Masoe 

  17 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Sl No.  Name of Revenue Villages  Sl No.  Name of Revenue Villages  Sl No.  Name of Revenue Villages 

119  Juri  166  Tulsipur  213  Dabha 

120  Masiadinath  167  Jawahi  214  Lasari Khurd 

121  Chakari  168  Sirvit  215  Durawal Khurd 

122  Sawat  169  Etwa  216  Bhuli 

123  Jamaghne  170  Saranga  217  Hhrihar Pur 

124  Padri Kalan  171  Tedhwa  218  Kunan 

125  Maid  172  Sirsiajethi  219  Balua 

126  Masiha Pathan  173  Kolariya  220  Kasari 

127  Belkuri Murpharkat  174  Dharura  221  Enam 

128  Mureladih  175  Sitabahar  222  Aghwar 

129  Parari Kurd  176  Karkoll  223  Bagauari 

130  Kharuaun  177  Tekuria  224  Unchidih 

131  Karrivarai  178  Mahuriya  225  Shlaiya 

132  Kamhria  179  Babanauli  226  Barahda 

133  Rudauli  180  Barkara  227  Bagathri Kalna 

134  Dhoa  181  Jait  228  Bagathari Khurd 

135  Tilauli Khurd  182  Tipara  229  Alahi Durawan 

136  Aruna  183  Manpur  230  Deori Khurd 

137  Vimauri  184  Khairahi  231  Durawal Kalna 

138  Velahi  185  Parashidubey  232  Shono 

139  Semari Misra  186  Bauar  233  Rajapurawa 

140  Khudia  187  Mamuna  234  Tiarashiv Datt 

141  Ataraila  188  Pawar  235  Chaktiara 

142  Purkhas  189  Kalwari  236  Karhi 

143  Phulawari  190  Burhr Khurd  237  Jeewar 

238  Bhagwantpur  285  Jurawat  332  Parsona 

239  Dahari  286  Tandi  333  Kamaharia 

  18 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Sl No.  Name of Revenue Villages  Sl No.  Name of Revenue Villages  Sl No.  Name of Revenue Villages 

240  Sihirshahi Parashe Dubey  287  Madainia  334  Birhulia 

241  Mahuresher  288  Jaderua  335  Mahulia 

242  Petrahi  289  Sirsiathkurai  336  Dehari 

243  Katawaria  290  Bharuha  337  Gouri Nisph 

244  Oani Chaubey  291  Bhadohi  338  Kathpurwa 

245  Orauli  292  Shirsia  339  Kasya Kalan 

246  Oanimishra  293  Atarauli Raja  340  Kushahi 

247  Deora  294  Sarauli  341  Bashdewa 

248  Jamashokar  295  Garaegarh  342  Kekarahi 

249  Kanhara  296  Dularu  343  Karaki 

250  Karma  297  Khairahi  344  Kasya Khurd 

251  Majhiganwa  298  Atarawa  345  Kucha Marwa 

252  Dohari  299  Baburahi  346  Khairawa No 2 

253  Welanow  300  Bantara  347  Kharahri 

254  Hinauti  301  Majhui  348  Shirkhora 

255  Koharaul  302  Mubarakpur  349  Jokahi 

256  Khaira  303  Baghor  350  Machhalawa 

257  Kapura  304  Dhotwa  351  Aelahi 

258  Khairi  305  Gorahi  352  Hinauta 

259  Chotakapur  306  Khane Azampur  353  Amaulia 

260  Barsota  307  Kutulupur  354  Chakara 

261  Welkhuri  308  Lohra  355  Parahi 

262  Uchaka  309  Sukrit  356  Amdih 

263  Bhruha  310  Bhatulia  357  Bhawanipur 

264  Pipri No. 1  311  Bakahi  358  Khamriha 

265  Lohdhara  312  Sirsia  359  Nagnar Haraia 

266  Jamagane  313  Padar  360  Baghauri 

  19 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Sl No.  Name of Revenue Villages  Sl No.  Name of Revenue Villages  Sl No.  Name of Revenue Villages 

267  Sauli  314  Kairwa  361  Bat 

268  Chakauli  315  Pipara  362  Madhupur 

269  Asatali  316  Kushhi  363  Takia Mu.Dargah 

270  Noni  317  Garhwa  364  Gordiha 

271  Kingari  318  Mangurahi  365  Bahera 

272  Chhuta  319  Darah  366  Purainiya 

273  Kurashat  320  Jori  367  Jigana 

274  Eanam  321  Sheokari  368  Alahi 

275  Petrahi  322  Murala Dih  369  Bargawn 

276  Umarikalna  323  Khekhara  370  Bishbhrpur 

277  Mishra  324  Basawa Nisph  371  Parsona 

278  Gajana  325  Tinatali  372  Pateara 

279  Naraina  326  Tilya  373  Domariya 

280  Arangi  327  Bhagauti  374  Rampur 

281  Gheuri  328  Papi  375  Baheri 

282  Dilahi  329  Patela  376  Kaithi 

283  Karanwah  330  Madar  377  Khrehari 

284  Bahera  331  Baghi  378  Deogarh 

379  Kushi  426  Urali  473  Dugaulia 

380  Tendee  427  Khewatha  474  Shikari 

381  Pakari  428  Mango  475  Bansdih 

382  Lashra  429  Mahokhar  476  Bichhwar 

383  Majhigaon Chaubey  430  Chandauli  477  Marachhi 


384  Shirpalpur  431  Tendu  478  Jamaganwa 

385  Majhigaon Mishra  432  Mahuari  479  Umarikhurd 

386  Ghuaskalan  433  Kamahar Dih  480  Kooran 

387  Ganguar  434  Bahura  481  Baraganwa 

  20 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Sl No.  Name of Revenue Villages  Sl No.  Name of Revenue Villages  Sl No.  Name of Revenue Villages 

388  Bagadiha  435  Papi  482  Gobariya 

389  Tirnahi  436  Majhiganwa  483  Barauli 

390  Beechhi  437  Raghunathpur  484  Shahganj 

391  Ghuashkurd  438  Bharganw  485  Sahuar 

392  Amauli  439  Bhunari  486  Sohdaul 

393  Shuhali  440  Raiwari  487  Manhawan 

394  Bithgon Nishoh  441  Bajotara  488  Amahar 

395  Bithgawn Nishph  442  Amahata Amahti  489  Pipari No 2 

396  Dharnipur  443  Beechhiya  490  Barnwa 

397  Karari  444  Khatauli  491  Onauli 

398  Mokarshim  445  Bhandar Khurd  492  Kushra 

399  Palikalna  446  Baghari  493  Thuter 

400  Darari  447  Bahuar  494  Tiwar 

401  Pipari  448  Bashauli  495  Adaura 

402  Belwa  449  Bashuari  496  Orhatha 

403  Lakhan Purwa  450  Tilauli  497  Raipura 

404  Garawa  451  Amauli  498  Rajpur 

405  Bhruiya  452  Mahuar Khurd  499  Shenduri 

406  Goithari  453  Patehra  500  Barak 

407  Jamuanua  454  Mahuar Kalna  501  Shonwat 

408  Dhuriya  455  Karauli  502  Shonauti 

409  Jamaganwa  456  Gordiha  503  Divar 

410  Nai Basti  457  Nipraj  504  Khajaraul 

411  Ratawal  458  Muther  505  Bhairawa 

412  Mahuaon  459  Kamojee  506  Majhali 

413  Hinauti  460  Marhra  507  Mushrdhara 

414  Hona  461  Beohari  508  Atarauli Kalan 

  21 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Sl No.  Name of Revenue Villages  Sl No.  Name of Revenue Villages  Sl No.  Name of Revenue Villages 

415  Hinduhari  462  Mahuali  509  Garwa 

416  Barwan  463  Khchar  510  Kewata 

417  Majhi Ganwa  464  Parashipandy  511  Tendui 

418  Shemari Bishunlal  465  Shajua  512  Obaradih 

419  Babhanauli Khurd  466  Shathi  513  Domahar 

420  Bhogar  467  Juriya  514  Selahata 

421  Babhanauli Kalan  468  Judauri Pardhan  515  Kusinisph 

422  Shango  469  Bherawal  516  Mhunyw Pandy 

423  Pashi Kalana  470  Ganguhar  517  Chorat 

424  Amokhr  471  Renua  518  Mahuna Gosani 

425  Pashi Khurd  472  Kolakari  519  Kunda 

520  Panauli  566  Piparwar  612  Shemara 

521  Sadari  567  Bisrekhi  613  Shahijan Kalna 

522  Jinhora  568  Jaimohara  614  Shindhora 

523  Naidiha  569  Sirsai  615  Bichapai 

524  Aurahi  570  Raikara  616  Ormaura 

525  Sidhi  571  Majhagawan  617  Lori 

526  Naunia  572  Naugai  618  Pushuli 

527  Athauna  573  Uchdih  619  Amarati 

528  Bhgawas  574  Lakshimanpur  620  Gorari 

529  Chausara  575  Chain  621  Barauli 

530  Kharera  576  Naugawan  622  Meuri Khurd 

531  Morahi  577  Bhawana  623  Jamgane 

532  Barauli  578  Dewerikhurd  624  Ghurma 

533  Khirahata  579  Halwai  625  Kaithi 

534  Garama  580  Bagpokhar  626  Baraila 

535  Gurwal  581  Bhanswar  627  Petrahi 

  22 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Sl No.  Name of Revenue Villages  Sl No.  Name of Revenue Villages  Sl No.  Name of Revenue Villages 

536  Bandha  582  Sahdeapaidar  628  Kamarhi 

537  Belwania  583  Magaradaha  629  Baghnaree 

538  Karaundia  584  Visahar  630  Belaha 

539  Rampur  585  Raunp  631  Patharaha 

540  Panti  586  Churk  632  Gangti 

541  Dhanawal  587  Shahijan Khurd  633  Paika 

542  Barsot  588  Musahee  634  Kewata 

543  Lohari  589  Kura  635  Rajdhan 

544  Ahraura  590  Teyara Nayak  636  Bachawar 

545  Sotil  591  Peetha  637  Mhowoh Khurd 

546  Jaimohra  592  Akachor  638  Kamharia 

547  Pateri  593  Beejauli  639  Belcupp 

548  Bakuli  594  Meuri Kalan  640  Mhowon Kalna 

549  Durkhuli  595  Arauly  641  Chihurali 

550  Guretha  596  Shajaur  642  Baluee 

551  Rajin  597  Lakhanwar Kalna  643  Maitapur 

552  Odar  598  Mangurahee  644  Kargara 

553  Thiwan  599  Kusamha  645  Bhbhaech 

554  Dhuria  600  Bijary Duban  646  Karki 

555  Kusmaha  601  Harhuna  647  Guradah 

556  Dewerikatha  602  Atarauli Khurd  648  Redia 

557  Peroh  603  Bijary Patkhan  649  Bandhwa 

558  Dhorkary  604  Bahuarah  650  Bhgawa 

559  Dharsara  605  Lakhanwar Khurd  651  Kurhul 

560  Marasara  606  Kharhari  652  Adalganj 

561  Dumaria Mithailal  607  Pali  653  Salkhan 

562  Silwar  608  Dhobahi  654  Awayee 

  23 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Sl No.  Name of Revenue Villages  Sl No.  Name of Revenue Villages  Sl No.  Name of Revenue Villages 

563  Dumaribharaulia  609  Bharganwa  655  Markundi 

564  Bharauli  610  Bhandra Kalan  656  Rudawali 

565  Dhadhi  611  Chhapaka  657  Patwdh 


658  Belach  660  Kandhaura  662  Aluar 

659  Pakari  661  Kanach  663  Bhadohi. 

 
Revised Villages list for Patwadh Group of Villages Scheme in ref to U.P jalnigam Executive Engineer vide 
Letter no. 340 / W‐17 (Harra, Kadra, Newari) / 2020‐21 dated 08/06/2020. 
 
 
 
 
 

  24 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

  25 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

  26 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

DESIGN GUID LINES:  


Design guislines issued vide letter no. 1499 / E‐46 / 2021 dated 12/02/2021

  27 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

  28 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

  29 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

  30 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

  31 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

  32 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

  33 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

  34 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

  35 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

  36 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

  37 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
                 Finally adopted Population for the Proposed Water Supply Scheme 
 

Year Population Adopted Remark

2011  570515   
2023  715560  In Base year 2023 
2038  931930  In Intermidiate year 2038 
2053  1211660  In Design Year 2053 

                Demand Estimation for the Design Stages. 

Population Net Demand in  Gross Demand in  Raw Water Demand (10%  Raw Water Demand for 


Year
Adopted MLD (55 LPCD)  MLD (15% UFW)  over Gross Demand)  16 Hours Pumping 

2011  570515  31.378  36.918  40.610  60.915 


2023  715560  39.356  46.304  50.934  76.401 
2038  931930  51.256  60.305  66.336  99.504 
2053  1211660  66.641  78.407  86.247  129.371 

This scheme will be under the category of Multi‐Village Scheme (MVS) and the source of water supply will 
be surface water. The source of this scheme is proposed from Son River at upstream of Patwadh village level 
surveys,  Elevation  surveys  are  conducted  to  finalize  the  list  of  the  beneficiary  villages.  Comprehensive 
planning has been done for the preparation the proposed scheme with the help of the data collected from 
these surveys. 

PROPOSED WATER SUPPLY SCHEME COMPONENTS

 SOURCE OF WATER SUPPLY SCHEM

Raw water source of the proposed Patwadh GOV multi village water supply scheme will be on Son River at 
Near  Patwadh  Villages.  An  MOU  (Memorandum  of  Understanding)  has  to  be  done  with  Chief  Engineer, 
(Sone), Irrigation  department, Varanasi to get required amount of  water from Son River There is sufficient 
amount of water available in Son River. Raw water intake is proposed to be constructed in the submergence, 
considering assurance for year round supply of the raw water to the scheme considering the demand of 120 
MLD at ultimate stage of 2053. 

 RAW WATER INTAKE ARRANGEMENT

Jack well of 14 m diameter is proposed to be constructed at location approved by the irrigation department. 
An overhead pump house of 6.0m height is proposed to be constructed above theJjack well. 

  38 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
 RAW WATER PUMPING MACHINERY

6 nos. of raw water pumps, 212.58 KW Vertical Turbine (VT) Pump with an  arrangement of force clear water 
lubrication with 38.50 m head and discharge of 23034 LPM, four working and two standby (3 W + 3 S) are 
proposed for lifting raw water from proposed head works to the proposed Water treatment Plant. Raw 
water pumps are designed for the intermediate stage demand. Arrangement of power supply and other 
electromechanical components are proposed accordingly. 

 RAW WATER RISING MAIN

Raw water rising main of 700 m, 1200 mm diameter, MS Pipe from proposed head to proposed water 
treatment plant at Patwadh village is proposed for raw water transmission. Raw water transmission is 
designed for the ultimate stage of the demand. 

 WATER TREATMENT PLANT

Water treatment plant of 120.00 MLD is proposed at Patwadh village considering the 80 MLD demand of 
Ultimate stage and 16 hours of pumping.  Aeration Fountain, Rapid Gravity Sand Filters, Chlorination unit, 
Flash Mixer, Clear water reservoir, back wash Tank and provision for staff quarters with other WTP 
equipment is considered in the proposal of the water treatment plant. Clear water reservoir is designed 
considering 2 hrs detention time form ultimate stage of demand. Water treatment is proposed at a distance 
of 700 m from Intake Tower due to non‐availability of sufficient land required for WTP nearby proposed 
intake Location. 
 
 Clear Water Reservoir

Clear water reservoir with pump house 14 no. & . Zonal Clear water reservoir is designed considering 1 hrs 
detention time form ultimate stage of demand Reservoir one no being proposed for systematic and fulfill 
water supply for the consumer’s. Treated water is pumped directly to proposed elevated service reservoir 
from the clear water pump house/ MBR. The clear water reservoir is located at different villages in the 
project area. Detailed Design of capacity of Clear water reservoirs are as tabulated below. 
 

  39 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
 
 
 

  40 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
CLEAR WATER PUMPING MACHINERY

REQUIRED PUMP  
SL  TYPE OF  NO OF PUMPS  LPM /  LPS / 
FROM  TO  LPM  HEAD  BKW  MARGIN 
No.  PUMP  WORKING  STANDBY  TOTAL  PUMP  PUMP 
1  Intake well  120MLD WTP  VT  69100  3  3  6  23034  384  38.5  193.25  212.58 
OHSR‐ Kanach  VT  486  1  1  2  486  9  62  7.29  9.48 
ZONE‐PATWADH,ZONE‐
2  MCWR at WTP  SALKHAN ,ZONE‐REDIA‐GLR2‐ VT  6398  4  2  6  1600  27  94  33.18  38.15 
GLR‐1 
GLR‐3 at Markundi  VT  55935  5  3  8  11187  187  68  166.22  182.84 

GLR‐2  OHSR, Zone‐Rudawli  HSC  377  1  1  2  377  7  37  3.39  4.74 



(Rudwali)  OHSR Zone‐Markundi  HSC  804  1  1  2  804  14  76  13.91  16.69 

GLR‐1  OHSR Zone‐Bhbhaech  HSC  1321  1  1  2  1321  23  33  9.92  11.91 



(Bhbhaech)  OHSR Zone‐Belcupp  HSC  1205  1  1  2  1205  21  59  16.20  18.63 
GLR‐3 
5  GLR‐4 (Lori)  VT  55935  10  5  15  5594  94  167  205.20  225.72 
(Markundi) 
OHSR Zone‐5‐3  VT  1894  1  1  2  1894  32  25  10.46  12.55 
6  GLR‐4 (Lori) 
GLR‐5 ,ZONE‐12‐3,ZONE‐9‐2  VT  54041  2  1  3  27021  451  17  100.22  110.24 
OHSR Zone ‐8D & 5‐2  VT  2616  1  1  2  2616  44  37  21.28  24.47 
GLR‐6 (Kekarahi), OHSR‐8C, 
VT  14458  3  1  4  4820  81  45  47.65  54.79 
GLR‐5  OHSR‐6C‐3 
7  GLR‐9 (Nipraj), GLR‐10 
(Gangur) 
(Kushara), OHSR‐8, OHSR‐12‐
VT  35447  3  1  4  11816  197  58  149.36  164.30 
1, OHSR‐12‐2, OHSR‐5‐1, 
OHSR‐9A‐1 

  41 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
REQUIRED PUMP  
SL  TYPE OF  NO OF PUMPS  LPM /  LPS / 
FROM  TO  LPM  HEAD  BKW  MARGIN 
No.  PUMP  WORKING  STANDBY  TOTAL  PUMP  PUMP 

GLR‐6 
8  GLR‐7 (Papi) & OHSR‐6C‐1  HSC  12594  3  2  5  4198  70  36  32.94  37.88 
(Kekarahi) 

GLR‐8, OHSR‐6 , OHSR‐6C, 
9  GLR‐7 (Papi)   VT  11904  2  1  3  5952  100  53  69.28  79.67 
OHSR‐6C‐2 & OHSR‐7A‐1 

OHSR 6A‐1  HSC  1033  1  1  2  1033  18  37  8.71  10.45 


 GLR‐8 (Tarauli 
10 
Raja)  OHSR‐6A & 6B , OHSR‐7B & 
HSC  6526  2  1  3  3263  55  59  42.42  48.78 
6A‐2 , OHSR‐6A‐3  & OHSR‐8B 

OHSR‐9‐1  HSC  1333  2  1  3  667  12  81  12.71  15.25 


11  GLR‐9 (Nipraj)  
OHSR‐9‐3  HSC  1321  1  1  2  1321  23  34  10.22  12.27 

OHSR‐10, OHSR‐9A & OHSR‐9  VT  4483  2  1  3  2242  38  74  36.76  42.27 


GLR‐10 
12 
(Kushara)  GLR‐11, GLR‐12, OHSR‐5B‐1, 
VT  23163  6  4  10  3861  65  42  35.69  41.04 
OHSR‐3B‐1 & OHSR‐3A‐3 

OHSR ‐3A‐1 & 3A‐2  HSC  1642  1  1  2  1642  28  33  12.08  14.49 


GLR‐11 
13 
(Jogani)  OHSR‐11B, OHSR‐4A & OHSR‐
HSC  3421  3  2  5  1141  20  61  15.95  18.34 
7A‐2 

  42 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
REQUIRED PUMP  
SL  TYPE OF  NO OF PUMPS  LPM /  LPS / 
FROM  TO  LPM  HEAD  BKW  MARGIN 
No.  PUMP  WORKING  STANDBY  TOTAL  PUMP  PUMP 

OHSR‐3‐1  VT  1204  1  1  2  1204  21  31  8.51  10.21 

GLR‐12   GLR‐13, OHSR‐2A, OHSR‐10A‐1 
14  VT  6643  2  1  3  3322  56  72  52.71  60.61 
(Khutana)  & OHSR‐10A‐2 
GLR‐14, OHSR‐3‐2 & 3‐3, 
OHSR‐11A‐1, OHSR‐11 &  VT  6847  2  1  3  3424  58  63  47.76  54.93 
OHSR‐1‐1 

OHSR‐ 11A   VT  678  1  1  2  678  12  37  5.80  7.55 


GLR‐13 ( 
15 
Beerkhurd) 
OHSR‐ 2 & OHSR‐2‐1   VT  2096  1  1  2  2096  35  105  48.04  55.25 

GLR ‐14  OHSR‐1, OHSR‐1A & OHSR‐1A‐
16  HSC  2750  2  1  3  1375  23  42  12.63  15.15 
(Sirsail)  1 

  43 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
1.1.1. Design Population 

In population forecast for Project area, the base population of year 2011 is adopted from census. Various
population projection are used in forecasting the town population for future years and name of methods are
given below:
a) Arithmetic increase method
b) Geometrical increase method
c) Incremental increase method
d) Graphical method
e) Semi Log Method
 
Based on earlier growth in population, the incremental increase method has been suggested for future
population keeping in view of growth trend and same has been applied in all villages. 
 

1.1.2. Per Capita Water Supply 

The Environmental Hygiene Committee suggested certain optimum service levels for communities based on
population groups. In the Code of Basic Requirements of Water Supply, Drainage and Sanitation as well as
the National Building Code, a minimum of 70 LPCD has been recommended for all residences provided in
Rural area. Though in the Manual on Sewerage and /sewage Treatment to conserve water, a minimum of 70
LPCD in now recommended. It is well recognized that the minimum water requirements for domestic and
other essential beneficial uses should be met through public water supply. Based on the objectives of full
coverage of rural communities with easy access to potable drinking water in quantities recommended to meet
the domestic and other essential non-domestic needs, the following recommendations are made.

Table 1.1.2‐1: Recommended Per Capita Water Supply Levels for Designing Schemes 

Recommended Maximum
Sl. No. Classification of towns/cities Water Supply Levels
(LPCD)
1 Water Supply for Rural Area 55 As per Jal Jivan Mission

Note:
i) In areas, where is provided through public stand posts, 40 LPCD should be considered;
ii) Figures exclude "Unaccounted for Water (UFW)" which should be limited to 15%.
 
 
 

  44 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
1.1.3. System Losses   

The recommendations regarding additional provision for water in water supply system by Jal Nigam and
SWSM, Government of Uttar Pradesh are as follows:

Table 1.1.3‐1: Maximum Permissible System Losses 

Sl. No. Parameter Percentage


Max Allowable Losses in Pipe
1 15%
Network
Treatment Losses& Raw Water
2 10%
Transmission Losses

In this project, system losses have been considered @25% and duly accounted for hydraulic design of
distribution system & the capacities of the reservoirs.
 

1.1.4. Design Parameter 

1.1.4.1. Peak Factor   

The following peak factors are recommended by CPHEEO manual for various population figures:

Table 1.1.4.1‐1: Peak Factors for Distribution System 

Sl. No. Population Size Peak Factor

1 For Population less than 50,000 3.0

2 For a population range of 50,000 to 2,00,000 2.5

3 For Population above 2,00,000 2.0

For small water supply schemes (Where supply


4 3.0
is effected through standposts for only 6 hours
 

1.1.4.2. Distribution Network: 

 
The distribution network has been designed by grouping of Gram Panchayat and One OHT has been
proposed. The farthest end of distribution network from OHT has been kept arround than the 5 km as
discussed with SWSM
The matter was discussed with client regarding pipe material and same has been adopted. The detail of pipe
material is given below:

  45 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Table 1.1.4.2‐1: Pipe material for Distribution network 

Sl.Nos Material Dia (MM) Specification

1 50 Medium Duty
2 GI 65 Medium Duty
3 80 Medium Duty
4 63 PE-100, PN-6
5 75 PE-100, PN-6
6 90 PE-100, PN-6
7 HDPE 110 PE-100, PN-6
8 140 PE-100, PN-6
9 160 PE-100, PN-6
10 200 PE-100, PN-6
11 100 K-7
12 150 K-7
13 200 K-7
DI
14 250 K-7
15 300 K-7
16 350 K-7

 
 

1.1.4.3. Transmission Main (Raw Water and Clear Water): 

The Raw transmission main system has been designed from the Intake well to Water Treatment Plant (WTP).
The Clear Water Transmission Line has been designed from Clear water Reservoirs (CWR) at WTP to
Intermediate Clear Water Reservoir, overhead Tank (OHT) for 16 hrs operation as decided by department
(SWM). A peak factor of 1.5 has beenconsidered for transmission system design a minimum residual
pressure of 3.0 m has been considered over the full supply level of the service reservoir.
The matter was discussed with client regarding pipe material and same has been adopted. The detail of pipe
material is given below:

  46 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
 
 

Table 1.1.4.3‐1: Pipe material for Raw Water & Clear Water Transmission Main 

Dia  Material  Specification 


1200  MS  As per relevant IS code 
1000  MS  As per relevant IS code 
1000  DI  K‐9 
900  DI  K‐9 
800  DI  K‐9 
600  DI  K‐9 
400  DI  K‐9 
350  DI  K‐9 
300  DI  K‐9 
250  DI  K‐9 
200  DI  K‐9 
150  DI  K‐9 

1.1.4.4. Pressure Requirement for Distribution System 

Piped water supplies should be designed on 24 hours basis to distribute water to consumers at adequate
pressure at all points. Intermittent supplies are either desirable from the public health point of view or
economical. For towns/villages where one-storied buildings are common and for supply to the ground level
storage tanks in multi-storeyed buildings, the minimum residual pressure at ferrule point should be 7m for
direct supply. Where two-storied buildings are common, it may be 12m and where three-storied buildings are
prevalent 17m or as stipulated by local byelaws. The pressure required for fire-fighting would have to be
boosted by the fire engines.

Continuous 24 hours water supply is ideal on following grounds amongst others:


i) It provides the most economical project design and best utilization of resources.
ii) It ensures that there is no intrusion of pollution in the distribution system thus ensuring quality of water
distributed.
iii) It provides high level of consumer satisfaction.
iv) It saves from substantial indirect costs on local storages and purification/disinfections equipment to be
provided at consumer end by the consumers.
In view of above, it is proposed to design the system for intermittent water supply scheme for 8 hours. Water
supply shall be provided with a minimum terminal pressure of 7 m for direct supply to households.

  47 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
1.1.4.5. Storage Capacity & Staging of Service Reservoirs 

1.2. Over Head Tank (OHT) 

The zoning has been done based on various factors as discussed in this chapter. Based on mass balance
curve, the capacity of OHT in proposed zones has been calculated.

Total 55 numbers of OHTs have been proposed in all proposed 60 zones. The Gram Sabha/panchayat has
agreed to provide the land free of cost for water works & OHT sites at all places. The details of OHTs are
mentioned in the table below:-
SL  ESR  OHSR 
ZONE  LOCATION  STAGING 
NO.  LEVEL  CAPACITY 
1  BELCUPP   Belcupp  209.83  22  450 
2  BHBHAECH  Bhbhaech  205.50  18  450 
3  REDIA  Kurhul  204.42  14  200 
4  SALKHAN  BAGHNAREE  213.50  10  500 
5  MARKUNDI  MARKUNDI  218.30  20  300 
6  RUDAWALI   RUDAWALI  202.70  22  150 
7  PATWDH   PATWDH  207.00  10  250 
8  KANACH  Kanach  191.60  16  175 
9  ZONE‐1  Barbaspur  306.60  15  350 
10  ZONE‐1‐1  Pathartal  302.00  19  300 
11  ZONE‐1A‐1  Sapahi  267.25  19  250 
12  ZONE‐1A  Parsauna  296.18  22  350 
13  ZONE‐2  Deogarha  334.30  10  350 
14  ZONE‐2‐1  Bardiya  340.20  19  400 
15  ZONE‐2A  Bhagahi  298.50  22  450 
16  ZONE‐3‐1  Khutaha  300.78  15  400 
17  ZONE‐3‐2 & 3‐3  Satohan  305.67  14  650 
18  ZONE‐11  Peroh  299.00  13  300 
19  ZONE‐11A  Beerkhurd  291.00  22  250 
20  ZONE‐11A‐1  Bhawana   296.30  18  200 
21  ZONE‐11B  Visahar  290.00  14  400 
22  ZONE‐10A‐1  Karaundia  318.50  18  400 
23  ZONE‐10A‐2  Kharahata  310.00  21  500 
24  ZONE‐10  Tendui  329.50  10  450 
BELKURI 
25  ZONE‐3B‐1  305.15  15  300 
MURPHARKAT 
26  ZONE‐3A‐1 & 3A‐2  Jogani  299.50  20  600 
27  ZONE‐3A‐3  Dhoa  300.00  13  400 
28  ZONE‐6  Sirsiathkurai  302.40  21  300 
29  ZONE‐6B & 6A  Lohra  289.95  19  800 
30  ZONE‐7B & 6A‐2  Bat  288.17  20  450 
31  ZONE‐6A‐1  Atarauli Raja  300.54  22  350 
32  ZONE‐6A‐3  KHAMRIHA  289.20  22  600 

  48 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
SL  ESR  OHSR 
ZONE  LOCATION  STAGING 
NO.  LEVEL  CAPACITY 
33  ZONE‐4A  Karkoll  295.40  22  550 
34  ZONE‐6C  Dilahi  310.50  15  500 
35  ZONE‐7A‐2  Imlipur  302.30  17  300 
36  ZONE‐7A‐1  Patehara  306.60  20  350 
37  ZONE‐6C‐1  Jokahi  310.20  17  250 
38  ZONE‐6C‐2  Bakahi  309.30  17  450 
39  ZONE‐6C‐3  Parsona  299.90  19  250 
40  ZONE‐5B‐1  Welanow  300.40  21  500 
41  ZONE‐9A‐1  SHLAIYA  305.85  19  650 
42  ZONE‐5‐1  Deori Kalan  305.50  17  250 
43  ZONE‐8B  Chandauli  298.70  22  450 
44  ZONE‐8  Bishbhrpur  314.20  16  400 
45  ZONE‐8C  Pashi Kalana  300.70  22  400 
46  ZONE‐8D & 5‐2  Ganguar  306.50  22  900 
47  ZONE‐5‐3  Lori  359.50  10  650 
48  ZONE‐9A  Dugaulia  333.50  14  450 
49  ZONE‐9  Mahuriya  328.90  17  650 
50  ZONE‐9‐1  Bahuar  342.40  18  450 
51  ZONE‐9‐2  Tilauli  344.70  10  250 
52  ZONE‐9‐3  Nipraj  315.50  19  450 
53  ZONE‐12‐1  Lashra  308.30  17  350 
54  ZONE‐12‐2  Atarauli Khurd  308.90  18  150 
55  ZONE‐12‐3  Raunp  331.30  10  300 

1.2.1.1. Hazen ‐ William’s Coefficient 

For determination of hydraulic gradient in water carrying closed conduits, it is proposed to use Hazen-
Williams formula.

 
Where,
S: Slope of Hydraulic grade line
r: Hydraulic Radius

  49 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Q: Flow in Conduit in Cum/hr
C: Hazen Williams Roughness Coefficient
D: Diameter of circular conduit in mm.
V: Velocity in mps
 

1.2.1.2. Coefficient of Roughness (C) 

The coefficient of roughness as recommended by Manual of Water Supply and Treatment by CPHEEO is as
follows:
Table 1.2.1.2‐1: Coefficient of Roughness for different pipe materials 

  50 | P a g e  
  PATWADH GOV DE
ETAIL PRO
OJECT REP
PORT    

 
 
 
  PATWADH GOV DETAIL PROJECT REPORT    
1.2.1.3. Flow Velocity 

The maximum velocity is normally restricted to prevent resulting scouring effect on pipe material. With
improvement in pipe material qualities, the scouring effect no longer remains major consideration in design of
water pipelines. However, the minimum design velocity is 0.60m/s and the maximum is 3 m/s will be
maintained in main lines.
 

1.2.1.4. Head Loss Gradient 

It is proposed to keep the head loss gradient below 1-7 m / 1000 meters in distribution network and
transmission main to achieve the optimized design.
 

1.2.1.5. Configuration of Distribution System on Approach   

It is proposed to design & implement the distribution system on District Metering Area (DMA) pattern to
effectively monitor NRW on different parts of the distribution system and each DMA will cover the one village.
The DMA shall have one entry point for the flow & its boundary shall be hydraulically sealed. As far as
possible, the area level difference in a DMA shall be kept minimum.
The zoning of distribution network has been done by clustering the GPs and One Overhead Tank has been
proposed in each proposed zone.
 

1.2.1.6. Appurtenances 

Valves are provided in larger mains at 1-5 km interval to facilitate repairs. Non rising spindle Sluice valves are
used for isolating or scouring and not intended for continuous throttling as erosion of the seats and body
cavitation may occur. Butterfly valves are used to regulate and stop the flow. In large size butterfly valves are
cheaper and occupy less space. These may involve higher friction loss than sluice valve and also not suitable
for continuous throttling.

Sluice valve and butterfly valve for higher sizes require geared hand wheel or power driven actuators. Sluice
valves of standard make as per IS: 14846 and Non Return Valves of standard makes as per
IS: 5312 are proposed to be provided at different locations as per the requirements to control
the flow or to segregate a portion for maintenance.

Scour valves are provided in valleys/depressions to dewater pipe line. Drain valves are of
standard make are proposed to be installed in the rising mains and distribution system at
lower points in the line to drain silt and water from the line whenever required.

  52 | P a g e  
  PATWADH GOV DE ETAIL PRO OJECT REP PORT    
Air valve
v size is one twelfth
h of pipe diameter when
n it serves purpose of only release of air and
one eighth when
n it serves purpose
p of admission
a ass well as rellease of air. Air release valves of
dard make are
stand a propose
ed to be insta
alled in the rising mains
s to protect the
t line from
m negative
pressure and ovver loads du
ue to the tra
apping of the
e air. Neces
ssary valvess shall be prrovided at
able location
suita ns generally it is kept ab
bout 1/8th of size of pipe
e dia. Standa
ard quality will
w reduce
the chances
c of any
a leakage and failure.

etic air valves


Kine s are used to
t release air entrapped
d during runn
ning of pipe line. Pressu
ure relief valvves, Check
valve
es, Pressure
e Reducing Valves,
V Ball Float Valvess, and Shut off valves are used for specific
s purp
poses.
 
Fire Hydrants ha
as been prop
posed in the
e distribution system as per
p the stand
dards follow
wed for
the provision
p of Fire hydrantts
 

1.2.1
1.7. Housse Connection

All th
he house co
onnection sh
hall be draw
wn from the distribution mains. The
e house connection sha
all be made
using
g ferrule or T arrangement; the pipe
e shall be P
PPR up to co
onsumer end
d and same will be conn
nected with
Multi-jet meter.
 

1.3. Water Treatm
W ment Plant (W
WTP) 

Wate
er Treatmen
nt Plant (WT
TP) for this scheme hass been prop
posed. The WTP will be designed as per the
CPH
HEEO manua
al.

1.3.1
1. Source Of Water Supplyy 

Existting villages
s water supp
ply system iss predomina
antly based on
o Ground W
Water. Dep
pleting waterr table over
the years
y indicattes more witthdrawal of water
w than the
t recharge
e and ground
d water extra
action from such areas
shou
uld be restriicted. As pe
er statistics available o
on in Ground
d Water tab
ble, sufficien
nt ground w
water is not
availlable.
Due scarrcity of wate
er, the surfac upply scheme has been proposed and Intake well & Water
ce water su
Trea
atment Plant (WTP) has been proposed at Bankk of Son Rive
er in Patwad
dh village.
  PATWADH GOV DETAIL PROJECT REPORT    

PUMP KW AS PER DESIGN 
SL  TYPE OF  NO OF PUMPS  LPM /  LPS / 
FROM  TO  LPM  HEAD  BKW  MARGIN 
No.  PUMP  WORKING  STANDBY  TOTAL  PUMP  PUMP 
1  Intake well  120MLD WTP  VT  69100  3  3  6  23034  384  38.5  193.25  212.58 
OHSR‐ Kanach  VT  486  1  1  2  486  9  62  7.29  9.48 
ZONE‐PATWADH,ZONE‐
2  MCWR at WTP  SALKHAN ,ZONE‐REDIA‐ VT  6398  4  2  6  1600  27  94  33.18  38.15 
GLR2‐GLR‐1 
GLR‐3 at Markundi  VT  55935  5  3  8  11187  187  68  166.22  182.84 

GLR‐2  OHSR, Zone‐Rudawli  HSC  377  1  1  2  377  7  37  3.39  4.74 



(Rudwali)  OHSR Zone‐Markundi  HSC  804  1  1  2  804  14  76  13.91  16.69 

GLR‐1  OHSR Zone‐Bhbhaech  HSC  1321  1  1  2  1321  23  33  9.92  11.91 



(Bhbhaech)  OHSR Zone‐Belcupp  HSC  1205  1  1  2  1205  21  59  16.20  18.63 
GLR‐3 
5  GLR‐4 (Lori)  VT  55935  10  5  15  5594  94  167  205.20  225.72 
(Markundi) 
OHSR Zone‐5‐3  VT  1894  1  1  2  1894  32  25  10.46  12.55 
6  GLR‐4 (Lori) 
GLR‐5 ,ZONE‐12‐3,ZONE‐9‐2  VT  54041  2  1  3  27021  451  17  100.22  110.24 
OHSR Zone ‐8D & 5‐2  VT  2616  1  1  2  2616  44  37  21.28  24.47 
GLR‐6 (Kekarahi), OHSR‐8C, 
VT  14458  3  1  4  4820  81  45  47.65  54.79 
OHSR‐6C‐3 
GLR‐5 

(Gangur)  GLR‐9 (Nipraj), GLR‐10 
(Kushara), OHSR‐8, OHSR‐
VT  35447  3  1  4  11816  197  58  149.36  164.30 
12‐1, OHSR‐12‐2, OHSR‐5‐1, 
OHSR‐9A‐1 

  54 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
PUMP KW AS PER DESIGN 
SL  TYPE OF  NO OF PUMPS  LPM /  LPS / 
FROM  TO  LPM  HEAD  BKW  MARGIN 
No.  PUMP  WORKING  STANDBY  TOTAL  PUMP  PUMP 

GLR‐6 
8  GLR‐7 (Papi) & OHSR‐6C‐1  HSC  12594  3  2  5  4198  70  36  32.94  37.88 
(Kekarahi) 

GLR‐8, OHSR‐6 , OHSR‐6C, 
9  GLR‐7 (Papi)   VT  11904  2  1  3  5952  100  53  69.28  79.67 
OHSR‐6C‐2 & OHSR‐7A‐1 

OHSR 6A‐1  HSC  1033  1  1  2  1033  18  37  8.71  10.45 


 GLR‐8 (Tarauli 
10  OHSR‐6A & 6B , OHSR‐7B & 
Raja) 
6A‐2 , OHSR‐6A‐3  & OHSR‐ HSC  6526  2  1  3  3263  55  59  42.42  48.78 
8B 

OHSR‐9‐1  HSC  1333  2  1  3  667  12  81  12.71  15.25 


11  GLR‐9 (Nipraj)  
OHSR‐9‐3  HSC  1321  1  1  2  1321  23  34  10.22  12.27 

OHSR‐10, OHSR‐9A & OHSR‐
VT  4483  2  1  3  2242  38  74  36.76  42.27 
GLR‐10  9 
12 
(Kushara)  GLR‐11, GLR‐12, OHSR‐5B‐1, 
VT  23163  6  4  10  3861  65  42  35.69  41.04 
OHSR‐3B‐1 & OHSR‐3A‐3 

OHSR ‐3A‐1 & 3A‐2  HSC  1642  1  1  2  1642  28  33  12.08  14.49 


GLR‐11 
13 
(Jogani)  OHSR‐11B, OHSR‐4A & 
HSC  3421  3  2  5  1141  20  61  15.95  18.34 
OHSR‐7A‐2 

  55 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
PUMP KW AS PER DESIGN 
SL  TYPE OF  NO OF PUMPS  LPM /  LPS / 
FROM  TO  LPM  HEAD  BKW  MARGIN 
No.  PUMP  WORKING  STANDBY  TOTAL  PUMP  PUMP 

OHSR‐3‐1  VT  1204  1  1  2  1204  21  31  8.51  10.21 

GLR‐12   GLR‐13, OHSR‐2A, OHSR‐
14  VT  6643  2  1  3  3322  56  72  52.71  60.61 
(Khutana)  10A‐1 & OHSR‐10A‐2 
GLR‐14, OHSR‐3‐2 & 3‐3, 
OHSR‐11A‐1, OHSR‐11 &  VT  6847  2  1  3  3424  58  63  47.76  54.93 
OHSR‐1‐1 

OHSR‐ 11A   VT  678  1  1  2  678  12  37  5.80  7.55 


GLR‐13 ( 
15 
Beerkhurd) 
OHSR‐ 2 & OHSR‐2‐1   VT  2096  1  1  2  2096  35  105  48.04  55.25 

GLR ‐14  OHSR‐1, OHSR‐1A & OHSR‐
16  HSC  2750  2  1  3  1375  23  42  12.63  15.15 
(Sirsail)  1A‐1 

 
 
 
 

  56 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
1.4. Sourcing of Power 

Power supply source for sourcing of Grid power would be dedicated for clear water pumping station (CWR). It is envisaged to source 11 KV Grid power with 11
KV single circuit overhead line from the nearest 33/11 KV sub-station from power reliability point of view. This circuit is to be routed in existing ROW alongside
the main road from nearest 33/11 kV Substation to pumping station. This 11 KV overhead line is proposed to be terminated at Double Pole Structure with Air
Break Switch, D.O. Fuse, outdoor/indoor HT cable termination kit, HT metering arrangement with provision of VCB for control of Distribution Transformer.
The 11 KV source will be transformed to 415 volts in conjunction with 11/0.415 KV distribution transformer for sourcing of power to LT Panels for Raw water
Intake, WTP & MCWR pumping stations for pumping of clear water to all facilities. Distribution Transformer for this facility has been sized for continuous
operation at maximum rating with 80% loading from better efficiency point of view.

1.5. Load Estimation 

Electrical Load has been estimated for each facility as per the details given below‐ 
 
LT PANEL AS PER DESIGN ‐PATWADH PROJECT 
Sl.NO  LOCATION  LT PANEL DESCRIPTION  UNIT  QTY 
INTAKE WELL ‐ Incomer 2500 A ‐ 3nos, bus‐coupler 2500 A ‐ 1nos , motor feeder‐630A (6 
1  INTAKE WELL  Set  1 
Nos),  capacitor feeder , lighting feeder, Spare feeder  

2  WTP   WTP  ‐ Incomer 1250A ‐ 3nos, bus‐coupler 1250A ‐ 1nos ,  motor feeder‐200A (10 Nos),  Set  1 


capacitor feeder , lighting feeder, Spare feeder  
MCWR  ‐ Incomer 5000 A ‐ 3nos, bus‐coupler 5000 A ‐ 1 no , motor feeder‐500A (8 Nos), 
3  MCWR   motor feeder‐160A (6 Nos), motor feeder‐63A (2 Nos),capacitor feeder , lighting feeder,  Set  1 
Spare feeder  
GLR‐1 (Babhech) ‐ Incomer 320 A ‐ 3nos, bus‐coupler 320 A ‐ 1 no , motor feeder‐100A (4 
4  GLR‐1 (Babhech)  Set  1 
Nos), capacitor feeder , lighting feeder, Spare feeder  
GLR‐2 (Rudwali) ‐ Incomer 320 A ‐ 3nos, bus‐coupler 320 A ‐ 1 no , motor feeder‐100A (4 
5  GLR‐2 (Rudwali)  Set  1 
Nos), capacitor feeder , lighting feeder, Spare feeder  
GLR‐3 (Markundi) ‐ Incomer 6300 A ‐ 3nos, bus‐coupler 6300 A ‐ 1 no , motor feeder‐
6  GLR‐3 (Markundi)  Set  1 
630A (15 Nos), capacitor feeder , lighting feeder, Spare feeder  

  57 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
LT PANEL AS PER DESIGN ‐PATWADH PROJECT 
Sl.NO  LOCATION  LT PANEL DESCRIPTION  UNIT  QTY 
GLR‐4 (Lori) ‐ Incomer 1250 A ‐ 3nos, bus‐coupler 1250 A ‐ 1 no , motor feeder‐400A (3 
7  GLR‐4 (Lori)  Set  1 
Nos), motor feeder‐100A (2 Nos), capacitor feeder , lighting feeder, Spare feeder  
GLR‐5 (Ganguar) ‐ Incomer 2500 A ‐ 3nos, bus‐coupler 2500 A ‐ 1 no , motor feeder‐
8  GLR‐5 (Ganguar)  500A(4 Nos), Motor feeder‐200A(4 Nos), Motor feeder‐100A(2 Nos)capacitor feeder ,  Set  1 
lighting feeder, Spare feeder  

9  GLR ‐6 (kekarahi)  GLR ‐6 (kekarahi) ‐ Incomer 630 A ‐ 3nos, bus‐coupler 630 A ‐ 1 no , motor feeder‐160A (5  Set  1 


Nos), capacitor feeder , lighting feeder, Spare feeder  

10  GLR‐7(Papi)  GLR‐7(Papi) ‐ Incomer 1250 A ‐ 3nos, bus‐coupler 1250 A ‐ 1 no , motor feeder‐250A (3  Set  1 


Nos),  capacitor feeder , lighting feeder, Spare feeder  

11  GLR‐8  ( Tarauli Raja)  GLR‐8  ( Tarauli Raja) ‐ Incomer 630 A ‐ 3nos, bus‐coupler 630 A ‐ 1 no , motor feeder‐ Set  1 


160A (3 Nos), motor feeder‐100A (2 Nos), capacitor feeder , lighting feeder, Spare feeder  

12  GLR‐9 (Nipraj)   GLR‐9 (Nipraj)  ‐ Incomer 320 A ‐ 3nos, bus‐coupler 320 A ‐ 1 no , motor feeder‐100A (5  Set  1 


Nos), capacitor feeder , lighting feeder, Spare feeder  

13  GLR‐10 (Kushara)  GLR‐10 (Kushara) ‐ Incomer 1250 A ‐ 3nos, bus‐coupler 1250 A ‐ 1 no , motor feeder‐ Set  1 


160A(13 Nos) , capacitor feeder , lighting feeder, Spare feeder  

14  GLR‐11 (Jogani)  GLR‐11 (Jogani) ‐ Incomer 320 A ‐ 3nos, bus‐coupler 320 A ‐ 1 no , motor feeder‐63A (7  Set  1 


Nos), capacitor feeder , lighting feeder, Spare feeder  

15  GLR‐12 (Khutana)  GLR‐12 (Khutana) ‐ Incomer 1250 A ‐ 3nos, bus‐coupler 1250 A ‐ 1 no , motor feeder‐ Set  1 


250A (6 Nos), motor feeder‐63A (2 Nos),capacitor feeder , lighting feeder, Spare feeder  

16  GLR‐13 ( Beerkhurd)  GLR‐13 ( Beerkhurd) ‐ Incomer 630 A ‐ 3nos, bus‐coupler 630 A ‐ 1 no , motor feeder‐ Set  1 


250A (2 Nos),  motor feeder‐63A (2 Nos), capacitor feeder , lighting feeder, Spare feeder  

17  GLR‐14 (Sirsail)  GLR‐14 (Sirsail) ‐ Incomer 250 A ‐ 3nos, bus‐coupler 250 A ‐ 1 no , motor feeder‐100A (3  Set  1 


Nos), motor feeder‐63A (2 Nos), capacitor feeder , lighting feeder, Spare feeder  
 

  58 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
All electrical infra comprising of DT, DG set, all HT and LT cables for sourcing of power have been designed
and engineered based on for clear water pumping ultimate load demand. During intermediate load the no. of
working pumps may be lesser than no. pumps working pumps at ultimate load, however ratings of pumps
have been kept same for both intermediate & ultimate load demand. This proposal will avoid Grid power
source obstruction at the time of augmenting electrical infra from intermediate water demand to ultimate water
demand apart from avoiding huge expenditure in augmentation of existing equipments as the electrical infra
designed for higher load will take care initial lower load demand. This proposal though will entail slight higher
initial cost but will be benefitted in the long run in the following terms: -
1) It will avoid any obstruction in power availability for clear water availability to residents thus reliability of
water supply at all times.
2) There will be no duplication of expenditure for change in rating of DT, DG set, cable ratings and new LT
panels thus less costly

To sum up REPL has proposed electrical infra in terms of DT, HT cable, DG, LT cable and LT panel initially
for ultimate water demand whereas additional pumps & LT cable for sourcing of power to additional pumps
will be provided during ultimate load as per system requirement described above.

1.6. Equipment Selection Methodology: 

1) 11/3.3/0.415 KV, Distribution Transformer sizing : -


At Intake the motor rating is higher i.e. 355 kW hence suitable voltage level for such motor rating will be 3.3
kV to minimize huge voltage drops & losses. So 3.3 kV Switchgear panel have been considered for power
sourcing to MV motors at intake & selected transformer for same will be of 11/3.3 kV, also an auxiliary
transformer of 25 kVA, 11/.433kV to cater LT load has been proposed. However at WTP & MCWR a common
11 kV feeder will feed the separate 11/.433kV dist. Transformers proposed for each location. Main LT panels
have been proposed at WTP & MCWR, all of them will be sourced with grid power from seperate Distribution
Transformer.
To sum up, total 18 nos. Motor Pumps shall be required for pumping water. However, 12 nos. standby pumps
have also been planned in these stations but stand by Pumps have not been considered in assessment of
total power requirement. Moreover, some power will be required for area lighting, building illumination and for
control & instrumentation. Power requirement on this account will be very negligible and will not reflect much
on the sizing of major electrical equipments.
Normally pumps will operate on Grid Power but considering importance of water in day to day life, 100%
emergency power has been planned so that water can be pumped at all the times.
Rating of following major electrical equipment’s have been thus selected with consideration of maximum
rating of motor pumps and number of working pumps at a time and is described below:-
Rating of T/F for sourcing of power to Main LT Panel inter alia Pump Motors has been considered for ultimate
load requirement though pumps of various ratings are proposed.

  59 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
 
 
 
TRANSFORMER RATING AS PER DESIGN 
KVA Rating as 
S.NO  LOCATION  Unit  Qty  Remark 
per IS:1180 

1  INTAKE WELL  1250  Nos  2    

2  WTP+MCWR  2500  Nos  2 


 

3  GLR‐1 (Babhech)  160  Nos  2 


 

4  GLR‐2 (Rudwali)  100  Nos  2    

5  GLR‐3 (Markundi)  3500  Nos  2 


 
6  GLR‐4 (Lori)  500  Nos  2    

7  GLR‐5 (Ganguar)  1250  Nos  2    

8  GLR ‐6 (kekarahi)  315  Nos  2 


 
9  GLR‐7(Papi)  500  Nos  2    
GLR‐8  ( Tarauli 
10  315  Nos  2    
Raja) 
11  GLR‐9 (Nipraj)   160  Nos  2 
 
12  GLR‐10 (Kushara)  500  Nos  2    

13  GLR‐11 (Jogani)  160  Nos  2 


 
14  GLR‐12 (Khutana)  500  Nos  2    

15  GLR‐13 ( Beerkhurd)  315  Nos  2    

16  GLR‐14 (Sirsail)  100  Nos  2    

Total 32

 
 
 
 
 
 
 

  60 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
2) DG Sets Sizing :
As one MV switchgear of 3.3 kV voltage rating has been selected at intake hence DG set at intake will also
be of 3.3 kV but at other locations LT panels have been proposed for MCWR, these LT panels will be
sourced with DG power from separate LT DG sets to be provided along each LT panel. Hence load demands
on DG sets will be same as for Grid power.
Hence selected DG sets ratings will be as following:

DG SET RATING AS PER DESIGN 
DG Rating as 
S.NO  LOCATION  Unit  Qty  Remark 
per IS/BS 
1  INTAKE WELL  1250  Nos  1    
2  WTP +MCWR  2500  Nos  1    
3  GLR‐1 (Babhech)  125  Nos  1    
4  GLR‐2 (Rudwali)  125  Nos  1    

5  GLR‐3 (Markundi)  3500  Nos  1 


 
6  GLR‐4 (Lori)  500  Nos  1    
7  GLR‐5 (Ganguar)  1250  Nos  1    

8  GLR ‐6 (kekarahi)  320  Nos  1 


 
9  GLR‐7(Papi)  500  Nos  1    
GLR‐8  ( Tarauli 
10  320  Nos  1    
Raja) 
11  GLR‐9 (Nipraj)   125  Nos  1    
12  GLR‐10 (Kushara)  500  Nos  1    

13  GLR‐11 (Jogani)  160  Nos  1 


 
14  GLR‐12 (Khutana)  500  Nos  1    

15  GLR‐13 ( Beerkhurd)  320  Nos  1 


 
16  GLR‐14 (Sirsail)  125  Nos  1    
         Total 16   

These DG sets will be required for ultimate load demand and for emergency use though initial load demand
expected on the system will be less. Higher rating DG has been proposed from overall economic
considerations as described above
 
Apart from design calculations for Intake, MCWR other design calculations in a similar manner for other
CWR’s required for pumping clear water throughout entire network of water supply scheme have been done
on separate excel based design sheet.
 

  61 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
1.7. Technical Specifications of 11 KV VCB, Distribution transformer, DG sets and LT Panels 

Brief Technical specifications of 11 KV cable, 11 KV VCB, Distribution Transformer, DG sets & LT panels are
described as under: -
 
a. 11 KV Cable
 
6.35 / 11 kV (E) grade, XLPE insulated, stranded Aluminium conductor, galvanised steel flat strip / round wire
armoured, extruded PVC type ST2 sheathed, heavy duty cable (to be laid on wall surface with necessary
clamps / in existing cable trench / cable trays / conduit / pipe sleeves at road crossing or floor as per site
requirement) conforming to IS:7098 (Part-2) & IEC:60502 (Part-2) of size 3C x 120 sq.mm.
 
b. 11 KV Vacuum Circuit Breaker
 
11 KV outdoor type both side extensible, HV Switchgear panel confirming to IS-3427, IS-2516 (Part-I &
II.sec.1 ) & IEC-60056 & IEC-62271-100/200 for use on 3phase, 50 Hz, unearthed AC supply system and
having breaking/ ruptuing capacity of 500 MVA (26.3 kA for 3sec) complete with spring charged mechanism,
ON-OFF mechanical push button, operation counters, Breaker TNC switch, Breaker L/R switch, necessary
auxiliary switches, closing coil, shunt trip, protection relays & Indicators etc., complete.
The panel shall comprise of air insulated busbars provided with heat shrinkable PVC sleeves. The VCB
trolley shall comprise of three vacuum interrupters with epoxy support insulators and self aligning finger type
isolating contacts and necessary mechanical interlocks, safety shutters, isolating plugs. Enclosure shall be
openable from front as well as rear end.
The breaker shall be Manual cum motorised mechanism with following accessories.
a) 96 x 96 mm square flush mounting type Ammeter & Volt meter with selector switches
b) Multi function meter
c) Double core, cast resin type current transofrmer having ratio as per requirement, one core for metering &
one core for protection having required class of accuracy.
d) Instantaneous under voltage relay & Temperature rise tripping Relay,
e) Triple pole IDMTL two over current and one earth fault relay with current setting range 50-200% and 10-
40%
f) Electrical closing. Coil & shunt trip coil operating on 110 V DC.
g) Auxiliary relay for anti pumping device.
h) Three limb, drawout type, feeder connected, cast resin insulated, three phase Potential transformer having
ratio & burden as per reqirement& Class 0.5 accuracy.
i) Annunciator Windows, Common Hooter / Alarm bell operating on 230 AC/ 110 V DC
j) Cable boxes suitable to terminate 3 core XLPE cable of required size (As per design).
k) 230V A.C. to 110 V D.C.power pack for closing & tripping circuit common.
l) Breaker ON-OFF, Auto trip and spring charged indicators.  
m) Phase indicating & panel illumination lamps with plug socket.
  62 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
n) Space Heater with Thermostat.
 
c. 11/0.415 KV Distribution Transformer
 
Outdoor type, three phase, oil immerged, distribution transformer of required KVA & voltage ratio, copper
double wound, vector group - Dyn11, HV delta connected & LV star connected with neutral brought out
connected to provide separate earthing terminals, bushing / cable box on HV side and cable box on LV side
suitable for cables or bus duct as per requirement with standard fittings, conforming to IS: 1180 (Part-1) /
2014 with its latest amendment including first fill of transformer oil & following accessories.
(a) Oil conservator with filling holes with cap and prismatic oil level gauge.
(b) Silica Gel dehydrating breather charged with silica gel
(c) Oil drain cum sampling valve with plug
(d) Oil filter valve
(e) Lifting Eyes / Hooks / Lugs
(f) Two earthing terminal
(g) Diagram and rating plate
(h) Air release plug
(i) Explosion vent with diaphragm
(j) Thermometer pocket
(k) Four bi-directional plain roller with base channel with hauling holes
(l) Fixed / Separate type radiator banks
(m) Off circuit externally operated tapping switch (For rating < 1000 kVA)
(n) 100 mm stem type oil temperature indicator (For rating < 500 kVA)
(o) Bucholtz relay with shut off valve (For rating ≥ 500 KVA)
(p) 150 mm dial type oil temperature indicator with Alarm / Trip contact (For rating ≥ 500 kVA)
(q) 150 mm dial type winding temperature indicator with Alarm / Tip contact (For rating ≥ 1000 kVA)
(r) Marshalling box (For rating ≥ 500 kVA)
(s) 150 mm dia. magnetic type oil gauge (For rating ≥ 1600 kVA)
(t) Inspection cover & Jacking lugs (For rating ≥ 1600 kVA)
 
d. DG Set
 
Brief specifications of LT DG set is outlined as under:-
“1500 RPM, 0.8 PF, 415V, Three (3) phase and water cooled “sound proof” diesel generator set with acoustic
enclosure/canopy, complete with battery and battery charger, exhaust system with silencer and 990 liters Day
tank.”
Suitable rating MCCB with O/L, E/F, S/C Trip thermal based control releases complete with rotary handle
has been proposed within DG set to take care of cable fault and thus will be part of DG set and thus TPN
Bus Bars from LV bushings within Box will be directly terminated in MCCB.

  63 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

DG power will be sourced to LT Panel controlled by incomer MCCB with O/L, E/F, S/C Trip micro processor
based releases. This incomer switchgear will be electrically and mechanically interlocked with similar rating
Grid incomer so that one source is available at a time thus to avoid paralleling of two different sources.
 
e. LT Panel
Brief specification of LT Panel is outlined as under: -
“Three phase and neutral, 415 V, 4 wire free standing floor mounted single front, single door LT panel with IP-
54 degree of protection made out of 14 SWG (2mm) CRCA sheet after seven tank process and painted with
epoxy powder coating.”
Grid and DG power will be sourced to LT Panel controlled by respective incomer MCCB with O/L, E/F, S/C
Tripmicro processorbased releases i.e. separate for each source. These incomer switchgears will be
electrically and mechanically interlocked so that one source is available at a time thus to avoid paralleling of
two different sources.
The LT panel will be designed so that individual starter is housed in a separate segregated compartment
fixed or withdrawal type as per rating.
Outgoing ratings will be suitable for range of motor loads as shown in SLD below.
Type of starting of motor of various ratings to limit the staring torque/ current shall be as detailed below: -
Up to 7.5 kW Direct ON Line (DOL)
Above 7.5 kWupto 22 kW Star/Delta
Above 22 kW upto 55 kW Soft Starter
Above 55 kW Variable Frequency Drive (VFD)
This LT panel will be designed and constructed in compliance with IEC 439-3.
  
 
Power Factor Correction Capacitors: -

The load within the recycled water pumping station will be predominantly inductive and the power factor shall
be essentially corrected to 0.95 lagging or more as compliance to statutory regulations. It is, therefore,
proposed to provide Three (3) phase capacitors either with each motor circuit or at centralized location within
separate compartment in the same LT panel. The rating of capacitor shall be selected at the time of detailed
design to correct the power factor of system approaching to unity at all times when the associated drive is
operating at maximum duty point with automatic switching ‘ON & OFF’ operation. The LT capacitor can be oil
or synthetic mineral oil impregnated type with paper or paper & plastic film dielectric in an oil tight steel tank
complete with discharge resistances.

  64 | P a g e  
  PATWADH GOV DE
ETAIL PRO
OJECT REP
PORT    

Quantum of cap
pacitor units in terms of KVAR has b
been assesssed on the b
basis of emp
pirical formula given, as
er, and expla
unde ained in figure shown be
elow: -

KVAR requiired = KW (Tan ф1


ф - Tan ф2
2)
KW = Total lo
oad (Inductivve)
Cos Φ1 = Power Factor befo
ore improvem
ment
Cos Φ2 = Power Factor afterr improveme
ent.
 
The Power sourcing arrrangement in
n form of Singgle Line Diagraam is illustratted belowfor clarity

1.7.1
1. Voltage Drrop Calculatioons:    
Volta
age Drop in lieu of powe
er sourcing arrangemen
nt has been calculated tto support siizing of cablle. It will be
noted that the vo
oltage drop is
i within limits of 3.5% o
of rated volta
age at tail end.
age Drop forr Steady Sta
Volta ate Condition
n for 3 phase
e load = 1.73
32 x IL x L x (R cosΦ + X sinΦ)
IL= Full
F load currrent
L = Length of cable
c in mete
er
R = Approx. Co esistance at 70 oC in ohm
ond. A.C. Re m/m
X = Approx. Re
eactance of Cable
C at 50 Hz in ohms//m
Φ = Steady state powerr factor
cosΦ
Φ = sin(cos-1
sinΦ -
(cosΦ))

1.7.2
2. BOQ/Estim
mated Cost: 

Com
mplete BOQ//Estimated cost
c for end to end pow
wer solution is attached as annexurre. This cosst has been
show
wn in summa
ary sheet.

1.7.3
3. Quantity EEstimation 

The items requirred for prope


er execution of work hass been taken
n from variou
us SOR acco
ording to the
e design,
wings and ex
draw xperience, an
nd the quantity of the respective item
m has been workout. Th
he detail of th
he items
cove
ers in the esttimate has been
b mention
ned below.
a) Intake Structture
b) Raw
R water rising main network.
c) Water
W treatm
ment plant.
d) Treated
T er rising main network.
wate
  PATWADH GOV DETAIL PROJECT REPORT    

e) Overhead Service Reservoir.


f) Distribution Network.
g) Road Restoration work.
h) House connection

HYDRAULIC MODEL
Building a Model
Details required for building a model are as mentioned below, the same details have collected.
 GIS base map
 Pipeline: material, diameters, age, condition friction coefficient, Elevation details
 Valve details
 Consumer data
 Flow and pressure information
 Elevations
 Demand locations and patterns of large consumers

Activities Involved in Network Modeling

 Design criteria based on guidelines of CPHEEO manual.


 Collection of the data & drawing of existing for the DMA’s from concerned department. If data is not
available in concerned Department, then it is required to collect by physical survey. Drawing the water
supply network features from source to individual tap in the software itself or importing data from
CAD files, GIS files and data sheets including pipe line, water tanks, reservoir, valves etc. On the
backdrop of Geo-reference digitized map of the Project area including deletion and correction of data
any. Giving required attribute features of water networks collected or generated.
 Population forecasting, demand projection and demand allocation in various stages as specified by
client.
 Building the model and validate it with at least three base scenarios and as many as child scenarios for
the existing as well as proposed water supply network.
 The three base scenarios shall include present stage, intermediate stage and ultimate stage.
 Running the base as well as child scenarios in steady state and extended period simulation mode to
check the adequacy of system for continuous water supply.
 The child scenarios for various stages shall include existing water supply network, proposed water
supply network, peak demand supply, rehabilitation plan, calibration for existing networks, DMA
zone, Time of day (TOD) benefit etc.

  66 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

SALIENT FEATURES

  67 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

SALIENT FEATURES 
 
1. Name of State        :  Uttar Pradesh 
2. Name of District      :  Sonbhadra 
3. Name of Tehsil        :  Robatganj and Ghorawal  
4. Name of Block        :  Robatganj,Ghorawal and Chopan. 
5. Name of Programme      :  Bundelkhand/Vindhya Region and Quality 
  Affected Villages Piped Water Supply Programme. 
6. Name of Scheme      :  Patwadh  GOV Proposed Water  
Supply Scheme 
7. Nos. of Revenue Villages    :  663 
8. Following list shows 663 Villages which are selected for proposed surface piped water supply scheme. 

Sl  Sl  Sl 


Name of Revenue Villages  Name of Revenue Villages  Name of Revenue Villages 
No.  No.  No. 

1  Karia  33  Majurahi  65  Koladiha 

2  Tendua  34  Kanhari  66  Bharkana 

3  Barbaspur  35  Siwadar  67  Bhagahi 

4  Ghuwas  36  Bantara  68  Baidawar 

5  Basahi  37  Deogarha  69  Jamua 

6  Lali  38  Hinauti  70  Sonabarsa 

7  Mukkha  39  Parwania  71  Khagia 

8  Amilia  40  Bardiya  72  Musha 

9  Amilaudha  41  Rumma  73  Mandha 

10  Karsoata  42  Manhwa  74  Snihawal 

11  Lahas  43  Khajuari  75  Janar 

12  Sirsain  44  Harankhuri  76  Beerkala 

13  Fulwary  45  Meejhun  77  Dorihar 

14  Madhaka  46  Chandwa  78  Khardeur 

15  Samerwar  47  Bhainshi  79  Mohani 

16  Mahokhar  48  Sonhati  80  Beerkhurd 

  68 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Sl  Sl  Sl 


Name of Revenue Villages  Name of Revenue Villages  Name of Revenue Villages 
No.  No.  No. 

17  Ubha  49  Dulahatha  81  Baraudhi 

18  Pathartal  50  Bar  82  Beheri 

19  Karry  51  Seegra  83  Majhgawan Chauhan 

20  Rahi  52  Baijanath  84  Kanhi 

21  Purana  53  Gawnkunda  85  Dharmauli 

22  Ghoria  54  Satdwari  86  Keweta 

23  Semera Kala  55  Chigori  87  Khakh 

24  Semera Khurd  56  Domakhri  88  Mahvarioa 

25  Babhari  57  Dhura Kund  89  Kewali 

26  Marni  58  Amadhi  90  Khadaha 

27  Murtiya  59  Manjhiganwa Mishra  91  Munghri 

28  Dholo  60  Kon  92  Khutaha 

29  Amli Pokhar  61  Bauradih  93  Samara 

30  Sapahi  62  Jurauli Kolani  94  Hinauti 

31  Tenthuhar  63  Lilwahi  95  Parsauna Khurd 

32  Parsauna  64  Koharatha  96  Junia 

97  Pidaria  144  Bahorika  191  Deori Kalan 

98  Parhi  145  Sahpurwa Kalan  192  Kushai 

99  Satohan  146  Pagia  193  Burar Kalan 

100  Newari  147  Bharawah  194  Nauganwa Kalan 

101  Nakawai  148  Khairwa  195  Kewati 

102  Visundhary  149  Birmaua  196  Dehra 

103  Amilia  150  Chakahi  197  Theru 

104  Tilauli Kalana  151  Mukasim  198  Babura 

105  Khuthnia  152  Uachka  199  Pursotampur 

106  Geduri  153  Pandepokhar  200  Nauganwa Khurd 

107  Sahpurwa Khurd  154  Ranitara  201  Organai 

  69 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Sl  Sl  Sl 


Name of Revenue Villages  Name of Revenue Villages  Name of Revenue Villages 
No.  No.  No. 

108  Kamhria  155  Barimahewa  202  Durha 

109  Bnardewa  156  Dudhia  203  Deora Raja 

110  Kathapura  157  Bhulahi  204  Bagaura 

111  Silahta  158  Teprasivadati  205  Belatand 

112  Jogani  159  Salaia  206  Khajurikhurd 

113  Naudiha  160  Jorwria  207  Usarikalan 

114  Khodaichak  161  Asana  208  Ushrikhurd 

115  Bisun Pur  162  Patehara  209  Lasari Kalan 

116  Atarwa  163  Khairawa Raja  210  Khajurikala 

117  Teti  164  Rajkhar  211  Bhurkura 

118  Gotauli  165  Pateri  212  Masoe 

119  Juri  166  Tulsipur  213  Dabha 

120  Masiadinath  167  Jawahi  214  Lasari Khurd 

121  Chakari  168  Sirvit  215  Durawal Khurd 

122  Sawat  169  Etwa  216  Bhuli 

123  Jamaghne  170  Saranga  217  Hhrihar Pur 

124  Padri Kalan  171  Tedhwa  218  Kunan 

125  Maid  172  Sirsiajethi  219  Balua 

126  Masiha Pathan  173  Kolariya  220  Kasari 

127  Belkuri Murpharkat  174  Dharura  221  Enam 

128  Mureladih  175  Sitabahar  222  Aghwar 

129  Parari Kurd  176  Karkoll  223  Bagauari 

130  Kharuaun  177  Tekuria  224  Unchidih 

131  Karrivarai  178  Mahuriya  225  Shlaiya 

132  Kamhria  179  Babanauli  226  Barahda 

133  Rudauli  180  Barkara  227  Bagathri Kalna 

134  Dhoa  181  Jait  228  Bagathari Khurd 

  70 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Sl  Sl  Sl 


Name of Revenue Villages  Name of Revenue Villages  Name of Revenue Villages 
No.  No.  No. 

135  Tilauli Khurd  182  Tipara  229  Alahi Durawan 

136  Aruna  183  Manpur  230  Deori Khurd 

137  Vimauri  184  Khairahi  231  Durawal Kalna 

138  Velahi  185  Parashidubey  232  Shono 

139  Semari Misra  186  Bauar  233  Rajapurawa 

140  Khudia  187  Mamuna  234  Tiarashiv Datt 

141  Ataraila  188  Pawar  235  Chaktiara 

142  Purkhas  189  Kalwari  236  Karhi 

143  Phulawari  190  Burhr Khurd  237  Jeewar 

238  Bhagwantpur  285  Jurawat  332  Parsona 

239  Dahari  286  Tandi  333  Kamaharia 

240  Sihirshahi Parashe Dubey  287  Madainia  334  Birhulia 

241  Mahuresher  288  Jaderua  335  Mahulia 

242  Petrahi  289  Sirsiathkurai  336  Dehari 

243  Katawaria  290  Bharuha  337  Gouri Nisph 

244  Oani Chaubey  291  Bhadohi  338  Kathpurwa 

245  Orauli  292  Shirsia  339  Kasya Kalan 

246  Oanimishra  293  Atarauli Raja  340  Kushahi 

247  Deora  294  Sarauli  341  Bashdewa 

248  Jamashokar  295  Garaegarh  342  Kekarahi 

249  Kanhara  296  Dularu  343  Karaki 

250  Karma  297  Khairahi  344  Kasya Khurd 

251  Majhiganwa  298  Atarawa  345  Kucha Marwa 

252  Dohari  299  Baburahi  346  Khairawa No 2 

253  Welanow  300  Bantara  347  Kharahri 

254  Hinauti  301  Majhui  348  Shirkhora 

255  Koharaul  302  Mubarakpur  349  Jokahi 

  71 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Sl  Sl  Sl 


Name of Revenue Villages  Name of Revenue Villages  Name of Revenue Villages 
No.  No.  No. 

256  Khaira  303  Baghor  350  Machhalawa 

257  Kapura  304  Dhotwa  351  Aelahi 

258  Khairi  305  Gorahi  352  Hinauta 

259  Chotakapur  306  Khane Azampur  353  Amaulia 

260  Barsota  307  Kutulupur  354  Chakara 

261  Welkhuri  308  Lohra  355  Parahi 

262  Uchaka  309  Sukrit  356  Amdih 

263  Bhruha  310  Bhatulia  357  Bhawanipur 

264  Pipri No. 1  311  Bakahi  358  Khamriha 

265  Lohdhara  312  Sirsia  359  Nagnar Haraia 

266  Jamagane  313  Padar  360  Baghauri 

267  Sauli  314  Kairwa  361  Bat 

268  Chakauli  315  Pipara  362  Madhupur 

269  Asatali  316  Kushhi  363  Takia Mu.Dargah 

270  Noni  317  Garhwa  364  Gordiha 

271  Kingari  318  Mangurahi  365  Bahera 

272  Chhuta  319  Darah  366  Purainiya 

273  Kurashat  320  Jori  367  Jigana 

274  Eanam  321  Sheokari  368  Alahi 

275  Petrahi  322  Murala Dih  369  Bargawn 

276  Umarikalna  323  Khekhara  370  Bishbhrpur 

277  Mishra  324  Basawa Nisph  371  Parsona 

278  Gajana  325  Tinatali  372  Pateara 

279  Naraina  326  Tilya  373  Domariya 

280  Arangi  327  Bhagauti  374  Rampur 

281  Gheuri  328  Papi  375  Baheri 

282  Dilahi  329  Patela  376  Kaithi 

  72 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Sl  Sl  Sl 


Name of Revenue Villages  Name of Revenue Villages  Name of Revenue Villages 
No.  No.  No. 

283  Karanwah  330  Madar  377  Khrehari 

284  Bahera  331  Baghi  378  Deogarh 

379  Kushi  426  Urali  473  Dugaulia 

380  Tendee  427  Khewatha  474  Shikari 

381  Pakari  428  Mango  475  Bansdih 

382  Lashra  429  Mahokhar  476  Bichhwar 

383  430  477 


Majhigaon Chaubey  Chandauli  Marachhi 
384  Shirpalpur  431  Tendu  478  Jamaganwa 

385  Majhigaon Mishra  432  Mahuari  479  Umarikhurd 

386  Ghuaskalan  433  Kamahar Dih  480  Kooran 

387  Ganguar  434  Bahura  481  Baraganwa 

388  Bagadiha  435  Papi  482  Gobariya 

389  Tirnahi  436  Majhiganwa  483  Barauli 

390  Beechhi  437  Raghunathpur  484  Shahganj 

391  Ghuashkurd  438  Bharganw  485  Sahuar 

392  Amauli  439  Bhunari  486  Sohdaul 

393  Shuhali  440  Raiwari  487  Manhawan 

394  Bithgon Nishoh  441  Bajotara  488  Amahar 

395  Bithgawn Nishph  442  Amahata Amahti  489  Pipari No 2 

396  Dharnipur  443  Beechhiya  490  Barnwa 

397  Karari  444  Khatauli  491  Onauli 

398  Mokarshim  445  Bhandar Khurd  492  Kushra 

399  Palikalna  446  Baghari  493  Thuter 

400  Darari  447  Bahuar  494  Tiwar 

401  Pipari  448  Bashauli  495  Adaura 

402  Belwa  449  Bashuari  496  Orhatha 

403  Lakhan Purwa  450  Tilauli  497  Raipura 

  73 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Sl  Sl  Sl 


Name of Revenue Villages  Name of Revenue Villages  Name of Revenue Villages 
No.  No.  No. 

404  Garawa  451  Amauli  498  Rajpur 

405  Bhruiya  452  Mahuar Khurd  499  Shenduri 

406  Goithari  453  Patehra  500  Barak 

407  Jamuanua  454  Mahuar Kalna  501  Shonwat 

408  Dhuriya  455  Karauli  502  Shonauti 

409  Jamaganwa  456  Gordiha  503  Divar 

410  Nai Basti  457  Nipraj  504  Khajaraul 

411  Ratawal  458  Muther  505  Bhairawa 

412  Mahuaon  459  Kamojee  506  Majhali 

413  Hinauti  460  Marhra  507  Mushrdhara 

414  Hona  461  Beohari  508  Atarauli Kalan 

415  Hinduhari  462  Mahuali  509  Garwa 

416  Barwan  463  Khchar  510  Kewata 

417  Majhi Ganwa  464  Parashipandy  511  Tendui 

418  Shemari Bishunlal  465  Shajua  512  Obaradih 

419  Babhanauli Khurd  466  Shathi  513  Domahar 

420  Bhogar  467  Juriya  514  Selahata 

421  Babhanauli Kalan  468  Judauri Pardhan  515  Kusinisph 

422  Shango  469  Bherawal  516  Mhunyw Pandy 

423  Pashi Kalana  470  Ganguhar  517  Chorat 

424  Amokhr  471  Renua  518  Mahuna Gosani 

425  Pashi Khurd  472  Kolakari  519  Kunda 

520  Panauli  566  Piparwar  612  Shemara 

521  Sadari  567  Bisrekhi  613  Shahijan Kalna 

522  Jinhora  568  Jaimohara  614  Shindhora 

523  Naidiha  569  Sirsai  615  Bichapai 

524  Aurahi  570  Raikara  616  Ormaura 

  74 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Sl  Sl  Sl 


Name of Revenue Villages  Name of Revenue Villages  Name of Revenue Villages 
No.  No.  No. 

525  Sidhi  571  Majhagawan  617  Lori 

526  Naunia  572  Naugai  618  Pushuli 

527  Athauna  573  Uchdih  619  Amarati 

528  Bhgawas  574  Lakshimanpur  620  Gorari 

529  Chausara  575  Chain  621  Barauli 

530  Kharera  576  Naugawan  622  Meuri Khurd 

531  Morahi  577  Bhawana  623  Jamgane 

532  Barauli  578  Dewerikhurd  624  Ghurma 

533  Khirahata  579  Halwai  625  Kaithi 

534  Garama  580  Bagpokhar  626  Baraila 

535  Gurwal  581  Bhanswar  627  Petrahi 

536  Bandha  582  Sahdeapaidar  628  Kamarhi 

537  Belwania  583  Magaradaha  629  Baghnaree 

538  Karaundia  584  Visahar  630  Belaha 

539  Rampur  585  Raunp  631  Patharaha 

540  Panti  586  Churk  632  Gangti 

541  Dhanawal  587  Shahijan Khurd  633  Paika 

542  Barsot  588  Musahee  634  Kewata 

543  Lohari  589  Kura  635  Rajdhan 

544  Ahraura  590  Teyara Nayak  636  Bachawar 

545  Sotil  591  Peetha  637  Mhowoh Khurd 

546  Jaimohra  592  Akachor  638  Kamharia 

547  Pateri  593  Beejauli  639  Belcupp 

548  Bakuli  594  Meuri Kalan  640  Mhowon Kalna 

549  Durkhuli  595  Arauly  641  Chihurali 

550  Guretha  596  Shajaur  642  Baluee 

551  Rajin  597  Lakhanwar Kalna  643  Maitapur 

  75 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Sl  Sl  Sl 


Name of Revenue Villages  Name of Revenue Villages  Name of Revenue Villages 
No.  No.  No. 

552  Odar  598  Mangurahee  644  Kargara 

553  Thiwan  599  Kusamha  645  Bhbhaech 

554  Dhuria  600  Bijary Duban  646  Karki 

555  Kusmaha  601  Harhuna  647  Guradah 

556  Dewerikatha  602  Atarauli Khurd  648  Redia 

557  Peroh  603  Bijary Patkhan  649  Bandhwa 

558  Dhorkary  604  Bahuarah  650  Bhgawa 

559  Dharsara  605  Lakhanwar Khurd  651  Kurhul 

560  Marasara  606  Kharhari  652  Adalganj 

561  Dumaria Mithailal  607  Pali  653  Salkhan 

562  Silwar  608  Dhobahi  654  Awayee 

563  Dumaribharaulia  609  Bharganwa  655  Markundi 

564  Bharauli  610  Bhandra Kalan  656  Rudawali 

565  Dhadhi  611  Chhapaka  657  Patwdh 

658  Belach  660  Kandhaura  662  Aluar 

659  Pakari  661  Kanach  663  Bhadohi. 

  76 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

9.  Rate of water supply  :  55 LPCD (As per FD SWSM Letter No.: 745/W‐17/2020 Dt. 16.07.2020 


      (Excluding Allowance for unaccounted loss of water) 
 
Scheme  Patwadh 
Water 
Water Demand Consideration for  Basis  @55 LPCD & 2053 
Demand 
Hydraulic  Population  1211660 
Basis 
LPCD  MLD 
Raw Water Demand  55/85/90  71.90  129 
Water Treatment Plant  55/85/95  68.11  120  
CWPM transmission  55/85  64.71   
OHR Demand/Distribution Design  55/85  64.71   
Distribution  Network  Demand  Including  55/85  64.71   
Losses 
End User/Per capita    55   
 
10.  Nature of Source    :  Surface Water 
11.  Name of Source    :  Son River 
12.  Source of Development    :  Intake Tower & Intake Sub‐station. 
 
 
 

  77 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
 
13.  VILLAGES OF PROJECT IN ROBATGANJ , GHORAWAL AND CHOPAN BLOCK AND THEIR CENSUS STATISTICS

Census Population SC/ST HH


Sr.No Village Name
1971 1981 1991 2001 2011 2011 2011

1 Karia 544 672 959 1345 1938 1487 325

2 Tendua 293 540 705 1010 1284 425 171

3 Barbaspur 187 172 240 352 468 114 60

4 Ghuwas 273 458 741 1291 1929 1349 319

5 Basahi 181 205 257 422 537 203 98

6 Lali 297 326 394 566 859 692 134

7 Mukkha 179 201 266 432 614 344 102

8 Amilia 49 52 94 81 332 239 53

9 Amilaudha 215 221 300 449 653 370 104

10 Karsoata 262 313 393 540 707 530 114

11 Lahas 235 289 388 516 798 517 127

12 Sirsain 390 229 840 992 1278 915 205

13 Fulwary 845 331 431 547 715 89 119

14 Madhaka 290 368 452 590 744 552 144

15 Samerwar 22 59 108 209 336 165 50

16 Mahokhar 101 101 256 386 534 67 77

17 Ubha 170 253 366 558 766 654 130

18 Pathartal 72 154 243 394 486 246 85

19 Karry 0 0 0 0 30 30 10

20 Rahi 196 303 518 713 925 361 149

21 Purana 478 904 1131 1563 2052 1163 368

  78 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Census Population SC/ST HH


Sr.No Village Name
1971 1981 1991 2001 2011 2011 2011

22 Ghoria 99 77 174 340 484 451 83

23 Semera Kala 108 79 158 258 323 284 58

24 Semera Khurd 0 0 0 0 24 24 5

25 Babhari 669 689 466 644 915 847 158

26 Marni 25 60 171 258 492 388 97

27 Murtiya 579 689 1040 1493 1998 937 311

28 Dholo 90 172 304 630 921 708 159

29 Amli Pokhar 133 219 347 596 863 519 134

30 Sapahi 65 117 196 380 536 406 82

31 Tenthuhar 271 380 787 1140 1583 1029 254

32 Parsauna 891 1278 1777 2625 3422 2654 569

33 Majurahi 178 148 181 279 370 352 61

34 Kanhari 589 774 1032 1385 2095 1794 364

35 Siwadar 357 616 958 1818 2207 1412 338

36 Bantara 28 33 47 45 87 0 17

37 Deogarha 301 355 437 666 864 737 157

38 Hinauti 163 60 1296 1800 2304 1513 414

39 Parwania 655 882 1196 1599 2135 1733 339

40 Bardiya 342 638 913 1525 2202 1086 419

41 Rumma 138 183 243 322 429 338 78

42 Manhwa 465 635 823 1181 1365 956 235

43 Khajuari 11 22 58 87 119 88 21

44 Harankhuri 190 84 364 484 595 72 102

  79 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Census Population SC/ST HH


Sr.No Village Name
1971 1981 1991 2001 2011 2011 2011

45 Meejhun 271 328 410 479 637 272 96

46 Chandwa 21 32 45 71 85 60 17

47 Bhainshi 70 90 113 150 177 144 41

48 Sonhati 85 123 179 256 382 189 88

49 Dulahatha 112 156 200 303 317 208 58

50 Bar 632 881 1194 1713 2185 1613 323

51 Seegra 25 19 23 42 54 39 11

52 Baijanath 140 194 321 401 552 397 84

53 Gawnkunda 132 165 195 256 268 206 42

54 Satdwari 252 329 406 558 610 268 84

55 Chigori 242 374 515 679 928 920 112

56 Domakhri 478 655 806 1024 1411 788 233

57 Dhura Kund 159 236 336 518 678 114 105

58 Amadhi 87 130 185 260 360 307 65

Manjhiganwa
59 156 208 282 371 517 287 78
Mishra

60 Kon 0 0 0 12 17 0 3

61 Bauradih 56 72 97 118 173 173 26

62 Jurauli Kolani 314 408 634 817 1016 933 210

63 Lilwahi 67 159 320 873 1140 520 190

64 Koharatha 572 768 967 1378 1507 1066 241

65 Koladiha 460 506 556 400 591 265 113

66 Bharkana 322 381 773 974 1257 750 251

  80 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Census Population SC/ST HH


Sr.No Village Name
1971 1981 1991 2001 2011 2011 2011

67 Bhagahi 80 107 132 191 197 136 20

68 Baidawar 0 0 0 0 25 0 3

69 Jamua 0 0 0 9 40 20 6

70 Sonabarsa 0 0 0 0 2 0 1

71 Khagia 346 484 634 944 1067 497 171

72 Musha 195 262 336 471 550 229 83

73 Mandha 372 394 417 339 442 219 82

74 Snihawal 201 184 184 153 179 111 27

75 Janar 77 115 171 259 378 135 61

76 Beerkala 127 219 348 646 852 66 159

77 Dorihar 323 444 613 841 1166 829 179

78 Khardeur 375 457 608 964 1261 625 202

79 Mohani 47 96 122 244 353 268 56

80 Beerkhurd 47 80 129 231 336 86 51

81 Baraudhi 111 247 307 486 603 554 123

82 Beheri 116 154 215 315 417 205 65

Majhgawan
83 250 295 325 571 651 406 98
Chauhan

84 Kanhi 655 788 948 1140 1373 467 238

85 Dharmauli 308 424 517 637 881 325 123

86 Keweta 330 378 520 742 837 483 142

87 Khakh 110 144 216 365 431 297 73

88 Mahvarioa 166 231 339 444 497 200 79

  81 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Census Population SC/ST HH


Sr.No Village Name
1971 1981 1991 2001 2011 2011 2011

89 Kewali 317 412 541 698 932 388 165

90 Khadaha 61 171 113 209 280 241 44

91 Munghri 258 322 461 633 791 469 129

92 Khutaha 793 1100 1526 2360 3049 1799 577

93 Samara 52 132 188 265 364 209 65

94 Hinauti 44 60 18 24 31 0 4

95 Parsauna Khurd 0 0 31 47 99 99 19

96 Junia 289 360 466 558 777 277 122

97 Pidaria 290 455 687 960 1309 399 179

98 Parhi 97 173 289 543 794 237 134

99 Satohan 363 537 878 1177 1631 795 246

100 Newari 562 837 1130 1887 2500 1406 408

101 Nakawai 36 89 158 213 335 155 53

102 Visundhary 427 1060 1380 2393 3295 1683 551

103 Amilia 49 52 94 81 809 524 163

104 Tilauli Kalana 1308 1541 2289 2920 3821 1561 652

105 Khuthnia 386 382 721 1143 1421 419 210

106 Geduri 66 94 76 122 116 0 15

107 Sahpurwa Khurd 0 20 80 127 192 45 30

108 Kamhria 91 20 73 91 137 9 22

109 Bnardewa 300 259 612 800 1003 671 170

110 Kathapura 85 145 215 295 401 17 54

111 Silahta 436 484 681 860 1087 615 190

  82 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Census Population SC/ST HH


Sr.No Village Name
1971 1981 1991 2001 2011 2011 2011

112 Jogani 1035 1129 1602 2123 2453 801 425

113 Naudiha 91 160 220 259 341 75 59

114 Khodaichak 0 0 0 3 14 0 4

115 Bisun Pur 43 59 69 108 109 45 19

116 Atarwa 101 191 209 352 426 158 88

117 Teti 67 90 122 160 248 0 24

118 Gotauli 71 97 139 181 219 39 36

119 Juri 206 135 204 189 246 65 47

120 Masiadinath 185 238 337 388 501 136 57

121 Chakari 0 191 92 92 85 0 14

122 Sawat 369 435 554 601 719 129 129

123 Jamaghne 228 696 225 264 353 88 76

124 Padri Kalan 32 74 125 156 256 54 41

125 Maid 0 24 107 163 251 154 44

126 Masiha Pathan 167 217 280 367 436 360 78

Belkuri
127 202 207 267 202 257 183 46
Murpharkat

128 Mureladih 724 917 1136 1470 1739 489 294

129 Parari Kurd 0 58 84 136 271 46 44

130 Kharuaun 331 497 705 1146 1390 443 225

131 Karrivarai 56 167 787 976 1098 460 186

132 Kamhria 432 668 164 253 332 198 62

133 Rudauli 95 142 175 257 326 217 54

  83 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Census Population SC/ST HH


Sr.No Village Name
1971 1981 1991 2001 2011 2011 2011

134 Dhoa 501 606 711 887 975 449 167

135 Tilauli Khurd 56 64 68 110 190 8 32

136 Aruna 269 399 682 857 1173 533 165

137 Vimauri 235 248 452 639 761 219 132

138 Velahi 66 126 214 456 576 248 76

139 Semari Misra 315 431 488 575 685 231 115

140 Khudia 200 263 314 405 525 151 90

141 Ataraila 108 144 200 142 148 46 22

142 Purkhas 548 1036 1485 1895 2324 1048 397

143 Phulawari 328 331 664 825 1113 539 206

144 Bahorika 153 248 303 369 494 151 87

145 Sahpurwa Kalan 59 111 169 212 285 7 31

146 Pagia 610 890 1207 1885 2170 319 304

147 Bharawah 179 152 535 767 1089 306 167

148 Khairwa 73 89 127 158 234 0 32

149 Birmaua 18 73 97 83 149 4 22

150 Chakahi 75 131 196 389 395 124 66

151 Mukasim 0 529 687 1182 1561 584 234

152 Uachka 126 164 227 350 427 308 71

153 Pandepokhar 291 396 564 810 1052 384 180

154 Ranitara 371 485 688 1050 1329 521 206

155 Barimahewa 768 1023 1379 1771 2478 471 367

156 Dudhia 242 285 344 483 629 188 100

  84 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Census Population SC/ST HH


Sr.No Village Name
1971 1981 1991 2001 2011 2011 2011

157 Bhulahi 0 52 93 111 144 7 20

158 Teprasivadati 423 97 449 634 702 237 106

159 Salaia 0 0 0 2 11 0 3

160 Jorwria 582 784 1012 1419 1675 584 293

161 Asana 199 255 317 419 489 18 77

162 Patehara 282 358 451 577 714 38 102

163 Khairawa Raja 90 89 91 110 128 15 12

164 Rajkhar 74 20 26 28 44 0 9

165 Pateri 23 21 300 371 435 154 73

166 Tulsipur 0 17 25 34 34 0 6

167 Jawahi 143 173 226 250 430 11 56

168 Sirvit 800 1069 1380 1908 2290 1059 412

169 Etwa 0 0 0 19 56 52 11

170 Saranga 806 1140 1514 2017 2382 597 427

171 Tedhwa 18 647 36 65 88 0 15

172 Sirsiajethi 451 645 900 1162 1300 488 225

173 Kolariya 191 177 348 530 646 443 100

174 Dharura 247 574 721 995 1426 423 218

175 Sitabahar 253 295 461 558 557 210 88

176 Karkoll 431 648 852 1237 1455 419 267

177 Tekuria 664 871 1101 1498 1751 904 329

178 Mahuriya 256 260 425 430 529 44 92

179 Babanauli 140 259 479 886 1517 414 244

  85 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Census Population SC/ST HH


Sr.No Village Name
1971 1981 1991 2001 2011 2011 2011

180 Barkara 195 275 387 544 838 407 158

181 Jait 295 385 502 655 808 355 132

182 Tipara 157 363 273 325 386 349 71

183 Manpur 832 1054 1336 1694 2195 167 417

184 Khairahi 170 140 214 319 422 39 90

185 Parashidubey 316 354 396 443 482 130 85

186 Bauar 102 145 206 293 406 85 84

187 Mamuna 0 461 557 749 975 326 163

188 Pawar 410 498 605 735 951 398 195

189 Kalwari 27 50 91 167 241 46 40

190 Burhr Khurd 577 605 634 664 804 307 126

191 Deori Kalan 151 199 234 367 463 144 95

192 Kushai 63 54 261 361 460 71 72

193 Burar Kalan 336 445 585 843 945 358 155

194 Nauganwa Kalan 147 174 213 266 334 40 54

195 Kewati 224 314 440 616 596 176 112

196 Dehra 53 71 95 127 152 128 27

197 Theru 124 172 239 333 392 0 42

198 Babura 112 154 211 289 387 0 57

199 Pursotampur 62 100 153 226 236 0 46

200 Nauganwa Khurd 240 307 393 503 596 0 103

201 Organai 489 602 761 1145 1247 339 176

202 Durha 0 0 55 94 153 20 20

  86 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Census Population SC/ST HH


Sr.No Village Name
1971 1981 1991 2001 2011 2011 2011

203 Deora Raja 88 110 179 210 229 85 37

204 Bagaura 390 455 531 620 765 332 146

205 Belatand 448 658 861 1331 1778 193 271

206 Khajurikhurd 137 144 149 229 302 47 49

207 Usarikalan 299 370 504 571 606 0 112

208 Ushrikhurd 257 287 301 349 497 254 85

209 Lasari Kalan 0 372 392 528 655 138 115

210 Khajurikala 157 196 207 266 364 222 54

211 Bhurkura 0 171 260 351 486 160 86

212 Masoe 0 349 475 650 858 23 153

213 Dabha 0 471 565 689 799 167 119

214 Lasari Khurd 0 0 0 9 6 0 1

215 Durawal Khurd 384 453 489 589 640 226 128

216 Bhuli 461 0 173 217 227 34 37

217 Hhrihar Pur 238 234 272 293 400 34 47

218 Kunan 0 144 131 164 185 137 37

219 Balua 0 0 62 102 180 1 37

220 Kasari 474 27 21 26 39 0 8

221 Enam 597 83 773 1119 1282 363 209

222 Aghwar 221 228 194 273 367 15 55

223 Bagauari 2 4 7 14 45 28 8

224 Unchidih 125 453 455 692 751 390 140

225 Shlaiya 0 0 451 471 731 348 125

  87 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Census Population SC/ST HH


Sr.No Village Name
1971 1981 1991 2001 2011 2011 2011

226 Barahda 194 0 363 422 525 166 121

227 Bagathri Kalna 149 191 243 328 490 449 104

228 Bagathari Khurd 17 59 139 177 294 212 65

229 Alahi Durawan 0 32 1 95 116 116 23

230 Deori Khurd 95 100 245 276 429 154 75

231 Durawal Kalna 415 503 542 696 718 256 179

232 Shono 63 57 77 106 130 30 22

233 Rajapurawa 0 68 68 101 117 45 15

234 Tiarashiv Datt 423 97 103 158 199 112 33

235 Chaktiara 5 0 5 8 8 0 2

236 Karhi 39 80 127 181 238 127 43

237 Jeewar 136 140 188 296 390 238 59

238 Bhagwantpur 90 139 169 211 248 57 51

239 Dahari 0 0 354 453 654 207 114

Sihirshahi
240 0 0 0 0 2 0 1
Parashe Dubey

241 Mahuresher 295 325 358 394 467 237 89

242 Petrahi 177 235 252 275 418 140 63

243 Katawaria 489 574 621 813 1013 336 131

244 Oani Chaubey 188 212 276 350 339 157 63

245 Orauli 315 456 525 685 745 295 145

246 Oanimishra 265 315 350 430 469 77 84

247 Deora 221 232 235 354 405 258 70

  88 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Census Population SC/ST HH


Sr.No Village Name
1971 1981 1991 2001 2011 2011 2011

248 Jamashokar 219 210 201 192 246 195 47

249 Kanhara 87 133 204 314 290 143 48

250 Karma 80 139 243 425 575 335 88

251 Majhiganwa 209 262 328 410 487 235 90

252 Dohari 171 216 223 341 427 127 74

253 Welanow 0 222 278 408 601 460 105

254 Hinauti 60 66 73 81 43 0 12

255 Koharaul 116 147 182 268 348 137 57

256 Khaira 274 310 351 511 609 296 99

257 Kapura 0 98 78 112 137 27 27

258 Khairi 54 45 64 87 79 27 14

259 Chotakapur 105 0 196 304 431 81 84

260 Barsota 119 130 502 630 810 312 142

261 Welkhuri 195 339 153 343 462 94 82

262 Uchaka 126 164 671 962 1138 69 188

263 Bhruha 215 0 405 539 733 215 115

264 Pipri No. 1 166 242 286 389 458 239 84

265 Lohdhara 15 40 74 124 212 76 35

266 Jamagane 247 267 369 567 608 169 96

267 Sauli 0 15 23 86 118 41 26

268 Chakauli 70 101 125 175 261 176 41

269 Asatali 34 57 66 117 163 88 28

270 Noni 277 344 409 437 680 438 117

  89 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Census Population SC/ST HH


Sr.No Village Name
1971 1981 1991 2001 2011 2011 2011

271 Kingari 349 424 673 944 1232 38 170

272 Chhuta 53 123 183 272 328 66 56

273 Kurashat 239 285 358 415 476 48 87

274 Eanam 70 707 170 172 255 156 45

275 Petrahi 180 256 352 467 632 329 101

276 Umarikalna 307 385 434 575 666 164 113

277 Mishra 3 33 35 37 66 6 10

278 Gajana 10 19 24 50 77 38 15

279 Naraina 0 240 310 407 489 186 82

280 Arangi 274 355 477 686 817 380 130

281 Gheuri 175 233 250 267 342 98 52

282 Dilahi 219 320 468 685 997 162 118

283 Karanwah 76 98 134 163 249 24 33

284 Bahera 681 1012 1243 1164 2370 300 393

285 Jurawat 187 237 300 380 465 126 85

286 Tandi 0 103 75 144 230 14 32

287 Madainia 274 334 414 588 693 87 92

288 Jaderua 808 1095 1536 2137 2630 1156 448

289 Sirsiathkurai 2225 2832 4010 6001 7289 2344 1208

290 Bharuha 215 313 359 487 557 254 94

291 Bhadohi 23 19 144 174 207 0 36

292 Shirsia 298 389 0 13 14 14 3

293 Atarauli Raja 158 118 211 342 349 126 60

  90 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Census Population SC/ST HH


Sr.No Village Name
1971 1981 1991 2001 2011 2011 2011

294 Sarauli 481 722 1083 1624 1970 257 333

295 Garaegarh 321 0 554 840 1148 281 187

296 Dularu 0 27 13 27 27 2 6

297 Khairahi 170 962 1299 1830 2469 427 314

298 Atarawa 150 268 380 463 699 60 85

299 Baburahi 244 350 604 683 954 159 127

300 Bantara 498 595 711 850 1016 418 182

301 Majhui 353 493 688 961 1342 436 201

302 Mubarakpur 599 836 1167 1630 2277 1262 397

303 Baghor 329 460 643 898 1255 575 160

304 Dhotwa 51 70 97 135 188 39 38

305 Gorahi 643 898 1255 1753 2448 450 367

306 Khane Azampur 204 285 398 556 776 255 153

307 Kutulupur 247 346 484 677 946 49 142

308 Lohra 1798 2511 3507 4899 6843 3057 1154

309 Sukrit 1813 2532 3536 4939 6899 1908 1176

310 Bhatulia 601 816 1029 1419 1636 223 282

311 Bakahi 359 469 548 810 962 265 148

312 Sirsia 300 394 518 681 928 245 153

313 Padar 0 123 355 465 515 330 103

314 Kairwa 0 79 154 194 225 106 28

315 Pipara 363 423 487 460 472 150 98

316 Kushhi 69 98 140 200 247 0 27

  91 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Census Population SC/ST HH


Sr.No Village Name
1971 1981 1991 2001 2011 2011 2011

317 Garhwa 44 70 111 175 231 0 33

318 Mangurahi 124 176 249 352 413 138 80

319 Darah 0 131 231 280 328 134 65

320 Jori 0 0 386 595 712 258 112

321 Sheokari 243 169 458 633 709 46 106

322 Murala Dih 0 0 0 32 24 1 5

323 Khekhara 196 311 429 635 606 239 100

324 Basawa Nisph 222 296 350 527 636 167 114

325 Tinatali 392 570 780 1093 1207 110 157

326 Tilya 306 277 524 735 870 112 129

327 Bhagauti 200 287 387 590 691 246 95

328 Papi 221 322 450 683 872 135 135

329 Patela 78 95 117 141 176 144 21

330 Madar 296 336 451 570 731 66 104

331 Baghi 290 293 454 727 786 138 129

332 Parsona 126 183 175 268 277 54 46

333 Kamaharia 18 20 59 88 129 0 23

334 Birhulia 137 159 253 328 363 181 58

335 Mahulia 92 126 111 152 197 65 33

336 Dehari 174 201 314 435 533 105 84

337 Gouri Nisph 231 259 381 538 610 299 119

338 Kathpurwa 85 94 218 317 420 30 55

339 Kasya Kalan 189 242 312 494 596 246 108

  92 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Census Population SC/ST HH


Sr.No Village Name
1971 1981 1991 2001 2011 2011 2011

340 Kushahi 94 103 81 120 143 33 25

341 Bashdewa 200 281 326 507 622 360 102

342 Kekarahi 541 962 1023 1451 1877 359 325

343 Karaki 791 412 634 1160 1452 750 209

344 Kasya Khurd 106 132 142 205 264 123 44

345 Kucha Marwa 166 207 279 335 472 95 77

346 Khairawa No 2 0 0 19 23 29 0 6

347 Kharahri 0 12 30 36 57 0 7

348 Shirkhora 15 8 18 43 102 3 17

349 Jokahi 47 50 78 198 343 54 62

350 Machhalawa 83 112 121 152 152 0 22

351 Aelahi 670 796 943 1122 1324 423 216

352 Hinauta 531 744 1042 1460 1826 592 239

353 Amaulia 228 384 340 569 607 132 100

354 Chakara 231 350 410 617 669 114 113

355 Parahi 1585 1720 1866 2024 2195 582 354

356 Amdih 1111 1204 1305 1415 1534 525 254

357 Bhawanipur 1719 1865 2023 2194 2379 687 382

358 Khamriha 797 864 937 1016 1102 414 178

359 Nagnar Haraia 2790 3025 3280 3557 3857 1590 661

360 Baghauri 127 138 150 163 177 19 29

361 Bat 2622 2842 3081 3340 3621 707 627

362 Madhupur 7025 7617 8259 8955 9710 1781 1515

  93 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Census Population SC/ST HH


Sr.No Village Name
1971 1981 1991 2001 2011 2011 2011

363 Takia Mu.Dargah 1755 1903 2063 2237 2426 995 425

364 Gordiha 198 268 251 415 434 50 76

365 Bahera 76 101 135 123 206 20 23

366 Purainiya 2 29 72 125 210 26 42

367 Jigana 394 485 571 698 717 236 154

368 Alahi 3 52 71 97 151 32 28

369 Bargawn 0 416 401 482 659 216 109

370 Bishbhrpur 0 16 70 158 208 0 31

371 Parsona 0 0 0 68 126 48 23

372 Pateara 39 45 82 129 154 23 27

373 Domariya 133 182 174 229 297 78 56

374 Rampur 237 312 427 462 579 0 109

375 Baheri 109 144 190 250 291 124 38

376 Kaithi 412 554 623 843 1138 353 164

377 Khrehari 170 120 173 262 360 221 50

378 Deogarh 217 249 286 328 435 264 82

379 Kushi 1444 2318 2394 2871 3569 910 537

380 Tendee 0 103 110 121 141 64 27

381 Pakari 443 455 797 773 1253 626 209

382 Lashra 508 596 615 867 1085 260 163

Majhigaon
383 125 161 239 275 382 127 54
Chaubey

384 Shirpalpur 249 249 467 555 749 197 112

  94 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Census Population SC/ST HH


Sr.No Village Name
1971 1981 1991 2001 2011 2011 2011

385 Majhigaon Mishra 223 363 382 432 507 176 78

386 Ghuaskalan 308 375 548 709 832 86 134

387 Ganguar 0 23 380 570 763 370 139

388 Bagadiha 0 2 7 48 74 23 14

389 Tirnahi 20 45 100 224 285 44 50

390 Beechhi 0 115 1397 1663 1981 430 344

391 Ghuashkurd 436 421 524 705 1674 510 319

392 Amauli 171 257 328 508 713 458 136

393 Shuhali 0 0 5 14 28 11 7

394 Bithgon Nishoh 351 437 602 35 92 13 15

395 Bithgawn Nishph 351 437 12 813 915 470 164

396 Dharnipur 264 48 430 559 592 36 99

397 Karari 533 639 777 772 986 442 159

398 Mokarshim 454 529 353 520 602 186 101

399 Palikalna 322 372 476 604 781 33 122

400 Darari 0 0 81 138 187 0 32

401 Pipari 385 501 620 685 815 11 130

402 Belwa 0 0 5 52 88 0 14

403 Lakhan Purwa 217 268 321 406 441 168 82

404 Garawa 135 363 209 293 321 0 58

405 Bhruiya 128 191 302 306 383 7 65

406 Goithari 156 169 208 306 354 190 63

407 Jamuanua 247 321 422 553 619 227 101

  95 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Census Population SC/ST HH


Sr.No Village Name
1971 1981 1991 2001 2011 2011 2011

408 Dhuriya 31 181 269 328 405 0 54

409 Jamaganwa 154 209 283 383 442 192 71

410 Nai Basti 0 40 177 418 492 38 73

411 Ratawal 27 40 56 74 99 37 17

412 Mahuaon 61 143 170 243 289 0 40

413 Hinauti 163 206 256 332 414 151 49

414 Hona 182 221 286 379 482 171 84

415 Hinduhari 335 407 659 909 1270 470 228

416 Barwan 302 367 491 607 798 236 132

417 Majhi Ganwa 188 286 142 203 272 170 49

Shemari
418 167 235 318 435 517 42 72
Bishunlal

Babhanauli
419 116 85 124 158 229 135 38
Khurd

420 Bhogar 172 189 238 287 349 113 67

421 Babhanauli Kalan 249 354 427 489 589 0 98

422 Shango 90 102 127 126 127 0 22

423 Pashi Kalana 339 432 474 587 740 224 120

424 Amokhr 365 492 572 759 927 435 159

425 Pashi Khurd 206 287 333 419 510 229 103

426 Urali 0 69 86 85 101 0 24

427 Khewatha 11 22 43 83 125 14 26

428 Mango 28 39 88 137 145 5 23

429 Mahokhar 93 101 151 228 286 0 44

  96 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Census Population SC/ST HH


Sr.No Village Name
1971 1981 1991 2001 2011 2011 2011

430 Chandauli 137 164 197 413 513 192 82

431 Tendu 145 213 280 375 419 89 78

432 Mahuari 288 433 651 978 1102 401 194

433 Kamahar Dih 493 715 948 1378 1690 235 239

434 Bahura 2145 3297 4477 5955 7420 1980 1100

435 Papi 151 208 286 393 459 286 95

436 Majhiganwa 291 327 367 412 500 131 102

437 Raghunathpur 702 881 1195 1616 2177 1337 453

438 Bharganw 0 86 2 3 9 2 3

439 Bhunari 39 0 74 103 126 68 27

440 Raiwari 87 129 162 188 239 141 59

441 Bajotara 86 114 163 185 211 20 51

442 Amahata Amahti 6 62 114 156 157 61 31

443 Beechhiya 291 72 477 567 639 240 123

444 Khatauli 323 434 584 785 800 449 151

445 Bhandar Khurd 66 97 68 121 188 0 38

446 Baghari 0 7 834 1244 1588 1059 332

447 Bahuar 1267 1493 1836 2373 3139 1665 590

448 Bashauli 683 876 1123 1439 1804 890 340

449 Bashuari 207 243 186 242 277 0 50

450 Tilauli 176 262 391 584 800 547 191

451 Amauli 171 257 328 508 831 364 133

452 Mahuar Khurd 96 98 100 102 140 75 28

  97 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Census Population SC/ST HH


Sr.No Village Name
1971 1981 1991 2001 2011 2011 2011

453 Patehra 36 45 80 120 141 63 26

454 Mahuar Kalna 21 434 60 88 118 9 19

455 Karauli 165 201 222 339 449 334 91

456 Gordiha 375 504 677 878 990 19 163

457 Nipraj 475 638 857 1151 1415 261 216

458 Muther 285 352 434 535 592 314 99

459 Kamojee 270 378 529 740 802 299 127

460 Marhra 0 0 417 522 669 247 122

461 Beohari 9 17 32 61 100 23 20

462 Mahuali 0 1 3 7 10 0 2

463 Khchar 0 0 191 267 328 87 60

464 Parashipandy 377 454 577 817 1055 385 186

465 Shajua 5 5 5 4 3 3 1

466 Shathi 0 243 290 385 498 57 87

467 Juriya 71 404 168 186 216 82 39

468 Judauri Pardhan 107 138 184 239 316 80 66

469 Bherawal 66 0 120 157 234 188 51

470 Ganguhar 178 314 64 90 135 69 25

471 Renua 99 247 341 409 493 82 96

472 Kolakari 315 0 495 645 900 725 172

473 Dugaulia 492 697 1181 1626 2173 1077 440

474 Shikari 239 180 450 661 833 397 171

475 Bansdih 0 1114 790 969 1185 96 209

  98 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Census Population SC/ST HH


Sr.No Village Name
1971 1981 1991 2001 2011 2011 2011

476 Bichhwar 0 73 98 110 78 8 13

477 Marachhi 62 480 384 478 540 155 100

478 Jamaganwa 554 696 750 981 1093 392 151

479 Umarikhurd 219 158 244 304 418 36 74

480 Kooran 0 0 0 0 4 0 1

481 Baraganwa 0 285 331 511 640 200 98

482 Gobariya 154 174 239 339 531 325 108

483 Barauli 193 234 342 379 536 39 85

484 Shahganj 666 586 808 1343 1628 296 245

485 Sahuar 418 523 544 944 1159 385 196

486 Sohdaul 406 146 211 284 405 88 63

487 Manhawan 0 0 218 286 366 69 65

488 Amahar 0 2 682 522 751 113 106

489 Pipari No 2 140 183 234 247 281 102 55

490 Barnwa 0 399 536 710 845 114 138

491 Onauli 315 144 160 217 308 233 67

492 Kushra 183 240 314 421 521 87 88

493 Thuter 0 0 1425 1778 2007 175 382

494 Tiwar 13 16 26 38 43 0 7

495 Adaura 154 46 85 146 197 96 32

496 Orhatha 0 556 888 1477 2103 646 366

497 Raipura 705 555 759 1100 1516 557 273

498 Rajpur 1003 1978 2581 3526 4424 1260 771

  99 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Census Population SC/ST HH


Sr.No Village Name
1971 1981 1991 2001 2011 2011 2011

499 Shenduri 113 453 457 708 955 279 183

500 Barak 0 847 982 1379 1479 228 241

501 Shonwat 101 394 65 74 101 32 20

502 Shonauti 31 129 62 140 238 13 37

503 Divar 267 590 582 790 1060 438 171

504 Khajaraul 326 508 752 850 1174 504 217

505 Bhairawa 135 159 186 222 253 195 36

506 Majhali 0 0 13 15 25 21 6

507 Mushrdhara 262 278 327 486 538 306 100

508 Atarauli Kalan 22 20 33 62 116 26 24

509 Garwa 83 194 104 125 179 47 34

510 Kewata 223 270 319 396 444 0 85

511 Tendui 209 445 538 744 804 41 151

512 Obaradih 281 328 394 530 657 290 112

513 Domahar 271 211 296 421 454 188 81

514 Selahata 451 590 584 950 1153 675 230

515 Kusinisph 416 597 657 844 1201 668 206

516 Mhunyw Pandy 294 349 403 493 537 221 92

517 Chorat 75 102 188 357 510 227 90

518 Mahuna Gosani 130 193 269 425 504 332 108

519 Kunda 77 53 9 63 82 3 15

520 Panauli 186 246 304 338 579 237 106

521 Sadari 146 226 261 410 555 274 101

  100 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Census Population SC/ST HH


Sr.No Village Name
1971 1981 1991 2001 2011 2011 2011

522 Jinhora 109 132 145 192 258 0 59

523 Naidiha 199 104 150 267 294 106 44

524 Aurahi 0 182 220 418 555 319 93

525 Sidhi 272 148 369 444 572 335 102

526 Naunia 0 0 0 0 22 0 2

527 Athauna 136 201 260 398 450 180 77

528 Bhgawas 37 62 46 121 204 0 28

529 Chausara 0 0 0 0 5 0 1

530 Kharera 3 28 58 97 187 27 34

531 Morahi 0 710 931 1130 1200 226 221

532 Barauli 193 234 342 379 816 615 132

533 Khirahata 450 563 701 881 1122 649 235

534 Garama 433 430 681 961 1266 1033 261

535 Gurwal 308 477 669 1079 1636 1051 345

536 Bandha 173 174 271 405 468 311 73

537 Belwania 423 558 738 987 1249 727 224

538 Karaundia 2 4 15 10 74 23 16

539 Rampur 237 110 193 332 396 91 54

540 Panti 95 120 147 215 317 180 47

541 Dhanawal 275 321 413 520 700 295 109

542 Barsot 0 410 192 264 421 332 79

543 Lohari 300 461 680 1088 1469 519 231

544 Ahraura 289 468 594 813 950 563 157

  101 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Census Population SC/ST HH


