You are on page 1of 11

INTERNATIONAL JOURNAL OF

PROJECT
MANAGEMENT
International Journal of Project Management 24 (2006) 156–166
www.elsevier.com/locate/ijproman

Unit-price-based model for evaluating competitive bids


a,*
Wei-Chih Wang , Han-Hsiang Wang a, Yu-Ting Lai a, John Chien-Chung Li b

a
Department of Civil Engineering, National Chiao Tung University, 1001, Ta-Hsueh Road, Hsinchu 300, Taiwan
b
Institute of Construction Management, National Central University, Taiwan

Received 7 September 2004; received in revised form 21 April 2005; accepted 7 June 2005

Abstract

A lump-sum lowest bid method allows project administrators of public construction projects to reject any bid if they determine
the bid price is unreasonable. In practice however, few bids are rejected because of the lack of an objective process for evaluating the
lowest bids. While past research assessed the bids based on total bid price, this study proposes a bid evaluation model developed
based on the level of unit prices. In the proposed model, the lowest bid is assessed according to the unit prices electronically obtained
from the owner and all qualified bidders. Moreover, a differential ratio is defined to measure the deviation between the unit prices
submitted by both the owner and the lowest bidder. The merits of this innovative model are demonstrated by applying it to two
subprojects of a building construction project. Practitioners and governmental officers have confirmed the feasibility of the model
provided the languages or clauses describing the modeling algorithms are explicated in the general or special conditions of tendering
documents.
 2005 Elsevier Ltd and IPMA. All rights reserved.

Keywords: Project procurement; Competitive bid; Electronic bidding; Unit price and cost item

1. Introduction Although project administrators of public construc-


tion projects are allowed to reject the lowest bid if the
A lump-sum lowest bid method awards the contract bid price is considered to be unreasonable, in reality,
for a construction project to the bidder who submits very few bids are rejected. Without an objective process
the lowest bid price. One major shortcoming of this described in the tender documents to support their bid
method is that the submission of offers that are unrea- evaluations, a rejected bidder may challenge such a prac-
sonably low is not unusual. Awarding contracts to tice by appealing to a court. Consequently, lengthy
unreasonably low bidders frequently causes delays and court procedures can delay the procurement process.
results in poor quality construction. Most such cases For example, Taiwan has tendered approximately
end up in contractual disputes or litigation. Also, statis- 201,819 public construction projects out in the last six
tically, projects awarded to the lowest bids are more year (i.e., from May 1998 to May 2004). Moreover, up
likely to experience excessive cost growth than are pro- to around 99.2% (=200,273/201,819) of the projects
jects awarded to more reasonable bids [1]. adopted the lowest bid method for tendering. The aver-
age bid ratio (winning bid divided by the project ceiling
*
price) of these projects was about 0.79. However, less
Corresponding author. Tel.: +886 3 5712121x54952; fax: +886 3 than 1% of these lowest-bid projects had executed a pro-
5716257.
E-mail addresses: weichih@mail.nctu.edu.tw (W.-C. Wang), rijo- cess for evaluating the lowest bid, despite many owners
wang.cv90g@nctu.edu.tw (H.-H. Wang), albert66@giga.net.tw (Y.-T. complaining that their lowest bids were suspiciously
Lai), johnli@cc.ncu.edu.tw (J. Chien-Chung Li). low.

0263-7863/$30.00  2005 Elsevier Ltd and IPMA. All rights reserved.


doi:10.1016/j.ijproman.2005.06.002
W.-C. Wang et al. / International Journal of Project Management 24 (2006) 156–166 157

The lowest bid method contains a prequalification 2. Current tendering practice of public construction
process to eliminate unqualified competitors. However, projects in Taiwan
this process focuses on bidder performance of past
projects and financial status rather than considering The Government Procurement Law in Taiwan, sub-
how each bidder plans to manage the current project sequently termed GPL, was promulgated on May 27,
(e.g., how the bidder allocates the costs to perform 1998, and took effect one year later [2]. GPL contains
the work). Since the Taiwanese economy is currently three tendering procedures, including open tendering,
suffering from low growth or even declining, unscru- selective tendering, and limited tendering. A public en-
pulous contractors may bid for a project using unrea- tity (project owner) generally applies open tendering to
sonably low prices simply to obtain the project for the procure most projects. Under open tendering, a public
sake of their survival. A low bid price may be politi- notice is issued to invite all interested suppliers to submit
cally desirable to project administrators, because it their bids. Meanwhile, in the selective tendering proce-
indicates that the project administrators are conscious dure, a public notice is issued inviting all interested sup-
of saving taxpayer money. However, an unrealistically pliers to submit their qualification documents for
low bid implies that the winner may cut corners dur- prequalification evaluation and, after the evaluation,
ing construction to maintain profits. Namely, the win- the qualified suppliers are invited to bid. An entity can
ner can perform the project in bad faith using apply the limited tendering procedure based on compli-
substituted equipment or materials with inferior qual- cated procurement situations. In the limited tendering
ity, constructing poor quality work, or allocating procedure, two or more suppliers are invited to compete
insufficient numbers of engineers and laborers for sav- for tendering, or alternatively only one supplier is
ing costs (as a result, the management quality is im- invited.
pacted). Hence, ensuring that the lowest bid price is GPL has two categories of contract-awarding meth-
reasonable given the work to be performed is essential ods: the lowest bid tendering method (LBT) and the
to successful project procurement. most favorable tendering method (MFT). If the LBT
Current models have focused on evaluating the method is used, a bidder that adheres to the require-
lowest bid based on total bid price. That is, the lowest ments set forth in the tender documentation and has
project bid is identified as discordant or unreasonable the lowest bid price is awarded the contract. If a pro-
using statistical procedures that investigate the dis- curement entity adopts the MFT method (a type of multi-
agreement between the lowest total bid price and the criteria bid evaluation method), the bidder with a tender
other submitted bid prices. Learning from interviews that fulfills the requirements set forth in the tender doc-
with several contractors in Taiwan, a rejected bidder umentation and whose proposal is most favorable to the
would be expected to respond to the project adminis- entity, is considered the winning bidder.
trators by asking: ‘‘which parts of my estimates are If the lowest bid method is adopted, the project
unreasonable or mistaken?’’ Certainly, the past ap- administrators or contracting officers normally should
proach that assesses bids based on total-bid-price level determine a project ceiling price or cost estimate to use
cannot adequately defend against such a bid-rejection as a threshold or reference point for accepting or reject-
argument. Consequently, administrators of public con- ing bids [2]. If the lowest bid exceeds the project ceiling
struction projects in Taiwan remain very reluctant to price, all bids are rejected; otherwise, the contract is
challenge the lowest bid because of the lack of a awarded to the lowest bidder. Additionally, if the total
quantitative model to objectively review the lowest or a part of the offered price of the lowest bid is suspi-
bid and to justify the decisions of the administrators. ciously low, and is likely to impair contract performance
The Public Construction Commission (PCC; Execu- quality, then the project administrators can ask the low-
tive Yuan, Taiwan) – the highest government entity est bidder to provide either a reasonable explanation or
responsible for public construction work – has initi- additional security before the deadline set by the project
ated this work. This work proposes an electronic-facil- administrators. If such a suspicious lowest bidder fails to
itated model that examines the lowest bid based on defend his estimates, the contract is not awarded to this
the unit prices of cost items of the project. The bidder; and the bidder offering the second lowest bid is
remainder of this paper is organized as follows. The then deemed the lowest bidder and the process repeats.
current procurement practice of public construction Nevertheless, most project owners simply request a
projects is examined first. Past research on the bidding suspicious lowest bidder to provide an additional secu-
area then is reviewed. Next, the proposed model is de- rity (called a ‘‘differential security bond’’) to ‘‘protect’’
scribed, and its detailed workings are demonstrated their projects and are reluctant to evaluate the lowest
using two example projects. Furthermore, feedback bid. Such reluctance is largely owing to that the pro-
from the government and industry is given, and the ject procurement process is likely to be suspended if
strengths of the model are discussed. Finally, conclu- the rejected bidder appeals to the court regarding
sions are provided. the rejection decision (or to the Complaint Review
158 W.-C. Wang et al. / International Journal of Project Management 24 (2006) 156–166

