You are on page 1of 2

RENCANA ANGGARAN BIAYA

PEKERJAAN STRUKTUR
KEGIATAN : REHABILITASI DAN PEMBANGUNAN GEDUNG SEKOLAH
PEKERJAAN : PEMBANGUNAN SMAN 10 SAMARINDA
LOKASI : KOTA SAMARINDA
TA : 2020

HARGA SATUAN JUMLAH HARGA Volume Bobot


NO URAIAN PEKERJAAN SAT. VOLUME BOBOT
( Rp ) ( Rp ) Hari Ini Hari Ini
1 2 3 4 5 6
C PEKERJAAN GEDUNG SEKOLAH TAHAP PERTAMA
C.I PEKERJAAN STRUKTUR
I PEKERJAAN TANAH
1 Pasang Bowplank M1 163.00 55,175.00 8,993,525.00 7.3 43.0 2
2 Galian Tanah M3 172.04 79,375.00 13,655,675.00 11.0 45.0 3
3 Urugan Tanah Kembali M3 44.48 26,458.33 1,176,866.67 1.0 33.0 1
4 Urugan Tanah Peninggi Lantai M3 439.10 114,500.00 50,276,950.00 40.6 0.0 0
5 Urugan pasir dibawah pile cap M3 5.83 121,750.00 709,802.50 0.6 0.0 0
6 Urugan pasir dibawah pondasi batu gunung M3 7.90 121,750.00 961,825.00 0.8 0.0 0
7 Urugan pasir dibawah lantai M3 48.52 121,750.00 5,907,310.00 4.8 0.0 0
8 Pondasi Batu Kosong M3 23.45 289,425.00 6,787,016.25 5.5 0.0 0
9 Pondasi Batu Gunung M3 62.19 529,570.00 32,933,958.30 26.6 0.0 0
10 Pondasi Batu Gunung ( Ramp Disabilitas ) M3 4.34 529,570.00 2,298,333.80 1.9 0.0 0
Jumlah I. 123,701,262.52 100 6

II PEKERJAAN STRUKTUR PONDASI


1 Pekerjaan Pondasi Mini Pile 30x30
- Pengadaan Tiang Pancang Mini Pile 30x30 M' 1,746.00 400,000.00 698,400,000.00 67.3 0.0 0
- Pemancangan Tiang Pancang Mini Pile 30x30 M' 1,746.00 75,000.00 130,950,000.00 12.6 0.0 0
- Test PDA (Pile Driving Analysis) Titik 3.00 16,000,000.00 48,000,000.00 4.6 0.0 0
2 Lantai kerja dibawah pondasi pile cap M3 8.33 831,557.46 6,926,873.64 0.7 0.0 0
3 Pekerjaan pondasi pile cap
Pile Cap P1
- Pembesian Ulir Kg 1,257.68 13,075.00 16,444,166.00 1.6 0.0 0
- Bekesting / Cetakan Untuk Pondasi M² 31.20 178,950.00 5,583,240.00 0.5 0.0 0
- Beton K-300 M³ 6.48 1,528,500.00 9,904,680.00 1.0 0.0 0
Pile Cap P2
- Pembesian Ulir Kg 3,356.43 13,075.00 43,885,322.25 4.2 0.0 0
- Bekesting / Cetakan Untuk Pondasi M² 61.34 178,950.00 10,976,793.00 1.1 0.0 0
- Beton K-300 M³ 17.52 1,528,500.00 26,779,320.00 2.6 0.0 0
Pile Cap P3
- Pembesian Ulir Kg 1,399.25 13,075.00 18,295,193.75 1.8 0.0 0
- Bekesting / Cetakan Untuk Pondasi M² 25.92 178,950.00 4,638,384.00 0.4 0.0 0
- Beton K-300 M³ 8.75 1,528,500.00 13,374,375.00 1.3 0.0 0
Pile Cap P4
- Pembesian Ulir Kg 131.46 13,075.00 1,718,839.50 0.2 0.0 0
- Bekesting / Cetakan Untuk Pondasi M² 3.84 178,950.00 687,168.00 0.1 0.0 0
- Beton K-300 M³ 0.58 1,528,500.00 886,530.00 0.1 0.0 0
Jumlah . 1,037,450,885.14 100 0

