Professional Documents
Culture Documents
SNLDistribution System WSBruendlinger
SNLDistribution System WSBruendlinger
net/publication/265141211
CITATIONS READS
10 817
1 author:
Roland Bründlinger
AIT Austrian Institute of Technology
82 PUBLICATIONS 1,159 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
European Research Infrastructure supporting Smart Grid and Smart Energy Systems Research, Technology Development, Validation and Roll Out –
Second Edition (ERIGrid 2.0) View project
All content following this page was uploaded by Roland Bründlinger on 29 August 2014.
Roland Bründlinger
Senior Engineer
AIT Austrian Institute of Technology, Vienna, Austria
13.05.2014 1
Contents
Background – Development and challenges of grid connected PV in Europe
13/05/2014
13.05.2014 2
Contents
Background – Development and challenges of grid connected PV in Europe
13/05/2014
13.05.2014 3
Source: EPIA, ” IEA-PVPS Task 14, Transition from Consumption to Supply Grids , to be published
Evolution of European cumulative installed PV capacity
For comparison:
Total installed generation capacity in
EU27 2011 approx. 850 GW (eurelectric figures)
Source: EPIA, ESTELA, EU-OEA, EWEA, Platts PowerVision, PV CYCLE
Net power generation capacity added in the EU28 in 2013
Key Challenges
Increased variability and
uncertainty
Increasing share of non-rotating
generation
Increasing share of distribution
system connected generation
Provision of grid support services
by RES?
Penetration levels in some regions
and countries have reached levels
where full PV grid integration
becomes critical to guarantee
operational stability
Coordinated development of Grid Code
Source: EPIA 2013, Reservices Project 2014 requirements for PV and DG needed.
7
Contents
Background – Development and challenges of grid connected PV in Europe
13/05/2014
13.05.2014 8
Framework for PV/DG interconnection in Europe
Country specific grid codes and standards
Up to now no EU wide directive on DER/PV grid
interconnection
Country specific grid codes, standards, DSO
guidelines…
Different legal and administrative levels
Fundamental differences between the countries
Generally complex, intransparent situation
Issues for manufacturers and project developers
Specific product settings for each country/market
Interpretation of the requirements and application in
practice
Increased costs and reduced competiveness
Critical issues for power system operation
Lack of coordination and compatibility
Risk of losing system security during critical events
due to undefined behavior of DER
5/13/2014 9
Current requirements for advanced grid support by PV
Connection to LV distribution grids
Full set of advanced grid support
requirements mandatory for :
DE: Systems >16 A (2012)
AT: Systems >16 A (2013)
IT: Units >3 kVA (2012)
DK: Systems >16 A (2013)
Main functions:
Reactive power control (typ.
PF(P) characteristic
Frequency control P(f)
No trip at low frequency
Remote limitation of P output
(DE, AT, IT)
5/13/2014 10
Current requirements for advanced grid support by PV
Connection to MV distribution grids
13/05/2014
13.05.2014 12
Framework for PV/DG interconnection in Europe
The new ENTSO-E Network Codes
2009: European Agency for the Cooperation of
Energy Regulators (ACER) issued an official
mandate to ENTSO-E (European Network of
Electricity TSOs) to develop draft “Network Codes”
A set of rules applying to one aspect of the
Source: ENTSO-E
energy sector
Developed by ACER, ENTSO-E & market
participants (transparent process)
Become legally binding (comitology process)
Ultimately have the same status as a
European Regulation
Goal: Strengthen the European internal electricity
market
5/13/2014 13
Framework for PV/DG interconnection in Europe
The new ENTSO-E Network Code RfG
Network Code on “Requirements for Grid Connection applicable to all
Generators (RfG)” is one of the first projects, aiming at
Establishing legally binding EU wide harmonization of grid
interconnection requirements
Ensuring and increasing the system security with a growing share of
RES and variable generation
Avoiding future regret and costly retrofits to ensure security of supply
Source: ENTSO-E
5/13/2014 14
Framework for PV/DG interconnection in Europe
ENTSO-E RfG Network Code
Basic approach
Applicable to all generators >0.8 kW
Balance European settings and regional specifics
Proportional approach from smallest generation to
largest plants
Application for (all) new generators in order to
ensure system security in a changing environment
accommodate evolution in the generation portfolio
reduce costs through standardization.
