Checklist for Lift Plan

Location: ADP Date: 08/03/2022


Activity: Lifting of Silo Hopper Modules
Subjects/Details Yes/No Remarks

1. Document Approval Verification


a) Is there a Lifting permit approved in all perspective? Yes Will be obtained Before Execution
b) MS/RA is Approved? (Ref: No & Date of review to be included) Yes D0203-FST-EMH-PM-00005-AD
c) Is there a Lift Plan showing lifting arrangements? Yes
d) Rigging plan/Rigging calculations available? Is it reviewed and Yes
approved by contractor Rigging Engineer /Lift Supervisor
e) Sitting plan of crane available /pick-up and place down Yes
positions marked with measurements in drawing.
f) Load on sling calculated and included in the drawing? Yes
2. Competent Persons Details
a) Is there a Rigging Engineer/ PIC Appointed for managing lifting Yes
operations? (Competent Person Form Submitted)
b) Is there a Lifting Supervisor Deployed for this activity? Yes
(Competent Person Form Submitted)
3. Crane
a) Load Chart of the crane(s) attached. (Operating radius, boom Yes Details available with lift plan
height/angle and its limitations to be included in the load
chart)
b) Valid Load Test Certificate for the crane(s) by DM approved Yes
third party. (Attach a copy)
c) Crane(s) fitted with an anemometer? Yes
d) Wind Speed. (Maximum wind speed crane they can operate as Yes
per manufacturers manual)
e) Valid UAE Registration Certificate is available.? Yes
f) Crane Operators Manual available.? Yes
g) Calibrated SLI fitted and working.? Yes
4. Crane Operator(s)
a) Valid UAE Driving License (Heavy Tractor) Yes

b) Valid competency certificate by third party. Yes


5. Rigger
a) Third Party competency certificate for the rigger. Yes
b) Method of Communication Yes
6. Load Details
a) Load details and dimensions included in the plan? Yes Details available in lift plan
b) Centre of gravity identified and included in the drawing. Yes
c) Load and Lifting points are checked for safe slinging? Yes
d) Capacity of Lifting point identified? Yes
7. Load Analysis Tailing
Main Crane
Crane
a) Weight of the Load 181 181
b) Load on cranes (distributed) 181 109.84
c) Weight of Hook block and wire rope 11 2.7
d) Weight of the Rigging Accessories
5 2.5
(Chains, slings, wire ropes, shackles, spreader beams pulleys

Lift Plan Checklist. Rev D Page 1 of 3


Checklist for Lift Plan
etc.) including scaffolding
e) Total Load on Crane(s) 7(b+c+d) = 197 115.04
8. SWL Analysis
a) Counterweight used on crane(s) 150 + 65 165
b) Central Ballast /Super Lift Counterweight (if any) 250 NA
c) Main Boom Length 78 36.9
d) Fly jib/Luffing boom length and degree if angle (if used) 12 NA
e) Maximum Working Radius 22 11
f) Super lift Radius 18 NA
g) (SWL) Crane Capacity as per load chart 232 145.50
9. Crane Safe Factor
a) Crane Safety factor = (Total Load/SWL*100) =_____%.
84.91% 79.06%
(Crane Safety factor shall be less than 85%)
10. Lifting Accessories (Chains, slings, wire ropes, shackles, pulleys.
Etc.)
a) Capacity of the lifting gears? Yes Details available in lift plan
b) DM approved 3rd party certificate? Yes
c) Are the slings protected from sharp edges? Yes No sharp edges in this specific lift
11. Surrounding Environment
a) Overhead Obstruction.? Yes Precaution measures taken for
tower crane rotations
b) Underground Utilities/Excavation edges? No
c) Adjacent Structures and traffic – if any.? No
d) Ground Bearing Capacity determined, and details included in Yes Calculation attached for required
the plan? (Ability to hold the weight of the crane along with GBP in MSRA.
load) Same has been checked for
ground condition
e) Crane pre-use inspection carried out by Contractor Yes
12. Wind Speed and other weather conditions determined? Checked at the time of lift and lift
carried out if it is safe
13. Transportation plan (if required) Yes Attached with MSRA

Lift Plan Checklist. Rev D Page 2 of 3


Checklist for Lift Plan
Lifting accessories (Configured chronologically from the hook of the crane, top to bottom)

# Accessory Type Dimensions Quantity SWL (tones) Certificate Reference


1 slings 10 m Grommet 4 Nos 186.3 MT AFWR0671, AFWR0672, AFWR0673, AFWR0674
10 m Grommet 4 Nos 134.4 MT AFWR0890, AFWR0891, AFWR0892, AFWR0893
15 m Grommet 2 Nos 120 MT AFWR0511, AFWR0513
9 m Grommet 1 Nos 77.9 MT AFWR0470, AFWR0471
6 m Grommet 8 Nos 76.1 MT AFWR0721
18 m sling 18.5 MT AFWR-0651, AFWR-0652, AFWR-0653, AFWR-
0654, AFWR-0655, AFWR-0656, AFWR-0657,
AFWR-0658

2 Spreader Beam 9m 1 No 400 MT AFSB0111


8.79 m 1 No 400 MT AFSB0112
6m 1 No 250 MT AFSB0079
13.56 m 1 No 250 MT AFSB0086

3 Bow Shackle 2 Nos 400 MT AFSH1149, AFSH1150


2 Nos 300 MT AFSH10937, AFSH0940
4 Nos 125 MT AFSH0534, AFSH0535, AFSH0537, AFSH0538
8 Nos 25 MT AFSH0981, AFSH0983, AFSH0985, AFSH0989,
AFSH0992, AFSH1003, AFSH1019, AFSH1022
2 Nos 85 MT AFSH0521, AFSH0523
8 Nos. 17 MT AFSH0292, AFSH0304, AFSH0327, AFSH0330,
AFSH0333, AFSH0335 AFSH1323, AFSH1324
4 Chain Block 6m 4 Nos 20 MT T190600007, T1906000010, T190600011
T190600015
Additional Checks

Description to verify Person Signature


Assigned
1
3
5
7
8
9
10
11
12
13
14

Lift Plan Checklist. Rev D Page 3 of 3

You might also like