Daily Report 24/05/2023

Goldwind Vietnam
Tra Vinh V1-2 Wind Farm

S/N:W-Tra Vinh V1-2 -DR-2023-05-24


Audience: Global Confidentiality: 2 / Confidential Author: Gu He
Title: Daily Log Version: 1.0 Checked: Liu Dongming
Documentation Number: : 1.000.26.027 Reason for issue: First release
Approved: Dai Guandong
Approval process: Manual Issue Date: Sep 2016

The present document, its content, its annexes and/or amendments (the “Document”) has been developed by GOLDWIND SCIENCE AND TECHNOLOGY CO. LTD. (“Goldwind”) for information purposes only, and contains
private and confidential information regarding Goldwind and its subsidiaries, directed exclusively to its addressee. Therefore it must not be disclosed, published or distributed, partially or totally, without the prior written consent of
Goldwind, and in any case expressly indicating the fact that Goldwind is the owner of all the intellectual property. All the content of the Document, whether it is texts, images, brands, trademarks, combination of colours or any other
element, its structure and design, the selection and way of press. In particular (notwithstanding the general confidentiality obligation), the addressee shall not reproduce (except for private use), copy, transform, distribute or publish to any
other third party, any of the information, totally or partially.

24 May 2023

1. Basic Information
Average Wind Speed Availability
WTG Production (kWh) Generation Time (h) Failure Time (h)
(m/s) (%)*
01 43500.00 6.87 24.00 0.00 100.00
02 43684.00 6.92 24.00 0.00 100.00
03 44049.00 6.93 24.00 0.00 100.00
04 43725.00 6.91 24.00 0.00 100.00
05 43489.00 6.90 24.00 0.00 100.00
06 41832.00 6.79 24.00 0.00 100.00
07 41581.00 6.82 24.00 0.00 100.00
08 42136.00 6.79 24.00 0.00 100.00
09 42308.00 6.86 24.00 0.00 100.00
10 42740.00 6.73 24.00 0.00 100.00
11 42695.00 6.82 24.00 0.00 100.00
12 43793.00 6.95 23.59 0.00 100.00
Total Production (kWh) 515,532 Total Failure Time (h) : 0.00
*The availability data is exported directly from SCADA, which does not exclude external factors.

2. Power generation downtime information


2.1 Downtime from wind turbine
Item Description Period Hours Remarks
WTG03 Fault troubleshoot - (31357)Low Oil Level of Hydraulic Station 9:40 To 14:05 4.41 Turbine fault

2.2 Downtime from Owner & Grid & BOP & Unsafe condition & Schedule Maintenance & Contract TB condition(Adjust &Culling
downtime)
Item Description Period Hours Remarks

2.3 Others (Non-GW supplier)


Item Description Period Hours Remarks
Audience: Global Confidentiality: 2 / Confidential Author: Gu He
Title: Daily Log Version: 1.0 Checked: Liu Dongming
Documentation Number: : 1.000.26.027 Reason for issue: First release
Approved: Dai Guandong
Approval process: Manual Issue Date: Sep 2016

The present document, its content, its annexes and/or amendments (the “Document”) has been developed by GOLDWIND SCIENCE AND TECHNOLOGY CO. LTD. (“Goldwind”) for information purposes only, and contains
private and confidential information regarding Goldwind and its subsidiaries, directed exclusively to its addressee. Therefore it must not be disclosed, published or distributed, partially or totally, without the prior written consent of
Goldwind, and in any case expressly indicating the fact that Goldwind is the owner of all the intellectual property. All the content of the Document, whether it is texts, images, brands, trademarks, combination of colours or any other
element, its structure and design, the selection and way of press. In particular (notwithstanding the general confidentiality obligation), the addressee shall not reproduce (except for private use), copy, transform, distribute or publish to any
other third party, any of the information, totally or partially.

24 May 2023

3. Spare part consumption


WTG Serial no. Spare part name or type Amount Remark

4. Work content
Items Description

Availability for a wind turbine (Ai) shall be calculated on a production period basis
Ai = (1 – (TA –TB)/ TCT) X 100%
Where:
TCT = Total calendar time in hours of the calculation period
TA = Accumulated number of shut down hours
TB = Number of shut down hours caused by external factors (Due to grid, owner request, etc.)

5. Adjustment of Turbine Availability


WTG Ai (%)
01 100.00
02 100.00
03 81.63
04 100.00
05 100.00
06 100.00
07 100.00
08 100.00
09 100.00
10 100.00
11 100.00
12 100.00

On behalf of Tra Vinh V1-2 Wind Farm On behalf of Goldwind International Vietnam CO., Ltd
By: By:

Signature: Signature:
Adverse Weather Condition Limitation

Operation Limitation Remark


Crew Transfer Vessel Operation Maximum wave height > 1.5 m 1. The data shall be subject to the latest
Weather Plus Software.
10-meter Wind Speed > 10m/s 2. Related work shall be suspended
Visibility > 50m immediately where each of Limitation
occurs.
Wind Speed > 8m/s for Rotor & Blade lifting 1. The basic data shall be subject to the latest
Weather Plus Software.
Wind Speed >10m/s for other Main Components 2. The accurate data shall be subject to
lifting except Rotor & Blade 10 minutes average wind speed measured by
Crane and Barge (Service Lifting) Anemometer on the top of Crane Boom/Arm
or WTG nacelle.
3. Related work shall be suspended
Visibility < 150m immediately where each of Limitation
occurs.

