Professional Documents
Culture Documents
By
Gayan Abeyrathna
(Master of Acc., BBM sp. In Acc. & Fin., DICA-SL)
Lecturer in Accountancy
Advanced Technological Institute
Kegalle
1
Outline
Introduction.
Cash flows, Incremental cash flows
Nature of Investment Decision.
Objective of Capital Budgeting.
Important Concepts of Capital Budgeting.
Investment Appraisal Methods.
Effect of Performance Measurement on Capital Investment Decisions.
Capital Investment Process
2
What is capital budgeting?
3
What is capital budgeting?(Contd……)
• Capital: Operating assets used in production
• Budget: A plan that details projected cash flows
during some period.
• Capital Budgeting: Process of analyzing projects
and deciding which ones to include in the capital
budget.
• Criteria: Project should maximize shareholders
wealth
4
Nature of Investment decisions
This includes expansion, acquisition, modernization and
replacement of long term assets, sale of a division of the
business etc.
Exchange of current funds for future benefits.
Funds are invested in long term assets.
The future benefits will occur to the firm over a series of
years.
Directly effect the firm value.
5
Independent and mutually exclusive
projects
7
Relevant cash flows
••The cash flows in the capital-budgeting
time line need to be relevant cash flows;
that is they need to be incremental in
nature.
8
9
Incremental Cash Flows
• • Those cash flows that will only occur if the project is
accepted.
• • Consider following costs/effects when determining the
incremental cash flows.
• •Sunk costs
• •Opportunity costs
• • Side effects – erosion and synergy
• •Allocated costs
9
10
Steps to capital budgeting
1. Estimate CFs (inflows & outflows).
2. Assess riskiness of CFs.
3. Determine the appropriate cost of capital.
4. Find NPV and/or IRR.
5. Accept if NPV > 0 and/or IRR > WACC.
10
Normal and Non-normal cash flow streams
0 1 1.6 2 3
Project S
CFt -100 70 100 50 20
Cumulative -100 -30 0 20 40
CFt -100 10 60 80
PV of CFt -100 9.09 49.59 60.11
Cumulative -100 -90.91 -41.32 18.79
15
Accounting Rate of Return
16
Calculation procedures
Average net profit per year (over the life of the project)
ARR =
Average investment cost
Total profit
Average net profit per year =
No. of life of the project
Initial investment
Average investment cost =
2
17
Acceptance criterion
In evaluating an investment project, the ARR of the project is
compared with a predetermined minimum acceptable
accounting Rate of return:
ARRs Comments
< minimum acceptable rate Reject project
= minimum acceptable rate Accept project
> minimum acceptable rate Accept project
Highest Choose highest ARR
18
Net Present Value (NPV)
•Sum of the PVs of all cash inflows and
outflows of a project:
n
CFt
NPV t
t0 ( 1 k )
19
Rationale for the NPV method
NPV= PV of inflows – Cost
= Net gain in wealth
• If projects are independent, accept if the project NPV > 0.
• If projects are mutually exclusive, accept projects with the
highest positive NPV, those that add the most value.
• In this example, would accept S if mutually exclusive (NPVs
> NPVL), and would accept both if independent.
20
Internal Rate of Return (IRR)
21
A project costs Rs.400 and produces a regular cash inflow of Rs.200 at
the end of each of the next three years. Calculate the IRR. If the
minimum rate of return is 15 %, suggest with reason whether you
Should accept the project or not.
22
P
IRR = L + P–N (H – L)
8.4
IRR = 22% + 8.4 – (-3.8) (24 – 22)%
= 23.38%
23
Modified Internal Rate of Return
(MIRR)
•MIRR is the discount rate that causes the PV
of a project’s terminal value (TV) to equal
the PV of costs.
•TV is found by compounding inflows at
WACC.
•Thus, MIRR assumes cash inflows are
reinvested at WACC.
24
Calculating MIRR
0 10% 1 2 3
27