Sr.No Village Name
1971 1981 1991 2001 2011 2011 2011

545 Sotil 467 575 794 1094 1415 532 312

546 Jaimohra 173 250 354 524 707 231 118

547 Pateri 23 21 79 178 258 151 50

548 Bakuli 270 356 360 363 401 194 68

549 Durkhuli 140 226 413 583 742 388 125

550 Guretha 398 419 587 879 1068 826 181

551 Rajin 19 32 69 101 216 142 38

552 Odar 394 372 511 801 960 552 174

553 Thiwan 13 16 873 1178 1480 610 268

554 Dhuria 31 46 38 66 103 38 14

555 Kusmaha 1293 532 768 1086 1330 261 233

556 Dewerikatha 583 458 568 789 1129 428 203

557 Peroh 727 1219 2008 3424 5441 2555 864

558 Dhorkary 120 655 446 827 1202 464 207

559 Dharsara 205 256 332 398 555 293 76

560 Marasara 171 242 402 601 837 647 132

561 Dumaria Mithailal 0 0 18 31 59 0 8

562 Silwar 317 417 583 789 876 365 155

563 Dumaribharaulia 0 0 9 10 13 0 3

564 Bharauli 477 633 877 1356 1666 586 270

565 Dhadhi 63 110 178 334 452 312 62

566 Piparwar 198 280 366 489 606 397 102

567 Bisrekhi 575 700 1033 1373 1845 967 306

  102 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Census Population SC/ST HH


Sr.No Village Name
1971 1981 1991 2001 2011 2011 2011

568 Jaimohara 3 7 16 48 75 25 13

569 Sirsai 126 239 407 852 1119 447 191

570 Raikara 0 0 9 9 9 0 1

571 Majhagawan 83 116 163 224 319 119 60

572 Naugai 143 217 360 597 727 376 124

573 Uchdih 125 453 137 231 317 69 56

574 Lakshimanpur 166 224 412 629 721 367 132

575 Chain 115 183 276 460 534 282 109

576 Naugawan 240 368 612 857 1097 343 171

577 Bhawana 294 388 463 694 726 450 137

578 Dewerikhurd 156 193 161 207 445 222 58

579 Halwai 64 62 143 180 233 70 36

580 Bagpokhar 403 436 735 1001 1025 609 162

581 Bhanswar 628 1658 1907 2595 4486 1512 723

582 Sahdeapaidar 1382 1602 1996 2525 2751 798 503

583 Magaradaha 695 1339 1689 2416 3215 1577 537

584 Visahar 250 847 1118 1502 2001 949 366

585 Raunp 751 921 1130 1387 2512 849 395

586 Churk 369 625 1058 1790 1530 350 289

587 Shahijan Khurd 307 544 676 1007 1430 525 241

588 Musahee 542 732 989 1336 1898 1073 340

589 Kura 311 342 376 413 472 137 86

590 Teyara Nayak 228 260 333 403 506 257 104

  103 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Census Population SC/ST HH


Sr.No Village Name
1971 1981 1991 2001 2011 2011 2011

591 Peetha 194 200 233 284 290 149 61

592 Akachor 251 386 593 911 1184 200 247

593 Beejauli 351 449 574 734 908 155 182

594 Meuri Kalan 179 217 238 285 411 133 83

595 Arauly 789 1075 1465 1997 1557 747 278

596 Shajaur 458 463 468 473 571 217 106

597 Lakhanwar Kalna 155 178 192 219 372 30 62

598 Mangurahee 66 148 147 189 234 8 34

599 Kusamha 0 1 4 22 49 0 8

600 Bijary Duban 155 226 242 243 218 101 39

601 Harhuna 264 353 437 518 487 293 75

602 Atarauli Khurd 1 4 13 45 42 0 7

603 Bijary Patkhan 48 73 110 166 307 31 44

604 Bahuarah 156 236 358 542 621 292 118

605 Lakhanwar Khurd 154 201 206 294 383 33 59

606 Kharhari 0 120 182 330 515 41 82

607 Pali 211 251 299 356 526 252 96

608 Dhobahi 141 179 228 291 370 187 62

609 Bharganwa 140 126 113 101 131 0 22

610 Bhandra Kalan 2 2 2 2 24 0 3

611 Chhapaka 0 530 603 883 1254 578 231

612 Shemara 90 107 105 110 46 16 8

613 Shahijan Kalna 1252 1709 1949 2339 2818 864 524

  104 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Census Population SC/ST HH


Sr.No Village Name
1971 1981 1991 2001 2011 2011 2011

614 Shindhora 0 0 0 62 201 159 40

615 Bichapai 252 379 424 580 1102 235 184

616 Ormaura 518 680 1146 1940 3006 645 536

617 Lori 743 1020 1400 1921 2241 1256 434

618 Pushuli 292 457 715 1118 2764 1021 540

619 Amarati 0 67 118 418 645 117 104

620 Gorari 160 220 303 418 707 136 106

621 Barauli 324 628 856 1215 1652 557 283

622 Meuri Khurd 52 69 92 122 170 33 35

623 Jamgane 247 203 332 427 515 314 90

624 Ghurma 184 263 382 624 998 160 174

625 Kaithi 396 557 783 930 1193 238 203

626 Baraila 81 93 107 123 152 108 29

627 Petrahi 163 187 214 259 233 114 41

628 Kamarhi 0 39 961 1795 2987 614 536

629 Baghnaree 358 484 513 573 799 271 167

630 Belaha 116 171 259 285 354 220 70

631 Patharaha 288 402 148 152 238 0 41

632 Gangti 221 333 409 497 659 311 129

633 Paika 314 362 453 542 609 259 118

634 Kewata 513 589 788 1028 1242 633 236

635 Rajdhan 322 453 652 826 1083 482 217

636 Bachawar 41 59 85 123 176 40 36

  105 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Census Population SC/ST HH


Sr.No Village Name
1971 1981 1991 2001 2011 2011 2011

637 Mhowoh Khurd 14 77 237 354 473 98 83

638 Kamharia 14 24 42 76 189 142 38

639 Belcupp 545 818 822 1250 1576 389 311

640 Mhowon Kalna 84 217 560 1065 1325 470 223

641 Chihurali 422 649 907 1268 1805 1055 281

642 Baluee 138 141 180 253 414 300 78

643 Maitapur 795 850 1192 1671 2048 144 420

644 Kargara 1365 1639 2088 2955 3723 799 626

645 Bhbhaech 640 887 1185 1583 2125 767 408

646 Karki 382 571 64 98 114 90 23

647 Guradah 979 1041 1799 2501 3133 1459 539

648 Redia 183 276 474 694 1044 470 204

649 Bandhwa 68 128 178 297 440 144 84

650 Bhgawa 2 3 4 5 6 0 1

651 Kurhul 1205 1605 1992 2880 3535 989 635

652 Adalganj 600 755 965 1564 1969 1214 408

653 Salkhan 2832 3506 4834 7864 10552 6111 1935

654 Awayee 281 385 469 779 984 454 172

655 Markundi 784 2928 2508 6417 7303 3432 1200

656 Rudawali 95 142 608 669 1136 1015 178

657 Patwdh 1404 2121 2896 4289 5911 3162 1135

658 Belach 557 841 1015 1851 2291 2032 398

659 Pakari 59 103 182 322 433 226 82

  106 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Census Population SC/ST HH


Sr.No Village Name
1971 1981 1991 2001 2011 2011 2011

660 Kandhaura 1695 333 753 1021 1161 500 203

661 Kanach 882 1222 1541 2218 2814 2034 469

662 Aluar 178 235 375 643 850 356 139

663 Bhadohi. 0 0 18 29 70 5 13

TOTAL 180289 242000 323001 445231 570515 224896 97208

  107 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

14. LIST OF GRAM PANCHAYATS, VILLAGES AND THEIR HABITATION COVERED IN THE
PROJECT AREA

Sl.No.  Block  Gram Panchayat  Village  Habitations  Population Census 2011 


               2011  SC / ST 
Kandhaura  Kandhaura  1161  500 
Pakari  Pakari  433  226 
1  Chopan  Kanach 
Kanach  1436  1102 
Kanach 
Korail  1378  932 
         3  4  4408  2760 
Belach  683  659 
Akelwa  550  411 
Belchha  Belach  Tekma  282  279 
2  Robertsganj  Agarihwa  590  534 
Chateni Tola  186  150 
Rudawali  886  900 
Rudawali  Rudawali 
Gadhakushtola  250  115 
         2  7  3427  3048 
Patwdh  1148  353 
Harijanbasti  956  414 
Barihawa  966  633 
3  Chopan  Patwdh  Patwdh  Baskatya  996  794 
Dupatia  678  195 
Gurihawa  553  401 
Bhortirawa  614  372 
         1  7  5911  3162 
Markundi  2128  348 
Baderhwar  467  550 
Balui  790  688 
Chakria  870  258 
4  Robertsganj  Markundi  Markundi  Owati  776  251 
Baskhadia  449  417 
Chouradih Tola  126  161 
Bahera Tola  1468  495 
Chhinar Pochha  229  265 
         1  9  7303  3433 
Chihurali  Karki  Karki  114  90 
Robertsganj 
Bhabhaich  Bhbhaech  Bhbhaech  2125  767 
Chopan  Gurdha  Aluar  Aluar  850  356 

Robertsganj  Maitapur  Maitapur  Maitapur  2048  144 
Guradah  741  338 
Chopan  Gurdha  Guradah 
Dhourahawa  631  144 

  108 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Sl.No.  Block  Gram Panchayat  Village  Habitations  Population Census 2011 
               2011  SC / ST 
Karamdand  579  337 
Putpuria  303  119 
Chhuhia Tola  260  130 
Budi Khar  620  391 
Kargara  850  442 
Upraundh  922  190 
Chopan  Kargara  Kargara 
Paschimi Tola  947  160 
Kewtan  1004  6 
         6  14  11994  3614 
Kewata  Baluee  Baluee  414  300 
Mhowon Kalna  Mhowon Kalna  Mhowon Kalna  1325  470 
Belcupp  1025  262 
Belcupp  Belcupp 
Birbal Madhuban  551  127 
Belcupp  Bachawar  Bachawar  176  40 
Paika  Gangti  Gangti  659  311 
Rajdhan  Rajdhan  Rajdhan  1083  482 
Mhowon Kalna  Mhowoh Khurd  Mhowoh Khurd  473  98 
6  Robertsganj 
Kewata  Kewata  Kewata  1242  633 
Paika  Patharaha  Patharaha  238  0 
Paika  Paika  Paika  609  259 
Baghnaree  Baghnaree  Baghnaree  799  271 
Baghnaree  Belaha  Belaha  354  220 
Chihurali  1067  670 
Chihurali  Chihurali 
Mahuaria  738  385 
Kewta  Kamharia  Kamharia  189  142 
         14  16  10942  4670 
Chopan  Ghatita  Bhgawa  Bhgawa  6  0 
Robertsganj  Kurhul  Kurhul  Kurhul  3535  989 

Robertsganj  Maitapur  Bandhwa  Bandhwa  440  144 
Robertsganj  Redia  Redia  Redia  1044  470 
         4  4  5025  1603 
Chopan  Adalganj  Adalganj  Adalganj  1969  1214 
Salkhan  2386  1398 
Dewaria Tola  933  621 
Lal Ganj  1068  748 
Autrawa  2732  1702 

Robertsganj  Salkan  Salkhan  Punma  1841  609 
Bhatwa  492  397 
Kharwar Tola  686  436 
Sahdiya Tola  289  151 
Jhariya Tola  124  48 

  109 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Sl.No.  Block  Gram Panchayat  Village  Habitations  Population Census 2011 
               2011  SC / ST 
Markundi  Awayee  Awayee  984  454 
         3  11  13504  7778 
Ghuwas  1845  1300 
Ghuwas  Ghuwas 
Sapiniya Tola  84  49 
Mukkha  Mukkha  Mukkha  614  344 
Amilia  Amilia  332  239 
Ghuwas 
Tendua  Tendua  1284  425 
AMILAUDHA  Amilaudha  Amilaudha  653  370 
9  Ghorawal 
TENDUA  Lahas  Lahas  798  517 
SIRSAIN  Sirsain  Sirsai  1278  915 
Karia  1420  986 
KARIA  Karia 
Parsiya  518  501 
GHUWAS  Barbaspur  Barbaspur  468  114 
TENDUA  Karry  Karry  30  30 
   10  12  9324  5790 
Basahi  155  61 
Sirsain  Basahi  Majhiyan Bashti  175  86 
Markahawa  207  56 
MADHAKA  Karsoata  Karsoata  707  530 
MADHAKA  Fulwary  Fulwary  715  89 
MADHAKA  Madhaka  Madhaka  744  552 
10  Ghorawal 
REHI  Samerwar  Samerwar  336  165 
Mukkha  Mahokhar  Mahokhar  534  67 
REHI  Pathartal  Pathartal  486  246 
REHI  Rahi  Rahi  925  361 
Purana 1  1233  613 
PURNA  Purana 
Purana 2  819  550 
   9  12  7036  3376 
PARSONA  Ghoria  Ghoria  484  451 
Semera Khurd  Semera Khurd  24  24 
Ghorawal 
KANHARI  Kanhari 1  1055  821 
Kanhari 
Kanhari 2  1040  973 
Tenthuhar  1204  855 
TENDUHAR  Tenthuhar 
11  Kol Basti  379  174 
Parsauna  2747  2117 
Ghorawal  PARSAUNA  Parsauna  Parsauna2  350  277 
Parsauna3  325  260 
TENDHUHAR  Majurahi  Majurahi  370  352 
TENDUHAR  Lali  Lali  859  692 
   7  11  8837  6996 
12  Ghorawal  Semera Kala  Semera Kala  323  284 

  110 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Sl.No.  Block  Gram Panchayat  Village  Habitations  Population Census 2011 
               2011  SC / ST 
KANHARI  Babhari  Babhari  915  847 
MURTIA  Ubha  Ubha  766  654 
AMILIPOKHER  Marni  Marni  492  388 
Murtiya 1  1361  665 
MOORTIYA  Murtiya 
Murtiya 2  637  272 
AMILIPOKHER  Dholo  Dholo  921  708 
AMILIPOKHER  Amli Pokhar  Amli Pokhar  863  519 
MURTIYA  Sapahi  Sapahi  536  406 
   8  9  6814  4743 
MAHAAW  Bantara  Bantara  87  0 
DEVGARH  Deogarha  Deogarha  864  737 
Hinauti  1134  774 
Majhali  136  84 
HINAUTI  Hinauti 
Chaukhara  433  328 
Varya  601  327 
Parwania 1  1294  1108 
PADWANIA  Parwania 
Parwania 2  841  625 
13  Ghorawal 
Deogarha  Rumma  Rumma  429  338 
GURWAL  Chigori  Chigori  928  920 
Manhwa 1  1041  839 
MAHAOW  Manhwa 
Manhwa 2  324  117 
MAHAAW  Khajuari  Khajuari  119  88 
KHAGIYA  Chandwa  Chandwa  85  60 
Koladiha  Dhura Kund  Dhura Kund  678  114 
MIJHUN  Dulahatha  Dulahatha  317  208 
   11  16  9311  6667 
Bardiya 1  1320  605 
BARDIYA  Bardiya 
Bardiya 2  882  481 
SATDWARI  Harankhuri  Harankhuri  595  72 
BARDIYA  Bhainshi  Bhainshi  177  144 
Bar  1235  949 
BARR  Bar  Bar Ii  382  275 
Bar Iii  568  389 

14  Ghorawal  SHIV DWAR  Seegra  Seegra  54  39 


BAIJNATH  Baijanath  Baijanath  552  397 
BAIJNATH  Gawnkunda  Gawnkunda  268  206 
SATDWARI  Satdwari  Satdwari  610  268 
BAIJNATH  Amadhi  Amadhi  360  307 
Siwadar  1721  1342 
SHIVDWAR  Siwadar 
Siwadar Ii  486  70 
Manjhiganw a  Manjhiganwa
Musha  517  287 
Mishra  Mishra 

  111 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Sl.No.  Block  Gram Panchayat  Village  Habitations  Population Census 2011 
               2011  SC / ST 
   11  15  9727  5831 
MIJHUN  Meejhun  Meejhun  637  272 
MIJHUN  Sonhati  Sonhati  382  189 
KOHARTHA  Bauradih  Bauradih  173  173 
Lilwahi  Lilwahi  Lilwahi  1140  520 
Koharatha 1  1366  934 
KOHARTHA  Koharatha 
Koharatha 2  141  132 
KOLDEHA  Koladiha  Koladiha  591  265 
BHARKANA  Bharkana  Bharkana  1257  750 
BHARKANA  Bhagahi  Bhagahi  197  136 
KOHARTHA  Baidawar  Baidawar  25  0 
15  Ghorawal 
Dorihar  Jamua  Jamua  40  20 
Musha  Sonabarsa  Sonabarsa  2  0 
KHAGIA  Khagia  Khagia  1067  497 
Musha  Musha  Musha  550  229 
Beerkala  Mandha  Mandha  442  219 
Musha  Snihawal  Snihawal  179  111 
Dorihar  Janar  Janar  378  135 
Beerkala  Beerkala  Beerkala  852  66 
Dorihar  Dorihar  Dorihar  1166  829 
KHARDEUR  Khardeur  Khardeur  1261  625 
   19  20  11846  6102 
KEWETA  Keweta  Kewata  837  483 
KEWETA  Khakh  Khakh  431  297 
KHRUANV  Mahvarioa  Mahvarioa  497  200 
Khutaha  2099  1263 
KHUTAHA  Khutaha 
Khutaha Ii  950  536 
Deewa  Thiwan  Thiwan  1480  610 
Bharauli  Dumaria Mithailal  Dumaria Mithailal  59  0 
16  Ghorawal 
Bharauli  Silwar  Silwar  876  365 
Bharauli  1155  333 
Bharauli  Bharauli  Mishragawa  339  196 
Nai Bashti  172  57 
Diwa  Piparwar  Piparwar  606  397 
KEVTA  Sirsai  Sirsai  1119  447 
BISREKHI  Majhagawan  Majhagawan  319  119 
   11  14  10939  5303 
Junia  Parsauna Khurd  Parsauna Khurd  99  99 
SATOHA  Satohan  Satohan  1631  795 
17  Ghorawal 
SATOHA  Nakawai  Nakawai  335  155 
VISHUNDHAR I  Visundhary  Visundhary  3295  1683 

  112 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Sl.No.  Block  Gram Panchayat  Village  Habitations  Population Census 2011 
               2011  SC / ST 
   4  4  5360  2732 
Kanhi  1028  289 
KANETI  Kanhi 
BAGHI  345  178 
KANETI  Dharmauli  Dharmauli  881  325 
Kewali  820  365 
MUGEHARI  Kewali 
Nai Chamar Basti  112  23 
KHRUAOV  Khadaha  Khadaha  280  241 
Munghri  716  401 
MUGEHAR  Munghri 
Colbasti  75  68 
MUGEHARI  Samara  Samara  364  209 
18  Ghorawal 
MUGEHARI  Hinauti  Hinauti  31  0 
Pidaria  1280  399 
PIDARIYA  Pidaria 
Bechanpura  29  0 
PIDARIYA  Parhi  Parhi  794  237 
Newari  Newari  Newari  2500  1406 
BAGPOKHAR  Amilia  Amilia  809  524 
Kharuaun  1116  407 
KHRUAOV  Kharuaun  Surhurwa  202  25 
Nauka Mati  72  11 
   12  18  11454  5108 
Kathapura  Sahpurwa Kalan  Sahpurwa Kalan  285  7 
Kathapura  Sahpurwa Khurd  Sahpurwa Khurd  192  45 
BAGPOKHAR  Bnardewa  Bnardewa  1003  671 
Kathapura  Kathapura  Kathapura  401  17 
SILHATA  Silahta  Silahta  1087  615 
Jogani 1  999  160 

19  Ghorawal  JOGINI  Jogani  Jogani 2  616  258 


Jogani 3  838  383 
Kathapurwa  Bhulahi  Bhulahi  144  7 
Sahdeapaidar  2515  744 
Sahdeapaidar 2(katri 
87  17 
SAHDEIYA  Sahdeapaidar  Tola) 
Maurya Basti  66  18 
Dihpura  83  19 
   8  13  8316  2961 
PIDARIYA  Tilauli Khurd  Tilauli Khurd  190  8 
Tilauli Kalana 1  1687  938 
Tilauli Kalana 2  734  272 
20  Ghorawal  TIKAULIKALA  Tilauli Kalana Tilauli Kalana 3  549  114 
Nai Basti  301  39 
Chandrma Katri  550  198 
Khuthnia  Khuthnia  Khuthania  1421  419 

  113 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Sl.No.  Block  Gram Panchayat  Village  Habitations  Population Census 2011 
               2011  SC / ST 
Kathapura  Kamhria  Kamhria  137  9 
Bagpokhar 1  636  468 
Bagpokhar  Bagpokhar  Bagpokhar 2  210  141 
Bakhrahiya  179  0 
   5  11  6594  2606 
KARIVAIRAN V  Karrivarai  Karibarai  1098  460 
KAREVIRAV  Kamhria  Kamhria  332  198 
DHOVA  Dhoa  Dhoa  975  449 
Aruna  Aruna  Aruna  1173  533 
DHOVA  Vimauri  Vimauri  761  219 
KHUTTANIYA Velahi  Velahi  576  248 
Aruna  Semari Misra  Semari Misra  685  231 
PHULWARI  Khudia  Khudia  525  151 
21  Ghorawal 
Khuthnia  Ataraila  Ataraila  148  46 
Purkhas 1  1532  738 
Purkhas 2  136  39 
PURKHAS  Purkhas  Purkhas 3  96  8 
Dhawahiya Tola  100  14 
Nawtaliya Tola  460  249 
PHULVARI  Phulawari  Phulwari  1113  539 
PHULVARI  Bahorika  Bahorika  494  151 
   12  16  10204  4273 
Bisun Pur  95  38 
MASIAADINATH  Bisun Pur 
Biyar Basti  14  7 
SIDDI  Teti  Teti  248  0 
Gotauli  138  28 
MASIAADINATH  Gotauli 
Kushawaha Basti  81  11 
Masiadinath  394  105 
MASIAADINATH  Masiadinath 
Pokhra Pua  107  31 
Sawat  692  127 
SERVAT  Sawat 
Kolbasti  27  2 
22  Ghorawal  JAMGAI  Jamaghne  Jamaghne  353  88 
Bakauli  Padri Kalan  Padri Kalan  256  54 
Maid  197  116 
JAMGAI  Maid 
Baburaha  54  38 
Masiha Pathan  381  315 
MASIAADINATH  Masiha Pathan 
Panditpur  55  45 
MASIAADINATH  Belkuri Murpharkat  Belkuri Mupharkat 257  183 
UCHKA  Naudiha  Naudiha  341  75 
Mureladih 1  1280  333 
MURELADEEH  Mureladih 
Mureladih 2  310  132 

  114 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Sl.No.  Block  Gram Panchayat  Village  Habitations  Population Census 2011 
               2011  SC / ST 
Farhada Tola  149  24 
Rudauli  254  187 
SERVAT  Rudauli 
Yadav Basti  72  30 
Aurahi  Welkhuri  Welkhuri  462  94 
Lohdhara  177  49 
MURELADEEH  Lohdhara 
Chamar Basti  35  27 
Bakauli  Chakauli  Chakauli  261  176 
Noni  644  396 
Bakauli  Noni 
Biyar Basti  36  42 
Adaura  136  84 
SIDHI  Adaura 
Yadav Basti  61  12 
Jamagani  Chausara  Chausara  5  0 
   19  31  7572  2849 
PHULVARI  Geduri  Geduri  116  0 
JORWARIA  Salaia  Salaia  11  0 
JORWARIA  Etwa  Etwa  56  52 
Sirvit 1  1073  591 
SIRVIT  Sirvit  Sirvit 2  1038  389 
Kumhar Basti  179  79 
Saranga 1  2134  438 
SARANGA  Saranga 
Saranga 2  248  159 
Tedhwa 1  48  0 
SIRSIAJETHI  Tedhwa 
Tedhwa 2  40  0 
Sirsiajethi 1  754  413 
23  Ghorawal  SIRSIYAJETHI  Sirsiajethi 
Sirsiajethi 2  546  75 
SILHATA  Kolariya  Kolariya  646  443 
Dharura  Dharura  Dharura  1426  423 
SIRSIYA JETHI  Sitabahar  Sitabahar  557  210 
KARKOLI  Karkoll  Karkoli  1455  419 
Tekuria  1554  853 
TEKURIA  Tekuria  Manthahiya Tola  90  17 
Bhawarahawa Tola  107  34 
KARKOLI  Mahuriya  Mahuriya  529  44 
KARMA  Madainia  Madainia  693  87 
KARMA  Karma  Karma  575  335 
   15  22  13875  5061 
PARASI PANDEY Bauar  Bauar  406  85 
Pawar  861  308 
PAWAR  Pawar 
24  Robertsganj  Budhaua Tola  90  90 
DEORI KHURD Deori Kalan  Deori Kalan  463  144 
DEHRI KALA  Kushai  Kushai  460  71 

  115 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Sl.No.  Block  Gram Panchayat  Village  Habitations  Population Census 2011 
               2011  SC / ST 
Deori Khurd  Dehra  Dehra  152  128 
Deori Khurd  Deori Khurd  Deori Khurd  429  154 
Deori Khurd  Rajapurawa  Rajapurawa  117  45 
Deori Khurd  Tiarashiv Datt  Tiarashiv Datt  199  112 
Deori Khurd  Chaktiara  Chaktiara  8  0 
Deori Khurd  Karhi  Karhi  238  127 
Deori Khurd  Bhagwantpur  Bhagwantpur  248  57 
Dahari  606  170 
DEHARI KALA  Dahari 
Harijan Basti  48  37 
Katawaria  950  273 
KATVARIYA  Katawaria 
Tal Tola  63  63 
Petrahi  Petrahi  Petrahi  632  329 
MAHURESAR  Deora  Deora  405  258 
KALVARIYA  Kanhara  Kanhara  290  143 
   16  19  6665  2594 
PARASI PANDEY Khairahi  Khairahi  422  39 
BUDHAR KALA  Mamuna  Mamuna  975  326 
PAWAR  Kalwari  Kalwari  241  46 
BUDHAR KHURD  Burhr Khurd  Burhr Khurd  804  307 
Burar Kalan  709  248 
BUDHAR KALA  Burar Kalan 
mamuna  236  110 
KATAWARIA  Nauganwa Kalan  Nauganwa Kalan  334  40 
Deori Khurd  Kewati  Kewati  596  176 
Deori Khurd  Theru  Theru  392  0 
25  Robertsganj 
Deori Khurd  Babura  Babura  387  0 
ORGAI‐P  Pursotampur  Pursotampur  236  0 
ORGAI‐P  Nauganwa Khurd  Nauganwa Khurd  596  0 
ORGAI  Organai  Organai  1247  339 
Barkara  518  201 
JAIT  Barkara 
Bhaglpur  320  206 
MANPUR  Manpur  Manpur  2195  167 
Ganguar  Tipara  Tipara  386  349 
Kaithi  Kaithi  Kaithi  1193  238 
   16  18  11787  2792 
SAHIJAN KALAN  Shahijan Khurd  Shahijan Khurd  1430  525 
Teyara Nayak  Peetha  Peetha  290  149 
Pushuli  2015  675 
BADHAULI  Pushuli 
26  Robertsganj  Kodvriya Tola  749  346 
BANDAULI  Amarati  Amarati  645  117 
Barauli  1142  158 
BADHOLI  Barauli 
Nai Basti  510  399 

  116 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Sl.No.  Block  Gram Panchayat  Village  Habitations  Population Census 2011 
               2011  SC / ST 
Ormaura  Ormaura  Ormaura  3006  645 
Bichapai  Bichapai  Bichapai  1102  235 
Chhapaka  Chhapaka  Chhapaka  1254  578 
Lori  1563  1090 
LODHI  Lori 
Bhilai Colony  678  166 
SAHIJAN KALAN  Shahijan Kalna  Shahijan Kalna  2818  864 
   10  13  17202  5947 
KHAIRA  Khajurikhurd  Khajurikhurd  302  47 
KHAIRA  Khajurikala  Khajurikala  364  222 
BARSOT  Bhurkura  Bhurkura  486  160 
BARSOT  Bhuli  Thauli  227  34 
BARSOT  Kunan  Kunan  185  137 
ENAM  Balua  Balua  180  1 
DOHARI  Dohari  Dohari  427  127 
KHAIRA  Welanow  Welanow  601  460 
KHAIRA  Hinauti  Hinauti  21  0 
DOHARI  Koharaul  Koharaul  348  137 
KHAIRA  Khaira  Khaira  609  296 
KHAIRA  Kapura  Kapura  137  27 
KHAIRA  Khairi  Khairi  79  27 
KINGARI  Chotakapur  Chotakapur  431  81 
BARSOT  Barsota  Barsota  810  312 
Uchaka  951  61 
27  Ghorawal  UCHKA  Uchaka 
Bahari Tola  187  8 
Bharuha  632  159 
UCHKA  Bhruha 
Madai Pura  101  56 
JAMGAI‐B  Pipri No. 1  Pipari No. 1  458  239 
JAMGAI  Jamagane  Jamagane  608  169 
KINGARI  Sauli  Sauli  118  41 
BARAWA  Asatali  Asatali  163  88 
KINGARI  Majhiganwa  Majhiganwa  487  235 
KINGARI  Kingari  Kingari  1232  38 
KINGARI  Chhuta  Chhuta  328  66 
Petrahi  Petrahi  Petrahi  418  140 
UMARIKALA  Mishra  Mishra  66  6 
Arangi  Arangi  Arangi  817  380 
KHAIRA  Khodaichak  Khodaichak  14  0 
Kolakari  Barnwa  Barnwa  845  114 
Kushra  Kushra  Kushra  521  87 
   30  32  13153  3955 
28  Ghorawal  SIRSIYA THAKURAI  Sirsiathkurai  Sirsiathkurai  2612  918 

  117 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Sl.No.  Block  Gram Panchayat  Village  Habitations  Population Census 2011 
               2011  SC / ST 
Khairpur  2256  759 
Papikala(rampat
1564  418 
hara) 
Belahawa  424  153 
Bagaia  226  70 
Kharra Tola  207  26 
   1  6  7289  2344 
MUBARAKPU R  Mubarakpur  Mubarakpur  2277  1262 
BAGHORI  Baghor  Baghor  1255  575 
29  Robertsganj 
GAURAHI  Gorahi  Gorahi  2448  450 
BAGHORI  Kutulupur  Kutulupur  946  49 
   4  4  6926  2336 
SARAULI  Atarauli Raja  Atarauli Raja  349  126 
Sarauli  1655  207 
SARAULI  Sarauli 
Sarauli2  315  50 
30  Ghorawal  GARAEGARH  Garaegarh  Garaegarh  1148  281 
MAJHUI  Majhui  Majhui  1342  436 
BHAWANIPUR  Bhawanipur  Bhawanipur  2379  687 
PARAHI  Parahi  Parahi  2195  582 
   6  7  9383  2369 
BANTARA  Bantara  Bantara  1016  418 
31  Robertsganj 
NAGNAR HARAIA  Nagnar Haraia  Nagnar Haraia  3857  1590 
   2  2  4873  2008 
Hinauta  1087  450 
HINAUTA  Hinauta 
Imliyadih  739  142 
AMDIH  Amdih  Amdih  1534  525 
32  Robertsganj  Khamriha  Khamriha  Khamriha  1102  414 
MADHUPUR  Madhupur  Madhupur  9710  1781 
CHAKARA  Amaulia  Amaulia  607  132 
CHAKARA  Chakara (50%)  Chakara  335  57 
   6  7  15114  3501 
LOHRA  Lohra  Lohra  6843  3057 
33  Robertsganj 
SUKRIT  Sukrit  Sukrit  6899  1908 
   2  2  13742  4965 
Ghorawal  Bharawah  Bharawah  Bharawah  1089  306 
Ghorawal  Bharawah  Khairwa  Khairwa  234  0 
Ghorawal  BAHERA  Dilahi  Dilahi  997  162 
Ghorawal  Bharawah  Tandi  Tandi  230  14 
34 
Jaderua 1  2000  881 
Ghorawal  JADERUA  Jaderua 
Jaderua 2  630  275 
Bahera 1  1760  176 
Ghorawal  BAHERA  Bahera 
Bahera 2  610  124 

  118 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Sl.No.  Block  Gram Panchayat  Village  Habitations  Population Census 2011 
               2011  SC / ST 
Ghorawal  DILAHI  Jurawat  Jurawat  465  126 
Robertsganj  BARUHA  Bharuha  Bharuha  557  254 
Robertsganj  BABURAHI  Bhadohi  Bhadohi  70  0 
Robertsganj  KHAIRAHI  Shirsia  Shirsia  14  14 
Kharahri  2266  427 
Robertsganj  KHAIRAHI  Khairahi 
Khairahi Bazar  203  0 
Robertsganj  Aelahi  Aelahi  Aelahi  1324  423 
   12  15  12449  3182 
Robertsganj  BASVA NISF  Dularu  Dularu  27  2 
Atarawa  347  46 
Robertsganj  BASWANISKA  Atarawa 
Futharawa  352  14 
Baburahi  679  98 
Robertsganj  BABURAHI  Baburahi 
Nai Basti  275  61 
Kharahri  52  0 
Robertsganj  KEKRAHI  Kharahri 
Khairahi Bazar  5  0 
Robertsganj  KEKRAHI  Shirkhora  Shirkhora  102  3 
Robertsganj  Silthary  Jokahi  Jokahi  343  54 
Robertsganj  PAPI  Bhagauti  Bhagauti  691  246 
Papi  432  48 
35  Miyan Tola  108  0 
Robertsganj  PAPI  Papi  Kushwaha Basti  108  0 
Kushwaha Basti Ii  108  0 
Harijan Basti  116  87 
Ghorawal  SIRSIA  Sirsia  Sirsia  928  245 
Ghorawal  SIRSIA  Kairwa  Kairwa  225  106 
Ghorawal  SIRSIYA  Pipara  Pipara  472  150 
Ghorawal  SIRSIA  Garhwa  Garhwa  231  0 
Robertsganj  KAKRAHI  Murala Dih  Murala Dih  24  1 
Basawa Nisph  362  47 
Robertsganj  BASAWA NISKA  Basawa Nisph  Kushwaha Basti  178  0 
Harijan Basti  96  120 
   14  23  6261  1328 
Robertsganj  CHAKARA  Chakara (50%)  Chakara  335  57 
Robertsganj  Gouri Nisph  Gouri Nisph  Gouri Nisph  610  299 
Robertsganj  MADAR  Kathpurwa  Kathpurwa  420  30 
Robertsganj  KAKARAHI  Kekarahi  Kekarahi  1113  56 
36           Bajar Tola  454  0 
         Harijan Basti  310  303 
Ghorawal  BHATAULIYA  Bhatulia  Bhataulia 1  934  124 
         Bhataulia 2  702  99 
Ghorawal  BAKAHI  Bakahi  Bakahi  891  253 

  119 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Sl.No.  Block  Gram Panchayat  Village  Habitations  Population Census 2011 
               2011  SC / ST 
         Pakrahiya  71  12 
Ghorawal  BAKAHI  Padar  Padar  515  330 
Robertsganj  MGURAHI  Mangurahi  Mangurahi  413  138 
Robertsganj  VAKDAD  Darah  Darah  328  134 
Robertsganj  SHEOKARI  Jori  Jori  712  258 
Robertsganj  SHEOKARI  Sheokari  Sheokari  709  46 
Robertsganj  MAGURAHI  Khekhara  Khekhara  410  173 
         Harijan Bashti  196  66 
Robertsganj  TINATALI  Tinatali  Tinatali  1207  110 
Ghorawal  SIRSIYA  Kushhi  Kushahi  247  0 
Robertsganj  HINAUTA  Tilya  Tilya  870  112 
   15  20  11447  2600 
MADAAR  Madar  Madar  731  66 
Baghi  620  107 
PASAHIKALA  Baghi 
Bagahi Chouraha  166  31 
Gouri Nisph  Parsona  Parsona  277  54 
DEHRI  Kamaharia  Kamaharia  129  0 
Gouri Nisph  Birhulia  Birhulia  363  181 
SHIVKHARI  Mahulia  Mahulia  197  65 
Dehari  350  105 
DEHRI  Dehari 
Kushwaha Basti  183  0 
Kasya Kalan URF  Kasya Kalan  476  126 
Kasya Kalan 
DEHRI  Harijan Basti  120  120 
37  Robertsganj 
Kushahi  125  19 
KEKARAHI  Kushahi 
Harijan Basti  18  14 
Bashdewa  368  132 
KARKI  Bashdewa  Kushwaha Bast  122  53 
Harijan Basti  132  175 
Karaki  817  292 
KARKI  Karaki  Kuswaha Basti  196  12 
Harijan Basti  439  446 
PAPI  Kasya Khurd  Kasya Khurd  264  123 
Gouri Nisph  Kucha Marwa  Kucha Marwa  472  95 
Karaki  Rajkhar  Rajkhar  44  0 
   14  22  6609  2216 
Ghorawal  BARIMAHEWA  Uachka  Uachka  427  308 
Barimahewa 1  2275  471 
Ghorawal  WARI MAHEWA  Barimahewa 
Barimahewa 2  203  0 
38 
Pagia 1  1037  110 
Ghorawal  PAGIA  Pagia 
Pagia 2  1133  209 
Robertsganj  PATERI  Khairawa Raja  Khairawa Raja  128  15 

  120 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Sl.No.  Block  Gram Panchayat  Village  Habitations  Population Census 2011 
               2011  SC / ST 
Asana  489  18 
Robertsganj  BHARUHA  Asana 
Kushwaha Basti  22  0 
Robertsganj  PATEHARA  Patehara  Patehara  714  38 
Robertsganj  PATEHARA  Patela  Patela  176  144 
Robertsganj  PATERI  Pateri  Pateri  435  154 
Robertsganj  BHARUHA  Tulsipur  Tulsipur  34  0 
Robertsganj  PATEHARA  Jawahi  Jawahi  430  11 
Robertsganj  PATERI  Gheuri  Gheuri  342  98 
Ghorawal  KARMA  Karanwah  Karanwah  249  24 
Robertsganj  PATERI  Khairawa No 2  Khairawa No 2  29  0 
Robertsganj  PATERI  Machhalawa  Machhalawa  152  0 
   14  17  8275  1600 
RANITARA  Birmaua  Birmaua  149  4 
RANITARA  Chakahi  Chakahi  395  124 
RANITARA  Mukasim  Mukasim  1561  584 
PANDEYPOKHAR  Pandepokhar  Pandepokhar  1052  384 
Ranitara  599  149 
39  Ghorawal  RANITARA  Ranitara  Jurhva Tala  319  198 
Deldar Nagar  411  174 
PANDEYPOKHAR  Dudhia  Dudhia  629  188 
PANDEYPOKHAR  Teprasivadati  Teprasivadati  702  237 
Jorwria  1371  453 
JORWARIA  Jorwria 
Jorwria 1  304  131 
   8  11  7492  2626 
TAKIA  Dhotwa  Dhotwa  188  39 
SUKRIT  Khane Azampur  Khane Azampur  776  255 
40  Robertsganj  BAGHAORI  Baghauri  Baghauri  177  19 
BAT  Bat  Bat  3621  707 
TAKIAMUDA RGAHA  Takia Mu.Dargah  Takia Mu.Dargah  2426  995 
   5  5  7188  2015 
Robertsganj  GORDIHA  Gordiha  Gordiha  434  50 
Robertsganj  KARAARI  Purainiya  Purainiya  210  26 
Robertsganj  JIGNA  Jigana  Jigana  717  236 
Robertsganj  JIGNA  Alahi  Alahi  151  32 
Robertsganj  BARGAWN  Bargawn  Bargawn  659  216 
41  Robertsganj  BARGAWN  Bishbhrpur  Bishbhrpur  208  0 
Robertsganj  JIGNA  Parsona  Parsona  126  48 
Robertsganj  BARGAWN  Pateara  Pateara  154  23 
Robertsganj  JIGNA  Domariya  Domariya  297  78 
Robertsganj  JIGNA  Rampur  Rampur  579  0 
Robertsganj  BARGAON  Baheri  Baheri  291  124 

  121 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Sl.No.  Block  Gram Panchayat  Village  Habitations  Population Census 2011 
               2011  SC / ST 
Robertsganj  DHOBAHI  Khrehari  Kharahri  360  221 
Robertsganj  BARWAN  Deogarh  Deogarh  435  264 
Robertsganj  KUSI  Kushi  Kushi  1955  468 
Robertsganj        Bawaraspur  464  212 
Robertsganj        Belahi  682  115 
Robertsganj        Kusi Belahi  468  115 
Robertsganj  BARGAON  Bahera  Bahera  206  20 
Robertsganj  MAHUARI  Tendee  Tendee  141  64 
Robertsganj  Kaithi  Kaithi  Kaithi  1138  353 
Robertsganj  PIPARI  Lakhan Purwa  Lakhan Purwa  441  168 
   18  21  10116  2833 
BABHANAULI KALA  Mahokhar  Mahokhar  286  0 
PASHI KALA  Chandauli  Chandauli  513  192 
MADHURAHI  Tendu  Tendu  419  89 
Mahuari  737  262 
MAHUARI  Mahuari 
Gour Basti  365  139 
KAMHARDEEH  Kamahar Dih  Kamahar Dih  1690  235 
42  Robertsganj  Bahura  2377  706 
Puran Basti  644  466 
Aurahwa  1470  305 
BAHURA  Bahura  Bohuara Ganj  1006  94 
Bairwa Gobar  887  187 
Bahuara Bangla  829  163 
Kurihawa  207  59 
   6  13  11430  2897 
PASHI KALA  Durha  Durha  153  20 
Deora Raja  213  74 
PASHI KALA  Deora Raja 
Harijan Bashti  16  11 
Deori Khurd  Nai Basti  Nai Basti  492  38 
Hinduhari  927  171 
HINDUARI  Hinduhari 
Harijan Basti  343  299 
JAMUANUA  Jamuanua  Jamuanua  619  227 
Dhuriya  270  0 
43  Robertsganj  JAMAGANWA  Dhuriya 
KUSHWAHA BASTI  135  0 
JAMAGANWA  Jamaganwa  Jamaganwa  442  192 
Ratawal  64  27 
BHARHIYA  Ratawal 
PANIKA TOLA  35  10 
JAMUAW  Mahuaon  Mahuaon  289  0 
NAI  Hinauti  Hinauti  414  151 
NAI  Hona  Hona  482  171 
BARWAN  Barwan  Barwan  798  236 

  122 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Sl.No.  Block  Gram Panchayat  Village  Habitations  Population Census 2011 
               2011  SC / ST 
PASHI KALA  Majhi Ganwa  Majhiganwa  272  170 
AMOKHAR  Shemari Bishunlal  Shemari Bishunlal  517  42 
BABHNAULI KALA  Babhanauli Khurd  Babhanauli Khurd  229  135 
BAMNAULI KALA  Bhogar  Bhogar  349  113 
BABHNAULI KALA  Babhanauli Kalan  Babhanauli Kalan  589  0 
AMOKHAR  Shango  Shango  127  0 
Pashi Kalana  594  98 
PASAHIKALA  Pashi Kalana 
Harijan Basti  146  126 
AMOKHAR  Amokhr  Amokhr  927  435 
Pashi Khurd  467  192 
PASHI KALA  Pashi Khurd 
Panikan Basti  43  37 
BABHNAULI KALA  Urali  Urali  101  0 
MAGURAHI  Khewatha  Khewatha  125  14 
AMOKHAR  Mango  Mango  145  5 
   24  30  10323  2994 
Robertsganj  PIPARI  Dharnipur  Dharnipur  592  36 
Robertsganj  KARARI  Karari  Karari  986  442 
Robertsganj  PALIYA KALA  Mokarshim  Mokarshim  602  186 
Robertsganj  PALIA KALA  Palikalna  Palikalna  781  33 
Robertsganj  PIPARI  Darari  Darari  187  0 
Robertsganj  PIPARI  Pipari  Pipari  815  11 
Robertsganj  PALIA KALNA  Belwa  Belwa  88  0 
Robertsganj  BHARHIYA  Garawa  Garawa  321  0 
44  Robertsganj  BHARHIYA  Bhruiya  Bhruiya  383  7 
Robertsganj  BHARHIYA  Goithari  Goithari  354  190 
Robertsganj  Beechhi  Beechhi  Beechhi  1981  430 
Robertsganj  Pakari  Tirnahi  Tirnahi  285  44 
Robertsganj  Pakari  Bagadiha  Bagadiha  74  23 
Robertsganj  Pakari  Pakari  Pakari  1253  626 
Robertsganj  Ghuwaskhurd  Ghuaskalan  Ghuaskalan  832  86 
Robertsganj  Ghuashkurd  Ghuashkurd  Ghuashkurd  1674  510 
Robertsganj  Ganguar  Ganguar  Ganguar  763  370 
   17  17  11971  2994 
Robertsganj  Shenduri  Marhra  Marhra  669  247 
Ghorawal  JUROLI COLONY Jurauli Kolani  Jurauli Kolani  1016  933 
Ghorawal  SAHUAR  Shathi  Sathahi  498  57 
Ghorawal  Jurauri Kolany  Judauri Pardhan  Jurauli Pradhani  316  80 
45 
Bheravar  174  141 
Ghorawal  Kolakari  Bherawal 
Badhauta Tola  60  47 
Ghorawal  Jurauri Kolany  Shikari  Seekari  833  397 
Ghorawal  JAMGAON  Jamaganwa  Jamganwa  692  268 

  123 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Sl.No.  Block  Gram Panchayat  Village  Habitations  Population Census 2011 
               2011  SC / ST 
Jamugawna 1  401  124 
Ghorawal  SAHUAR  Kooran  Kooran  4  0 
Ghorawal  JAMGAON  Gobariya  Gobariya  531  325 
Ghorawal  SAHUAR  Barauli  Barauli  536  39 
Ghorawal  BELATAND  Shahganj  Shahganj  1628  296 
Ghorawal  SAHUAR  Sahuar  Sahuar  1159  385 
Ghorawal  JAMGAON  Manhawan  Manhawan  366  69 
Raipura  1391  500 
Robertsganj  Raipura  Raipura 
Kotiya  125  57 
Rajpur  2594  594 
Maeedhiya  332  56 
Robertsganj  Rajpur  Rajpur 
Kotya  1328  577 
Mhuariya  170  33 
Shenduri  614  235 
Robertsganj  Shenduri  Shenduri 
Badha Tola  341  44 
Robertsganj  Barak  Barak  Barak  1479  228 
Robertsganj  BANAURA 2  Shonwat  Shonwat  101  32 
   18  25  17358  5764 
Robertsganj  PARASI PANDEY Parashidubey  Parashidubey  482  130 
Robertsganj  UNCH DEEH  Aghwar  Aghwar  367  15 
Robertsganj  UNCHDEEH  Unchidih  Unchidih  751  390 
Raghunath Pur  2009  1318 
Ghorawal  Raghunathpur  Raghunathpur 
Hardihawa Tola  168  19 
Robertsganj  Bashauli  Bashauli  Bashauli  1486  639 
         Gandara Tola  189  185 
         Balhail Tola  129  66 
Ghorawal  Beechhiya  Bharganw  Bharganw  9  2 
Ghorawal  KHATAULI  Bhunari  Bhunari  126  68 
Ghorawal  Beechhiya  Raiwari  Raiwari  239  141 
46  Ghorawal  Beechhiya  Bajotara  Bajotara  211  20 
Ghorawal  KHATAULI  Amahata Amahti  Amahata Amahati  157  61 
Ghorawal  Beechhiya  Beechhiya  Beechhiya  639  240 
Ghorawal  KHATAULI  Khatauli  Khatauli  800  449 
Bahuar  1914  1023 
Robertsganj  Bahuar  Bahuar  Kacharia Tola  594  194 
Badhain  631  448 
Bashuari  161  0 
Robertsganj  Shenduri  Bashuari 
Masna Tola  116  0 
Robertsganj  MUTHER  Beohari  Beohari  100  23 
Robertsganj  MUTHER  Khchar  Khchar  328  87 
Robertsganj  BANAURA 2  Majhiganwa  Majhiganwa  500  131 

  124 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Sl.No.  Block  Gram Panchayat  Village  Habitations  Population Census 2011 
               2011  SC / ST 
   16  20  12106  5649 
Petrahi  Bhandar Khurd  Bhandar Khurd  188  0 
Gordiha  Gordiha  Gordiha  990  19 
Petrahi  Tilauli  Tilauli  800  547 
Baghuari  Baghari  Baghari  1588  1059 
Amauli  Amauli  Amauli  831  364 
Gordiha  Mahuar Khurd  Mahuar Khurd  140  75 
47  Robertsganj  Amauli  Papi  Papi  459  286 
Amauli  Patehra  Patehra  141  63 
Gordiha  Mahuar Kalna  Mahuar Kalna  118  9 
Petrahi  Petrahi  Petrahi  233  114 
Petrahi  Shindhora  Shindhora  201  159 
Petrahi  Bhandra Kalan  Bhandra Kalan  24  0 
Petrahi  Shemara  Shemara  46  16 
   14  16  5759  2711 
BABHNAULI  Babanauli  Babanauli  1517  414 
JAIT  Jait  Jait  808  355 
Gordiha  Karauli  Karauli  449  334 
Nipraj  Nipraj  Nipraj  1415  261 
MUTHER  Muther  Muther  592  314 
Nipraj  Kamojee  Kamojee  802  299 
48  Robertsganj 
Parashipandy  Parashipandy  Parashipandy  1055  385 
Kamarhi  Kamarhi  Kamarhi  2987  614 
Ghurma  Ghurma  Ghurma  998  160 
Petrahi  Gorari  Gorari  707  136 
Ghurma  Baraila  Baraila  152  108 
Ghurma  Jamgane  Jamgane  515  314 
   12  14  11997  3694 
Belatand 1  1309  160 
BELATAD  Belatand 
Belatand 2  469  33 
DOHARI  Atarwa  Atarwa  426  158 
BALDIH  Juriya  Juria  216  82 
BALDIH  Ganguhar  Ganguhar  135  69 
MARACHI  Renua  Renua  493  82 
49  Ghorawal  Kolakari  Kolakari  Kolakari  900  725 
Dugaulia  1157  506 
Dugaulia  Dugaulia  Hariya  763  383 
Tilahar  253  188 
Bansdih  1063  72 
BALDIH  Bansdih 
Bansdih 1  122  24 
MARACHI  Bichhwar  Bijhawr  78  8 

  125 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Sl.No.  Block  Gram Panchayat  Village  Habitations  Population Census 2011 
               2011  SC / ST 
MARACHI  Marachhi  Marachi  540  155 
MARACHI  Umarikhurd  Umarikhurd  418  36 
KOLKARI  Baraganwa  Baraganwa  640  200 
Kushra  Sohdaul  Sohdaul  405  88 
Kushra  Pipari No 2  Pipari No 2  281  102 
Kolakari  Onauli  Onauli  308  233 
Orhatha  Orhatha  Orhatha  2103  646 
   16  20  12079  3950 
Ghorawal  DABHA  Chakari  Chakari  85  0 
Robertsganj     Mahuali  Mahuali  10  0 
Robertsganj  BANAURA 2  Shajua  Shajua  3  3 
Shonauti  143  9 
Robertsganj  BANAURA 2  Shonauti 
Naee Basti  95  4 
Ghorawal  AMAUD  Usarikalan  Usarikala  606  0 
Ghorawal  AMAUD  Ushrikhurd  Usharikhurd  497  254 
Ghorawal  DABHA  Lasari Kalan  Lasari Kalan  655  138 
Ghorawal  DABHA  Masoe  Masoe  858  23 
Ghorawal  DABHA  Dabha  Dabha  799  167 
Ghorawal  DABHA  Lasari Khurd  Lasari Khurd  6  0 
Ghorawal  Durawal Khurd  Durawal Khurd  Durawal Khurd  640  226 
Ghorawal  Durawal Khurd  Hhrihar Pur  Hhrihar Pur  400  34 
Ghorawal  Durawal Khurd  Kasari  Kasari  39  0 
Shlaiya  620  321 
Robertsganj  UNCHDEEH  Shlaiya 
Mahuaa Tal  111  27 

50  Ghorawal  ENAM  Enam  Enam 1  1019  260 


         Enam 2  263  103 
Robertsganj  BANAURA II  Bagaura  Bagaura  765  332 
Robertsganj  BANAURA II  Bagauari  Bagauari  45  28 
Robertsganj  Barahda  Barahda  Barahda  525  166 
Robertsganj  Barahda  Bagathri Kalna  Bagathri Kalna  490  449 
Robertsganj  DURAWAL KALNA Bagathari Khurd  Bagathari Khurd  294  212 
Robertsganj  UNCHIDIH  Alahi Durawan Alahi Durawan  116  116 
Robertsganj  DURAVAL KALA  Durawal Kalna  Durawal Kalna  562  132 
         Bela Bandi  156  124 
Robertsganj  DURAVAL KALNA Shono  Shono  130  30 
Robertsganj  Deori Khurd  Jeewar  Jeewar  390  238 
Sihirshahi Parashe Sihirshahi Parashe 
Robertsganj  ORAULI  2  0 
Dubey  Dubey 
Robertsganj  MAHURESAR  Mahuresher  Mahuresher  467  237 
Robertsganj  MAHURESAR  Oani Chaubey  Oani Chaubey  339  157 
Robertsganj  ORAULI  Orauli  Orauli  745  295 
Robertsganj  MAHURESAR  Oanimishra  Oanimishra  381  55 

  126 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Sl.No.  Block  Gram Panchayat  Village  Habitations  Population Census 2011 
               2011  SC / ST 
         Samstipur  88  22 
Robertsganj  MAHURESAR  Jamashokar  Jamashokar  246  195 
Ghorawal  Amahar  Amahar/Amaud  Amahar  751  113 
Robertsganj  ORAULI  Eanam  Eanam  255  156 
Robertsganj  ORAULI  Kurashat  Kurashat  476  48 
Robertsganj  UMARIKALA  Umarikalna  Umarikalna  666  164 
Robertsganj  MAHURESAR  Gajana  Gajana  77  38 
Naraina  373  135 
Robertsganj  UMARIKALA  Naraina 
Sikthiya Tola  116  51 
Thuter  1302  78 
Ghorawal  Thuter  Thuter  Nauka Tola  311  42 
Chandikapur  394  55 
Ghorawal  SAHUAR  Tiwar  Tiwar  43  0 
   38  46  17354  5237 
JAMGAI  Juri  Juri  246  65 
Bakauli  Parari Kurd  Parari Kurd  271  46 
MUSARDHARA  Mushrdhara  Mushrdhara  538  306 
Panauli  Atarauli Kalan  Atarauli Kalan  116  26 
Tendui  Kewata  Kewata  444  0 
Tendui  Tendui  Tendui  804  41 
Obaradeeh  Obaradih  Obaradih  657  290 
MUSARDHARA  Domahar  Domahar  454  188 
Selahata  1092  655 
Obaradeeh  Selahata 
Hardihawa Tola  61  20 
Kusinisph  Kusinisph  Kusinisph  1201  668 
MAHUWAW 
Mhunyw Pandy  Mahuaw Pandey  537  221 
PANDEY 
51  Ghorawal  MAHUWAW 
Mahuna Gosani  Mahuna Gosani  504  332 
PANDEY 
Panauli  Kunda  Kunda  82  3 
Sidhi  Sadari  Sadari  555  274 
Obaradeeh  Jinhora  Jinhora  258  0 
Kusinisph  Naidiha  Naidiha  294  106 
Aurahi  Aurahi  Aurahi  555  319 
Sidhi  Sidhi  Sidhi  572  335 
Sidhi  Athauna  Athauna  450  180 
MASIAADINATH  Bhgawas  Bhagawas  204  0 
Jamagani  Kharera  Kharera  187  27 
Morahi 1  936  160 
MORAHI  Morahi  Morahi 2  190  44 
Bahari Tola  74  22 
   22  25  11282  4328 

  127 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Sl.No.  Block  Gram Panchayat  Village  Habitations  Population Census 2011 
               2011  SC / ST 
Barauli  Barauli  Barauli  816  615 
Gurwal  Gurwal  Gurwal  1636  1051 
Barauli  Bandha  Bandha  468  311 
Belwania  Belwania  Belwania  1249  727 
Belwania  Karaundia  Karaundia  74  23 
Belwania  Rampur  Rampur  396  91 
Dhanawal  Panti  Panti  317  180 
Dhanawal  Dhanawal  Dhanawal  700  295 
52  Ghorawal 
Lohari  1109  364 
LOHANDI  Lohari  Jogiyabeer  235  65 
Kachaha Tola  125  90 
Ahraura  813  542 
Ahraura  Ahraura 
Kevalipur  137  21 
Bakuli  Durkhuli  Durkhuli  742  388 
Guretha  Guretha  Guretha  1068  826 
AHRAURA  Rajin  Rajin  216  142 
   13  16  10101  5731 
Divar  784  243 
Divar  Divar 
Pal Basti  276  195 
Khajaraul  Khajaraul  Khajaraul  1174  504 
Divar  Bhairawa  Bhairawa  253  195 
MUSARDHARA  Majhali  Majhali  25  21 
Khajaraul  Garwa  Garwa  179  47 
Panauli  Chorat  Chorat  510  227 
Panauli  Panauli  Panauli  579  237 
MORAHI  Naunia  Naunia  22  0 
Domakhri  506  339 
DOMKHARI  Domakhri  Kolpurawa  582  268 
Daurpura  323  181 
53  Ghorawal 
Khirahata  657  454 
Khirahata  Khirahata 
Yadav Basti  465  195 
DIVER  Garama  Garama  1266  1033 
Barsot  314  256 
SOTIL  Barsot 
Kushwaha Basti  107  76 
Sotil  947  397 
SOTIL  Sotil 
Sadkepura  468  135 
Bakuli  Jaimohra  Jaimohra  707  231 
Bakuli  Pateri  Pateri  258  151 
Bakuli  Bakuli  Bakauli  401  194 
Odar  549  486 
KUSUMHA  Odar 
Kushwaha Nai Basti  411  66 

  128 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Sl.No.  Block  Gram Panchayat  Village  Habitations  Population Census 2011 
               2011  SC / ST 
Bakuli  Dhuria  Dhuria  103  38 
Kusmaha  1178  224 
KUSUMHA  Kusmaha 
Jawarahi Tola  152  37 
   19  27  13196  6430 
DEVARI KATH  Dewerikatha  Dewerikatha  1129  428 
54  Ghorawal  PERHA  Peroh  Peroh  5441  2555 
DEVARIKATH  Dhorkary  Dhorkary  1202  464 
         3  3  7772  3447 
Beheri  Mohani  Mohani  353  268 
Beheri  Beerkhurd  Beerkhurd  336  86 
MAGHIGAWA 
Baraudhi  Baraudhi  603  554 
CHAUHAN 
MAGHIGAWA 
Kon  Kon  17  0 
CHAUHAN 
Beheri  Beheri  Beheri  417  205 
MAJHIGAVA  Majhgawan
Majhgawan Chauhan  651  406 
55  Ghorawal  CHOHAN  Chauhan 
MARSARA  Marasara  Marasara  837  647 
BHARAUJI  Dumaribharaulia  Dumaribharaulia  13  0 
Dharsara  Dhadhi  Dhadhi  452  312 
Dharsara  Dharsara  Dharsara  555  293 
Bisrekhi 1  1058  296 
BISREKHI  Bisrekhi 
Bisrekhi 2  787  671 
MARSADA  Jaimohara  Jaimohara  75  25 
   12  13  6154  3763 
Junia  Junia  Junia  777  277 
Dharsara  Raikara  Raikara  9  0 
MARASARA  Naugai  Naugai  727  376 
MARASARA  Uchdih  Uchdih  317  69 
Bhawana  Lakshimanpur  Lakshimanpur  721  367 
56  Ghorawal  NAUGAWAN AND 
Chain  Chain  534  282 
LAL 
MAUGAWAN
Naugawan  Naugawan  1097  343 
ANDLAL 
Bhawana  Bhawana  Bhawana  726  450 
JUDIA  Dewerikhurd  Dewerikhurd  445  222 
Bhawana  Halwai  Halwai  233  70 
   10  10  5586  2456 
Bhanswar  2032  686 
Bhanswar Ii  601  352 
BHAINSWAR  Bhanswar 
57  Ghorawal  Bhanswar Iii  1022  334 
Bhanswar Iv  831  140 
MAGAR DAHA  Magaradaha  Magaradaha 1  1988  937 

  129 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Sl.No.  Block  Gram Panchayat  Village  Habitations  Population Census 2011 
               2011  SC / ST 
Magaradaha 2  1227  640 
Visahar 1  1294  457 
Visahar 2  554  347 
VISAHAR  Visahar 
Dihpura  66  55 
Jaljaliya  87  90 
   3  10  9702  4038 
Robertsganj  AMAULI  Amauli  Amauli  713  458 
Robertsganj  KARARI  Shuhali  Shuhali  28  11 
Robertsganj  BITHGAON NISHOH  Bithgon Nishoh  Bithgon Nishoh  92  13 
Robertsganj  BITHGAON NISHPH  Bithgawn Nishph  Bithgawn Nishph  915  470 
Robertsganj  Shajaur  Majhigaon Mishra  Majhigaon Mishra  507  176 
Robertsganj  Bithgawn Nishph B  Shirpalpur  Shirpalpur  749  197 
Robertsganj  Lashra  Lashra  Lashra  1085  260 
58  Robertsganj  Shajaur  Majhigaon Chaubey  Majhigaon Chaubey  382  127 
Robertsganj  BEEJAULI  Pali  Pali  526  252 
Robertsganj  Beejauli  Beejauli  Beejauli  908  155 
Robertsganj  Teyara Nayak  Meuri Kalan  Meuri Kalan  411  133 
Robertsganj  Teyara Nayak  Teyara Nayak  Teyara Nayak  506  257 
Robertsganj  Dhobahi  Akachor  Akachor  1184  200 
Robertsganj  Shajaur  Shajaur  Shajaur  571  217 
Robertsganj  Teyara Nayak  Meuri Khurd  Meuri Khurd  170  33 
   15  15  8747  2959 
Robertsganj  DHOBHI  Dhobahi  Dhobahi  370  187 
Robertsganj  Silthary  Mangurahee  Mangurahee  234  8 
Robertsganj  Harhuna  Kusamha  Kusamha  49  0 
Robertsganj  Harhuna  Atarauli Khurd  Atarauli Khurd  42  0 
Robertsganj  SIDDHIKALA  Lakhanwar Khurd  Lakhanwar Khurd  383  33 
59 
Robertsganj  Kharhari  Kharhari  Kharhari  515  41 
Robertsganj  Silthari  Bharganwa  Bharganwa  131  0 
Robertsganj  Sidhi Kalana  Lakhanwar Kalna  Lakhanwar Kalna  372  30 
Robertsganj  Bhaburahi  Bhadohi  Bhadohi  207  0 
Robertsganj  Arauly  Arauly  Arauly  1557  747 
   10  10  3860  1046 
Robertsganj  Harhuna  Bijary Duban  Bijary Duban  218  101 
Robertsganj  Harhuna  Bahuarah  Bahuarah  621  292 
Robertsganj  Harhuna  Harhuna  Harhuna  487  293 
Robertsganj  Harhuna  Bijary Patkhan  Bijary Patkhan  307  31 
60 
Robertsganj  Kura  Kura  Kura  472  137 
Robertsganj  RAUP  Raunp  Raunp  1860  430 
         Mahulia Tola  652  419 
Robertsganj  Kura  Musahee  Musahee  1045  405 

  130 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Sl.No.  Block  Gram Panchayat  Village  Habitations  Population Census 2011 
               2011  SC / ST 
         Charkonwa  853  668 
Robertsganj  Churk  Churk  Churk  1530  350 
   8  10  8045  3126 
Total  663  880  570515  224891 

15. PROJECTED POPULATION FOR BASE YAER,INTERMEDIATE YAER AND ULTIMATE YAER
BY INCREMENTAL METHOD AS SUGGESTED BY DPR.

1.0 Population Projection


3. The Population figure of village include in the scheme has been calculated as follows :-

Population Projection
Decade
Sl.No. Year Population Increase % of Increase
Increase
1 1971 180289

2 242000 61711 0.34


1981
3 323001 81001 19290 0.33
1991
4 445231 122230 41229 0.38
2001
5 570515 125284 3054 0.28
2011
Total 390226 63573 1.33

Average d =97557 I =21191 0.33

  131 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Population for Last 5 Decade
600000 570515

500000 445231

400000
Population

323001
300000
242000
180289
200000

100000

0
1971 1981 1991 2001 2011
Year

Summary of Population projected by Various Method
Semi log 

1245000
Method

570515

560600

760000
Graph 

1230000 925000
680000
545538
Population Projection Methods

855000
Method
Simple 

570515

475320

565105
Incremental  Graph 

655000 735000
625000
545538
Progression Progression Increase

980120
570515

715560

931930

1211660 792040
634090
545538
Arithmetica Geometrica

1232160

1202850
570515

803330

1889930 894220

664770
545538

846150
570515

687590

833920

980260 733420

620690
545538

0 400000 800000 1200000


Population
2051 2036 2021 2011

  132 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

A). Arithmetical Progression Method:-


The population at the end of any year is given the following expression.
Pn = P + d x 0.1 x n
Where,
Pn =Population after and years after base year
P =Population at the end of base year 2011 570515
which is
d =Average increase in population decade 97557
n =No. of years after base year

i)- Population in year 2023 = 570515 + (1.2 X 97557)

= 687582.80 ≈ 687590

ii)- Population in year 2038 = 570515 + (2.7 X 97557)

= 833917.55 ≈ 833920

iii)- Population in year 2053 = 570515 + (4.2 X 97557)

= 980252.30 ≈ 980260

B). Geometrical progression Method:-


The population at the end of any year is given the following expression.
Pn = P ( 1 + r ) 0.1 x n

Geometrical Mean of Percentage Increase(rg)


r = ( 0.34 X 0.33 X 0.38 X 0.28 )1/4

r = 0.330 ≈ 0.330
Where,
Pn = Population after and years after base year
P= Population at the end of base year 2011 which is 570515
r= Geometric decadal increase which is 0.33
n= No. of years after base year

i)- Population in year 2023 = 570515 ( 1 + 0.330 )1.2

= 803320.845248993 ≈ 803330.00

ii)- Population in year 2038 = 570515 (1 + 0.330 )2.7

= 1232158.27488124 ≈ 1232160.00

  133 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

ii)- Population in year 2053 = 570515 ( 1 + 0.330 )4.2

= 1889922.34340405 ≈ 1889930.00

C). Incremental Progression Method:-


The population at the end of any year is given the following
expression.
Pn=P + n x d x 0.1 + ( 0.1 x n ) ( 0.1 x n + 1 ) x I / 2
Where,
Pn = Population after and years after base year
P = Population at the end of base year 2011 which is 570515.00
d = Average increase in population decade- 97557
n = No. of years after base year
I = Incremental Increase 21191
i)- Population in year 2023 = 570515 + ( 1.2 X 97557 ) + 1.2 ( 1 + 1.2 ) X ( 21191 / 2 )

Population in year 2023 = 715554.92 ≈ 715560

ii)- Population in year 2038 = 570515 + ( 2.7 X 97557 ) + 2.7 ( 1 + 2.7 ) X ( 21191 / 2 )

Population in year 2038 = 931925.93 ≈ 931930

iii)- Population in year 2053 = 570515 + ( 4.2 X 97557 ) + 4.2 ( 1+ 4.2 ) X ( 21191 / 2 )

Population in year 2053 = 1211658.0 ≈ 1211660

D). Simple Graph Method:-


Sl. No. Year Population
1 2023 475320
2 2038 565105
3 2053 655000

Semi Log Graph


E).
Method:-
S. No. Year Population
1 2023 560600
2 2038 760000
3 2053 1230000

  134 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Simple Graph Method:‐ 
 
1971  206287
1981  240117
1991  277851
2001  342771
2011  421894
2023  475320
2038  565105
2053  655000

700000

600000

500000

400000

Series1
Linear (Series1)
300000

200000

100000

0
1961 1971 1981 1991 2001 2011 2021 2031 2041 2051

  135 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Semi Log Graph Method:‐ 

1971  206287
1981  240117
1991  277851
2001  342771
2011  421894
2023  560600
2038  760000
2053  1230000

10000000

1000000

100000

10000

Series1
1000 Expon. (Series1)

100

10

1
1960 1980 2000 2020 2040 2060

  136 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Population Projection arrived by different methods is tabulated as below:-


Year
Sl.No. Method
2011 2023 2038 2053
1 Arithmetical Progression 570,515 687,590 833,920 980,260
2 Geometrical Progression 570,515 803,330 1,232,160 1,889,930
3 Incremental Increase 570,515 715,560 931,930 1,211,660
4 Simple Graph Method 570,515 475,320 565,105 655,000
5 Semi log Graph Method 570,515 560,600 760,000 1,230,000

F). CONCLUSION:-
From the above table, it is observed that the population figures obtained by
Arithmetical Progression Method, Simple Graph Method and incremental graph
Method are on lower side, whereas population figure obtained by Geometrical
Increase Method and Semi Log Graph Method is on higher side but calculation by
Incremental Increase Method is quite reasonable considering recent growth pattern of
this scheme.

Sl. No. Year Population


1 2023 715560
2 2038 931930
3 2053 1211660

  137 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Population
Sl.No Villages
2011 2023 2038 2053
1 Karia  1938 2431 3166 4116
2 Tendua  1284 1610 2097 2727
3 Barbaspur  468 587 764 994
4 Ghuwas  1929 2419 3151 4097
5 Basahi  537 674 877 1140
6 Lali  859 1077 1403 1824
7 Mukkha  614 770 1003 1304
8 Amilia  332 416 542 705
9 Amilaudha  653 819 1067 1387
10 Karsoata  707 887 1155 1502
11 Lahas  798 1001 1304 1695
12 Sirsain  1278 1603 2088 2714
13 Fulwary  715 897 1168 1519
14 Madhaka  744 933 1215 1580
15 Samerwar  336 421 549 714
16 Mahokhar  534 670 872 1134
17 Ubha  766 961 1251 1627
18 Pathartal  486 610 794 1032
19 Karry  30 38 49 64
20 Rahi  925 1160 1511 1965
21 Purana  2052 2574 3352 4358
22 Ghoria  484 607 791 1028
23 Semera Kala  323 405 528 686
24 Semera Khurd  24 30 39 51
25 Babhari  915 1148 1495 1943
26 Marni  492 617 804 1045
27 Murtiya  1998 2506 3264 4243
28 Dholo  921 1155 1504 1956
29 Amli Pokhar  863 1082 1410 1833
30 Sapahi  536 672 876 1138
31 Tenthuhar  1583 1985 2586 3362
32 Parsauna  3422 4292 5590 7268
33 Majurahi  370 464 604 786
34 Kanhari  2095 2628 3422 4449
35 Siwadar  2207 2768 3605 4687
36 Bantara  87 109 142 185
37 Deogarha  864 1084 1411 1835
38 Hinauti  2304 2890 3764 4893
39 Parwania  2135 2678 3487 4534

  138 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Population
Sl.No Villages
2011 2023 2038 2053
40 Bardiya  2202 2762 3597 4677
41 Rumma  429 538 701 911
42 Manhwa  1365 1712 2230 2899
43 Khajuari  119 149 194 253
44 Harankhuri  595 746 972 1264
45 Meejhun  637 799 1041 1353
46 Chandwa  85 107 139 181
47 Bhainshi  177 222 289 376
48 Sonhati  382 479 624 811
49 Dulahatha  317 398 518 673
50 Bar  2185 2741 3569 4641
51 Seegra  54 68 88 115
52 Baijanath  552 692 902 1172
53 Gawnkunda  268 336 438 569
54 Satdwari  610 765 996 1296
55 Chigori  928 1164 1516 1971
56 Domakhri  1411 1770 2305 2997
57 Dhura Kund  678 850 1108 1440
58 Amadhi  360 452 588 765
59 Manjhiganwa Mishra  517 648 845 1098
60 Kon  17 21 28 36
61 Bauradih  173 217 283 367
62 Jurauli Kolani  1016 1274 1660 2158
63 Lilwahi  1140 1430 1862 2421
64 Koharatha  1507 1890 2462 3201
65 Koladiha  591 741 965 1255
66 Bharkana  1257 1577 2053 2670
67 Bhagahi  197 247 322 418
68 Baidawar  25 31 41 53
69 Jamua  40 50 65 85
70 Sonabarsa  2 3 3 4
71 Khagia  1067 1338 1743 2266
72 Musha  550 690 898 1168
73 Mandha  442 554 722 939
74 Snihawal  179 225 292 380
75 Janar  378 474 617 803
76 Beerkala  852 1069 1392 1809
77 Dorihar  1166 1462 1905 2476
78 Khardeur  1261 1582 2060 2678
79 Mohani  353 443 577 750

  139 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Population
Sl.No Villages
2011 2023 2038 2053
80 Beerkhurd  336 421 549 714
81 Baraudhi  603 756 985 1281
82 Beheri  417 523 681 886
83 Majhgawan Chauhan  651 817 1063 1383
84 Kanhi  1373 1722 2243 2916
85 Dharmauli  881 1105 1439 1871
86 Keweta  837 1050 1367 1778
87 Khakh  431 541 704 915
88 Mahvarioa  497 623 812 1056
89 Kewali  932 1169 1522 1979
90 Khadaha  280 351 457 595
91 Munghri  791 992 1292 1680
92 Khutaha  3049 3824 4981 6475
93 Samara  364 457 595 773
94 Hinauti  31 39 51 66
95 Parsauna Khurd  99 124 162 210
96 Junia  777 975 1269 1650
97 Pidaria  1309 1642 2138 2780
98 Parhi  794 996 1297 1686
99 Satohan  1631 2046 2664 3464
100 Newari  2500 3136 4084 5310
101 Nakawai  335 420 547 711
102 Visundhary  3295 4133 5382 6998
103 Amilia  809 1015 1321 1718
104 Tilauli Kalana  3821 4792 6242 8115
105 Khuthnia  1421 1782 2321 3018
106 Geduri  116 145 189 246
107 Sahpurwa Khurd  192 241 314 408
108 Kamhria  137 172 224 291
109 Bnardewa  1003 1258 1638 2130
110 Kathapura  401 503 655 852
111 Silahta  1087 1363 1776 2309
112 Jogani  2453 3077 4007 5210
113 Naudiha  341 428 557 724
114 Khodaichak  14 18 23 30
115 Bisun Pur  109 137 178 231
116 Atarwa  426 534 696 905
117 Teti  248 311 405 527
118 Gotauli  219 275 358 465
119 Juri  246 309 402 522

  140 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Population
Sl.No Villages
2011 2023 2038 2053
120 Masiadinath  501 628 818 1064
121 Chakari  85 107 139 181
122 Sawat  719 902 1174 1527
123 Jamaghne  353 443 577 750
124 Padri Kalan  256 321 418 544
125 Maid  251 315 410 533
126 Masiha Pathan  436 547 712 926
127 Belkuri Murpharkat  257 322 420 546
128 Mureladih  1739 2181 2841 3693
129 Parari Kurd  271 340 443 576
130 Kharuaun  1390 1743 2271 2952
131 Karrivarai  1098 1377 1794 2332
132 Kamhria  332 416 542 705
133 Rudauli  326 409 533 692
134 Dhoa  975 1223 1593 2071
135 Tilauli Khurd  190 238 310 404
136 Aruna  1173 1471 1916 2491
137 Vimauri  761 954 1243 1616
138 Velahi  576 722 941 1223
139 Semari Misra  685 859 1119 1455
140 Khudia  525 658 858 1115
141 Ataraila  148 186 242 314
142 Purkhas  2324 2915 3796 4936
143 Phulawari  1113 1396 1818 2364
144 Bahorika  494 620 807 1049
145 Sahpurwa Kalan  285 357 466 605
146 Pagia  2170 2722 3545 4609
147 Bharawah  1089 1366 1779 2313
148 Khairwa  234 293 382 497
149 Birmaua  149 187 243 316
150 Chakahi  395 495 645 839
151 Mukasim  1561 1958 2550 3315
152 Uachka  427 536 697 907
153 Pandepokhar  1052 1319 1718 2234
154 Ranitara  1329 1667 2171 2823
155 Barimahewa  2478 3108 4048 5263
156 Dudhia  629 789 1027 1336
157 Bhulahi  144 181 235 306
158 Teprasivadati  702 880 1147 1491
159 Salaia  11 14 18 23

  141 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Population
Sl.No Villages
2011 2023 2038 2053
160 Jorwria  1675 2101 2736 3557
161 Asana  489 613 799 1039
162 Patehara  714 896 1166 1516
163 Khairawa Raja  128 161 209 272
164 Rajkhar  44 55 72 93
165 Pateri  435 546 711 924
166 Tulsipur  34 43 56 72
167 Jawahi  430 539 702 913
168 Sirvit  2290 2872 3741 4864
169 Etwa  56 70 91 119
170 Saranga  2382 2988 3891 5059
171 Tedhwa  88 110 144 187
172 Sirsiajethi  1300 1631 2124 2761
173 Kolariya  646 810 1055 1372
174 Dharura  1426 1789 2329 3029
175 Sitabahar  557 699 910 1183
176 Karkoll  1455 1825 2377 3090
177 Tekuria  1751 2196 2860 3719
178 Mahuriya  529 663 864 1123
179 Babanauli  1517 1903 2478 3222
180 Barkara  838 1051 1369 1780
181 Jait  808 1013 1320 1716
182 Tipara  386 484 631 820
183 Manpur  2195 2753 3586 4662
184 Khairahi  422 529 689 896
185 Parashidubey  482 605 787 1024
186 Bauar  406 509 663 862
187 Mamuna  975 1223 1593 2071
188 Pawar  951 1193 1553 2020
189 Kalwari  241 302 394 512
190 Burhr Khurd  804 1008 1313 1708
191 Deori Kalan  463 581 756 983
192 Kushai  460 577 751 977
193 Burar Kalan  945 1185 1544 2007
194 Nauganwa Kalan  334 419 546 709
195 Kewati  596 748 974 1266
196 Dehra  152 191 248 323
197 Theru  392 492 640 833
198 Babura  387 485 632 822
199 Pursotampur  236 296 386 501

  142 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Population
Sl.No Villages
2011 2023 2038 2053
200 Nauganwa Khurd  596 748 974 1266
201 Organai  1247 1564 2037 2648
202 Durha  153 192 250 325
203 Deora Raja  229 287 374 486
204 Bagaura  765 959 1250 1625
205 Belatand  1778 2230 2904 3776
206 Khajurikhurd  302 379 493 641
207 Usarikalan  606 760 990 1287
208 Ushrikhurd  497 623 812 1056
209 Lasari Kalan  655 822 1070 1391
210 Khajurikala  364 457 595 773
211 Bhurkura  486 610 794 1032
212 Masoe  858 1076 1402 1822
213 Dabha  799 1002 1305 1697
214 Lasari Khurd  6 8 10 13
215 Durawal Khurd  640 803 1045 1359
216 Bhuli  227 285 371 482
217 Hhrihar Pur  400 502 653 850
218 Kunan  185 232 302 393
219 Balua  180 226 294 382
220 Kasari  39 49 64 83
221 Enam  1282 1608 2094 2723
222 Aghwar  367 460 599 779
223 Bagauari  45 56 74 96
224 Unchidih  751 942 1227 1595
225 Shlaiya  731 917 1194 1552
226 Barahda  525 658 858 1115
227 Bagathri Kalna  490 615 800 1041
228 Bagathari Khurd  294 369 480 624
229 Alahi Durawan  116 145 189 246
230 Deori Khurd  429 538 701 911
231 Durawal Kalna  718 901 1173 1525
232 Shono  130 163 212 276
233 Rajapurawa  117 147 191 248
234 Tiarashiv Datt  199 250 325 423
235 Chaktiara  8 10 13 17
236 Karhi  238 299 389 505
237 Jeewar  390 489 637 828
238 Bhagwantpur  248 311 405 527
239 Dahari  654 820 1068 1389

  143 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Population
Sl.No Villages
2011 2023 2038 2053
Sihirshahi Parashe 
Dubey  2 3 3 4
240
241 Mahuresher  467 586 763 992
242 Petrahi  418 524 683 888
243 Katawaria  1013 1271 1655 2151
244 Oani Chaubey  339 425 554 720
245 Orauli  745 934 1217 1582
246 Oanimishra  469 588 766 996
247 Deora  405 508 662 860
248 Jamashokar  246 309 402 522
249 Kanhara  290 364 474 616
250 Karma  575 721 939 1221
251 Majhiganwa  487 611 796 1034
252 Dohari  427 536 697 907
253 Welanow  601 754 982 1276
254 Hinauti  43 54 70 91
255 Koharaul  348 436 568 739
256 Khaira  609 764 995 1293
257 Kapura  137 172 224 291
258 Khairi  79 99 129 168
259 Chotakapur  431 541 704 915
260 Barsota  810 1016 1323 1720
261 Welkhuri  462 579 755 981
262 Uchaka  1138 1427 1859 2417
263 Bhruha  733 919 1197 1557
264 Pipri No. 1  458 574 748 973
265 Lohdhara  212 266 346 450
266 Jamagane  608 763 993 1291
267 Sauli  118 148 193 251
268 Chakauli  261 327 426 554
269 Asatali  163 204 266 346
270 Noni  680 853 1111 1444
271 Kingari  1232 1545 2012 2617
272 Chhuta  328 411 536 697
273 Kurashat  476 597 778 1011
274 Eanam  255 320 417 542
275 Petrahi  632 793 1032 1342
276 Umarikalna  666 835 1088 1414
277 Mishra  66 83 108 140
278 Gajana  77 97 126 164

  144 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Population
Sl.No Villages
2011 2023 2038 2053
279 Naraina  489 613 799 1039
280 Arangi  817 1025 1335 1735
281 Gheuri  342 429 559 726
282 Dilahi  997 1250 1629 2117
283 Karanwah  249 312 407 529
284 Bahera  2370 2973 3871 5033
285 Jurawat  465 583 760 988
286 Tandi  230 288 376 488
287 Madainia  693 869 1132 1472
288 Jaderua  2630 3299 4296 5586
289 Sirsiathkurai  7289 9142 11907 15480
290 Bharuha  557 699 910 1183
291 Bhadohi  207 260 338 440
292 Shirsia  14 18 23 30
293 Atarauli Raja  349 438 570 741
294 Sarauli  1970 2471 3218 4184
295 Garaegarh  1148 1440 1875 2438
296 Dularu  27 34 44 57
297 Khairahi  2469 3097 4033 5244
298 Atarawa  699 877 1142 1485
299 Baburahi  954 1197 1558 2026
300 Bantara  1016 1274 1660 2158
301 Majhui  1342 1683 2192 2850
302 Mubarakpur  2277 2856 3719 4836
303 Baghor  1255 1574 2050 2665
304 Dhotwa  188 236 307 399
305 Gorahi  2448 3070 3999 5199
306 Khane Azampur  776 973 1268 1648
307 Kutulupur  946 1187 1545 2009
308 Lohra  6843 8583 11178 14533
309 Sukrit  6899 8653 11269 14652
310 Bhatulia  1636 2052 2672 3475
311 Bakahi  962 1207 1571 2043
312 Sirsia  928 1164 1516 1971
313 Padar  515 646 841 1094
314 Kairwa  225 282 368 478
315 Pipara  472 592 771 1002
316 Kushhi  247 310 403 525
317 Garhwa  231 290 377 491
318 Mangurahi  413 518 675 877

  145 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Population
Sl.No Villages
2011 2023 2038 2053
319 Darah  328 411 536 697
320 Jori  712 893 1163 1512
321 Sheokari  709 889 1158 1506
322 Murala Dih  24 30 39 51
323 Khekhara  606 760 990 1287
324 Basawa Nisph  636 798 1039 1351
325 Tinatali  1207 1514 1972 2563
326 Tilya  870 1091 1421 1848
327 Bhagauti  691 867 1129 1468
328 Papi  872 1094 1424 1852
329 Patela  176 221 287 374
330 Madar  731 917 1194 1552
331 Baghi  786 986 1284 1669
332 Parsona  277 347 452 588
333 Kamaharia  129 162 211 274
334 Birhulia  363 455 593 771
335 Mahulia  197 247 322 418
336 Dehari  533 669 871 1132
337 Gouri Nisph  610 765 996 1296
338 Kathpurwa  420 527 686 892
339 Kasya Kalan  596 748 974 1266
340 Kushahi  143 179 234 304
341 Bashdewa  622 780 1016 1321
342 Kekarahi  1877 2354 3066 3986
343 Karaki  1452 1821 2372 3084
344 Kasya Khurd  264 331 431 561
345 Kucha Marwa  472 592 771 1002
346 Khairawa No 2  29 36 47 62
347 Kharahri  57 71 93 121
348 Shirkhora  102 128 167 217
349 Jokahi  343 430 560 728
350 Machhalawa  152 191 248 323
351 Aelahi  1324 1661 2163 2812
352 Hinauta  1826 2290 2983 3878
353 Amaulia  607 761 992 1289
354 Chakara  669 839 1093 1421
355 Parahi  2195 2753 3586 4662
356 Amdih  1534 1924 2506 3258
357 Bhawanipur  2379 2984 3886 5053
358 Khamriha  1102 1382 1800 2340

  146 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Population
Sl.No Villages
2011 2023 2038 2053
359 Nagnar Haraia  3857 4838 6300 8191
360 Baghauri  177 222 289 376
361 Bat  3621 4542 5915 7690
362 Madhupur  9710 12179 15861 20622
363 Takia Mu.Dargah  2426 3043 3963 5152
364 Gordiha  434 544 709 922
365 Bahera  206 258 336 438
366 Purainiya  210 263 343 446
367 Jigana  717 899 1171 1523
368 Alahi  151 189 247 321
369 Bargawn  659 827 1076 1400
370 Bishbhrpur  208 261 340 442
371 Parsona  126 158 206 268
372 Pateara  154 193 252 327
373 Domariya  297 373 485 631
374 Rampur  579 726 946 1230
375 Baheri  291 365 475 618
376 Kaithi  1138 1427 1859 2417
377 Khrehari  360 452 588 765
378 Deogarh  435 546 711 924
379 Kushi  3569 4476 5830 7580
380 Tendee  141 177 230 299
381 Pakari  1253 1572 2047 2661
382 Lashra  1085 1361 1772 2304
Majhigaon Chaubey  382 479 624 811
383
384 Shirpalpur  749 939 1223 1591
Majhigaon Mishra  507 636 828 1077
385
386 Ghuaskalan  832 1044 1359 1767
387 Ganguar  763 957 1246 1620
388 Bagadiha  74 93 121 157
389 Tirnahi  285 357 466 605
390 Beechhi  1981 2485 3236 4207
391 Ghuashkurd  1674 2100 2734 3555
392 Amauli  713 894 1165 1514
393 Shuhali  28 35 46 59
394 Bithgon Nishoh  92 115 150 195
395 Bithgawn Nishph  915 1148 1495 1943
396 Dharnipur  592 743 967 1257
397 Karari  986 1237 1611 2094
398 Mokarshim  602 755 983 1279

  147 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Population
Sl.No Villages
2011 2023 2038 2053
399 Palikalna  781 980 1276 1659
400 Darari  187 235 305 397
401 Pipari  815 1022 1331 1731
402 Belwa  88 110 144 187
403 Lakhan Purwa  441 553 720 937
404 Garawa  321 403 524 682
405 Bhruiya  383 480 626 813
406 Goithari  354 444 578 752
407 Jamuanua  619 776 1011 1315
408 Dhuriya  405 508 662 860
409 Jamaganwa  442 554 722 939
410 Nai Basti  492 617 804 1045
411 Ratawal  99 124 162 210
412 Mahuaon  289 362 472 614
413 Hinauti  414 519 676 879
414 Hona  482 605 787 1024
415 Hinduhari  1270 1593 2075 2697
416 Barwan  798 1001 1304 1695
417 Majhi Ganwa  272 341 444 578
Shemari Bishunlal  517 648 845 1098
418
419 Babhanauli Khurd  229 287 374 486
420 Bhogar  349 438 570 741
Babhanauli Kalan  589 739 962 1251
421
422 Shango  127 159 207 270
423 Pashi Kalana  740 928 1209 1572
424 Amokhr  927 1163 1514 1969
425 Pashi Khurd  510 640 833 1083
426 Urali  101 127 165 215
427 Khewatha  125 157 204 265
428 Mango  145 182 237 308
429 Mahokhar  286 359 467 607
430 Chandauli  513 643 838 1090
431 Tendu  419 526 684 890
432 Mahuari  1102 1382 1800 2340
433 Kamahar Dih  1690 2120 2761 3589
434 Bahura  7420 9306 12120 15759
435 Papi  459 576 750 975
436 Majhiganwa  500 627 817 1062
437 Raghunathpur  2177 2730 3556 4624
438 Bharganw  9 11 15 19

  148 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Population
Sl.No Villages
2011 2023 2038 2053
439 Bhunari  126 158 206 268
440 Raiwari  239 300 390 508
441 Bajotara  211 265 345 448
442 Amahata Amahti  157 197 256 333
443 Beechhiya  639 801 1044 1357
444 Khatauli  800 1003 1307 1699
445 Bhandar Khurd  188 236 307 399
446 Baghari  1588 1992 2594 3373
447 Bahuar  3139 3937 5128 6667
448 Bashauli  1804 2263 2947 3831
449 Bashuari  277 347 452 588
450 Tilauli  800 1003 1307 1699
451 Amauli  831 1042 1357 1765
452 Mahuar Khurd  140 176 229 297
453 Patehra  141 177 230 299
454 Mahuar Kalna  118 148 193 251
455 Karauli  449 563 733 954
456 Gordiha  990 1242 1617 2103
457 Nipraj  1415 1775 2311 3005
458 Muther  592 743 967 1257
459 Kamojee  802 1006 1310 1703
460 Marhra  669 839 1093 1421
461 Beohari  100 125 163 212
462 Mahuali  10 13 16 21
463 Khchar  328 411 536 697
464 Parashipandy  1055 1323 1723 2241
465 Shajua  3 4 5 6
466 Shathi  498 625 813 1058
467 Juriya  216 271 353 459
468 Judauri Pardhan  316 396 516 671
469 Bherawal  234 293 382 497
470 Ganguhar  135 169 221 287
471 Renua  493 618 805 1047
472 Kolakari  900 1129 1470 1911
473 Dugaulia  2173 2725 3550 4615
474 Shikari  833 1045 1361 1769
475 Bansdih  1185 1486 1936 2517
476 Bichhwar  78 98 127 166
477 Marachhi  540 677 882 1147
478 Jamaganwa  1093 1371 1785 2321

  149 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Population
Sl.No Villages
2011 2023 2038 2053
479 Umarikhurd  418 524 683 888
480 Kooran  4 5 7 8
481 Baraganwa  640 803 1045 1359
482 Gobariya  531 666 867 1128
483 Barauli  536 672 876 1138
484 Shahganj  1628 2042 2659 3458
485 Sahuar  1159 1454 1893 2461
486 Sohdaul  405 508 662 860
487 Manhawan  366 459 598 777
488 Amahar  751 942 1227 1595
489 Pipari No 2  281 352 459 597
490 Barnwa  845 1060 1380 1795
491 Onauli  308 386 503 654
492 Kushra  521 653 851 1107
493 Thuter  2007 2517 3278 4262
494 Tiwar  43 54 70 91
495 Adaura  197 247 322 418
496 Orhatha  2103 2638 3435 4466
497 Raipura  1516 1901 2476 3220
498 Rajpur  4424 5549 7227 9396
499 Shenduri  955 1198 1560 2028
500 Barak  1479 1855 2416 3141
501 Shonwat  101 127 165 215
502 Shonauti  238 299 389 505
503 Divar  1060 1329 1731 2251
504 Khajaraul  1174 1472 1918 2493
505 Bhairawa  253 317 413 537
506 Majhali  25 31 41 53
507 Mushrdhara  538 675 879 1143
508 Atarauli Kalan  116 145 189 246
509 Garwa  179 225 292 380
510 Kewata  444 557 725 943
511 Tendui  804 1008 1313 1708
512 Obaradih  657 824 1073 1395
513 Domahar  454 569 742 964
514 Selahata  1153 1446 1883 2449
515 Kusinisph  1201 1506 1962 2551
516 Mhunyw Pandy  537 674 877 1140
517 Chorat  510 640 833 1083
518 Mahuna Gosani  504 632 823 1070

  150 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Population
Sl.No Villages
2011 2023 2038 2053
519 Kunda  82 103 134 174
520 Panauli  579 726 946 1230
521 Sadari  555 696 907 1179
522 Jinhora  258 324 421 548
523 Naidiha  294 369 480 624
524 Aurahi  555 696 907 1179
525 Sidhi  572 717 934 1215
526 Naunia  22 28 36 47
527 Athauna  450 564 735 956
528 Bhgawas  204 256 333 433
529 Chausara  5 6 8 11
530 Kharera  187 235 305 397
531 Morahi  1200 1505 1960 2549
532 Barauli  816 1023 1333 1733
533 Khirahata  1122 1407 1833 2383
534 Garama  1266 1588 2068 2689
535 Gurwal  1636 2052 2672 3475
536 Bandha  468 587 764 994
537 Belwania  1249 1567 2040 2653
538 Karaundia  74 93 121 157
539 Rampur  396 497 647 841
540 Panti  317 398 518 673
541 Dhanawal  700 878 1143 1487
542 Barsot  421 528 688 894
543 Lohari  1469 1842 2400 3120
544 Ahraura  950 1192 1552 2018
545 Sotil  1415 1775 2311 3005
546 Jaimohra  707 887 1155 1502
547 Pateri  258 324 421 548
548 Bakuli  401 503 655 852
549 Durkhuli  742 931 1212 1576
550 Guretha  1068 1340 1745 2268
551 Rajin  216 271 353 459
552 Odar  960 1204 1568 2039
553 Thiwan  1480 1856 2418 3143
554 Dhuria  103 129 168 219
555 Kusmaha  1330 1668 2173 2825
556 Dewerikatha  1129 1416 1844 2398
557 Peroh  5441 6824 8888 11556
558 Dhorkary  1202 1508 1963 2553

  151 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Population
Sl.No Villages
2011 2023 2038 2053
559 Dharsara  555 696 907 1179
560 Marasara  837 1050 1367 1778
Dumaria Mithailal  59 74 96 125
561
562 Silwar  876 1099 1431 1860
Dumaribharaulia  13 16 21 28
563
564 Bharauli  1666 2090 2721 3538
565 Dhadhi  452 567 738 960
566 Piparwar  606 760 990 1287
567 Bisrekhi  1845 2314 3014 3918
568 Jaimohara  75 94 123 159
569 Sirsai  1119 1403 1828 2377
570 Raikara  9 11 15 19
571 Majhagawan  319 400 521 677
572 Naugai  727 912 1188 1544
573 Uchdih  317 398 518 673
574 Lakshimanpur  721 904 1178 1531
575 Chain  534 670 872 1134
576 Naugawan  1097 1376 1792 2330
577 Bhawana  726 911 1186 1542
578 Dewerikhurd  445 558 727 945
579 Halwai  233 292 381 495
580 Bagpokhar  1025 1286 1674 2177
581 Bhanswar  4486 5626 7328 9527
582 Sahdeapaidar  2751 3450 4494 5843
583 Magaradaha  3215 4032 5252 6828
584 Visahar  2001 2510 3269 4250
585 Raunp  2512 3151 4103 5335
586 Churk  1530 1919 2499 3249
587 Shahijan Khurd  1430 1794 2336 3037
588 Musahee  1898 2381 3100 4031
589 Kura  472 592 771 1002
590 Teyara Nayak  506 635 827 1075
591 Peetha  290 364 474 616
592 Akachor  1184 1485 1934 2515
593 Beejauli  908 1139 1483 1928
594 Meuri Kalan  411 515 671 873
595 Arauly  1557 1953 2543 3307
596 Shajaur  571 716 933 1213
Lakhanwar Kalna  372 467 608 790
597
598 Mangurahee  234 293 382 497

  152 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Population
Sl.No Villages
2011 2023 2038 2053
599 Kusamha  49 61 80 104
600 Bijary Duban  218 273 356 463
601 Harhuna  487 611 796 1034
602 Atarauli Khurd  42 53 69 89
603 Bijary Patkhan  307 385 501 652
604 Bahuarah  621 779 1014 1319
605 Lakhanwar Khurd  383 480 626 813
606 Kharhari  515 646 841 1094
607 Pali  526 660 859 1117
608 Dhobahi  370 464 604 786
609 Bharganwa  131 164 214 278
610 Bhandra Kalan  24 30 39 51
611 Chhapaka  1254 1573 2048 2663
612 Shemara  46 58 75 98
613 Shahijan Kalna  2818 3534 4603 5985
614 Shindhora  201 252 328 427
615 Bichapai  1102 1382 1800 2340
616 Ormaura  3006 3770 4910 6384
617 Lori  2241 2811 3661 4759
618 Pushuli  2764 3467 4515 5870
619 Amarati  645 809 1054 1370
620 Gorari  707 887 1155 1502
621 Barauli  1652 2072 2699 3509
622 Meuri Khurd  170 213 278 361
623 Jamgane  515 646 841 1094
624 Ghurma  998 1252 1630 2120
625 Kaithi  1193 1496 1949 2534
626 Baraila  152 191 248 323
627 Petrahi  233 292 381 495
628 Kamarhi  2987 3746 4879 6344
629 Baghnaree  799 1002 1305 1697
630 Belaha  354 444 578 752
631 Patharaha  238 299 389 505
632 Gangti  659 827 1076 1400
633 Paika  609 764 995 1293
634 Kewata  1242 1558 2029 2638
635 Rajdhan  1083 1358 1769 2300
636 Bachawar  176 221 287 374
637 Mhowoh Khurd  473 593 773 1005
638 Kamharia  189 237 309 401

  153 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Population
Sl.No Villages
2011 2023 2038 2053
639 Belcupp  1576 1977 2574 3347
640 Mhowon Kalna  1325 1662 2164 2814
641 Chihurali  1805 2264 2948 3833
642 Baluee  414 519 676 879
643 Maitapur  2048 2569 3345 4350
644 Kargara  3723 4670 6081 7907
645 Bhbhaech  2125 2665 3471 4513
646 Karki  114 143 186 242
647 Guradah  3133 3930 5118 6654
648 Redia  1044 1309 1705 2217
649 Bandhwa  440 552 719 934
650 Bhgawa  6 8 10 13
651 Kurhul  3535 4434 5774 7508
652 Adalganj  1969 2470 3216 4182
653 Salkhan  10552 13235 17237 22410
654 Awayee  984 1234 1607 2090
655 Markundi  7303 9160 11929 15510
656 Rudawali  1136 1425 1856 2413
657 Patwdh  5911 7414 9656 12554
658 Belach  2291 2873 3742 4866
659 Pakari  433 543 707 920
660 Kandhaura  1161 1456 1896 2466
661 Kanach  2814 3529 4597 5976
662 Aluar  850 1066 1388 1805
663 Bhadohi.  70 88 114 149
Total 570515 715560 931930 1211660

  154 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
16. POPULATION

Sl. No. Year Population


1 As Per Census 2011 570515

2 Base Yaer 2023 715560

3 Middle Yaer 2038 931930

4 Design Yaer 2053 1211660

Clear Water Demand


Sl. No. Year Population
in MLD

1 As Per Census 2011 570515 36.92


2 Base Yaer 2023 715560 46.30
3 Middle Yaer 2038 931930 60.31
4 Design Yaer 2053 1211660 78.41

HYDRAULIC MODEL
Building a Model
Details required for building a model are as mentioned below, the same details have collected.
 GIS base map
 Pipeline: material, diameters, age, condition friction coefficient, Elevation details
 Valve details
 Consumer data
 Flow and pressure information
 Elevations
 Demand locations and patterns of large consumers

Activities Involved in Network Modeling

 Design criteria based on guidelines of CPHEEO manual.


 Collection of the data & drawing of existing for the DMA’s from concerned department. If data is not
available in concerned Department, then it is required to collect by physical survey. Drawing the water
supply network features from source to individual tap in the software itself or importing data from
CAD files, GIS files and data sheets including pipe line, water tanks, reservoir, valves etc. On the
backdrop of Geo-reference digitized map of the Project area including deletion and correction of data
any. Giving required attribute features of water networks collected or generated.
 Population forecasting, demand projection and demand allocation in various stages as specified by
client.
 Building the model and validate it with at least three base scenarios and as many as child scenarios for
the existing as well as proposed water supply network.

  155 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
 The three base scenarios shall include present stage, intermediate stage and ultimate stage.
 Running the base as well as child scenarios in steady state and extended period simulation mode to
check the adequacy of system for continuous water supply.
 The child scenarios for various stages shall include existing water supply network, proposed water
supply network, peak demand supply, rehabilitation plan, calibration for existing networks, DMA
zone, Time of day (TOD) benefit etc.
 Allocating the demands to the nearest nodes using consumer data for present stage and allocating the
demand by creating Thiessen polygon and using load builder with any appropriate method for design
stages.
 Checking the demand and supply of the zone including determining the capacity of reservoir using
mass curve and rezoning of operational zones.
 Checking the status of reservoir with respect to inflow and outflow of water tanks
 Setting the Flow Control Valves (FCV) for required inflow to the tank, plotting the various profiles
with respect to ground level and Hydraulic Grade Level (HGL).
 Provide valve details based on ground reality
 Demarcation of various district meter areas (DMAS) showing suitable location of district bulk meter
and size of bulk mete.
 Preparing the rehabilitation plan by necessary replacement of pipe and valve etc. using the hydraulic
model, running the model.
 Preparation of report, drawing and printing the same in presentation form. Detailed immediate
recommendation to rectify the existing water supply network and suggestion to convert the intermittent
water supply to continuous water supply stage wise also included in report.

Software Used

In this project, we have used Water GEMS software of Bentley.

DRAWING OF ACTIVE TOPOLOGY

The shape files of the roads, buildings, river etc. are exported to Water Gems and are created as
background layers. The various components of the pipe network such as reservoir, pipe, junctions,
valves and tanks etc. are drawn on the background layer.

ALLOCATION OF DEMAND TO NODES

Boundaries of all the villages of the Project area are added to the basic GIS map of the Project area
also, considered whether the Project area is developing out of the village boundary. Hence the probable
area out of village has also demarcated. A GIS layer of population has created as per above mentioned
subject..

DESIGN DISTRICT METHOD AREA

Water Supply projects may be designed normally to meet the requirements over a thirty-year period
after their completion. The time lag between design and completion of the project should also be taken
into account which should not exceed two years to three years depending on the size of the project.
The thirty year period may however be modified in regard to certain components of the project
depending on their useful life or the facility for carrying out extensions when required and rate of
interest so that expenditure far ahead of utility is avoided. Necessary land for future

  156 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
expansion/duplication of components should be acquired in the beginning itself. Where expensive
tunnels and large aqueducts are involved entailing large capital outlay for duplication, system may be
designed for ultimate project requirements. Where failure such as collapse of steel pipes under
vacuum put the pipe line out of commission for a long time or the pipe location presents special
hazards such as floods, ice, and mining etc. duplicate lines may be necessary.
As per CPHEEO Manual stipulate design period, for some components, it may be modified depending
on its useful life, facility for carrying out extensions when required and interest rate so that
expenditure far ahead of utility is avoided. Land for future extension should be acquired in beginning
itself. Project components may be designed to meet the requirements of the following design period.
 
 
 
 
Table 1.7.3‐1: Design Periods as per CPHEEO Guidelines and Current Practice 

Design
Sl. No Data Source period in
years
Pumping
1 i) Pump house (civil works) 30
ii) Electric motors and pumps 15
2 Water treatment units 15
3 Water Intake Structure 15
Pipe connection to several treatment units and other small
3 30
appurtenances
4 Raw water and clear water convening mains 30
Clear water reservoirs at the head works, balancing tanks and
5 30
service reservoirs (over head or ground level)
6 Distribution system 30
 
Note:
i. The capacities of various components calculated on above basis shall be subjected to water reservation
for drinking purpose.
ii. Design period for long transmission pipelines (15 years/30 years) shall be decided for individual schemes
keeping in view the availability of ROW (right of way), sizing of pipe line for 15 years and 30 years,
availability of funds etc. Possibility of 1 line /2 parallel lines shall also be evaluated on techno-economic
basis.

