Report Practice P3K - Safril Erwin Hidayat - 2004101010130 PDF
Report Practice P3K - Safril Erwin Hidayat - 2004101010130 PDF
Disusun Oleh :
SAFRIL MUHAMAD ERWIN HIDAYAT
2004101010130
Dosen Pembimbing :
Nama : Dr. Ir. Saiful Husin, M.T.
NIP : 195501011987021001
Dikerjakan Oleh :
SAFRIL MUHAMAD ERWIN HIDAYAT
2004101010130
( .......... )
Dosen Pembimbing
KATA PENGANTAR
Penulis i
Praktikum Perencanaan & Pengendalian Proyek Konstruksi
DAFTAR ISI
BAB I PENDAHULUAN
1.1 Deskripsi Umum Proyek ..................................................................................... 1
1.2 Lokasi Proyek ...................................................................................................... 1
BAB II TINJAUAN PUSTAKA
2.1 Metode Penjadwalan Proyek Konstruksi ............................................................ 3
2.1.1 Bar Chart.....................................................................................................3
2.1.2 Kurva S........................................................................................................4
2.2 Work Breakdown Structure (WBS)..................................................................... 5
2.3 Logika Ketergantungan ....................................................................................... 6
2.4 Durasi Pekerjaan.................................................................................................. 8
2.5 Float dan Lintasan Kritis......................................................................................8
2.5.1 Float.............................................................................................................8
2.5.2 Total Float...................................................................................................9
2.5.3 Lintasan Kritis.............................................................................................9
BAB III RENCANA DAN PENJADWALAN PROYEK
3.1 Rencana Work Breakdown Structure (WBS) .................................................... 11
3.2 Analisis Hubungan Ketergantungan Antar Pekerjaan ....................................... 17
3.3 Analisis Durasi Pekerjaan ................................................................................. 22
3.4 Penjadwalan Proyek .......................................................................................... 22
3.4.1 Bar Chart dan Kurva S..............................................................................22
3.4.2 Network Planning.....................................................................................22
3.5 Analisis Float.....................................................................................................23
3.6 Analisis Lintasan Kritis.....................................................................................28
BAB IV KESIMPULAN DAN SARAN
4.1 Kesimpulan ........................................................................................................ 33
4.2 Saran .................................................................................................................. 34
ii
BAB I
Praktikum Perencanaan & Pengendalian Proyek Konstruksi
BAB I
PENDAHULUAN
1
Praktikum Perencanaan & Pengendalian Proyek Konstruksi
BAB I
5
Praktikum Perencanaan & Pengendalian Proyek Konstruksi
BAB II
TINJAUAN PUSTAKA
Bar chart adalah sekumpulan daftar kegiatan yang disusun dalam kolom
arah vertikal, dan kolom arah horizontal menunjukkan skala waktu. Saat mulai dan
akhir dari sebuah kegiatan dapat terlihat dengan jelas sedangkan durasi kegiatan
digam- barkan oleh panjangnya diagram batang. Bagan balok terdiri atas sumbu x
dan sumbu y, sumbu y yang menyatakan uraian kegiatan atau paket kerja dari
lingkup proyek se- dangkan sumbu x menyatakan durasi atau waktu yang
dibutuhkan dalam setiap aktifi- tas dengan satuan harian, mingguan dan bulanan.
Langkah pertama dalam menyiapkan sebuah bar chart adalah dengan men-
gidentifikasi daftar aktivitas yang ingin ditampilkan dalam sebuah schedule. Setelah
durasi dari setiap aktifitas diestimasi dan ditentukan, plot durasi tersebut pada
sumbu horizontal yang ada dan tentukanlah skala waktu yang tepat, bisa dalam hari,
minggu, bulan atau hari kalender, sesuai dengan yang dibutuhkan. Bar chart
biasanya digunakan untuk mengetahui waktu penyelesaian pekerjaan sehingga
proyek dapat diselesaikan tepat waktu, serta untuk mengetahui alternatif jalur
penyelesaian peker- jaan dan waktu penyelesaian jika melalui jalur tersebut.
3
Praktikum Perencanaan & Pengendalian Proyek Konstruksi
2.1.2 Kurva S
Kurva–S adalah suatu kurva yang disusun untuk menunjukkan hubungan an-
tara nilai kumulatif biaya atau jam-orang (man-hours) yang telah digunakan atau
per- sentase penyelesaian pekerjaan terhadap waktu. Kurva S menggambarkan
hubungan antara item pekerjaan dengan waktu/jadwal pelaksanaan dan biaya
kumulatif peker- jaan. Kurva S dapat memberikan gambaran kemajuan pekerjaan
terhadap waktu, di- mana kemajuan pekerjaan direfleksikan terhadap bobot
penyerapan biaya.
Kurva S dapat digunakan pada tahap perencanaan dan pengendalian proyek.
Pada tahap perencanaan terdapat kurva S rencana sebagai pedoman/acuan
pelaksanaan proyek. Sementara pada tahap tahap pengendalian, dapat digunakan
kurva S aktual sebagai pembanding dengan kurva S rencana. Pada Kurva–S, sumbu
mendatar menun-jukkan waktu kalender, dan sumbu vertikal.
Untuk menentukan bobot pekerjaan, pendekatan yang dilakukan dapat berupa
perhitungan persentase berdasarkan biaya per item pekerjaan/kegiatan dibagi total
anggaran atau berdasarkan volume rencana dari komponen kegiatan ter- hadap
volume total kegiatan. Kurva S dapat digunakan pada tahap perencanaan dan
pengendalian proyek. Pada tahap perencanaan terdapat kurva S rencana sebagai pe-
doman/acuan pelaksanaan proyek. Sementara pada tahap tahap pengendalian, dapat
digunakan kurva S aktual sebagai pembanding dengan kurva S rencana. Kurve yang
berbentuk huruf ”S” tersebut lebih banyak terbentuk karena kelaziman dalam
pelaksanaan proyek yaitu:
a) Kemajuan pada awal-awalnya bergerak lambat.
4
Praktikum Perencanaan & Pengendalian Proyek Konstruksi
100%
Hari
Struktur WBS menyerupai gambar piramida di mana sebagai level satu yaitu
posisi puncak mengidentifikasikan proyek secara keseluruhan. Selanjutnya level 2
dibagi berdasarkan kriteria tertentu seperti bidang keahllian, lokasi peker- jaan,
atau urutan pelaksanaan pekerjaan. Demikian level-level di bawahnya disebut level
3, level 4, dan seterusnya sampai pada level terkecil yang disebut paket peker
jaan,yang disebut work package (WP) .
5
Praktikum Perencanaan & Pengendalian Proyek Konstruksi
6
Praktikum Perencanaan & Pengendalian Proyek Konstruksi
7
Praktikum Perencanaan & Pengendalian Proyek Konstruksi
Dari persamaan diatas dapat dilihat bahwa ada 3 faktor yang akan
mempengaruhi durasi pekerjaan, yaitu volume, produktivitas dan asumsi jumlah
pekerja. Tingkat produktivitas yang ditentukan berdasarkan nilai koefisien
tenaga kerja pada AHSP 2022, hubungan produktivitas dan koefesien adalah:
𝐼
𝑃=
𝐾
2.5.1 Float
8
Praktikum Perencanaan & Pengendalian Proyek Konstruksi
kurun waktu masing-masing kegiatan yang menjadi unsur proyek, karena adanya
kegiatan yang paralel. Bila jaringan kerja hanya mempunyai satu titik awal
(initial node) dan satu titik akhir (terminal node), maka jalur kritis juga berarti
jalur yang memiliki jumlah waktu penyelesaian terbesar/terlama, dan jumlah
waktu tersebut merupakan waktu proyek yang tercepat. Kadang dijumpai lebih
dari satu jalur kritis dalam sebuah jaringan kerja.
2.5.2 Total Float
Total float suatu kegiatan sama dengan waktu selesai paling akhir,
dikurangi waktu selesai paling awal, atau waktu mulai paling akhir dikurangi
waktu mulai paling awal dari kegiatan tersebut.
TF = LF – EF
= LS – ES
Arti penting dari float total adalah menunjukkan jumlah waktu yang
diperkenankan suatu kegiatan boleh ditunda, tanpa mempengaruhi jadwal
penyelesaian proyek secara keseluruhan.
2.5.3 Lintasan Kritis
Lintasan kristis (critical path) adalah lintasan terpanjang, dalam hal total
waktu, diantara semua lintasan yang ada pada suatu network diagram.
Lintasan kritis inilah yang akan menentukan total durasi tercepat untuk
menyelesaikan semua kegiatan pada proyek tersebut.
Kegiatan-kegiatan yang berada pada lintasan kristis adalah kegiatan kritis,
yang harus dapat diselesaikan sesuai dengan waktu yang telah direncanakan.
Apabila ada satu kegiatan saja yang pelaksanaannya terlambat atau tertunda, akan
menyebabkan keterlambatan penyelesaian proyek secara keseluruhan.
Pada tampilan Network Diagram, kegiatan-kegiatan yang berada pada
lintasan kritis secara otomatis sudah ditampilkan dengan format warna merah.
Tetapi tidak demikian pada tampilan Gantt Chart, dimana kegiatan kritis maupun
kegiatan non- kritis ditampilkan dengan format warna yang sama, jadi harus
terlebih dahulu diubah ke format critical task dan Warna balok yang
menggambarkan kegiatan kritis akan berubah, yang merupakan jalur kritis akan
keluar keterangan YES sedangkan yang tidak akan berketerangan NO.
9
BAB III
10
BAB III
RENCANA PENJADWALAN PROYEK
2 PEKERJAAN TANAH
2.1 PEKERJAAN GALIAN
2.1.1 Galian Tanah Pondasi Menerus
2.1.2 Galian Tanah Pondasi Tapak
2.2 PEKERJAAN TIMBUNAN
2.2.1 Urugan Kembali Bekas Galian
2.2.2 Pasir Urugan Bawah Pondasi
2.2.3 Pasir Urugan dibawah Lantai
2.2.4 Timbunan Tanah Dibawah Lantai
3 PEKERJAAN STRUKTUR
3.1 LANTAI 1
3.1.1 PEKERJAAN PONDASI TAPAK BETON BERTULANG
3.1.1.1 Lantai Kerja Pondasi Tapak Setempat ( K.175)
3.1.2 Pekerjaan Beton Bertulang Pondasi Tapak
3.1.2.1 Cor Beton K 250
3.1.2.2 Pembesian
3.1.2.3 Bekisting
3.1.3 Pekerjaan Pondasi Menerus
3.1.3.1 Anstamping / Pasangan Batu Kosong Tebal 10 Cm
3.1.3.2 Pasangan Pondasi Batu Gunung 1 PC : 4 PS
3.1.4 Sloof (30/40)
3.1.4.1 Pembesian
3.1.4.2 Bekisting
3.1.4.3 Cor Beton K 250
3.1.5 Sloof (15/20)
11
3.1.5.1 Pembesian
3.1.5.2 Bekisting
3.1.5.3 Cor Beton K 175
3.1.6 Kolom Uk. 30/40
3.1.6.1 Pembesian
3.1.6.2 Bekisting
3.1.6.3 Cor Beton K 250
3.1.7 Kolom Uk. 15/15
3.1.7.1 Pembesian
3.1.7.2 Bekisting
3.1.7.3 Cor Beton K 175
3.1.8 Balok Latai (13/13) Elevasi ± 2.23 m
3.1.8.1 Pembesian
3.1.8.2 Bekisting
3.1.8.3 Cor Beton K 175
