LAPORAN PRAKTIKUM PERENCANAAN DAN

PENGENDALIAN PROYEK KONSTRUKSI

Untuk Memenuhi Sebagian Syarat-Syarat Kurikulum


Jurusan Teknik Sipil Fakultas Teknik
Universitas Syiah Kuala

Disusun Oleh :
SAFRIL MUHAMAD ERWIN HIDAYAT
2004101010130

Dosen Pembimbing :
Nama : Dr. Ir. Saiful Husin, M.T.
NIP : 195501011987021001

JURUSAN TEKNIK SIPIL


FAKULTAS TEKNIK
UNIVERSITAS SYIAH KUALA
DARUSSALAM - BANDA ACEH
2023
LEMBAR PENILAIAN

PRAKTIKUM PENGENDALIAN DAN PENJADWALAN PROYEK


KONSTRUKSI

Dikerjakan Oleh :
SAFRIL MUHAMAD ERWIN HIDAYAT
2004101010130

Untuk Memenuhi Sebagian Dari Syarat – syarat

KurikulumJurusan Teknik Sipil Fakultas Teknik

Universitas Syiah Kuala

Dan kepadanya diberikan Nilai :

( .......... )

Banda Aceh, Mei 2023

Dosen Pembimbing

Dr. Ir. Saiful Husin, M.T.


195501011987021001
Praktikum Perencanaan & Pengendalian Proyek Konstruksi

KATA PENGANTAR

Assalamualaikum Wr. Wb.


Segala puji dan syukur atas kehadirat Allah SWT yang telah memberikan rahmat
dan karunia-Nya yang tiada henti bagi kita semua terutama bagi penulis sehingga dapat
melaksanakan Praktikum Perencanaan dan Pengendalian Proyek Konstruksi dan
menyelesaikan laporan praktikum tepat pada waktunya. Tidak lupa pula shalawat
beriring salam penulis sanjungkan kepangkuan baginda Rasulullah SAW beserta
keluarganya yang mana atas perjuangan beliau lah kita dapat terhindar dari alam
kebodohan dan menuju ke alam yang penuh dengan ilmu pengetahuan.
Dalam melaksanakan proses praktikum dan penyusunan laporan Praktikum
Perencanaan dan Pengendalian Proyek Konstruksi ini, penulis telah banyak
mendapatkan pengarahan dan bimbingan yang sangat bermanfaat. Oleh karenanya,
dalam kesempatan ini penulis mengucapkan terima kasih kepada Bapak Dr. Ir. Saiful
Husin, S.T., MT. selaku dosen pembimbing mata kuliah Praktikum Perencanaan dan
Pengendalian Proyek Konstruksi, dan Kakak Cut Annisa WM, S.T. yang telah
meluangkan waktu, tenaga dan ilmu untuk membimbing penulis, sehingga tugas
praktikum ini dapat diselesaikan.
Penulis menyadari sepenuhnya bahwa dalam pelaksanaan dan penyusunan
laporan praktikum ini masih jauh dari kata sempurna, untuk itu penulis mengharapkan
kritik dan saran yang membangun demi kesempurnaan penulisan laporan dimasa
mendatang.
Akhirnya penulis mengharapkan semoga laporan Praktikum Perencanaan dan
Pengendalian Proyek Konstruksi ini dapat bermanfaat bagi penulis pribadi khususnya
dan rekan-rekan sesama mahasiswa Fakultas Teknik Unsyiah umumnya.

Banda Aceh, Mei 2023

Penulis i
Praktikum Perencanaan & Pengendalian Proyek Konstruksi

DAFTAR ISI

KATA PENGANTAR ................................................................................................................. i


DAFTAR ISI ............................................................................................................................... ii

BAB I PENDAHULUAN
1.1 Deskripsi Umum Proyek ..................................................................................... 1
1.2 Lokasi Proyek ...................................................................................................... 1
BAB II TINJAUAN PUSTAKA
2.1 Metode Penjadwalan Proyek Konstruksi ............................................................ 3
2.1.1 Bar Chart.....................................................................................................3
2.1.2 Kurva S........................................................................................................4
2.2 Work Breakdown Structure (WBS)..................................................................... 5
2.3 Logika Ketergantungan ....................................................................................... 6
2.4 Durasi Pekerjaan.................................................................................................. 8
2.5 Float dan Lintasan Kritis......................................................................................8
2.5.1 Float.............................................................................................................8
2.5.2 Total Float...................................................................................................9
2.5.3 Lintasan Kritis.............................................................................................9
BAB III RENCANA DAN PENJADWALAN PROYEK
3.1 Rencana Work Breakdown Structure (WBS) .................................................... 11
3.2 Analisis Hubungan Ketergantungan Antar Pekerjaan ....................................... 17
3.3 Analisis Durasi Pekerjaan ................................................................................. 22
3.4 Penjadwalan Proyek .......................................................................................... 22
3.4.1 Bar Chart dan Kurva S..............................................................................22
3.4.2 Network Planning.....................................................................................22
3.5 Analisis Float.....................................................................................................23
3.6 Analisis Lintasan Kritis.....................................................................................28
BAB IV KESIMPULAN DAN SARAN
4.1 Kesimpulan ........................................................................................................ 33
4.2 Saran .................................................................................................................. 34

DAFTAR PUSTAKA ................................................................................................................. 35


LAMPIRAN

ii
BAB I
Praktikum Perencanaan & Pengendalian Proyek Konstruksi

BAB I
PENDAHULUAN

1.1. Deskripsi Umum Proyek

Pusat Kesehatan Masyarakat (Puskesmas) merupakan salah satu pelayanan


kesehatan masyarakat yang amat penting. Kebutuhan akan gedung Puskesmas
pada saat ini terus bertambah, hal ini bersinergi dengan keinginan pemerintah
untuk meningkatkan kualitas kesehatan di berbagai daerah.
Permasalahan pembangunan gedung Puskesmas ini menjadi kompleks,
dimana dengan pertumbuhan penduduk yang kian meningkat, maka meningkat
pula kebutuhan akan pusat pelayan kesehatan masyarakat. Dalam hal ini,
keberadaan seorang estimator akan sangat membantu. Seorang estimator harus
mampu memperkirakan berapa anggaran dan waktu yang diperlukan untuk
pembangunan tersebut.
Untuk menghindari atau mengurangi resiko pembengkakan biaya yang tak
terkontrol, maka kita perlu mengetahui parameter utama yang sangat
mempengaruhi dalam hal pembuatan bangunan. Parameter itu antara lain yaitu
luas bangunan, tipe bangunan, lokasi proyek, material yang digunakan, hingga
uraian pekerjaan yang telah dirinci secara jelas yang dimulai dari tahapan awal
hingga tahapan akhir dimana bangunan tersebut siap digunakan.

1.2. Lokasi Proyek


Proyek pembangunan Puskesma berlantai dua memiliki luas bangunan
409,5 m2 ini berlokasi di Kecamatan Blangpidie Kabupaten Aceh Barat Daya.

1
Praktikum Perencanaan & Pengendalian Proyek Konstruksi

BAB I

5
Praktikum Perencanaan & Pengendalian Proyek Konstruksi

BAB II

TINJAUAN PUSTAKA

2.1 Metode Penjadwalan Proyek Konstruksi

2.1.1 Bar Chart

Bar chart adalah sekumpulan daftar kegiatan yang disusun dalam kolom
arah vertikal, dan kolom arah horizontal menunjukkan skala waktu. Saat mulai dan
akhir dari sebuah kegiatan dapat terlihat dengan jelas sedangkan durasi kegiatan
digam- barkan oleh panjangnya diagram batang. Bagan balok terdiri atas sumbu x
dan sumbu y, sumbu y yang menyatakan uraian kegiatan atau paket kerja dari
lingkup proyek se- dangkan sumbu x menyatakan durasi atau waktu yang
dibutuhkan dalam setiap aktifi- tas dengan satuan harian, mingguan dan bulanan.

Kelemahan atau kekurangan barchart adalah penyajian informasi bagan


balok- nya yang terbatas, maksudnya hubungan antar kegiatan tidak jelas. Lintasan
kritis kegiatan proyek tidak dapat diketahui, karena urutan kegiatan kurang terinci
maka bila terjadi keterlambatan proyek, prioritas kegiatan yang akan dikoreksi
menjadi sulit un- tuk dilakukan. Pada pengendalian waktu di lapangan agar semua
kegiatan dalam suatu proyek dapat diinformasikan secara lengkap maka pada
diagram batang ini disertakan kolom: volume pekerjaan, bobot pekerjaan,
persentase bobot pekerjaan rencana, per- sentase bobot pekerjaan aktual, deviasi
yang terjadi, dan bisa dilengkapi dengan kurva s.

Langkah pertama dalam menyiapkan sebuah bar chart adalah dengan men-
gidentifikasi daftar aktivitas yang ingin ditampilkan dalam sebuah schedule. Setelah
durasi dari setiap aktifitas diestimasi dan ditentukan, plot durasi tersebut pada
sumbu horizontal yang ada dan tentukanlah skala waktu yang tepat, bisa dalam hari,
minggu, bulan atau hari kalender, sesuai dengan yang dibutuhkan. Bar chart
biasanya digunakan untuk mengetahui waktu penyelesaian pekerjaan sehingga
proyek dapat diselesaikan tepat waktu, serta untuk mengetahui alternatif jalur
penyelesaian peker- jaan dan waktu penyelesaian jika melalui jalur tersebut.

3
Praktikum Perencanaan & Pengendalian Proyek Konstruksi

2.1.2 Kurva S
Kurva–S adalah suatu kurva yang disusun untuk menunjukkan hubungan an-
tara nilai kumulatif biaya atau jam-orang (man-hours) yang telah digunakan atau
per- sentase penyelesaian pekerjaan terhadap waktu. Kurva S menggambarkan
hubungan antara item pekerjaan dengan waktu/jadwal pelaksanaan dan biaya
kumulatif peker- jaan. Kurva S dapat memberikan gambaran kemajuan pekerjaan
terhadap waktu, di- mana kemajuan pekerjaan direfleksikan terhadap bobot
penyerapan biaya.
Kurva S dapat digunakan pada tahap perencanaan dan pengendalian proyek.
Pada tahap perencanaan terdapat kurva S rencana sebagai pedoman/acuan
pelaksanaan proyek. Sementara pada tahap tahap pengendalian, dapat digunakan
kurva S aktual sebagai pembanding dengan kurva S rencana. Pada Kurva–S, sumbu
mendatar menun-jukkan waktu kalender, dan sumbu vertikal.
Untuk menentukan bobot pekerjaan, pendekatan yang dilakukan dapat berupa
perhitungan persentase berdasarkan biaya per item pekerjaan/kegiatan dibagi total
anggaran atau berdasarkan volume rencana dari komponen kegiatan ter- hadap
volume total kegiatan. Kurva S dapat digunakan pada tahap perencanaan dan
pengendalian proyek. Pada tahap perencanaan terdapat kurva S rencana sebagai pe-
doman/acuan pelaksanaan proyek. Sementara pada tahap tahap pengendalian, dapat
digunakan kurva S aktual sebagai pembanding dengan kurva S rencana. Kurve yang
berbentuk huruf ”S” tersebut lebih banyak terbentuk karena kelaziman dalam
pelaksanaan proyek yaitu:
a) Kemajuan pada awal-awalnya bergerak lambat.

b) Kemudian diikuti oleh kegiatan yang bergerak cepat dalam kurun


waktu yang lebih lama.
c) Pada akhirnya kegiatan menurun kembali dan berhenti

4
Praktikum Perencanaan & Pengendalian Proyek Konstruksi

100%

Hari

2.2 Work Breakdown Structure (WBS)

Work Breakdown Structure (WBS) adalah suatu metode pengorganisasian


menjadi struktur pelaporan hiraerkis. WBS digunakan untuk melakukan breakdown
atau memecah tiap proses pekerjaan mejadi lebih detail. Hal ini dimaksudkan agar
proses perencanaan proyek memiliki tingkat yang lebih baik. WBS disusun ber-
dasarkan dasar pebelajaran seluruh dokumen proyek yang meliputi kontrak
,gambar-gambar, dan spesifikasi. Proyek kemudian diuraikan menjadi bagian-
bagian dengan mengikuti pola struktur dan hirarki tertentu menjadi item-item
pekerjaan yang cukup terperinci.

Work Breakdown Structure (WBS) merupakan suatu cara untuk membagi-


bagi pekerjaan suatu proyek konstruksi dan mempunyai sifat hirarkis dan logis,
yaitu makin lama makin terinci dengan lingkup yang juga mengecil, menjadi divisi-
divisi dan subdivisi pekerjaan sampai pada bagian terkecil, atau struktur rincian
lingkup kerja atau proyek dari kegiatan yang paling awal hingga kegiatan paling
akhir, sedangkan kompleksibilitasnya makin berkurang sampai akhirnya dianggap
cukup terinci tetapi masih dapat dikelola dengan baik.

Struktur WBS menyerupai gambar piramida di mana sebagai level satu yaitu
posisi puncak mengidentifikasikan proyek secara keseluruhan. Selanjutnya level 2
dibagi berdasarkan kriteria tertentu seperti bidang keahllian, lokasi peker- jaan,
atau urutan pelaksanaan pekerjaan. Demikian level-level di bawahnya disebut level
3, level 4, dan seterusnya sampai pada level terkecil yang disebut paket peker
jaan,yang disebut work package (WP) .

5
Praktikum Perencanaan & Pengendalian Proyek Konstruksi

2.3 Logika Ketergantungan

Logika ketergantungan antar pekerjaan memperlihatkan alur pekerjaan


hingga selesainya suatu proyek. Pekerjaan-pekerjaan tersebut saling berhubungan
dengan kata lain satu pekerjaan akan bergantung dengan pekerjaan lainnya. Oleh
karena itu, kita harus menganalisa ketergantungan antar pekerjaannya untuk
mengetahui tahapan pekerjaan pada sebuah proyek, ini semua dimaksudkan agar
proyek yang dibangun mencapai spesifikasi teknis yang diinginkan serta selesai
dalam waktu yang ditentukan. Logika ketergantungan ini nantinya akan
digunakan untuk membuat network planning.
Hubungan antar pekerjaan dalam sebuah proyek tidak semua sama. Ada
pekerjaan yang dikerjakan sebelum pekerjaan lain selesai. Ada juga pekerjaan
yang mulainya harus bersamaan atau selesainya harus bersamaan. Hubungan
ketergantungan antar pekerjaan dibedakan dalam beberapa macam :
1. Finish to Start (FS) : Hubungan ketergantungan dimana suatu pekerjaan
boleh dikerjakan setelah pekerjaan sebelumnya selesai.

2. Finish to Finish (FF) : Suatu hubungan ketergantungan dimana suat pekerjaan


harus selesai bersamaan dengan pekerjaan lain.

3. Start to Start (SS) : Suatu hubungan ketergantungan dimana suatu


pekerjaan dimulai bersamaan dengan pekerjaan lain.

6
Praktikum Perencanaan & Pengendalian Proyek Konstruksi

4. Start to Finish (SF) : Suatu hubungan ketergantungan dimana suatu


pekerjaan baru boleh selesai setelah pekerjaan lain mulai dikerjakan.

Hubungan Lag Time dan Lead Time


1. Lag Time merupakan tenggang waktu antara selesainya suatu pekerjaan
dengan dimulainya pekerjaan lain. Simbol : (+) atau %. Contoh : Predesessor
: 3FS + 3d, artinya pekerjaan pengecatan bisa dilaksanakan 3 hari setelah
pekerjaan plesteran selesai.

2. Lead Time merupakan penumpukan waktu antara selesainya suatu pekerjaan


dengan dimulainya pekerjaan lain. Simbol : (-) atau %. Contoh : 3FS-3d,
artinya pekerjaan plesteran harus dimulai 3 hari sebelum pemasangan genting
selesai.

7
Praktikum Perencanaan & Pengendalian Proyek Konstruksi

2.4 Durasi Pekerjaan

Setelah melakukan pengelompokan pekerjaan (Work Breakdown


Structure) dan mengitung volume pekerjaan, tahapan selanjutnya adalah
menentukan waktu pelaksanaan pekerjaan secara detail. Penjadwalan pekerjaan
meliputi penentuan durasi masing-masing pekerjaan, kapan suatu pekerjaan
dimulai dan kapan waktu selesainya, yang nantinya ketika semuanya
diakumulasikan akan menghasilkan durasi keseluruhan dari proyek. Dalam
menentukan durasi dari suatu pekerjaan biasanya digunakan formulasi sebagai
berikut :
𝑉𝑜𝑙𝑢𝑚𝑒
𝐷𝑢𝑟𝑎𝑠i = 𝑥 𝑃𝑟𝑜𝑑𝑢𝑘𝑡i𝑣i𝑡𝑎𝑠
𝐽𝑢𝑚𝑙𝑎ℎ 𝑇𝑒𝑛𝑎𝑔𝑎 𝐾𝑒𝑟j𝑎

Dari persamaan diatas dapat dilihat bahwa ada 3 faktor yang akan
mempengaruhi durasi pekerjaan, yaitu volume, produktivitas dan asumsi jumlah
pekerja. Tingkat produktivitas yang ditentukan berdasarkan nilai koefisien
tenaga kerja pada AHSP 2022, hubungan produktivitas dan koefesien adalah:

𝐼
𝑃=
𝐾

Hasil dari penjadwalan (schedulling) ini akan digunakan


sebagai dasar/informasi serta acuan bagi pengendalian yang akan
dilakukan. Dalam Pembangunan Gedung IGD Puskesmas Blangpidie,
Kabupaten Aceh Barat Daya, diperlukan waktu atau durasi dalam proses
pengerjaannya. Serta berapa banyak jumlah tenaga kerja yang akan dipakai untuk
proyek tersebut. Maka dari itu perlu adanya perencanaan durasi proyek serta
jumlah tenaga kerjanya.

2.5 Analisis Float dan Lintasan Kritis

2.5.1 Float

Float digunakan untuk menentukan jalur kritis suatu proyek. Waktu


penyelesaian proyek umumnya tidak sama dengan total waktu hasil penjumlahan

8
Praktikum Perencanaan & Pengendalian Proyek Konstruksi

kurun waktu masing-masing kegiatan yang menjadi unsur proyek, karena adanya
kegiatan yang paralel. Bila jaringan kerja hanya mempunyai satu titik awal
(initial node) dan satu titik akhir (terminal node), maka jalur kritis juga berarti
jalur yang memiliki jumlah waktu penyelesaian terbesar/terlama, dan jumlah
waktu tersebut merupakan waktu proyek yang tercepat. Kadang dijumpai lebih
dari satu jalur kritis dalam sebuah jaringan kerja.
2.5.2 Total Float

Total float suatu kegiatan sama dengan waktu selesai paling akhir,
dikurangi waktu selesai paling awal, atau waktu mulai paling akhir dikurangi
waktu mulai paling awal dari kegiatan tersebut.
TF = LF – EF

= LS – ES
Arti penting dari float total adalah menunjukkan jumlah waktu yang
diperkenankan suatu kegiatan boleh ditunda, tanpa mempengaruhi jadwal
penyelesaian proyek secara keseluruhan.
2.5.3 Lintasan Kritis
Lintasan kristis (critical path) adalah lintasan terpanjang, dalam hal total
waktu, diantara semua lintasan yang ada pada suatu network diagram.
Lintasan kritis inilah yang akan menentukan total durasi tercepat untuk
menyelesaikan semua kegiatan pada proyek tersebut.
Kegiatan-kegiatan yang berada pada lintasan kristis adalah kegiatan kritis,
yang harus dapat diselesaikan sesuai dengan waktu yang telah direncanakan.
Apabila ada satu kegiatan saja yang pelaksanaannya terlambat atau tertunda, akan
menyebabkan keterlambatan penyelesaian proyek secara keseluruhan.
Pada tampilan Network Diagram, kegiatan-kegiatan yang berada pada
lintasan kritis secara otomatis sudah ditampilkan dengan format warna merah.
Tetapi tidak demikian pada tampilan Gantt Chart, dimana kegiatan kritis maupun
kegiatan non- kritis ditampilkan dengan format warna yang sama, jadi harus
terlebih dahulu diubah ke format critical task dan Warna balok yang
menggambarkan kegiatan kritis akan berubah, yang merupakan jalur kritis akan
keluar keterangan YES sedangkan yang tidak akan berketerangan NO.

9
BAB III

10
BAB III
RENCANA PENJADWALAN PROYEK

3.1 Rencana Work Breakdown Structure (WBS)

WBS Pembangunan RPS SMKN 1 Darul Kamal

WBS URAIAN PEKERJAAN


1 PEKERJAAN PERSIAPAN
1.1 Papan Nama Proyek Uk. 90 x120
1.2 Administrasi/Dokumentasi dan Pelaporan
1.3 Direksi Keet/sewa
1.4 Perlengkapan P3k
1.5 Pengukuran dan Pemasangan Bouwplank
1.6 Pagar Pelindung Proyek
1.7 Rencana Keselamatan dan Kesehatan Kerja

2 PEKERJAAN TANAH
2.1 PEKERJAAN GALIAN
2.1.1 Galian Tanah Pondasi Menerus
2.1.2 Galian Tanah Pondasi Tapak
2.2 PEKERJAAN TIMBUNAN
2.2.1 Urugan Kembali Bekas Galian
2.2.2 Pasir Urugan Bawah Pondasi
2.2.3 Pasir Urugan dibawah Lantai
2.2.4 Timbunan Tanah Dibawah Lantai

3 PEKERJAAN STRUKTUR
3.1 LANTAI 1
3.1.1 PEKERJAAN PONDASI TAPAK BETON BERTULANG
3.1.1.1 Lantai Kerja Pondasi Tapak Setempat ( K.175)
3.1.2 Pekerjaan Beton Bertulang Pondasi Tapak
3.1.2.1 Cor Beton K 250
3.1.2.2 Pembesian
3.1.2.3 Bekisting
3.1.3 Pekerjaan Pondasi Menerus
3.1.3.1 Anstamping / Pasangan Batu Kosong Tebal 10 Cm
3.1.3.2 Pasangan Pondasi Batu Gunung 1 PC : 4 PS
3.1.4 Sloof (30/40)
3.1.4.1 Pembesian
3.1.4.2 Bekisting
3.1.4.3 Cor Beton K 250
3.1.5 Sloof (15/20)

11
3.1.5.1 Pembesian
3.1.5.2 Bekisting
3.1.5.3 Cor Beton K 175
3.1.6 Kolom Uk. 30/40
3.1.6.1 Pembesian
3.1.6.2 Bekisting
3.1.6.3 Cor Beton K 250
3.1.7 Kolom Uk. 15/15
3.1.7.1 Pembesian
3.1.7.2 Bekisting
3.1.7.3 Cor Beton K 175
3.1.8 Balok Latai (13/13) Elevasi ± 2.23 m
3.1.8.1 Pembesian
3.1.8.2 Bekisting
3.1.8.3 Cor Beton K 175
3.1.9 Ring Balok Uk. 25/40 Elevasi ± 3.45 m
3.1.9.1 Pembesian
3.1.9.2 Bekisting
3.1.9.3 Cor Beton K 250
3.1.10 Ring Balok Uk. 15/20 Elevasi ± 3.45 m
3.1.10.1 Pembesian
3.1.10.2 Bekisting
3.1.10.3 Cor Beton K 175
3.1.11 Plat Tangga dan Plat Bordes Tebal 10cm
3.1.11.1 Pembesian
3.1.11.2 Bekisting
3.1.11.3 Cor Beton K 250
3.2 LANTAI 2
3.2.1 Kolom Uk. 30/30
3.2.1.1 Pembesian
3.2.1.2 Bekisting
3.2.1.3 Cor Beton K 250
3.2.2 Kolom Uk. 15/15
3.2.2.1 Pembesian
3.2.2.2 Bekisting
3.2.2.3 Cor Beton K 175
3.2.3 Balok Latai (13/13) Elevasi ± 6.23 m
3.2.3.1 Pembesian
3.2.3.2 Bekisting
3.2.3.3 Cor Beton K 175
3.2.4 Ring Balok Uk. 25/40 Elevasi ± 7.50 m
3.2.4.1 Pembesian
3.2.4.2 Bekisting
3.2.4.3 Cor Beton K 250
3.2.5 Ring Balok Uk. 15/20 Elevasi ±7.5 m
3.2.5.1 Pembesian
3.2.5.2 Bekisting
12
3.2.5.3 Cor Beton K 175
3.2.6 Plat Lantai Tebal 12cm
3.2.6.1 Pembesian
3.2.6.2 Bekisting
3.2.6.3 Cor Beton K 250
3.2.7 Plat dak dan Talang Beton
3.2.7.1 Pembesian
3.2.7.2 Bekisting
3.2.7.3 Cor Beton K 250
3.2.8 PEKERJAAN ATAP
3.2.8.1 Rangka kuda-kuda dan gording baja ringan Multytruss