III PEKERJAAN STRUKTUR LANTAI 1


1 Pekerjaan Kolom
Kolom (K1)
- Pembesian Polos Kg 2,830.67 12,130.00 34,336,027.10 3 2830.7 3
- Pembesian Ulir Kg 4,901.79 13,075.00 64,090,904.25 6 0.0 0
- Bekesting / Cetakan Untuk Kolom M² 548.80 282,750.00 155,173,200.00 14 0.0 0
HARGA SATUAN JUMLAH HARGA Volume Bobot
NO URAIAN PEKERJAAN SAT. VOLUME BOBOT
( Rp ) ( Rp ) Hari Ini Hari Ini
1 2 3 4 5 6
- Beton K-300 M³ 54.88 1,528,500.00 83,884,080.00 8 0.0 0
Kolom (K3)
- Pembesian Polos Kg 61.35 12,130.00 744,175.50 0 0.0 0
- Pembesian Ulir Kg 87.97 13,075.00 1,150,207.75 0 0.0 0
- Bekesting / Cetakan Untuk Kolom M² 9.60 282,750.00 2,714,400.00 0 0.0 0
- Beton K-300 M³ 0.64 1,528,500.00 978,240.00 0 0.0 0
2 Pekerjaan Tie Beam (TB)
Tie Beam (B1)
- Pembesian Polos Kg 2,863.89 12,130.00 34,738,985.70 3 2863.9 3
- Pembesian Ulir Kg 8,490.68 13,075.00 111,015,641.00 10 0.0 0
- Bekesting / Cetakan Untuk Sloof M² 197.29 188,950.00 37,277,945.50 3 0.0 0
- Beton K-300 M³ 42.28 1,528,500.00 64,624,980.00 6 0.0 0
Tie Beam (B2)
- Pembesian Polos Kg 1,278.95 12,130.00 15,513,663.50 1 0.0 0
- Pembesian Ulir Kg 4,284.99 13,075.00 56,026,244.25 5 0.0 0
- Bekesting / Cetakan Untuk Sloof M² 89.04 188,950.00 16,824,108.00 2 0.0 0
- Beton K-300 M³ 19.08 1,528,500.00 29,163,780.00 3 0.0 0
Tie Beam (B3)
- Pembesian Polos Kg 299.16 12,130.00 3,628,810.80 0 0.0 0
- Bekesting / Cetakan Untuk Balok M² 5.55 290,250.00 1,610,887.50 0 0.0 0
- Beton K-300 M³ 1.04 1,528,500.00 1,589,640.00 0 0.0 0
3 Pekerjaan Plat Lantai
Plat Lantai tebal 12
- Pembesian Polos Kg 10,793.67 12,130.00 130,927,217.10 12 0.0 0
- Cor Lantai Kerja M³ 48.52 831,557.46 40,347,167.97 4 0.0 0
- Beton K-300 M³ 116.44 1,528,500.00 177,978,540.00 16 0.0 0
4 Pekerjaan Tangga
- Pembesian Polos Kg 201.66 12,130.00 2,446,135.80 0 0.0 0
- Pembesian Ulir Kg 1,411.40 13,075.00 18,454,055.00 2 0.0 0
- Bekesting / Cetakan Untuk Plat M² 47.16 296,750.00 13,994,730.00 1 0.0 0
- Beton K-300 M³ 7.82 1,528,500.00 11,952,870.00 1 0.0 0
Jumlah III. 1,111,186,636.72 100 6

IV PEKERJAAN STRUKTUR LANTAI 2


1 Pekerjaan Balok
Balok B1
- Pembesian Polos Kg 2,944.95 12,130.00 35,722,243.50 3.4 0.0 0
- Pembesian Ulir Kg 8,618.95 13,075.00 112,692,771.25 10.8 0.0 0
- Bekesting / Cetakan Untuk Balok M² 315.19 290,250.00 91,483,897.50 8.8 176.0 4.9
- Beton K-300 M³ 43.98 1,528,500.00 67,223,430.00 6.4 0.0 0
Balok B2
- Pembesian Polos Kg 1,275.52 12,130.00 15,472,057.60 1.5 0.0 0
- Pembesian Ulir Kg 4,284.99 13,075.00 56,026,244.25 5.4 0.0 0
- Bekesting / Cetakan Untuk Balok M² 136.74 290,250.00 39,688,785.00 3.8 0.0 0
- Beton K-300 M³ 19.08 1,528,500.00 29,163,780.00 2.8 0.0 0
Balok B3
- Pembesian Polos Kg 299.16 12,130.00 3,628,810.80 0.3 0.0 0
- Bekesting / Cetakan Untuk Balok M² 10.76 290,250.00 3,123,090.00 0.3 0.0 0
- Beton K-300 M³ 1.04 1,528,500.00 1,589,640.00 0.2 0.0 0
Balok B5
- Pembesian Polos Kg 194.52 12,130.00 2,359,527.60 0.2 0.0 0
- Pembesian Ulir Kg 344.94 13,075.00 4,510,090.50 0.4 0.0 0
- Bekesting / Cetakan Untuk Balok M² 17.89 290,250.00 5,192,572.50 0.5 0.0 0
- Beton K-300 M³ 1.54 1,528,500.00 2,353,890.00 0.2 0.0 0
Plat Lantai tebal 12
- Pembesian Kg 10,396.92 12,130.00 126,114,639.60 12.1 0.0 0
- Bekesting / Cetakan Untuk Plat M² 929.54 296,750.00 275,840,995.00 26.5 0.0 0
- Beton K-300 M³ 111.55 1,528,500.00 170,504,175.00 16.4 0.0 0
Jumlah IV. 1,042,690,640.10 100.0 4.9