  157 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PROPOSED ZONING FOR SUPPLYING WATER BY GRAVITY THROUGH OHSR:-

ZONE WISE AND HABITAION WISE POPULATION


Proposed 
OHR Capacity As per 
OHR 
Population Census 2011  LPCD  KLD for  Mass Balancing  
Gram Capacity 
Sl.No.  Block  Village  Habitations  ZONE  Intermidiate  ( In KLD) 
Panchayat  ( In KLD) 
Year 2038 
55 / 0.85  @ 55 LPCD  As per 
2011  SC / ST  2023  SC / ST  2038  SC / ST  2053  SC / ST 
= 64.71   ( Asked by SWSM)  SWSM 
Kandhaura  Kandhaura  1161  500  1456 627 1896 817 2466 1062
Pakari  Pakari  433  226  543 283 707 369 920 480
1  Chopan  Kanach  Kanach 
Kanach  1436  1102  1801 1382 2346 1800 3050 2340
Kanach 
Korail  1378  932  1728 1169 2251 1522 2927 1979
         3  4  Total  4408  2760  5529  3462  7200  4508  9362  5862  64.71  466  167.50  175 
Belach  683  659  857 827 1116 1076 1451 1400
Akelwa  550  411  690 515 898 671 1168 873
Belchha  Belach  Tekma  282  279  354 350 461 456 599 593
2  Robertsganj  Agarihwa  Rudawal  590  534  740 670 964 872 1253 1134
Chateni Tola  186  150  233 188 304 245 395 319
Rudawali  886  900  1111 1129 1447 1470 1882 1911
Rudawali  Rudawali 
Gadhakushtola  250  115  314 144 408 188 531 244
         2  7  Total  3427  3048  4298  3823  5598  4979  7278  6473  64.71  362  130.07  150 
Patwdh  1148  353  1440 443 1875 577 2438 750
Harijanbasti  956  414  1199 519 1562 676 2030 879
Barihawa  966  633  1212 794 1578 1034 2052 1344
3  Chopan  Patwdh  Patwdh  Baskatya  Patwdh  996  794  1249 996 1627 1297 2115 1686
Dupatia  678  195  850 245 1108 319 1440 414
Gurihawa  553  401  694 503 903 655 1174 852
Bhortirawa  614  372  770 467 1003 608 1304 790
         1  7  Total  5911  3162  7414  3966  9656  5165  12554  6715  64.71  625  224.60  250 
Markundi  2128  348  2669 436 3476 568 4519 739
Baderhwar  467  550  586 690 763 898 992 1168
Balui  790  688  991 863 1290 1124 1678 1461
Chakria  870  258  1091 324 1421 421 1848 548
4  Robertsganj  Markundi  Markundi  Owati  Markundi  776  251  973 315 1268 410 1648 533
Baskhadia  449  417  563 523 733 681 954 886
Chouradih Tola  126  161  158 202 206 263 268 342
Bahera Tola  1468  495  1841 621 2398 809 3118 1051
Chhinar Pochha  229  265  287 332 374 433 486 563
         1  9  Total  7303  3433  9160  4306  11929  5608  15510  7291  64.71  772  277.47  300 
Chihurali  Karki  Karki  114  90  143 113 186 147 242 191
Robertsganj 
5  Bhabhaich  Bhbhaech  Bhbhaech  Bhbhaech  2125  767  2665 962 3471 1253 4513 1629
Chopan  Gurdha  Aluar  Aluar  850  356  1066 447 1388 582 1805 756

  158 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
ZONE WISE AND HABITAION WISE POPULATION
Proposed 
OHR Capacity As per 
OHR 
Population Census 2011  LPCD  KLD for  Mass Balancing  
Gram Capacity 
Sl.No.  Block  Village  Habitations  ZONE  Intermidiate  ( In KLD) 
Panchayat  ( In KLD) 
Year 2038 
55 / 0.85  @ 55 LPCD  As per 
2011  SC / ST  2023  SC / ST  2038  SC / ST  2053  SC / ST 
= 64.71   ( Asked by SWSM)  SWSM 
Robertsganj  Maitapur  Maitapur  Maitapur  2048  144  2569 181 3345 235 4350 306
Guradah  741  338  929 424 1210 552 1574 718
Dhourahawa  631  144  791 181 1031 235 1340 306
Karamdand  579  337  726 423 946 550 1230 716
Chopan  Gurdha  Guradah 
Putpuria  303  119  380 149 495 194 644 253
Chhuhia Tola  260  130  326 163 425 212 552 276
Budi Khar  620  391  778 490 1013 639 1317 830
Kargara  850  442  1066 554 1388 722 1805 939
Upraundh  922  190  1156 238 1506 310 1958 404
Chopan  Kargara  Kargara 
Paschimi Tola  947  160  1188 201 1547 261 2011 340
Kewtan  1004  6  1259 8 1640 10 2132 13
         6  14  Total  11994  3614  15043  4533  19592  5903  25473  7675  64.71  1268  455.66  450 
Kewata  Baluee  Baluee  414  300  519 376 676 490 879 637
Mhowon Kalna  Mhowon Kalna  Mhowon Kalna  1325  470  1662 589 2164 768 2814 998
Belcupp  1025  262  1286 329 1674 428 2177 556
Belcupp  Belcupp  Birbal
551  127  691 159 900 207 1170 270
Madhuban 
Belcupp  Bachawar  Bachawar  176  40  221 50 287 65 374 85
Paika  Gangti  Gangti  659  311  827 390 1076 508 1400 661
Rajdhan  Rajdhan  Rajdhan  1083  482  1358 605 1769 787 2300 1024
6  Robertsganj  Mhowon Kalna  Mhowoh Khurd  Mhowoh Khurd  Belcupp  473  98  593 123 773 160 1005 208
Kewata  Kewata  Kewata  1242  633  1558 794 2029 1034 2638 1344
Paika  Patharaha  Patharaha  238  0  299 0 389 0 505 0
Paika  Paika  Paika  609  259  764 325 995 423 1293 550
Baghnaree  Baghnaree  Baghnaree  799  271  1002 340 1305 443 1697 576
Baghnaree  Belaha  Belaha  354  220  444 276 578 359 752 467
Chihurali  1067  670  1338 840 1743 1094 2266 1423
Chihurali  Chihurali 
Mahuaria  738  385  926 483 1206 629 1567 818
Kewta  Kamharia  Kamharia  189  142  237 178 309 232 401 302
         14  16  Total  10942  4670  13724  5857  17874  7628  23239  9918  64.71  1157  415.81  450 
Chopan  Ghatita  Bhgawa  Bhgawa  6  0  8 0 10 0 13 0
Robertsganj  Kurhul  Kurhul  Kurhul  3535  989  4434 1240 5774 1616 7508 2100
7  Redia 
Robertsganj  Maitapur  Bandhwa  Bandhwa  440  144  552 181 719 235 934 306
Robertsganj  Redia  Redia  Redia  1044  470  1309 589 1705 768 2217 998
         4  4  Total  5025  1603  6303  2011  8208  2618  10672  3404  64.71  531  190.87  200 
Salkhan  2386  1398  2993 1753 3898 2284 5067 2969
8  Robertsganj  Salkan  Salkhan  Dewaria Tola  Baghnaree  933  621  1170 779 1524 1014 1982 1319
Lal Ganj  1068  748  1340 938 1745 1222 2268 1589

  159 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
ZONE WISE AND HABITAION WISE POPULATION
Proposed 
OHR Capacity As per 
OHR 
Population Census 2011  LPCD  KLD for  Mass Balancing  
Gram Capacity 
Sl.No.  Block  Village  Habitations  ZONE  Intermidiate  ( In KLD) 
Panchayat  ( In KLD) 
Year 2038 
55 / 0.85  @ 55 LPCD  As per 
2011  SC / ST  2023  SC / ST  2038  SC / ST  2053  SC / ST 
= 64.71   ( Asked by SWSM)  SWSM 
Autrawa  2732  1702  3427 2135 4463 2780 5802 3615
Punma  1841  609  2309 764 3007 995 3910 1293
Bhatwa  492  397  617 498 804 648 1045 843
Kharwar Tola  686  436  860 547 1121 712 1457 926
Sahdiya Tola  289  151  362 189 472 247 614 321
Jhariya Tola  124  48  156 60 203 78 263 102
Markundi  Awayee  Awayee  984  454  1234 569 1607 742 2090 964
Chopan  Adalganj  Adalganj  Adalganj  1969  1214  2470 1523 3216 1983 4182 2578
         3  11  Total  13504  7778  16937  9755  22059  12705  28680  16519  64.71  1427  512.84  500 
Ghuwas  1845  1300  2314 1631 3014 2124 3918 2761
Ghuwas  Ghuwas 
Sapiniya Tola  84  49  105 61 137 80 178 104
Mukkha  Mukkha  Mukkha  614  344  770 431 1003 562 1304 731
Amilia  Amilia  332  239  416 300 542 390 705 508
Ghuwas 
Tendua  Tendua  1284  425  1610 533 2097 694 2727 903
AMILAUDHA  Amilaudha  Amilaudha  653  370  819 464 1067 604 1387 786
9  Ghorawal  ZONE‐1 
TENDUA  Lahas  Lahas  798  517  1001 648 1304 845 1695 1098
SIRSAIN  Sirsain  Sirsai  1278  915  1603 1148 2088 1495 2714 1943
Karia  1420  986  1781 1237 2320 1611 3016 2094
KARIA  Karia 
Parsiya  518  501  650 628 846 818 1100 1064
GHUWAS  Barbaspur  Barbaspur  468  114  587 143 764 186 994 242
TENDUA  Karry  Karry  30  30  38 38 49 49 64 64
   10  12  Total  9324  5790  11694  7262  15231  9458  19802  12297  64.71  986  354.32  350 
Basahi  155  61  194 77 253 100 329 130
Sirsain  Basahi  Majhiyan Bashti  175  86  219 108 286 140 372 183
Markahawa  207  56  260 70 338 91 440 119
MADHAKA  Karsoata  Karsoata  707  530  887 665 1155 866 1502 1126
MADHAKA  Fulwary  Fulwary  715  89  897 112 1168 145 1519 189
MADHAKA  Madhaka  Madhaka  744  552  933 692 1215 902 1580 1172
10  Ghorawal  ZONE‐1‐1 
REHI  Samerwar  Samerwar  336  165  421 207 549 270 714 350
Mukkha  Mahokhar  Mahokhar  534  67  670 84 872 109 1134 142
REHI  Pathartal  Pathartal  486  246  610 309 794 402 1032 522
REHI  Rahi  Rahi  925  361  1160 453 1511 590 1965 767
Purana 1  1233  613  1546 769 2014 1001 2619 1302
PURNA  Purana 
Purana 2  819  550  1027 690 1338 898 1739 1168
   9  12  Total  7036  3376  8825  4234  11493  5515  14943  7170  64.71  744  267.38  300 
PARSONA  Ghoria  Ghoria  484  451  607 566 791 737 1028 958
11  Ghorawal  ZONE‐1A 
KANHARI  Semera Khurd  Semera Khurd  24  24  30 30 39 39 51 51

  160 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
ZONE WISE AND HABITAION WISE POPULATION
Proposed 
OHR Capacity As per 
OHR 
Population Census 2011  LPCD  KLD for  Mass Balancing  
Gram Capacity 
Sl.No.  Block  Village  Habitations  ZONE  Intermidiate  ( In KLD) 
Panchayat  ( In KLD) 
Year 2038 
55 / 0.85  @ 55 LPCD  As per 
2011  SC / ST  2023  SC / ST  2038  SC / ST  2053  SC / ST 
= 64.71   ( Asked by SWSM)  SWSM 
Kanhari 1  1055  821  1323 1030 1723 1341 2241 1744
Kanhari 
Kanhari 2  1040  973  1304 1220 1699 1589 2209 2066
Tenthuhar  1204  855  1510 1072 1967 1397 2557 1816
TENDUHAR  Tenthuhar 
Kol Basti  379  174  475 218 619 284 805 370
Parsauna  2747  2117  3445 2655 4487 3458 5834 4496
Ghorawal  PARSAUNA  Parsauna  Parsauna2  350  277  439 347 572 452 743 588
Parsauna3  325  260  408 326 531 425 690 552
TENDHUHAR  Majurahi  Majurahi  370  352  464 441 604 575 786 748
TENDUHAR  Lali  Lali  859  692  1077 868 1403 1130 1824 1470
   7  11  Total  8837  6996  11084  8775  14435  11428  18768  14858  64.71  934  335.69  350 
Semera Kala  Semera Kala  323  284  405 356 528 464 686 603
KANHARI  Babhari  Babhari  915  847  1148 1062 1495 1384 1943 1799
MURTIA  Ubha  Ubha  766  654  961 820 1251 1068 1627 1389
AMILIPOKHER  Marni  Marni  492  388  617 487 804 634 1045 824
12  Ghorawal  Murtiya 1  ZONE‐1A‐1  1361  665  1707 834 2223 1086 2890 1412
MOORTIYA  Murtiya 
Murtiya 2  637  272  799 341 1041 444 1353 578
AMILIPOKHER  Dholo  Dholo  921  708  1155 888 1504 1157 1956 1504
AMILIPOKHER  Amli Pokhar  Amli Pokhar  863  519  1082 651 1410 848 1833 1102
MURTIYA  Sapahi  Sapahi  536  406  672 509 876 663 1138 862
   8  9  Total  6814  4743  8546  5949  11131  7748  14472  10073  64.71  720  258.75  250 
MAHAAW  Bantara  Bantara  87  0  109 0 142 0 185 0
DEVGARH  Deogarha  Deogarha  864  737  1084 924 1411 1204 1835 1565
Hinauti  1134  774  1422 971 1852 1264 2408 1644
Majhali  136  84  171 105 222 137 289 178
HINAUTI  Hinauti 
Chaukhara  433  328  543 411 707 536 920 697
Varya  601  327  754 410 982 534 1276 694
Parwania 1  1294  1108  1623 1390 2114 1810 2748 2353
PADWANIA  Parwania 
Parwania 2  841  625  1055 784 1374 1021 1786 1327
13  Ghorawal  ZONE‐2 
Deogarha  Rumma  Rumma  429  338  538 424 701 552 911 718
GURWAL  Chigori  Chigori  928  920  1164 1154 1516 1503 1971 1954
Manhwa 1  1041  839  1306 1052 1700 1370 2211 1782
MAHAOW  Manhwa 
Manhwa 2  324  117  406 147 529 191 688 248
MAHAAW  Khajuari  Khajuari  119  88  149 110 194 144 253 187
KHAGIYA  Chandwa  Chandwa  85  60  107 75 139 98 181 127
Koladiha  Dhura Kund  Dhura Kund  678  114  850 143 1108 186 1440 242
MIJHUN  Dulahatha  Dulahatha  317  208  398 261 518 340 673 442
   11  16  Total  9311  6667  11678  8362  15209  10890  19775  14159  64.71  984  353.63  350 

  161 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
ZONE WISE AND HABITAION WISE POPULATION
Proposed 
OHR Capacity As per 
OHR 
Population Census 2011  LPCD  KLD for  Mass Balancing  
Gram Capacity 
Sl.No.  Block  Village  Habitations  ZONE  Intermidiate  ( In KLD) 
Panchayat  ( In KLD) 
Year 2038 
55 / 0.85  @ 55 LPCD  As per 
2011  SC / ST  2023  SC / ST  2038  SC / ST  2053  SC / ST 
= 64.71   ( Asked by SWSM)  SWSM 
Bardiya 1  1320  605  1656 759 2156 988 2803 1285
BARDIYA  Bardiya 
Bardiya 2  882  481  1106 603 1441 786 1873 1022
SATDWARI  Harankhuri  Harankhuri  595  72  746 90 972 118 1264 153
BARDIYA  Bhainshi  Bhainshi  177  144  222 181 289 235 376 306
Bar  1235  949  1549 1190 2017 1550 2623 2015
BARR  Bar  Bar Ii  382  275  479 345 624 449 811 584
Bar Iii  568  389  712 488 928 635 1206 826

14  Ghorawal  SHIV DWAR  Seegra  Seegra  ZONE‐2‐1  54  39  68 49 88 64 115 83


BAIJNATH  Baijanath  Baijanath  552  397  692 498 902 648 1172 843
BAIJNATH  Gawnkunda  Gawnkunda  268  206  336 258 438 336 569 438
SATDWARI  Satdwari  Satdwari  610  268  765 336 996 438 1296 569
BAIJNATH  Amadhi  Amadhi  360  307  452 385 588 501 765 652
Siwadar  1721  1342  2159 1683 2811 2192 3655 2850
SHIVDWAR  Siwadar 
Siwadar Ii  486  70  610 88 794 114 1032 149
Manjhiganw a  Manjhiganwa
Musha  517  287  648 360 845 469 1098 610
Mishra  Mishra 
   11  15  Total  9727  5831  12200  7313  15889  9525  20658  12384  64.71  1028  369.41  400 
MIJHUN  Meejhun  Meejhun  637  272  799 341 1041 444 1353 578
MIJHUN  Sonhati  Sonhati  382  189  479 237 624 309 811 401
KOHARTHA  Bauradih  Bauradih  173  173  217 217 283 283 367 367
Lilwahi  Lilwahi  Lilwahi  1140  520  1430 652 1862 849 2421 1104
Koharatha 1  1366  934  1713 1171 2231 1526 2901 1984
KOHARTHA  Koharatha 
Koharatha 2  141  132  177 166 230 216 299 280
KOLDEHA  Koladiha  Koladiha  591  265  741 332 965 433 1255 563
BHARKANA  Bharkana  Bharkana  1257  750  1577 941 2053 1225 2670 1593
BHARKANA  Bhagahi  Bhagahi  197  136  247 171 322 222 418 289
KOHARTHA  Baidawar  Baidawar  25  0  31 0 41 0 53 0
15  Ghorawal  ZONE‐2A 
Dorihar  Jamua  Jamua  40  20  50 25 65 33 85 42
Musha  Sonabarsa  Sonabarsa  2  0  3 0 3 0 4 0
KHAGIA  Khagia  Khagia  1067  497  1338 623 1743 812 2266 1056
Musha  Musha  Musha  550  229  690 287 898 374 1168 486
Beerkala  Mandha  Mandha  442  219  554 275 722 358 939 465
Musha  Snihawal  Snihawal  179  111  225 139 292 181 380 236
Dorihar  Janar  Janar  378  135  474 169 617 221 803 287
Beerkala  Beerkala  Beerkala  852  66  1069 83 1392 108 1809 140
Dorihar  Dorihar  Dorihar  1166  829  1462 1040 1905 1354 2476 1761
KHARDEUR  Khardeur  Khardeur  1261  625  1582 784 2060 1021 2678 1327
   19  20  Total  11846  6102  14858  7653  19350  9968  25159  12959  64.71  1252  449.97  450 

  162 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
ZONE WISE AND HABITAION WISE POPULATION
Proposed 
OHR Capacity As per 
OHR 
Population Census 2011  LPCD  KLD for  Mass Balancing  
Gram Capacity 
Sl.No.  Block  Village  Habitations  ZONE  Intermidiate  ( In KLD) 
Panchayat  ( In KLD) 
Year 2038 
55 / 0.85  @ 55 LPCD  As per 
2011  SC / ST  2023  SC / ST  2038  SC / ST  2053  SC / ST 
= 64.71   ( Asked by SWSM)  SWSM 
KEWETA  Keweta  Kewata  837  483  1050 606 1367 789 1778 1026
KEWETA  Khakh  Khakh  431  297  541 373 704 485 915 631
KHRUANV  Mahvarioa  Mahvarioa  497  200  623 251 812 327 1056 425
Khutaha  2099  1263  2633 1584 3429 2063 4458 2682
KHUTAHA  Khutaha 
Khutaha Ii  950  536  1192 672 1552 876 2018 1138
Deewa  Thiwan  Thiwan  1480  610  1856 765 2418 996 3143 1296
Dumaria Dumaria
Bharauli  59  0  74 0 96 0 125 0
16  Ghorawal  Mithailal  Mithailal  ZONE‐3‐1 
Bharauli  Silwar  Silwar  876  365  1099 458 1431 596 1860 775
Bharauli  1155  333  1449 418 1887 544 2453 707
Bharauli  Bharauli  Mishragawa  339  196  425 246 554 320 720 416
Nai Bashti  172  57  216 71 281 93 365 121
Diwa  Piparwar  Piparwar  606  397  760 498 990 648 1287 843
KEVTA  Sirsai  Sirsai  1119  447  1403 561 1828 730 2377 949
BISREKHI  Majhagawan  Majhagawan  319  119  400 149 521 194 677 253
   11  14  Total  10939  5303  13720  6651  17869  8662  23232  11263  64.71  1156  415.47  400 
Junia  Parsauna Khurd  Parsauna Khurd  99  99  124 124 162 162 210 210
SATOHA  Satohan  Satohan  1631  795  2046 997 2664 1299 3464 1688
17  Ghorawal  ZONE‐3‐2 
SATOHA  Nakawai  Nakawai  335  155  420 194 547 253 711 329
VISHUNDHAR I  Visundhary  Visundhary  3295  1683  4133 2111 5382 2749 6998 3574
   4  4  Total  5360  2732  6723  3427  8756  4463  11384  5802  64.71  567 
Kanhi  1028  289  1289 362 1679 472 2183 614
KANETI  Kanhi 
BAGHI  345  178  433 223 564 291 733 378
KANETI  Dharmauli  Dharmauli  881  325  1105 408 1439 531 1871 690
Kewali  820  365  1028 458 1339 596 1742 775
MUGEHARI  Kewali  Nai Chamar
112  23  140 29 183 38 238 49
Basti 
KHRUAOV  Khadaha  Khadaha  280  241  351 302 457 394 595 512
Munghri  716  401  898 503 1170 655 1521 852 Zone-3-2
MUGEHAR  Munghri 
18  Ghorawal  Colbasti  ZONE‐3‐3  75  68  94 85 123 111 159 144 & 3-3
MUGEHARI  Samara  Samara  364  209  457 262 595 341 773 444 1778  638.94  650 
MUGEHARI  Hinauti  Hinauti  31  0  39 0 51 0 66 0
Pidaria  1280  399  1605 500 2091 652 2718 847
PIDARIYA  Pidaria 
Bechanpura  29  0  36 0 47 0 62 0
PIDARIYA  Parhi  Parhi  794  237  996 297 1297 387 1686 503
Newari  Newari  Newari  2500  1406  3136 1763 4084 2297 5310 2986
BAGPOKHAR  Amilia  Amilia  809  524  1015 657 1321 856 1718 1113
KHRUAOV  Kharuaun  Kharuaun  1116  407  1400 510 1823 665 2370 864

  163 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
ZONE WISE AND HABITAION WISE POPULATION
Proposed 
OHR Capacity As per 
OHR 
Population Census 2011  LPCD  KLD for  Mass Balancing  
Gram Capacity 
Sl.No.  Block  Village  Habitations  ZONE  Intermidiate  ( In KLD) 
Panchayat  ( In KLD) 
Year 2038 
55 / 0.85  @ 55 LPCD  As per 
2011  SC / ST  2023  SC / ST  2038  SC / ST  2053  SC / ST 
= 64.71   ( Asked by SWSM)  SWSM 
Surhurwa  202  25  253 31 330 41 429 53
Nauka Mati  72  11  90 14 118 18 153 23
   12  18  Total  11454  5108  14366  6407  18710  8344  24326  10848  64.71  1211 
Kathapura  Sahpurwa Kalan  Sahpurwa Kalan  285  7  357 9 466 11 605 15
Kathapura  Sahpurwa Khurd  Sahpurwa Khurd  192  45  241 56 314 74 408 96
BAGPOKHAR  Bnardewa  Bnardewa  1003  671  1258 842 1638 1096 2130 1425
Kathapura  Kathapura  Kathapura  401  17  503 21 655 28 852 36
SILHATA  Silahta  Silahta  1087  615  1363 771 1776 1005 2309 1306
Jogani 1  999  160  1253 201 1632 261 2122 340

19  Ghorawal  JOGINI  Jogani  Jogani 2  ZONE‐3A‐1  616  258  773 324 1006 421 1308 548
Jogani 3  838  383  1051 480 1369 626 1780 813
Kathapurwa  Bhulahi  Bhulahi  144  7  181 9 235 11 306 15
Sahdeapaidar  2515  744  3154 933 4108 1215 5341 1580
Sahdeapaidar
87  17  109 21 142 28 185 36
SAHDEIYA  Sahdeapaidar  2(katri Tola) 
Maurya Basti  66  18  83 23 108 29 140 38
Dihpura  83  19  104 24 136 31 176 40
   8  13  Total  8316  2961  10430  3714  13584  4837  17662  6289  64.71  879 
PIDARIYA  Tilauli Khurd  Tilauli Khurd  190  8  238 10 310 13 404 17
Tilauli Kalana 1  1687  938  2116 1176 2756 1532 3583 1992 Zone-3A-
Tilauli Kalana 2  734  272  921 341 1199 444 1559 578 1 & 3A-2
TIKAULIKALA  Tilauli Kalana Tilauli Kalana 3  549  114  689 143 897 186 1166 242 1576  566.40  600 
Nai Basti  301  39  378 49 492 64 639 83
20  Ghorawal  Chandrma Katri  ZONE‐3A‐2  550  198  690 248 898 323 1168 421
Khuthnia  Khuthnia  Khuthania  1421  419  1782 526 2321 684 3018 890
Kathapura  Kamhria  Kamhria  137  9  172 11 224 15 291 19
Bagpokhar 1  636  468  798 587 1039 764 1351 994
Bagpokhar  Bagpokhar  Bagpokhar 2  210  141  263 177 343 230 446 299
Bakhrahiya  179  0  225 0 292 0 380 0
   5  11  Total  6594  2606  8270  3269  10771  4257  14004  5535  64.71  697 
KARIVAIRAN V  Karrivarai  Karibarai  1098  460  1377 577 1794 751 2332 977
KAREVIRAV  Kamhria  Kamhria  332  198  416 248 542 323 705 421
DHOVA  Dhoa  Dhoa  975  449  1223 563 1593 733 2071 954
Aruna  Aruna  Aruna  1173  533  1471 669 1916 871 2491 1132
21  Ghorawal  ZONE‐3A‐3 
DHOVA  Vimauri  Vimauri  761  219  954 275 1243 358 1616 465
KHUTTANIYA Velahi  Velahi  576  248  722 311 941 405 1223 527
Aruna  Semari Misra  Semari Misra  685  231  859 290 1119 377 1455 491
PHULWARI  Khudia  Khudia  525  151  658 189 858 247 1115 321

  164 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
ZONE WISE AND HABITAION WISE POPULATION
Proposed 
OHR Capacity As per 
OHR 
Population Census 2011  LPCD  KLD for  Mass Balancing  
Gram Capacity 
Sl.No.  Block  Village  Habitations  ZONE  Intermidiate  ( In KLD) 
Panchayat  ( In KLD) 
Year 2038 
55 / 0.85  @ 55 LPCD  As per 
2011  SC / ST  2023  SC / ST  2038  SC / ST  2053  SC / ST 
= 64.71   ( Asked by SWSM)  SWSM 
Khuthnia  Ataraila  Ataraila  148  46  186 58 242 75 314 98
Purkhas 1  1532  738  1921 926 2503 1206 3254 1567
Purkhas 2  136  39  171 49 222 64 289 83
PURKHAS  Purkhas  Purkhas 3  96  8  120 10 157 13 204 17
Dhawahiya Tola  100  14  125 18 163 23 212 30
Nawtaliya Tola  460  249  577 312 751 407 977 529
PHULVARI  Phulawari  Phulwari  1113  539  1396 676 1818 880 2364 1145
PHULVARI  Bahorika  Bahorika  494  151  620 189 807 247 1049 321
   12  16  Total  10204  4273  12798  5359  16668  6980  21671  9075  64.71  1079  387.78  400 
Bisun Pur  95  38  119 48 155 62 202 81
MASIAADINATH  Bisun Pur 
Biyar Basti  14  7  18 9 23 11 30 15
SIDDI  Teti  Teti  248  0  311 0 405 0 527 0
Gotauli  138  28  173 35 225 46 293 59
MASIAADINATH  Gotauli 
Kushawaha Basti  81  11  102 14 132 18 172 23
Masiadinath  394  105  494 132 644 172 837 223
MASIAADINATH  Masiadinath 
Pokhra Pua  107  31  134 39 175 51 227 66
Sawat  692  127  868 159 1130 207 1470 270
SERVAT  Sawat 
Kolbasti  27  2  34 3 44 3 57 4
JAMGAI  Jamaghne  Jamaghne  353  88  443 110 577 144 750 187
Bakauli  Padri Kalan  Padri Kalan  256  54  321 68 418 88 544 115
Maid  197  116  247 145 322 189 418 246
JAMGAI  Maid 
Baburaha  54  38  68 48 88 62 115 81
Masiha Pathan  381  315  478 395 622 515 809 669
22  Ghorawal  MASIAADINATH  Masiha Pathan  ZONE‐3B‐1 
Panditpur  55  45  69 56 90 74 117 96
Belkuri Belkuri
MASIAADINATH  257  183  322 230 420 299 546 389
Murpharkat  Mupharkat
UCHKA  Naudiha  Naudiha  341  75  428 94 557 123 724 159
Mureladih 1  1280  333  1605 418 2091 544 2718 707
MURELADEEH  Mureladih  Mureladih 2  310  132  389 166 506 216 658 280
Farhada Tola  149  24  187 30 243 39 316 51
Rudauli  254  187  319 235 415 305 539 397
SERVAT  Rudauli 
Yadav Basti  72  30  90 38 118 49 153 64
Aurahi  Welkhuri  Welkhuri  462  94  579 118 755 154 981 200
Lohdhara  177  49  222 61 289 80 376 104
MURELADEEH  Lohdhara 
Chamar Basti  35  27  44 34 57 44 74 57
Bakauli  Chakauli  Chakauli  261  176  327 221 426 287 554 374
Noni  644  396  808 497 1052 647 1368 841
Bakauli  Noni 
Biyar Basti  36  42  45 53 59 69 76 89

  165 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
ZONE WISE AND HABITAION WISE POPULATION
Proposed 
OHR Capacity As per 
OHR 
Population Census 2011  LPCD  KLD for  Mass Balancing  
Gram Capacity 
Sl.No.  Block  Village  Habitations  ZONE  Intermidiate  ( In KLD) 
Panchayat  ( In KLD) 
Year 2038 
55 / 0.85  @ 55 LPCD  As per 
2011  SC / ST  2023  SC / ST  2038  SC / ST  2053  SC / ST 
= 64.71   ( Asked by SWSM)  SWSM 
Adaura  136  84  171 105 222 137 289 178
SIDHI  Adaura 
Yadav Basti  61  12  77 15 100 20 130 25
Jamagani  Chausara  Chausara  5  0  6 0 8 0 11 0
   19  31  Total  7572  2849  9497  3573  12369  4654  16081  6051  64.71  800  287.47  300 
PHULVARI  Geduri  Geduri  116  0  145 0 189 0 246 0
JORWARIA  Salaia  Salaia  11  0  14 0 18 0 23 0
JORWARIA  Etwa  Etwa  56  52  70 65 91 85 119 110
Sirvit 1  1073  591  1346 741 1753 965 2279 1255
SIRVIT  Sirvit  Sirvit 2  1038  389  1302 488 1696 635 2205 826
Kumhar Basti  179  79  225 99 292 129 380 168
Saranga 1  2134  438  2677 549 3486 715 4532 930
SARANGA  Saranga 
Saranga 2  248  159  311 199 405 260 527 338
Tedhwa 1  48  0  60 0 78 0 102 0
SIRSIAJETHI  Tedhwa 
Tedhwa 2  40  0  50 0 65 0 85 0
Sirsiajethi 1  754  413  946 518 1232 675 1601 877
23  Ghorawal  SIRSIYAJETHI  Sirsiajethi  ZONE‐4A 
Sirsiajethi 2  546  75  685 94 892 123 1160 159
SILHATA  Kolariya  Kolariya  646  443  810 556 1055 724 1372 941
Dharura  Dharura  Dharura  1426  423  1789 531 2329 691 3029 898
SIRSIYA JETHI  Sitabahar  Sitabahar  557  210  699 263 910 343 1183 446
KARKOLI  Karkoll  Karkoli  1455  419  1825 526 2377 684 3090 890
Tekuria  1554  853  1949 1070 2538 1393 3300 1812

TEKURIA  Tekuria  Manthahiya Tola  90  17  113 21 147 28 191 36


Bhawarahawa
107  34  134 43 175 56 227 72
Tola 
KARKOLI  Mahuriya  Mahuriya  529  44  663 55 864 72 1123 93
KARMA  Madainia  Madainia  693  87  869 109 1132 142 1472 185
KARMA  Karma  Karma  575  335  721 420 939 547 1221 711
   15  22  Total  13875  5061  17403  6348  22665  8267  29468  10749  64.71  1467  527.25  550 
PARASI PANDEY Bauar  Bauar  406  85  509 107 663 139 862 181
Pawar  861  308  1080 386 1406 503 1829 654
PAWAR  Pawar 
Budhaua Tola  90  90  113 113 147 147 191 191
DEORI KHURD Deori Kalan  Deori Kalan  463  144  581 181 756 235 983 306
DEHRI KALA  Kushai  Kushai  460  71  577 89 751 116 977 151
24  Robertsganj  ZONE‐5‐1 
Deori Khurd  Dehra  Dehra  152  128  191 161 248 209 323 272
Deori Khurd  Deori Khurd  Deori Khurd  429  154  538 193 701 252 911 327
Deori Khurd  Rajapurawa  Rajapurawa  117  45  147 56 191 74 248 96
Deori Khurd  Tiarashiv Datt  Tiarashiv Datt  199  112  250 140 325 183 423 238
Deori Khurd  Chaktiara  Chaktiara  8  0  10 0 13 0 17 0

  166 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
ZONE WISE AND HABITAION WISE POPULATION
Proposed 
OHR Capacity As per 
OHR 
Population Census 2011  LPCD  KLD for  Mass Balancing  
Gram Capacity 
Sl.No.  Block  Village  Habitations  ZONE  Intermidiate  ( In KLD) 
Panchayat  ( In KLD) 
Year 2038 
55 / 0.85  @ 55 LPCD  As per 
2011  SC / ST  2023  SC / ST  2038  SC / ST  2053  SC / ST 
= 64.71   ( Asked by SWSM)  SWSM 
Deori Khurd  Karhi  Karhi  238  127  299 159 389 207 505 270
Deori Khurd  Bhagwantpur  Bhagwantpur  248  57  311 71 405 93 527 121
Dahari  606  170  760 213 990 278 1287 361
DEHARI KALA  Dahari 
Harijan Basti  48  37  60 46 78 60 102 79
Katawaria  950  273  1192 342 1552 446 2018 580
KATVARIYA  Katawaria 
Tal Tola  63  63  79 79 103 103 134 134
Petrahi  Petrahi  Petrahi  632  329  793 413 1032 537 1342 699
MAHURESAR  Deora  Deora  405  258  508 324 662 421 860 548
KALVARIYA  Kanhara  Kanhara  290  143  364 179 474 234 616 304
   16  19  Total  6665  2594  8359  3253  10887  4237  14155  5509  64.71  705  253.40  250 
PARASI PANDEY Khairahi  Khairahi  422  39  529 49 689 64 896 83
BUDHAR KALA  Mamuna  Mamuna  975  326  1223 409 1593 533 2071 692
PAWAR  Kalwari  Kalwari  241  46  302 58 394 75 512 98

BUDHAR KHURD  Burhr Khurd  Burhr Khurd  804  307  1008 385 1313 501 1708 652

Burar Kalan  709  248  889 311 1158 405 1506 527


BUDHAR KALA  Burar Kalan 
mamuna  236  110  296 138 386 180 501 234
KATAWARIA  Nauganwa Kalan  Nauganwa Kalan  334  40  419 50 546 65 709 85
Deori Khurd  Kewati  Kewati  596  176  748 221 974 287 1266 374
Deori Khurd  Theru  Theru  392  0  492 0 640 0 833 0
25  Robertsganj  Zone‐5‐2 
Deori Khurd  Babura  Babura  387  0  485 0 632 0 822 0
ORGAI‐P  Pursotampur  Pursotampur  236  0  296 0 386 0 501 0
Nauganwa Nauganwa
ORGAI‐P  596  0  748 0 974 0 1266 0
Khurd  Khurd 
ORGAI  Organai  Organai  1247  339  1564 425 2037 554 2648 720
Barkara  518  201  650 252 846 328 1100 427
JAIT  Barkara 
Bhaglpur  320  206  401 258 523 336 680 438
MANPUR  Manpur  Manpur  2195  167  2753 209 3586 273 4662 355
Ganguar  Tipara  Tipara  386  349  484 438 631 570 820 741
Kaithi  Kaithi  Kaithi  1193  238  1496 299 1949 389 2534 505
   16  18  Total  11787  2792  14784  3502  19254  4561  25033  5930  64.71  1246 
PIPARI  Dharnipur  Dharnipur  592  36  743  45  967  59  1257  76 
KARARI  Karari  Karari  986  442  1237  554  1611  722  2094  939 
PALIYA KALA  Mokarshim  Mokarshim  602  186  755  233  983  304  1279  395  Zone-8D
27  Robertsganj  PALIA KALA  Palikalna  Palikalna  ZONE‐8D  781  33  980  41  1276  54  1659  70  & 5-2
PIPARI  Darari  Darari  187  0  235  0  305  0  397  0  2511  902.43  900 
PIPARI  Pipari  Pipari  815  11  1022  14  1331  18  1731  23 
PALIA KALNA  Belwa  Belwa  88  0  110  0  144  0  187  0 

  167 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
ZONE WISE AND HABITAION WISE POPULATION
Proposed 
OHR Capacity As per 
OHR 
Population Census 2011  LPCD  KLD for  Mass Balancing  
Gram Capacity 
Sl.No.  Block  Village  Habitations  ZONE  Intermidiate  ( In KLD) 
Panchayat  ( In KLD) 
Year 2038 
55 / 0.85  @ 55 LPCD  As per 
2011  SC / ST  2023  SC / ST  2038  SC / ST  2053  SC / ST 
= 64.71   ( Asked by SWSM)  SWSM 
BHARHIYA  Garawa  Garawa  321  0  403  0  524  0  682  0 
BHARHIYA  Bhruiya  Bhruiya  383  7  480  9  626  11  813  15 
BHARHIYA  Goithari  Goithari  354  190  444  238  578  310  752  404 
Beechhi  Beechhi  Beechhi  1981  430  2485  539  3236  702  4207  913 
Pakari  Tirnahi  Tirnahi  285  44  357  55  466  72  605  93 
Pakari  Bagadiha  Bagadiha  74  23  93  29  121  38  157  49 
Pakari  Pakari  Pakari  1253  626  1572  785  2047  1023  2661  1329 
Ghuwaskhurd  Ghuaskalan  Ghuaskalan  832  86  1044  108  1359  140  1767  183 
Ganguar  Ganguar  Ganguar  763  370  957  464  1246  604  1620  786 
Ghuashkurd  Ghuashkurd  Ghuashkurd  1674  510  2100  640  2734  833  3555  1083 
   17  17  Total  11971  2994  15014  3755  19554  4891  25424  6359  64.71  1265 
SAHIJAN KALAN  Shahijan Khurd  Shahijan Khurd  1430  525  1794 658 2336 858 3037 1115
Teyara Nayak  Peetha  Peetha  290  149  364 187 474 243 616 316
Pushuli  2015  675  2527 847 3291 1103 4279 1434
BADHAULI  Pushuli 
Kodvriya Tola  749  346  939 434 1223 565 1591 735
BANDAULI  Amarati  Amarati  645  117  809 147 1054 191 1370 248
Barauli  1142  158  1432 198 1865 258 2425 336
BADHOLI  Barauli 
28  Robertsganj  Nai Basti  ZONE‐5‐3  510  399  640 500 833 652 1083 847
Ormaura  Ormaura  Ormaura  3006  645  3770 809 4910 1054 6384 1370
Bichapai  Bichapai  Bichapai  1102  235  1382 295 1800 384 2340 499
Chhapaka  Chhapaka  Chhapaka  1254  578  1573 725 2048 944 2663 1228
Lori  1563  1090  1960 1367 2553 1781 3320 2315
LODHI  Lori 
Bhilai Colony  678  166  850 208 1108 271 1440 353
SAHIJAN KALAN  Shahijan Kalna  Shahijan Kalna  2818  864  3534 1084 4603 1411 5985 1835
   10  13  Total  17202  5947  21575  7459  28099  9714  36534  12630  64.71  1818  653.34  650 
KHAIRA  Khajurikhurd  Khajurikhurd  302  47  379 59 493 77 641 100
KHAIRA  Khajurikala  Khajurikala  364  222  457 278 595 363 773 471
BARSOT  Bhurkura  Bhurkura  486  160  610 201 794 261 1032 340
BARSOT  Bhuli  Thauli  227  34  285 43 371 56 482 72
BARSOT  Kunan  Kunan  185  137  232 172 302 224 393 291
ENAM  Balua  Balua  180  1  226 1 294 2 382 2
29  Ghorawal  ZONE‐5B‐1 
DOHARI  Dohari  Dohari  427  127  536 159 697 207 907 270
KHAIRA  Welanow  Welanow  601  460  754 577 982 751 1276 977
KHAIRA  Hinauti  Hinauti  21  0  26 0 34 0 45 0
DOHARI  Koharaul  Koharaul  348  137  436 172 568 224 739 291
KHAIRA  Khaira  Khaira  609  296  764 371 995 484 1293 629
KHAIRA  Kapura  Kapura  137  27  172 34 224 44 291 57

  168 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
ZONE WISE AND HABITAION WISE POPULATION
Proposed 
OHR Capacity As per 
OHR 
Population Census 2011  LPCD  KLD for  Mass Balancing  
Gram Capacity 
Sl.No.  Block  Village  Habitations  ZONE  Intermidiate  ( In KLD) 
Panchayat  ( In KLD) 
Year 2038 
55 / 0.85  @ 55 LPCD  As per 
2011  SC / ST  2023  SC / ST  2038  SC / ST  2053  SC / ST 
= 64.71   ( Asked by SWSM)  SWSM 
KHAIRA  Khairi  Khairi  79  27  99 34 129 44 168 57
KINGARI  Chotakapur  Chotakapur  431  81  541 102 704 132 915 172
BARSOT  Barsota  Barsota  810  312  1016 391 1323 510 1720 663
Uchaka  951  61  1193 77 1553 100 2020 130
UCHKA  Uchaka 
Bahari Tola  187  8  235 10 305 13 397 17
Bharuha  632  159  793 199 1032 260 1342 338
UCHKA  Bhruha 
Madai Pura  101  56  127 70 165 91 215 119
JAMGAI‐B  Pipri No. 1  Pipari No. 1  458  239  574 300 748 390 973 508
JAMGAI  Jamagane  Jamagane  608  169  763 212 993 276 1291 359
KINGARI  Sauli  Sauli  118  41  148 51 193 67 251 87
BARAWA  Asatali  Asatali  163  88  204 110 266 144 346 187
KINGARI  Majhiganwa  Majhiganwa  487  235  611 295 796 384 1034 499
KINGARI  Kingari  Kingari  1232  38  1545 48 2012 62 2617 81
KINGARI  Chhuta  Chhuta  328  66  411 83 536 108 697 140
Petrahi  Petrahi  Petrahi  418  140  524 176 683 229 888 297
UMARIKALA  Mishra  Mishra  66  6  83 8 108 10 140 13
Arangi  Arangi  Arangi  817  380  1025 477 1335 621 1735 807
KHAIRA  Khodaichak  Khodaichak  14  0  18 0 23 0 30 0
Kolakari  Barnwa  Barnwa  845  114  1060 143 1380 186 1795 242
Kushra  Kushra  Kushra  521  87  653 109 851 142 1107 185
   30  32  Total  13153  3955  16497  4961  21485  6460  27934  8400  64.71  1390  499.56  500 
Sirsiathkurai  2612  918  3276 1151 4267 1500 5547 1950
Khairpur  2256  759  2830 952 3685 1240 4791 1612
Papikala(rampat
SIRSIYA 1564  418  1962 524 2555 683 3322 888
30  Ghorawal  Sirsiathkurai  hara)  ZONE‐6 
THAKURAI 
Belahawa  424  153  532 192 693 250 900 325
Bagaia  226  70  283 88 369 114 480 149
Kharra Tola  207  26  260 33 338 42 440 55
   1  6  Total  7289  2344  9142  2940  11907  3829  15480  4978  64.71  770  276.69  300 
MUBARAKPU R  Mubarakpur  Mubarakpur  2277  1262  2856 1583 3719 2061 4836 2680
BAGHORI  Baghor  Baghor  1255  575  1574 721 2050 939 2665 1221
31  Robertsganj  ZONE‐6A 
GAURAHI  Gorahi  Gorahi  2448  450  3070 564 3999 735 5199 956
BAGHORI  Kutulupur  Kutulupur  946  49  1187 61 1545 80 2009 104
   4  4  Total  6926  2336  8687  2930  11314  3816  14709  4961  64.71  732 
LOHRA  Lohra  Lohra  6843  3057  8583 3834 11178 4994 14533 6492 2185  785.22  800 
32  Robertsganj  ZONE‐6B 
SUKRIT  Sukrit  Sukrit  6899  1908  8653 2393 11269 3117 14652 4052
Zone-6A & 6B
   2  2  Total  13742  4965  17236  6227  22447  8110  29185  10545  64.71  1453 
33  Ghorawal  SARAULI  Atarauli Raja  Atarauli Raja  ZONE‐6A‐1  349  126  438 158 570 206 741 268

  169 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
ZONE WISE AND HABITAION WISE POPULATION
Proposed 
OHR Capacity As per 
OHR 
Population Census 2011  LPCD  KLD for  Mass Balancing  
Gram Capacity 
Sl.No.  Block  Village  Habitations  ZONE  Intermidiate  ( In KLD) 
Panchayat  ( In KLD) 
Year 2038 
55 / 0.85  @ 55 LPCD  As per 
2011  SC / ST  2023  SC / ST  2038  SC / ST  2053  SC / ST 
= 64.71   ( Asked by SWSM)  SWSM 
Sarauli  1655  207  2076 260 2703 338 3515 440
SARAULI  Sarauli 
Sarauli2  315  50  395 63 515 82 669 106
GARAEGARH  Garaegarh  Garaegarh  1148  281  1440 352 1875 459 2438 597
MAJHUI  Majhui  Majhui  1342  436  1683 547 2192 712 2850 926
BHAWANIPUR  Bhawanipur  Bhawanipur  2379  687  2984 862 3886 1122 5053 1459
PARAHI  Parahi  Parahi  2195  582  2753 730 3586 951 4662 1236
   6  7  Total  9383  2369  11768  2971  15327  3870  19928  5031  64.71  992  356.47  350 
Hinauta  1087  450  1363 564 1776 735 2309 956
HINAUTA  Hinauta 
Imliyadih  739  142  927 178 1207 232 1569 302
AMDIH  Amdih  Amdih  1534  525  1924 658 2506 858 3258 1115
34  Robertsganj  Khamriha  Khamriha  Khamriha  Zone‐6A‐3  1102  414  1382 519 1800 676 2340 879
MADHUPUR  Madhupur  Madhupur  9710  1781  12179 2234 15861 2909 20622 3782
CHAKARA  Amaulia  Amaulia  607  132  761 166 992 216 1289 280
CHAKARA  Chakara 50%  Chakara 50%  335  57  420 71 546 93 710 121
   6  7  Total  15114  3501  18956  4391  24687  5719  32098  7435  64.71  1598  574.25  600 
Bharawah  Bharawah  Bharawah  1089  306  1366 384 1779 500 2313 650
Bharawah  Khairwa  Khairwa  234  0  293 0 382 0 497 0
BAHERA  Dilahi  Dilahi  997  162  1250 203 1629 265 2117 344
Bharawah  Tandi  Tandi  230  14  288 18 376 23 488 30
Ghorawal  Jaderua 1  2000  881  2508 1105 3267 1439 4248 1871
JADERUA  Jaderua 
Jaderua 2  630  275  790 345 1029 449 1338 584
Bahera 1  1760  176  2207 221 2875 287 3738 374
BAHERA  Bahera 
35  Bahera 2  ZONE‐6C  610  124  765 156 996 203 1296 263
DILAHI  Jurawat  Jurawat  465  126  583 158 760 206 988 268
BARUHA  Bharuha  Bharuha  557  254  699 319 910 415 1183 539
BABURAHI  Bhadohi  Bhadohi  70  0  88 0 114 0 149 0
KHAIRAHI  Shirsia  Shirsia  14  14  18 18 23 23 30 30
Robertsganj 
Kharahri  2266  427  2842 536 3701 697 4813 907
KHAIRAHI  Khairahi 
Khairahi Bazar  203  0  255 0 332 0 431 0
Aelahi  Aelahi  Aelahi  1324  423  1661 531 2163 691 2812 898
   12  15  Total  12449  3182  15614  3991  20335  5198  26439  6758  64.71  1316  472.91  500 
BASVA NISF  Dularu  Dularu  27  2  34 3 44 3 57 4
Atarawa  347  46  435 58 567 75 737 98
BASWANISKA  Atarawa 
Futharawa  352  14  441 18 575 23 748 30
36  Robertsganj  ZONE‐6C‐1 
Baburahi  679  98  852 123 1109 160 1442 208
BABURAHI  Baburahi 
Nai Basti  275  61  345 77 449 100 584 130
KEKRAHI  Kharahri  Kharahri  52  0  65 0 85 0 110 0

  170 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
ZONE WISE AND HABITAION WISE POPULATION
Proposed 
OHR Capacity As per 
OHR 
Population Census 2011  LPCD  KLD for  Mass Balancing  
Gram Capacity 
Sl.No.  Block  Village  Habitations  ZONE  Intermidiate  ( In KLD) 
Panchayat  ( In KLD) 
Year 2038 
55 / 0.85  @ 55 LPCD  As per 
2011  SC / ST  2023  SC / ST  2038  SC / ST  2053  SC / ST 
= 64.71   ( Asked by SWSM)  SWSM 
Khairahi Bazar  5  0  6 0 8 0 11 0
KEKRAHI  Shirkhora  Shirkhora  102  3  128 4 167 5 217 6
Silthary  Jokahi  Jokahi  343  54  430 68 560 88 728 115
PAPI  Bhagauti  Bhagauti  691  246  867 309 1129 402 1468 522
Papi  432  48  542 60 706 78 917 102
Miyan Tola  108  0  135 0 176 0 229 0

PAPI  Papi  Kushwaha Basti  108  0  135 0 176 0 229 0


Kushwaha Basti
108  0  135 0 176 0 229 0
Ii 
Harijan Basti  116  87  145 109 189 142 246 185
SIRSIA  Sirsia  Sirsia  928  245  1164 307 1516 400 1971 520
SIRSIA  Kairwa  Kairwa  225  106  282 133 368 173 478 225
Ghorawal 
SIRSIYA  Pipara  Pipara  472  150  592 188 771 245 1002 319
SIRSIA  Garhwa  Garhwa  231  0  290 0 377 0 491 0
KAKRAHI  Murala Dih  Murala Dih  24  1  30 1 39 2 51 2
Basawa Nisph  362  47  454 59 591 77 769 100
Robertsganj 
BASAWA NISKA  Basawa Nisph  Kushwaha Basti  178  0  223 0 291 0 378 0
Harijan Basti  96  120  120 151 157 196 204 255
   14  23  Total  6261  1328  7853  1666  10227  2169  13297  2820  64.71  662  237.88  250 
Gouri Nisph  Gouri Nisph  Gouri Nisph  610  299  765 375 996 488 1296 635

MADAR  Kathpurwa  Kathpurwa  420  30  527 38 686 49 892 64


Robertsganj  Kekarahi  1113  56  1396 70 1818 91 2364 119
KAKARAHI  Kekarahi  Bajar Tola  454  0  569 0 742 0 964 0
Harijan Basti  310  303  389 380 506 495 658 644
Bhataulia 1  934  124  1171 156 1526 203 1984 263
BHATAULIYA  Bhatulia 
Bhataulia 2  702  99  880 124 1147 162 1491 210
Ghorawal  Bakahi  891  253  1118 317 1455 413 1892 537
BAKAHI  Bakahi 
37  Pakrahiya  ZONE‐6C‐2  71  12  89 15 116 20 151 25
BAKAHI  Padar  Padar  515  330  646 414 841 539 1094 701
MGURAHI  Mangurahi  Mangurahi  413  138  518 173 675 225 877 293
VAKDAD  Darah  Darah  328  134  411 168 536 219 697 285
SHEOKARI  Jori  Jori  712  258  893 324 1163 421 1512 548
SHEOKARI  Sheokari  Sheokari  709  46  889 58 1158 75 1506 98
Robertsganj 
Khekhara  410  173  514 217 670 283 871 367
MAGURAHI  Khekhara 
Harijan Bashti  196  66  246 83 320 108 416 140
TINATALI  Tinatali  Tinatali  1207  110  1514 138 1972 180 2563 234
HINAUTA  Tilya  Tilya  870  112  1091 140 1421 183 1848 238

  171 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
ZONE WISE AND HABITAION WISE POPULATION
Proposed 
OHR Capacity As per 
OHR 
Population Census 2011  LPCD  KLD for  Mass Balancing  
Gram Capacity 
Sl.No.  Block  Village  Habitations  ZONE  Intermidiate  ( In KLD) 
Panchayat  ( In KLD) 
Year 2038 
55 / 0.85  @ 55 LPCD  As per 
2011  SC / ST  2023  SC / ST  2038  SC / ST  2053  SC / ST 
= 64.71   ( Asked by SWSM)  SWSM 
Ghorawal  SIRSIYA  Kushhi  Kushahi  247  0  310 0 403 0 525 0
Robertsganj  CHAKARA  Chakara 50%  Chakara 50%  334  57  419 72 547 93 711 121
   15  20  Total  11446  2600  14356  3262  18698  4247  24310  5522  64.71  1210  434.87  450 
MADAAR  Madar  Madar  731  66  917 83 1194 108 1552 140
Baghi  620  107  778 134 1013 175 1317 227
PASAHIKALA  Baghi  Bagahi
166  31  208 39 271 51 353 66
Chouraha 
Gouri Nisph  Parsona  Parsona  277  54  347 68 452 88 588 115
DEHRI  Kamaharia  Kamaharia  129  0  162 0 211 0 274 0
Gouri Nisph  Birhulia  Birhulia  363  181  455 227 593 296 771 384
SHIVKHARI  Mahulia  Mahulia  197  65  247 82 322 106 418 138
Dehari  350  105  439 132 572 172 743 223
DEHRI  Dehari 
Kushwaha Basti  183  0  230 0 299 0 389 0
Kasya Kalan URF  Kasya Kalan  476  126  597 158 778 206 1011 268
Kasya Kalan 
DEHRI  Harijan Basti  120  120  151 151 196 196 255 255
38  Robertsganj  Zone‐6C‐3 
Kushahi  125  19  157 24 204 31 265 40
KEKARAHI  Kushahi 
Harijan Basti  18  14  23 18 29 23 38 30
Bashdewa  368  132  462 166 601 216 782 280
KARKI  Bashdewa  Kushwaha Bast  122  53  153 66 199 87 259 113
Harijan Basti  132  175  166 219 216 286 280 372
Karaki  817  292  1025 366 1335 477 1735 620
KARKI  Karaki  Kuswaha Basti  196  12  246 15 320 20 416 25
Harijan Basti  439  446  551 559 717 729 932 947
PAPI  Kasya Khurd  Kasya Khurd  264  123  331 154 431 201 561 261
Gouri Nisph  Kucha Marwa  Kucha Marwa  472  95  592 119 771 155 1002 202
Karaki  Rajkhar  Rajkhar  44  0  55 0 72 0 93 0
   14  22  Total  6609  2216  8289  2779  10796  3620  14036  4706  64.71  699  251.25  250 
Ghorawal  BARIMAHEWA  Uachka  Uachka  427  308  536 386 697 503 907 654
Barimahewa 1  2275  471  2853 591 3716 769 4832 1000
Ghorawal  WARI MAHEWA  Barimahewa 
Barimahewa 2  203  0  255 0 332 0 431 0
Pagia 1  1037  110  1301 138 1694 180 2202 234
Ghorawal  PAGIA  Pagia 
Pagia 2  1133  209  1421 262 1851 341 2406 444
39  Robertsganj  PATERI  Khairawa Raja  Khairawa Raja  Zone‐7A‐1  128  15  161 19 209 25 272 32
Asana  489  18  613 23 799 29 1039 38
Robertsganj  BHARUHA  Asana 
Kushwaha Basti  22  0  28 0 36 0 47 0
Robertsganj  PATEHARA  Patehara  Patehara  714  38  896 48 1166 62 1516 81
Robertsganj  PATEHARA  Patela  Patela  176  144  221 181 287 235 374 306
Robertsganj  PATERI  Pateri  Pateri  435  154  546 193 711 252 924 327

  172 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
ZONE WISE AND HABITAION WISE POPULATION
Proposed 
OHR Capacity As per 
OHR 
Population Census 2011  LPCD  KLD for  Mass Balancing  
Gram Capacity 
Sl.No.  Block  Village  Habitations  ZONE  Intermidiate  ( In KLD) 
Panchayat  ( In KLD) 
Year 2038 
55 / 0.85  @ 55 LPCD  As per 
2011  SC / ST  2023  SC / ST  2038  SC / ST  2053  SC / ST 
= 64.71   ( Asked by SWSM)  SWSM 
Robertsganj  BHARUHA  Tulsipur  Tulsipur  34  0  43 0 56 0 72 0
Robertsganj  PATEHARA  Jawahi  Jawahi  430  11  539 14 702 18 913 23
Robertsganj  PATERI  Gheuri  Gheuri  342  98  429 123 559 160 726 208
Ghorawal  KARMA  Karanwah  Karanwah  249  24  312 30 407 39 529 51
Robertsganj  PATERI  Khairawa No 2  Khairawa No 2  29  0  36 0 47 0 62 0
Robertsganj  PATERI  Machhalawa  Machhalawa  152  0  191 0 248 0 323 0
   14  17  Total  8275  1600  10379  2007  13517  2614  17574  3398  64.71  875  314.47  350 
RANITARA  Birmaua  Birmaua  149  4  187 5 243 7 316 8
RANITARA  Chakahi  Chakahi  395  124  495 156 645 203 839 263
RANITARA  Mukasim  Mukasim  1561  584  1958 732 2550 954 3315 1240

PANDEYPOKHAR  Pandepokhar  Pandepokhar  1052  384  1319 482 1718 627 2234 816

Ranitara  599  149  751 187 978 243 1272 316

40  Ghorawal  RANITARA  Ranitara  Jurhva Tala  ZONE‐7A‐2  319  198  400 248 521 323 677 421
Deldar Nagar  411  174  515 218 671 284 873 370

PANDEYPOKHAR  Dudhia  Dudhia  629  188  789 236 1027 307 1336 399

PANDEYPOKHAR  Teprasivadati  Teprasivadati  702  237  880 297 1147 387 1491 503

Jorwria  1371  453  1720 568 2240 740 2912 962


JORWARIA  Jorwria 
Jorwria 1  304  131  381 164 497 214 646 278
   8  11  Total  7492  2626  9397  3294  12238  4290  15912  5577  64.71  792  284.63  300 
TAKIA  Dhotwa  Dhotwa  188  39  236 49 307 64 399 83
SUKRIT  Khane Azampur  Khane Azampur  776  255  973 320 1268 417 1648 542

41  Robertsganj  BAGHAORI  Baghauri  Baghauri  ZONE‐7B  177  19  222 24 289 31 376 40
BAT  Bat  Bat  3621  707  4542 887 5915 1155 7690 1502
TAKIAMUDA Takia Takia
2426  995  3043 1248 3963 1625 5152 2113
RGAHA  Mu.Dargah  Mu.Dargah 
   5  5  Total  7188  2015  9015  2527  11742  3291  15266  4279  64.71  760 
BANTARA  Bantara  Bantara  1016  418  1274 524 1660 683 2158 888 1275.00  458.25  450 
42  Robertsganj  NAGNAR ZONE‐6A‐2 
HARAIA 
Nagnar Haraia  Nagnar Haraia  3857  1590  4838 1994 6300 2597 8191 3377 Zone-7B & 6A-2
   2  2  Total  4873  2008  6112  2519  7960  3280  10349  4265  64.71  515 
GORDIHA  Gordiha  Gordiha  434  50  544 63 709 82 922 106
KARAARI  Purainiya  Purainiya  210  26  263 33 343 42 446 55
JIGNA  Jigana  Jigana  717  236  899 296 1171 386 1523 501
43  Robertsganj  ZONE‐8 
JIGNA  Alahi  Alahi  151  32  189 40 247 52 321 68
BARGAWN  Bargawn  Bargawn  659  216  827 271 1076 353 1400 459
BARGAWN  Bishbhrpur  Bishbhrpur  208  0  261 0 340 0 442 0

  173 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
ZONE WISE AND HABITAION WISE POPULATION
Proposed 
OHR Capacity As per 
OHR 
Population Census 2011  LPCD  KLD for  Mass Balancing  
Gram Capacity 
Sl.No.  Block  Village  Habitations  ZONE  Intermidiate  ( In KLD) 
Panchayat  ( In KLD) 
Year 2038 
55 / 0.85  @ 55 LPCD  As per 
2011  SC / ST  2023  SC / ST  2038  SC / ST  2053  SC / ST 
= 64.71   ( Asked by SWSM)  SWSM 
JIGNA  Parsona  Parsona  126  48  158 60 206 78 268 102
BARGAWN  Pateara  Pateara  154  23  193 29 252 38 327 49
JIGNA  Domariya  Domariya  297  78  373 98 485 127 631 166
JIGNA  Rampur  Rampur  579  0  726 0 946 0 1230 0
BARGAON  Baheri  Baheri  291  124  365 156 475 203 618 263
DHOBAHI  Khrehari  Kharahri  360  221  452 277 588 361 765 469
BARWAN  Deogarh  Deogarh  435  264  546 331 711 431 924 561
Kushi  1955  468  2452 587 3193 764 4152 994
Bawaraspur  464  212  582 266 758 346 985 450
KUSI  Kushi 
Belahi  682  115  855 144 1114 188 1448 244
Kusi Belahi  468  115  587 144 764 188 994 244
MAHUARI  Tendee  Tendee  141  64  177 80 230 105 299 136
Kaithi  Kaithi  Kaithi  1138  353  1427 443 1859 577 2417 750
PIPARI  Lakhan Purwa  Lakhan Purwa  441  168  553 211 720 274 937 357
BARGAON  Bahera  Bahera  206  20  258 25 336 33 438 42
   18  21  Total  10116  2833  12688  3553  16524  4628  21484  6017  64.71  1069  384.16  400 
BABHANAULI
Mahokhar  Mahokhar  286  0  359  0  467  0  607  0 
KALA 
PASHI KALA  Chandauli  Chandauli  513  192  643  241  838  314  1090  408 
MADHURAHI  Tendu  Tendu  419  89  526  112  684  145  890  189 
Mahuari  737  262  924  329  1204  428  1565  556 
MAHUARI  Mahuari 
Gour Basti  365  139  458  174  596  227  775  295 
KAMHARDEEH  Kamahar Dih  Kamahar Dih  1690  235  2120  295  2761  384  3589  499 
44  Robertsganj  Bahura  ZONE‐8B  2377  706  2981  885  3883  1153  5048  1499 
Puran Basti  644  466  808  584  1052  761  1368  990 
Aurahwa  1470  305  1844  383  2401  498  3122  648 
BAHURA  Bahura  Bohuara Ganj  1006  94  1262  118  1643  154  2137  200 
Bairwa Gobar  887  187  1113  235  1449  305  1884  397 
Bahuara Bangla  829  163  1040  204  1354  266  1761  346 
Kurihawa  207  59  260  74  338  96  440  125 
   6  13  Total  11430  2897  14336  3634  18671  4732  24275  6153  64.71  1208  434.10  450 
PASHI KALA  Durha  Durha  153  20  192  25  250  33  325  42 
Deora Raja  213  74  267  93  348  121  452  157 
PASHI KALA  Deora Raja 
Harijan Bashti  16  11  20  14  26  18  34  23 
45  Robertsganj  Deori Khurd  Nai Basti  Nai Basti  ZONE‐8C  492  38  617  48  804  62  1045  81 
Hinduhari  927  171  1163  214  1514  279  1969  363 
HINDUARI  Hinduhari 
Harijan Basti  343  299  430  375  560  488  728  635 
JAMUANUA  Jamuanua  Jamuanua  619  227  776  285  1011  371  1315  482 

  174 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
ZONE WISE AND HABITAION WISE POPULATION
Proposed 
OHR Capacity As per 
OHR 
Population Census 2011  LPCD  KLD for  Mass Balancing  
Gram Capacity 
Sl.No.  Block  Village  Habitations  ZONE  Intermidiate  ( In KLD) 
Panchayat  ( In KLD) 
Year 2038 
55 / 0.85  @ 55 LPCD  As per 
2011  SC / ST  2023  SC / ST  2038  SC / ST  2053  SC / ST 
= 64.71   ( Asked by SWSM)  SWSM 
Dhuriya  270  0  339  0  441  0  573  0 
JAMAGANWA  Dhuriya  KUSHWAHA 
135  0  169  0  221  0  287  0 
BASTI 
JAMAGANWA  Jamaganwa  Jamaganwa  442  192  554  241  722  314  939  408 
Ratawal  64  27  80  34  105  44  136  57 
BHARHIYA  Ratawal 
PANIKA TOLA  35  10  44  13  57  16  74  21 
JAMUAW  Mahuaon  Mahuaon  289  0  362  0  472  0  614  0 
NAI  Hinauti  Hinauti  414  151  519  189  676  247  879  321 
NAI  Hona  Hona  482  171  605  214  787  279  1024  363 
BARWAN  Barwan  Barwan  798  236  1001  296  1304  386  1695  501 
PASHI KALA  Majhi Ganwa  Majhiganwa  272  170  341  213  444  278  578  361 
Shemari Shemari
AMOKHAR  517  42  648  53  845  69  1098  89 
Bishunlal  Bishunlal 
BABHNAULI Babhanauli Babhanauli
229  135  287  169  374  221  486  287 
KALA  Khurd  Khurd 
BAMNAULI
Bhogar  Bhogar  349  113  438  142  570  185  741  240 
KALA 
BABHNAULI Babhanauli Babhanauli
589  0  739  0  962  0  1251  0 
KALA  Kalan  Kalan 
AMOKHAR  Shango  Shango  127  0  159  0  207  0  270  0 
Pashi Kalana  594  98  745  123  970  160  1262  208 
PASAHIKALA  Pashi Kalana 
Harijan Basti  146  126  183  158  238  206  310  268 
AMOKHAR  Amokhr  Amokhr  927  435  1163  546  1514  711  1969  924 
Pashi Khurd  467  192  586  241  763  314  992  408 
PASHI KALA  Pashi Khurd 
Panikan Basti  43  37  54  46  70  60  91  79 
BABHNAULI
Urali  Urali  101  0  127  0  165  0  215  0 
KALA 
MAGURAHI  Khewatha  Khewatha  125  14  157  18  204  23  265  30 
AMOKHAR  Mango  Mango  145  5  182  6  237  8  308  11 
   24  30  Total  10323  2994  12947  3755  16863  4891  21924  6359  64.71  1091  392.09  400 
Robertsganj  Shenduri  Marhra  Marhra  669  247  839  310  1093  403  1421  525 
JUROLI COLONY Jurauli Kolani  Jurauli Kolani  1016  933  1274  1170  1660  1524  2158  1982 
SAHUAR  Shathi  Sathahi  498  57  625  71  813  93  1058  121 
Jurauri Kolany  Judauri Pardhan  Jurauli Pradhani  316  80  396  100  516  131  671  170 
Bheravar  174  141  218  177  284  230  370  299 
46  Kolakari  Bherawal  ZONE‐9 
Ghorawal  Badhauta Tola  60  47  75  59  98  77  127  100 
Jurauri Kolany  Shikari  Seekari  833  397  1045  498  1361  648  1769  843 
Jamganwa  692  268  868  336  1130  438  1470  569 
JAMGAON  Jamaganwa 
Jamugawna 1  401  124  503  156  655  203  852  263 
SAHUAR  Kooran  Kooran  4  0  5  0  7  0  8  0 

  175 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
ZONE WISE AND HABITAION WISE POPULATION
Proposed 
OHR Capacity As per 
OHR 
Population Census 2011  LPCD  KLD for  Mass Balancing  
Gram Capacity 
Sl.No.  Block  Village  Habitations  ZONE  Intermidiate  ( In KLD) 
Panchayat  ( In KLD) 
Year 2038 
55 / 0.85  @ 55 LPCD  As per 
2011  SC / ST  2023  SC / ST  2038  SC / ST  2053  SC / ST 
= 64.71   ( Asked by SWSM)  SWSM 
JAMGAON  Gobariya  Gobariya  531  325  666  408  867  531  1128  690 
SAHUAR  Barauli  Barauli  536  39  672  49  876  64  1138  83 
BELATAND  Shahganj  Shahganj  1628  296  2042  371  2659  484  3458  629 
SAHUAR  Sahuar  Sahuar  1159  385  1454  483  1893  629  2461  818 
JAMGAON  Manhawan  Manhawan  366  69  459  87  598  113  777  147 
Raipura  1391  500  1745  627  2272  817  2954  1062 
Raipura  Raipura 
Kotiya  125  57  157  71  204  93  265  121 
Rajpur  2594  594  3253  745  4237  970  5509  1262 
Maeedhiya  332  56  416  70  542  91  705  119 
Rajpur  Rajpur 
Kotya  1328  577  1666  724  2169  943  2820  1225 
Robertsganj 
Mhuariya  170  33  213  41  278  54  361  70 
Shenduri  614  235  770  295  1003  384  1304  499 
Shenduri  Shenduri 
Badha Tola  341  44  428  55  557  72  724  93 
Barak  Barak  Barak  1479  228  1855  286  2416  372  3141  484 
BANAURA 2  Shonwat  Shonwat  101  32  127  40  165  52  215  68 
   18  25  Total  17358  5764  21771  7229  28354  9415  36865  12242  64.71  1835  659.47  650 
PARASI PANDEY Parashidubey  Parashidubey  482  130  605  163  787  212  1024  276 
Robertsganj  UNCH DEEH  Aghwar  Aghwar  367  15  460  19  599  25  779  32 
UNCHDEEH  Unchidih  Unchidih  751  390  942  489  1227  637  1595  828 
Raghunath Pur  2009  1318  2520  1653  3282  2153  4267  2799 
Raghunathpur  Raghunathpur 
Hardihawa Tola  168  19  211  24  274  31  357  40 
Beechhiya  Bharganw  Bharganw  9  2  11  3  15  3  19  4 
KHATAULI  Bhunari  Bhunari  126  68  158  85  206  111  268  144 

Ghorawal  Beechhiya  Raiwari  Raiwari  239  141  300  177  390  230  508  299 
Beechhiya  Bajotara  Bajotara  211  20  265  25  345  33  448  42 
Amahata Amahata
KHATAULI  157  61  197  77  256  100  333  130 
Amahti  Amahati 
47  Beechhiya  Beechhiya  Beechhiya  ZONE‐9‐1  639  240  801  301  1044  392  1357  510 
KHATAULI  Khatauli  Khatauli  800  449  1003  563  1307  733  1699  954 
Bahuar  1914  1023  2401  1283  3126  1671  4065  2173 
Bahuar  Bahuar  Kacharia Tola  594  194  745  243  970  317  1262  412 
Badhain  631  448  791  562  1031  732  1340  951 
Bashuari  161  0  202  0  263  0  342  0 
Shenduri  Bashuari 
Robertsganj  Masna Tola  116  0  145  0  189  0  246  0 
MUTHER  Beohari  Beohari  100  23  125  29  163  38  212  49 
MUTHER  Khchar  Khchar  328  87  411  109  536  142  697  185 
Bashauli  1486  639  1864  801  2427  1044  3156  1357 
Bashauli  Bashauli 
Gandara Tola  189  185  237  232  309  302  401  393 

  176 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
ZONE WISE AND HABITAION WISE POPULATION
Proposed 
OHR Capacity As per 
OHR 
Population Census 2011  LPCD  KLD for  Mass Balancing  
Gram Capacity 
Sl.No.  Block  Village  Habitations  ZONE  Intermidiate  ( In KLD) 
Panchayat  ( In KLD) 
Year 2038 
55 / 0.85  @ 55 LPCD  As per 
2011  SC / ST  2023  SC / ST  2038  SC / ST  2053  SC / ST 
= 64.71   ( Asked by SWSM)  SWSM 
Balhail Tola  129  66  162  83  211  108  274  140 
BANAURA 2  Majhiganwa  Majhiganwa  500  131  627  164  817  214  1062  278 
   17  23  Total  12106  5649  15184  7085  19775  9228  25711  11997  64.71  1280  459.97  450 
Petrahi  Bhandar Khurd  Bhandar Khurd  188  0  236  0  307  0  399  0 
Petrahi  Tilauli  Tilauli  800  547  1003  686  1307  894  1699  1162 
Amauli  Amauli  Amauli  831  364  1042  457  1357  595  1765  773 
Gordiha  Mahuar Khurd  Mahuar Khurd  140  75  176  94  229  123  297  159 
Amauli  Papi  Papi  459  286  576  359  750  467  975  607 
Amauli  Patehra  Patehra  141  63  177  79  230  103  299  134 
48  Robertsganj  Gordiha  Mahuar Kalna  Mahuar Kalna  ZONE‐9‐2  118  9  148  11  193  15  251  19 
Petrahi  Petrahi  Petrahi  233  114  292  143  381  186  495  242 
Petrahi  Shindhora  Shindhora  201  159  252  199  328  260  427  338 
Petrahi  Bhandra Kalan  Bhandra Kalan  24  0  30  0  39  0  51  0 
Petrahi  Shemara  Shemara  46  16  58  20  75  26  98  34 
Gordiha  Gordiha  Gordiha  990  19  1242 24 1617 31 2103 40
Baghuari  Baghari  Baghari  1588  1059  1992  1328  2594  1730  3373  2249 
   13  13  Total  5759  2711  7223  3400  9407  4428  12231  5758  64.71  609  218.90  250 
BABHNAULI  Babanauli  Babanauli  1517  414  1903  519  2478  676  3222  879 
JAIT  Jait  Jait  808  355  1013  445  1320  580  1716  754 
Gordiha  Karauli  Karauli  449  334  563  419  733  546  954  709 
Nipraj  Nipraj  Nipraj  1415  261  1775  327  2311  426  3005  554 
MUTHER  Muther  Muther  592  314  743  394  967  513  1257  667 
Nipraj  Kamojee  Kamojee  802  299  1006  375  1310  488  1703  635 
49  Robertsganj  ZONE‐9‐3 
Parashipandy  Parashipandy  Parashipandy  1055  385  1323  483  1723  629  2241  818 
Kamarhi  Kamarhi  Kamarhi  2987  614  3746  770  4879  1003  6344  1304 
Ghurma  Ghurma  Ghurma  998  160  1252  201  1630  261  2120  340 
Petrahi  Gorari  Gorari  707  136  887  171  1155  222  1502  289 
Ghurma  Baraila  Baraila  152  108  191  135  248  176  323  229 
Ghurma  Jamgane  Jamgane  515  314  646  394  841  513  1094  667 
   12  14  Total  11997  3694  15047  4633  19597  6034  25479  7845  64.71  1268  455.66  450 
Belatand 1  1309  160  1642  201  2138  261  2780  340 
BELATAD  Belatand 
Belatand 2  469  33  588  41  766  54  996  70 
DOHARI  Atarwa  Atarwa  426  158  534  198  696  258  905  336 
50  Ghorawal  BALDIH  Juriya  Juria  Zone‐9A  216  82  271  103  353  134  459  174 
BALDIH  Ganguhar  Ganguhar  135  69  169  87  221  113  287  147 
MARACHI  Renua  Renua  493  82  618  103  805  134  1047  174 
Kolakari  Kolakari  Kolakari  900  725  1129  909  1470  1184  1911  1540 

  177 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
ZONE WISE AND HABITAION WISE POPULATION
Proposed 
OHR Capacity As per 
OHR 
Population Census 2011  LPCD  KLD for  Mass Balancing  
Gram Capacity 
Sl.No.  Block  Village  Habitations  ZONE  Intermidiate  ( In KLD) 
Panchayat  ( In KLD) 
Year 2038 
55 / 0.85  @ 55 LPCD  As per 
2011  SC / ST  2023  SC / ST  2038  SC / ST  2053  SC / ST 
= 64.71   ( Asked by SWSM)  SWSM 
Dugaulia  1157  506  1451  635  1890  827  2457  1075 
Dugaulia  Dugaulia  Hariya  763  383  957  480  1246  626  1620  813 
Tilahar  253  188  317  236  413  307  537  399 
Bansdih  1063  72  1333  90  1736  118  2258  153 
BALDIH  Bansdih 
Bansdih 1  122  24  153  30  199  39  259  51 
MARACHI  Bichhwar  Bijhawr  78  8  98  10  127  13  166  17 
MARACHI  Marachhi  Marachi  540  155  677  194  882  253  1147  329 
MARACHI  Umarikhurd  Umarikhurd  418  36  524  45  683  59  888  76 
KOLKARI  Baraganwa  Baraganwa  640  200  803  251  1045  327  1359  425 
Kushra  Sohdaul  Sohdaul  405  88  508  110  662  144  860  187 
Kushra  Pipari No 2  Pipari No 2  281  102  352  128  459  167  597  217 
Kolakari  Onauli  Onauli  308  233  386  292  503  381  654  495 
Orhatha  Orhatha  Orhatha  2103  646  2638  810  3435  1055  4466  1372 
   16  20  Total  12079  3950  15150  4954  19731  6452  25653  8389  64.71  1277  458.94  450 
DABHA  Chakari  Chakari  85  0  107  0  139  0  181  0 
AMAUD  Usarikalan  Usarikala  606  0  760  0  990  0  1287  0 
AMAUD  Ushrikhurd  Usharikhurd  497  254  623  319  812  415  1056  539 
DABHA  Lasari Kalan  Lasari Kalan  655  138  822  173  1070  225  1391  293 
DABHA  Masoe  Masoe  858  23  1076  29  1402  38  1822  49 
DABHA  Dabha  Dabha  799  167  1002  209  1305  273  1697  355 
Ghorawal 
DABHA  Lasari Khurd  Lasari Khurd  6  0  8  0  10  0  13  0 
Durawal Khurd  Durawal Khurd  Durawal Khurd  640  226  803  283  1045  369  1359  480 
Durawal Khurd  Hhrihar Pur  Hhrihar Pur  400  34  502  43  653  56  850  72 
Durawal Khurd  Kasari  Kasari  39  0  49  0  64  0  83  0 
Enam 1  1019  260  1278  326  1665  425  2164  552 
ENAM  Enam 
51  Enam 2  ZONE‐9A‐1  263  103  330  129  430  168  559  219 
BANAURA II  Bagaura  Bagaura  765  332  959  416  1250  542  1625  705 
BANAURA II  Bagauari  Bagauari  45  28  56  35  74  46  96  59 
Barahda  Barahda  Barahda  525  166  658  208  858  271  1115  353 
Barahda  Bagathri Kalna  Bagathri Kalna  490  449  615  563  800  733  1041  954 
DURAWAL
Bagathari Khurd  Bagathari Khurd  294  212  369  266  480  346  624  450 
KALNA
Robertsganj 
UNCHIDIH  Alahi Durawan Alahi Durawan  116  116  145  145  189  189  246  246 
Durawal Kalna  562  132  705  166  918  216  1194  280 
DURAVAL KALA  Durawal Kalna 
Bela Bandi  156  124  196  156  255  203  331  263 
DURAVAL
Shono  Shono  130  30  163  38  212  49  276  64 
KALNA
Deori Khurd  Jeewar  Jeewar  390  238  489  299  637  389  828  505 

  178 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
ZONE WISE AND HABITAION WISE POPULATION
Proposed 
OHR Capacity As per 
OHR 
Population Census 2011  LPCD  KLD for  Mass Balancing  
Gram Capacity 
Sl.No.  Block  Village  Habitations  ZONE  Intermidiate  ( In KLD) 
Panchayat  ( In KLD) 
Year 2038 
55 / 0.85  @ 55 LPCD  As per 
2011  SC / ST  2023  SC / ST  2038  SC / ST  2053  SC / ST 
= 64.71   ( Asked by SWSM)  SWSM 
Sihirshahi Sihirshahi
ORAULI  2  0  3  0  3  0  4  0 
Parashe Dubey  Parashe Dubey 
MAHURESAR  Mahuresher  Mahuresher  467  237  586  297  763  387  992  503 
MAHURESAR  Oani Chaubey  Oani Chaubey  339  157  425  197  554  256  720  333 
ORAULI  Orauli  Orauli  745  295  934  370  1217  482  1582  627 
Oanimishra  381  55  478  69  622  90  809  117 
MAHURESAR  Oanimishra 
Samstipur  88  22  110  28  144  36  187  47 
MAHURESAR  Jamashokar  Jamashokar  246  195  309  245  402  319  522  414 
Ghorawal  Amahar  Amahar/Amaud  Amahar  751  113  942  142  1227  185  1595  240 
ORAULI  Eanam  Eanam  255  156  320  196  417  255  542  331 
ORAULI  Kurashat  Kurashat  476  48  597  60  778  78  1011  102 
UMARIKALA  Umarikalna  Umarikalna  666  164  835  206  1088  268  1414  348 
Robertsganj 
MAHURESAR  Gajana  Gajana  77  38  97  48  126  62  164  81 
Naraina  373  135  468  169  609  221  792  287 
UMARIKALA  Naraina 
Sikthiya Tola  116  51  145  64  189  83  246  108 
Thuter  1302  78  1633  98  2127  127  2765  166 
Thuter  Thuter  Nauka Tola  311  42  390  53  508  69  661  89 
Ghorawal 
Chandikapur  394  55  494  69  644  90  837  117 
SAHUAR  Tiwar  Tiwar  43  0  54  0  70  0  91  0 
Shlaiya  620  321  778  403  1013  524  1317  682 
UNCHDEEH  Shlaiya 
Mahuaa Tal  111  27  139  34  181  44  236  57 
   Mahuali  Mahuali  10  0  13  0  16  0  21  0 
Robertsganj 
BANAURA 2  Shajua  Shajua  3  3  4  4  5  5  6  6 
Shonauti  143  9  179  11  234  15  304  19 
BANAURA 2  Shonauti 
Naee Basti  95  4  119  5  155  7  202  8 
   38  46  Total  17354  5237  21766  6568  28348  8555  36856  11122  64.71  1834  659.12  650 
JAMGAI  Juri  Juri  246  65  309  82  402  106  522  138 
Bakauli  Parari Kurd  Parari Kurd  271  46  340  58  443  75  576  98 
MUSARDHARA  Mushrdhara  Mushrdhara  538  306  675  384  879  500  1143  650 
Panauli  Atarauli Kalan  Atarauli Kalan  116  26  145  33  189  42  246  55 
Tendui  Kewata  Kewata  444  0  557  0  725  0  943  0 
52  Ghorawal  Tendui  Tendui  Tendui  ZONE‐10  804  41  1008  51  1313  67  1708  87 
Obaradeeh  Obaradih  Obaradih  657  290  824  364  1073  474  1395  616 
MUSARDHARA  Domahar  Domahar  454  188  569  236  742  307  964  399 
Selahata  1092  655  1370  822  1784  1070  2319  1391 
Obaradeeh  Selahata 
Hardihawa Tola  61  20  77  25  100  33  130  42 
Kusinisph  Kusinisph  Kusinisph  1201  668  1506  838  1962  1091  2551  1419 

  179 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
ZONE WISE AND HABITAION WISE POPULATION
Proposed 
OHR Capacity As per 
OHR 
Population Census 2011  LPCD  KLD for  Mass Balancing  
Gram Capacity 
Sl.No.  Block  Village  Habitations  ZONE  Intermidiate  ( In KLD) 
Panchayat  ( In KLD) 
Year 2038 
55 / 0.85  @ 55 LPCD  As per 
2011  SC / ST  2023  SC / ST  2038  SC / ST  2053  SC / ST 
= 64.71   ( Asked by SWSM)  SWSM 
MAHUWAW 
Mhunyw Pandy  Mahuaw Pandey  537  221  674  277  877  361  1140  469 
PANDEY 
MAHUWAW 
Mahuna Gosani  Mahuna Gosani  504  332  632  416  823  542  1070  705 
PANDEY 
Panauli  Kunda  Kunda  82  3  103  4  134  5  174  6 
Sidhi  Sadari  Sadari  555  274  696  344  907  448  1179  582 
Obaradeeh  Jinhora  Jinhora  258  0  324  0  421  0  548  0 
Kusinisph  Naidiha  Naidiha  294  106  369  133  480  173  624  225 
Aurahi  Aurahi  Aurahi  555  319  696  400  907  521  1179  677 
Sidhi  Sidhi  Sidhi  572  335  717  420  934  547  1215  711 
Sidhi  Athauna  Athauna  450  180  564  226  735  294  956  382 
MASIAADINATH  Bhgawas  Bhagawas  204  0  256  0  333  0  433  0 
Jamagani  Kharera  Kharera  187  27  235  34  305  44  397  57 
Morahi 1  936  160  1174  201  1529  261  1988  340 
MORAHI  Morahi  Morahi 2  190  44  238  55  310  72  404  93 
Bahari Tola  74  22  93  28  121  36  157  47 
   22  25  Total  11282  4328  14150  5428  18429  7070  23961  9192  64.71  1193  428.75  450 
Barauli  Barauli  Barauli  816  615  1023  771  1333  1005  1733  1306 
Gurwal  Gurwal  Gurwal  1636  1051  2052  1318  2672  1717  3475  2232 
Barauli  Bandha  Bandha  468  311  587  390  764  508  994  661 
Belwania  Belwania  Belwania  1249  727  1567  912  2040  1188  2653  1544 
Belwania  Karaundia  Karaundia  74  23  93  29  121  38  157  49 
Belwania  Rampur  Rampur  396  91  497  114  647  149  841  193 
Dhanawal  Panti  Panti  317  180  398  226  518  294  673  382 
Dhanawal  Dhanawal  Dhanawal  700  295  878  370  1143  482  1487  627 
53  Ghorawal  ZONE‐10A‐1 
Lohari  1109  364  1391  457  1812  595  2355  773 
LOHANDI  Lohari  Jogiyabeer  235  65  295  82  384  106  499  138 
Kachaha Tola  125  90  157  113  204  147  265  191 
Ahraura  813  542  1020  680  1328  885  1727  1151 
Ahraura  Ahraura 
Kevalipur  137  21  172  26  224  34  291  45 
Bakuli  Durkhuli  Durkhuli  742  388  931  487  1212  634  1576  824 
Guretha  Guretha  Guretha  1068  826  1340  1036  1745  1349  2268  1754 
AHRAURA  Rajin  Rajin  216  142  271  178  353  232  459  302 
   13  16  Total  10101  5731  12669  7188  16500  9362  21453  12172  64.71  1068  383.81  400 
Divar  784  243  983  305  1281  397  1665  516 
Divar  Divar 
Pal Basti  276  195  346  245  451  319  586  414 
54  Ghorawal  ZONE‐10A‐2 
Khajaraul  Khajaraul  Khajaraul  1174  504  1472  632  1918  823  2493  1070 
Divar  Bhairawa  Bhairawa  253  195  317  245  413  319  537  414 

  180 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
ZONE WISE AND HABITAION WISE POPULATION
Proposed 
OHR Capacity As per 
OHR 
Population Census 2011  LPCD  KLD for  Mass Balancing  
Gram Capacity 
Sl.No.  Block  Village  Habitations  ZONE  Intermidiate  ( In KLD) 
Panchayat  ( In KLD) 
Year 2038 
55 / 0.85  @ 55 LPCD  As per 
2011  SC / ST  2023  SC / ST  2038  SC / ST  2053  SC / ST 
= 64.71   ( Asked by SWSM)  SWSM 
MUSARDHARA  Majhali  Majhali  25  21  31  26  41  34  53  45 
Khajaraul  Garwa  Garwa  179  47  225  59  292  77  380  100 
Panauli  Chorat  Chorat  510  227  640  285  833  371  1083  482 
Panauli  Panauli  Panauli  579  237  726  297  946  387  1230  503 
MORAHI  Naunia  Naunia  22  0  28  0  36  0  47  0 
Domakhri  506  339  635  425  827  554  1075  720 
DOMKHARI  Domakhri  Kolpurawa  582  268  730  336  951  438  1236  569 
Daurpura  323  181  405  227  528  296  686  384 
Khirahata  657  454  824  569  1073  742  1395  964 
Khirahata  Khirahata 
Yadav Basti  465  195  583  245  760  319  988  414 
DIVER  Garama  Garama  1266  1033  1588  1296  2068  1687  2689  2194 
Barsot  314  256  394  321  513  418  667  544 
SOTIL  Barsot 
Kushwaha Basti  107  76  134  95  175  124  227  161 
Sotil  947  397  1188  498  1547  648  2011  843 
SOTIL  Sotil 
Sadkepura  468  135  587  169  764  221  994  287 
Bakuli  Jaimohra  Jaimohra  707  231  887  290  1155  377  1502  491 
Bakuli  Pateri  Pateri  258  151  324  189  421  247  548  321 
Bakuli  Bakuli  Bakauli  401  194  503  243  655  317  852  412 
Odar  549  486  689  610  897  794  1166  1032 
KUSUMHA  Odar  Kushwaha Nai
411  66  515  83  671  108  873  140 
Basti 
Bakuli  Dhuria  Dhuria  103  38  129  48  168  62  219  81 
Kusmaha  1178  224  1477  281  1924  366  2502  476 
KUSUMHA  Kusmaha 
Jawarahi Tola  152  37  191  46  248  60  323  79 
   19  27  Total  13196  6430  16551  8065  21556  10503  28026  13656  64.71  1395  501.37  500 
DEVARI KATH  Dewerikatha  Dewerikatha  1129  428  1416  537  1844  699  2398  909 
55  Ghorawal  PERHA  Peroh  Peroh  ZONE‐11  5441  2555  6824  3205  8888  4174  11556  5426 
DEVARIKATH  Dhorkary  Dhorkary  1202  464  1508  582  1963  758  2553  985 
         3  3  Total  7772  3447  9748  4323  12695  5631  16506  7321  64.71  822  295.41  300 
Beheri  Mohani  Mohani  353  268  443  336  577  438  750  569 
Beheri  Beerkhurd  Beerkhurd  336  86  421  108  549  140  714  183 
MAGHIGAWA 
Baraudhi  Baraudhi  603  554  756  695  985  905  1281  1177 
CHAUHAN 
MAGHIGAWA 
56  Ghorawal  Kon  Kon  ZONE‐11A  17  0  21  0  28  0  36  0 
CHAUHAN 
Beheri  Beheri  Beheri  417  205  523  257  681  335  886  435 
MAJHIGAVA  Majhgawan Majhgawan
651  406  817  509  1063  663  1383  862 
CHOHAN  Chauhan  Chauhan 
MARSARA  Marasara  Marasara  837  647  1050  811  1367  1057  1778  1374 

  181 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
ZONE WISE AND HABITAION WISE POPULATION
Proposed 
OHR Capacity As per 
OHR 
Population Census 2011  LPCD  KLD for  Mass Balancing  
Gram Capacity 
Sl.No.  Block  Village  Habitations  ZONE  Intermidiate  ( In KLD) 
Panchayat  ( In KLD) 
Year 2038 
55 / 0.85  @ 55 LPCD  As per 
2011  SC / ST  2023  SC / ST  2038  SC / ST  2053  SC / ST 
= 64.71   ( Asked by SWSM)  SWSM 
BHARAUJI  Dumaribharaulia  Dumaribharaulia  13  0  16  0  21  0  28  0 
Dharsara  Dhadhi  Dhadhi  452  312  567  391  738  510  960  663 
Dharsara  Dharsara  Dharsara  555  293  696  367  907  479  1179  622 
Bisrekhi 1  1058  296  1327  371  1728  484  2247  629 
BISREKHI  Bisrekhi 
Bisrekhi 2  787  671  987  842  1286  1096  1671  1425 
MARSADA  Jaimohara  Jaimohara  75  25  94  31  123  41  159  53 
   12  13  Total  6154  3763  7719  4720  10052  6147  13070  7992  64.71  650  233.57  250 
Junia  Junia  Junia  777  277  975  347  1269  452  1650  588 
Dharsara  Raikara  Raikara  9  0  11  0  15  0  19  0 
MARASARA  Naugai  Naugai  727  376  912  472  1188  614  1544  799 
MARASARA  Uchdih  Uchdih  317  69  398  87  518  113  673  147 
Bhawana  Lakshimanpur  Lakshimanpur  721  367  904  460  1178  599  1531  779 
57  Ghorawal  NAUGAWAN ZONE‐11A‐1 
Chain  Chain  534  282  670  354  872  461  1134  599 
AND LAL 
MAUGAWAN
Naugawan  Naugawan  1097  343  1376  430  1792  560  2330  728 
ANDLAL 
Bhawana  Bhawana  Bhawana  726  450  911  564  1186  735  1542  956 
JUDIA  Dewerikhurd  Dewerikhurd  445  222  558  278  727  363  945  471 
Bhawana  Halwai  Halwai  233  70  292  88  381  114  495  149 
   10  10  Total  5586  2456  7006  3080  9125  4012  11864  5216  64.71  590  212.00  200 
Bhanswar  2032  686  2549  860  3319  1121  4316  1457 
Bhanswar Ii  601  352  754  441  982  575  1276  748 
BHAINSWAR  Bhanswar 
Bhanswar Iii  1022  334  1282  419  1669  546  2171  709 
Bhanswar Iv  831  140  1042  176  1357  229  1765  297 
Magaradaha 1  1988  937  2493  1175  3247  1531  4222  1990 
58  Ghorawal  MAGAR DAHA  Magaradaha  ZONE‐11B 
Magaradaha 2  1227  640  1539  803  2004  1045  2606  1359 
Visahar 1  1294  457  1623  573  2114  747  2748  971 
Visahar 2  554  347  695  435  905  567  1177  737 
VISAHAR  Visahar 
Dihpura  66  55  83  69  108  90  140  117 
Jaljaliya  87  90  109  113  142  147  185  191 
   3  10  Total  9702  4038  12169  5065  15848  6596  20605  8576  64.71  1026  368.72  400 
AMAULI  Amauli  Amauli  713  458  894  574  1165  748  1514  973 
KARARI  Shuhali  Shuhali  28  11  35  14  46  18  59  23 
BITHGAON 
Bithgon Nishoh  Bithgon Nishoh  92  13  115  16  150  21  195  28 
59  Robertsganj  NISHOH  ZONE‐12‐1 
BITHGAON  Bithgawn
Bithgawn Nishph  915  470  1148  589  1495  768  1943  998 
NISHPH  Nishph 
Majhigaon Majhigaon
Shajaur  507  176  636  221  828  287  1077  374 
Mishra  Mishra 

  182 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
ZONE WISE AND HABITAION WISE POPULATION
Proposed 
OHR Capacity As per 
OHR 
Population Census 2011  LPCD  KLD for  Mass Balancing  
Gram Capacity 
Sl.No.  Block  Village  Habitations  ZONE  Intermidiate  ( In KLD) 
Panchayat  ( In KLD) 
Year 2038 
55 / 0.85  @ 55 LPCD  As per 
2011  SC / ST  2023  SC / ST  2038  SC / ST  2053  SC / ST 
= 64.71   ( Asked by SWSM)  SWSM 
Bithgawn 
Shirpalpur  Shirpalpur  749  197  939  247  1223  322  1591  418 
Nishph B 
Lashra  Lashra  Lashra  1085  260  1361  326  1772  425  2304  552 
Majhigaon Majhigaon
Shajaur  382  127  479  159  624  207  811  270 
Chaubey  Chaubey 
BEEJAULI  Pali  Pali  526  252  660  316  859  412  1117  535 
Beejauli  Beejauli  Beejauli  908  155  1139  194  1483  253  1928  329 
Teyara Nayak  Meuri Kalan  Meuri Kalan  411  133  515  167  671  217  873  282 
Teyara Nayak  Teyara Nayak  Teyara Nayak  506  257  635  322  827  420  1075  546 
Dhobahi  Akachor  Akachor  1184  200  1485  251  1934  327  2515  425 
Shajaur  Shajaur  Shajaur  571  217  716  272  933  354  1213  461 
Teyara Nayak  Meuri Khurd  Meuri Khurd  170  33  213  41  278  54  361  70 
   15  15  Total  8747  2959  10971  3711  14288  4833  18577  6284  64.71  925  332.41  350 
DHOBHI  Dhobahi  Dhobahi  370  187  464  235  604  305  786  397 
Silthary  Mangurahee  Mangurahee  234  8  293  10  382  13  497  17 
Harhuna  Kusamha  Kusamha  49  0  61  0  80  0  104  0 
Harhuna  Atarauli Khurd  Atarauli Khurd  42  0  53  0  69  0  89  0 
Lakhanwar Lakhanwar
SIDDHIKALA  383  33  480  41  626  54  813  70 
Khurd  Khurd 
60  Robertsganj  ZONE‐12‐2 
Kharhari  Kharhari  Kharhari  515  41  646  51  841  67  1094  87 
Silthari  Bharganwa  Bharganwa  131  0  164  0  214  0  278  0 
Lakhanwar
Sidhi Kalana  Lakhanwar Kalna  372  30  467  38  608  49  790  64 
Kalna 
Bhaburahi  Bhadohi  Bhadohi  207  0  260  0  338  0  440  0 
Arauly  Arauly  Arauly  1557  747  1953  937  2543  1220  3307  1586 
   10  10  Total  3860  1046  4841  1312  6305  1709  8198  2221  64.71  408  146.63  150 
Harhuna  Bijary Duban  Bijary Duban  218  101  273  127  356  165  463  215 
Harhuna  Harhuna  Harhuna  487  293  611  367  796  479  1034  622 
Harhuna  Bijary Patkhan  Bijary Patkhan  307  31  385  39  501  51  652  66 
Kura  Kura  Kura  472  137  592  172  771  224  1002  291 
Raunp  1860  430  2333  539  3038  702  3950  913 
61  Robertsganj  RAUP  Raunp  ZONE‐12‐3 
Mahulia Tola  652  419  818  526  1065  684  1385  890 
Musahee  1045  405  1311  508  1707  662  2219  860 
Kura  Musahee 
Charkonwa  853  668  1070  838  1393  1091  1812  1419 
Harhuna  Bahuarah  Bahuarah  621  292  779  366  1014  477  1319  620 
Churk  Churk  Churk  1530  350  1919  439  2499  572  3249  743 
   8  10  Total  8045  3126  10090  3921  13141  5106  17086  6639  64.71  850  305.50  300 
Total  663  879     570515  224891  715560  282066  931930  367357  1211660  477624 

  183 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Population Water Demand OHT


Sl.Nos Zones In Kld
Capacity
Say
2011 2038 KL
1 Kanach 4408 466 167.50  175.00
2 Rudawali 3427 362 130.07  150.00
3 Patwdh 5911 625 224.54  250.00
4 Salkhan 13504 1427 512.84  500.00
5 Markundi 7303 772 277.47  300.00
6 Bhbhaech 11994 1268 455.66  450.00
7 Belcupp 10942 1157 415.81  450.00
8 Redia 5025 531 190.87  200.00
9 ZONE-1 9324 986 354.32  350.00
10 ZONE-1A 8837 934 335.69  350.00
11 ZONE-1-1 7036 744 267.38  300.00
12 ZONE-1A-1 6814 720 258.75  250.00
13 ZONE-2 9311 984 353.63  350.00
14 ZONE-2-1 9727 1028 369.41  400.00
15 ZONE-2A 11846 1252 449.97  450.00
16 ZONE-3-1 10939 1156 415.47  400.00
17 ZONE-3-2 5360 567 203.61 
650.00
18 ZONE-3-3 11454 1211 435.33 
19 ZONE-3A-1 8316 879 315.91 
600.00
20 ZONE-3A-2 6594 697 250.49 
21 ZONE-3A-3 10204 1079 387.78  400.00
22 ZONE-3B-1 7572 800 287.47  300.00
23 ZONE-4A 13875 1467 527.25  550.00
24 ZONE-5-1 6665 705 253.40  250.00
25 ZONE-5-3 17202 1818 653.34  650.00
26 ZONE-5B-1 13153 1390 499.56  500.00
27 ZONE-6 7289 770 276.69  300.00
28 ZONE-6A 6926 732 263.2 
800.00
29 ZONE-6B 13742 1453 522.02 
30 ZONE-6A-1 9383 992 356.47  350.00
31 ZONE-6A-2 4873 515 185.2 
450.00
32 ZONE-7B 7188 760 273.05 
33 Zone-6A-3 15113.5 1598 574.25  600.00
34 ZONE-6C 12449 1316 472.91  500.00
35 ZONE-6C-1 6261 662 237.88  250.00
36 ZONE-6C-2 11446.5 1210 434.87  450.00

  184 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Population Water Demand OHT


Sl.Nos Zones In Kld
Capacity
Say
2011 2038 KL
37 ZONE-6C-3 6609 699 251.25  250.00
38 Zone-7A-1 8275 875 314.47  350.00
39 Zone-7A-2 7492 792 284.63  300.00
40 ZONE-8 10116 1069 384.16  400.00
41 ZONE-8B 11430 1208 434.10  450.00
42 ZONE-8C 10323 1091 392.09  400.00
43 ZONE-8D 11971 1265 454.74 
900.00
44 ZONE-5-2 11787 1246 447.69 
45 ZONE-9 17358 1835 659.47  650.00
46 ZONE-9-1 12106 1280 459.97  450.00
47 ZONE-9-2 5759 609 218.90  200.00
48 ZONE-9-3 11997 1268 455.66  450.00
49 Zone-9A 12079 1277 458.94  450.00
50 ZONE-9A-1 17354 1834 659.12  650.00
51 ZONE-10 11282 1193 428.75  450.00
52 ZONE-10A-1 10101 1068 383.81  400.00
53 ZONE-10A-2 13196 1395 501.37  500.00
54 ZONE-11 7772 822 295.41  300.00
55 ZONE-11A 6154 650 233.57  250.00
56 ZONE-11A-1 5586 590 212.00  200.00
57 ZONE-11B 9702 1026 368.72  400.00
58 ZONE-12-1 8747 925 332.41  350.00
59 ZONE-12-2 3860 408 146.63  150.00
60 ZONE-12-3 8045 850 305.50  300.00

  185 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐ BELCUPP 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  1157  KLD 
B ‐ Average Hour Demand 'a'  48.21  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         = (24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supplies. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  415.81 
Say   450  KLD 

  186 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐ BHBHAECH 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  1268  KLD 
B ‐ Average Hour Demand 'a'  52.83  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  455.66 
Say   450  KLD 

  187 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐ MARKUNDI 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  772  KLD 
B ‐ Average Hour Demand 'a'  32.17  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  277.47 
Say   300  KLD 

  188 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐ RUDAWALI 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  362  KLD 
B ‐ Average Hour Demand 'a'  15.08  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  130.07 
Say   150  KLD 

  189 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐ PATWDH 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  625  KLD 
B ‐ Average Hour Demand 'a'  26.04  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  224.60 
Say   250  KLD 

  190 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐REDIA 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  531  KLD 
B ‐ Average Hour Demand 'a'  22.13  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  190.87 
Say   200  KLD 

  191 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐ SALKHAN 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  1427  KLD 
B ‐ Average Hour Demand 'a'  59.46  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  512.84 
Say   500  KLD 

  192 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐ KANACH 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  466  KLD 
B ‐ Average Hour Demand 'a'  19.42  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  167.50 
Say   175  KLD 

  193 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐ 1 (BARBASPUR) 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  986  KLD 
B ‐ Average Hour Demand 'a'  41.08  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  354.32 
Say   350  KLD 

  194 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐ 1‐1 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  744  KLD 
B ‐ Average Hour Demand 'a'  31.00  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  267.38 
Say   300  KLD 

  195 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐ 1A‐1 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  720  KLD 
B ‐ Average Hour Demand 'a'  30.00  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  258.75 
Say   250  KLD 

  196 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐ 1A 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  934  KLD 
B ‐ Average Hour Demand 'a'  38.92  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  335.69 
Say   350  KLD 

  197 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐ 2 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  984  KLD 
B ‐ Average Hour Demand 'a'  41.00  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  353.63 
Say   350  KLD 

  198 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐ 2‐1 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  1028  KLD 
B ‐ Average Hour Demand 'a'  42.83  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  369.41 
Say   400  KLD 

  199 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐ 2A 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  1252  KLD 
B ‐ Average Hour Demand 'a'  52.17  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  449.97 
Say   450  KLD 

  200 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐ 3‐1 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  1156  KLD 
B ‐ Average Hour Demand 'a'  48.17  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  415.47 
Say   400  KLD 

  201 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐ 3‐2 & 3‐3 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  1778  KLD 
B ‐ Average Hour Demand 'a'  74.08  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  638.94 
Say   650  KLD 

  202 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐ 11 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  822  KLD 
B ‐ Average Hour Demand 'a'  34.25  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  295.41 
Say   300  KLD 

  203 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐ 11A 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  650  KLD 
B ‐ Average Hour Demand 'a'  27.08  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  233.57 
Say   250  KLD 

  204 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐ 11A‐1 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  590  KLD 
B ‐ Average Hour Demand 'a'  24.58  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  212.00 
Say   200  KLD 

  205 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐ 11B 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  1026  KLD 
B ‐ Average Hour Demand 'a'  42.75  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  368.72 
Say   400  KLD 

  206 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐ 10A‐1 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  1068  KLD 
B ‐ Average Hour Demand 'a'  44.50  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  383.81 
Say   400  KLD 

  207 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐ 10A‐2 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  1395  KLD 
B ‐ Average Hour Demand 'a'  58.13  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  501.37 
Say   500  KLD 

  208 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐ 10 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  1193  KLD 
B ‐ Average Hour Demand 'a'  49.71  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  428.75 
Say   450  KLD 

  209 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐3B‐1 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  800  KLD 
B ‐ Average Hour Demand 'a'  33.33  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  287.47 
Say   300  KLD 

  210 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐3A‐1 & 3A‐2 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  1576  KLD 
B ‐ Average Hour Demand 'a'  65.67  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  566.40 
Say   600  KLD 

  211 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐3A‐3 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  1079  KLD 
B ‐ Average Hour Demand 'a'  44.96  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  387.78 
Say   400  KLD 

  212 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐6 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  770  KLD 
B ‐ Average Hour Demand 'a'  32.08  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  276.69 
Say   300  KLD 

  213 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐6B & 6A 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  2185  KLD 
B ‐ Average Hour Demand 'a'  91.04  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  785.22 
Say   800  KLD 

  214 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐7B & 6A‐2 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  1275  KLD 
B ‐ Average Hour Demand 'a'  53.13  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  458.25 
Say   450  KLD 

  215 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐6A‐1 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  992  KLD 
B ‐ Average Hour Demand 'a'  41.33  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  356.47 
Say   350  KLD 

  216 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐6A‐3 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  1598  KLD 
B ‐ Average Hour Demand 'a'  66.58  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  574.25 
Say   600  KLD 

  217 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐4A 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  1467  KLD 
B ‐ Average Hour Demand 'a'  61.13  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  527.25 
Say   550  KLD 

  218 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐6C 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  1316  KLD 
B ‐ Average Hour Demand 'a'  54.83  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  472.91 
Say   500  KLD 

  219 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐7A‐2 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  792  KLD 
B ‐ Average Hour Demand 'a'  33.00  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  284.63 
Say   300  KLD 

  220 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐7A‐1 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  875  KLD 
B ‐ Average Hour Demand 'a'  36.46  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  314.47 
Say   350  KLD 

  221 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐6C‐1 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  662  KLD 
B ‐ Average Hour Demand 'a'  27.58  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  237.88 
Say   250  KLD 

  222 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐6C‐2 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  1210  KLD 
B ‐ Average Hour Demand 'a'  50.42  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  434.87 
Say   450  KLD 

  223 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐6C‐3 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  699  KLD 
B ‐ Average Hour Demand 'a'  29.13  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  251.25 
Say   250  KLD 

  224 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐5B‐1 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  1390  KLD 
B ‐ Average Hour Demand 'a'  57.92  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  499.56 
Say   500  KLD 

  225 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐9A‐1 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  1834  KLD 
B ‐ Average Hour Demand 'a'  76.42  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  659.12 
Say   650  KLD 

  226 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐5‐1 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  705  KLD 
B ‐ Average Hour Demand 'a'  29.38  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  253.40 
Say   250  KLD 

  227 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐8B 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  1208  KLD 
B ‐ Average Hour Demand 'a'  50.33  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  434.10 
Say   450  KLD 

  228 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐8 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  1069  KLD 
B ‐ Average Hour Demand 'a'  44.54  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  384.16 
Say   400  KLD 

  229 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐8C 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  1091  KLD 
B ‐ Average Hour Demand 'a'  45.46  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  392.09 
Say   400  KLD 

  230 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐8D & 5‐2 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  2511  KLD 
B ‐ Average Hour Demand 'a'  104.63  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  902.43 
Say   900  KLD 

  231 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐5‐3 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  1818  KLD 
B ‐ Average Hour Demand 'a'  75.75  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  653.34 
Say   650  KLD 

  232 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐9A 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  1277  KLD 
B ‐ Average Hour Demand 'a'  53.21  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  458.94 
Say   450  KLD 

  233 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐9 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  1835  KLD 
B ‐ Average Hour Demand 'a'  76.46  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  659.47 
Say   650  KLD 

  234 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐9‐1 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  1280  KLD 
B ‐ Average Hour Demand 'a'  53.33  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  459.97 
Say   450  KLD 

  235 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐9‐2 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  609  KLD 
B ‐ Average Hour Demand 'a'  25.38  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  218.90 
Say   250  KLD 

  236 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐9‐3 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  1268  KLD 
B ‐ Average Hour Demand 'a'  52.83  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  455.66 
Say   450  KLD 

  237 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐12‐1 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  925  KLD 
B ‐ Average Hour Demand 'a'  38.54  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  332.41 
Say   350  KLD 

  238 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐12‐2 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  408  KLD 
B ‐ Average Hour Demand 'a'  17.00  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  146.63 
Say   150  KLD 

  239 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PATWDH GOV PIPED WATER SUPPLY SCHEME 
DISTRICT SONBHADRA, UTTAR PRADESH  
STORAGE CAPACITY OF RESERVOIR OF ZONE ‐12‐3 
(DRAW OFF PATTERN) 
A ‐ Water Requirement for intermidiate year  850  KLD 
B ‐ Average Hour Demand 'a'  35.42  KL/Hr 
C ‐ Peak Factor = 3.0 
D ‐ Peak Hour Demand = 3.0a 
E ‐ Average Pumping Hour = 16 Hour 
F ‐ Average Hourly input = 24/16 = 1.5a         =(24 hrs/Average Pumping Hrs.) 
Assume 16 Hrs electric supply. 