4 PEKERJAAN ARSITEKTUR
4.1 LANTAI 1
4.1.1 Pekerjaan Dinding
4.1.2 Pekerjaan Lantai
4.1.2.1 Pekerjaan Beton Tumbuk Tebal 7 cm (K 125)
4.1.2.2 Pekerjaan Lantai Granite 60 x 60 Cm (Halus)
4.1.2.3 Pekerjaan Lantai Granite 60 x 60 Cm (Kasar)
4.1.2.4 Pekerjaan Lantai Keramik untuk Ruangan Wc/Km 20 X 20 Cm
4.1.2.5 Pasangan Dinding Keramik KM/WC 20 x 25 cm
4.1.3 Pekerjaan Pintu, Jendela, Ventilasi
Pintu Panel Kaca Tempered Glass 12mm + Aksesoris Lengkap
4.1.3.1
Terpasang (Type P1)
Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris Lengkap
4.1.3.2
Terpasang Sesuai Gambar ( Type P2)
Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris Lengkap
4.1.3.3
Terpasang Sesuai Gambar ( Type P5)
Kusen UPVC + Daun Pintu UPVC+ Aksesoris Lengkap
4.1.3.4
Terpasang Sesuai Gambar (Type P4)
Kusen UPVC + Daun Pintu UPVC+ Aksesoris Lengkap
4.1.3.5
Terpasang Sesuai Gambar (Type P3)
Kusen UPVC + Daun Jendela dan Ventilasi Kaca 5mm +
4.1.3.6
Aksesoris Lengkap Terpasang Sesuai Gambar (Type JV1)
Kusen UPVC + Daun Jendela dan Ventilasi Kaca 5mm +
4.1.3.7
Aksesoris Lengkap Terpasang Sesuai Gambar (Type J2)
Kusen UPVC + Daun ventilasi Kaca 5mm + Aksesoris Lengkap
4.1.3.8
Terpasang Sesuai Gambar (Type V2)
4.1.4 Pekerjaan Plafond
Pasang Plafon PVC/Fiber + Rangka + Aksesoris Lengkap
4.1.4.1
Terpasang Sesuai Gambar
4.1.5 Pekerjaan Pengecatan
4.1.5.1 Pengecatan Tembok dan Sealer 3x(L/D) Setara Vinilex
4.2 LANTAI 2
4.2.1 Pekerjaan Dinding
4.2.1.1 Pasangan Trasram Bata 1 PC : 2 PP
4.2.1.2 Pasangan Dinding Bata 1 PC : 4 PP
4.2.1.3 Plesteran Trasram Bata 1 PC : 2 PP
4.2.1.4 Plesteran Dinding Bata 1PC : 4 PP
13
4.2.1.5 Plasteran Beton 1 PC : 3 PP
4.2.1.6 Pesangan Batu Alam Tempel Susun Sirih + cat Vernis Batu Alam
4.2.2 Pekerjaan Lantai
4.2.2.1 Pekerjaan Beton Tumbuk Tebal 7 cm (K 125)
4.2.2.2 Pekerjaan Lantai Granite 60 x 60 Cm (Halus)
4.2.2.3 Pekerjaan Lantai Keramik untuk Ruangan Wc/Km 20 X 20 Cm
4.2.2.4 Pasangan Dinding Keramik KM/WC 20 x 25 cm
4.2.3 Pekerjaan Pintu, Jendela, Ventilasi
Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris Lengkap
4.2.3.1
Terpasang Sesuai Gambar ( Type P2)
Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris Lengkap
4.2.3.2
Terpasang Sesuai Gambar ( Type P5)
Kusen UPVC + Daun Pintu UPVC+ Aksesoris Lengkap
4.2.3.3
Terpasang Sesuai Gambar (Type P4)
Kusen UPVC + Daun Pintu UPVC+ Aksesoris Lengkap
4.2.3.4
Terpasang Sesuai Gambar (Type P3)
Kusen UPVC + Daun Jendela dan Ventilasi Kaca 5mm +
4.2.3.5
Aksesoris Lengkap Terpasang Sesuai Gambar (Type JV1)
Kusen UPVC + Daun Jendela dan Ventilasi Kaca 5mm +
4.2.3.6
Aksesoris Lengkap Terpasang Sesuai Gambar (Type J2)
Kusen UPVC + Daun ventilasi Kaca 5mm + Aksesoris Lengkap
4.2.3.7
Terpasang Sesuai Gambar (Type V2)
4.2.4 PEKERJAAN ATAP
4.2.4.1 Penutup Atap genteng Onduline
4.2.4.2 Rabung genteng Onduline
4.2.4.3 Lisplank Kalsiboard 300 X 2400 X 8 mm Bermotif
4.2.5 Pekerjaan Plafond
Pasang Plafon PVC/Fiber + Rangka + Aksesoris Lengkap
4.2.5.1
Terpasang Sesuai Gambar
4.2.6 Pekerjaan Pengecatan
4.2.6.1 Pengecatan Tembok dan Sealer 3x(L/D) Setara Vinilex

5 PEKERJAAN ELEKTRIKAL
Instlasi titik penerangan, instalasi termasuk kabel NYA 2,5 mm
5.1
dalam pipa PVC fitting lampu dan kelengkapan instalasi terpasang
Instalasi titik Stop kontak, instalasi termasuk kabel NYA 2,5 mm
5.2
dalam pipa PVC fitting lampu dan kelengkapan instalasi terpasang
5.3 Pemasangan Box Sekring
5.4 Pemasukan Arus Listrik 12 Ampere
5.5 LANTAI 1
5.5.1 Armatur
5.5.1.1 Lampu Downlight 23 watt + Accesori Lengkap Terpasang
5.5.1.2 Lampu RM TL 2X36 watt + Accesori Lengkap Terpasang
5.5.2 Saklar lampu Merk Setara Broco 2 seri
5.5.2.1 Sakalar 1 Seri setara Broco
5.5.2.2 Sakalar 2 Seri setara Broco
5.5.2.3 Stop Kontak
5.6 LANTAI 2
5.6.1 Armatur
14
5.6.1.1 Lampu Downlight 23 watt + Accesori Lengkap Terpasang
5.6.1.2 Lampu RM TL 2X36 watt + Accesori Lengkap Terpasang

6 PEKERJAAN MEKANIKAL
PEKERJAAN BESI, ALUMUNIUM, ORNAMEN DAN
6.1
DINDING COMPOSITE
Pekerjaan Almunium Composite Panel Setara Seven Type PVDF +
6.1.1
Rangka + Aksesoris Lengkap Terpasang Sesuai Gambar
Huruf Timbul Gedung IGD + Aksesoris Lengkap Terpasang Sesuai
6.1.2
Gambar (Bahan Stainless)
Huruf Timbul Gedung Utama + Aksesoris Lengkap Terpasang
6.1.3
Sesuai Gambar (Bahan Stainless)
Logo Puskesmas + Aksesoris Lengkap Terpasang Sesuai Gambar
6.1.4
(Bahan Stainless)
Reling Tangga Stainless + Aksesoris Lengkap Terpasang Sesuai
6.1.5
Gambar
Handrail (Pegangan Tangan) Stainless + Aksesoris Lengkap
6.1.6
Terpasang Sesuai Gambar
6.2 PEKERJAAN SALURAN DRAINASE
6.2.1 Galian Tanah Saluran
6.2.2 Pasangan Bata Dinding Saluran 1 PC : 2 PP
6.2.3 Pasangan Plasteran Bata Dinding Saluran 1 PC : 2 PP
6.2.4 Cor Lantai Saluran
6.2.5 Buis Beton Dia. 20 cm
6.2.6 Pemasangan Grill Saluran Bentuk Sesuai Gambar + Cat Meni Hitam
6.3 LANTAI 1
6.3.1 Pekerjaan Sanitasi
6.3.1.1 INSTALASI AIR KOTOR
6.3.1.1.1 Pasang Flordrain
6.3.1.1.2 Pipa SNI 3 Inch AW
6.3.1.2 INSTALASI AIR BERSIH
Memasang Wastafel + Keran Air + Pembungan Air Type Sifon
6.3.1.2.1
angsa Aksesoris Lengkap Terpasang Setara Toto
6.3.1.2.2 Pipa SNI 1/2 Inch AW
6.3.1.2.3 Pasang Pipa Air Sampai Ketitik Air
6.3.1.3 INSTALASI AIR HUJAN
6.3.1.3.1 Pipa SNI 2 1/2 Inch AW
6.3.1.4 INSTALASI KOTORAN
6.3.1.4.1 Pipa SNI 3 Inch AW
6.3.1.4.2 Septick Tank + Resapan Lengkap Terpasang
6.3.1.4.3 Pasang Kloset Duduk SetaraToto
6.4 LANTAI 2
6.4.1 Pekerjaan Sanitasi
6.4.1.1 INSTALASI AIR BERSIH
6.4.1.1.1 Bak Mandi Pyber Glass (60 x 60)
6.4.1.1.2 Pasang Kran Air 1/2"
6.4.1.1.3 Pipa SNI 1 Inch AW
6.4.1.1.4 Pipa SNI 1/2 Inch AW

15
6.4.1.1.5 Pasang Pipa Air Sampai Ketitik Air
6.4.1.2 INSTALASI AIR KOTOR
6.4.1.2.1 Pipa SNI 3 Inch AW
6.4.1.2.2 Pasang Flordrain
6.4.1.3 INSTALASI KOTORAN
6.4.1.3.1 Pipa SNI 3 Inch AW
6.4.1.3.2 Pasang Kloset Jongkok Setara American Standar
6.4.1.4 INSTALASI AIR HUJAN
6.4.1.4.1 Pipa SNI 2 1/2 Inch AW

7 PEKERJAAN FINISHING
7.1 Pekerjan Pot Bunga
7.1.1 Pasangan Dinding Bata 1PC : 4 PP
7.1.2 Plasteran Dinding Bata 1PC : 4 PP
7.1.3 Pesangan Batu Alam Tempel Susun Sirih + Cat Vernis Batu Alam
7.1.4 Relif Pot Bunga Sesuai Gambar
7.2 Pembentukan Relif Pada Kolom Lengkap Terpasang Sesuai Gambar
7.3 Pembentukan Relif Pada Dinding Lengkap Terpasang Sesuai Gambar
7.4 Pembersihan Akhir

16
Praktikum Perencanaan & Pengendalian Proyek Konstruksi

3.2 Analisis Hubungan Ketergantungan Antar Pekerjaan

No WBS Uraian Pekerjaan Durasi Predesesor

1 1 PEKERJAAN PERSIAPAN 6 days


2 1.1 Papan Nama Proyek Uk. 90 x120 1 day
3 1.2 Administrasi/Dokumentasi dan Pelaporan 1 day 2SS
4 1.3 Direksi Keet/sewa 6 days 2SS
5 1.4 Perlengkapan P3k 1 day 2SS
6 1.5 Pengukuran dan Pemasangan Bouwplank 2 days 2SS
7 1.6 Pekerjaan Kesehatan dan Keselamatan Kerja 1 day 2SS
8 1.7 Pagar pelindung proyek 2 days 2SS
9 2 PEKERJAAN TANAH 36 days
10 2.1 PEKERJAAN GALIAN 8 days
11 2.1.1 Galian Tanah Pondasi Tapak 4 days 8
12 2.1.2 Galian Tanah Pondasi Menerus 4 days 11
13 2.2 PEKERJAAN TIMBUNAN 28 days
14 2.2.1 Urugan Kembali Bekas Galian 4 days 188
15 2.2.2 Pasir Urugan Bawah Pondasi Menerus 5 days 12
16 2.2.3 Pasir Urugan dibawah Lantai 3 days 17
17 2.2.4 Timbunan Tanah Dibawah Lantai 9 days 14
18 3 PEKERJAAN STRUKTUR 88 days
19 3.1 LANTAI 1 1 day
20 3.2 PEKERJAAN PONDASI TAPAK BETON BERTULANG 51 days
21 3.2.1 Lantai Kerja Pondasi Tapak Setempat ( K.175) 1 day 11
22 3.2.2 Pekerjaan Beton Bertulang Pondasi Tapak 9 days
23 3.2.2.1 Cor Beton K 250 2 days 25
24 3.2.2.2 Pembesian 5 days 21
25 3.2.2.3 Bekisting 2 days 24
26 3.2.3 Pekerjaan Pondasi Menerus 5 days
27 3.2.3.1 Anstamping / Pasangan Batu Kosong Tebal 10 Cm 2 days 23
28 3.2.3.2 Pasangan Pondasi Batu Gunung 1 PC : 4 PS 3 days 27
29 3.2.4 Sloof (30/40) 7 days
30 3.2.4.1 Pembesian 2 days 28
31 3.2.4.2 Bekisting 3 days 30
32 3.2.4.3 Cor Beton K 250 2 days 31
33 3.2.5 Sloof (15/20) 3 days
34 3.2.5.1 Pembesian 1 day 28
35 3.2.5.2 Bekisting 1 day 34
36 3.2.5.3 Cor Beton K 175 1 day 35
37 3.2.6 Kolom Uk. 30/40 6 days
38 3.2.6.1 Pembesian 2 days 32
39 3.2.6.2 Bekisting 2 days 38
40 3.2.6.3 Cor Beton K 250 2 days 39

17
Praktikum Perencanaan & Pengendalian Proyek Konstruksi

41 3.2.7 Kolom Uk. 15/15 3 days


42 3.2.7.1 Pembesian 1 day 40
43 3.2.7.2 Bekisting 1 day 42
44 3.2.7.3 Cor Beton K 175 1 day 43
45 3.2.8 Balok Latai (13/13) Elevasi ± 2.23 m 3 days
46 3.2.8.1 Pembesian 1 day 47
47 3.2.8.2 Bekisting 2 days 96
48 3.2.8.3 Cor Beton K 175 1 day 47
49 3.2.9 Balok Uk. 25/40 Elevasi ± 3.45 m 5 days
50 3.2.9.1 Pembesian 2 days 96
51 3.2.9.2 Bekisting 2 days 54
52 3.2.9.3 Cor Beton K 250 2 days 51
53 3.2.10 Ring Balok Uk. 15/20 Elevasi ± 3.45 m 3 days
54 3.2.10.1 Pembesian 1 day 96
55 3.2.10.2 Bekisting 1 day 54
56 3.2.10.3 Cor Beton K 175 1 day 55
57 3.2.11 Plat Tangga dan Plat Bordes Tebal 10cm 3 days
58 3.2.11.1 Pembesian 1 day 85
59 3.2.11.2 Bekisting 1 day 58
60 3.2.11.3 Cor Beton K 250 1 day 59
61 3.3 LANTAI 2 42 days
62 3.3.1 Kolom Uk. 30/30 6 days
63 3.3.1.1 Pembesian 2 days 60
64 3.3.1.2 Bekisting 2 days 63
65 3.3.1.3 Cor Beton K 250 2 days 64
66 3.3.2 Kolom Uk. 15/15 4 days
67 3.3.2.1 Pembesian 1 day 65
68 3.3.2.2 Bekisting 2 days 67
69 3.3.2.3 Cor Beton K 175 1 day 68
70 3.3.3 Balok Latai (13/13) Elevasi ± 6.23 m 2 days
71 3.3.3.1 Pembesian 1 day 123
72 3.3.3.2 Bekisting 1 day 123
73 3.3.3.3 Cor Beton K 175 1 day 72
74 3.3.4 Ring Balok Uk. 25/40 Elevasi ± 7.50 m 6 days
75 3.3.4.1 Pembesian 2 days 123
76 3.3.4.2 Bekisting 2 days 75
77 3.3.4.3 Cor Beton K 250 2 days 76
78 3.3.5 Ring Balok Uk. 15/20 Elevasi ±7.5 m 3 days
79 3.3.5.1 Pembesian 1 day 123
80 3.3.5.2 Bekisting 1 day 79
81 3.3.5.3 Cor Beton K 175 1 day 80
82 3.3.6 Plat Lantai Tebal 12cm 8 days
83 3.3.6.1 Pembesian 4 days 84
84 3.3.6.2 Bekisting 2 days 52

18
Praktikum Perencanaan & Pengendalian Proyek Konstruksi

85 3.3.6.3 Cor Beton K 250 2 days 83


86 3.3.7 Plat dak dan Talang Beton 3 days
87 3.3.7.1 Pembesian 1 day 77
88 3.3.7.2 Bekisting 1 day 87
89 3.3.7.3 Cor Beton K 250 1 day 88
90 3.3.8 PEKERJAAN ATAP 8 days
Rangka kuda-kuda dan gording baja ringan
91 3.3.8.1 8 days 89
Multytruss
92 4 PEKERJAAN ARSITEKTUR 88 days
93 4.1 LANTAI 1 42 days
94 4.1.1 Pekerjaan Dinding 18 days
95 4.1.1.1 Pasangan Trasram Bata 1 PC : 2 PP 1 day 40
96 4.1.1.2 Pasangan Dinding Bata 1 PC : 4 PP 6 days 95
97 4.1.1.3 Plesteran Trasram Bata 1 PC : 2 PP 1 day 184
98 4.1.1.4 Plesteran Dinding Bata 1PC : 4 PP 9 days 97
99 4.1.1.5 Plasteran Beton 1 PC : 3 PP 7 days 97
Pesangan Batu Alam Tempel Susun Sirih + cat
100 4.1.1.6 2 days 98
Vernis Batu Alam
101 4.1.2 Pekerjaan Lantai 27 days
102 4.1.2.1 Pekerjaan Beton Tumbuk Tebal 7 cm (K 125) 1 day 16
103 4.1.2.2 Pekerjaan Lantai Granite 60 x 60 Cm (Halus) 5 days 117
104 4.1.2.3 Pekerjaan Lantai Granite 60 x 60 Cm (Kasar) 3 days 103
Pekerjaan Lantai Keramik untuk Ruangan Wc/Km
105 4.1.2.4 1 day 104
20 X 20 Cm
106 4.1.2.5 Pasangan Dinding Keramik KM/WC 20 x 25 cm 2 days 105
107 4.1.3 Pekerjaan Pintu, Jendela, Ventilasi 38 days
Pintu Panel Kaca Tempered Glass 12mm +
108 4.1.3.1 1 day 160
Aksesoris Lengkap Terpasang (Type P1)
Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris
109 4.1.3.2 2 days 160
Lengkap Terpasang Sesuai Gambar ( Type P2)
Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris
110 4.1.3.3 1 day 16
Lengkap Terpasang Sesuai Gambar ( Type P5)
Kusen UPVC + Daun Pintu UPVC+ Aksesoris
111 4.1.3.4 1 day 160
Lengkap Terpasang Sesuai Gambar (Type P4)
Kusen UPVC + Daun Pintu UPVC+ Aksesoris
112 4.1.3.5 1 day 160
Lengkap Terpasang Sesuai Gambar (Type P3)
Kusen UPVC + Daun Jendela dan Ventilasi Kaca
113 4.1.3.6 5mm + Aksesoris Lengkap Terpasang Sesuai Gambar 2 days 160
(Type JV1)
Kusen UPVC + Daun Jendela dan Ventilasi Kaca
114 4.1.3.7 5mm + Aksesoris Lengkap Terpasang Sesuai Gambar 1 day 16
(Type J2)
Kusen UPVC + Daun ventilasi Kaca 5mm +
115 4.1.3.8 1 day 160
Aksesoris Lengkap Terpasang Sesuai Gambar (Type V2)
116 4.1.4 Pekerjaan Plafond 4 days
Pasang Plafon PVC/Fiber + Rangka + Aksesoris
117 4.1.4.1 4 days 98
Lengkap Terpasang Sesuai Gambar
118 4.1.5 Pekerjaan Pengecatan 4 days
Pengecatan Tembok dan Sealer 3x(L/D) Setara
119 4.1.5.1 4 days 106
Vinilex
120 4.2 LANTAI 2 59 days
121 4.2.1 Pekerjaan Dinding 43 days
122 4.2.1.1 Pasangan Trasram Bata 1 PC : 2 PP 2 days 65

19
Praktikum Perencanaan & Pengendalian Proyek Konstruksi

123 4.2.1.2 Pasangan Dinding Bata 1 PC : 4 PP 6 days 122


124 4.2.1.3 Plesteran Trasram Bata 1 PC : 2 PP 1 day 91
125 4.2.1.4 Plesteran Dinding Bata 1PC : 4 PP 14 days 124
126 4.2.1.5 Plasteran Beton 1 PC : 3 PP 3 days 125
Pesangan Batu Alam Tempel Susun Sirih + cat
127 4.2.1.6 2 days 125
Vernis Batu Alam
128 4.2.2 Pekerjaan Lantai 10 days
129 4.2.2.1 Pekerjaan Beton Tumbuk Tebal 7 cm (K 125) 2 days 125
130 4.2.2.2 Pekerjaan Lantai Granite 60 x 60 Cm (Halus) 5 days 145
Pekerjaan Lantai Keramik untuk Ruangan Wc/Km
131 4.2.2.3 1 day 130
20 X 20 Cm
132 4.2.2.4 Pasangan Dinding Keramik KM/WC 20 x 25 cm 1 day 131
133 4.2.3 Pekerjaan Pintu, Jendela, Ventilasi 1 day
Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris
134 4.2.3.1 1 day 168
Lengkap Terpasang Sesuai Gambar ( Type P2)
Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris
135 4.2.3.2 1 day 168
Lengkap Terpasang Sesuai Gambar ( Type P5)
Kusen UPVC + Daun Pintu UPVC+ Aksesoris
136 4.2.3.3 1 day 168
Lengkap Terpasang Sesuai Gambar (Type P4)
Kusen UPVC + Daun Jendela dan Ventilasi Kaca
137 4.2.3.4 5mm + Aksesoris Lengkap Terpasang Sesuai Gambar 1 day 168
(Type JV1)
Kusen UPVC + Daun Jendela dan Ventilasi Kaca
138 4.2.3.5 5mm + Aksesoris Lengkap Terpasang Sesuai Gambar 1 day 168
(Type J2)
Kusen UPVC + Daun ventilasi Kaca 5mm +
139 4.2.3.6 1 day 168
Aksesoris Lengkap Terpasang Sesuai Gambar (Type V2)
140 4.2.4 PEKERJAAN ATAP 10 days
141 4.2.4.1 Penutup Atap genteng Onduline 5 days 91
142 4.2.4.2 Rabung genteng Onduline 2 days 141
143 4.2.4.3 Lisplank Kayu 2/20 cm 3 days 142
144 4.2.5 Pekerjaan Plafond 3 days
Pasang Plafon PVC/Fiber + Rangka + Aksesoris
145 4.2.5.1 3 days 125
Lengkap Terpasang Sesuai Gambar
146 4.2.6 Pekerjaan Pengecatan 4 days
Pengecatan Tembok dan Sealer 3x(L/D) Setara
147 4.2.6.1 4 days 132
Vinilex
148 5 PEKERJAAN ELEKTRIKAL 52 days
Instlasi titik penerangan, instalasi termasuk kabel
149 5.1 NYA 2,5 mm dalam pipa PVC fitting lampu dan 1 day 119
kelengkapan instalasi terpasang
Instalasi titik Stop kontak, instalasi termasuk kabel
150 5.2 NYA 2,5 mm dalam pipa PVC fitting lampu dan 1 day 119
kelengkapan instalasi terpasang
151 5.3 Pemasangan Box Sekring 1 day 119
152 5.4 Pemasukan Arus Listrik 12 Ampere 1 day 119
153 5.5 LANTAI 1 4 days
154 5.5.1 Armatur 2 days
Lampu Downlight 23 watt + Accesori Lengkap
155 5.5.1.1 1 day 150
Terpasang
Lampu RM TL 2X36 watt + Accesori Lengkap
156 5.5.1.2 1 day 155
Terpasang
157 5.5.2 Saklar lampu Merk Setara Broco 2 seri 2 days
158 5.5.2.1 Sakalar 1 Seri setara Broco 1 day 156

20
Praktikum Perencanaan & Pengendalian Proyek Konstruksi

159 5.5.2.2 Sakalar 2 Seri setara Broco 1 day 156


160 5.5.2.3 Stop Kontak 1 day 159
161 5.6 LANTAI 2 4 days
162 5.6.1 Armatur 2 days
Lampu Downlight 23 watt + Accesori Lengkap
163 5.6.1.1 1 day 147
Terpasang
Lampu RM TL 2X36 watt + Accesori Lengkap
164 5.6.1.2 1 day 163
Terpasang
165 5.6.2 Saklar lampu Merk Setara Broco 2 seri 2 days
166 5.6.2.1 Sakalar 1 Seri setara Broco 1 day 164
167 5.6.2.2 Sakalar 2 Seri setara Broco 1 day 164
168 5.6.2.3 Stop Kontak 1 day 167
169 6 PEKERJAAN MEKANIKAL 132 days
170 6.1 PEKERJAAN SALURAN DRAINASE 10 days
171 6.1.1 Pasangan Bata Dinding Saluran 1 PC : 2 PP 2 days 136
Pasangan Plasteran Bata Dinding Saluran 1 PC : 2
172 6.1.2 2 days 171
PP
173 6.1.3 Cor Lantai Saluran 2 days 172
174 6.1.4 Buis Beton Dia. 20 cm 2 days 173
Pemasangan Grill Saluran Bentuk Sesuai Gambar +
175 6.1.5 2 days 174
Cat Meni Hitam
176 6.2 LANTAI 1 96 days
177 6.2.1 Pekerjaan Sanitasi 1 day
178 6.2.2 INSTALASI AIR KOTOR 3 days
179 6.2.2.1 Pasang Floordrain 1 day 105
180 6.2.2.2 Pipa SNI 3 Inch AW 1 day 106
181 6.2.3 INSTALASI AIR BERSIH 27 days
Memasang Wastafel + Keran Air + Pembungan Air
182 6.2.3.1 Type Sifon angsa Aksesoris Lengkap Terpasang Setara 1 day 106
Toto
183 6.2.3.2 Pipa SNI 1/2 Inch AW 1 day 102
184 6.2.3.3 Pasang Pipa Air Sampai Ketitik Air 1 day 102
185 6.2.4 INSTALASI AIR HUJAN 1 day
186 6.2.4.1 Pipa SNI 2 1/2 Inch AW 1 day 142
187 6.2.5 INSTALASI KOTORAN 43 days
188 6.2.5.1 Pipa SNI 3 Inch AW 1 day 28
189 6.2.5.2 Septick Tank + Resapan Lengkap Terpasang 1 day 188
190 6.2.5.3 Pasang Kloset Duduk SetaraToto 1 day 105
191 6.3 LANTAI 2 114 days
192 6.3.1 Pekerjaan Sanitasi 1 day
193 6.3.2 INSTALASI AIR BERSIH 64 days
194 6.3.2.1 Bak Mandi Pyber Glass (60 x 60) 1 day 132
195 6.3.2.2 Pasang Kran Air 1/2" 1 day 98
196 6.3.2.3 Pipa SNI 1 Inch AW 1 day 98
197 6.3.2.4 Pipa SNI 1/2 Inch AW 1 day 98
198 6.3.2.5 Pasang Pipa Air Sampai Ketitik Air 1 day 98
199 6.3.3 INSTALASI AIR KOTOR 64 days
200 6.3.3.1 Pipa SNI 3 Inch AW 1 day 98

21
Praktikum Perencanaan & Pengendalian Proyek Konstruksi

201 6.3.3.2 Pasang Flordrain 1 day 132


202 6.3.4 INSTALASI KOTORAN 19 days
203 6.3.4.1 Pipa SNI 3 Inch AW 1 day 142
204 6.3.4.2 Pasang Kloset Jongkok Setara American Standar 1 day 132
205 6.3.5 INSTALASI AIR HUJAN 1 day
206 6.3.5.1 Pipa SNI 2 1/2 Inch AW 1 day 142
207 7 PEKERJAAN FINISHING 10 days
PEKERJAAN BESI, ALUMUNIUM, ORNAMEN DAN
208 7.1 5 days
DINDING COMPOSITE
Pekerjaan Almunium Composite Panel Setara Seven
209 7.1.1 Type PVDF + Rangka + Aksesoris Lengkap Terpasang 3 days 175
Sesuai Gambar
Huruf Timbul Gedung IGD + Aksesoris Lengkap
210 7.1.2 2 days 209
Terpasang Sesuai Gambar (Bahan Stainless)
Huruf Timbul Gedung Utama + Aksesoris Lengkap
211 7.1.3 2 days 209
Terpasang Sesuai Gambar (Bahan Stainless)
Logo Puskesmas + Aksesoris Lengkap Terpasang
212 7.1.4 2 days 209
Sesuai Gambar (Bahan Stainless)
Reling Tangga Stainless + Aksesoris Lengkap
213 7.1.5 2 days 209
Terpasang Sesuai Gambar
Handrail (Pegangan Tangan) Stainless + Aksesoris
214 7.1.6 2 days 209
Lengkap Terpasang Sesuai Gambar
215 7.2 Pekerjan Pot Bunga 5 days
216 7.2.1 Pasangan Dinding Bata 1PC : 4 PP 2 days 214
217 7.2.2 Plasteran Dinding Bata 1PC : 4 PP 1 day 216
Pesangan Batu Alam Tempel Susun Sirih + Cat
218 7.2.3 1 day 216
Vernis Batu Alam
219 7.2.4 Relif Pot Bunga Sesuai Gambar 2 days 216
220 7.3 Pembersihan Akhir 1 day 219

3.3 Analisis Durasi Pekerjaan


Analisis Durasi Pekerjaan pada pembangaunan Gedung IGD
Puskesmas Blangpidie Kabupaten Aceh Barat Daya bisa dilihat
pada lampiran.