Board for Government Procurement in Taiwan) and designed an A-plus-B method that regarded construc-
the project administrators cannot strongly defend their tion cost and time as selection criteria. This method is
decisions. Accordingly, very few bids are rejected. a converted lowest bid method [18]. The average bid
Notably, this is even the case for projects with a bid method attempts to identify the average bid value by
ratio of only 0.3–0.4 (that is, the winning bid is only totaling all bid prices and then dividing this number
30–40% of the cost estimate of the owner). As ex- by the total number of bids. The winning bidder is the
pected, disputes, arbitrations or lawsuits or contractor one whose bidding price is nearest to but below the aver-
bankruptcies frequently occur in relation to these low- age bid value [19]. In the multi-criteria evaluation meth-
bid projects in Taiwan (including those provided by od, Alsugair [20] proposed a framework, involving 36
differential security bonds). evaluation factors grouped into nine classes. Also, Lai
Notably, in a few cases, a lowest bidder may seek et al. [21] presented a six-criteria-based bid evaluation
rejection by intentionally providing poor explanations model currently used in China. Besides the above meth-
to defend their low bids when they find that their bid ods, Holt [22] collected and reviewed various potential
is actually too low owing to a poor or mistaken estima- methods, including the multi-attribute utility theory,
tion. In such a case, this bidder can still refund their bid cluster analysis method, multiple regression method,
bond following rejection; otherwise, their bid bond may and fuzzy set theory method.
not be refunded. A refusal to provide an explanation Determination of project ceiling price – Before open-
would be considered an intentional interference in the ing the bidding, a project cost threshold or cost estimate
tendering process. must be decided by a project owner as a reference for
evaluating competing bids. Wang [23] proposed a sys-
tematic procedure that is developed according to a util-
3. Pertinent literature ity-based multi-criteria evaluation model and a cost
model. In the procedure of Wang, the multi-criteria
Pertinent research on bidding can be broadly classi- evaluation model is applied to reflect owner preferences
fied into six categories: prequalification, determination regarding the decision criteria, and the cost model is de-
of bid mark-up, selection of bid-awarding method, rived to establish a cumulative cost distribution for set-
determination of project ceiling price, adjustment of ting cost threshold boundaries.
bid unit prices following project awarding, and evalua- Adjustment of bid unit prices following project award-
tion of competitive bids. ing – The research in this category deals with the assess-
Prequalification – As a pre-tender process, prequalifi- ment and adjustment of unit prices for a lump-sum
cation assesses the capabilities of contractors to project that has already been awarded [24]. The main
complete a contract satisfactorily [3], and it is a deci- objective of this type of research is to produce a reason-
sion-making process that involves a wide range of crite- able allocation of total bid price to each cost item for
ria for which information is often qualitative, subjective, preventing an unbalanced bid.
and imprecise [4]. These criteria include past failures, Evaluation of competitive bids – The research most
financial status, financial stability, credit ratings, experi- relevant to this investigation is that evaluating competi-
ence, ability, management personnel, and management tive bids for a lump-sum bidding project. This type of re-
knowledge [5]. Lo et al. [6] concluded that improper pre- search examines the decision to accept or reject the
qualification requirements severely delayed a project lowest project bid depending on whether or not the low-
and increased the cost to the project owner. est bid price is considered reasonable [25,26]. For exam-
Determination of bid mark-up – Numerous studies ple, Crowley and Hancher [25] proposed a quantitative
have examined bid mark-up strategies from the perspec- method that comprised preparation and examination
tive of the number of competitors involved [7], the re- phases. The preparation phase used the bid records of
source constraints and opportunity costs of the bidder historical projects to develop a suitable transformation
[8], the cost uncertainty [9], the probability of winning scale (for isolating inherent bid variation from variabil-
the bid [10], and other factors influencing the bids [11]. ity arising from project size alone) and a discordant
Meanwhile, other researchers attempted to implement threshold (a measure of disagreement). Extensive histor-
bid make-up strategies using mathematical methods, ical data were required to establish the threshold limits
including utility theory [12], neural networks [13], fuzzy of discordant bids for bid assessments. The examination
set theory [14], analytic hierarchy process [15], and case- phase assessed apparently low bids according to the ex-
based reasoning [16]. pected recurrence of scale deviations between the med-
Selection of bid-awarding method – Besides the afore- ian (market value) and the low bid. Based on the
mentioned lowest bid and the most favorable tendering preferences of the owners regarding the expected recur-
methods, other typical contractor selection methods in- rence, the bid can either be accepted or rejected. Crow-
clude the A + B method, average bid method and multi- ley [27] investigated the most effective models (median
criteria evaluation methods. Herbsman and Ellis [17] and normalized median absolute deviation, respectively)
W.-C. Wang et al. / International Journal of Project Management 24 (2006) 156–166 159