3.1.9 Ring Balok Uk. 25/40 Elevasi ± 3.45 m
3.1.9.1 Pembesian
3.1.9.2 Bekisting
3.1.9.3 Cor Beton K 250
3.1.10 Ring Balok Uk. 15/20 Elevasi ± 3.45 m
3.1.10.1 Pembesian
3.1.10.2 Bekisting
3.1.10.3 Cor Beton K 175
3.1.11 Plat Tangga dan Plat Bordes Tebal 10cm
3.1.11.1 Pembesian
3.1.11.2 Bekisting
3.1.11.3 Cor Beton K 250
3.2 LANTAI 2
3.2.1 Kolom Uk. 30/30
3.2.1.1 Pembesian
3.2.1.2 Bekisting
3.2.1.3 Cor Beton K 250
3.2.2 Kolom Uk. 15/15
3.2.2.1 Pembesian
3.2.2.2 Bekisting
3.2.2.3 Cor Beton K 175
3.2.3 Balok Latai (13/13) Elevasi ± 6.23 m
3.2.3.1 Pembesian
3.2.3.2 Bekisting
3.2.3.3 Cor Beton K 175
3.2.4 Ring Balok Uk. 25/40 Elevasi ± 7.50 m
3.2.4.1 Pembesian
3.2.4.2 Bekisting
3.2.4.3 Cor Beton K 250
3.2.5 Ring Balok Uk. 15/20 Elevasi ±7.5 m
3.2.5.1 Pembesian
3.2.5.2 Bekisting
12
3.2.5.3 Cor Beton K 175
3.2.6 Plat Lantai Tebal 12cm
3.2.6.1 Pembesian
3.2.6.2 Bekisting
3.2.6.3 Cor Beton K 250
3.2.7 Plat dak dan Talang Beton
3.2.7.1 Pembesian
3.2.7.2 Bekisting
3.2.7.3 Cor Beton K 250
3.2.8 PEKERJAAN ATAP
3.2.8.1 Rangka kuda-kuda dan gording baja ringan Multytruss
4 PEKERJAAN ARSITEKTUR
4.1 LANTAI 1
4.1.1 Pekerjaan Dinding
4.1.2 Pekerjaan Lantai
4.1.2.1 Pekerjaan Beton Tumbuk Tebal 7 cm (K 125)
4.1.2.2 Pekerjaan Lantai Granite 60 x 60 Cm (Halus)
4.1.2.3 Pekerjaan Lantai Granite 60 x 60 Cm (Kasar)
4.1.2.4 Pekerjaan Lantai Keramik untuk Ruangan Wc/Km 20 X 20 Cm
4.1.2.5 Pasangan Dinding Keramik KM/WC 20 x 25 cm
4.1.3 Pekerjaan Pintu, Jendela, Ventilasi
Pintu Panel Kaca Tempered Glass 12mm + Aksesoris Lengkap
4.1.3.1
Terpasang (Type P1)
Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris Lengkap
4.1.3.2
Terpasang Sesuai Gambar ( Type P2)
Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris Lengkap
4.1.3.3
Terpasang Sesuai Gambar ( Type P5)
Kusen UPVC + Daun Pintu UPVC+ Aksesoris Lengkap
4.1.3.4
Terpasang Sesuai Gambar (Type P4)
Kusen UPVC + Daun Pintu UPVC+ Aksesoris Lengkap
4.1.3.5
Terpasang Sesuai Gambar (Type P3)
Kusen UPVC + Daun Jendela dan Ventilasi Kaca 5mm +
4.1.3.6
Aksesoris Lengkap Terpasang Sesuai Gambar (Type JV1)
Kusen UPVC + Daun Jendela dan Ventilasi Kaca 5mm +
4.1.3.7
Aksesoris Lengkap Terpasang Sesuai Gambar (Type J2)
Kusen UPVC + Daun ventilasi Kaca 5mm + Aksesoris Lengkap
4.1.3.8
Terpasang Sesuai Gambar (Type V2)
4.1.4 Pekerjaan Plafond
Pasang Plafon PVC/Fiber + Rangka + Aksesoris Lengkap
4.1.4.1
Terpasang Sesuai Gambar
4.1.5 Pekerjaan Pengecatan
4.1.5.1 Pengecatan Tembok dan Sealer 3x(L/D) Setara Vinilex
4.2 LANTAI 2
4.2.1 Pekerjaan Dinding
4.2.1.1 Pasangan Trasram Bata 1 PC : 2 PP
4.2.1.2 Pasangan Dinding Bata 1 PC : 4 PP
4.2.1.3 Plesteran Trasram Bata 1 PC : 2 PP
4.2.1.4 Plesteran Dinding Bata 1PC : 4 PP
13
4.2.1.5 Plasteran Beton 1 PC : 3 PP
4.2.1.6 Pesangan Batu Alam Tempel Susun Sirih + cat Vernis Batu Alam
4.2.2 Pekerjaan Lantai
4.2.2.1 Pekerjaan Beton Tumbuk Tebal 7 cm (K 125)
4.2.2.2 Pekerjaan Lantai Granite 60 x 60 Cm (Halus)
4.2.2.3 Pekerjaan Lantai Keramik untuk Ruangan Wc/Km 20 X 20 Cm
4.2.2.4 Pasangan Dinding Keramik KM/WC 20 x 25 cm
4.2.3 Pekerjaan Pintu, Jendela, Ventilasi
Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris Lengkap
4.2.3.1
Terpasang Sesuai Gambar ( Type P2)
Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris Lengkap
4.2.3.2
Terpasang Sesuai Gambar ( Type P5)
Kusen UPVC + Daun Pintu UPVC+ Aksesoris Lengkap
4.2.3.3
Terpasang Sesuai Gambar (Type P4)
Kusen UPVC + Daun Pintu UPVC+ Aksesoris Lengkap
4.2.3.4
Terpasang Sesuai Gambar (Type P3)
Kusen UPVC + Daun Jendela dan Ventilasi Kaca 5mm +
4.2.3.5
Aksesoris Lengkap Terpasang Sesuai Gambar (Type JV1)
Kusen UPVC + Daun Jendela dan Ventilasi Kaca 5mm +
4.2.3.6
Aksesoris Lengkap Terpasang Sesuai Gambar (Type J2)
Kusen UPVC + Daun ventilasi Kaca 5mm + Aksesoris Lengkap
4.2.3.7
Terpasang Sesuai Gambar (Type V2)
4.2.4 PEKERJAAN ATAP
4.2.4.1 Penutup Atap genteng Onduline
4.2.4.2 Rabung genteng Onduline
4.2.4.3 Lisplank Kalsiboard 300 X 2400 X 8 mm Bermotif
4.2.5 Pekerjaan Plafond
Pasang Plafon PVC/Fiber + Rangka + Aksesoris Lengkap
4.2.5.1
Terpasang Sesuai Gambar
4.2.6 Pekerjaan Pengecatan
4.2.6.1 Pengecatan Tembok dan Sealer 3x(L/D) Setara Vinilex
5 PEKERJAAN ELEKTRIKAL
Instlasi titik penerangan, instalasi termasuk kabel NYA 2,5 mm
5.1
dalam pipa PVC fitting lampu dan kelengkapan instalasi terpasang
Instalasi titik Stop kontak, instalasi termasuk kabel NYA 2,5 mm
5.2
dalam pipa PVC fitting lampu dan kelengkapan instalasi terpasang
5.3 Pemasangan Box Sekring
5.4 Pemasukan Arus Listrik 12 Ampere
5.5 LANTAI 1
5.5.1 Armatur
5.5.1.1 Lampu Downlight 23 watt + Accesori Lengkap Terpasang
5.5.1.2 Lampu RM TL 2X36 watt + Accesori Lengkap Terpasang
5.5.2 Saklar lampu Merk Setara Broco 2 seri
5.5.2.1 Sakalar 1 Seri setara Broco
5.5.2.2 Sakalar 2 Seri setara Broco
5.5.2.3 Stop Kontak
5.6 LANTAI 2
5.6.1 Armatur
14
5.6.1.1 Lampu Downlight 23 watt + Accesori Lengkap Terpasang
5.6.1.2 Lampu RM TL 2X36 watt + Accesori Lengkap Terpasang
6 PEKERJAAN MEKANIKAL
PEKERJAAN BESI, ALUMUNIUM, ORNAMEN DAN
6.1
DINDING COMPOSITE
Pekerjaan Almunium Composite Panel Setara Seven Type PVDF +
6.1.1
Rangka + Aksesoris Lengkap Terpasang Sesuai Gambar
Huruf Timbul Gedung IGD + Aksesoris Lengkap Terpasang Sesuai
6.1.2
Gambar (Bahan Stainless)
Huruf Timbul Gedung Utama + Aksesoris Lengkap Terpasang
6.1.3
Sesuai Gambar (Bahan Stainless)
Logo Puskesmas + Aksesoris Lengkap Terpasang Sesuai Gambar
6.1.4
(Bahan Stainless)
Reling Tangga Stainless + Aksesoris Lengkap Terpasang Sesuai
6.1.5
Gambar
Handrail (Pegangan Tangan) Stainless + Aksesoris Lengkap
6.1.6
Terpasang Sesuai Gambar
6.2 PEKERJAAN SALURAN DRAINASE
6.2.1 Galian Tanah Saluran
6.2.2 Pasangan Bata Dinding Saluran 1 PC : 2 PP
6.2.3 Pasangan Plasteran Bata Dinding Saluran 1 PC : 2 PP
6.2.4 Cor Lantai Saluran
6.2.5 Buis Beton Dia. 20 cm
6.2.6 Pemasangan Grill Saluran Bentuk Sesuai Gambar + Cat Meni Hitam
6.3 LANTAI 1
6.3.1 Pekerjaan Sanitasi
6.3.1.1 INSTALASI AIR KOTOR
6.3.1.1.1 Pasang Flordrain
6.3.1.1.2 Pipa SNI 3 Inch AW
6.3.1.2 INSTALASI AIR BERSIH
Memasang Wastafel + Keran Air + Pembungan Air Type Sifon
6.3.1.2.1
angsa Aksesoris Lengkap Terpasang Setara Toto
6.3.1.2.2 Pipa SNI 1/2 Inch AW
6.3.1.2.3 Pasang Pipa Air Sampai Ketitik Air
6.3.1.3 INSTALASI AIR HUJAN
6.3.1.3.1 Pipa SNI 2 1/2 Inch AW
6.3.1.4 INSTALASI KOTORAN
6.3.1.4.1 Pipa SNI 3 Inch AW
6.3.1.4.2 Septick Tank + Resapan Lengkap Terpasang
6.3.1.4.3 Pasang Kloset Duduk SetaraToto
6.4 LANTAI 2
6.4.1 Pekerjaan Sanitasi
6.4.1.1 INSTALASI AIR BERSIH
6.4.1.1.1 Bak Mandi Pyber Glass (60 x 60)
6.4.1.1.2 Pasang Kran Air 1/2"
6.4.1.1.3 Pipa SNI 1 Inch AW
6.4.1.1.4 Pipa SNI 1/2 Inch AW
15
6.4.1.1.5 Pasang Pipa Air Sampai Ketitik Air
6.4.1.2 INSTALASI AIR KOTOR
6.4.1.2.1 Pipa SNI 3 Inch AW
6.4.1.2.2 Pasang Flordrain
6.4.1.3 INSTALASI KOTORAN
6.4.1.3.1 Pipa SNI 3 Inch AW
6.4.1.3.2 Pasang Kloset Jongkok Setara American Standar
6.4.1.4 INSTALASI AIR HUJAN
6.4.1.4.1 Pipa SNI 2 1/2 Inch AW
7 PEKERJAAN FINISHING
7.1 Pekerjan Pot Bunga
7.1.1 Pasangan Dinding Bata 1PC : 4 PP
7.1.2 Plasteran Dinding Bata 1PC : 4 PP
7.1.3 Pesangan Batu Alam Tempel Susun Sirih + Cat Vernis Batu Alam
7.1.4 Relif Pot Bunga Sesuai Gambar
7.2 Pembentukan Relif Pada Kolom Lengkap Terpasang Sesuai Gambar
7.3 Pembentukan Relif Pada Dinding Lengkap Terpasang Sesuai Gambar
7.4 Pembersihan Akhir
16
Praktikum Perencanaan & Pengendalian Proyek Konstruksi
17
Praktikum Perencanaan & Pengendalian Proyek Konstruksi
18
Praktikum Perencanaan & Pengendalian Proyek Konstruksi
19
Praktikum Perencanaan & Pengendalian Proyek Konstruksi
20
Praktikum Perencanaan & Pengendalian Proyek Konstruksi
21
Praktikum Perencanaan & Pengendalian Proyek Konstruksi
0 Pembangunan Gedung IGD Puskesmas Blangpidie 142 days Mon 02/01/23 Tue 18/07/23 Mon 02/01/23 Tue 18/07/23 Mon 02/01/23 Tue 18/07/23 Yes 0 days 0 days
1 PEKERJAAN PERSIAPAN 6 days Mon 02/01/23 Mon 09/01/23 Mon 02/01/23 Tue 18/07/23 Mon 02/01/23 Mon 09/01/23 Yes 0 days 0 days
1.1 Papan Nama Proyek Uk. 90 x120 1 day Mon 02/01/23 Mon 02/01/23 Mon 02/01/23 Mon 02/01/23 Mon 02/01/23 Mon 02/01/23 Yes 0 days 0 days
1.2 Administrasi/Dokumentasi dan Pelaporan 1 day 2SS Mon 02/01/23 Mon 02/01/23 Tue 18/07/23 Tue 18/07/23 Mon 02/01/23 Mon 02/01/23 No 141 days 141 days
1.3 Direksi Keet/sewa 6 days 2SS Mon 02/01/23 Mon 09/01/23 Tue 11/07/23 Tue 18/07/23 Mon 02/01/23 Mon 09/01/23 No 136 days 136 days
1.4 Perlengkapan P3k 1 day 2SS Mon 02/01/23 Mon 02/01/23 Tue 18/07/23 Tue 18/07/23 Mon 02/01/23 Mon 02/01/23 No 141 days 141 days
1.5 Pengukuran dan Pemasangan Bouwplank 2 days 2SS Mon 02/01/23 Tue 03/01/23 Mon 17/07/23 Tue 18/07/23 Mon 02/01/23 Tue 03/01/23 No 140 days 140 days
1.6 Pekerjaan Kesehatan dan Keselamatan Kerja 1 day 2SS Mon 02/01/23 Mon 02/01/23 Tue 18/07/23 Tue 18/07/23 Mon 02/01/23 Mon 02/01/23 No 141 days 141 days
1.7 Pagar pelindung proyek 2 days 2SS Mon 02/01/23 Tue 03/01/23 Mon 02/01/23 Tue 03/01/23 Mon 02/01/23 Tue 03/01/23 Yes 0 days 0 days
2 PEKERJAAN TANAH 36 days Wed 04/01/23 Wed 22/02/23 Wed 04/01/23 Tue 18/07/23 Wed 04/01/23 Wed 22/02/23 Yes 0 days 0 days
2.1 PEKERJAAN GALIAN 8 days Wed 04/01/23 Fri 13/01/23 Wed 04/01/23 Tue 11/07/23 Wed 04/01/23 Fri 13/01/23 Yes 0 days 0 days
2.1.1 Galian Tanah Pondasi Tapak 4 days 8 Wed 04/01/23 Mon 09/01/23 Wed 04/01/23 Mon 09/01/23 Wed 04/01/23 Mon 09/01/23 Yes 0 days 0 days
2.1.2 Galian Tanah Pondasi Menerus 4 days 11 Tue 10/01/23 Fri 13/01/23 Thu 06/07/23 Tue 11/07/23 Tue 10/01/23 Fri 13/01/23 No 0 days 127 days
2.2 PEKERJAAN TIMBUNAN 28 days Mon 16/01/23 Wed 22/02/23 Thu 04/05/23 Tue 18/07/23 Mon 16/01/23 Wed 22/02/23 No 78 days 78 days
2.2.1 Urugan Kembali Bekas Galian 4 days 188 Wed 01/02/23 Mon 06/02/23 Thu 04/05/23 Tue 09/05/23 Wed 01/02/23 Mon 06/02/23 No 0 days 66 days
2.2.2 Pasir Urugan Bawah Pondasi Menerus 5 days 12 Mon 16/01/23 Fri 20/01/23 Wed 12/07/23 Tue 18/07/23 Mon 16/01/23 Fri 20/01/23 No 127 days 127 days
2.2.3 Pasir Urugan dibawah Lantai 3 days 17 Mon 20/02/23 Wed 22/02/23 Tue 23/05/23 Thu 25/05/23 Mon 20/02/23 Wed 22/02/23 No 0 days 66 days
2.2.4 Timbunan Tanah Dibawah Lantai 9 days 14 Tue 07/02/23 Fri 17/02/23 Wed 10/05/23 Mon 22/05/23 Tue 07/02/23 Fri 17/02/23 No 0 days 66 days