3.4 Penjadwalan Proyek


3.4.1 Bar Chart dan Kurva S
Bar Chart dan Kurva S pada pembangaunan Gedung IGD
Puskesmas Blangpidie Kabupaten Aceh Barat Daya bisa dilihat
pada lampiran.
3.4.2 Network Planning
Network Planning pada pembangaunan Gedung IGD Puskesmas
Blangpidie Kabupaten Aceh Barat Daya bisa dilihat pada
lampiran
22
Praktikum Perencanaan & Pengendalian Proyek Konstruksi
3.5 Analisis Float dan Lintasan Kritis
Total
WBS Item Pekerjaan Duration Predecessors Start Finish Late Start Late Finish Early Start Early Finish Critical Free Slack
Slack

0 Pembangunan Gedung IGD Puskesmas Blangpidie 142 days Mon 02/01/23 Tue 18/07/23 Mon 02/01/23 Tue 18/07/23 Mon 02/01/23 Tue 18/07/23 Yes 0 days 0 days
1 PEKERJAAN PERSIAPAN 6 days Mon 02/01/23 Mon 09/01/23 Mon 02/01/23 Tue 18/07/23 Mon 02/01/23 Mon 09/01/23 Yes 0 days 0 days
1.1 Papan Nama Proyek Uk. 90 x120 1 day Mon 02/01/23 Mon 02/01/23 Mon 02/01/23 Mon 02/01/23 Mon 02/01/23 Mon 02/01/23 Yes 0 days 0 days
1.2 Administrasi/Dokumentasi dan Pelaporan 1 day 2SS Mon 02/01/23 Mon 02/01/23 Tue 18/07/23 Tue 18/07/23 Mon 02/01/23 Mon 02/01/23 No 141 days 141 days
1.3 Direksi Keet/sewa 6 days 2SS Mon 02/01/23 Mon 09/01/23 Tue 11/07/23 Tue 18/07/23 Mon 02/01/23 Mon 09/01/23 No 136 days 136 days
1.4 Perlengkapan P3k 1 day 2SS Mon 02/01/23 Mon 02/01/23 Tue 18/07/23 Tue 18/07/23 Mon 02/01/23 Mon 02/01/23 No 141 days 141 days
1.5 Pengukuran dan Pemasangan Bouwplank 2 days 2SS Mon 02/01/23 Tue 03/01/23 Mon 17/07/23 Tue 18/07/23 Mon 02/01/23 Tue 03/01/23 No 140 days 140 days
1.6 Pekerjaan Kesehatan dan Keselamatan Kerja 1 day 2SS Mon 02/01/23 Mon 02/01/23 Tue 18/07/23 Tue 18/07/23 Mon 02/01/23 Mon 02/01/23 No 141 days 141 days
1.7 Pagar pelindung proyek 2 days 2SS Mon 02/01/23 Tue 03/01/23 Mon 02/01/23 Tue 03/01/23 Mon 02/01/23 Tue 03/01/23 Yes 0 days 0 days
2 PEKERJAAN TANAH 36 days Wed 04/01/23 Wed 22/02/23 Wed 04/01/23 Tue 18/07/23 Wed 04/01/23 Wed 22/02/23 Yes 0 days 0 days
2.1 PEKERJAAN GALIAN 8 days Wed 04/01/23 Fri 13/01/23 Wed 04/01/23 Tue 11/07/23 Wed 04/01/23 Fri 13/01/23 Yes 0 days 0 days
2.1.1 Galian Tanah Pondasi Tapak 4 days 8 Wed 04/01/23 Mon 09/01/23 Wed 04/01/23 Mon 09/01/23 Wed 04/01/23 Mon 09/01/23 Yes 0 days 0 days
2.1.2 Galian Tanah Pondasi Menerus 4 days 11 Tue 10/01/23 Fri 13/01/23 Thu 06/07/23 Tue 11/07/23 Tue 10/01/23 Fri 13/01/23 No 0 days 127 days
2.2 PEKERJAAN TIMBUNAN 28 days Mon 16/01/23 Wed 22/02/23 Thu 04/05/23 Tue 18/07/23 Mon 16/01/23 Wed 22/02/23 No 78 days 78 days
2.2.1 Urugan Kembali Bekas Galian 4 days 188 Wed 01/02/23 Mon 06/02/23 Thu 04/05/23 Tue 09/05/23 Wed 01/02/23 Mon 06/02/23 No 0 days 66 days
2.2.2 Pasir Urugan Bawah Pondasi Menerus 5 days 12 Mon 16/01/23 Fri 20/01/23 Wed 12/07/23 Tue 18/07/23 Mon 16/01/23 Fri 20/01/23 No 127 days 127 days
2.2.3 Pasir Urugan dibawah Lantai 3 days 17 Mon 20/02/23 Wed 22/02/23 Tue 23/05/23 Thu 25/05/23 Mon 20/02/23 Wed 22/02/23 No 0 days 66 days
2.2.4 Timbunan Tanah Dibawah Lantai 9 days 14 Tue 07/02/23 Fri 17/02/23 Wed 10/05/23 Mon 22/05/23 Tue 07/02/23 Fri 17/02/23 No 0 days 66 days
3 PEKERJAAN STRUKTUR 88 days Mon 02/01/23 Wed 03/05/23 Tue 10/01/23 Tue 18/07/23 Mon 02/01/23 Wed 03/05/23 No 6 days 6 days
3.1 LANTAI 1 1 day Mon 02/01/23 Mon 02/01/23 Tue 18/07/23 Tue 18/07/23 Mon 02/01/23 Mon 02/01/23 No 141 days 141 days
3.2 PEKERJAAN PONDASI TAPAK BETON BERTULANG 51 days Tue 10/01/23 Tue 21/03/23 Tue 10/01/23 Tue 18/07/23 Tue 10/01/23 Tue 21/03/23 Yes 0 days 0 days
3.2.1 Lantai Kerja Pondasi Tapak Setempat ( K.175) 1 day 11 Tue 10/01/23 Tue 10/01/23 Tue 10/01/23 Tue 10/01/23 Tue 10/01/23 Tue 10/01/23 Yes 0 days 0 days
3.2.2 Pekerjaan Beton Bertulang Pondasi Tapak 9 days Wed 11/01/23 Mon 23/01/23 Wed 11/01/23 Mon 23/01/23 Wed 11/01/23 Mon 23/01/23 Yes 0 days 0 days
3.2.2.1 Cor Beton K 250 2 days 25 Fri 20/01/23 Mon 23/01/23 Fri 20/01/23 Mon 23/01/23 Fri 20/01/23 Mon 23/01/23 Yes 0 days 0 days
3.2.2.2 Pembesian 5 days 21 Wed 11/01/23 Tue 17/01/23 Wed 11/01/23 Tue 17/01/23 Wed 11/01/23 Tue 17/01/23 Yes 0 days 0 days
3.2.2.3 Bekisting 2 days 24 Wed 18/01/23 Thu 19/01/23 Wed 18/01/23 Thu 19/01/23 Wed 18/01/23 Thu 19/01/23 Yes 0 days 0 days
3.2.3 Pekerjaan Pondasi Menerus 5 days Tue 24/01/23 Mon 30/01/23 Tue 24/01/23 Mon 30/01/23 Tue 24/01/23 Mon 30/01/23 Yes 0 days 0 days
3.2.3.1 Anstamping / Pasangan Batu Kosong Tebal 10 Cm 2 days 23 Tue 24/01/23 Wed 25/01/23 Tue 24/01/23 Wed 25/01/23 Tue 24/01/23 Wed 25/01/23 Yes 0 days 0 days
3.2.3.2 Pasangan Pondasi Batu Gunung 1 PC : 4 PS 3 days 27 Thu 26/01/23 Mon 30/01/23 Thu 26/01/23 Mon 30/01/23 Thu 26/01/23 Mon 30/01/23 Yes 0 days 0 days
3.2.4 Sloof (30/40) 7 days Tue 31/01/23 Wed 08/02/23 Tue 31/01/23 Wed 08/02/23 Tue 31/01/23 Wed 08/02/23 Yes 0 days 0 days
3.2.4.1 Pembesian 2 days 28 Tue 31/01/23 Wed 01/02/23 Tue 31/01/23 Wed 01/02/23 Tue 31/01/23 Wed 01/02/23 Yes 0 days 0 days
3.2.4.2 Bekisting 3 days 30 Thu 02/02/23 Mon 06/02/23 Thu 02/02/23 Mon 06/02/23 Thu 02/02/23 Mon 06/02/23 Yes 0 days 0 days
3.2.4.3 Cor Beton K 250 2 days 31 Tue 07/02/23 Wed 08/02/23 Tue 07/02/23 Wed 08/02/23 Tue 07/02/23 Wed 08/02/23 Yes 0 days 0 days
3.2.5 Sloof (15/20) 3 days Tue 31/01/23 Thu 02/02/23 Fri 14/07/23 Tue 18/07/23 Tue 31/01/23 Thu 02/02/23 No 118 days 118 days
3.2.5.1 Pembesian 1 day 28 Tue 31/01/23 Tue 31/01/23 Fri 14/07/23 Fri 14/07/23 Tue 31/01/23 Tue 31/01/23 No 0 days 118 days
3.2.5.2 Bekisting 1 day 34 Wed 01/02/23 Wed 01/02/23 Mon 17/07/23 Mon 17/07/23 Wed 01/02/23 Wed 01/02/23 No 0 days 118 days
3.2.5.3 Cor Beton K 175 1 day 35 Thu 02/02/23 Thu 02/02/23 Tue 18/07/23 Tue 18/07/23 Thu 02/02/23 Thu 02/02/23 No 118 days 118 days
3.2.6 Kolom Uk. 30/40 6 days Thu 09/02/23 Thu 16/02/23 Thu 09/02/23 Thu 16/02/23 Thu 09/02/23 Thu 16/02/23 Yes 0 days 0 days
3.2.6.1 Pembesian 2 days 32 Thu 09/02/23 Fri 10/02/23 Thu 09/02/23 Fri 10/02/23 Thu 09/02/23 Fri 10/02/23 Yes 0 days 0 days
3.2.6.2 Bekisting 2 days 38 Mon 13/02/23 Tue 14/02/23 Mon 13/02/23 Tue 14/02/23 Mon 13/02/23 Tue 14/02/23 Yes 0 days 0 days
3.2.6.3 Cor Beton K 250 2 days 39 Wed 15/02/23 Thu 16/02/23 Wed 15/02/23 Thu 16/02/23 Wed 15/02/23 Thu 16/02/23 Yes 0 days 0 days
3.2.7 Kolom Uk. 15/15 3 days Fri 17/02/23 Tue 21/02/23 Fri 14/07/23 Tue 18/07/23 Fri 17/02/23 Tue 21/02/23 No 105 days 105 days
3.2.7.1 Pembesian 1 day 40 Fri 17/02/23 Fri 17/02/23 Fri 14/07/23 Fri 14/07/23 Fri 17/02/23 Fri 17/02/23 No 0 days 105 days
3.2.7.2 Bekisting 1 day 42 Mon 20/02/23 Mon 20/02/23 Mon 17/07/23 Mon 17/07/23 Mon 20/02/23 Mon 20/02/23 No 0 days 105 days
3.2.7.3 Cor Beton K 175 1 day 43 Tue 21/02/23 Tue 21/02/23 Tue 18/07/23 Tue 18/07/23 Tue 21/02/23 Tue 21/02/23 No 105 days 105 days

23
Praktikum Perencanaan & Pengendalian Proyek Konstruksi
Total
WBS Item Pekerjaan Duration Predecessors Start Finish Late Start Late Finish Early Start Early Finish Critical Free Slack
Slack
3.2.8 Balok Latai (13/13) Elevasi ± 2.23 m 3 days Tue 28/02/23 Thu 02/03/23 Fri 14/07/23 Tue 18/07/23 Tue 28/02/23 Thu 02/03/23 No 98 days 98 days
3.2.8.1 Pembesian 1 day 47 Thu 02/03/23 Thu 02/03/23 Tue 18/07/23 Tue 18/07/23 Thu 02/03/23 Thu 02/03/23 No 98 days 98 days
3.2.8.2 Bekisting 2 days 96 Tue 28/02/23 Wed 01/03/23 Fri 14/07/23 Mon 17/07/23 Tue 28/02/23 Wed 01/03/23 No 0 days 98 days
3.2.8.3 Cor Beton K 175 1 day 47 Thu 02/03/23 Thu 02/03/23 Tue 18/07/23 Tue 18/07/23 Thu 02/03/23 Thu 02/03/23 No 98 days 98 days
3.2.9 Balok Uk. 25/40 Elevasi ± 3.45 m 5 days Tue 28/02/23 Mon 06/03/23 Wed 01/03/23 Tue 18/07/23 Tue 28/02/23 Mon 06/03/23 No 1 day 1 day
3.2.9.1 Pembesian 2 days 96 Tue 28/02/23 Wed 01/03/23 Mon 17/07/23 Tue 18/07/23 Tue 28/02/23 Wed 01/03/23 No 99 days 99 days
3.2.9.2 Bekisting 2 days 54 Wed 01/03/23 Thu 02/03/23 Wed 01/03/23 Thu 02/03/23 Wed 01/03/23 Thu 02/03/23 Yes 0 days 0 days
3.2.9.3 Cor Beton K 250 2 days 51 Fri 03/03/23 Mon 06/03/23 Fri 03/03/23 Mon 06/03/23 Fri 03/03/23 Mon 06/03/23 Yes 0 days 0 days
3.2.10 Ring Balok Uk. 15/20 Elevasi ± 3.45 m 3 days Tue 28/02/23 Thu 02/03/23 Tue 28/02/23 Tue 18/07/23 Tue 28/02/23 Thu 02/03/23 Yes 0 days 0 days
3.2.10.1 Pembesian 1 day 96 Tue 28/02/23 Tue 28/02/23 Tue 28/02/23 Tue 28/02/23 Tue 28/02/23 Tue 28/02/23 Yes 0 days 0 days
3.2.10.2 Bekisting 1 day 54 Wed 01/03/23 Wed 01/03/23 Mon 17/07/23 Mon 17/07/23 Wed 01/03/23 Wed 01/03/23 No 0 days 98 days
3.2.10.3 Cor Beton K 175 1 day 55 Thu 02/03/23 Thu 02/03/23 Tue 18/07/23 Tue 18/07/23 Thu 02/03/23 Thu 02/03/23 No 98 days 98 days
3.2.11 Plat Tangga dan Plat Bordes Tebal 10cm 3 days Fri 17/03/23 Tue 21/03/23 Fri 17/03/23 Tue 21/03/23 Fri 17/03/23 Tue 21/03/23 Yes 0 days 0 days
3.2.11.1 Pembesian 1 day 85 Fri 17/03/23 Fri 17/03/23 Fri 17/03/23 Fri 17/03/23 Fri 17/03/23 Fri 17/03/23 Yes 0 days 0 days
3.2.11.2 Bekisting 1 day 58 Mon 20/03/23 Mon 20/03/23 Mon 20/03/23 Mon 20/03/23 Mon 20/03/23 Mon 20/03/23 Yes 0 days 0 days
3.2.11.3 Cor Beton K 250 1 day 59 Tue 21/03/23 Tue 21/03/23 Tue 21/03/23 Tue 21/03/23 Tue 21/03/23 Tue 21/03/23 Yes 0 days 0 days
3.3 LANTAI 2 42 days Tue 07/03/23 Wed 03/05/23 Tue 07/03/23 Tue 18/07/23 Tue 07/03/23 Wed 03/05/23 Yes 0 days 0 days
3.3.1 Kolom Uk. 30/30 6 days Wed 22/03/23 Wed 29/03/23 Wed 22/03/23 Wed 29/03/23 Wed 22/03/23 Wed 29/03/23 Yes 0 days 0 days
3.3.1.1 Pembesian 2 days 60 Wed 22/03/23 Thu 23/03/23 Wed 22/03/23 Thu 23/03/23 Wed 22/03/23 Thu 23/03/23 Yes 0 days 0 days
3.3.1.2 Bekisting 2 days 63 Fri 24/03/23 Mon 27/03/23 Fri 24/03/23 Mon 27/03/23 Fri 24/03/23 Mon 27/03/23 Yes 0 days 0 days
3.3.1.3 Cor Beton K 250 2 days 64 Tue 28/03/23 Wed 29/03/23 Tue 28/03/23 Wed 29/03/23 Tue 28/03/23 Wed 29/03/23 Yes 0 days 0 days
3.3.2 Kolom Uk. 15/15 4 days Thu 30/03/23 Tue 04/04/23 Thu 13/07/23 Tue 18/07/23 Thu 30/03/23 Tue 04/04/23 No 75 days 75 days
3.3.2.1 Pembesian 1 day 65 Thu 30/03/23 Thu 30/03/23 Thu 13/07/23 Thu 13/07/23 Thu 30/03/23 Thu 30/03/23 No 0 days 75 days
3.3.2.2 Bekisting 2 days 67 Fri 31/03/23 Mon 03/04/23 Fri 14/07/23 Mon 17/07/23 Fri 31/03/23 Mon 03/04/23 No 0 days 75 days
3.3.2.3 Cor Beton K 175 1 day 68 Tue 04/04/23 Tue 04/04/23 Tue 18/07/23 Tue 18/07/23 Tue 04/04/23 Tue 04/04/23 No 75 days 75 days
3.3.3 Balok Latai (13/13) Elevasi ± 6.23 m 2 days Tue 11/04/23 Wed 12/04/23 Mon 17/07/23 Tue 18/07/23 Tue 11/04/23 Wed 12/04/23 No 69 days 69 days
3.3.3.1 Pembesian 1 day 123 Tue 11/04/23 Tue 11/04/23 Tue 18/07/23 Tue 18/07/23 Tue 11/04/23 Tue 11/04/23 No 70 days 70 days
3.3.3.2 Bekisting 1 day 123 Tue 11/04/23 Tue 11/04/23 Mon 17/07/23 Mon 17/07/23 Tue 11/04/23 Tue 11/04/23 No 0 days 69 days
3.3.3.3 Cor Beton K 175 1 day 72 Wed 12/04/23 Wed 12/04/23 Tue 18/07/23 Tue 18/07/23 Wed 12/04/23 Wed 12/04/23 No 69 days 69 days
3.3.4 Ring Balok Uk. 25/40 Elevasi ± 7.50 m 6 days Tue 11/04/23 Tue 18/04/23 Tue 11/04/23 Tue 18/04/23 Tue 11/04/23 Tue 18/04/23 Yes 0 days 0 days
3.3.4.1 Pembesian 2 days 123 Tue 11/04/23 Wed 12/04/23 Tue 11/04/23 Wed 12/04/23 Tue 11/04/23 Wed 12/04/23 Yes 0 days 0 days
3.3.4.2 Bekisting 2 days 75 Thu 13/04/23 Fri 14/04/23 Thu 13/04/23 Fri 14/04/23 Thu 13/04/23 Fri 14/04/23 Yes 0 days 0 days
3.3.4.3 Cor Beton K 250 2 days 76 Mon 17/04/23 Tue 18/04/23 Mon 17/04/23 Tue 18/04/23 Mon 17/04/23 Tue 18/04/23 Yes 0 days 0 days
3.3.5 Ring Balok Uk. 15/20 Elevasi ±7.5 m 3 days Tue 11/04/23 Thu 13/04/23 Fri 14/07/23 Tue 18/07/23 Tue 11/04/23 Thu 13/04/23 No 68 days 68 days
3.3.5.1 Pembesian 1 day 123 Tue 11/04/23 Tue 11/04/23 Fri 14/07/23 Fri 14/07/23 Tue 11/04/23 Tue 11/04/23 No 0 days 68 days
3.3.5.2 Bekisting 1 day 79 Wed 12/04/23 Wed 12/04/23 Mon 17/07/23 Mon 17/07/23 Wed 12/04/23 Wed 12/04/23 No 0 days 68 days
3.3.5.3 Cor Beton K 175 1 day 80 Thu 13/04/23 Thu 13/04/23 Tue 18/07/23 Tue 18/07/23 Thu 13/04/23 Thu 13/04/23 No 68 days 68 days
3.3.6 Plat Lantai Tebal 12cm 8 days Tue 07/03/23 Thu 16/03/23 Tue 07/03/23 Thu 16/03/23 Tue 07/03/23 Thu 16/03/23 Yes 0 days 0 days
3.3.6.1 Pembesian 4 days 84 Thu 09/03/23 Tue 14/03/23 Thu 09/03/23 Tue 14/03/23 Thu 09/03/23 Tue 14/03/23 Yes 0 days 0 days
3.3.6.2 Bekisting 2 days 52 Tue 07/03/23 Wed 08/03/23 Tue 07/03/23 Wed 08/03/23 Tue 07/03/23 Wed 08/03/23 Yes 0 days 0 days
3.3.6.3 Cor Beton K 250 2 days 83 Wed 15/03/23 Thu 16/03/23 Wed 15/03/23 Thu 16/03/23 Wed 15/03/23 Thu 16/03/23 Yes 0 days 0 days
3.3.7 Plat dak dan Talang Beton 3 days Wed 19/04/23 Fri 21/04/23 Wed 19/04/23 Fri 21/04/23 Wed 19/04/23 Fri 21/04/23 Yes 0 days 0 days
3.3.7.1 Pembesian 1 day 77 Wed 19/04/23 Wed 19/04/23 Wed 19/04/23 Wed 19/04/23 Wed 19/04/23 Wed 19/04/23 Yes 0 days 0 days
3.3.7.2 Bekisting 1 day 87 Thu 20/04/23 Thu 20/04/23 Thu 20/04/23 Thu 20/04/23 Thu 20/04/23 Thu 20/04/23 Yes 0 days 0 days
3.3.7.3 Cor Beton K 250 1 day 88 Fri 21/04/23 Fri 21/04/23 Fri 21/04/23 Fri 21/04/23 Fri 21/04/23 Fri 21/04/23 Yes 0 days 0 days
3.3.8 PEKERJAAN ATAP 8 days Mon 24/04/23 Wed 03/05/23 Mon 24/04/23 Wed 03/05/23 Mon 24/04/23 Wed 03/05/23 Yes 0 days 0 days
3.3.8.1 Rangka kuda-kuda dan gording baja ringan Multytruss 8 days 89 Mon 24/04/23 Wed 03/05/23 Mon 24/04/23 Wed 03/05/23 Mon 24/04/23 Wed 03/05/23 Yes 0 days 0 days

