Question 1

Correct

Mark 1.00 out of 1.00

In which model the Project risk factor is considered?

a. incremental model

b. 
1. Spiral model.

c. Prototyping model

d.
Waterfall model.

Question 2

Correct

Mark 1.00 out of 1.00

In which model the Project risk factor is considered?

a. Waterfall model.

b. Prototyping model

c. 
1. Spiral model.

d. incremental model
Question 3

Correct

Mark 1.00 out of 1.00

An individual who plans and directs the work.

a. Project manager 

b. Stakeholder

c. Programmer

d. Team leader

Question 4

Correct

Mark 1.00 out of 1.00

Which of the options is correct for the prototyping model of software development?

a. both a & b

b. When requirements are well defined.

c. For projects with large development teams.

d. When a customer cannot define requirements clearly. 

Question 5

Correct

Mark 1.00 out of 1.00

__________ is not suitable for accommodating any change?

a. PROTOTYPE

b. SPIRAL

c. RAD

d. WATERFALL 