1.-Cronograma de Ejecucion Fisica
1.-Cronograma de Ejecucion Fisica
DEPARTAMENTO HUANUCO”
CARTEL DE IDENTIFICACION DE LA OBRA DE 1.20 x 2.40 M 1 1 01/11/2022 01/11/2022 2CC 0 S/ 851.89 1.00 und
1 dias
ACERO GRADO 60 FY=4200 KG/CM2 PARA PEDESTALES 3 3 11/11/2022 13/11/2022 23CC-2 0 S/ 4,980.51 3 dias 657.06 kg
ESTRUCTURAS METÁLICAS 30 30 16/11/2022 15/12/2022 0 S/ 154,532.47
COLUMNAS 5 5 16/11/2022 20/11/2022 0 S/ 51,820.68
COLUMNA METALICA 200X300MM E=6MM (C-1) 3 3 18/11/2022 20/11/2022 35 0 S/ 41,463.76 3 dias 101.22 m
ANCLAJE DE COLUMNAS 3 3 16/11/2022 18/11/2022 29 0 S/ 10,356.92 3 dias 14.00 und
VIGAS 6 6 20/11/2022 25/11/2022 0 S/ 7,488.38
CERCHA METALICA LATERAL (VIGA METALICA) 3 3 20/11/2022 22/11/2022 34 0 S/ 6,416.78 3 dias 52.08 m
ANCLAJE CERCHA METALICA 4 4 22/11/2022 25/11/2022 37 0 S/ 1,071.60 4 dias 24.00 und
TECHO 17 17 20/11/2022 06/12/2022 0 S/ 70,766.15
ARMADO Y MONTAJE DE TIJERALES EN ARCO CON TUBOS METALICOS 8 8 22/11/2022 29/11/2022 38CC 0 S/ 34,227.41 8 dias 7.00 und
ARMADO Y MONTAJE DE CORREAS METALICAS DE 50mmX100mm E=3mm 8 8 29/11/2022 06/12/2022 40 0 S/ 16,354.67 8 dias 410.20 m
ARMADO Y MONTAJE DE ARRIOSTRAMIENTO DE TIJERAL FIERRO LISO Ø5/8" 5 5 29/11/2022 03/12/2022 40 0 S/ 7,958.29 5 dias 747.96 m
ARMADO Y MONTAJE DE APOYO FIJO DE TIJERALES EN ARCO 3 3 20/11/2022 22/11/2022 34 0 S/ 6,112.89 3 dias 7.00 und
ARMADO Y MONTAJE DE APOYO MOVIL DE TIJERALES EN ARCO 3 3 20/11/2022 22/11/2022 43CC 0 S/ 6,112.89 3 dias 7.00 und
COBERTURA 10 10 06/12/2022 15/12/2022 0 S/ 24,457.26
SUMINISTRO E INSTALACION DE CALAMINA ALUZINC TR5 E=0.30MM 10 10 06/12/2022 15/12/2022 41 0 S/ 24,457.26 10 dias 581.90 m²
ARQUITECTURA 33 33 16/11/2022 18/12/2022 0
REPOSICION DE PISOS Y PAVIMENTOS 3 3 25/11/2022 27/11/2022 0 S/ 4,117.28
AFIRMADO E=0.20M 2 2 25/11/2022 26/11/2022 17 0 S/ 476.60 2 dias 44.13 m²
REPOSICION DE LOSA DE CONCRETO E=0.15m 2 2 26/11/2022 27/11/2022 49 0 S/ 3,640.68 2 dias 50.94 m²
ACABADOS 2 2 16/11/2022 17/11/2022 0 S/ 27.57
TARRAJEO CON MORTERO 1:5 E=1.5CM. 2 2 16/11/2022 17/11/2022 29 0 S/ 27.57 2 dias 0.67 m²
PINTURA 32 32 17/11/2022 18/12/2022 0 S/ 1,049.93
PINTURA LATEX EN PEDESTALES 2 2 17/11/2022 18/11/2022 52 0 S/ 7.20 2 dias 0.67 m²
PINTURA EN CARPINTERIA METALICA (ESMALTE Y ANTICORROSIVA) 4 4 15/12/2022 18/12/2022 46 0 S/ 1,042.73 4 dias 85.54 m²
INSTALACIONES SANITARIAS 6 6 06/12/2022 11/12/2022 0
DRENAJE PLUVIAL 6 6 06/12/2022 11/12/2022 0 S/ 6,720.19
TUBERIA PVC D= 3" INC/ ACCESORIOS DE FIJACION 3 3 06/12/2022 08/12/2022 46CC 0 S/ 1,313.12 3 dias 29.00 m
CODO PVC SAL 3"X90º 4 4 06/12/2022 09/12/2022 58CC 0 S/ 613.80 4 dias 12.00 und