Rate of  Total  Difference 


Total  Rate of  Total  Cummulative  Cummulative 
S.No  Hours  Draw  Draw  Excess / 
Hour  Inflow  Inflow  inflow  Draw off 
off  off  Deficit 
1  0.00‐2.00  2.00  0.00  0.00  0.00  0.08  0.16  0.16  0.160 
2  2.00‐4.00  2.00  1.50  3.00  3.00  0.08  0.16  0.32  ‐2.680 
3  4.00‐5.00  1.00  1.50  1.50  4.50  0.20  0.20  0.52  ‐3.980 
4  5.00‐6.00  1.00  1.50  1.50  6.00  0.50  0.50  1.02  ‐4.980 
5  6.00‐8.00  2.00  1.50  3.00  9.00  3.00  6.00  7.02  ‐1.980 
6  8.00‐9.00  1.00  1.50  1.50  10.50  3.00  3.00  10.02  ‐0.480 
7  9.00‐10.00  1.00  1.50  1.50  12.00  2.00  2.00  12.02  0.020 
8  10.00‐12.00  2.00  0.00  0.00  12.00  1.00  2.00  14.02  2.020 
9  12.00‐13.30  1.50  0.00  0.00  12.00  1.00  1.50  15.52  3.520 
10  13.30‐14.00  0.50  0.00  0.00  12.00  0.25  0.13  15.65  3.645 
11  14.00‐14.30  0.50  1.50  0.75  12.75  0.25  0.13  15.77  3.020 
12  14.30‐15.30  1.00  1.50  1.50  14.25  0.24  0.24  16.01  1.760 
13  15.30‐16.00  0.50  1.50  0.75  15.00  1.00  0.50  16.51  1.510 
14  16.00‐16.30  0.50  1.50  0.75  15.75  1.00  0.50  17.01  1.260 
15  16.30‐17.00  0.50  1.50  0.75  16.50  2.00  1.00  18.01  1.510 
16  17.00‐18.00  1.00  1.50  1.50  18.00  2.00  2.00  20.01  2.010 
17  18.00‐19.00  1.00  1.50  1.50  19.50  2.00  2.00  22.01  2.510 
18  19.00‐20.30  1.50  1.50  2.25  21.75  1.00  1.50  23.51  1.760 
19  20.30‐21.00  0.50  1.50  0.75  22.50  0.50  0.25  23.76  1.260 
20  21.00‐22.00  1.00  1.50  1.50  24.00  0.08  0.08  23.84  ‐0.160 
21  22.00‐23.00  1.00  0.00  0.00  24.00  0.08  0.08  23.92  ‐0.080 
22  23.00‐24.00  1.00  0.00  0.00  24.00  0.08  0.08  24.00  0.000 

Balancing Capacity of Reservoir = Maximum excess ‐ Maximum deficit 
Balancing Capacity of Reservoir =   3.645  (‐)  ‐4.98 
=  8.625  x a 
=  305.50 
Say   300  KLD 

  240 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Nature of Treatment : Rapid Gravity Sand Filter
Capacity of Treatment Plant : 120 MLD
1.7.3.1. Transmission Main (Raw Water and Clear Water): 

The Raw transmission main system has been designed from the Intake well to Water Treatment Plant (WTP).
The Clear Water Transmission Line has been designed from Clear water Reservoirs (CWR) at WTP to
Intermediate Clear Water Reservoir, overhead Tank (OHT) for 16 hrs operation as decided by department
(SWM). A peak factor of 1.5 has beenconsidered for transmission system design a minimum residual
pressure of 3.0 m has been considered over the full supply level of the service reservoir.
The matter was discussed with client regarding pipe material and same has been adopted. The detail of pipe
material is given below:

Table 1.7.3.1‐1: Pipe material for Raw Water & Clear Water Transmission Main 

Dia  Material  Length (M) 


1200  MS  700 
1000  MS  3,185 
1000  DIK‐9  21,881 
900  DIK‐9  231 
800  DIK‐9  16,779 
600  DIK‐9  25,567 
400  DIK‐9  43,291 
350  DIK‐9  10,769 
300  DIK‐9  41,137 
250  DIK‐9  75,659 
200  DIK‐9  63,424 
150  DIK‐9  34,060 
Total  3,36,683 

PROPOSED CLEAR WATER RESERVOIR (CWR) CAPACITIES 
DESIGN OF CAPACITY OF GLRs 
Description  WTP‐GLR 
GLR‐1 + GLR‐2 +GLR‐3 + 
Feeding GLR & OHSR  BAGHNAREE + PATWADH + 
REDIA + KANACH 
Population  1211660 
Daily Demand (MLD)‐(55/0.85 = 64.71 LPCD)  117.61 
Hours of Pumping (Hrs.)  16 
Rate of Water supply Ltrs. / Hrs.)  4900416.67 
Required capacity of Sump (Two Hour Capacity)   9800833 
CWR Capacity as per Demand (in KL)  9801 
Say (in KL)  9500 

  241 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

POPULATION 
Sl.No  TO  FROM  Intermediate  Ultimate 
Intial Year 
Year  Year 

Intake Well  Intake Well 
1  715560  931930  1211660 

ZONE‐PATWADH,ZONE‐C(SALKHAN) , 
ZONE‐C (REDIA)‐GLR2‐GLR‐1 
2  MCWR Patwadh  72879  94916  123406 
PMP‐ZONE ‐GLR‐3   637153  829814  1078892 
PMP‐KANACH  5529  7200  9362 
      Total  715560  931930  1211660 
PMP‐(Babhech)  15043  19592  25473 
GLR‐1  (Babhech) 
3  PMP‐(Belcup)  13724  17874  23239 
      Total  28767  37466  48711 
PMP‐Rudwali  4298  5598  7278 
GLR‐2 (Rudwali) 
4  PMP‐Markundi  9160  11929  15510 
      Total  13458  17527  22788 
5  GLR‐3 (Markundi)  GLR‐4  637153  829814  1078893 
PMP‐ZONE‐5‐3  21575  28099  36534 
GLR‐4 (LORI)  PMP‐GLR‐5 ,ZONE‐12‐3, 
6  ZONE‐9‐2  615577  801715  1042359 
      Total  637153  829814  1078893 
PMP‐ZONE‐12‐1,ZONE‐8,ZONE‐12‐2, 
PMP‐GLR‐9,ZONE‐5‐1,ZONE‐9A‐1,GLR‐ 406406  529292  688166 
10 
7  GLR‐5  (Ganguar) 
PMP‐ZONE‐8D&5‐2  27699  36074  46902 
PMP‐GLR‐6,ZONE‐8C,ZONE‐6C‐3  164950  214826  279310 
      Total  599056  780193  1014377 
8  GLR ‐6 (Murala Dih)  PMP GLR‐7,ZONE‐6C‐1  143713  187168  243350 
PMP‐GLR‐8 AND ZONE‐6C‐2,ZONE‐7A‐
9  GLR‐7  (Papi) 
1,ZONE‐6C,ZONE‐6  135550  176537  229528 
PMP‐ZONE‐6A‐3,ZONE‐8B,ZONE‐
GLR‐8 (ATARAULI 
10  7B&6A‐2,ZONE‐6A&6B  74761  97367  126593 
RAJA) 
PMP‐ZONE‐6A‐1  11768  15327  19928 
      Total  86529  112694  146521 
PMP‐(ZONE‐9‐1)  15184  19775  25711 
11  GLR‐9 (Nipraj) 
PMP‐(ZONE‐9‐3)  15047  19597  25479 
      Total  30231  39372  51190 

PMP‐ZONE‐10, ZONE‐9A AND ZONE‐9 . 
51071  66514  86479 
12  GLR‐10 (Kushra) 
PMP‐GLR‐11,ZONE‐3B‐1, 
ZONE‐3A‐3,ZONE‐5B‐1 GLR‐12  263849  343628  446773 
      Total 
314920  410142  533252 

  242 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
POPULATION 
Sl.No  TO  FROM  Intermediate  Ultimate 
Intial Year 
Year  Year 
PMP‐(ZONE‐3A‐1 AND 3A‐2)  18701  24355  31666 
13  GLR‐11 (Jogani) 
PMP‐ZONE‐7A‐2 ,ZONE‐ 4A ,ZONE‐11B 
38968  50751  65984 
      Total  57669  75106  97650 
PMP‐ZONE‐3‐1  13720  17869  23232 
PMP‐ZONE‐10A‐1,ZONE‐10A‐2,ZONE‐
14  GLR‐12 (Khutaha)  2A,GLR‐13  75675  98556  128140 
PMP‐ZONE‐3‐2&3‐3 ,ZONE‐11A‐
1,ZONE‐11,ZONE‐1‐1, GLR‐14  77993  101575  132064 
      Total  167388  218000  283436 
PMP‐ZON‐2,ZONE‐2‐1  23878  31098  40433 
GLR‐13 (Beerkhurd) 
15  PMP‐ZONE‐11A  7719  10052  13070 
      Total  31597  41150  53503 
PMP‐ZONE‐1,ZONE‐1A, 
GLR‐14 (Sirsain) 
16  ZONE‐1A‐1.  31325  40796  53042 

  243 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

DESIGN OF CAPACITY OF GLRs 
Description  GLR‐1  GLR‐2  GLR‐3  GLR‐4  GLR‐5  GLR‐6  GLR‐7  GLR‐8  GLR‐9  GLR‐10  GLR‐11  GLR‐12  GLR‐13  GLR‐14 
Population  48711  22788  1078893  1078893  1013042  242912  229615  145810  51190  533252  97650  283436  53503  53042 
Daily Demand 
(MLD)‐(55/0.85 =  4.73  2.21  104.72  104.72  98.33  23.58  22.29  14.15  4.97  51.76  9.48  27.51  5.19  5.15 
64.71 LPCD) 
Hours of Pumping 
16  16  16  16  16  16  16  16  16  16  16  16  16  16 
(Hrs.) 
Rate of Water 
197083.33  92083.33  4363333.3  4363333.33  4097083.33  982500  928750  589583.33  207083.33  2156666.67  395000  1146250  216250  214583.33 
supply Ltrs. / Hrs.) 
Required capacity 
of Sump (One  197083  92083  4363333  4363333  4097083  982500  928750  589583  207083  2156667  395000  1146250  216250  214583 
Hour Capacity)  
CWR Capacity as 
197  92  4363  4363  4097  983  929  590  207  2157  395  1146  216  215 
per Demand (in KL) 
Say (in KL)  200  100  4400  4400  4100  1000  950  600  200  2200  400  1200  250  250 

  244 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

1.7.3.2. Distribution Network: 

 
The distribution network has been designed by grouping of Gram Panchayat and One OHT has been
proposed. The farthest end of distribution network from OHT has been kept arround than the 5 km and
elevation as discussed with SWSM
The matter was discussed with client regarding pipe material and same has been adopted. The detail of pipe
material is given below:

Table 1.7.3.2‐1: Pipe material for Distribution network 

Sl.Nos Material Dia (MM) Length (M)

1 50 187590
2 GI 65 72552
3 80 28342
4 63 1804340
5 75 154661
6 90 144279
7 HDPE 110 136720
8 140 163198
9 160 103311
10 200 101816
11 100 40175
12 150 32756
13 200 92347
DIK-7
14 250 90121
15 300 32444
16 350 3853
Total 3188505

  245 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

  246 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

  247 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Details of Elevated Service Reservoirs


STAGING  OHSR CAPACITY 
SL NO.  ZONE  LOCATION 
HEIGHT (M)  (KL) 
1  BELCUPP   Belcupp  22  450 
2  BHBHAECH  Bhbhaech  18  450 
3  REDIA  Kurhul  14  200 
4  SALKHAN  BAGHNAREE  10  500 
5  MARKUNDI  MARKUNDI  20  300 
6  RUDAWALI  RUDAWALI  22  150 
7  PATWDH  PATWDH  10  250 
8  KANACH  Kanach  16  175 
9  ZONE‐1  Barbaspur  15  350 
10  ZONE‐1‐1  Pathartal  19  300 
11  ZONE‐1A‐1  Sapahi  19  250 
12  ZONE‐1A  Parsauna  22  350 
13  ZONE‐2  Deogarha  10  350 
14  ZONE‐2‐1  Bardiya  19  400 
15  ZONE‐2A  Bhagahi  22  450 
16  ZONE‐3‐1  Khutaha  15  400 
17  ZONE‐3‐2 & 3‐3  Satohan  14  650 
18  ZONE‐11  Peroh  13  300 
19  ZONE‐11A  Beerkhurd  22  250 
20  ZONE‐11A‐1  Bhawana   18  200 
21  ZONE‐11B  Visahar  14  400 
22  ZONE‐10A‐1  Karaundia  18  400 
23  ZONE‐10A‐2  Kharahata  21  500 
24  ZONE‐10  Tendui  10  450 
BELKURI 
25  ZONE‐3B‐1  15  300 
MURPHARKAT 
26  ZONE‐3A‐1 & 3A‐2  Jogani  20  600 
27  ZONE‐3A‐3  Velahi  13  400 
28  ZONE‐6  Sirsiathkurai  21  300 
29  ZONE‐6B & 6A  Lohra  19  800 
30  ZONE‐7B & 6A‐2  Bat  20  450 
31  ZONE‐6A‐1  Atarauli Raja  22  350 
32  ZONE‐6A‐3  KHAMRIHA  22  600 
33  ZONE‐4A  Karkoll  22  550 
34  ZONE‐6C  Dilahi  15  500 
35  ZONE‐7A‐2  Imlipur  17  300 
36  ZONE‐7A‐1  Patehara  20  350 
37  ZONE‐6C‐1  Jokahi  17  250 
38  ZONE‐6C‐2  Bakahi  17  450 
39  ZONE‐6C‐3  Parsona  19  250 
40  ZONE‐5B‐1  Welanow  21  500 

  248 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Details of Elevated Service Reservoirs
STAGING  OHSR CAPACITY 
SL NO.  ZONE  LOCATION 
HEIGHT (M)  (KL) 
41  ZONE‐9A‐1  SHLAIYA  19  650 
42  ZONE‐5‐1  Deori Kalan  17  250 
43  ZONE‐8B  Chandauli  22  450 
44  ZONE‐8  Bishbhrpur  16  400 
45  ZONE‐8C  Pashi Kalana  22  400 
46  ZONE‐8D & 5‐2  Ganguar  22  900 
47  ZONE‐5‐3  Lori  10  650 
48  ZONE‐9A  Dugaulia  14  450 
49  ZONE‐9  Mahuriya  17  650 
50  ZONE‐9‐1  Bahuar  18  450 
51  ZONE‐9‐2  Tilauli  10  250 
52  ZONE‐9‐3  Nipraj  19  450 
53  ZONE‐12‐1  Lashra  17  350 
54  ZONE‐12‐2  Atarauli Khurd  18  150 
55  ZONE‐12‐3  Raunp  10  300 

1. Pumping Machinery:

PUMP KW & RATES AS PER DESIGN  
TYPE  NO OF PUMPS  LPM /  LPS / 
SL 
FROM  TO  OF  LPM  HEAD 
No.  W  S  TOTAL  PUMP  PUMP 
PUMP 
2303
1  Intake well  120MLD WTP  VT  69100  3  3  6  384  38.5 

OHSR‐ Kanach  VT  486  1  1  2  486  9  62 

ZONE‐PATWADH,ZONE‐
2  MCWR at WTP  SALKHAN ,ZONE‐REDIA‐GLR2‐ VT  6398  4  2  6  1600  27  94 
GLR‐1 
1118
GLR‐3 at Markundi  VT  55935  5  3  8  187  68 

OHSR, Zone‐Rudawli  HSC  377  1  1  2  377  7  37 


3  GLR‐2 (Rudwali) 
OHSR Zone‐Markundi  HSC  804  1  1  2  804  14  76 

OHSR Zone‐Bhbhaech  HSC  1321  1  1  2  1321  23  33 


4  GLR‐1 (Bhbhaech) 
OHSR Zone‐Belcupp  HSC  1205  1  1  2  1205  21  59 

  249 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
PUMP KW & RATES AS PER DESIGN  
TYPE  NO OF PUMPS  LPM /  LPS / 
SL 
FROM  TO  OF  LPM  HEAD 
No.  W  S  TOTAL  PUMP  PUMP 
PUMP 

5  GLR‐3 (Markundi)  GLR‐4 (Lori)  VT  55935  10  5  15  5594  94  167 

OHSR Zone‐5‐3  VT  1894  1  1  2  1894  32  25 


6  GLR‐4 (Lori) 
2702
GLR‐5 ,ZONE‐12‐3,,ZONE‐9‐2  VT  54041  2  1  3  451  17 

OHSR Zone ‐8D & 5‐2  VT  2616  1  1  2  2616  44  37 

GLR‐6 (Kekarahi), OHSR‐8C, 
VT  14458  3  1  4  4820  81  45 
OHSR‐6C‐3 
7  GLR‐5 (Gangur) 
GLR‐9 (Nipraj), GLR‐10 
(Kushara), OHSR‐8, OHSR‐12‐ 1181
VT  35447  3  1  4  197  58 
1, OHSR‐12‐2, OHSR‐5‐1,  6 
OHSR‐9A‐1 

8  GLR‐6 (Kekarahi)  GLR‐7 (Papi) & OHSR‐6C‐1  HSC  12594  3  2  5  4198  70  36 

GLR‐8, OHSR‐6 , OHSR‐6C, 
9  GLR‐7 (Papi)   VT  11904  2  1  3  5952  100  53 
OHSR‐6C‐2 & OHSR‐7A‐1 

OHSR 6A‐1  HSC  1033  1  1  2  1033  18  37 


 GLR‐8 ( Tarauli 
10 
Raja)  OHSR‐6A & 6B , OHSR‐7B & 
HSC  6526  2  1  3  3263  55  59 
6A‐2 , OHSR‐6A‐3  & OHSR‐8B 

OHSR‐9‐1  HSC  1333  2  1  3  667  12  81 


11  GLR‐9 (Nipraj)  
OHSR‐9‐3  HSC  1321  1  1  2  1321  23  34 

OHSR‐10, OHSR‐9A & OHSR‐9  VT  4483  2  1  3  2242  38  74 


12  GLR‐10 (Kushara) 
GLR‐11, GLR‐12, OHSR‐5B‐1, 
VT  23163  6  4  10  3861  65  42 
OHSR‐3B‐1 & OHSR‐3A‐3 

OHSR ‐3A‐1 & 3A‐2  HSC  1642  1  1  2  1642  28  33 


13  GLR‐11 (Jogani) 
OHSR‐11B, OHSR‐4A & OHSR‐
HSC  3421  3  2  5  1141  20  61 
7A‐2 

  250 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
PUMP KW & RATES AS PER DESIGN  
TYPE  NO OF PUMPS  LPM /  LPS / 
SL 
FROM  TO  OF  LPM  HEAD 
No.  W  S  TOTAL  PUMP  PUMP 
PUMP 

OHSR‐3‐1  VT  1204  1  1  2  1204  21  31 

GLR‐13, OHSR‐2A, OHSR‐10A‐1 
14  GLR‐12  (Khutana)  & OHSR‐10A‐2  VT  6643  2  1  3  3322  56  72 

GLR‐14, OHSR‐3‐2 & 3‐3, 
OHSR‐11A‐1, OHSR‐11 &  VT  6847  2  1  3  3424  58  63 
OHSR‐1‐1 

OHSR‐ 11A   VT  678  1  1  2  678  12  37 


GLR‐13 ( 
15 
Beerkhurd) 
OHSR‐ 2 & OHSR‐2‐1   VT  2096  1  1  2  2096  35  105 

OHSR‐1, OHSR‐1A & OHSR‐1A‐
16  GLR ‐14 (Sirsail)  HSC  2750  2  1  3  1375  23  42 

DG SET DESCRIPTION 
DG Rating as 
S.NO  LOCATION  Unit  Qty 
per IS/BS 
1  INTAKE WELL  1250  Nos  1 
2  WTP +MCWR  2500  Nos  1 
3  GLR‐1 (Babhech)  125  Nos  1 
4  GLR‐2 (Rudwali)  125  Nos  1 
5  GLR‐3 (Markundi)  3500  Nos  1 
6  GLR‐4 (Lori)  500  Nos  1 
7  GLR‐5 (Ganguar)  1250  Nos  1 
8  GLR ‐6 (kekarahi)  320  Nos  1 
9  GLR‐7(Papi)  500  Nos  1 
10  GLR‐8  ( Atarauli Raja)  320  Nos  1 
11  GLR‐9 (Nipraj)   125  Nos  1 
12  GLR‐10 (Kushara)  500  Nos  1 
13  GLR‐11 (Jogani)  160  Nos  1 
14  GLR‐12 (Khutana)  500  Nos  1 
15  GLR‐13 ( Beerkhurd)  320  Nos  1 
16  GLR‐14 (Sirsain)  125  Nos  1 
Total 16

  251 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
TRANSFORMER RATING AS PER DESIGN 
KVA Rating as 
Sl.NO  LOCATION  Unit  Qty 
per IS:1180 

1  INTAKE WELL  1250  Nos  2 

2  WTP+MCWR  2500  Nos  2 

3  GLR‐1 (Babhech)  160  Nos  2 

4  GLR‐2 (Rudwali)  100  Nos  2 

5  GLR‐3 (Markundi)  3500  Nos  2 

6  GLR‐4 (Lori)  500  Nos  2 

7  GLR‐5 (Ganguar)  1250  Nos  2 

8  GLR ‐6 (kekarahi)  315  Nos  2 

9  GLR‐7(Papi)  500  Nos  2 

10  GLR‐8  ( Atarauli Raja)  315  Nos  2 

11  GLR‐9 (Nipraj)   160  Nos  2 

12  GLR‐10 (Kushara)  500  Nos  2 

13  GLR‐11 (Jogani)  160  Nos  2 

14  GLR‐12 (Khutana)  500  Nos  2 

15  GLR‐13 ( Beerkhurd)  315  Nos  2 

16  GLR‐14 (Sirsain)  100  Nos  2 

Total 32

  252 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Sl.No  Valves Description  Unit  Qty 


A  Sluice Valves PN 1.0       
1  150 mm dia  Nos  27 
2  200 mm dia  Nos  30 
3  250 mm dia  Nos  35 
4  300 mm dia  Nos  11 
5  350 mm dia  Nos  5 
6  400 mm dia  Nos  17 
7  600 mm dia  Nos  12 
8  800 mm dia  Nos  3 
9  900 mm dia  Nos  1 
10  1000 mm dia  Nos  12 
B  Scour Valves PN 1.0       
   150 mm dia  Nos  41 
   200 mm dia  Nos  43 
   300 mm dia  Nos  12 
   400 mm dia  Nos  8 
   500 mm dia  Nos  1 
600 mm dia  Nos  8 

C  Under ground sluice value type fire hydrant consisting of 100 mm 
dia sluice valve  Nos  55 
D  Air Valve       
   50 mm dia  Nos  44 
   80 mm dia  Nos  87 
   100 mm dia  Nos  31 
   150 mm dia  Nos  46 
E  Flow Control Valve       
   150 mm dia  Nos  12 
   200 mm dia  Nos  13 
   250 mm dia  Nos  16 
   300 mm dia  Nos  4 
   350 mm dia  Nos  1 
   400 mm dia  Nos  6 
   600 mm dia  Nos  4 
   800 mm dia  Nos  2 
   1000 mm dia  Nos  3 
F  Pressure Reducing Valve       
   50 mm dia  Nos  1 
   65 mm dia  Nos  5 
   80 mm dia  Nos  5 
   100 mm dia  Nos  22 
   150 mm dia  Nos  21 
   200 mm dia  Nos  6 
   250 mm dia  Nos  3 
   300 mm dia  Nos  2 
  253 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

ELECTRICAL SYSTEM 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
  254 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Electrical Systems: 
 
a. General Information 
 
i. The Electrical system have been designed for an intermediate demand for the year 2038  
ii. The reference ambient temperature for design of all Electrical Equipment’s ‐ 50° C 
iii. System Voltage 
 
a. Incoming Supply          :  11kV, 3‐Ph, Wire, 50Hz, AC 
b. Plant Power Distribution       :  415V, 3‐Ph, 4‐Wire, 50Hz, AC 
c. Voltage variation          :  +10% to ‐10% 
d. Frequency variation          :  +5% to ‐5% 
e. Combined variation          :  +10% to ‐10% 
f. Neutral Earthing          :  Solid Earthing 
 
iv. Fault Level 
 
a. 11kV System  :  25kA for 1 Sec 
b. 415V System  :  50kA for 1 sec 
 
v. Starters for Electrical Motors 
 
a. Motors up to 7.5kW                :  DOL Starters 
b. Motors above 7.5kW to 75kW   :  Star Delta Starters 
c. Motors above 75kW                :  Soft starters 
d. Altitude                                         :  Less than 1000m MSL 
e. Humidity                              :   5 to 100% RH(non‐condensing) 
 
b.  Capacity and Sizing of Components 
 
a. Transformer shall be designed to cater the demand of intermediate for year 2038. With One Working and One 
Standby of same capacity. 
b. 415V Diesel Generator set of required rating is designed for full load of standby duty for concerned section. 
c. 415V LT Switchboard is designed to fed the entire plant load by taking power supply from the secondary of the 
Transformers. 
d. 415V  LT  APFC  panels  (Automatic  Power  Factor  Correction)  shall  be  designed  to  improve  the  system  power 
factor to 0.95 lag. 
e. Earthing shall be carried out as per the IS 3043: 2018 (Second Revision). 
f. Lightning protection shall be provided as per IEC 62305–Part 2&3 ‐ 2012. 
g. Lighting shall be carried out as per IS 16102, 16103 – Part 1&2 reaffirmed 2017. 
h. All the designs shall be based on CPHEEO Guidelines, UPPCL Norms, & relevant IS standard. 
i. LT Cables: 1.1kV cables shall be of the Cross‐linked Polyethylene insulation (XLPE) with Cores of cross‐sectional 
area greater than 2.5mm². 
j. Control Cables: 1.1KV cables shall be of stranded copper. 
k. Cable carrier system shall comprise of pre‐fabricated GI ladder type cable trays. 
l. The material of Earthing & Lightning conductors considered shall be as specified in signed contract document 
& in‐line with respective IS Standards. 
m. All the indoor & outdoor area shall be provided with LED lighting fixtures. 
n. The lux levels shall be considered as per signed contract document or relevant IS specification. 
 
 
 

  255 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

CONTROL PHILOSOPHY 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

  256 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
INSTRUMENTATION SCOPE AND CONSIDERATIONS 
 
The  scope  of  instrumentation,  control  and  automation  (ICA)  works  for  Mahadev  Group  Of  Villages  Water  Supply 
Project comprises of design, manufacture, programming and configuration, off site testing, delivery to site, installation 
and  erection,  testing,  commissioning,  setting  to  work  and  provision  of  documentation  for  a  complete  supervisory, 
instrumentation, control and automation system including Wireless Data transmission (as required) to provide remote 
monitoring. 
 
A PLC based Control system shall be provided at raw water pumping station, Water Treatment plant & Intermediate 
Booster Pumping stations and OHTs (as applicable). 
 
A  Centralized  monitoring  station  shall  be  provided  at  respective  WTP  for  centralized  monitoring  of  complete  Water 
intake, treatment, and supply and distribution system. 
 
PLC  based  control  systems  in  raw  water  pumping  station  &  other  Intermediate  Booster  Pumping  stations  shall  be 
communicated  with  respective  WTP  Centralized  monitoring  system  through  GPRS  based  wireless  communication 
system.  Filter  bed  Remote  IO  Panels/  consoles  in  WTP  &  Clear  water  pumping  stations  RIO  panels  shall  be 
communicated  with  respective  WTP  Centralized  monitoring  system  through  GPS/GPRS/LAN  based  communication 
system. 
 
In  this  scheme,  a  total  of  25  Elevated  Service  Reservoirs  are  available.  Field  Instruments  from  each  OHT  shall  be 
communicated  with  respective  WTP  Centralized  monitoring  system  through  GPRS  based  wireless  communication 
system. 
 
Raw Water Pump house (RWPH) 
 
The  raw  water  intake  well  cum  pump  house  shall  be  provided  with  the  following  design  provisions  for  effective 
monitoring and control. 
 
1. Field Instrumentation 
 
 1 No. Ultrasonic type level transmitter will be provided for monitoring of intake water level. Low–Low level set 
point activation derived from transmitter signal received at PLC will trip the running pumps. 
 
 1  No  Bourdon  type  Pressure  gauge  with  dial  size  of  150mm  will  be  provided  at  discharge  of  each  pump  & 
pumping main for local indication of discharge pressure. 
 
 1 No. Diaphragm type Pressure Switch will be provided at each individual pump outlet and 1 No. Diaphragm 
type  Pressure  Transmitter  will  be  provided  at  Common  discharge  line  for  pressure  measurement  &  Remote 
indication. 
 1 No. Electromagnetic flow meter will be provided at common delivery line of the pumping main for measuring 
the flow rate & total discharge flow. 
 
 All  analogue  field  instruments  (Transmitters)  shall  be  hooked  up  with  the  respective  Pumping  station  PLC 
System through Conventional hardwire based 4‐20mA signal for continuous monitoring, control, interlock and 
recording. 
 
2. UPS System 
 
1 No. standalone UPS System of suitable rating for providing 230V AC output supply & SMF Ni‐Cd battery bank with 
capacity for 30 minutes battery backup system will be provided in control room for powering of all field instruments 

  257 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
and PLC hardware. 
 
3. Automation 
 
One  no.  of  standalone  PLC/SCADA  system,  Power  supply  module,  communication  module,  and  non‐redundant  IO 
modules  (suitable  for  IOs  in  the  raw  water  pump  house  area)  with  the  following  shall  be  provided  at  PLC  /  SCADA 
Control room for complete monitoring and control. 
 
 One no. Operator cum Engineering Workstation with 24” Monitor 
 One no. A4 Black and White Printer 
 Industrial grade Ethernet switches 
 GSM/GPRS based wireless communication modem 
 Alarm annunciators 
 
Following Software provisions with necessary licenses shall be provided as minimum requirements: 
 
 HMI SCADA Software 
 PLC Programming software (programming as per IEC 61131‐3) 
 Windows Operating Software (latest version) 
 Application software (as per PLC OEM Standard) 
 Web SCADA Software 
 MS Office 
 Antivirus Software (as per PLC OEM recommendation) 
 
Multifunction  Meters  &  other  IEDs  (as  applicable)  for  electrical  parameters  monitoring  shall  be  provided  along  with 
Modbus RS 485 Communication for interfacing with the PLC / SCADA system. 
The raw water pumping station shall be communicated with central monitoring system PLC and SCADA (at WTP area) 
through non‐redundant GSM/GPRS based wireless communication. 
 
Water Treatment Plant (WTP) 
 
In  this  scheme,  water  treatment  plant  is  designed  with  treated  water  output  capacity  of  44  MLD  in  the  scheme  for 
treating the raw water from respective Intake locations. 
 
The  treatment  plant  shall  consist  of  water  treatment  and  filtering  units  and  the  details  on  the  same  are  already 
provided in water Treatment philosophy. 
 
Control  and  operations  of  WTP  process  will  be  done  through  PLC/SCADA  for  remote  operation  or  manually  through 
LPBS near the equipment for manual operation. 
 
The  following  design  provisions  are  considered  in  this  water  treatment  process  plant  for  effective  monitoring  and 
control. 
 
1. Field Instrumentation 
 
 Ultrasonic  type  flow  meter  (open  channel)  shall  be  provided  in  the  upstream  of  the  Parshall  flume  for  raw 
water flow measurement. 
 
 01 No. Ultrasonic type flow meter (open channel) shall be provided for measuring the WTP filter outlet flow 
rate. 
 

  258 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
 PH meter, Turbidity meter (each 1 no.) will be provided for continuous monitoring of quality & characteristics 
of raw water at WTP inlet & outlet & Residual Chlorine Analyser (1 No.) at the outlet of the WTP. 
 
 Each filter bed shall be provided with the following instruments 
 
o Loss  of  head  transmitter  (LOHT),  Differential  Pressure  type,  to  identify  the  clogging  of  filter  bed  and 
indication to start back wash. 
o Rate of flow Transmitter (ROFT), Ultrasonic type, shall be provided for measuring the instantaneous rate 
of filtered water flow. 
 
 01 no. Ultrasonic type level transmitter and Float & Board type level indicator are provided in backwash tank. 
 Suitable type Pressure gauges will be provided at delivery side of each pump (Sludge pumps/Recycle pumps/ 
backwash water pumps/air blowers/chlorination Booster pumps & dosing pumps, etc.) for local indication of 
discharge pressure. 
 
 One  no.  Conductivity  type (one  set  point Level  switch  with  Low set‐point)  will  be  provided  in each  chemical 
dosing tank for control & monitoring of chemical dosing pumps operation and One no. Float & board type level 
is considered for local indication. 
 
 One  no.  conductivity  type  Level  switch  (one  set  point  Level  switch  with  Low  set‐point)  shall  be  provided  in 
sludge sump & dirty backwash recycle Tank. 
 
 Required field instruments will be provided by respective vendor for chlorination systems. 
 
All  field  instruments  (Transmitters  /  Analyzers)  shall  be  hooked  up  with  the  respective  Water  treatment  Plant  PLC 
system  through  conventional  hardwire  based  4‐20mA  signal  for  continuous  monitoring,  control,  interlock  and 
recording. 
2. UPS System 
 
1 No. standalone UPS System of suitable rating for providing 230V AC output supply & SMF Ni Cd battery bank with 
capacity for 30 minutes battery backup system will be provided in control room for powering of all field instruments 
and PLC hardware’s. 
 
3. Automation 
 
One  no.  of  redundant  hot  standby  PLC/SCADA  system,  redundant  Power  supply  module,  redundant  communication 
module, and non‐redundant IO modules (suitable for IOs in the water treatment plant area) with the following shall be 
provided  at  PLC  /  SCADA  Control  room  for  complete  monitoring  and  control  of  WTP  including  Inlet  works, 
Clariflocculator, filtration plant, chemical dosing system, chlorination system, Sludge treatment, Wash water handling 
& recirculation system for control & monitoring of WTP (in both local and remote). 
 
i. One no. Operator Workstation with 24” Monitor 
ii. One no. Engineering Workstation with 24” Monitor 
iii. One no. FEP cum Historian server with 24” Monitor 
iv. One no. Laptop with 15.6” Monitor (for programming purpose only) 
v. 1 no. A4 sized Black & White Printer 
vi. GSM/GPRS based wireless communication modem 
vii. Industrial grade Ethernet switches 
viii. Alarm annunciators 
 
The following software provisions (with necessary licenses) shall be provided as minimum requirements. 
 
  259 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
 HMI SCADA Software 
 PLC Programming software (programming as per IEC 61131‐3) 
 Windows Operating Software (latest version) 
 Application software (as per PLC OEM Standard) 
 Web SCADA Software 
 MS Office 
Antivirus Software (as per PLC OEM recommendation) 
Multifunction  Meters  &  other  IEDs  (as  applicable)  for  electrical  parameters  monitoring  shall  be  provided  along  with 
Modbus RS 485 Communication for interfacing with the PLC / SCADA system. 
 
Each filter operation shall be automatic through PLC system & also from the local filter console desk with HMI touch 
screen  per  two  filter  beds.  And  it  will  further  communicate  to  central  control  system  through  non‐redundant  fiber 
optic‐based communication. 
 
Respective  WTP  PLC  system  will  act  as  Central  monitoring  station  for  respective  rural  piped  water  supply 
scheme/project. 
 
Clear water pump house & Reservoir/ Intermediate Clear water booster pumping station 
 
In each scheme, the Clear water/ Intermediate pump house shall be provided with the following design provisions for 
effective monitoring and control. 
 
1. Field Instrumentation 
 
o 01 No. Ultrasonic type level transmitter shall be provided for monitoring of each compartment reservoir water 
level. Low–Low level set point activation derived from transmitter signal received at PLC will trip the running 
pumps. 
o 01 no. Float & board type Level indicator shall be provided for local indication of level. 
o 01  no.  Compound  pressure  gauge  with  dial  size  of  150mm  shall  be  provided  at  inlet  of  each  pump  for 
indication of inlet suction pressure (for HSC pumps only). 
o 01 no. Bourdon type Pressure gauge with dial size of 150mm shall be provided at discharge of each pump and 
pumping main for local indication of discharge pressure. 
o 1 no. Pressure switch with configurable set point (within the range) shall be provided at each individual pump 
discharge for Pressure monitoring and enabling the operation of pumps. 
o 01  No.  Pressure  transmitter  shall  be  provided  at  each  common  discharge  line  for  pressure  measurement  & 
Remote indication. 
o 01 No. Electromagnetic flow meter shall be provided at each common delivery line of the pumping main for 
measuring the flow rate & total discharge flow. 
All  analogue  field  instruments  (Transmitters)  shall  be  hooked  up  with  the  respective  Pumping  station  PLC  System 
through Conventional hardwire based 4‐20mA signal for continuous monitoring, control, interlock and recording. 
 
 
2. UPS System 
 
1 No. standalone UPS System of suitable rating for providing 230V AC output supply & SMF Ni‐Cd battery bank with 
capacity for 30 minutes battery backup system will be provided in control room for powering of all field instruments 
and PLC hardware. 
 
 
 
 

  260 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
3. Automation 
 
One no. of standalone PLC/SCADA system, Power supply module, communication Dual SIM and IO modules (suitable 
for IOs in the clear water pump house area) with the following items along with required accessories shall be provided 
at PLC / SCADA Control room for complete monitoring and control (in both local and remote). 
 
i. One no. Operator Workstation with 24” Monitor 
ii. Industrial grade Managed Ethernet switches 
iii. Alarm annunciators 
iv. GSM / GPRS based wireless communication modem 
 
Following Software provisions with necessary licenses shall be provided as minimum requirements: 
 
i. HMI SCADA Software 
ii. Windows Operating Software (latest version) 
iii. Application software (as per PLC OEM Standard) 
iv. MS Office 
Antivirus Software (as per PLC OEM recommendation) 
Multifunction  Meters  &  other  IEDs  (as  applicable)  for  electrical  parameters  monitoring  shall  be  provided  along  with 
Modbus RS 485 Communication for interfacing with the PLC / SCADA system. 
 
For  field  Cabling  from  field  Instruments  to  PLC,  660/1100V  grade,  Multi  Stranded  Copper  conductor  with  PVC 
insulation, shielding, outer sheath and GI round wire‐armoured cable shall be considered. For analog signals, individual 
and overall shielded 0.5 Sq.mm Cooper cable shall be considered. For digital signals, 1.5 sq.mm Copper cable shall be 
considered. For Power cables, 2.5 Sq.mm Copper cable shall be taken into consideration. 
 
Electronic  grounding  (Earthing)  with  separate  electronic  grid  shall  be  provided  at  the  respective  clear  water  Pump 
house. Looped Signal ground cable shall be connected to electronic earth grid and Looped Frame ground cable shall be 
connected with the electrical earth grid itself. Earth pit electrode size and insertion depth shall be calculated based on 
soil resistivity reports to bring the resistance less than 1 Ohm. 
 
Communication between Clear water pumping station at WTP and Central monitoring station PLC/SCADA shall be done 
through non‐redundant GSM/GPRS based wireless communication. 
 
Overhead Tanks (OHT) / Elevated Service Reservoirs (ESR) 
 
In each ESR area, the following design provisions are considered for effective monitoring. 
 
1. Field instrumentation 
 
i. 1 No. Electromagnetic flow meter will be provided at inlet of the reservoir for measuring the flow rate & 
totalized flow. 
ii. One no. Ultrasonic type level transmitter shall be provided at each ESR for monitoring the tank water level. 
iii. One no. Pressure transmitter at the inlet line for pressure measurement. 
iv. One no. Float and board type Level indicator for local monitoring of ESR level. 
 
All  analogue  field  instruments  (Transmitters  /  Analyzers)  shall  be  hooked  up  with  the  respective  ESR  –  RTU  System 
through Conventional hardwire based 4‐20mA signal for continuous monitoring, control, interlock and recording. 
 
2. UPS System 
 

  261 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
1 No. 600 VA, Solar power system (Solar cell, charger, inverter), 230 V AC output suitable for 24 hrs battery backup for 
powering of all field instruments and PLC/RTU hardware. 
 
3. Automation 
 
1  No.  RTU/HMI  system  shall  be  considered  at  each  ESR  for  effective  control  &  monitoring  (by  measuring  the  field 
instruments). 
 
For  field  Cabling  from  field  Instruments  to  PLC,  660/1100V  grade,  Multi  Stranded  Copper  conductor  with  PVC 
insulation, shielding, outer sheath and GI round wire armoured cable shall be considered. 
 
For analog signals, individual and overall shielded 0.5 Sq.mm Cooper cable shall be considered. For digital signals, 1.5 
sq.mm Copper cable shall be considered. For Power cables, 2.5 Sq.mm Copper cable shall be taken into consideration. 
Also,  for communication,  GSM /  GPRS  based wireless  communication  modem  (Dual  band,  Multi‐slot  Class  10  (4:2:5) 
with antenna & RJ45 communication port) shall be considered for effective communication between respective Central 
monitoring station and ESR. 
Design Control & Operation Philosophy 
 
Each system PLC is used to perform following basic operations 
 
 Providing ON/OFF commands to various drives, actuators on the predefined sequence of operation, fulfilment 
of safety interlocks to optimize the operation. 
 Reading the  values of  different process parameters  from  field  instruments, electrical  devices,  energy  meters 
etc. installed in the plant. 
 Communicating  with  the  PC  based  SCADA  software  to  achieve  functionality  of  HMI,  Data  Storage  and 
Reporting 
 PLC  capacity  is  designed  to  handle  the  required  number  of  Digital  Inputs,  Digital  Outputs,  Analog 
Inputs/outputs, communication ports and protocol, memory capacity and processing speed. 
 For  appropriate  operation  of  the  system,  norms  are  defined  considering  various  devices  to  be  connected  to 
PLC. 
PLC input output considerations for drives, field instruments shall be as per Specification / Design basis and as per OEM 
recommendation. 
Operation Philosophy 
 

LOCAL MODE @ 
LPBS  @ FIELD 
MCC 

SELECTOR SWITCH AUTOMATIC @ 
  @ MCC  HMI 

REMOTE MODE 
MANUAL @ HMI 
@ MCC 

TEST @ HMI 

Figure 1: Pump/Valve Operation Philosophy 

  262 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
 
1. Remote Mode 
 
This  mode  is  valid  only  if  the  provided  equipment  of  the  pumping  station  like  Motor  Drives,  Pumps  are  healthy. 
Local/Remote  selector  switch  provided  in  the  respective  Motor  control  panel  are  selected  to  “Remote”  position  for 
PLC‐SCADA operation and respective position feedback will be indicated on HMI Screen. The provided SCADA system 
consist of AUTO, MANUAL & TEST modes of operation 
 
2. Local Mode 
 
The selector switch provided on electrical panel (MCC) is selected to LOCAL and status of mode selection is fed to PLC 
and  indicated  on  HMI  Screen.  In  this  mode  the  drive  can  be  started/  stopped  from  LPBS  near  equipment  or  MCC 
through push button provided on panel. PLC shall have the supremacy control and will monitor the status of pump in 
case of any abnormal process conditions then PLC panel shall trip the pump, if PLC is Online & healthy. 
3. Overall Operation 
 
All the workstations shall have suitable SCADA modules will be connected on Ethernet network. The Operation Station 
of each section will have following facilities 
 
 SCADA MIMIC diagram with animation to show the status of equipment and process of the respective section. 
 Facility to Pop –up alarms as they occur in the pumping station. 
 Facility to accept and reset the alarms. 
 Facility to display & print Alarm history with real time stamp. 
 Facility to display and print trends for key process parameters like, Level, Flow, pressure data with real time 
stamp. 
 Facility to display and print periodic process reports, operating time of all key equipment. 
 The work station will store all the data which will be retrieved by operation terminals for purpose of display of 
reports and trends. 
 
Thus, the complete automation system is defined with following parameters: 
 
 Display of Status of the pumping station and operation of pumping station from SCADA screen. 
 Display and processing of alarms & reports. 
 Sequential operation or logic of operation of the pumping station 
 
 
 
Log in and security 
 
The system has 3 levels of password facility for operation of the pumping station. Unless logged in the system will not 
respond to any operation. Following is the description of levels of protection. 
 
Level 1: Operator Level which enables operator to operate any device in Auto or manual Mode or check and print the 
trends & reports. 
 
Level 2: Supervisor level allows supervisor to change the process parameters and set points within specified limit. 
 
Level 3: Designer Level, allows the commissioning engineer to change equipment related variables, which should not 
be changed once the plant is put in to operation. 
 
 

  263 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Plant Monitoring and Control from SCADA: 
 
The  SCADA  screen  will  display  the  status  of  the  plant  as  per  the  P&I  Diagram  with  same  method  of  tagging  the 
equipment. The color code for this display is based on standard prevailing practice. For Dynamic MIMIC which indicates 
the status of equipment, standard color code shall be followed for pumps & valves. 
 
Process parameters 
 
The  process  parameters  are  indicated  in  the  SCADA  screen  will  have  the  tag  number  and  the  actual  values  with 
appropriate units. Since all the equipment’s / parts may not be accommodated in one screen, the plant or section of 
plant can be divided in to sub screen and navigation keys to switch the screen are provided on each screen. 
 
Buttons and data entry 
 
For operation of any equipment, soft button is provided in SCADA screen. A pop window is generated for operation or 
data entry once operator clicks the mouse on the equipment. 
 
Alarms 
 
All incoming and PLC internal generated alarms shall be immediately indicated at the SCADA Screen. This should help 
operators to overcome critical situations of any equipment or of the plant. 
 
Reporting 
 
Daily process report generated by SCADA will be available in the work station. With reference to the same data, weekly 
& monthly reports shall be generated & the alarm Report also been generated for any pre‐defined interval. 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

  264 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

OPERATION AND MAINTENANCE 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

  265 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
OPERATION AND MAINTENANCE 
NEED FOR O&M 
Any system however well it is designed has to be operated and maintained properly if it is to function effectively. To 
ensure this,  personnel of requisite qualification, experience and training in required numbers should be  selected  for 
the  installation.  Adequate  funds  should  be  provided  for  the  procurement  of  consumables  and  spares  required  for 
operation and maintenance of the system. Maintenance schedules should be prepared taking into consideration the 
manufacturer’s  recommendations  and  it  should  be  ensured  that  the  schedules  are  adhered  to.  Compliance  to  the 
preventive maintenance schedules should be monitored. Maintenance schedules should be prepared after discussion 
with  all  concerned  to  ensure  that  adequate  time  would  be  made  available  for  the  maintenance  of  the  system.  Non 
adherence  to  preventive  maintenance  schedules  will  lead  to  break  down  of  the  system  resulting  in  losses, 
environmental problems etc. 
OPERATION AND MAINTENANCE PLAN 
A comprehensive operation and maintenance plan shall be prepared to cover all the facilities. This plan shall contain 
what actions are to be taken, when these activities are to be performed, how these actions are to be taken and why 
these actions are required. Good housekeeping is required to ensure that all equipment, buildings, surrounding areas 
and facilities  are kept clean and orderly and shall  look that it is being frequently cleaned  and  attended to. A central 
operation and maintenance cell shall be created which will have responsibility for supervision, monitoring and analysis 
of all operation maintenance activities contained in the operation and maintenance plan. Officers shall be identified for 
monitoring whether the operation maintenance plans are followed or whether supervision of the plan is being done. 
The  supervisor’s  check  lists,  checked  by  monitoring  officers  shall  be  analyzed  by  the  top  management  to  locate 
persistent deficiencies and initiate corrective action. 
COMMON FEATURES OF OPERATION AND MAINTENANCE 
In  the  operation  and  maintenance  of  water  works,  there  are  certain  common  features  to  be  considered  by  the 
authority controlling the water works. These are briefly stated below: 
Availability of Detailed Plans, Drawing, O&M Manual 
When a water works will be taken over for O&M, it should be ensuring that at least 5‐6 sets of the detailed drawing 
maps of each of the components of the water works along with all relevant O&M manual will be available with the GP. 
One of the set may be preserved as a reference set in apex office for reference. The other sets must be corrected and 
updated whenever any addition/alterations/deletions will be done to nay of the structures and equipment. 
Schedule of Daily Operation 
For each of the activity where operators will be employed, a detailed scheme and schedule of unit operation should be 
worked out and a copy of the same should be available with each operator. This schedule of unit operations may have 
to  be  altered  to  suit  changes  in  raw  water  quality,  hours  of  the  availability  of  power,  break  downs  and  up‐set 
conditions etc. 
Schedule of Inspection of Machinery 
A regular schedule of  inspection of machinery, equipment their lubrication and servicing program must be prepared 
and  circulated.  Appropriate  supervisory  control  should  be  exercised  to  see  that  these  inspections,  lubrications  and 
servicing are being regularly carried out. 
Records 
For  each  piece  of  equipment  and  machinery  a  record  register  should  be  maintained  in  which  all  records  of  the 
equipment  such  as  servicing,  lubricating,  replacement  of  parts,  operating  hours  and  other  important  data  will  be 
entered. 
Records of Quality of Water 
Complete  records  of  bacteriological  and  chemical  analysis  of  water  from  source  to  the  consumer’s  tap  should  be 
maintained  and  reviewed.  Chart  should  also  be  prepared  for  the  important  characteristics  of  the  water  and  any 
changes in these characteristics as compared to the standards must be taken note of. 
Records of Key Activities of O & M 
For planning future augmentations and improvements of a water works in operation, it will be advisable to maintain 
certain key records such as daily  and  cumulative  supply over the year, number of connections of various sizes given 
and cumulative number of connections each month, water treated and supply billed. 
 

  266 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Staff Positions 
Appropriate  charts  indication  the  standard  staff  for  each  of  the  unit  of  operation  and  maintenance  and  the  staff 
actually in position shall be maintained at each office for review. 
Inventory of Stores 
A reasonable assessment of the stores and spare parts of machinery required over a period of time say, one year or 
half a year should be made and an inventory of the same prepared. Issues and replacement of store articles should be 
watched  and  procurement  procedures  lay  down  and  supervised.  The  aim  should  be  than  any  material  required  for 
replacement is available at any time for the maintenance. 
O & M OF INDIVIDUAL COMPONENTS 
Maintenance of Intakes (Intake Tower): 
 It  should  be  ensuring  that  sufficient  water  level  will  maintained  at  head  works  in  order  to  ensure  drawl  of 
required quantity of water into stake works without vortex formations. 
 All  intake  strainers  should  be  cleaned  at  frequent  interval  particularly  during  monsoon  to  prevent  fish  or 
floating matter into intake works. 
 All damages to structural components of intake works particularly during floods should be promptly repaired. 
 Sufficient  stock  of  rubble  should  be  maintained  at  intake  works  site  for  use  to  temporarily  overcome  the 
problems of scours at spillways and other places. 
 A  schedule  of  painting  of  steel  and  other  structural  part  of  intake  works  should  be  prepared  and  followed 
scrupulously to avoid damage to structure. 
 The raw water holding structure intake well should be de‐silted immediately after monsoon to remove salted 
silt. 
Maintenance of Pumps & Pumping Machinery: 
 Pump Operation Submersible/Centrifugal: 
The pumps will in use and the specification of O&M schedule provided by manufacturers shall be followed. However, 
the following points shall be observed while operating the pumps: 
 Dry running of the pumps should be avoided. 
 Centrifugal pumps have to be primed before starting. 
 Pumps should be operated only within the recommended range on the head‐discharge Characteristics of the 
pump.  
 If pump is operated at point away from duty point, the pump efficiency normally reduces. 
 Operation  near  the  shut  off  should  be  avoided,  as  the  operation  near  the  shut  off  causes  substantial 
recirculation within the pump, resulting in overheating of water in the casing and consequently, overheating of 
the pump. 
 Voltage during operation of pump‐motor set should be within + 10% of rated voltage. Similarly, current should 
be below the rated current as per name plate on the motor. 
 Whether the delivery valve should be opened or closed at the time of starting should be decided by examining 
shape of the power‐discharge characteristic of the pump. Pump of low and medium specific speeds draw lesser 
power at shut off head and power required increases from shut off to normal operating point. Hence in order 
to reduce starting load on motor, a pump of low or medium specific speed is started against closed delivery 
valve. Normally the pumps used in water supply schemes are of low and medium specific speeds. Hence, such 
pumps need to be started against closed delivery valve. The pumps of high specific speed draw more power at 
shut off. Such pumps should be started with the delivery valve open. 
 The delivery valve should be operated gradually to avoid sudden change in flow velocity which can cause water 
hammer pressures. It is also necessary to control opening of delivery valve during pipeline ‐ filling period so 
that  the  head  on  the  pump  is  within  its  operating  range  to  avoid  operation  on  low  head  and  consequent 
overloading. This is particularly important during charging of the pumping main initially or after shutdown. As 
head increases the valve shall be gradually opened. 
 When  the  pumps  are  to  be  operated  in  series,  they  should  be  started  and  stopped  sequentially,  but  with 
minimum time lag. Any pump, next in sequence should be started immediately after the delivery valve of the 
previous  pump  is  even  partly  opened.  Due  care  should  be  taken  to  keep  the  air  vent  of  the  pump  next  in 
sequence open, before starting that pump. 

  267 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
 The stuffing box should let a drip of leakage to ensure that no air is passing into the pump and that the packing 
is getting adequate water for cooling and lubrication. When the stuffing box is grease sealed, adequate refill of 
the grease should be maintained. 
 The running of the duty pumps and the standby should be scheduled so that no pump remains idle for long 
period  and  all pumps are  in ready‐to run condition.  Similarly, unequal running should be ensured so that all 
pumps  do  not  wear equally  and  become  due for  overhaul  simultaneously. If  any undue  vibration  or  noise  is 
noticed, the pump should be stopped immediately and cause for vibration or noise be checked and rectified. 
 Bypass valves of all reflux valve, sluice valve and butterfly valve shall be kept in closed position during normal 
operation of the pumps. 
 Frequent starting and stopping should be avoided as each start causes overloading of motor, starter, contactor 
and contacts. Though overloading lasts for a few seconds, it reduces life of the equipment. 
 Additional Points for Operation of the Pumps 
Submersible pumps: 
 Correct rotations 
 Pump should below static water level before starting, and continues to be below draw down level throughout 
the operation 
Undesirable Operations: 
 Following undesirable operations should be avoided: 
 Operation  at  Higher  Head‐  The  pump  should  never  be  operated  at  head  higher  than  maximum 
recommended. Such operation results in excessive recirculation in the pump, overheating of the water and the 
pump. Another problem, which arises if pump is operated at a head higher than the recommended maximum 
head, is that the radial reaction on the pump shaft than the recommended maximum head, is that the radial 
reaction on the pump shaft increases causing excessive unbalanced forces on the shaft which may cause failure 
of the pump shaft. As a useful guide, appropriate marking on pressure gauge be made. Such operation is also 
inefficient as efficiency at higher head is normally low. 
 Operation  at  Lower  Head‐  If  pump  will  be  operated  at  lower  head  than  recommended  minimum  head, 
radial  reaction  on  the  pump  shaft  increases  causing  excessive  unbalanced  forces  on  shaft  which  may  cause 
failure  of  the  pump  shaft.  As  useful  guide,  appropriate  markings  on  both  pressure  gauge  and  ammeter  are 
made. Such operation is also inefficient as efficiency at lower head is normally low. 
 Operation  on  Higher  Suction  Lift‐  If  pump  will  be  operated  on  higher  suction  lift  than  permissible  value, 
pressure at the eye of impeller and suction side falls below vapor pressure. This will result in flashing of water 
into vapor. These vapor bubbles during passage collapse resulting in cavitation in the pump, pitting on suction 
side  of  impeller  and  casing  and  excessive  vibrations.  In  addition  to  mechanical  damage  due  to  pitting, 
discharge of the pump also reduces drastically. 
 Throttled operation‐ At times if motor will continuously have overloaded, the delivery valve will be throttled 
to increase head on the pump and reduce power drawn from motor. Such operation will result in inefficient 
running as energy will be wasted in throttling. In such cases, it will preferable to reduce diameter of impeller 
which will reduce power drawn from motor. Installation of variable voltage &variable frequency (VVVF) drive 
as a remedial measure will be recommended. 
 Operation  with  Strainer/Foot  Valve  Clogged‐  If  the  strainer  or  foot  valve  will  clogged,  the  friction  loss  in 
strainer  increases  to  high  magnitude  which would result  in  pressure  at  the eye  of the  impeller  falling  below 
water  vapor  pressure, causing  cavitation  and  pitting similar to operation  on  higher  suction lift. The  strainers 
and foot valves should be periodically cleaned particularly during monsoon. 
 Operation with Occurrence of Vortices‐ If vibration continues even after taking all precautions, vortex may be 
the cause. All parameters necessary for vortex‐free operation should be checked. 
 Starting The Pumps: 
Following points should be checked before starting the pump. 
 Power is available in all 3 phases. 
 All connections are properly thimble 
 Trip circuit for relays is in healthy state\Check voltage in all 3 phases 
 The voltage in all phases should be almost same and within + 10% of rated voltage, as per permissible voltage 

  268 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
variation. 
 Check functioning of lubrication system specifically for oil lubricated and clear water lubricated VT pumps and 
oil lubricated bearings 
 Check stuffing box to ensure that it is packed properly 
 Check and ensure that the pump is free to rotate 
 Check over current setting if the pump is not operated for a week or longer period 
 Before starting it shall be ensured that the water level in the sump/intake is above low water level and inflow 
from the source or preceding pumping station is adequate. 
 Stopping The Pump: 
 Stopping the Pump under Normal Condition 
 Steps to be followed for stopping a pump of low and medium specific speed are as follows: 
 Close the delivery valve gradually (sudden or fast closing should not be resorted to which can give rise to water 
hammer pressures). 
 Switch off the motor. 
 Open the air vent in case of V.T. and submersible pump. 
 Stop  lubricating  oil  or  clear  water  supply  in  case  of  oil  lubricated  or  clear  water  lubricated  VT  pump  as 
applicable. 
DUTIES OF PUMP OPERATOR & MAINTENANCE OF RECORDS 
Pump operator will the most important functionary in the set up since it is he who will be in direct contact with the 
people  all  the  time.  The  higher  officers  could  maintain  contact  only  periodically.  The  pump  operator’s  primary 
responsibility  will  to  run  the  machinery  and  keep  it  in  proper  order.  Besides  he  will  have  to  act  a  link  between  the 
consumers & the officials of the department. The pump operator should maintain the following record. 
Log Book 
The log book should be maintained on a daily basis & incorporate the following things. 
 Date   Time of start of pumping set 
 Total hours of pumping   Volt meter reading 
 Depth gauge reading   Spring Level at time of start 
 Time taken to restore water level   Signature of P.O. 
 Time of switching off   Spring Level at time of switching off 
 Ampere meter reading   Signature of Inspecting Officer 
 Remarks Columns   
Complaint Register 
Complaint register should be properly maintained and all the complaints should be entered chronologically along with 
the remedial measures taken. The complaint should be self‐specific & the following should be clearly mentioned 
 Date of Complaint   Nature of Complaint 
 Complainants name & address   Place of Complaint 
 Time  for  which  the  complaint  is   Date  on  which  noted  by  the  field  staff 
witnessing it  (if any) 
 Date of Compliance   Any Special Remarks 
 Remarks or Comments by  the Senior   
Officers 
   
Movement Register 
The P.O. should maintain a movement registers. So that inspecting officers would be able to check the attendance. 
Meeting Register with Corporation 
The P.O. should meet the authority once a month & enter the minutes of meeting in the register. The Sub Divisional 
Officer should personally attend these meeting once in two months. This would help in proper co‐ordination between 
the department & the consumers. 
 
 

  269 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
MAINTENANCE OF WATER TREATMENT PLANT 
Preventive Maintenance 
Typical steps should follow: 
 Keeping electric motors free of dirt and moisture. 
 Assuring good ventilation at valve and pump vaults, sumps. 
 Checking pumps and motors for leaks, unusual noise and vibrations, overheating or signs of wear. 
 Inspecting alignment of shafts and couplings. 
 Checking for proper valve operation. 
 Checking for free flow of sludge in sludge removal collection and discharge systems. 
 Good House Keeping. 
For Cleaning 
 Close the inlet valve. 
 Allow water to deplete about 10 to 20 cm below the sand surface. 
 Allow the drying of sand bed. 
 Remove  the  top  1‐2  cm  of  sand  layer  by  manually.  A  manual  operation  will  have  preferred  till  labour  will 
cheap. 
 After cleaning, level the sand surface. 
Chlorination Register 
The register should have the following pts. 
 Date 
 Qty. of bleaching powder added 
 Pt. at which residual chlorine checked 
 Amount of residual chlorine 
 Sign of in charge, of WTP  
 Sign of inspecting authority  
The in‐charge of WTP should check the residual chlorine once a week and make an entry himself. 
Maintenance of Pumping Main 
The pumping mains will damage due to burst in pipe lines, tampering by anti‐social elements, temperature variations, 
etc. Such damages should be observed and attended to immediately. Readymade pipe sleeves, rubber sheets, and pipe 
clamps, etc. shall be always being kept in stock to stop the leakages in cracked pipes temporarily. If the pipes will be 
developed major cracks or severely damaged such pipes need to be replaced with good ones. The appurtenances  in 
the piping main such as sluice valves, scour valves, air release valves, etc. shall be protected against tampering by anti‐
social elements by always closing the lid and locking the valve chambers. 
MAINTENANCE OF OVERHEAD TANK (STORAGE RESERVOIR) 
To  prevent  bacterial  contamination  of  water  and  to  maintain  hygienic  condition  of  water  it  is  necessary  that  clear 
water storage tanks should be periodically cleaned and disinfected. It would be necessary to clean them once in three 
months or more frequently (if required). A program is proposed to be prepared and display boards shall be exhibited 
near the tank indicating last cleaning date and the next cleaning date. Men entering the tank should use clean pair of 
gum boots, which will be washed just before entering the water tank. Brushes used must also be in clean condition; 
preferably they should be soaked in bleaching powder solution at least for one hour before use. Also hand gloves shall 
be used in cleaning. 
CLEANING OPERATION 
The water level in the tank could be got depleted by consuming the water on previous day before taking up cleaning to 
avoid wastage of water. About 75 mm of water could be kept in the tank to which decanted, clear bleaching powder 
solution having concentration of 10 mg/lit chlorine may be added and the bottom and side walls of the tank scrubbed 
well using the brush and thoroughly cleaned. Dirty water could be added to the tank and the bottom and side walls of 
the  tank  cleaned  and  washed  thoroughly.  On  completion  of  the  cleaning,  it  is  necessary  that  the  side  walls  and  the 
bottom  of  the  tank  will  be  disinfected  using  a  strong  solution  of  decanted  clear  bleaching  powder  solution  having 
strength of 50 mg/lit of chlorine. Solution should be splashed on the side walls and bottom of the tank by means of 
small cans and the entire wall surfaces and bottom of the tank drenched by the solution. About one hour of reaction 

  270 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
period may be allowed to complete disinfection to take place. The tank may be decommissioned after one hour and 
put in to normal use. 
SAFETY PRECAUTIONS 
Usage of gum boots and hand gloves are necessary in order to prevent contamination of the tank and also to prevent 
skin irritation to workmen due to chlorine solution. Tank must be properly ventilated by keeping all manholes in open 
position when the cleaning operation is in progress. Un‐trained workmen shall not be engaged for cleaning. Workmen 
shall not be permitted into tank containing water more than 15 cm depth. Water level should be 134 reduced prior to 
allowing men inside to prevent accidents. Guard bars may be provided an outlet/scour opening provided at the bottom 
and side walls of the tank may be checked frequently and covers are to be replaced in position and locked. 
MAINTENANCE OF DISTRIBUTION SYSTEM 
Distribution system will have the likelihood of getting contaminated causing secondary pollution of once treated water 
before it will reach the consumers. Hence, the distribution system will need and deserves a careful maintenance. 
Preventive Maintenance Schedule 
A preventive maintenance schedule for Servicing of Valves and Maintenance of Valve Chambers, Maintenance of the 
pipelines: may include the tasks, set priorities, issue of work orders for tasks to be performed, list of scheduled tasks 
not completed, record of when the tasks are completed and maintaining a record of tools, materials, labour and costs 
will be required to complete each task. 
Leakage Control 
Wastage  of  water  in  the  system  and  distribution  network  will  occur  by  way  of  leakage  from  pipes,  joints  &  fittings, 
reservoirs and overflow from reservoirs & sumps. The objective of leakage control program is to reduce the wastage to 
a minimum and minimize the time that elapses between the occurrence of a leak and its repair. The volume of water 
lost  through  each  leak  should  be  reduced  by  taking  whatever  action  will  technically  and  economically  feasible  to 
ensure that the leak will be repaired as quickly as possible. To achieve this, the organization shall prescribe procedures 
for  identifying,  reporting,  repairing  and  accounting  for  all  visible  leaks.  It  will  be  beneficial  for  the  agency  if  the 
procedures involve the conscious and active participation of the population served by the agency apart from its own 
staff.  The  Management  has  to  process  the  data  and  evaluate  the  work  on  detection  and  location  of  leaks  and  for 
dissemination  of  the  results  and  initiate  actions  to  control  the  overall  problem  of  water  loss.  Interim  measures  for 
reduction/control  of  leakage  should  be  initiated  by  controlling  pressures  in  the  water  distribution  system  where 
feasible. 
 Leakage through House Connections: Leakage should be controlled at the point of house connection and in the 
consumer pipe by adopting correct plumbing practices and improving the methods used for tapping the main 
and  giving  house  connection  and  strict  quality  control  on  the  pipe  material  used  for  house  connection.  An 
analysis of leaks in house connections and investigation of reasons for leaks in the house connections shall be 
carried out to initiate action on reducing the leakage through house connections 
 Procedures for reporting Visible Leaks: authority should establish procedures whereby the population served 
by the authority can notifies the visible leaks. The authority staff should also report visible leaks found by them 
while carrying out other works on the water supply system. The authority will have to establish procedures for 
prompt repair of leaks and for attending efficiently and accurately to the leaks. Critical areas where leaks often 
will occur have to be identified and appropriate corrective measures have tube implemented. 
 Procedures  for  Detecting  Invisible  Leaks:  Establishment  of  procedures  for  detecting  and  locating  non‐visible 
leaks shall be compatible with the technological, operational and financial capability of the agency. Selection 
and  procurement  of  equipment  for  detection  and  location  of  leaks  must  take  into  account  the  cost‐
effectiveness and the financial capability of the organization. 
Cross Connections 
Contaminated  water  through  cross  connections  of  water  supply  lines  with  sewers  and  drains  will  be  a  problem 
prevailing widely. Regular survey will have to be undertaken to identify potential areas likely to be affected by cross 
connections  and  back‐flow. All  field personnel  should  be constantly  alert  for situations  where cross  connections  will 
likely  to  exist.  After  identifying  the  cross  connections,  remedial  measures  should  take  up  which  include:  providing 
horizontal  and  vertical  separation  between  the  water  main  and  the  sewer/drain,  providing  a  sleeve  pipe  to  the 
consumer pipes crossing a drain, modifying the piping including changing corroded piping with non‐corrodible piping, 
providing double check/non return valves at the consumer end etc. 

  271 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
PLUMBING PRACTICES FOR DRINKING WATER SUPPLY 
The internal plumbing system of the consumer shall conform to the National Building Code and also particularly to the 
bye laws of concerned water utility/local authority. The various types of plumbing materials are being used, namely GI, 
MDPE  &  PVC,  etc.  and  require  different  maintenance  practices.  Hence  specific  requirement  of  maintenance  should 
follow as per the CPHEEO Manual/ Manufacturer’s recommendations. 
QUALITY OF PIPE MATERIAL FOR HOUSE CONNECTION 
The  authority  shall  ensure  that  the  connection  and  communication  pipe  from  the  street  main  up  to  the  consumer 
premises  will  be  laid  as  per  correct  plumbing  practices  and  adopt  improved  methods  for  tapping  the  main.  Strict 
quality control will be required on the pipe material used for house connection. The bye Laws shall lay down rules for 
defining the ownership and responsibility for maintaining the point of connection and the communication pipe. 
CONTAMINATION THROUGH HOUSE CONNECTION 
While laying the consumer connection pipes there will a need to avoid contamination of water supplies. This can be 
achieved  by  maintaining  horizontal  and  vertical  separation  between  the  water  supply  communication  pipe  and  the 
sewer/drain. In some instances, a sleeve pipe may be required to be provided to the consumer pipes crossing a drain. 
Contamination by possible back flow would also be prevented by ensuring provision of double check/non‐return valves 
at the consumer end. 
RULES FOR CONSUMER CONNECTIONS 
The authority shall formulate rules for sanction of consumer connection, tapping the mains and laying the connection 
piping. Water utility shall undertake inspection of the consumer premises before releasing the connection to ensure 
that the internal plumbing system of the consumer conforms to the National Building Code. Authority shall supervise 
the process of drilling/tapping of the main for giving connection and the laying of the consumer piping. The process of 
submission  of  applications  for  connections  by  consumers  and  carrying  out  the  connection  work  through  licensed 
plumbers  is  also  prevalent  in  some  utilities.  In  such  cases  the  authority  shall  formulate  procedures  for  licensing  the 
plumbers  including  the  qualifications  to  be  possessed  by  the  plumber,  facilities  and  tools  to  be  available  with  the 
plumber for the work to be undertaken by the plumber. Authority shall closely observe the quality of materials used 
and works done by him and he should act as per procedures laid down in the bye laws for approval of the connection 
works, renewal or cancellation of the plumbers’ licenses or any other requirement depending on their performance or 
non‐performance. 
CHLORINE RESIDUAL TESTING AT CONSUMER END 
A  minimum  chlorine  residual  of  about  0.2  ‐0.5  mg/l  at  the  selected  monitoring  point/  consumer’s  end  is  often 
maintained to ensure that even a little contamination is destroyed by the chlorine. Hence, absence of residual chlorine 
could  indicate  potential  presence  of  heavy  contamination.  If  routine  checks  at  a  monitoring  point  will  carried  out, 
required  chlorine  residuals  and  any  sudden  absence  of  residual  chlorine  should  alert  the  operating  staff  to  take  up 
prompt investigation. Immediate steps should be taken are: 
 Re‐testing for residual chlorine 
 Checking chlorination equipment 
 Searching for source of contamination, which has caused the increased chlorine demand 
 Immediate stoppage of supplies from the contaminated pipelines 
 WATER QUALITY 
Water quality is a critical component of water supply delivery system. Assessment of the water quality situation is in a 
way  evaluation  of  the  total  system  beginning  with  the  water  supply  source,  its  extraction,  transport,  storage  and 
delivery. Contamination at all levels will not be uncommon however the focus has always remained on the source with 
little or no efforts to make the supply and distribution system contamination free. 
The  water  sample  from  source,  WTP  and  consumer  end  should  be  collected  and  send  to  Testing  Lab/PHC  for  the 
analysis. The water quality should be checked regularly and record should be maintained at authority. 
CHEMICAL AND BACTERIOLOGICAL EXAMINATION OF SOURCE 
Bacteriological examination of the water from sources should be done twice in pre monsoon period (April & July) and 
twice  in  post  monsoon  period  (October  &  January)  every  year.  Same  way  chemical  examination  of  the  water  from 
sources  shall  be  done  once  in  pre  monsoon  period  and  once  in  post  monsoon  period  every  year.  A  tap  shall  be 

  272 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
provided on the rising main of the source well so samples of water can be collected regularly. 
CONSUMER GRIEVANCES REDRESSAL PLAN 
The  Water  Supply  Scheme  is  maintained  by  authority.  Following  mechanism  for  complaint  communication  and 
redressal should be setup as follows, 
Complaint Communication 
A  complaint  cell  should  be  created  in  the  authority  office  equipped  with  necessary  soft  &  hard  skills  duly  giving 
adequate  publicity  about  the  nature  of  complaint  can  be  made  and  also  the  details  such  as  telephone  number/ 
concern employee etc. of the complaint cell. 
Immediately after receipt of complaint, a compliant number will be assigned and informed to the complainant, if the 
complaint is received by phone. 
Redressal System 
Complaint received should be examined and determined by authority is within an hour of receipt of compliant. 
The authority Complaint Cell will create necessary files/ documents in register the name and address of complainant, 
mode of receipt of complaint, assigning of complaint number, relative person who is attending the complaint, etc. 
The respective person should take action within two days and report to the complaint cell. 
The complaint cell may inform the final action taken, to the complainant immediately after receipt of details received 
from the concerned person. 
The authority would review the status of complaints received every week. 
Remedial Measures for Improving Efficiencies 
Besides  according  high  priority  to  maintenance  and  preventive  measures,  as  part  of  an  effective  O&M  schedule, 
following  measures  like  metering,  leakage  reduction,  tariff  systems,  water‐saving  devices,  regulations,  reuse  and 
cultivation of appropriate plant species, and information and education should have implemented for the purpose as 
under: 
 Metering:  
Metering recommendations both at source level and user level. Metering at source level involves measuring the water 
flows impounded, conveyed and distributed. Metering at user level is to measure each user’s consumption periodically 
in order to charge for the service. The metering would have an influence on domestic water use, with reductions of up 
to  25%  in  areas  that  previously  had  no  metering.  A  strategy  for  the  installation  of  meters  at  all  user  level  is  to  be 
identified and implemented. 
 Leakage Control:  
Leakage constitutes a major part of losses in drinking water systems: leaks in purification plants, distribution networks 
and  home  outlets  leading  to  wrong  estimates,  unauthorized  outlets  and  unrecorded  volumes.  Leaks  in  the  supply 
network may be visible or concealed; they first rise up through the soil or pavement, the latter are not visible and flow 
into the drainage system  or aquifer.  Leakage reduction through detection and repairs can save  lot of  water.  Studies 
carried out by Ministry of Urban Development suggest that proper maintenance by keeping valves clean and repairing 
in time can increase the carrying capacity of pipes considerably and wastage could be brought down to 12 percent to 
15 percent of the supply. Severe penalties may be levied on those found responsible for leakage and wastage of water. 
 Water conservation measures:  
A paradigm shift is required to promote a conservation ethics in the society. Wherever feasible, artificial recharge of 
ground  water  and  rainwater  harvesting  has  to  be  encouraged.  Rainwater  may  be  charged  into  the  groundwater 
aquifers  through  any  suitable  structures  like  dug  wells,  bore  wells,  recharge  trenches  and  recharge  pits.  Various 
recharge  structures  are  possible;  some  of  which  promote  the  percolation  of  water  through  soil  strata  at  shallower 
depth (recharge trenches, permeable pavements) whereas others conduct water to greater depths from where it joins 
the ground water (e.g. recharge wells). At many locations existing structures like wells, pits and tanks can be modified 
as recharge structures, eliminating the need to construct any structures afresh. Instead of constantly looking for new 
and distant sources of water supply, the local bodies should lay emphasis on water harvesting. The rooftops of various 
buildings  could  be  used  wherever  possible  as  hard  catchments  of  rainwater  for  use  after  its  treatment  as  also  for 
ground  water  recharge.  The  Ministry  of  Urban  Development  had  already  forwarded  the  guidelines  on  roof  top 
rainwater harvesting and artificial recharge of ground water (prepared by the Central Ground Water Board) to all the 
States  including  the  CPWD  to  implement  rain  water  harvesting  and  artificial  recharge  of  ground  water  in  all  the 

  273 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
government  buildings  to  start  with.  The  Town  and  Country  Planning  Organization  (TCPO)  has  also  prepared  model 
building byelaws incorporating mandatory provision of rainwater harvesting and recycle of wastewater. This has been 
circulated  to  all  the  States  for  preparing  similar  byelaws  by  the  respective  Local  Bodies  (LBs),  so  that  rainwater 
harvesting can be implemented in all the premises having plinth area more than 100 sq. m. Use of treated effluents, in 
place of filtered water for horticulture and gardening, and fitting of waste‐not taps on public places to avoid wastage of 
water should be encouraged. Water‐efficient systems for flushing should be made mandatory. Conservation of water 
should be recurring theme for both users as well as those managing the water supply system. 
 Restricting over‐exploitation:  
Exploitation of ground water resources should be so regulated as not to exceed the recharging possibilities, as also to 
ensure  social  equity.  The  detrimental  environmental  consequences  of  over‐exploitation  of  ground  water  need  to  be 
effectively  prevented  by  the  Central  and  State  Governments.  Over  exploitation  of  ground  water  should  be  avoided 
especially near the coast to prevent ingress of seawater into sweet water aquifers. 
Public Awareness and Participation 
Mass campaign should be started through all available media and by the utility management itself setting an example 
for conservation. All urban dwellers should be made aware of the source from which water is being brought to the city 
and from which additional water will have to be brought in future. They should be aware of the costs involved, not only 
in financial terms, but also the costs that other communities have to incur in terms of opportunity lost by not using the 
water.  Public  awareness  needs  to  be  created  for  reducing  water  consumption.  Women's  participation  is  particularly 
important and needs to be encouraged to the maximum as they are the major users and have to fetch water from a 
distance if the local system does not work. Congenial environment has to be created for motivating people, community 
and local governments to come forward and take up operation, maintenance and management of the system. 
Water Saving Techniques 
 Plumbing: Low‐flow plumbing fixtures and retrofit programs are permanent, onetime conservation measures 
that can be implemented automatically with little or no additional cost over their lifetimes. In some cases, they 
can even save the resident money over the long term. 
 Toilets:  Residential  demands  account  for  about  three‐fourths  of  the  total  urban  water  demand.  Indoor  use 
accounts  for  roughly  60  percent  of  all  residential  use,  and  of  this,  toilets  use  nearly  40  percent.  Traditional 
toilets use between 16 and 20 liters per flush, which means an average consumption of 80‐100 liters daily per 
inhabitant;  water‐efficient  toilets  using  only  6  liters  per  flush  can  reduce  that  figure  to  30  liters  a  day  per 
inhabitant. In new construction and building rehabilitation or remodeling there is a great potential to reduce 
water consumption by installing low flush toilets. Since low‐flush toilets use less water, they also reduce the 
volume of wastewater produced. 
 Showers: Showers account for about 20 percent of total indoor water use. By replacing standard 20 liter‐per‐
minute  showerheads  with  10  liter‐per‐minute  showerheads  half  of  the  water  can  be  saved.  This  can  be 
accomplished by using new shower‐head designs or flow reducers. 
 Indoor  leak  detection:  A  great  deal  of  water  is  lost  in  homes  through  leaks  in  pipes,  plumbing  fixtures  and 
toilets. The real solution is the manufacture of leak proof fittings. 
REDUCTION IN NON REVENUE WATER (NRW) 
Reduction in NRW to acceptable levels is vital for the financial sustainability of the water utility. NRW can be reduced 
through  appropriate  technical  and  managerial  actions,  and  therefore  monitoring  NRW  can  trigger  such  corrective 
measures.  Reduction  of  real  losses  can  be  used  to  meet  currently  unsatisfied  demand  or  to  defer  future  capital 
expenditures to provide additional supply capacity. Reduction of NRW is desirable not just from a financial stand point, 
but also from economic and environmental benefits. 
NRW is also influenced by factors outside the control of the water utility such  as ‐ topography of the village, age of 
network,  length  of  network  per  connection  and  water  use  per  capita.  It  is  therefore,  recommended  that  the  utility 
should implement rehabilitation plan of distribution network & comprehensive leak control program through private 
agencies  to  reduce  nonrevenue  water  and  improve  metering,  reading,  billing,  &  recovery  system.  The  reduction  of 
NRW  /  UFW  can  be  checked  by  properly  designing  the  distribution  system  with  installation  of  sluice  valves  for  its 
careful  and  timely  operation.  The  possibility  of  NRW  has  been  marked  from  the  house  connections.  Hence  all  the 
house connections shall be metered and properly checked and regulated. 

  274 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
 
OPERATING RECOMMENDATIONS 
Important points as follows shall be observed while operating the pumps. 
(a) Dry running of the pumps should be avoided. 
(b) Centrifugal pumps have to be primed before starting. 
(c)  Pumps  should  be  operated  only  within  the  recommended  range  on  the  head  ‐  discharge  characteristics  of  the 
pump. 
 If pump is operated at point away from duty point, the pump efficiency normally reduces. 
 Operation  near  the  shut  off  should  be  avoided,  as  the  operation  near  the  shut  off  causes  substantial 
recirculation within the pump, resulting in overheating of water in the casing and consequently, in overheating 
of the pump. 
(d) Voltage during operation of pump‐motor set should be within + 10% of rated voltage. Similarly, current should be 
below the rated current as per name plate on the motor. 
(e)  Whether  the  delivery  valve  should  be  opened  or  closed  at  the  time  of  starting  should  be  decided  by  examining 
shape of the power‐discharge characteristic of the pump. Pump of low and medium specific speeds draw lesser power 
at  shut  off  head  and  power  required  increases  from  shut  off  to  normal  operating  point.  Hence  in  order  to  reduce 
starting load on motor, a pump of low or medium specific speed is started against closed delivery valve. Normally the 
pumps used in water supply schemes are of low and medium specific speeds. Hence, such pumps need to be started 
against closed delivery valve. The pumps of high specific speed draw more power at shut off. Such pumps should be 
started with the delivery valve open. 
(f)  The  delivery  valve  should  be  operated  gradually  to  avoid  sudden  change  in  flow  velocity  which  can  cause  water 
hammer pressures. It is also necessary to control opening of delivery valve during pipeline ‐ filling period so that the 
head on the pump is within its operating range to avoid operation on low head and consequent overloading. This is 
particularly  important  during  charging  of  the  pumping  main  initially  or  after  shutdown.  As  head  increases  the  valve 
shall be gradually opened. 
(g) When the pumps are to be operated in parallel, the pumps should be started and stopped with a time lag between 
two pumps to restrict change of flow velocity to minimum and to restrict the dip in voltage in incoming feeder. The 
time lag should be adequate to allow stabilizing the head on the pump, as indicated by a pressure gauge. 
(h) When the pumps are to be operated in series, they should be started and stopped sequentially, but with minimum 
time lag. Any pump, next in sequence should be started immediately after the delivery valve of the previous pump is 
even partly opened. Due care should be taken to keep the air vent of the pump next in sequence open, before starting 
that pump. 
(i) The stuffing box should let a drip of leakage to ensure that no air is passing into the pump and that the packing is 
getting  adequate  water  for  cooling  and  lubrication.  When  the  stuffing  box  is  grease  sealed,  adequate  refill  of  the 
grease should be maintained.  
(j) The running of the duty pumps and the standby should be scheduled so that no pump remains idle for long period 
and all  pumps  are  in ready‐to run condition.  Similarly,  unequal  running  should be  ensured so  that all  pumps  do  not 
wear equally and become due for overhaul simultaneously. 
(k) If any undue vibration or noise is noticed, the pump should be stopped immediately and cause for vibration or noise 
be checked and rectified. 
(l)  Bypass  valves  of  all  reflux  valve,  sluice  valve  and  butterfly  valve  shall  be  kept  in  closed  position  during  normal 
operation of the pumps. 
(m) Frequent starting and stopping should be avoided as each start causes overloading of motor, starter, contactor and 
contacts. Though overloading lasts for a few seconds, it reduces life of the equipment. 
Following points should be checked before starting the pump: 
1. Power is available in all 3 phases. 
2. Trip circuit for relays is in healthy state. 
3. Check  voltage  in  all  3  phases.  The  voltage  in  all  phases  should  be  almost  same  and  within  +  10%  of  rated 
voltage, as per permissible voltage variation. 
4. Check functioning of lubrication system specifically for oil lubricated and clear water lubricated VT pumps and 
oil lubricated bearings. Check stuffing box to ensure that it is packed properly. 
5. Check and ensure that the pump is free to rotate. 

  275 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
6. Check over current setting if the pump is not operated for a week or longer period. 
7. Before starting it shall be ensured that the water level in the sump/intake is above low water level and inflow 
from the source or preceding pumping station is adequate. 
It is also noted that there is lack of maintenance in the system; no preventive measures are applied in daily practice. 
Lack of preventive and timely maintenance or poor maintenance can cause undue wear and tear of fast moving parts, 
and  premature  failure  of  the  equipment.  Such  premature  failure  or  breakdown  causes  immense  hardship  to  the 
consumers and staff, and avoidable increase in repair cost. The shortcomings in maintenance can also result in increase 
in  hydraulic  and  power  losses  and  low  efficiency.  Inefficient  running  of  the  pump  increases  burden  of  power  cost. 
Importance of preventive maintenance, therefore, need not be overstressed. Appropriate maintenance schedule and 
procedure  need  to  be  prescribed  for  all  electrical  and  mechanical  equipment  based  on  manufacturers’ 
recommendations, characteristics of the equipment, site and environment conditions i.e. temperature, humidity, dust 
condition, etc. The maintenance schedules also need to be reviewed and revised in the light of experience and analysis 
of failures and breakdown at the pumping station. The preventive maintenance schedule shall detail the maintenance 
to  be  carried  out  at  regular  intervals  i.e.  daily,  monthly,  quarterly,  half  yearly,  annually  etc.  or  operation  hours.  The 
schedule  shall  also  include  inspections  and  tests  to  be  performed  at  appropriate  interval  or  periodicity.  General 
guidelines  for  maintenance  schedules  for  pumps  and  associated  electrical  and  mechanical  equipment  are  enlisted 
below.  The  guidelines  should  not  be  considered  as  total,  full‐fledged  and  comprehensive  as  characteristics  of 
equipment  and  site  conditions  differ  from  place  to  place.  For  example,  in  dust  laden  environment  or  places  where 
occurrence of storms are frequent, blowing of dust in motor, renewal of oil and grease in bearing shall have to be done 
at lesser intervals than specified in general guideline. 
DAILY MAINTENANCE 
 Clean the pump, motor and other accessories. 
 Check coupling bushes/rubber spider. 
 Check stuffing box, gland etc. 
ROUTINE OBSERVATIONS OF IRREGULARITIES 
The pump operator should be watchful and should take appropriate action on any irregularity noticed in the operation 
of the pumps. Particular attention should be paid to following irregularities. 
1. Changes in sound of running pump and motor. 
2. Abrupt changes in bearing temperature. 
3. Oil leakage from bearings. 
4. Leakage from stuffing box or mechanical seal. 
5. Changes in voltage. 
6. Changes in current. 
7. Changes in vacuum gauge and pressure gauge readings. 
8. Sparks or leakage current in motor, starter, switch‐gears, cable etc. 
9. Overheating of motor, starter, switch gear, cable etc. 
10. Record of operations and observations 
11. A log book should be maintained to record the hourly observations, which should cover the following items. 
12. Timings when the pumps are started operated and stopped during 24 hours. 
13. Voltage in all three phases. 
14. Current drawn by each pump‐motor set and total current drawn at the installation. 
15. Frequency. 
16. Readings of vacuum and pressure gauges. 
17. Motor winding temperature. 
18. Bearing temperature for pump and motor. 
19. Water level in intake/sump. 
20. Flow meter reading. 
21. Daily PF over 24 hour’s duration. 
22. Any specific problem or event in the pumping installation or pumping system e.g. burst in pipeline, tripping or 
fault, power failure. 
 

  276 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
OVERHAUL A PUMP 
Overhauling of pump is expected after specified period of operation to increase the life of pump. It is difficult to specify 
the  periodicity  or  interval  for  overhaul  in  the  form  of  period  of  service  in  months/years  or  operation  hours,  as 
deterioration of pump depends on nature of service, type of installation i.e. wet pit or dry pit, quality of water handled, 
quality of material of construction, maintenance, experience with particular make & type of pump etc. 
However generally, following operational hours may be taken as broad guidelines for overhauling. 
 Submersible pump – 5000 – 6000 hours. 
 Vertical turbine pumps – 12000 hours. 
 Centrifugal pump – 15000 hours. 
TOOLS AND TESTING EQUIPMENT’S 
The pumping installation should be equipped with all necessary tools, testing instruments and special tools required 
for  repairs  and  testing.  Their  quantity  and  special  tools  depend  on  size  and  importance  of  installation.  Generally 
following tools and testing instruments shall be provided. 
Tools: ‐ 
1. Double ended spanner set and ring spanner set. 
2. Box spanner set. 
3. Hammers (of various sizes and functions). 
4. Screw driver set. 
5. Chisel. 
6. Nose pliers, cutting pliers. 
7. Flies of various sizes and smooth/rough surfaces. 
8. Adjustable spanner. 
9. Pipe wrenches. 
10. Bearing puller. 
11. Torque wrench. 
12. Clamps for column pipes, tube and line shaft. 
13. Specials tools such as grinder, blower, drilling machine. 
14. Tap and die set. 
15. Bench vice. 
16. Crimpling tool. 
17. Heating stove for heating sleeves. 
18. Test instruments. 
19. Insulation tester. 
20. Tongue tester. 
21. AVO meter. 
22. Test lamp. 
23. Earth resistance tester. 
24. Wattmeter, CT and PT. 
25. Dial gauge, tachometer. 
26. Safety in Pump House. 
Following safety precautions should be observed while working in a pump house. 
1. No electric live part shall be kept exposed. Particular care should be taken not to keep the motor terminals, 
starter door, panel door etc. in open condition. 
2. Guard for pump – motor coupling and for extended shaft shall be provided. 
3. Top cover of the VHS (vertical hollow shaft) motor shall not be unnecessarily kept in dismantled condition. 
4. Helmet, gumboots, hand gloves, torch and emergency lamp etc. shall be provided to the workers. 
5. Shock proof rubber matting shall be kept in front of panel and starters. 
6. Discharging devices shall also be provided to work safely on HT side of transformer. 
7. Firefighting  equipment  suitable  for  electrical  fire  shall  be  provided.  The  fire  extinguisher  shall  be  thoroughly 
checked and recharged once in a year. 
8. Damaged wooden flooring, damaged grating etc. shall be repaired on priority. 

  277 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
9. Safety railing shall be provided above all openings, unwalled edges of flooring and all such places vulnerable 
for falling or slipping of staff. 
10. First aid box shall be kept at visible and accessible place. The first aid box shall be checked once in a month and 
all used items shall be replenished. 
11. Staff shall be trained in the following aspects to enhance safety awareness and skills to handle safety aspects. 
12. Firefighting. 
13. Safety procedures and practices in electrical work. 
14. First aid (general). 
15. First aid for electric shock. 

  278 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

COST ABSTRACT

  279 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
Construction of Patwadh group of villages Water Supply Scheme, District‐ Sonbhadra 
(Based on Surface Water) and relevant works including Commissioning and Operation & 
Maintenance for 10 Years 
 
COST ABSTRACT OF PROJECT 
 
1. Name of State:            UTTAR PRADESH 
2.  Name of District          SONBHADRA 
        3.  Name of Programme          State Water And Sanitation Mission 
        4.  Name of Scheme          PATWADH GOV 
        5.  No. of Villages            663 Nos. 
        6. Zone‐wise population at different Stage   
  Census Year 2011  Initial Stage year 2023  Middle Stage year 2038  Ultimate Stage year 2053 
Total Population  570515  715560  931930  1211660 

7. Zone Wise Comparision of RCC Over Head Service Reservoir 
As Per BOQ  As Per Design 
OHSR‐1 ‐ 850 KL, 18 m staging  150KL,Staging‐18m‐1Nos 
OHSR‐1A 300 KL, 21 m staging  150KL,Staging‐22m‐1Nos 
OHSR‐1B 350 KL, 19 m staging  175KL,Staging‐16m‐1Nos 
OHSR‐2 1050 KL, 18 m staging  200KL,Staging‐14m‐1Nos 
OHSR‐2A 700 KL, 22 m staging  200KL,Staging‐18m‐1Nos 
OHSR‐3 1000 KL, 16 m staging  250KL,Staging‐10m‐2Nos 
OHSR‐3A 500 KL, 10 m staging  250KL,Staging‐17m‐2Nos 
OHSR‐3B 900 KL, 20 m staging  250KL,Staging‐19m‐2Nos 
OHSR‐4 800 KL, 16 m staging  250KL,Staging‐22m‐1Nos 
OHSR‐4A 600 KL, 18 m staging  300KL,Staging‐10m‐1Nos 
OHSR‐5 800 KL, 18 m staging  300KL,Staging‐13m‐1Nos 
OHSR‐5A 1000 KL, 18 m staging  300KL,Staging‐15m‐1Nos 
OHSR‐5B 700 KL, 18 m staging  300KL,Staging‐17m‐1Nos 
OHSR‐6 750 KL, 22 m staging  300KL,Staging‐19m‐1Nos 
OHSR‐6A 600 KL, 18 m staging  300KL,Staging‐20m‐1Nos 
OHSR‐6B 950 KL, 22 m staging  300KL,Staging‐21m‐1Nos 
OHSR‐7 1250 KL, 18 m staging  350KL,Staging‐10m‐1Nos 
OHSR‐7A 600 KL, 20 m staging  350KL,Staging‐15m‐1Nos 
OHSR‐7B 750 KL, 18 m staging  350KL,Staging‐17m‐1Nos 
OHSR‐8 450 KL, 17 m staging  350KL,Staging‐20m‐1Nos 
OHSR‐8A 1050 KL, 18 m staging  350KL,Staging‐22m‐2Nos 
OHSR‐8B 750 KL, 18 m staging  400KL,Staging‐14m‐1Nos 
OHSR‐9 1000 KL, 18 m staging  400KL,Staging‐15m‐1Nos 
OHSR‐9A 1450 KL, 20 m staging  400KL,Staging‐16m‐1Nos 
OHSR‐10 700 KL, 12 m staging  400KL,Staging‐18m‐1Nos 
OHSR‐10A 950 KL, 20 m staging  400KL,Staging‐19m‐1Nos 
OHSR‐11 350 KL, 12 m staging  400KL,Staging‐20m‐1Nos 
  280 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
As Per BOQ  As Per Design 
OHSR‐11A 650 KL, 20 m staging  400KL,Staging‐22m‐1Nos 
OHSR‐11B 650 KL, 20 m staging  450KL,Staging‐10m‐1Nos 
OHSR‐12 850 KL, 18 m staging  450KL,Staging‐14m‐1Nos 
OHSR‐12A 1100 KL, 17 m staging  450KL,Staging‐17m‐1Nos 
OHSR‐1 Belcup 500 KL, 24 m staging  450KL,Staging‐18m‐2Nos 
OHSR‐2 Babhaech 550 KL, 18 m staging  450KL,Staging‐19m‐1Nos 
OHSR‐3 Adalganj 850 KL, 24 m staging  450KL,Staging‐20m‐1Nos 
OHSR‐4 Markundi 400 KL, 15 m staging  450KL,Staging‐22m‐3Nos 
OHSR‐5 Rudawali 50 KL, 15 m staging  500KL,Staging‐10m‐1Nos 
OHSR‐6 Patwadh 400 KL, 18 m staging  500KL,Staging‐15m‐1Nos 
OHSR‐7 Patwadh 200 KL, 12 m staging  500KL,Staging‐21m‐2Nos 
   550KL,Staging‐22m‐1Nos 
   600KL,Staging‐20m‐1Nos 
   600KL,Staging‐22m‐1Nos 
   650KL,Staging‐10m‐1Nos 
   650KL,Staging‐14m‐1Nos 
   650KL,Staging‐17m‐1Nos 
   650KL,Staging‐19m‐1Nos 
   800KL,Staging‐19m‐1Nos 
   900KL,Staging‐22m‐1Nos 
   
8. Zone Wise Comparision of Clear Water Reservoir 

As Per BOQ  As Per Design 
CWR at WTP of 9500 KL Capacity  CWR at WTP of 9500 KL Capacity 
GLR‐1 (8500 KL )  GLR‐1 (200 KL ) 
GLR‐2 (8100 KL )  GLR‐2 (100 KL) 
GLR‐4 (7500 KL )  GLR‐3 (4400KL) 
GLR‐5 (2200 KL )  GLR‐4 (4400 KL) 
GLR‐6 (250 KL )  GLR‐5 (4100 KL ) 
GLR‐7 (4100 KL )  GLR‐6 (1000KL) 
GLR‐8 (4100 KL )  GLR‐7 (950 KL ) 
GLR‐9 (1900 KL )  GLR‐8 (600 KL ) 
GLR‐10 (500 KL )  GLR‐9 (200 KL) 
GLR‐11 (800 KL )  GLR‐10 (2200 KL ) 
GLR‐12 (600 KL )  GLR‐11  (400KL) 
GLR‐13 (600 KL )  GLR‐12 (1200KL) 
GLR‐14 (400 KL )  GLR‐13 (250 KL ) 
GLR‐15 (250 KL )  GLR‐14 (250 KL) 
GLR‐2 Adalganj (350 KL )    
GLR‐3 Bhbhaech (200 KL )    
GLR‐4 Rudawali (150 KL )    

  281 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    
 9. Diameter Wise Pipe Comparision  
 
S.No  Type/ Class/ Size of Pipe  Length As Per BOQ  Length As Per Design 
1  50 mm dia GI Pipe  826637  187590 
2  65 mm dia GI Pipe  276206  72552 
3  80 mm dia GI Pipe  209796  28342 
4  100 mm dia DI Pipe Class K‐7  320070  40175 
5  150 mm dia DI pipe Class K‐7  290568  32756 
6  200 mm dia DI pipe Class K‐7  151556  92347 
7  250 mm dia DI pipe Class K‐7  101410  90121 
8  300 mm dia DI pipe Class K‐7  35487  32444 
9  350 mm dia DI pipe Class K‐7  32435  3853 
10  400 mm dia DI pipe Class K‐7  8372  0 
11  150 mm dia DI pipe Class K‐9  27818  34060 
12  200 mm dia DI pipe Class K‐9  72783  63424 
13  250 mm dia DI pipe Class K‐9  35216  75659 
14  300 mm dia DI pipe Class K‐9  41019  41137 
15  350 mm dia DI pipe Class K‐9  5666  10769 
16  400 mm dia DI pipe Class K‐9  19580  43291 
17  600 mm dia DI pipe Class K‐9  27386  25567 
18  800 mm dia DI pipe Class K‐9  16642  16779 
19  900 mm dia DI pipe Class K‐9  4476  231 
20  1000 mm dia DI pipe Class K‐9  18916  21881 
21  1100 mm dia DI pipe Class K‐9  600  0 
22  63 mm dia HDPE PIPE(PE100)‐PN6  2000  1804340 
23  75 mm dia HDPE PIPE(PE100) ‐PN6  1000  154661 
24  90 mm dia HDPE PIPE(PE100)‐PN6  800  144279 
25  110 mm dia HDPE PIPE(PE100)‐PN6  600  136720 
26  140 mm dia HDPE PIPE(PE100)‐PN6  400  163198 
27  160 mm dia HDPE PIPE(PE100)‐PN6  200  103311 
28  200 mm dia HDPE PIPE(PE100)‐PN6  200  101816 
1000mm Dia 8mm thick MS pipe with inside food grade 
29  epoxy coating of 700 micron thickness and outside  3185 
bitumen coating with 406 micron thickness    
1200mm Dia 9 mm thick MS pipe with inside food grade 
30  epoxy coating of 700 micron thickness and outside  700 
bitumen coating with 406 micron thickness    

  282 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

10.Total Cost Variation  

Total Cost as per BOQ  Total Cost as per Design 
Description  % Change 
(Rs)  (Rs) 
CAPEX  7780007464.00  7897774329.00  +1.51% 
OPEX  984000400.00  984000400.00  0 

There is an overall 1.51% increase in cost of the scheme as per above statement and 
enclosed DPR. 

  283 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

Item Rate BOQ (Schedule G) (Revised)


Client: State Water & Sanitation Mission, Lucknow

Name of Work: Construction of Patwdh group of Villages Water


Supply Scheme, District – Sonbhadra (Based on surface Water) and
Relevent works including Commissioning and Operating &
Maintenance for 10 Years.

NIT No: 2180 / W-17 / BID / 2020-21, Dated 06.01.2021.

Contract Agreement No.: 97 / ED /2021-22, Dated 16.06.2021.

  284 | P a g e  
  PATWADH GOV DETAIL PROJECT REPORT    

PRICE SCHEDULE

  285 | P a g e  
Item Rate BoQ (Schedule G) (Revised)
Tender Inviting Authority: State Water & Sanitation Mission, Lucknow
Name of Work: Pipe water supply scheme for Patwadh  Group of Villages in district Sonbhadra with relevant works including Commissioning and Operation & Maintenance for 10 Years.
NIT No: 2180/W‐17/BID/2020‐21  Dated: 06‐01‐2021
Name of Bidder: M/s.NCC LIMITED
 PRICE SCHEDULE As Per Revised BOQ
S.no Item Description Quantity Units Rates (in Rs.) Amount (in Rs.)
1 2 3 4 5 6
BUILD PHASE (PART ‐ A) 
1.00 Construction of Intake well as per site conditions. 
Intake Well ‐ Survey, Site investigation, soil testing, Designing, Planning, Construction and Commissioning of intake well of minimum of 5 m diameter,
including excavation of soil i.e. Kankar mixed morrom/soft/hard rock, PCC for bedding in lean concrete of minimum grade of M‐15, R.C.C. in grade M‐30
or above in raft/ pile foundation, R.C.C. M‐30 in or above grade in walling and top slab, with supply of all type steel bars of approved quality and cement
as approved by the Employer, water inlet (Rose pieces of required size opening) having different intake capacity of water at different level,as per site
investigation, Designing, Planning, construction and commissioning, as per direction of Engineer.

1.01 At Pathwad: Intake Well of minimum internal size of 5 M Dia & 9.1 m Height 1.00 Job                   23,936,250                        23,936,250 


2.00 Construction of Jack well cum pump house as per site conditions. 
Survey, Site investigation, soil testing, Planning, Designing, Construction and Commissioning of Jack well and pump house as detailed below.
For construction of pump house of minimum height of 6 m with required length of RCCfootbridge of minimum  2.5 m clear width or minimum width for 
carriout the pumping main whichever is higher, pump floor level minimum 1 m above HFL, water inlet opening having different intake capacity of water 
at different inlet points, construction of staircase, Pump house, operating Slab, gantry girder on corbel, cement concrete floor with hardener, Circular 
Balcony minimum 1m width, staircase post‐column beams, development of land, approach road etc. arrangement should be made inside pump house 
such that to fix required nos. of VT Pumps , Power Control Panels and starters, instrumentation & SCADA & wireless telemetry (voice & Data), internal 
and external electrifications and adequate LED lighting including excavation of soil i.e. Kankar mixed morrom/soft/hard rock and lean concrete of 
minimum grade of M‐15 and R.C.C. in grade M‐30 or above in raft/ pile foundation, Walling, Intake R.C.C. wall with supply of all type steel bars of 
approved quality and cement as approved by the Employer, cofferdam construction as per site requirement, diversion arrangement of flow of river 
during construction by making bunds across the river supply gunny bags, sand, fixing suitable size of steel girder, dismantling and refixing etc. and also 
supply and fixing of collapsible gate, collapsible door, Aluminium window as per relevant specifications, including of three‐coat whitewashing, internal 
two coat snowcem painting, external painting with apex ultima/equivalent paint, all steelwork must be painted with red oxide paint and two coat of 
anticorrosive paint etc. and internal and external electrification of intake well, supply and fixing of three‐row railing with M.S. Angle posts supply and 
fixing of inlet opening of required capacity, dewatering, including supply of all materials, all labour T&P etc. required for proper completion of works as 
per direction of the Engineer. Cost of VT Pumps , Panels, Scada, Panel Board, pipe manifolds etc. are not covered in this item.

2.01 At Patwadh: Jack Well of minimum internal size of 14 M Dia & 22.09M Height  1.00 Job                 108,096,803                      108,096,803 


2.02 MS Connecting Main with strainer ‐ Survey, Site investigation, Designing, Planning, Construction and Commissioning of MS, connecting main of MS pipe
of suitable diameter, (confirming to the Indian Standard Specification inclusive cost of jointing materials, including third party inspection charges,
including transit insurance, railway freight, unloading from railway wagon, loading in to the truck, transportation to standard store/ site of work,
unloading, stacking etc. including excavation of soil i.e. Kankar mixed morrom/soft/hard rock, providing, lowering, laying & jointing, Hydraulic testing of
MS pipe of proper class & diameter meters, including laying and fixing of precast concrete, (1:3:6) Encasement to pipe ,Providing sluice Valves of
appropriate size and number, including all fitting, chamber for clean plug, Clean plug of proper numbers, Supply, laying & Jointing of strainers as per
design, including refilling,  dewatering, removing surplus material as directed by Engineer‐in‐Charge

2.03 At Patwadh: MS pipe of minium diameter 1600 mm Dia & 85 M Length for intake well & SS  stainer of Apropriate size, 2 Nos.  1.00 Job                   16,976,091                        16,976,091 

Page 1 of 17
 PRICE SCHEDULE As Per Revised BOQ
S.no Item Description Quantity Units Rates (in Rs.) Amount (in Rs.)
1 2 3 4 5 6
3.00 Construction of Water Treatment Plant 
Survey, Investigation, Planning, Design, Construction and Commissioning of WTP as per of capacity as given below. 
For construction of WTP, Admin Building with Command Control Room,  and fire fighting arrangements, first aid arrangements Circular Cascading 
Aerator, Inlet chamber, alum dosing, pre‐sedimentation Tank, Rapid Mix, Vertical Flow Clarifloculator, Rapid Gravity Filter with Back Wash Arrangement, 
Proper Sludge Disposal and Backwash water disposal arrangements to nearest drain/low laying area & Appurtenant Works of the below‐mentioned 
capacity, automated through PLC with outputs to SCADA, walkway in between WTP components with railing, Guard Room, Chemical Store House, 
Gaseous Chlorination Plant, Development of WTP area with adequate plantation, Rainwater harvesting unit. Raw water to be treated and filtered. Lean 
concrete to be used of grade not less than M‐10 and other structures in minimum M‐30 grade of concrete. Cement and steel should be as per approved 
by the Employer/IS code. Collapsible MS steel doors and aluminium windows to be provided including of three‐coat whitewashing, internal two coat 
snowcem painting, external painting with apex ultima/equivalent paint, all steelwork must be painted with red oxide paint and two coat of anticorrosive 
paint etc. and internal and external electrification with adequate LED lights for the compound, including automation, instrumentation & SCADA, wireless 
telemetry (voice & data). Including water testing kits, lab building and essential lab equipment as mentioned no. 40. Including of supply of all materials, 
labour T&P etc. required for proper completion of works as per direction of the Engineer.

3.01 At : Capacity of 120 MLD  1.00 Job                 510,640,000                      510,640,000 


4.00 Clear Water Reservoir 
CLEAR WATER RESERVOIR ‐ Survey, Investigation, Soil Testing, Planning, Designing, Construction, Commissioning of CWR of capacity as detailed below.
The Concrete in a minimum grade of M‐30 and steel to be used as per IS code and approved by Employer. Seismic effects and wind load with earthquake
resistance should be taken into account in the design. CWR should be provided with a ventilator, manhole of adequate size. An aluminium ladder
minimum of 0.45 m wide in manhole should be provided. Ultrasonic water level indicator should be provided along with lighting conductor as per IS
2309. PCC of M‐10 grade to be used in bed blocks. Overflow arrangement with the supply & installation of pressure pipe of the same dia as that of the
inlet, for taking overflow water to a suitable low lying area. Painting of all steel and concrete pipes with 3 coats of approved cement plaster and
anticorrosive paint including all labour, material, T & P etc., all required for proper completion of works as per the direction of the Engineer.
Bidders are advised to take SBC at 12 MT/SQM for construction of CWR. If actual SBC is more than 12MT/SQM, the structure will be designed at 12
MT/SQM. In case less than 12 MT/SQM, as per actual.

4.01 CWR at WTP of 9500 KL Capacity 1.00 Job                   80,818,600                        80,818,600 


4.02 GLR‐1 (200 KL ) 1.00 Job                     4,124,400                           4,124,400 
4.03 GLR‐2 (100 KL) 1.00 Job                     3,338,800                           3,338,800 
4.04 GLR‐3 (4400KL) 1.00 Job                   41,231,234                        41,231,234 
4.05 GLR‐4 (4400 KL) 1.00 Job                   41,231,234                        41,231,234 
4.06 GLR‐5 (4100 KL ) 1.00 Job                   38,494,400                        38,494,400 
4.07 GLR‐6 (1000KL) 1.00 Job                     8,780,865                           8,780,865 
4.08 GLR‐7 (950 KL ) 1.00 Job                     8,549,649                           8,549,649 
4.09 GLR‐8 (600 KL ) 1.00 Job                     6,383,000                           6,383,000 
4.10 GLR‐9 (200 KL) 1.00 Job                     4,124,400                           4,124,400 
4.11 GLR‐10 (2200 KL ) 1.00 Job                   15,495,960                        15,495,960 
4.12 GLR‐11  (400KL) 1.00 Job                     5,401,000                           5,401,000 
4.13 GLR‐12 (1200KL) 1.00 Job                     9,705,731                           9,705,731 
4.14 GLR‐13 (250 KL ) 1.00 Job                     4,419,000                           4,419,000 
4.15 GLR‐14 (250 KL) 1.00 Job                     4,419,000                           4,419,000 
4.16 Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of 12 MT/Sqm for 1 MT/Sqm or part thereof 1.00 MT/Sqm                     1,000,000  Rate Only

Page 2 of 17
 PRICE SCHEDULE As Per Revised BOQ
S.no Item Description Quantity Units Rates (in Rs.) Amount (in Rs.)
1 2 3 4 5 6
5.00 PUMP HOUSE ‐Survey, Investigation, Planning, Designing, Construction, Commissioning of Pump houes of required size to accommodate required nos of 
pumps mentioned item nos. 
For the construction of Pump House above CWR, minimum 4.5 m height is to be kept with suitable arrangements to install and dismantle VT pumps and 
installation of Fire Extinguishers, Power wiring & earthling system, rubber resistance sheets, spares for motors & switchgear, internal & external 
electrifications and adequate LED lighting, brickwork 1:4 (one cement and four sand), plasterwork 1:6 (one cement and six sand). Steel and cement to be 
used as per approved by Engineer‐in charge / IS code. Reinforced Cement Concrete minimum M‐25 to be used including fixing of doors, windows, 
shutters, glass panels with gantry girder arrangement with supply and fixing of suitable sizes of steel girder including snowcem painting two coat over 
one priming coat using approved Colour and shade and whitewashing three coat of ceiling of pump house and painting over new ironwork with one coat 
of primer and two coat of approved paint including cost of all arrangement of staircase, balcony with medium G.I pipe 20 mm size three row railing, 
shuttering, scaffolding and water with supply of all materials, labours T&P etc. required for proper completion of works as per direction of the Engineer.

(Pump House at)
5.01 CWR at WTP of 22m x 14.5m x 5m 1.00 Job                     8,214,430                           8,214,430 
5.02 GLR‐1‐ 6mx 5.5m x 5m 1.00 Job                         850,412                              850,412 
5.03 GLR‐2 ‐ 6m x 4.5m x 5m 1.00 Job                         695,256                              695,256 
5.04 GLR‐3 ‐ 22m x 14.5m x 5m 1.00 Job                     8,214,430                           8,214,430 
5.05 GLR‐4 ‐ 22m x 14.5m x 5m 1.00 Job                     8,214,430                           8,214,430 
5.06 GLR‐5  ‐ 22m x 14.5m x 5m 1.00 Job                     8,214,430                           8,214,430 
5.07 GLR‐6 ‐ 10m x 8m x 5m 1.00 Job                     2,060,236                           2,060,236 
5.08 GLR‐7 ‐ 10m x 8m x 5m 1.00 Job                     2,060,236                           2,060,236 
5.09 GLR‐8 ‐ 8m x 6.5m x 5m 1.00 Job                     1,339,448                           1,339,448 
5.10 GLR‐9 ‐ 6mx 5.5m x 5m 1.00 Job                         850,412                              850,412 
5.11 GLR‐10 ‐ 14m x 8.5m x 5m 1.00 Job                     3,064,822                           3,064,822 
5.12 GLR‐11  ‐ 8m x 6.5m x 5m 1.00 Job                     1,339,448                           1,339,448 
5.13 GLR‐12 ‐ 10m x 8m x 5m 1.00 Job                     2,060,236                           2,060,236 
5.14 GLR‐13 ‐  8m x 6m x 5m 1.00 Job                     1,236,338                           1,236,338 
5.15 GLR‐14 ‐ 8m x 6m x 5m 1.00 Job                     1,236,338                           1,236,338 
6.00 Construction of electric power sub‐station room‐ 
Survey, Investigation, Soil Testing, Planning, Designing, Construction of electric power sub‐station room of required size. Construction of RCC frame
structure room including excavation of soil i.e. Kankar mixed morrom/soft/hard rock, PCC for bedding in lean concrete of minimum grade of M‐15, R.C.C.
in grade M‐25 or above in footing, foundation, plinth beam, column, lintel beam, chajja, roof slab, brick work in CM 1:6 (1 cement & 6 sand) in walling,
Internal plaster 12 mm thick for walls & celling in CM 1:6 (1 cement & 6 Sand), External plaster 20 mm thick in CM 1:4 (1 cement & 4 sand), providing
laying hand cut polished kota stone flooring 25 mm to 30 mm thick on bed of CM 1:6 (1 cement & 6 sand) including cement float, filling jointing with
neat cement slurry, curing polishing and cleaning, providing cable duct of required size, including fixing of rolling shutter, aluminium windows &
ventilator with glass panels as per specifications, providing and applying white washing in two coat to new plaster surface, internal two coat snowcem
painting including priming coat, external painting with apex ultima/equivalent paint including priming, painting over new iron work with one coat of
primer and two coat oil paint of approved make including cost of all arrangement of shuttering, scaffolding including all materials, labours T&P etc. for
proper completion of works as per direction of the Engineer. 

 (Construction of electric power sub‐station room at)
6.01 CWR at WTP of 19 m x 5.5 m x 5.0 m 1.00 Job                     1,876,602                           1,876,602 
6.02 GLR‐1 ‐ 6 m x 2.5 m x 5.0m 1.00 Job                         294,600                              294,600 
6.03 GLR‐2 ‐  6.0 m x 2.5m x 5.0m 1.00 Job                         294,600                              294,600 
6.04 GLR‐3 ‐ 19 m x 5.5m x 5.0m 1.00 Job                     1,876,602                           1,876,602 
6.05 GLR‐4 ‐  19 m x 5.5m x 5.0m 1.00 Job                     1,876,602                           1,876,602 
6.06 GLR‐5 ‐ 19 m x 5.5m x 5.0m 1.00 Job                     1,876,602                           1,876,602 
6.07 GLR‐6 ‐ 7 m x 4.5m x 5.0m 1.00 Job                         586,254                              586,254 

Page 3 of 17
 PRICE SCHEDULE As Per Revised BOQ
S.no Item Description Quantity Units Rates (in Rs.) Amount (in Rs.)
1 2 3 4 5 6
6.08 GLR‐7 ‐ 7 m x 4.5m x 5.0m 1.00 Job                         586,254                              586,254 
6.09 GLR‐8 ‐ 6 m x 2.5m x 5.0m 1.00 Job                         294,600                              294,600 
6.10 GLR‐9 ‐ 6 m x 2.5 m x 5.0m 1.00 Job                         294,600                              294,600 
6.11 GLR‐10 ‐ 10 m x 4.5m x 5.0m 1.00 Job                         824,880                              824,880 
6.12 GLR‐11 ‐ 6 m x 2.5 m x 5.0m 1.00 Job                         294,600                              294,600 
6.13 GLR‐12 ‐ 7 m x 4.5m x 5.0m 1.00 Job                         586,254                              586,254 
6.14  GLR‐13 ‐ 6 m x 2.5 m x 5.0m 1.00 Job                         294,600                              294,600 
6.15 GLR‐14 ‐  6.0 m x 2.5m x 5.0m 1.00 Job                         294,600                              294,600 
7.00 Design, Supply, Erection and Testing of V.T. / HSC pump water‐lubricated to lift the required discharge at required head with sufficient column pipe
including shaft with discharge head and bowl assembly all complete as per IS:2010 along with power control panel, soft starters, control system panels,
voltage stabilizer of required capacity, EM Flow Meters, piping manifolds( Suction and delivery including all specials like bend, Tee,NRV, Sluice valve etc.)
instrumentation & SCADA, wireless telemetry (voice & Data) including all materials, labour, T&P etc. all required for proper completion of works as per
the direction of the Engineer.
7.01 Intake to WTP (69100 LPM, 6(3W+3S) Nos, 212.58 KW, 38.5m Head ) ‐VT 1.00 Set                   31,965,854                        31,965,854 
7.02 MCWR to OHSR‐Kanach (486 LPM, 2(1W+1S) Nos, 9.48 KW, 62m Head ) ‐ VT 1.00 Set                     1,992,478                           1,992,478 
7.03 MCWR to OHSR‐Patwadh, OHSR‐Salkhan , OHSR‐Redia, GLR‐2 & GLR‐1 (6398 LPM, 6(4W+2S)Nos, 38.15KW, 94m Head)‐VT 1.00 Set                     9,936,858                           9,936,858 
7.04 MCWR to GLR‐3 (Markundi) (55935 LPM, 8(5W+3S)Nos, 182.84KW, 68m Head)‐VT 1.00 Set                   35,297,008                        35,297,008 
7.05 GLR‐1 (Bhbhaech) to OHSR‐Bhbhaech (1321 LPM, 2(1W+1S) Nos, 11.91 KW, 33m Head )‐HSC 1.00 Set                     1,732,248                           1,732,248 
7.06 GLR‐1 (Bhbhaech) to OHSR‐Belcupp (1205 LPM, 2(1W+1S) Nos, 18.63 KW, 59m Head )‐HSC 1.00 Set                     1,712,608                           1,712,608 
7.07 GLR‐2 (Rudawali) to OHSR‐Rudawali (377 LPM, 2(1W+1S) Nos, 4.74 KW, 37m Head )‐HSC 1.00 Set                     1,654,670                           1,654,670 
7.08 GLR‐2 (Rudawali) to OHSR‐Markundi (804 LPM, 2(1W+1S) Nos, 16.69KW, 76m Head )‐HSC 1.00 Set                     1,623,246                           1,623,246 
7.09 GLR‐3 (Markundi) to GLR‐4 (Lori) (55935 LPM, 15(10W+5S)Nos, 225.72 KW, 167m Head)‐VT 1.00 Set                   88,794,038                        88,794,038 
7.10 GLR‐4 (Lori) to OHSR‐Zone 5‐3 (1894 LPM, 2(1W+1S)Nos, 12.55KW,25m Head)‐VT 1.00 Set                     2,354,836                           2,354,836 
7.11 GLR‐4 (Lori) to GLR‐5 (Gangur), OHSR‐Zone 12‐3 & OHSR‐Zone 9‐2 (54041 LPM, 3(2W+1S)Nos, 110.24 KW,17m Head)‐VT 1.00 Set                   13,217,478                        13,217,478 
7.12 GLR‐5 (Gangur) to OHSR‐Zone 8D & 5‐2 (2616 LPM, 2(1W+1S)Nos, 24.47KW,37m Head)‐VT 1.00 Set                     2,071,038                           2,071,038 
7.13 GLR‐5 (Gangur) to GLR‐6 (Kekarahi), OHSR‐Zone 8C & OHSR‐Zone 6C‐3 (14458 LPM, 4(3W+1S)Nos, 54.79KW,45m Head)‐VT 1.00 Set                     6,001,984                           6,001,984 
7.14 GLR‐5 (Gangur) to GLR‐9 (Nipraj), GLR‐10 (Kushara), OHSR‐Zone 8, OHSR‐Zone 12‐1, OHSR‐Zone 12‐2, OHSR‐Zone 5‐1 & OHSR‐Zone 9A‐1 (35447 LPM, 1.00 Set                   17,648,504                        17,648,504 
4(3W+1S)Nos, 164.30 KW,58m Head)‐VT
7.15 GLR‐6 (Kekarahi) to GLR‐7 (Papi) & OHSR‐Zone 6C‐1 (12594 LPM, 5(3W+2S)Nos, 37.88 KW,36m Head)‐HSC 1.00 Set                     6,827,355                           6,827,355 
7.16 GLR‐7 (Papi) to GLR‐8 (Tarauli Raja), OHSR‐Zone 6, OHSR‐Zone 6C, OHSR‐Zone 6C‐2 & OHSR‐Zone 7A‐1 (11904 LPM, 3(2W+1S)Nos, 79.67 KW,53m Head)‐ 1.00 Set                     7,104,279                           7,104,279 
VT
7.17 GLR‐8 (Tarauli Raja) to OHSR‐Zone 6A‐1 (1033 LPM, 2(1W+1S)Nos, 10.45KW,37m Head)‐HSC 1.00 Set                     1,800,006                           1,800,006 
7.18 GLR‐8 (Tarauli Raja) to OHSR‐Zone 6A & 6B, OHSR‐Zone 7B & 6A‐2, OHSR‐Zone 6A‐3 & OHSR‐Zone 8B (6526 LPM, 3(2W+1S)Nos, 48.78 KW,59m Head)‐ 1.00 Set                     4,501,488                           4,501,488 
HSC
7.19 GLR‐9 (Nipraj) to OHSR‐Zone 9‐1 (1333 LPM, 3(2W+1S)Nos, 15.25KW,81m Head)‐HSC 1.00 Set                     2,568,912                           2,568,912 
7.20 GLR‐9 (Nipraj) to OHSR‐Zone 9‐3 (1321 LPM, 2(1W+1S)Nos, 12.27KW,34m Head)‐HSC 1.00 Set                     2,267,438                           2,267,438 
7.21 GLR‐10 (Kushara) to OHSR‐Zone 10, OHSR‐Zone 9A &OHSR‐Zone 9  (4483 LPM, 3(2W+1S)Nos, 42.27KW,74m Head)‐VT 1.00 Set                     5,120,148                           5,120,148 
7.22 GLR‐10 (Kushara) to GLR‐11(Jogani), GLR‐12(Khutana), OHSR‐Zone 5B‐1, OHSR‐Zone 3B‐1 & OHSR‐Zone 3A‐3 (23163 LPM, 10(6W+4S)Nos,41.04KW,42m 1.00 Set                   13,654,710                        13,654,710 
Head)‐VT
7.23 GLR‐11 (Jogani) to  OHSR‐Zone 3A‐1 & 3A‐2 (1642 LPM, 2(1W+1S)Nos, 14.49KW,33m Head)‐HSC 1.00 Set                     1,654,670                           1,654,670 
7.24 GLR‐11 (Jogani) to  OHSR‐Zone 11B, OHSR‐Zone 4A & OHSR‐Zone 7A‐2 (3421 LPM, 5(3W+2S)Nos, 18.34KW,61m Head)‐HSC 1.00 Set                     4,281,520                           4,281,520 
7.25 GLR‐12 (Khutana) to  OHSR‐Zone 3‐1 (1204 LPM, 2(1W+1S)Nos, 10.21KW,31m Head)‐VT 1.00 Set                     1,992,478                           1,992,478 
7.26 GLR‐12 (Khutana) to  GLR‐13(Beerkhurd), OHSR‐Zone2A, OHSR‐Zone 10A‐1 & OHSR‐Zone 10A‐2 (6643 LPM, 3(2W+1S)Nos, 60.61KW,72m Head)‐VT 1.00 Set                     6,034,167                           6,034,167 

7.27 GLR‐12 (Khutana) to  GLR‐14(Sirasil), OHSR‐Zone 3‐2 & 3‐3, OHSR‐Zone 11A‐1, OHSR‐11 & OHSR‐Zone 1‐1 (6847 LPM, 3(2W+1S)Nos, 54.93KW,63m Head)‐ 1.00 Set                     6,034,167                           6,034,167 


VT
7.28 GLR‐13 (Beerkhurd) to  OHSR‐Zone 11A (678 LPM, 2(1W+1S)Nos, 7.55KW,37m Head)‐VT 1.00 Set                     1,255,978                           1,255,978 

Page 4 of 17
 PRICE SCHEDULE As Per Revised BOQ
S.no Item Description Quantity Units Rates (in Rs.) Amount (in Rs.)
1 2 3 4 5 6
7.29 GLR‐13 (Beerkhurd) to  OHSR‐Zone 2 & OHSR 2‐1 (2096 LPM, 2(1W+1S)Nos, 55.25KW,105m Head)‐VT 1.00 Set                     4,022,778                           4,022,778 
7.30 GLR‐14 (Sirsail) to  OHSR‐Zone 1, OHSR‐Zone 1A & OHSR 1A‐1 (2750 LPM, 3(2W+1S)Nos, 15.15KW,42m Head)‐HSC 1.00 Set                     2,434,869                           2,434,869 
8.00 Survey, Investigation, Planning, Construction, Commissioning, Design, Drawing as per latest I.S. CODE & all design should be vetted by any IIT institute or
govt engineering college. for construction of electric power sub‐station room for 50 KVA above load of minimum size 4 x 3.5 x 3.5 meter or as per
requirement including supplying and fixing transformer (As per following KVA ), transformer foundation, supplying & fixing of Air handling unit, Bus
Coupler with 2 incoming & 1 outgoing ACB, steel tubular pole, ACSR Conductor, Lighting arrestor, Disc and Pin insulation, Stone Metal Spreading,
including cable inside the substation as per requirement along with snowcem painting two coat over one priming coat using approved Colour and shade
and white washing three coat constructed room and painting over new iron work with one coat of primer and two coat of approved paint including cost
of all arrangement of shuttering, scaffolding and water with supply of all materials, labours T&P etc. required for proper completion of works as per
direction of the Engineer.