24
Praktikum Perencanaan & Pengendalian Proyek Konstruksi
Total
WBS Item Pekerjaan Duration Predecessors Start Finish Late Start Late Finish Early Start Early Finish Critical Free Slack
Slack
4 PEKERJAAN ARSITEKTUR 88 days Fri 17/02/23 Tue 20/06/23 Fri 17/02/23 Tue 18/07/23 Fri 17/02/23 Tue 20/06/23 Yes 0 days 0 days
4.1 LANTAI 1 42 days Fri 17/02/23 Mon 17/04/23 Fri 17/02/23 Tue 18/07/23 Fri 17/02/23 Mon 17/04/23 Yes 0 days 0 days
4.1.1 Pekerjaan Dinding 18 days Fri 17/02/23 Tue 14/03/23 Fri 17/02/23 Tue 18/07/23 Fri 17/02/23 Tue 14/03/23 Yes 0 days 0 days
4.1.1.1 Pasangan Trasram Bata 1 PC : 2 PP 1 day 40 Fri 17/02/23 Fri 17/02/23 Fri 17/02/23 Fri 17/02/23 Fri 17/02/23 Fri 17/02/23 Yes 0 days 0 days
4.1.1.2 Pasangan Dinding Bata 1 PC : 4 PP 6 days 95 Mon 20/02/23 Mon 27/02/23 Mon 20/02/23 Mon 27/02/23 Mon 20/02/23 Mon 27/02/23 Yes 0 days 0 days
4.1.1.3 Plesteran Trasram Bata 1 PC : 2 PP 1 day 184 Mon 27/02/23 Mon 27/02/23 Tue 30/05/23 Tue 30/05/23 Mon 27/02/23 Mon 27/02/23 No 0 days 66 days
4.1.1.4 Plesteran Dinding Bata 1PC : 4 PP 9 days 97 Tue 28/02/23 Fri 10/03/23 Wed 31/05/23 Mon 12/06/23 Tue 28/02/23 Fri 10/03/23 No 0 days 66 days
4.1.1.5 Plasteran Beton 1 PC : 3 PP 7 days 97 Tue 28/02/23 Wed 08/03/23 Mon 10/07/23 Tue 18/07/23 Tue 28/02/23 Wed 08/03/23 No 94 days 94 days
4.1.1.6 Pesangan Batu Alam Tempel Susun Sirih + cat Vernis Batu Alam 2 days 98 Mon 13/03/23 Tue 14/03/23 Mon 17/07/23 Tue 18/07/23 Mon 13/03/23 Tue 14/03/23 No 90 days 90 days
4.1.2 Pekerjaan Lantai 27 days Thu 23/02/23 Fri 31/03/23 Fri 26/05/23 Mon 03/07/23 Thu 23/02/23 Fri 31/03/23 No 66 days 66 days
4.1.2.1 Pekerjaan Beton Tumbuk Tebal 7 cm (K 125) 1 day 16 Thu 23/02/23 Thu 23/02/23 Fri 26/05/23 Fri 26/05/23 Thu 23/02/23 Thu 23/02/23 No 0 days 66 days
4.1.2.2 Pekerjaan Lantai Granite 60 x 60 Cm (Halus) 5 days 117 Fri 17/03/23 Thu 23/03/23 Mon 19/06/23 Fri 23/06/23 Fri 17/03/23 Thu 23/03/23 No 0 days 66 days
4.1.2.3 Pekerjaan Lantai Granite 60 x 60 Cm (Kasar) 3 days 103 Fri 24/03/23 Tue 28/03/23 Mon 26/06/23 Wed 28/06/23 Fri 24/03/23 Tue 28/03/23 No 0 days 66 days
4.1.2.4 Pekerjaan Lantai Keramik untuk Ruangan Wc/Km 20 X 20 Cm 1 day 104 Wed 29/03/23 Wed 29/03/23 Thu 29/06/23 Thu 29/06/23 Wed 29/03/23 Wed 29/03/23 No 0 days 66 days
4.1.2.5 Pasangan Dinding Keramik KM/WC 20 x 25 cm 2 days 105 Thu 30/03/23 Fri 31/03/23 Fri 30/06/23 Mon 03/07/23 Thu 30/03/23 Fri 31/03/23 No 0 days 66 days
4.1.3 Pekerjaan Pintu, Jendela, Ventilasi 38 days Thu 23/02/23 Mon 17/04/23 Mon 17/07/23 Tue 18/07/23 Thu 23/02/23 Mon 17/04/23 No 66 days 66 days
4.1.3.1 Pintu Panel Kaca Tempered Glass 12mm + Aksesoris Lengkap Terpasang (Type 1 day
P1) 160 Fri 14/04/23 Fri 14/04/23 Tue 18/07/23 Tue 18/07/23 Fri 14/04/23 Fri 14/04/23 No 67 days 67 days
4.1.3.2 Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris Lengkap Terpasang Sesuai Gambar
2 days ( Type P2)
160 Fri 14/04/23 Mon 17/04/23 Mon 17/07/23 Tue 18/07/23 Fri 14/04/23 Mon 17/04/23 No 66 days 66 days
4.1.3.3 Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris Lengkap Terpasang Sesuai Gambar
1 day ( Type P5)
16 Thu 23/02/23 Thu 23/02/23 Tue 18/07/23 Tue 18/07/23 Thu 23/02/23 Thu 23/02/23 No 103 days 103 days
4.1.3.4 Kusen UPVC + Daun Pintu UPVC+ Aksesoris Lengkap Terpasang Sesuai Gambar 1 day
(Type P4) 160 Fri 14/04/23 Fri 14/04/23 Tue 18/07/23 Tue 18/07/23 Fri 14/04/23 Fri 14/04/23 No 67 days 67 days
4.1.3.5 Kusen UPVC + Daun Pintu UPVC+ Aksesoris Lengkap Terpasang Sesuai Gambar 1 day
(Type P3) 160 Fri 14/04/23 Fri 14/04/23 Tue 18/07/23 Tue 18/07/23 Fri 14/04/23 Fri 14/04/23 No 67 days 67 days
4.1.3.6 Kusen UPVC + Daun Jendela dan Ventilasi Kaca 5mm + Aksesoris Lengkap Terpasang
2 days Sesuai Gambar
160 (TypeFriJV1)
14/04/23 Mon 17/04/23 Mon 17/07/23 Tue 18/07/23 Fri 14/04/23 Mon 17/04/23 No 66 days 66 days
4.1.3.7 Kusen UPVC + Daun Jendela dan Ventilasi Kaca 5mm + Aksesoris Lengkap Terpasang
1 day Sesuai Gambar
16 (TypeThu
J2)23/02/23 Thu 23/02/23 Tue 18/07/23 Tue 18/07/23 Thu 23/02/23 Thu 23/02/23 No 103 days 103 days
4.1.3.8 Kusen UPVC + Daun ventilasi Kaca 5mm + Aksesoris Lengkap Terpasang Sesuai1 day
Gambar (Type160
V2) Fri 14/04/23 Fri 14/04/23 Tue 18/07/23 Tue 18/07/23 Fri 14/04/23 Fri 14/04/23 No 67 days 67 days
4.1.4 Pekerjaan Plafond 4 days Mon 13/03/23 Thu 16/03/23 Tue 13/06/23 Fri 16/06/23 Mon 13/03/23 Thu 16/03/23 No 66 days 66 days
4.1.4.1 Pasang Plafon PVC/Fiber + Rangka + Aksesoris Lengkap Terpasang Sesuai Gambar
4 days 98 Mon 13/03/23 Thu 16/03/23 Tue 13/06/23 Fri 16/06/23 Mon 13/03/23 Thu 16/03/23 No 0 days 66 days
4.1.5 Pekerjaan Pengecatan 4 days Mon 03/04/23 Thu 06/04/23 Tue 04/07/23 Fri 07/07/23 Mon 03/04/23 Thu 06/04/23 No 66 days 66 days
4.1.5.1 Pengecatan Tembok dan Sealer 3x(L/D) Setara Vinilex 4 days 106 Mon 03/04/23 Thu 06/04/23 Tue 04/07/23 Fri 07/07/23 Mon 03/04/23 Thu 06/04/23 No 0 days 66 days
4.2 LANTAI 2 59 days Thu 30/03/23 Tue 20/06/23 Thu 30/03/23 Tue 18/07/23 Thu 30/03/23 Tue 20/06/23 Yes 0 days 0 days
4.2.1 Pekerjaan Dinding 43 days Thu 30/03/23 Mon 29/05/23 Thu 30/03/23 Tue 18/07/23 Thu 30/03/23 Mon 29/05/23 Yes 0 days 0 days
4.2.1.1 Pasangan Trasram Bata 1 PC : 2 PP 2 days 65 Thu 30/03/23 Fri 31/03/23 Thu 30/03/23 Fri 31/03/23 Thu 30/03/23 Fri 31/03/23 Yes 0 days 0 days
4.2.1.2 Pasangan Dinding Bata 1 PC : 4 PP 6 days 122 Mon 03/04/23 Mon 10/04/23 Mon 03/04/23 Mon 10/04/23 Mon 03/04/23 Mon 10/04/23 Yes 0 days 0 days
4.2.1.3 Plesteran Trasram Bata 1 PC : 2 PP 1 day 91 Thu 04/05/23 Thu 04/05/23 Thu 04/05/23 Thu 04/05/23 Thu 04/05/23 Thu 04/05/23 Yes 0 days 0 days
4.2.1.4 Plesteran Dinding Bata 1PC : 4 PP 14 days 124 Fri 05/05/23 Wed 24/05/23 Fri 05/05/23 Wed 24/05/23 Fri 05/05/23 Wed 24/05/23 Yes 0 days 0 days
4.2.1.5 Plasteran Beton 1 PC : 3 PP 3 days 125 Thu 25/05/23 Mon 29/05/23 Fri 14/07/23 Tue 18/07/23 Thu 25/05/23 Mon 29/05/23 No 36 days 36 days
4.2.1.6 Pesangan Batu Alam Tempel Susun Sirih + cat Vernis Batu Alam 2 days 125 Thu 25/05/23 Fri 26/05/23 Mon 17/07/23 Tue 18/07/23 Thu 25/05/23 Fri 26/05/23 No 37 days 37 days
4.2.2 Pekerjaan Lantai 10 days Thu 25/05/23 Wed 07/06/23 Tue 30/05/23 Tue 18/07/23 Thu 25/05/23 Wed 07/06/23 No 3 days 3 days
4.2.2.1 Pekerjaan Beton Tumbuk Tebal 7 cm (K 125) 2 days 125 Thu 25/05/23 Fri 26/05/23 Mon 17/07/23 Tue 18/07/23 Thu 25/05/23 Fri 26/05/23 No 37 days 37 days
4.2.2.2 Pekerjaan Lantai Granite 60 x 60 Cm (Halus) 5 days 145 Tue 30/05/23 Mon 05/06/23 Tue 30/05/23 Mon 05/06/23 Tue 30/05/23 Mon 05/06/23 Yes 0 days 0 days
4.2.2.3 Pekerjaan Lantai Keramik untuk Ruangan Wc/Km 20 X 20 Cm 1 day 130 Tue 06/06/23 Tue 06/06/23 Tue 06/06/23 Tue 06/06/23 Tue 06/06/23 Tue 06/06/23 Yes 0 days 0 days
4.2.2.4 Pasangan Dinding Keramik KM/WC 20 x 25 cm 1 day 131 Wed 07/06/23 Wed 07/06/23 Wed 07/06/23 Wed 07/06/23 Wed 07/06/23 Wed 07/06/23 Yes 0 days 0 days
4.2.3 Pekerjaan Pintu, Jendela, Ventilasi 1 day Tue 20/06/23 Tue 20/06/23 Tue 20/06/23 Tue 18/07/23 Tue 20/06/23 Tue 20/06/23 Yes 0 days 0 days
4.2.3.1 Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris Lengkap Terpasang Sesuai Gambar
1 day ( Type P2)
168 Tue 20/06/23 Tue 20/06/23 Tue 18/07/23 Tue 18/07/23 Tue 20/06/23 Tue 20/06/23 No 20 days 20 days
4.2.3.2 Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris Lengkap Terpasang Sesuai Gambar
1 day ( Type P5)
168 Tue 20/06/23 Tue 20/06/23 Tue 18/07/23 Tue 18/07/23 Tue 20/06/23 Tue 20/06/23 No 20 days 20 days
4.2.3.3 Kusen UPVC + Daun Pintu UPVC+ Aksesoris Lengkap Terpasang Sesuai Gambar 1 day
(Type P4) 168 Tue 20/06/23 Tue 20/06/23 Tue 20/06/23 Tue 20/06/23 Tue 20/06/23 Tue 20/06/23 Yes 0 days 0 days
4.2.3.4 Kusen UPVC + Daun Jendela dan Ventilasi Kaca 5mm + Aksesoris Lengkap Terpasang
1 day Sesuai Gambar
168 (TypeTueJV1)
20/06/23 Tue 20/06/23 Tue 18/07/23 Tue 18/07/23 Tue 20/06/23 Tue 20/06/23 No 20 days 20 days
4.2.3.5 Kusen UPVC + Daun Jendela dan Ventilasi Kaca 5mm + Aksesoris Lengkap Terpasang
1 day Sesuai Gambar
168 (TypeTueJ2)20/06/23 Tue 20/06/23 Tue 18/07/23 Tue 18/07/23 Tue 20/06/23 Tue 20/06/23 No 20 days 20 days
4.2.3.6 Kusen UPVC + Daun ventilasi Kaca 5mm + Aksesoris Lengkap Terpasang Sesuai1 day
Gambar (Type168
V2) Tue 20/06/23 Tue 20/06/23 Tue 18/07/23 Tue 18/07/23 Tue 20/06/23 Tue 20/06/23 No 20 days 20 days

25
Praktikum Perencanaan & Pengendalian Proyek Konstruksi
Total
WBS Item Pekerjaan Duration Predecessors Start Finish Late Start Late Finish Early Start Early Finish Critical Free Slack
Slack
4.2.4 PEKERJAAN ATAP 10 days Thu 04/05/23 Wed 17/05/23 Wed 05/07/23 Tue 18/07/23 Thu 04/05/23 Wed 17/05/23 No 44 days 44 days
4.2.4.1 Penutup Atap genteng Onduline 5 days 91 Thu 04/05/23 Wed 10/05/23 Wed 05/07/23 Tue 11/07/23 Thu 04/05/23 Wed 10/05/23 No 0 days 44 days
4.2.4.2 Rabung genteng Onduline 2 days 141 Thu 11/05/23 Fri 12/05/23 Wed 12/07/23 Thu 13/07/23 Thu 11/05/23 Fri 12/05/23 No 0 days 44 days
4.2.4.3 Lisplank Kayu 2/20 cm 3 days 142 Mon 15/05/23 Wed 17/05/23 Fri 14/07/23 Tue 18/07/23 Mon 15/05/23 Wed 17/05/23 No 44 days 44 days
4.2.5 Pekerjaan Plafond 3 days Thu 25/05/23 Mon 29/05/23 Thu 25/05/23 Mon 29/05/23 Thu 25/05/23 Mon 29/05/23 Yes 0 days 0 days
4.2.5.1 Pasang Plafon PVC/Fiber + Rangka + Aksesoris Lengkap Terpasang Sesuai Gambar3 days 125 Thu 25/05/23 Mon 29/05/23 Thu 25/05/23 Mon 29/05/23 Thu 25/05/23 Mon 29/05/23 Yes 0 days 0 days
4.2.6 Pekerjaan Pengecatan 4 days Thu 08/06/23 Tue 13/06/23 Thu 08/06/23 Tue 13/06/23 Thu 08/06/23 Tue 13/06/23 Yes 0 days 0 days
4.2.6.1 Pengecatan Tembok dan Sealer 3x(L/D) Setara Vinilex 4 days 132 Thu 08/06/23 Tue 13/06/23 Thu 08/06/23 Tue 13/06/23 Thu 08/06/23 Tue 13/06/23 Yes 0 days 0 days
5 PEKERJAAN ELEKTRIKAL 52 days Fri 07/04/23 Mon 19/06/23 Wed 14/06/23 Tue 18/07/23 Fri 07/04/23 Mon 19/06/23 No 21 days 21 days
5.1 Instlasi titik penerangan, instalasi termasuk kabel NYA 2,5 mm dalam pipa PVC fitting
1 day lampu dan119
kelengkapanFriinstalasi
07/04/23 terpasang
Fri 07/04/23 Tue 18/07/23 Tue 18/07/23 Fri 07/04/23 Fri 07/04/23 No 72 days 72 days
5.2 Instalasi titik Stop kontak, instalasi termasuk kabel NYA 2,5 mm dalam pipa PVC1fitting
day lampu dan119
kelengkapan instalasi terpasang
Fri 07/04/23 Fri 07/04/23 Mon 10/07/23 Mon 10/07/23 Fri 07/04/23 Fri 07/04/23 No 0 days 66 days
5.3 Pemasangan Box Sekring 1 day 119 Fri 07/04/23 Fri 07/04/23 Tue 18/07/23 Tue 18/07/23 Fri 07/04/23 Fri 07/04/23 No 72 days 72 days
5.4 Pemasukan Arus Listrik 12 Ampere 1 day 119 Fri 07/04/23 Fri 07/04/23 Tue 18/07/23 Tue 18/07/23 Fri 07/04/23 Fri 07/04/23 No 72 days 72 days
5.5 LANTAI 1 4 days Mon 10/04/23 Thu 13/04/23 Tue 11/07/23 Tue 18/07/23 Mon 10/04/23 Thu 13/04/23 No 66 days 66 days
5.5.1 Armatur 2 days Mon 10/04/23 Tue 11/04/23 Tue 11/07/23 Wed 12/07/23 Mon 10/04/23 Tue 11/04/23 No 66 days 66 days
5.5.1.1 Lampu Downlight 23 watt + Accesori Lengkap Terpasang 1 day 150 Mon 10/04/23 Mon 10/04/23 Tue 11/07/23 Tue 11/07/23 Mon 10/04/23 Mon 10/04/23 No 0 days 66 days
5.5.1.2 Lampu RM TL 2X36 watt + Accesori Lengkap Terpasang 1 day 155 Tue 11/04/23 Tue 11/04/23 Wed 12/07/23 Wed 12/07/23 Tue 11/04/23 Tue 11/04/23 No 0 days 66 days
5.5.2 Saklar lampu Merk Setara Broco 2 seri 2 days Wed 12/04/23 Thu 13/04/23 Thu 13/07/23 Tue 18/07/23 Wed 12/04/23 Thu 13/04/23 No 66 days 66 days
5.5.2.1 Sakalar 1 Seri setara Broco 1 day 156 Wed 12/04/23 Wed 12/04/23 Tue 18/07/23 Tue 18/07/23 Wed 12/04/23 Wed 12/04/23 No 69 days 69 days
5.5.2.2 Sakalar 2 Seri setara Broco 1 day 156 Wed 12/04/23 Wed 12/04/23 Thu 13/07/23 Thu 13/07/23 Wed 12/04/23 Wed 12/04/23 No 0 days 66 days
5.5.2.3 Stop Kontak 1 day 159 Thu 13/04/23 Thu 13/04/23 Fri 14/07/23 Fri 14/07/23 Thu 13/04/23 Thu 13/04/23 No 0 days 66 days
5.6 LANTAI 2 4 days Wed 14/06/23 Mon 19/06/23 Wed 14/06/23 Tue 18/07/23 Wed 14/06/23 Mon 19/06/23 Yes 0 days 0 days
5.6.1 Armatur 2 days Wed 14/06/23 Thu 15/06/23 Wed 14/06/23 Thu 15/06/23 Wed 14/06/23 Thu 15/06/23 Yes 0 days 0 days
5.6.1.1 Lampu Downlight 23 watt + Accesori Lengkap Terpasang 1 day 147 Wed 14/06/23 Wed 14/06/23 Wed 14/06/23 Wed 14/06/23 Wed 14/06/23 Wed 14/06/23 Yes 0 days 0 days
5.6.1.2 Lampu RM TL 2X36 watt + Accesori Lengkap Terpasang 1 day 163 Thu 15/06/23 Thu 15/06/23 Thu 15/06/23 Thu 15/06/23 Thu 15/06/23 Thu 15/06/23 Yes 0 days 0 days
5.6.2 Saklar lampu Merk Setara Broco 2 seri 2 days Fri 16/06/23 Mon 19/06/23 Fri 16/06/23 Tue 18/07/23 Fri 16/06/23 Mon 19/06/23 Yes 0 days 0 days
5.6.2.1 Sakalar 1 Seri setara Broco 1 day 164 Fri 16/06/23 Fri 16/06/23 Tue 18/07/23 Tue 18/07/23 Fri 16/06/23 Fri 16/06/23 No 22 days 22 days
5.6.2.2 Sakalar 2 Seri setara Broco 1 day 164 Fri 16/06/23 Fri 16/06/23 Fri 16/06/23 Fri 16/06/23 Fri 16/06/23 Fri 16/06/23 Yes 0 days 0 days
5.6.2.3 Stop Kontak 1 day 167 Mon 19/06/23 Mon 19/06/23 Mon 19/06/23 Mon 19/06/23 Mon 19/06/23 Mon 19/06/23 Yes 0 days 0 days
6 PEKERJAAN MEKANIKAL 132 days Mon 02/01/23 Tue 04/07/23 Wed 03/05/23 Tue 18/07/23 Mon 02/01/23 Tue 04/07/23 No 10 days 10 days
6.1 PEKERJAAN SALURAN DRAINASE 10 days Wed 21/06/23 Tue 04/07/23 Wed 21/06/23 Tue 04/07/23 Wed 21/06/23 Tue 04/07/23 Yes 0 days 0 days
6.1.1 Pasangan Bata Dinding Saluran 1 PC : 2 PP 2 days 136 Wed 21/06/23 Thu 22/06/23 Wed 21/06/23 Thu 22/06/23 Wed 21/06/23 Thu 22/06/23 Yes 0 days 0 days
6.1.2 Pasangan Plasteran Bata Dinding Saluran 1 PC : 2 PP 2 days 171 Fri 23/06/23 Mon 26/06/23 Fri 23/06/23 Mon 26/06/23 Fri 23/06/23 Mon 26/06/23 Yes 0 days 0 days
6.1.3 Cor Lantai Saluran 2 days 172 Tue 27/06/23 Wed 28/06/23 Tue 27/06/23 Wed 28/06/23 Tue 27/06/23 Wed 28/06/23 Yes 0 days 0 days
6.1.4 Buis Beton Dia. 20 cm 2 days 173 Thu 29/06/23 Fri 30/06/23 Thu 29/06/23 Fri 30/06/23 Thu 29/06/23 Fri 30/06/23 Yes 0 days 0 days
6.1.5 Pemasangan Grill Saluran Bentuk Sesuai Gambar + Cat Meni Hitam 2 days 174 Mon 03/07/23 Tue 04/07/23 Mon 03/07/23 Tue 04/07/23 Mon 03/07/23 Tue 04/07/23 Yes 0 days 0 days
6.2 LANTAI 1 96 days Mon 02/01/23 Mon 15/05/23 Wed 03/05/23 Tue 18/07/23 Mon 02/01/23 Mon 15/05/23 No 46 days 46 days
6.2.1 Pekerjaan Sanitasi 1 day Mon 02/01/23 Mon 02/01/23 Tue 18/07/23 Tue 18/07/23 Mon 02/01/23 Mon 02/01/23 No 141 days 141 days
6.2.2 INSTALASI AIR KOTOR 3 days Thu 30/03/23 Mon 03/04/23 Tue 18/07/23 Tue 18/07/23 Thu 30/03/23 Mon 03/04/23 No 76 days 76 days
6.2.2.1 Pasang Floordrain 1 day 105 Thu 30/03/23 Thu 30/03/23 Tue 18/07/23 Tue 18/07/23 Thu 30/03/23 Thu 30/03/23 No 78 days 78 days
6.2.2.2 Pipa SNI 3 Inch AW 1 day 106 Mon 03/04/23 Mon 03/04/23 Tue 18/07/23 Tue 18/07/23 Mon 03/04/23 Mon 03/04/23 No 76 days 76 days
6.2.3 INSTALASI AIR BERSIH 27 days Fri 24/02/23 Mon 03/04/23 Mon 29/05/23 Tue 18/07/23 Fri 24/02/23 Mon 03/04/23 No 66 days 66 days
6.2.3.1 Memasang Wastafel + Keran Air + Pembungan Air Type Sifon angsa Aksesoris1Lengkap
day Terpasang
106 Setara Toto
Mon 03/04/23 Mon 03/04/23 Tue 18/07/23 Tue 18/07/23 Mon 03/04/23 Mon 03/04/23 No 76 days 76 days
6.2.3.2 Pipa SNI 1/2 Inch AW 1 day 102 Fri 24/02/23 Fri 24/02/23 Tue 18/07/23 Tue 18/07/23 Fri 24/02/23 Fri 24/02/23 No 102 days 102 days
6.2.3.3 Pasang Pipa Air Sampai Ketitik Air 1 day 102 Fri 24/02/23 Fri 24/02/23 Mon 29/05/23 Mon 29/05/23 Fri 24/02/23 Fri 24/02/23 No 0 days 66 days