3 PEKERJAAN STRUKTUR 88 days Mon 02/01/23 Wed 03/05/23 Tue 10/01/23 Tue 18/07/23 Mon 02/01/23 Wed 03/05/23 No 6 days 6 days
3.1 LANTAI 1 1 day Mon 02/01/23 Mon 02/01/23 Tue 18/07/23 Tue 18/07/23 Mon 02/01/23 Mon 02/01/23 No 141 days 141 days
3.2 PEKERJAAN PONDASI TAPAK BETON BERTULANG 51 days Tue 10/01/23 Tue 21/03/23 Tue 10/01/23 Tue 18/07/23 Tue 10/01/23 Tue 21/03/23 Yes 0 days 0 days
3.2.1 Lantai Kerja Pondasi Tapak Setempat ( K.175) 1 day 11 Tue 10/01/23 Tue 10/01/23 Tue 10/01/23 Tue 10/01/23 Tue 10/01/23 Tue 10/01/23 Yes 0 days 0 days
3.2.2 Pekerjaan Beton Bertulang Pondasi Tapak 9 days Wed 11/01/23 Mon 23/01/23 Wed 11/01/23 Mon 23/01/23 Wed 11/01/23 Mon 23/01/23 Yes 0 days 0 days
3.2.2.1 Cor Beton K 250 2 days 25 Fri 20/01/23 Mon 23/01/23 Fri 20/01/23 Mon 23/01/23 Fri 20/01/23 Mon 23/01/23 Yes 0 days 0 days
3.2.2.2 Pembesian 5 days 21 Wed 11/01/23 Tue 17/01/23 Wed 11/01/23 Tue 17/01/23 Wed 11/01/23 Tue 17/01/23 Yes 0 days 0 days
3.2.2.3 Bekisting 2 days 24 Wed 18/01/23 Thu 19/01/23 Wed 18/01/23 Thu 19/01/23 Wed 18/01/23 Thu 19/01/23 Yes 0 days 0 days
3.2.3 Pekerjaan Pondasi Menerus 5 days Tue 24/01/23 Mon 30/01/23 Tue 24/01/23 Mon 30/01/23 Tue 24/01/23 Mon 30/01/23 Yes 0 days 0 days
3.2.3.1 Anstamping / Pasangan Batu Kosong Tebal 10 Cm 2 days 23 Tue 24/01/23 Wed 25/01/23 Tue 24/01/23 Wed 25/01/23 Tue 24/01/23 Wed 25/01/23 Yes 0 days 0 days
3.2.3.2 Pasangan Pondasi Batu Gunung 1 PC : 4 PS 3 days 27 Thu 26/01/23 Mon 30/01/23 Thu 26/01/23 Mon 30/01/23 Thu 26/01/23 Mon 30/01/23 Yes 0 days 0 days
3.2.4 Sloof (30/40) 7 days Tue 31/01/23 Wed 08/02/23 Tue 31/01/23 Wed 08/02/23 Tue 31/01/23 Wed 08/02/23 Yes 0 days 0 days
3.2.4.1 Pembesian 2 days 28 Tue 31/01/23 Wed 01/02/23 Tue 31/01/23 Wed 01/02/23 Tue 31/01/23 Wed 01/02/23 Yes 0 days 0 days
3.2.4.2 Bekisting 3 days 30 Thu 02/02/23 Mon 06/02/23 Thu 02/02/23 Mon 06/02/23 Thu 02/02/23 Mon 06/02/23 Yes 0 days 0 days
3.2.4.3 Cor Beton K 250 2 days 31 Tue 07/02/23 Wed 08/02/23 Tue 07/02/23 Wed 08/02/23 Tue 07/02/23 Wed 08/02/23 Yes 0 days 0 days
3.2.5 Sloof (15/20) 3 days Tue 31/01/23 Thu 02/02/23 Fri 14/07/23 Tue 18/07/23 Tue 31/01/23 Thu 02/02/23 No 118 days 118 days
3.2.5.1 Pembesian 1 day 28 Tue 31/01/23 Tue 31/01/23 Fri 14/07/23 Fri 14/07/23 Tue 31/01/23 Tue 31/01/23 No 0 days 118 days
3.2.5.2 Bekisting 1 day 34 Wed 01/02/23 Wed 01/02/23 Mon 17/07/23 Mon 17/07/23 Wed 01/02/23 Wed 01/02/23 No 0 days 118 days
3.2.5.3 Cor Beton K 175 1 day 35 Thu 02/02/23 Thu 02/02/23 Tue 18/07/23 Tue 18/07/23 Thu 02/02/23 Thu 02/02/23 No 118 days 118 days
3.2.6 Kolom Uk. 30/40 6 days Thu 09/02/23 Thu 16/02/23 Thu 09/02/23 Thu 16/02/23 Thu 09/02/23 Thu 16/02/23 Yes 0 days 0 days
3.2.6.1 Pembesian 2 days 32 Thu 09/02/23 Fri 10/02/23 Thu 09/02/23 Fri 10/02/23 Thu 09/02/23 Fri 10/02/23 Yes 0 days 0 days
3.2.6.2 Bekisting 2 days 38 Mon 13/02/23 Tue 14/02/23 Mon 13/02/23 Tue 14/02/23 Mon 13/02/23 Tue 14/02/23 Yes 0 days 0 days
3.2.6.3 Cor Beton K 250 2 days 39 Wed 15/02/23 Thu 16/02/23 Wed 15/02/23 Thu 16/02/23 Wed 15/02/23 Thu 16/02/23 Yes 0 days 0 days
3.2.7 Kolom Uk. 15/15 3 days Fri 17/02/23 Tue 21/02/23 Fri 14/07/23 Tue 18/07/23 Fri 17/02/23 Tue 21/02/23 No 105 days 105 days
3.2.7.1 Pembesian 1 day 40 Fri 17/02/23 Fri 17/02/23 Fri 14/07/23 Fri 14/07/23 Fri 17/02/23 Fri 17/02/23 No 0 days 105 days
3.2.7.2 Bekisting 1 day 42 Mon 20/02/23 Mon 20/02/23 Mon 17/07/23 Mon 17/07/23 Mon 20/02/23 Mon 20/02/23 No 0 days 105 days
3.2.7.3 Cor Beton K 175 1 day 43 Tue 21/02/23 Tue 21/02/23 Tue 18/07/23 Tue 18/07/23 Tue 21/02/23 Tue 21/02/23 No 105 days 105 days
23
Praktikum Perencanaan & Pengendalian Proyek Konstruksi
Total
WBS Item Pekerjaan Duration Predecessors Start Finish Late Start Late Finish Early Start Early Finish Critical Free Slack
Slack
3.2.8 Balok Latai (13/13) Elevasi ± 2.23 m 3 days Tue 28/02/23 Thu 02/03/23 Fri 14/07/23 Tue 18/07/23 Tue 28/02/23 Thu 02/03/23 No 98 days 98 days
3.2.8.1 Pembesian 1 day 47 Thu 02/03/23 Thu 02/03/23 Tue 18/07/23 Tue 18/07/23 Thu 02/03/23 Thu 02/03/23 No 98 days 98 days
3.2.8.2 Bekisting 2 days 96 Tue 28/02/23 Wed 01/03/23 Fri 14/07/23 Mon 17/07/23 Tue 28/02/23 Wed 01/03/23 No 0 days 98 days
3.2.8.3 Cor Beton K 175 1 day 47 Thu 02/03/23 Thu 02/03/23 Tue 18/07/23 Tue 18/07/23 Thu 02/03/23 Thu 02/03/23 No 98 days 98 days
3.2.9 Balok Uk. 25/40 Elevasi ± 3.45 m 5 days Tue 28/02/23 Mon 06/03/23 Wed 01/03/23 Tue 18/07/23 Tue 28/02/23 Mon 06/03/23 No 1 day 1 day
3.2.9.1 Pembesian 2 days 96 Tue 28/02/23 Wed 01/03/23 Mon 17/07/23 Tue 18/07/23 Tue 28/02/23 Wed 01/03/23 No 99 days 99 days
3.2.9.2 Bekisting 2 days 54 Wed 01/03/23 Thu 02/03/23 Wed 01/03/23 Thu 02/03/23 Wed 01/03/23 Thu 02/03/23 Yes 0 days 0 days
3.2.9.3 Cor Beton K 250 2 days 51 Fri 03/03/23 Mon 06/03/23 Fri 03/03/23 Mon 06/03/23 Fri 03/03/23 Mon 06/03/23 Yes 0 days 0 days
3.2.10 Ring Balok Uk. 15/20 Elevasi ± 3.45 m 3 days Tue 28/02/23 Thu 02/03/23 Tue 28/02/23 Tue 18/07/23 Tue 28/02/23 Thu 02/03/23 Yes 0 days 0 days
3.2.10.1 Pembesian 1 day 96 Tue 28/02/23 Tue 28/02/23 Tue 28/02/23 Tue 28/02/23 Tue 28/02/23 Tue 28/02/23 Yes 0 days 0 days
3.2.10.2 Bekisting 1 day 54 Wed 01/03/23 Wed 01/03/23 Mon 17/07/23 Mon 17/07/23 Wed 01/03/23 Wed 01/03/23 No 0 days 98 days
3.2.10.3 Cor Beton K 175 1 day 55 Thu 02/03/23 Thu 02/03/23 Tue 18/07/23 Tue 18/07/23 Thu 02/03/23 Thu 02/03/23 No 98 days 98 days
3.2.11 Plat Tangga dan Plat Bordes Tebal 10cm 3 days Fri 17/03/23 Tue 21/03/23 Fri 17/03/23 Tue 21/03/23 Fri 17/03/23 Tue 21/03/23 Yes 0 days 0 days
3.2.11.1 Pembesian 1 day 85 Fri 17/03/23 Fri 17/03/23 Fri 17/03/23 Fri 17/03/23 Fri 17/03/23 Fri 17/03/23 Yes 0 days 0 days
3.2.11.2 Bekisting 1 day 58 Mon 20/03/23 Mon 20/03/23 Mon 20/03/23 Mon 20/03/23 Mon 20/03/23 Mon 20/03/23 Yes 0 days 0 days
3.2.11.3 Cor Beton K 250 1 day 59 Tue 21/03/23 Tue 21/03/23 Tue 21/03/23 Tue 21/03/23 Tue 21/03/23 Tue 21/03/23 Yes 0 days 0 days
3.3 LANTAI 2 42 days Tue 07/03/23 Wed 03/05/23 Tue 07/03/23 Tue 18/07/23 Tue 07/03/23 Wed 03/05/23 Yes 0 days 0 days
3.3.1 Kolom Uk. 30/30 6 days Wed 22/03/23 Wed 29/03/23 Wed 22/03/23 Wed 29/03/23 Wed 22/03/23 Wed 29/03/23 Yes 0 days 0 days
3.3.1.1 Pembesian 2 days 60 Wed 22/03/23 Thu 23/03/23 Wed 22/03/23 Thu 23/03/23 Wed 22/03/23 Thu 23/03/23 Yes 0 days 0 days
3.3.1.2 Bekisting 2 days 63 Fri 24/03/23 Mon 27/03/23 Fri 24/03/23 Mon 27/03/23 Fri 24/03/23 Mon 27/03/23 Yes 0 days 0 days
3.3.1.3 Cor Beton K 250 2 days 64 Tue 28/03/23 Wed 29/03/23 Tue 28/03/23 Wed 29/03/23 Tue 28/03/23 Wed 29/03/23 Yes 0 days 0 days
3.3.2 Kolom Uk. 15/15 4 days Thu 30/03/23 Tue 04/04/23 Thu 13/07/23 Tue 18/07/23 Thu 30/03/23 Tue 04/04/23 No 75 days 75 days
3.3.2.1 Pembesian 1 day 65 Thu 30/03/23 Thu 30/03/23 Thu 13/07/23 Thu 13/07/23 Thu 30/03/23 Thu 30/03/23 No 0 days 75 days
3.3.2.2 Bekisting 2 days 67 Fri 31/03/23 Mon 03/04/23 Fri 14/07/23 Mon 17/07/23 Fri 31/03/23 Mon 03/04/23 No 0 days 75 days
3.3.2.3 Cor Beton K 175 1 day 68 Tue 04/04/23 Tue 04/04/23 Tue 18/07/23 Tue 18/07/23 Tue 04/04/23 Tue 04/04/23 No 75 days 75 days
3.3.3 Balok Latai (13/13) Elevasi ± 6.23 m 2 days Tue 11/04/23 Wed 12/04/23 Mon 17/07/23 Tue 18/07/23 Tue 11/04/23 Wed 12/04/23 No 69 days 69 days
3.3.3.1 Pembesian 1 day 123 Tue 11/04/23 Tue 11/04/23 Tue 18/07/23 Tue 18/07/23 Tue 11/04/23 Tue 11/04/23 No 70 days 70 days
3.3.3.2 Bekisting 1 day 123 Tue 11/04/23 Tue 11/04/23 Mon 17/07/23 Mon 17/07/23 Tue 11/04/23 Tue 11/04/23 No 0 days 69 days
3.3.3.3 Cor Beton K 175 1 day 72 Wed 12/04/23 Wed 12/04/23 Tue 18/07/23 Tue 18/07/23 Wed 12/04/23 Wed 12/04/23 No 69 days 69 days
3.3.4 Ring Balok Uk. 25/40 Elevasi ± 7.50 m 6 days Tue 11/04/23 Tue 18/04/23 Tue 11/04/23 Tue 18/04/23 Tue 11/04/23 Tue 18/04/23 Yes 0 days 0 days
3.3.4.1 Pembesian 2 days 123 Tue 11/04/23 Wed 12/04/23 Tue 11/04/23 Wed 12/04/23 Tue 11/04/23 Wed 12/04/23 Yes 0 days 0 days
3.3.4.2 Bekisting 2 days 75 Thu 13/04/23 Fri 14/04/23 Thu 13/04/23 Fri 14/04/23 Thu 13/04/23 Fri 14/04/23 Yes 0 days 0 days
3.3.4.3 Cor Beton K 250 2 days 76 Mon 17/04/23 Tue 18/04/23 Mon 17/04/23 Tue 18/04/23 Mon 17/04/23 Tue 18/04/23 Yes 0 days 0 days
3.3.5 Ring Balok Uk. 15/20 Elevasi ±7.5 m 3 days Tue 11/04/23 Thu 13/04/23 Fri 14/07/23 Tue 18/07/23 Tue 11/04/23 Thu 13/04/23 No 68 days 68 days
3.3.5.1 Pembesian 1 day 123 Tue 11/04/23 Tue 11/04/23 Fri 14/07/23 Fri 14/07/23 Tue 11/04/23 Tue 11/04/23 No 0 days 68 days
3.3.5.2 Bekisting 1 day 79 Wed 12/04/23 Wed 12/04/23 Mon 17/07/23 Mon 17/07/23 Wed 12/04/23 Wed 12/04/23 No 0 days 68 days
3.3.5.3 Cor Beton K 175 1 day 80 Thu 13/04/23 Thu 13/04/23 Tue 18/07/23 Tue 18/07/23 Thu 13/04/23 Thu 13/04/23 No 68 days 68 days
3.3.6 Plat Lantai Tebal 12cm 8 days Tue 07/03/23 Thu 16/03/23 Tue 07/03/23 Thu 16/03/23 Tue 07/03/23 Thu 16/03/23 Yes 0 days 0 days
3.3.6.1 Pembesian 4 days 84 Thu 09/03/23 Tue 14/03/23 Thu 09/03/23 Tue 14/03/23 Thu 09/03/23 Tue 14/03/23 Yes 0 days 0 days
3.3.6.2 Bekisting 2 days 52 Tue 07/03/23 Wed 08/03/23 Tue 07/03/23 Wed 08/03/23 Tue 07/03/23 Wed 08/03/23 Yes 0 days 0 days
3.3.6.3 Cor Beton K 250 2 days 83 Wed 15/03/23 Thu 16/03/23 Wed 15/03/23 Thu 16/03/23 Wed 15/03/23 Thu 16/03/23 Yes 0 days 0 days
3.3.7 Plat dak dan Talang Beton 3 days Wed 19/04/23 Fri 21/04/23 Wed 19/04/23 Fri 21/04/23 Wed 19/04/23 Fri 21/04/23 Yes 0 days 0 days
3.3.7.1 Pembesian 1 day 77 Wed 19/04/23 Wed 19/04/23 Wed 19/04/23 Wed 19/04/23 Wed 19/04/23 Wed 19/04/23 Yes 0 days 0 days
3.3.7.2 Bekisting 1 day 87 Thu 20/04/23 Thu 20/04/23 Thu 20/04/23 Thu 20/04/23 Thu 20/04/23 Thu 20/04/23 Yes 0 days 0 days
3.3.7.3 Cor Beton K 250 1 day 88 Fri 21/04/23 Fri 21/04/23 Fri 21/04/23 Fri 21/04/23 Fri 21/04/23 Fri 21/04/23 Yes 0 days 0 days
3.3.8 PEKERJAAN ATAP 8 days Mon 24/04/23 Wed 03/05/23 Mon 24/04/23 Wed 03/05/23 Mon 24/04/23 Wed 03/05/23 Yes 0 days 0 days
3.3.8.1 Rangka kuda-kuda dan gording baja ringan Multytruss 8 days 89 Mon 24/04/23 Wed 03/05/23 Mon 24/04/23 Wed 03/05/23 Mon 24/04/23 Wed 03/05/23 Yes 0 days 0 days
24
Praktikum Perencanaan & Pengendalian Proyek Konstruksi
Total
WBS Item Pekerjaan Duration Predecessors Start Finish Late Start Late Finish Early Start Early Finish Critical Free Slack
Slack
4 PEKERJAAN ARSITEKTUR 88 days Fri 17/02/23 Tue 20/06/23 Fri 17/02/23 Tue 18/07/23 Fri 17/02/23 Tue 20/06/23 Yes 0 days 0 days