8.01 Intake well  1250KVA 2.00 Nos                      4,009,506                           8,019,012 


8.02 WTP & MCWR ‐ 2500KVA 2.00 Nos                      5,378,414                        10,756,828 
8.03 GLR‐1 (Bhbhaech) ‐ 160KVA 2.00 Nos                      1,078,236                           2,156,472 
8.04 GLR‐2 (Rudawali) ‐ 100KVA 2.00 Nos                          903,440                           1,806,880 
8.05 GLR‐3 (Markundi) ‐ 3500KVA 2.00 Nos                      6,473,540                        12,947,080 
8.06 GLR‐4 (Lori) ‐ 500KVA 2.00 Nos                      1,858,926                           3,717,852 
8.07 GLR‐5 (Ganguar) ‐ 1250KVA 2.00 Nos                      4,009,506                           8,019,012 
8.08 GLR‐6 (Kekarahi) ‐ 315KVA 2.00 Nos                      1,642,739                           3,285,478 
8.09 GLR‐7 (Papi) ‐ 500KVA 2.00 Nos                      1,858,926                           3,717,852 
8.10 GLR‐8 (Tarauli Raja) ‐ 315KVA 2.00 Nos                      1,642,739                           3,285,478 
8.11 GLR‐9 (Nipraj) ‐ 160KVA 2.00 Nos                      1,078,236                           2,156,472 
8.12 GLR‐10 (Kushara) ‐ 500KVA 2.00 Nos                      1,858,926                           3,717,852 
8.13 GLR‐11 (Jogani) ‐ 160KVA 2.00 Nos                      1,078,236                           2,156,472 
8.14 GLR‐12 (Khutana) ‐ 500KVA 2.00 Nos                      1,858,926                           3,717,852 
8.15 GLR‐13 (Beerkhurd) ‐ 315KVA 2.00 Nos                      1,642,739                           3,285,478 
8.16 GLR‐14 (Sirsail) ‐ 100KVA 2.00 Nos                          903,440                           1,806,880 
9.00 Construction of Over Head Tank of different capacities and staging heights as mentioned below. Supply of all materials labour T&P etc. compete and 
construction of R.C.C.    (M30 Grade) with main components,  Instruments & SCADA, wireless telemetry (voice & Data)  including cost of soil testing.  All 
the components of O.H.T. will be casted in M30 concrete with cement, coarse sand and approved stone grit as per I.S. 11682 and I.S.456.Seismic effects 
and wind load should be taken into consideration as I.S. 1893 for earthquake resistance and I.S. 875 part‐III for wind load on structure (this area is in 
seismic Zone III and high damage risk zone for wind) Proper ventilator at top dome in circular shape along with an R.C.C. cover  and thickness, pillar of 
ventilator should be minimum 50 cm height.The space between top dome and R.C.C. cover should be covered with mosquito net of standard quality 
along with expanded metaled mesh, Ultrasonic type Water level indicator and EM flow meter and residual chlorine sensor/ transmitter. The indicator 
board scale made of 3mm thick M.S. plate should have a clear width of minimum 25cm painted with good Asian paint. It should also consists of 3mm 
brass wire rope minimum 4 smooth pulleys about 8 cm dia with guides,15cm dia copper ball float which shall be completely wate tight suitable pointer of 
brass etc.Lightening conductor as per I.S.S.2309 of its latest amendments of latest electricity rules.It should consist proper elevation rod with 5 or more 

Page 5 of 17
 PRICE SCHEDULE As Per Revised BOQ
S.no Item Description Quantity Units Rates (in Rs.) Amount (in Rs.)
1 2 3 4 5 6
fork points proper down conductors of prescribed metal of propr size prescribed by ISS 2309‐1969 and ISS 3013‐1966C.I. manhole of min 60x60cm size 
made of M.S.channel section with adequate cover made of M.S. sheet of minimum 3mm thickness hinged with manhole with locking aarrangement.This 
manhole should be fix at top dome at proper place.Supply, fixing,jointing of following size of C.I.D/F Pipes with C.I.D/F specials conforming to IS 
8329/2000 as vertical pipes for inlet,outlet,overflow and washout as per latest / relevant I.S. specifications  with all jointing materials for proper 
completion of work including other appurtenant works and exeavation in all types of soil. Including Out let pipes of maximum size of distribution system, 
Inlet pipes of rising main size, Over flow pipes of minimum size of rising main & Wash out pipe 100 mm dia.Supply and Fixing of manually operated 
valves/sliuce valves with hand wheels as per ISS 700/1969 or its latest amendments class “A” working pressure 10 Kg/cm2 Including cartage from its 
store to the site of work, lowering them into trenches, fixing in position and testing etc.complete, Construction of bed blocks in 1:2:4 PCC with 
cement,coarse sand and approved stone grit under each duck foot bend to support the vertical pipes.These bed blocks should supported on the raft not 
on the soil.Construction of sluice valve chamber for above sluice valve/Butterfly valve as per standard design and drawing including supply of all labour 
T&P complete. Construction of washout / overflow chamber as per standard design and drawing.Painting of all concrete surface and steel pipe works 
with three coats of approved cement paint and anticorrosive paints.Supply & laying of 200 mm dia PVC pipe as per I.S.‐4985/2000 or as latest / relevant 
specification including all taxes and insurance etc.F.O.R. destination for disposal of water from overflow and washout chamber to suitable point   outside 
the water works compound including excavation of trenches.laying of pipe line etc.required for proper completion of works as per direction of the 
Engineer.
Bidders are advised to take SBC at 12 MT/SQM for construction of O.H.T. If actual SBC is more than 12MT/SQM, the structure will be designed at 12 
MT/SQM. In case less than 

9.01 OHSR‐ Zone‐Markundi ;1‐1 ; 6 ; 3B‐1 ; 7A‐2 ; 11 ; 12‐3 ‐ 300 KL, 21 m staging  7.00 Job                     6,385,946                        44,701,622 


9.02 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                         330,000  Rate only
9.03 Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of 12 MT/Sqm for 1 MT/Sqm or part thereof 1.00 MT/Sqm                         460,000  Rate only
9.04 OHSR‐ Zone‐1 ; 1A ; 2 ; 6A‐1 ; 12‐1 ; 7A‐1 ‐ 350 KL, 19 m staging  6.00 Job                     7,094,950                        42,569,700 
9.05 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                         370,000  Rate only
9.06 Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of 12 MT/Sqm for 1 MT/Sqm or part thereof 1.00 MT/Sqm                         510,000  Rate only
9.07 OHSR‐ Zone 8D & 5‐2‐ 900 KL, 20 m staging 1.00 Job                   15,151,278                        15,151,278 
9.08 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                         780,000  Rate only
9.09 Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of 12 MT/Sqm for 1 MT/Sqm or part thereof 1.00 MT/Sqm                     1,090,000  Rate only
9.10 OHSR‐ Zone‐6A & 6B ‐ 800 KL, 16 m staging  1.00 Job                   12,401,678                        12,401,678 
9.11 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                         640,000  Rate only
9.12 Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of 12 MT/Sqm for 1 MT/Sqm or part thereof 1.00 MT/Sqm                         890,000  Rate only
9.13 OHSR‐ Zone‐6A‐3 ; 3A‐1 & 3A‐2 ‐ 600 KL, 18 m staging  2.00 Job                   10,184,322                        20,368,644 
9.14 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                         520,000  Rate only
9.15 Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of 12 MT/Sqm for 1 MT/Sqm or part thereof 1.00 MT/Sqm                         730,000  Rate only
9.16 OHSR‐ Zone‐Bhabecha ; 2A ; 6C‐2 ; 7B & 6A‐2 ; 8B ; 9‐1 ; 9‐3 ; 9A ; 10 ;Belcupp ‐  450 KL, 17 m staging  10.00 Job                     8,450,110                        84,501,100 
9.17 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                         440,000  Rate only
9.18 Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of 12 MT/Sqm for 1 MT/Sqm or part thereof 1.00 MT/Sqm                         610,000  Rate only
9.19 OHSR‐ Zone‐5‐3 ; 9 ; 3‐2 & 3‐3 ; 9A‐1 ‐ 650 KL, 20 m staging 4.00 Job                   11,367,632                        45,470,528 
9.20 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                         580,000  Rate only
9.21 Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of 12 MT/Sqm for 1 MT/Sqm or part thereof 1.00 MT/Sqm                         820,000  Rate only
9.22 OHSR‐ Zone‐5B‐1 ;6C ;10A‐2 ; Salkhan ‐ 500 KL, 24 m staging  4.00 Job                     9,987,922                        39,951,688 
9.23 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                         510,000  Rate only
9.24 Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of 12 MT/Sqm for 1 MT/Sqm or part thereof 1.00 MT/Sqm                         720,000  Rate only
9.25 OHSR‐ Zone‐4A  ‐ 550 KL, 18 m staging  1.00 Job                     9,500,850                           9,500,850 
9.26 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                         490,000  Rate only
9.27 Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of 12 MT/Sqm for 1 MT/Sqm or part thereof 1.00 MT/Sqm                         680,000  Rate only

Page 6 of 17
 PRICE SCHEDULE As Per Revised BOQ
S.no Item Description Quantity Units Rates (in Rs.) Amount (in Rs.)
1 2 3 4 5 6
9.28 OHSR‐ Zone‐3‐1 ; 2‐1 ; 3A‐3 ; 8 ; 8C ; 10A‐1 ; 11B  ‐ 400 KL, 15 m staging  7.00 Job                     6,685,456                        46,798,192 
9.29 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                         350,000  Rate only
9.30 Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of 12 MT/Sqm for 1 MT/Sqm or part thereof 1.00 MT/Sqm                         480,000  Rate only
9.31 OHSR‐ Zone‐Redia ; 11A‐1 ‐ 200 KL, 12 m staging 2.00 Job                     3,920,144                           7,840,288 
9.32 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                         200,000  Rate only
9.33 Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of 12 MT/Sqm for 1 MT/Sqm or part thereof 1.00 MT/Sqm                         280,000  Rate only
9.34 OHSR‐  Zone‐Pathwad ;5‐1 ; 11A ; 6C‐1 ; 1A‐1 ; 6C‐3 ; 9‐2 ‐ 250 KL, 12 m staging  7.00 Job                     4,900,180                        34,301,260 
9.35 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                         250,000  Rate only
9.36 Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of 12 MT/Sqm for 1 MT/Sqm or part thereof 1.00 MT/Sqm                         350,000  Rate only
9.37 OHSR‐ Zone‐12‐2 ; Rudawali ‐ 150 KL, 12 m staging   2.00 Job                     2,940,108                           5,880,216 
9.38 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                         150,000  Rate only
9.39 Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of 12 MT/Sqm for 1 MT/Sqm or part thereof 1.00 MT/Sqm                         210,000  Rate only
9.40 OHSR‐  Zone‐Kanach ‐ 175KL, 12 m staging  1.00 Job                     3,430,126                           3,430,126 
9.41 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                         175,000  Rate only
9.42 Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of 12 MT/Sqm for 1 MT/Sqm or part thereof 1.00 MT/Sqm                         245,000  Rate only
10.00 Excavation of earth in ordinary soil (loam, clay or sand) for pipe line and rising main /Feeder Main & Distribution System trenches including lift upto 1.50
m and lead upto 50 m and refilling watering, ramming of the excavated earth into the trench and also disposal of surplus earth upto 50m from the center
of the trenches including supply of all material labour, T&P etc required for proper completion of works as per direction of the Engineer.

10.01 Excavation of Hard Rock 159100 Cum.                             1,277                      203,170,700 


10.02 Excavation of Medium Rock Cum.                                982                      310,066,500 
315750
10.03 Excavation in mixed soil with bajri kankar mooram etc. 432950 Cum.                                216                        93,517,200 
10.04 Excavation in ordinary soil Cum.                                147                      290,838,765 
1978495
11.00 Supply, Laying & Jointing of following sizes (G.I./HDPE / D.I. K‐7 / 9) pipes for rising/feeder main & distribution system conforming to latest/relevant
I.S.4984 / 14151 / 12786 / 13488, 8329/2000 Specifications with all jointing materials such as CIS/S or D.F specials conforming to latest /relevant I.S.
specifications with rubber gasket also, suitable for G.I. / D.I /HDPE pipes, as per IS‐1239 /2000 and IS 8329/2000 or their latest amendment including
F.O.R. destination and all taxes and insurance etc. with loading, unloading and Carting up to site of work, also including specials for these pipes and
lowering them into the trenches and laying true to alignment and gradient and jointing etc. complete (including hydro testing of pipe lines and cutting of
pipes for making up the length but excluding the cost of trenches).all required for proper completion of works as per direction of the Engineer.
(Details of pipes in group given in seperate annex.)

11.01 50 mm dia GI Pipe 187590.00 Rmt                                467                        87,604,530 


11.02 65 mm dia GI Pipe 72552.00 Rmt                                598                        43,386,096 
11.03 80 mm dia GI Pipe 28342.00 Rmt                                735                        20,831,370 
11.04 100 mm dia DI Pipe Class K‐7 40175.00 Rmt                             1,119                        44,955,825 
11.05 150 mm dia DI pipe Class K‐7 32756.00 Rmt                             1,640                        53,719,840 
11.06 200 mm dia DI pipe Class K‐7 92347.00 Rmt                             1,890                      174,535,830 
11.07 250 mm dia DI pipe Class K‐7 90121.00 Rmt                             2,475                      223,049,475 
11.08 300 mm dia DI pipe Class K‐7 32444.00 Rmt                             3,118                      101,160,392 
11.09 350 mm dia DI pipe Class K‐7 3853.00 Rmt                             3,879                        14,945,787 
11.11 150 mm dia DI pipe Class K‐9 34060.00 Rmt                             1,964                        66,893,840 
11.12 200 mm dia DI pipe Class K‐9 63424.00 Rmt                             2,313                      146,699,712 
11.13 250 mm dia DI pipe Class K‐9 75659.00 Rmt                             3,064                      231,819,176 
11.14 300 mm dia DI pipe Class K‐9 41137.00 Rmt                             3,884                      159,776,108 
11.15 350 mm dia DI pipe Class K‐9 10769.00 Rmt                             4,812                        51,820,428 
11.16 400 mm dia DI pipe Class K‐9 43291.00 Rmt                             5,612                      242,949,092 

Page 7 of 17
 PRICE SCHEDULE As Per Revised BOQ
S.no Item Description Quantity Units Rates (in Rs.) Amount (in Rs.)
1 2 3 4 5 6
11.17 600 mm dia DI pipe Class K‐9 25567.00 Rmt                           10,085                      257,843,195 
11.18 800 mm dia DI pipe Class K‐9 16779.00 Rmt                           15,810                      265,275,990 
11.19 900 mm dia DI pipe Class K‐9 231.00 Rmt                           19,100                           4,412,100 
11.20 1000 mm dia DI pipe Class K‐9 21881.00 Rmt                           22,714                      497,005,034 
11.22 63 mm dia HDPE PIPE(PE100) ‐ 6KG/CM2 1804340.00 Rmt                                246                      443,867,640 
11.23 75 mm dia HDPE PIPE(PE100) ‐ 6KG/CM2 154661.00 Rmt                                344                        53,203,384 
11.24 90 mm dia HDPE PIPE(PE100) ‐ 6KG/CM2 144279.00 Rmt                                452                        65,214,108 
11.25 110 mm dia HDPE PIPE(PE100) ‐ 6KG/CM2 136720.00 Rmt                                648                        88,594,560 
11.26 140 mm dia HDPE PIPE(PE100) ‐ 6KG/CM2 163198.00 Rmt                             1,080                      176,253,840 
11.27 160 mm dia HDPE PIPE(PE100) ‐ 6KG/CM2 103311.00 Rmt                             1,178                      121,700,358 
11.28 200 mm dia HDPE PIPE(PE100) ‐ 6KG/CM2 101816.00 Rmt                             1,694                      172,476,304 

MS Pipe as per IS 3589 and MS special 
11.29 1000mm Dia 8mm thick MS pipe with inside food grade epoxy coating of 700 micron thickness and outside bitumen coating with 406 micron thickness 3185.00 Rmt                           32,291                      102,846,835 

11.32 1200mm Dia 9mm thick MS pipe with inside food grade epoxy coating of 700 micron thickness and outside bitumen coating with 406 micron thickness 700.00 Rmt                           34,655                        24,258,500 

12.00 Clearing & grubbing including uprooting of rank vegetation, grass, brush wood, trees and saplings incase of dense forest and removal of rubbish up to a 197775.00 Sqm                                  20                           3,955,500 
distance of 50 m outside the periphery of the area cleared
13.00 Filling in plinth and floors,bedding in trenches and filling in trenches of HDPE pipe at hard/medium rock locations with approved murum from excavated 147228 Cum.                                589                        86,717,205 
materials from foundation 15cm to 20cm layers including watering and compaction complete.(Provisional)
14.00 Supply and carting up to site of work of the following dia D.I. sluice valves, class I, working pressure 10 Kg/cm2 confirming to IS: 780/1969 or its latest
amendments, F.O.R. destination, and lowering them into the already prepared trenches, fixing in position and jointing them with pipelines and testing
etc. complete  and also including supply of jointing materials etc. complete .including all  taxes and insurance, as per instructions of Engineer ‐in ‐charge.

14.01 150 mm dia. 27.00 Nos.                           21,604                              583,308 


14.02 200 mm dia. 30.00 Nos.                           39,280                           1,178,400 
14.03 250 mm dia. 35.00 Nos.                           58,920                           2,062,200 
14.04 300 mm dia. 11.00 Nos.                           68,740                              756,140 
14.05 350 mm dia. 5.00 Nos.                         117,005                              585,025 
14.06 400 mm dia. 17.00 Nos.                         164,902                           2,803,334 
14.07 600 mm dia. 12.00 Nos.                         498,856                           5,986,272 
14.08 800mm dia. 3.00 Nos.                         805,240                           2,415,720 
14.09 900 mm dia 1.00 Nos.                     1,310,184                           1,310,184 
14.10 1000 mm dia 12.00 Nos.                     1,473,000                        17,676,000 
Scour Valve
14.11 150 mm dia 41.00 Nos.                           21,604                              885,764 
14.12 200 mm dia 43.00 Nos.                           39,280                           1,689,040 
14.13 300 mm dia 12.00 Nos.                           68,740                              824,880 
14.14 400mm dia 8.00 Nos.                         164,902                           1,319,216 
14.15 500mm dia 1.00 Nos.                         290,415                              290,415 
14.16 600mm dia 8.00 Nos.                         498,856                           3,990,848 

Page 8 of 17
 PRICE SCHEDULE As Per Revised BOQ
S.no Item Description Quantity Units Rates (in Rs.) Amount (in Rs.)
1 2 3 4 5 6
15.00 Pressure Reducing Valve (Distribution System) ‐ Providing and fixing Pressure reducing valves PN‐16 of approved make confirming to relevant ISS with
latest amendments of following diameters and types and conveying to work site, loading, unloading, stacking, and fixing DI valve with tail pieces, etc.
complete with all lead and lifts and as directed by Engineer‐in‐charge.The rate is inclusive of cost of requird numbers of bolt, nuts, rubber packing, MS
flanges MS tail pieces, reducers etc. complete in order to succesfully install with water tightness. Material of construction shall be as follows: Body &
Cover – Ductile Iron EN 1563 (ASTM A 536). Internal parts – Stainless steel & Bronze. Control Trim ‐ Stainless steel 316 Elastomer ‐ EPDM Coating ‐ Fusion
bonded epoxy, WRAS approved.

15.01 50mm dia. 1.00 Nos.                         117,270                              117,270 


15.02 65mm dia. 5.00 Nos.                         122,946                              614,730 
15.03 80mm dia. 5.00 Nos.                         128,740                              643,700 
15.04 100mm dia. 22.00 Nos.                         165,074                           3,631,628 
15.05 150mm dia. 21.00 Nos.                         267,791                           5,623,611 
15.06 200mm dia. 6.00 Nos.                         354,797                           2,128,782 
15.07 250mm dia. 3.00 Nos.                         468,905                           1,406,715 
15.08 300mm dia. 2.00 Nos.                         669,920                           1,339,840 
16.00 Supply and installation of under ground sluice value type fire hydrant consisting of 100 mm dia sluice valve, 100mm dia tail pieces, 100mm dia duck foot
bend and 100 mm dia standard makes iron coupling with cap and etc. complete conforming to latest/relevent I.S.specifications including all taxes and
insurance up to site of work and lowering them into the trenches, fixing in position and jointing them with pipelines and testing etc. complete (including
supply of jointing materials etc. complete as per instructions of Engineer.(100 mm diameter)

16.01 100mm 55.00 Nos.                           40,262                           2,214,410 


17.00 Providing and supplying Kinetic Double Orifice type Air Valves confirming to IS 14845 specifications having small orifice elastic ball resting on a gun metal
orifice nipple, large orifice vulcanite ball seating on moulded seat ring, with built in Kinetic features, isolating sluice valve mounted in horizontal position
and operated by wheel gearing, inlet face and drilled, including insurance,loading, unloading, transporation upto stores in all respect etc complete

17.01 50 mm dia 44.00 Nos.                           22,291                              980,804 


17.02 80 mm dia 87.00 Nos.                           27,496                           2,392,152 
17.03 100 mm dia 31.00 Nos.                           29,460                              913,260 
17.04 150 mm dia 46.00 Nos.                           37,660                           1,732,360 
18.00 Construction of following type chambers as per department type design and drawing including Heavy duty R.C.C. Manhole Cover and all materials,
labour,  T&P etc complete for proper completion of work as per instructions of Engineer. (masonry Type)
Sluice valve chamber (masonry Type)
18.01 Upto 200 mm Dia. 57.00 Nos.                           17,578                           1,001,946 
18.02 SV Chamber for 250mm dia ‐300 mm dia 46.00 Nos.                           37,807                           1,739,122 
18.03 Sluice Valve Chamber for 350‐400 Dia 22.00 Nos.                           47,725                           1,049,950 
18.04 Sluice Valve Chamber  500 ‐ 600mm Dia 12.00 Nos.                           64,714                              776,568 
18.05 Sluice Valve Chamber  700 ‐ 800mm Dia 3.00 Nos.                           73,945                              221,835 
18.06 Sluice Valve Chamber  900 ‐ 1000 mm Dia 13.00 Nos.                           86,514                           1,124,682 
18.07 Sluice valve chamber (surface box Type) 653.00 Nos.                             9,820                           6,412,460 
Air Valve Chamber
18.08  Air Valve Chamber 50mm dia ‐ 80 mm dia 131.00 Nos.                           41,931                           5,492,961 
18.09  Air Valve Chamber 100mm dia ‐ 150 mm dia 77.00 Nos.                           49,787                           3,833,599 
Scour valve chamber
18.10 Scour Valve Chamber 150mm dia ‐ 200 mm dia  84.00 Nos.                           23,077                           1,938,468 
18.11 Scour Valve Chamber 250mm dia ‐ 300mm dia 12.00 Nos.                           49,527                              594,326 
18.12 Scour Valve Chamber 350mm dia ‐ 400mm dia 8.00 Nos.                           62,520                              500,158 
18.13 Scour Valve Chamber 500mm dia ‐ 600mm dia 9.00 Nos.                           84,775                              762,978 

Page 9 of 17
 PRICE SCHEDULE As Per Revised BOQ
S.no Item Description Quantity Units Rates (in Rs.) Amount (in Rs.)
1 2 3 4 5 6
Fire Hydrant chamber
18.14 Fire Hydrant chamber 55.00 Nos.                           24,550                           1,350,250 
PRV Valve Chamber
18.15  Chamber (1 x 1 x 1.2 m) Dia <150mm 54.00 Nos.                           21,408                           1,156,032 
18.16  Chamber (1.2m x 1m x 1.2 m) Dia 200mm‐300mm 11.00 Nos.                           29,460                              324,060 
19.00 Design and construction of Thrust Block made in R.C.C. with cement, coarse sand & 20 mm gauge stone ballast in proportion of 1:1.5:3, for pipe line,
including supply of MS reinforcement wrought to required shape as necessary ,its bending, fixing & binding the same with 0.50 mm thick binding wire in
position & necessary centering & shuttering including curing and supply of all materials, labour, T & P etc. required for proper completion of the work
and as per specifications for RCC work for following pipe diameter as per instructions of Engineer.

19.01  Pipe Dia 150mm 132.00 Nos.                           11,588                           1,529,616 


19.02 Pipe Dia  200mm  233.00 Nos.                           19,051                           4,438,883 
19.03 Pipe Dia  250mm  330.00 Nos.                           21,604                           7,129,320 
19.04 Pipe Dia  300mm  171.00 Nos.                           27,103                           4,634,613 
19.05 Pipe Dia 350mm‐New Item 48.00 Nos.                           30,148                           1,447,104 
19.06 Pipe Dia  400mm  173.00 Nos.                           33,192                           5,742,216 
19.07 Pipe Dia  600mm  102.00 Nos.                           47,136                           4,807,872 
19.08 Pipe Dia  800mm  86.00 Nos.                           63,634                           5,472,524 
19.09 Pipe Dia  900mm  3.00 Nos.                           72,864                              218,592 
19.10 Pipe Dia  1000mm  154.00 Nos.                           82,095                        12,642,630 
20.00 Dismantling of Following type of surfaces including sorting out and stacking of serviceable materials and disposal of unserviceable materials upto a
distance of 50m as per instructions of Engineer
20.01 Bituminous Road 100597.00 sqm                                147                        14,787,759 
20.02 CC Road 2931.00 sqm                                314                              920,334 
20.03 BOE Road 9568.00 sqm                                  79                              755,872 
20.04 Interlocking Road 2574.00 sqm                                142                              365,508 
21.00 Restoration of the following type of road surface with old and new materials including supply of all materials, labour, T&P etc. required for proper
completion of the work as per instructions of Engineer.
21.01 Bituminous Road 100597.00 sqm                             1,375                      138,320,875 
21.02 CC Road 2931.00 sqm                             2,455                           7,195,605 
21.03 BOE Road 9568.00 sqm                                786                           7,520,448 
21.04 Interlocking Road 2574.00 sqm                                982                           2,527,668 
22.00 Construction of single tap pillar type stand post as per type design as per instructions of Engineer 653.00 Nos.                           19,640                        12,824,920 
23.00 Survey, Investigation, Design, Drawing, Planning, Construction as per latest I.S. CODE, for Nala crossing, including excavation in soil mixed with moorum,
shingle, kankar, soft rock, hard rock for foundation, dewatering and diveration of water, PCC M‐15 for bedding, RCC M‐25 for foundation/piles,
pedestral, MS claps of required width and thickness with one coats of anticorrosive paint and over it two coats of oil painting, including all fastening
arrangement nut and bolts, all type steel bars of approved quality and cement as approved by the employer, Mild Steel or iron work, other unforeseen
Items, site clearance,  etc., as per detailed design and drawing or as directed by Engineer‐in‐charge

Nallah Crossing RCC Pier over pile cap and pile
23.01 Up to 65 mm ‐ 100 mm dia 84.00 Mtr.                           39,280                           3,299,520 
23.02 150mm ‐ 200 mm dia 222.00 Mtr.                           44,190                           9,810,180 
23.03 250mm ‐ 300 mm dia 127.00 Mtr.                           46,154                           5,861,558 
23.04 350mm ‐ 400 mm dia 115.00 Mtr.                           47,136                           5,420,640 
23.05 450mm ‐ 500 mm dia 55.00 Mtr.                           48,118                           2,646,490 
23.06 600mm ‐ 700 mm dia 120.00 Mtr.                           54,010                           6,481,200 
Nallah Crossing with RCC Pedestral 

Page 10 of 17
 PRICE SCHEDULE As Per Revised BOQ
S.no Item Description Quantity Units Rates (in Rs.) Amount (in Rs.)
1 2 3 4 5 6
23.07  Size 400 mm X 300 mm X 900 mm 90.00 Nos.                             2,553                              229,770 
23.08 Size 450 mm X 300 mm X 900 mm 111.00 Nos.                             2,750                              305,250 
23.09 Size 500 mm X 300 mm X 900 mm 170.00 Nos.                             2,946                              500,820 
23.10 Size 550 mm X 300 mm X 900 mm 281.00 Nos.                             3,241                              910,721 
23.11 Size 600mm X 300mm X 1000 mm 254.00 Nos.                             3,633                              922,782 
23.12 Size 700mm X 300mm X 1000 mm 617.00 Nos.                             4,615                           2,847,455 
23.13 Size 750mm X 300mm X 1000 mm 29.00 Nos.                             4,910                              142,390 
23.14 Size 900mm X 300m mm X1000 mm 132.00 Nos.                             5,401                              712,932 
23.15 Size 1000mmX300mX1000 mm  98.00 Nos.                             5,990                              587,020 
23.16 Size 1100 mm X 300m X 1000 mm 50.00 Nos.                             6,481                              324,050 
24.00 Road Crossing with open cut ‐ Excavation in foundation of trench of proper size in soil mixed with moorum, Shingle, Kankar, soft rock, hard rock,
including refilling, dressing and ramming earth or sand or bajri, ballast, including providing, supply, carting, lowering, laying and jointing of casing pipe of
RCC NP‐3 with appropriate size, with rubber ring joint, sand filling in gap inside RCC pipe, insertion of distribution pipe into the encasing pipe including
supply of T&P, including concrete of 150 mm thick in with 40mm gauge brick ballast local sand and cement in proportion of 8:4:1, provision for
barricading, labour for traffic diversion etc.  Complete for proper completion of work as per instruction of Engineer.

24.01 50 mm dia. Pipe 1104.00 Mtr.                             1,375                           1,518,000 


24.02 65‐100 mm dia. Pipe 1500.00 Mtr.                             1,669                           2,503,500 
24.03 125‐150 mm dia. Pipe 1600.00 Mtr.                             2,062                           3,299,200 
24.04 200 mm dia. Pipe 1350.00 Mtr.                             2,259                           3,049,650 
24.05 250 mm dia. Pipe 750.00 Mtr.                             3,633                           2,724,750 
24.06 300 mm dia. Pipe 450.00 Mtr.                             4,419                           1,988,550 
24.07 350 mm dia. Pipe 350.00 Mtr.                             4,714                           1,649,900 
24.08 400 mm dia. Pipe 214.00 Mtr.                             5,303                           1,134,842 
24.09 450‐500 mm dia. Pipe 350.00 Mtr.                             6,579                           2,302,650 
24.10 600 mm dia. Pipe 184.00 Mtr.                             7,660                           1,409,440 
24.11 800 mm dia. Pipe 154.00 Mtr.                           10,507                           1,618,078 
24.12 900 mm dia. Pipe 110.00 Mtr.                           11,980                           1,317,800 
25.00 Survey, Investigation, Design, Drawing, Planning, Construction as per latest I.S. CODE, for River crossing, including excavation in soil mixed with moorum,
shingle, kankar, soft rock, hard rock for foundation, dewatering and diveration of water,construction of coffer dam, PCC M‐15 for bedding, RCC M‐30
grade for foundation/raft/piles, RCC M‐30 grade for pedestral & chairs, MS clamps of required width and thickness, including all fastening arrangement
nut and bolts, all type steel bars of approved quality and cement as approved by the employer, Mild Steel or iron work, stuctural steel work in single
stanchions composed of RSJ, channel, etc, with caps, bases, mild steel plates, angles, brackets, cleats, gusset plates, anchor bolts, etc. including cutting,
fabrication, hoisting, erecting, fixing in position, making riveted/ bolted / welded connections and one coats of anticorrosive paint and over it two coats
of oil painting, etc other unforeseen Items, site clearance,  etc. as per detailed design and drawing or as directed by Engineer‐in‐charge

25.01 RCC Pier over pile cap and pile for  dia up to 100mm ‐  200mm 100.00 Mtr.                           73,650                           7,365,000 

Page 11 of 17
 PRICE SCHEDULE As Per Revised BOQ
S.no Item Description Quantity Units Rates (in Rs.) Amount (in Rs.)
1 2 3 4 5 6
26.00 Survey site Investigation Planning , design Drawings as per State Road manual and vetting / checked from State Road Divisional Office and taking NOC for
trenchless crossing of National highway road and Railway track(crossing length 15m to 25m ), Road for of required dia Rising main pipe with casing pipe
as required for proper completion of work also including security money deposited to State Road department and Execution of all work in the present of
State Road staff / Engineers including of supply of required dia MS carrier pipe and required size of MS casing pipe as per drawing and as per (IS:3589 &
made from confining to IS:2062) with 750 Micron PU coating internally and 250 micron anti corrosive bituminous paint externally by trenchless
technology method at an average depth 3.60 mtr from normal ground level up to top of casing pipe including excavation & filling of Pit, Dewatering
arrangement, Supporting system for soil, also including supply and fixing of 2 no Sluice valve ISI Mark, construction of sluice valve chamber etc. all
complete work including supply & fixing specials in carrier pipe over main pipe, as per specification given in the bid documents including supply of all
materials, labour T&P etc. for proper completion of work as per instruction of Engineer.

Road Crossing  
26.01 50 mm 100.00 Mtr.                             7,561                              756,100 
26.02 65 mm 100.00 Mtr.                             7,561                              756,100 
26.03 80mm 61.00 Mtr.                             7,561                              461,221 
26.04 100mm 100.00 Mtr.                             9,427                              942,700 
26.05 125 mm 100.00 Mtr.                           13,944                           1,394,400 
26.06 150mm 100.00 Mtr.                           13,944                           1,394,400 
26.07 200mm 100.00 Mtr.                           16,301                           1,630,100 
26.08 250mm 98.00 Mtr.                           21,899                           2,146,102 
26.09 300mm 100.00 Mtr.                           25,630                           2,563,000 
26.10 450mm 17.00 Mtr.                           47,136                              801,312 
Railway Crossing
26.11 500mm 60.00 Mtr.                           58,920                           3,535,200 
27.00 Making house connection should be done atleast 2 m inside the boundary wall with provision of tap from distribution line to outer wall of house, with 121719.00 Nos.                             2,558                      311,357,202 
supply of 1 m G.I. pipe & average 10.0 mtr. MDP Pipe including specials, Brass ferrule, Saddle clamp etc. of suitable size, T&P etc. including excavation,
laying and jointing for proper completion of work as per instructions of Engineer
28.00 Construction of 1.5 m high and 115mm thick boundary wall with 230 mmx230 mm thick pillar made in Brick masonry in 1 cement and 4 sand mortar, the 11462.00 Rmt                             5,156                        59,098,072 
spacing between two pillar should not be more than 3.0 m c/c and the depth of foundation should not be less than 0.60m, at the site of water works as
per departmental type design and drawing, and, as per specifications given in the bid document including supply of all materials, labour T&P etc.for
proper completion of work as per instructions of Engineer
29.00 Supply and fixing of 3.6 m x 1.50 m MS gate including fabrication and supply of steel and construction of bounary wall pillars of size 1.5mx0.30mx0.30m 61.00 No.                           41,244                           2,515,884 
with ornamental brick work 115mm th. around RCC, as per departmental type design and drawing and as per specifications laid down in the bid
document, including supply of all material, labour,T&P etc.required for proper completion of work as per instructions of Engineer

30.00 Supply and fixing of 1.5m wide MS wicket gate including fabrication and supply of steel and construction of boundary wall pillars etc. as per specifications 61.00 No.                           14,730                              898,530 
laid down in the bid document, including supply of all material, labour,T&P etc.required for proper completion of work as per instructions of Engineer

31.00 Construction of Brick on edge pavement for approach to water works/ ESR, as per departmental type design and drawing and as per specifications laid 20865.00 Sqm.                                737                        15,377,505 
down in the bid document, including supply of all materials , labour, T&P etc.required for proper completion of work as per instructions of Engineer ‐in ‐
charge.
32.00 Construction of semi circular 300 mm dia drain for water works, as per departmental type design and drawing and as per specifications laid down in the 2530.00 Rmt                             1,768                           4,473,040 
bid document, including supply of all materials, labour, T&P etc.required for proper completion of work as per instructions of Engineer

33.00 Earth filling work for proper leveling of water work site, in accordance with the contour map and Grid map of existing site enclosed, including leveling, 55084.00 Cum.                                334                        18,398,056 
dressing, excavation and filling of earth where necessary and also including all labour, materials, T&P etc.required for proper completion of works and
also including carriage of earth from within a distance of about 8 km. from the site of works as per instructions of Engineer (Provisional)

Page 12 of 17
 PRICE SCHEDULE As Per Revised BOQ
S.no Item Description Quantity Units Rates (in Rs.) Amount (in Rs.)
1 2 3 4 5 6
34.00 Available earth filling work for proper leveling of water work site, in accordance with the contour map and Grid map of existing site enclosed, including 316390.00 Cum.                                128                        40,497,920 
leveling, dressing, excavation and filling of earth where necessary and also including all labour, materials, T&P etc.required for proper completion of
works and also including carriage of earth from within a distance of about 8 km. from the site of works as per instructions of Engineer (Provisional)

35.00 Soft landscaping works including providing and planting of decorative plants, ground cover, shrubs in ground by mixing good soil with manure/ sludge, 73445.00 sqm                                255                        18,728,475 
spraying insecticides & pesticides all materials, labour T&P etc. required for completion of the work. including levelling, dressing and filling of earth where 
necessary for develop of water work  site. (Good soil will be paid seperately)
36.00 Guard Room‐Supply of all materials labour T&P etc. compete and construction of Guard Room of 2m x 2.5m x 2.6m ht. at site of RCC CWR  14.00 Nos.                         245,500                           3,437,000 

37.00 SINGLE ROOM STAFF QUARTER‐ construction of staff quarter for pump operator, chaukidar, pump attendent as per departmental type design attached 14.00 Nos.                     1,865,800                        26,121,200 
with tender documents SINGLE ROOM STAFF QUARTER‐ construction of staff quarter for pump operator, chaukidar, pump attendent as per departmental
type design attached with tender documents including excavation in foundation in ordinary soil/ kanker/ morrum/ soft rock/hard rock,PCC 1:4:8 with
cement local sand and 40mm guage ballastFirst class brick work in 1:4 cement and sand mortar, 12 mm thick plaster in 1:6 cement and sand mortar,mild
steel or iron work ,supply and filling of carted earth up to plinth level ,25mm thick 1:2:4 plain cement concrete floor and 45 cm wide apron with 2 cm
guage stone ballast laid in pannels,finished with 3 mm floating coat of neat cement and 75 mm thick base concrete 1:4:8 ,supply and fiximg of 3mm thick
glass strip of 25 mm width in joint ,MS angle iron chaukhat 40x40x5mm size ,40 mm thick ISI flush door shesham wood,window shutter ,HDPE Tank of
500 liter capacity ,galvanized mosquito proof heavy quality iron wire guage 1.50mm mesh over window with wood batten 50x12 mm and snowcem
painting two coat over one priming coat using approved colour and shade and white washing of ceiling of staff quarters and internal wiring of staff
quarter as per direction of EIC,construction of Septic tank sanitary works with fixtures,pipes etc. and all type of plumbing work in kitchen ,bathroom and
W/C, with supply of all materials ,labours , tools and plants etc all complete as per direcdtion of EIC

38.00 DOUBLE ROOM STAFF QUARTER‐ construction of staff quarter for pump operator, chaukidar, pump attendent as per departmental type design attached 4.00 Nos.                     2,455,000                           9,820,000 
with tender documents including excavation in foundation in ordinary soil/ kanker/ morrum/ soft rock/hard rock,PCC 1:4:8 with cement local sand and
40mm guage ballastFirst class brick work in 1:4 cement and sand mortar, 12 mm thick plaster in 1:6 cement and sand mortar,mild steel or iron work
,supply and filling of carted earth up to plinth level ,25mm thick 1:2:4 plain cement concrete floor and 45 cm wide apron with 2 cm guage stone ballast
laid in pannels,finished with 3 mm floating coat of neat cement and 75 mm thick base concrete 1:4:8 ,supply and fiximg of 3mm thick glass strip of 25
mm width in joint ,MS angle iron chaukhat 40x40x5mm size ,40 mm thick ISI flush door shesham wood,window shutter ,HDPE Tank of 500 liter capacity
,galvanized mosquito proof heavy quality iron wire guage 1.50mm mesh over window with wood batten 50x12 mm and snowcem painting two coat over
one priming coat using approved colour and shade and white washing of ceiling of staff quarters and internal wiring of staff quarter as per direction of
EIC,construction of Septic tank sanitary works with fixtures,pipes etc. and all type of plumbing work in kitchen ,bathroom and W/C, with supply of all
materials ,labours , tools and plants etc all complete as per direcdtion of EIC

39.00 Supply and fixing of Electromagnetic Flow Water Meter (with totalizer) for measurement of bulk flow at outlets of every pump stations and inlets of
CWRs/OHTs including construction of RCC/RB chambers of required size and as per instrucions of Engineer Incharge.
39.01 800mm dia 3.00 Nos.                     1,188,220                           3,564,660 
39.02 500mm dia 1.00 Nos.                         451,720                              451,720 
39.03 400mm dia 4.00 Nos.                         351,065                           1,404,260 
39.04 250mm dia 5.00 Nos.                         213,880                           1,069,400 
39.05 200mm dia 2.00 Nos.                         192,472                              384,944 
39.06 150mm dia 34.00 Nos.                         166,351                           5,655,934 
39.07 80mm dia 12.00 Nos.                         112,930                           1,355,160 
40.00 Supply & Fixing of Flow control valve/Diaphragm Valve/Altitude control valve, including construction of RCC/RB chambers of required size and as per
instrucions of Engineer Incharge.
40.01 1000mm dia 3.00 Nos.                     3,039,290                           9,117,870 
40.02 800mm dia 2.00 Nos.                     2,528,650                           5,057,300 

Page 13 of 17
 PRICE SCHEDULE As Per Revised BOQ
S.no Item Description Quantity Units Rates (in Rs.) Amount (in Rs.)
1 2 3 4 5 6
40.03 600mm dia 4.00 Nos.                     1,755,816                           7,023,264 
40.04 400mm dia 6.00 Nos.                         925,044                           5,550,264 
40.05 350mm dia 1.00 Nos.                         536,172                              536,172 
40.06 300mm dia 4.00 Nos.                         470,378                           1,881,512 
40.07 250mm dia 16.00 Nos.                         367,268                           5,876,288 
40.08 200mm dia 13.00 Nos.                         279,870                           3,638,310 
40.09 150mm dia 12.00 Nos.                         235,680                           2,828,160 
41.00 Supply and installation of Pressure Feed Type Chlorinating Dozer of given capacity complete with Rota‐meter, regulating valves, dosing pipe of reputed
make and other related accessories including for manual mixing of bleaching powder for following Zones. for following Zones :

41.01 GLR‐2 (Rudwali) to OHSR Zone‐Rudawli‐8GL 1.00 Nos.                           42,226                                42,226 


41.02 GLR‐2 (Rudwali) to OHSR Zone‐Markundi‐24GL 1.00 Nos.                           49,100                                49,100 
41.03 GLR‐1 (Bhbhaech) to OHSR Zone‐Bhbhaech‐32GL 1.00 Nos.                           49,100                                49,100 
41.04 GLR‐1 (Bhbhaech) to OHSR Zone‐Belcupp‐32GL 1.00 Nos.                           49,100                                49,100 
41.05 GLR‐4 (Lori) to OHSR Zone‐5‐3 ‐56GL 1.00 Nos.                           75,614                                75,614 
41.06 GLR‐4 (Lori) to ZONE‐12‐3‐16GL 1.00 Nos.                           45,172                                45,172 
41.07 GLR‐4 (Lori) to ZONE‐9‐2 ‐16GL 1.00 Nos.                           45,172                                45,172 
41.08 GLR‐5 (Gangur) to OHSR Zone ‐8D & 5‐2 ‐72GL 1.00 Nos.                           93,290                                93,290 
41.09 GLR‐5 (Gangur) to OHSR‐8C ‐24GL 1.00 Nos.                           49,100                                49,100 
41.10 GLR‐5 (Gangur) to OHSR‐6C‐3 ‐16GL 1.00 Nos.                           45,172                                45,172 
41.11 GLR‐5 (Gangur) to OHSR‐8 ‐24GL 1.00 Nos.                           49,100                                49,100 
41.12 GLR‐5 (Gangur) to OHSR‐12‐1 ‐24GL 1.00 Nos.                           49,100                                49,100 
41.13 GLR‐5 (Gangur) to OHSR‐12‐2 ‐8GL 1.00 Nos.                           42,226                                42,226 
41.14 GLR‐5 (Gangur) to OHSR‐5‐1‐16GL 1.00 Nos.                           45,172                                45,172 
41.15 GLR‐5 (Gangur) to OHSR‐9A‐1‐40GL 1.00 Nos.                           57,938                                57,938 
41.16 GLR‐6 (Kekarahi) to OHSR‐6C‐1 ‐16GL 1.00 Nos.                           45,172                                45,172 
41.17 GLR‐7 (Papi) to OHSR‐6 ‐16GL 1.00 Nos.                           45,172                                45,172 
41.18 GLR‐7 (Papi) to OHSR‐6C ‐32GL 1.00 Nos.                           49,100                                49,100 
41.19 GLR‐7 (Papi) to OHSR‐6C‐2 ‐24GL 1.00 Nos.                           49,100                                49,100 
41.20 GLR‐7 (Papi) to OHSR‐7A‐1‐16GL 1.00 Nos.                           45,172                                45,172 
41.21  GLR‐8 (Atarauli Raja) to OHSR 6A‐1‐32GL 1.00 Nos.                           49,100                                49,100 
41.22  GLR‐8 (Atarauli Raja) to OHSR‐6A & 6B , OHSR‐7B & 6A‐2 , OHSR‐6A‐3  & OHSR‐8B ‐176GL 1.00 Nos.                         208,184                              208,184 
41.23 GLR‐9 (Nipraj)  to OHSR‐9‐1 ‐32GL 1.00 Nos.                           49,100                                49,100 
41.24 GLR‐9 (Nipraj) to  OHSR‐9‐3 ‐32GL 1.00 Nos.                           49,100                                49,100 
41.25 GLR‐10 (Kushara) to OHSR‐10, OHSR‐9A & OHSR‐9 ‐120GL 1.00 Nos.                         146,318                              146,318 
41.26 GLR‐10 (Kushara) to OHSR‐5B‐1 ‐32GL 1.00 Nos.                           49,100                                49,100 
41.27 GLR‐10 (Kushara) to OHSR‐3B‐1 ‐16GL 1.00 Nos.                           45,172                                45,172 
41.28 GLR‐10 (Kushara) to OHSR‐3A‐3 ‐24GL 1.00 Nos.                           49,100                                49,100 
41.29 GLR‐11 (Jogani) to OHSR ‐3A‐1 & 3A‐2 ‐48GL 1.00 Nos.                           66,776                                66,776 
41.30 GLR‐11 (Jogani) to OHSR‐11B, OHSR‐4A & OHSR‐7A‐2 ‐96GL 1.00 Nos.                         119,804                              119,804 
41.31 GLR‐12  (Khutaha) to OHSR‐3‐1 ‐32GL 1.00 Nos.                           49,100                                49,100 
41.32 GLR‐12  (Khutaha) to OHSR‐2A ‐24GL 1.00 Nos.                           49,100                                49,100 
41.33 GLR‐12  (Khutaha) to OHSR‐10A‐1 ‐24GL 1.00 Nos.                           49,100                                49,100 
41.34 GLR‐12  (Khutaha) to OHSR‐10A‐2 ‐32GL 1.00 Nos.                           49,100                                49,100 
41.35 GLR‐12  (Khutana) to OHSR‐3‐2 & 3‐3 ‐40GL 1.00 Nos.                           57,938                                57,938 
41.36 GLR‐12  (Khutana) to OHSR‐11A‐1 ‐16GL 1.00 Nos.                           45,172                                45,172 
41.37 GLR‐12  (Khutana) to OHSR‐11 ‐16GL 1.00 Nos.                           45,172                                45,172 

Page 14 of 17
 PRICE SCHEDULE As Per Revised BOQ
S.no Item Description Quantity Units Rates (in Rs.) Amount (in Rs.)
1 2 3 4 5 6
41.38 GLR‐12  (Khutana) to OHSR‐1‐1 ‐16GL 1.00 Nos.                           45,172                                45,172 
41.39 GLR‐13 ( Beerkhurd)OHSR‐ 11A ‐16GL 1.00 Nos.                           45,172                                45,172 
41.40 GLR‐13 ( Beerkhurd)OHSR‐ 2 & OHSR‐2‐1 ‐56GL 1.00 Nos.                           75,614                                75,614 
41.41 GLR ‐14 (Sirsain)OHSR‐1, OHSR‐1A & OHSR‐1A‐1‐72GL 1.00 Nos.                           93,290                                93,290 
42.00 Providing and Installation of 415 V Diesel Generator set with alternator as per the manufacturers specification, Single/multi runs of PVC insulated & PVC
sheathed / XLPE power cable of 1.1 KV grade of required size laying in ground including excavation, sand cushioning, protective covering and refilling the
trench, End termination with brass compression gland and aluminium lugs for said cable, D G set Earthing with 600 x 600 x 3 mm copper plate with 40
mm dia x 4.5 mtrs long G.I. vertically pipe having 12 mm dia holes spaced 5 mm apart drilled upto 2 mtr from the bottom complete vertically with its top
at least 3 mtrs below ground level with earthing lead of No.6 to 8 SWG GI wire / G I Strip in GI Pipe upto DG set, 30 cm square C.I. box with hinged cover
masonry enclosure, funnel at top, alternate layers of charcoal/ coke and salt at least 150 mm thick around G I Pipe etc complete, Rate of D G Set
including transportation, loading and unloading complete with all above materials, Also Construction of RCC DG Foundation with Galvanized iron roofing
0.63 mm thick shed supported with RCC pillar complete including all labour, material as per the detailed drawing and specification or as per the direction
of the Engineer

DG SET
42.01 Intake well ‐ 1250KVA 1.00 Set                   10,927,696                        10,927,696 
42.02 WTP & MCWR ‐ 2500KVA 1.00 Set                   18,922,158                        18,922,158 
42.03 GLR‐1 (Bhbhaech) ‐ 125KVA 1.00 Set                     1,120,462                           1,120,462 
42.04 GLR‐2 (Rudawali) ‐ 125KVA 1.00 Set                     1,120,462                           1,120,462 
42.05 GLR‐3 (Markundi) ‐ 3500KVA 1.00 Set                   26,491,021                        26,491,021 
42.06 GLR‐4 (Lori) ‐ 500KVA 1.00 Set                     4,238,312                           4,238,312 
42.07 GLR‐5 (Ganguar) ‐ 1250KVA 1.00 Set                   10,888,416                        10,888,416 
42.08 GLR‐6 (Kekarahi) ‐ 320KVA 1.00 Set                     3,258,626                           3,258,626 
42.09 GLR‐7 (Papi) ‐ 500KVA 1.00 Set                     4,238,312                           4,238,312 
42.10 GLR‐8 (Tarauli Raja) ‐ 320KVA 1.00 Set                     3,258,626                           3,258,626 
42.11 GLR‐9 (Nipraj) ‐ 125KVA 1.00 Set                     1,120,462                           1,120,462 
42.12 GLR‐10 (Kushara) ‐ 500KVA 1.00 Set                     4,238,312                           4,238,312 
42.13 GLR‐11 (Jogani) ‐ 160KVA 1.00 Set                     1,580,178                           1,580,178 
42.14 GLR‐12 (Khutana) ‐ 500KVA 1.00 Set                     4,238,312                           4,238,312 
42.15 GLR‐13 (Beerkhurd) ‐ 320KVA 1.00 Set                     3,258,626                           3,258,626 
42.16 GLR‐14 (Sirsail) ‐ 125KVA 1.00 Set                     1,120,462                           1,120,462 
43.00 Supply, installation, testing and commissioning of L T panels comprising of A.C.B / M.C.C.B . /M.C.B suitable C.Ts operated ampere meter, On/Off
indicator selector switch and internal wiring etc."&" complete including Amp meter, Voltmeter, frequencymeter, P.F. meter, Capacitor, single phasing
preventer, Selector switch, fuses etc ‐1 set. enclosed in 16 guage CRCA sheet metal work, doors, busbars, gaskets for doors, painting, feeder designation
etc., Single / multi runs of PVC insulated & PVC sheathed / XLPE power cable of 1.1 KV grade of required size laying in ground including excavation, sand
cushioning, protective covering and refilling the trench, End termination with brass compression gland and aluminium lugs for said cable, complete.
Earthing with 600 x 600 x 3 mm copper plate with 40 mm dia x 4.5 mtrs long G.I. vertically pipe having 12 mm dia holes spaced 5 mm apart drilled upto
2 mtr from the bottom complete vertically with its top at least 3 mtrs below ground level with earthing lead of No.6 to 8 SWG GI wire / G I Strip in GI Pipe
upto L T Panel, 30 cm square C.I. box with hinged cover masonry enclosure, funnel at top, alternate layers of charcoal/ coke and salt at least 150 mm
thick around G I Pipe etc complete including all labour, material as per the detailed drawing. Internal concealed electrification with 1.5 sq.mm. FRLSH
PVC insulated 1100 V grade multistrand single core copper conductor cable in 20 mm dia heavy duty (2mm thick) PVC conduit with 1 nos. 1.5
sq. mm. FRLSH PVC insulated 1100 V grade multistrand single core copper conductor cable as earth continuity wire drawn inside the
conduit complete in all respect. C02 type fire extinguisher 4.5 kg. capacity (ISI Marked IS : 2878 & TAC approved) complete with initial charge
and wall bracket and specification or as per the direction of the Engineer. as minimum requirement for complition of work as item mention below 

Page 15 of 17
 PRICE SCHEDULE As Per Revised BOQ
S.no Item Description Quantity Units Rates (in Rs.) Amount (in Rs.)
1 2 3 4 5 6
43.01 INTAKE WELL ‐ Incomer 2500 A ‐ 3nos, bus‐coupler 2500 A ‐ 1nos , motor feeder‐630A (6 Nos),  capacitor feeder , lighting feeder, Spare feeder  1.00 Set                     4,576,244                           4,576,244 

43.02 WTP  ‐ Incomer 1250A ‐ 3nos, bus‐coupler 1250A ‐ 1nos ,  motor feeder‐200A (10 Nos), capacitor feeder , lighting feeder, Spare feeder  1.00 Set                     3,071,696                           3,071,696 


43.03 MCWR ‐ Incomer 5000 A ‐ 3nos, bus‐coupler 5000 A ‐ 1 no , motor feeder‐500A (8 Nos), motor feeder‐160A (6 Nos), motor feeder‐63A (2 Nos),capacitor 1.00 Set                     7,532,001                           7,532,001 
feeder , lighting feeder, Spare feeder 
43.04 GLR‐1 (Babhech) ‐ Incomer 320 A ‐ 3nos, bus‐coupler 320 A ‐ 1 no , motor feeder‐100A (4 Nos), capacitor feeder , lighting feeder, Spare feeder  1.00 Set                     1,470,054                           1,470,054 

43.05 GLR‐2 (Rudwali) ‐ Incomer 320 A ‐ 3nos, bus‐coupler 320 A ‐ 1 no , motor feeder‐100A (4 Nos), capacitor feeder , lighting feeder, Spare feeder  1.00 Set                     1,470,054                           1,470,054 

43.06 GLR‐3 (Markundi) ‐ Incomer 6300 A ‐ 3nos, bus‐coupler 6300 A ‐ 1 no , motor feeder‐630A (15 Nos), capacitor feeder , lighting feeder, Spare feeder  1.00 Set                   14,928,650                        14,928,650 

43.07 GLR‐4 (Lori) ‐ Incomer 1250 A ‐ 3nos, bus‐coupler 1250 A ‐ 1 no , motor feeder‐400A (3 Nos), motor feeder‐100A (2 Nos), capacitor feeder , lighting 1.00 Set                     2,530,614                           2,530,614 
feeder, Spare feeder 
43.08 GLR‐5 (Ganguar) ‐ Incomer 2500 A ‐ 3nos, bus‐coupler 2500 A ‐ 1 no , motor feeder‐500A(4 Nos), Motor feeder‐200A(4 Nos), Motor feeder‐100A(2 1.00 Set                     4,617,929                           4,617,929 
Nos)capacitor feeder , lighting feeder, Spare feeder 
43.09 GLR ‐6 (kekarahi) ‐ Incomer 630 A ‐ 3nos, bus‐coupler 630 A ‐ 1 no , motor feeder‐160A (5 Nos), capacitor feeder , lighting feeder, Spare feeder  1.00 Set                     2,605,246                           2,605,246 

43.10 GLR‐7(Papi) ‐ Incomer 1250 A ‐ 3nos, bus‐coupler 1250 A ‐ 1 no , motor feeder‐250A (3 Nos),  capacitor feeder , lighting feeder, Spare feeder  1.00 Set                     2,052,380                           2,052,380 

43.11 GLR‐8 ( Tarauli Raja) ‐ Incomer 630 A ‐ 3nos, bus‐coupler 630 A ‐ 1 no , motor feeder‐160A (3 Nos), motor feeder‐100A (2 Nos), capacitor feeder , lighting 1.00 Set                     2,605,246                           2,605,246 
feeder, Spare feeder 
43.12 GLR‐9 (Nipraj)  ‐ Incomer 320 A ‐ 3nos, bus‐coupler 320 A ‐ 1 no , motor feeder‐100A (5 Nos), capacitor feeder , lighting feeder, Spare feeder  1.00 Set                     1,470,054                           1,470,054 

43.13 GLR‐10 (Kushara) ‐ Incomer 1250 A ‐ 3nos, bus‐coupler 1250 A ‐ 1 no , motor feeder‐160A(13 Nos) , capacitor feeder , lighting feeder, Spare feeder  1.00 Set                     3,993,205                           3,993,205 

43.14 GLR‐11 (Jogani) ‐ Incomer 320 A ‐ 3nos, bus‐coupler 320 A ‐ 1 no , motor feeder‐63A (7 Nos), capacitor feeder , lighting feeder, Spare feeder  1.00 Set                     1,470,054                           1,470,054 

43.15 GLR‐12 (Khutana) ‐ Incomer 1250 A ‐ 3nos, bus‐coupler 1250 A ‐ 1 no , motor feeder‐250A (6 Nos), motor feeder‐63A (2 Nos),capacitor feeder , lighting 1.00 Set                     2,530,614                           2,530,614 
feeder, Spare feeder 
43.16 GLR‐13 ( Beerkhurd) ‐ Incomer 630 A ‐ 3nos, bus‐coupler 630 A ‐ 1 no , motor feeder‐250A (2 Nos), motor feeder‐63A (2 Nos), capacitor feeder , lighting 1.00 Set                     2,605,246                           2,605,246 
feeder, Spare feeder 
43.17 GLR‐14 (Sirsail) ‐ Incomer 250 A ‐ 3nos, bus‐coupler 250 A ‐ 1 no , motor feeder‐100A (3 Nos), motor feeder‐63A (2 Nos), capacitor feeder , lighting 1.00 Set                     1,129,300                           1,129,300 
feeder, Spare feeder 

Page 16 of 17
 PRICE SCHEDULE As Per Revised BOQ
S.no Item Description Quantity Units Rates (in Rs.) Amount (in Rs.)
1 2 3 4 5 6
44.00 Design, Engineering, supply, Installation, Testing and commissioning of Automation & SCADA (PLC GSM based) system to Control water supply in OHT
and ventilation inside pumping station electrical room. 
44.01 Intake 1.00 No. 982,000  982,000 
44.02 WTP/CWR 1.00 No. 2,946,000  2,946,000 
44.03 GLR 5.00 No. 982,000  4,910,000 
44.04 GLR & OHSR 18.00 No. 982,000  17,676,000 
44.05 OHSR 46.00 No. 491,000  22,586,000 
45.00 Sufficient number of lights and around Water works compound external/street lightening system ‐ Solar based LED (110 to 130 Watts) with poles of 9.00 70.00 Nos. 31,228  2,185,960 
m long, foundation in 1:3:6, Including solar pannel & wiring etc. all complete as per directions of the Engineer. 
Subtotal of Part (A)                  7,897,774,329 
O & M
46.00 Operation and Maintenance of whole water Supply system constructed under this work, after completion of trial run for providing continous water
supply in the covered area and households  @ 55 lpcd at the minimum residual pressure of 7 M.
Fixed operation charges
46.01 Year‐1 (During defect liabilities period) 1.00 Year 78,230,400  78,230,400 
46.02 Year‐2 1.00 Year 82,142,000  82,142,000 
46.03 Year‐3 1.00 Year 86,250,000  86,250,000 
46.04 Year‐4 1.00 Year 90,563,000  90,563,000 
46.05 Year‐5 1.00 Year 95,092,000  95,092,000 
46.06 Year‐6 1.00 Year 99,847,000  99,847,000 
46.07 Year‐7 1.00 Year                 104,840,000  104,840,000 
46.08 Year‐8 1.00 Year                 110,082,000  110,082,000 
46.09 Year‐9 1.00 Year                 115,587,000  115,587,000 
46.10 Year‐10 1.00 Year                 121,367,000  121,367,000 
Subtotal of Part (B) 984,000,400 
Total (Part A + Part B)                  8,881,774,729 
Note 1. The contractor shall quote the rates inclisive of all taxes (excluding GST).
2. GST applicable amount will be paid extra based on submission of original challans receipts from the concerned authorities.
3. Standard Drawigs are avialable with the employer and bidders are allowed to review the same at SWSM office.
4. Rate Only Items as in BOQ to be Mreasured and paid as per actual site measurement / drg approval for the variations.
5. Above arrived quantities  based on site and scope given by client  and are as per available data /survey/designs and the quantities are liable to change as per actual site condition.
6. Actuals may vary with project report.

Page 17 of 17
COMPARETIVE SHEET
Item Rate BOQ (Schedule G)
Tender Inviting Authority: State Water & Sanitation Mission, Lucknow
Name of Work: Pipe water supply scheme for Patwadh  Group of Villages in district Sonbhadra with relevant works including Commissioning and Operation & Maintenance for 10 Years.

NIT No: 2180/W‐17/BID/2020‐21  Dated: 06‐01‐2021
Name of Bidder: M/s.NCC LIMITED

Original BOQ Revised BOQ

Rates after  Rates after 
Amount  Amount Difference in 
S.no Item Description Qty Units Discount in figures  S.no Item Description Qty Units Discount in figures  Remarks
(in Rs.) (in Rs.) Amount (Rs.)
(in Rs.) (in Rs.)

1 2 3 4 5 6 1 2 3 4 5 6 7
BUILD PHASE (PART ‐ A)  BUILD PHASE (PART ‐ A) 
Construction of Intake well as per site conditions.  Construction of Intake well as per site conditions. 
Intake Well ‐ Survey, Site investigation, soil testing, Designing, Planning, Intake Well ‐ Survey, Site investigation, soil testing, Designing, Planning,
Construction and Commissioning of intake well of minimum of 5 m diameter, Construction and Commissioning of intake well of minimum of 5 m

including excavation of soil i.e. Kankar mixed morrom/soft/hard rock, PCC for diameter, including excavation of soil i.e. Kankar mixed
morrom/soft/hard rock, PCC for bedding in lean concrete of minimum
bedding in lean concrete of minimum grade of M‐15, R.C.C. in grade M‐30 or
grade of M‐15, R.C.C. in grade M‐30 or above in raft/ pile foundation,
1.00 above in raft/ pile foundation, R.C.C. M‐30 in or above grade in walling and top 1.00
R.C.C. M‐30 in or above grade in walling and top slab, with supply of all
slab, with supply of all type steel bars of approved quality and cement as
type steel bars of approved quality and cement as approved by the
approved by the Employer, water inlet (Rose pieces of required size opening) Employer, water inlet (Rose pieces of required size opening) having
having different intake capacity of water at different level,as per site different intake capacity of water at different level,as per site
investigation, Designing, Planning, construction and commissioning, as per investigation, Designing, Planning, construction and commissioning, as
direction of Engineer per direction of Engineer
At Pathwad: Intake Well of minimum internal size of 5 M Dia & 9.1 m
1.01 At Pathwad: Intake Well of minimum internal size of 5 M Dia & 5.6 m Height 1.00 Job               14,730,000                     14,730,000  1.01 1.00 Job               23,936,250                      23,936,250                     9,206,250 
Height
                   14,730,000                      23,936,250                     9,206,250 
2.00 Construction of Jack well cum pump house as per site conditions.  2.00 Construction of Jack well cum pump house as per site conditions. 
Survey, Site investigation, soil testing, Planning, Designing, Construction and Survey, Site investigation, soil testing, Planning, Designing, Construction
Commissioning of Jack well and pump house as detailed below. and Commissioning of Jack well and pump house as detailed below.
For construction of pump house of minimum height of 6 m with required For construction of pump house of minimum height of 6 m with
required length of RCCfootbridge of minimum 2.5 m clear width or
length of RCCfootbridge of minimum 2.5 m clear width or minimum width for
minimum width for carriout the pumping main whichever is higher,
carriout the pumping main whichever is higher, pump floor level minimum 1 m
pump floor level minimum 1 m above HFL, water inlet opening having
above HFL, water inlet opening having different intake capacity of water at
different intake capacity of water at different inlet points, construction
different inlet points, construction of staircase, Pump house, operating Slab, of staircase, Pump house, operating Slab, gantry girder on corbel,
gantry girder on corbel, cement concrete floor with hardener, Circular Balcony cement concrete floor with hardener, Circular Balcony minimum 1m
minimum 1m width, staircase post‐column beams, development of land, width, staircase post‐column beams, development of land, approach
approach road etc. arrangement should be made inside pump house such that road etc. arrangement should be made inside pump house such that to
to fix required nos. of VT Pumps , Power Control Panels and starters, fix required nos. of VT Pumps , Power Control Panels and starters,
instrumentation & SCADA & wireless telemetry (voice & Data), internal and instrumentation & SCADA & wireless telemetry (voice & Data), internal
external electrifications and adequate LED lighting including excavation of soil and external electrifications and adequate LED lighting including
excavation of soil i.e. Kankar mixed morrom/soft/hard rock and lean
i.e. Kankar mixed morrom/soft/hard rock and lean concrete of minimum grade
concrete of minimum grade of M‐15 and R.C.C. in grade M‐30 or above
of M‐15 and R.C.C. in grade M‐30 or above in raft/ pile foundation, Walling,
in raft/ pile foundation, Walling, Intake R.C.C. wall with supply of all
Intake R.C.C. wall with supply of all type steel bars of approved quality and
type steel bars of approved quality and cement as approved by the
cement as approved by the Employer, cofferdam construction as per site Employer, cofferdam construction as per site requirement, diversion
requirement, diversion arrangement of flow of river during construction by arrangement of flow of river during construction by making bunds
making bunds across the river supply gunny bags, sand, fixing suitable size of across the river supply gunny bags, sand, fixing suitable size of steel
steel girder, dismantling and refixing etc. and also supply and fixing of girder, dismantling and refixing etc. and also supply and fixing of
collapsible gate, collapsible door, Aluminium window as per relevant collapsible gate, collapsible door, Aluminium window as per relevant
specifications, including of three‐coat whitewashing, internal two coat specifications, including of three‐coat whitewashing, internal two coat
snowcem painting, external painting with apex ultima/equivalent paint, all snowcem painting, external painting with apex ultima/equivalent paint,
all steelwork must be painted with red oxide paint and two coat of
steelwork must be painted with red oxide paint and two coat of anticorrosive
anticorrosive paint etc. and internal and external electrification of
paint etc. and internal and external electrification of intake well, supply and
intake well, supply and fixing of three‐row railing with M.S. Angle posts
fixing of three‐row railing with M.S. Angle posts supply and fixing of inlet
supply and fixing of inlet opening of required capacity, dewatering,
opening of required capacity, dewatering, including supply of all materials, all including supply of all materials, all labour T&P etc. required for proper
labour T&P etc. required for proper completion of works as per direction of the completion of works as per direction of the Engineer. Cost of VT Pumps
Engineer. Cost of VT Pumps , Panels, Scada, Panel Board, pipe manifolds etc. , Panels, Scada, Panel Board, pipe manifolds etc. are not covered in this
are not covered in this item. item.
At Patwadh: Jack Well of minimum internal size of 14 M Dia & 22.09M
2.01 At Patwadh: Jack Well of minimum internal size of 14 M Dia & 22.09 M Height  1.00 Job             108,096,803                   108,096,803  2.01 1.00 Job             108,096,803                   108,096,803  0.00
Height 

Page 1 of 20
Rates after  Rates after 
Amount  Amount Difference in 
S.no Item Description Qty Units Discount in figures  S.no Item Description Qty Units Discount in figures  Remarks
(in Rs.) (in Rs.) Amount (Rs.)
(in Rs.) (in Rs.)

MS Connecting Main with strainer ‐ Survey, Site investigation,


DI K‐7 Connecting Main with strainer ‐ Survey, Site investigation, Designing,
Designing, Planning, Construction and Commissioning of MS,
Planning, Construction and Commissioning of DI K‐7, connecting main of DI K‐7
connecting main of MS pipe of suitable diameter, (confirming to the
pipe of suitable diameter, (confirming to the Indian Standard Specification
Indian Standard Specification inclusive cost of jointing materials,
inclusive cost of jointing materials, including third party inspection charges,
including third party inspection charges, including transit insurance,
including transit insurance, railway freight, unloading from railway wagon,
railway freight, unloading from railway wagon, loading in to the truck,
loading in to the truck, transportation to standard store/ site of work,
transportation to standard store/ site of work, unloading, stacking etc.
unloading, stacking etc. including excavation of soil i.e. Kankar mixed
2.02 2.02 including excavation of soil i.e. Kankar mixed morrom/soft/hard rock,
morrom/soft/hard rock, providing, lowering, laying & jointing, Hydraulic
providing, lowering, laying & jointing, Hydraulic testing of MS pipe of
testing of DI K‐7 pipe of proper class & diameter meters, including laying and
proper class & diameter meters, including laying and fixing of precast
fixing of precast concrete, (1:3:6) Encasement to pipe ,Providing sluice Valves
concrete, (1:3:6) Encasement to pipe ,Providing sluice Valves of
of appropriate size and number, including all fitting, chamber for clean plug,
appropriate size and number, including all fitting, chamber for clean
Clean plug of proper numbers, Supply, laying & Jointing of strainers as per
plug, Clean plug of proper numbers, Supply, laying & Jointing of
design, including refilling, dewatering, removing surplus material as directed
strainers as per design, including refilling, dewatering, removing
by Engineer‐in‐Charge
surplus material as directed by Engineer‐in‐Charge

At Patwadh: DI K‐7 pipe of minium diameter 1000 mm Dia & 400 M Length for At Patwadh: MS pipe of minium diameter 1600 mm Dia & 85 M Length
2.03 1.00 Job               15,096,286                     15,096,286  2.03 1.00 Job               16,976,091                      16,976,091                     1,879,805 
intake well & SS  stainer of Apropriate size, 4 Nos.  for intake well & SS  stainer of Apropriate size, 2 Nos. 
                 123,193,089                   125,072,894                     1,879,805 
Construction of Water Treatment Plant  Construction of Water Treatment Plant 
Survey, Investigation, Planning, Design, Construction and Commissioning of Survey, Investigation, Planning, Design, Construction and
WTP as per of capacity as given below.  Commissioning of WTP as per of capacity as given below. 
For construction of WTP, Admin Building with Command Control Room, and For construction of WTP, Admin Building with Command Control Room,
fire fighting arrangements, first aid arrangements Circular Cascading Aerator, and fire fighting arrangements, first aid arrangements Circular
Cascading Aerator, Inlet chamber, alum dosing, pre‐sedimentation
Inlet chamber, alum dosing, pre‐sedimentation Tank, Rapid Mix, Vertical Flow
Tank, Rapid Mix, Vertical Flow Clarifloculator, Rapid Gravity Filter with
Clarifloculator, Rapid Gravity Filter with Back Wash Arrangement, Proper
Back Wash Arrangement, Proper Sludge Disposal and Backwash water
Sludge Disposal and Backwash water disposal arrangements to nearest
disposal arrangements to nearest drain/low laying area & Appurtenant
drain/low laying area & Appurtenant Works of the below‐mentioned capacity,
Works of the below‐mentioned capacity, automated through PLC with
automated through PLC with outputs to SCADA, walkway in between WTP outputs to SCADA, walkway in between WTP components with railing,
components with railing, Guard Room, Chemical Store House, Gaseous Guard Room, Chemical Store House, Gaseous Chlorination Plant,
Chlorination Plant, Development of WTP area with adequate plantation, Development of WTP area with adequate plantation, Rainwater
Rainwater harvesting unit. Raw water to be treated and filtered. Lean concrete harvesting unit. Raw water to be treated and filtered. Lean concrete to
3.00 to be used of grade not less than M‐10 and other structures in minimum M‐30 3.00 be used of grade not less than M‐10 and other structures in minimum
grade of concrete. Cement and steel should be as per approved by the M‐30 grade of concrete. Cement and steel should be as per approved
Employer/IS code. Collapsible MS steel doors and aluminium windows to be by the Employer/IS code. Collapsible MS steel doors and aluminium
provided including of three‐coat whitewashing, internal two coat snowcem windows to be provided including of three‐coat whitewashing, internal
painting, external painting with apex ultima/equivalent paint, all steelwork two coat snowcem painting, external painting with apex
ultima/equivalent paint, all steelwork must be painted with red oxide
must be painted with red oxide paint and two coat of anticorrosive paint etc.
paint and two coat of anticorrosive paint etc. and internal and external
and internal and external electrification with adequate LED lights for the
electrification with adequate LED lights for the compound, including
compound, including automation, instrumentation & SCADA, wireless
automation, instrumentation & SCADA, wireless telemetry (voice &
telemetry (voice & data). Including water testing kits, lab building and essential
data). Including water testing kits, lab building and essential lab
lab equipment as mentioned no. 40. Including of supply of all materials, labour equipment as mentioned no. 40. Including of supply of all materials,
T&P etc. required for proper completion of works as per direction of the labour T&P etc. required for proper completion of works as per
Engineer. direction of the Engineer.

3.01 At : Capacity of 120 MLD  1.00 Job             510,640,000                   510,640,000  3.01 At : Capacity of 120 MLD  1.00 Job             510,640,000                   510,640,000  0.00
                 510,640,000                   510,640,000  0.00
4.00 Clear Water Reservoir  4.00 Clear Water Reservoir 

Page 2 of 20
Rates after  Rates after 
Amount  Amount Difference in 
S.no Item Description Qty Units Discount in figures  S.no Item Description Qty Units Discount in figures  Remarks
(in Rs.) (in Rs.) Amount (Rs.)
(in Rs.) (in Rs.)

CLEAR WATER RESERVOIR ‐ Survey, Investigation, Soil Testing, Planning,


CLEAR WATER RESERVOIR ‐ Survey, Investigation, Soil Testing, Planning, Designing, Construction, Commissioning of CWR of capacity as detailed
Designing, Construction, Commissioning of CWR of capacity as detailed below. below.
The Concrete in a minimum grade of M‐30 and steel to be used as per IS code The Concrete in a minimum grade of M‐30 and steel to be used as per
and approved by Employer. Seismic effects and wind load with earthquake IS code and approved by Employer. Seismic effects and wind load with
resistance should be taken into account in the design. CWR  should be provided  earthquake resistance should be taken into account in the design. CWR
with a ventilator, manhole of adequate size. An aluminium ladder minimum of should be provided with a ventilator, manhole of adequate size. An
0.45 m wide in manhole should be provided. Ultrasonic water level indicator aluminium ladder minimum of 0.45 m wide in manhole should be
should be provided along with lighting conductor as per IS 2309. PCC of M‐10 provided. Ultrasonic water level indicator should be provided along
grade to be used in bed blocks. Overflow arrangement with the supply & with lighting conductor as per IS 2309. PCC of M‐10 grade to be used in
installation of pressure pipe of the same dia as that of the inlet, for taking bed blocks. Overflow arrangement with the supply & installation of
overflow water to a suitable low lying area. Painting of all steel and concrete pressure pipe of the same dia as that of the inlet, for taking overflow
pipes with 3 coats of approved cement plaster and anticorrosive paint water to a suitable low lying area. Painting of all steel and concrete
including all labour, material, T & P etc., all required for proper completion of pipes with 3 coats of approved cement plaster and anticorrosive paint
works as per the direction of the Engineer. including all labour, material, T & P etc., all required for proper
Bidders are advised to take SBC at 12 MT/SQM for construction of CWR. If completion of works as per the direction of the Engineer.
actual SBC is more than 12MT/SQM, the structure will be designed at 12 Bidders are advised to take SBC at 12 MT/SQM for construction of
MT/SQM. In case less than 12 MT/SQM, as per actual. CWR. If actual SBC is more than 12MT/SQM, the structure will be
designed at 12 MT/SQM. In case less than 12 MT/SQM, as per actual.

4.01 CWR at WTP of 9500 KL Capacity 1.00 Job               80,818,600                     80,818,600  4.01 CWR at WTP of 9500 KL Capacity 1.00 Job               80,818,600                      80,818,600  0.00
4.02 GLR‐1 (8500 KL ) 1.00 Job               75,132,820                     75,132,820  4.02 GLR‐1 (200 KL ) 1.00 Job                 4,124,400                        4,124,400                 ‐71,008,420 
4.03 GLR‐2 (8100 KL ) 1.00 Job               71,813,660                     71,813,660  4.03 GLR‐2 (100 KL) 1.00 Job                 3,338,800                        3,338,800                 ‐68,474,860 
4.04 GLR‐4 (7500 KL ) 1.00 Job               69,511,852                     69,511,852  4.04 GLR‐3 (4400KL) 1.00 Job               41,231,234                      41,231,234                 ‐28,280,618 
4.05 GLR‐5 (2200 KL ) 1.00 Job               15,495,960                     15,495,960  4.05 GLR‐4 (4400 KL) 1.00 Job               41,231,234                      41,231,234                   25,735,274 
4.06 GLR‐6 (250 KL ) 1.00 Job                 4,419,000                       4,419,000  4.06 GLR‐5 (4100 KL ) 1.00 Job               38,494,400                      38,494,400                   34,075,400 
4.07 GLR‐7 (4100 KL ) 1.00 Job               38,494,400                     38,494,400  4.07 GLR‐6 (1000KL) 1.00 Job                 8,780,865                        8,780,865                 ‐29,713,535 
4.08 GLR‐8 (4100 KL ) 1.00 Job               38,494,400                     38,494,400  4.08 GLR‐7 (950 KL ) 1.00 Job                 8,549,649                        8,549,649                 ‐29,944,751 
4.09 GLR‐9 (1900 KL ) 1.00 Job               12,942,760                     12,942,760  4.09 GLR‐8 (600 KL ) 1.00 Job                 6,383,000                        6,383,000                    ‐6,559,760 
4.10 GLR‐10 (500 KL ) 1.00 Job                 5,892,000                       5,892,000  4.10 GLR‐9 (200 KL) 1.00 Job                 4,124,400                        4,124,400                    ‐1,767,600 
4.11 GLR‐11 (800 KL ) 1.00 Job                 7,856,000                       7,856,000  4.11 GLR‐10 (2200 KL ) 1.00 Job               15,495,960                      15,495,960                     7,639,960 
4.12 GLR‐12 (600 KL ) 1.00 Job                 6,383,000                       6,383,000  4.12 GLR‐11  (400KL) 1.00 Job                 5,401,000                        5,401,000                       ‐982,000 
4.13 GLR‐13 (600 KL ) 1.00 Job                 6,383,000                       6,383,000  4.13 GLR‐12 (1200KL) 1.00 Job                 9,705,731                        9,705,731                     3,322,731 
4.14 GLR‐14 (400 KL ) 1.00 Job                 5,401,000                       5,401,000  4.14 GLR‐13 (250 KL ) 1.00 Job                 4,419,000                        4,419,000                       ‐982,000 
4.15 GLR‐15 (250 KL ) 1.00 Job                 4,419,000                       4,419,000  4.15 GLR‐14 (250 KL) 1.00 Job                 4,419,000                        4,419,000  0.00
Extra for cost variation due to soil bearing capacity (SBC) from assumed MT/Sq
4.16 GLR‐2 Adalganj (350 KL ) 1.00 Job                 5,106,400                       5,106,400  4.16 1.00                 1,000,000  Rate Only
SBC of 12 MT/Sqm for 1 MT/Sqm or part thereof m
4.17 GLR‐3 Bhbhaech (200 KL ) 1.00 Job                 4,124,400                       4,124,400 
4.18 GLR‐4 Rudawali (150 KL ) 1.00 Job                 3,731,600                       3,731,600 
Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of
4.19 1.00 MT/Sqm                 1,000,000 
12 MT/Sqm for 1 MT/Sqm or part thereof
                 456,419,852                   276,517,273               ‐179,902,579 
PUMP HOUSE ‐Survey, Investigation, Planning, Designing, Construction,
PUMP HOUSE ‐Survey, Investigation, Planning, Designing, Construction, Commissioning of Pump houes of required size to accommodate
Commissioning of Pump houes of required size to accommodate required nos required nos of pumps mentioned item nos. 
of pumps mentioned item nos.  For the construction of Pump House above CWR, minimum 4.5 m
For the construction of Pump House above CWR, minimum 4.5 m height is to height is to be kept with suitable arrangements to install and dismantle
be kept with suitable arrangements to install and dismantle VT pumps and VT pumps and installation of Fire Extinguishers, Power wiring &
installation of Fire Extinguishers, Power wiring & earthling system, rubber earthling system, rubber resistance sheets, spares for motors &
resistance sheets, spares for motors & switchgear, internal & external switchgear, internal & external electrifications and adequate LED
electrifications and adequate LED lighting, brickwork 1:4 (one cement and four lighting, brickwork 1:4 (one cement and four sand), plasterwork 1:6
sand), plasterwork 1:6 (one cement and six sand). Steel and cement to be used (one cement and six sand). Steel and cement to be used as per
5.00 as per approved by Engineer‐in charge / IS code. Reinforced Cement Concrete 5.00 approved by Engineer‐in charge / IS code. Reinforced Cement Concrete
minimum M‐25 to be used including fixing of doors, windows, shutters, glass minimum M‐25 to be used including fixing of doors, windows, shutters,
panels with gantry girder arrangement with supply and fixing of suitable sizes glass panels with gantry girder arrangement with supply and fixing of
of steel girder including snowcem painting two coat over one priming coat suitable sizes of steel girder including snowcem painting two coat over
using approved Colour and shade and whitewashing three coat of ceiling of one priming coat using approved Colour and shade and whitewashing
pump house and painting over new ironwork with one coat of primer and two three coat of ceiling of pump house and painting over new ironwork
coat of approved paint including cost of all arrangement of staircase, balcony with one coat of primer and two coat of approved paint including cost
with medium G.I pipe 20 mm size three row railing, shuttering, scaffolding and of all arrangement of staircase, balcony with medium G.I pipe 20 mm
water with supply of all materials, labours T&P etc. required for proper size three row railing, shuttering, scaffolding and water with supply of
completion of works as per direction of the Engineer. all materials, labours T&P etc. required for proper completion of works
as per direction of the Engineer.
(Pump House at) (Pump House at)
5.01 CWR at WTP of 14 m x 12.50 m x 5.0 m 1.00 Job                 4,506,398                       4,506,398  5.01 CWR at WTP of 22m x 14.5m x 5m 1.00 Job                 8,214,430                        8,214,430                     3,708,032 
5.02 GLR1 ‐ 22 m x 14.5m x 5.0m 1.00 Job                 8,214,430                       8,214,430  5.02 GLR‐1‐ 6mx 5.5m x 5m 1.00 Job                    850,412                           850,412                    ‐7,364,018 
5.03 GLR‐2 ‐ 22 m x 14.5m x 5.0m 1.00 Job                 8,214,430                       8,214,430  5.03 GLR‐2 ‐ 6m x 4.5m x 5m 1.00 Job                    695,256                           695,256                    ‐7,519,174 
5.04 GLR‐4 ‐ 22 m x 12 m x 5.0m 1.00 Job                 6,798,386                       6,798,386  5.04 GLR‐3 ‐ 22m x 14.5m x 5m 1.00 Job                 8,214,430                        8,214,430                     1,416,044 
5.05 GLR‐5 ‐ 14 m x 8.5m x 5.0m 1.00 Job                 3,064,822                       3,064,822  5.05 GLR‐4 ‐ 22m x 14.5m x 5m 1.00 Job                 8,214,430                        8,214,430                     5,149,608 
5.06 GLR‐6 ‐ 8 m x 6m x 5.0m 1.00 Job                 1,236,338                       1,236,338  5.06 GLR‐5  ‐ 22m x 14.5m x 5m 1.00 Job                 8,214,430                        8,214,430                     6,978,092 
5.07 GLR‐7 ‐ 22 m x 14.5m x 5.0m 1.00 Job                 8,214,430                       8,214,430  5.07 GLR‐6 ‐ 10m x 8m x 5m 1.00 Job                 2,060,236                        2,060,236                    ‐6,154,194 
5.08 GLR‐8 ‐ 11 m x 9.5m x 5.0m 1.00 Job                 2,690,680                       2,690,680  5.08 GLR‐7 ‐ 10m x 8m x 5m 1.00 Job                 2,060,236                        2,060,236                       ‐630,444 
Page 3 of 20
Rates after  Rates after 
Amount  Amount Difference in 
S.no Item Description Qty Units Discount in figures  S.no Item Description Qty Units Discount in figures  Remarks
(in Rs.) (in Rs.) Amount (Rs.)
(in Rs.) (in Rs.)

5.09 GLR‐9 ‐ 11 m x 9.5m x 5.0m 1.00 Job                 2,690,680                       2,690,680  5.09 GLR‐8 ‐ 8m x 6.5m x 5m 1.00 Job                 1,339,448                        1,339,448                    ‐1,351,232 
5.10 GLR‐10 ‐ 10 m x 8m x 5.0m 1.00 Job                 2,060,236                       2,060,236  5.10 GLR‐9 ‐ 6mx 5.5m x 5m 1.00 Job                    850,412                           850,412                    ‐1,209,824 
5.11 GLR‐11 ‐ 10 m x 6.5m x 5.0m 1.00 Job                 1,674,310                       1,674,310  5.11 GLR‐10 ‐ 14m x 8.5m x 5m 1.00 Job                 3,064,822                        3,064,822                     1,390,512 
5.12 GLR‐12 ‐ 8 m x 6.5m x 5.0m 1.00 Job                 1,339,448                       1,339,448  5.12 GLR‐11  ‐ 8m x 6.5m x 5m 1.00 Job                 1,339,448                        1,339,448  0.00
5.13 GLR‐13 ‐ 8 m x 6.5m x 5.0m 1.00 Job                 1,339,448                       1,339,448  5.13 GLR‐12 ‐ 10m x 8m x 5m 1.00 Job                 2,060,236                        2,060,236                        720,788 
5.14 GLR‐14 ‐ 8 m x 6.5m x 5.0m 1.00 Job                 1,339,448                       1,339,448  5.14 GLR‐13 ‐  8m x 6m x 5m 1.00 Job                 1,236,338                        1,236,338                       ‐103,110 
5.15 GLR‐15 ‐ 8 m x 4.5m x 5.0m 1.00 Job                     927,008                          927,008  5.15 GLR‐14 ‐ 8m x 6m x 5m 1.00 Job                 1,236,338                        1,236,338                        309,330 
5.16 GLR‐2 Adalganj ‐ 9.5 m x5. 5m x 5.0m 1.00 Job                 1,345,340                       1,345,340 
5.17 GLR‐3 Bhbhaech  6 m x 5.5m x 5m 1.00 Job                     850,412                          850,412 
5.18 GLR‐4 Rudawali ‐ 6 m x4.5m x 5.0m 1.00 Job                     695,256                          695,256 
                   57,201,500                      49,650,902                   ‐7,550,598 
Construction of electric power sub‐station room‐  Construction of electric power sub‐station room‐ 
Survey, Investigation, Soil Testing, Planning, Designing, Construction of electric Survey, Investigation, Soil Testing, Planning, Designing, Construction of
power sub‐station room of required size. Construction of RCC frame structure electric power sub‐station room of required size. Construction of RCC
room including excavation of soil i.e. Kankar mixed morrom/soft/hard rock, frame structure room including excavation of soil i.e. Kankar mixed
morrom/soft/hard rock, PCC for bedding in lean concrete of minimum
PCC for bedding in lean concrete of minimum grade of M‐15, R.C.C. in grade M‐
grade of M‐15, R.C.C. in grade M‐25 or above in footing, foundation,
25 or above in footing, foundation, plinth beam, column, lintel beam, chajja,
plinth beam, column, lintel beam, chajja, roof slab, brick work in CM 1:6
roof slab, brick work in CM 1:6 (1 cement & 6 sand) in walling, Internal plaster (1 cement & 6 sand) in walling, Internal plaster 12 mm thick for walls &
12 mm thick for walls & celling in CM 1:6 (1 cement & 6 Sand), External plaster celling in CM 1:6 (1 cement & 6 Sand), External plaster 20 mm thick in
20 mm thick in CM 1:4 (1 cement & 4 sand), providing laying hand cut CM 1:4 (1 cement & 4 sand), providing laying hand cut polished kota
polished kota stone flooring 25 mm to 30 mm thick on bed of CM 1:6 (1 stone flooring 25 mm to 30 mm thick on bed of CM 1:6 (1 cement & 6
6.00 6.00
cement & 6 sand) including cement float, filling jointing with neat cement sand) including cement float, filling jointing with neat cement slurry,
slurry, curing polishing and cleaning, providing cable duct of required size, curing polishing and cleaning, providing cable duct of required size,
including fixing of rolling shutter, aluminium windows & ventilator with glass including fixing of rolling shutter, aluminium windows & ventilator with
panels as per specifications, providing and applying white washing in two coat glass panels as per specifications, providing and applying white washing
in two coat to new plaster surface, internal two coat snowcem painting
to new plaster surface, internal two coat snowcem painting including priming
including priming coat, external painting with apex ultima/equivalent
coat, external painting with apex ultima/equivalent paint including priming,
paint including priming, painting over new iron work with one coat of
painting over new iron work with one coat of primer and two coat oil paint of primer and two coat oil paint of approved make including cost of all
approved make including cost of all arrangement of shuttering, scaffolding arrangement of shuttering, scaffolding including all materials, labours
including all materials, labours T&P etc. for proper completion of works as per T&P etc. for proper completion of works as per direction of the
direction of the Engineer.  Engineer. 
 (Construction of electric power sub‐station room at)  (Construction of electric power sub‐station room at)
6.01 CWR at WTP of 19 m x 5.5 m x 5.0 m 1.00 Job                 1,876,602                       1,876,602  6.01 CWR at WTP of 19 m x 5.5 m x 5.0 m 1.00 Job                 1,876,602                        1,876,602  0.00
6.02 GLR‐1 ‐ 19 m x 5.5m x 5.0m 1.00 Job                 1,876,602                       1,876,602  6.02 GLR‐1 ‐ 6 m x 2.5 m x 5.0m 1.00 Job                    294,600                           294,600                    ‐1,582,002 
6.03 GLR‐2 ‐ 19 m x 5.5m x 5.0m 1.00 Job                 1,876,602                       1,876,602  6.03 GLR‐2 ‐  6.0 m x 2.5m x 5.0m 1.00 Job                    294,600                           294,600                    ‐1,582,002 
6.04 GLR‐4 ‐ 13 m x 5.5m x 5.0m 1.00 Job                 1,293,294                       1,293,294  6.04 GLR‐3 ‐ 19 m x 5.5m x 5.0m 1.00 Job                 1,876,602                        1,876,602                        583,308 
6.05 GLR‐5 ‐ 10 m x 4.5m x 5.0m 1.00 Job                     824,880                          824,880  6.05 GLR‐4 ‐  19 m x 5.5m x 5.0m 1.00 Job                 1,876,602                        1,876,602                     1,051,722 
6.06 GLR‐6 ‐ 6.0 m x 2.5m x 5.0m 1.00 Job                     294,600                          294,600  6.06 GLR‐5 ‐ 19 m x 5.5m x 5.0m 1.00 Job                 1,876,602                        1,876,602                     1,582,002 
6.07 GLR‐7 ‐ 19 m x 5.5m x 5.0m 1.00 Job                 1,876,602                       1,876,602  6.07 GLR‐6 ‐ 7 m x 4.5m x 5.0m 1.00 Job                    586,254                           586,254                    ‐1,290,348 
6.08 GLR‐8 ‐ 7 m x 4.5m x 5.0m 1.00 Job                     586,254                          586,254  6.08 GLR‐7 ‐ 7 m x 4.5m x 5.0m 1.00 Job                    586,254                           586,254  0.00
6.09 GLR‐9 ‐7 m x 4.5m x 5.0m 1.00 Job                     586,254                          586,254  6.09 GLR‐8 ‐ 6 m x 2.5m x 5.0m 1.00 Job                    294,600                           294,600                       ‐291,654 
6.10 GLR‐10 ‐ 7 m x 4.5m x 5.0m 1.00 Job                     586,254                          586,254  6.10 GLR‐9 ‐ 6 m x 2.5 m x 5.0m 1.00 Job                    294,600                           294,600                       ‐291,654 
6.11 GLR‐11 ‐ 6 m x 2.5m x 5.0m 1.00 Job                     294,600                          294,600  6.11 GLR‐10 ‐ 10 m x 4.5m x 5.0m 1.00 Job                    824,880                           824,880                        530,280 
6.12 GLR‐12 ‐ 6 m x 2.5m x 5.0m 1.00 Job                     294,600                          294,600  6.12 GLR‐11 ‐ 6 m x 2.5 m x 5.0m 1.00 Job                    294,600                           294,600  0.00
6.13 GLR‐13 ‐ 6 m x 2.5m x 5.0m 1.00 Job                     294,600                          294,600  6.13 GLR‐12 ‐ 7 m x 4.5m x 5.0m 1.00 Job                    586,254                           586,254                        291,654 
6.14 GLR‐14 ‐ 6 m x 2.5m x 5.0m 1.00 Job                     294,600                          294,600  6.14  GLR‐13 ‐ 6 m x 2.5 m x 5.0m 1.00 Job                    294,600                           294,600  0.00
6.15 GLR‐15 ‐ 6.0 m x 2.5 m x 5.0m 1.00 Job                     294,600                          294,600  6.15 GLR‐14 ‐  6.0 m x 2.5m x 5.0m 1.00 Job                    294,600                           294,600  0.00
6.16 GLR‐2 Adalganj ‐ 6 m x 2.5 m x 5.0m 1.00 Job                     294,600                          294,600 
6.17 GLR‐3 Bhbhaech  ‐ 6 m x 2.5 m x 5.0m 1.00 Job                     294,600                          294,600 
6.18 GLR‐4 Rudawali ‐ 6 m x 2.5 m x 5.0m 1.00 Job                     294,600                          294,600 
                   14,034,744                      12,152,250                   ‐1,882,494 
Design, Supply, Erection and Testing of V.T. pump water‐lubricated to lift the Design, Supply, Erection and Testing of V.T. / HSC pump water‐
required discharge at required head with sufficient column pipe including shaft lubricated to lift the required discharge at required head with sufficient
with discharge head and bowl assembly all complete as per IS:2010 along with column pipe including shaft with discharge head and bowl assembly all
complete as per IS:2010 along with power control panel, soft starters,
power control panel, soft starters, control system panels, voltage stabilizer of
control system panels, voltage stabilizer of required capacity, EM Flow
7.00 required capacity, EM Flow Meters, piping manifolds( Suction and delivery 7.00
Meters, piping manifolds( Suction and delivery including all specials like
including all specials like bend, Tee,NRV, Sluice valve etc.) instrumentation &
bend, Tee,NRV, Sluice valve etc.) instrumentation & SCADA, wireless
SCADA, wireless telemetry (voice & Data) including all materials, labour, T&P telemetry (voice & Data) including all materials, labour, T&P etc. all
etc. all required for proper completion of works as per the direction of the required for proper completion of works as per the direction of the
Engineer. Engineer.
Intake to WTP (69100 LPM, 6(3W+3S) Nos, 212.58 KW, 38.5m Head ) ‐
7.01 Intake to WTP (23800 LPM, 6(3W+3S) Nos, 205.15 KW, 32m Head )  1.00 Set               29,145,760                     29,145,760  7.01 1.00 Set               31,965,854                      31,965,854                     2,820,094 
VT
MCWR to OHSR‐Kanach (486 LPM, 2(1W+1S) Nos, 9.48 KW, 62m Head )
7.02 CWR to GLR1 (14500 LPM, 6(4W+2S) Nos, 205.15 KW, 53m Head )  1.00 Set               26,472,756                     26,472,756  7.02 1.00 Set                 1,992,478                        1,992,478                 ‐24,480,278 
‐ VT
GLR‐1 to peak CH 2000 m (4850 LPM, 18(12W+6S) Nos, 205.15 KW, 153m MCWR to OHSR‐Patwadh, OHSR‐Salkhan , OHSR‐Redia, GLR‐2 & GLR‐1 
7.03 1.00 Set               71,024,132                     71,024,132  7.03 1.00 Set                 9,936,858                        9,936,858                 ‐61,087,274 
Head ) (6398 LPM, 6(4W+2S)Nos, 38.15KW, 94m Head)‐VT
MCWR to GLR‐3 (Markundi) (55935 LPM, 8(5W+3S)Nos, 182.84KW,
7.04 GLR‐2 to OHSR 12A (2500 LPM, 2(1W+1S) Nos, 22.38 KW, 28m Head )   1.00 Set                 2,733,888                       2,733,888  7.04 1.00 Set               35,297,008                      35,297,008                   32,563,120 
68m Head)‐VT
GLR‐1 (Bhbhaech) to OHSR‐Bhbhaech (1321 LPM, 2(1W+1S) Nos, 11.91
7.05 GLR‐2 to OHSR 12 (1950 LPM, 2(1W+1S) Nos, 18.65 KW, 30m Head ) 1.00 Set                 1,708,680                       1,708,680  7.05 1.00 Set                 1,732,248                        1,732,248                    ‐1,076,272 
KW, 33m Head )‐HSC

Page 4 of 20
Rates after  Rates after 
Amount  Amount Difference in 
S.no Item Description Qty Units Discount in figures  S.no Item Description Qty Units Discount in figures  Remarks
(in Rs.) (in Rs.) Amount (Rs.)
(in Rs.) (in Rs.)

GLR‐1 (Bhbhaech) to OHSR‐Belcupp (1205 LPM, 2(1W+1S) Nos, 18.63


7.06 GLR‐2 to OHSR‐9 (2300 LPM, 2(1W+1S) Nos, 37.3 KW, 37m Head )  1.00 Set                 2,071,038                       2,071,038  7.06 1.00 Set                 1,712,608                        1,712,608                         ‐87,398 
KW, 59m Head )‐HSC
GLR‐2 (Rudawali) to OHSR‐Rudawali (377 LPM, 2(1W+1S) Nos, 4.74 KW,
7.07 GLR‐4 to OHSR‐8A (2450 LPM, 2(1W+1S) Nos, 22.38 KW, 30m Head ) 1.00 Set                 2,808,520                       2,808,520  7.07 1.00 Set                 1,654,670                        1,654,670                         ‐54,010 
37m Head )‐HSC
GLR‐2 (Rudawali) to OHSR‐Markundi (804 LPM, 2(1W+1S) Nos,
7.08 GLR‐4 to OHSR‐8 (1050 LPM, 2(1W+1S) Nos, 18.65 KW, 51m Head )   1.00 Set                 1,800,006                       1,800,006  7.08 1.00 Set                 1,623,246                        1,623,246                       ‐447,792 
16.69KW, 76m Head )‐HSC
GLR‐3 (Markundi) to GLR‐4 (Lori) (55935 LPM, 15(10W+5S)Nos, 225.72
7.09 GLR‐4 to GLR‐5 (14550 LPM, 2(1W+1S) Nos, 93.25 KW, 21m Head ) 1.00 Set                 4,903,126                       4,903,126  7.09 1.00 Set               88,794,038                      88,794,038                   83,890,912 
KW, 167m Head)‐VT
GLR‐4 (Lori) to OHSR‐Zone 5‐3 (1894 LPM, 2(1W+1S)Nos, 12.55KW,25m
7.10 GLR‐5 to OHSR‐7 ‐ (2800 LPM, 2(1W + 1S) Nos, 37.3 KW, 40m Head ) 1.00 Set                 3,102,138                       3,102,138  7.10 1.00 Set                 2,354,836                        2,354,836                       ‐747,302 
Head)‐VT
GLR‐4 (Lori) to GLR‐5 (Gangur), OHSR‐Zone 12‐3 & OHSR‐Zone 9‐2
7.11 GLR‐5 to OHSR‐8B ‐ (1750 LPM, 2(1W + 1S) Nos, 37.3 KW, 75m Head ) 1.00 Set                 3,312,286                       3,312,286  7.11 1.00 Set               13,217,478                      13,217,478                     9,905,192 
(54041 LPM, 3(2W+1S)Nos, 110.24 KW,17m Head)‐VT
GLR‐5 (Gangur) to OHSR‐Zone 8D & 5‐2 (2616 LPM, 2(1W+1S)Nos,
7.12 GLR‐5 to OHSR‐11 ‐ (6500 LPM, 2(1W + 1S) Nos, 37.3 KW, 21m Head ) 1.00 Set                 3,806,232                       3,806,232  7.12 1.00 Set                 2,071,038                        2,071,038                    ‐1,735,194 
24.47KW,37m Head)‐VT
GLR‐5 (Gangur) to GLR‐6 (Kekarahi), OHSR‐Zone 8C & OHSR‐Zone 6C‐3
7.13 GLR‐5 to OHSR‐6 ‐ (3500 LPM, 2(1W + 1S) Nos, 37.3 KW, 26m Head ) 1.00 Set                 2,071,038                       2,071,038  7.13 1.00 Set                 6,001,984                        6,001,984                     3,930,946 
(14458 LPM, 4(3W+1S)Nos, 54.79KW,45m Head)‐VT
GLR‐5 (Gangur) to GLR‐9 (Nipraj), GLR‐10 (Kushara), OHSR‐Zone 8,
GLR‐6 to OHSR‐4 ‐ (1800 LPM, 2(1W + 1S) Nos, 14.92 KW, 27m Head ) & OHSR
7.14 1.00 Set                 4,511,308                       4,511,308  7.14 OHSR‐Zone 12‐1, OHSR‐Zone 12‐2, OHSR‐Zone 5‐1 & OHSR‐Zone 9A‐1 1.00 Set               17,648,504                      17,648,504                   13,137,196 
6 (1750 LPM, 2(1W + 1S) Nos, 37.3 KW, 60m Head )
(35447 LPM, 4(3W+1S)Nos, 164.30 KW,58m Head)‐VT
GLR‐6 (Kekarahi) to GLR‐7 (Papi) & OHSR‐Zone 6C‐1 (12594 LPM,
7.15 GLR‐12 to OHSR‐7A ‐ (1350 LPM, 2(1W + 1S) Nos, 14.92 KW, 31m Head ) 1.00 Set                 2,267,438                       2,267,438  7.15 1.00 Set                 6,827,355                        6,827,355                     4,559,917 
5(3W+2S)Nos, 37.88 KW,36m Head)‐HSC
GLR‐7 (Papi) to GLR‐8 (Tarauli Raja), OHSR‐Zone 6, OHSR‐Zone 6C,
7.16 GLR‐12 to CH 2890m ‐ (3850 LPM, 2(1W + 1S) Nos, 44.76 KW, 39m Head ) 1.00 Set                 2,730,942                       2,730,942  7.16 OHSR‐Zone 6C‐2 & OHSR‐Zone 7A‐1 (11904 LPM, 3(2W+1S)Nos, 79.67 1.00 Set                 7,104,279                        7,104,279                     4,373,337 
KW,53m Head)‐VT
GLR‐8 (Tarauli Raja) to OHSR‐Zone 6A‐1 (1033 LPM, 2(1W+1S)Nos,
7.17 GLR‐7 to OHSR 5, 5A ‐ (4050 LPM, 2(1W + 1S) Nos, 37.3 KW, 29m Head ) 1.00 Set                 3,112,940                       3,112,940  7.17 1.00 Set                 1,800,006                        1,800,006                    ‐1,312,934 
10.45KW,37m Head)‐HSC
GLR‐8 (Tarauli Raja) to OHSR‐Zone 6A & 6B, OHSR‐Zone 7B & 6A‐2,
7.18 GLR‐7 to GLR‐8 ‐ (25100 LPM, 2(1W + 1S) Nos, 93.25 KW, 14m Head ) 1.00 Set                 6,224,898                       6,224,898  7.18 OHSR‐Zone 6A‐3 & OHSR‐Zone 8B (6526 LPM, 3(2W+1S)Nos, 48.78 1.00 Set                 4,501,488                        4,501,488                    ‐1,723,410 
KW,59m Head)‐HSC
GLR‐9 (Nipraj) to OHSR‐Zone 9‐1 (1333 LPM, 3(2W+1S)Nos,
7.19 GLR‐8 to OHSR‐10 ‐ (1600 LPM, 2(1W + 1S) Nos, 37.3 KW, 64m Head ) 1.00 Set                 2,773,168                       2,773,168  7.19 1.00 Set                 2,568,912                        2,568,912                       ‐204,256 
15.25KW,81m Head)‐HSC
GLR‐9 (Nipraj) to OHSR‐Zone 9‐3 (1321 LPM, 2(1W+1S)Nos,
7.20 GLR‐8 to OHSR‐9A ‐ (3300 LPM, 2(1W + 1S) Nos, 55.95 KW, 56m Head ) 1.00 Set                 3,000,992                       3,000,992  7.20 1.00 Set                 2,267,438                        2,267,438                       ‐733,554 
12.27KW,34m Head)‐HSC
GLR‐10 (Kushara) to OHSR‐Zone 10, OHSR‐Zone 9A &OHSR‐Zone 9
7.21 GLR‐8 to GLR‐13 ‐ (6050 LPM, 2(1W + 1S) Nos, 37.3 KW, 14m Head ) 1.00 Set                 2,271,366                       2,271,366  7.21 1.00 Set                 5,120,148                        5,120,148                     2,848,782 
(4483 LPM, 3(2W+1S)Nos, 42.27KW,74m Head)‐VT
GLR‐10 (Kushara) to GLR‐11(Jogani), GLR‐12(Khutana), OHSR‐Zone 5B‐
7.22 GLR‐8 to GLR‐9 ‐(1500 LPM, 2(1W + 1S) Nos, 74.6 KW, 19m Head ) 1.00 Set                 1,332,574                       1,332,574  7.22 1, OHSR‐Zone 3B‐1 & OHSR‐Zone 3A‐3 (23163 LPM, 1.00 Set               13,654,710                      13,654,710                   12,322,136 
10(6W+4S)Nos,41.04KW,42m Head)‐VT
GLR‐11 (Jogani) to OHSR‐Zone 3A‐1 & 3A‐2 (1642 LPM, 2(1W+1S)Nos,
7.23 GLR‐8 to OHSR‐5B ‐ (1650 LPM, 2(1W + 1S) Nos, 18.65 KW, 40m Head ) 1.00 Set                 1,789,204                       1,789,204  7.23 1.00 Set                 1,654,670                        1,654,670                       ‐134,534 
14.49KW,33m Head)‐HSC
GLR‐11 (Jogani) to  OHSR‐Zone 11B, OHSR‐Zone 4A & OHSR‐Zone 7A‐2 
7.24 GLR‐13 to OHSR 3B (2050 LPM, (1W + 1S) Nos, 18.65 KW, 31m Head )  1.00 Set                 2,434,378                       2,434,378  7.24 1.00 Set                 4,281,520                        4,281,520                     1,847,142 
(3421 LPM, 5(3W+2S)Nos, 18.34KW,61m Head)‐HSC
GLR‐12 (Khutana) to  OHSR‐Zone 3‐1 (1204 LPM, 2(1W+1S)Nos, 
7.25 GLR‐13 to GLR‐14 (4000 LPM, (1W + 1S) Nos, 55.95 KW, 43m Head )  1.00 Set                 3,109,994                       3,109,994  7.25 1.00 Set                 1,992,478                        1,992,478                    ‐1,117,516 
10.21KW,31m Head)‐VT
GLR‐12 (Khutana) to  GLR‐13(Beerkhurd), OHSR‐Zone2A, OHSR‐Zone 
7.26 GLR‐14 to OHSR‐3A (1250 LPM, (1W + 1S) Nos, 11.19 KW, 21m Head )  1.00 Set                 1,992,478                       1,992,478  7.26 10A‐1 & OHSR‐Zone 10A‐2 (6643 LPM, 3(2W+1S)Nos, 60.61KW,72m  1.00 Set                 6,034,167                        6,034,167                     4,041,689 
Head)‐VT
GLR‐12 (Khutana) to  GLR‐14(Sirasil), OHSR‐Zone 3‐2 & 3‐3, OHSR‐Zone 
7.27 GLR‐14 to OHSR‐4A (1400 LPM, (1W + 1S) Nos, 18.65 KW, 38m Head )  1.00 Set                 1,623,246                       1,623,246  7.27 11A‐1, OHSR‐11 & OHSR‐Zone 1‐1 (6847 LPM, 3(2W+1S)Nos,  1.00 Set                 6,034,167                        6,034,167                     4,410,921 
54.93KW,63m Head)‐VT
GLR‐13 (Beerkhurd) to  OHSR‐Zone 11A (678 LPM, 2(1W+1S)Nos, 
7.28 GLR‐14 to OHSR 11B (1500 LPM, (1W + 1S) Nos, 14.92 KW, 30m Head )  1.00 Set                 1,654,670                       1,654,670  7.28 1.00 Set                 1,255,978                        1,255,978                       ‐398,692 
7.55KW,37m Head)‐VT
GLR‐13 (Beerkhurd) to  OHSR‐Zone 2 & OHSR 2‐1 (2096 LPM, 
7.29 GLR‐11 to OHSR‐6A (1350 LPM, (1W + 1S) Nos, 74.6 KW, 29m Head )  1.00 Set                 2,102,462                       2,102,462  7.29 1.00 Set                 4,022,778                        4,022,778                     1,920,316 
2(1W+1S)Nos, 55.25KW,105m Head)‐VT
GLR‐14 (Sirsail) to  OHSR‐Zone 1, OHSR‐Zone 1A & OHSR 1A‐1 (2750 
7.30 GLR‐11 to GLR‐12 (5200 LPM, (1W + 1S) Nos, 74.6 KW, 13m Head )  1.00 Set                 2,171,202                       2,171,202  7.30 1.00 Set                 2,434,869                        2,434,869                        263,667 
LPM, 3(2W+1S)Nos, 15.15KW,42m Head)‐HSC
7.31 GLR‐9 to OHSR‐10A (2150 LPM, (1W + 1S) Nos, 44.76 KW, 66m Head )  1.00 Set                 3,413,432                       3,413,432 
GLR‐9 to Khardeur CH 7027m (3900 LPM, (1W + 1S) Nos, 111.9 KW, 93m Head
7.32 1.00 Set                 4,736,186                       4,736,186 

7.33 GLR‐9 to OHSR‐3 (2300 LPM, (1W + 1S) Nos, 22.38 KW, 34m Head )  1.00 Set                 2,065,146                       2,065,146 
7.34 GLR‐9 to GLR‐10 (4350 LPM, (1W + 1S) Nos, 22.38 KW, 18m Head )  1.00 Set                 2,177,094                       2,177,094 
7.35 GLR‐10 to OHSR‐11 (850 LPM, (1W + 1S) Nos, 7.46 KW, 23m Head )  1.00 Set                 1,732,248                       1,732,248 
7.36 GLR‐10 to GLR‐15 (3500 LPM, (1W + 1S) Nos, 37.3 KW, 39m Head )  1.00 Set                 2,618,012                       2,618,012 
7.37 GLR‐15 to OHSR‐1 (2000 LPM, (1W + 1S) Nos, 18.65 KW, 29m Head )  1.00 Set                 2,354,836                       2,354,836 
7.38 GLR‐15 to OHSR‐1A (700 LPM, (1W + 1S) Nos,11.19 KW, 39m Head )  1.00 Set                 1,255,978                       1,255,978 
7.39 GLR‐15 to OHSR‐1B (850 LPM, (1W + 1S) Nos, 18.65 KW, 78m Head )  1.00 Set                 1,712,608                       1,712,608 
CWR to OHSR‐6 Patwadh(900 LPM, (1W + 1S) Nos, 74.6 KW, 70m Head ) & GLR‐
7.40 2 Adalganj (4350 LPM, (1W + 1S) Nos, 74.6 KW, 59m Head ) & GLR‐4 Rudawali 1.00 Set                 5,042,570                       5,042,570 
(1050 LPM, (1W + 1S) Nos, 22.38 KW, 58m Head )
GLR‐ 2 Adalganj to OHSR‐3 Adalganj (1950 LPM, (1W + 1S) Nos, 22.38
7.41 KW,34.5m Head ) & GLR‐3 Babhaech (2400 LPM, (1W + 1S) Nos, 29.84 KW,32 1.00 Set                 4,602,634                       4,602,634 
m Head )

Page 5 of 20
Rates after  Rates after 
Amount  Amount Difference in 
S.no Item Description Qty Units Discount in figures  S.no Item Description Qty Units Discount in figures  Remarks
(in Rs.) (in Rs.) Amount (Rs.)
(in Rs.) (in Rs.)