26
Praktikum Perencanaan & Pengendalian Proyek Konstruksi
Total
WBS Item Pekerjaan Duration Predecessors Start Finish Late Start Late Finish Early Start Early Finish Critical Free Slack
Slack
6.2.4 INSTALASI AIR HUJAN 1 day Mon 15/05/23 Mon 15/05/23 Tue 18/07/23 Tue 18/07/23 Mon 15/05/23 Mon 15/05/23 No 46 days 46 days
6.2.4.1 Pipa SNI 2 1/2 Inch AW 1 day 142 Mon 15/05/23 Mon 15/05/23 Tue 18/07/23 Tue 18/07/23 Mon 15/05/23 Mon 15/05/23 No 46 days 46 days
6.2.5 INSTALASI KOTORAN 43 days Tue 31/01/23 Thu 30/03/23 Wed 03/05/23 Tue 18/07/23 Tue 31/01/23 Thu 30/03/23 No 66 days 66 days
6.2.5.1 Pipa SNI 3 Inch AW 1 day 28 Tue 31/01/23 Tue 31/01/23 Wed 03/05/23 Wed 03/05/23 Tue 31/01/23 Tue 31/01/23 No 0 days 66 days
6.2.5.2 Septick Tank + Resapan Lengkap Terpasang 1 day 188 Wed 01/02/23 Wed 01/02/23 Tue 18/07/23 Tue 18/07/23 Wed 01/02/23 Wed 01/02/23 No 119 days 119 days
6.2.5.3 Pasang Kloset Duduk SetaraToto 1 day 105 Thu 30/03/23 Thu 30/03/23 Tue 18/07/23 Tue 18/07/23 Thu 30/03/23 Thu 30/03/23 No 78 days 78 days
6.3 LANTAI 2 114 days Mon 02/01/23 Thu 08/06/23 Tue 18/07/23 Tue 18/07/23 Mon 02/01/23 Thu 08/06/23 No 28 days 28 days
6.3.1 Pekerjaan Sanitasi 1 day Mon 02/01/23 Mon 02/01/23 Tue 18/07/23 Tue 18/07/23 Mon 02/01/23 Mon 02/01/23 No 141 days 141 days
6.3.2 INSTALASI AIR BERSIH 64 days Mon 13/03/23 Thu 08/06/23 Tue 18/07/23 Tue 18/07/23 Mon 13/03/23 Thu 08/06/23 No 28 days 28 days
6.3.2.1 Bak Mandi Pyber Glass (60 x 60) 1 day 132 Thu 08/06/23 Thu 08/06/23 Tue 18/07/23 Tue 18/07/23 Thu 08/06/23 Thu 08/06/23 No 28 days 28 days
6.3.2.2 Pasang Kran Air 1/2" 1 day 98 Mon 13/03/23 Mon 13/03/23 Tue 18/07/23 Tue 18/07/23 Mon 13/03/23 Mon 13/03/23 No 91 days 91 days
6.3.2.3 Pipa SNI 1 Inch AW 1 day 98 Mon 13/03/23 Mon 13/03/23 Tue 18/07/23 Tue 18/07/23 Mon 13/03/23 Mon 13/03/23 No 91 days 91 days
6.3.2.4 Pipa SNI 1/2 Inch AW 1 day 98 Mon 13/03/23 Mon 13/03/23 Tue 18/07/23 Tue 18/07/23 Mon 13/03/23 Mon 13/03/23 No 91 days 91 days
6.3.2.5 Pasang Pipa Air Sampai Ketitik Air 1 day 98 Mon 13/03/23 Mon 13/03/23 Tue 18/07/23 Tue 18/07/23 Mon 13/03/23 Mon 13/03/23 No 91 days 91 days
6.3.3 INSTALASI AIR KOTOR 64 days Mon 13/03/23 Thu 08/06/23 Tue 18/07/23 Tue 18/07/23 Mon 13/03/23 Thu 08/06/23 No 28 days 28 days
6.3.3.1 Pipa SNI 3 Inch AW 1 day 98 Mon 13/03/23 Mon 13/03/23 Tue 18/07/23 Tue 18/07/23 Mon 13/03/23 Mon 13/03/23 No 91 days 91 days
6.3.3.2 Pasang Flordrain 1 day 132 Thu 08/06/23 Thu 08/06/23 Tue 18/07/23 Tue 18/07/23 Thu 08/06/23 Thu 08/06/23 No 28 days 28 days
6.3.4 INSTALASI KOTORAN 19 days Mon 15/05/23 Thu 08/06/23 Tue 18/07/23 Tue 18/07/23 Mon 15/05/23 Thu 08/06/23 No 28 days 28 days
6.3.4.1 Pipa SNI 3 Inch AW 1 day 142 Mon 15/05/23 Mon 15/05/23 Tue 18/07/23 Tue 18/07/23 Mon 15/05/23 Mon 15/05/23 No 46 days 46 days
6.3.4.2 Pasang Kloset Jongkok Setara American Standar 1 day 132 Thu 08/06/23 Thu 08/06/23 Tue 18/07/23 Tue 18/07/23 Thu 08/06/23 Thu 08/06/23 No 28 days 28 days
6.3.5 INSTALASI AIR HUJAN 1 day Mon 15/05/23 Mon 15/05/23 Tue 18/07/23 Tue 18/07/23 Mon 15/05/23 Mon 15/05/23 No 46 days 46 days
6.3.5.1 Pipa SNI 2 1/2 Inch AW 1 day 142 Mon 15/05/23 Mon 15/05/23 Tue 18/07/23 Tue 18/07/23 Mon 15/05/23 Mon 15/05/23 No 46 days 46 days
7 PEKERJAAN FINISHING 10 days Wed 05/07/23 Tue 18/07/23 Wed 05/07/23 Tue 18/07/23 Wed 05/07/23 Tue 18/07/23 Yes 0 days 0 days
PEKERJAAN BESI, ALUMUNIUM, ORNAMEN DAN DINDING
7.1 5 days Wed 05/07/23 Tue 11/07/23 Wed 05/07/23 Tue 18/07/23 Wed 05/07/23 Tue 11/07/23 Yes 0 days 0 days
COMPOSITE
7.1.1 Terpasang Sesuai
3 days Lengkap 175
Pekerjaan Almunium Composite Panel Setara Seven Type PVDF + Rangka + Aksesoris Gambar
Wed 05/07/23 Fri 07/07/23 Wed 05/07/23 Fri 07/07/23 Wed 05/07/23 Fri 07/07/23 Yes 0 days 0 days
7.1.2 Huruf Timbul Gedung IGD + Aksesoris Lengkap Terpasang Sesuai Gambar (Bahan Stainless)
2 days 209 Mon 10/07/23 Tue 11/07/23 Mon 17/07/23 Tue 18/07/23 Mon 10/07/23 Tue 11/07/23 No 5 days 5 days
7.1.3 Huruf Timbul Gedung Utama + Aksesoris Lengkap Terpasang Sesuai Gambar (Bahan2 daysStainless) 209 Mon 10/07/23 Tue 11/07/23 Mon 17/07/23 Tue 18/07/23 Mon 10/07/23 Tue 11/07/23 No 5 days 5 days
7.1.4 Logo Puskesmas + Aksesoris Lengkap Terpasang Sesuai Gambar (Bahan Stainless)2 days 209 Mon 10/07/23 Tue 11/07/23 Mon 17/07/23 Tue 18/07/23 Mon 10/07/23 Tue 11/07/23 No 5 days 5 days
7.1.5 Reling Tangga Stainless + Aksesoris Lengkap Terpasang Sesuai Gambar 2 days 209 Mon 10/07/23 Tue 11/07/23 Mon 17/07/23 Tue 18/07/23 Mon 10/07/23 Tue 11/07/23 No 5 days 5 days
7.1.6 2 days
Handrail (Pegangan Tangan) Stainless + Aksesoris Lengkap Terpasang Sesuai Gambar 209 Mon 10/07/23 Tue 11/07/23 Mon 10/07/23 Tue 11/07/23 Mon 10/07/23 Tue 11/07/23 Yes 0 days 0 days
7.2 Pekerjan Pot Bunga 5 days Wed 12/07/23 Tue 18/07/23 Wed 12/07/23 Tue 18/07/23 Wed 12/07/23 Tue 18/07/23 Yes 0 days 0 days
7.2.1 Pasangan Dinding Bata 1PC : 4 PP 2 days 214 Wed 12/07/23 Thu 13/07/23 Wed 12/07/23 Thu 13/07/23 Wed 12/07/23 Thu 13/07/23 Yes 0 days 0 days
7.2.2 Plasteran Dinding Bata 1PC : 4 PP 1 day 216 Fri 14/07/23 Fri 14/07/23 Tue 18/07/23 Tue 18/07/23 Fri 14/07/23 Fri 14/07/23 No 2 days 2 days
7.2.3 Pesangan Batu Alam Tempel Susun Sirih + Cat Vernis Batu Alam 1 day 216 Fri 14/07/23 Fri 14/07/23 Tue 18/07/23 Tue 18/07/23 Fri 14/07/23 Fri 14/07/23 No 2 days 2 days
7.2.4 Relif Pot Bunga Sesuai Gambar 2 days 216 Fri 14/07/23 Mon 17/07/23 Fri 14/07/23 Mon 17/07/23 Fri 14/07/23 Mon 17/07/23 Yes 0 days 0 days
7.3 Pembersihan Akhir 1 day 219 Tue 18/07/23 Tue 18/07/23 Tue 18/07/23 Tue 18/07/23 Tue 18/07/23 Tue 18/07/23 Yes 0 days 0 days

Float dan lintasan kritis pada network planning ditandai dengan simbol FS-TS untuk float dan simbol warna merah dengan jumlah
pekerjan untuk lintasan kritis dapat dilihat pada lampian.

27
Praktikum Perencanaan & Pengendalian Proyek Konstruksi

3.6 Lintasan Kritis


Free
Total Float
Float
WBS Uraian Pekerjaan Durasi Critical
(Ffij = Ej-
(Tfij = Lj-Ei-D)
Ei-D)
1 PEKERJAAN PERSIAPAN 6 days 0 days 0 days Yes
1.1 Papan Nama Proyek Uk. 90 x120 1 day 0 days 0 days Yes
1.2 Administrasi/Dokumentasi dan Pelaporan 1 day 141 days 141 days No
1.3 Direksi Keet/sewa 6 days 136 days 136 days No
1.4 Perlengkapan P3k 1 day 141 days 141 days No
1.5 Pengukuran dan Pemasangan Bouwplank 2 days 140 days 140 days No
1.6 Pekerjaan Kesehatan dan Keselamatan Kerja 1 day 141 days 141 days No
1.7 Pagar pelindung proyek 2 days 0 days 0 days Yes
2 PEKERJAAN TANAH 36 days 0 days 0 days Yes
2.1 PEKERJAAN GALIAN 8 days 0 days 0 days Yes
2.1.1 Galian Tanah Pondasi Tapak 4 days 0 days 0 days Yes
2.1.2 Galian Tanah Pondasi Menerus 4 days 127 days 0 days No
2.2 PEKERJAAN TIMBUNAN 28 days 78 days 78 days No
2.2.1 Urugan Kembali Bekas Galian 4 days 66 days 0 days No
2.2.2 Pasir Urugan Bawah Pondasi Menerus 5 days 127 days 127 days No
2.2.3 Pasir Urugan dibawah Lantai 3 days 66 days 0 days No
2.2.4 Timbunan Tanah Dibawah Lantai 9 days 66 days 0 days No
3 PEKERJAAN STRUKTUR 88 days 6 days 6 days No
3.1 LANTAI 1 1 day 141 days 141 days No
PEKERJAAN PONDASI TAPAK BETON
3.2 51 days 0 days 0 days Yes
BERTULANG
3.2.1 Lantai Kerja Pondasi Tapak Setempat ( K.175) 1 day 0 days 0 days Yes
3.2.2 Pekerjaan Beton Bertulang Pondasi Tapak 9 days 0 days 0 days Yes
3.2.2.1 Cor Beton K 250 2 days 0 days 0 days Yes
3.2.2.2 Pembesian 5 days 0 days 0 days Yes
3.2.2.3 Bekisting 2 days 0 days 0 days Yes
3.2.3 Pekerjaan Pondasi Menerus 5 days 0 days 0 days Yes
Anstamping / Pasangan Batu Kosong Tebal 10
3.2.3.1 2 days 0 days 0 days Yes
Cm
3.2.3.2 Pasangan Pondasi Batu Gunung 1 PC : 4 PS 3 days 0 days 0 days Yes
3.2.4 Sloof (30/40) 7 days 0 days 0 days Yes
3.2.4.1 Pembesian 2 days 0 days 0 days Yes
3.2.4.2 Bekisting 3 days 0 days 0 days Yes
3.2.4.3 Cor Beton K 250 2 days 0 days 0 days Yes
3.2.5 Sloof (15/20) 3 days 118 days 118 days No
3.2.5.1 Pembesian 1 day 118 days 0 days No
3.2.5.2 Bekisting 1 day 118 days 0 days No
3.2.5.3 Cor Beton K 175 1 day 118 days 118 days No
3.2.6 Kolom Uk. 30/40 6 days 0 days 0 days Yes
3.2.6.1 Pembesian 2 days 0 days 0 days Yes
3.2.6.2 Bekisting 2 days 0 days 0 days Yes
3.2.6.3 Cor Beton K 250 2 days 0 days 0 days Yes
3.2.7 Kolom Uk. 15/15 3 days 105 days 105 days No
3.2.7.1 Pembesian 1 day 105 days 0 days No
3.2.7.2 Bekisting 1 day 105 days 0 days No
3.2.7.3 Cor Beton K 175 1 day 105 days 105 days No
3.2.8 Balok Latai (13/13) Elevasi ± 2.23 m 3 days 98 days 98 days No
3.2.8.1 Pembesian 1 day 98 days 98 days No
3.2.8.2 Bekisting 2 days 98 days 0 days No
3.2.8.3 Cor Beton K 175 1 day 98 days 98 days No
3.2.9 Balok Uk. 25/40 Elevasi ± 3.45 m 5 days 1 day 1 day No
3.2.9.1 Pembesian 2 days 99 days 99 days No
3.2.9.2 Bekisting 2 days 0 days 0 days Yes
3.2.9.3 Cor Beton K 250 2 days 0 days 0 days Yes
3.2.10 Ring Balok Uk. 15/20 Elevasi ± 3.45 m 3 days 0 days 0 days Yes

28
Praktikum Perencanaan & Pengendalian Proyek Konstruksi

3.2.10.1 Pembesian 1 day 0 days 0 days Yes


3.2.10.2 Bekisting 1 day 98 days 0 days No
3.2.10.3 Cor Beton K 175 1 day 98 days 98 days No
3.2.11 Plat Tangga dan Plat Bordes Tebal 10cm 3 days 0 days 0 days Yes
3.2.11.1 Pembesian 1 day 0 days 0 days Yes
3.2.11.2 Bekisting 1 day 0 days 0 days Yes
3.2.11.3 Cor Beton K 250 1 day 0 days 0 days Yes
3.3 LANTAI 2 42 days 0 days 0 days Yes
3.3.1 Kolom Uk. 30/30 6 days 0 days 0 days Yes
3.3.1.1 Pembesian 2 days 0 days 0 days Yes
3.3.1.2 Bekisting 2 days 0 days 0 days Yes
3.3.1.3 Cor Beton K 250 2 days 0 days 0 days Yes
3.3.2 Kolom Uk. 15/15 4 days 75 days 75 days No
3.3.2.1 Pembesian 1 day 75 days 0 days No
3.3.2.2 Bekisting 2 days 75 days 0 days No
3.3.2.3 Cor Beton K 175 1 day 75 days 75 days No
3.3.3 Balok Latai (13/13) Elevasi ± 6.23 m 2 days 69 days 69 days No
3.3.3.1 Pembesian 1 day 70 days 70 days No
3.3.3.2 Bekisting 1 day 69 days 0 days No
3.3.3.3 Cor Beton K 175 1 day 69 days 69 days No
3.3.4 Ring Balok Uk. 25/40 Elevasi ± 7.50 m 6 days 0 days 0 days Yes
3.3.4.1 Pembesian 2 days 0 days 0 days Yes
3.3.4.2 Bekisting 2 days 0 days 0 days Yes
3.3.4.3 Cor Beton K 250 2 days 0 days 0 days Yes
3.3.5 Ring Balok Uk. 15/20 Elevasi ±7.5 m 3 days 68 days 68 days No
3.3.5.1 Pembesian 1 day 68 days 0 days No
3.3.5.2 Bekisting 1 day 68 days 0 days No
3.3.5.3 Cor Beton K 175 1 day 68 days 68 days No
3.3.6 Plat Lantai Tebal 12cm 8 days 0 days 0 days Yes
3.3.6.1 Pembesian 4 days 0 days 0 days Yes
3.3.6.2 Bekisting 2 days 0 days 0 days Yes
3.3.6.3 Cor Beton K 250 2 days 0 days 0 days Yes
3.3.7 Plat dak dan Talang Beton 3 days 0 days 0 days Yes
3.3.7.1 Pembesian 1 day 0 days 0 days Yes
3.3.7.2 Bekisting 1 day 0 days 0 days Yes
3.3.7.3 Cor Beton K 250 1 day 0 days 0 days Yes
3.3.8 PEKERJAAN ATAP 8 days 0 days 0 days Yes
Rangka kuda-kuda dan gording baja ringan
3.3.8.1 8 days 0 days 0 days Yes
Multytruss
4 PEKERJAAN ARSITEKTUR 88 days 0 days 0 days Yes
4.1 LANTAI 1 42 days 0 days 0 days Yes
4.1.1 Pekerjaan Dinding 18 days 0 days 0 days Yes
4.1.1.1 Pasangan Trasram Bata 1 PC : 2 PP 1 day 0 days 0 days Yes
4.1.1.2 Pasangan Dinding Bata 1 PC : 4 PP 6 days 0 days 0 days Yes
4.1.1.3 Plesteran Trasram Bata 1 PC : 2 PP 1 day 66 days 0 days No
4.1.1.4 Plesteran Dinding Bata 1PC : 4 PP 9 days 66 days 0 days No
4.1.1.5 Plasteran Beton 1 PC : 3 PP 7 days 94 days 94 days No
Pesangan Batu Alam Tempel Susun Sirih + cat
4.1.1.6 2 days 90 days 90 days No
Vernis Batu Alam
4.1.2 Pekerjaan Lantai 27 days 66 days 66 days No
4.1.2.1 Pekerjaan Beton Tumbuk Tebal 7 cm (K 125) 1 day 66 days 0 days No
4.1.2.2 Pekerjaan Lantai Granite 60 x 60 Cm (Halus) 5 days 66 days 0 days No
4.1.2.3 Pekerjaan Lantai Granite 60 x 60 Cm (Kasar) 3 days 66 days 0 days No
Pekerjaan Lantai Keramik untuk Ruangan
4.1.2.4 1 day 66 days 0 days No
Wc/Km 20 X 20 Cm
4.1.2.5 Pasangan Dinding Keramik KM/WC 20 x 25 cm 2 days 66 days 0 days No
4.1.3 Pekerjaan Pintu, Jendela, Ventilasi 38 days 66 days 66 days No
Pintu Panel Kaca Tempered Glass 12mm +
4.1.3.1 1 day 67 days 67 days No
Aksesoris Lengkap Terpasang (Type P1)
4.1.3.2 Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris 2 days 66 days 66 days No

29
Praktikum Perencanaan & Pengendalian Proyek Konstruksi

Lengkap Terpasang Sesuai Gambar ( Type P2)


Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris
4.1.3.3 1 day 103 days 103 days No
Lengkap Terpasang Sesuai Gambar ( Type P5)
Kusen UPVC + Daun Pintu UPVC+ Aksesoris
4.1.3.4 1 day 67 days 67 days No
Lengkap Terpasang Sesuai Gambar (Type P4)
Kusen UPVC + Daun Pintu UPVC+ Aksesoris
4.1.3.5 1 day 67 days 67 days No
Lengkap Terpasang Sesuai Gambar (Type P3)
Kusen UPVC + Daun Jendela dan Ventilasi Kaca
4.1.3.6 5mm + Aksesoris Lengkap Terpasang Sesuai Gambar 2 days 66 days 66 days No
(Type JV1)
Kusen UPVC + Daun Jendela dan Ventilasi Kaca
4.1.3.7 5mm + Aksesoris Lengkap Terpasang Sesuai Gambar 1 day 103 days 103 days No
(Type J2)
Kusen UPVC + Daun ventilasi Kaca 5mm +
4.1.3.8 1 day 67 days 67 days No
Aksesoris Lengkap Terpasang Sesuai Gambar (Type V2)
4.1.4 Pekerjaan Plafond 4 days 66 days 66 days No
Pasang Plafon PVC/Fiber + Rangka + Aksesoris
4.1.4.1 4 days 66 days 0 days No
Lengkap Terpasang Sesuai Gambar
4.1.5 Pekerjaan Pengecatan 4 days 66 days 66 days No
Pengecatan Tembok dan Sealer 3x(L/D) Setara
4.1.5.1 4 days 66 days 0 days No
Vinilex
4.2 LANTAI 2 59 days 0 days 0 days Yes
4.2.1 Pekerjaan Dinding 43 days 0 days 0 days Yes
4.2.1.1 Pasangan Trasram Bata 1 PC : 2 PP 2 days 0 days 0 days Yes
4.2.1.2 Pasangan Dinding Bata 1 PC : 4 PP 6 days 0 days 0 days Yes
4.2.1.3 Plesteran Trasram Bata 1 PC : 2 PP 1 day 0 days 0 days Yes
4.2.1.4 Plesteran Dinding Bata 1PC : 4 PP 14 days 0 days 0 days Yes
4.2.1.5 Plasteran Beton 1 PC : 3 PP 3 days 36 days 36 days No
Pesangan Batu Alam Tempel Susun Sirih + cat
4.2.1.6 2 days 37 days 37 days No
Vernis Batu Alam
4.2.2 Pekerjaan Lantai 10 days 3 days 3 days No
4.2.2.1 Pekerjaan Beton Tumbuk Tebal 7 cm (K 125) 2 days 37 days 37 days No
4.2.2.2 Pekerjaan Lantai Granite 60 x 60 Cm (Halus) 5 days 0 days 0 days Yes
Pekerjaan Lantai Keramik untuk Ruangan
4.2.2.3 1 day 0 days 0 days Yes
Wc/Km 20 X 20 Cm
4.2.2.4 Pasangan Dinding Keramik KM/WC 20 x 25 cm 1 day 0 days 0 days Yes
4.2.3 Pekerjaan Pintu, Jendela, Ventilasi 1 day 0 days 0 days Yes
Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris
4.2.3.1 1 day 20 days 20 days No
Lengkap Terpasang Sesuai Gambar ( Type P2)
Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris
4.2.3.2 1 day 20 days 20 days No
Lengkap Terpasang Sesuai Gambar ( Type P5)
Kusen UPVC + Daun Pintu UPVC+ Aksesoris
4.2.3.3 1 day 0 days 0 days Yes
Lengkap Terpasang Sesuai Gambar (Type P4)
Kusen UPVC + Daun Jendela dan Ventilasi Kaca
4.2.3.4 5mm + Aksesoris Lengkap Terpasang Sesuai Gambar 1 day 20 days 20 days No
(Type JV1)
Kusen UPVC + Daun Jendela dan Ventilasi Kaca
4.2.3.5 5mm + Aksesoris Lengkap Terpasang Sesuai Gambar 1 day 20 days 20 days No
(Type J2)
Kusen UPVC + Daun ventilasi Kaca 5mm +
4.2.3.6 1 day 20 days 20 days No
Aksesoris Lengkap Terpasang Sesuai Gambar (Type V2)
4.2.4 PEKERJAAN ATAP 10 days 44 days 44 days No
4.2.4.1 Penutup Atap genteng Onduline 5 days 44 days 0 days No
4.2.4.2 Rabung genteng Onduline 2 days 44 days 0 days No
4.2.4.3 Lisplank Kayu 2/20 cm 3 days 44 days 44 days No
4.2.5 Pekerjaan Plafond 3 days 0 days 0 days Yes
Pasang Plafon PVC/Fiber + Rangka + Aksesoris
4.2.5.1 3 days 0 days 0 days Yes
Lengkap Terpasang Sesuai Gambar
4.2.6 Pekerjaan Pengecatan 4 days 0 days 0 days Yes
Pengecatan Tembok dan Sealer 3x(L/D) Setara
4.2.6.1 4 days 0 days 0 days Yes
Vinilex