4.1 LANTAI 1 42 days Fri 17/02/23 Mon 17/04/23 Fri 17/02/23 Tue 18/07/23 Fri 17/02/23 Mon 17/04/23 Yes 0 days 0 days
4.1.1 Pekerjaan Dinding 18 days Fri 17/02/23 Tue 14/03/23 Fri 17/02/23 Tue 18/07/23 Fri 17/02/23 Tue 14/03/23 Yes 0 days 0 days
4.1.1.1 Pasangan Trasram Bata 1 PC : 2 PP 1 day 40 Fri 17/02/23 Fri 17/02/23 Fri 17/02/23 Fri 17/02/23 Fri 17/02/23 Fri 17/02/23 Yes 0 days 0 days
4.1.1.2 Pasangan Dinding Bata 1 PC : 4 PP 6 days 95 Mon 20/02/23 Mon 27/02/23 Mon 20/02/23 Mon 27/02/23 Mon 20/02/23 Mon 27/02/23 Yes 0 days 0 days
4.1.1.3 Plesteran Trasram Bata 1 PC : 2 PP 1 day 184 Mon 27/02/23 Mon 27/02/23 Tue 30/05/23 Tue 30/05/23 Mon 27/02/23 Mon 27/02/23 No 0 days 66 days
4.1.1.4 Plesteran Dinding Bata 1PC : 4 PP 9 days 97 Tue 28/02/23 Fri 10/03/23 Wed 31/05/23 Mon 12/06/23 Tue 28/02/23 Fri 10/03/23 No 0 days 66 days
4.1.1.5 Plasteran Beton 1 PC : 3 PP 7 days 97 Tue 28/02/23 Wed 08/03/23 Mon 10/07/23 Tue 18/07/23 Tue 28/02/23 Wed 08/03/23 No 94 days 94 days
4.1.1.6 Pesangan Batu Alam Tempel Susun Sirih + cat Vernis Batu Alam 2 days 98 Mon 13/03/23 Tue 14/03/23 Mon 17/07/23 Tue 18/07/23 Mon 13/03/23 Tue 14/03/23 No 90 days 90 days
4.1.2 Pekerjaan Lantai 27 days Thu 23/02/23 Fri 31/03/23 Fri 26/05/23 Mon 03/07/23 Thu 23/02/23 Fri 31/03/23 No 66 days 66 days
4.1.2.1 Pekerjaan Beton Tumbuk Tebal 7 cm (K 125) 1 day 16 Thu 23/02/23 Thu 23/02/23 Fri 26/05/23 Fri 26/05/23 Thu 23/02/23 Thu 23/02/23 No 0 days 66 days
4.1.2.2 Pekerjaan Lantai Granite 60 x 60 Cm (Halus) 5 days 117 Fri 17/03/23 Thu 23/03/23 Mon 19/06/23 Fri 23/06/23 Fri 17/03/23 Thu 23/03/23 No 0 days 66 days
4.1.2.3 Pekerjaan Lantai Granite 60 x 60 Cm (Kasar) 3 days 103 Fri 24/03/23 Tue 28/03/23 Mon 26/06/23 Wed 28/06/23 Fri 24/03/23 Tue 28/03/23 No 0 days 66 days
4.1.2.4 Pekerjaan Lantai Keramik untuk Ruangan Wc/Km 20 X 20 Cm 1 day 104 Wed 29/03/23 Wed 29/03/23 Thu 29/06/23 Thu 29/06/23 Wed 29/03/23 Wed 29/03/23 No 0 days 66 days
4.1.2.5 Pasangan Dinding Keramik KM/WC 20 x 25 cm 2 days 105 Thu 30/03/23 Fri 31/03/23 Fri 30/06/23 Mon 03/07/23 Thu 30/03/23 Fri 31/03/23 No 0 days 66 days
4.1.3 Pekerjaan Pintu, Jendela, Ventilasi 38 days Thu 23/02/23 Mon 17/04/23 Mon 17/07/23 Tue 18/07/23 Thu 23/02/23 Mon 17/04/23 No 66 days 66 days
4.1.3.1 Pintu Panel Kaca Tempered Glass 12mm + Aksesoris Lengkap Terpasang (Type 1 day
P1) 160 Fri 14/04/23 Fri 14/04/23 Tue 18/07/23 Tue 18/07/23 Fri 14/04/23 Fri 14/04/23 No 67 days 67 days
4.1.3.2 Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris Lengkap Terpasang Sesuai Gambar
2 days ( Type P2)
160 Fri 14/04/23 Mon 17/04/23 Mon 17/07/23 Tue 18/07/23 Fri 14/04/23 Mon 17/04/23 No 66 days 66 days
4.1.3.3 Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris Lengkap Terpasang Sesuai Gambar
1 day ( Type P5)
16 Thu 23/02/23 Thu 23/02/23 Tue 18/07/23 Tue 18/07/23 Thu 23/02/23 Thu 23/02/23 No 103 days 103 days
4.1.3.4 Kusen UPVC + Daun Pintu UPVC+ Aksesoris Lengkap Terpasang Sesuai Gambar 1 day
(Type P4) 160 Fri 14/04/23 Fri 14/04/23 Tue 18/07/23 Tue 18/07/23 Fri 14/04/23 Fri 14/04/23 No 67 days 67 days
4.1.3.5 Kusen UPVC + Daun Pintu UPVC+ Aksesoris Lengkap Terpasang Sesuai Gambar 1 day
(Type P3) 160 Fri 14/04/23 Fri 14/04/23 Tue 18/07/23 Tue 18/07/23 Fri 14/04/23 Fri 14/04/23 No 67 days 67 days
4.1.3.6 Kusen UPVC + Daun Jendela dan Ventilasi Kaca 5mm + Aksesoris Lengkap Terpasang
2 days Sesuai Gambar
160 (TypeFriJV1)
14/04/23 Mon 17/04/23 Mon 17/07/23 Tue 18/07/23 Fri 14/04/23 Mon 17/04/23 No 66 days 66 days
4.1.3.7 Kusen UPVC + Daun Jendela dan Ventilasi Kaca 5mm + Aksesoris Lengkap Terpasang
1 day Sesuai Gambar
16 (TypeThu
J2)23/02/23 Thu 23/02/23 Tue 18/07/23 Tue 18/07/23 Thu 23/02/23 Thu 23/02/23 No 103 days 103 days
4.1.3.8 Kusen UPVC + Daun ventilasi Kaca 5mm + Aksesoris Lengkap Terpasang Sesuai1 day
Gambar (Type160
V2) Fri 14/04/23 Fri 14/04/23 Tue 18/07/23 Tue 18/07/23 Fri 14/04/23 Fri 14/04/23 No 67 days 67 days
4.1.4 Pekerjaan Plafond 4 days Mon 13/03/23 Thu 16/03/23 Tue 13/06/23 Fri 16/06/23 Mon 13/03/23 Thu 16/03/23 No 66 days 66 days
4.1.4.1 Pasang Plafon PVC/Fiber + Rangka + Aksesoris Lengkap Terpasang Sesuai Gambar
4 days 98 Mon 13/03/23 Thu 16/03/23 Tue 13/06/23 Fri 16/06/23 Mon 13/03/23 Thu 16/03/23 No 0 days 66 days
4.1.5 Pekerjaan Pengecatan 4 days Mon 03/04/23 Thu 06/04/23 Tue 04/07/23 Fri 07/07/23 Mon 03/04/23 Thu 06/04/23 No 66 days 66 days
4.1.5.1 Pengecatan Tembok dan Sealer 3x(L/D) Setara Vinilex 4 days 106 Mon 03/04/23 Thu 06/04/23 Tue 04/07/23 Fri 07/07/23 Mon 03/04/23 Thu 06/04/23 No 0 days 66 days
4.2 LANTAI 2 59 days Thu 30/03/23 Tue 20/06/23 Thu 30/03/23 Tue 18/07/23 Thu 30/03/23 Tue 20/06/23 Yes 0 days 0 days
4.2.1 Pekerjaan Dinding 43 days Thu 30/03/23 Mon 29/05/23 Thu 30/03/23 Tue 18/07/23 Thu 30/03/23 Mon 29/05/23 Yes 0 days 0 days
4.2.1.1 Pasangan Trasram Bata 1 PC : 2 PP 2 days 65 Thu 30/03/23 Fri 31/03/23 Thu 30/03/23 Fri 31/03/23 Thu 30/03/23 Fri 31/03/23 Yes 0 days 0 days
4.2.1.2 Pasangan Dinding Bata 1 PC : 4 PP 6 days 122 Mon 03/04/23 Mon 10/04/23 Mon 03/04/23 Mon 10/04/23 Mon 03/04/23 Mon 10/04/23 Yes 0 days 0 days
4.2.1.3 Plesteran Trasram Bata 1 PC : 2 PP 1 day 91 Thu 04/05/23 Thu 04/05/23 Thu 04/05/23 Thu 04/05/23 Thu 04/05/23 Thu 04/05/23 Yes 0 days 0 days
4.2.1.4 Plesteran Dinding Bata 1PC : 4 PP 14 days 124 Fri 05/05/23 Wed 24/05/23 Fri 05/05/23 Wed 24/05/23 Fri 05/05/23 Wed 24/05/23 Yes 0 days 0 days
4.2.1.5 Plasteran Beton 1 PC : 3 PP 3 days 125 Thu 25/05/23 Mon 29/05/23 Fri 14/07/23 Tue 18/07/23 Thu 25/05/23 Mon 29/05/23 No 36 days 36 days
4.2.1.6 Pesangan Batu Alam Tempel Susun Sirih + cat Vernis Batu Alam 2 days 125 Thu 25/05/23 Fri 26/05/23 Mon 17/07/23 Tue 18/07/23 Thu 25/05/23 Fri 26/05/23 No 37 days 37 days
4.2.2 Pekerjaan Lantai 10 days Thu 25/05/23 Wed 07/06/23 Tue 30/05/23 Tue 18/07/23 Thu 25/05/23 Wed 07/06/23 No 3 days 3 days
4.2.2.1 Pekerjaan Beton Tumbuk Tebal 7 cm (K 125) 2 days 125 Thu 25/05/23 Fri 26/05/23 Mon 17/07/23 Tue 18/07/23 Thu 25/05/23 Fri 26/05/23 No 37 days 37 days
4.2.2.2 Pekerjaan Lantai Granite 60 x 60 Cm (Halus) 5 days 145 Tue 30/05/23 Mon 05/06/23 Tue 30/05/23 Mon 05/06/23 Tue 30/05/23 Mon 05/06/23 Yes 0 days 0 days
4.2.2.3 Pekerjaan Lantai Keramik untuk Ruangan Wc/Km 20 X 20 Cm 1 day 130 Tue 06/06/23 Tue 06/06/23 Tue 06/06/23 Tue 06/06/23 Tue 06/06/23 Tue 06/06/23 Yes 0 days 0 days
4.2.2.4 Pasangan Dinding Keramik KM/WC 20 x 25 cm 1 day 131 Wed 07/06/23 Wed 07/06/23 Wed 07/06/23 Wed 07/06/23 Wed 07/06/23 Wed 07/06/23 Yes 0 days 0 days
4.2.3 Pekerjaan Pintu, Jendela, Ventilasi 1 day Tue 20/06/23 Tue 20/06/23 Tue 20/06/23 Tue 18/07/23 Tue 20/06/23 Tue 20/06/23 Yes 0 days 0 days
4.2.3.1 Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris Lengkap Terpasang Sesuai Gambar
1 day ( Type P2)
168 Tue 20/06/23 Tue 20/06/23 Tue 18/07/23 Tue 18/07/23 Tue 20/06/23 Tue 20/06/23 No 20 days 20 days
4.2.3.2 Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris Lengkap Terpasang Sesuai Gambar
1 day ( Type P5)
168 Tue 20/06/23 Tue 20/06/23 Tue 18/07/23 Tue 18/07/23 Tue 20/06/23 Tue 20/06/23 No 20 days 20 days
4.2.3.3 Kusen UPVC + Daun Pintu UPVC+ Aksesoris Lengkap Terpasang Sesuai Gambar 1 day
(Type P4) 168 Tue 20/06/23 Tue 20/06/23 Tue 20/06/23 Tue 20/06/23 Tue 20/06/23 Tue 20/06/23 Yes 0 days 0 days
4.2.3.4 Kusen UPVC + Daun Jendela dan Ventilasi Kaca 5mm + Aksesoris Lengkap Terpasang
1 day Sesuai Gambar
168 (TypeTueJV1)
20/06/23 Tue 20/06/23 Tue 18/07/23 Tue 18/07/23 Tue 20/06/23 Tue 20/06/23 No 20 days 20 days
4.2.3.5 Kusen UPVC + Daun Jendela dan Ventilasi Kaca 5mm + Aksesoris Lengkap Terpasang
1 day Sesuai Gambar
168 (TypeTueJ2)20/06/23 Tue 20/06/23 Tue 18/07/23 Tue 18/07/23 Tue 20/06/23 Tue 20/06/23 No 20 days 20 days
4.2.3.6 Kusen UPVC + Daun ventilasi Kaca 5mm + Aksesoris Lengkap Terpasang Sesuai1 day
Gambar (Type168
V2) Tue 20/06/23 Tue 20/06/23 Tue 18/07/23 Tue 18/07/23 Tue 20/06/23 Tue 20/06/23 No 20 days 20 days
25
Praktikum Perencanaan & Pengendalian Proyek Konstruksi
Total
WBS Item Pekerjaan Duration Predecessors Start Finish Late Start Late Finish Early Start Early Finish Critical Free Slack
Slack
4.2.4 PEKERJAAN ATAP 10 days Thu 04/05/23 Wed 17/05/23 Wed 05/07/23 Tue 18/07/23 Thu 04/05/23 Wed 17/05/23 No 44 days 44 days
4.2.4.1 Penutup Atap genteng Onduline 5 days 91 Thu 04/05/23 Wed 10/05/23 Wed 05/07/23 Tue 11/07/23 Thu 04/05/23 Wed 10/05/23 No 0 days 44 days
4.2.4.2 Rabung genteng Onduline 2 days 141 Thu 11/05/23 Fri 12/05/23 Wed 12/07/23 Thu 13/07/23 Thu 11/05/23 Fri 12/05/23 No 0 days 44 days
4.2.4.3 Lisplank Kayu 2/20 cm 3 days 142 Mon 15/05/23 Wed 17/05/23 Fri 14/07/23 Tue 18/07/23 Mon 15/05/23 Wed 17/05/23 No 44 days 44 days
4.2.5 Pekerjaan Plafond 3 days Thu 25/05/23 Mon 29/05/23 Thu 25/05/23 Mon 29/05/23 Thu 25/05/23 Mon 29/05/23 Yes 0 days 0 days
4.2.5.1 Pasang Plafon PVC/Fiber + Rangka + Aksesoris Lengkap Terpasang Sesuai Gambar3 days 125 Thu 25/05/23 Mon 29/05/23 Thu 25/05/23 Mon 29/05/23 Thu 25/05/23 Mon 29/05/23 Yes 0 days 0 days
4.2.6 Pekerjaan Pengecatan 4 days Thu 08/06/23 Tue 13/06/23 Thu 08/06/23 Tue 13/06/23 Thu 08/06/23 Tue 13/06/23 Yes 0 days 0 days
4.2.6.1 Pengecatan Tembok dan Sealer 3x(L/D) Setara Vinilex 4 days 132 Thu 08/06/23 Tue 13/06/23 Thu 08/06/23 Tue 13/06/23 Thu 08/06/23 Tue 13/06/23 Yes 0 days 0 days
5 PEKERJAAN ELEKTRIKAL 52 days Fri 07/04/23 Mon 19/06/23 Wed 14/06/23 Tue 18/07/23 Fri 07/04/23 Mon 19/06/23 No 21 days 21 days
5.1 Instlasi titik penerangan, instalasi termasuk kabel NYA 2,5 mm dalam pipa PVC fitting
1 day lampu dan119
kelengkapanFriinstalasi
07/04/23 terpasang
Fri 07/04/23 Tue 18/07/23 Tue 18/07/23 Fri 07/04/23 Fri 07/04/23 No 72 days 72 days
5.2 Instalasi titik Stop kontak, instalasi termasuk kabel NYA 2,5 mm dalam pipa PVC1fitting
day lampu dan119
kelengkapan instalasi terpasang
Fri 07/04/23 Fri 07/04/23 Mon 10/07/23 Mon 10/07/23 Fri 07/04/23 Fri 07/04/23 No 0 days 66 days
5.3 Pemasangan Box Sekring 1 day 119 Fri 07/04/23 Fri 07/04/23 Tue 18/07/23 Tue 18/07/23 Fri 07/04/23 Fri 07/04/23 No 72 days 72 days
5.4 Pemasukan Arus Listrik 12 Ampere 1 day 119 Fri 07/04/23 Fri 07/04/23 Tue 18/07/23 Tue 18/07/23 Fri 07/04/23 Fri 07/04/23 No 72 days 72 days
5.5 LANTAI 1 4 days Mon 10/04/23 Thu 13/04/23 Tue 11/07/23 Tue 18/07/23 Mon 10/04/23 Thu 13/04/23 No 66 days 66 days