Work inside WTG -Tower Wind Speed > 18m/s


1. The basic data shall be subject to the latest
Weather Plus Software& 100- meter
Work inside WTG -Nacelle Wind Speed > 15m/s
height wind speed.
Work outside the WTG - Tower Wind Speed > 12m/s 2. The accurate data shall be subject to
10 minutes average wind speed
Work outside the WTG -Nacelle Wind Speed > 12m/s
measured by Anemometer on the top of WTG
Work inside WTG -Hub Wind Speed > 10m/s nacelle.
Use of Davitt Crane inside Wind Speed >10m/s 3. Related work shall be suspended
Nacelle immediately where each of Limitation
occurs.
Use of Davitt Cranes on Tower Wind Speed >10m/s
platform
Detailed Response Hour
Time Type of Requests Supplier’s Response Time
Minor failures which could be settled via remote Immediately
reset.
Minor failures which could not be settled via Within 1 hour
Business Days within Normal remote reset.
Business Hours Major failures which takes time for work Within 2 hours
preparation (tools and equipment, transportation,
personnel, etc.) and
reporting works.
Business Days beyond Normal Operations in a remote method no later than 9:00 Within 2 hours
Business Hours as stand-by pm of each day.
During holidays and weekends as Operations in a remote method no later than 9:00 Within 2 hours
stand-by pm of each day.
Emergency conditions Major incidents which endangered the immediately
safety operation of personnel and WTG
Force Majeure Events and extreme Subject to Article 7 Report immediately
weather conditions
Other special requests as the case may be. longer Response Hour in case of special
request
Remarks:
Response refers to any actions taken by Supplier at the Supplier’s receiving any fault notification, such as
acknowledgement via e-mail, phone calls, corrective planning, etc.
Exhibit E - Availability Performance Standard
A. Availability. The availability of each Turbine Equipment for determining the Average Availability shall be calculated
on an annual basis as:
Availability (%) = ( 1 - (TA - TB) / TCT) x 100%
Where:
“TCT” shall mean the total calendar time in hours of the calculation period (i.e. for availability on an annual basis TCT =
8,760 hours, except for the first year where TCT shall be the actual hours starting from Service Commencement Date
(inclusive) until 31 December).
“TA” means the total annually cumulative number of shut down hours.
“TB” means the total annually cumulative number of the shut-down hours caused by the events and circumstances which are
not considered as Turbine Equipment errors due to one or more of the following factors:
(a) The Turbine Equipment is stopped or damaged due to an event or circumstance for which Supplier is not liable,
including events and circumstances of Force Majeure and event listed in Clause 2.14,

(b) Any stoppages ordered by Buyer or third parties which is not caused or attributable to the operation of the
Turbine Equipment,

(c) Activation of the operating state ‘Pause’ by, or on request from, Buyer provided that such activation or
request is not due to a fault in one or more of the Turbine Equipment supplied by Supplier pursuant to this

(d) Activation of the emergency stop button for safety reasons provided that such activation or request is not
due to a fault in one or more of the Turbine Equipment supplied by Supplier pursuant to this Agreement,

(e) Wind speeds outside the operational limits of Turbine Equipment as set forth in the Exhibit O,

(f) Temperature outside the operational limits of Turbine Equipment as set forth in the Exhibit O,

(g) Lightning or induction caused by lightning resulting in stoppage of the Turbine Equipment,

(h) Icing of the blades of one of more Turbine Equipment, resulting in stoppage of the Turbine Equipment,

(i) Technical standby events, such as untwisting of cables, pre-heating or cooling or auto-lubrication

(j) Scheduled maintenance. However, the total downtime of such Scheduled maintenance shall not exceeds sixty (60)
hours per year. For avoidance of doubt, the maximum “TB” allowed for the Schedule maintenance is 60 hours per year.

(k) Any electrical outage not caused by the Turbine Equipment or times where the electrical grid is not within
the Operating Parameters,

(l) Defects in the balance of plant as listed in Balance of Plant Specification, including without limitation the
sub-station, cables or other equipment not forming a part of the Turbine Equipment and its relevant work,

(m) Repair due to grid failures or grid fluctuations outside the parameters set out in the Exhibit O,
(n) Such hours where access to faulted Turbine Equipment is necessary and, due to adverse weather conditions or lack of
maintenance of roads, such access to the Turbine Equipment or the Project Site is unsafe or otherwise prevented, provided
that such lack of accessibility shall be subjected to Buyer’s approval. In this case, Supplier shall provide reasons and support
materials to Buyer for consideration. Buyer shall act reasonably considering safety and international wind industry practice
to judge and provide reasonable comments or approval to the Supplier in regards to counting such hours as “TB”,

(o) The performance of the Services (as defined in the Service and Availability Agreement) is suspended by
Supplier in accordance with the Section 10.4.2 of this Agreement,

(p) Inability to restart due to Buyer-caused communication line failure,

(q) Repair or maintenance delayed due to Buyer or any other Person other than Supplier Responsible Parties,

(r) Stoppage caused by the improper operation or maintenance by Buyer Responsible Parties,

(s) Force Majeure,

(t) Compliance with Wind Sector Management Requirements,

For avoidance of doubt, “TA” and “TB” shall be reset to zero (0) on 1st January every year. For the first year of Service, the
“TA” and “TB” shall be counted starting from the Service Commencement Date until 31 December.

B. Average Availability. The average availability of the Turbine Equipment (“Average Availability”) in the Project over a
specific period of time shall be computed as:
Average Availability = Where
Ai : is the availability of each Turbine Equipment pursuant to the calculation under this Exhibit E, and
n : is the number of Turbine Equipment in the Project.

C. Availability Liquidated Damages. If the Average Availability is below the Availability Warranty, the Availability
Liquidated Damages payable by Supplier to Buyer in accordance with Section 6.2 and 12.4 shall be computed as:

Availability Liquidated Damages =

“Actual Period Revenue” means the actual gross revenues received by Buyer for the sale of the energy
production from Project during the relevant period.