30
Praktikum Perencanaan & Pengendalian Proyek Konstruksi

5 PEKERJAAN ELEKTRIKAL 52 days 21 days 21 days No


Instlasi titik penerangan, instalasi termasuk kabel
5.1 NYA 2,5 mm dalam pipa PVC fitting lampu dan 1 day 72 days 72 days No
kelengkapan instalasi terpasang
Instalasi titik Stop kontak, instalasi termasuk kabel
5.2 NYA 2,5 mm dalam pipa PVC fitting lampu dan 1 day 66 days 0 days No
kelengkapan instalasi terpasang
5.3 Pemasangan Box Sekring 1 day 72 days 72 days No
5.4 Pemasukan Arus Listrik 12 Ampere 1 day 72 days 72 days No
5.5 LANTAI 1 4 days 66 days 66 days No
5.5.1 Armatur 2 days 66 days 66 days No
Lampu Downlight 23 watt + Accesori Lengkap
5.5.1.1 1 day 66 days 0 days No
Terpasang
Lampu RM TL 2X36 watt + Accesori Lengkap
5.5.1.2 1 day 66 days 0 days No
Terpasang
5.5.2 Saklar lampu Merk Setara Broco 2 seri 2 days 66 days 66 days No
5.5.2.1 Sakalar 1 Seri setara Broco 1 day 69 days 69 days No
5.5.2.2 Sakalar 2 Seri setara Broco 1 day 66 days 0 days No
5.5.2.3 Stop Kontak 1 day 66 days 0 days No
5.6 LANTAI 2 4 days 0 days 0 days Yes
5.6.1 Armatur 2 days 0 days 0 days Yes
Lampu Downlight 23 watt + Accesori Lengkap
5.6.1.1 1 day 0 days 0 days Yes
Terpasang
Lampu RM TL 2X36 watt + Accesori Lengkap
5.6.1.2 1 day 0 days 0 days Yes
Terpasang
5.6.2 Saklar lampu Merk Setara Broco 2 seri 2 days 0 days 0 days Yes
5.6.2.1 Sakalar 1 Seri setara Broco 1 day 22 days 22 days No
5.6.2.2 Sakalar 2 Seri setara Broco 1 day 0 days 0 days Yes
5.6.2.3 Stop Kontak 1 day 0 days 0 days Yes
132
6 PEKERJAAN MEKANIKAL 10 days 10 days No
days
6.1 PEKERJAAN SALURAN DRAINASE 10 days 0 days 0 days Yes
6.1.1 Pasangan Bata Dinding Saluran 1 PC : 2 PP 2 days 0 days 0 days Yes
Pasangan Plasteran Bata Dinding Saluran 1 PC : 2
6.1.2 2 days 0 days 0 days Yes
PP
6.1.3 Cor Lantai Saluran 2 days 0 days 0 days Yes
6.1.4 Buis Beton Dia. 20 cm 2 days 0 days 0 days Yes
Pemasangan Grill Saluran Bentuk Sesuai Gambar +
6.1.5 2 days 0 days 0 days Yes
Cat Meni Hitam
6.2 LANTAI 1 96 days 46 days 46 days No
6.2.1 Pekerjaan Sanitasi 1 day 141 days 141 days No
6.2.2 INSTALASI AIR KOTOR 3 days 76 days 76 days No
6.2.2.1 Pasang Floordrain 1 day 78 days 78 days No
6.2.2.2 Pipa SNI 3 Inch AW 1 day 76 days 76 days No
6.2.3 INSTALASI AIR BERSIH 27 days 66 days 66 days No
Memasang Wastafel + Keran Air + Pembungan
6.2.3.1 Air Type Sifon angsa Aksesoris Lengkap Terpasang 1 day 76 days 76 days No
Setara Toto
6.2.3.2 Pipa SNI 1/2 Inch AW 1 day 102 days 102 days No
6.2.3.3 Pasang Pipa Air Sampai Ketitik Air 1 day 66 days 0 days No
6.2.4 INSTALASI AIR HUJAN 1 day 46 days 46 days No
6.2.4.1 Pipa SNI 2 1/2 Inch AW 1 day 46 days 46 days No
6.2.5 INSTALASI KOTORAN 43 days 66 days 66 days No
6.2.5.1 Pipa SNI 3 Inch AW 1 day 66 days 0 days No
6.2.5.2 Septick Tank + Resapan Lengkap Terpasang 1 day 119 days 119 days No
6.2.5.3 Pasang Kloset Duduk SetaraToto 1 day 78 days 78 days No
114
6.3 LANTAI 2 28 days 28 days No
days
6.3.1 Pekerjaan Sanitasi 1 day 141 days 141 days No
6.3.2 INSTALASI AIR BERSIH 64 days 28 days 28 days No
6.3.2.1 Bak Mandi Pyber Glass (60 x 60) 1 day 28 days 28 days No

31
Praktikum Perencanaan & Pengendalian Proyek Konstruksi

6.3.2.2 Pasang Kran Air 1/2" 1 day 91 days 91 days No


6.3.2.3 Pipa SNI 1 Inch AW 1 day 91 days 91 days No
6.3.2.4 Pipa SNI 1/2 Inch AW 1 day 91 days 91 days No
6.3.2.5 Pasang Pipa Air Sampai Ketitik Air 1 day 91 days 91 days No
6.3.3 INSTALASI AIR KOTOR 64 days 28 days 28 days No
6.3.3.1 Pipa SNI 3 Inch AW 1 day 91 days 91 days No
6.3.3.2 Pasang Flordrain 1 day 28 days 28 days No
6.3.4 INSTALASI KOTORAN 19 days 28 days 28 days No
6.3.4.1 Pipa SNI 3 Inch AW 1 day 46 days 46 days No
6.3.4.2 Pasang Kloset Jongkok Setara American Standar 1 day 28 days 28 days No
6.3.5 INSTALASI AIR HUJAN 1 day 46 days 46 days No
6.3.5.1 Pipa SNI 2 1/2 Inch AW 1 day 46 days 46 days No
7 PEKERJAAN FINISHING 10 days 0 days 0 days Yes
PEKERJAAN BESI, ALUMUNIUM, ORNAMEN DAN
7.1 5 days 0 days 0 days Yes
DINDING COMPOSITE
Pekerjaan Almunium Composite Panel Setara
7.1.1 Seven Type PVDF + Rangka + Aksesoris Lengkap 3 days 0 days 0 days Yes
Terpasang Sesuai Gambar
Huruf Timbul Gedung IGD + Aksesoris Lengkap
7.1.2 2 days 5 days 5 days No
Terpasang Sesuai Gambar (Bahan Stainless)
Huruf Timbul Gedung Utama + Aksesoris Lengkap
7.1.3 2 days 5 days 5 days No
Terpasang Sesuai Gambar (Bahan Stainless)
Logo Puskesmas + Aksesoris Lengkap Terpasang
7.1.4 2 days 5 days 5 days No
Sesuai Gambar (Bahan Stainless)
Reling Tangga Stainless + Aksesoris Lengkap
7.1.5 2 days 5 days 5 days No
Terpasang Sesuai Gambar
Handrail (Pegangan Tangan) Stainless + Aksesoris
7.1.6 2 days 0 days 0 days Yes
Lengkap Terpasang Sesuai Gambar
7.2 Pekerjan Pot Bunga 5 days 0 days 0 days Yes
7.2.1 Pasangan Dinding Bata 1PC : 4 PP 2 days 0 days 0 days Yes
7.2.2 Plasteran Dinding Bata 1PC : 4 PP 1 day 2 days 2 days No
Pesangan Batu Alam Tempel Susun Sirih + Cat
7.2.3 1 day 2 days 2 days No
Vernis Batu Alam
7.2.4 Relif Pot Bunga Sesuai Gambar 2 days 0 days 0 days Yes
7.3 Pembersihan Akhir 1 day 0 days 0 days Yes

32
BAB IV
Praktikum Perencanaan & Pengendalian Proyek Konstruksi

BAB IV
KESIMPULAN DAN SARAN

4.1 Kesimpulan
Dari hasil analisis pembahasan yang telah diuraikan pada bab sebelumnya,
dapat ditarik kesimpulan sebagai berikut:
• Hasil perencanaan dapat disimpulkan bahwa upaya peningkatan kualitas
perencanaan dan pengendalian jadwal pada suatu proyek akan
mengakibatkan meningkatnya hasil kinerja waktu suatu proyek itu sendiri.
Dalam tulisan ini peningkatan kualitas dapat dicapai dengan menggunakan
suatu program Microsoft Project 2021, karena dengan menggunakan aplikasi
tersebut dapat dengan cepat melakukan penjadwalan ulang jika suatu
pekerjaan mengalami keterlambatan dari jadwal yang telah direncanakan.
• Logika ketergantungan antar pekerjaan memperlihatkan alur pekerjaan
hingga selesainya suatu proyek. Pekerjaan-pekerjaan tersebut saling
berhubungan dengan kata lain satu pekerjaan akan bergantung dengan
pekerjaan lainnya. Terdapat tiga macam konstrain yang dipakai dalam logika
ketergantungan :
a) Finish to Start (FS)

b) Start to Start (SS)

c) Finish to Finish (FF)

• Lintasan kritis (critical path) adalah lintasan terpanjang, dalam hal total
waktu, diantara semua lintasan yang ada pada suatu network diagram.
Lintasan kritis inilah yang akan menentukan total durasi tercepat untuk
menyelesaikan semua kegiatan pada proyek tersebut.
• Dari hasil perencanaan jadwal oleh penulis dengan menggunakan Microsoft
Project 2021 diperoleh hasil 142 hari kerja, waktu penyelesaian proyek.

33
Praktikum Perencanaan & Pengendalian Proyek Konstruksi

4.2 Saran

• Mahasiswa harus memahami maksud dan tujuan dari perencanaan dan


pengendalian biaya sehingga dalam pengerjaannya lebih mudah dan tidak
mengulur-ulur waktu.
• Mahasiswa seharusnya harus lebih sering berkonsultasi dalam
menyelesaikan tugas praktikum ini, baik itu dengan dosen maupun dengan
asisten laboratorium yang selama ini telah membantu dalam pelaksanaan
praktikum.
• Perlu adanya pengembangan dan pelatihan tentang pemanfaatan Microsoft
Project 2021, agar software ini dapat secara optimal dalam membantu
memecahkan masalah- masalah dalam manajemen proyek yang
membutuhkan penjadwalan yang akurat.
• Penjadwalan proyek yang lebih detail akan membantu kita dalam mengontrol
baik biaya maupun perkembangan proyek apakah sesuai target atau tidak.

34
Praktikum Perencanaan & Pengendalian Proyek Konstruksi

DAFTAR PUSTAKA

1. Anonim 2020, Keputusan Gubernur Nanggroe Aceh Darussalam (NAD),


Peneta- pan Standar Barang dan Harga Satuan Barang Kebutuhan
Pemerintah Aceh Barat Daya, Bagian Umum Sekretariat Kabupaten Aceh
Barat Daya, 2021

2. Anonim, 2022, Analisis Harga Satuan Pekerjaan Bidang Pekerjaan


Umum,

3. Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat.

4. Badan Standardisasi Nasional (BSN), Standar Nasional Indonesia 2016 (SNI-


2016)

5. Ibrahim, Bachtiar H, Rencana Dan Estimate Of Cost, Bumi Aksara, Jakarta


1993.

6. Ir. Asiyanto, MBA, IPM, Construction Project Cost Management (cetakan


kedua), PT. Pradnya Paramita, Jakarta 2005.

35
LAMPIRAN
Praktikum Perencanaan & Pengendalian Proyek Konstruksi

a. Gambar Proyek

36
Praktikum Perencanaan & Pengendalian Proyek Konstruksi

37
Praktikum Perencanaan & Pengendalian Proyek Konstruksi

38
Pa ge 39
Pa ge 40
RENCANA ANGGARAN BIAYA

WBS URAIAN PEKERJAAN ANALISA VOLUME SAT HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

1 PEKERJAAN PERSIAPAN
1.1 Papan Nama Proyek Uk. 90 x120 Taksir 1,00 UNIT Rp 250.000,00 Rp 250.000,00
1.2 Administrasi/Dokumentasi dan Pelaporan Taksir 1,00 LS Rp 300.000,00 Rp 300.000,00
1.3 Direksi Keet/sewa AHSP PU : A.2.2.1.6 24,00 M3 Rp 451.808,55 Rp 10.843.405,20
1.4 Perlengkapan P3k Taksir 1,00 PAKET Rp 500.000,00 Rp 500.000,00
1.5 Pengukuran dan Pemasangan Bouwplank AHSP PU : A.2.2.1.4 68,00 M2 Rp 907.396,00 Rp 61.702.928,00
1.6 Sistem Manajemen Kesehatan dan Keselamatan Kerja ANSMK3 1,00 PAKET Rp 4.961.100,00 Rp 4.961.100,00
1.7 Pagar pelindung proyek AHSP PU : A.2.2.1.2 52,50 M2 Rp 271.860,00 Rp 14.272.650,00
Sub Jumlah Rp 92.830.083,20
2 PEKERJAAN TANAH
2.1 PEKERJAAN GALIAN
2.1.1 Galian Tanah Pondasi Tapak AHSP PU : A.2.3.1.1 70,20 M3 Rp 80.960,00 Rp 5.683.392,00
2.1.2 Galian Tanah Pondasi Menerus AHSP PU : A.2.3.1.2 71,30 M3 Rp 99.153,00 Rp 7.069.608,90
Sub Jumlah Rp 12.753.000,90
2.2 PEKERJAAN TIMBUNAN
2.2.1 Urugan Kembali Bekas Galian AHSP PU : A.2.3.1.9 35,38 M3 Rp 58.420,00 Rp 2.066.609,62
2.2.2 Pasir Urugan Bawah Pondasi Menerus AHSP PU : A.2.3.1.11 71,30 M3 Rp 232.484,00 Rp 16.576.109,20
2.2.3 Pasir Urugan dibawah Lantai AHSP PU : A.2.3.1.11 20,48 M3 Rp 232.484,00 Rp 4.760.109,90
2.2.4 Timbunan Tanah Dibawah Lantai AHSP PU : A.2.3.1.15 266,18 M3 Rp 192.620,00 Rp 51.270.628,50
Sub Jumlah Rp 74.673.457,22
3 PEKERJAAN STRUKTUR
3.1 LANTAI 1
3.1.1 PEKERJAAN PONDASI TAPAK BETON BERTULANG
3.1.1.1 Lantai Kerja Pondasi Tapak Setempat ( K.175) AHSP PU : A.4.1.1.5 3,78 M3 Rp 1.106.050,19 Rp 4.180.869,74
3.1.2 Pekerjaan Beton Bertulang Pondasi Tapak
3.1.2.1 Cor Beton K 250 AHSP PU : A.4.1.1.8 21,60 M3 Rp 1.205.727,51 Rp 26.043.714,20
3.1.2.2 Pembesian AHSP PU : A.4.1.1.17a 7348,56 KG Rp 18.676,23 Rp 137.243.445,14
3.1.2.3 Bekisting AHSP PU : A.4.1.1.20 115,20 M2 Rp 116.725,00 Rp 13.446.720,00
3.1.3 Pekerjaan Pondasi Menerus
3.1.3.1 Anstamping / Pasangan Batu Kosong Tebal 10 Cm AHSP PU : A.3.2.1.9 6,60 M3 Rp 492.246,00 Rp 3.249.561,97
3.1.3.2 Pasangan Pondasi Batu Gunung 1 PC : 4 PS AHSP PU : A.3.2.1.2 28,01 M3 Rp 960.244,25 Rp 26.898.842,05
3.1.4 Sloof (30/40)
3.1.4.1 Pembesian AHSP PU : A.4.1.1.17a 2098,78 KG Rp 18.676,23 Rp 39.197.298,00
3.1.4.2 Bekisting AHSP PU : A.4.1.1.21 197,40 M2 Rp 125.350,00 Rp 24.744.090,00
3.1.4.3 Cor Beton K 250 AHSP PU : A.4.1.1.8 13,25 M3 Rp 1.205.727,51 Rp 15.973.478,04

Pa ge 41
WBS URAIAN PEKERJAAN ANALISA VOLUME SAT HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

3.1.5 Sloof (15/20)


3.1.5.1 Pembesian AHSP PU : A.4.1.1.17a 237,81 KG Rp 18.676,23 Rp 4.441.338,23
3.1.5.2 Bekisting AHSP PU : A.4.1.1.21 3,15 M2 Rp 125.350,00 Rp 394.852,50
3.1.5.3 Cor Beton K 175 AHSP PU : A.4.1.1.5 0,14 M3 Rp 1.205.727,51 Rp 162.773,21
3.1.6 Kolom Uk. 30/40
3.1.6.1 Pembesian AHSP PU : A.4.1.1.17a 1525,50 KG Rp 18.733,39 Rp 28.577.712,28
3.1.6.2 Bekisting AHSP PU : A.4.1.1.22 134,40 M2 Rp 93.320,49 Rp 12.542.273,52
3.1.6.3 Cor Beton K 250 AHSP PU : A.4.1.1.8 9,94 M3 Rp 1.207.973,46 Rp 12.002.424,29
3.1.7 Kolom Uk. 15/15
3.1.7.1 Pembesian AHSP PU : A.4.1.1.17a 68,49 KG Rp 18.676,23 Rp 1.279.049,11
3.1.7.2 Bekisting AHSP PU : A.4.1.1.22 9,60 M2 Rp 125.350,00 Rp 1.203.360,00
3.1.7.3 Cor Beton K 175 AHSP PU : A.4.1.1.5 0,78 M3 Rp 1.207.973,46 Rp 937.689,40
3.1.8 Balok Latai (13/13) Elevasi ± 2.23 m
3.1.8.1 Pembesian AHSP PU : A.4.1.1.17a 252,27 KG Rp 18.676,23 Rp 4.711.508,57
3.1.8.2 Bekisting AHSP PU : A.4.1.1.23 1398,36 M2 Rp 125.350,00 Rp 175.284.426,00
3.1.8.3 Cor Beton K 175 AHSP PU : A.4.1.1.5 1,20 M3 Rp 1.207.973,46 Rp 1.448.018,32
3.1.9 Ring Balok Uk. 25/30 Elevasi ± 3.45 m
3.1.9.1 Pembesian AHSP PU : A.4.1.1.17a 1332,43 KG Rp 18.676,23 Rp 24.884.675,76
3.1.9.2 Bekisting AHSP PU : A.4.1.1.23 136,50 M2 Rp 125.350,00 Rp 17.110.275,00
3.1.9.3 Cor Beton K 250 AHSP PU : A.4.1.1.8 12,80 M3 Rp 1.207.973,46 Rp 15.457.228,38
3.1.10 Ring Balok Uk. 15/20 Elevasi ± 3.45 m
3.1.10.1 Pembesian AHSP PU : A.4.1.1.17a 25,01 KG Rp 18.676,23 Rp 467.167,22
3.1.10.2 Bekisting AHSP PU : A.4.1.1.23 3,15 M2 Rp 125.350,00 Rp 394.852,50
3.1.10.3 Cor Beton K 175 AHSP PU : A.4.1.1.5 0,12 M3 Rp 1.207.973,46 Rp 147.493,56
3.1.11 Plat Tangga dan Plat Bordes Tebal 10cm
3.1.11.1 Pembesian AHSP PU : A.4.1.1.17a 338,00 KG Rp 18.676,23 Rp 6.312.649,20
3.1.11.2 Bekisting AHSP PU : A.4.1.1.26 29,06 M2 Rp 125.350,00 Rp 3.642.921,70
3.1.11.3 Cor Beton K 250 AHSP PU : A.4.1.1.8 0,90 M3 Rp 1.207.973,46 Rp 1.081.136,25
Sub Jumlah Rp 603.461.844,14
3.2 LANTAI 2
3.2.1 Kolom Uk. 30/30 Rp -
3.2.1.1 Pembesian AHSP PU : A.4.1.1.17a 756,27 KG Rp 18.676,23 Rp 14.124.278,74
3.2.1.2 Bekisting AHSP PU : A.4.1.1.22 109,44 M2 Rp 93.320,49 Rp 10.212.994,15
3.2.1.3 Cor Beton K 250 AHSP PU : A.4.1.1.8 6,91 M3 Rp 1.207.973,46 Rp 8.349.512,55

Pa ge 42
WBS URAIAN PEKERJAAN ANALISA VOLUME SAT HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

3.2.2 Kolom Uk. 15/15


3.2.2.1 Pembesian AHSP PU : A.4.1.1.17a 65,13 KG Rp 18.676,23 Rp 1.216.426,07
3.2.2.2 Bekisting AHSP PU : A.4.1.1.22 109,44 M2 Rp 93.320,49 Rp 10.212.994,15
3.2.2.3 Cor Beton K 175 AHSP PU : A.4.1.1.5 0,86 M3 Rp 1.207.973,46 Rp 1.043.689,07
3.2.3 Balok Latai (13/13) Elevasi ± 6.23 m
3.2.3.1 Pembesian AHSP PU : A.4.1.1.17a 279,66 KG Rp 18.676,23 Rp 5.223.069,19
3.2.3.2 Bekisting AHSP PU : A.4.1.1.23 50,44 M2 Rp 125.350,00 Rp 6.322.654,00
3.2.3.3 Cor Beton K 175 AHSP PU : A.4.1.1.5 1,34 M3 Rp 1.207.973,46 Rp 1.620.318,82
3.2.4 Ring Balok Uk. 25/30 Elevasi ± 7.50 m
3.2.4.1 Pembesian AHSP PU : A.4.1.1.17a 1332,43 KG Rp 18.676,23 Rp 24.884.675,76
3.2.4.2 Bekisting AHSP PU : A.4.1.1.23 115,50 M2 Rp 125.350,00 Rp 14.477.925,00
3.2.4.3 Cor Beton K 250 AHSP PU : A.4.1.1.8 12,80 M3 Rp 1.207.973,46 Rp 15.462.060,28
3.2.5 Ring Balok Uk. 15/20 Elevasi ±7.5 m
3.2.5.1 Pembesian AHSP PU : A.4.1.1.17a 25,01 KG Rp 18.676,23 Rp 467.167,22
3.2.5.2 Bekisting AHSP PU : A.4.1.1.23 3,15 M2 Rp 125.350,00 Rp 394.852,50
3.2.5.3 Cor Beton K 175 AHSP PU : A.4.1.1.5 0,12 M3 Rp 1.207.973,46 Rp 147.493,56
3.2.6 Plat Lantai Tebal 12cm
3.2.6.1 Pembesian AHSP PU : A.4.1.1.17a 5163,15 KG Rp 18.676,23 Rp 96.428.226,14
3.2.6.2 Bekisting AHSP PU : A.4.1.1.24 217,23 M2 Rp 262.055,10 Rp 56.926.229,37
3.2.6.3 Cor Beton K 250 AHSP PU : A.4.1.1.8 20,33 M3 Rp 1.207.973,46 Rp 24.561.120,36
3.2.7 Plat dak dan Talang Beton
3.2.7.1 Pembesian AHSP PU : A.4.1.1.17a 412,54 KG Rp 18.676,23 Rp 7.704.607,36
3.2.7.2 Bekisting AHSP PU : A.4.1.1.24 61,20 M2 Rp 262.055,10 Rp 16.037.772,12
3.2.7.3 Cor Beton K 250 AHSP PU : A.4.1.1.8 4,54 M3 Rp 1.207.973,46 Rp 5.489.031,40
3.2.8 PEKERJAAN ATAP
3.2.8.1 Rangka kuda-kuda dan gording baja ringan Multytruss AHSP PU : A.4.2.1.24 234,57 M2 Rp 215.174,58 Rp 50.473.502,01
Sub Jumlah Rp 371.780.599,81
4 PEKERJAAN ARSITETKTUR
4.1 LANTAI 1
4.1.1 Pekerjaan Dinding
4.1.1.1 Pasangan Trasram Bata 1 PC : 2 PP AHSP PU: A.4.4.1.7 38,84 M2 Rp 159.729,25 Rp 6.203.404,88
4.1.1.2 Pasangan Dinding Bata 1 PC : 4 PP AHSP PU : A.4.4.1.9 283,29 M2 Rp 144.902,88 Rp 41.049.463,01
4.1.1.3 Plesteran Trasram Bata 1 PC : 2 PP AHSP PU : A.4.4.2.22 77,67 M2 Rp 76.337,92 Rp 5.929.166,25
4.1.1.4 Plesteran Dinding Bata 1PC : 4 PP AHSP PU: A. 4.4.2.24 566,58 M2 Rp 145.322,63 Rp 82.336.892,87
4.1.1.5 Plasteran Beton 1 PC : 3 PP AHSP PU : A.4.4.2.23 185,04 M2 Rp 69.469,20 Rp 12.854.580,77
4.1.1.6 Pesangan Batu Alam Tempel Susun Sirih + cat Vernis Batu Alam AHSP PU : A.4.4.3.58 95,55 M2 Rp 505.971,25 Rp 48.345.552,94

Pa ge 43
WBS URAIAN PEKERJAAN ANALISA VOLUME SAT HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