5.5.1 Armatur 2 days Mon 10/04/23 Tue 11/04/23 Tue 11/07/23 Wed 12/07/23 Mon 10/04/23 Tue 11/04/23 No 66 days 66 days
5.5.1.1 Lampu Downlight 23 watt + Accesori Lengkap Terpasang 1 day 150 Mon 10/04/23 Mon 10/04/23 Tue 11/07/23 Tue 11/07/23 Mon 10/04/23 Mon 10/04/23 No 0 days 66 days
5.5.1.2 Lampu RM TL 2X36 watt + Accesori Lengkap Terpasang 1 day 155 Tue 11/04/23 Tue 11/04/23 Wed 12/07/23 Wed 12/07/23 Tue 11/04/23 Tue 11/04/23 No 0 days 66 days
5.5.2 Saklar lampu Merk Setara Broco 2 seri 2 days Wed 12/04/23 Thu 13/04/23 Thu 13/07/23 Tue 18/07/23 Wed 12/04/23 Thu 13/04/23 No 66 days 66 days
5.5.2.1 Sakalar 1 Seri setara Broco 1 day 156 Wed 12/04/23 Wed 12/04/23 Tue 18/07/23 Tue 18/07/23 Wed 12/04/23 Wed 12/04/23 No 69 days 69 days
5.5.2.2 Sakalar 2 Seri setara Broco 1 day 156 Wed 12/04/23 Wed 12/04/23 Thu 13/07/23 Thu 13/07/23 Wed 12/04/23 Wed 12/04/23 No 0 days 66 days
5.5.2.3 Stop Kontak 1 day 159 Thu 13/04/23 Thu 13/04/23 Fri 14/07/23 Fri 14/07/23 Thu 13/04/23 Thu 13/04/23 No 0 days 66 days
5.6 LANTAI 2 4 days Wed 14/06/23 Mon 19/06/23 Wed 14/06/23 Tue 18/07/23 Wed 14/06/23 Mon 19/06/23 Yes 0 days 0 days
5.6.1 Armatur 2 days Wed 14/06/23 Thu 15/06/23 Wed 14/06/23 Thu 15/06/23 Wed 14/06/23 Thu 15/06/23 Yes 0 days 0 days
5.6.1.1 Lampu Downlight 23 watt + Accesori Lengkap Terpasang 1 day 147 Wed 14/06/23 Wed 14/06/23 Wed 14/06/23 Wed 14/06/23 Wed 14/06/23 Wed 14/06/23 Yes 0 days 0 days
5.6.1.2 Lampu RM TL 2X36 watt + Accesori Lengkap Terpasang 1 day 163 Thu 15/06/23 Thu 15/06/23 Thu 15/06/23 Thu 15/06/23 Thu 15/06/23 Thu 15/06/23 Yes 0 days 0 days
5.6.2 Saklar lampu Merk Setara Broco 2 seri 2 days Fri 16/06/23 Mon 19/06/23 Fri 16/06/23 Tue 18/07/23 Fri 16/06/23 Mon 19/06/23 Yes 0 days 0 days
5.6.2.1 Sakalar 1 Seri setara Broco 1 day 164 Fri 16/06/23 Fri 16/06/23 Tue 18/07/23 Tue 18/07/23 Fri 16/06/23 Fri 16/06/23 No 22 days 22 days
5.6.2.2 Sakalar 2 Seri setara Broco 1 day 164 Fri 16/06/23 Fri 16/06/23 Fri 16/06/23 Fri 16/06/23 Fri 16/06/23 Fri 16/06/23 Yes 0 days 0 days
5.6.2.3 Stop Kontak 1 day 167 Mon 19/06/23 Mon 19/06/23 Mon 19/06/23 Mon 19/06/23 Mon 19/06/23 Mon 19/06/23 Yes 0 days 0 days
6 PEKERJAAN MEKANIKAL 132 days Mon 02/01/23 Tue 04/07/23 Wed 03/05/23 Tue 18/07/23 Mon 02/01/23 Tue 04/07/23 No 10 days 10 days
6.1 PEKERJAAN SALURAN DRAINASE 10 days Wed 21/06/23 Tue 04/07/23 Wed 21/06/23 Tue 04/07/23 Wed 21/06/23 Tue 04/07/23 Yes 0 days 0 days
6.1.1 Pasangan Bata Dinding Saluran 1 PC : 2 PP 2 days 136 Wed 21/06/23 Thu 22/06/23 Wed 21/06/23 Thu 22/06/23 Wed 21/06/23 Thu 22/06/23 Yes 0 days 0 days
6.1.2 Pasangan Plasteran Bata Dinding Saluran 1 PC : 2 PP 2 days 171 Fri 23/06/23 Mon 26/06/23 Fri 23/06/23 Mon 26/06/23 Fri 23/06/23 Mon 26/06/23 Yes 0 days 0 days
6.1.3 Cor Lantai Saluran 2 days 172 Tue 27/06/23 Wed 28/06/23 Tue 27/06/23 Wed 28/06/23 Tue 27/06/23 Wed 28/06/23 Yes 0 days 0 days
6.1.4 Buis Beton Dia. 20 cm 2 days 173 Thu 29/06/23 Fri 30/06/23 Thu 29/06/23 Fri 30/06/23 Thu 29/06/23 Fri 30/06/23 Yes 0 days 0 days
6.1.5 Pemasangan Grill Saluran Bentuk Sesuai Gambar + Cat Meni Hitam 2 days 174 Mon 03/07/23 Tue 04/07/23 Mon 03/07/23 Tue 04/07/23 Mon 03/07/23 Tue 04/07/23 Yes 0 days 0 days
6.2 LANTAI 1 96 days Mon 02/01/23 Mon 15/05/23 Wed 03/05/23 Tue 18/07/23 Mon 02/01/23 Mon 15/05/23 No 46 days 46 days
6.2.1 Pekerjaan Sanitasi 1 day Mon 02/01/23 Mon 02/01/23 Tue 18/07/23 Tue 18/07/23 Mon 02/01/23 Mon 02/01/23 No 141 days 141 days
6.2.2 INSTALASI AIR KOTOR 3 days Thu 30/03/23 Mon 03/04/23 Tue 18/07/23 Tue 18/07/23 Thu 30/03/23 Mon 03/04/23 No 76 days 76 days
6.2.2.1 Pasang Floordrain 1 day 105 Thu 30/03/23 Thu 30/03/23 Tue 18/07/23 Tue 18/07/23 Thu 30/03/23 Thu 30/03/23 No 78 days 78 days
6.2.2.2 Pipa SNI 3 Inch AW 1 day 106 Mon 03/04/23 Mon 03/04/23 Tue 18/07/23 Tue 18/07/23 Mon 03/04/23 Mon 03/04/23 No 76 days 76 days
6.2.3 INSTALASI AIR BERSIH 27 days Fri 24/02/23 Mon 03/04/23 Mon 29/05/23 Tue 18/07/23 Fri 24/02/23 Mon 03/04/23 No 66 days 66 days
6.2.3.1 Memasang Wastafel + Keran Air + Pembungan Air Type Sifon angsa Aksesoris1Lengkap
day Terpasang
106 Setara Toto
Mon 03/04/23 Mon 03/04/23 Tue 18/07/23 Tue 18/07/23 Mon 03/04/23 Mon 03/04/23 No 76 days 76 days
6.2.3.2 Pipa SNI 1/2 Inch AW 1 day 102 Fri 24/02/23 Fri 24/02/23 Tue 18/07/23 Tue 18/07/23 Fri 24/02/23 Fri 24/02/23 No 102 days 102 days
6.2.3.3 Pasang Pipa Air Sampai Ketitik Air 1 day 102 Fri 24/02/23 Fri 24/02/23 Mon 29/05/23 Mon 29/05/23 Fri 24/02/23 Fri 24/02/23 No 0 days 66 days
26
Praktikum Perencanaan & Pengendalian Proyek Konstruksi
Total
WBS Item Pekerjaan Duration Predecessors Start Finish Late Start Late Finish Early Start Early Finish Critical Free Slack
Slack
6.2.4 INSTALASI AIR HUJAN 1 day Mon 15/05/23 Mon 15/05/23 Tue 18/07/23 Tue 18/07/23 Mon 15/05/23 Mon 15/05/23 No 46 days 46 days
6.2.4.1 Pipa SNI 2 1/2 Inch AW 1 day 142 Mon 15/05/23 Mon 15/05/23 Tue 18/07/23 Tue 18/07/23 Mon 15/05/23 Mon 15/05/23 No 46 days 46 days
6.2.5 INSTALASI KOTORAN 43 days Tue 31/01/23 Thu 30/03/23 Wed 03/05/23 Tue 18/07/23 Tue 31/01/23 Thu 30/03/23 No 66 days 66 days
6.2.5.1 Pipa SNI 3 Inch AW 1 day 28 Tue 31/01/23 Tue 31/01/23 Wed 03/05/23 Wed 03/05/23 Tue 31/01/23 Tue 31/01/23 No 0 days 66 days
6.2.5.2 Septick Tank + Resapan Lengkap Terpasang 1 day 188 Wed 01/02/23 Wed 01/02/23 Tue 18/07/23 Tue 18/07/23 Wed 01/02/23 Wed 01/02/23 No 119 days 119 days
6.2.5.3 Pasang Kloset Duduk SetaraToto 1 day 105 Thu 30/03/23 Thu 30/03/23 Tue 18/07/23 Tue 18/07/23 Thu 30/03/23 Thu 30/03/23 No 78 days 78 days
6.3 LANTAI 2 114 days Mon 02/01/23 Thu 08/06/23 Tue 18/07/23 Tue 18/07/23 Mon 02/01/23 Thu 08/06/23 No 28 days 28 days
6.3.1 Pekerjaan Sanitasi 1 day Mon 02/01/23 Mon 02/01/23 Tue 18/07/23 Tue 18/07/23 Mon 02/01/23 Mon 02/01/23 No 141 days 141 days
6.3.2 INSTALASI AIR BERSIH 64 days Mon 13/03/23 Thu 08/06/23 Tue 18/07/23 Tue 18/07/23 Mon 13/03/23 Thu 08/06/23 No 28 days 28 days
6.3.2.1 Bak Mandi Pyber Glass (60 x 60) 1 day 132 Thu 08/06/23 Thu 08/06/23 Tue 18/07/23 Tue 18/07/23 Thu 08/06/23 Thu 08/06/23 No 28 days 28 days
6.3.2.2 Pasang Kran Air 1/2" 1 day 98 Mon 13/03/23 Mon 13/03/23 Tue 18/07/23 Tue 18/07/23 Mon 13/03/23 Mon 13/03/23 No 91 days 91 days
6.3.2.3 Pipa SNI 1 Inch AW 1 day 98 Mon 13/03/23 Mon 13/03/23 Tue 18/07/23 Tue 18/07/23 Mon 13/03/23 Mon 13/03/23 No 91 days 91 days
6.3.2.4 Pipa SNI 1/2 Inch AW 1 day 98 Mon 13/03/23 Mon 13/03/23 Tue 18/07/23 Tue 18/07/23 Mon 13/03/23 Mon 13/03/23 No 91 days 91 days
6.3.2.5 Pasang Pipa Air Sampai Ketitik Air 1 day 98 Mon 13/03/23 Mon 13/03/23 Tue 18/07/23 Tue 18/07/23 Mon 13/03/23 Mon 13/03/23 No 91 days 91 days
6.3.3 INSTALASI AIR KOTOR 64 days Mon 13/03/23 Thu 08/06/23 Tue 18/07/23 Tue 18/07/23 Mon 13/03/23 Thu 08/06/23 No 28 days 28 days
6.3.3.1 Pipa SNI 3 Inch AW 1 day 98 Mon 13/03/23 Mon 13/03/23 Tue 18/07/23 Tue 18/07/23 Mon 13/03/23 Mon 13/03/23 No 91 days 91 days
6.3.3.2 Pasang Flordrain 1 day 132 Thu 08/06/23 Thu 08/06/23 Tue 18/07/23 Tue 18/07/23 Thu 08/06/23 Thu 08/06/23 No 28 days 28 days
6.3.4 INSTALASI KOTORAN 19 days Mon 15/05/23 Thu 08/06/23 Tue 18/07/23 Tue 18/07/23 Mon 15/05/23 Thu 08/06/23 No 28 days 28 days
6.3.4.1 Pipa SNI 3 Inch AW 1 day 142 Mon 15/05/23 Mon 15/05/23 Tue 18/07/23 Tue 18/07/23 Mon 15/05/23 Mon 15/05/23 No 46 days 46 days
6.3.4.2 Pasang Kloset Jongkok Setara American Standar 1 day 132 Thu 08/06/23 Thu 08/06/23 Tue 18/07/23 Tue 18/07/23 Thu 08/06/23 Thu 08/06/23 No 28 days 28 days
6.3.5 INSTALASI AIR HUJAN 1 day Mon 15/05/23 Mon 15/05/23 Tue 18/07/23 Tue 18/07/23 Mon 15/05/23 Mon 15/05/23 No 46 days 46 days
6.3.5.1 Pipa SNI 2 1/2 Inch AW 1 day 142 Mon 15/05/23 Mon 15/05/23 Tue 18/07/23 Tue 18/07/23 Mon 15/05/23 Mon 15/05/23 No 46 days 46 days
7 PEKERJAAN FINISHING 10 days Wed 05/07/23 Tue 18/07/23 Wed 05/07/23 Tue 18/07/23 Wed 05/07/23 Tue 18/07/23 Yes 0 days 0 days
PEKERJAAN BESI, ALUMUNIUM, ORNAMEN DAN DINDING
7.1 5 days Wed 05/07/23 Tue 11/07/23 Wed 05/07/23 Tue 18/07/23 Wed 05/07/23 Tue 11/07/23 Yes 0 days 0 days
COMPOSITE
7.1.1 Terpasang Sesuai
3 days Lengkap 175
Pekerjaan Almunium Composite Panel Setara Seven Type PVDF + Rangka + Aksesoris Gambar
Wed 05/07/23 Fri 07/07/23 Wed 05/07/23 Fri 07/07/23 Wed 05/07/23 Fri 07/07/23 Yes 0 days 0 days
7.1.2 Huruf Timbul Gedung IGD + Aksesoris Lengkap Terpasang Sesuai Gambar (Bahan Stainless)
2 days 209 Mon 10/07/23 Tue 11/07/23 Mon 17/07/23 Tue 18/07/23 Mon 10/07/23 Tue 11/07/23 No 5 days 5 days
7.1.3 Huruf Timbul Gedung Utama + Aksesoris Lengkap Terpasang Sesuai Gambar (Bahan2 daysStainless) 209 Mon 10/07/23 Tue 11/07/23 Mon 17/07/23 Tue 18/07/23 Mon 10/07/23 Tue 11/07/23 No 5 days 5 days
7.1.4 Logo Puskesmas + Aksesoris Lengkap Terpasang Sesuai Gambar (Bahan Stainless)2 days 209 Mon 10/07/23 Tue 11/07/23 Mon 17/07/23 Tue 18/07/23 Mon 10/07/23 Tue 11/07/23 No 5 days 5 days
7.1.5 Reling Tangga Stainless + Aksesoris Lengkap Terpasang Sesuai Gambar 2 days 209 Mon 10/07/23 Tue 11/07/23 Mon 17/07/23 Tue 18/07/23 Mon 10/07/23 Tue 11/07/23 No 5 days 5 days
7.1.6 2 days
Handrail (Pegangan Tangan) Stainless + Aksesoris Lengkap Terpasang Sesuai Gambar 209 Mon 10/07/23 Tue 11/07/23 Mon 10/07/23 Tue 11/07/23 Mon 10/07/23 Tue 11/07/23 Yes 0 days 0 days
7.2 Pekerjan Pot Bunga 5 days Wed 12/07/23 Tue 18/07/23 Wed 12/07/23 Tue 18/07/23 Wed 12/07/23 Tue 18/07/23 Yes 0 days 0 days
7.2.1 Pasangan Dinding Bata 1PC : 4 PP 2 days 214 Wed 12/07/23 Thu 13/07/23 Wed 12/07/23 Thu 13/07/23 Wed 12/07/23 Thu 13/07/23 Yes 0 days 0 days
7.2.2 Plasteran Dinding Bata 1PC : 4 PP 1 day 216 Fri 14/07/23 Fri 14/07/23 Tue 18/07/23 Tue 18/07/23 Fri 14/07/23 Fri 14/07/23 No 2 days 2 days
7.2.3 Pesangan Batu Alam Tempel Susun Sirih + Cat Vernis Batu Alam 1 day 216 Fri 14/07/23 Fri 14/07/23 Tue 18/07/23 Tue 18/07/23 Fri 14/07/23 Fri 14/07/23 No 2 days 2 days
7.2.4 Relif Pot Bunga Sesuai Gambar 2 days 216 Fri 14/07/23 Mon 17/07/23 Fri 14/07/23 Mon 17/07/23 Fri 14/07/23 Mon 17/07/23 Yes 0 days 0 days
7.3 Pembersihan Akhir 1 day 219 Tue 18/07/23 Tue 18/07/23 Tue 18/07/23 Tue 18/07/23 Tue 18/07/23 Tue 18/07/23 Yes 0 days 0 days
Float dan lintasan kritis pada network planning ditandai dengan simbol FS-TS untuk float dan simbol warna merah dengan jumlah
pekerjan untuk lintasan kritis dapat dilihat pada lampian.