GLR‐ 3 Babhaech to OHSR‐2 Babhaech (1250 LPM, (1W + 1S) Nos, 22.38
7.42 KW,28.5m Head ) & OHSR‐1 Belcupp (1200 LPM, (1W + 1S) Nos, 3.73 KW,55m 1.00 Set                 3,901,486                       3,901,486 
Head )
GLR‐ 4 Rudawali to OHSR‐5 Rudawali (150 LPM, (1W + 1S) Nos, 3.73 KW,27m
7.43 1.00 Set                 3,172,842                       3,172,842 
Head ) & OHSR‐4 Markundi (900 LPM, (1W + 1S) Nos, 18.65 KW,59 m Head )
                 238,847,932                   287,557,811                   48,709,879 
Survey, Investigation, Planning, Construction, Commissioning, Design, Drawing Survey, Investigation, Planning, Construction, Commissioning, Design,
as per latest I.S. CODE & all design should be vetted by any IIT institute or govt Drawing as per latest I.S. CODE & all design should be vetted by any IIT
engineering college. for construction of electric power sub‐station room for 50 institute or govt engineering college. for construction of electric power
sub‐station room for 50 KVA above load of minimum size 4 x 3.5 x 3.5
KVA above load of minimum size 4 x 3.5 x 3.5 meter or as per requirement
meter or as per requirement including supplying and fixing transformer
including supplying and fixing transformer (As per following KVA ), transformer
(As per following KVA ), transformer foundation, supplying & fixing of
foundation, supplying & fixing of Air handling unit, Bus Coupler with 2 Air handling unit, Bus Coupler with 2 incoming & 1 outgoing ACB, steel
incoming & 1 outgoing ACB, steel tubular pole, ACSR Conductor, Lighting tubular pole, ACSR Conductor, Lighting arrestor, Disc and Pin insulation,
8.00 8.00
arrestor, Disc and Pin insulation, Stone Metal Spreading, including cable inside Stone Metal Spreading, including cable inside the substation as per
the substation as per requirement along with snowcem painting two coat over requirement along with snowcem painting two coat over one priming
coat using approved Colour and shade and white washing three coat
one priming coat using approved Colour and shade and white washing three
constructed room and painting over new iron work with one coat of
coat constructed room and painting over new iron work with one coat of
primer and two coat of approved paint including cost of all
primer and two coat of approved paint including cost of all arrangement of arrangement of shuttering, scaffolding and water with supply of all
shuttering, scaffolding and water with supply of all materials, labours T&P etc. materials, labours T&P etc. required for proper completion of works as
required for proper completion of works as per direction of the Engineer. per direction of the Engineer.
8.01 Intake well  1250 KVA 1.00 Nos                  4,009,506                       4,009,506  8.01 Intake well  1250KVA 2.00 Nos                  4,009,506                        8,019,012                     4,009,506 
8.02 WTP ‐ 1250 KVA 1.00 Nos                  4,009,506                       4,009,506  8.02 WTP & MCWR ‐ 2500KVA 2.00 Nos                  5,378,414                      10,756,828                     6,747,322 
8.03 CWR1A  1500 KVA 1.00 Nos                  4,249,114                       4,249,114  8.03 GLR‐1 (Bhbhaech) ‐ 160KVA 2.00 Nos                  1,078,236                        2,156,472                    ‐3,221,942 
8.04 MARKUNDI  VILLAGE ‐ GLR‐1A 2500 KVA 1.00 Nos                  5,378,414                       5,378,414  8.04 GLR‐2 (Rudawali) ‐ 100KVA 2.00 Nos                     903,440                        1,806,880                    ‐3,571,534 
8.05 MARKUNDI  VILLAGE ‐ GLR‐1B 2500 kva 1.00 Nos                  5,378,414                       5,378,414  8.05 GLR‐3 (Markundi) ‐ 3500KVA 2.00 Nos                  6,473,540                      12,947,080                   11,399,448 
8.06 CHHAPAKA VILLAGE‐GLR‐2 250 kva 1.00 Nos                  1,547,632                       1,547,632  8.06 GLR‐4 (Lori) ‐ 500KVA 2.00 Nos                  1,858,926                        3,717,852                        603,930 
8.07 GANGUR VILLAGE‐GLR‐4 800 kva 1.00 Nos                  3,113,922                       3,113,922  8.07 GLR‐5 (Ganguar) ‐ 1250KVA 2.00 Nos                  4,009,506                        8,019,012                     6,243,556 
8.08 PAPI VILLAGE ‐ GLR‐5 400 kva 1.00 Nos                  1,775,456                       1,775,456  8.08 GLR‐6 (Kekarahi) ‐ 315KVA 2.00 Nos                  1,642,739                        3,285,478                     1,845,866 
8.09 BHARAWAH VILLAGE ‐ GLR‐6 200 kva  1.00 Nos                  1,439,612                       1,439,612  8.09 GLR‐7 (Papi) ‐ 500KVA 2.00 Nos                  1,858,926                        3,717,852                     1,858,926 
8.10 UNCHIDIH VILLAGE ‐ GLR‐7 500 kva  1.00 Nos                  1,858,926                       1,858,926  8.10 GLR‐8 (Tarauli Raja) ‐ 315KVA 2.00 Nos                  1,642,739                        3,285,478                     1,213,458 
8.11 SIDDHI VILLAGE ‐ GLR‐8  630 kva  1.00 Nos                  2,072,020                       2,072,020  8.11 GLR‐9 (Nipraj) ‐ 160KVA 2.00 Nos                  1,078,236                        2,156,472                       ‐457,612 
8.12 KHUTHA VILLAGE‐GLR‐9 400 kva 1.00 Nos                  2,614,084                       2,614,084  8.12 GLR‐10 (Kushara) ‐ 500KVA 2.00 Nos                  1,858,926                        3,717,852                     2,278,240 
8.13 PEROHA VILLAGE‐GLR‐10 200 kva 1.00 Nos                  1,439,612                       1,439,612  8.13 GLR‐11 (Jogani) ‐ 160KVA 2.00 Nos                  1,078,236                        2,156,472                     1,240,266 
8.14 AMAULIA GLR 11  125 KVA 1.00 Nos                      916,206                          916,206  8.14 GLR‐12 (Khutana) ‐ 500KVA 2.00 Nos                  1,858,926                        3,717,852                     2,170,220 
8.15 BHWANIPUR GLR 12 ‐ 250 KVA 1.00 Nos                  1,547,632                       1,547,632  8.15 GLR‐13 (Beerkhurd) ‐ 315KVA 2.00 Nos                  1,642,739                        3,285,478                     1,666,160 
8.16 GLR 13 CAMPUS   300 KVA 1.00 Nos                  1,619,318                       1,619,318  8.16 GLR‐14 (Sirsail) ‐ 100KVA 2.00 Nos                     903,440                        1,806,880                        818,988 
8.17 GLR 14 CAMPUS  150 KVA  1.00 Nos                      987,892                          987,892 
8.18 GLR 15 CAMPUS 150 KVA  1.00 Nos                      987,892                          987,892 
8.19 PATWADH CWR  ‐ 500 KVA 1.00 Nos                  1,858,926                       1,858,926 
8.20 ADALGANJ GLSR 2 200 KVA  1.00 Nos                  1,439,612                       1,439,612 
8.21 BHBHAECH GLSR‐3  125 KVA  1.00 Nos                      916,206                          916,206 
8.22 RUDAWALI GLSR‐4  100 KVA  1.00 Nos                      903,440                          903,440 
                   50,063,342                      74,552,950                   24,489,608 
Construction of Over Head Tank of different capacities and staging heights as Construction of Over Head Tank of different capacities and staging
mentioned below. Supply of all materials labour T&P etc. compete and heights as mentioned below. Supply of all materials labour T&P etc.
construction of R.C.C. (M30 Grade) with main components, Instruments & compete and construction of R.C.C. (M30 Grade) with main
SCADA, wireless telemetry (voice & Data) including cost of soil testing. All the components, Instruments & SCADA, wireless telemetry (voice & Data)
components of O.H.T. will be casted in M30 concrete with cement, coarse sand including cost of soil testing. All the components of O.H.T. will be
and approved stone grit as per I.S. 11682 and I.S.456.Seismic effects and wind casted in M30 concrete with cement, coarse sand and approved stone
load should be taken into consideration as I.S. 1893 for earthquake resistance grit as per I.S. 11682 and I.S.456.Seismic effects and wind load should
and I.S. 875 part‐III for wind load on structure (this area is in seismic Zone III be taken into consideration as I.S. 1893 for earthquake resistance and
and high damage risk zone for wind) Proper ventilator at top dome in circular I.S. 875 part‐III for wind load on structure (this area is in seismic Zone III
shape along with an R.C.C. cover and thickness, pillar of ventilator should be and high damage risk zone for wind) Proper ventilator at top dome in
minimum 50 cm height.The space between top dome and R.C.C. cover should circular shape along with an R.C.C. cover and thickness, pillar of
be covered with mosquito net of standard quality along with expanded ventilator should be minimum 50 cm height.The space between top
metaled mesh, Ultrasonic type Water level indicator and EM flow meter and dome and R.C.C. cover should be covered with mosquito net of
residual chlorine sensor/ transmitter. The indicator board scale made of 3mm standard quality along with expanded metaled mesh, Ultrasonic type
thick M.S. plate should have a clear width of minimum 25cm painted with good Water level indicator and EM flow meter and residual chlorine sensor/
Asian paint. It should also consists of 3mm brass wire rope minimum 4 smooth transmitter. The indicator board scale made of 3mm thick M.S. plate
pulleys about 8 cm dia with guides,15cm dia copper ball float which shall be should have a clear width of minimum 25cm painted with good Asian
completely wate tight suitable pointer of brass etc.Lightening conductor as per paint. It should also consists of 3mm brass wire rope minimum 4
I.S.S.2309 of its latest amendments of latest electricity rules.It should consist smooth pulleys about 8 cm dia with guides,15cm dia copper ball float
proper elevation rod with 5 or more fork points proper down conductors of which shall be completely wate tight suitable pointer of brass
prescribed metal of propr size prescribed by ISS 2309‐1969 and ISS 3013‐ etc.Lightening conductor as per I.S.S.2309 of its latest amendments of
1966C.I. manhole of min 60x60cm size made of M.S.channel section with latest electricity rules.It should consist proper elevation rod with 5 or
9 00 9 00

Page 6 of 20
Rates after  Rates after 
Amount  Amount Difference in 
S.no Item Description Qty Units Discount in figures  S.no Item Description Qty Units Discount in figures  Remarks
(in Rs.) (in Rs.) Amount (Rs.)
(in Rs.) (in Rs.)

9.00 9.00
adequate cover made of M.S. sheet of minimum 3mm thickness hinged with more fork points proper down conductors of prescribed metal of propr
manhole with locking aarrangement.This manhole should be fix at top dome at size prescribed by ISS 2309‐1969 and ISS 3013‐1966C.I. manhole of min
proper place.Supply, fixing,jointing of following size of C.I.D/F Pipes with 60x60cm size made of M.S.channel section with adequate cover made
C.I.D/F specials conforming to IS 8329/2000 as vertical pipes for of M.S. sheet of minimum 3mm thickness hinged with manhole with
inlet,outlet,overflow and washout as per latest / relevant I.S. specifications locking aarrangement.This manhole should be fix at top dome at
with all jointing materials for proper completion of work including other proper place.Supply, fixing,jointing of following size of C.I.D/F Pipes
appurtenant works and exeavation in all types of soil. Including Out let pipes of with C.I.D/F specials conforming to IS 8329/2000 as vertical pipes for
maximum size of distribution system, Inlet pipes of rising main size, Over flow inlet,outlet,overflow and washout as per latest / relevant I.S.
pipes of minimum size of rising main & Wash out pipe 100 mm dia.Supply and specifications with all jointing materials for proper completion of work
Fixing of manually operated valves/sliuce valves with hand wheels as per ISS including other appurtenant works and exeavation in all types of soil.
700/1969 or its latest amendments class “A” working pressure 10 Kg/cm2 Including Out let pipes of maximum size of distribution system, Inlet
Including cartage from its store to the site of work, lowering them into pipes of rising main size, Over flow pipes of minimum size of rising main
trenches, fixing in position and testing etc.complete, Construction of bed & Wash out pipe 100 mm dia.Supply and Fixing of manually operated
blocks in 1:2:4 PCC with cement,coarse sand and approved stone grit under valves/sliuce valves with hand wheels as per ISS 700/1969 or its latest
each duck foot bend to support the vertical pipes.These bed blocks should amendments class “A” working pressure 10 Kg/cm2 Including cartage
supported on the raft not on the soil.Construction of sluice valve chamber for from its store to the site of work, lowering them into trenches, fixing in
above sluice valve/Butterfly valve as per standard design and drawing including position and testing etc.complete, Construction of bed blocks in 1:2:4
supply of all labour T&P complete. Construction of washout / overflow PCC with cement,coarse sand and approved stone grit under each duck
chamber as per standard design and drawing.Painting of all concrete surface foot bend to support the vertical pipes.These bed blocks should
and steel pipe works with three coats of approved cement paint and supported on the raft not on the soil.Construction of sluice valve
anticorrosive paints.Supply & laying of 200 mm dia PVC pipe as per I.S.‐ chamber for above sluice valve/Butterfly valve as per standard design
4985/2000 or as latest / relevant specification including all taxes and insurance  and drawing including supply of all labour T&P complete. Construction 
OHSR‐ Zone‐Markundi ;1‐1 ; 6 ; 3B‐1 ; 7A‐2 ; 11 ; 12‐3 ‐300 KL, 21 m
9.01 OHSR‐1 ‐ 850 KL, 18 m staging 1.00 Job               13,768,622                     13,768,622  9.01 7.00 Job                 6,385,946                      44,701,622                   30,933,000 
staging 
Variation of 32m decrease in 
9.02 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                     710,000  9.02 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                    330,000   Rate only  staging will be measured  as 
per actual design & drawing.
Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of Extra for cost variation due to soil bearing capacity (SBC) from assumed MT/Sq
9.03 1.00 MT/Sqm                     990,000  9.03 1.00                    460,000   Rate only 
12 MT/Sqm for 1 MT/Sqm or part thereof SBC of 12 MT/Sqm for 1 MT/Sqm or part thereof m
9.04 OHSR‐1A 300 KL, 21 m staging 1.00 Job                 6,385,946                       6,385,946  9.04 OHSR‐ Zone‐1 ; 1A ; 2 ; 6A‐1 ; 12‐1 ; 7A‐1 ‐ 350 KL, 19 m staging  6.00 Job                 7,094,950                      42,569,700                   36,183,754 
Variation of 8m decrease in 
9.05 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                     330,000  9.05 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                    370,000   Rate only  staging will be measured  as 
per actual design & drawing.
Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of Extra for cost variation due to soil bearing capacity (SBC) from assumed MT/Sq
9.06 1.00 MT/Sqm                     460,000  9.06 1.00                    510,000   Rate only 
12 MT/Sqm for 1 MT/Sqm or part thereof SBC of 12 MT/Sqm for 1 MT/Sqm or part thereof m
9.07 OHSR‐1B 350 KL, 19 m staging 1.00 Job                 7,094,950                       7,094,950  9.07 OHSR‐ Zone 8D & 5‐2‐ 900 KL, 20 m staging 1.00 Job               15,151,278                      15,151,278                     8,056,328 
Variation of 2m increase in 
9.08 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                     370,000  9.08 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                    780,000   Rate only  staging will be measured  as 
per actual design & drawing.
Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of Extra for cost variation due to soil bearing capacity (SBC) from assumed MT/Sq
9.09 1.00 MT/Sqm                     510,000  9.09 1.00                 1,090,000   Rate only 
12 MT/Sqm for 1 MT/Sqm or part thereof SBC of 12 MT/Sqm for 1 MT/Sqm or part thereof m
9.10 OHSR‐2 1050 KL, 18 m staging 1.00 Job               16,718,550                     16,718,550  9.10 OHSR‐ Zone‐6A & 6B ‐ 800 KL, 16 m staging  1.00 Job               12,401,678                      12,401,678                    ‐4,316,872 
Variation of 3m increase in 
9.11 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                     860,000  9.11 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                    640,000   Rate only  staging will be measured  as 
per actual design & drawing.
Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of Extra for cost variation due to soil bearing capacity (SBC) from assumed MT/Sq
9.12 1.00 MT/Sqm                 1,200,000  9.12 1.00                    890,000   Rate only 
12 MT/Sqm for 1 MT/Sqm or part thereof SBC of 12 MT/Sqm for 1 MT/Sqm or part thereof m
9.13 OHSR‐2A 700 KL, 22 m staging 1.00 Job               12,770,910                     12,770,910  9.13 OHSR‐ Zone‐6A‐3 ; 3A‐1 & 3A‐2 ‐ 600 KL, 18 m staging  2.00 Job               10,184,322                      20,368,644                     7,597,734 
Variation of 6m increase in 
9.14 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                     660,000  9.14 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                    520,000   Rate only  staging will be measured  as 
per actual design & drawing.
Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of Extra for cost variation due to soil bearing capacity (SBC) from assumed MT/Sq
9.15 1.00 MT/Sqm                     920,000  9.15 1.00                    730,000   Rate only 
12 MT/Sqm for 1 MT/Sqm or part thereof SBC of 12 MT/Sqm for 1 MT/Sqm or part thereof m
OHSR‐ Zone‐Bhabecha ; 2A ; 6C‐2 ; 7B & 6A‐2 ; 8B ; 9‐1 ; 9‐3 ; 9A ; 10
9.16 OHSR‐3 1000 KL, 16 m staging 1.00 Job               15,073,700                     15,073,700  9.16 10.00 Job                 8,450,110                      84,501,100                   69,427,400 
;Belcupp ‐ 450 KL, 17 m staging 
Variation of 12m increase in 
9.17 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                     770,000  9.17 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                    440,000   Rate only  staging will be measured  as 
per actual design & drawing.
Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of Extra for cost variation due to soil bearing capacity (SBC) from assumed MT/Sq
9.18 1.00 MT/Sqm                 1,080,000  9.18 1.00                    610,000   Rate only 
12 MT/Sqm for 1 MT/Sqm or part thereof SBC of 12 MT/Sqm for 1 MT/Sqm or part thereof m
9.19 OHSR‐3A 500 KL, 10 m staging 1.00 Job                 7,343,396                       7,343,396  9.19 OHSR‐ Zone‐5‐3 ; 9 ; 3‐2 & 3‐3 ; 9A‐1 ‐ 650 KL, 20 m staging 4.00 Job               11,367,632                      45,470,528                   38,127,132 
Variation of 20m decrease in 
9.20 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                     380,000  9.20 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                    580,000   Rate only  staging will be measured  as 
per actual design & drawing.
Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of Extra for cost variation due to soil bearing capacity (SBC) from assumed MT/Sq
9.21 1.00 MT/Sqm                     530,000  9.21 1.00                    820,000   Rate only 
12 MT/Sqm for 1 MT/Sqm or part thereof SBC of 12 MT/Sqm for 1 MT/Sqm or part thereof m
9.22 OHSR‐3B 900 KL, 20 m staging 1.00 Job               15,151,278                     15,151,278  9.22 OHSR‐ Zone‐5B‐1 ;6C ;10A‐2 ; Salkhan ‐ 500 KL, 24 m staging  4.00 Job                 9,987,922                      39,951,688                   24,800,410 

Page 7 of 20
Rates after  Rates after 
Amount  Amount Difference in 
S.no Item Description Qty Units Discount in figures  S.no Item Description Qty Units Discount in figures  Remarks
(in Rs.) (in Rs.) Amount (Rs.)
(in Rs.) (in Rs.)

Variation of 29m decrease in 
9.23 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                     780,000  9.23 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                    510,000   Rate only  staging will be measured  as 
per actual design & drawing.
Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of Extra for cost variation due to soil bearing capacity (SBC) from assumed MT/Sq
9.24 1.00 MT/Sqm                 1,090,000  9.24 1.00                    720,000   Rate only 
12 MT/Sqm for 1 MT/Sqm or part thereof SBC of 12 MT/Sqm for 1 MT/Sqm or part thereof m
9.25 OHSR‐4 800 KL, 16 m staging 1.00 Job               12,401,678                     12,401,678  9.25 OHSR‐ Zone‐4A  ‐ 550 KL, 18 m staging  1.00 Job                 9,500,850                        9,500,850                    ‐2,900,828 
Variation of 4m increase in 
9.26 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                     640,000  9.26 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                    490,000   Rate only  staging will be measured  as 
per actual design & drawing.
Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of Extra for cost variation due to soil bearing capacity (SBC) from assumed MT/Sq
9.27 1.00 MT/Sqm                     890,000  9.27 1.00                    680,000   Rate only 
12 MT/Sqm for 1 MT/Sqm or part thereof SBC of 12 MT/Sqm for 1 MT/Sqm or part thereof m
9.28 OHSR‐4A 600 KL, 18 m staging 1.00 Job               10,184,322                     10,184,322  9.28 OHSR‐ Zone‐3‐1 ; 2‐1 ; 3A‐3 ; 8 ; 8C ; 10A‐1 ; 11B ‐ 400 KL, 15 m staging  7.00 Job                 6,685,456                      46,798,192                   36,613,870 

Variation of 19m increase in 
9.29 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                     520,000  9.29 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                    350,000   Rate only  staging will be measured  as 
per actual design & drawing.
Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of Extra for cost variation due to soil bearing capacity (SBC) from assumed MT/Sq
9.30 1.00 MT/Sqm                     730,000  9.30 1.00                    480,000   Rate only 
12 MT/Sqm for 1 MT/Sqm or part thereof SBC of 12 MT/Sqm for 1 MT/Sqm or part thereof m
9.31 OHSR‐5 800 KL, 18 m staging 1.00 Job               13,245,216                     13,245,216  9.31 OHSR‐ Zone‐Redia ; 11A‐1 ‐ 200 KL, 12 m staging 2.00 Job                 3,920,144                        7,840,288                    ‐5,404,928 
Variation of 8m increase in 
9.32 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                     680,000  9.32 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                    200,000   Rate only  staging will be measured  as 
per actual design & drawing.
Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of Extra for cost variation due to soil bearing capacity (SBC) from assumed MT/Sq
9.33 1.00 MT/Sqm                     950,000  9.33 1.00                    280,000   Rate only 
12 MT/Sqm for 1 MT/Sqm or part thereof SBC of 12 MT/Sqm for 1 MT/Sqm or part thereof m
OHSR‐ Zone‐Pathwad ;5‐1 ; 11A ; 6C‐1 ; 1A‐1 ; 6C‐3 ; 9‐2 ‐ 250 KL, 12 m
9.34 OHSR‐5A 1000 KL, 18 m staging 1.00 Job               16,052,754                     16,052,754  9.34 7.00 Job                 4,900,180                      34,301,260                   18,248,506 
staging 
Variation of 30m increase in 
9.35 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                     820,000  9.35 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                    250,000   Rate only  staging will be measured  as 
per actual design & drawing.
Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of Extra for cost variation due to soil bearing capacity (SBC) from assumed MT/Sq
9.36 1.00 MT/Sqm                 1,150,000  9.36 1.00                    350,000   Rate only 
12 MT/Sqm for 1 MT/Sqm or part thereof SBC of 12 MT/Sqm for 1 MT/Sqm or part thereof m
9.37 OHSR‐5B 700 KL, 18 m staging 1.00 Job               11,531,626                     11,531,626  9.37 OHSR‐ Zone‐12‐2 ; Rudawali ‐ 150 KL, 12 m staging   2.00 Job                 2,940,108                        5,880,216                    ‐5,651,410 
Variation of 16m increase in 
9.38 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                     590,000  9.38 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                    150,000   Rate only  staging will be measured  as 
per actual design & drawing.
Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of Extra for cost variation due to soil bearing capacity (SBC) from assumed MT/Sq
9.39 1.00 MT/Sqm                     830,000  9.39 1.00                    210,000   Rate only 
12 MT/Sqm for 1 MT/Sqm or part thereof SBC of 12 MT/Sqm for 1 MT/Sqm or part thereof m
9.40 OHSR‐6 750 KL, 22 m staging 1.00 Job               13,655,692                     13,655,692  9.40 OHSR‐  Zone‐Kanach ‐ 175KL, 12 m staging  1.00                 3,430,126                        3,430,126                 ‐10,225,566 
Variation of 4m increase in 
9.41 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                     700,000  9.41 Variation in Staging of RCC Overhead Tank increased/decreased  1.00                    175,000   Rate only  staging will be measured  as 
per actual design & drawing.
Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of Extra for cost variation due to soil bearing capacity (SBC) from assumed
9.42 1.00 MT/Sqm                     980,000  9.42 1.00                    245,000   Rate only 
12 MT/Sqm for 1 MT/Sqm or part thereof SBC of 12 MT/Sqm for 1 MT/Sqm or part thereof
9.43 OHSR‐6A 600 KL, 18 m staging 1.00 Job               10,166,646                     10,166,646 
9.44 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                     520,000 
Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of
9.45 1.00 MT/Sqm                     730,000 
12 MT/Sqm for 1 MT/Sqm or part thereof
9.46 OHSR‐6B 950 KL, 22 m staging 1.00 Job               16,868,796                     16,868,796 
9.47 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                     860,000 
Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of
9.48 1.00 MT/Sqm                 1,210,000 
12 MT/Sqm for 1 MT/Sqm or part thereof
9.49 OHSR‐7 1250 KL, 18 m staging 1.00 Job               19,546,710                     19,546,710 
9.50 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                 1,000,000 
Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of
9.51 1.00 MT/Sqm                 1,400,000 
12 MT/Sqm for 1 MT/Sqm or part thereof
9.52 OHSR‐7A 600 KL, 20 m staging 1.00 Job               10,643,898                     10,643,898 
9.53 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                     550,000 
Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of
9.54 1.00 MT/Sqm                     760,000 
12 MT/Sqm for 1 MT/Sqm or part thereof
9.55 OHSR‐7B 750 KL, 18 m staging 1.00 Job               12,302,496                     12,302,496 
9.56 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                     630,000 
Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of
9.57 1.00 MT/Sqm                     880,000 
12 MT/Sqm for 1 MT/Sqm or part thereof
9.58 OHSR‐8 450 KL, 17 m staging 1.00 Job                 8,450,110                       8,450,110 
9.59 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                     440,000 
Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of
9.60 1.00 MT/Sqm                     610,000 
12 MT/Sqm for 1 MT/Sqm or part thereof
Page 8 of 20
Rates after  Rates after 
Amount  Amount Difference in 
S.no Item Description Qty Units Discount in figures  S.no Item Description Qty Units Discount in figures  Remarks
(in Rs.) (in Rs.) Amount (Rs.)
(in Rs.) (in Rs.)

9.61 OHSR‐8A 1050 KL, 18 m staging 1.00 Job               16,718,550                     16,718,550 


9.62 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                     860,000 
Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of
9.63 1.00 MT/Sqm                 1,200,000 
12 MT/Sqm for 1 MT/Sqm or part thereof
9.64 OHSR‐8B 750 KL, 18 m staging 1.00 Job               12,302,496                     12,302,496 
9.65 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                     630,000 
Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of
9.66 1.00 MT/Sqm                     880,000 
12 MT/Sqm for 1 MT/Sqm or part thereof
9.67 OHSR‐9 1000 KL, 18 m staging 1.00 Job               15,926,076                     15,926,076 
9.68 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                     820,000 
Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of
9.69 1.00 MT/Sqm                 1,140,000 
12 MT/Sqm for 1 MT/Sqm or part thereof
9.70 OHSR‐9A 1450 KL, 20 m staging 1.00 Job               23,475,692                     23,475,692 
9.71 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                 1,200,000 
Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of
9.72 1.00 MT/Sqm                 1,680,000 
12 MT/Sqm for 1 MT/Sqm or part thereof
9.73 OHSR‐10 700 KL, 12 m staging 1.00 Job               10,462,228                     10,462,228 
9.74 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                     540,000 
Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of
9.75 1.00 MT/Sqm                     750,000 
12 MT/Sqm for 1 MT/Sqm or part thereof
9.76 OHSR‐10A 950 KL, 20 m staging 1.00 Job               16,730,334                     16,730,334 
9.77 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                     860,000 
Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of
9.78 1.00 MT/Sqm                 1,200,000 
12 MT/Sqm for 1 MT/Sqm or part thereof
9.79 OHSR‐11 350 KL, 12 m staging 1.00 Job                 5,689,708                       5,689,708 
9.80 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                     290,000 
Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of
9.81 1.00 MT/Sqm                     410,000 
12 MT/Sqm for 1 MT/Sqm or part thereof
9.82 OHSR‐11A 650 KL, 20 m staging 1.00 Job               11,367,632                     11,367,632 
9.83 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                     580,000 
Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of
9.84 1.00 MT/Sqm                     820,000 
12 MT/Sqm for 1 MT/Sqm or part thereof
9.85 OHSR‐11B 650 KL, 20 m staging 1.00 Job               11,367,632                     11,367,632 
9.86 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                     580,000 
Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of
9.87 1.00 MT/Sqm                     820,000 
12 MT/Sqm for 1 MT/Sqm or part thereof
9.88 OHSR‐12 850 KL, 18 m staging 1.00 Job               13,795,136                     13,795,136 
9.89 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                     710,000 
Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of
9.90 1.00 MT/Sqm                     990,000 
12 MT/Sqm for 1 MT/Sqm or part thereof
9.91 OHSR‐12A 1100 KL, 17 m staging 1.00 Job               17,247,848                     17,247,848 
9.92 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                     880,000 
Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of
9.93 1.00 MT/Sqm                 1,230,000 
12 MT/Sqm for 1 MT/Sqm or part thereof
9.94 OHSR‐1 Belcup 500 KL, 24 m staging 1.00 Job                 9,987,922                       9,987,922 
9.95 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                     510,000 
Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of
9.96 1.00 MT/Sqm                     720,000 
12 MT/Sqm for 1 MT/Sqm or part thereof
9.97 OHSR‐2 Babhaech 550 KL, 18 m staging 1.00 Job                 9,500,850                       9,500,850 
9.98 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                     490,000 
Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of
9.99 1.00 MT/Sqm                     680,000 
12 MT/Sqm for 1 MT/Sqm or part thereof
10.00 OHSR‐3 Adalganj 850 KL, 24 m staging 1.00 Job               16,232,460                     16,232,460 
10.01 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                     830,000 
Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of
10.02 1.00 MT/Sqm                 1,160,000 
12 MT/Sqm for 1 MT/Sqm or part thereof
10.03 OHSR‐4 Markundi 400 KL, 15 m staging 1.00 Job                 6,685,456                       6,685,456 
10.04 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                     350,000 
Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of
10.05 1.00 MT/Sqm                     480,000 
12 MT/Sqm for 1 MT/Sqm or part thereof
10.06 OHSR‐5 Rudawali 50 KL, 15 m staging 1.00 Job                 2,776,114                       2,776,114 
10.07 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                     150,000 
Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of
10.08 1.00 MT/Sqm                     200,000 
12 MT/Sqm for 1 MT/Sqm or part thereof
10.09 OHSR‐6 Patwadh 400 KL, 18 m staging 1.00 Job                 7,712,628                       7,712,628 
10.10 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                     400,000 
Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of
10.11 1.00 MT/Sqm                     550,000 
12 MT/Sqm for 1 MT/Sqm or part thereof
10.12 OHSR‐7 Patwadh 200 KL, 12 m staging 1.00 Job                 3,920,144                       3,920,144 
10.13 Variation in Staging of RCC Overhead Tank increased/decreased  1.00 M                     200,000 
Extra for cost variation due to soil bearing capacity (SBC) from assumed SBC of
10.14 1.00 MT/Sqm                     280,000 
12 MT/Sqm for 1 MT/Sqm or part thereof
                 461,256,202                   412,867,170                 ‐48,389,032 

Page 9 of 20
Rates after  Rates after 
Amount  Amount Difference in 
S.no Item Description Qty Units Discount in figures  S.no Item Description Qty Units Discount in figures  Remarks
(in Rs.) (in Rs.) Amount (Rs.)
(in Rs.) (in Rs.)

Excavation of earth in ordinary soil (loam, clay or sand) for pipe line and rising Excavation of earth in ordinary soil (loam, clay or sand) for pipe line and
main /Feeder Main & Distribution System trenches including lift upto 1.50 m rising main /Feeder Main & Distribution System trenches including lift
upto 1.50 m and lead upto 50 m and refilling watering, ramming of the
and lead upto 50 m and refilling watering, ramming of the excavated earth into
10.00 10.00 excavated earth into the trench and also disposal of surplus earth upto
the trench and also disposal of surplus earth upto 50m from the center of the
50m from the center of the trenches including supply of all material
trenches including supply of all material labour, T&P etc required for proper labour, T&P etc required for proper completion of works as per
completion of works as per direction of the Engineer. direction of the Engineer.
10.01 Excavation of Hard Rock 108188 Cum.                         1,277                   138,155,604  10.01 Excavation of Hard Rock 159100 Cum.                         1,277                   203,170,700                   65,015,096 
10.02 Excavation of Medium Rock 108188 Cum.                            982                   106,240,253  10.02 Excavation of Medium Rock 315750 Cum.                            982                   310,066,500                 203,826,247 
10.03 Excavation in mixed soil with bajri kankar mooram etc. 432751 Cum.                            216                     93,474,112  10.03 Excavation in mixed soil with bajri kankar mooram etc. 432950 Cum.                            216                      93,517,200                          43,088 
10.04 Excavation in ordinary soil 1633241 Cum.                            147                   240,086,427  10.04 Excavation in ordinary soil 1978495 Cum.                            147                   290,838,765                   50,752,338 
                 577,956,395                   897,593,165                319,636,770 
Supply, Laying & Jointing of following sizes (G.I./HDPE / D.I. K‐7 / 9) pipes for Supply, Laying & Jointing of following sizes (G.I./HDPE / D.I. K‐7 / 9)
rising/feeder main & distribution system conforming to latest/relevant I.S.4984 pipes for rising/feeder main & distribution system conforming to
latest/relevant I.S.4984 / 14151 / 12786 / 13488, 8329/2000
/ 14151 / 12786 / 13488, 8329/2000 Specifications with all jointing materials
Specifications with all jointing materials such as CIS/S or D.F specials
such as CIS/S or D.F specials conforming to latest /relevant I.S. specifications
conforming to latest /relevant I.S. specifications with rubber gasket
with rubber gasket also, suitable for G.I. / D.I /HDPE pipes, as per IS‐1239 also, suitable for G.I. / D.I /HDPE pipes, as per IS‐1239 /2000 and IS
/2000 and IS 8329/2000 or their latest amendment including F.O.R. destination 8329/2000 or their latest amendment including F.O.R. destination and
11.00 and all taxes and insurance etc. with loading, unloading and Carting up to site 11.00 all taxes and insurance etc. with loading, unloading and Carting up to
of work, also including specials for these pipes and lowering them into the site of work, also including specials for these pipes and lowering them
into the trenches and laying true to alignment and gradient and
trenches and laying true to alignment and gradient and jointing etc. complete
jointing etc. complete (including hydro testing of pipe lines and cutting
(including hydro testing of pipe lines and cutting of pipes for making up the
of pipes for making up the length but excluding the cost of trenches).all
length but excluding the cost of trenches).all required for proper completion of required for proper completion of works as per direction of the
works as per direction of the Engineer. Engineer.
(Details of pipes in group given in seperate annex.) (Details of pipes in group given in seperate annex.)
11.01 50 mm dia GI Pipe 826637.00 Rmt                            467                   386,039,479  11.01 50 mm dia GI Pipe 187590.00 Rmt                            467                      87,604,530               ‐298,434,949 
11.02 65 mm dia GI Pipe 276206.00 Rmt                            598                   165,171,188  11.02 65 mm dia GI Pipe 72552.00 Rmt                            598                      43,386,096               ‐121,785,092 
11.03 80 mm dia GI Pipe 209796.00 Rmt                            735                   154,200,060  11.03 80 mm dia GI Pipe 28342.00 Rmt                            735                      20,831,370               ‐133,368,690 
11.04 100 mm dia DI Pipe Class K‐7 320070.00 Rmt                         1,119                   358,158,330  11.04 100 mm dia DI Pipe Class K‐7 40175.00 Rmt                         1,119                      44,955,825               ‐313,202,505 
11.05 150 mm dia DI pipe Class K‐7 290568.00 Rmt                         1,640                   476,531,520  11.05 150 mm dia DI pipe Class K‐7 32756.00 Rmt                         1,640                      53,719,840               ‐422,811,680 
11.06 200 mm dia DI pipe Class K‐7 151556.00 Rmt                         1,890                   286,440,840  11.06 200 mm dia DI pipe Class K‐7 92347.00 Rmt                         1,890                   174,535,830               ‐111,905,010 
11.07 250 mm dia DI pipe Class K‐7 101410.00 Rmt                         2,475                   250,989,750  11.07 250 mm dia DI pipe Class K‐7 90121.00 Rmt                         2,475                   223,049,475                 ‐27,940,275 
11.08 300 mm dia DI pipe Class K‐7 35487.00 Rmt                         3,118                   110,648,466  11.08 300 mm dia DI pipe Class K‐7 32444.00 Rmt                         3,118                   101,160,392                    ‐9,488,074 
11.09 350 mm dia DI pipe Class K‐7 32435.00 Rmt                         3,879                   125,815,365  11.09 350 mm dia DI pipe Class K‐7 3853.00 Rmt                         3,879                      14,945,787               ‐110,869,578 
11.10 400 mm dia DI pipe Class K‐7 8372.00 Rmt                         4,606                     38,561,432 
11.11 150 mm dia DI pipe Class K‐9 27818.00 Rmt                         1,964                     54,634,552  11.10 150 mm dia DI pipe Class K‐9 34060.00 Rmt                         1,964                      66,893,840                   12,259,288 
11.12 200 mm dia DI pipe Class K‐9 72783.00 Rmt                         2,313                   168,347,079  11.11 200 mm dia DI pipe Class K‐9 63424.00 Rmt                         2,313                   146,699,712                 ‐21,647,367 
11.13 250 mm dia DI pipe Class K‐9 35216.00 Rmt                         3,064                   107,901,824  11.12 250 mm dia DI pipe Class K‐9 75659.00 Rmt                         3,064                   231,819,176                 123,917,352 
11.14 300 mm dia DI pipe Class K‐9 41019.00 Rmt                         3,884                   159,317,796  11.13 300 mm dia DI pipe Class K‐9 41137.00 Rmt                         3,884                   159,776,108                        458,312 
11.15 350 mm dia DI pipe Class K‐9 5666.00 Rmt                         4,812                     27,264,792  11.14 350 mm dia DI pipe Class K‐9 10769.00 Rmt                         4,812                      51,820,428                   24,555,636 
11.16 400 mm dia DI pipe Class K‐9 19580.00 Rmt                         5,612                   109,882,960  11.15 400 mm dia DI pipe Class K‐9 43291.00 Rmt                         5,612                   242,949,092                 133,066,132 
11.17 600 mm dia DI pipe Class K‐9 27386.00 Rmt                       10,085                   276,187,810  11.16 600 mm dia DI pipe Class K‐9 25567.00 Rmt                      10,085                   257,843,195                 ‐18,344,615 
11.18 800 mm dia DI pipe Class K‐9 16642.00 Rmt                       15,810                   263,110,020  11.17 800 mm dia DI pipe Class K‐9 16779.00 Rmt                      15,810                   265,275,990                     2,165,970 
11.19 900 mm dia DI pipe Class K‐9 4476.00 Rmt                       19,100                     85,491,600  11.18 900 mm dia DI pipe Class K‐9 231.00 Rmt                      19,100                        4,412,100                 ‐81,079,500 
11.20 1000 mm dia DI pipe Class K‐9 18916.00 Rmt                       22,714                   429,658,024  11.19 1000 mm dia DI pipe Class K‐9 21881.00 Rmt                      22,714                   497,005,034                   67,347,010 
11.21 1100 mm dia DI pipe Class K‐9 600.00 Rmt                       26,691                     16,014,600 
11.22 63 mm dia HDPE PIPE(PE100) ‐ 6KG/CM2 2000.00 Rmt                            246                          492,000  11.20 63 mm dia HDPE PIPE(PE100) ‐ 6KG/CM2 1804340.00 Rmt                            246                   443,867,640                 443,375,640 
11.23 75 mm dia HDPE PIPE(PE100) ‐ 6KG/CM2 1000.00 Rmt                            344                          344,000  11.21 75 mm dia HDPE PIPE(PE100) ‐ 6KG/CM2 154661.00 Rmt                            344                      53,203,384                   52,859,384 
11.24 90 mm dia HDPE PIPE(PE100) ‐ 6KG/CM2 800.00 Rmt                            452                          361,600  11.22 90 mm dia HDPE PIPE(PE100) ‐ 6KG/CM2 144279.00 Rmt                            452                      65,214,108                   64,852,508 
11.25 110 mm dia HDPE PIPE(PE100) ‐ 6KG/CM2 600.00 Rmt                            648                          388,800  11.23 110 mm dia HDPE PIPE(PE100) ‐ 6KG/CM2 136720.00 Rmt                            648                      88,594,560                   88,205,760 
11.26 140 mm dia HDPE PIPE(PE100) ‐ 6KG/CM2 400.00 Rmt                         1,080                          432,000  11.24 140 mm dia HDPE PIPE(PE100) ‐ 6KG/CM2 163198.00 Rmt                         1,080                   176,253,840                 175,821,840 
11.27 160 mm dia HDPE PIPE(PE100) ‐ 6KG/CM2 200.00 Rmt                         1,178                          235,600  11.25 160 mm dia HDPE PIPE(PE100) ‐ 6KG/CM2 103311.00 Rmt                         1,178                   121,700,358                 121,464,758 
11.28 200 mm dia HDPE PIPE(PE100) ‐ 6KG/CM2 200.00 Rmt                         1,694                          338,800  11.26 200 mm dia HDPE PIPE(PE100) ‐ 6KG/CM2 101816.00 Rmt                         1,694                   172,476,304                 172,137,504 
MS Pipe as per IS 3589 and MS special 
1000mm Dia 8mm thick MS pipe with inside food grade epoxy coating
11.27 of 700 micron thickness and outside bitumen coating with 406 micron 3185.00 Rmt                      32,291                   102,846,835                 102,846,835 
thickness
1200mm Dia 9mm thick MS pipe with inside food grade epoxy coating
11.28 of 700 micron thickness and outside bitumen coating with 406 micron 700.00 Rmt                      34,655                      24,258,500                   24,258,500 
thickness
             4,052,960,287                3,937,099,349               ‐115,860,938 
Clearing & grubbing including uprooting of rank vegetation, grass,
Clearing & grubbing including uprooting of rank vegetation, grass, brush wood,
brush wood, trees and saplings incase of dense forest and removal of
12.00 trees and saplings incase of dense forest and removal of rubbish up to a 197775.00 Sqm                               20                       3,955,500  12.00 197775.00 Sqm                              20                        3,955,500  0
rubbish up to a distance of 50 m outside the periphery of the area
distance of 50 m outside the periphery of the area cleared
cleared
                     3,955,500                        3,955,500  0

Page 10 of 20
Rates after  Rates after 
Amount  Amount Difference in 
S.no Item Description Qty Units Discount in figures  S.no Item Description Qty Units Discount in figures  Remarks
(in Rs.) (in Rs.) Amount (Rs.)
(in Rs.) (in Rs.)

Filling in plinth and floors,bedding in trenches and filling in trenches of


Filling in plinth and floors murum bedding in trenches with approved murum
HDPE pipe at hard/medium rock locations with approved murum from
13.00 from excavated materials from foundation 15cm to 20cm layers including 1000.00 Cum.                            589                          589,000  13.00 147228 Cum.                            589                      86,717,205                   86,128,205 
excavated materials from foundation 15cm to 20cm layers including
watering and compaction complete.(Provisional)
watering and compaction complete.(Provisional)
                        589,000                      86,717,205                   86,128,205 
Supply and carting up to site of work of the following dia D.I. sluice valves, class Supply and carting up to site of work of the following dia D.I. sluice

I, working pressure 10 Kg/cm2 confirming to IS: 780/1969 or its latest valves, class I, working pressure 10 Kg/cm2 confirming to IS: 780/1969
or its latest amendments, F.O.R. destination, and lowering them into
amendments, F.O.R. destination, and lowering them into the already prepared
14.00 14.00 the already prepared trenches, fixing in position and jointing them
trenches, fixing in position and jointing them with pipelines and testing etc.
with pipelines and testing etc. complete and also including supply of
complete and also including supply of jointing materials etc. complete jointing materials etc. complete .including all taxes and insurance, as
.including all  taxes and insurance, as per instructions of Engineer ‐in ‐charge. per instructions of Engineer ‐in ‐charge.
14.01 50 mm  dia. 539.00 Nos.                         9,820                       5,292,980  14.01 150 mm dia. 27.00 Nos.                      21,604                           583,308                    ‐2,916,540 
14.02 65 mm dia. 232.00 Nos.                       12,275                       2,847,800  14.02 200 mm dia. 30.00 Nos.                      39,280                        1,178,400                    ‐1,885,440 
14.03 80 mm dia. 212.00 Nos.                       15,712                       3,330,944  14.03 250 mm dia. 35.00 Nos.                      58,920                        2,062,200                    ‐1,944,360 
14.04 100 mm dia.  180.00 Nos.                       17,676                       3,181,680  14.04 300 mm dia. 11.00 Nos.                      68,740                           756,140                    ‐2,543,380 
14.05 350 mm dia. 5.00 Nos.                    117,005                           585,025                    ‐2,691,115 
14.05 150 mm dia. 162.00 Nos.                       21,604                       3,499,848  14.06 400 mm dia. 17.00 Nos.                    164,902                        2,803,334                       ‐659,608 
14.06 200 mm dia. 78.00 Nos.                       39,280                       3,063,840  14.07 600 mm dia. 12.00 Nos.                    498,856                        5,986,272                     4,988,560 
14.07 250 mm dia. 68.00 Nos.                       58,920                       4,006,560  14.08 800mm dia. 3.00 Nos.                    805,240                        2,415,720                     1,610,480 
14.08 300 mm dia. 48.00 Nos.                       68,740                       3,299,520  14.09 900 mm dia 1.00 Nos.                 1,310,184                        1,310,184                       ‐162,816 
14.09 350 mm dia. 28.00 Nos.                     117,005                       3,276,140  14.10 1000 mm dia 12.00 Nos.                 1,473,000                      17,676,000                   17,676,000 
14.10 400 mm dia. 21.00 Nos.                     164,902                       3,462,942 
14.11 450 mm dia. 12.00 Nos.                     211,069                       2,532,828  Scour Valve
14.12 500 mm dia. 9.00 Nos.                     290,415                       2,613,735  14.11 150 mm dia 41.00 Nos.                      21,604                           885,764                        259,248 
14.13 600 mm dia. 2.00 Nos.                     498,856                          997,712  14.12 200 mm dia 43.00 Nos.                      39,280                        1,689,040                    ‐1,649,760 
14.14 800mm dia. 1.00 Nos.                     805,240                          805,240  14.13 300 mm dia 12.00 Nos.                      68,740                           824,880                 ‐51,343,583 
14.15 900mm dia. 1.00 Nos.                 1,310,184                       1,310,184  14.14 400mm dia 8.00 Nos.                    164,902                        1,319,216                     1,319,216 
14.16 1000 mm dia 1.00 Nos.                 1,473,000                       1,473,000  14.15 500mm dia 1.00 Nos.                    290,415                           290,415                        173,145 
Scour Valve 14.16 600mm dia 8.00 Nos.                    498,856                        3,990,848                     3,376,118 
14.17 50 mm  dia. 144.00 Nos.                         9,820                       1,414,080 
14.18 65 mm dia. 26.00 Nos.                       12,275                          319,150 
14.19 80 mm dia. 32.00 Nos.                       15,712                          502,784 
14.20 100 mm dia 55.00 Nos.                       17,676                          972,180 
14.21 150 mm dia 29.00 Nos.                       21,604                          626,516 
14.22 200 mm dia 85.00 Nos.                       39,280                       3,338,800 
                   52,168,463                      44,356,746                   ‐7,811,717 
Pressure Reducing Valve (Distribution System) ‐ Providing and fixing Pressure Pressure Reducing Valve (Distribution System) ‐ Providing and fixing
reducing valves PN‐16 of approved make confirming to relevant ISS with latest Pressure reducing valves PN‐16 of approved make confirming to
amendments of following diameters and types and conveying to work site, relevant ISS with latest amendments of following diameters and types

loading, unloading, stacking, and fixing DI valve with tail pieces, etc. complete and conveying to work site, loading, unloading, stacking, and fixing DI
valve with tail pieces, etc. complete with all lead and lifts and as
with all lead and lifts and as directed by Engineer‐in‐charge.The rate is inclusive
directed by Engineer‐in‐charge.The rate is inclusive of cost of requird
15.00 of cost of requird numbers of bolt, nuts, rubber packing, MS flanges MS tail 15.00
numbers of bolt, nuts, rubber packing, MS flanges MS tail pieces,
pieces, reducers etc. complete in order to succesfully install with water
reducers etc. complete in order to succesfully install with water
tightness. Material of construction shall be as follows: Body & Cover – Ductile tightness. Material of construction shall be as follows: Body & Cover –
Iron EN 1563 (ASTM A 536). Internal parts – Stainless steel & Bronze. Control Ductile Iron EN 1563 (ASTM A 536). Internal parts – Stainless steel &
Trim ‐ Stainless steel 316 Elastomer ‐ EPDM Coating ‐ Fusion bonded epoxy, Bronze. Control Trim ‐ Stainless steel 316 Elastomer ‐ EPDM Coating ‐
WRAS approved. Fusion bonded epoxy, WRAS approved.
15.01 50mm dia. 1.00 Nos.                     117,270                          117,270  15.01 50mm dia. 1.00 Nos.                    117,270                           117,270  0.00
15.02 65mm dia. 5.00 Nos.                     122,946                          614,730  15.02 65mm dia. 5.00 Nos.                    122,946                           614,730  0.00
15.03 80mm dia. 5.00 Nos.                     128,740                          643,700  15.03 80mm dia. 5.00 Nos.                    128,740                           643,700  0.00
15.04 100mm dia. 22.00 Nos.                     165,074                       3,631,628  15.04 100mm dia. 22.00 Nos.                    165,074                        3,631,628  0.00
15.05 150mm dia. 21.00 Nos.                     267,791                       5,623,611  15.05 150mm dia. 21.00 Nos.                    267,791                        5,623,611  0.00
15.06 200mm dia. 6.00 Nos.                     354,797                       2,128,782  15.06 200mm dia. 6.00 Nos.                    354,797                        2,128,782  0.00
15.07 250mm dia. 3.00 Nos.                     468,905                       1,406,715  15.07 250mm dia. 3.00 Nos.                    468,905                        1,406,715  0.00
15.08 300mm dia. 2.00 Nos.                     669,920                       1,339,840  15.08 300mm dia. 2.00 Nos.                    669,920                        1,339,840  0.00
                   15,506,276                      15,506,276  0.00
Supply and installation of under ground sluice value type fire hydrant
consisting of 100 mm dia sluice valve, 100mm dia tail pieces, 100mm dia duck Supply and installation of under ground sluice value type fire hydrant
foot bend and 100 mm dia standard makes iron coupling with cap and etc. consisting of 100 mm dia sluice valve, 100mm dia tail pieces, 100mm
complete conforming to latest/relevent I.S.specifications including all taxes and dia duck foot bend and 100 mm dia standard makes iron coupling with
insurance up to site of work and lowering them into the trenches, fixing in cap and etc. complete conforming to latest/relevent I.S.specifications
16.00 position and jointing them with pipelines and testing etc. complete (including 16.00
including all taxes and insurance up to site of work and lowering them
supply of jointing materials etc. complete as per instructions of Engineer.(100 into the trenches, fixing in position and jointing them with pipelines
mm diameter) and testing etc. complete (including supply of jointing materials etc.
complete as per instructions of Engineer.(100 mm diameter)

16.01 100mm 39.00 Nos.                       40,262                       1,570,218  16.01 100mm 55.00 Nos.                      40,262                        2,214,410                        644,192 
Page 11 of 20
Rates after  Rates after 
Amount  Amount Difference in 
S.no Item Description Qty Units Discount in figures  S.no Item Description Qty Units Discount in figures  Remarks
(in Rs.) (in Rs.) Amount (Rs.)
(in Rs.) (in Rs.)

                     1,570,218                        2,214,410                        644,192 


Providing and supplying Kinetic Double Orifice type Air Valves confirming to IS
14845 specifications having small orifice elastic ball resting on a gun metal Providing and supplying Kinetic Double Orifice type Air Valves
orifice nipple, large orifice vulcanite ball seating on moulded seat ring, with confirming to IS 14845 specifications having small orifice elastic ball
built in Kinetic features, isolating sluice valve mounted in horizontal position resting on a gun metal orifice nipple, large orifice vulcanite ball seating
17.00 and operated by wheel gearing, inlet face and drilled, including 17.00 on moulded seat ring, with built in Kinetic features, isolating sluice
insurance,loading, unloading, transporation upto stores in all respect etc valve mounted in horizontal position and operated by wheel gearing,
complete inlet face and drilled, including insurance,loading, unloading,
transporation upto stores in all respect etc complete

17.01 40mm dia 119.00 Nos.                       17,185                       2,045,015  17.01 50 mm dia 44.00 Nos.                      22,291                           980,804                    ‐1,064,211 
17.02 50 mm dia 124.00 Nos.                       22,291                       2,764,084  17.02 80 mm dia 87.00 Nos.                      27,496                        2,392,152                       ‐371,932 
17.03 80 mm dia 126.00 Nos.                       27,496                       3,464,496  17.03 100 mm dia 31.00 Nos.                      29,460                           913,260                    ‐2,551,236 
17.04 100 mm dia 109.00 Nos.                       29,460                       3,211,140  17.04 150 mm dia 46.00 Nos.                      37,660                        1,732,360                    ‐1,478,780 
17.05 150 mm dia 150.00 Nos.                       37,660                       5,649,000 
                   17,133,735                        6,018,576                 ‐11,115,159 
Construction of following type chambers as per department type design and Construction of following type chambers as per department type design
drawing including Heavy duty R.C.C. Manhole Cover and all materials, labour, and drawing including Heavy duty R.C.C. Manhole Cover and all
18.00 18.00
T&P etc complete for proper completion of work as per instructions of materials, labour, T&P etc complete for proper completion of work as
Engineer. (masonry Type) per instructions of Engineer. (masonry Type)
Sluice valve chamber (masonry Type) Sluice valve chamber (masonry Type)
18.01 Upto 200 mm Dia. 417.00 Nos.                       17,578                       7,330,026  18.01 Upto 200 mm Dia. 57.00 Nos.                      17,578                        1,001,946                    ‐6,328,080 
18.02 SV Chamber for 250mm dia ‐300 mm dia 119.00 Nos.                       37,807                       4,499,033  18.02 SV Chamber for 250mm dia ‐300 mm dia 46.00 Nos.                      37,807                        1,739,122                    ‐2,759,911 
18.03 Sluice Valve Chamber for 350‐400 Dia 46.00 Nos.                       47,725                       2,195,350  18.03 Sluice Valve Chamber for 350‐400 Dia 22.00 Nos.                      47,725                        1,049,950                    ‐1,145,400 
18.04 Sluice Valve Chamber  500 ‐ 600mm Dia 22.00 Nos.                       64,714                       1,423,708  18.04 Sluice Valve Chamber  500 ‐ 600mm Dia 12.00 Nos.                      64,714                           776,568                       ‐647,140 
18.05 Sluice Valve Chamber  700 ‐ 800mm Dia 3.00 Nos.                       73,945                          221,835  18.05 Sluice Valve Chamber  700 ‐ 800mm Dia 3.00 Nos.                      73,945                           221,835  0.00
18.06 Sluice Valve Chamber  900 ‐ 1000 mm Dia 2.00 Nos.                       86,514                          173,028  18.06 Sluice Valve Chamber  900 ‐ 1000 mm Dia 13.00 Nos.                      86,514                        1,124,682                        951,654 
18.07 Sluice valve chamber (surface box Type)
18.08 Sluice valve chamber (surface box Type) 1114.00 Nos.                         9,820                     10,939,480  18.07 Sluice valve chamber (surface box Type) 653.00 Nos.                         9,820                        6,412,460                    ‐4,527,020 
Air Valve Chamber Air Valve Chamber
18.09  Air Valve Chamber 50mm dia ‐ 80 mm dia 370.00 Nos.                       41,931                     15,514,470  18.08  Air Valve Chamber 50mm dia ‐ 80 mm dia 131.00 Nos.                      41,931                        5,492,961                 ‐10,021,509 
18.10  Air Valve Chamber 100mm dia ‐ 150 mm dia 259.00 Nos.                       49,787                     12,894,833  18.09  Air Valve Chamber 100mm dia ‐ 150 mm dia 77.00 Nos.                      49,787                        3,833,599                    ‐9,061,234 
Scour valve chamber Scour valve chamber
18.11 Scour Valve Chamber 50mm dia ‐ 100 mm dia  276.00 Nos.                       21,309                       5,881,284  18.10 Scour Valve Chamber 150mm dia ‐ 200 mm dia  84.00 Nos.                      23,077                        1,938,468                    ‐3,942,816 
18.12 Scour Valve Chamber 150mm dia ‐ 200 mm dia  114.00 Nos.                       23,077                       2,630,778  18.11 Scour Valve Chamber 250MM DIA ‐ 300mm dia 12.00 Nos.                      49,527                           594,326                    ‐2,036,452 
Fire Hydrant chamber 18.12 Scour Valve Chamber 350MM DIA ‐ 400mm dia 8.00 Nos.                      62,520                           500,158                        500,158 
18.13 Fire Hydrant chamber 39.00 Nos.                       24,550                          957,450  18.13 Scour Valve Chamber 500mm dia ‐ 600mm dia 9.00 Nos.                      84,775                           762,978                       ‐194,472 
PRV Valve Chamber Fire Hydrant chamber
18.14  Chamber (1 x 1 x 1.2 m) Dia <150mm 33.00 Nos.                       21,408                          706,464  18.14 Fire Hydrant chamber 55.00 Nos.                      24,550                        1,350,250                        392,800 
18.15  Chamber (1.2m x 1m x 1.2 m) Dia 200mm‐300mm 27.00 Nos.                       29,460                          795,420  PRV Valve Chamber
18.16  Chamber (1.2m x 1.2m x 1.2 m) Dia 400mm‐600mm 5.00 Nos.                       31,424                          157,120  18.15  Chamber (1 x 1 x 1.2 m) Dia <150mm 54.00 Nos.                      21,408                        1,156,032                        449,568 
18.16  Chamber (1.2m x 1m x 1.2 m) Dia 200mm‐300mm 11.00 Nos.                      29,460                           324,060                       ‐471,360 

                   66,320,279                      28,279,395                 ‐38,040,884 


Design and construction of Thrust Block made in R.C.C. with cement, coarse Design and construction of Thrust Block made in R.C.C. with cement,
sand & 20 mm gauge stone ballast in proportion of 1:1.5:3, for pipe line, coarse sand & 20 mm gauge stone ballast in proportion of 1:1.5:3, for
including supply of MS reinforcement wrought to required shape as necessary pipe line, including supply of MS reinforcement wrought to required
,its bending, fixing & binding the same with 0.50 mm thick binding wire in shape as necessary ,its bending, fixing & binding the same with 0.50
19.00 19.00
position & necessary centering & shuttering including curing and supply of all mm thick binding wire in position & necessary centering & shuttering
materials, labour, T & P etc. required for proper completion of the work and as including curing and supply of all materials, labour, T & P etc. required
per specifications for RCC work for following pipe diameter as per instructions for proper completion of the work and as per specifications for RCC
of Engineer. work for following pipe diameter as per instructions of Engineer.
19.01  Pipe Dia up to 100mm 40.00 Nos.                         6,088                          243,520  19.01  Pipe Dia 150mm 132.00 Nos.                      11,588                        1,529,616                     1,286,096 
19.02  Pipe Dia 150mm 101.00 Nos.                       11,588                       1,170,388  19.02 Pipe Dia  200mm  233.00 Nos.                      19,051                        4,438,883                     3,268,495 
19.03 Pipe Dia  200mm  134.00 Nos.                       19,051                       2,552,834  19.03 Pipe Dia  250mm  330.00 Nos.                      21,604                        7,129,320                     4,576,486 
19.04 Pipe Dia  250mm  158.00 Nos.                       21,604                       3,413,432  19.04 Pipe Dia  300mm  171.00 Nos.                      27,103                        4,634,613                     1,221,181 
19.05 Pipe Dia  300mm  32.00 Nos.                       27,103                          867,296  19.05 Pipe Dia 350mm 48.00 Nos.                      30,148                        1,447,104                        579,808 
19.06 Pipe Dia  400mm  115.00 Nos.                       33,192                       3,817,080  19.06 Pipe Dia  400mm  173.00 Nos.                      33,192                        5,742,216                     1,925,136 
19.07 Pipe Dia  450mm  4.00 Nos.                       39,869                          159,476  19.07 Pipe Dia  600mm  102.00 Nos.                      47,136                        4,807,872                     4,648,396 
19.08 Pipe Dia  500mm  4.00 Nos.                       43,797                          175,188  19.08 Pipe Dia  800mm  86.00 Nos.                      63,634                        5,472,524                     5,297,336 
19.09 Pipe Dia  600mm  61.00 Nos.                       47,136                       2,875,296  19.09 Pipe Dia  900mm  3.00 Nos.                      72,864                           218,592                    ‐2,656,704 
19.10 Pipe Dia  800mm  25.00 Nos.                       63,634                       1,590,850  19.10 Pipe Dia  1000mm  154.00 Nos.                      82,095                      12,642,630                   11,051,780 
19.11 Pipe Dia  900mm  94.00 Nos.                       72,864                       6,849,216 
19.12 Pipe Dia  1000mm  4.00 Nos.                       82,095                          328,380 
                   24,042,956                      48,063,370                   24,020,414 
Dismantling of Following type of surfaces including sorting out and stacking of  Dismantling of Following type of surfaces including sorting out and
serviceable materials and disposal of unserviceable materials upto a distance of 
20.00 50m as per instructions of Engineer 20.00 stacking of serviceable materials and disposal of unserviceable

materials upto a distance of 50m as per instructions of Engineer
Page 12 of 20
Rates after  Rates after 
Amount  Amount Difference in 
S.no Item Description Qty Units Discount in figures  S.no Item Description Qty Units Discount in figures  Remarks
(in Rs.) (in Rs.) Amount (Rs.)
(in Rs.) (in Rs.)

20.01 Bituminous Road 100597.00 sqm                            147                     14,787,759  20.01 Bituminous Road 100597.00 sqm                            147                      14,787,759  0.00
20.02 CC Road 2931.00 sqm                            314                          920,334  20.02 CC Road 2931.00 sqm                            314                           920,334  0.00
20.03 BOE Road 9568.00 sqm                               79                          755,872  20.03 BOE Road 9568.00 sqm                              79                           755,872  0.00
20.04 Interlocking Road 2574.00 sqm                            142                          365,508  20.04 Interlocking Road 2574.00 sqm                            142                           365,508  0.00
                   16,829,473                      16,829,473  0.00
Restoration of the following type of road surface with old and new materials Restoration of the following type of road surface with old and new
21.00 including supply of all materials, labour, T&P etc. required for proper 21.00 materials including supply of all materials, labour, T&P etc. required for
completion of the work as per instructions of Engineer. proper completion of the work as per instructions of Engineer.
21.01 Bituminous Road 100597.00 sqm                         1,375                   138,320,875  21.01 Bituminous Road 100597.00 sqm                         1,375                   138,320,875  0.00
21.02 CC Road 2931.00 sqm                         2,455                       7,195,605  21.02 CC Road 2931.00 sqm                         2,455                        7,195,605  0.00
21.03 BOE Road 9568.00 sqm                            786                       7,520,448  21.03 BOE Road 9568.00 sqm                            786                        7,520,448  0.00
21.04 Interlocking Road 2574.00 sqm                            982                       2,527,668  21.04 Interlocking Road 2574.00 sqm                            982                        2,527,668  0.00
                 155,564,596                   155,564,596  0.00
Construction of single tap pillar type stand post as per type design as per Construction of single tap pillar type stand post as per type design as
22.00 653.00 Nos.                       19,640                     12,824,920  22.00 653.00 Nos.                      19,640                      12,824,920  0.00
instructions of Engineer per instructions of Engineer
                   12,824,920                      12,824,920  0.00
Survey, Investigation, Design, Drawing, Planning, Construction as per latest I.S. Survey, Investigation, Design, Drawing, Planning, Construction as per
CODE, for Nala crossing, including excavation in soil mixed with moorum, latest I.S. CODE, for Nala crossing, including excavation in soil mixed
shingle, kankar, soft rock, hard rock for foundation, dewatering and diveration with moorum, shingle, kankar, soft rock, hard rock for foundation,
of water, PCC M‐15 for bedding, RCC M‐25 for foundation/piles, pedestral, MS dewatering and diveration of water, PCC M‐15 for bedding, RCC M‐25
claps of required width and thickness with one coats of anticorrosive paint and for foundation/piles, pedestral, MS claps of required width and
over it two coats of oil painting, including all fastening arrangement nut and thickness with one coats of anticorrosive paint and over it two coats of
23.00 bolts, all type steel bars of approved quality and cement as approved by the 23.00 oil painting, including all fastening arrangement nut and bolts, all type
employer, Mild Steel or iron work, other unforeseen Items, site clearance, etc., steel bars of approved quality and cement as approved by the
as per detailed design and drawing or as directed by Engineer‐in‐charge employer, Mild Steel or iron work, other unforeseen Items, site
clearance, etc., as per detailed design and drawing or as directed by
Engineer‐in‐charge

Nallah Crossing RCC Pier over pile cap and pile Nallah Crossing RCC Pier over pile cap and pile
23.01 Up to 65 mm ‐ 100 mm dia 84.00 Mtr.                       39,280                       3,299,520  23.01 Up to 65 mm ‐ 100 mm dia 84.00 Mtr.                      39,280                        3,299,520  0.00
23.02 150mm ‐ 200 mm dia 222.00 Mtr.                       44,190                       9,810,180  23.02 150mm ‐ 200 mm dia 222.00 Mtr.                      44,190                        9,810,180  0.00
23.03 250mm ‐ 300 mm dia 127.00 Mtr.                       46,154                       5,861,558  23.03 250mm ‐ 300 mm dia 127.00 Mtr.                      46,154                        5,861,558  0.00
23.04 350mm ‐ 400 mm dia 115.00 Mtr.                       47,136                       5,420,640  23.04 350mm ‐ 400 mm dia 115.00 Mtr.                      47,136                        5,420,640  0.00
23.05 450mm ‐ 500 mm dia 55.00 Mtr.                       48,118                       2,646,490  23.05 450mm ‐ 500 mm dia 55.00 Mtr.                      48,118                        2,646,490  0.00
23.06 600mm ‐ 700 mm dia 120.00 Mtr.                       54,010                       6,481,200  23.06 600mm ‐ 700 mm dia 120.00 Mtr.                      54,010                        6,481,200  0.00
Nallah Crossing with RCC Pedestral  Nallah Crossing with RCC Pedestral 
23.07  Size 400 mm X 300 mm X 900 mm 90.00 Nos.                         2,553                          229,770  23.07  Size 400 mm X 300 mm X 900 mm 90.00 Nos.                         2,553                           229,770  0.00
23.08 Size 450 mm X 300 mm X 900 mm 111.00 Nos.                         2,750                          305,250  23.08 Size 450 mm X 300 mm X 900 mm 111.00 Nos.                         2,750                           305,250  0.00
23.09 Size 500 mm X 300 mm X 900 mm 170.00 Nos.                         2,946                          500,820  23.09 Size 500 mm X 300 mm X 900 mm 170.00 Nos.                         2,946                           500,820  0.00
23.10 Size 550 mm X 300 mm X 900 mm 281.00 Nos.                         3,241                          910,721  23.10 Size 550 mm X 300 mm X 900 mm 281.00 Nos.                         3,241                           910,721  0.00
23.11 Size 600mm X 300mm X 1000 mm 254.00 Nos.                         3,633                          922,782  23.11 Size 600mm X 300mm X 1000 mm 254.00 Nos.                         3,633                           922,782  0.00
23.12 Size 700mm X 300mm X 1000 mm 617.00 Nos.                         4,615                       2,847,455  23.12 Size 700mm X 300mm X 1000 mm 617.00 Nos.                         4,615                        2,847,455  0.00
23.13 Size 750mm X 300mm X 1000 mm 29.00 Nos.                         4,910                          142,390  23.13 Size 750mm X 300mm X 1000 mm 29.00 Nos.                         4,910                           142,390  0.00
23.14 Size 900mm X 300m mm X1000 mm 132.00 Nos.                         5,401                          712,932  23.14 Size 900mm X 300m mm X1000 mm 132.00 Nos.                         5,401                           712,932  0.00
23.15 Size 1000mmX300mX1000 mm  98.00 Nos.                         5,990                          587,020  23.15 Size 1000mmX300mX1000 mm  98.00 Nos.                         5,990                           587,020  0.00
23.16 Size 1100 mm X 300m X 1000 mm 50.00 Nos.                         6,481                          324,050  23.16 Size 1100 mm X 300m X 1000 mm 50.00 Nos.                         6,481                           324,050  0.00
                   41,002,778                      41,002,778  0.00
Road Crossing with open cut ‐ Excavation in foundation of trench of proper size Road Crossing with open cut ‐ Excavation in foundation of trench of
in soil mixed with moorum, Shingle, Kankar, soft rock, hard rock, including proper size in soil mixed with moorum, Shingle, Kankar, soft rock, hard
refilling, dressing and ramming earth or sand or bajri, ballast, including rock, including refilling, dressing and ramming earth or sand or bajri,
providing, supply, carting, lowering, laying and jointing of casing pipe of RCC ballast, including providing, supply, carting, lowering, laying and
NP‐3 with appropriate size, with rubber ring joint, sand filling in gap inside RCC jointing of casing pipe of RCC NP‐3 with appropriate size, with rubber
pipe, insertion of distribution pipe into the encasing pipe including supply of ring joint, sand filling in gap inside RCC pipe, insertion of distribution
24.00 T&P, including concrete of 150 mm thick in with 40mm gauge brick ballast 24.00 pipe into the encasing pipe including supply of T&P, including concrete
local sand and cement in proportion of 8:4:1, provision for barricading, labour of 150 mm thick in with 40mm gauge brick ballast local sand and
for traffic diversion etc. Complete for proper completion of work as per cement in proportion of 8:4:1, provision for barricading, labour for
instruction of Engineer. traffic diversion etc. Complete for proper completion of work as per
instruction of Engineer.

24.01 50 mm dia. Pipe 1104.00 Mtr.                         1,375                       1,518,000  24.01 50 mm dia. Pipe 1104.00 Mtr.                         1,375                        1,518,000  0.00
24.02 65‐100 mm dia. Pipe 1500.00 Mtr.                         1,669                       2,503,500  24.02 65‐100 mm dia. Pipe 1500.00 Mtr.                         1,669                        2,503,500  0.00
24.03 125‐150 mm dia. Pipe 1600.00 Mtr.                         2,062                       3,299,200  24.03 125‐150 mm dia. Pipe 1600.00 Mtr.                         2,062                        3,299,200  0.00
24.04 200 mm dia. Pipe 1350.00 Mtr.                         2,259                       3,049,650  24.04 200 mm dia. Pipe 1350.00 Mtr.                         2,259                        3,049,650  0.00
24.05 250 mm dia. Pipe 750.00 Mtr.                         3,633                       2,724,750  24.05 250 mm dia. Pipe 750.00 Mtr.                         3,633                        2,724,750  0.00
24.06 300 mm dia. Pipe 450.00 Mtr.                         4,419                       1,988,550  24.06 300 mm dia. Pipe 450.00 Mtr.                         4,419                        1,988,550  0.00
24.07 350 mm dia. Pipe 350.00 Mtr.                         4,714                       1,649,900  24.07 350 mm dia. Pipe 350.00 Mtr.                         4,714                        1,649,900  0.00
24.08 400 mm dia. Pipe 214.00 Mtr.                         5,303                       1,134,842  24.08 400 mm dia. Pipe 214.00 Mtr.                         5,303                        1,134,842  0.00
24.09 450‐500 mm dia. Pipe 350.00 Mtr.                         6,579                       2,302,650  24.09 450‐500 mm dia. Pipe 350.00 Mtr.                         6,579                        2,302,650  0.00
24.10 600 mm dia. Pipe 184.00 Mtr.                         7,660                       1,409,440  24.10 600 mm dia. Pipe 184.00 Mtr.                         7,660                        1,409,440  0.00
24.11 800 mm dia. Pipe 154.00 Mtr.                       10,507                       1,618,078  24.11 800 mm dia. Pipe 154.00 Mtr.                      10,507                        1,618,078  0.00
24.12 900 mm dia. Pipe 110.00 Mtr.                       11,980                       1,317,800  24.12 900 mm dia. Pipe 110.00 Mtr.                      11,980                        1,317,800  0.00
                   24,516,360                      24,516,360  0.00
Page 13 of 20
Rates after  Rates after 
Amount  Amount Difference in 
S.no Item Description Qty Units Discount in figures  S.no Item Description Qty Units Discount in figures  Remarks
(in Rs.) (in Rs.) Amount (Rs.)
(in Rs.) (in Rs.)

Survey, Investigation, Design, Drawing, Planning, Construction as per latest I.S.


CODE, for River crossing, including excavation in soil mixed with moorum,
Survey, Investigation, Design, Drawing, Planning, Construction as per
shingle, kankar, soft rock, hard rock for foundation, dewatering and diveration
latest I.S. CODE, for River crossing, including excavation in soil mixed
of water,construction of coffer dam, PCC M‐15 for bedding, RCC M‐30 grade
with moorum, shingle, kankar, soft rock, hard rock for foundation,
for foundation/raft/piles, RCC M‐30 grade for pedestral & chairs, MS clamps of
dewatering and diveration of water,construction of coffer dam, PCC M‐
required width and thickness, including all fastening arrangement nut and
15 for bedding, RCC M‐30 grade for foundation/raft/piles, RCC M‐30
bolts, all type steel bars of approved quality and cement as approved by the
grade for pedestral & chairs, MS clamps of required width and
employer, Mild Steel or iron work, stuctural steel work in single stanchions
thickness, including all fastening arrangement nut and bolts, all type
composed of RSJ, channel, etc, with caps, bases, mild steel plates, angles,
steel bars of approved quality and cement as approved by the
25.00 brackets, cleats, gusset plates, anchor bolts, etc. including cutting, fabrication, 25.00
employer, Mild Steel or iron work, stuctural steel work in single
hoisting, erecting, fixing in position, making riveted/ bolted / welded
stanchions composed of RSJ, channel, etc, with caps, bases, mild steel
connections and one coats of anticorrosive paint and over it two coats of oil
plates, angles, brackets, cleats, gusset plates, anchor bolts, etc.
painting, etc other unforeseen Items, site clearance, etc. as per detailed design
including cutting, fabrication, hoisting, erecting, fixing in position,
and drawing or as directed by Engineer‐in‐charge
making riveted/ bolted / welded connections and one coats of
anticorrosive paint and over it two coats of oil painting, etc other
unforeseen Items, site clearance, etc. as per detailed design and
drawing or as directed by Engineer‐in‐charge

25.01 RCC Pier over pile cap and pile for dia up to 100mm ‐  200mm 100.00 Mtr.                       73,650                       7,365,000  25.01 RCC Pier over pile cap and pile for  dia up to 100mm ‐  200mm 100.00 Mtr.                      73,650                        7,365,000  0.00
                     7,365,000                        7,365,000  0.00

Survey site Investigation Planning , design Drawings as per State Road


Survey site Investigation Planning , design Drawings as per State Road manual manual and vetting / checked from State Road Divisional Office and
and vetting / checked from State Road Divisional Office and taking NOC for taking NOC for trenchless crossing of National highway road and
trenchless crossing of National highway road and Railway track(crossing length Railway track(crossing length 15m to 25m ), Road for of required dia
15m to 25m ), Road for of required dia Rising main pipe with casing pipe as Rising main pipe with casing pipe as required for proper completion of
required for proper completion of work also including security money work also including security money deposited to State Road
deposited to State Road department and Execution of all work in the present department and Execution of all work in the present of State Road staff
of State Road staff / Engineers including of supply of required dia MS carrier / Engineers including of supply of required dia MS carrier pipe and
pipe and required size of MS casing pipe as per drawing and as per (IS:3589 & required size of MS casing pipe as per drawing and as per (IS:3589 &
made from confining to IS:2062) with 750 Micron PU coating internally and made from confining to IS:2062) with 750 Micron PU coating internally
26.00 26.00
250 micron anti corrosive bituminous paint externally by trenchless technology and 250 micron anti corrosive bituminous paint externally by trenchless
method at an average depth 3.60 mtr from normal ground level up to top of technology method at an average depth 3.60 mtr from normal ground
casing pipe including excavation & filling of Pit, Dewatering arrangement, level up to top of casing pipe including excavation & filling of Pit,
Supporting system for soil, also including supply and fixing of 2 no Sluice valve Dewatering arrangement, Supporting system for soil, also including
ISI Mark, construction of sluice valve chamber etc. all complete work including supply and fixing of 2 no Sluice valve ISI Mark, construction of sluice
supply & fixing specials in carrier pipe over main pipe, as per specification given valve chamber etc. all complete work including supply & fixing specials
in the bid documents including supply of all materials, labour T&P etc. for in carrier pipe over main pipe, as per specification given in the bid
proper completion of work as per instruction of Engineer. documents including supply of all materials, labour T&P etc. for proper
completion of work as per instruction of Engineer.

Road Crossing   Road Crossing  
26.01 50 mm 100.00 Mtr.                         7,561                          756,100  26.01 50 mm 100.00 Mtr.                         7,561                           756,100  0.00
26.02 65 mm 100.00 Mtr.                         7,561                          756,100  26.02 65 mm 100.00 Mtr.                         7,561                           756,100  0.00
26.03 80mm 61.00 Mtr.                         7,561                          461,221  26.03 80mm 61.00 Mtr.                         7,561                           461,221  0.00
26.04 100mm 100.00 Mtr.                         9,427                          942,700  26.04 100mm 100.00 Mtr.                         9,427                           942,700  0.00
26.05 125 mm 100.00 Mtr.                       13,944                       1,394,400  26.05 125 mm 100.00 Mtr.                      13,944                        1,394,400  0.00
26.06 150mm 100.00 Mtr.                       13,944                       1,394,400  26.06 150mm 100.00 Mtr.                      13,944                        1,394,400  0.00
26.07 200mm 100.00 Mtr.                       16,301                       1,630,100  26.07 200mm 100.00 Mtr.                      16,301                        1,630,100  0.00
26.08 250mm 98.00 Mtr.                       21,899                       2,146,102  26.08 250mm 98.00 Mtr.                      21,899                        2,146,102  0.00
26.09 300mm 100.00 Mtr.                       25,630                       2,563,000  26.09 300mm 100.00 Mtr.                      25,630                        2,563,000  0.00
26.10 450mm 17.00 Mtr.                       47,136                          801,312  26.10 450mm 17.00 Mtr.                      47,136                           801,312  0.00
Railway Crossing Railway Crossing
26.11 500mm 60.00 Mtr.                       58,920                       3,535,200  26.11 500mm 60.00 Mtr.                      58,920                        3,535,200  0.00
                   16,380,635                      16,380,635  0.00
Making house connection should be done atleast 2 m inside the boundary wall Making house connection should be done atleast 2 m inside the
with provision of tap from distribution line to outer wall of house, with supply boundary wall with provision of tap from distribution line to outer wall
of 1 m G.I. pipe & average 10.0 mtr. MDP Pipe including specials, Brass ferrule, of house, with supply of 1 m G.I. pipe & average 10.0 mtr. MDP Pipe
Saddle clamp etc. of suitable size, T&P etc. including excavation, laying and including specials, Brass ferrule, Saddle clamp etc. of suitable size, T&P
27.00 121719.00 Nos.                         2,558                   311,357,202  27.00 121719.00 Nos.                         2,558                   311,357,202  0.00
jointing for proper completion of work as per instructions of Engineer etc. including excavation, laying and jointing for proper completion of
work as per instructions of Engineer

                 311,357,202                   311,357,202  0.00

Page 14 of 20
Rates after  Rates after 
Amount  Amount Difference in 
S.no Item Description Qty Units Discount in figures  S.no Item Description Qty Units Discount in figures  Remarks
(in Rs.) (in Rs.) Amount (Rs.)
(in Rs.) (in Rs.)

Construction of 1.5 m high and 115mm thick boundary wall with 230 mmx230 Construction of 1.5 m high and 115mm thick boundary wall with 230
mm thick pillar made in Brick masonry in 1 cement and 4 sand mortar, the mmx230 mm thick pillar made in Brick masonry in 1 cement and 4 sand
spacing between two pillar should not be more than 3.0 m c/c and the depth of mortar, the spacing between two pillar should not be more than 3.0 m
foundation should not be less than 0.60m, at the site of water works as per c/c and the depth of foundation should not be less than 0.60m, at the
departmental type design and drawing, and, as per specifications given in the site of water works as per departmental type design and drawing, and,
28.00 8042.00 Rmt                         5,156                     41,464,552  28.00 11462.00 Rmt                         5,156                      59,098,072                   17,633,520 
bid document including supply of all materials, labour T&P etc.for proper as per specifications given in the bid document including supply of all
completion of work as per instructions of Engineer materials, labour T&P etc.for proper completion of work as per
instructions of Engineer

                   41,464,552                      59,098,072                   17,633,520 


Supply and fixing of 3.6 m x 1.50 m MS gate including fabrication and
Supply and fixing of 3.6 m x 1.50 m MS gate including fabrication and supply of
supply of steel and construction of bounary wall pillars of size
steel and construction of bounary wall pillars of size 1.5mx0.30mx0.30m with
1.5mx0.30mx0.30m with ornamental brick work 115mm th. around
ornamental brick work 115mm th. around RCC, as per departmental type
29.00 42.00 No.                       41,244                       1,732,248  29.00 RCC, as per departmental type design and drawing and as per 61.00 No.                      41,244                        2,515,884                        783,636 
design and drawing and as per specifications laid down in the bid document,
specifications laid down in the bid document, including supply of all
including supply of all material, labour,T&P etc.required for proper completion
material, labour,T&P etc.required for proper completion of work as per
of work as per instructions of Engineer
instructions of Engineer
                     1,732,248                        2,515,884                        783,636 
Supply and fixing of 1.5m wide MS wicket gate including fabrication and supply Supply and fixing of 1.5m wide MS wicket gate including fabrication and
of steel and construction of boundary wall pillars etc. as per specifications laid supply of steel and construction of boundary wall pillars etc. as per
down in the bid document, including supply of all material, labour,T&P specifications laid down in the bid document, including supply of all
30.00 etc.required for proper completion of work as per instructions of Engineer 42.00 No.                       14,730                          618,660  30.00 material, labour,T&P etc.required for proper completion of work as per 61.00 No.                      14,730                           898,530                        279,870 
instructions of Engineer

                        618,660                           898,530                        279,870 


Construction of Brick on edge pavement for approach to water works/ ESR, as Construction of Brick on edge pavement for approach to water works/
per departmental type design and drawing and as per specifications laid down ESR, as per departmental type design and drawing and as per
in the bid document, including supply of all materials , labour, T&P etc.required specifications laid down in the bid document, including supply of all
31.00 for proper completion of work as per instructions of Engineer ‐in ‐charge. 20865.00 Sqm.                            737                     15,377,505  31.00 materials , labour, T&P etc.required for proper completion of work as 20865.00 Sqm.                            737                      15,377,505  0.00
per instructions of Engineer ‐in ‐charge.

                   15,377,505                      15,377,505  0.00


Construction of semi circular 300 mm dia drain for water works, as per
Construction of semi circular 300 mm dia drain for water works, as per
departmental type design and drawing and as per specifications laid
departmental type design and drawing and as per specifications laid down in
32.00 2530.00 Rmt                         1,768                       4,473,040  32.00 down in the bid document, including supply of all materials, labour, 2530.00 Rmt                         1,768                        4,473,040  0.00
the bid document, including supply of all materials, labour, T&P etc.required
T&P etc.required for proper completion of work as per instructions of
for proper completion of work as per instructions of Engineer
Engineer
                     4,473,040                        4,473,040  0.00
Earth filling work for proper leveling of water work site, in accordance
Earth filling work for proper leveling of water work site, in accordance with the
with the contour map and Grid map of existing site enclosed, including
contour map and Grid map of existing site enclosed, including leveling,
leveling, dressing, excavation and filling of earth where necessary and
dressing, excavation and filling of earth where necessary and also including all
33.00 55084.00 Cum.                            334                     18,398,056  33.00 also including all labour, materials, T&P etc.required for proper 55084.00 Cum.                            334                      18,398,056  0.00
labour, materials, T&P etc.required for proper completion of works and also
completion of works and also including carriage of earth from within a
including carriage of earth from within a distance of about 8 km. from the site
distance of about 8 km. from the site of works as per instructions of
of works as per instructions of Engineer (Provisional)
Engineer (Provisional)
                   18,398,056                      18,398,056  0.00
Available earth filling work for proper leveling of water work site, in
Available earth filling work for proper leveling of water work site, in
accordance with the contour map and Grid map of existing site
accordance with the contour map and Grid map of existing site enclosed,
enclosed, including leveling, dressing, excavation and filling of earth
including leveling, dressing, excavation and filling of earth where necessary and
34.00 316390.00 Cum.                            128                     40,497,920  34.00 where necessary and also including all labour, materials, T&P 316390.00 Cum.                            128                      40,497,920  0.00
also including all labour, materials, T&P etc.required for proper completion of
etc.required for proper completion of works and also including carriage
works and also including carriage of earth from within a distance of about 8
of earth from within a distance of about 8 km. from the site of works as
km. from the site of works as per instructions of Engineer (Provisional)
per instructions of Engineer (Provisional)
                   40,497,920                      40,497,920  0.00
Soft landscaping works including providing and planting of decorative
Soft landscaping works including providing and planting of decorative plants,
plants, ground cover, shrubs in ground by mixing good soil with
ground cover, shrubs in ground by mixing good soil with manure/ sludge,
manure/ sludge, spraying insecticides & pesticides all materials, labour
35.00 spraying insecticides & pesticides all materials, labour T&P etc. required for 73445.00 sqm                            255                     18,728,475  35.00 73445.00 sqm                            255                      18,728,475  0.00
T&P etc. required for completion of the work. including levelling,
completion of the work. including levelling, dressing and filling of earth where
dressing and filling of earth where necessary for develop of water work
necessary for develop of water work  site. (Good soil will be paid seperately)
site. (Good soil will be paid seperately)
                   18,728,475                      18,728,475  0.00
Guard Room‐Supply of all materials labour T&P etc. compete and construction Guard Room‐Supply of all materials labour T&P etc. compete and
36.00 1.00 Nos.                     245,500                          245,500  36.00 14.00 Nos.                    245,500                        3,437,000                     3,191,500 
of Guard Room of 2m x 2.5m x 2.6m ht. at site of RCC CWR  construction of Guard Room of 2m x 2.5m x 2.6m ht. at site of RCC CWR 
                        245,500                        3,437,000                     3,191,500 

Page 15 of 20
Rates after  Rates after 
Amount  Amount Difference in 
S.no Item Description Qty Units Discount in figures  S.no Item Description Qty Units Discount in figures  Remarks
(in Rs.) (in Rs.) Amount (Rs.)
(in Rs.) (in Rs.)

SINGLE ROOM STAFF QUARTER‐ construction of staff quarter for pump


SINGLE ROOM STAFF QUARTER‐ construction of staff quarter for pump operator, chaukidar, pump attendent as per departmental type design
operator, chaukidar, pump attendent as per departmental type design attached with tender documents including excavation in foundation in
attached with tender documents including excavation in foundation in ordinary ordinary soil/ kanker/ morrum/ soft rock/hard rock,PCC 1:4:8 with
soil/ kanker/ morrum/ soft rock/hard rock,PCC 1:4:8 with cement local sand cement local sand and 40mm guage ballastFirst class brick work in 1:4
and 40mm guage ballastFirst class brick work in 1:4 cement and sand mortar, cement and sand mortar, 12 mm thick plaster in 1:6 cement and sand
12 mm thick plaster in 1:6 cement and sand mortar,mild steel or iron work mortar,mild steel or iron work ,supply and filling of carted earth up to
,supply and filling of carted earth up to plinth level ,25mm thick 1:2:4 plain plinth level ,25mm thick 1:2:4 plain cement concrete floor and 45 cm
cement concrete floor and 45 cm wide apron with 2 cm guage stone ballast wide apron with 2 cm guage stone ballast laid in pannels,finished with 3
laid in pannels,finished with 3 mm floating coat of neat cement and 75 mm mm floating coat of neat cement and 75 mm thick base concrete 1:4:8
37.00 thick base concrete 1:4:8 ,supply and fiximg of 3mm thick glass strip of 25 mm 22.00 Nos.                 1,865,800                     41,047,600  37.00 ,supply and fiximg of 3mm thick glass strip of 25 mm width in joint ,MS 14.00 Nos.                 1,865,800                      26,121,200                 ‐14,926,400 
width in joint ,MS angle iron chaukhat 40x40x5mm size ,40 mm thick ISI flush angle iron chaukhat 40x40x5mm size ,40 mm thick ISI flush door
door shesham wood,window shutter ,HDPE Tank of 500 liter capacity shesham wood,window shutter ,HDPE Tank of 500 liter capacity
,galvanized mosquito proof heavy quality iron wire guage 1.50mm mesh over ,galvanized mosquito proof heavy quality iron wire guage 1.50mm
window with wood batten 50x12 mm and snowcem painting two coat over one mesh over window with wood batten 50x12 mm and snowcem painting
priming coat using approved colour and shade and white washing of ceiling of two coat over one priming coat using approved colour and shade and
staff quarters and internal wiring of staff quarter as per direction of white washing of ceiling of staff quarters and internal wiring of staff
EIC,construction of Septic tank sanitary works with fixtures,pipes etc. and all quarter as per direction of EIC,construction of Septic tank sanitary
type of plumbing work in kitchen ,bathroom and W/C, with supply of all works with fixtures,pipes etc. and all type of plumbing work in kitchen
materials ,labours , tools and plants etc all complete as per direcdtion of EIC ,bathroom and W/C, with supply of all materials ,labours , tools and
plants etc all complete as per direcdtion of EIC
                   41,047,600                      26,121,200                 ‐14,926,400 
DOUBLE ROOM STAFF QUARTER‐ construction of staff quarter for
DOUBLE ROOM STAFF QUARTER‐ construction of staff quarter for pump pump operator, chaukidar, pump attendent as per departmental type
operator, chaukidar, pump attendent as per departmental type design design attached with tender documents including excavation in
attached with tender documents including excavation in foundation in ordinary foundation in ordinary soil/ kanker/ morrum/ soft rock/hard rock,PCC
soil/ kanker/ morrum/ soft rock/hard rock,PCC 1:4:8 with cement local sand 1:4:8 with cement local sand and 40mm guage ballastFirst class brick
and 40mm guage ballastFirst class brick work in 1:4 cement and sand mortar, work in 1:4 cement and sand mortar, 12 mm thick plaster in 1:6 cement
12 mm thick plaster in 1:6 cement and sand mortar,mild steel or iron work and sand mortar,mild steel or iron work ,supply and filling of carted
,supply and filling of carted earth up to plinth level ,25mm thick 1:2:4 plain earth up to plinth level ,25mm thick 1:2:4 plain cement concrete floor
cement concrete floor and 45 cm wide apron with 2 cm guage stone ballast and 45 cm wide apron with 2 cm guage stone ballast laid in
laid in pannels,finished with 3 mm floating coat of neat cement and 75 mm pannels,finished with 3 mm floating coat of neat cement and 75 mm
38.00 thick base concrete 1:4:8 ,supply and fiximg of 3mm thick glass strip of 25 mm 4.00 Nos.                 2,455,000                       9,820,000  38.00 thick base concrete 1:4:8 ,supply and fiximg of 3mm thick glass strip of 4.00 Nos.                 2,455,000                        9,820,000  0.00
width in joint ,MS angle iron chaukhat 40x40x5mm size ,40 mm thick ISI flush 25 mm width in joint ,MS angle iron chaukhat 40x40x5mm size ,40 mm
door shesham wood,window shutter ,HDPE Tank of 500 liter capacity thick ISI flush door shesham wood,window shutter ,HDPE Tank of 500
,galvanized mosquito proof heavy quality iron wire guage 1.50mm mesh over liter capacity ,galvanized mosquito proof heavy quality iron wire guage
window with wood batten 50x12 mm and snowcem painting two coat over one 1.50mm mesh over window with wood batten 50x12 mm and snowcem
priming coat using approved colour and shade and white washing of ceiling of painting two coat over one priming coat using approved colour and
staff quarters and internal wiring of staff quarter as per direction of shade and white washing of ceiling of staff quarters and internal wiring
EIC,construction of Septic tank sanitary works with fixtures,pipes etc. and all of staff quarter as per direction of EIC,construction of Septic tank
type of plumbing work in kitchen ,bathroom and W/C, with supply of all sanitary works with fixtures,pipes etc. and all type of plumbing work in
materials ,labours , tools and plants etc all complete as per direcdtion of EIC kitchen ,bathroom and W/C, with supply of all materials ,labours , tools
and plants etc all complete as per direcdtion of EIC
                     9,820,000                        9,820,000  0.00

Supply and fixing of Electromagnetic Flow Water Meter (with totalizer) for Supply and fixing of Electromagnetic Flow Water Meter (with totalizer)
measurement of bulk flow at outlets of every pump stations and inlets of for measurement of bulk flow at outlets of every pump stations and
39.00 39.00
CWRs/OHTs including construction of RCC/RB chambers of required size and as inlets of CWRs/OHTs including construction of RCC/RB chambers of
per instrucions of Engineer Incharge. required size and as per instrucions of Engineer Incharge.

39.01 800 mm dia 2.00 Nos.                 1,188,220                       2,376,440  39.01 800mm dia 3.00 Nos.                 1,188,220                        3,564,660                     1,188,220 
39.02 700 mm dia 8.00 Nos.                     982,000                       7,856,000  39.02 500mm dia 1.00 Nos.                    451,720                           451,720                    ‐7,404,280 
39.03 500 mm dia 4.00 Nos.                     451,720                       1,806,880  39.03 400mm dia 4.00 Nos.                    351,065                        1,404,260                       ‐402,620 
39.04 450 mm dia 2.00 Nos.                     402,620                          805,240  39.04 250mm dia 5.00 Nos.                    213,880                        1,069,400                        264,160 
39.05 400 mm dia 2.00 Nos.                     351,065                          702,130  39.05 200mm dia 2.00 Nos.                    192,472                           384,944                       ‐317,186 
39.06 350 mm dia 2.00 Nos.                     341,736                          683,472  39.06 150mm dia 34.00 Nos.                    166,351                        5,655,934                     4,972,462 
39.07 300 mm dia 2.00 Nos.                     267,350                          534,700  39.07 80mm dia 12.00 Nos.                    112,930                        1,355,160                        820,460 
39.08 250 mm dia 5.00 Nos.                     213,880                       1,069,400 
39.09 200 mm dia 15.00 Nos.                     192,472                       2,887,080 
39.10 150 mm dia 25.00 Nos.                     166,351                       4,158,775 
39.11 80 mm dia 1.00 Nos.                     112,930                          112,930 
                   22,993,047                      13,886,078                   ‐9,106,969 
Supply & Fixing of Flow control valve/Diaphragm Valve/Altitude control valve, Supply & Fixing of Flow control valve/Diaphragm Valve/Altitude control
including construction of RCC/RB chambers of required size and as per valve, including construction of RCC/RB chambers of required size and
40.00 instrucions of Engineer Incharge. 40.00 as per instrucions of Engineer Incharge.

40.01 100mm dia 1.00 Nos.                     152,210                          152,210  40.01 1000mm dia 3.00 Nos.                 3,039,290                        9,117,870                     8,965,660 
40.02 150 mm dia 3.00 Nos.                     235,680                          707,040  40.02 800mm dia 2.00 Nos.                 2,528,650                        5,057,300                     4,350,260 
40.03 200 mm dia 2.00 Nos.                     279,870                          559,740  40.03 600mm dia 4.00 Nos.                 1,755,816                        7,023,264                     6,463,524 
40.04 250 mm dia 2.00 Nos.                     367,268                          734,536  40.04 400mm dia 6.00 Nos.                    925,044                        5,550,264                     4,815,728 
40.05 300 mm dia 2.00 Nos.                     470,378                          940,756  40.05 350mm dia 1.00 Nos.                    536,172                           536,172                       ‐404,584 
40.06 350 mm dia 4.00 Nos.                     536,172                       2,144,688  40.06 300mm dia 4.00 Nos.                    470,378                        1,881,512                       ‐263,176 
40.07 400 mm dia 7.00 Nos.                     925,044                       6,475,308  40.07 250mm dia 16.00 Nos.                    367,268                        5,876,288                       ‐599,020 
40.08 500 mm dia 3.00 Nos.                 1,468,090                       4,404,270  40.08 200mm dia 13.00 Nos.                    279,870                        3,638,310                       ‐765,960 
Page 16 of 20
Rates after  Rates after 
Amount  Amount Difference in 
S.no Item Description Qty Units Discount in figures  S.no Item Description Qty Units Discount in figures  Remarks
(in Rs.) (in Rs.) Amount (Rs.)
(in Rs.) (in Rs.)

40.09 600 mm dia 2.00 Nos.                 1,755,816                       3,511,632  40.09 150mm dia 12.00 Nos.                    235,680                        2,828,160                       ‐683,472 
40.10 700 mm dia 2.00 Nos.                 2,113,264                       4,226,528 
40.11 800 mm dia 1.00 Nos.                 2,528,650                       2,528,650 
40.12 1000 mm dia 1.00 Nos.                 3,039,290                       3,039,290 
                   29,424,648                      41,509,140                   12,084,492 
Supply and installation of Pressure Feed Type Chlorinating Dozer of given
Supply and installation of Pressure Feed Type Chlorinating Dozer of
capacity complete with Rota‐meter, regulating valves, dosing pipe of reputed
given capacity complete with Rota‐meter, regulating valves, dosing pipe
make and other related accessories including for manual mixing of bleaching
41.00 41.00 of reputed make and other related accessories including for manual
powder for following Zones. for following Zones :
mixing of bleaching powder for following Zones. for following Zones :

41.01 GLR‐2, Chhapaka to OHSR 12A Chhapaka 40 GL 1.00 Nos.                       57,938                             57,938  41.01 GLR‐2 (Rudwali) to OHSR Zone‐Rudawli‐8GL 1.00 Nos.                      42,226                             42,226                         ‐15,712 
41.02 GLR‐2, Chhapaka to OHSR 12A Chhapaka 16GL 1.00 Nos.                       45,172                             45,172  41.02 GLR‐2 (Rudwali) to OHSR Zone‐Markundi‐24GL 1.00 Nos.                      49,100                             49,100                             3,928 
41.03 GLR‐2, Chhapaka to OHSR 12 Awayee 40GL 1.00 Nos.                       57,938                             57,938  41.03 GLR‐1 (Bhbhaech) to OHSR Zone‐Bhbhaech‐32GL 1.00 Nos.                      49,100                             49,100                           ‐8,838 
41.04 GLR‐2, Chhapaka to OHSR 12 Awayee 8 GL 1.00 Nos.                       42,226                             42,226  41.04 GLR‐1 (Bhbhaech) to OHSR Zone‐Belcupp‐32GL 1.00 Nos.                      49,100                             49,100                             6,874 
41.05 GLR‐9 to OHSR‐11A 40 GL 1.00 Nos.                       57,938                             57,938  41.05 GLR‐4 (Lori) to OHSR Zone‐5‐3 ‐56GL 1.00 Nos.                      75,614                             75,614                          17,676 
41.06 GLR‐2, Chhapaka to OHSR 9 Tilauli 40 GL 1.00 Nos.                       57,938                             57,938  41.06 GLR‐4 (Lori) to ZONE‐12‐3‐16GL 1.00 Nos.                      45,172                             45,172                         ‐12,766 
41.07 GLR‐2, Chhapaka to OHSR 9 Tilauli 8GL 1.00 Nos.                       42,226                             42,226  41.07 GLR‐4 (Lori) to ZONE‐9‐2 ‐16GL 1.00 Nos.                      45,172                             45,172                             2,946 
41.08 GLR‐4 Ganguar to OHSR 8A 40 GL 1.00 Nos.                       57,938                             57,938  41.08 GLR‐5 (Gangur) to OHSR Zone ‐8D & 5‐2 ‐72GL 1.00 Nos.                      93,290                             93,290                          35,352 
41.09 GLR‐4 Ganguar to OHSR 8A 16GL 1.00 Nos.                       45,172                             45,172  41.09 GLR‐5 (Gangur) to OHSR‐8C ‐24GL 1.00 Nos.                      49,100                             49,100                             3,928 
41.10 GLR‐4 Ganguar to OHSR 8 Bargawn 24 GL 1.00 Nos.                       49,100                             49,100  41.10 GLR‐5 (Gangur) to OHSR‐6C‐3 ‐16GL 1.00 Nos.                      45,172                             45,172                           ‐3,928 
41.11 GLR‐5 Papi to OHSR 7 40 GL 1.00 Nos.                       57,938                             57,938  41.11 GLR‐5 (Gangur) to OHSR‐8 ‐24GL 1.00 Nos.                      49,100                             49,100                           ‐8,838 
41.12 GLR‐5 Papi to OHSR 7 24GL 1.00 Nos.                       49,100                             49,100  41.12 GLR‐5 (Gangur) to OHSR‐12‐1 ‐24GL 1.00 Nos.                      49,100                             49,100  0.00
41.13 GLR‐5 Papi to OHSR 8B 40GL 1.00 Nos.                       57,938                             57,938  41.13 GLR‐5 (Gangur) to OHSR‐12‐2 ‐8GL 1.00 Nos.                      42,226                             42,226                         ‐15,712 
41.14 GLR‐11 to OHSR‐6A 32GL 1.00 Nos.                       49,100                             49,100  41.14 GLR‐5 (Gangur) to OHSR‐5‐1‐16GL 1.00 Nos.                      45,172                             45,172                           ‐3,928 
41.15 GLR‐11 to GLR‐12 40GL 2.00 Nos.                       57,938                          115,876  41.15 GLR‐5 (Gangur) to OHSR‐9A‐1‐40GL 1.00 Nos.                      57,938                             57,938                         ‐57,938 
41.16 GLR‐11 to GLR‐12 32GL 1.00 Nos.                       49,100                             49,100  41.16 GLR‐6 (Kekarahi) to OHSR‐6C‐1 ‐16GL 1.00 Nos.                      45,172                             45,172                           ‐3,928 
41.17 GLR‐12 to OHSR‐7A 32GL 1.00 Nos.                       49,100                             49,100  41.17 GLR‐7 (Papi) to OHSR‐6 ‐16GL 1.00 Nos.                      45,172                             45,172                           ‐3,928 
41.18 GLR‐12 to OHSR‐7B & OHSR 6B 40GL 2.00 Nos.                       57,938                          115,876  41.18 GLR‐7 (Papi) to OHSR‐6C ‐32GL 1.00 Nos.                      49,100                             49,100                         ‐66,776 
41.19 GLR‐12 to OHSR‐7B & OHSR 6B 8GL 1.00 Nos.                       42,226                             42,226  41.19 GLR‐7 (Papi) to OHSR‐6C‐2 ‐24GL 1.00 Nos.                      49,100                             49,100                             6,874 
41.20 GLR‐6 to OHSR 4 40GL 1.00 Nos.                       57,938                             57,938  41.20 GLR‐7 (Papi) to OHSR‐7A‐1‐16GL 1.00 Nos.                      45,172                             45,172                         ‐12,766 
41.21 GLR‐6 to OHSR‐6 40GL 1.00 Nos.                       57,938                             57,938  41.21  GLR‐8 (Atarauli Raja) to OHSR 6A‐1‐32GL 1.00 Nos.                      49,100                             49,100                           ‐8,838 
GLR‐8 (Atarauli Raja) to OHSR‐6A & 6B , OHSR‐7B & 6A‐2 , OHSR‐6A‐3
41.22 GLR‐7 to OHSR‐5 & OHSR 5A 40GL 2.00 Nos.                       57,938                          115,876  41.22 1.00 Nos.                    208,184                           208,184                          92,308 
& OHSR‐8B ‐176GL
41.23 GLR‐7 to OHSR‐5 & OHSR 5A 8GL 1.00 Nos.                       42,226                             42,226  41.23 GLR‐9 (Nipraj)  to OHSR‐9‐1 ‐32GL 1.00 Nos.                      49,100                             49,100                             6,874 
41.24 GLR‐8 to OHSR‐10 40GL 1.00 Nos.                       57,938                             57,938  41.24 GLR‐9 (Nipraj) to  OHSR‐9‐3 ‐32GL 1.00 Nos.                      49,100                             49,100                           ‐8,838 
41.25 GLR‐8 to OHSR‐9A 40GL 1.00 Nos.                       57,938                             57,938  41.25 GLR‐10 (Kushara) to OHSR‐10, OHSR‐9A & OHSR‐9 ‐120GL 1.00 Nos.                    146,318                           146,318                          88,380 
41.26 GLR‐8 to OHSR‐9A 32GL 1.00 Nos.                       49,100                             49,100  41.26 GLR‐10 (Kushara) to OHSR‐5B‐1 ‐32GL 1.00 Nos.                      49,100                             49,100  0.00
41.27 GLR‐8 to OHSR 5B 40GL 1.00 Nos.                       57,938                             57,938  41.27 GLR‐10 (Kushara) to OHSR‐3B‐1 ‐16GL 1.00 Nos.                      45,172                             45,172                         ‐12,766 
41.28 GLR‐13 to OHSR‐3B 40GL 1.00 Nos.                       57,938                             57,938  41.28 GLR‐10 (Kushara) to OHSR‐3A‐3 ‐24GL 1.00 Nos.                      49,100                             49,100                           ‐8,838 
41.29 GLR‐13 to OHSR‐3B 8GL 1.00 Nos.                       42,226                             42,226  41.29 GLR‐11 (Jogani) to OHSR ‐3A‐1 & 3A‐2 ‐48GL 1.00 Nos.                      66,776                             66,776                          24,550 
41.30 GLR‐14 to OHSR‐3A 32GL 1.00 Nos.                       49,100                             49,100  41.30 GLR‐11 (Jogani) to OHSR‐11B, OHSR‐4A & OHSR‐7A‐2 ‐96GL 1.00 Nos.                    119,804                           119,804                          70,704 
41.31 GLR‐14 to OHSR‐4A 32GL 1.00 Nos.                       49,100                             49,100  41.31 GLR‐12  (Khutaha) to OHSR‐3‐1 ‐32GL 1.00 Nos.                      49,100                             49,100  0.00
41.32 GLR‐14 to OHSR‐11B 32GL 1.00 Nos.                       49,100                             49,100  41.32 GLR‐12  (Khutaha) to OHSR‐2A ‐24GL 1.00 Nos.                      49,100                             49,100  0.00
41.33 GLR‐9 to OHSR‐10A 40GL 1.00 Nos.                       57,938                             57,938  41.33 GLR‐12  (Khutaha) to OHSR‐10A‐1 ‐24GL 1.00 Nos.                      49,100                             49,100                           ‐8,838 
41.34 GLR‐9 to OHSR‐10A 8GL 1.00 Nos.                       42,226                             42,226  41.34 GLR‐12  (Khutaha) to OHSR‐10A‐2 ‐32GL 1.00 Nos.                      49,100                             49,100                             6,874 
41.35 GLR‐9 to OHSR‐2A & OHSR‐2 Deoghar 40GL 2.00 Nos.                       57,938                          115,876  41.35 GLR‐12  (Khutana) to OHSR‐3‐2 & 3‐3 ‐40GL 1.00 Nos.                      57,938                             57,938                         ‐57,938 
41.36 GLR‐9 to OHSR‐2A & OHSR‐2 Deoghar 8GL 1.00 Nos.                       42,226                             42,226  41.36 GLR‐12  (Khutana) to OHSR‐11A‐1 ‐16GL 1.00 Nos.                      45,172                             45,172                             2,946 
41.37 GLR‐9 to OHSR‐3 Satohan 40GL 1.00 Nos.                       57,938                             57,938  41.37 GLR‐12  (Khutana) to OHSR‐11 ‐16GL 1.00 Nos.                      45,172                             45,172                         ‐12,766 
41.38 GLR‐9 to OHSR‐3 Satohan 16GL 1.00 Nos.                       45,172                             45,172  41.38 GLR‐12  (Khutana) to OHSR‐1‐1 ‐16GL 1.00 Nos.                      45,172                             45,172  0.00
41.39 GLR‐10 to OHSR‐11 24GL 1.00 Nos.                       49,100                             49,100  41.39 GLR‐13 ( Beerkhurd)OHSR‐ 11A ‐16GL 1.00 Nos.                      45,172                             45,172                           ‐3,928 
41.40 GLR‐15 to OHSR‐1 40GL 1.00 Nos.                       57,938                             57,938  41.40 GLR‐13 ( Beerkhurd)OHSR‐ 2 & OHSR‐2‐1 ‐56GL 1.00 Nos.                      75,614                             75,614                          17,676 
41.41 GLR‐15 to OHSR‐1  8GL 1.00 Nos.                       42,226                             42,226  41.41 GLR ‐14 (Sirsain)OHSR‐1, OHSR‐1A & OHSR‐1A‐1‐72GL 1.00 Nos.                      93,290                             93,290                          51,064 
41.42 GLR‐15 to OHSR‐1A  16GL 1.00 Nos.                       45,172                             45,172 
41.43 GLR‐15 to OHSR‐1B  24GL 1.00 Nos.                       49,100                             49,100 
41.44 from GLR‐2 Adalganj to OHSR‐3 Adalganj  40GL 3.00 Nos.                       57,938                          173,814 
41.45 from GLR‐2 Adalganj to GLR‐3 Bhbhaech 8GL 2.00 Nos.                       42,226                             84,452 
41.46 from GLR‐2 Adalganj to GLR‐3 Bhbhaech  40GL 1.00 Nos.                       57,938                             57,938 
41.47 from GLR‐3 Bhbhaech to OHSR‐2 Bhbhaech 32 GL 1.00 Nos.                       49,100                             49,100 
41.48 from GLR‐3 Bhbhaech to OHSR‐2 Bhbhaech 40GL 1.00 Nos.                       57,938                             57,938 
41.49 from GLR‐3 Bhbhaech to OHSR‐1 Belcupp 40GL 1.00 Nos.                       57,938                             57,938 
41.50 from GLR‐4 Rudawali to OHSR‐5 Rudawali 8 GL 1.00 Nos.                       42,226                             42,226 
41.51 from GLR‐4 Rudawali to OHSR‐4 Markundi 32GL 1.00 Nos.                       49,100                             49,100 
                     3,021,614                        2,455,982                       ‐565,632 

Page 17 of 20
Rates after  Rates after 
Amount  Amount Difference in 
S.no Item Description Qty Units Discount in figures  S.no Item Description Qty Units Discount in figures  Remarks
(in Rs.) (in Rs.) Amount (Rs.)
(in Rs.) (in Rs.)