for location and scale estimators designed to achieve the categories contained in the projectÕs written specifi-
more accurate bid evaluations. Additionally, Skitmore cations, such as those of the Construction Specification
et al. [28] employed seven data sets to conduct a bid- Institute (CSI) for building projects. The other approach
spread analysis to explore the nature and statistical employs a work breakdown structure (WBS) to identify
properties of bids, and concluded that bids were entirely work items by their location on the project. The devel-
random, being drawn from a lognormal distribution. oped model is based on the CSI estimate format that
Overall, current bid evaluation models have four major is commonly used in public construction projects in Tai-
characteristics; (1) the bid evaluations emphasize the to- wan. Thus, the costs of a construction project are orga-
tal bid price; (2) the models require that a database of nized according to four levels of estimates: (1) total bid
previous bids of past projects be established; (3) the ac- price; (2) level of project summary or bid summary. This
cept/reject decisions in existing models are made com- level summarizes various cost categories. Typical cost
pletely based on various statistical analyses (such as categories for a building project include direct costs,
the t value and the Z score); (4) no mechanism is pro- such as site-work excavation, concrete, equipment,
vided to enable the lowest bidders to defend their mechanical, and other indirect costs, such as tax, insur-
estimates. ance, and overheads (or profits); (3) cost item level (also
called the bill item or line item, and here simply termed
‘‘item’’). Each cost category is subdivided into smaller
4. Electronic-facilitated unit-price-based bid evaluation cost items for particular construction processes. For
model example, the cost items for the second-level site-work
excavation cost category may be subdivided into slurry
4.1. Reasons of adopting a unit-price-based approach wall, piling, finish grading, and so on. The cost of an
item equals the product of its unit price and quantity;
A bidder must determine the unit price of each cost (4) unit price level. A unit price is expressed as the cost
item to prepare a detailed estimate of a project. Then, required to complete a unit of work associated with a
the unit price multiplied by the quantity for each item cost item, for example the cost of constructing a square
yields the costs of the item. The sum of the costs of all meter of slurry wall. The term ‘‘cost item’’ here implies
cost items is the total bid price of the project. Such a de- the cost item in the third level.
tailed estimate takes a long time for a responsible bidder
to make. When a bidder is rejected because his bid is too 4.3. Prerequisite of the model
low, he is certainly expected to challenge the project
administrators by asking, ‘‘which aspects of my esti- The proposed model depends on an electronic bid-
mates are unreasonable?’’ Current models evaluate low ding process. The notice to bidders or general conditions
bids from the total bid price and neglect a detailed eval- (part of the bid package documents) must contain infor-
uation of the cost estimate. The modeling results are mation concerning the rules of the model algorithms to
such that convincing the rejected bidder of the unrea- ensure that the model can be executed (that is, to be
sonableness of his total bid price, developed from a de- open and fair while avoiding any disputes from bidders).
tailed cost estimate approach is difficult. Therefore, a The tender documents must also state that a bidder
model that can provide detailed evaluations of cost should submit his bidding package with an electronic
items is sought. The cost of an item is dominated by spreadsheet file (such as Excel) of project cost estimates.
the unit price. Accordingly, a unit-price-based bid eval- A submitted bidding package without this completed file
uation model is proposed to support the bid-rejection will be disqualified.
decisions to identify which of the estimates in a low
bid are unreasonable. 4.4. The model
Moreover, the unit-price-based approach offers
added value: it allows the ambiguous specifications After the lowest bid is found, the model is applied to
and drawings associated with high or low cost items sub- determine whether the bid price is reasonable. The de-
mitted by the bidder, to be clarified. Such clarification tails of the model are illustrated as follows (see Fig. 1).
helps to reduce disputes during the execution of con- First of all, if the lowest bid equals or exceeds 80% of
struction work related to cost items. Hence, the control the project ceiling price, then this lowest bid is consid-
of the construction is improved. ered reasonable and the contract should be awarded to
the lowest bidder. Otherwise, this lowest bid should be
4.2. Project cost further evaluated. The reasons for using 80% as a
threshold are: (1) eighty percent of the project ceiling
In practice, two approaches have evolved for organiz- price is a commonly used reference to determine whether
ing construction work items to estimate project costs an extra differential security bond should be provided
[29]. One approach is to identify work according to in most construction projects in Taiwan. For example,
160 W.-C. Wang et al. / International Journal of Project Management 24 (2006) 156–166

(bidder 1) (NT$)
The lowest bid is found

Unit price

3300
255,000

661,000

70
No
Lowest bid < 0.8 Project ceiling price?

Yes
Preparation step: integrating the unitprices from the owner and all

Maximum unit
qualified bidders in to a single file

price (NT$)

6500

550
312,000

736,000
Evaluation step: evaluating the unitprice submitted by
the lowest bidder

Clarification step: clarifying the suspiciously

Average unit
price (NT$)
unreasonable unit prices

5103

173
255,577

653,000
Decision step: deciding whether the total bid price is
reasonable

Minimum unit
Is the lowest bid reasonable?

price (NT$)
No Yes

3300
230,600

578,000

55
The second lowest bid is The contract is awarded
deemed the lowest bid to the lowest bidder

D = (B  O)/O (%)
Fig. 1. The proposed model.