CANALETA DE F° G° E= 1/32" 3 3 09/12/2022 11/12/2022 59 0 S/ 4,679.37 3 dias 58.58 m
EMBUDO DE CANALETA A DRENAJE PLUVIAL 3 3 06/12/2022 08/12/2022 58CC 0 S/ 113.90 3 dias 2.00 und
INSTALACIONES ELECTRICAS 16 15 15/12/2022 30/12/2022 0
SALIDA DE LUZ Y FUERZA 3 3 15/12/2022 17/12/2022 0 S/ 194.96
SALIDA PARA REFLECTORES 3 3 15/12/2022 17/12/2022 71CC 0 S/ 194.96 3 dias 8.00 pto
TUBERIAS Y CONDUCTORES 8 8 17/12/2022 24/12/2022 0 S/ 4,299.11
TUBERIA PVC-SAP 40 MM DIAMETRO 3 3 17/12/2022 19/12/2022 64 0 S/ 1,045.59 3 dias 45.98 m
TUBERIA FLEXIBLE CONDUIT 25 MM DIAMETRO 5 5 17/12/2022 21/12/2022 66CC+1 0 S/ 1,704.11 5 dias 72.30 m
CABLE ELECTRICO NYY 4 MM2 4 4 21/12/2022 24/12/2022 67 0 S/ 703.62 4 dias 126.55 m
CABLE ELECTRICO N2XH 6 MM2 4 4 21/12/2022 24/12/2022 68CC 0 S/ 845.79 4 dias 144.58 m
TABLEROS 3 3 15/12/2022 17/12/2022 0 S/ 452.10
TABLERO DE DISTRIBUCION 16 POLOS CAJA TIPO GABINETE7/INC MURETE 3 3 15/12/2022 17/12/2022 55CC 0 S/ 452.10 3 dias 1.00 und
PUESTA A TIERRA 3 3 15/12/2022 17/12/2022 0 S/ 1,692.41
SUMINISTRO E INSTALACION DE PUESTA A TIERRA R<=15 OHMIOS 3 3 15/12/2022 17/12/2022 71CC 0 S/ 1,692.41 3 dias 1.00 und
ARTEFACTOS ELECTRICOS 5 4 24/12/2022 28/12/2022 0 S/ 5,710.54
REFLECTOR LED DE 400W 5 4 24/12/2022 28/12/2022 69 0 S/ 5,011.68 4 dias 8.00 und
INTERRUPTOR THERMOMAGNETICO 3 x 40A 4 3 24/12/2022 27/12/2022 69 0 S/ 306.90 3 dias 3.00 und
INTERRUPTOR DIFERENCIAL BIPOLAR 2x40A 4 3 24/12/2022 27/12/2022 69 0 S/ 391.96 3 dias 2.00 und
PRUEBAS ELECTRICAS 3 3 28/12/2022 30/12/2022 0 S/ 350.00
PRUEBA CORRIENTE Y BALANCEO DE CARGA 3 3 28/12/2022 30/12/2022 75 0 S/ 200.00 3 dias 1.00 gbl
PRUEBA DE CONTINUIDAD 3 3 28/12/2022 30/12/2022 75 0 S/ 150.00 3 dias 1.00 gbl
PLAN DE MANEJO AMBIENTAL, SEGURIDAD Y SALUD 59 58 01/11/2022 29/12/2022 0
PLAN DE MANEJO AMBIENTAL 59 58 01/11/2022 29/12/2022 0 S/ 834.21
PROGRAMA DE MANEJO DE EFLUENTES Y RESIDUOS SOLIDOS 59 58 01/11/2022 29/12/2022 0 S/ 420.34
CONTENEDORES DE POLIETILENO DE ALTA DENSIDAD 59 58 01/11/2022 29/12/2022 0 S/ 420.34 58 dias 1.00 gbl
PROGRAMA DE SEGUIMIENTO Y CONTROL AMBIENTAL 59 58 01/11/2022 29/12/2022 0 S/ 270.02
SEÑALIZACIÓN DEL ÁREA DE TRABAJO 59 58 01/11/2022 29/12/2022 0 S/ 270.02 58 dias 1.00 gbl
PLAN DE CIERRE Y ABANDONO 2 2 28/12/2022 29/12/2022 0 S/ 143.85
DESMONTAJE DE OBRAS PROVISIONALES 2 2 28/12/2022 29/12/2022 75 0 S/ 143.85 2 dias 1.00 gbl
PLAN PARA LA VIGILANCIA, PREVENCION Y CONTROL DEL COVID-19 EN EL TRABAJO 59 58 01/11/2022 29/12/2022 0 S/ 1,337.24
ELABORACION DE DOCUMENTOS 59 58 01/11/2022 29/12/2022 0 S/ 500.00
ELABORACION DEL PLAN PARA LA VIGILANCIA, PREVENCION Y CONTROL DEL COVID-19 59 58 01/11/2022 29/12/2022 0 S/ 500.00 58 dias 1.00 gbl