Providing and Installation of 415 V Diesel Generator set with alternator


Providing and Installation of 415 V Diesel Generator set with alternator as per as per the manufacturers specification, Single/multi runs of PVC
the manufacturers specification, Single/multi runs of PVC insulated & PVC insulated & PVC sheathed / XLPE power cable of 1.1 KV grade of
sheathed / XLPE power cable of 1.1 KV grade of required size laying in ground required size laying in ground including excavation, sand cushioning,
including excavation, sand cushioning, protective covering and refilling the protective covering and refilling the trench, End termination with brass
trench, End termination with brass compression gland and aluminium lugs for compression gland and aluminium lugs for said cable, D G set Earthing
said cable, D G set Earthing with 600 x 600 x 3 mm copper plate with 40 mm with 600 x 600 x 3 mm copper  plate with 40 mm dia x 4.5 mtrs long G.I. 
dia x 4.5 mtrs long G.I. vertically pipe having 12 mm dia holes spaced 5 mm vertically pipe having 12 mm dia holes spaced 5 mm apart drilled upto
apart drilled upto 2 mtr from the bottom complete vertically with its top at 2 mtr from the bottom complete vertically with its top at least 3 mtrs
42.00 least 3 mtrs below ground level with earthing lead of No.6 to 8 SWG GI wire / 42.00 below ground level with earthing lead of No.6 to 8 SWG GI wire / G I
G I Strip in GI Pipe upto DG set, 30 cm square C.I. box with hinged cover Strip in GI Pipe upto DG set, 30 cm square C.I. box with hinged cover
masonry enclosure, funnel at top, alternate layers of charcoal/ coke and salt at masonry enclosure, funnel at top, alternate layers of charcoal/ coke and 
least 150 mm thick around G I Pipe etc complete, Rate of D G Set including salt at least 150 mm thick around G I Pipe etc complete, Rate of D G
transportation, loading and unloading complete with all above materials, Also Set including transportation, loading and unloading complete with all
Construction of RCC DG Foundation with Galvanized iron roofing 0.63 mm thick  above materials, Also Construction of RCC DG Foundation with
shed supported with RCC pillar complete including all labour, material as per Galvanized iron roofing 0.63 mm thick shed supported with RCC pillar
the detailed drawing and specification or as per the direction of the Engineer complete including all labour, material as per the detailed drawing and
specification or as per the direction of the Engineer

DG SET DG SET
42.01 Intake well  ‐ 1250 KVA 1.00 Set               10,927,696                     10,927,696  42.01 Intake well ‐ 1250KVA 1.00 Set               10,927,696                      10,927,696  0.00
42.02 WTP @ PATWADH 2 1250 KVA  1.00 Set               10,888,416                     10,888,416  42.02 WTP & MCWR ‐ 2500KVA 1.00 Set               18,922,158                      18,922,158                     8,033,742 
42.03 CWR1A  1500 KVA  1.00 Set               14,563,060                     14,563,060  42.03 GLR‐1 (Bhbhaech) ‐ 125KVA 1.00 Set                 1,120,462                        1,120,462                 ‐13,442,598 
42.04 MARKUNDI  VILLAGE ‐ GLR‐1A 2500 KVA  1.00 Set               18,922,158                     18,922,158  42.04 GLR‐2 (Rudawali) ‐ 125KVA 1.00 Set                 1,120,462                        1,120,462                 ‐17,801,696 
42.05 MARKUNDI  VILLAGE ‐ GLR‐1B  2500 KVA  1.00 Set               18,922,158                     18,922,158  42.05 GLR‐3 (Markundi) ‐ 3500KVA 1.00 Set               26,491,021                      26,491,021                     7,568,863 
42.06 CHHAPAKA VILLAGE‐GLR‐2  225 KVA  1.00 Set                 2,247,798                       2,247,798  42.06 GLR‐4 (Lori) ‐ 500KVA 1.00 Set                 4,238,312                        4,238,312                     1,990,514 
42.07 GANGUR VILLAGE‐GLR‐4  750 KVA  1.00 Set                 6,215,078                       6,215,078  42.07 GLR‐5 (Ganguar) ‐ 1250KVA 1.00 Set               10,888,416                      10,888,416                     4,673,338 
42.08 PAPI VILLAGE ‐ GLR‐5  365 KVA  1.00 Set                 3,716,870                       3,716,870  42.08 GLR‐6 (Kekarahi) ‐ 320KVA 1.00 Set                 3,258,626                        3,258,626                       ‐458,244 
42.09 BHARAWAH VILLAGE ‐ GLR‐6  180  KVA  1.00 Set                 1,552,542                       1,552,542  42.09 GLR‐7 (Papi) ‐ 500KVA 1.00 Set                 4,238,312                        4,238,312                     2,685,770 
42.10 UNCHIDIH VILLAGE ‐ GLR‐8  600 KVA  1.00 Set                 4,918,838                       4,918,838  42.10 GLR‐8 (Tarauli Raja) ‐ 320KVA 1.00 Set                 3,258,626                        3,258,626                    ‐1,660,212 
42.11 SIDDHI VILLAGE ‐ GLR‐7  500 KVA  1.00 Set                 4,238,312                       4,238,312  42.11 GLR‐9 (Nipraj) ‐ 125KVA 1.00 Set                 1,120,462                        1,120,462                    ‐3,117,850 
42.12 KHUTHA VILLAGE‐GLR‐9  365 KVA  1.00 Set                 3,716,870                       3,716,870  42.12 GLR‐10 (Kushara) ‐ 500KVA 1.00 Set                 4,238,312                        4,238,312                        521,442 
42.13 PEROHA VILLAGE‐GLR‐10 ‐ 180 KVA  1.00 Set                 1,552,542                       1,552,542  42.13 GLR‐11 (Jogani) ‐ 160KVA 1.00 Set                 1,580,178                        1,580,178                          27,636 
42.14 AMAULIA GLR 11  180 KVA  1.00 Set                 1,552,542                       1,552,542  42.14 GLR‐12 (Khutana) ‐ 500KVA 1.00 Set                 4,238,312                        4,238,312                     2,685,770 
42.15 BHWANIPUR GLR 12 ‐ 225 KVA  1.00 Set                 2,247,798                       2,247,798  42.15 GLR‐13 (Beerkhurd) ‐ 320KVA 1.00 Set                 3,258,626                        3,258,626                     1,010,828 
42.16 GLR 13 CAMPUS  ‐ 275 KVA  1.00 Set                 2,443,216                       2,443,216  42.16 GLR‐14 (Sirsail) ‐ 125KVA 1.00 Set                 1,120,462                        1,120,462                    ‐1,322,754 
42.17 GLR 14 CAMPUS  ‐140 KVA  1.00 Set                 1,382,656                       1,382,656 
42.18 GLR 15 CAMPUS  ‐ 140 KVA  1.00 Set                 1,382,656                       1,382,656 
42.19 PATWADH CWR  ‐ 400 KVA  1.00 Set                 3,939,784                       3,939,784 
42.20 ADALGANJ GLSR 2  ‐  180 KVA  1.00 Set                 1,552,542                       1,552,542 
42.21 BHBHAECH GLSR‐3  ‐ 125 KVA  1.00 Set                 1,120,462                       1,120,462 
42.22 RUDAWALI GLSR‐4  ‐ 90 KVA  1.00 Set                 1,086,092                       1,086,092 
                 119,090,086                   100,020,443                 ‐19,069,643 
Supply, installation, testing and commissioning of L T panels comprising of Supply, installation, testing and commissioning of L T  panels comprising 
A.C.B / M.C.C.B . /M.C.B suitable C.Ts operated ampere meter, On/Off of A.C.B / M.C.C.B . /M.C.B suitable C.Ts operated ampere meter,
indicator selector switch and internal wiring etc."&" complete including Amp On/Off indicator selector switch and internal wiring etc."&" complete
meter, Voltmeter, frequencymeter, P.F. meter, Capacitor, single phasing including Amp meter, Voltmeter, frequencymeter, P.F. meter,
preventer, Selector switch, fuses etc ‐1 set. enclosed in 16 guage CRCA sheet Capacitor, single phasing preventer, Selector switch, fuses etc ‐1 set.
metal work, doors, busbars, gaskets for doors, painting, feeder designation enclosed in 16 guage CRCA sheet metal work, doors, busbars, gaskets
etc., Single / multi runs of PVC insulated & PVC sheathed / XLPE power cable of for doors, painting, feeder designation etc., Single / multi runs of PVC
1.1 KV grade of required size laying in ground including excavation, sand insulated & PVC sheathed / XLPE power cable of 1.1 KV grade of
cushioning, protective covering and refilling the trench, End termination with required size laying in ground including excavation, sand cushioning,
brass compression gland and aluminium lugs for said cable, complete. Earthing protective covering and refilling the trench, End termination with brass
with 600 x 600 x 3 mm copper plate with 40 mm dia x 4.5 mtrs long G.I. compression gland and aluminium lugs for said cable, complete.
43.00 43.00
vertically pipe having 12 mm dia holes spaced 5 mm apart drilled upto 2 mtr Earthing with 600 x 600 x 3 mm copper plate with 40 mm dia x 4.5
from the bottom complete vertically with its top at least 3 mtrs below ground mtrs long G.I. vertically pipe having 12 mm dia holes spaced 5 mm
level with earthing lead of No.6 to 8 SWG GI wire / G I Strip in GI Pipe upto L T apart drilled upto 2 mtr from the bottom complete vertically with its
Panel, 30 cm square C.I. box with hinged cover masonry enclosure, funnel at top at least 3 mtrs below ground level with earthing lead of No.6 to 8
top, alternate layers of charcoal/ coke and salt at least 150 mm thick around G SWG GI wire / G I Strip in GI Pipe upto L T Panel, 30 cm square C.I. box
I Pipe etc complete including all labour, material as per the detailed drawing. with hinged cover masonry enclosure, funnel at top, alternate layers of
Internal concealed electrification with 1.5 sq.mm. FRLSH PVC insulated charcoal/ coke and salt at least 150 mm thick around G I Pipe etc
1100 V grade multistrand single core copper conductor cable in 20 mm dia complete including all labour, material as per the detailed drawing.
heavy duty (2mm thick) PVC conduit with 1 nos. 1.5 sq. mm. FRLSH PVC Internal concealed electrification with 1.5 sq.mm. FRLSH PVC
insulated 1100 V grade multistrand single core copper conductor insulated 1100 V grade multistrand single core copper conductor
cable    as    earth continuity wire drawn inside the conduit complete in all  cable  in 20 mm dia heavy duty (2mm  thick)  PVC  conduit  with  1  nos.  
INTAKE WELL ‐ Incomer 2500 A ‐ 3nos, bus‐coupler 2500 A ‐ 1nos ,
Intake well Incomer 3200 A ‐ 2 nos, bus‐coupler 3200 A ‐ 1 no , motor feeder‐
43.01 1.00 Set                 4,172,518                       4,172,518  43.01 motor feeder‐630A (6 Nos), capacitor feeder , lighting feeder, Spare 1.00 Set                 4,576,244                        4,576,244                        403,726 
500A capacoitor feeder , lighting feeder, Spare feeder 
feeder 
WTP @ PATWADH 2 Incomer 2500 A ‐ 2 nos, bus‐coupler 2500 A ‐ 1 no , motor
WTP ‐ Incomer 1250A ‐ 3nos, bus‐coupler 1250A ‐ 1nos , motor feeder‐
43.02 feeder‐ 2000A , WTP Feeder 2500A Capacoitor feeder , lighting feeder, Spare 1.00 Set                 5,250,754                       5,250,754  43.02 1.00 Set                 3,071,696                        3,071,696                    ‐2,179,058 
200A (10 Nos), capacitor feeder , lighting feeder, Spare feeder 
feeder 

Page 18 of 20
Rates after  Rates after 
Amount  Amount Difference in 
S.no Item Description Qty Units Discount in figures  S.no Item Description Qty Units Discount in figures  Remarks
(in Rs.) (in Rs.) Amount (Rs.)
(in Rs.) (in Rs.)

MCWR ‐ Incomer 5000 A ‐ 3nos, bus‐coupler 5000 A ‐ 1 no , motor


CWR1A Incomer4000 A ‐ 2 nos, bus‐coupler 4000 A ‐ 1 no , Motor feeder‐
43.03 1.00 Set                 4,900,180                       4,900,180  43.03 feeder‐500A (8 Nos), motor feeder‐160A (6 Nos), motor feeder‐63A (2 1.00 Set                 7,532,001                        7,532,001                     2,631,821 
500A ,  Capacoitor feeder , lighting feeder, Spare feeder 
Nos),capacitor feeder , lighting feeder, Spare feeder 

GLR‐1 (Babhech) ‐ Incomer 320 A ‐ 3nos, bus‐coupler 320 A ‐ 1 no ,


MARKUNDI VILLAGE ‐ GLR‐1A Incomer 4000 A ‐ 2 nos, bus‐coupler 4000 A ‐ 1
43.04 1.00 Set                 4,900,180                       4,900,180  43.04 motor feeder‐100A (4 Nos), capacitor feeder , lighting feeder, Spare 1.00 Set                 1,470,054                        1,470,054                    ‐3,430,126 
no , Motor feeder‐ 500A ,  Capacoitor feeder , lighting feeder, Spare feeder 
feeder 
GLR‐2 (Rudwali) ‐ Incomer 320 A ‐ 3nos, bus‐coupler 320 A ‐ 1 no ,
MARKUNDI VILLAGE ‐ GLR‐1B Incomer 4000 A ‐ 2 nos, bus‐coupler 4000 A ‐ 1
43.05 1.00 Set                 4,900,180                       4,900,180  43.05 motor feeder‐100A (4 Nos), capacitor feeder , lighting feeder, Spare 1.00 Set                 1,470,054                        1,470,054                    ‐3,430,126 
no , Motor feeder‐ 500A ,  Capacoitor feeder , lighting feeder, Spare feeder 
feeder 
GLR‐3 (Markundi) ‐ Incomer 6300 A ‐ 3nos, bus‐coupler 6300 A ‐ 1 no ,
CHHAPAKA VILLAGE‐GLR‐2 Incomer 500 A ‐ 2 nos, bus‐coupler 500 A ‐ 1 no ,
43.06 1.00 Set                 1,432,738                       1,432,738  43.06 motor feeder‐630A (15 Nos), capacitor feeder , lighting feeder, Spare 1.00 Set               14,928,650                      14,928,650                   13,495,912 
Motor feeder‐ 100A ,  Capacoitor feeder , lighting feeder, Spare feeder 
feeder 
GLR‐4 (Lori) ‐ Incomer 1250 A ‐ 3nos, bus‐coupler 1250 A ‐ 1 no , motor
GANGUR VILLAGE‐GLR‐4 Incomer 1400 A ‐ 2 nos, bus‐coupler 1400 A ‐ 1 no ,
43.07 1.00 Set                 2,530,614                       2,530,614  43.07 feeder‐400A (3 Nos), motor feeder‐100A (2 Nos), capacitor feeder , 1.00 Set                 2,530,614                        2,530,614  0.00
Motor feeder‐320A ,  Capacoitor feeder , lighting feeder, Spare feeder 
lighting feeder, Spare feeder 

GLR‐5 (Ganguar) ‐ Incomer 2500 A ‐ 3nos, bus‐coupler 2500 A ‐ 1 no ,


PAPI VILLAGE ‐ GLR‐5 Incomer 800 A ‐ 2 nos, bus‐coupler 800 A ‐ 1 no , Motor
43.08 1.00 Set                 4,770,556                       4,770,556  43.08 motor feeder‐500A(4 Nos), Motor feeder‐200A(4 Nos), Motor feeder‐ 1.00 Set                 4,617,929                        4,617,929                       ‐152,627 
feeder‐100A ,  Capacoitor feeder , lighting feeder, Spare feeder 
100A(2 Nos)capacitor feeder , lighting feeder, Spare feeder 

GLR ‐6 (kekarahi) ‐ Incomer 630 A ‐ 3nos, bus‐coupler 630 A ‐ 1 no ,


BHARAWAH VILLAGE ‐ GLR‐6 Incomer 400 A ‐ 2 nos, bus‐coupler400 A ‐ 1 no ,
43.09 1.00 Set                 1,129,300                       1,129,300  43.09 motor feeder‐160A (5 Nos), capacitor feeder , lighting feeder, Spare 1.00 Set                 2,605,246                        2,605,246                     1,475,946 
Motor feeder‐ 100A ,  Capacoitor feeder , lighting feeder, Spare feeder 
feeder 

UNCHIDIH VILLAGE ‐ GLR‐7 Incomer 1250 A ‐ 2 nos, bus‐coupler 1250 A ‐ 1 no GLR‐7(Papi) ‐ Incomer 1250 A ‐ 3nos, bus‐coupler 1250 A ‐ 1 no , motor
43.10 1.00 Set                 2,052,380                       2,052,380  43.10 1.00 Set                 2,052,380                        2,052,380  0.00
, Motor feeder‐ 200A ,  Capacoitor feeder , lighting feeder, Spare feeder  feeder‐250A (3 Nos),  capacitor feeder , lighting feeder, Spare feeder 

GLR‐8 ( Tarauli Raja) ‐ Incomer 630 A ‐ 3nos, bus‐coupler 630 A ‐ 1 no ,


SIDDHI VILLAGE ‐ GLR‐8 Incomer 1250 A ‐ 2 nos, bus‐coupler 1250 A ‐ 1 no ,
43.11 1.00 Set                 3,071,696                       3,071,696  43.11 motor feeder‐160A (3 Nos), motor feeder‐100A (2 Nos), capacitor 1.00 Set                 2,605,246                        2,605,246                       ‐466,450 
Motor feeder‐ 160A ,  Capacoitor feeder , lighting feeder, Spare feeder 
feeder , lighting feeder, Spare feeder 

KHUTHA VILLAGE‐GLR‐9 Incomer 800 A ‐ 2 nos, bus‐coupler 800 A ‐ 1 no , GLR‐9 (Nipraj) ‐ Incomer 320 A ‐ 3nos, bus‐coupler 320 A ‐ 1 no , motor
43.12 1.00 Set                 2,605,246                       2,605,246  43.12 1.00 Set                 1,470,054                        1,470,054                    ‐1,135,192 
Motor feeder‐ 100A ,  Capacoitor feeder , lighting feeder, Spare feeder  feeder‐100A (5 Nos), capacitor feeder , lighting feeder, Spare feeder 

GLR‐10 (Kushara) ‐ Incomer 1250 A ‐ 3nos, bus‐coupler 1250 A ‐ 1 no ,


PEROHA VILLAGE‐GLR‐10 Incomer 400 A ‐ 2 nos, bus‐coupler 400 A ‐ 1 no ,
43.13 1.00 Set                 1,129,300                       1,129,300  43.13 motor feeder‐160A(13 Nos) , capacitor feeder , lighting feeder, Spare 1.00 Set                 3,993,205                        3,993,205                     2,863,905 
Motor feeder‐ 100A ,  Capacoitor feeder , lighting feeder, Spare feeder 
feeder 
GLR‐11 (Jogani) ‐ Incomer 320 A ‐ 3nos, bus‐coupler 320 A ‐ 1 no ,
AMAULIA GLR 11 Incomer 250 A ‐ 2 nos, bus‐coupler 250 A ‐ 1 no , Motor
43.14 1.00 Set                 1,096,894                       1,096,894  43.14 motor feeder‐63A (7 Nos), capacitor feeder , lighting feeder, Spare 1.00 Set                 1,470,054                        1,470,054                        373,160 
feeder‐ 100A ,  Capacoitor feeder , lighting feeder, Spare feeder 
feeder 
GLR‐12 (Khutana) ‐ Incomer 1250 A ‐ 3nos, bus‐coupler 1250 A ‐ 1 no ,
BHWANIPUR GLR 12 Incomer 500 A ‐ 2 nos, bus‐coupler 500 A ‐ 1 no ,
43.15 1.00 Set                 1,152,868                       1,152,868  43.15 motor feeder‐250A (6 Nos), motor feeder‐63A (2 Nos),capacitor feeder 1.00 Set                 2,530,614                        2,530,614                     1,377,746 
Motor feeder‐ 100A ,  Capacoitor feeder , lighting feeder, Spare feeder 
, lighting feeder, Spare feeder 
GLR‐13 ( Beerkhurd) ‐ Incomer 630 A ‐ 3nos, bus‐coupler 630 A ‐ 1 no ,
GLR 13 CAMPUS Incomer 630 A ‐ 2 nos, bus‐coupler 630 A ‐ 1 no , Motor
43.16 1.00 Set                 1,359,088                       1,359,088  43.16 motor feeder‐250A (2 Nos), motor feeder‐63A (2 Nos), capacitor 1.00 Set                 2,605,246                        2,605,246                     1,246,158 
feeder‐ 125A ,  Capacoitor feeder , lighting feeder, Spare feeder 
feeder , lighting feeder, Spare feeder 
GLR‐14 (Sirsail) ‐ Incomer 250 A ‐ 3nos, bus‐coupler 250 A ‐ 1 no , motor
GLR 14 CAMPUS Incomer 320 A ‐ 2 nos, bus‐coupler 300 A ‐ 1 no , Motor
43.17 1.00 Set                 1,470,054                       1,470,054  43.17 feeder‐100A (3 Nos), motor feeder‐63A (2 Nos), capacitor feeder , 1.00 Set                 1,129,300                        1,129,300                       ‐340,754 
feeder‐ 125A ,  Capacoitor feeder , lighting feeder, Spare feeder 
lighting feeder, Spare feeder 
GLR 15 CAMPUS Incomer 320 A ‐ 2 nos, bus‐coupler 320 A ‐ 1 no , Motor
43.18 1.00 Set                 1,470,054                       1,470,054 
feeder‐ 50A ,  Capacoitor feeder , lighting feeder, Spare feeder 
PATWADH CWR Incomer 1000 A ‐ 2 nos, bus‐coupler 1000 A ‐ 1 no ,Motor
43.19 feeder‐ 160A , WTP Feeder 1000A Capacoitor feeder , lighting feeder, Spare 1.00 Set                 2,923,414                       2,923,414 
feeder 
ADALGANJ GLSR 2 Incomer 400 A ‐ 2 nos, bus‐coupler 400 A ‐ 1 no , Motor
43.20 1.00 Set                 1,152,868                       1,152,868 
feeder‐ 80A ,  Capacoitor feeder , lighting feeder, Spare feeder 
BHBHAECH GLSR‐3 Incomer 250 A ‐ 2 nos, bus‐coupler 250 A ‐ 1 no , Motor
43.21 1.00 Set                 1,129,300                       1,129,300 
feeder‐ 80A ,  Capacoitor feeder , lighting feeder, Spare feeder 
RUDAWALI GLSR‐4 Incomer 200 A ‐ 2 nos, bus‐coupler 200 A ‐ 1 no , Motor
43.22 1.00 Set                 1,129,300                       1,129,300 
feeder‐ 50A ,  Capacoitor feeder , lighting feeder, Spare feeder 
                   55,729,482                      60,658,587                     4,929,105 

Design, Engineering, supply, Installation, Testing and commissioning of Design, Engineering, supply, Installation, Testing and commissioning of
44.00 Automation & SCADA (PLC GSM based) system to Control water supply in OHT 44.00 Automation & SCADA (PLC GSM based) system to Control water supply
and ventilation inside pumping station electrical room.  in OHT and ventilation inside pumping station electrical room. 

44.01 Intake 1.00 No.                     982,000                          982,000  44.01 Intake 1.00 No.                    982,000                           982,000  0.00
44.02 WTP/CWR 1.00 No.                 2,946,000                       2,946,000  44.02 WTP/CWR 1.00 No.                 2,946,000                        2,946,000  0.00
44.03 GLR 3.00 No.                     982,000                       2,946,000  44.03 GLR 5.00 No.                    982,000                        4,910,000                     1,964,000 
44.04 GLR & OHSR 14.00 No.                     982,000                     13,748,000  44.04 GLR & OHSR 18.00 No.                    982,000                      17,676,000                     3,928,000 
44.05 OHSR 23.00 No.                     491,000                     11,293,000  44.05 OHSR 46.00 No.                    491,000                      22,586,000                   11,293,000 
                   31,915,000                      49,100,000                   17,185,000 
Page 19 of 20
Rates after  Rates after 
Amount  Amount Difference in 
S.no Item Description Qty Units Discount in figures  S.no Item Description Qty Units Discount in figures  Remarks
(in Rs.) (in Rs.) Amount (Rs.)
(in Rs.) (in Rs.)

Sufficient number of lights and around Water works compound external/street Sufficient number of lights and around Water works compound
lightening system ‐ Solar based LED (110 to 130 Watts) with poles of 9.00 m external/street lightening system ‐ Solar based LED (110 to 130 Watts)
45.00 32.00 Nos.                       31,228                          999,296  45.00 70.00 Nos.                      31,228                        2,185,960                     1,186,664 
long, foundation in 1:3:6, Including solar pannel & wiring etc. all complete as with poles of 9.00 m long, foundation in 1:3:6, Including solar pannel &
per directions of the Engineer.  wiring etc. all complete as per directions of the Engineer. 
                        999,296                        2,185,960                     1,186,664 

Subtotal of Part (A)              7,780,007,464  Subtotal of Part (A)               7,897,774,329                117,766,865 

46.00 46.00
Operation and Maintenance of whole water Supply system constructed under Operation and Maintenance of whole water Supply system
this work, after completion of trial run for providing continous water supply in constructed under this work, after completion of trial run for providing
the covered area and households @ 55 lpcd at the minimum residual pressure continous water supply in the covered area and households @ 55 lpcd
of 7 M. at the minimum residual pressure of 7 M.
Fixed operation charges Fixed operation charges
46.01 Year‐1 (During defect liabilities period) 1.00 Year               78,230,400                     78,230,400  46.01 Year‐1 (During defect liabilities period) 1.00 Year               78,230,400                      78,230,400  0.00
46.02 Year‐2 1.00 Year               82,142,000                     82,142,000  46.02 Year‐2 1.00 Year               82,142,000                      82,142,000  0.00
46.03 Year‐3 1.00 Year               86,250,000                     86,250,000  46.03 Year‐3 1.00 Year               86,250,000                      86,250,000  0.00
46.04 Year‐4 1.00 Year               90,563,000                     90,563,000  46.04 Year‐4 1.00 Year               90,563,000                      90,563,000  0.00
46.05 Year‐5 1.00 Year               95,092,000                     95,092,000  46.05 Year‐5 1.00 Year               95,092,000                      95,092,000  0.00
46.06 Year‐6 1.00 Year               99,847,000                     99,847,000  46.06 Year‐6 1.00 Year               99,847,000                      99,847,000  0.00
46.07 Year‐7 1.00 Year             104,840,000                   104,840,000  46.07 Year‐7 1.00 Year             104,840,000                   104,840,000  0.00
46.08 Year‐8 1.00 Year             110,082,000                   110,082,000  46.08 Year‐8 1.00 Year             110,082,000                   110,082,000  0.00
46.09 Year‐9 1.00 Year             115,587,000                   115,587,000  46.09 Year‐9 1.00 Year             115,587,000                   115,587,000  0.00
46.10 Year‐10 1.00 Year             121,367,000                   121,367,000  46.10 Year‐10 1.00 Year             121,367,000                   121,367,000  0.00
Subtotal of Part (B)                  984,000,400  Subtotal of Part (B)                  984,000,400  0.00

Total (Part A + Part B)              8,764,007,864  Total (Part A + Part B)               8,881,774,729                117,766,865 


Note 1. The contractor shall quote the rates inclisive of all taxes (excluding GST).
2. GST applicable amount will be paid extra based on submission of original challans receipts from the concerned authorities.
3. Standard Drawigs are avialable with the employer and bidders are allowed to review the same at SWSM office.
4. Rate Only Items as in BOQ to be Mreasured and paid as per actual site measurement / drg approval for the variations.
5. Above arrived quantities  based on site and scope given by client  and are as per available data /survey/designs and the quantities are liable to change as per actual site condition.
6. Actuals may vary with project report.

Page 20 of 20
  PATWADH GOV DETAIL PROJECT REPORT    

SCHEDULE – J

Price Break up for Payment during Bill Period

  286 | P a g e  
NCC LIMITED
Patwadh GOV WSP, District ‐ Sonbhadra
Ananlysis For Clear Water Reservoir

S.No. Item Description Unit Rate Remarks


CLEAR WATER RESERVOIR ‐ Survey, Investigation, Soil Testing, Planning,
Designing, Construction, Commissioning of CWR of capacity as detailed below.
The Concrete in a minimum grade of M‐30 and steel to be used as per IS code
and approved by Employer. Seismic effects and wind load with earthquake
resistance should be taken into account in the design. CWR should be
provided with a ventilator, manhole of adequate size. An aluminium ladder
minimum of 0.45 m wide in manhole should be provided. Ultrasonic water
level indicator should be provided along with lighting conductor as per IS 2309.
PCC of M‐10 grade to be used in bed blocks. Overflow arrangement with the
supply & installation of pressure pipe of the same dia as that of the inlet, for
taking overflow water to a suitable low lying area. Painting of all steel and
concrete pipes with 3 coats of approved cement plaster and anticorrosive
paint including all labour, material, T & P etc., all required for proper
completion of works as per the direction of the Engineer.
Bidders are advised to take SBC at 12 MT/SQM for construction of CWR. If
actual SBC is more than 12MT/SQM, the structure will be designed at 12
MT/SQM. In case less than 12 MT/SQM, as per actual.

1 For 4400 KL
A B
1 7500 KL 69511852
2 4100 KL 38494400
3 4400 KL
Rate arrived for 4400KL on Interpolation basis KL 41231234
Rate for 4400KL = (B1‐B2)/(A1‐A2)X(A3‐A2)+B2

2 For 1200 KL
A B
1 1900 KL 12942760
2 800 KL 7856000
3 1200 KL
Rate arrived for 1200KL on Interpolation basis KL 9705731
Rate for 1200KL = (B1‐B2)/(A1‐A2)X(A3‐A2)+B2

3 For 1000 KL
A B
1 1900 KL 12942760
2 800 KL 7856000
3 1000 KL
Rate arrived for 1000KL on Interpolation basis KL 8780865
Rate for 1000KL = (B1‐B2)/(A1‐A2)X(A3‐A2)+B2

4 For 950 KL
A B
1 1000 KL 8780865
2 800 KL 7856000
3 950 KL
Rate arrived for 950KL on Interpolation basis KL 8549649
Rate for 950KL = (B1‐B2)/(A1‐A2)X(A3‐A2)+B2

5 For 100 KL
A B
1 200 KL 4124400
2 150 KL 3731600
3 100 KL
Rate arrived for 100KL on Interpolation basis KL 3338800
Rate for 100KL = (B1‐B2)/(A1‐A2)X(A3‐A2)+B2
NCC LIMITED
Patwadh GOV WSP, District ‐ Sonbhadra
Ananlysis For Thrust Block

S.No. Item Description Unit Rate Remarks


Design and construction of Thrust Block made in R.C.C. with cement, coarse sand & 20 mm gauge stone ballast in
proportion of 1:1.5:3, for pipe line, including supply of MS reinforcement wrought to required shape as necessary
,its bending, fixing & binding the same with 0.50 mm thick binding wire in position & necessary centering &
shuttering including curing and supply of all materials, labour, T & P etc. required for proper completion of the
work and as per specifications for RCC work for following pipe diameter as per instructions of Engineer.

1 For 350mm dia
A B
1 400 HP 33192
2 300 HP 27103
3 350
Rate arrived for 350mm dia on Interpolation basis HP 30148
Rate for 350mm dia = (B1‐B2)/(A1‐A2)X(A3‐A2)+B2
NCC LIMITED
Patwadh GOV WSP, District ‐ Sonbhadra
Thrustblock Quantity

Length   Pressure 
S.No. Start Node Stop Node Dia (mm) Qty Total Qty
(m) Class
1 J‐639 Patwdh Zone F 196 150 DI‐K9 1
2 J‐641 Zone‐3B‐1 350 150 DI‐K9 2
3 J‐646 J‐647 308 150 DI‐K9 2
4 J‐647 Zone‐5‐1 614 150 DI‐K9 3
5 J‐664 Zone‐7B and 6A‐2 630 150 DI‐K9 3
6 J‐79 Zone C‐REDIA 749 150 DI‐K9 3
7 J‐687 J‐646 1,115 150 DI‐K9 4
8 J‐698 Zone‐11A‐1 1,412 150 DI‐K9 5
9 J‐700 Zone‐11 2,056 150 DI‐K9 7
10 J‐659 Zone‐1 438 150 DI‐K9 2
11 J‐730 Zone‐12‐2 5,998 150 DI‐K9 20
12 J‐772 Markundi Zone D 3,894 150 DI‐K9 13
13 MGLR MCPW PMP‐3 12 150 DI‐K9 1
14 MCPW PMP‐3 Kanach Zone G 5,728 150 DI‐K9 20
132
15 GLR‐12 R‐46 PMP‐3 4 150 DI‐K9 1
16 R‐46 PMP‐3 Zone‐3‐1 29 150 DI‐K9 1
17 GLR‐13 R‐49 PMP‐1 3 150 DI‐K9 1
18 R‐49 PMP‐1 Zone‐11A 23 150 DI‐K9 1
19 GLR‐2 R‐38 PMP‐1 4 150 DI‐K9 1
20 R‐38 PMP‐1 Rudawali Zone E 12 150 DI‐K9 1
21 GLR‐2 R‐38 PMP‐2 4 150 DI‐K9 1
22 R‐38 PMP‐2 J‐772 24 150 DI‐K9 1
23 J‐796 Zone‐12‐3 2,129 150 DI‐K9 8
24 J‐817 Zone‐6C‐1 316 150 DI‐K9 2
25 J‐821 Zone‐1A‐1 3,347 150 DI‐K9 12
26 J‐826 Zone‐2 1,134 150 DI‐K9 4
27 J‐689 Zone‐11B 1,108 150 DI‐K9 4
28 J‐834 J‐689 2,369 150 DI‐K9 8
29 J‐650 J‐122 410 200 DI‐K9 2
30 J‐696 Zone‐10 1,472 200 DI‐K9 5
31 J‐122 J‐696 1,808 200 DI‐K9 7
32 J‐710 Zone‐7A‐1 2,141 200 DI‐K9 8
33 J‐662 Zone‐6C 478 200 DI‐K9 2
34 J‐767 J‐632 1,266 200 DI‐K9 5
35 J‐666 J‐770 7,343 200 DI‐K9 25
36 J‐770 CWR‐2 43 200 DI‐K9 1
37 GLR‐1 PMP‐4 4 200 DI‐K9 1
38 PMP‐4 J‐767 1,314 200 DI‐K9 5
39 GLR‐1 R‐52 PMP‐1 3 200 DI‐K9 1
40 R‐52 PMP‐1 Bhbhaech Zone B 3 200 DI‐K9 1
41 GLR‐9 R‐42 PMP‐1 3 200 DI‐K9 1
42 R‐42 PMP‐1 Zone‐9‐3 10 200 DI‐K9 1
43 GLR‐9 R‐42 PMP‐2 3 200 DI‐K9 1
NCC LIMITED
Patwadh GOV WSP, District ‐ Sonbhadra
Thrustblock Quantity

Length   Pressure 
S.No. Start Node Stop Node Dia (mm) Qty Total Qty
(m) Class
44 R‐42 PMP‐2 Zone‐9‐1 5,136 200 DI‐K9 18
45 J‐802 Zone‐7A‐2 652 200 DI‐K9 3
46 J‐801 J‐802 4,127 200 DI‐K9 14
233
47 J‐632 J‐810 1,768 200 DI‐K9 6
48 J‐810 Belcupp Zone A 1,384 200 DI‐K9 5
49 J‐667 J‐666 686 200 DI‐K9 3
50 J‐681 Zone‐10A‐1 873 200 DI‐K9 3
51 J‐752 Zone‐6A‐3 1,129 200 DI‐K9 4
52 J‐685 Zone‐3A‐3 998 200 DI‐K9 4
53 J‐691 Zone‐8C 1,317 200 DI‐K9 5
54 J‐702 Zone‐1‐1 1,721 200 DI‐K9 6
55 J‐670 Zone‐3‐2 and 3‐3 2,078 200 DI‐K9 7
56 J‐706 Zone‐6C‐3 1,502 200 DI‐K9 6
57 J‐720 Zone‐9‐2 2,010 200 DI‐K9 7
58 J‐730 Zone‐12‐1 3,704 200 DI‐K9 13
59 J‐717 J‐750 4,814 200 DI‐K9 17
60 J‐733 Zone‐9A‐1 258 200 DI‐K9 1
61 J‐718 J‐796 620 200 DI‐K9 3
62 J‐750 J‐821 8,665 200 DI‐K9 29
63 J‐741 J‐826 3,144 200 DI‐K9 11
64 J‐728 J‐834 537 200 DI‐K9 2
65 J‐649 Zone‐9A 370 250 DI‐K9 2
66 J‐660 J‐661 743 250 DI‐K9 3
67 J‐662 J‐663 590 250 DI‐K9 3
68 J‐675 CWR‐14 1,013 250 DI‐K9 5
69 J‐679 J‐680 1,181 250 DI‐K9 5
70 J‐661 Zone‐10A‐2 1,292 250 DI‐K9 6
71 J‐712 Zone‐6C‐2 2,070 250 DI‐K9 9
72 J‐663 Zone‐6 4,963 250 DI‐K9 20
73 J‐741 Zone‐2‐1 4,251 250 DI‐K9 18
74 J‐752 Zone‐8B 6,070 250 DI‐K9 25
75 J‐728 J‐679 2,255 250 DI‐K9 10
76 J‐659 J‐717 2,581 250 DI‐K9 11
77 J‐757 J‐730 1,889 250 DI‐K9 8
78 J‐757 Zone‐8 8,258 250 DI‐K9 34
79 J‐681 J‐660 2,876 250 DI‐K9 12
80 J‐762 Zone‐5B‐1 3,185 250 DI‐K9 13
81 J‐79 J‐677 1,602 250 DI‐K9 7
82 J‐128 J‐693 443 250 DI‐K9 2
83 J‐732 CWR‐8 3,319 250 DI‐K9 14
84 J‐693 CWR‐13 1,234 250 DI‐K9 5
85 J‐785 J‐741 4,254 250 DI‐K9 18
330
86 J‐677 CWR‐1 969 250 DI‐K9 4
NCC LIMITED
Patwadh GOV WSP, District ‐ Sonbhadra
Thrustblock Quantity

Length   Pressure 
S.No. Start Node Stop Node Dia (mm) Qty Total Qty
(m) Class
87 GLR‐4 R‐51 PMP‐1 4 250 DI‐K9 1
88 R‐51 PMP‐1 Zone‐5‐3 9 250 DI‐K9 1
89 GLR‐13 R‐49 PMP‐2 4 250 DI‐K9 1
90 R‐49 PMP‐2 J‐785 1,239 250 DI‐K9 5
91 GLR‐14 R‐50 PMP‐1 4 250 DI‐K9 1
92 R‐50 PMP‐1 J‐659 561 250 DI‐K9 3
93 GLR‐8 R‐54 PMP‐1 3 250 DI‐K9 1
94 R‐54 PMP‐1 Zone‐6A‐1 6 250 DI‐K9 1
95 GLR‐5 R‐23 PMP‐1 3 250 DI‐K9 1
96 R‐23 PMP‐1 Zone‐8D and 5‐2 10 250 DI‐K9 1
97 J‐797 J‐757 1,785 250 DI‐K9 8
98 GLR‐11 PMP‐28 17 250 DI‐K9 1
99 PMP‐28 Zone‐3A‐1 and 3A‐2 17 250 DI‐K9 1
100 J‐680 J‐801 927 250 DI‐K9 4
101 J‐801 Zone‐4A 4,706 250 DI‐K9 19
102 J‐717 J‐808 6,358 250 DI‐K9 26
103 J‐808 Zone‐1A 1,004 250 DI‐K9 5
104 J‐811 Zone C‐SALKHAM 42 250 DI‐K9 1
105 J‐128 J‐830 2,180 250 DI‐K9 9
106 J‐830 Zone‐2A 1,346 250 DI‐K9 6
107 J‐716 J‐675 2,219 300 DI‐K9 9
108 J‐734 J‐664 3,306 300 DI‐K9 14
109 J‐664 Zone‐6B and 6A 4,998 300 DI‐K9 20
110 J‐654 J‐128 6,085 300 DI‐K9 25
111 J‐673 J‐662 500 300 DI‐K9 2
112 J‐650 J‐722 1,588 300 DI‐K9 7
113 J‐734 J‐752 1,029 300 DI‐K9 5 171
114 J‐654 J‐681 8,606 300 DI‐K9 35
115 J‐702 J‐716 889 300 DI‐K9 4
116 J‐710 J‐673 1,731 300 DI‐K9 7
117 J‐722 J‐649 1,094 300 DI‐K9 5
118 J‐649 Zone‐9 5,281 300 DI‐K9 22
119 J‐806 J‐710 3,811 300 DI‐K9 16
120 J‐709 J‐650 690 350 DI‐K9 3
121 J‐700 J‐702 6,149 350 DI‐K9 25
122 J‐698 J‐700 1,159 350 DI‐K9 5
123 J‐776 J‐709 1,570 350 DI‐K9 7
124 GLR‐10 R‐44 PMP‐1 5 350 DI‐K9 1 48
125 R‐44 PMP‐1 J‐776 147 350 DI‐K9 1
126 GLR‐11 PMP‐29 21 350 DI‐K9 1
127 PMP‐29 J‐728 149 350 DI‐K9 1
128 J‐811 J‐79 878 350 DI‐K9 4
NCC LIMITED
Patwadh GOV WSP, District ‐ Sonbhadra
Thrustblock Quantity

Length   Pressure 
S.No. Start Node Stop Node Dia (mm) Qty Total Qty
(m) Class
129 J‐130 J‐714 4,369 400 DI‐K9 16
130 J‐725 J‐639 681 400 DI‐K9 3
131 J‐639 J‐667 680 400 DI‐K9 3
132 J‐667 J‐765 3,787 400 DI‐K9 14
133 J‐714 CWR‐11 5,038 400 DI‐K9 19
134 MGLR MCPW PMP‐1 13 400 DI‐K9 1
135 MCPW PMP‐1 J‐725 2,986 400 DI‐K9 11
136 J‐807 J‐712 2,652 400 DI‐K9 10
137 J‐806 J‐807 24 400 DI‐K9 1
138 J‐765 J‐811 3,428 400 DI‐K9 13
139 J‐706 J‐813 1,044 400 DI‐K9 4
140 J‐813 CWR‐6 87 400 DI‐K9 1
141 J‐670 J‐698 4,984 400 DI‐K9 19
142 J‐712 J‐479 4,343 400 DI‐K9 16 173
143 J‐780 J‐670 636 400 DI‐K9 3
144 J‐781 J‐654 492 400 DI‐K9 2
145 J‐788 J‐780 314 400 DI‐K9 2
146 GLR‐12 R‐46 PMP‐1 5 400 DI‐K9 1
147 R‐46 PMP‐1 J‐788 442 400 DI‐K9 2
148 GLR‐12 R‐46 PMP‐2 7 400 DI‐K9 1
149 R‐46 PMP‐2 J‐781 303 400 DI‐K9 2
150 J‐479 CWR‐8 100 400 DI‐K9 1
151 J‐792 J‐734 5,122 400 DI‐K9 19
152 GLR‐8 R‐54 PMP‐2 4 400 DI‐K9 1
153 R‐54 PMP‐2 J‐792 111 400 DI‐K9 1
154 J‐69 CWR‐7 900 400 DI‐K9 4
155 J‐817 J‐69 692 400 DI‐K9 3
156 J‐762 J‐641 1,663 600 DI‐K9 7
157 J‐691 J‐706 3,539 600 DI‐K9 13
158 J‐641 J‐685 4,664 600 DI‐K9 17
159 J‐685 J‐130 5,062 600 DI‐K9 19
160 J‐130 J‐782 1,870 600 DI‐K9 7
161 J‐782 CWR‐12 686 600 DI‐K9 3
162 GLR‐10 R‐44 PMP‐1 5 600 DI‐K9 1
163 GLR‐5 R‐23 PMP‐2 5 600 DI‐K9 1 102
164 R‐23 PMP‐2 J‐691 6,076 600 DI‐K9 23
165 GLR‐7 PMP‐30 3 600 DI‐K9 1
166 PMP‐30 J‐806 903 600 DI‐K9 4
167 GLR‐6 PMP‐31 13 600 DI‐K9 1
168 PMP‐31 J‐817 800 600 DI‐K9 3
169 R‐44 PMP‐1 J‐835 147 600 DI‐K9 1
170 J‐835 J‐762 91 600 DI‐K9 1
NCC LIMITED
Patwadh GOV WSP, District ‐ Sonbhadra
Thrustblock Quantity

Length   Pressure 
S.No. Start Node Stop Node Dia (mm) Qty Total Qty
(m) Class
171 J‐736 J‐732 985 800 DI‐K9 5
172 J‐797 J‐736 4,264 800 DI‐K9 22
173 J‐732 J‐687 2,397 800 DI‐K9 12 86
174 J‐687 J‐733 727 800 DI‐K9 4
175 J‐733 CWR‐10 8,406 800 DI‐K9 43
176 GLR‐5 R‐23 PMP‐3 6 900 DI‐K9 1
3
177 R‐23 PMP‐3 J‐797 215 900 DI‐K9 2
178 J‐644 J‐645 360 1000 MS 2
179 J‐720 J‐726 76 1000 DI‐K9 1
180 J‐726 J‐747 6,298 1000 DI‐K9 32
181 J‐655 J‐718 191 1000 DI‐K9 1
182 J‐718 J‐720 2,074 1000 DI‐K9 11
183 J‐645 CWR‐4 1,502 1000 MS 8
184 J‐747 CWR‐5 225 1000 DI‐K9 2 154
185 MGLR MCPW PMP‐2 14 1000 DI‐K9 1
186 MCPW PMP‐2 CWR‐3 13,559 1000 DI‐K9 89
187 GLR‐3 R‐53 PMP‐1 6 1000 MS 1
188 R‐53 PMP‐1 J‐644 317 1000 MS 2
189 GLR‐4 PMP‐8 5 1000 DI‐K9 1
190 PMP‐8 J‐655 432 1000 DI‐K9 3
TOTAL QTY 1432.00
ZONE WISE DISTRIBUTION PIPE ( GI & DI‐K7 )
Zones Babaecha Kanach Markundi Patwadh Redia Rudwali Belcup Salkhan Total
Sl.No DIA
Pipe type GI (MEDIUM DUTY) & DI K‐7 (Length in M)
1 50 GI 24960 13748 18989 26546 18746 28616 33445 22540
           187,590                 467
2 65 GI 9742 6250 9705 10647 6544 6945 13034 9685
             72,552                 598
3 80 GI 4180 2963 3803 5691 324 2453 5378 3550
             28,342                 735
GI Total 38882 22961 32497 42884 25614 38014 51857 35775
           288,484
4 100 DI-K7 6581 3704 7267 6217 3084 4565 3336 5421
             40,175              1,119
5 150 DI-K7 6210 4506 1547 2133 2789 2834 10899 1838
             32,756              1,640
6 200 DI-K7 3097 1313 2964 215 2541 1479 4535 1403
             17,547              1,890
7 250 DI-K7 2414 0 1420 834 0 0 398 1086
                6,152              2,475
8 300 DI-K7 70 0 0 0 744 3468
                4,282              3,118
DI Total         18,372           9,523         13,198           9,399           8,414           8,878        19,912        13,216            100,912
 GI + DI Total         57,254         32,484         45,695         52,283         34,028         46,892        71,769        48,991            389,396

ZONE WISE DISTRIBUTION PIPE ( HDPE & DI‐K7 )
Zones ZONE‐1 ZONE‐1‐1 ZONE‐1A‐1 ZONE‐1A ZONE‐2 ZONE‐2‐1 ZONE‐2A ZONE‐3‐1 ZONE‐3‐2 ZONE‐3‐3
Sl.No DIA
Pipe type
1 63 HDPE 40240 26062 14669 38744 33477 25608 37458 30189 33988 37338
2 75 HDPE 5896 2193 1520 3200 4115 2994 3784 3091 2755 1883
3 90 HDPE 3839 1919 474 5365 2656 5376 3847 1631 2739 3413
4 110 HDPE 2303 1967 905 4502 3085 2118 2326 1304 1236 3060
5 140 HDPE 3388 1838 5359 4014 3844 2781 5374 5580 2089 6719
6 160 HDPE 2845 3693 1474 6997 1848 1706 1540 2263 377 1973
7 200 HDPE 3991 620 3225 3838 944 2177 237 787 1920
HDPE Total 62502 37672 25021 66047 52863 41527 56506 44295 43971 56306
8 200 DI-K7 2889 2722 2910 2227 1658 1282 872
9 250 DI-K7 560 123 3150 427 2939 3034 1379 1994 327 2444
10 300 DI-K7 460 2131 238 1697
11 350 DI-K7
12 400 DI-K7
DI Total           1,020           3,012           5,872           3,337           2,939           5,261           5,168           3,514                 1,199              4,141
HDPE + DI Total         63,522         40,684         30,893         69,384         55,802         46,788        61,674        47,809              45,170            60,447
ZONE WISE DISTRIBUTION PIPE ( HDPE & DI‐K7 )
Zones ZONE‐3A‐1 ZONE‐3A‐2 ZONE‐3A‐3 ZONE‐3B‐1 ZONE‐4A ZONE‐5‐1 ZONE‐5‐3 ZONE‐5B‐1 ZONE‐6
Sl.No DIA
Pipe type
1 63 HDPE 26080 28614 35191 29555 56993 22526 49548 44823 27382
2 75 HDPE 1574 1888 2611 2569 6013 1542 4750 3174 2537
3 90 HDPE 2972 1441 2205 2364 4778 3802 1785 2493 1971
4 110 HDPE 1379 1993 2543 1671 4301 3373 1496 5997 2648
5 140 HDPE 2499 2093 1959 1126 2218 2113 2495 1890 3525
6 160 HDPE 594 1717 1280 3146 2690 795 740 2700 698
7 200 HDPE 951 3856 1909 2741 2016 636 5162 4773 2733
HDPE Total 36049 41602 47698 43172 79009 34787 65976 65850 41494
8 200 DI-K7 1311 1148 1234 195 4763 1964 1290 2031
9 250 DI-K7 1132 2168 3028 918 2144 2106 4775 1579 124
10 300 DI-K7 127 420 378 640 259
11 350 DI-K7
12 400 DI-K7
DI Total                            2,443              3,316              4,389              1,533              7,285              4,070              6,705              3,869                 124
HDPE + DI Total                         38,492            44,918            52,087            44,705            86,294            38,857            72,681            69,719            41,618
ZONE WISE DISTRIBUTION PIPE ( HDPE & DI‐K7 )
Zones ZONE‐6A ZONE‐6B ZONE‐6A‐1 ZONE‐6A‐3 ZONE‐6C ZONE‐6C‐1 ZONE‐6C‐2 ZONE‐6C‐3 ZONE‐ 6A‐2
Sl.No DIA
Pipe type HDPE, PE‐100, PN‐6 & DI K‐7 (Length in 
1 63 HDPE 34890 41120 47186 29603 42198 29604 42802 22614 50747
2 75 HDPE 2678 4570 3171 3594 3026 2181 2185 2577 4305
3 90 HDPE 620 2425 2263 4995 2367 2985 3820 1797 2369
4 110 HDPE 1739 3397 4056 4420 2474 1339 2057 614 1611
5 140 HDPE 693 3639 3300 2563 2027 1591 3574 2470 3211
6 160 HDPE 1645 3122 2211 1138 5899 814 690 1153 0
7 200 HDPE 2777 2634 691 2550 498 1915 2638 1229 835
HDPE Total 45042 60907 62878 48863 58489 40429 57766 32454 63078
8 200 DI-K7 2840 925 1134 443 4820 1842 1962 1928
9 250 DI-K7 462 1384 453 1736 1003 6161 1860 2303
10 300 DI-K7 846 791 43 766 619 23
11 350 DI-K7 355 511
12 400 DI-K7
DI Total              3,686              2,178              2,561              2,017              7,686              1,003              8,026              3,822              4,231
HDPE + DI Total            48,728            63,085            65,439            50,880            66,175            41,432            65,792            36,276            67,309
ZONE WISE DISTRIBUTION PIPE ( HDPE & DI‐K7 )
Zones ZONE‐7B  ZONE‐7A‐1 ZONE‐7A‐2 ZONE‐8 ZONE‐8B ZONE‐8C ZONE‐8D ZONE‐5‐2 ZONE‐9 ZONE‐9‐1
Sl.No DIA
Pipe type M)
1 63 HDPE 57444 37032 18849 43430 37188 38708 29758 44184 39472 36329
2 75 HDPE 2131 2533 3104 2343 4945 3127 2740 3354 3341 2679
3 90 HDPE 1411 3158 1367 4364 5516 4007 1720 2178 2776 3542
4 110 HDPE 2091 6122 1113 5032 2982 2426 1028 4307 3300 2261
5 140 HDPE 2033 3798 2905 1809 3527 1707 3809 5088 2220 4908
6 160 HDPE 2826 186 2134 4947 3848 2077 2635 2749 3061 2305
7 200 HDPE 634 4244 1595 1790 4097 3857 615 568 2779 1406
HDPE Total 68570 57073 31067 63715 62103 55909 42305 62428 56949 53430
8 200 DI-K7 176 2086 1177 611 808 1089 566 1865
9 250 DI-K7 1301 776 2045 2520 530 2877 3247 1780 649 444
10 300 DI-K7 307 490 1115 935 1464 3626 2150
11 350 DI-K7 948 517
12 400 DI-K7
DI Total              1,477                 776              4,131              4,004              1,968              4,603              4,990              4,333              4,841              4,976
HDPE + DI Total            70,047            57,849            35,198            67,719            64,071            60,512            47,295            66,761            61,790            58,406
ZONE WISE DISTRIBUTION PIPE ( HDPE & DI‐K7 )
Zones ZONE‐9‐2 ZONE‐9‐3 ZONE‐9A ZONE‐9A‐1 ZONE‐10 ZONE‐10A‐1 ZONE‐10A‐2 ZONE‐11 ZONE‐11A ZONE‐11A‐1
Sl.No DIA
Pipe type
1 63 HDPE 26004 26734 29698 52092 35261 28241 40020 33017 26459 28736
2 75 HDPE 1576 1678 2326 4592 1991 3892 3775 4384 1949 2704
3 90 HDPE 3043 1123 2349 3089 3030 1677 2102 4413 1501 2171
4 110 HDPE 2054 1615 2532 2791 4647 2987 4564 1854 2290 856
5 140 HDPE 2731 5246 2582 2680 9019 2530 5656 4772 1344 1138
6 160 HDPE 1343 57 2644 1934 1290 1055 3010 254 36 1335
7 200 HDPE 2657 1567 3299 1498 1800 1466 2003 1023 1073
HDPE Total 36751 39110 43698 70477 56736 42182 60593 50697 34602 38013
8 200 DI-K7 645 2629 1681 3150 2114 3328 1850 612 2370 254
9 250 DI-K7 1008 1975 4320 763 564 2233 524 1752 1254
10 300 DI-K7 42 372 1370 606 870 1418 606
11 350 DI-K7 1522
12 400 DI-K7
DI Total                 645              3,679              4,028            10,362              3,483              4,762              5,501              1,742              4,122              1,508
HDPE + DI Total            37,396            42,789            47,726            80,839            60,219            46,944            66,094            52,439            38,724            39,521
Zones ZONE‐11B ZONE‐12‐1 ZONE‐12‐2 ZONE‐12‐3 TOTAL
Sl.No DIA
Pipe type
1 63 HDPE 31439 22585 24142 38269      1,804,340
2 75 HDPE 4216 1756 1159 1990          154,661
3 90 HDPE 4438 1720 2825 2048          144,279
4 110 HDPE 1058 3320 3586 1990          136,720
5 140 HDPE 1826 3602 2202 2094          163,198
6 160 HDPE 2195 2266 1251 2125          103,311
7 200 HDPE 1438 1125 1059 1940          101,816
HDPE Total 46610 36374 36224 50456      2,608,325
8 200 DI-K7 1732 840 530 297            74,800
9 250 DI-K7 2947 278 469            83,969
10 300 DI-K7 1634 1421 298            28,162
11 350 DI-K7              3,853
12 400 DI-K7                  ‐
DI Total              6,313              2,539                 530              1,064          190,784
HDPE + DI Total            52,923            38,913            36,754            51,520      2,799,109
Patwadh GOV WSP
Boundary Wall Length

CAPACITY DIMENSION Length Of 


SR. NO. ZONE BLOCK LOCATION STAGING STRUCTURE GHATA NO. OHSR Boundary Wall 
OHSR GLR REQUIRED AVAILABLE
(Rmt)
BELCUPP 
1 Robertsganj Belcupp 450 22 OHSR 40 m X 40 m 25 m X 25 m 100
(ZONE‐1)
BHABHAECH 
2 Robertsganj Bhbhaech 450 200 18 OHSR + GLR‐2 3384 KA 40 m X 40 m 60 m X 42 m 204
(ZONE‐2)
REDIA 
3 Obra Kurhul 200 14 OHSR 396 40 m X 40 m 30 m X 30 m 120
(ZONE‐3A)
SALKHAN 
4 Robertsganj Salkhan 500 10 OHSR 3078 , 3079 40 m X 40 m 40 m X 40 m 160
(ZONE‐3B)
MARKUNDI 
5 Robertsganj Markundi 300 20 OHSR 2418 40 m X 40 m 32 m X 32 m 128
(ZONE‐4)
RUDAWALI 
6 Robertsganj Rudawali 150 100 22 OHSR + GLR‐3 15/3 MI 40 m X 40 m 50 m X 50 m 200
(ZONE‐5)
PATWDH 
7 Obra Patwadh 250 10 OHSR 623 40 m X 40 m 40 m X 40 m 160
(ZONE‐6)
KANACH 
8 Obra Kanach 150 16 OHSR 171 KHA 40 m X 40 m 30 m X 30 m 120
(ZONE‐7)
9 ZONE‐1 Ghorawal Barbaspur 350 15 OHSR  76 MI 75 m X 75 m 25 m X 30 m 110
10 ZONE‐1‐1 Ghorawal Pathartal 300 19 OHSR 89 40 m X 40 m 40 m X 40 m 160
11 ZONE‐1A‐1 Ghorawal Sapahi 250 19 OHSR 111 MI 40 m X 40 m 40 m X 40 m 160
12 ZONE‐1A Ghorawal Parsauna 350 22 OHSR 34 MI 40 m X 40 m 30 m X 30 m 120
13 ZONE‐2 Ghorawal Deogarha 350 10 OHSR 399 GA MI 40 m X 40 m 40 m X 40 m 160
14 ZONE‐2‐1 Ghorawal Bardiya 400 19 OHSR 1055 MI 40 m X 40 m 40 m X 40 m 160
32 KA
15 ZONE‐2A Ghorawal Bharkana 450 22 OHSR 40 m X 40 m 40 m X 40 m 160
(Section 6,4 )
16 ZONE‐3‐1 Ghorawal Khutaha 400 1200 15 OHSR + GLR‐13 760 MI 75 m X 75 m 50 m X 60 m 220
17 ZONE‐3‐2 & 3‐3 Ghorawal Satohan 650 14 OHSR 277 ,288 40 m X 40 m 30 m X 30 m 120
18 ZONE‐11 Ghorawal Peroh 300 13 OHSR  833 KHA 75 m X 75 m 25 m X 25 m 100
19 ZONE‐11A Ghorawal Birkhurd 250 22 OHSR + GLR‐14 195 60 m X 60 m 60 m X 60 m 240
20 ZONE‐11A‐1 Ghorawal Bhawana  200 250 18 OHSR 282 MI  40 m X 40 m 40 m X 40 m 160
21 ZONE‐11B Ghorawal Visahar 400 14 OHSR 550 KA 40 m X 40 m 40 m X 40 m 160
22 ZONE‐10A‐1 Ghorawal Karaundia 400 18 OHSR 154 40 m X 40 m 40 m X 40 m 160
23 ZONE‐10A‐2 Ghorawal Khirahata 500 21 OHSR 302 40 m X 40 m 30 m X 30 m 120
24 ZONE‐10 Ghorawal Tendui 450 10 OHSR 367 MI 40 m X 40 m 30 m X 30 m 120
25 ZONE‐3B‐1 Ghorawal Belkuri/ Teti 300 15 OHSR 306 40 m X 40 m 40 m X 100 m 280
26 ZONE‐3A‐1 & 3A‐2 Ghorawal Jogini 600 400 20 OHSR + GLR‐12 469 MI 40 m X 40 m 40 m X 40 m 160
27 ZONE‐3A‐3 Ghorawal Karrivaroi 400 20 OHSR  411 75 m X 75 m 110 m X 110 m 440
28 ZONE‐6 Robertsganj Sirsiathkurai 300 21 OHSR 1006 KA MI 40 m X 40 m 30 m X 110 m 280
29 ZONE‐6B & 6A Robertsganj Lohara 800 19 OHSR 269 40 m X 40 m 40 m X 45 m 170
30 ZONE‐7B & 6A‐2 Robertsganj Bat 450 20 OHSR 166 MI 40 m X 40 m 30 m X 30 m 120

Page 1 of 2
Patwadh GOV WSP
Boundary Wall Length

CAPACITY DIMENSION Length Of 


SR. NO. ZONE BLOCK LOCATION STAGING STRUCTURE GHATA NO. OHSR Boundary Wall 
OHSR GLR REQUIRED AVAILABLE
(Rmt)
31 ZONE‐6A‐1 Robertsganj Bhawanipur 350 600 22 OHSR + GLR‐9 43 75 m X 75 m 75 m X 75 m 300
32 ZONE‐6A‐3 Robertsganj Kamhariya 600 22 OHSR 54 MI 40 m X 40 m 30 m X 30 m 120
33 ZONE‐4A Ghorawal Karkoll 550 22 OHSR 397 MI 40 m X 40 m 40 m X 40 m 160
34 ZONE‐6C Robertsganj Dilahi 500 15 OHSR 17 40 m X 40 m 39 m X 39 m 156
35 ZONE‐7A‐2 Ghorawal Jorwariya 300 17 OHSR 712 40 m X 40 m 30 m X 30 m 120
36 ZONE‐7A‐1 Robertsganj Jawahi 300 20 OHSR 450 40 m X 40 m 26 m X 30 m 112
37 ZONE‐6C‐1 Ghorawal Jokahi 250 17 OHSR 1/3 MI 40 m X 40 m 30 m X 45 m 150
38 ZONE‐6C‐2 Robertsganj Bakahi 450 17 OHSR 133 40 m X 40 m 40 m X 40 m 160
39 ZONE‐6C‐3 Robertsganj Parsona 250 19 OHSR 96 40 m X 40 m 30 m X 39 m 138
40 ZONE‐5B‐1 Ghorawal Welanow 500 21 OHSR 156 KA 40 m X 40 m 40 m X 40 m 160
41 ZONE‐9A‐1 Robertsganj Shalaiya 650 19 OHSR  235 MI  75 m X 75 m 60 m X 80 m 280
42 ZONE‐5‐1 Robertsganj Deori Kalan 250 17 OHSR 54 40 m X 40 m 30 m X 30 m 120
43 ZONE‐8B Robertsganj Chandoli 450 22 OHSR 58kha 40 m X 40 m 35 m X 35 m 140
44 ZONE‐8 Robertsganj Bishbhrpur 400 16 OHSR 51 40 m X 40 m 30 m X 30 m 120
45 ZONE‐8C Robertsganj Pashi Kalana 400 22 OHSR 238 239 40 m X 40 m 35 m X 40 m 150
46 ZONE‐8D & 5‐2 Robertsganj Ganguar 900 4100 22 OHSR + GLR‐6 107 75 m X 75 m 90 m X 29 m 238
47 ZONE‐5‐3 Robertsganj Lodhi 650 4400 10 OHSR + GLR‐5 1175 KHA 75 m X 75 m 97 m X 54 m 302
48 ZONE‐9A Ghorawal Dugaulia 450 19 OHSR 656 40 m X 40 m 30 m X 40 m 140
49 ZONE‐9 Robertsganj Judoli ‐Kalani 650 17 OHSR 112 KHA 40 m X 40 m 30 m X 30 m 120
50 ZONE‐9‐1 Robertsganj Bahuar 450 18 OHSR 1116 40 m X 40 m 40 m X 40 m 160
51 ZONE‐9‐2 Robertsganj Tilauli/ Semera 250 10 OHSR 56 MI 40 m X 40 m 30 m X 41 m 142
52 ZONE‐9‐3 Robertsganj Nipraj 450 200 19 OHSR + GLR‐10 222 50 m X 50 m 30m X 30m 120
53 ZONE‐12‐1 Robertsganj Lashra 350 17 OHSR 18 40 m X 40 m 40 m X 40 m 160
54 ZONE‐12‐2 Robertsganj Arouly 150 18 OHSR 355 40 m X 40 m 40 m X 40 m 160
55 ZONE‐12‐3 Robertsganj Raunp 300 10 OHSR 913 40 m X 40 m 75 m X 75 m 300
MARKUNDI 
56 Robertsganj Markundi 4400 GLR 913 110 mX110 m 110 mX110 m 440
(ZONE‐4)
57 ZONE‐6C‐2 Robertsganj Kuchamarwa  1000 GLR 86 50 m X 50 m 50 m X 50 m 200
58 PAPI Robertsganj Papi 950 GLR 73 25 m X 25 m 25 m X 25 m 100
59 ZONE‐5B‐1 Robertsganj Kushra 2200 GLR 50 m X 50 m 50 m X 50 m 200
60 ZONE‐1 Ghorawal Sirsain 250 GLR 76 mi 50 m X 50 m 50 m X 50 m 200
61 WTP 1022
Total Length 11462

Page 2 of 2
Patwadh GOV WSP
Earthwork Excavation Quantity
Exacavation Quantity (cum)
S.No Dia Pipe Type Zone Soil Strata Length (m) Width (m) Depth (m)
Hard Rock Medium Rock Mixed Soil Ordinary Soil
63 HDPE 40240 0.66 1.06 1418 1418 25524
75 HDPE 5896 0.68 1.08 214 214 3850
90 HDPE 3839 0.69 1.09 144 144 2599
110 HDPE 2303 0.71 1.11 91 91 1633
140 HDPE 3388 0.74 1.14 143 143 2572
160 HDPE 2845 0.76 1.16 125 125 2257
200 HDPE 3991 0.80 1.20 192 192 3448
200 DI‐K7 90% Soil,  0 0.80 1.20 0 0 0
1 Zone‐1
250 DI‐K7 10% rock 560 0.85 1.25 30 30 536
300 DI‐K7 460 0.90 1.30 27 27 484
350 DI‐K7 0 0.95 1.35 0 0 0
400 DI‐K7 0 1.00 1.40 0 0 0
150 DI‐K9 437 0.75 1.15 19 19 339
200 DI‐K9 1383 0.80 1.20 66 66 1195
250 DI‐K9 7630 0.85 1.25 405 405 7296
300 DI‐K9 528 0.90 1.30 31 31 556
Total 73500 2905 2905 52289

63 HDPE 26062 0.66 1.06 1837 918 15613


75 HDPE 2193 0.68 1.08 159 80 1353
90 HDPE 1919 0.69 1.09 144 72 1227
110 HDPE 1967 0.71 1.11 155 78 1318
140 HDPE 1838 0.74 1.14 155 78 1318
160 HDPE 3693 0.76 1.16 326 163 2767
200 HDPE 0 0.80 1.20 0 0 0
10%  Rock , 
2 200 DI‐K7 Zone‐1‐1 2889 0.80 1.20 277 139 2357
90% Soil
250 DI‐K7 123 0.85 1.25 13 7 111
300 DI‐K7 0 0.90 1.30 0 0 0
350 DI‐K7 0 0.95 1.35 0 0 0
400 DI‐K7 0 1.00 1.40 0 0 0
200 DI‐K9 1720 0.80 1.20 165 83 1404
300 DI‐K9 2580 0.90 1.30 302 151 2566
350 DI‐K9 3918 0.95 1.35 502 251 4271
Total 48902 4035 2020 34305

Page 1 of 29
Patwadh GOV WSP
Earthwork Excavation Quantity
Exacavation Quantity (cum)
S.No Dia Pipe Type Zone Soil Strata Length (m) Width (m) Depth (m)
Hard Rock Medium Rock Mixed Soil Ordinary Soil
63 HDPE 14669 0.66 1.06 517 2585 1034 6203
75 HDPE 1520 0.68 1.08 55 276 110 662
90 HDPE 474 0.69 1.09 18 89 36 214
110 HDPE 905 0.71 1.11 36 178 71 428
140 HDPE 5359 0.74 1.14 226 1130 452 2713
160 HDPE 1474 0.76 1.16 65 325 130 780
200 HDPE 70% Soil,  620 0.80 1.20 30 149 60 357
3 Zone‐1A‐1
200 DI‐K7 30% Rock 2722 0.80 1.20 131 653 261 1568
250 DI‐K7 3150 0.85 1.25 167 837 335 2008
300 DI‐K7 0 0.90 1.30 0 0 0 0
350 DI‐K7 0 0.95 1.35 0 0 0 0
400 DI‐K7 0 1.00 1.40 0 0 0 0
150 DI‐K9 3347 0.75 1.15 144 722 289 1732
200 DI‐K9 7152 0.80 1.20 343 1716 687 4120
Total 41392 1732 8660 3465 20785

63 HDPE 38744 0.66 1.06 1365 2731 4096 19114


75 HDPE 3200 0.68 1.08 116 232 348 1625
90 HDPE 5365 0.69 1.09 202 404 605 2825
110 HDPE 4502 0.71 1.11 177 355 532 2484
140 HDPE 4014 0.74 1.14 169 339 508 2370
160 HDPE 6997 0.76 1.16 308 617 925 4318
200 HDPE 85% Soil,  3225 0.80 1.20 155 310 464 2167
4 Zone‐1A
200 DI‐K7 15% Rock 2910 0.80 1.20 140 279 419 1956
250 DI‐K7 427 0.85 1.25 23 45 68 318
300 DI‐K7 0 0.90 1.30 0 0 0 0
350 DI‐K7 0 0.95 1.35 0 0 0 0
400 DI‐K7 0 1.00 1.40 0 0 0 0
200 DI‐K9 4947 0.80 1.20 237 475 712 3324
250 DI‐K9 3887 0.85 1.25 206 413 619 2891
Total 78218 3098 6200 9296 43392

Page 2 of 29
Patwadh GOV WSP
Earthwork Excavation Quantity
Exacavation Quantity (cum)
S.No Dia Pipe Type Zone Soil Strata Length (m) Width (m) Depth (m)
Hard Rock Medium Rock Mixed Soil Ordinary Soil
63 HDPE 33477 0.66 1.06 1180 9437 8258 4719
75 HDPE 4115 0.68 1.08 149 1194 1045 597
90 HDPE 2656 0.69 1.09 100 799 699 400
110 HDPE 3085 0.71 1.11 122 973 851 486
140 HDPE 3844 0.74 1.14 162 1297 1135 649
160 HDPE 1848 0.76 1.16 81 652 570 326
200 HDPE 45% Rock,  3838 0.80 1.20 184 1474 1290 737
5 Zone‐2
200 DI‐K7 55%  Soil  0 0.80 1.20 0 0 0 0
250 DI‐K7 2939 0.85 1.25 156 1249 1093 625
300 DI‐K7 0 0.90 1.30 0 0 0 0
350 DI‐K7 0 0.95 1.35 0 0 0 0
400 DI‐K7 0 1.00 1.40 0 0 0 0
150 DI‐K9 1134 0.75 1.15 49 391 342 196
200 DI‐K9 1418 0.80 1.20 68 545 476 272
Total 58354 2251 18011 15759 9007

63 HDPE 25608 0.66 1.06 902 3610 1805 10829


75 HDPE 2994 0.68 1.08 109 435 217 1304
90 HDPE 5376 0.69 1.09 202 809 404 2426
110 HDPE 2118 0.71 1.11 83 334 167 1002
140 HDPE 2781 0.74 1.14 117 469 235 1408
160 HDPE 1706 0.76 1.16 75 301 150 902
200 HDPE 70% Soil,  944 0.80 1.20 45 181 91 544
6 Zone‐2‐1
200 DI‐K7 30% Rock 2227 0.80 1.20 107 428 214 1283
250 DI‐K7 3034 0.85 1.25 161 645 322 1934
300 DI‐K7 0 0.90 1.30 0 0 0 0
350 DI‐K7 0 0.95 1.35 0 0 0 0
400 DI‐K7 0 1.00 1.40 0 0 0 0
200 DI‐K9 1725 0.80 1.20 83 331 166 994
250 DI‐K9 7350 0.85 1.25 390 1562 781 4686
Total 55863 2274 9105 4552 27312

Page 3 of 29
Patwadh GOV WSP
Earthwork Excavation Quantity
Exacavation Quantity (cum)
S.No Dia Pipe Type Zone Soil Strata Length (m) Width (m) Depth (m)
Hard Rock Medium Rock Mixed Soil Ordinary Soil
63 HDPE 37458 0.66 1.06 1320 3960 21119
75 HDPE 3784 0.68 1.08 137 412 2197
90 HDPE 3847 0.69 1.09 145 434 2315
110 HDPE 2326 0.71 1.11 92 275 1466
140 HDPE 5374 0.74 1.14 227 680 3627
160 HDPE 1540 0.76 1.16 68 204 1086
200 HDPE 5% Rock ,  2177 0.80 1.20 104 313 1672
7 Zone‐2A
200 DI‐K7 95% Soil 1658 0.80 1.20 80 239 1273
250 DI‐K7 1379 0.85 1.25 73 220 1172
300 DI‐K7 2131 0.90 1.30 125 374 1995
350 DI‐K7 0 0.95 1.35 0 0 0
400 DI‐K7 0 1.00 1.40 0 0 0
250 DI‐K9 6669 0.85 1.25 354 1063 5669
300 DI‐K9 757 0.90 1.30 44 133 709
Total 69100 2769 8307 44300

63 HDPE 30189 0.66 1.06 3191 18085


75 HDPE 3091 0.68 1.08 336 1906
90 HDPE 1631 0.69 1.09 184 1043
110 HDPE 1304 0.71 1.11 154 874
140 HDPE 5580 0.74 1.14 706 4001
160 HDPE 2263 0.76 1.16 299 1696
200 HDPE 237 0.80 1.20 34 193
200 DI‐K7 1282 0.80 1.20 185 1046
8 Zone‐3‐1 Soil
250 DI‐K7 1994 0.85 1.25 318 1801
300 DI‐K7 238 0.90 1.30 42 237
350 DI‐K7 0 0.95 1.35 0 0
400 DI‐K7 0 1.00 1.40 0 0
200 DI‐K9 1091 0.80 1.20 157 890
300 DI‐K9 5362 0.90 1.30 941 5333
400 DI‐K9 2824 1.00 1.40 593 3361
600 DI‐K9 1181 1.20 1.60 340 1927
Total 58267 7480 42393

Page 4 of 29
Patwadh GOV WSP
Earthwork Excavation Quantity
Exacavation Quantity (cum)
S.No Dia Pipe Type Zone Soil Strata Length (m) Width (m) Depth (m)
Hard Rock Medium Rock Mixed Soil Ordinary Soil
63 HDPE 33988 0.66 1.06 2395 21558
75 HDPE 2755 0.68 1.08 200 1799
90 HDPE 2739 0.69 1.09 206 1854
110 HDPE 1236 0.71 1.11 97 877
140 HDPE 2089 0.74 1.14 176 1586
160 HDPE 377 0.76 1.16 33 299
200 HDPE 787 0.80 1.20 76 680
9 Zone‐3‐2 Soil
200 DI‐K7 872 0.80 1.20 84 753
250 DI‐K7 327 0.85 1.25 35 313
300 DI‐K7 0 0.90 1.30 0 0
350 DI‐K7 0 0.95 1.35 0 0
400 DI‐K7 0 1.00 1.40 0 0
200 DI‐K9 987 0.80 1.20 95 853
400 DI‐K9 1806 1.00 1.40 253 2276
Total 47963 3650 32848

63 HDPE 37338 0.66 1.06 2631 23683


75 HDPE 1883 0.68 1.08 137 1230
90 HDPE 3413 0.69 1.09 257 2310
110 HDPE 3060 0.71 1.11 241 2170
140 HDPE 6719 0.74 1.14 567 5101
160 HDPE 1973 0.76 1.16 174 1565
200 HDPE 1920 0.80 1.20 184 1659
10 Zone‐3‐3 Soil
200 DI‐K7 0 0
250 DI‐K7 2444 0.85 1.25 260 2337
300 DI‐K7 1697 0.90 1.30 199 1787
350 DI‐K7 0 0.95 1.35 0 0
400 DI‐K7 0 1.00 1.40 0 0
400 DI‐K9 3895 1.00 1.40 545 4908
600 DI‐K9 4009 1.20 1.60 770 6928
Total 68351 5965 53678

Page 5 of 29
Patwadh GOV WSP
Earthwork Excavation Quantity
Exacavation Quantity (cum)
S.No Dia Pipe Type Zone Soil Strata Length (m) Width (m) Depth (m)
Hard Rock Medium Rock Mixed Soil Ordinary Soil
63 HDPE 26098 0.66 1.06 920 4598 3679 9197
75 HDPE 1574 0.68 1.08 57 286 228 571
90 HDPE 2972 0.69 1.09 112 559 447 1118
110 HDPE 1379 0.71 1.11 54 272 217 543
140 HDPE 2499 0.74 1.14 105 527 422 1054
160 HDPE 594 0.76 1.16 26 131 105 262
200 HDPE 951 0.80 1.20 46 228 183 456
200 DI‐K7 1311 0.80 1.20 63 315 252 629
Soil 70% , 
11 250 DI‐K7 Zone‐3A‐1 1132 0.85 1.25 60 301 241 601
Rock 30%
300 DI‐K7 0 0.90 1.30 0 0 0 0
350 DI‐K7 0 0.95 1.35 0 0 0 0
400 DI‐K7 0 1.00 1.40 0 0 0 0
150 DI‐K9 1156 0.75 1.15 50 249 199 499
200 DI‐K9 537 0.80 1.20 26 129 103 258
250 DI‐K9 4047 0.85 1.25 215 1075 860 2150
350 DI‐K9 170 0.95 1.35 11 55 44 109
400 DI‐K9 443 1.00 1.40 31 155 124 310
Total 44863 1776 8880 7104 17757

63 HDPE 28614 0.66 1.06 8067 4033 8067


75 HDPE 1888 0.68 1.08 548 274 548
90 HDPE 1441 0.69 1.09 434 217 434
110 HDPE 1993 0.71 1.11 628 314 628
140 HDPE 2093 0.74 1.14 706 353 706
160 HDPE 1717 0.76 1.16 605 303 605
Soil 60% , 
12 200 HDPE Zone‐3A‐2 3856 0.80 1.20 1481 740 1481
Rock40%
200 DI‐K7 1148 0.80 1.20 441 220 441
250 DI‐K7 2168 0.85 1.25 921 461 921
300 DI‐K7 0 0.90 1.30 0 0 0
350 DI‐K7 0 0.95 1.35 0 0 0
400 DI‐K7 0 1.00 1.40 0 0 0
400 DI‐K9 5067 1.00 1.40 2838 1419 2838
Total 49985 16669 8334 16669

Page 6 of 29
Patwadh GOV WSP
Earthwork Excavation Quantity
Exacavation Quantity (cum)
S.No Dia Pipe Type Zone Soil Strata Length (m) Width (m) Depth (m)
Hard Rock Medium Rock Mixed Soil Ordinary Soil
63 HDPE 35191 0.66 1.06 1240 23561
75 HDPE 2611 0.68 1.08 95 1800
90 HDPE 2205 0.69 1.09 83 1575
110 HDPE 2543 0.71 1.11 100 1904
140 HDPE 1959 0.74 1.14 83 1570
160 HDPE 1280 0.76 1.16 56 1072
200 HDPE 1909 0.80 1.20 92 1741
13 Zone‐3A‐3 Soil
200 DI‐K7 1234 0.80 1.20 59 1125
250 DI‐K7 3028 0.85 1.25 161 3056
300 DI‐K7 127 0.90 1.30 7 141
350 DI‐K7 0 0.95 1.35 0 0
400 DI‐K7 0 1.00 1.40 0 0
200 DI‐K9 209 0.80 1.20 10 191
600 DI‐K9 1986 1.20 1.60 191 3622
Total 54282 2177 41358

63 HDPE 29555 0.66 1.06 2083 18747


75 HDPE 2569 0.68 1.08 186 1678
90 HDPE 2284 0.69 1.09 172 1546
110 HDPE 1671 0.71 1.11 132 1185
140 HDPE 1206 0.74 1.14 102 916
160 HDPE 3146 0.76 1.16 277 2496
200 HDPE 2741 0.80 1.20 263 2368
200 DI‐K7 195 0.80 1.20 19 168
14 Zone‐3B‐1 Soil
250 DI‐K7 918 0.85 1.25 98 878
300 DI‐K7 420 0.90 1.30 49 442
350 DI‐K7 0 0.95 1.35 0 0
400 DI‐K7 0 1.00 1.40 0 0
150 DI‐K9 193 0.75 1.15 17 150
200 DI‐K9 788 0.80 1.20 76 681
250 DI‐K9 511 0.85 1.25 54 489
600 DI‐K9 4584 1.20 1.60 880 7921
Total 50781 4408 39665

Page 7 of 29
Patwadh GOV WSP
Earthwork Excavation Quantity
Exacavation Quantity (cum)
S.No Dia Pipe Type Zone Soil Strata Length (m) Width (m) Depth (m)
Hard Rock Medium Rock Mixed Soil Ordinary Soil
63 HDPE 56993 0.66 1.06 2008 38159
75 HDPE 6013 0.68 1.08 218 4145
90 HDPE 4778 0.69 1.09 180 3414
110 HDPE 4301 0.71 1.11 169 3220
140 HDPE 2218 0.74 1.14 94 1778
160 HDPE 2690 0.76 1.16 119 2253
200 HDPE 2016 0.80 1.20 97 1839
15 Zone‐4A Soil
200 DI‐K7 4763 0.80 1.20 229 4344
250 DI‐K7 2144 0.85 1.25 114 2164
300 DI‐K7 378 0.90 1.30 22 420
350 DI‐K7 0 0.95 1.35 0 0
400 DI‐K7 0 1.00 1.40 0 0
200 DI‐K9 3265 0.80 1.20 157 2978
250 DI‐K9 5053 0.85 1.25 268 5100
Total 94612 3675 69814

63 HDPE 22526 0.66 1.06 1588 14288


75 HDPE 1542 0.68 1.08 112 1007
90 HDPE 3802 0.69 1.09 286 2574
110 HDPE 3373 0.71 1.11 266 2392
140 HDPE 2113 0.74 1.14 178 1604
160 HDPE 795 0.76 1.16 70 631
16 200 HDPE Zone‐5‐1 Soil 636 0.80 1.20 61 550
200 DI‐K7 1964 0.80 1.20 189 1697
250 DI‐K7 2106 0.85 1.25 224 2014
300 DI‐K7 0 0.90 1.30 0 0
350 DI‐K7 0 0.95 1.35 0 0
400 DI‐K7 0 1.00 1.40 0 0
150 DI‐K9 709 0.75 1.15 61 550
Total 39566 3035 27307

Page 8 of 29
Patwadh GOV WSP
Earthwork Excavation Quantity
Exacavation Quantity (cum)
S.No Dia Pipe Type Zone Soil Strata Length (m) Width (m) Depth (m)
Hard Rock Medium Rock Mixed Soil Ordinary Soil
63 HDPE 44184 0.66 1.06 3114 3114 24912
75 HDPE 3354 0.68 1.08 243 243 1947
90 HDPE 2178 0.69 1.09 164 164 1310
110 HDPE 4307 0.71 1.11 339 339 2715
140 HDPE 5088 0.74 1.14 429 429 3434
160 HDPE 2749 0.76 1.16 242 242 1939
200 HDPE 568 0.80 1.20 55 55 436
10% Rock , 
17 200 DI‐K7 Zone‐5‐2 1089 0.80 1.20 105 105 836
90% Soil
250 DI‐K7 1780 0.85 1.25 189 189 1513
300 DI‐K7 1464 0.90 1.30 171 171 1370
350 DI‐K7 0 0.95 1.35 0 0 0
400 DI‐K7 0 1.00 1.40 0 0 0
250 DI‐K9 637 0.85 1.25 68 68 541
600 DI‐K9 2100 1.20 1.60 403 403 3226
800 DI‐K9 4769 1.40 1.80 1202 1202 9614
Total 74267 6724 6724 53793

63 HDPE 49548 0.66 1.06 5238 5238 3492 20952


75 HDPE 4750 0.68 1.08 517 517 345 2068
90 HDPE 1785 0.69 1.09 201 201 134 805
110 HDPE 1496 0.71 1.11 177 177 118 707
140 HDPE 2495 0.74 1.14 316 316 210 1263
160 HDPE 740 0.76 1.16 98 98 65 391
200 HDPE 5162 0.80 1.20 743 743 496 2973
30% Rock ,  
18 200 DI‐K7 Zone‐5‐3 1290 0.80 1.20 186 186 124 743
70% soil 
250 DI‐K7 4775 0.85 1.25 761 761 507 3044
300 DI‐K7 640 0.90 1.30 112 112 75 449
350 DI‐K7 0 0.95 1.35 0 0 0 0
400 DI‐K7 0 1.00 1.40 0 0 0 0
200 DI‐K9 2236 0.80 1.20 322 322 215 1288
250 DI‐K9 12 0.85 1.25 2 2 1 8
1000 DI‐K9 6914 1.60 2.00 3319 3319 2212 13275
Total 81843 11992 11992 7994 47966

Page 9 of 29
Patwadh GOV WSP
Earthwork Excavation Quantity
Exacavation Quantity (cum)
S.No Dia Pipe Type Zone Soil Strata Length (m) Width (m) Depth (m)
Hard Rock Medium Rock Mixed Soil Ordinary Soil
63 HDPE 44823 0.66 1.06 6318 3159 28431
75 HDPE 3174 0.68 1.08 461 230 2073
90 HDPE 2493 0.69 1.09 375 187 1687
110 HDPE 5997 0.71 1.11 945 473 4254
140 HDPE 1890 0.74 1.14 319 159 1435
160 HDPE 2700 0.76 1.16 476 238 2142
200 HDPE 4773 0.80 1.20 916 458 4124
200 DI‐K7 2031 0.80 1.20 390 195 1755
19 Zone‐5B‐1 Soil
250 DI‐K7 1579 0.85 1.25 336 168 1510
300 DI‐K7 259 0.90 1.30 61 30 273
350 DI‐K7 0 0.95 1.35 0 0 0
400 DI‐K7 0 1.00 1.40 0 0 0
250 DI‐K9 2673 0.85 1.25 568 284 2556
350 DI‐K9 147 0.95 1.35 38 19 170
600 DI‐K9 147 1.20 1.60 56 28 254
800 DI‐K9 2907 1.40 1.80 1465 733 6593
Total 75593 12724 6361 57257

63 HDPE 27382 0.66 1.06 3860 2895 12544


75 HDPE 2537 0.68 1.08 368 276 1197
90 HDPE 1971 0.69 1.09 296 222 964
110 HDPE 2648 0.71 1.11 417 313 1356
140 HDPE 3525 0.74 1.14 595 446 1933
160 HDPE 698 0.76 1.16 123 92 400
80% Soil, 
20 200 HDPE Zone‐6 2733 0.80 1.20 525 394 1705
20%  Rock 
200 DI‐K7 0 0.80 1.20 0 0 0
250 DI‐K7 124 0.85 1.25 26 20 86
300 DI‐K7 0 0.90 1.30 0 0 0
350 DI‐K7 0 0.95 1.35 0 0 0
400 DI‐K7 0 1.00 1.40 0 0 0
250 DI‐K9 2736 0.85 1.25 581 436 1890
Total 44354 6791 5094 22075

Page 10 of 29
Patwadh GOV WSP
Earthwork Excavation Quantity
Exacavation Quantity (cum)
S.No Dia Pipe Type Zone Soil Strata Length (m) Width (m) Depth (m)
Hard Rock Medium Rock Mixed Soil Ordinary Soil
63 HDPE 34890 0.66 1.06 2459 6147 15983
75 HDPE 2678 0.68 1.08 194 486 1263
90 HDPE 620 0.69 1.09 47 117 303
110 HDPE 1687 0.71 1.11 133 332 864
140 HDPE 693 0.74 1.14 58 146 380
160 HDPE 90% Soil,  1697 0.76 1.16 150 374 972
21 Zone‐6A
200 HDPE 10%  Rock  2777 0.80 1.20 267 666 1733
200 DI‐K7 2840 0.80 1.20 273 682 1772
250 DI‐K7 0 0 0
300 DI‐K7 846 0.90 1.30 99 247 643
350 DI‐K7 0 0 0
400 DI‐K7 0 0 0
Total 48728 3680 9197 23913

63 HDPE 41120 0.66 1.06 2898 5796 20286


75 HDPE 4570 0.68 1.08 332 663 2321
90 HDPE 2425 0.69 1.09 182 365 1277
110 HDPE 3397 0.71 1.11 268 535 1874
140 HDPE 3639 0.74 1.14 307 614 2149
160 HDPE 3122 0.76 1.16 275 550 1927
90% Soil, 
22 200 HDPE Zone‐6B 2634 0.80 1.20 253 506 1770
10%  Rock 
200 DI‐K7 925 0.80 1.20 89 178 622
250 DI‐K7 462 0.85 1.25 49 98 344
300 DI‐K7 791 0.90 1.30 93 185 648
350 DI‐K7 0 0.95 1.35 0 0 0
400 DI‐K7 0 1.00 1.40 0 0 0
300 DI‐K9 4151 0.90 1.30 486 971 3400
Total 67236 5232 10461 36618

Page 11 of 29
Patwadh GOV WSP
Earthwork Excavation Quantity
Exacavation Quantity (cum)
S.No Dia Pipe Type Zone Soil Strata Length (m) Width (m) Depth (m)
Hard Rock Medium Rock Mixed Soil Ordinary Soil
63 HDPE 47186 0.66 1.06 3326 6651 23279
75 HDPE 3171 0.68 1.08 230 460 1611
90 HDPE 2263 0.69 1.09 170 340 1191
110 HDPE 4056 0.71 1.11 320 639 2238
140 HDPE 3300 0.74 1.14 278 557 1949
160 HDPE 2211 0.76 1.16 195 390 1364
200 HDPE 90% Soil,  691 0.80 1.20 66 133 464
23 Zone‐6A‐1
200 DI‐K7 10%  Rock  1134 0.80 1.20 109 218 762
250 DI‐K7 1384 0.85 1.25 147 294 1029
300 DI‐K7 43 0.90 1.30 5 10 35
350 DI‐K7 0 0.95 1.35 0 0 0
400 DI‐K7 0 1.00 1.40 0 0 0
250 DI‐K9 10 0.85 1.25 1 2 7
400 DI‐K9 6431 1.00 1.40 900 1801 6302
Total 71880 5747 11495 40231

63 HDPE 50747 0.66 1.06 3576 32188


75 HDPE 4305 0.68 1.08 312 2811
90 HDPE 2369 0.69 1.09 178 1604
110 HDPE 1611 0.71 1.11 127 1143
140 HDPE 3211 0.74 1.14 271 2438
160 HDPE 0.76 1.16 0 0
24 200 HDPE Zone‐6A‐2 Soil 835 0.80 1.20 80 721
200 DI‐K7 1928 0.80 1.20 185 1666
250 DI‐K7 2303 0.85 1.25 245 2202
300 DI‐K7 0 0.90 1.30 0 0
350 DI‐K7 0 0.95 1.35 0 0
400 DI‐K7 0 1.00 1.40 0 0
300 DI‐K9 1414 0.90 1.30 165 1489
Total 68723 5139 46262

Page 12 of 29
Patwadh GOV WSP
Earthwork Excavation Quantity
Exacavation Quantity (cum)
S.No Dia Pipe Type Zone Soil Strata Length (m) Width (m) Depth (m)
Hard Rock Medium Rock Mixed Soil Ordinary Soil
63 HDPE 29603 0.66 1.06 6259 14604
75 HDPE 3594 0.68 1.08 782 1826
90 HDPE 4995 0.69 1.09 1127 2630
110 HDPE 4420 0.71 1.11 1045 2438
140 HDPE 2563 0.74 1.14 649 1514
160 HDPE 1138 0.76 1.16 301 702
200 HDPE 2550 0.80 1.20 734 1714
200 DI‐K7 443 0.80 1.20 128 298
25 Zone‐6A‐3 Soil
250 DI‐K7 453 0.85 1.25 144 337
300 DI‐K7 766 0.90 1.30 269 627
350 DI‐K7 355 0.95 1.35 137 319
400 DI‐K7 0 1.00 1.40 0 0
200 DI‐K9 1128 0.80 1.20 325 758
250 DI‐K9 2171 0.85 1.25 692 1615
300 DI‐K9 2219 0.90 1.30 779 1817
400 DI‐K9 1085 1.00 1.40 456 1063
Total 57483 13827 32262

63 HDPE 42198 0.66 1.06 5948 23792


75 HDPE 3026 0.68 1.08 439 1757
90 HDPE 1414 0.69 1.09 213 851
110 HDPE 3391 0.71 1.11 534 2138
140 HDPE 2027 0.74 1.14 342 1368
160 HDPE 5899 0.76 1.16 1040 4160
200 HDPE 498 0.80 1.20 96 382
26 200 DI‐K7 Zone‐6C Soil 4856 0.80 1.20 932 3729
250 DI‐K7 1736 0.85 1.25 369 1476
300 DI‐K7 619 0.90 1.30 145 579
350 DI‐K7 511 0.95 1.35 131 524
400 DI‐K7 0 1.00 1.40 0 0
200 DI‐K9 837 0.80 1.20 161 643
250 DI‐K9 2817 0.85 1.25 599 2394
300 DI‐K9 3535 0.90 1.30 827 3309
Total 73364 11776 47102

Page 13 of 29
Patwadh GOV WSP
Earthwork Excavation Quantity
Exacavation Quantity (cum)
S.No Dia Pipe Type Zone Soil Strata Length (m) Width (m) Depth (m)
Hard Rock Medium Rock Mixed Soil Ordinary Soil

63 HDPE 29604 0.66 1.06 1043 12518 1043 6259


75 HDPE 2181 0.68 1.08 79 950 79 475
90 HDPE 2985 0.69 1.09 112 1347 112 674
110 HDPE 1339 0.71 1.11 53 633 53 317
140 HDPE 1591 0.74 1.14 67 805 67 403
160 HDPE 814 0.76 1.16 36 431 36 215
200 HDPE 1915 0.80 1.20 92 1103 92 552
200 DI‐K7 0 0.80 1.20 0 0 0 0
35% Soil, 
27 250 DI‐K7 Zone‐6C‐1 1003 0.85 1.25 53 639 53 320
65%  Rock 
300 DI‐K7 0 0.90 1.30 0 0 0 0
350 DI‐K7 0 0.95 1.35 0 0 0 0
400 DI‐K7 0 1.00 1.40 0 0 0 0
150 DI‐K9 315 0.75 1.15 14 163 14 82
250 DI‐K9 1571 0.85 1.25 83 1002 83 501
300 DI‐K9 987 0.90 1.30 58 693 58 346
400 DI‐K9 7333 1.00 1.40 513 6160 513 3080
600 DI‐K9 1719 1.20 1.60 165 1980 165 990
Total 53357 2368 28424 2368 14214

63 HDPE 42802 0.66 1.06 3017 6033 21116


75 HDPE 2185 0.68 1.08 159 317 1110
90 HDPE 3820 0.69 1.09 287 575 2011
110 HDPE 1714 0.71 1.11 135 270 946
140 HDPE 3583 0.74 1.14 302 605 2116
160 HDPE 1024 0.76 1.16 90 181 632
200 HDPE 2638 0.80 1.20 253 506 1773
90% Soil, 
28 200 DI‐K7 Zone‐6C‐2 1842 0.80 1.20 177 354 1238
10%  Rock
250 DI‐K7 6161 0.85 1.25 655 1309 4582
300 DI‐K7 23 0.90 1.30 3 5 19
350 DI‐K7 0 0.95 1.35 0 0 0
400 DI‐K7 0 1.00 1.40 0 0 0
200 DI‐K9 1274 0.80 1.20 122 245 856
250 DI‐K9 1338 0.85 1.25 142 284 995
400 DI‐K9 2141 1.00 1.40 300 599 2098
Total 70545 5642 11283 39492

Page 14 of 29
Patwadh GOV WSP
Earthwork Excavation Quantity
Exacavation Quantity (cum)
S.No Dia Pipe Type Zone Soil Strata Length (m) Width (m) Depth (m)
Hard Rock Medium Rock Mixed Soil Ordinary Soil

63 HDPE 22614 0.66 1.06 1594 3188 11156


75 HDPE 2577 0.68 1.08 187 374 1309
90 HDPE 1797 0.69 1.09 135 270 946
110 HDPE 614 0.71 1.11 48 97 339
140 HDPE 2486 0.74 1.14 210 419 1468
160 HDPE 1137 0.76 1.16 100 200 702
200 HDPE 90% Soil,  1229 0.80 1.20 118 236 826
29 Zone‐6C‐3
200 DI‐K7 10% Rock 1962 0.80 1.20 188 377 1318
250 DI‐K7 1860 0.85 1.25 198 395 1383
300 DI‐K7 0 0.90 1.30 0 0 0
350 DI‐K7 0 0.95 1.35 0 0 0
400 DI‐K7 0 1.00 1.40 0 0 0
200 DI‐K9 705 0.80 1.20 68 135 474
600 DI‐K9 2107 1.20 1.60 405 809 2832
Total 39088 3251 6500 22753

63 HDPE 57444 0.66 1.06 2024 38461


75 HDPE 2131 0.68 1.08 77 1469
90 HDPE 1411 0.69 1.09 53 1008
110 HDPE 2091 0.71 1.11 82 1566
140 HDPE 2033 0.74 1.14 86 1629
160 HDPE 2826 0.76 1.16 125 2367
200 HDPE 634 0.80 1.20 30 578
30 Zone‐7B Soil
200 DI‐K7 176 0.80 1.20 8 161
250 DI‐K7 1301 0.85 1.25 69 1313
300 DI‐K7 0 0.90 1.30 0 0
350 DI‐K7 0 0.95 1.35 0 0
400 DI‐K7 0 1.00 1.40 0 0
150 DI‐K9 630 0.75 1.15 27 516
300 DI‐K9 1545 0.90 1.30 90 1717
Total 72222 2671 50785

Page 15 of 29
Patwadh GOV WSP
Earthwork Excavation Quantity
Exacavation Quantity (cum)
S.No Dia Pipe Type Zone Soil Strata Length (m) Width (m) Depth (m)
Hard Rock Medium Rock Mixed Soil Ordinary Soil
63 HDPE 37032 0.66 1.06 5220 20879
75 HDPE 2533 0.68 1.08 368 1470
90 HDPE 3158 0.69 1.09 475 1900
110 HDPE 6122 0.71 1.11 965 3860
140 HDPE 3798 0.74 1.14 641 2563
160 HDPE 186 0.76 1.16 33 131
200 HDPE 4244 0.80 1.20 815 3259
31 Zone‐7A‐1 Soil
200 DI‐K7 0 0
250 DI‐K7 776 0.85 1.25 165 660
300 DI‐K7 0 0.90 1.30 0 0
350 DI‐K7 0 0.95 1.35 0 0
400 DI‐K7 0 1.00 1.40 0 0
200 DI‐K9 1781 0.80 1.20 342 1368
300 DI‐K9 1519 0.90 1.30 355 1422
Total 61149 9379 37512

63 HDPE 18849 0.66 1.06 10627 2657


75 HDPE 3104 0.68 1.08 1802 450
90 HDPE 1367 0.69 1.09 822 206
110 HDPE 1113 0.71 1.11 702 175
140 HDPE 2905 0.74 1.14 1961 490
160 HDPE 2134 0.76 1.16 1505 376
20% Soil, 
32 200 HDPE Zone‐7A‐2 1595 0.80 1.20 1225 306
80% Rock
200 DI‐K7 2086 0.80 1.20 1602 401
250 DI‐K7 2045 0.85 1.25 1738 435
300 DI‐K7 0 0.90 1.30 0 0
350 DI‐K7 0 0.95 1.35 0 0
400 DI‐K7 0 1.00 1.40 0 0
200 DI‐K9 1513 0.80 1.20 1162 290
Total 36711 23146 5786

Page 16 of 29
Patwadh GOV WSP
Earthwork Excavation Quantity
Exacavation Quantity (cum)
S.No Dia Pipe Type Zone Soil Strata Length (m) Width (m) Depth (m)
Hard Rock Medium Rock Mixed Soil Ordinary Soil
63 HDPE 43430 0.66 1.06 3061 6122 21426
75 HDPE 2343 0.68 1.08 170 340 1190
90 HDPE 4364 0.69 1.09 328 656 2298
110 HDPE 5032 0.71 1.11 397 793 2776
140 HDPE 1809 0.74 1.14 153 305 1068
160 HDPE 4947 0.76 1.16 436 872 3053
90% Soil, 
33 200 HDPE Zone‐8 1790 0.80 1.20 172 344 1203
10% Rock
200 DI‐K7 1177 0.80 1.20 113 226 791
250 DI‐K7 2520 0.85 1.25 268 536 1874
300 DI‐K7 307 0.90 1.30 36 72 251
350 DI‐K7 0 0.95 1.35 0 0 0
400 DI‐K7 0 1.00 1.40 0 0 0
250 DI‐K9 3280 0.85 1.25 349 697 2440
Total 70999 5483 10963 38370

63 HDPE 37188 0.66 1.06 5242 20967


75 HDPE 4945 0.68 1.08 718 2871
90 HDPE 5516 0.69 1.09 830 3319
110 HDPE 2982 0.71 1.11 470 1880
140 HDPE 3527 0.74 1.14 595 2380
160 HDPE 3848 0.76 1.16 678 2714
34 200 HDPE Zone‐8B Soil 4097 0.80 1.20 787 3146
200 DI‐K7 0 0
250 DI‐K7 530 0.85 1.25 113 451
300 DI‐K7 490 0.90 1.30 115 459
350 DI‐K7 948 0.95 1.35 243 973
400 DI‐K7 0 1.00 1.40 0 0
250 DI‐K9 3058 0.85 1.25 650 2599
Total 67129 10441 41759

Page 17 of 29
Patwadh GOV WSP
Earthwork Excavation Quantity
Exacavation Quantity (cum)
S.No Dia Pipe Type Zone Soil Strata Length (m) Width (m) Depth (m)
Hard Rock Medium Rock Mixed Soil Ordinary Soil
63 HDPE 38708 0.66 1.06 5456 21824
75 HDPE 3127 0.68 1.08 454 1815
90 HDPE 4007 0.69 1.09 603 2411
110 HDPE 2426 0.71 1.11 382 1530
140 HDPE 1707 0.74 1.14 288 1152
160 HDPE 2077 0.76 1.16 366 1465
200 HDPE 3857 0.80 1.20 741 2962
35 200 DI‐K7 Zone‐8C Soil 611 0.80 1.20 117 469
250 DI‐K7 2877 0.85 1.25 611 2445
300 DI‐K7 1115 0.90 1.30 261 1044
350 DI‐K7 0 0.95 1.35 0 0
400 DI‐K7 0 1.00 1.40 0 0
200 DI‐K9 838 0.80 1.20 161 644
250 DI‐K9 1054 0.85 1.25 224 896
600 DI‐K9 3122 1.20 1.60 1199 4795
Total 65526 10863 43452

63 HDPE 29758 0.66 1.06 2097 2097 16778


75 HDPE 2740 0.68 1.08 199 199 1591
90 HDPE 1720 0.69 1.09 129 129 1035
110 HDPE 1028 0.71 1.11 81 81 648
140 HDPE 3809 0.74 1.14 321 321 2571
160 HDPE 2635 0.76 1.16 232 232 1858
200 HDPE 615 0.80 1.20 59 59 472
200 DI‐K7 808 0.80 1.20 78 78 621
250 DI‐K7 10% Rock ,  3247 0.85 1.25 345 345 2760
36 Zone‐8D
300 DI‐K7 90% Soil 935 0.90 1.30 109 109 875
350 DI‐K7 0 0.95 1.35 0 0 0
400 DI‐K7 0 1.00 1.40 0 0 0
200 DI‐K9 405 0.80 1.20 39 39 311
250 DI‐K9 7607 0.85 1.25 808 808 6466
600 DI‐K9 374 1.20 1.60 72 72 574
800 DI‐K9 790 1.40 1.80 199 199 1593
900 DI‐K9 220 1.50 1.90 63 63 502
1000 DI‐K9 2385 1.60 2.00 763 763 6106
Total 59076 5594 5594 44761

63 HDPE 39472 0.66 1.06 11127 16691


75 HDPE 3341 0.68 1.08 970 1455

Page 18 of 29
Patwadh GOV WSP
Earthwork Excavation Quantity
Exacavation Quantity (cum)
S.No Dia Pipe Type Zone Soil Strata Length (m) Width (m) Depth (m)
Hard Rock Medium Rock Mixed Soil Ordinary Soil
90 HDPE 2776 0.69 1.09 835 1253
110 HDPE 3300 0.71 1.11 1040 1560
140 HDPE 2220 0.74 1.14 749 1124
160 HDPE 3061 0.76 1.16 1079 1619
60% Soil , 
37 200 HDPE Zone‐9 2779 0.80 1.20 1067 1601
40% Rock
200 DI‐K7 566 0.80 1.20 217 326
250 DI‐K7 649 0.85 1.25 276 414
300 DI‐K7 3626 0.90 1.30 1697 2545
350 DI‐K7 0 0.95 1.35 0 0
400 DI‐K7 0 1.00 1.40 0 0
300 DI‐K9 1457 0.90 1.30 682 1023
Total 63247 19739 29611

63 HDPE 36329 0.66 1.06 5121 7681 2560 10241


75 HDPE 2679 0.68 1.08 389 583 194 778
90 HDPE 3542 0.69 1.09 533 799 266 1066
110 HDPE 2261 0.71 1.11 356 535 178 713
140 HDPE 4908 0.74 1.14 828 1242 414 1656
160 HDPE 2305 0.76 1.16 406 610 203 813
200 HDPE 1406 0.80 1.20 270 405 135 540
50% Soil , 
38 200 DI‐K7 Zone‐9‐1 1865 0.80 1.20 358 537 179 716
50% Rock
250 DI‐K7 444 0.85 1.25 94 142 47 189
300 DI‐K7 2150 0.90 1.30 503 755 252 1006
350 DI‐K7 517 0.95 1.35 133 199 66 265
400 DI‐K7 0 1.00 1.40 0 0 0 0
150 DI‐K9 1326 0.75 1.15 229 343 114 457
200 DI‐K9 2709 0.80 1.20 520 780 260 1040
800 DI‐K9 1449 1.40 1.80 730 1095 365 1461
Total 63890 10470 15706 5233 20941

Page 19 of 29
Patwadh GOV WSP
Earthwork Excavation Quantity
Exacavation Quantity (cum)
S.No Dia Pipe Type Zone Soil Strata Length (m) Width (m) Depth (m)
Hard Rock Medium Rock Mixed Soil Ordinary Soil
63 HDPE 26004 0.66 1.06 9163 2749 6414
75 HDPE 1576 0.68 1.08 572 172 400
90 HDPE 3043 0.69 1.09 1144 343 801
110 HDPE 2054 0.71 1.11 809 243 567
140 HDPE 2731 0.74 1.14 1152 346 806
160 HDPE 1343 0.76 1.16 592 178 414
50% Soil , 
39 200 HDPE Zone‐9‐2 0 0 0
50% Rock
200 DI‐K7 645 0.80 1.20 310 93 217
250 DI‐K7 0 0.85 1.25 0 0 0
300 DI‐K7 0 0.90 1.30 0 0 0
350 DI‐K7 0 0.95 1.35 0 0 0
400 DI‐K7 0 1.00 1.40 0 0 0
200 DI‐K9 1470 0.80 1.20 706 212 494
Total 38866 14448 4336 10113

63 HDPE 26734 0.66 1.06 3768 15073


75 HDPE 1678 0.68 1.08 244 974
90 HDPE 1123 0.69 1.09 169 676
110 HDPE 1615 0.71 1.11 255 1018
140 HDPE 5246 0.74 1.14 885 3540
160 HDPE 57 0.76 1.16 10 40
200 HDPE 2657 0.80 1.20 510 2041
40 200 DI‐K7 Zone‐9‐3 Soil 2629 0.80 1.20 505 2019
250 DI‐K7 1008 0.85 1.25 214 857
300 DI‐K7 42 0.90 1.30 10 39
350 DI‐K7 0 0.95 1.35 0 0
400 DI‐K7 0 1.00 1.40 0 0
200 DI‐K9 1365 0.80 1.20 262 1048
250 DI‐K9 2681 0.85 1.25 570 2279
800 DI‐K9 817 1.40 1.80 412 1647
Total 47652 7814 31251

Page 20 of 29
Patwadh GOV WSP
Earthwork Excavation Quantity
Exacavation Quantity (cum)
S.No Dia Pipe Type Zone Soil Strata Length (m) Width (m) Depth (m)
Hard Rock Medium Rock Mixed Soil Ordinary Soil
63 HDPE 29698 0.66 1.06 1047 3140 3140 13605
75 HDPE 2326 0.68 1.08 84 253 253 1097
90 HDPE 2349 0.69 1.09 88 265 265 1148
110 HDPE 2532 0.71 1.11 100 299 299 1297
140 HDPE 2582 0.74 1.14 109 327 327 1416
160 HDPE 2644 0.76 1.16 117 350 350 1515
200 HDPE 1567 0.80 1.20 75 226 226 978
80% Soil , 
41 200 DI‐K7 Zone‐9A 1681 0.80 1.20 81 242 242 1049
20% Rock
250 DI‐K7 1975 0.85 1.25 105 315 315 1364
300 DI‐K7 372 0.90 1.30 22 65 65 283
350 DI‐K7 0 0.95 1.35 0 0 0 0
400 DI‐K7 0 1.00 1.40 0 0 0 0
250 DI‐K9 270 0.85 1.25 14 43 43 186
300 DI‐K9 5502 0.90 1.30 322 966 966 4184
800 DI‐K9 1382 1.40 1.80 174 522 522 2264
Total 54880 2338 7013 7013 30386

63 HDPE 52092 0.66 1.06 3671 33042


75 HDPE 4592 0.68 1.08 333 2999
90 HDPE 3089 0.69 1.09 232 2091
110 HDPE 2791 0.71 1.11 220 1980
140 HDPE 2680 0.74 1.14 226 2035
160 HDPE 1934 0.76 1.16 171 1535
200 HDPE 90% Soil ,  3299 0.80 1.20 317 2850
42 Zone‐9A‐1
200 DI‐K7 10% Rock 3150 0.80 1.20 302 2722
250 DI‐K7 4320 0.85 1.25 459 4131
300 DI‐K7 1370 0.90 1.30 160 1443
350 DI‐K7 1522 0.95 1.35 195 1757
400 DI‐K7 0 1.00 1.40 0 0
200 DI‐K9 257 0.80 1.20 25 222
800 DI‐K9 4661 1.40 1.80 1175 10571
Total 85757 7486 67378

Page 21 of 29
Patwadh GOV WSP
Earthwork Excavation Quantity
Exacavation Quantity (cum)
S.No Dia Pipe Type Zone Soil Strata Length (m) Width (m) Depth (m)
Hard Rock Medium Rock Mixed Soil Ordinary Soil
63 HDPE 35261 0.66 1.06 4970 4970 4970 9940
75 HDPE 1991 0.68 1.08 289 289 289 578
90 HDPE 3030 0.69 1.09 456 456 456 912
110 HDPE 4647 0.71 1.11 732 732 732 1465
140 HDPE 9019 0.74 1.14 1522 1522 1522 3043
160 HDPE 1290 0.76 1.16 227 227 227 455
200 HDPE 1498 0.80 1.20 288 288 288 575
200 DI‐K7 2114 0.80 1.20 406 406 406 812
60% Soil , 
43 250 DI‐K7 Zone‐10 763 0.85 1.25 162 162 162 324
40% Rock
300 DI‐K7 606 0.90 1.30 142 142 142 284
350 DI‐K7 0 0.95 1.35 0 0 0 0
400 DI‐K7 0 1.00 1.40 0 0 0 0
150 DI‐K9 156 0.75 1.15 27 27 27 54
200 DI‐K9 3689 0.80 1.20 708 708 708 1417
300 DI‐K9 1000 0.90 1.30 234 234 234 468
350 DI‐K9 2260 0.95 1.35 580 580 580 1159
600 DI‐K9 2275 1.20 1.60 874 874 874 1747
Total 69599 11617 11617 11617 23233

63 HDPE 28241 0.66 1.06 995 4976 13932


75 HDPE 3892 0.68 1.08 141 706 1977
90 HDPE 1677 0.69 1.09 63 315 883
110 HDPE 2987 0.71 1.11 118 589 1648
140 HDPE 2530 0.74 1.14 107 534 1494
160 HDPE 1055 0.76 1.16 47 233 651
200 HDPE 1800 0.80 1.20 86 432 1210
95% Soil , 5% 
44 200 DI‐K7 Zone‐10A‐1 3328 0.80 1.20 160 799 2236
Rock 
250 DI‐K7 564 0.85 1.25 30 150 419
300 DI‐K7 870 0.90 1.30 51 254 713
350 DI‐K7 0 0.95 1.35 0 0 0
400 DI‐K7 0 1.00 1.40 0 0 0
200 DI‐K9 873 0.80 1.20 42 210 587
250 DI‐K9 2556 0.85 1.25 136 679 1901
300 DI‐K9 5131 0.90 1.30 300 1501 4202
Total 55504 2276 11378 31853

Page 22 of 29
Patwadh GOV WSP
Earthwork Excavation Quantity
Exacavation Quantity (cum)
S.No Dia Pipe Type Zone Soil Strata Length (m) Width (m) Depth (m)
Hard Rock Medium Rock Mixed Soil Ordinary Soil
63 HDPE 40020 0.66 1.06 2820 25384
75 HDPE 3775 0.68 1.08 274 2465
90 HDPE 2102 0.69 1.09 158 1423
110 HDPE 4564 0.71 1.11 360 3237
140 HDPE 5656 0.74 1.14 477 4294
160 HDPE 3010 0.76 1.16 265 2388
45 200 HDPE Zone‐10A‐2 Soil 1466 0.80 1.20 141 1267
200 DI‐K7 1850 0.80 1.20 178 1598
250 DI‐K7 2233 0.85 1.25 237 2135
300 DI‐K7 1418 0.90 1.30 166 1493
350 DI‐K7 0 0.95 1.35 0 0
400 DI‐K7 0 1.00 1.40 0 0
250 DI‐K9 2354 0.85 1.25 250 2251
Total 68448 5326 47935

63 HDPE 33017 0.66 1.06 3490 2327 3490 13962


75 HDPE 4384 0.68 1.08 477 318 477 1909
90 HDPE 4413 0.69 1.09 498 332 498 1991
110 HDPE 1854 0.71 1.11 219 146 219 877
140 HDPE 4772 0.74 1.14 604 403 604 2415
160 HDPE 254 0.76 1.16 34 22 34 134
200 HDPE 75% Soil ,  2003 0.80 1.20 288 192 288 1154
46 Zone‐11
200 DI‐K7 25% Rock 612 0.80 1.20 88 59 88 353
250 DI‐K7 524 0.85 1.25 84 56 84 334
300 DI‐K7 606 0.90 1.30 106 71 106 425
350 DI‐K7 0 0.95 1.35 0 0 0 0
400 DI‐K7 0 1.00 1.40 0 0 0 0
150 DI‐K9 2055 0.75 1.15 266 177 266 1063
350 DI‐K9 2952 0.95 1.35 568 379 568 2272
Total 57446 6722 4482 6722 26889

Page 23 of 29
Patwadh GOV WSP
Earthwork Excavation Quantity
Exacavation Quantity (cum)
S.No Dia Pipe Type Zone Soil Strata Length (m) Width (m) Depth (m)
Hard Rock Medium Rock Mixed Soil Ordinary Soil
63 HDPE 26459 0.66 1.06 1865 16783
75 HDPE 1949 0.68 1.08 141 1273
90 HDPE 1501 0.69 1.09 113 1016
110 HDPE 2290 0.71 1.11 180 1624
140 HDPE 1344 0.74 1.14 113 1020
160 HDPE 36 0.76 1.16 3 29
200 HDPE 1023 0.80 1.20 98 884
47 200 DI‐K7 Zone‐11A Soil 2370 0.80 1.20 228 2048
250 DI‐K7 1752 0.85 1.25 186 1675
300 DI‐K7 0 0.90 1.30 0 0
350 DI‐K7 0 0.95 1.35 0 0
400 DI‐K7 0 1.00 1.40 0 0
150 DI‐K9 26 0.75 1.15 2 20
250 DI‐K9 928 0.85 1.25 99 887
300 DI‐K9 3432 0.90 1.30 402 3614
Total 43110 3430 30873

63 HDPE 28736 0.66 1.06 2025 3038 15189


75 HDPE 2704 0.68 1.08 196 294 1472
90 HDPE 2171 0.69 1.09 163 245 1225
110 HDPE 856 0.71 1.11 67 101 506
140 HDPE 1138 0.74 1.14 96 144 720
160 HDPE 1335 0.76 1.16 118 177 883
200 HDPE 1073 0.80 1.20 103 155 773
90 % soil &   
48 200 DI‐K7 Zone‐11A‐1 254 0.80 1.20 24 37 183
10 % Rock
250 DI‐K7 1254 0.85 1.25 133 200 999
300 DI‐K7 0 0.90 1.30 0 0 0
350 DI‐K7 0 0.95 1.35 0 0 0
400 DI‐K7 0 1.00 1.40 0 0 0
150 DI‐K9 1412 0.75 1.15 122 183 913
350 DI‐K9 434 0.95 1.35 56 83 417
400 DI‐K9 2487 1.00 1.40 348 522 2611
Total 43854 3451 5179 25891

Page 24 of 29
Patwadh GOV WSP
Earthwork Excavation Quantity
Exacavation Quantity (cum)
S.No Dia Pipe Type Zone Soil Strata Length (m) Width (m) Depth (m)
Hard Rock Medium Rock Mixed Soil Ordinary Soil
63 HDPE 31439 0.66 1.06 4431 4431 4431 8863
75 HDPE 4216 0.68 1.08 612 612 612 1224
90 HDPE 4438 0.69 1.09 668 668 668 1335
110 HDPE 1058 0.71 1.11 167 167 167 334
140 HDPE 1826 0.74 1.14 308 308 308 616
160 HDPE 2195 0.76 1.16 387 387 387 774
60% Soil , 
49 200 HDPE Zone‐11B 1438 0.80 1.20 276 276 276 552
40% Rock
200 DI‐K7 1732 0.80 1.20 333 333 333 665
250 DI‐K7 2947 0.85 1.25 626 626 626 1252
300 DI‐K7 1634 0.90 1.30 382 382 382 765
350 DI‐K7 0 0.95 1.35 0 0 0 0
400 DI‐K7 0 1.00 1.40 0 0 0 0
150 DI‐K9 2320 0.75 1.15 400 400 400 800
Total 55243 8590 8590 8590 17180

63 HDPE 22585 0.66 1.06 4775 11142


75 HDPE 1756 0.68 1.08 382 892
90 HDPE 1720 0.69 1.09 388 906
110 HDPE 3320 0.71 1.11 785 1832
140 HDPE 3602 0.74 1.14 912 2127
160 HDPE 2266 0.76 1.16 599 1398
200 HDPE 1125 0.80 1.20 324 756
50 Zone‐12‐1 Soil
200 DI‐K7 840 0.80 1.20 242 564
250 DI‐K7 278 0.85 1.25 89 207
300 DI‐K7 1421 0.90 1.30 499 1164
350 DI‐K7 0 0.95 1.35 0 0
400 DI‐K7 0 1.00 1.40 0 0
150 DI‐K9 3056 0.75 1.15 791 1845
200 DI‐K9 3298 0.80 1.20 950 2216
Total 45267 10736 25049

Page 25 of 29
Patwadh GOV WSP
Earthwork Excavation Quantity
Exacavation Quantity (cum)
S.No Dia Pipe Type Zone Soil Strata Length (m) Width (m) Depth (m)
Hard Rock Medium Rock Mixed Soil Ordinary Soil
63 HDPE 24142 0.66 1.06 1701 15313
75 HDPE 1159 0.68 1.08 84 757
90 HDPE 2825 0.69 1.09 212 1912
110 HDPE 3586 0.71 1.11 283 2544
140 HDPE 2202 0.74 1.14 186 1672
160 HDPE 1251 0.76 1.16 110 993
51 200 HDPE Zone‐12‐2 Soil 1059 0.80 1.20 102 915
200 DI‐K7 530 0.80 1.20 51 458
250 DI‐K7 0 0.85 1.25 0 0
300 DI‐K7 0 0.90 1.30 0 0
350 DI‐K7 0 0.95 1.35 0 0
400 DI‐K7 0 1.00 1.40 0 0
150 DI‐K9 1032 0.75 1.15 89 801
Total 37786 2818 25365

63 HDPE 38269 0.66 1.06 5394 5394 8091 8091


75 HDPE 1990 0.68 1.08 289 289 433 433
90 HDPE 2048 0.69 1.09 308 308 462 462
110 HDPE 1990 0.71 1.11 314 314 470 470
140 HDPE 2094 0.74 1.14 353 353 530 530
160 HDPE 2125 0.76 1.16 375 375 562 562
40% rock, 
52 200 HDPE Zone‐12‐3 1940 0.80 1.20 372 372 559 559
60% Soil 
200 DI‐K7 297 0.80 1.20 57 57 86 86
250 DI‐K7 469 0.85 1.25 100 100 149 149
300 DI‐K7 298 0.90 1.30 70 70 105 105
350 DI‐K7 0 0.95 1.35 0 0 0 0
400 DI‐K7 0 1.00 1.40 0 0 0 0
150 DI‐K9 4038 0.75 1.15 697 697 1045 1045
Total 55558 8329 8329 12492 12492

Page 26 of 29
Patwadh GOV WSP
Earthwork Excavation Quantity
Exacavation Quantity (cum)
S.No Dia Pipe Type Zone Soil Strata Length (m) Width (m) Depth (m)
Hard Rock Medium Rock Mixed Soil Ordinary Soil
50 GI 33346 0.65 1.05 6828 15931
65 GI 13783 0.67 1.07 2928 6833
80 GI 5304 0.68 1.08 1169 2727
100 DI‐K7 6893 0.70 1.10 1592 3715
150 DI‐K7 5409 0.75 1.15 1400 3266
Zone‐1 
53 200 DI‐K7 Soil 5531 0.80 1.20 1593 3717
Belcup
250 DI‐K7 1364 0.85 1.25 435 1014
300 DI‐K7 143 0.90 1.30 50 117
200 DI‐K9 3151 0.80 1.20 907 2117
250 DI‐K9 372 0.85 1.25 119 277
1000 DI‐K9 1485 1.60 2.00 1426 3326
Total 76781 18447 43040

50 GI 24960 0.65 1.05 5111 11925


65 GI 9742 0.67 1.07 2070 4830
80 GI 4180 0.68 1.08 921 2149
100 DI‐K7 6581 0.70 1.10 1520 3547
150 DI‐K7 6210 0.75 1.15 1607 3749
200 DI‐K7 Zone‐2  3097 0.80 1.20 892 2081
54 Soil
250 DI‐K7 Bhbhaech 2414 0.85 1.25 769 1795
300 DI‐K7 70 0.90 1.30 25 57
150 DI‐K9 465 0.75 1.15 120 281
200 DI‐K9 2580 0.80 1.20 743 1734
250 DI‐K9 2571 0.85 1.25 820 1912
350 DI‐K9 548 0.95 1.35 211 492
Total 63418 14809 34552

50 GI 18746 0.65 1.05 3838 8956


65 GI 6544 0.67 1.07 1390 3244
80 GI 324 0.68 1.08 71 167
100 DI‐K7 Zone‐3A  3084 0.70 1.10 712 1662
55 150 DI‐K7 Kurhul /  Soil 2789 0.75 1.15 722 1684
200 DI‐K7 Redia 2541 0.80 1.20 732 1708
250 DI‐K7 0 0.85 1.25 0 0
300 DI‐K7 0 0.90 1.30 0 0
150 DI‐K9 284 0.75 1.15 73 171
Total 34312 7538 17592

Page 27 of 29
Patwadh GOV WSP
Earthwork Excavation Quantity
Exacavation Quantity (cum)
S.No Dia Pipe Type Zone Soil Strata Length (m) Width (m) Depth (m)
Hard Rock Medium Rock Mixed Soil Ordinary Soil

50 GI 22540 0.65 1.05 1538 1538 12307


65 GI 9624 0.67 1.07 682 682 5453
80 GI 3611 0.68 1.08 265 265 2122
100 DI‐K7 5421 0.70 1.10 417 417 3339
150 DI‐K7 Zone‐3B  90% Soil,  1838 0.75 1.15 159 159 1268
56
200 DI‐K7 Salkhan 10% Rock 1403 0.80 1.20 135 135 1078
250 DI‐K7 1086 0.85 1.25 115 115 923
300 DI‐K7 3468 0.90 1.30 406 406 3246
400 DI‐K9 8314 1.00 1.40 1164 1164 9312
1000 DI‐K9 1472 1.60 2.00 471 471 3768
Total 58777 5352 5352 42816

50 GI 18989 0.65 1.05 5184 3888 3888


65 GI 9705 0.67 1.07 2749 2062 2062
80 GI 3803 0.68 1.08 1117 838 838
100 DI‐K7 7267 0.70 1.10 2238 1679 1679
150 DI‐K7 Zone‐4  60% Soil,  1547 0.75 1.15 534 400 400
57
200 DI‐K7 Markundi 40% Rock 2964 0.80 1.20 1138 854 854
250 DI‐K7 1420 0.85 1.25 604 453 453
300 DI‐K7 0 0.90 1.30 0 0 0
150 DI‐K9 2268 0.75 1.15 782 587 587
1000 DI‐K9 3756 1.60 2.00 4808 3606 3606
Total 51719 19154 14367 14367

50 GI 28616 0.65 1.05 3906 3906 11718


65 GI 6945 0.67 1.07 984 984 2951
80 GI 2453 0.68 1.08 360 360 1081
100 DI‐K7 4565 0.70 1.10 703 703 2109
150 DI‐K7 Zone‐5  80% Soil,  2834 0.75 1.15 489 489 1467
58
200 DI‐K7 Rudawali 20% Rock 1479 0.80 1.20 284 284 852
250 DI‐K7 0 0.85 1.25 0 0 0
300 DI‐K7 0 0.90 1.30 0 0 0
150 DI‐K9 1669 0.75 1.15 288 288 864
200 DI‐K9 4138 0.80 1.20 794 794 2383
Total 52699 7808 7808 23425

50 GI 26546 0.65 1.05 10871 3624 1812 1812


65 GI 10647 0.67 1.07 4524 1508 754 754

Page 28 of 29
Patwadh GOV WSP
Earthwork Excavation Quantity
Exacavation Quantity (cum)
S.No Dia Pipe Type Zone Soil Strata Length (m) Width (m) Depth (m)
Hard Rock Medium Rock Mixed Soil Ordinary Soil
80 GI 5691 0.68 1.08 2508 836 418 418
100 DI‐K7 6217 0.70 1.10 2872 957 479 479
150 DI‐K7 2133 0.75 1.15 1104 368 184 184
200 DI‐K7 Zone‐6  80% Rock,  215 0.80 1.20 124 41 21 21
59
250 DI‐K7 Patwadh 20% Soil 834 0.85 1.25 532 177 89 89
300 DI‐K7 0 0.90 1.30 0 0 0 0
150 DI‐K9 1406 0.75 1.15 728 243 121 121
200 DI‐K9 3932 0.80 1.20 2265 755 377 377
400 DI‐K9 7499 1.00 1.40 6299 2100 1050 1050
1000 DI‐K9 6859 1.60 2.00 13169 4390 2195 2195
Total 71979 44996 14999 7500 7500

50 GI 13748 0.65 1.05 1407 1407 6568


65 GI 6250 0.67 1.07 664 664 3098
80 GI 2963 0.68 1.08 326 326 1523
100 DI‐K7 3704 0.70 1.10 428 428 1996
Zone‐6  15% Rock, 
60 150 DI‐K7 4506 0.75 1.15 583 583 2720
Kanach 85% Soil
200 DI‐K7 1313 0.80 1.20 189 189 882
250 DI‐K7 0 0.85 1.25 0 0 0
300 DI‐K7 0 0.90 1.30 0 0 0
150 DI‐K9 4528 0.75 1.15 586 586 2734
Total 37012 4183 4183 19521
Overall Total 159100 315750 432950 1978495

Page 29 of 29
REV.NO.   DESCRIPTTION  D
DATE  CHECKED  APPROVED

REV ‐ 2  01.12.21

PROCESS DESIGN CALCULATION OF JACKWELL


CUM PUMP HOUSE OF PATWADH GOV

N
NCC LIMITED  
EN
NGINEERING DESIGN AND
D TECHNOLOG
GY DEPARTMEENT 

Project  Constructiion  of  Patw


wadh  Grou up  of  Villagges  Water  Supply  Schheme,  Distrrict  – 
Sonbhadraa  (Based  on
n  Surface  W
Water)  and  relevant 
r wo
orks  includin
ng  Commissiioning 
and Operaation & Main ntenance forr 10 Years 
PMC  
Consultants  CEINSYS TECH
H LTD. 