Differential ratio
suppose that the project ceiling price is $100 million and
the lowest bid is $70 million (bid ratio is 70%), then the
lowest bidder must submit an extra bond of $10 million

20

36

46
4
(80% of $100 million–$70 million) to the project owner;
(2) using 80% as a threshold indicates that a bid exceed-
(lowest bid)
Unit price

ing the average bid ratio (about 0.79) of past projects in B (NT$)

5000
250,000

640,000

70
Taiwan is directly treated as reasonable.
Preparation step – Then, if the lowest bid is viewed as
suspicious (that is, bid ratio < 0.8), the preparation step
(owner) O (NT$)

is performed to facilitate the bid assessments. Prepara-


tion involves establishing an integrated file by combin-
Unit price

ing the unit prices from all parties (including the


311,882

996,710
4797

130
owner and the qualified bidders) into a single spread-
sheet. Table 1 gives an example of the data found in
such an integrated spreadsheet file. In this integrated file,
Quantity

a differential ratio, Dj, for cost item j is defined:


345
34

10
10,004

Dj ¼ ðBj  Oj Þ=Oj ; ð1Þ


where Bj and Oj denote the unit prices submitted by the
Example of integrated spreadsheet of cost estimate

Each

Each
Unit

M2

M3

lowest bidder and owner, respectively, for cost item j. A


positive Dj implies that the unit price submitted by the
Piling 140 cm2 (30.5 m depth)

Piling 260 cm2 (30.5 m depth)

lowest bidder exceeds that assessed by the owner, and


vice versa. A higher positive or lower negative value of
Dj indicates a greater difference between Bj and Oj.
Notably, in Table 1, dollar values are represented in
Item description

New Taiwan (NT) dollars (1 US dollar @ 30 New Tai-


Finish grading

wan dollars). Subsequently, dollar values are expressed


Excavation
Slurry wall

in NT dollars.
Evaluation step – Next, the evaluation step is executed
to examine whether the unit prices submitted by the low-
est bidder are reasonable. Specifically, based on the cal-
Item no.
Table 1

culated differential ratio of each cost item, each unit


1–16
1–1
1–2

1–9
...

...

price (Bj) submitted by the lowest bidder is assessed to


1
W.-C. Wang et al. / International Journal of Project Management 24 (2006) 156–166 161

determine which of the following three categories it falls ders (excluding the lowest bidder), and resembles the
into: calculation of the maximum unit price (maxj) of cost
item j. The rule-based phase then works as follows.
 Reasonable unit price – If r1 6 Dj 6 r1, (r1 denotes a
constant between 0 and 1 or a percentage between 0%  A suspiciously low Bj (that is, r2 6 Dj < r1) is
and 100%), then Bj is reasonable. Namely, if the dif- revised to a reasonable one if minj 6 Bj. Practically,
ference (percentage difference) between the unit prices provided at least one qualified bidder proposes a unit
provided by the lowest bidder and the owner falls price even lower than or equal to Bj, then it is hard to
within a specified range, then Bj is directly considered reject Bj.
reasonable. For example, a value of 0.3 (or 30%) for  A suspiciously high Bj (that is, r1 < Dj 6 r2) is revised
r1 indicates that Bj is reasonable if 0.3 6 Dj 6 0.3. to a reasonable one if Bj 6 maxj. In practice, at least
Restated, Bj is acceptable if it lies between 0.7 Oj one qualified bidder proposes a unit price even higher
and 1.3 Oj. than or equal to Bj, in which case it is hard to reject
 Suspicious unit price – If r2 6 Dj < r1 or Bj.
r1 < Dj 6 r2, then Bj is suspicious. Notably, r1 < r2
for example, r1 = 0.3 and r2 = 0.4. Namely, Bj is sus- If a suspicious Bj does not pass the above the
picious because it is slightly low, but not too low rule-based phase, then the explanation-based phase
(such as, 0.4 6 Dj < 0.3); or it is slightly high, continues to evaluate Bj. That is, the bidder is given an
but not too high (such as, 0.3 < Dj 6 0.4). opportunity to explain or offer evidence to back up their
 Unreasonable unit price – If Dj < r2 or r2 < Dj, estimate. Based on discussions with several practitioners
then Bj is directly deemed unreasonable. Restated, and governmental officers in Taiwan, several types of
Bj is not classified into either the reasonable or the accepting or rejecting the lowest bidderÕs explanation
suspicious unit price is unreasonable. are identified and summarized in Table 2. Generally, if
the lowest bidder can provide evidence demonstrating
The values r1 and r2 are used to help identify reason- that the low unit price results from the types of self-sup-
able, suspicious and unreasonable unit prices. The deter- plied equipment, guaranteed low price from material
mined values of r1 and r2 for a project are related to the suppliers, guaranteed low price from subcontractors,
bid ratio (lowest bid divided by the project ceiling price) and mistaken owner estimates, then the explanation is
of the project. In the proposed model, if the lowest bid is accepted and Bj is considered reasonable. However,
under 80% (approximately the mean bid ratio of previ- the explanations, including mistakenly filled in data,
ous projects in Taiwan) of the project ceiling price, then bidding strategy and false interpretation of work
this lowest bid should be further evaluated. Therefore, requirements, should not be accepted and Bj should be
on average, the unit price submitted by the lowest bidder considered unreasonable. Moreover, if the suspicious-
is expected to be at least 20% lower than that assessed by ness of Bj results from the ambiguous specifications pro-
the owner. Then, setting the value of r1 greater than 20% vided in the tendering documentation, then further
or 0.2 is practical. Setting r1 6 0.2 (e.g., r1 = 0.1) will discussion is needed. If the specifications are determined
probably cause most unit prices to be either suspicious to be too vague (namely, implying the faults are caused
or unreasonable. In contrast, higher r1 values result in by the owner side), then Bj is reasonable; otherwise, it is
more reasonable unit prices. unreasonable. Following this step, each suspicious unit
Since r1 > 0.2 and r1 < r2, r2 > r1 > 0.2. The value of price can eventually be treated as either reasonable or
r2 relates to the lowest bid ratio that is regarded as unreasonable.
acceptable. For instance, if project administrators re- Decision step – Finally, the model decides whether the
gard a bid ratio of 60% as the lowest acceptable bid ratio total bid price is reasonable. This decision is made based
(meaning that the lowest bid is 40% less than the project on whether the amount of the total unreasonable cost
ceiling price), r2 can be set to 0.4, because, on average, (TUC) exceeds the total bid price (TBP) by a predefined
the unit price submitted by the lowest bidder is 40% threshold ratio, TR (for example, 30%). The total unrea-
smaller than that evaluated by the owner at a bid ratio sonable cost, TUC, is given by
of 60%.
Clarification step – The clarification step is used to X
J
TUC ¼ ðBj  Qj Þ; ð2Þ
clarify the suspicious unit prices. This step is executed j¼1
by a rule-based phase and an explanation-based phase.
In the rule-based phase, the minimum and maximum where Qj denotes the quantity in relation to the unrea-
unit prices submitted by other qualified bidders with re- sonable unit price Bj for cost item j. Bj · Qj is termed
spect to each cost item are calculated first. The minimum the extended cost for item j. Consequently, the lowest
unit price, minj, of cost item j then is calculated accord- bid price is considered unreasonable if the value of
ing to the unit prices proposed by all other qualified bid- TUC/TBP exceeds the value of TR (that is, indicating
162 W.-C. Wang et al. / International Journal of Project Management 24 (2006) 156–166

