REPLANTEO DE CURVA VERTICAL
o Calculando las elevaciones para cada progresiva a lo
largo de las tangentes.

Elevaciones desde PCV a PIV:

Elev = Elev piv – (m*distancia)


Elev = k2 + 580 = 500 - (0.08 * 60m) = 495.20 m
Elev = k2 + 590 = 500 – (0.08 * 50m) = 496.00 m
Elev = k2 + 600 = 500 – (0.08 * 40m) = 496.80 m
Elev = k2 + 610 = 500 – (0.08 * 30m) = 497.60 m
Elev = k2 + 620 = 500 – (0.08 * 20m) = 498.40 m
Elev = k2 + 630 = 500 – (0.08 * 10m) = 499.20 m
Elev = k2 + 640 = 500 – (0.08 * 0m) = 500.00 m

2
Elevaciones desde PIV a PTV:

Elev k2 + 650 = 500 – (0.03 * 10m) = 499.70 m


Elev k2 + 660 = 500 – (0.03 * 20m) = 499.40 m
Elev k2 + 670 = 500 – (0.03 * 30m) =499.10 m
Elev k2 + 680 = 500 – (0.03 * 40m) = 498.80 m
Elev k2 + 690 = 500 – (0.03 * 50m) = 498.50 m
Elev k2 + 700 = 500 – (0.03 * 60m) = 498.20 m

o Calculando la corrección de elevación (y) para cada


progresiva.

𝐴 = |𝑆ₗ − 𝑆₂|
𝐴 = 8% − (−3%)
𝐴 = 8% + 3%
𝐴 = 11%

𝐴
𝑦 = 𝑥²( )
200 𝐿
11%
Para 𝑘2 + 580 = (0)2 ∗ =0𝑚
200(120)
11%
Para 𝑘2 + 590 = (10)2 ∗ = 0.05 𝑚
200(120)
11%
Para 𝑘2 + 600 = (20)2 ∗ = 0.18 𝑚
200(120)
11%
Para 𝑘2 + 610 = (30)2 ∗ = 0.41 𝑚
200(120)

11%
Para 𝑘2 + 620 = (40)2 ∗ = 0.73 𝑚
200(120)

3
11%
Para 𝑘2 + 630 = (50)2 ∗ = 0.15 𝑚
200(120)
11%
Para 𝑘2 + 640 = (60)2 ∗ = 1.65 𝑚
200(120)

De PIV a PTV

11%
Para 𝑘2 + 640 = (60)2 ∗ = 1.65 𝑚
200(120)
11%
Para 𝑘2 + 650 = (50)2 ∗ = 0.15 𝑚
200(120)

11%
Para 𝑘2 + 660 = (40)2 ∗ = 0.73 𝑚
200(120)
11%
Para 𝑘2 + 670 = (30)2 ∗ = 0.41 𝑚
200(120)
11%
Para 𝑘2 + 680 = (20)2 ∗ = 0.18 𝑚
200(120)
11%
Para 𝑘2 + 690 = (10)2 ∗ = 0.05 𝑚
200(120)

11%
Para 𝑘2 + 700 = (0)2 ∗ =0𝑚
200(120)

4
o Calculando cota en la rasante de la curva.

Cota rasante = (cota en tangente) – (y)

𝑘2 + 580 = (495.20𝑚) − (0) = 495.20 𝑚𝑒𝑡𝑟𝑜𝑠


𝑘2 + 590 = (496.00𝑚) − (0.05) = 495.95 𝑚𝑒𝑡𝑟𝑜𝑠
𝑘2 + 600 = (496.80𝑚) − (0.18) = 496.62 𝑚𝑒𝑡𝑟𝑜𝑠
𝑘2 + 610 = (497.60𝑚) − (0.41) = 497.19 𝑚𝑒𝑡𝑟𝑜𝑠
𝑘2 + 620 = (498.40𝑚) − (0.73) = 497.67 𝑚𝑒𝑡𝑟𝑜𝑠
𝑘2 + 630 = (499.20𝑚) − (0.15) = 499.05 𝑚𝑒𝑡𝑟𝑜𝑠
𝑘2 + 640 = (500.00𝑚) − (1.65) = 498.35 𝑚𝑒𝑡𝑟𝑜𝑠
𝑘2 + 650 = (499.70𝑚) − (0.15) = 499.55 𝑚𝑒𝑡𝑟𝑜𝑠
𝑘2 + 660 = (499.40𝑚) − (0.73) = 498.67 𝑚𝑒𝑡𝑟𝑜𝑠
𝑘2 + 670 = (499.10𝑚) − (0.41) = 498.69 𝑚𝑒𝑡𝑟𝑜𝑠
𝑘2 + 680 = (498.80𝑚) − (0.18) = 498.62 𝑚𝑒𝑡𝑟𝑜𝑠
𝑘2 + 690 = (498.50𝑚) − (0.05) = 498.45 𝑚𝑒𝑡𝑟𝑜𝑠
𝑘2 + 700 = (498.20) − (0) = 498.20 𝑚𝑒𝑡𝑟𝑜𝑠

o Verificando la Externa Vertical:

𝑘2 + 640 = (500.00𝑚) − (1.65) = 498.35 𝑚𝑒𝑡𝑟𝑜𝑠

𝐴𝐿
𝐸=
800

(11%)(120)
𝐸=
800

𝐸 = 1.65 𝑚𝑒𝑡𝑟𝑜𝑠

5
6
o CUADRO DE REPLANTEO DE CURVA VERTICAL

POGRESIVAS COTA EN TANGENTE CORRECCION COTA EN RASANTE


DE COTA (Y)
K2 + 580 495.20 METROS 0.00 METROS 495.20 METROS
K2 + 590 496.00 METROS 0.05 METROS 495.95 METROS
K2 + 600 496.80 METROS 0.18 METROS 496.62 METROS
K2 + 610 497.60 METROS 0.41 METROS 497.19 METROS
K2 + 620 498.40 METROS 0.73 METROS 497.67 METROS
K2 + 630 499.20 METROS 0.15 METROS 499.05 METROS
K2 + 640 PUNTO 500.00 METROS 1.65 METROS 498.35 METROS
MEDIO
K2 + 650 499.70 METROS 0.15 METROS 499.55 METROS
K2 + 660 499.40 METROS 0.73 METROS 498.67 METROS
K2 + 670 499.10 METROS 0.41 METROS 498.69 METROS
K2 + 680 498.80 METROS 0.18 METROS 498.62 METROS
K2 + 690 498.50 METROS 0.05 METROS 498.45 METROS
K2 + 700 498.20 METROS 0.00 METROS 498.20 METROS