Client  Exxecutive Direector, 
Sttate Water &
& Sanitation Mission 
U.P. Jal Nigam
m Compound d Rana Prataap Marg, Luccknow ‐ 2260
001 

DO
OCUMENT NO.  UP/NCC/W W&E/PATWA ADH/JACKWELL/01  Revv.No.2 Date:03.12..21 
This  Document  is  the  Prroperty  of  NCC 
N Limited  and  must  not  n be  Prepared By 
passed on to any person or body not authorized by us to recceive it  Revviewed By 
nor  be  copied  or  otherw
wise  made  use  either  in  full  or  in  part 
p by  App proved By 
su
uch person o or body withhout our prio or permissioon in writing.. 

PATWADH GOV
Hydraulic Design of Intake well & Jack well Structure for Patwadh MVS
Sr. No. Particulars Value Unit
Hydraulic Data
I Population 1211660
Daily Raw Water Demand (MLD)-(55/0.85)*1.10 = 71.18 LPCD) in
II 86.25 MLD
24 Hrs
III Hours of Pumping (Hrs.) 16.00 hrs
IV Design Flow ( Maximum Daily Demand) 129.00 mld
V Highest Flood Level (Elevation) in msl 175.60 m
VI Minimum Water Level (Elevation) in msl 164.50 m
VII Bottom (bed) Level (Elevation) in msl 162.00 m
VIII GL of Jack well 170.00 m
IX GL of Intake well 162.00 m
Design Calculations
1 Size of Intake Port Pipe
Maximum Permissible Velocity through Port is 0.60 m/s
3
Maximum Flow Discharge Q 1.49 m / sec
Nos. of Port 5.00 nos
Maximum Flow Discharge of each Port 0.30 m3 / sec
Required Area of each Port 0.50 m2
Diameter of Circular Port 0.80 m
Provide Diameter of circular port 1.0 m
Actual Velocity Through Port 0.38 m/s
Velocity for 1.5 DISCHARGE 0.57 m/s
Okay
2 Design of Strainer
Length beyound Port Pipeline outside well 1.00 m
Diameter of pipe 1.00 m
Diameter of Stainer Panel 1.10
Surface Area of Stainer Panel 4.40 m2
Width of sqare edge bar 6.00 mm
Clear Opening of bar 15.00 mm
Clear Area of one opning 225.00 mm2
Effective arae of one opning 441.00 mm2
No. of Opening 9987 nos
Net Open Area in the Screen 2.25 m2
Velocith through Screen 0.13 m/s
Velocity is less than 0.30 m/s & Hence it is O.K.
Actal Velocity through strainer for TWICE THE VOLUME 0.27 m/s
Okay
3 Head Loss Calculations

Head Loss through Coarse Screen


2 2
hL = (v – vv )/(2g*0.7) 0.0013 m
Where 'v' is the velocity through the screen &

‘ vv’ is the velocity upstream of the screen (0 in most of the cases)

Head Loss through Intake Port


2
hL = (v/Cd) / 2g 0.0205 m

Where Cd is the coefficient of discharge of orifice (usually 0.6)

Head Loss in pipe


Q = 1.292 x 10-5 x CD2.63S0.54

1
Sr. No. Particulars Value Unit
Q 1075.00 m3 / hr
C 120
D 1000.00 mm
S 0.00016 m/m
Let Length of pipe 1.50 m
Total Loss 0.0002 m
Total Head Loss 0.0220 m
Negligible
4 Layout of Port
Port for Minimum Water Level
Port Top Elevation 163.80 m
Port Bottom Elevation 163.00 m
PortCenter Line Elevation 163.40 m
5 Design of Connecting Pipe from Intake to Jack Well
Maximum Flow Discharge 1.49 m3 / sec
Number of Pipe 2.00 nos
Flow through Each Pipe 0.747 m3 / sec
Permissible Velocity 0.60 m/s
Diameter of Pipe required 1.26 m
Provide Diameter 1.60 m
Actual Velocity 0.37 m/s
Velocity for 1.5 Discharge 0.56 m/s
Okay
Head Loss
Q = 1.292 x 10-5 x CD2.63S0.54
Q 2687.50 m3 / hr
C 120.00
D 1600.00 mm
S 0.00009 m/m
Length of Pipe 85.00 m
Head Loss 0.01 m
Negligible
Pipe Invert level 162.00 m
Min ht of submerged Pump / Bowl of Pump 1.50 m
Water depth above Pump 1.50 m
Bottom invert level 159.00 m
6 Scour Depth Calculation
Flood Discharge by HFL method
Flood Discharge Q = AV 42517.00 m3 / sec
Span of the River at HFL 1000 m
Flood discharge per meter width 'q' 42.52 m3 / sec / m
Silt factor for course sand 'f' (average) 1.00
Scour depth d = 1.34 (q2 / f)1/3 16.32 m
Scouring Effect = 2.0 d 34.65 m
Scour Level (as per scour depth) 141.0 m

At Jack Well location hard rock has encountered at 6 m below at GL ie. at level 164 m , hence
scour depth will not govern the foundation of Jack well. The foundation level will approximately
at 158 m level. Final level will be fixed in structural design of the well. At Intake well location Soil
exploration is yet to be done but looking the proximity to the Jack Well location , the foundation
level is also taken as 158 m but it is subject to verification of strata after soil exploration is done.
Foundation level of well (as per invert level) 158.00 m
Provide Foundation Level 158.0 m

2
 Jackwell Diameter Calculation
Natural Ground Level(NGL) of Intake / Jack well = 170.00 m
High Flood Level = 175.60 m
Plinth Level of Jack Well considering 1.50 m above HFL  = 177.10 m
Ultimate demand for year 2053 considering 16 hours 
= 129.30 MLD
pumping
Discharge for 16 hours operation = 89.79 m3/min
Minimum storage in Intake / Jack Well between LWL and 
suction level of pump for Minimum of 5 min of Pumping  = 449.00 m3 89.79*5
rate
Assuming Suction depth by keeping 5 min of Detention 
= 5.50 m
time (H)
Low water Level = 164.50 m
Calculated Suction Level = 159.00 m
Level with Provision of silt accumulation in the Jack well 
= 160.00 m
(Considering 1m silt accumulation depth)
Water depth below LWL = 4.50 m
Minimum 
submergence depth 
Minimum submergence for pump (bowl assembly)
= 2.90 m 1.8 m As per 
(LWL ‐ Pipe dia ‐ Level after Silt Accumulation)
CPHEEO table 11.5, 
Hence OK
Bottom Floor level of Intake / Jack Well = 159.00 m
Total Depth of Intake / Jack well from Plinth Level = 18.10 m
Total Depth of Intake / Jack well below NGL = 11.00 m
Available water Depth after all provision below LWL = 2.90 m
Area of Intake / Jack well = 154.83 m2 For 5 min detention
Diameter = 14.00 m
Say,  = 14.00 m

Note: Also as per attached GAD minimum required dia to Accommodate 6 nos Pumps, Panels, Pipe of required 
dia and Movement space minimum required dia for Jack Well is 14 M. Also same is covered in our BOQ.

3
RI
VE
R
FL
OW

X = 707623.959
Y = 2713210.226

30
.0m
17

17
0
17 0.

.7
72

4
0. 8

3
17 75
17
171 0.
76 2
0. 1
74

170
2 17 17

17
17
17
17 17

.5
0.
0.
0. 0.
0. 0.

9
.8
80

66
9
81 69
17 179115 6

7
58
6
1 3
0.
48
8
17 17
0. 0.
23 1573
06.5

170
17 3 17 17 17 17 17 17 17 17
0. 0. 0. 0. 1. 1. 0. 0. 0.
9

X = 707646.164
20 41 59 88 11 03 73 44

16
3 1 8 8 5 2 43 9 1

Y = 2713127.221
9.
97
17

8
0
17

16
0.

9.
26

169
72
84

.5
.65
16 16 16 17 16 17 17 17 17 17 17 17 17

16
5. 16 9. 9. 0. 9. 0. 0. 1. 1. 1. 0. 0. 0.
79 68 89 10 82 50 86 26 23 08 80 48 18

5.5
5 9. 9 6 4 6 7 2 8 4 3 8
46

00
8

0
16

17
0
9.

16
98

9.
5

21

169
4

16
1
1
1

16 16 16 17 17 17 17

16
16
16
6
17
17
7
17
17
6

6.0
16

5.
6.
9.
9.
0.
1.
1.
0.
0.
9.

9. 9. 9. 0. 0. 1. 0.
8.

00
38 59 97 09 83 19 22

38
07
17
79
51
24
43
86
54
93

2 2 6 4 1

0
95

8
5
4
8
2
4
6
7
4
6

16
3. 9 171.5
16
48 9.
16 70
3 16 8. 9

168

16
6. 70
4

6
44

.5
5

.50
16 16 16 16 16 16 16 16 16 16 16 16 17 17 17 17 17 17 17 17 17 17 16 16

00
5. 5. 6. 6. 7. 8. 8. 8. 9. 9. 9. 9. 0. 0. 0. 1. 1. 1. 1. 0. 0. 0. 9. 9. 16
23 57 0 76 15 44 66 86 07 35 74 17 98 31 31 71 06 40 55 3 89 60 28 96 68 9.15
2 9 73 6 6 9 7 5 3 3 0 3 6 6 1 3 4 9 25 9 8 5 1 4 69

55
.4
16 34

.0m
8

16

16
16 .1

176.80

5.0
94

0
8.

00

16
09
16 16 16 16 16 16 2 16 16 16 16 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 16 16

4.5
8

0
5. 6. 6. 6. 7. 7. 8. 9. 9. 0. 0. 0. 0. 0. 0. 0. 1. 1. 1. 1. 1. 0. 0. 0. 9. 9.
16 28 32 65 9 41 86 .3
6 83 40 79 15 27 23 54 6 76 97 27 51 68 3 02 59 32 02 70 43
4 2 3 83 6 5 1 5 5 7 5 7 4 6 5 1 91 9 4 4 2 2

0 168
3. 170
59 16

16
2 9.

7.5
26
16 1

001
3.

7
27
8 16 16 16 16 16 17 17 17 17 17 17 16
10

16
16
16
16
16
16
16
17
17
16
17
17
17
17
17
17
17
16
16

7
9
0
9

3.
4.
6.
7.
8.
0.
0.
9.
0.
1.
1.
1.
1.
0.
9.

5. 7. 8. .4 9. 0. 0. 0. 1. 1. 0. 9.

.9
.7
.0
.7

83 80 76 5 99 21 82 98 44 53 28 53
1.1

82
75
64
54
07
43
24
96
45
30
56
82
20
68
32

.7 88.12.46
1 7 0 9 5 6 4 2 2
3

8
9
9
2
78
2
21
5
2
9
4
2
5
9
7
1
24
63
4

07 34486.0
06 1166 168.5
00
0

54.
16 16 16 16 16 16 16 16 16 16 16 17 17 17 17 17 16 17 17 17 17 17 17 17 17 17 17 17 16 16 16 16

16
9

92
17

5. 6. 7. 7. 7. 8. 8. 8. 8. 9. 0. 0. 0. 0. 0. 9. 0. 0. 1. 1. 1. 1. 1. 1. 1. 0. 0. 9. 9. 9. 9.
6 .4 7
2

85 67 27 45 73 10 37 90 35 10 39 47 26 09 99 38 65 17 52 61 74 97 27 73 27 98 76 64 46

8.5
2 5 0 4 8 2 9 26 3 9 87 5 8 3 1 6 3 6 5 4 6 5 8 45 4 2 8 6 2 2 6

00
16

0
9.
35

169
1

6
116 9
171
16 16 16 16 16 16 16 16 16 16 17 17 16 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 16 16 16 16 16
0

9
8. .00
6. 7. 8. 8. 8. 8. 8. 9. 9. 9. 0. 9. 0. 0. 0. 0. 0. 0. 1. 1. 1. 1. 1. 1. 1. 1. 0. 0. 9. 9. 9. 9. 9.
88 53 19 16 20 50 68 08 3 53 09 .5 9391 85 49 29 08 25 66 04 32 84 172 91 87 71 47 17 65 18 93 71 60 52 37

96 00
3 7 2 9 6 8 9 3 04 9 1 27 24 6 6 8 6 3 1 9 1 7 4 6 8 8 7 7 4 4 2 9 3
172

16

169.5
9.5
17

1
1
1
1
1
1

16 16 16 17

00
17 17 17 17 17 17 17 16 16 16

6
16
16
16
6
17
17
17
17
17
17
17
17
7
17
17
6
16

1.0

69
6M

8.
9.
9.
9.
9.
0.
0.
0.
0.
0.
1.
1.
1.
1.
0.
0.
9.
9.

9. 9. 9. 0. 00 1. 0. 1. 1. 1. 1. 0. 9. 9. 9.

671097
x

.9
7

05 10 64 73 0 00 16 04 53 76 33 17 63 59 41

40
36
06
28
45
20
83
72
21
65
83
70
54
98
57
85
52

(G 7M x
4 2 0 4 5 4 5 5 1 5

0
7
8
8
9
33
5
5
8
5
3
5
7
1
5
6
8
7

.91.0
DG I RO 4.5M
S OF 16

0459 00
125 ET S )

0
0 K ED 9.
VA

7
87
AM
F 1

0.0
10M
(R x 7M

00
EL

0
EC CC R x 4.5
O M
17

170
TR PC
16 17 17 16 17 16 17 17 ICA OF) C
17 17 17 17 17 170 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 16 16 16 16 16
9. 0. 0. 9. 0. 9. 0. 0. LR
OO 0. 0. 0. 1 0. 0..23 0. 0. 0. 0. 1. 1. 1. 1. 1. 1. 1. 1. 0. 0. 0. 9. 9. 9. 9. 9.
91 54 26 96 00 95 22 41 M 5 81 91 .0 98 83191 49 33 43 74 31 55 59 52 46 39 34 1 79 43 04 77 69 59 52 43
7 7 6 7 7 6 8 0 91 5 7 04 4 18 5 1 4 1 2 9 1 7 8 8 6 89 3 5 2 7 9 9

17
0.5
00
En

0
tran
17 e c
16

26
17 17 17 17 17 17 17 17 17 17 17 17 17 0. 17 17 17 17 17 17 17 17 17 17 17 17 17 17 16 16 16 16 16 16 169.3
78
1. 1. 1. 0. 0. 0. 0. 1. 1. 1. 0 0. 0. 45 0. 0. 0. 1. 1. 1. 1. 1. 1. 1. 1. 1. 0. 0. 9. 9. 9. 9. 9. 9. 9. 01
0 .8 6 0 7

170.5
43 46 16 86 91 99 99 17 14 78 6712 42 49 03 40 44 42 30 15 09 03 69 25 95 83 64 55 44 30

171.1
4 4 5 7 1 7 7 9 53 7 97 1 78 2 4 1 6 2 8 9 9 6 12 3 8 4 5 5 6
11/
0 17
(12 .433
50 K 0.
KV V ST
A) R 57
FO UCT
UR UR
4

1
1
1
1
1

PO E
17 17 17 17 17 17 17 17 17 17 17 16 16 16

7
17
17
17
7
17
17
17
7
17
17
17
7
17
17
17
17
6
6
16
16

LE

2.
2.
1.
1.
1.
1.
1.
1.
0.
0.
1.
1.
1.
1.
0.
0.
9.
9.
9.
9.

2. 1. 1. 1. 0. 0. 1. 1. 0. 0. 0. 9. 9. 9.

1 1
36 81 75 18 17 52 78 25 02 82 73 68 94 63 34

63
06
76
90
76
59
41
05
57
63
24
27
22
20
58
05
83
74
59
45

3 5 3 4 6 6 3 5 9 7 7

6
5
6
4
7
1
0
0
5
4
3
7
9
5
8
5
3
9
3
3

1.0

0. 70.
00
0

79 86
8 7
60.

X = 707695.388
0M

Y = 2713151.567

17
1.
17

21
17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 16 16 16 16 16 16 16 16

0
173.3 3. 2. 2. 2. 2. 2. 2. 1. 1. 1.
1.5 0. 0. 0. 1. 1. 1. 1. 1. 1. 0. 0. 0. 0. 0. 9. 9. 9. 9. 9. 9. 9. 9
3.65 26 96 66 71 80 57 24 8 49 00
31 80 71 77 08 10 08 06 03 01 94 74 53 3 20 92 90 82 71 66 57 52 .3
6
400 2 4 5 9 8 8 4 93 5
0
4 2 5 4 5 8 4 7 3 7 2 7 67 1 1 9 7 3 2 2 3 3
0 17
1.
55
3

171
17
2.0 17
17 17 17 17 17 17 17 17 17 0
00 1. 17 17 17 17 17 17 17 17 17 17 17 17 16 16 16 16 16 16 16 16 16
3. 3. 3. 3. 3. 3. 2. 2. 1. 89 1. 0. 0. 0. 0. 0. 0. 0. 0. 0. 0. 0. 9. 9. 9. 9. 9. 9. 9. 9. 9.
63 17 66 62 56
173 44 20 86 60 9 6 10 91 94 91 89 86 84 82 79 66 45 2 76 75 77 76 70 59 57 51 45 16
2 3.50 0 6 .50 0 1 8 0 0 83 2 8 6 2 8 4 6 5 9 54 5 4 4 5 8 9 5 9 9.
00
00
17 28
17
2. 1. 8
2.5
17 239
18
8
0
00 171
6

1
1

17 17 117 17 17 17 16 16 16 16

17
17
17
17
17
17
17
16
16
16
16
16
16

3
72
2
0
9
69
9

3.
3.
.
0.
0.
9.
9.
9.
.
9.

3. 3. 722. 0. 0. 0. 9. 9. 9. 9.

.4
.7
.3
.5
5

61 38 .552 67 60 58 97 60 56 43

62
61
99
65
62
61
61
51
48

7 2 5 4 1 8 5 5
11 .3 1

91
7
5
5
29
1
8
82
93
88
5
4
2
6
93

833
96.9. 3769.
2930 32

17
2

17
0.

2
65

.6
17
8

22
0.
56 170 17 16
17 17 17 17 17 117 6 .5 0 17 17 16 16 16 16 16 16 16 16 16 16
.4 9 9.
170.652

3. 3. 3. 3. 3. 722. 0. 9. 9. 9. 9. 9. 9. 9. 9. 9.
48 55 58 50 10 .662 74 170.3 30 8 52 42 44 46 45 47 47 43 .3
6
27
3 8 6 9 1 271 17 0. 87 4 29 7 1 1 2 2 5 3 9 8 8
2. 38 17
53 1 0.
17 1 28
2.
62 6
0 17
17 17 17 17 0. 16 16 16 16 16 16 16 16 16
9

17
3. 3. 3. 2. 16 9. 9. 9. 9. 9. 9. 9. 9. .3
5

2.
20 26 12 68 80 42 21 17 24 29 41 40 4
5 0 6 3 8 7 9 9 7 4 8 9

61
9
17
X = 707711.442

17 0.
Y = 2713260.952

04
170.13

2. 4 17 16
61 0 9.
8 22
1 9
16
1

16 16

17
16
16
16

9.

1772

3
69

9
9.
9.
.
9.

9. 9.

.0
2..73 50 08
24
15
03
21
36

618 1 169 3

34
4
9
2
8

7 16
34.

17 17 9.
80
31

2.
61
3.
06 3
6 2
16

16 16 16 16
9.

9. 9. 8. 9.
68
16

25 02 94 31
2

1 6 6 5
9.
27
1

16
9.
56
1 16
169.57

9.5
16 16
9. 9.
44 14
9
16
H

9.
31
T

9
LI
N
E
C
R
O
SS
169.3

X = 707742.341
Y = 2713246.045

RIV
ER
FL
OW

SO
X = 707623.959
Y = 2713210.226

30.

NR
0m

VE I
17 17
R
17 0. 0.
74 72
0. 3 8
75
17

171 2
0.

17
76

0.
1

17 17 17 81
170
17 17
17
17

0. 0. 0. 1
.5
0. 0.
0.
0.

17 171 89 80 69
74 66
91
95

6 6 3
2 7
5
8

0.
48
8
17
17

0.
0.

23 17
0.5
53

17 3 17 17 17 17
6

170
17
17
17
17

0. 0. 1. 0. 0.
0.
0.
1.
0.

16 20 41 03 94 73
X = 707646.164
59
88
11
44

9. 3 1 2 3 9
Y = 2713127.221
8
8
5
1

97
17

8
0

16
17
0.

9.
72
26

84
169

.65
16 16 3 16 17 16 17 17 17 17 17 17 17 17
.5

5. 16 9. 9. 0. 9. 0. 0. 1. 1. 1. 0. 0. 0.
16

79 9. 68 89 10 82 50 86 26 23 08 80 48 18
5.5

5 46 9 6 4 6 7 2 8 4 3 8
00

8
0

17
16

16 0
9.

9.
98

21
5

169

4
16

16 16 16 16 16 16 16 17 17 17 17 17 17 17 17 17 16
5. 6. 16 9. 9. 9. 9. 9. 0. 0. 0. 1. 1. 1. 0. 0. 0. 9.
6.0

38 07 8. 17 38 59 79 97 09 51 83 24 43 19 86 54 22 93
00

8 5 95 4 2 8 2 2 6 4 6 4 7 4 1 6
0

16 9 16
3. 171.5 9.
48 16 70
3 8. 9
70
168

4
.5

16166.5
5

16 16 16 16 16 16 16 16 16 16 16 17 17 17 17 17 17 17 17 17 17 16 16
RI
6. 00
16

5. 5. 6. 6. 7. 8. 8. 9. 9. 9. 9. 0. 0. 0. 1. 1. 1. 1. 0. 0. 0. 9. 9. 16
44 0
8.

23 57 07 76 15 66 86 07 35 74 17 98 31 31 71 06 40 55 32 89 60 28 96 68 9.5
16
3 6
44

2 9 6 7 5 3 3 0 3 6 6 1 3 4 9 5 9 8 5 1 4
9

9.
55

16 43
4
.0m

8.
16
16

16 19
VE
168

5.0
7.0

8. 4
0

09
00

16

16 16 2 16 16 17 17 17 17 17 17 17 17 16 16
16
16
16
16
16
16
17
17
17
17
17
17
17

4.5

6. 7. 9. 9. 0. 0. 0. 0. 1. 1. 1. 0. 9. 9.
0
5.
6.
6.
7.
8.
8.
0.
0.
0.
1.
1.
0.
0.

16 98 41 40 79 15 6 76 97 68 39 02 59 70 43
R
28
32
65
86
36
83
27
23
54
27
51
32
02

3. 3 6 5 5 7 6 1 1 9 2 2
0 168

4
2
3
5
1
5
7
4
5
4
4

59 170 16
16

2 9.
26
7.5

16 16 1
00

3.
0

27 7.
70
16 8 16 16 16 16 16 7 16 17 17 17 17 17 17 17 17 16 16 16
10

16
16
16
16
16
16
17
17
17
17
17
17
17

3. 4. 5. 7. 8. 8. 9. 0. 0. 0. 0. 0. 1. 1. 1. 9. 9. 9.
6.
7.
7.
8.
9.
9.
0.
1.
1.
1.
0.
0.
0.

82 75 83 97 07 44 99 43 24 21 82 98 82 53 20 76 53 32
1.1

64
54
80
76
23
72
96
45
30
44
56
68
28
02

8.16

8 9 1 8 2 9 5 2 5 9 4 7 3 2 4
3

9
2
7
0
1
9
4
2
6
5
1
2
4

6
FL
45 8.0
16 168.5
4 00
0

16

16 16 16 16 16 17 17 17 17 17 17 17 17 16 16 16
3.
16
16
16
16
16
16
17
17
16
17
17
17
17
17
17
16

6. 7. 7. 8. 8.
16

0. 0. 0. 0. 1. 1. 1. 1. 9. 9. 9.
82
92
17

5.
7.
8.
8.
9.
54. 9.
0.
0.
9.
0.
1.
1.
1.
0.
0.
9.

67 27 45 62 90 39 47 26 65 17 97 74 27 76 64 46
2

8.5

85
73
10
37
35
48
10
09
99
38
52
61
74
73
27
98

5 0 4 6 3 8 3 1 5 8 5 4 2 2 6
2
8
2
9
9
5
6
3
6
4
6
5
2
8
6

16
OW
16
00

3.
0

74 9.
35
0 1
7 169

16 16
8.
16

16 16 16 16 16 16 16 16 16 16 16 16 16 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 16 16 16 16 16
171

16 3.84 16 96
9.0

16 4. 4. 7 5. 6. 6. 7. 8. 8. 8. 8. 8. 9. 9. 9. 0. 0. 9. 9 0. 0. 0. 0. 0. 0. 1. 1. 1. 1. 1. 1. 1. 1. 0. 0. 9. 9. 9. 9. 9.
3. 63 93 50 17 88 53 19 16 20 50 68 08 30 53 09 52 31
99 85 49 29 08 25 66 04 32 84 91 87 71 47 17 65 18 93 71 60 52 37
00

172
0

83 6 9 4 3 3 7 2 9 6 8 9 3 4 9 1 7 24 6 6 8 6 3 1 9 1 7 4 6 8 8 7 7 4 4 2 9 3
7 172
16

169.5

17
9.5

16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 17 17 17 1.0 17
16 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 16 16 16 16 16
00

4. 4. 5. 6. 7. 8. 8. 9. 9. 9. 9. 9. 9. 9. 9. 0. 0. 0. 0.
9. 1. 0. 0. 0. 0. 1. 1. 1. 1. 1. 1. 1. 1. 0. 0. 0. 9. 9. 9. 9. 9.
0

00
16
17

34 92 53 24 06 24 40 05 36 06 10 28 45 64 93 20 73 83
0 94
90 00 72 21 16 65 04 53 7 83 76 70 54 33 98 57 17 85 63 59 52 41
3. 6 3 5 3 3 3 0 4 7 8 2 8 9 0 3 5 4 5 59 5 8 5 4 3 5 5 7 1 5 5 6 1 8 5 7
67
6
16
0
17

1.0 9.87
00 1
0.0

16
00

3. 17
0

1669 16 16 16 16 16 17 16 17 17 17 170. 17 17 17 17 17 17 17 16 16 16
6.5
16
16
17
16
17
16
17
17
17
17
17
17
17
17
17
17
17
17
16
16

3.3 4. 00 6. 7. 8. 0. 9. 0. 0. 0. 0.23 0. 0. 1. 1. 1. 1. 0. 9. 9. 9.
5.
6.
0.
9.
0.
9.
0.
0.
0.
1.
170170.
0.
0.
1.
1.
1.
1.
0.
0.
9.
9.

85 24 0 78 62 93 26 96 00 59 81 81
391 49 33 55 59 34 18 79 69 59 52
31
28
09
91
54
95
22
41
91
00
98
43
74
31
52
46
39
43
04
77
43
w

8 1 6 8 3 6 7 7 1 5 18 5 1 9 1 6 9 3 7 9
0
0
6
7
7
6
8
0
7
4
4
4
1
2
7
8
8
5
2
9

166
.500
17

0
0.5
00

Entra
nce
16
0 17

9.
0.

16 16 16 16 16 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 16 16 16 30
16
16
17
17
17
17
17
17
17
17
17
17
17
17
17
17
16
16
16
16

78

4. 4. 6. 8. 9. 0. 1. 0. 0. 1. 1. 0. 0. 0. 0. 1. 1. 1. 1. 0. 0. 9. 9. 9.
6.
7.
1.
1.
1.
0.
0.
1.
1.
0.
0.
1.
1.
1.
1.
1.
9.
9.
9.
9.

54

09 86 52 36 18 66 16 86 91 05 14 72
61 42 49 6 44 42 03 01 69 25 7 64 55 1
170.5

98
87
80
43
46
99
99
17
12
89
78
03
40
30
15
09
95
83
44
30

16

7 4 1 8 2 7 5 7 1 3 7 78 2 4 6 2 6 2 4 5
3
2
1
4
4
7
7
9
6
7
1
1
8
9
9
3
8
5
6

3.

166.
0000
80

17
2

0.
57
4
RI
16 16 16 16 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 16 16 16
16
16
16
16
17
17
17
17
17
17
17
17
17
17
17
17
17
17
17
17
16
16
16
16

5. 6. 7. 9. 0. 1. 2. 1. 1. 1. 1. 0. 0. 0. 1. 1. 0. 0. 0. 9. 9. 9.
4.
5.
8.
9.
2.
2.
2.
1.
1.
1.
1.
1.
0.
0.
1.
1.
1.
1.
0.
0.
9.
9.
9.
9.

82 71 37 84 55 75 06 76 81 59 41 17 17 52 57 63 25 22 73 68 58 74 63 59
61
16
21
19
58
63
36
90
76
75
18
05
79
78
24
27
20
02
82
05
94
83
45
34

1.0
7 5 9 6 0 0 173.00 5 6 5 1 0 0. 6 5 4 3 9 9 8 9 3
5
5
8
9
2
6
3
4
7
3
4
0
8
6
3
7
5
5
5
7
3
3
7

00
00 60. 0 86
7
VE
16 0M
X = 707695.388

3.
Y = 2713151.567

75 17
8
16

1.
6.

16 16 16 16 16 16 16 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 21 17 17 17 17 17 17 17 17 17 17 17 17 17 17 16 16 16 16 16 16 16 16
R
1616 17
0 0.
50

3. 4.60 5. 6. 6. 6. 7. 8. 9. 0. 1. 1. 2. 3. 3. 2. 2. 2. 2. 2. 2. 1. 1. 1. 1.5
80 0. 0. 1. 1. 1. 1. 1. 1. 0. 0. 0. 0. 0. 9. 9. 9. 9. 9. 9. 9. 9.
77 00 03 38 77 79 52 39 34 28 83 61 14 173.36 26 96 66 71 80 57 24 89 49 31 71 77 08 10 08 06 03 01 94 74 53 36 20 92 90 82 71 66 57 52 36
00

00
166 3.5 0 2
13
.000
1 5 6 5 4 4 0 9 7 8 4 7 400 2 4 5 9 8 8 4 3 5 17 4 5 4 5 8 4 7 3 7 2 7 7 1 1 9 7 3 2 2 3 3
0 0
1.
55
3
171

16 2.0
17
17
3. 16 16 16 16 16 16 16 16 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 00 1. 17 17 17 17 17 17 17 17 17 17 17 17 16 16 16 16 16 16 16 16 16
77 4. 6. 6. 7. 7. 8. 9. 9. 0. 1. 1. 2. 3. 3. 3. 3. 3. 3. 3. 3. 2. 2. 1.
0 89 1. 0. 0. 0. 0. 0. 0. 0. 0. 0. 0. 0. 9. 9. 9. 9. 9. 9. 9. 9. 9.
FL
7 50 09 78 33 96 65 43 69 34 08 87 71 06 33 63 173 66 62 56
173 44 20 86 60 98 6 10 91 94 91 89 86 84 82 79 66 45 25 76 75 77 76 70 59 57 51 45
1 8 5 6 3 8 0 2 17 6 0 1 3 2 8 8 4 9 4 5 8 9 5 16
3 1 2 2 4 7 2 .50 0 .50 8 0 0 6 2 6 5 4 4 5 9 9.
3. 00
00
17 28
50 17
16 00 2. 1. 8
23 18
3.
17
89
2.5
9 8
1 0
00 171
16 16 16 16 16 16 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 16 16 16 16 16 16 16 16 16 16 16
16 16
5. 6. 7. 7. 8. 9. 0. 0. 0. 1. 1. 2. 3. 3. 3. 3. 3. 3. 3. 3. 2. 2. 2. 0. 0. 0. 0. 0. 0. 9. 9. 9. 9. 9. 9. 9. 9. 9. 9. 9.
9. 9.
16
17

29
OW
91 51 13 99 50 43 05 40 77 15 72 37 09 34 43 49 61 62 61 38 99 72 52 67 65 62 60 58 38 97 59 58 60 61 61 56 51 48 43 33 30
3.
2.

4 6 1 7 6 8 9 8 0 3 7 1 8 1 6 1 7 7 5 2 5 9 3 5 1 8 4 2 1 3 8 8 5 4 5 2 6 5 7 39
76
58

3
16

3
9.

16

17
32
2

7.5

0.
17

65
2.

17
00

16
8
62

7.5
0.
2

00 56 170 17 16
16 0 16 16 17 17 17 17 17 17 17 17 17 17 6 .5 0. 17 16 16 16 16 16
16
16
16
16
17
17
17
17
17
17
17
17
16
16
16
16
16

7. 7. 8. 1. 1. 1. 2. 2. 3. 3. 3. 3. 0. 9. 9. 9. 9. 9. 9.
170.652

16 47 27
4.
5.
6.
9.
0.
0.
2.
2.
3.
3.
3.
2.
9.
9.
9.
9.
9.

32 48 39 05 33 77 36 96 22 58 50 10 2. 30 82 52 45 47 47
17 17

3. 62 4 8
59
25
57
63
49
84
19
19
41
48
55
62
42
44
46
43
36

3 7 6 1 1 0 1 2 3 6 9 1 17 4 9 7 2 5 3
0. 0.

8
2
7
4
8
9
9
0
5
3
8
7
7
1
1
2
9
8

80 1 2. 17
38 38

6 53
1

17 0.
1 28
2. 6
62
S

0 17
N

16 16 16 17 17 17 17 17 17 17 17
17 0. 16 16 16 16
16
16
16
17
17
17
17
17
17
17
17
16
16
16
16
16

8. 9. 9. 1. 2. 2. 2. 2. 2. 3. 2. 16 9. 9. 9. 9.
6.
6.
7.
0.
1.
1.
2.
2.
2.
3.
3.
9.
9.
9.
9.
9.

64 72 96 97 33 60 18 64 79 12 2.68 5 80 24 29 41
66
89
71
67
11
65
51
35
98
20
26
42
21
17
40
34

8 0 0 5 5 6 5 9 1 6 613 8 9 7 4
7
9
3
2
3
9
5
0
7
5
0
7
9
8
9

9 17
0.
X = 707711.442

17 04
Y = 2713260.952

2.
170.13

4 17
16

61 0
9.

8
22

173.
16 17 17 17 17 17 17 17 17 17 16 16 16
9

16

0000
17
16
16
16
17
17
17
17
17
17
17
17
16
16
16

9.

6. 0. 0. 0. 2. 2. 2. 2. 2. 2. 9. 9. 9.
7.
8.
9.
1.
2.
2.
2.
2.
2.
3.
2.
9.
9.
9.

91 17 94 96 85 98 84 25 12 59 2. 03 08 21
92
4

61
70
38
14
47
13
83
64
43
72
03
73
50
15
36

9 8 6 0 2 0 0 5 5 1 9 169 3 2
7
7
1
4
9
7
9
9
5
4
8
1
4
8

7
148
16
34.

17
9.

.5
17

3.
31

80

2.
3

06
6
61

2
6

16 16 16 16 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 16 16 16 16
172.0000
16

5. 6. 7. 9. 0. 0. 1. 2. 2. 2. 3. 3. 3. 3. 2. 2. 2. 2. 2. 2. 172.
9.

9. 9. 8.
64 65 88 12 21 62 45 29 81 84 22 13 25 00 81 63 45 24 07 94 2.72 25 02 94 169.31
68

61
2

1 1 9 7 2 4 9 9 7 1 4 4 1 3 9 6 2 3 7 3 1 1 6 6 9. 5
27
5
16 1
17 9.
2. 56
61 1 16
4 9.5
169.57

16 16 16 16 16 16 16 16 17 17 17 17 17 17 17 17 17 17 17 17 17 17 16 16
44

5. 5. 6. 6. 7. 7. 8. 9. 0. 1. 2. 3. 3. 3. 3. 3. 2. 2. 2. 2. 2. 172. 9. 9.
11 59 07 56 04 53 33 57 81 92 93 17 21 15 08 05 96 83 64 49 21 2.52 44 14
1 5 9 3 7 1 5 3 1 3 2 4 0 7 5 6 2 2 8 4 3 618 9
3
16
17 9.
H

2. 31
.42
T

61 9
2
17

16 16 16 16 16 16 16 16 16 16 17 17 17 17 17 17 17 17 17 17 17 17
2.

5. 5. 6. 6. 7. 7. 7. 8. 8. 9. 0. 1. 2. 2. 2. 3. 3. 2. 2. 2. 2. 172.
LIN

82

06 54 03 51 00 48 96 45 93 42 01 25 53 73 96 05 03 96 73 73 66 2. 45
3
E

4 8 2 6 0 4 9 3 7 1 9 7 0 9 0 4 4 3 1 6 1 613
1
C

17
2.
R

172.50 17 59
O

17
00 2. 8
56
17 2. 6
16 16 16 16 16 16 17 17 17 53
SS

16
16
16
16
16
16
16
17
17
17
17

4. 5. 6. 6. 8. 9. 1. 1. 2. 2. 4
4.
5.
5.
7.
7.
8.
9.
0.
0.
2.
2.

04 98 47 95 89 37 31 79 54 50
17 17

53
01
50
43
92
40
85
34
82
62
48

9 5 0 4 0 4 1 5 1 3
2. 2.

3
7
1
8
2
6
8
2
7
2
4

17
17

16 16
44 38

16 164.5000 165.5000 16
166.0000 16 16 16 2.
5 3

166.5000 16
2.

167.0000 167.5000 17
16

4. 4. 165.0000 5. 168.0000 168.5000 16 169.0000 17 17 17 17 59


16

6. 170.0000 170.5000
16

6. 7. 171.0000 171.5000
169.3

7. 172.0000
16
17

8.
5.

40 9. 169.5000
33

84 29 0. 2.
7.

19 64 1. 1. 4
8.

09 2.
2

99
9.
0.

89 34 28
74

2 4 4 69 14 59 04
54

4 3
44

3
4

3
79
24

3
3

3
3

2 2 2 0
3
2

2
X = 707742.341

BT
E

Y = 2713246.045

RO
AD
17
2.
42
0

NCC LIMITED
X = 707714.749
Y = 2712993.134

TO
KA
NA
CH
X = 707753.504

Ceinsys Tech Ltd.


Y = 2713014.850
TBM NO 1029 ON EP RL-173.292
X = 707743.564 Y = 2713046.110
N
w

E
S

55.0m

Entrance
Size-3.50m x 4.0m
30.0m

60.0M

J
TO ROBERTSGAN
B.T. ROAD
TO KANACH
VENTILATOR

R.L. 182.00 M.
00
5.

RAIL BEAM
Ø

Entrance
WINDOW

WALKWAY
R.L. 177.00 M.

HFL Beam Approach Ramp


R.L. 175.60 M. Length - 60.0m

Rungs Pipe Dia


1600 mm G.L. 172.50 M.
Manhole
1.0m x 1.0m
FGL
R.L. 171.00 M.

168.10 M. N.G.L.

L.W.L - 164.50 M

163.00 M. Diameter - 1600 M R.L. 162.00 M.


LENGTH - 85 M
R.L. 162.00 M.
R.B.L. 162.00 M.
161.00 M.

R.L. 159.00 M.

158.00 M. R.L. 158.00 M.

SILT PIT
Ceinsys Tech Ltd.
2.0X2.0X1.0
Subject to Soil exploration and structure design of Raft Subject to structure design of Raft
NCC LIMITED
REV.NO. DESCRIPTION DATE CHECKED APPROVED

REV-1 27.11.2021
REV-2 04.12.2021

HYDRAULIC DESIGN OF RAW WATER


RISING MAIN (1200 mm MS PIPE)

NCC LIMITED, HYDERABAD

Project Construction of Patwdh group of Villages Water Supply Scheme, District - Sonbhadra

Executive Director,

Client State Water & Sanitation Mission


U.P. Jal Nigam Compound Rana Pratap Marg, Lucknow - 226001

HYDRAULIC DESIGN RWRM


DOCUMENT
NCC/W&E/PATWDH/RWRM/001 Rev. No. 2 Date: 04/12/2021
NO.

This Document is the Property of NCC Limited and must not be passed Prepared By
on to any person or body not authorized by us to receive it nor be copied Reviewed By
or otherwise made use either in full or in part by such person or body
Approved By
without our prior permission in writing.
Total Water Demand for Scheme
In Base year In Intermidiate In Design
S.N. Description
2023 year 2038 Year 2053

1 Population of Patwadh Villages and habitation 715560 931930 1211660


2 Water demand at Consumer End-MLD 46.30 60.30 78.39
Water Treatment Plant (WTP) 2% Extra WTP
3 47.22 61.50 79.96
Losess

Raw water Demand at Intake well


4 50.93 66.33 86.23
 Design of Intake well
Design Criteria
River Bed Level 162.0 m
Lowest Water Level of River 164.50 m
Highest Flood Level River  175.6 m
Pump Floor Level of Intake Well 177.0 m
Pipe Level  178.0 m
Roof level of pump house 183.8 m
Ultimate Demand for year 2053 (24 hrs) 86.2 MLD
Number of working Hour 16.0 Hr
Design Intake well for Volume
Ultimate demand for year 2053 (16 hrs) 129.0 MLD
Design of wet well
Discharge for 16 Hour Operation 89.83 cum/min
Consider detention time  5.0 Min
=89.83*5 449.0 cum
Assuming the internal dia. of well 14.0 m
Surface Area of Well =3.14*14*14/4 153.9 sqm

Depth of required water 2.9 m
5.5 m, Say

Provide silt pocket 0.7 m below the required depth of intake well
Bottom  level of Intake well (LWL‐Depth of required water‐0.7) m 159.0 m
Foundation level of Intake well(Bottom Level of intake level‐1.1)m 158.0 m
Total Height of Intake well (Pump Floor‐Bottom level)m 18.0 m
Height of Pump house 6.8 m
Height of Pump house (Say) 6.8 m
Size of Intake well
Dia. Of Well= 14.0 m
Adopted Dia for Installation of Pumps 14.0 m
Height of Well = 18
Height of Pump House= 6.8
Design of intake opening

Total Intake water for 24 Hour  86.2 MLD


Discharge for 16 Hour operation 1.5 cum/sec
Let Us provide 4 Ports at Three Differeent Levels fitted with Coarse 
Screen

Size of Pipe connected in River at Above LWL & Below LWL 
Design discharge 16 hour Operation 89.83 cum/min
Number of Proposed Pipe 1.0 no
Assume Velocity 0.75 m/s
Required Area of Pipe 2.00 Sqm
Dia. of Opening in meters 1.594666 m
1594.67 mm
Say 1600.00
As discussed with the Officials of SWSM, It is decided that Pipe will be proposed to be 
conencted with Intake Well at different levels. Total three number of Pipes will be proposed 
i.e. one Below LWL,  and two between HFL & LWL
Design of Raw Water pumping Main from Intake to WTP
From: Intake To: WTP
1) Water
Year Peak Discharge Pipe Dia in mm Material Thickness (mm) HWC Rate Rs/m
requirement :
A. Initial 2021 50.93 mld 1100 MS 10 140 31236
B. Intermediate 2036 66.33 mld 1200 MS 9 140 30552
C. Ultimate 2051 86.23 mld 1300 MS 9 140 33060
2) Pumping main LENGTH 700.00 M 1400 MS 9 140 35682
3) Static head for pump ST.HEAD 38.50 M 1500 MS 9 140 38525
4) Design period YEAR 30 yr. Lowest Water Level of River 165 m
5) Combined eff. of pump set EFF. % 72 % Higest level in route (Hump) 200 m
6) Cost of pumping unit Rs./KW 15000 Rs Residual pressure 3 m
7) Interest rate INTEREST 10.00 %
8) Life of electric motor & pump set P.Yrs 15 yr.
9) Energy charges per kWh P/KWH 850 paise
10) Pumping hours for discharge at the end of 15 years hours 16 hrs
CALCULATIONS: 1st 15 years 2nd 15 years
1) Discharge at Start OF PERIOD 50.93 mld 66.33 mld
2) Discharge at the end of 15 yrs 66.33 mld 86.23 mld
3) Average Flow 1152 lps 1497 lps
4) Average Discharge 58.63 mld 76.28 mld
5) Avg.pumping hours during the period 14.14 hrs 14.15 hrs
6) KW required at combined efficiency of pumping set 15.68 * H1 20.38 * H2
7) Annual charges for energy Rs. 43907.53 * KW1 43942.16 * KW2
Modified Hazen William's Formula
V= 143.534CR r0.6575 S0.5525
h= [L(Q/CR)1.81 ]/[994.62D4.81]
Friction Head Loss (First 15 years)
3 CR
Dia. in mm L (m) Q (m /s) Q/CR (Q/CR)1.81 994.62 Dia (D) (m) D4.81 (mm) h( First 15 yrs)
(Constant)
1100 1000 1.152 1.000 1.152 1.291 994.620 1.100 1.582 0.821
1200 1000 1.152 1.000 1.152 1.291 994.620 1.200 2.404 0.540
1300 1000 1.152 1.000 1.152 1.291 994.620 1.300 3.532 0.367
1400 1000 1.152 1.000 1.152 1.291 994.620 1.400 5.045 0.257
1500 1000 1.152 1.000 1.152 1.291 994.620 1.500 7.031 0.185
Design of Raw Water pumping Main from Intake to WTP
From: Intake To: WTP
Velocity
r=A/P=D/4
Dia. in mm CR r0.6575 (m) S (Slope) S0.5525 V (m/s)
(m)
1100 143.534 1.000 0.275 0.428 0.001 0.020 1.212
1200 143.534 1.000 0.300 0.453 0.001 0.016 1.018
1300 143.534 1.000 0.325 0.478 0.000 0.013 0.868
1400 143.534 1.000 0.350 0.501 0.000 0.010 0.748
1500 143.534 1.000 0.375 0.525 0.000 0.009 0.652
Friction Head Loss (Second 15 years)
h ( Second 15
Dia. in mm L Q CR Q/CR (Q/CR)1.81 994.62 Dia (D) (m) D4.81
yrs)
1100 1,000.000 1.497 1.000 1.497 2.076 994.620 1.100 1.582 1.320
1200 1,000.000 1.497 1.000 1.497 2.076 994.620 1.200 2.404 0.868
1300 1,000.000 1.497 1.000 1.497 2.076 994.620 1.300 3.532 0.591
1400 1,000.000 1.497 1.000 1.497 2.076 994.620 1.400 5.045 0.414
1500 1,001.000 1.497 1.000 1.497 2.076 995.620 1.500 7.031 0.297
Velocity
Dia. in mm 143.534 CR r=A/P=D/4 r0.6575 S S0.5525 V
1100 143.534 1.000 0.275 0.428 0.001 0.026 1.575
1200 143.534 1.000 0.300 0.453 0.001 0.020 1.324
1300 143.534 1.000 0.325 0.478 0.001 0.016 1.128
1400 143.534 1.000 0.350 0.501 0.000 0.014 0.972
1500 143.534 1.000 0.375 0.525 0.000 0.011 0.847
Design of Raw Water pumping Main from Intake to WTP
From: Intake To: WTP
TABLE 1 - VELOCITY AND HEADLOSSES FOR DIFFERENT PIPE SIZES
total losses
total losses Friction head other
Pipe Size in Velocity in Friction head other losses at (H2)
S No friction head loss per Km Velocity in m/sec (H1) including loss in total pipe losses
mm m/sec loss 10% including
static head length at 10%
static head
1st stage 2nd stage
1st stage flow 2nd stage flow 1st stage flow 38.5 700.00 38.5
flow flow
2nd stage flow
1 1100 0.82 1.32 1.21 1.58 0.57 0.06 39.13 0.92 0.09 39.52
2 1200 0.54 0.87 1.02 1.32 0.38 0.04 38.92 0.61 0.06 39.17
3 1300 0.37 0.59 0.87 1.13 0.26 0.03 38.78 0.41 0.04 38.95
4 1400 0.26 0.41 0.75 0.97 0.18 0.02 38.70 0.29 0.03 38.82
5 1500 0.18 0.30 0.65 0.85 0.13 0.01 38.64 0.21 0.02 38.73
TABLE 2 - KILOWATTS & COST OF PUMP SETS REQUIRED FOR DIFFERENT PIPE SIZES AND PIPE COST
1st
2nd stage
stage flow in 58.63 76.28
flow in MLD
MLD
H1 total Kw required cost of total cost of
KW reqd plus pump cost at Rs H2 total head in Pump cost at Rs
S No Pipe Dia in mm class of Pipe head in plus 50% pipe per pipe in
50% stand by per Kw meters per KW
meters stand by meter thousand Rs
15000 15000 700
1 1100 10 39.13 920 13806 39.52 1208 18124 31236 21865
2 1200 9 38.92 915 13730 39.17 1198 17965 30552 21386
3 1300 9 38.78 912 13683 38.95 1191 17867 33060 23142
4 1400 9 38.70 910 13653 38.82 1187 17804 35682 24977
5 1500 9 38.64 909 13633 38.73 1184 17763 38525 26968
Design of Raw Water pumping Main from Intake to WTP
From: Intake To: WTP
TABLE 3 - COMPARATIVE STATEMENT OF OVERALL COST OF PUMPING MAIN FOR DIFFERENT PIPE SIZES
1st stage
58.63 mld 2nd stage flow 76.28 mld
flow
Cost of pump Annual capitalized Pump Cost of pump set Annual Energy capitalized Pump Present cost of
set Energy energy cost cost+capitalized Charges energy cost cost+capitalize pump and Grand total
S No Charges energy cost d energy cost capitalized cost Pipe Dia cost first and
of 2nd stage second stage

Thousand Thousand
Thousand Rs Thousand Rs Thousand Rs Thousand Rs Thousand Rs Thousand Rs Thousand Rs mm Thousand Rs
Rs Rs
1 13,806 1,718 13,069 26,875 18,124 1,736 13,207 31,331 7,501 1,100 56,241
2 13,730 1,709 12,996 26,726 17,965 1,721 13,091 31,056 7,435 1,200 55,548
3 13,683 1,703 12,952 26,635 17,867 1,712 13,020 30,887 7,394 1,300 57,171
4 13,653 1,699 12,924 26,577 17,804 1,706 12,974 30,778 7,369 1,400 58,923
5 13,633 1,697 12,905 26,538 17,763 1,702 12,944 30,707 7,351 1,500 60,857
Minimum Capitalized cost Rs 55,548 Thousands
Optimum pipe size corresponds to minimum capitalized cost 1200 mm
Water Hammer Calculations & Design of Pumping Main
From : Intake
To : WTP

1. Daily demand : 86.23 ML

2. Design capacity of main 129.35 MLD Working Hour 16

3. Length of main : 700 m

4. Velocity head at higest point "x" 3 m

5. Lowest point on main : 164.5 m

FSL of Discharge Pt. :

6. Higest level in route (Hump) 200.00 m

7. Static head for


Water Hammer : 35.50 m

Water hammer Head : Cond.1 : (Static+Frictional) Head < Permissible


a.V working pressure
H max = ---------- Cond.2 : (Static+Frictional+Hmax)
g AND < Field test p
pressure
1425 (Static + Frictional)*1.5
Where, a= K (Kg/m2) Bulk Modulus of water 207000000
(1 + K.d / E.C)
E(Kg/m2) Modulus of elastisity of pipe
Dia.(mm) Class C (mm) a material 21000000000
1100 m 10 988
1200 m 10 965 g (m/s2) Accelertion due to gravity 9.81
1300 m 10 944
1400 m 10 924 C (mm) Wall thickness of pipe
1500 m 10 906
d(mm) Diameter of pipe

V (m/Sec) Normal flow velocity

H max (m) a . v / g

Thickness Calculations

t = P * D / (2 * F *S * E)
Design factor F 0.6
Stress 60 % of the specified minimum
yield stress (0.6*275 for Fe450)
Specified Minimum Yield Strength (MPa)= KPa for S 275000 Kpa
Longitudinal joint factor E 1
From : Intake
To : WTP

Pipe Velocity H Fr. head 10 % for Total (m) Static Thickness of


Corrosion Total Adopted
S.N. +Hammer Pipe (mm) t Thickness Thickness Thickness P. work. P.F.T. Cond.1 Cond.2
= P * D / (2 *
(mm) (mm) (mm)
dia. (mm) m / sec max (m) m. 'y' spl. 'z' x+y+z x+y+z F *S * E)

1 1200 1.32 130.21 0.61 0.06 3.67 169.37 6.2 3 9.2 9 412.50 675.00 OK OK

Internal Pressure at Minimum Yield


Barlow's formula
Specified Minimum Yield Strength (MPa)= KPa for S 275000 Kpa
Py= 2St/D
4125.00 Kpa
412.50 m

Ultimate Pressure at Minimum Yield


Specified Minimum Ultimate (Tensile) Strength
(MPa)= KPa for the specified material. S 450000 Kpa

Py= 2St/D
6750.00 Kpa
675.00 m

Collapse or buckling of Pipe


If negative pressure in the liquid occurs, resulting in a positive stress in th epipe wall, the situation is more complex. IN this case there is a risk of collapse
or buckling.
The maximum permissible stress in length directions
Pe = 2Ee3/D3
174.66 Kg/cm2
17.47 mhwc
A safety factor γm = 2.00
Design buckling pressure 8.73 mhwc
10.00 m Ref‐ Water Hammer
which is near to (but less than) full vacuum
Pipe Thickness Calculations
Description Symbol Particulars Unit
Working Pressure P 1680 Kpa
(As per Calculations)
1 Kpa 0.001 N/mm2

Test pressure (1.0 times of Working Pressure) 1680 Kpa


Diameter D 1200 mm
Design factor F 0.6
Stress 60 % of the specified minimum
yield stress (0.6*275 for Fe450)
Specified Minimum Yield Strength (MPa)=
S 275000 Kpa
KPa for the specified material.
Longitudinal joint factor E 1

T = P * D / (2 * F *S * E)
Thickness of Pipe T 6.1 mm
Thickess for Corrosion 3 mm
Adopted Thickness 9.1 mm
Say 9 mm
Patwadh Gov Water supply Scheme
19.0 Pump Design at Intake for Ultimate

S.N Description Unit Particulars


1 Rate of Pumping for 24 Hour Operation (q) lph 3592917
lps 998.00
2 Static Head m 35.50
a LSL at Starting point m 164.5
b FSL at discharge m 200
3 Frictional head m
a Operating Hour hr 16
b Discharge for Operating Hour given in S. no-3.a mld 129.35
lps 1497.11
c Length of main m 700
d Pipe details
Dia. mm 1200
Type 0
Class 0
e C 0
f hf m/km 0.00
g Total frictional loss m 0.00
h Add for losses in bends
valves etc at 20 % of
above 'f' m 0.00
i Total frictional head m 0.00
Friction Loss in Suction & Delivery Pipe m 5
4 Velocity head at End point m 5
5 Total head on pump (h) m 45.50
Efficiency of Pump % 72.00
6 BHP reqd.
qxh
------------- BHP 1261.45
75 x 0.7
7 Add 10 % extra for altitude 1.10
and temperature variation BHP (1BHP = 1.014 HP) 1387.60
8 Total HP required HP 1368.44
9 Total HP proposed HP 1370.00

10 Description of Pumps
Provide VT pumps,
No. of working pumps for stage 1 4.00 No

343.00 HP Electrical
Discharging combinely 1498.00 lps
375.00 lps
Total head of 46.00 m
No of standby pumps : 2.00

Provide 4 Pumps working with 46 m head and 375 LPS and2 standby i.e 343 H.P each, to be
arranged a single pipe of 1200 mm Dia MS pipe will be connected with the Inlet chamber of WTP
from Intake.
Design of Mechanical Items of Inake
A Calculations of Mechanical Items
No. Suction Pipe (Working) 4.00 No
No. Suction Pipe (Standby) 2.00 No
Total Discharge Pump 1498.00 LPS
Discharge per working pump 375 LPS
Diameter Meter of Suction Pipe 565 mm
Adopted Diameter for Suction Pipe 600 mm
Delivery Pipe of Individual 516 mm
Adopted Pump Delivery Pipe of Individual 600 mm
Common Delivery Pipe 1030 mm
Adopted Common Delivery Pipe 1100 mm

B Material Statement for Suction & Delivery Pipe
Adopted Diameter for Suction Pipe 600 mm
Length of Suction Pipe 84 m
Adopted Delivery Pipe of Individual 600 mm
Length of Pump Delivery Pipe 30 m
Adopted Common Delivery Pipe 1100 mm
Length of Common Delivery Pipe 24 m
Gentry Crane for Lifting of Pumps 1 No
Pressure Gauge for pump delivery pipe 6 No
NRV for pump delivery pipe 6 No
Sluice Valve for pump delivery pipe 6 No
Flow Meter for pump delivery pipe 6 No
Air Valve for pump delivery pipe 6 No
Sluice Valve for common pump delivery pipe 1 No
Flow Meter for common pump delivery pipe 1 No
Level Indicator for Intake well 3 No.

C Material Statement for Suction & Delivery Pipe
No of RCC Pipe at three different level 3 No.
Length of Pipe of each pipe 50 m
Total Length of Pipe 150 m
Gate Sluice Valve with Spendle 3  No.
Diameter of Pipe Connected with Intake & River 1600 mm
Patwadh Gov Water supply Scheme
19.0 Pump Design at Intake for Intermediate

S.N Description Unit Particulars


1 Rate of Pumping for 24 Hour Operation (q) lph 2763750
lps 768.00
2 Static Head m 35.50
a LSL at Starting point m 164.5
b FSL at discharge m 200
3 Frictional head m
a Operating Hour hr 16
b Discharge for Operating Hour given in S. no-3.a mld 99.50
lps 1151.63
c Length of main m 700
d Pipe details
Dia. mm 1200
Type 0
Class 0
e C 0
f hf m/km 0.00
g Total frictional loss m 0.00
h Add for losses in bends
valves etc at 20 % of
above 'f' m 0.00
i Total frictional head m 0.00
Friction Loss in Suction & Delivery Pipe m 5
4 Velocity head at End point m 5
5 Total head on pump (h) m 45.50
Efficiency of Pump % 72.00
6 BHP reqd.
qxh
------------- BHP 970.35
75 x 0.7
7 Add 10 % extra for altitude 1.10
and temperature variation BHP (1BHP = 1.014 HP) 1067.39
8 Total HP required HP 1052.65
9 Total HP proposed HP 1060.00

10 Description of Pumps
Provide VT pumps,
No. of working pumps for stage 1 4.00 No

265.00 HP Electrical
Discharging combinely 1152.00 lps
288.00 lps
Total head of 46.00 m
No of standby pumps : 2.00

Provide 4 Pumps working with 46 m head and 288 LPS and2 standby i.e 265 H.P each, to be
arranged a single pipe of 1200 mm Dia MS pipe will be connected with the Inlet chamber of WTP
from Intake.
Design of Mechanical Items of Inake
A Calculations of Mechanical Items
No. Suction Pipe (Working) 4.00 No
No. Suction Pipe (Standby) 2.00 No
Total Discharge Pump 1152.00 LPS
Discharge per working pump 288 LPS
Diameter Meter of Suction Pipe 495 mm
Adopted Diameter for Suction Pipe 500 mm
Delivery Pipe of Individual 452 mm
Adopted Pump Delivery Pipe of Individual 500 mm
Common Delivery Pipe 903 mm
Adopted Common Delivery Pipe 1000 mm

B Material Statement for Suction & Delivery Pipe
Adopted Diameter for Suction Pipe 500 mm
Length of Suction Pipe 84 m
Adopted Delivery Pipe of Individual 500 mm
Length of Pump Delivery Pipe 30 m
Adopted Common Delivery Pipe 1000 mm
Length of Common Delivery Pipe 24 m
Gentry Crane for Lifting of Pumps 1 No
Pressure Gauge for pump delivery pipe 6 No
NRV for pump delivery pipe 6 No
Sluice Valve for pump delivery pipe 6 No
Flow Meter for pump delivery pipe 6 No
Air Valve for pump delivery pipe 6 No
Sluice Valve for common pump delivery pipe 1 No
Flow Meter for common pump delivery pipe 1 No
Level Indicator for Intake well 3 No.

C Material Statement for Suction & Delivery Pipe
No of RCC Pipe at three different level 3 No.
Length of Pipe of each pipe 50 m
Total Length of Pipe 150 m
Gate Sluice Valve with Spendle 3  No.
Diameter of Pipe Connected with Intake & River 1600 mm
M
0
W.T.P.

.0
00
INTAKE WELL

.7
Ch
0
46
7.

0
17

00
M

9.
0

18
.0
.0

M
Ch

0
.0
65
R.W.R.M 1200MM Ø

.6
6

0
85

Ch
0

60
.1
2.
M.S. PIPE

6.

0
17

0
0

Ch. 140.00 M 18

90
18

55
20

8.
M

9.
7.

20
18
0
LENGTH - 700M.

18
7
5.0

Ch. 105.00 M 1

9.

0
00
.3

M
18

00
M
Ch

.5

.00
1.

0
3

Ch. 175.00

19

40
M
Ch. 70.00 M 17

30
2.

0
Ch. 210.00

.6
19

20
M

Ch
0
7.
Ch. 245.00

35

0
0
19

0
M

00

0
00

50
55

9
00
9.

45

45
0.

7.
Ch. 280.00

19

6.
9.

6.

3.
M

20

9.
19

19
19

19

19

18
Ch. 315.00

M
Ch. 350.00

Ch. 490.00 M

Ch. 525.00 M

Ch. 560.00 M

Ch. 595.00 M
Ch. 385.00

Ch. 420.00

Ch. 455.00
R.W.R.M 1200MM Ø
M.S. PIPE
LENGTH - 700M.

SURVEY PLAN OF RAW WATER RISNG MAIN FROM INTAKE WELL TO W.T.P.

A.V.

A.V.

LEGEND
A.V.

A.V. AIR VALVE


SC.
PRV

SC. SCOUR VALVE

PRESSURE REDUCING
PRV VALVE

SC.

REV. DATE DESCRIPTION DRAWN DESIGN CHKD APPD

PROJECT:
CONSTRUCTION OF PATWDH GROUP OF
VILLAGES WATER SUPPLY SCHEME, DISTRICT
SONBHADRA
CLIENT: EXECUTIVE DIRECTOR
STATE WATER AND SANITATION MISSION LACKNOW,UP
NAMAMI GANGA & RURAL WATER SUPPLY DEPARTMENT
GOVERNMENT OF UTTAR PRADESH
PMC
CONSULTANTS:
CEINSYS TECH LTD.

CONTRACTOR:

NCC LIMITED
HYDERABAD

DATE NAME TITLE:

RELEASE STATUS DESIGN


R.W.R.M. FROM INTAKE WELL
PRELIMINARY DRAWN

FOR INFORMATION CHECKED


TO W.T.P.
FOR APPROVAL APPROVED NCC DRG. NO.: UP/SONBHADRA/PATWDH/RWRM/001 REV.R2

FOR CONSTRUCTION DEPARTMENT: CIVIL (planning) EDTD DRG. NO.: REV.

AS-BUILT SCALE: SHEET: 01 OF 01


REV.NO.   DESCRIPTTION  D
DATE  CHECKED  APPROVED

REV ‐ 1  15.11.2021
REV ‐ 2 27.11.2021
REV ‐ 3 14.12.2021

PROCESS DESIGN OF 120 MLD WTP OF


PATWADH GOV

N
NCC LIMITED  
EN
NGINEERING DESIGN AND
D TECHNOLOG
GY DEPARTMEENT 

Project  Constructiion  of  Patw


wadh  Grou up  of  Villagges  Water  Supply  Schheme,  Distrrict  – 
Sonbhadraa  (Based  on
n  Surface  W
Water)  and  relevant 
r wo
orks  includin
ng  Commissiioning 
and Operaation & Main ntenance forr 10 Years 
PMC  
Consultants  CEINSYS TECH
H LTD. 

Client  Exxecutive Direector, 
Sttate Water &
& Sanitation Mission 
U.P. Jal Nigam
m Compound d Rana Prataap Marg, Luccknow ‐ 2260
001 

DO
OCUMENT NO.  NCC/PATWADH/WTP/PDC/H/001  Revv.No.3 Date:14.12..21 
This  Document  is  the  Prroperty  of  NCC 
N Limited  and  must  not  n be  Prepared By 
passed on to any person or body not authorized by us to recceive it  Revviewed By 
nor  be  copied  or  otherw
wise  made  use  either  in  full  or  in  part 
p by  App proved By 
su
uch person o or body withhout our prio or permissioon in writing.. 

PATWADH GOV
PATWADH GOV

DESIGN OF 120 ML WATER TREATMENT PLANT OF PATWADH MVPWSS

Particular Formula Value Unit

Clear Water Required at CWS at WTP for Distribution 80.08 mld


Raw Water to be treated in a day (at Clarifloculator) In 16 Hour 85.14 ML

Raw Water to be treated in a day (at Filter ) In 16 Hour 84.71 ML


Clear Water Sump Demand In 16 Hour 84.29 ML
Pumping Hour 16 hour
Capacity per hour at clarifloculator C5/C8 5.321 ML
Capacity per hour in cum at clarifloculator 5321.25 m3 / hr
Capacity per sec in cum at clarifloculator 1.4781 m3 / sec
Capacity in lps 1478.125 lps

Raw water to be treated in a day if operated 24 hour In 24 Hours 127.71 ML


ML,
Clear Water if Operated for 24 Hrs In 24 Hours 120.1 Okay
Over Loading on Pipe & Channel 20% 1.20
AERATION FOUNTAIN

Nos of Cascade 3 to 6 4 nos


Trade of Cascade 1.25 m
m / m3
2
Area requird for cascade fountain 0.015 to 0.045 0.02 / hr
Area of Areation fountain upto launder 106.43 m2
Dia of cascade areator upto launder Area wise 11.64 m
Dia of RCC Central Shaft 1600 mm
1.6 m
Diameter of 1st Trade 4.10 m
nd
Diameter of 2 Trade 6.60 m
rd
Diameter of 3 Trade 9.10 m
th
Diameter of 4 Trade 11.60 m
Dia upto launder Rise and tread wise 11.60 m
Keep rise of cascade 0.2 to 0.4 0.3 m
Let dia of central shaft 1600 mm
1.6 m
Velocity through shaft (central pipe) 0.6 to 0.9 0.88 m/s
Since velocity is approximately 0.9 m/s, it shall have stilling effect hence OK
Keep width of launder 1.5 m

1
PATWADH GOV
Particular Formula Value Unit
Depth of launder (Liquid Depth) 0.75 m
Velocity of flow through launder 0.79 m/s
Velocity is around 0.75 m/s , hence OK
Provide Free board 0.5 m
Provide 1.2 m wide walk way peripherically
RAW WATER CHANNEL & PARSHALL FLUME
Designed flow Q 1.774 m3 / sec
Width of Channel (assume) 2 m
Water depth in Channel 1.00 m
Flow Velocity 0.89 m/s
Provide Free board 0.5 m
FLUME
Use standard Parshall Flumes No. 8 As per BIS 14371 -1996. Dimensions are as per Table No.1. Drawing Fig
No.1.
Throat Dimension b 1
l 0.6
X 0.05
Y 0.075
hp1 0.23
Entrance Section b1 1.68
l1 1.7
le 1.734
la 1.161
Exit Section b2 1.3
l2 0.92
hp2 0.072
Side Wall Height hc 1
Upstream head ha Q = 2.397ha1.569 0.825

DISTRIBUTION CHAMBER (1,2 & 5)


Detention time 10 sec
3
Flow 1.478 m / sec
Assume SWD 1.0 m
Let Length of chamber 4.5 m
Width of Chamber 3.285 m
Say 3.5 m
FLASH MIXER CHANNEL
Flow 0.887 m3 / sec

2
PATWADH GOV
Particular Formula Value Unit
Width of Channel (assume) 1.4 m
Water depth in Channel 0.70 m
Flow Velocity 0.9 m
Provide Free board 0.5 m
MECHANICAL FLASH MIXER
Design Flow 1.478 m3 / sec
One for two
Number of Flash Mixer 2 nos
Clarifloculator
Design Flow per Flash Mixer 0.74 m3 / sec
Detention time 30 to 60 sec 45 sec
Volumetric Capacity 33.26 m3
Take SWD (Side Water Depth) 4 m
Plan area required 8.31 m2
Diameter required 3.25 m
Provide diameter 3.30 m

Provide Free board 0.5 m

SWD/ Diameter ratio 1 to 3 1.21 Okay


1/2
Power Requirement G = (P / µVol)
Product 'Gt' 18000
Velocity Gradient 'G' 300 to 600 400 per sec
o
Absolute Viscosity of Water ‘µ’ at 25 C 0.00089 kg/m/s
Power Required in Watt 'P' 4735.91 Watt
Total Power Required 9471.83 Watt
OUTLET PIPE FROM FLASH MIXER TO CLARIFIER
Water shall be conveyed through pipe conduit from flash mixer to clariflocculator
Velocity permitted 0.8 m to 1.8 1.3 m/s
3
Flow per Clarifer 0.443 m / sec
Size of Pipe 0.659 m
Provide size 700 mm
Actual Velocity 1.152 m/s

CLARIFLOCCULATOR
Design Flow 1.4781
No of Clariflocculator 4
Design Flow per Clariflocculator 0.370 m3 / sec
Central Inlet Shaft
This shall be in RCC 850 mm diameter with rectangular openings 8 numbers at top (just below FSL)

3
PATWADH GOV
Particular Formula Value Unit
Diameter of inlet shaft 0.85 m
Velocity at inlet shaft 0.78 m/s
Outlet Opening (Port) at central shaft
Width of Port 0.16 m
Depth of Port 0.45 m
Nos. of Ports 8 Nos.
Velocity through Ports 0.77 m/s
Flocculator
Detention time 10 to 40 minute 30 minutes
Volumetric Capacity required 665.16 m3
Add volume of central shaft
RCC wall thickness of central shaft Let 0.25 m
Depth of Central Shaft 2.5 to 4.5 4.5 m
Volume of central shaft 6.44 m3
Total Volume of flocculation zone 671.60 m3
Diameter of flocculation zone 13.78 m

Provide diameter 13.80 m

Let Bottom floor slope towards central Shaft 1 to 12


SWD at Flocculator 3.98 m
Volume of Flocculator Zone (Effective) 589.78 m3
Detention Period excluding sludge Zone 26.60 minutes
Okay
Consider Outer RCC Partition of flocculator 0.25 m
Outer diameter of flocculation zone 14.30 m
Area occupied by flocculation zone 160.61 m2
Power Requirement G = (P / µVol)1/2
Product 'Gt' 75000
Velocity Gradient 'G' 10 to 75 41.7 per sec
o
Absolute Viscosity of Water ‘µ’ at 25 C 0.00089 kg/m/s
Power Required in Watt 'P' 1027.76 Watt
Clarifir Zone
Detention time 2 to 2.5 hours 2.5 hours
m /m2/d
3
Consider Surface rating 25 to 75 36 ay
Area requirement as per surface rating 886.88 m2
Total area of clariflocculator 1047.48 m2

4
PATWADH GOV
Particular Formula Value Unit
Diameter of clariflocculator As per Surface Area 36.52 m
Total Volume of clarifier zone 3325.78 m3
Total volume of clariflocculator 4048.51 m3
Dia. required from total volume As per Volume 33.85 m
Provide diameter 36.52 m
SWD at Clarifer 3.06 m
Volume of Clarifer Zone (Effective) 2709.78 m3
Detention Period excluding sludge Zone 2.04 Hr.
Okay
Free Board 0.50 m
Walk way on top of the clarifer Wall 1.20 m
Peripheral Launder
Consider inside decanting launder to withdraw clarified water and transmitting same to rapid gravity filter.
Width of Launder (assume) 0.8 m
Water depth in Launder 0.400 m
Velocity of flow through launder 0.69 m/s
Check For Weir Loading
Total length of weir 109.02 m
Weir Loading 292.86 m3/m/d
ay
less than 300.00 m3/m/d
ay
Hence Okay
Drainage
cum/da
Volume of CLF Sludge zone V = 1.048 x d2 x h 72.02
y
V = 0.7854 X h (d12 -d2) cum/da
Volume of Sludge drain 3.02
y
cum/da
Volume of Central Shaft V = 0.7854 x d2 x h 2.07
y
cum/da
Available Volume for Sludge 72.98
y
Provide capacity for Sludge tank 75 Cum
Let length of sludge tank 8.0 m
Water depth 3.0 m
Width of sludge tank 3.13 m
Free Board 0.50 m
Capacity Provided for Sludge Accumulation 10.94 cum
Provide Sludge tank Size 8.0m x 3.20m x 3.0 m
Diameter of Drainage Pipe 500 mm

5
PATWADH GOV
Particular Formula Value Unit
Provide 500 mm dia. drainage pipe with sluice valve to drain the system. Also provide constant bleeding
arrangement to manifold to avoid choking of drain line and also to know the sludge quality.
Constant telescopic bleed arrangement
Diameter of Vertical Stand Pipe 150 mm
This shall consist of vertical stand pipe of 150 mm dia. and adjustable funnel at launder level. Stand pipe is
connected to drain pipe manifold with isolating valve. Overflow of funnel is drained to drain chamber. Funnel
level can be adjusted from walkway top with hand wheel.
Outlet Settled Water Channel to Rapid Gravity Filter
Design flow after one Clarifloculator 0.441 m3 / sec
Provide Channel width 1 m
Water Depth in Channel 0.5 m
velocity of flow in Channel 0.88 m/s
Free Board 0.3 m
Design flow after two clariflocuulator ( Two cfl) Feeder Channel to filters 0.8824 m3 / sec
Provide Channel Width 1.4 m
Water depth in Channel 0.7
Velocity of flow in Channel 0.90 m/s
Provide Free board 0.3 m
DISTRIBUTION CHAMBER - CLARIFER CHANNEL
TO FILTER (3&4)
Detention time 10 sec
3
Flow 0.882 m / sec
Assume SWD 1.0 m
Let Length of chamber 3.5 m
Width of Chamber 2.5 m
Say 2.5 m

RAPID GRAVITY FILTER

Filter Sizing
Design Flow 1.47 m3 / sec
Design Flow 5294.64 m3 / hr
m3/m2/
Rate of filteration 5
hr
Area of filteration required 1058.93 m2
Provide No of beds (Eight Twin Filter) 16 nos
Sectional area of each Bed 66.18 m2
Let L /B ratio 1.11 to 1.66 1.33

6
PATWADH GOV
Particular Formula Value Unit
Let Length of each bed 9.4 m
Width of the bed 7.1 m
Filter Inlet Port (For Twin Bed)
Critical condition - One
Design flow per bed twin filter is being back 0.14781 m3 / sec
washed
Redistribute tow filter
Design Flow for twin bed 0.29562 m3 / sec
flow in other 6 filters
Let Velocity of flow 1.00 m/s
Diameter of Port 0.614 m
0.620 m
Provide 0.7 m
Actual Velocity 0.77 m/s
Filter Outlet ( Single section)
Critical condition - One
Design flow per bed twin filter is being back 0.14707
washed
Let velocity of flow 1 m/s
Diameter of Outlet 0.433 m
0.440 m
Provide 0.45 m
Actual Velocity 0.92 m/s
(Back Wash Tank to
Filter Back Wash Water (Out let Pipe)
Manifold)
Velocity of flow 3 m/s
3
m /min/
Back Wash rate 0.6
m2
Total discharge rate for backwash per bed 0.6674 m3 / sec
Dia of back wash pipe 0.532 m
Provide diameter 600 mm
0.600 m
Dia of Sluice Valve 600 mm
Actual Velocity attained Okay 2.36 m/s
Air Piping
m3/min/
Rate of air scour 0.75
m2
3
Total air requirement 50.055 m /min
0.83425 m3 / sec
Velocity 30 to 35
Dia of air pipe 0.1882 m
m/sec
0.200 m

7
PATWADH GOV
Particular Formula Value Unit
Actual Velocity attained 26.55 m/s
Provide air blower@0.35 kg/sqcm 3010 m3/hr
Filter Under Drain System
Filter Sectional area 66.74 m2

Area of Perforations 0.3% *area of filter bed 0.30%

0.20022 m2
Dia of perforations 0.01 m
0.000078
Area of one perforation m2
5
No of perforations 2550 nos
Area of laterals 2xArea of Perforations 0.40044 m2
Area of Underdrain (Manifold) 2xArea of laterals 0.80088 m2
Length of filter bed 9.4 m
Spacing of a laterals c/c 0.3 m
(Length of filter bed /
No of laterals 30.33 nos
spacing of lateral) -1
Provide 31 nos

Number of Lateral on both side of central Manifold 62 nos

Length of each laterals 3.1 m


(i.e. 21 holes on either
Perforations per pipe 42 nos
side of pipe)
Provide 21 holes of 3 mm at top of laterals for air release
0.012917
Area of one lateral m2
42
Dia of lateral 0.128 m
Provide diameter class 6 PVC pipe 140 mm
Provide width of under drain (Manifold) 0.90 m
Depth (Manifold) 0.890 m
Say 0.90 m
Provide under drain 900 mm x 900 mm
Wash Water Trough
Back Wash Flow 0.6674 m3 / sec
Nos of trough per bed 3 nos
3
Flow per trough per bed 0.2225 m / sec
Assume trough width 0.5 m
3/2
Flow depth in trough q=1.376bh 0.469 m
Round off (For rounding Only) 0.001 m
Overall depth 0.470 m

8
PATWADH GOV
Particular Formula Value Unit
Let Slab Thickness of Trough 0.150
Provide 3 nos. trough 500 mm x 470 mm
Wash Water Gullet
Let Gullet Width "b" 0.9 m
3
Back Wash Flow Per bed 0.6674 m / sec
3/2
Flow depth in gullet q=1.376bh 0.66 m
Free board 0.1 m
Overall depth 0.76 m
Back Wash Channel ( for One bed)
Flow rate Q 0.6674 m3 / sec
Width of Channel B 1.00 m
Depth of Channel D 0.50 m
Flow Velocity V 1.33 m/s
Okay
Value of 'n' for Concrete n 0.013
[Q.n(B+2D)0.667 /
Slope of Back Wash Channel
(B.D)1.667 ]2 0.00191 m/m
Length of Back Wash Channel 90.00 m
Drop 0.17 m
Free board 0.50 m
Size of Gate 1.0 x 1.0 mxm
Size of Control Chamber Length 1.50 m
Width 1.50 m
3
Flow rate through Control Chamber 0.2941 m / sec
Velocity of flow 0.13 m/s
Outlet Control Weir
Design Flow 0.2941 m3 / sec
Provide Weir Width 1000.00 mm
1.00 m
Effective Head 'H' Q = 1.84 L H3/2 0.2944 m
294.37 mm
Provide Free board 0.3
Provide weir at inspection chamber 1000 wide for twin bed
Media
Sand 750 mm
Gravel
Grit 100 mm
6 mm to 12 mm 125 mm
12 mm to 25 mm 125 mm
25 mm to 50 mm 150 mm

9
PATWADH GOV
Particular Formula Value Unit
Total Depth 1250 mm
1.25 m
Water Depth over Crest of weir at filter sand 2
Crest height over sand bed, m 0.2
Depth of Water above sand surface 2.2 m
Free board 0.5 m
Total Depth of filter box 3.95 m

Min Ht of Trough bottom from Sand top layer 0.566 m

Trough bottom from bed level 1.816 m


Let trough bottom thickness 0.150 m
Trough top from bed level 2.44 m
Say 2.4 m
Chemical House For one month
Ground Floor
Alum doze 50 mg/l
Alum requirement for 1 months 127710.0 kg
Bulk density of alum 840 kg / m3
Volume required 152.04 m3
Stack Height 2 m
Plan Area required 76.02 m2
Lime Doze 25 mg/l
Lime requirement for 1 months 63855.00 kg
Bulk density of Lime 900 kg / m3
Volume required 70.95 m3
Stack Height 2 m
Plan Area required 35.48 m2
Total Plan Area required 111.49 m2
Actual Plan Area required With 20 % free area 133.79 m2
Provide 10 m x 15 m for Chemical Store, Actual Provided 150 sqm.
Note:- Provide alum and lime pump of discharge [21285/ (8*3600)] = 0.8 l/s and 10 m head.
Alum & Lime mixing
First Floor
tank
Nos of tank for Alum 3 nos for 8 hours each 3 nos
Alum required / hr 266.06 kg
Strength of Alum suspension 10%
Tank Capacity 21285.00 litre
Nos of tank for Lime 3 no for 8 hours each 3 nos
Lime required / hr 133.03 kg
Strength of Lime suspension 5%

10
PATWADH GOV
Particular Formula Value Unit
Tank Capacity 21285.00 litre
Provide 3.3 m x 3.3 m x 2.4 m tank i/c 0.4 m free board
Pipe Diameter for filling Alum and Lime tank from Back
Wash Tank
Let Filling Hour 8.00 hr
Volume 42.57 m3
Discharge Rate 0.00148 m3 / sec
Velocity of Flow 1.00 m/s
Diameter of pipe 0.043 m
Provide Diameter 50.00 mm
0.050 m
Actual Velocity 0.75 m/s
Chlorination by gas
Chlorine Gas dose Pre Chlorination 5 mg/l
Flow in Raw Water channel 5321.25 m3 / hr
chlorine required per hour 26606.3 g/hr
Provide Chlorinator (1 w +1s) 26.61 kg/hr
Chlorine Gas dose Post Chlorination 2 mg/l
Flow in the Clear Water Sump per Hour 5268.13 m3 / hr
10536.3 g/hr
Provide Chlorinator (1 w +1s) 10.54 kg/hr

Chlorine Tonner
Chlorine required 37.14 kg/hr
for 1 month 26742.60 kg
Capacity of Tonner 900 kg
No. of Tonner will be required for 1 month 30 nos.
Provide No. of Tonner 30 nos
Chlorination Dosing Chamber
Clear Water Flow per minute 88.69 m3 /
min
Detention Period 5 min
Volume of tank 443 m3
Let depth of the tank 2.5 m
Length of the Rectangular Tank 15 m
Width of the rectangular tank 11.8 m
Wash Water Tank
Duration of washing ( two bed ) 10 min
Water Required for washing twin bed With 10 % Extra 880.968 m3
Provide 885 cum capacity tank Over Head Tank, mini head required 10 m, free board 0.3 m

11
PATWADH GOV
Particular Formula Value Unit
Wash Water Pump
Filling Hour 2 hrs
Nos required (one as stand bye) 2 nos
(must be filled in 2
Discharge per Hr 440.484 m3/hr
hours)
122.36 lps
Head approximately 18 m
HP of Pump QH /( 75n ) 41.95 HP
KW 31.30 KW
Back Wash tank Filling inlet pipe
Flow rate 0.122 m3 / sec
Let Velocity of flow 1.00 m/s
Diameter of the Pipe 0.39 m
Provide 400.00 mm
0.40 m
Velocity in pipe 0.97 m/s
By pass arrangements
Provide bypass shutters at entry of flash mixer size 1400 mm wide x 700 mm leaf size; and another at bypass
channel 2000 mm x 1000 mm (raw water channel to extend up to filter inlet channel as by pass channel).
Pure Water Sump
Detention Time Given 120 min 2 Hour
Capacity as per detention period 10590 m3
Capacity given in tender 12000 m3
Capacity Provided 12000 m3
Water Depth (Live) 4.3 m
Free Board 0.5 m
Water Depth (Dead) 0.15 m
Length of Sump 70 m
Width of Sump 40.00 m
Recirculation Tank
Capacity of Back Wash
Volume of Back Wash of 2 filter bed 880.968 m3
Tank
Capacity Provided for Back Wash Water 885 m3
Let length of Recirculation tank 24.0 m
Water depth 3.0 m
Width of sludge tank 12.29 m
Provide width 12.50 m
Free Board 0.50 m
Capacity Provided for Sludge Accumulation 211 m3

12
PATWADH GOV
Particular Formula Value Unit
Design of Pipe Line From Filter Back Wash Chamber to Recycle Tank
Value of Manning Coefficient 'C' 100
Diameter of Pipe 'D' 1 m
3
Discharge through Pipe 'Q' 0.6674 m / sec
Velocity in Pipe 0.850 m/s
Hydraulic gradient for Pipe 'S' [ 3.5875Q / CD2.63 ]1.852 0.0010 m/m
Let Length of Pipe 70 m
Frictional Loss 0.07 m
Other Losses (Entry, exit etc) 2.2 v2 / 2g 0.08 m
Total Head Loss 0.15 m
Bottom of Back wash chamber 182.00 m
Pipe inlet level 179.50 m
Available Head 2.50 m
Hence Back Wash Water from Chamber to Recycle Tank will flow through Gravity
Design of Pipe Line From Clarifer outlet to Intermediate Chamber
Value of Manning Coefficient 'C' 100
Diameter of Pipe 'D' 0.5 m
3
Discharge through Pipe 'Q' Desludge in two hour 0.1859 m / sec
Velocity in Pipe 0.95 m/s
Hydraulic gradient for Pipe 'S' [ 3.5875Q / CD2.63 ]1.852 0.0027 m/m
Let Length of Pipe 50 m
Frictional Loss 0.14 m
Other Losses (Entry, exit etc.) 2.2 v2 / 2g 0.10 m
Total Head Loss 0.24 m
Bottom of Clarifloculator Sludge Chamber 180.20 m
Bottom of Intermediate Chamber 179.70 m
Available Head 0.50 m
Hence sludge water from clarifer outlet to Intermediate Chamber will flow through gravity
Design of Pipe Line From Intermediate Chamber to Sludge Tank
Value of Manning Coefficient 'C' 100
Diameter of Pipe 'D' 0.5 m
3
Discharge through Pipe 'Q' Desluge in two hour 0.1859 m / sec
Velocity in Pipe 0.95 m/s
Hydraulic gradient for Pipe 'S' [ 3.5875Q / CD2.63 ]1.852 0.0027 m/m
Let Length of Pipe 60 m
Frictional Loss 0.16 m

13
PATWADH GOV
Particular Formula Value Unit
Other Losses (Entry, exit etc.) 2.2 v2 / 2g 0.10 m
Total Head Loss 0.26 m
Bottom of Intermediate Chamber 179.70 m
Pipe inlet level 179.00 m
Available Head 0.70 m
Hence sludge water from Intermediate Chamber to recycle tank will flow through gravity
Design of Pipe Line from Recirculation Tank to Raw Water Channel
Value of Manning Coefficient 'C' 100
Diameter of Pipe 'D' 0.4 m
3
Discharge through Pipe 'Q' (In2 hours) 0.122 m / sec
Velocity in Pipe Q/A 0.97 m/s
Hydraulic gradient for Pipe 'S' [ 3.5875Q / CD ] 2.63 1.852 0.0037 m/m
Let Length of Pipe 150 m
Frictional Loss 0.56 m
Other Losses 0.11 m
Static Loss 15 m
Total Head Loss H 15.67 m
Discharge of Pump in lps (Q) Q 122.36 lps
Efficiency of Pump n 0.7
H P of Pump QH / (75n) 36.51 HP
KW of Pump 27.24 KW
Design of Pipe Line from Sludge Tank to Raw Water Channel
Value of Manning Coefficient 'C' 100
Diameter of Pipe 'D' 0.1 m
3
Discharge through Pipe 'Q' (In2 hours) 0.010 m / sec
Velocity in Pipe Q/A 1.29 m/s
Hydraulic gradient for Pipe 'S' [ 3.5875Q / CD2.63 ]1.852 0.0317 m/m
Let Length of Pipe 125 m
Frictional Loss 3.96 m
Other Losses 0.19 m
Static Loss 15 m
Total Head Loss H 19.15 m
Discharge of Pump in lps (Q) Q 10.14 lps
Efficiency of Pump n 0.7
H P of Pump QH / (75n) 3.70 HP
KW of Pump 2.76 KW
Design of Sludge Pipe line from Recirculation Tank to Natural drain
Value of Manning Coefficient 'C' 100
Diameter of Pipe 'D' 0.3 m

14
PATWADH GOV
Particular Formula Value Unit
Discharge through Pipe 'Q' (In 1.0 hours) 0.059 m3 / sec
Velocity in Pipe Q/A 0.83 m/s
Hydraulic gradient for Pipe 'S' [ 3.5875Q / CD2.63 ]1.852 0.0039 m/m
Let Length of Pipe 35 m
Frictional Loss 0.14 m
Other Losses 0.08 m
Total Head Loss 0.21 m
Bottom of Sludge Tank 174.50 m
NGL of Natural Drain 173.50 m
Available Head 1.00 m
Hence Sludge water from Recirculation tank to Natural Drain will flow through gravity
Design of Sludge Pipe line from Sludge Tank to Natural drain
Value of Manning Coefficient 'C' 100
Diameter of Pipe 'D' 0.1 m
3
Discharge through Pipe 'Q' (In 1.0 hours) 0.003 m / sec
Velocity in Pipe Q/A 0.39 m/s
Hydraulic gradient for Pipe 'S' [ 3.5875Q / CD2.63 ]1.852 0.0034 m/m
Let Length of Pipe 35 m
Frictional Loss 0.12 m
Other Losses 0.02 m
Total Head Loss 0.14 m
Bottom of Sludge Tank 175.00 m
NGL of Natural Drain 173.50 m
Available Head 1.50 m
Hence Sludge water from Sludge tank to Natural Drain will flow through gravity
Sludge calculation for Clariflocculator and Filter Beds
Inlet TSS Average at Clariflocculator 500 mg/l
Outlet TSS 100 mg/l
Reduction in TSS 400 mg/l
Total Solids 400 mg/l
Flow 5321.25 m3 / hr
Total Sludge Generated 2128.50 Kg/hr
Sludge Generated per day 34056.00 Kg
Sludge Conistency 5 %
Weight of Sludge 50 kg/cum
Volume of Sludge generated per day 681.12 cum/day
Depth of tank 3.0 m
Width of tank 10.0 m
Length of tank 22.7 m
say 23.0 m
15
PATWADH GOV
Particular Formula Value Unit
Provide Sludge tank capacity 690 cum
Total Solids Average at Filter Beds 100.00 mg/l
Flow 5321.25 m3 / hr
Total Sludge Generated 532.13 Kg/hr
Sludge Generated per day 8514.0 Kg
Sludge Conistency 5 %
Weight of Sludge 50 kg/cum
Volume of Sludge generated per day 170.28 cum/day
Capacity Provided for Sludge Accumulation 210.9 cum

16
PATWADH GOV
Particular Formula Value Unit
AERATION FOUNTAIN
Average Diameter of Launder 12.35 m
Central Length of Launder 38.779 m
Half Length of Launder 19.389 m
5
Width of Lander 'B' 1.5 m
Depth of flow 'D' 0.75 m
Value of 'n' for RCC 0.013
Flow through Lander 'Q' 0.8869 m3 /
sec
Hydraulic gradient for Channels [Q.n(B+2D)0.667 / (B.D)1.667 ]2 0.0003 m/m
(Launder) 'S' 9
Loss of Head in Launder 0.0075 m
7.54 mm
Provide drop in Launder 0.05 m
Level ( msl ) of Tip of areator 189.5 m
Drop of Cascade 1.2 m
Drop of Launder 1.25 m
Invert of U/S of Launder 187.05 m
Invert of D/S of Launder 187.00 m

RAW WATER CHANNEL


Let length of Raw Water Channel up to Distribution chamber 25 m
Width of Channel 'B' 2 m
Depth of flow 'D' 1.00 m
Flow through Channel 'Q' 1.774 m3 /
sec
Value of 'n' for RCC 0.013
Hydraulic gradient for Channel 'S' [Q.n(B+2D)0.667 / (B.D)1.667 ]2 0.0003 m/m
4
Loss of Head in Channel 0.0084 m
Head Loss at Flume 0.158 m
Total Loss 0.166 m
Provide Drop (in slope) up to Distribution chamber 0.4
Freeboard in Channel 0.5 m
Provide drop from Launder vertical drop 0.25 m
Invert of Raw Water Channel at Start 186.75 m
Invert of Raw Water Channel at end 186.35 m
Top Water Level at the Start of Channel 187.75 m
Top Water Level at the end of Channel 187.35 m
Level (msl ) of Top of Channel 188.25 m

17
PATWADH GOV
Particular Formula Value Unit
RW CHANNEL TO FLASH MIXER
Assume drop from Raw water Chanel to 0.1
Distribution Chamber 1 m

Drop from DC 1 to Flash Mixer Channel 0.1


Invert of Distribution Chamber 186.25
Top Water Level of distribution chamber 187.25
Invert of Flash Mixer Channel 186.15 m
Top water level of Channel 186.85 m
FLASH MIXER & CLARIFLOCCULATOR
Assume Drop in flash Mixer 0.5 m
Top Water Level of flash Mixer 186.35 m
Bottom of flash Mixer 182.35 m
Let Length of Pipe from F M to Central Shaft 40 m
Diameter of Pipe 'D' 0.7 m
Discharge through Pipe 'Q' 0.443 3
m / sec
Manning Coefficient 'C' 100
Hydraulic gradient for Pipe 'S' [ 3.5875Q / CD2.63 ]1.852 0.00265 m/m
Loss of Head in Pipe 0.1062 m
Velocity through Pipe 1.152 m/s
Loss in entry, bend & exit 1.5 V2 /2g 0.1015 m
Diameter of Central Shaft 0.85 m
Depth of Central Shaft 4.5 m
Slope of floor 1 to 12 0.083 m/m
Depth at floculatar wall 3.98
Depth at clarifer wall 3.06
Hydraulic gradient for Central Shaft 0.00103 m/m
Loss of Head in Central Shaft 0.0046 m
Total Head loss 0.2123 m
But Provide Drop 0.3 m
Top water level of Central Shaft 186.05 m
Invert of Central Shaft bottom 181.55
RL of floculator bottom 182.07 m
RL of Clarifer bottom 183.0 m
Provide a drop between FSL of clariflocculator 0.1 m
and TWL in launder at start
TWL of Launder at the Start 185.95 m

Invert of Launder at Start 185.55 m

18
PATWADH GOV
Particular Formula Value Unit
Width of Lander 'B' 0.8 m
Depth of flow in Launder 'D' 0.400 m
Value of 'n' for RCC 0.013
Discharge through Launder 'Q' 0.5295 m3 / sec

Hydraulic gradient for Channels (Launder) 'S' [Q.n(B+2D)0.667 / (B.D)1.667 ]2 0.00396 m/m
Mean Diameter of Launder 35.72 m
Half Length of Launder 56.08 m
Drop of Head in Launder 0.22 m
TWL of Launder at the end 185.73 m
Invert of Launder at the end 185.33 m
Channel between Clarifier to Chamber Chamber 3 &4
Design flow in Channel 'Q' 0.4412 m3 / sec
Channel Width 'B' 1 m
Water Depth in Channel 'D' 0.50 m
Value of 'n' for RCC 0.013
Hydraulic gradient for Channel 'S' [Q.n(B+2D)0.667 / (B.D)1.667 ]2 0.00084 m/m
Let Length of Channel Chamber 3 &4 30 m
Loss of Head 0.025 m
Provide drop at the Start of Channel 0.1 m
Invert of channel bottom at start 185.23 m
TWL at start 185.73 m
TWL at channel outlet 185.70 m
Invert of channel bottom outlet 185.20 m

Drop at Chamber Chamber 3 &4 0.2 m


By Pass Channel From Distribution Chamber 1
to Filter Channel
Design flow in Channel 'Q' 1.774 m3 / sec
Channel Width 'B' 2 m
Water Depth in Channel 'D' 1.00 m
Velocity of Flow 0.89 m/s
Value of 'n' for RCC 0.013
Hydraulic gradient for Channel 'S' [Q.n(B+2D)0.667 / (B.D)1.667 ]2 0.00034 m/m

Let Length of Channel 35 m


Loss of Head 0.012 m
Provide drop at the Start of Channel 0.2 m
Invert of of channel bottom at start 186.05 m

19
PATWADH GOV
Particular Formula Value Unit
TWL at start 187.05 m
TWL at channel outlet 187.04 m
Invert of channel bottom outlet 186.04 m
Provide Channel Invert at outlet 185.20
New TWL at Channel Outlet 186.20
Inlet Pipe to filter
Value of Manning Coefficient 'C' 100
Diameter of Pipe 'D' 0.700 m
Discharge through Pipe 'Q' 0.2956 m/s
Hydraulic gradient for Pipe 'S' [ 3.5875Q / CD2.63 ]1.852 0.00125 m/m
2
Let Length of Pipe 2 m
i. Frictional Loss 0.003 m
ii. Due to Gate Valve 0.2 v2 / 2g
iii. Entry v2 / 2g
iv. Exit v2 / 2g
Velocity in the pipe 1 m/s
Total Head Loss 0.11 m
FSL in filter bed 185.39 m
But Provide FSL in filter 185.34 m
Depth of filter box 3.95 m
Depth of filter box without freeboard 3.45 m
Invert of filter bottom 181.89 m
Depth of Underdrain / Manifold 0.900 m
Let thickness of T junction 0.15
Invert of manifold pit/underdrain 180.84 m
Head Loss through filter 2 m
TWL of upstream of control chamber 183.34 m
TWL of U/S Clear Water Channel 183.24 m
Invert of U/S Clear Water Channel 182.24 m
Filter Sand bed top level 183.14 m
Filter bottom level 181.89 m
Trough invert level 183.85 m
Trough top level 184.32 m
Gullet top level 184.42 m
Gullet invert level 183.66 m
FILTER TO CLEAR WATER CHAMBER
NO 5
Provide drop between Control 0.1 m
Chamber and U/S of Channel
20
PATWADH GOV
Particular Formula Value Unit
3
Let flow through Channel 'Q' 1.7560 m / sec
Length of Clear Water Channel 'L' 60 m
Width of Channel 'B' 2 m
Water Depth of Channel 'D' 1.000 m
Velocity in Channel 0.88 m/s
Value of 'n' for RCC 0.013
Hydraulic gradient for Channel 'S' [Q.n(B+2D)0.667 / (B.D)1.667 ]2 0.00033 m/m
Loss of Head in Channel 0.0197 m
TWL at inlet of Chamber 5 183.22 m
Let drop in chamber invert 0.1 m
TWL at outlet of Chamber 5 183.12 M
CHAMBER 5 TO CDT
Let length of Pipe from Chamber 5 to CDT 50 m
Diameter of Pipe 'D' 1.6 m
Value of Manning Coefficient 'C' 100
Hydraulic gradient for Pipe 'S' [ 3.5875Q / CD2.63 ]1.852 0.00061 m/m
Loss of Head in Pipe 0.030 m
Velocity in pipe 1.05 m/s
Total Loss of Head in Pipe 0.15 m
Provide drop between pipe & CDT 0.3 m
TWL at Inlet of CDT 182.67 m
Let Loss in CDT 0.1 m
TWL at Outlet of CDT 182.57 m
CHLORINE DOSING TANK (CDT )TO CLEAR WATER RESERVOIR
(CWR)
Let length of Pipe from CDT to CWS 35 m
Diameter of Pipe 'D' 1.6 m
Value of Manning Coefficient 'C' 100
Hydraulic gradient for Pipe 'S' [ 3.5875Q / CD2.63 ]1.852 0.00061 m/m
Loss of Head in Pipe 0.0212 m
Velocity in pipe 1.05 m/s
Total Loss of Head in Pipe 0.14 m
Provide drop between pipe & CWR 0.5 m
TWL of Clear Water Sump 181.92 m
Invert of Clear Water Sump 177.47 m

21
PATWADH GOV

Particular Formula Value Unit


WASH WATER PUMP
Filling Hour 2 hrs
Nos required (one as stand bye) 2 nos
Discharge per Hr (must be filled in 2 hours) 440.48 m3/hr
0.122 m3 / sec
Value of Manning Coefficient 'C' 100
Diameter of Pipe 'D' 0.4 m
Velocity in Pipe Q/A 0.97 m/s
Hydraulic gradient for Pipe 'S' [ 3.5875Q / CD2.63 ]1.852 0.0037 m/m
Length of Pipe 85.0 m
Frictional Loss 0.32 m
Other Losses 0.032 m
(Top Level of wash water tank -
Static Loss Invert of CWR)
15.35 m
Consider residual head 2.0 m
Total Head Required H 17.70 m
Discharge of Pump in lps (Q) Q 122.36 lps
Efficiency of Pump n 0.70
H P of Pump QH / (75n) 41.25 HP
KW of Pump 30.77 KW

22
11/15/21, 12:56 PM WQMIS

Jal Jeevan Mission


Har Ghar Jal

State level water analysis laboratory , U.P Jal Nigam, Lucknow


6 Rana pratap Marg Lucknow
9936065451

Test report
Sample ID U48708L158S770346

User Information

Name NCC Limited Mobile: 8607989718

Email: wenv.rolucknow@gmail.com Pin 226030


Code:

Full House No- Villa No.D/2/150, Sector-D,Pocket-2, Near Shopping,Village- ,Gram Panchayat-UTTAAR GAON, Block- MOHANLALGANJ,District- LUCKNOW,State-
Address:

Sample description
Source Raw water Village: UTTAAR GAON
of
Sample:

Gram UTTAAR GAON Block: MOHANLALGANJ


Panchayat:

District: LUCKNOW State: UTTAR PRADESH

Latitude: 24.51736513 Longitude: 83.04980350

Date & time of sample collection Date & time of sample received in lab Date & time of sample analysed Date & time of report generation

09.08.21 | 08:30 AM 10.08.21 | 01:15 PM 12.08.21 | 03:53 PM 12.08.21 | 09:26 PM

Test results
Report no 770346

Requirement Permissible limit (in absence of Test


S. Unit of (acceptable limit) as per alternate source) as per BIS result
No. Parameters tested measurement BIS 10500 10500 value Remarks

1 pH NA 6.5-8.5 No Relaxation 7.63

2 Turbidity NTU 1 5 159.67

3 TDS Milligram/liter 500 2000 136

Total Alkalinity (as


4 Calcium Milligram/liter 200 600 85
Carbonate)

https://neer.icmr.org.in/puser_final_report_print_download2.php?c2FtcGxlc19pZF9kZXRhaWxz=NzcwMzQ2 1/2
11/15/21, 12:56 PM WQMIS

Requirement Permissible limit (in absence of Test


S. Unit of (acceptable limit) as per alternate source) as per BIS result
No. Parameters tested measurement BIS 10500 10500 value Remarks

5 Chloride (as Cl) Milligram/liter 250 1000 17.25

6 Fluoride (as F) Milligram/liter 1 1.5 0.20

7 Nitrate (as NO3) Milligram/liter 45 No Relaxation 9.50

8 Sulphate (as SO4) Milligram/liter 200 400 32

Total Hardness (As


9 Milligram/liter 200 600 80
CaCO3)

10 Total Arsenic (As As) Milligram/liter 0.01 No Relaxation 0.001

11 Iron (As Fe) Milligram/liter 1 No Relaxation 1.20

Shall not be detectable


12 E. coli* CFU/100 ml No Relaxation 06
in any 100 ml sample

Total coliform Shall not be detectable


13 CFU/ 100 ml No Relaxation 00
bacteria* in any 100 ml sample

14 Colour Hazen units 5 15 0.00

Note:

1)*indicates parameters that are not NABL accredited.

2)This test results related to the sample tested above

3)The report shall not to be reproduced in full without approval of authority

4)This is the end of the report

Authorised signatory
Anil kumar

Jal Jeevan Mission aims at potable tap water supply to every home
Let's join hands to ensure drinking water is potable. It helps in preventing water borne diseases and improve public health.

Designed & Developed by BMI Division @ICMR. Copyright ©copy NJJM 2020

https://neer.icmr.org.in/puser_final_report_print_download2.php?c2FtcGxlc19pZF9kZXRhaWxz=NzcwMzQ2 2/2
I
J
L

E
K

A
B
D
H

C
G
5000
00
207.00
50
208.00
00
208.00
50
209.00
00

17
209.00
50
210.00
00
210.00
50
211.00
00
211.00
50
212.00
00
212.00
50

NCC LIMITED
213.00
00
213.00
50
214.00
00
214.00
50
215.00

Ceinsys Tech Ltd.


00
215.00
50
216.00
00
216.00
50
217.00
00
217.00
50
218.00
00
218.00

0
50

EXECUTIVE DIRECTOR,
00
00
219.00

00

0 0 0
0000

00 00 00
.00
.50
219.

8.5

7.0 7.5 8.0


17 17 17
17
179
179
180.

0
176.5000

00
16

9.5
21
00
219.00
00
218.50
14

00
218.00
00
217.50
00
217.00
LA
ND
00
216.50
SC
AP
G IN
00
216.00
RWRM
UTE- OP RO
00
215.50
T. 3
13
LA

00
215.00
00
214.50
NA

00
214.00
00
213.50
00
213.00
00
212.50
12
DOOR

W.C.900 T YARD
COUR 3795
1300X 3325X
W.C.900

You might also like