Table 2
Types of accepting/rejecting of bidder explanation or evidence
No. BidderÕs explanation or evidence Description Suggested decision
1 Self-supplied equipment The unit price associated with executing these equipment-related Accepted
cost items is lower than if acquired in the normal market
2 Guaranteed low price from material suppliers Certain materials can be provided at a low price because they are Accepted
provided in large volume for this and other projects in which the
bidder is involved
3 Guaranteed low price from subcontractors Several subcontractors and crews are happy to charge low prices to Accepted
maintain good relationships with the bidder to gain future job
opportunities
4 OwnerÕs mistaken estimates The unit price estimated by the owner is unreasonable or wrong Accepted
5 Mistakenly filled in data The bidder filled in the cost data mistakenly Rejected
6 Bidding strategy Frequently, many Taiwanese bidders argue that they are willing to Rejected
faithfully perform the job even when the work is expected to be
non-profitable. The unreasonably low unit prices are submitted
only to win the contract to keep the bidderÕs company alive
7 False interpretation of work requirements The bidder had wrong interpretation of the amount of the work Rejected
required for a particular cost item
8 Ambiguous technical specifications The bidder prefers to a low unit price of the cost item that has Discussed
ambiguous specifications

that the percentage of the unreasonable costs over the fast-tracked for completion by mid 2000). Notably, in
total bid price is too high); otherwise, the bid is treated reality the two subprojects were both awarded to the
as reasonable. Unreasonable lowest bids are rejected. lowest bidder. The architectural subproject attracted
Furthermore, the second lowest bid is considered the eight bidders, one of whom was disqualified during the
lowest bid, and the above-mentioned modeling steps prequalification process. Furthermore, the electrical
are repeated to evaluate this new lowest bid. subproject attracted eight bidders who were all qualified.
The determined value of TR for a project is also re-
lated to the bid ratio of the project. The lowest bid is 5.1. Evaluation results
considered to be reasonable if its bid ratio exceeds 0.8
(or 80%). Namely, a 20% difference between the bid The lowest of the qualified bids for the architectural
price and the project ceiling price is reasonable. Accord- project was $830,000,000 representing a bid ratio of up
ingly, TR is suggested to exceed 0.2, indicating that the to 0.94 (=$830,000,000/$880,000,000). Using the pro-
total unreasonable costs can reasonably exceed the bid posed model, the lowest bid can then be considered rea-
price by 20%. Similarly, the highest value of TR is re- sonable because the bid ratio is over 0.8; this subproject
lated to the lowest bid ratio that is acceptable to the accordingly can be tendered out. However, the model is
project administrators. For example, if project adminis- also applied to the architectural subproject to further
trators consider a bid ratio of 60% to be the lowest examine the reasonableness of the proposed unit prices
acceptable bid ratio, then the value of TR may equal of the lowest bid. Additionally, the electrical subproject
0.4 (=10.6). Thus, the value of TR will be set between has a bid ratio (0.76 = $121,510,000/$159,900,000) of
0.2 and 0.4. below 0.8, and certainly should be further evaluated.
Suppose r1 = 0.3 and r2 = 0.4. Then, following con-
ducting the preparation and evaluation steps of the pro-
5. Example posed model, Table 3 lists the numbers of unit prices
that are treated as reasonable, suspicious or unreason-
The proposed model is applied to two subprojects able for each subproject. In the architectural subproject,
(architectural and electrical) of a building project to only about 46.05% (263/571) of cost items have a rea-
demonstrate its potential merits. The building project sonable unit price, and up to around 53.95% of unit
is in central Taipei, Taiwan. Besides three underground prices are either suspicious or unreasonable. Similarly,
floors, the project includes a 14-story hotel-like dormi- the number of cost items with reasonable unit prices is
tory, a six-story educational building, a three-story of- also less than half (34.03%) of the total number of cost
fice building, and a six-story building including an items (1619) in the electrical subproject. The middle of
800-seat meeting hall, and a 200-person convention hall. Table 3 illustrates the two extreme values of differential
The total project budget is approximately NT ratio found in each subproject. The extreme differential
$1,278,000,000 (US $42,600,000). (The project was ratio values indicate how widely the unit prices proposed
W.-C. Wang et al. / International Journal of Project Management 24 (2006) 156–166 163

