Professional Documents
Culture Documents
Ruling
For determination is the preliminary objection dated 20th June 2022 filed
by the first defendant. The objection on a point of law was to the effect
that the entire suit as filed is fatally defective and bad in law for the
reason that the same is time barred having been filed outside the
limitation period as provided by section 4(1) (a) of the Limitation of
Actions Act.
The first defendant prayed that the entire suit be struck out with costs.
The relevant contract in this case is the sale of land agreement dated 5th
November 2013 which required the first defendant to build the plaintiff
seven permanent rooms, erect a gated perimeter fence and to dig and
construct a pit latrine. The agreement did not provide for a completion
date so the same was to be within reasonable time.
The question then is when did the breach of contract occur? It was
argued that the breach occurred when the plaintiff realised that's the first
defendant was taking him for a ride. He then wrote to him a demand
letter dated 22nd May 2020 asking the first defendant to fulfill his part of
the contract within 14 days. The first defendant failed to honour the
demand notice and that is when the breach of the agreement arose and
the cause of action accrued.
Since there were no strict timelines within which two carry out the
constructions mentions in the contract then the contention that the suit
was time barred hereby fails. The cause of action arose only after the
discovery by the plaintiff of the first defendant's mischief, though this
must be proved during the hearing by evidence. I also know note that
this is an unpleaded issue.
This court now find that the preliminary objection has no merit and
procedure to dismiss it