27
Praktikum Perencanaan & Pengendalian Proyek Konstruksi
28
Praktikum Perencanaan & Pengendalian Proyek Konstruksi
29
Praktikum Perencanaan & Pengendalian Proyek Konstruksi
30
Praktikum Perencanaan & Pengendalian Proyek Konstruksi
31
Praktikum Perencanaan & Pengendalian Proyek Konstruksi
32
BAB IV
Praktikum Perencanaan & Pengendalian Proyek Konstruksi
BAB IV
KESIMPULAN DAN SARAN
4.1 Kesimpulan
Dari hasil analisis pembahasan yang telah diuraikan pada bab sebelumnya,
dapat ditarik kesimpulan sebagai berikut:
• Hasil perencanaan dapat disimpulkan bahwa upaya peningkatan kualitas
perencanaan dan pengendalian jadwal pada suatu proyek akan
mengakibatkan meningkatnya hasil kinerja waktu suatu proyek itu sendiri.
Dalam tulisan ini peningkatan kualitas dapat dicapai dengan menggunakan
suatu program Microsoft Project 2021, karena dengan menggunakan aplikasi
tersebut dapat dengan cepat melakukan penjadwalan ulang jika suatu
pekerjaan mengalami keterlambatan dari jadwal yang telah direncanakan.
• Logika ketergantungan antar pekerjaan memperlihatkan alur pekerjaan
hingga selesainya suatu proyek. Pekerjaan-pekerjaan tersebut saling
berhubungan dengan kata lain satu pekerjaan akan bergantung dengan
pekerjaan lainnya. Terdapat tiga macam konstrain yang dipakai dalam logika
ketergantungan :
a) Finish to Start (FS)
• Lintasan kritis (critical path) adalah lintasan terpanjang, dalam hal total
waktu, diantara semua lintasan yang ada pada suatu network diagram.
Lintasan kritis inilah yang akan menentukan total durasi tercepat untuk
menyelesaikan semua kegiatan pada proyek tersebut.
• Dari hasil perencanaan jadwal oleh penulis dengan menggunakan Microsoft
Project 2021 diperoleh hasil 142 hari kerja, waktu penyelesaian proyek.
33
Praktikum Perencanaan & Pengendalian Proyek Konstruksi
4.2 Saran
34
Praktikum Perencanaan & Pengendalian Proyek Konstruksi
DAFTAR PUSTAKA
35
LAMPIRAN
Praktikum Perencanaan & Pengendalian Proyek Konstruksi
a. Gambar Proyek
36
Praktikum Perencanaan & Pengendalian Proyek Konstruksi
37
Praktikum Perencanaan & Pengendalian Proyek Konstruksi
38
Pa ge 39
Pa ge 40
RENCANA ANGGARAN BIAYA
WBS URAIAN PEKERJAAN ANALISA VOLUME SAT HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
1 PEKERJAAN PERSIAPAN
1.1 Papan Nama Proyek Uk. 90 x120 Taksir 1,00 UNIT Rp 250.000,00 Rp 250.000,00
1.2 Administrasi/Dokumentasi dan Pelaporan Taksir 1,00 LS Rp 300.000,00 Rp 300.000,00
1.3 Direksi Keet/sewa AHSP PU : A.2.2.1.6 24,00 M3 Rp 451.808,55 Rp 10.843.405,20
1.4 Perlengkapan P3k Taksir 1,00 PAKET Rp 500.000,00 Rp 500.000,00
1.5 Pengukuran dan Pemasangan Bouwplank AHSP PU : A.2.2.1.4 68,00 M2 Rp 907.396,00 Rp 61.702.928,00
1.6 Sistem Manajemen Kesehatan dan Keselamatan Kerja ANSMK3 1,00 PAKET Rp 4.961.100,00 Rp 4.961.100,00
1.7 Pagar pelindung proyek AHSP PU : A.2.2.1.2 52,50 M2 Rp 271.860,00 Rp 14.272.650,00
Sub Jumlah Rp 92.830.083,20
2 PEKERJAAN TANAH
2.1 PEKERJAAN GALIAN
2.1.1 Galian Tanah Pondasi Tapak AHSP PU : A.2.3.1.1 70,20 M3 Rp 80.960,00 Rp 5.683.392,00
2.1.2 Galian Tanah Pondasi Menerus AHSP PU : A.2.3.1.2 71,30 M3 Rp 99.153,00 Rp 7.069.608,90
Sub Jumlah Rp 12.753.000,90
2.2 PEKERJAAN TIMBUNAN
2.2.1 Urugan Kembali Bekas Galian AHSP PU : A.2.3.1.9 35,38 M3 Rp 58.420,00 Rp 2.066.609,62
2.2.2 Pasir Urugan Bawah Pondasi Menerus AHSP PU : A.2.3.1.11 71,30 M3 Rp 232.484,00 Rp 16.576.109,20
2.2.3 Pasir Urugan dibawah Lantai AHSP PU : A.2.3.1.11 20,48 M3 Rp 232.484,00 Rp 4.760.109,90
2.2.4 Timbunan Tanah Dibawah Lantai AHSP PU : A.2.3.1.15 266,18 M3 Rp 192.620,00 Rp 51.270.628,50
Sub Jumlah Rp 74.673.457,22
3 PEKERJAAN STRUKTUR
3.1 LANTAI 1
3.1.1 PEKERJAAN PONDASI TAPAK BETON BERTULANG
3.1.1.1 Lantai Kerja Pondasi Tapak Setempat ( K.175) AHSP PU : A.4.1.1.5 3,78 M3 Rp 1.106.050,19 Rp 4.180.869,74
3.1.2 Pekerjaan Beton Bertulang Pondasi Tapak
3.1.2.1 Cor Beton K 250 AHSP PU : A.4.1.1.8 21,60 M3 Rp 1.205.727,51 Rp 26.043.714,20
3.1.2.2 Pembesian AHSP PU : A.4.1.1.17a 7348,56 KG Rp 18.676,23 Rp 137.243.445,14
3.1.2.3 Bekisting AHSP PU : A.4.1.1.20 115,20 M2 Rp 116.725,00 Rp 13.446.720,00
3.1.3 Pekerjaan Pondasi Menerus
3.1.3.1 Anstamping / Pasangan Batu Kosong Tebal 10 Cm AHSP PU : A.3.2.1.9 6,60 M3 Rp 492.246,00 Rp 3.249.561,97
3.1.3.2 Pasangan Pondasi Batu Gunung 1 PC : 4 PS AHSP PU : A.3.2.1.2 28,01 M3 Rp 960.244,25 Rp 26.898.842,05
3.1.4 Sloof (30/40)
3.1.4.1 Pembesian AHSP PU : A.4.1.1.17a 2098,78 KG Rp 18.676,23 Rp 39.197.298,00
3.1.4.2 Bekisting AHSP PU : A.4.1.1.21 197,40 M2 Rp 125.350,00 Rp 24.744.090,00
3.1.4.3 Cor Beton K 250 AHSP PU : A.4.1.1.8 13,25 M3 Rp 1.205.727,51 Rp 15.973.478,04
Pa ge 41
WBS URAIAN PEKERJAAN ANALISA VOLUME SAT HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
Pa ge 42
WBS URAIAN PEKERJAAN ANALISA VOLUME SAT HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
Pa ge 43
WBS URAIAN PEKERJAAN ANALISA VOLUME SAT HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
Pa ge 44
WBS URAIAN PEKERJAAN ANALISA VOLUME SAT HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
Pa ge 45
WBS URAIAN PEKERJAAN ANALISA VOLUME SAT HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
5.6 LANTAI 2
5.6.1 Armatur
5.6.1.1 Lampu Downlight 23 watt + Accesori Lengkap Terpasang Taksir 19,00 bh Rp 170.000,00 Rp 3.230.000,00
5.6.1.2 Lampu RM TL 2X36 watt + Accesori Lengkap Terpasang Taksir 4,00 unit Rp 500.000,00 Rp 2.000.000,00
5.6.2 Saklar lampu Merk Setara Broco 2 seri Rp -
5.6.2.1 Sakalar 1 Seri setara Broco Taksir 5,00 bh Rp 20.000,00 Rp 100.000,00
5.6.2.2 Sakalar 2 Seri setara Broco Taksir 3,00 bh Rp 20.000,00 Rp 60.000,00
5.6.2.3 Stop Kontak Taksir 9,00 bh Rp 20.000,00 Rp 180.000,00
Sub Jumlah Rp 5.570.000,00
6 PEKERJAAN MEKANIKAL
6.1 PEKERJAAN SALURAN DRAINASE
6.1.1 Pasangan Bata Dinding Saluran 1 PC : 2 PP AHSP PU : A.4.4.1.7 5,04 M2 Rp 159.729,25 Rp 805.035,42
6.1.2 Pasangan Plasteran Bata Dinding Saluran 1 PC : 2 PP AHSP PU : A.4.4.2.2 2,24 M2 Rp 76.337,92 Rp 170.996,94
6.1.3 Cor Lantai Saluran AHSP PU : A.4.1.1.2 3,92 M2 Rp 1.177.318,25 Rp 4.615.087,54
6.1.4 Buis Beton Dia. 20 cm Taksir 1,68 M2 Rp 60.000,00 Rp 100.800,00
6.1.5 Pemasangan Grill Saluran Bentuk Sesuai Gambar + Cat Meni Hitam Taksir 11,20 M2 Rp 200.000,00 Rp 2.240.000,00
Sub Jumlah Rp 7.931.919,90
6.2 LANTAI 1
6.2.1 Pekerjaan Sanitasi
6.2.1.1 INSTALASI AIR KOTOR
6.2.1.1.1 Pasang Flordrain Taksir 3,00 buah Rp 20.000,00 Rp 60.000,00
6.2.1.1.2 Pipa SNI 3 Inch AW Taksir 7,00 M Rp 70.000,00 Rp 490.000,00
6.2.1.2 INSTALASI AIR BERSIH
6.2.1.2.1 Memasang Wastafel + Keran Air + Pembungan Air Type Sifon angsa Aksesoris Lengkap
Taksir Terpasang Setara
4,00 Toto buah Rp 900.000,00 Rp 3.600.000,00
6.2.1.2.2 Pipa SNI 1/2 Inch AW Taksir 14,00 M Rp 35.000,00 Rp 490.000,00
6.2.1.2.3 Pasang Pipa Air Sampai Ketitik Air Taksir 1,00 LS Rp 300.000,00 Rp 300.000,00
6.2.1.3 INSTALASI AIR HUJAN
6.2.1.3.1 Pipa SNI 2 1/2 Inch AW Taksir 14,00 M Rp 63.000,00 Rp 882.000,00
6.2.1.4 INSTALASI KOTORAN
6.2.1.4.1 Pipa SNI 3 Inch AW Taksir 7,00 M Rp 70.000,00 Rp 490.000,00
6.2.1.4.2 Septick Tank + Resapan Lengkap Terpasang Taksir 2,00 LS Rp 2.000.000,00 Rp 4.000.000,00
6.2.1.4.3 Pasang Kloset Duduk SetaraToto Taksir 2,00 buah Rp 1.750.000,00 Rp 3.500.000,00
Sub Jumlah Rp 13.812.000,00
Pa ge 46
WBS URAIAN PEKERJAAN ANALISA VOLUME SAT HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
6.3 LANTAI 2
6.3.1 Pekerjaan Sanitasi
6.3.1.1 INSTALASI AIR BERSIH
6.3.1.1.2 Bak Mandi Pyber Glass (60 x 60) Taksir 5,00 buah Rp 400.000,00 Rp 2.000.000,00
6.3.1.1.3 Pipa SNI 1 Inch AW Taksir 14,00 M Rp 58.000,00 Rp 812.000,00
6.3.1.1.4 Pipa SNI 1/2 Inch AW Taksir 14,00 M Rp 35.000,00 Rp 490.000,00
6.3.1.1.5 Pasang Pipa Air Sampai Ketitik Air Taksir 1,00 LS Rp 300.000,00 Rp 300.000,00
6.3.1.2 INSTALASI AIR KOTOR
6.3.1.2.1 Pipa SNI 3 Inch AW Taksir 7,00 M Rp 70.000,00 Rp 490.000,00
6.3.1.2.2 Pasang Flordrain Taksir 2,00 buah Rp 20.000,00 Rp 40.000,00
6.3.1.3 INSTALASI KOTORAN
6.3.1.3.1 Pipa SNI 3 Inch AW Taksir 6,00 M Rp 70.000,00 Rp 420.000,00
6.3.1.3.2 Pasang Kloset Jongkok Setara American Standar Taksir 3,00 buah Rp 600.000,00 Rp 1.800.000,00
6.3.1.4 INSTALASI AIR HUJAN
6.3.1.4.1 Pipa SNI 2 1/2 Inch AW Taksir 14,00 M Rp 63.000,00 Rp 882.000,00
Sub Jumlah Rp 7.234.000,00
7 PEKERJAAN FINISHING
7.1 PEKERJAAN BESI, ALUMUNIUM, ORNAMEN DAN DINDING COMPOSITE
7.1.1 Pekerjaan Almunium Composite Panel Setara Seven Type PVDF + Rangka + Aksesoris Taksir
Lengkap Terpasang
21,76
Sesuai Gambar
M2 Rp 850.000,00 Rp 18.496.000,00
7.1.2 Huruf Timbul Gedung IGD + Aksesoris Lengkap Terpasang Sesuai Gambar (Bahan Stainless)
Taksir 1,00 Ls Rp 4.500.000,00 Rp 4.500.000,00
7.1.3 Huruf Timbul Gedung Utama + Aksesoris Lengkap Terpasang Sesuai Gambar (Bahan Taksir
Stainless) 1,00 Ls Rp 4.500.000,00 Rp 4.500.000,00
7.1.4 Logo Puskesmas + Aksesoris Lengkap Terpasang Sesuai Gambar (Bahan Stainless) Taksir 1,00 Ls Rp 3.000.000,00 Rp 3.000.000,00
7.1.5 Reling Tangga Stainless + Aksesoris Lengkap Terpasang Sesuai Gambar Taksir 8,68 M Rp 500.000,00 Rp 4.340.000,00
7.1.6 Handrail (Pegangan Tangan) Stainless + Aksesoris Lengkap Terpasang Sesuai GambarTaksir 13,14 M Rp 300.000,00 Rp 3.942.000,00
7.2 Pekerjan Pot Bunga
7.2.1 Pasangan Dinding Bata 1PC : 4 PP AHSP PU : A. 4.4.1.9 7,70 M2 Rp 145.322,63 Rp 1.118.984,21
7.2.2 Plasteran Dinding Bata 1PC : 4 PP AHSP PU : A.4.4.2.4 7,70 M2 Rp 69.469,20 Rp 534.912,84
7.2.3 Pesangan Batu Alam Tempel Susun Sirih + Cat Vernis Batu Alam AHSP PU : A.4.4.3.58 4,28 M2 Rp 458.350,00 Rp 1.961.738,00
7.2.4 Relif Pot Bunga Sesuai Gambar Taksir 9,50 M Rp 200.000,00 Rp 1.900.000,00
7.5 Pembersihan Akhir Taksir 1,00 unit Rp 1.000.000,00 Rp 1.000.000,00
Sub Jumlah Rp 45.293.635,05