Table 3
Number of reasonable, suspicious and unreasonable unit prices in each subproject
Subproject Ceiling price Lowest bid Bid Total no. Smallest D (%) Largest D (%) No. of items
ratio of items
Reasonable Suspicious Unreasonable
Architectural 880,000,000 830,000,000 0.94 571 98 5347 263 (46.05%) 61 (10.68%) 247 (43.26%)
Electrical 159,900,000 121,510,000 0.76 1619 100 2668 551 (34.03%) 209 (12.91%) 859 (53.06%)

by both owner and lowest bidder can vary. For example, 5.2. Evaluation results of an alternative model
in the architectural subproject, the smallest and largest
values of Dj are 98% and 5,347%, respectively. Cer- The above model considers the minimum unit price
tainly, the unit prices corresponding to these two ex- (minj) and maximum unit price (maxj) submitted by
treme values of Dj should be categorized as other qualified bidders with respect to each cost item j
unreasonable. for clarifying suspicious unit prices. An alternative ap-
Table 4 further shows the sums of the extended costs proach is considering the average unit price (avej) calcu-
of the reasonable, suspicious and unreasonable items in lated from the prices submitted by all qualified bidders
each subproject. In the architectural subproject, the rea- (including the lowest bidder) in the evaluation step. In
sonable cost is approximately 76.89% of the total bid an alternative model, the criteria used to assess each unit
price. Assume that the threshold ratio (TR ) is prede- price (Bj) can be as follows:
fined as 30%. Although the suspicious unit prices have
not been clarified, the lowest bid of this subproject can  Reasonable unit price – If r1 6 Dj 6 r1, then Bj is
be directly considered reasonable because the sum of reasonable. This criterion is the same as that of the
both the suspicious and unreasonable costs is just original model.
23.11% (below 30%).  Suspicious unit price – If {r2 6 Dj 6 r1 and
As indicated earlier, the lowest bid price of an electri- (1  r2)avej 6 Bj} or {r1 < Dj 6 r2 and Bj 6 (1 + r2)-
cal subproject is suspicious (namely, bid ratio is below avej} then Bj is suspicious. For example, suppose
0.8). Based on the proposed model, although the suspi- r1 = 0.3 and r2 = 0.4. Then, if {0.4 6 Dj < 0.3
cious items have not been clarified, the lowest bid of the and 0.6avej 6 Bj} or {0.3 < Dj 6 0.4 and Bj 6 1.4
electrical subproject can be directly considered unrea- avej} then Bj is suspicious. This criterion is stricter
sonable. Namely, the unreasonable cost of the lowest than that of the original model. The practical implica-
bid is up to 44.30%, which exceeds the threshold ratio tion is that a slightly low Bj, such as,
(30%). Thus, the lowest bid of the electrical subproject 0.4 6 Dj < 0.3 can be treated as suspicious pro-
should be rejected. And the second lowest then becomes vided it is not too low, for example, Bj must be greater
the lowest; the modeling steps then should be repeated. than or equal to 0.6avej. Furthermore, a slightly high
However, as noted earlier, this electrical subproject Bj such as, 0.3 < Dj 6 0.4 can be treated as suspicious
was awarded to the lowest bidder and no bid assess- provided it is not too high (for example, Bj must be
ments were conducted. To learn more about the effect lower than or equal to 1.4avej).
of this lowest bid on the subproject, the owner of the  Unreasonable unit price – If Bj is not considered
subproject and the electrical contractor were inter- either reasonable or suspicious, then it is considered
viewed. The owner indicated that the contractor had unreasonable.
been proposing to use substituted equipment and mate-
rials throughout the construction phase to reduce costs. Clarification then is conducted to clarify the suspi-
Consequently, arguments frequently arise between the cious unit prices based on the aforementioned explana-
owner and the contractor. Additionally, the contractor tion-based phase. Also suppose r1 = 0.3 and r2 = 0.4.
admitted that his bidding strategy was simply intended According to the alternative model, Table 5 lists the rea-
to gain the contract, increase the business volume of sonable, suspicious and unreasonable costs for the same
his company, and thus allow him to profit on sales of subprojects. This alternative model suggests the same
shares. decisions in accepting/rejecting the lowest bids for the

Table 4
Reasonable, suspicious and unreasonable costs in each subproject
Lowest bid Reasonable cost Suspicious cost Unreasonable cost Suggested decision (threshold ratio = 30%)
Architectural 830,000,000 638,188,895 (76.89%) 62,837,514 (7.57%) 128,973,591 (15.54%) Accept the bid (7.57% + 15.54%
= 23.11% < 30%)
Electrical 121,510,000 49,817,797 (41.00%) 17,867,780 (14.70%) 53,824,423 (44.30%) Reject the bid (44.30% > 30%)
164 W.-C. Wang et al. / International Journal of Project Management 24 (2006) 156–166

Table 5
Reasonable, suspicious and unreasonable costs in each subproject based on an alternative model
Lowest bid Reasonable cost Suspicious cost Unreasonable cost Suggested decision (Threshold ratio = 30%)
Architectural 830,000,000 638,188,895 (76.89%) 60,216,198 (7.25%) 31,594,907 (15.86%) Accept the bid (7.25% + 15.86%
= 23.11% < 30%)
Electrical 121,510,000 49,817,797 (41.00%) 14,482,868 (11.92%) 57,209,335 (47.08%) Reject the bid (47.08% > 30%)