4.1.2 Pekerjaan Lantai


4.1.2.1 Pekerjaan Beton Tumbuk Tebal 7 cm (K 125) AHSP PU : A.4.1.1.2 9,96 M3 Rp 1.177.318,25 Rp 11.721.792,56
4.1.2.2 Pekerjaan Lantai Granite 60 x 60 Cm (Halus) AHSP PU : A.4.4.3.9 a 147,28 M2 Rp 452.773,40 Rp 66.682.428,87
4.1.2.3 Pekerjaan Lantai Granite 60 x 60 Cm (Kasar) AHSP PU : A.4.4.3.9 a 48,73 M2 Rp 452.773,40 Rp 22.063.647,78
4.1.2.4 Pekerjaan Lantai Keramik untuk Ruangan Wc/Km 20 X 20 Cm AHSP PU : A.4.4.3.36 7,49 M2 Rp 240.782,40 Rp 1.804.062,13
4.1.2.5 Pasangan Dinding Keramik KM/WC 20 x 25 cm AHSP PU : A.4.4.3.65 44,93 M2 Rp 260.049,50 Rp 11.684.024,04
4.1.3 Pekerjaan Pintu, Jendela, Ventilasi
4.1.3.1 Pintu Panel Kaca Tempered Glass 12mm + Aksesoris Lengkap Terpasang (Type P1)
Taksir 2,00 Unit Rp 7.000.000,00 Rp 14.000.000,00
4.1.3.2 Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris Lengkap Terpasang Sesuai Gambar
Taksir
( Type P2) 5,00 Unit Rp 1.500.000,00 Rp 7.500.000,00
4.1.3.3 Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris Lengkap Terpasang Sesuai Gambar
Taksir
( Type P5) 1,00 Unit Rp 3.000.000,00 Rp 3.000.000,00
4.1.3.4 Kusen UPVC + Daun Pintu UPVC+ Aksesoris Lengkap Terpasang Sesuai Gambar (Type
TaksirP4) 1,00 Unit Rp 1.500.000,00 Rp 1.500.000,00
4.1.3.5 Kusen UPVC + Daun Pintu UPVC+ Aksesoris Lengkap Terpasang Sesuai Gambar (Type
TaksirP3) 2,00 Unit Rp 2.000.000,00 Rp 4.000.000,00
4.1.3.6 Kusen UPVC + Daun Jendela dan Ventilasi Kaca 5mm + Aksesoris Lengkap Terpasang
Taksir
Sesuai Gambar (Type
6,00 JV1) Unit Rp 5.000.000,00 Rp 30.000.000,00
4.1.3.7 Kusen UPVC + Daun Jendela dan Ventilasi Kaca 5mm + Aksesoris Lengkap Terpasang
Taksir
Sesuai Gambar (Type
4,00 J2) Unit Rp 1.000.000,00 Rp 4.000.000,00
4.1.3.8 Kusen UPVC + Daun ventilasi Kaca 5mm + Aksesoris Lengkap Terpasang Sesuai Gambar
Taksir (Type V2) 3,00 Unit Rp 300.000,00 Rp 900.000,00
4.1.4 Pekerjaan Plafond
4.1.4.1 Pasang Plafon PVC/Fiber + Rangka + Aksesoris Lengkap Terpasang Sesuai AHSP
Gambar
PU: A.4.5.1.7 a 199,13 M2 Rp 292.853,25 Rp 58.314.989,11
4.1.5 Pekerjaan Pengecatan
4.1.5.1 Pengecatan Tembok dan Sealer 3x(L/D) Setara Vinilex AHSP PU : A.4.7.1.10b 855,73 M2 Rp 28.500,00 Rp 24.388.291,61
Sub Jumlah Rp 458.278.296,81
4.2 LANTAI 2
4.2.1 Pekerjaan Dinding
4.2.1.1 Pasangan Trasram Bata 1 PC : 2 PP AHSP PU: A.4.4.1.7 23,97 M2 Rp 159.729,25 Rp 3.828.710,12
4.2.1.2 Pasangan Dinding Bata 1 PC : 4 PP AHSP PU : A.4.4.1.9 347,75 M2 Rp 145.322,63 Rp 50.535.942,84
4.2.1.3 Plesteran Trasram Bata 1 PC : 2 PP AHSP PU : A.4.4.2.22 47,94 M2 Rp 76.337,92 Rp 3.659.639,88
4.2.1.4 Plesteran Dinding Bata 1PC : 4 PP AHSP PU: A. 4.4.2.24 695,50 M2 Rp 69.465,75 Rp 48.313.429,13
4.2.1.5 Plasteran Beton 1 PC : 3 PP AHSP PU : A.4.4.2.23 69,12 M2 Rp 69.469,20 Rp 4.801.711,10
4.2.1.6 Pesangan Batu Alam Tempel Susun Sirih + cat Vernis Batu Alam AHSP PU : A.4.4.3.58 95,55 M2 Rp 505.971,25 Rp 48.345.552,94
4.2.2 Pekerjaan Lantai
4.2.2.1 Pekerjaan Beton Tumbuk Tebal 7 cm (K 125) AHSP PU : A.4.1.1.2 8,38 M3 Rp 1.177.318,25 Rp 9.862.836,47
4.2.2.2 Pekerjaan Lantai Granite 60 x 60 Cm (Halus) AHSP PU : A.4.4.3.9 a 165,66 M2 Rp 452.773,40 Rp 75.005.309,51
4.2.2.3 Pekerjaan Lantai Keramik untuk Ruangan Wc/Km 20 X 20 Cm AHSP PU : A.4.4.3.36 5,00 M2 Rp 240.782,40 Rp 1.202.708,09
4.2.2.4 Pasangan Dinding Keramik KM/WC 20 x 25 cm AHSP PU : A.4.4.3.65 24,14 M2 Rp 260.049,50 Rp 6.277.594,93

Pa ge 44
WBS URAIAN PEKERJAAN ANALISA VOLUME SAT HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

4.2.3 Pekerjaan Pintu, Jendela, Ventilasi


4.2.3.1 Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris Lengkap Terpasang Sesuai Gambar
Taksir
( Type P2) 4,00 Unit Rp 1.500.000,00 Rp 6.000.000,00
4.2.3.2 Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris Lengkap Terpasang Sesuai Gambar
Taksir
( Type P5) 1,00 Unit Rp 3.000.000,00 Rp 3.000.000,00
4.2.3.3 Kusen UPVC + Daun Pintu UPVC+ Aksesoris Lengkap Terpasang Sesuai Gambar (Type
TaksirP4) 2,00 Unit Rp 1.500.000,00 Rp 3.000.000,00
4.2.3.5 Kusen UPVC + Daun Jendela dan Ventilasi Kaca 5mm + Aksesoris Lengkap Terpasang
Taksir
Sesuai Gambar (Type
8,00 JV1) Unit Rp 5.000.000,00 Rp 40.000.000,00
4.2.3.6 Kusen UPVC + Daun Jendela dan Ventilasi Kaca 5mm + Aksesoris Lengkap Terpasang
Taksir
Sesuai Gambar (Type
4,00 J2) Unit Rp 1.000.000,00 Rp 4.000.000,00
4.2.3.7 Kusen UPVC + Daun ventilasi Kaca 5mm + Aksesoris Lengkap Terpasang Sesuai Gambar
Taksir (Type V2) 2,00 Unit Rp 300.000,00 Rp 600.000,00
4.2.4 PEKERJAAN ATAP
4.2.4.1 Penutup Atap genteng Onduline AHSP PU : A.4.5.2.43 234,56 M2 Rp 318.499,40 Rp 74.708.684,36
4.2.4.2 Rabung genteng Onduline AHSP PU : A.4.5.2.44 35,72 M Rp 184.308,20 Rp 6.583.488,90
4.2.4.3 Lisplank Kayu 2/20 cm AHSP PU : A.4.6.1.29 65,22 M Rp 112.424,00 Rp 7.332.293,28
4.2.5 Pekerjaan Plafond
4.2.5.1 Pasang Plafon PVC/Fiber + Rangka + Aksesoris Lengkap Terpasang SesuaiAHSP
Gambar
PU : A.4.5.1.7 a 167,55 M2 Rp 292.445,00 Rp 48.999.159,75
4.2.6 Pekerjaan Pengecatan
4.2.6.1 Pengecatan Tembok dan Sealer 3x(L/D) Setara Vinilex AHSP PU : A.4.7.1.10b 855,73 M2 Rp 29.183,78 Rp 24.973.422,34
Sub Jumlah Rp 471.030.483,66
5 PEKERJAAN ELEKTRIKAL
5.1 Instlasi titik penerangan, instalasi termasuk kabel NYA 2,5 mm dalam pipa PVC fitting
Taksir
lampu dan kelengkapan
76,00 instalasi
titikterpasang
Rp 80.000,00 Rp 6.080.000,00
5.2 Instalasi titik Stop kontak, instalasi termasuk kabel NYA 2,5 mm dalam pipa PVC fitting
Taksir
lampu dan kelengkapan
17,00 instalasi
titik terpasang
Rp 80.000,00 Rp 1.360.000,00
5.3 Pemasangan Box Sekring Taksir 1,00 bh Rp 80.000,00 Rp 80.000,00
5.4 Pemasukan Arus Listrik 12 Ampere Taksir 1,00 titik Rp 3.500.000,00 Rp 3.500.000,00
Sub Jumlah Rp 11.020.000,00
5.5 LANTAI 1
5.5.1 Armatur
5.5.1.1 Lampu Downlight 23 watt + Accesori Lengkap Terpasang Taksir 16,00 bh Rp 170.000,00 Rp 2.720.000,00
5.5.1.2 Lampu RM TL 2X36 watt + Accesori Lengkap Terpasang Taksir 6,00 unit Rp 500.000,00 Rp 3.000.000,00
5.5.2 Saklar lampu Merk Setara Broco 2 seri
5.5.2.1 Sakalar 1 Seri setara Broco Taksir 7,00 bh Rp 20.000,00 Rp 140.000,00
5.5.2.2 Sakalar 2 Seri setara Broco Taksir 3,00 bh Rp 20.000,00 Rp 60.000,00
5.5.2.3 Stop Kontak Taksir 9,00 bh Rp 20.000,00 Rp 180.000,00
Sub Jumlah Rp 6.100.000,00

Pa ge 45
WBS URAIAN PEKERJAAN ANALISA VOLUME SAT HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

5.6 LANTAI 2
5.6.1 Armatur
5.6.1.1 Lampu Downlight 23 watt + Accesori Lengkap Terpasang Taksir 19,00 bh Rp 170.000,00 Rp 3.230.000,00
5.6.1.2 Lampu RM TL 2X36 watt + Accesori Lengkap Terpasang Taksir 4,00 unit Rp 500.000,00 Rp 2.000.000,00
5.6.2 Saklar lampu Merk Setara Broco 2 seri Rp -
5.6.2.1 Sakalar 1 Seri setara Broco Taksir 5,00 bh Rp 20.000,00 Rp 100.000,00
5.6.2.2 Sakalar 2 Seri setara Broco Taksir 3,00 bh Rp 20.000,00 Rp 60.000,00
5.6.2.3 Stop Kontak Taksir 9,00 bh Rp 20.000,00 Rp 180.000,00
Sub Jumlah Rp 5.570.000,00
6 PEKERJAAN MEKANIKAL
6.1 PEKERJAAN SALURAN DRAINASE
6.1.1 Pasangan Bata Dinding Saluran 1 PC : 2 PP AHSP PU : A.4.4.1.7 5,04 M2 Rp 159.729,25 Rp 805.035,42
6.1.2 Pasangan Plasteran Bata Dinding Saluran 1 PC : 2 PP AHSP PU : A.4.4.2.2 2,24 M2 Rp 76.337,92 Rp 170.996,94
6.1.3 Cor Lantai Saluran AHSP PU : A.4.1.1.2 3,92 M2 Rp 1.177.318,25 Rp 4.615.087,54
6.1.4 Buis Beton Dia. 20 cm Taksir 1,68 M2 Rp 60.000,00 Rp 100.800,00
6.1.5 Pemasangan Grill Saluran Bentuk Sesuai Gambar + Cat Meni Hitam Taksir 11,20 M2 Rp 200.000,00 Rp 2.240.000,00
Sub Jumlah Rp 7.931.919,90
6.2 LANTAI 1
6.2.1 Pekerjaan Sanitasi
6.2.1.1 INSTALASI AIR KOTOR
6.2.1.1.1 Pasang Flordrain Taksir 3,00 buah Rp 20.000,00 Rp 60.000,00
6.2.1.1.2 Pipa SNI 3 Inch AW Taksir 7,00 M Rp 70.000,00 Rp 490.000,00
6.2.1.2 INSTALASI AIR BERSIH
6.2.1.2.1 Memasang Wastafel + Keran Air + Pembungan Air Type Sifon angsa Aksesoris Lengkap
Taksir Terpasang Setara
4,00 Toto buah Rp 900.000,00 Rp 3.600.000,00
6.2.1.2.2 Pipa SNI 1/2 Inch AW Taksir 14,00 M Rp 35.000,00 Rp 490.000,00
6.2.1.2.3 Pasang Pipa Air Sampai Ketitik Air Taksir 1,00 LS Rp 300.000,00 Rp 300.000,00
6.2.1.3 INSTALASI AIR HUJAN
6.2.1.3.1 Pipa SNI 2 1/2 Inch AW Taksir 14,00 M Rp 63.000,00 Rp 882.000,00
6.2.1.4 INSTALASI KOTORAN
6.2.1.4.1 Pipa SNI 3 Inch AW Taksir 7,00 M Rp 70.000,00 Rp 490.000,00
6.2.1.4.2 Septick Tank + Resapan Lengkap Terpasang Taksir 2,00 LS Rp 2.000.000,00 Rp 4.000.000,00
6.2.1.4.3 Pasang Kloset Duduk SetaraToto Taksir 2,00 buah Rp 1.750.000,00 Rp 3.500.000,00
Sub Jumlah Rp 13.812.000,00

Pa ge 46
WBS URAIAN PEKERJAAN ANALISA VOLUME SAT HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

6.3 LANTAI 2
6.3.1 Pekerjaan Sanitasi
6.3.1.1 INSTALASI AIR BERSIH
6.3.1.1.2 Bak Mandi Pyber Glass (60 x 60) Taksir 5,00 buah Rp 400.000,00 Rp 2.000.000,00
6.3.1.1.3 Pipa SNI 1 Inch AW Taksir 14,00 M Rp 58.000,00 Rp 812.000,00
6.3.1.1.4 Pipa SNI 1/2 Inch AW Taksir 14,00 M Rp 35.000,00 Rp 490.000,00
6.3.1.1.5 Pasang Pipa Air Sampai Ketitik Air Taksir 1,00 LS Rp 300.000,00 Rp 300.000,00
6.3.1.2 INSTALASI AIR KOTOR
6.3.1.2.1 Pipa SNI 3 Inch AW Taksir 7,00 M Rp 70.000,00 Rp 490.000,00
6.3.1.2.2 Pasang Flordrain Taksir 2,00 buah Rp 20.000,00 Rp 40.000,00
6.3.1.3 INSTALASI KOTORAN
6.3.1.3.1 Pipa SNI 3 Inch AW Taksir 6,00 M Rp 70.000,00 Rp 420.000,00
6.3.1.3.2 Pasang Kloset Jongkok Setara American Standar Taksir 3,00 buah Rp 600.000,00 Rp 1.800.000,00
6.3.1.4 INSTALASI AIR HUJAN
6.3.1.4.1 Pipa SNI 2 1/2 Inch AW Taksir 14,00 M Rp 63.000,00 Rp 882.000,00
Sub Jumlah Rp 7.234.000,00
7 PEKERJAAN FINISHING
7.1 PEKERJAAN BESI, ALUMUNIUM, ORNAMEN DAN DINDING COMPOSITE
7.1.1 Pekerjaan Almunium Composite Panel Setara Seven Type PVDF + Rangka + Aksesoris Taksir
Lengkap Terpasang
21,76
Sesuai Gambar
M2 Rp 850.000,00 Rp 18.496.000,00
7.1.2 Huruf Timbul Gedung IGD + Aksesoris Lengkap Terpasang Sesuai Gambar (Bahan Stainless)
Taksir 1,00 Ls Rp 4.500.000,00 Rp 4.500.000,00
7.1.3 Huruf Timbul Gedung Utama + Aksesoris Lengkap Terpasang Sesuai Gambar (Bahan Taksir
Stainless) 1,00 Ls Rp 4.500.000,00 Rp 4.500.000,00
7.1.4 Logo Puskesmas + Aksesoris Lengkap Terpasang Sesuai Gambar (Bahan Stainless) Taksir 1,00 Ls Rp 3.000.000,00 Rp 3.000.000,00
7.1.5 Reling Tangga Stainless + Aksesoris Lengkap Terpasang Sesuai Gambar Taksir 8,68 M Rp 500.000,00 Rp 4.340.000,00
7.1.6 Handrail (Pegangan Tangan) Stainless + Aksesoris Lengkap Terpasang Sesuai GambarTaksir 13,14 M Rp 300.000,00 Rp 3.942.000,00
7.2 Pekerjan Pot Bunga
7.2.1 Pasangan Dinding Bata 1PC : 4 PP AHSP PU : A. 4.4.1.9 7,70 M2 Rp 145.322,63 Rp 1.118.984,21
7.2.2 Plasteran Dinding Bata 1PC : 4 PP AHSP PU : A.4.4.2.4 7,70 M2 Rp 69.469,20 Rp 534.912,84
7.2.3 Pesangan Batu Alam Tempel Susun Sirih + Cat Vernis Batu Alam AHSP PU : A.4.4.3.58 4,28 M2 Rp 458.350,00 Rp 1.961.738,00
7.2.4 Relif Pot Bunga Sesuai Gambar Taksir 9,50 M Rp 200.000,00 Rp 1.900.000,00
7.5 Pembersihan Akhir Taksir 1,00 unit Rp 1.000.000,00 Rp 1.000.000,00
Sub Jumlah Rp 45.293.635,05
JUMLAH Rp 2.181.769.320,69
JUMLAH HARGA PER TOTAL LUAS BANGUNAN Rp 5.327.886,01

Pa ge 47
REKAPITULASI RENCANA ANGGARAN BIAYA

PEKERJAAN : PEMBANGUNAN IGD PUSKESMAS BLANGPIDIE ( 2 LANTAI )


LOKASI : KECAMATAN BLANGPIDIE KABUPATEN ACEH BARAT DAYA
SUMBER DANA : OTSUS
TAHUN ANGGARAN : 2022

NO JENIS PEKERJAAN HARGA PEKERJAAN


1 PEKERJAAN PERSIAPAN Rp 92.830.083
2 PEKERJAAN TANAH Rp 87.426.458
3 PEKERJAAN STRUKTUR LANTAI I Rp 603.461.844
4 PEKERJAAN STRUKTUR LANTAI II Rp 371.780.600
5 PEKERJAAN ARSITEKTUR LANTAI I Rp 458.278.297
6 PEKERJAAN ARSITEKTUR LANTAI II Rp 471.030.484
7 PEKERJAAN ELEKTRIKAL LANTAI I Rp 17.120.000
8 PEKERJAAN ELEKTRIKAL LANTAI II Rp 5.570.000
9 PEKERJAAN MEKANIKAL LANTAI I Rp 21.743.920
10 PEKERJAAN MEKANIKAL LANTAI II Rp 7.234.000
11 PEKERJAAN FINISHING Rp 45.293.635
JUMLAH HARGA PEKERJAAN Rp 2.181.769.321

PPN (11%) Rp 239.994.625


TOTAL HARGA PEKERJAAN Rp 2.421.763.946
DIBULATKAN Rp 2.421.764.000

TERBILANG : "Dua Miliyar Empat Ratus Dua Puluh Satu Juta Tujuh Ratus Enam
Puluh Empat Ribu Rupiah"

Pa ge 48
DURASI PEKERJAAN
Koefisien Pekerja Asumsi Jumlah Pekerja
Koefisien Produktivita Durasi Pembulatan
WBS URAIAN PEKERJAAN Volume Satuan Analisa Tenaga
P T M K Terpakai s (hari) Durasi (hari) P T M K
Kerja
1 PEKERJAAN PERSIAPAN
1.1 Pembersihan Lapangan 600,00 M2 Taksir 0,100 0,050 0,100 10,000 12 5,00 5 12 0 0 6
1.2 Papan Nama Proyek Uk. 90 x120 1,00 UNIT Taksir 1,00 1
1.3 Administrasi/Dokumentasi dan Pelaporan 1,00 LS Taksir 1,00 1
1.4 Direksi Keet/sewa 24,00 M3 AHSP PU : A.2.2.1.6 1,000 1,500 0,500 0,150 1,500 0,667 6 6,00 6 4 6 1 1
1.5 Perlengkapan P3k 1,00 PAKET Taksir 1,00 1
1.6 Pengukuran dan Pemasangan Bouwplank 68,00 M2 AHSP PU : A.2.2.1.4 0,100 0,100 0,005 0,001 0,100 10,000 4 1,70 2 4 4 1 1
1.7 Pagar pelindung proyek 52,50 M2 AHSP PU : A.2.2.1.2 0,300 0,100 0,015 0,010 0,100 10,000 3 1,75 2 9 3 1 1
1.8 Pekerjaan SMK3 1,00 LS AN SMK3 1,00 1
2 PEKERJAAN TANAH
2.1 PEKERJAAN GALIAN
2.1.1 Galian Tanah Pondasi Tapak 70,20 M3 AHSP PU : A.2.3.1.1 0,300 0,010 0,300 3,333 6 3,51 4 6 1
2.1.2 Galian Tanah Pondasi Menerus 71,30 M3 AHSP PU : A.2.3.1.1 0,300 0,010 0,300 3,333 6 3,57 4 6 1
2.2 PEKERJAAN TIMBUNAN
2.2.1 Urugan Kembali Bekas Galian 35,38 M3 AHSP PU : A.2.3.1.9 0,500 0,050 0,500 2,000 5 3,54 4 5 1
2.2.2 Pasir Urugan Bawah Pondasi Menerus 71,30 M3 AHSP PU : A.2.3.1.11 0,300 0,010 0,300 3,333 5 4,28 5 5 1
2.2.3 Pasir Urugan dibawah Lantai 20,48 M3 AHSP PU : A.2.3.1.11 0,300 0,010 0,300 3,333 3 2,05 3 3 1
2.2.4 Timbunan Tanah Dibawah Lantai 266,18 M3 AHSP PU : A.2.3.1.15 0,250 0,025 0,250 4,000 8 8,32 9 8 1
3 PEKERJAAN STRUKTUR
3.1 LANTAI 1
3.1.1 PEKERJAAN PONDASI TAPAK BETON BERTULANG
3.1.1.1 Lantai Kerja Pondasi Tapak Setempat ( K.175) 3,78 M3 AHSP PU : A.4.1.1.5 1,650 0,275 0,083 0,028 0,275 3,636 2 0,52 1 2 2 1 1
3.1.2 Pekerjaan Beton Bertulang Pondasi Tapak
3.1.2.1 Cor Beton K 250 21,60 M3 AHSP PU : A.4.1.1.8 1,650 0,275 0,083 0,028 0,275 3,636 3 1,98 2 1 3 1 1
3.1.2.2 Pembesian 7.348,56 KG AHSP PU : A.4.1.1.17a 0,070 0,070 0,004 0,007 0,004 250,000 6 4,90 5 6 6 1 1
3.1.2.3 Bekisting 115,20 M2 AHSP PU : A.4.1.1.20 0,520 0,260 0,026 0,026 0,260 38,462 2 1,50 2 1 2 1 1
3.1.3 Pekerjaan Pondasi Menerus
3.1.3.1 Anstamping / Pasangan Batu Kosong Tebal 10 Cm 6,60 M3 AHSP PU : A.3.2.1.9 0,780 0,390 0,039 0,039 0,390 2,564 2 1,29 2 1 2 1 1
3.1.3.2 Pasangan Pondasi Batu Gunung 1 PC : 4 PS 28,01 M3 AHSP PU : A.3.2.1.2 1,500 0,750 0,075 0,075 0,750 1,333 6 3,50 4 3 6 1 1
3.1.4 Sloof (30/40)
3.1.4.1 Pembesian 2.098,78 KG AHSP PU : A.4.1.1.17a 0,070 0,070 0,004 0,007 0,070 250,000 4 2,10 3 4 4 1 1
3.1.4.2 Bekisting 197,40 M2 AHSP PU : A.4.1.1.21 0,520 0,260 0,026 0,026 0,260 38,462 3 1,71 2 2 3 1 1
3.1.4.3 Cor Beton K 250 13,25 M3 AHSP PU : A.4.1.1.8 1,650 0,275 0,083 0,028 0,275 3,636 3 1,21 2 1 3 1 1
3.1.5 Sloof (15/20) 0,000
3.1.5.1 Pembesian 237,81 KG AHSP PU : A.4.1.1.17a 0,070 0,070 0,004 0,007 0,070 250,000 4 0,24 1 4 4 1 1
3.1.5.2 Bekisting 3,15 M2 AHSP PU : A.4.1.1.21 0,520 0,260 0,026 0,026 0,260 38,462 1 0,08 1 1 1 1 1
3.1.5.3 Cor Beton K 175 0,14 M3 AHSP PU : A.4.1.1.5 1,650 0,275 0,083 0,028 0,275 3,636 1 0,04 1 1 1 1 1
3.1.6 Kolom Uk. 30/40
3.1.6.1 Pembesian 1.525,50 KG AHSP PU : A.4.1.1.17a 0,070 0,070 0,004 0,007 0,070 250,000 6 1,02 2 6 6 1 1
3.1.6.2 Bekisting 134,40 M2 AHSP PU : A.4.1.1.22 0,660 0,330 0,033 0,033 0,330 30,303 4 1,11 2 2 4 1 1
3.1.6.3 Cor Beton K 250 9,94 M3 AHSP PU : A.4.1.1.8 1,650 0,275 0,083 0,028 0,275 3,636 2 1,37 2 0 2 1 1
3.1.7 Kolom Uk. 15/15 0
3.1.7.1 Pembesian 68,49 KG AHSP PU : A.4.1.1.17a 0,070 0,070 0,004 0,007 0,070 250,000 1 0,27 1 1 1 1 1
3.1.7.2 Bekisting 9,60 M2 AHSP PU : A.4.1.1.22 0,660 0,330 0,033 0,033 0,330 30,303 1 0,32 1 1 1 1 1
3.1.7.3 Cor Beton K 175 0,78 M3 AHSP PU : A.4.1.1.5 1,650 0,275 0,083 0,028 0,275 3,636 1 0,21 1 1 3 1 1