JUMLAH Rp 2.181.769.320,69
JUMLAH HARGA PER TOTAL LUAS BANGUNAN Rp 5.327.886,01
Pa ge 47
REKAPITULASI RENCANA ANGGARAN BIAYA
TERBILANG : "Dua Miliyar Empat Ratus Dua Puluh Satu Juta Tujuh Ratus Enam
Puluh Empat Ribu Rupiah"
Pa ge 48
DURASI PEKERJAAN
Koefisien Pekerja Asumsi Jumlah Pekerja
Koefisien Produktivita Durasi Pembulatan
WBS URAIAN PEKERJAAN Volume Satuan Analisa Tenaga
P T M K Terpakai s (hari) Durasi (hari) P T M K
Kerja
1 PEKERJAAN PERSIAPAN
1.1 Pembersihan Lapangan 600,00 M2 Taksir 0,100 0,050 0,100 10,000 12 5,00 5 12 0 0 6
1.2 Papan Nama Proyek Uk. 90 x120 1,00 UNIT Taksir 1,00 1
1.3 Administrasi/Dokumentasi dan Pelaporan 1,00 LS Taksir 1,00 1
1.4 Direksi Keet/sewa 24,00 M3 AHSP PU : A.2.2.1.6 1,000 1,500 0,500 0,150 1,500 0,667 6 6,00 6 4 6 1 1
1.5 Perlengkapan P3k 1,00 PAKET Taksir 1,00 1
1.6 Pengukuran dan Pemasangan Bouwplank 68,00 M2 AHSP PU : A.2.2.1.4 0,100 0,100 0,005 0,001 0,100 10,000 4 1,70 2 4 4 1 1
1.7 Pagar pelindung proyek 52,50 M2 AHSP PU : A.2.2.1.2 0,300 0,100 0,015 0,010 0,100 10,000 3 1,75 2 9 3 1 1
1.8 Pekerjaan SMK3 1,00 LS AN SMK3 1,00 1
2 PEKERJAAN TANAH
2.1 PEKERJAAN GALIAN
2.1.1 Galian Tanah Pondasi Tapak 70,20 M3 AHSP PU : A.2.3.1.1 0,300 0,010 0,300 3,333 6 3,51 4 6 1
2.1.2 Galian Tanah Pondasi Menerus 71,30 M3 AHSP PU : A.2.3.1.1 0,300 0,010 0,300 3,333 6 3,57 4 6 1
2.2 PEKERJAAN TIMBUNAN
2.2.1 Urugan Kembali Bekas Galian 35,38 M3 AHSP PU : A.2.3.1.9 0,500 0,050 0,500 2,000 5 3,54 4 5 1
2.2.2 Pasir Urugan Bawah Pondasi Menerus 71,30 M3 AHSP PU : A.2.3.1.11 0,300 0,010 0,300 3,333 5 4,28 5 5 1
2.2.3 Pasir Urugan dibawah Lantai 20,48 M3 AHSP PU : A.2.3.1.11 0,300 0,010 0,300 3,333 3 2,05 3 3 1
2.2.4 Timbunan Tanah Dibawah Lantai 266,18 M3 AHSP PU : A.2.3.1.15 0,250 0,025 0,250 4,000 8 8,32 9 8 1
3 PEKERJAAN STRUKTUR
3.1 LANTAI 1
3.1.1 PEKERJAAN PONDASI TAPAK BETON BERTULANG
3.1.1.1 Lantai Kerja Pondasi Tapak Setempat ( K.175) 3,78 M3 AHSP PU : A.4.1.1.5 1,650 0,275 0,083 0,028 0,275 3,636 2 0,52 1 2 2 1 1
3.1.2 Pekerjaan Beton Bertulang Pondasi Tapak
3.1.2.1 Cor Beton K 250 21,60 M3 AHSP PU : A.4.1.1.8 1,650 0,275 0,083 0,028 0,275 3,636 3 1,98 2 1 3 1 1
3.1.2.2 Pembesian 7.348,56 KG AHSP PU : A.4.1.1.17a 0,070 0,070 0,004 0,007 0,004 250,000 6 4,90 5 6 6 1 1
3.1.2.3 Bekisting 115,20 M2 AHSP PU : A.4.1.1.20 0,520 0,260 0,026 0,026 0,260 38,462 2 1,50 2 1 2 1 1
3.1.3 Pekerjaan Pondasi Menerus
3.1.3.1 Anstamping / Pasangan Batu Kosong Tebal 10 Cm 6,60 M3 AHSP PU : A.3.2.1.9 0,780 0,390 0,039 0,039 0,390 2,564 2 1,29 2 1 2 1 1
3.1.3.2 Pasangan Pondasi Batu Gunung 1 PC : 4 PS 28,01 M3 AHSP PU : A.3.2.1.2 1,500 0,750 0,075 0,075 0,750 1,333 6 3,50 4 3 6 1 1
3.1.4 Sloof (30/40)
3.1.4.1 Pembesian 2.098,78 KG AHSP PU : A.4.1.1.17a 0,070 0,070 0,004 0,007 0,070 250,000 4 2,10 3 4 4 1 1
3.1.4.2 Bekisting 197,40 M2 AHSP PU : A.4.1.1.21 0,520 0,260 0,026 0,026 0,260 38,462 3 1,71 2 2 3 1 1
3.1.4.3 Cor Beton K 250 13,25 M3 AHSP PU : A.4.1.1.8 1,650 0,275 0,083 0,028 0,275 3,636 3 1,21 2 1 3 1 1
3.1.5 Sloof (15/20) 0,000
3.1.5.1 Pembesian 237,81 KG AHSP PU : A.4.1.1.17a 0,070 0,070 0,004 0,007 0,070 250,000 4 0,24 1 4 4 1 1
3.1.5.2 Bekisting 3,15 M2 AHSP PU : A.4.1.1.21 0,520 0,260 0,026 0,026 0,260 38,462 1 0,08 1 1 1 1 1
3.1.5.3 Cor Beton K 175 0,14 M3 AHSP PU : A.4.1.1.5 1,650 0,275 0,083 0,028 0,275 3,636 1 0,04 1 1 1 1 1
3.1.6 Kolom Uk. 30/40
3.1.6.1 Pembesian 1.525,50 KG AHSP PU : A.4.1.1.17a 0,070 0,070 0,004 0,007 0,070 250,000 6 1,02 2 6 6 1 1
3.1.6.2 Bekisting 134,40 M2 AHSP PU : A.4.1.1.22 0,660 0,330 0,033 0,033 0,330 30,303 4 1,11 2 2 4 1 1
3.1.6.3 Cor Beton K 250 9,94 M3 AHSP PU : A.4.1.1.8 1,650 0,275 0,083 0,028 0,275 3,636 2 1,37 2 0 2 1 1
3.1.7 Kolom Uk. 15/15 0
3.1.7.1 Pembesian 68,49 KG AHSP PU : A.4.1.1.17a 0,070 0,070 0,004 0,007 0,070 250,000 1 0,27 1 1 1 1 1
3.1.7.2 Bekisting 9,60 M2 AHSP PU : A.4.1.1.22 0,660 0,330 0,033 0,033 0,330 30,303 1 0,32 1 1 1 1 1
3.1.7.3 Cor Beton K 175 0,78 M3 AHSP PU : A.4.1.1.5 1,650 0,275 0,083 0,028 0,275 3,636 1 0,21 1 1 3 1 1
Pa ge 49
Koefisien Pekerja Asumsi Jumlah Pekerja
Koefisien Produktivita Durasi Pembulatan
WBS URAIAN PEKERJAAN Volume Satuan Analisa Tenaga
P T M K Terpakai s (hari) Durasi (hari) P T M K
Kerja
3.1.8 Balok Latai (13/13) Elevasi ± 2.23 m
3.1.8.1 Pembesian 252,27 KG AHSP PU : A.4.1.1.17a 0,070 0,070 0,004 0,007 0,070 250,000 2 0,50 1 2 2 1 1
3.1.8.2 Bekisting 139 M2 AHSP PU : A.4.1.1.23 0,660 0,330 0,033 0,033 0,330 30,303 4 1,15 2 2 4 1 1
3.1.8.3 Cor Beton K 175 1,20 M3 AHSP PU : A.4.1.1.5 1,650 0,275 0,083 0,028 0,275 3,636 1 0,33 1 1 1 1 1
3.1.9 Balok Uk. 25/30 Elevasi ± 3.45 m
3.1.9.1 Pembesian 1.332 KG AHSP PU : A.4.1.1.17a 0,070 0,070 0,004 0,007 0,070 250,000 4 1,33 2 4 4 1 1
3.1.9.2 Bekisting 136,50 M2 AHSP PU : A.4.1.1.23 0,660 0,330 0,033 0,033 0,330 30,303 4 1,13 2 2 4 1 1
3.1.9.3 Cor Beton K 250 12,80 M3 AHSP PU : A.4.1.1.8 1,650 0,275 0,083 0,028 0,275 3,636 4 0,88 1 1 4 1 1
3.1.10 Balok Uk. 15/20 Elevasi ± 3.45 m
3.1.10.1 Pembesian 25,01 KG AHSP PU : A.4.1.1.17a 0,070 0,070 0,004 0,007 0,070 250,000 4 0,03 1 4 4 1 1
3.1.10.2 Bekisting 3,15 M2 AHSP PU : A.4.1.1.23 0,660 0,330 0,033 0,033 0,330 30,303 2 0,05 1 1 2 1 1
3.1.10.3 Cor Beton K 175 0,12 M3 AHSP PU : A.4.1.1.5 1,650 0,275 0,083 0,028 0,275 3,636 1 0,03 1 1 1 1 1
3.1.11 Plat Tangga dan Plat Bordes Tebal 10cm
3.1.11.1 Pembesian 338,00 KG AHSP PU : A.4.1.1.17a 0,070 0,070 0,004 0,007 0,070 250,000 2 0,68 1 2 2 1 1
3.1.11.2 Bekisting 29,06 M2 AHSP PU : A.4.1.1.26 0,660 0,330 0,033 0,033 0,330 30,303 2 0,48 1 1 2 1 1
3.1.11.3 Cor Beton K 250 0,90 M3 AHSP PU : A.4.1.1.8 1,650 0,275 0,083 0,028 0,275 3,636 1 0,25 1 1 1 1 1
3.2 LANTAI 2
3.2.1 Kolom Uk. 30/30
3.2.1.1 Pembesian 756,27 KG AHSP PU : A.4.1.1.17a 0,070 0,070 0,004 0,007 0,070 250,000 3 1,01 2 3 3 1 1
3.2.1.2 Bekisting 109,44 M2 AHSP PU : A.4.1.1.22 0,660 0,330 0,033 0,033 0,330 30,303 3 1,20 2 2 3 1 1
3.2.1.3 Cor Beton K 250 6,91 M3 AHSP PU : A.4.1.1.8 1,650 0,275 0,083 0,028 0,275 3,636 2 0,95 1 1 2 1 1
3.2.2 Kolom Uk. 15/15
3.2.2.1 Pembesian 65,13 KG AHSP PU : A.4.1.1.17a 0,070 0,070 0,004 0,007 0,070 250,000 1 0,26 1 1 1 1 1
3.2.2.2 Bekisting 109,44 M2 AHSP PU : A.4.1.1.22 0,660 0,330 0,033 0,033 0,330 30,303 2 1,81 2 1 2 1 1
3.2.2.3 Cor Beton K 175 0,86 M3 AHSP PU : A.4.1.1.5 1,650 0,275 0,083 0,028 0,275 3,636 1 0,24 1 1 1 1 1
3.2.3 Balok Latai (13/13) Elevasi ± 6.23 m
3.2.3.1 Pembesian 279,66 KG AHSP PU : A.4.1.1.17a 0,070 0,070 0,004 0,007 0,070 250,000 2 0,56 1 2 2 1 1
3.2.3.2 Bekisting 50,44 M2 AHSP PU : A.4.1.1.23 0,660 0,330 0,033 0,033 0,330 30,303 2 0,83 1 1 2 1 1
3.2.3.3 Cor Beton K 175 1,34 M3 AHSP PU : A.4.1.1.5 1,650 0,275 0,083 0,028 0,275 3,636 1 0,37 1 1 1 1 1
3.2.4 Ring Balok Uk. 25/30 Elevasi ± 7.50 m
3.2.4.1 Pembesian 1.332 KG AHSP PU : A.4.1.1.17a 0,070 0,070 0,004 0,007 0,070 250,000 3 1,78 2 3 3 1 1
3.2.4.2 Bekisting 115,50 M2 AHSP PU : A.4.1.1.23 0,660 0,330 0,033 0,033 0,330 30,303 2 1,91 2 1 2 1 1
3.2.4.3 Cor Beton K 250 12,80 M3 AHSP PU : A.4.1.1.8 1,650 0,275 0,083 0,028 0,275 3,636 2 1,76 2 1 2 1 1
3.2.5 Ring Balok Uk. 15/20 Elevasi ±7.5 m
3.2.5.1 Pembesian 25,01 KG AHSP PU : A.4.1.1.17a 0,070 0,070 0,004 0,007 0,070 250,000 1 0,10 1 1 1 1 1
3.2.5.2 Bekisting 3,15 M2 AHSP PU : A.4.1.1.23 0,660 0,330 0,033 0,033 0,330 30,303 1 0,10 1 1 1 1 1
3.2.5.3 Cor Beton K 175 0,12 M3 AHSP PU : A.4.1.1.5 1,650 0,275 0,083 0,028 0,275 3,636 1 0,03 1 1 1 1 1
3.2.6 Plat Lantai Tebal 12cm
3.2.6.1 Pembesian 5.163 KG AHSP PU : A.4.1.1.17a 0,070 0,070 0,004 0,007 0,070 250,000 6 3,44 4 6 6 1 1
3.2.6.2 Bekisting 217,23 M2 AHSP PU : A.4.1.1.24 0,660 0,330 0,033 0,033 0,330 30,303 4 1,79 2 2 4 1 1
3.2.6.3 Cor Beton K 250 20,33 M3 AHSP PU : A.4.1.1.8 1,650 0,275 0,083 0,028 0,275 3,636 3 1,86 2 1 3 1 1
3.2.7 Plat dak dan Talang Beton
3.2.7.1 Pembesian 412,54 KG AHSP PU : A.4.1.1.17a 0,070 0,070 0,004 0,007 0,070 250,000 2 0,83 1 2 2 1 1
3.2.7.2 Bekisting 61,20 M2 AHSP PU : A.4.1.1.24 0,660 0,330 0,033 0,033 0,330 30,303 3 0,67 1 2 3 1 1
3.2.7.3 Cor Beton K 250 4,54 M3 AHSP PU : A.4.1.1.8 1,650 0,275 0,083 0,028 0,275 3,636 2 0,62 1 1 2 1 1
Pa ge 50
Koefisien Pekerja Asumsi Jumlah Pekerja
Koefisien Produktivita Durasi Pembulatan
WBS URAIAN PEKERJAAN Volume Satuan Analisa Tenaga
P T M K Terpakai s (hari) Durasi (hari) P T M K
Kerja
3.2.8 PEKERJAAN ATAP
3.2.8.1 Rangka kuda-kuda dan gording baja ringan Multytruss 234,57 M2 AHSP PU : A.4.2.1.24 0,200 0,450 0,050 0,010 0,450 5,000 6 7,82 8 3 6 1 1
4 PEKERJAAN ARSITETKTUR
4.1 LANTAI 1
4.1.1 Pekerjaan Dinding
4.1.1.1 Pasangan Trasram Bata 1 PC : 2 PP 38,84 M2 AHSP PU: A.4.4.1.7 0,300 0,100 0,015 0,010 0,100 10,000 4 0,97 1 1 4 1 1
4.1.1.2 Pasangan Dinding Bata 1 PC : 4 PP 283,29 M2 AHSP PU : A.4.4.1.9 0,300 0,100 0,015 0,010 0,100 10,000 5 5,67 6 2 5 1 1
4.1.1.3 Plesteran Trasram Bata 1 PC : 2 PP 77,67 M2 AHSP PU : A.4.4.2.2 0,300 0,150 0,015 0,015 0,150 66,667 3 0,39 1 2 3 2 2
4.1.1.4 Plesteran Dinding Bata 1PC : 4 PP 566,58 M2 AHSP PU: A. 4.4.2.4 0,300 0,150 0,015 0,015 0,150 6,667 10 8,50 9 5 10 1 1
4.1.1.5 Plasteran Beton 1 PC : 3 PP 185,04 M2 AHSP PU : A.4.4.2.3 0,300 0,150 0,015 0,015 0,150 6,667 4 6,94 7 2 4 1 1
4.1.1.6 Pesangan Batu Alam Tempel Susun Sirih + cat Vernis Batu Alam 95,55 M2 AHSP PU : A.4.4.3.58 0,700 0,350 0,035 0,035 0,350 28,571 3 1,11 2 2 3 1 1
4.1.2 Pekerjaan Lantai
4.1.2.1 Pekerjaan Beton Tumbuk Tebal 7 cm (K 125) 9,96 M3 AHSP PU : A.4.1.1.2 1,650 0,275 0,083 0,028 0,275 3,636 3 0,91 1 1 3 1 1
4.1.2.2 Pekerjaan Lantai Granite 60 x 60 Cm (Halus) 147,28 M2 AHSP PU : A.4.4.3.9 a 0,250 0,125 0,013 0,013 0,125 8,000 4 4,60 5 2 4 1 1
4.1.2.3 Pekerjaan Lantai Granite 60 x 60 Cm (Kasar) 48,73 M2 AHSP PU : A.4.4.3.9 a 0,250 0,125 0,013 0,013 0,125 8,000 3 2,03 3 2 3 1 1