architectural and electrical subprojects. Generally, when tronic file with a fulfilled unit price for each cost item,
applied to the two subprojects, the results of this alter- the steps of evaluating a lowest bid, and the explicit
native model closely resemble those of the original values of r1, r2 and TR.
model. For example, in the architectural subproject, the  The committee members entrusted with reviewing the
reasonable costs evaluated using both models are identi- explanations/evidence of the lowest bidder should be
cal. Moreover, the percentages of the suspicious costs carefully selected. Besides the representatives from
obtained from the original and alternative models are the architect/engineer of the project, the outside
7.57% and 7.25%, respectively, and the difference is only experts and union representatives should be consid-
0.32%. Additionally, the percentages of unreasonable ered as members of the committee. Moreover, audit-
costs obtained from the original and alternative models ing officers should be formally invited to witness the
are 15.54% and 15.86%, respectively. Notably, either the evaluation process for purposes of declaring it fair
original or alternative models are recommended pro- and open.
vided the required languages or clauses of the tendering  Furthermore, the reasons for accepting/rejecting a
documents have specified a particular model to be used unit price are suggested to be publicized to enable
for the bid evaluations. the evaluation experience (similar to historical court
cases) to be applied to future projects.
 The records (including the explanations and evidence
6. Discussions provided by the bidder) of those bid evaluation meet-
ings should constitute part of the contractual docu-
The proposed model was demonstrated to several ments, legalizing the model results.
industrial practitioners and governmental officers in  The proposed model can inspire bidders to recognize
Taiwan. Overall, those to whom the model was demon- the benefits of submitting accurate estimates, eventu-
strated strongly praised its ability to improve current ally improving their estimation skills.
public procurement practices in Taiwan. Also, during  The time required to evaluate the lowest bid should
this investigation, the following lessons were learned. be sufficient to execute the model steps. Based on
the experience of Wang [24], the time period may be
 Successfully implementing the preparation step of the 14–21 calendar days depending on the number of pro-
model depends on all biddersÕ submitting electronic ject cost items involved. Moreover, during this per-
spreadsheet files. However, submitting the bid pro- iod, the preparation step typically takes 2–3 days,
posal with an electronic file should be feasible based the evaluation step takes 2–4 days, and the clarifica-
on the experience learned from a preceding research tion step takes 10 to 14 days.
of Wang [24]. The research of Wang [24] focused on  One method of shortening the evaluation time is to
the phase in which the project was awarded to the reduce the number of cost items requiring evaluation.
lowest bidder, and established an electronic-based For example, the 1619 cost items in the electrical sub-
procedure to support review and adjustment of the project can be reduced to only include certain signif-
proposed unit prices of the lowest bidder. And none icant cost items that mostly govern project quality. If
of the bidders for several practical projects failed to those significant unit prices are evaluated as being
meet the requirement to submit an electronic file. reasonable, the potential adverse impact of a low
Additionally, a Taiwanese administrative order has bid can be limited. Typical significant cost items
suggested that a public construction project with a may include: (1) structure related (for example piling
budget exceeding NT $50,000,000 (US $1,666,667) and steel materials); (2) quality-related (for example
be procured by forcing the bidders to submit their inspector fees, laboratory fees, and drawing composi-
cost estimates in electronic format, further increasing tion fees); (3) governmental regulation-related (for
the feasibility of using an electronic-facilitated bid example environmental protection fees, waste dirt
evaluation process [24]. dumping fees, and construction insurance fees); and
 The tendering documentation should explicitly con- equipment-related (for example chiller, process
tain language or clauses to force the legal execution exhaust system, heating, ventilation and air condi-
of the evaluation process. For example, the language tioning, and fire protection system). Therefore,
should include the requirement to submit an elec- instead of preparing a long list of cost items in the
W.-C. Wang et al. / International Journal of Project Management 24 (2006) 156–166 165

electronic file, a short list containing only the signifi- der may appreciate this model if his unreasonably low
cant cost items can be used. Notably, the total bid bid price is caused by mistaken estimates. Therefore,
price (TBP ) in Eq. (2) should then be replaced with both project administrators and bidders should be
the sum of the costs of these significant items. willing to accept the proposed bid evaluation model,
 Fixing the costs offered (or fixing a minimum bid because it can support a win-win situation.
price) by suitable legal contracts and defining appro-
priate quality measures could perhaps help mitigate
the adverse consequences of unreasonably low bids.
However, in such a case, project administrators 7. Conclusions
should adopt a different bid-awarding method (such
as multi-criteria evaluation method rather than the This study proposes a unit-price-based model for
low-bid method discussed herein) to award project evaluating competitive bids. The developed model and
contracts, because the bid prices of all bidders will existing models have two similarities; (1) they all con-
be the same (when the costs offered are fixed) or will sider the bid prices submitted by other qualified bidders,
be very close (when the minimum bid price is fixed). and (2) they all allow the second lowest bid to continue
Hence, the bid price is not an appropriate criterion. to be evaluated if the lowest bid is rejected. However, the
Additional criteria should be defined for selecting a presented model differs in four main ways from the
winner. Hence, the feasibility of fixing the costs or existing models. First, in the proposed model, the assess-
minimum costs for bid evaluation should be ment of a lowest bid concerns unit prices rather than the
addressed by future research. total bid price (the total bid price is also used a criterion
 Because the key evaluation criterion, Dj, is calculated to indicate whether a lowest bid should be further eval-
based on the value of the estimated unit price of the uated). Second, the proposed model evaluates a low bid
owner (Oj), it is important to ensure the value of Oj based on the unit price data (submitted by the owner
is reasonable. In a poor estimation situation, under- and the other qualified bidders) obtained for the project
estimating is more likely than over-estimating, based of interest rather than from historical data. The use of
on experience of public construction projects in Tai- data concerning historical projects to evaluate bids can
wan [23]. Under-estimation reveals that the ownerÕs easily be challenged, primarily because the quality-re-
project ceiling price and associated unit prices (Oj) lated specifications of a particular cost item (even with
are low. Hence, the difference between the unit prices the same item name) in different projects may vary, so
submitted by the owner and the lowest bidder tends the corresponding unit prices of the cost item in various
to be small. Consequently, the unit price (Bj) submit- projects are also likely to vary. Third, in the developed
ted by the lowest bidder is unlikely to be treated as model, the evaluation and clarification steps identify
unreasonable, unless it is extremely low. Generally, which parts of a low bid are unreasonable. The decision
under-estimations favor the lowest bidders. To estab- is made according to whether the total unreasonable
lish a fair bid evaluation environment, the proposed cost exceeds the total bid price by a predefined threshold
model can be extended to consider only those cost ratio. Restated, the accept/reject decisions are not made
items that have acceptable ownerÕs unit prices. For based on statistical analyses. Fourth, the clarification
instance, if the ownerÕs unit price (Oj) is between the step in the proposed model enables the low bidder to de-
minimum unit price (minj) and the maximum unit fend suspicious unit prices. Therefore, the low bidder
price (maxj) submitted by other qualified bidders, also participates in the bid evaluation process. Eventu-
then Oj is acceptable. Otherwise, Oj is unacceptable ally, the low bidder will likely be satisfied with the deci-
and the corresponding cost item j should be excluded sion even if he is rejected. Notably, Government
from the bid evaluations. Procurement Law in Taiwan mandates such a clarifica-
 Although the execution of the proposed model is tion step in any proposed bid evaluation model [2].
straightforward, it should be presented to project The entire modeling process can be viewed as an elec-
administrators of public procurement entities and tronically facilitated evaluation of the cost allocation of
contractors via conferences, training programs and the low bid. Although the proposed model may not be
other means. Conferences and training programs developed based on complex mathematical theories, its
are often held to promote a new administration order practical implications can contribute to current public
or governmental regulations in Taiwan. Accordingly, procurement practice, as indicated by several industrial
the project administrators and contractors will be practitioners in Taiwan. After the lowest bid is consid-
familiar with the modeling steps when the model is ered reasonable (namely, the contract is won), the model
implemented. proposed by Wang can be used to revise the unreason-
 A low bidder can also be a beneficiary because the able unit prices to reasonable ones given the fixed total
execution of the developed model can help to clarify bid price (that is, to reshuffle the unreasonable costs)
ambiguous tendering documents. A rejected low bid- [24]. The finalized contractual unit prices then can serve
166 W.-C. Wang et al. / International Journal of Project Management 24 (2006) 156–166