Application for existing generators (retrofit) only if
technically justifiable,
benefits demonstrated by Cost Benefit Analysis
approved by National Regulatory Authority
5/13/2014 https://www.entsoe.eu/major-projects/network-code-development/requirements-for-generators/ 15
Framework for PV/DG interconnection in Europe
ENTSO-E RfG Network Code
Standardized definition of generator types and
associated functionalities/ requirements depending on
transmission grid region
connection level (voltage)
generator capacity and technology (synchronous or converter based)
5/13/2014 16
Framework for PV/DG interconnection in Europe
ENTSO-E RfG Network Code
5/13/2014 17
Framework for PV/DG interconnection in Europe
ENTSO-E RfG Network Code
Overview of aspects and requirements addressed by the RfG
Addressed system Requirement Type Type Type
aspect A B C/D
Frequency stability Operating frequency ranges X X X
RoCoF withstand capability X X X
Limited Frequency Sensitive Mode - Overfrequency X X X
Constant active power output regardless of changes in X X X
Frequency
Limitation of power reduction at underfrequency X X X
Automatic connection X X X
Remote ON/OFF X X
Active power reduction remote control X
Additional requirements related to frequency control X
Provision of synthetic inertia X
5/13/2014 18
Framework for PV/DG interconnection in Europe
ENTSO-E RfG Network Code
Overview of aspects and requirements addressed by the RfG
Addressed system Requirement Type Type Type
aspect A B C/D
Robustness of Fault-ride-through X X
power generating
Post-fault active power recovery X X
modules
System restoration Coordinated reconnection X X
General system Control schemes and settings X X
management
Electrical protection and control schemes and settings X X
Priority ranking of protection and control X X
Information exchange X X
Additional requirements to monitoring X
Voltage stability Reactive power capability X X
Fast reacting reactive power injection X X
Additional requirements for reactive power capability X
5/13/2014 and control modes 19
Framework for PV/DG interconnection in Europe
ENTSO-E RfG Network Code
Some further aspects related to the RfG
Eventually, the RfG will have the character of a EU directive Later
amendments will be very difficult
Definitions in RfG leave wide room for variation/interpretation by the local
TSOs/NRAs
After its implementation the RfG will
Define system relevant minimum requirements for all generators
Provide a basis for national codes and standards
However, the RfG will not
Provide a true harmonization of the requirements across Europe
Provide “product specifications” which can be easily be implemented by
manufacturers
Provide harmonized certification, type testing or modeling procedures
Provide requirements related to communication protocols or technologies
(e.g. IEC 61850, DNP3)
5/13/2014 20
Framework for PV/DG interconnection in Europe
ENTSO-E RfG Network Code
Recent steps
Jan-March 2012: Open public consultation with all stakeholders
July 2012 – March 2013: Review of RfG draft by ACER
October 2013: Implementation Guideline published
European Commission comitology procedure started in January 2014
Further implementation of the code at national level via existing processes
Definition of detailed local requirements and conditions by national
TSOs in collaboration with NRAs
Amendments/ modifications to existing national guidelines
Planned to be legally binding from 2017
5/13/2014 21
Framework for PV/DG interconnection in Europe
ENTSO-E RfG Network Code
Resources
RfG webpage:
https://www.entsoe.eu/major-projects/network-code-
development/requirements-for-generators/
Implementation Guideline:
https://www.entsoe.eu/fileadmin/user_upload/_library/resources/RfG/13
1016_-_NC_RfG_implementation_guideline.pdf
5/13/2014 22
Contents
Background – Development and challenges of grid connected PV in Europe
13/05/2014
13.05.2014 23
Summary and key conclusions
ECOGRID EU www.eu-ecogrid.net
metaPV www.metapv.eu
PV GRID http://www.pvgrid.eu
REserviceS www.reservices-project.eu
IGREENGrid www.igreengrid-fp7.eu
PV PARITY www.pvparity.eu
13.05.2014 25
Thank you very much for your attention!
Roland Bründlinger
AIT Austrian Institute of Technology
Giefinggasse 2, 1210 Wien, Austria
roland.bruendlinger@ait.ac.at
13.05.2014 26