4.1.2.4 Pekerjaan Lantai Keramik untuk Ruangan Wc/Km 20 X 20 Cm 7,49 M2 AHSP PU : A.4.4.3.36 0,700 0,350 0,035 0,035 0,350 28,571 1 0,26 1 1 1 1 1
4.1.2.5 Pasangan Dinding Keramik KM/WC 20 x 25 cm 44,93 M2 AHSP PU : A.4.4.3.65 0,900 0,450 0,045 0,045 0,450 22,222 2 1,01 2 1 2 1 1
4.1.3 Pekerjaan Pintu, Jendela, Ventilasi
4.1.3.1 Pintu Panel Kaca Tempered Glass 12mm + Aksesoris Lengkap Terpasang (Type
2,00 P1)Unit Taksir 1,00 1
4.1.3.2 Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris Lengkap Terpasang Sesuai 5,00
Gambar
Unit
( Type P2) Taksir 2,00 2
4.1.3.3 Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris Lengkap Terpasang Sesuai 1,00
Gambar
Unit
( Type P5) Taksir 1,00 1
4.1.3.4 Kusen UPVC + Daun Pintu UPVC+ Aksesoris Lengkap Terpasang Sesuai Gambar
1,00 (Type
UnitP4) Taksir 1,00 1
4.1.3.5 Kusen UPVC + Daun Pintu UPVC+ Aksesoris Lengkap Terpasang Sesuai Gambar
2,00 (Type
UnitP3) Taksir 1,00 1
4.1.3.6 Kusen UPVC + Daun Jendela dan Ventilasi Kaca 5mm + Aksesoris Lengkap6,00
Terpasang
Unit
Sesuai GambarTaksir
(Type JV1) 2,00 2
4.1.3.7 Kusen UPVC + Daun Jendela dan Ventilasi Kaca 5mm + Aksesoris Lengkap4,00
Terpasang
Unit
Sesuai GambarTaksir
(Type J2) 2,00 2
4.1.3.8 Kusen UPVC + Daun ventilasi Kaca 5mm + Aksesoris Lengkap Terpasang Sesuai
3,00 Gambar
Unit (Type V2) Taksir 1,00 1
4.1.4 Pekerjaan Plafond
4.1.4.1 Pasang Plafon PVC/Fiber + Rangka + Aksesoris Lengkap Terpasang Sesuai
199,13
Gambar M2 AHSP PU: A.4.5.1.7 a 0,100 0,050 0,005 0,005 0,050 20,000 3 3,32 4 2 3 1 1
4.1.5 Pekerjaan Pengecatan
4.1.5.1 Pengecatan Tembok dan Sealer 3x(L/D) Setara Vinilex 855,73 M2 AHSP PU : A.4.7.1.10b 0,020 0,063 0,003 0,006 0,063 50,000 5 3,42 4 2 5 1 1
4.2 LANTAI 2
4.2.1 Pekerjaan Dinding
4.2.1.1 Pasangan Trasram Bata 1 PC : 2 PP 23,97 M2 AHSP PU: A.4.4.1.7 0,300 0,100 0,015 0,010 0,100 10,000 2 1,20 2 1 2 1 1
4.2.1.2 Pasangan Dinding Bata 1 PC : 4 PP 347,75 M2 AHSP PU : A.4.4.1.9 0,300 0,100 0,015 0,010 0,100 10,000 6 5,80 6 2 6 1 1
4.2.1.3 Plesteran Trasram Bata 1 PC : 2 PP 47,94 M2 AHSP PU : A.4.4.2.2 0,300 0,150 0,015 0,015 0,150 66,667 3 0,24 1 2 3 1 1
4.2.1.4 Plesteran Dinding Bata 1PC : 4 PP 695,50 M2 AHSP PU: A. 4.4.2.4 0,300 0,150 0,015 0,015 0,150 6,667 5 13,53 14 3 5 1 1
4.2.1.5 Plasteran Beton 1 PC : 3 PP 69,12 M2 AHSP PU : A.4.4.2.3 0,300 0,150 0,015 0,015 0,150 6,667 4 2,59 3 2 4 1 1
4.2.1.6 Pesangan Batu Alam Tempel Susun Sirih + cat Vernis Batu Alam 95,55 M2 AHSP PU : A.4.4.3.58 0,700 0,350 0,035 0,035 0,350 28,571 2 1,67 2 1 2 1 1
4.2.2 Pekerjaan Lantai
4.2.2.1 Pekerjaan Beton Tumbuk Tebal 7 cm (K 125) 8,38 M3 AHSP PU : A.4.1.1.2 1,650 0,275 0,083 0,028 0,275 3,636 2 1,15 2 1 2 1 1
4.2.2.2 Pekerjaan Lantai Granite 60 x 60 Cm (Halus) 165,66 M2 AHSP PU : A.4.4.3.9 a 0,250 0,125 0,013 0,013 0,125 8,000 5 4,14 5 3 5 1 1
4.2.2.3 Pekerjaan Lantai Keramik untuk Ruangan Wc/Km 20 X 20 Cm 5,00 M2 AHSP PU : A.4.4.3.36 0,700 0,350 0,035 0,035 0,350 28,571 1 0,17 1 1 1 1 1
4.2.2.4 Pasangan Dinding Keramik KM/WC 20 x 25 cm 24,14 M2 AHSP PU : A.4.4.3.65 0,900 0,450 0,045 0,045 0,450 22,222 2 0,54 1 1 2 1 1
Pa ge 51
Koefisien Pekerja Asumsi Jumlah Pekerja
Koefisien Produktivita Durasi Pembulatan
WBS URAIAN PEKERJAAN Volume Satuan Analisa Tenaga
P T M K Terpakai s (hari) Durasi (hari) P T M K
Kerja
4.2.3 Pekerjaan Pintu, Jendela, Ventilasi
4.2.3.1 Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris Lengkap Terpasang Sesuai 4,00
Gambar Unit
( Type P2) Taksir 1,00 1
4.2.3.2 Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris Lengkap Terpasang Sesuai 1,00
Gambar Unit
( Type P5) Taksir 1,00 1
4.2.3.3 Kusen UPVC + Daun Pintu UPVC+ Aksesoris Lengkap Terpasang Sesuai Gambar 2,00 (TypeUnitP4) Taksir 1,00 1
4.2.3.5 Kusen UPVC + Daun Jendela dan Ventilasi Kaca 5mm + Aksesoris Lengkap8,00 TerpasangUnit
Sesuai GambarTaksir
(Type JV1) 1,00 1
4.2.3.6 Kusen UPVC + Daun Jendela dan Ventilasi Kaca 5mm + Aksesoris Lengkap4,00 TerpasangUnit
Sesuai GambarTaksir
(Type J2) 1,00 1
4.2.3.7 Kusen UPVC + Daun ventilasi Kaca 5mm + Aksesoris Lengkap Terpasang Sesuai 2,00 Gambar
Unit (Type V2) Taksir 1,00 1
4.2.4 PEKERJAAN ATAP
4.2.4.1 Penutup Atap genteng Onduline 234,56 M2 AHSP PU : A.4.5.2.43 0,200 0,100 0,001 0,010 0,100 10,000 5 4,69 5 3 5 1 1
4.2.4.2 Rabung genteng Onduline 35,72 M AHSP PU : A.4.5.2.44 0,250 0,150 0,013 0,015 0,150 6,667 4 1,34 2 2 4 1 1
4.2.4.3 Lisplank Kayu 2/20 cm 65,22 M AHSP PU : A.4.6.1.29 0,100 0,200 0,005 0,020 0,200 5,000 5 2,61 3 3 5 1 1
4.2.5 Pekerjaan Plafond
4.2.5.1 Pasang Plafon PVC/Fiber + Rangka + Aksesoris Lengkap Terpasang Sesuai 167,55
Gambar M2 AHSP PU : A.4.5.1.7 a 0,1 0,05 0,005 0,005 0,050 20,000 3 2,79 3 2 3 1 1
4.2.6 Pekerjaan Pengecatan
4.2.6.1 Pengecatan Tembok dan Sealer 3x(L/D) Setara Vinilex 855,73 M2 AHSP PU : A.4.7.1.10b 0,02 0,063 0,003 0,006 0,063 50,000 5 3,42 4 2 5 1 1
5 PEKERJAAN ELEKTRIKAL
5.1 Instlasi titik penerangan, instalasi termasuk kabel NYA 2,5 mm dalam pipa PVC
76,00
fitting titik
lampu dan kelengkapan
Taksir instalasi terpasang 1,00 1
5.2 Instalasi titik Stop kontak, instalasi termasuk kabel NYA 2,5 mm dalam pipa PVC
17,00fitting
titik
lampu dan kelengkapan
Taksir instalasi terpasang 1,00 1
5.3 Pemasangan Box Sekring 1,00 bh Taksir 1,00 1
5.4 Pemasukan Arus Listrik 12 Ampere 1,00 titik Taksir 1,00 1
5.5 LANTAI 1
5.5.1 Armatur
5.5.1.1 Lampu Downlight 23 watt + Accesori Lengkap Terpasang 16,00 bh Taksir 1,00 1
5.5.1.2 Lampu RM TL 2X36 watt + Accesori Lengkap Terpasang 6,00 unit Taksir 1,00 1
5.5.2 Saklar lampu Merk Setara Broco 2 seri
5.5.2.1 Sakalar 1 Seri setara Broco 7,00 bh Taksir 1,00 1
5.5.2.2 Sakalar 2 Seri setara Broco 3,00 bh Taksir 1,00 1
5.5.2.3 Stop Kontak 9,00 bh Taksir 1,00 1
5.6 LANTAI 2
5.6.1 Armatur
5.6.1.1 Lampu Downlight 23 watt + Accesori Lengkap Terpasang 19,00 bh Taksir 1,00 1
5.6.1.2 Lampu RM TL 2X36 watt + Accesori Lengkap Terpasang 4,00 unit Taksir 1,00 1
5.6.2 Saklar lampu Merk Setara Broco 2 seri
5.6.2.1 Sakalar 1 Seri setara Broco 5,00 bh Taksir 1,00 1
5.6.2.2 Sakalar 2 Seri setara Broco 3,00 bh Taksir 1,00 1
5.6.2.3 Stop Kontak 9,00 bh Taksir 1,00 1
6 PEKERJAAN MEKANIKAL
6.1 PEKERJAAN SALURAN DRAINASE
6.1.1 Pasangan Bata Dinding Saluran 1 PC : 2 PP 5,04 M2 AHSP PU : A.4.4.1.7 0,300 0,100 0,015 0,010 0,100 10,000 1 0,50 1 1 1 1 1
6.1.2 Pasangan Plasteran Bata Dinding Saluran 1 PC : 2 PP 2,24 M2 AHSP PU : A.4.4.2.2 0,300 0,150 0,015 0,015 0,150 6,667 1 0,34 1 1 1 1 1
6.1.3 Cor Lantai Saluran 3,92 M2 AHSP PU : A.4.1.1.2 1,650 0,275 0,083 0,028 0,275 3,636 1 1,08 2 1 1 1 1
6.1.4 Buis Beton Dia. 20 cm 1,68 M2 Taksir 0,100 1,00 1
6.1.5 Pemasangan Grill Saluran Bentuk Sesuai Gambar + Cat Meni Hitam 11,20 M2 Taksir 0,100 1,00 1
6.2 LANTAI 1
6.2.1 Pekerjaan Sanitasi
6.2.1.1 INSTALASI AIR KOTOR
6.2.1.1.1 Pasang Flordrain 3,00 buah Taksir 1,00 1
6.2.1.1.2 Pipa SNI 3 Inch AW 7,00 M Taksir 1,00 1
Pa ge 52
Koefisien Pekerja Asumsi Jumlah Pekerja
Koefisien Produktivita Durasi Pembulatan
WBS URAIAN PEKERJAAN Volume Satuan Analisa Tenaga
P T M K Terpakai s (hari) Durasi (hari) P T M K
Kerja
6.2.1.2 INSTALASI AIR BERSIH
6.2.1.2.1 Memasang Wastafel + Keran Air + Pembungan Air Type Sifon angsa Aksesoris
4,00 Lengkap
buah Terpasang Setara
Taksir Toto 1,00 1
6.2.1.2.2 Pipa SNI 1/2 Inch AW 14,00 M Taksir 1,00 1
6.2.1.2.3 Pasang Pipa Air Sampai Ketitik Air 1,00 LS Taksir 1,00 1
6.2.1.3 INSTALASI AIR HUJAN
6.2.1.3.1 Pipa SNI 2 1/2 Inch AW 14,00 M Taksir 1,00 1
6.2.1.4 INSTALASI KOTORAN
6.2.1.4.1 Pipa SNI 3 Inch AW 7,00 M Taksir 1,00 1
6.2.1.4.2 Septick Tank + Resapan Lengkap Terpasang 2,00 LS Taksir 1,00 1
6.2.1.4.3 Pasang Kloset Duduk SetaraToto 2,00 buah Taksir 1,00 1
6.2.1.4.4 LANTAI 2
6.3 Pekerjaan Sanitasi
6.3.1 INSTALASI AIR BERSIH
6.3.1.1 Bak Mandi Pyber Glass (60 x 60) 5,00 buah Taksir 1,00 1
6.3.1.1.2 Pipa SNI 1 Inch AW 14,00 M Taksir 1,00 1
6.3.1.1.3 Pipa SNI 1/2 Inch AW 14,00 M Taksir 1,00 1
6.3.1.1.4 Pasang Pipa Air Sampai Ketitik Air 1,00 LS Taksir 1,00 1
6.3.1.1.5 INSTALASI AIR KOTOR
6.3.1.2 Pipa SNI 3 Inch AW 7,00 M Taksir 1,00 1
6.3.1.2.1 Pasang Flordrain 2,00 buah Taksir 1,00 1
6.3.1.2.2 INSTALASI KOTORAN
6.3.1.3 Pipa SNI 3 Inch AW 6,00 M Taksir 1,00 1
6.3.1.3.1 Pasang Kloset Jongkok Setara American Standar 3,00 buah Taksir 1,00 1
6.3.1.3.2 INSTALASI AIR HUJAN
6.3.1.4 Pipa SNI 2 1/2 Inch AW 14,00 M Taksir 1,00 1
7 PEKERJAAN FINISHING
7.1 PEKERJAAN BESI, ALUMUNIUM, ORNAMEN DAN DINDING COMPOSITE
7.1.1 Pekerjaan Almunium Composite Panel Setara Seven Type PVDF + Rangka +21,76AksesorisM2Lengkap Terpasang
Taksir
Sesuai Gambar 3,00 3
7.1.2 Huruf Timbul Gedung IGD + Aksesoris Lengkap Terpasang Sesuai Gambar (Bahan1,00 Stainless)
Ls Taksir 2,00 2
7.1.3 Huruf Timbul Gedung Utama + Aksesoris Lengkap Terpasang Sesuai Gambar (Bahan
1,00 Stainless)
Ls Taksir 2,00 2
7.1.4 Logo Puskesmas + Aksesoris Lengkap Terpasang Sesuai Gambar (Bahan Stainless)
1,00 Ls Taksir 2,00 2
7.1.5 Reling Tangga Stainless + Aksesoris Lengkap Terpasang Sesuai Gambar 8,68 M Taksir 2,00 2
7.1.6 Handrail (Pegangan Tangan) Stainless + Aksesoris Lengkap Terpasang Sesuai13,14
Gambar M Taksir 2,00 2
7.2 Pekerjan Pot Bunga
7.2.1 Pasangan Dinding Bata 1PC : 4 PP 7,70 M2 AHSP PU : A. 4.4.1.9 0,300 0,100 0,015 0,010 0,100 10,000 2 0,39 1 1 2 1 1
7.2.2 Plasteran Dinding Bata 1PC : 4 PP 7,70 M2 AHSP PU : A.4.4.2.4 0,300 0,150 0,015 0,015 0,150 6,667 2 0,58 1 1 2 1 1
7.2.3 Pesangan Batu Alam Tempel Susun Sirih + Cat Vernis Batu Alam 4,28 M2 AHSP PU : A.4.4.3.58 0,700 0,350 0,035 0,035 0,350 2,857 2 0,75 1 1 2 1 1
7.2.4 Relif Pot Bunga Sesuai Gambar 9,50 M Taksir 0,100 2,00 2
7.3 Pembersihan Akhir 1,00 unit Taksir 0,100 1,00 1
Pa ge 53