CRONOGRAMA DE AVANCE DE TRABAJOS DE CAMPO

PROGRAMADO EJECUTADO
FECHA # DIA # PUNTOS # PUNTOS # PUNTOS # PUNTOS
ZONA ZONA
TOTALES TOTALES COMPLETADOS FALTANTES
21/04/2023 1 6 15 7 17 9 8
22/04/2023 2 12 24 1 8 8 0
23/04/2023 3 8 12 7 8 8 0
24/04/2023 4 5 10 8 12 9 3
25/04/2023 5 7 17 12 25 25 0
26/04/2023 6 1 8 4 23 19 4
27/04/2023 7 13 27 13 32 32 0
28/04/2023 8 13 26 13 22 22 0
29/04/2023 9 4 23 8 3 2 0
30/04/2023 10 3 14 8 1 1 0
1/05/2023 11 9 7 9 9 9 0
2/05/2023 12 11 9 3 15 11 4
PTOS. PROGRAMADOS: 192 PTOS. EJECUTADOS: 155 8 80.73 %

11 9 9
5 y Saldo 4 14 14
2 14 14
3/05/2023 13 2 17 6 15 15
PTOS. PROGRAMADOS QUE FALTAN: 17 PTOS. A EJECUTAR: 52

TOTAL DE PUNTOS PROGRAMADOS: 209 TOTAL DE PUNTOS A EJECUTAR: 215