as a mutually agreeable basis for handling future change [12] Dozzi SP, AbouRizk SM, Schroeder SL. Utility-theory model for
orders. Then, a fully electronic government procurement bid markup decisions. J Construct Eng Manage 1996;122(2):
119–124.
system may be established. [13] Moselhi O, Hegazy T, Fazio P. DBID: analogy-based DSS for
bidding in construction. J Construct Eng Manage 1993;119(3):
466–479.
Acknowledgements [14] Fayek A. Competitive bidding strategy model and software
system for bid preparation. J Construct Eng Manage 1998;
124(1):1–10.
The writers like to thank the reviewers for their care- [15] Chua DKH, Li D. Key factors in bid reasoning models. J
ful evaluation and thoughtful comments. Also, the writ- Construct Eng Manage 2000;126(5):349–57.
ers thank the National Science Council of Taiwan for [16] Chua DKH, Li DZ, Chan WT. Case-based reasoning approach in
financially supporting this research under Contract bid decision making. J Construct Eng Manage 2001;127(1):35–45.
No. NSC92-2211-E-009-005. [17] Herbsman ZJ. Ellis RD. Multiparameter bidding system innova-
tion in contract administration. J Construct Eng Manage
1992;118(1):142–50.
[18] Fayek A, Ghoshal I, AbouRizk S. A survey of the bidding
References practices of Canadian civil engineering construction contractors.
Canadian J Civil Eng 1999;26(1):13–25.
[1] Crowley LG, Hancher DE. Risk assessment of competitive [19] Ioannou PG, Leu SS. Average-bid method – competitive bidding
procurement. J Construct Eng Manage 1995;121(2):230–7. strategy. J Construct Eng Manage 1993;119(1):131–47.
[2] Public Construction Commission, Executive Yuan, Taiwan, [20] Alsugair AM. Framework for evaluating bids of construction
Government Procurement Law; 1998. Available from: http:// contractors. J Manage Eng 1999;15(2):72–8.
plan3.pcc.gov.tw/gplaw/egplaw/. [21] Lai KK, Liu AL, Wang SY. A method used for evaluating bids in
[3] Russell JS. Model for owner prequalification of contractor. J the Chinese construction industry. Int J Project Manage
Manage Eng 1990;6(1):59–75. 2004;22(3):193–201.
[4] Russell JS, Skibniewski MJ. Decision criteria in contractor [22] Holt GD. Which contract selection methodology? Int J Project
prequalification. J Manage Eng 1988;4(2):148–64. Manage 1998;16(3):153–64.
[5] Hatush Z, Skitmore M. Evaluating contractor prequalification [23] Wang WC. Supporting project cost threshold decisions via a
data: selection criteria and project success factors. Construct mathematical cost model. Int J Project Manage 2004;
Manage Econom 1997;15(2):129–47. 22(2):99–108.
[6] Lo W, Krizek RJ, Hadavi A. Effects of high prequalification [24] Wang WC. Electronic-based procedure for managing unbalanced
requirements. Construct Manage Econom 1999;17(5):603–12. bids. J Construct Eng Manage 2004;130(3):455–60.
[7] Carr RI. Impact of number of bidding on competition. J [25] Crowley LG, Hancher DE. Evaluation of competitive bids. J
Construct Eng Manage 1983;109(1):61–73. Construct Eng Manage 1995;121(2):238–45.
[8] Carr RI. Competitive bidding and opportunity costs. J Construct [26] Hiyassat MA. Construction bid price evaluation. Can J Civil Eng
Eng Manage 1987;113(1):151–65. 2001;28:264–70.
[9] Chapman CB, Ward SC, Bennell JA. Incorporating uncertainty in [27] Crowley LG. Robust statistical estimators for use within
competitive bidding. Int J Project Manage 2000;18(5):337–47. competitive bid data. J Construct Eng Manage 1997;123(1):
[10] Cagno E, Caron F, Perego A. Multi-criteria assessment of the 53–63.
probability of winning in the competitive bidding process. Int J [28] Skitmore M, Drew D, Ngai S. Bid-spread. J Construct Eng
Project Manage 2001;19(6):313–24. Manage 2001;127(2):149–53.
[11] Wanous M, Boussabaine AH, Lewis I. To bid or not to bid: a [29] Peurifoy RL, Oberlender GD. Estimating construction costs. 4th
parametric solution. Construct Manage Econom 2000;18:457–66. ed. New York (NY): McGraw-Hill; 1989.

You might also like