MONITORING PEKERJAAN PONDASI /ERECTION TOWER DAN STRINGGING PEMBANGUNAN SUTT 150 KV
SECTION KID - PAKNING LOT 2 ( TW 96 - TW 182 )
Kontrak No. : Pekerjaan : Pekerjaan pondasi pembangunan SUTT 150 Kv sec.KID - PAKNING LOT 2
Erection & Stringging
Nomor tower TW 96 TW 97 TW 98 TW 99 TW 100 TW 101 TW 102 TW 103 TW 104 TW 105 TW 106 TW 107 Type Tower Klas pondasi D C D C D C D C D C D C D C D C D C D C D C D C Cor chimney A B A B A B A B A B A B A B A B A B A B A B A B D C D C D C D C D C D C D C D C D C D C D C D C Cor PAD A B A B A B A B A B A B A B A B A B A B A B A B D C D C D C D C D C D C D C D C D C D C D C D C Galian tanah A B A B A B A B A B A B A B A B A B A B A B A B D C D C D C D C D C D C D C D C D C D C D C D C Bore Pile A B A B A B A B A B A B A B A B A B A B A B A B Sondir / Boring Re Survey Pembebasan Lahan Span ( m) Row Stringging No urut 1 2 3 4 5 6 7 8 9 10 Manpower
Erection & Stringging
Nomor tower TW 108 TW 109 TW 110 TW 111 TW 112 TW 113 TW 114 TW 115 TW 116 TW 117 TW 118 TW 119 Type Tower Klas pondasi D C D C D C D C D C D C D C D C D C D C D C D C Cor chimney A B A B A B A B A B A B A B A B A B A B A B A B D C D C D C D C D C D C D C D C D C D C D C D C Cor PAD A B A B A B A B A B A B A B A B A B A B A B A B D C D C D C D C D C D C D C D C D C D C D C D C Galian tanah A B A B A B A B A B A B A B A B A B A B A B A B D C D C D C D C D C D C D C D C D C D C D C D C Bore Pile A B A B A B A B A B A B A B A B A B A B A B A B Sondir / Boring Re Survey Pembebasan Lahan Span ( m) Row Stringging No urut Manpower