Pa ge 49
Koefisien Pekerja Asumsi Jumlah Pekerja
Koefisien Produktivita Durasi Pembulatan
WBS URAIAN PEKERJAAN Volume Satuan Analisa Tenaga
P T M K Terpakai s (hari) Durasi (hari) P T M K
Kerja
3.1.8 Balok Latai (13/13) Elevasi ± 2.23 m
3.1.8.1 Pembesian 252,27 KG AHSP PU : A.4.1.1.17a 0,070 0,070 0,004 0,007 0,070 250,000 2 0,50 1 2 2 1 1
3.1.8.2 Bekisting 139 M2 AHSP PU : A.4.1.1.23 0,660 0,330 0,033 0,033 0,330 30,303 4 1,15 2 2 4 1 1
3.1.8.3 Cor Beton K 175 1,20 M3 AHSP PU : A.4.1.1.5 1,650 0,275 0,083 0,028 0,275 3,636 1 0,33 1 1 1 1 1
3.1.9 Balok Uk. 25/30 Elevasi ± 3.45 m
3.1.9.1 Pembesian 1.332 KG AHSP PU : A.4.1.1.17a 0,070 0,070 0,004 0,007 0,070 250,000 4 1,33 2 4 4 1 1
3.1.9.2 Bekisting 136,50 M2 AHSP PU : A.4.1.1.23 0,660 0,330 0,033 0,033 0,330 30,303 4 1,13 2 2 4 1 1
3.1.9.3 Cor Beton K 250 12,80 M3 AHSP PU : A.4.1.1.8 1,650 0,275 0,083 0,028 0,275 3,636 4 0,88 1 1 4 1 1
3.1.10 Balok Uk. 15/20 Elevasi ± 3.45 m
3.1.10.1 Pembesian 25,01 KG AHSP PU : A.4.1.1.17a 0,070 0,070 0,004 0,007 0,070 250,000 4 0,03 1 4 4 1 1
3.1.10.2 Bekisting 3,15 M2 AHSP PU : A.4.1.1.23 0,660 0,330 0,033 0,033 0,330 30,303 2 0,05 1 1 2 1 1
3.1.10.3 Cor Beton K 175 0,12 M3 AHSP PU : A.4.1.1.5 1,650 0,275 0,083 0,028 0,275 3,636 1 0,03 1 1 1 1 1
3.1.11 Plat Tangga dan Plat Bordes Tebal 10cm
3.1.11.1 Pembesian 338,00 KG AHSP PU : A.4.1.1.17a 0,070 0,070 0,004 0,007 0,070 250,000 2 0,68 1 2 2 1 1
3.1.11.2 Bekisting 29,06 M2 AHSP PU : A.4.1.1.26 0,660 0,330 0,033 0,033 0,330 30,303 2 0,48 1 1 2 1 1
3.1.11.3 Cor Beton K 250 0,90 M3 AHSP PU : A.4.1.1.8 1,650 0,275 0,083 0,028 0,275 3,636 1 0,25 1 1 1 1 1
3.2 LANTAI 2
3.2.1 Kolom Uk. 30/30
3.2.1.1 Pembesian 756,27 KG AHSP PU : A.4.1.1.17a 0,070 0,070 0,004 0,007 0,070 250,000 3 1,01 2 3 3 1 1
3.2.1.2 Bekisting 109,44 M2 AHSP PU : A.4.1.1.22 0,660 0,330 0,033 0,033 0,330 30,303 3 1,20 2 2 3 1 1
3.2.1.3 Cor Beton K 250 6,91 M3 AHSP PU : A.4.1.1.8 1,650 0,275 0,083 0,028 0,275 3,636 2 0,95 1 1 2 1 1
3.2.2 Kolom Uk. 15/15
3.2.2.1 Pembesian 65,13 KG AHSP PU : A.4.1.1.17a 0,070 0,070 0,004 0,007 0,070 250,000 1 0,26 1 1 1 1 1
3.2.2.2 Bekisting 109,44 M2 AHSP PU : A.4.1.1.22 0,660 0,330 0,033 0,033 0,330 30,303 2 1,81 2 1 2 1 1
3.2.2.3 Cor Beton K 175 0,86 M3 AHSP PU : A.4.1.1.5 1,650 0,275 0,083 0,028 0,275 3,636 1 0,24 1 1 1 1 1
3.2.3 Balok Latai (13/13) Elevasi ± 6.23 m
3.2.3.1 Pembesian 279,66 KG AHSP PU : A.4.1.1.17a 0,070 0,070 0,004 0,007 0,070 250,000 2 0,56 1 2 2 1 1
3.2.3.2 Bekisting 50,44 M2 AHSP PU : A.4.1.1.23 0,660 0,330 0,033 0,033 0,330 30,303 2 0,83 1 1 2 1 1
3.2.3.3 Cor Beton K 175 1,34 M3 AHSP PU : A.4.1.1.5 1,650 0,275 0,083 0,028 0,275 3,636 1 0,37 1 1 1 1 1
3.2.4 Ring Balok Uk. 25/30 Elevasi ± 7.50 m
3.2.4.1 Pembesian 1.332 KG AHSP PU : A.4.1.1.17a 0,070 0,070 0,004 0,007 0,070 250,000 3 1,78 2 3 3 1 1
3.2.4.2 Bekisting 115,50 M2 AHSP PU : A.4.1.1.23 0,660 0,330 0,033 0,033 0,330 30,303 2 1,91 2 1 2 1 1
3.2.4.3 Cor Beton K 250 12,80 M3 AHSP PU : A.4.1.1.8 1,650 0,275 0,083 0,028 0,275 3,636 2 1,76 2 1 2 1 1
3.2.5 Ring Balok Uk. 15/20 Elevasi ±7.5 m
3.2.5.1 Pembesian 25,01 KG AHSP PU : A.4.1.1.17a 0,070 0,070 0,004 0,007 0,070 250,000 1 0,10 1 1 1 1 1
3.2.5.2 Bekisting 3,15 M2 AHSP PU : A.4.1.1.23 0,660 0,330 0,033 0,033 0,330 30,303 1 0,10 1 1 1 1 1
3.2.5.3 Cor Beton K 175 0,12 M3 AHSP PU : A.4.1.1.5 1,650 0,275 0,083 0,028 0,275 3,636 1 0,03 1 1 1 1 1
3.2.6 Plat Lantai Tebal 12cm
3.2.6.1 Pembesian 5.163 KG AHSP PU : A.4.1.1.17a 0,070 0,070 0,004 0,007 0,070 250,000 6 3,44 4 6 6 1 1
3.2.6.2 Bekisting 217,23 M2 AHSP PU : A.4.1.1.24 0,660 0,330 0,033 0,033 0,330 30,303 4 1,79 2 2 4 1 1
3.2.6.3 Cor Beton K 250 20,33 M3 AHSP PU : A.4.1.1.8 1,650 0,275 0,083 0,028 0,275 3,636 3 1,86 2 1 3 1 1
3.2.7 Plat dak dan Talang Beton
3.2.7.1 Pembesian 412,54 KG AHSP PU : A.4.1.1.17a 0,070 0,070 0,004 0,007 0,070 250,000 2 0,83 1 2 2 1 1
3.2.7.2 Bekisting 61,20 M2 AHSP PU : A.4.1.1.24 0,660 0,330 0,033 0,033 0,330 30,303 3 0,67 1 2 3 1 1
3.2.7.3 Cor Beton K 250 4,54 M3 AHSP PU : A.4.1.1.8 1,650 0,275 0,083 0,028 0,275 3,636 2 0,62 1 1 2 1 1

Pa ge 50
Koefisien Pekerja Asumsi Jumlah Pekerja
Koefisien Produktivita Durasi Pembulatan
WBS URAIAN PEKERJAAN Volume Satuan Analisa Tenaga
P T M K Terpakai s (hari) Durasi (hari) P T M K
Kerja
3.2.8 PEKERJAAN ATAP
3.2.8.1 Rangka kuda-kuda dan gording baja ringan Multytruss 234,57 M2 AHSP PU : A.4.2.1.24 0,200 0,450 0,050 0,010 0,450 5,000 6 7,82 8 3 6 1 1
4 PEKERJAAN ARSITETKTUR
4.1 LANTAI 1
4.1.1 Pekerjaan Dinding
4.1.1.1 Pasangan Trasram Bata 1 PC : 2 PP 38,84 M2 AHSP PU: A.4.4.1.7 0,300 0,100 0,015 0,010 0,100 10,000 4 0,97 1 1 4 1 1
4.1.1.2 Pasangan Dinding Bata 1 PC : 4 PP 283,29 M2 AHSP PU : A.4.4.1.9 0,300 0,100 0,015 0,010 0,100 10,000 5 5,67 6 2 5 1 1
4.1.1.3 Plesteran Trasram Bata 1 PC : 2 PP 77,67 M2 AHSP PU : A.4.4.2.2 0,300 0,150 0,015 0,015 0,150 66,667 3 0,39 1 2 3 2 2
4.1.1.4 Plesteran Dinding Bata 1PC : 4 PP 566,58 M2 AHSP PU: A. 4.4.2.4 0,300 0,150 0,015 0,015 0,150 6,667 10 8,50 9 5 10 1 1
4.1.1.5 Plasteran Beton 1 PC : 3 PP 185,04 M2 AHSP PU : A.4.4.2.3 0,300 0,150 0,015 0,015 0,150 6,667 4 6,94 7 2 4 1 1
4.1.1.6 Pesangan Batu Alam Tempel Susun Sirih + cat Vernis Batu Alam 95,55 M2 AHSP PU : A.4.4.3.58 0,700 0,350 0,035 0,035 0,350 28,571 3 1,11 2 2 3 1 1
4.1.2 Pekerjaan Lantai
4.1.2.1 Pekerjaan Beton Tumbuk Tebal 7 cm (K 125) 9,96 M3 AHSP PU : A.4.1.1.2 1,650 0,275 0,083 0,028 0,275 3,636 3 0,91 1 1 3 1 1
4.1.2.2 Pekerjaan Lantai Granite 60 x 60 Cm (Halus) 147,28 M2 AHSP PU : A.4.4.3.9 a 0,250 0,125 0,013 0,013 0,125 8,000 4 4,60 5 2 4 1 1
4.1.2.3 Pekerjaan Lantai Granite 60 x 60 Cm (Kasar) 48,73 M2 AHSP PU : A.4.4.3.9 a 0,250 0,125 0,013 0,013 0,125 8,000 3 2,03 3 2 3 1 1
4.1.2.4 Pekerjaan Lantai Keramik untuk Ruangan Wc/Km 20 X 20 Cm 7,49 M2 AHSP PU : A.4.4.3.36 0,700 0,350 0,035 0,035 0,350 28,571 1 0,26 1 1 1 1 1
4.1.2.5 Pasangan Dinding Keramik KM/WC 20 x 25 cm 44,93 M2 AHSP PU : A.4.4.3.65 0,900 0,450 0,045 0,045 0,450 22,222 2 1,01 2 1 2 1 1
4.1.3 Pekerjaan Pintu, Jendela, Ventilasi
4.1.3.1 Pintu Panel Kaca Tempered Glass 12mm + Aksesoris Lengkap Terpasang (Type
2,00 P1)Unit Taksir 1,00 1
4.1.3.2 Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris Lengkap Terpasang Sesuai 5,00
Gambar
Unit
( Type P2) Taksir 2,00 2
4.1.3.3 Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris Lengkap Terpasang Sesuai 1,00
Gambar
Unit
( Type P5) Taksir 1,00 1
4.1.3.4 Kusen UPVC + Daun Pintu UPVC+ Aksesoris Lengkap Terpasang Sesuai Gambar
1,00 (Type
UnitP4) Taksir 1,00 1
4.1.3.5 Kusen UPVC + Daun Pintu UPVC+ Aksesoris Lengkap Terpasang Sesuai Gambar
2,00 (Type
UnitP3) Taksir 1,00 1
4.1.3.6 Kusen UPVC + Daun Jendela dan Ventilasi Kaca 5mm + Aksesoris Lengkap6,00
Terpasang
Unit
Sesuai GambarTaksir
(Type JV1) 2,00 2
4.1.3.7 Kusen UPVC + Daun Jendela dan Ventilasi Kaca 5mm + Aksesoris Lengkap4,00
Terpasang
Unit
Sesuai GambarTaksir
(Type J2) 2,00 2
4.1.3.8 Kusen UPVC + Daun ventilasi Kaca 5mm + Aksesoris Lengkap Terpasang Sesuai
3,00 Gambar
Unit (Type V2) Taksir 1,00 1
4.1.4 Pekerjaan Plafond
4.1.4.1 Pasang Plafon PVC/Fiber + Rangka + Aksesoris Lengkap Terpasang Sesuai
199,13
Gambar M2 AHSP PU: A.4.5.1.7 a 0,100 0,050 0,005 0,005 0,050 20,000 3 3,32 4 2 3 1 1
4.1.5 Pekerjaan Pengecatan
4.1.5.1 Pengecatan Tembok dan Sealer 3x(L/D) Setara Vinilex 855,73 M2 AHSP PU : A.4.7.1.10b 0,020 0,063 0,003 0,006 0,063 50,000 5 3,42 4 2 5 1 1
4.2 LANTAI 2
4.2.1 Pekerjaan Dinding
4.2.1.1 Pasangan Trasram Bata 1 PC : 2 PP 23,97 M2 AHSP PU: A.4.4.1.7 0,300 0,100 0,015 0,010 0,100 10,000 2 1,20 2 1 2 1 1
4.2.1.2 Pasangan Dinding Bata 1 PC : 4 PP 347,75 M2 AHSP PU : A.4.4.1.9 0,300 0,100 0,015 0,010 0,100 10,000 6 5,80 6 2 6 1 1
4.2.1.3 Plesteran Trasram Bata 1 PC : 2 PP 47,94 M2 AHSP PU : A.4.4.2.2 0,300 0,150 0,015 0,015 0,150 66,667 3 0,24 1 2 3 1 1
4.2.1.4 Plesteran Dinding Bata 1PC : 4 PP 695,50 M2 AHSP PU: A. 4.4.2.4 0,300 0,150 0,015 0,015 0,150 6,667 5 13,53 14 3 5 1 1
4.2.1.5 Plasteran Beton 1 PC : 3 PP 69,12 M2 AHSP PU : A.4.4.2.3 0,300 0,150 0,015 0,015 0,150 6,667 4 2,59 3 2 4 1 1
4.2.1.6 Pesangan Batu Alam Tempel Susun Sirih + cat Vernis Batu Alam 95,55 M2 AHSP PU : A.4.4.3.58 0,700 0,350 0,035 0,035 0,350 28,571 2 1,67 2 1 2 1 1
4.2.2 Pekerjaan Lantai
4.2.2.1 Pekerjaan Beton Tumbuk Tebal 7 cm (K 125) 8,38 M3 AHSP PU : A.4.1.1.2 1,650 0,275 0,083 0,028 0,275 3,636 2 1,15 2 1 2 1 1
4.2.2.2 Pekerjaan Lantai Granite 60 x 60 Cm (Halus) 165,66 M2 AHSP PU : A.4.4.3.9 a 0,250 0,125 0,013 0,013 0,125 8,000 5 4,14 5 3 5 1 1
4.2.2.3 Pekerjaan Lantai Keramik untuk Ruangan Wc/Km 20 X 20 Cm 5,00 M2 AHSP PU : A.4.4.3.36 0,700 0,350 0,035 0,035 0,350 28,571 1 0,17 1 1 1 1 1
4.2.2.4 Pasangan Dinding Keramik KM/WC 20 x 25 cm 24,14 M2 AHSP PU : A.4.4.3.65 0,900 0,450 0,045 0,045 0,450 22,222 2 0,54 1 1 2 1 1

Pa ge 51
Koefisien Pekerja Asumsi Jumlah Pekerja
Koefisien Produktivita Durasi Pembulatan
WBS URAIAN PEKERJAAN Volume Satuan Analisa Tenaga
P T M K Terpakai s (hari) Durasi (hari) P T M K
Kerja
4.2.3 Pekerjaan Pintu, Jendela, Ventilasi
4.2.3.1 Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris Lengkap Terpasang Sesuai 4,00
Gambar Unit
( Type P2) Taksir 1,00 1
4.2.3.2 Kusen UPVC + Daun Pintu Kaca 5mm + Aksesoris Lengkap Terpasang Sesuai 1,00
Gambar Unit
( Type P5) Taksir 1,00 1
4.2.3.3 Kusen UPVC + Daun Pintu UPVC+ Aksesoris Lengkap Terpasang Sesuai Gambar 2,00 (TypeUnitP4) Taksir 1,00 1
4.2.3.5 Kusen UPVC + Daun Jendela dan Ventilasi Kaca 5mm + Aksesoris Lengkap8,00 TerpasangUnit
Sesuai GambarTaksir
(Type JV1) 1,00 1
4.2.3.6 Kusen UPVC + Daun Jendela dan Ventilasi Kaca 5mm + Aksesoris Lengkap4,00 TerpasangUnit
Sesuai GambarTaksir
(Type J2) 1,00 1
4.2.3.7 Kusen UPVC + Daun ventilasi Kaca 5mm + Aksesoris Lengkap Terpasang Sesuai 2,00 Gambar
Unit (Type V2) Taksir 1,00 1
4.2.4 PEKERJAAN ATAP
4.2.4.1 Penutup Atap genteng Onduline 234,56 M2 AHSP PU : A.4.5.2.43 0,200 0,100 0,001 0,010 0,100 10,000 5 4,69 5 3 5 1 1
4.2.4.2 Rabung genteng Onduline 35,72 M AHSP PU : A.4.5.2.44 0,250 0,150 0,013 0,015 0,150 6,667 4 1,34 2 2 4 1 1
4.2.4.3 Lisplank Kayu 2/20 cm 65,22 M AHSP PU : A.4.6.1.29 0,100 0,200 0,005 0,020 0,200 5,000 5 2,61 3 3 5 1 1
4.2.5 Pekerjaan Plafond
4.2.5.1 Pasang Plafon PVC/Fiber + Rangka + Aksesoris Lengkap Terpasang Sesuai 167,55
Gambar M2 AHSP PU : A.4.5.1.7 a 0,1 0,05 0,005 0,005 0,050 20,000 3 2,79 3 2 3 1 1
4.2.6 Pekerjaan Pengecatan
4.2.6.1 Pengecatan Tembok dan Sealer 3x(L/D) Setara Vinilex 855,73 M2 AHSP PU : A.4.7.1.10b 0,02 0,063 0,003 0,006 0,063 50,000 5 3,42 4 2 5 1 1
5 PEKERJAAN ELEKTRIKAL
5.1 Instlasi titik penerangan, instalasi termasuk kabel NYA 2,5 mm dalam pipa PVC
76,00
fitting titik
lampu dan kelengkapan
Taksir instalasi terpasang 1,00 1
5.2 Instalasi titik Stop kontak, instalasi termasuk kabel NYA 2,5 mm dalam pipa PVC
17,00fitting
titik
lampu dan kelengkapan
Taksir instalasi terpasang 1,00 1
5.3 Pemasangan Box Sekring 1,00 bh Taksir 1,00 1
5.4 Pemasukan Arus Listrik 12 Ampere 1,00 titik Taksir 1,00 1
5.5 LANTAI 1
5.5.1 Armatur
5.5.1.1 Lampu Downlight 23 watt + Accesori Lengkap Terpasang 16,00 bh Taksir 1,00 1
5.5.1.2 Lampu RM TL 2X36 watt + Accesori Lengkap Terpasang 6,00 unit Taksir 1,00 1
5.5.2 Saklar lampu Merk Setara Broco 2 seri
5.5.2.1 Sakalar 1 Seri setara Broco 7,00 bh Taksir 1,00 1
5.5.2.2 Sakalar 2 Seri setara Broco 3,00 bh Taksir 1,00 1
5.5.2.3 Stop Kontak 9,00 bh Taksir 1,00 1
5.6 LANTAI 2
5.6.1 Armatur
5.6.1.1 Lampu Downlight 23 watt + Accesori Lengkap Terpasang 19,00 bh Taksir 1,00 1
5.6.1.2 Lampu RM TL 2X36 watt + Accesori Lengkap Terpasang 4,00 unit Taksir 1,00 1
5.6.2 Saklar lampu Merk Setara Broco 2 seri
5.6.2.1 Sakalar 1 Seri setara Broco 5,00 bh Taksir 1,00 1
5.6.2.2 Sakalar 2 Seri setara Broco 3,00 bh Taksir 1,00 1
5.6.2.3 Stop Kontak 9,00 bh Taksir 1,00 1
6 PEKERJAAN MEKANIKAL
6.1 PEKERJAAN SALURAN DRAINASE
6.1.1 Pasangan Bata Dinding Saluran 1 PC : 2 PP 5,04 M2 AHSP PU : A.4.4.1.7 0,300 0,100 0,015 0,010 0,100 10,000 1 0,50 1 1 1 1 1
6.1.2 Pasangan Plasteran Bata Dinding Saluran 1 PC : 2 PP 2,24 M2 AHSP PU : A.4.4.2.2 0,300 0,150 0,015 0,015 0,150 6,667 1 0,34 1 1 1 1 1
6.1.3 Cor Lantai Saluran 3,92 M2 AHSP PU : A.4.1.1.2 1,650 0,275 0,083 0,028 0,275 3,636 1 1,08 2 1 1 1 1
6.1.4 Buis Beton Dia. 20 cm 1,68 M2 Taksir 0,100 1,00 1
6.1.5 Pemasangan Grill Saluran Bentuk Sesuai Gambar + Cat Meni Hitam 11,20 M2 Taksir 0,100 1,00 1
6.2 LANTAI 1
6.2.1 Pekerjaan Sanitasi
6.2.1.1 INSTALASI AIR KOTOR
6.2.1.1.1 Pasang Flordrain 3,00 buah Taksir 1,00 1
6.2.1.1.2 Pipa SNI 3 Inch AW 7,00 M Taksir 1,00 1

Pa ge 52
Koefisien Pekerja Asumsi Jumlah Pekerja
Koefisien Produktivita Durasi Pembulatan
WBS URAIAN PEKERJAAN Volume Satuan Analisa Tenaga
P T M K Terpakai s (hari) Durasi (hari) P T M K
Kerja
6.2.1.2 INSTALASI AIR BERSIH
6.2.1.2.1 Memasang Wastafel + Keran Air + Pembungan Air Type Sifon angsa Aksesoris
4,00 Lengkap
buah Terpasang Setara
Taksir Toto 1,00 1
6.2.1.2.2 Pipa SNI 1/2 Inch AW 14,00 M Taksir 1,00 1
6.2.1.2.3 Pasang Pipa Air Sampai Ketitik Air 1,00 LS Taksir 1,00 1
6.2.1.3 INSTALASI AIR HUJAN
6.2.1.3.1 Pipa SNI 2 1/2 Inch AW 14,00 M Taksir 1,00 1
6.2.1.4 INSTALASI KOTORAN
6.2.1.4.1 Pipa SNI 3 Inch AW 7,00 M Taksir 1,00 1
6.2.1.4.2 Septick Tank + Resapan Lengkap Terpasang 2,00 LS Taksir 1,00 1
6.2.1.4.3 Pasang Kloset Duduk SetaraToto 2,00 buah Taksir 1,00 1
6.2.1.4.4 LANTAI 2
6.3 Pekerjaan Sanitasi
6.3.1 INSTALASI AIR BERSIH
6.3.1.1 Bak Mandi Pyber Glass (60 x 60) 5,00 buah Taksir 1,00 1
6.3.1.1.2 Pipa SNI 1 Inch AW 14,00 M Taksir 1,00 1
6.3.1.1.3 Pipa SNI 1/2 Inch AW 14,00 M Taksir 1,00 1
6.3.1.1.4 Pasang Pipa Air Sampai Ketitik Air 1,00 LS Taksir 1,00 1
6.3.1.1.5 INSTALASI AIR KOTOR
6.3.1.2 Pipa SNI 3 Inch AW 7,00 M Taksir 1,00 1
6.3.1.2.1 Pasang Flordrain 2,00 buah Taksir 1,00 1
6.3.1.2.2 INSTALASI KOTORAN
6.3.1.3 Pipa SNI 3 Inch AW 6,00 M Taksir 1,00 1
6.3.1.3.1 Pasang Kloset Jongkok Setara American Standar 3,00 buah Taksir 1,00 1
6.3.1.3.2 INSTALASI AIR HUJAN
6.3.1.4 Pipa SNI 2 1/2 Inch AW 14,00 M Taksir 1,00 1
7 PEKERJAAN FINISHING
7.1 PEKERJAAN BESI, ALUMUNIUM, ORNAMEN DAN DINDING COMPOSITE
7.1.1 Pekerjaan Almunium Composite Panel Setara Seven Type PVDF + Rangka +21,76AksesorisM2Lengkap Terpasang
Taksir
Sesuai Gambar 3,00 3
7.1.2 Huruf Timbul Gedung IGD + Aksesoris Lengkap Terpasang Sesuai Gambar (Bahan1,00 Stainless)
Ls Taksir 2,00 2
7.1.3 Huruf Timbul Gedung Utama + Aksesoris Lengkap Terpasang Sesuai Gambar (Bahan
1,00 Stainless)
Ls Taksir 2,00 2
7.1.4 Logo Puskesmas + Aksesoris Lengkap Terpasang Sesuai Gambar (Bahan Stainless)
1,00 Ls Taksir 2,00 2
7.1.5 Reling Tangga Stainless + Aksesoris Lengkap Terpasang Sesuai Gambar 8,68 M Taksir 2,00 2
7.1.6 Handrail (Pegangan Tangan) Stainless + Aksesoris Lengkap Terpasang Sesuai13,14
Gambar M Taksir 2,00 2
7.2 Pekerjan Pot Bunga
7.2.1 Pasangan Dinding Bata 1PC : 4 PP 7,70 M2 AHSP PU : A. 4.4.1.9 0,300 0,100 0,015 0,010 0,100 10,000 2 0,39 1 1 2 1 1
7.2.2 Plasteran Dinding Bata 1PC : 4 PP 7,70 M2 AHSP PU : A.4.4.2.4 0,300 0,150 0,015 0,015 0,150 6,667 2 0,58 1 1 2 1 1
7.2.3 Pesangan Batu Alam Tempel Susun Sirih + Cat Vernis Batu Alam 4,28 M2 AHSP PU : A.4.4.3.58 0,700 0,350 0,035 0,035 0,350 2,857 2 0,75 1 1 2 1 1
7.2.4 Relif Pot Bunga Sesuai Gambar 9,50 M Taksir 0,100 2,00 2
7.3 Pembersihan Akhir 1,00 unit Taksir 0,100 1,00 1

Pa ge 53