PROJECT INSTALLATION SCHEDULE

RELAYOUT BUNDLE CONVEYOR LU 25 TO CP 13


Start Date : 03/04/2023 GL Name : Sulistiono
Finish Date : 13/05/2023 PM/PL Name : Melli Yantie

Apr-23
No Activity Duration (days) Resources Tools Material Status WEEK 14 WEEK 15 WEEK 17
2 3 4 5 6 7 8 9 10 11 12 13 14 15 23 24 25 26 27 28 29 30

1 Preparation Area 1 Hari


2 Dismantle support Conveyor 3 hari
3 Dismantle section conveyor 3 Hari
4 Dismantle Chain Conveyor 3 Hari
5 Dismantle Motor Conveyor 3 Hari
6 Dismantle Guide Rail dan accesoris Conveyor 3 Hari
7 Dismantle Kabel Tray Bundle Conveyor 2 Hari
8 Dismantle Isolator motor dan sensor Bundle Conveyor 2 Hari
9 Dismantle Kabel Existing 2 Hari
10 Install support Conveyor LU 25 to CP 13 4 Hari
Sulistiono (Leader), Satam (SIO
11 Install section conveyor LU 25 to CP 13 3 hari Tool Set, Scissor Lift,
Scissorlift,TKBT II), Dimas (TKBT II), Bundle Conveyor
12 Install Chain Conveyor LU 25 to CP 13 3 hari Hand Lift, Bor
Endang (TKBT II), Deden (Support), LU 25 to CP 13
13 Install Motor Conveyor LU 25 to CP 13 old 3 hari Tangan, Gerinda
Doni (Support)
14 Install Guide Rail dan accesoris Conveyor LU 25 to CP 13 3 hari
15 Install Kabel Tray Bundle Conveyor LU 25 to CP 13 3 Hari
16 Install Isolator motor dan sensor Bundle Conveyor LU 25 to CP 13 2 Hari
17 Wiring kabel motor dan sensor Bundle Conveyor LU 25 to CP 13 2 hari

18 Conection kabel motor dan sensor Bundle Conveyor LU 25 to CP 13 2 Hari


19 Progaming Bundle Conveyor LU 25 to CP 13 3 Hari
20 Trial Bundle Conveyor LU 25 to CP 13 3 Hari
21 Commissioning Bundle Conveyor LU 25 to CP 13 new 3 Hari
22 Gemba 2 Hari

Approval date : GL name :

( ) ( )