Professional Documents
Culture Documents
Carbon Trust Alistair Morris
Carbon Trust Alistair Morris
5
continents
400+
experts and consultants
20
years of experience in
sustainability consultancy
World leading offshore wind programmes
Market agnostic Market Specific
Generic solution for OSW Addressing specific market challenges
The Offshore Renewables JIP (ORJIP) National Offshore Wind R&D Consortium
Offshore Renewables JIP aims to reduce consenting and (NOWRDC)
environmental risks for offshore projects.
Prioritize, support, and promote research and development
activities that reduce cost and risk of offshore wind
The Integrator development projects throughout the U.S.
The Integrator is designed to examine the interplay between
offshore wind, existing infrastructure, and other technologies
to highlight opportunities for innovation investment.
Floating Offshore Wind R&D in Japan
Sustainability JIP (SUSJIP)
The Sustainability joint industry programme aims to
decarbonise offshore wind farm developments and
support developers to achieve net zero targets.
Floating Wind Joint Industry Programme
Objective: Overcome challenges and advance opportunities for commercial scale floating wind
Phase IV
Wind Turbine Numerical Modelling Phase IV
Access & Floating Floating Wind Technology
2020 Availability wind yield
Generators for Guidelines & Reference
Acceleration Competition
Floating Wind Standards Platform Designs
Development Competition
O&M Heavy lift O&M Tow-to-Port Mooring Systems in
2019 Offshore Maintenance Challenging
Maintenance Environments
Phase II
Heavy Lift Turbine
Monitoring
2018 & Inspection
Offshore Requirements &
Operations Foundation Scaling
Phase I
Electrical
2017 Systems
Mooring
Systems
Infrastructure
& Logistics
Stage 1
• Currently all the global installed capacity has been assembled on the quay side
and then towed to their respective site location from port.
• The installation process for a floating turbines varies with both substructure type
Kincardine turbine tow out
e.g. Barge, Semi-Submersible, Spar and TLP and material e.g. concrete or steel.
7
Floating Installation Challenges
WTG
A number of factors will be need to be considered in context to larger scale floating wind turbine installation.
8
Floating Installation Challenges
Ports
• Trends across both floating and bottom fixed offshore wind which are likely to
have significant consequences upon port development:
• The increase in size and number of turbines will require more space for
components during installation.
• Greater number and variety of specialist vessels will be required to support
and install turbines, floaters and anchors/mooring lines.
wind farms.
9
Floating Installation Challenges
Anchors and Mooring Lines
• Optimising and developing the mooring lines top connection to the floater will help to
increase the efficiency during both installation and through-life maintenance.
• Currently there appears to be a limited capacity and availability of anchor laying vessels
across the market and this will have an impact upon installation.
• Increasing the understanding around mooring line development and the different respective
materials available will impact upon the installation strategy used.
• The FLWJIP programme is currently running a project titled Moorings System Redundancy,
Reliability and Integrity (MRR&I) with the aim to understand if high failure rates seen in other
sectors should be applied to floating offshore wind and how best the industry can correctly
capture and quantify potential floating wind-specific failure within project planning.
Hywind Scotland
10
Stick Building of Turbines On-Site (SBOS) Project:
Overview
• The aim of this project was to identify and assess the innovative methods to
permit WTG assembly at floating offshore wind farm sites.
• The project has looked to identify enabling technologies that allow for
assembly and installation of WTGs on-site using a floating installation
vessel. As well as the required operational procedures for stick-building on
site.
Kincardine turbine installation
• It has helped understand the different installation methods that can be used
for floating WTGs in context to their versatility and potential to reduce costs.
11
Stick Building of Turbines On-Site (SBOS) Project:
Summary
WP1 Technology WP2 Scenario WP3 Installation WP4 Hydrodynamic WP5 Conclusions &
Identification Definition Methodology Modelling Recommendations
1. Narbonne, France
Monohull installation, shuttling components Benign Weather
2. Strait of Taiwan
Semi submersible crane vessel installation
Moderate Weather
with one critical lift, shuttling components
3. Morro Bay, US
Complete installation solution using an
installation vessel, feeding components Harsh Weather
12
Stick Building of Turbines On-Site (SBOS) Project:
Summary
Hydrodynamic
• Five installation scenarios for floating-to-floating WTG installation were analyses
developed. The installation scenarios consisted of the following activities:
• Onshore preparation – which considered the component load out at Static models
marshalling facility
• Transport – which considered the deck layout, transit route and duration
Dynamic
• Offshore installation – which considered the load in, WTG assembly and Analyses
WTG installation (frequency
domain)
• For the five installation scenarios the different transportation and installation Limit
steps were identified. With a specific focus on lift-off, hoisting and set-down. Definition
• As part of the installation scenario development the operational steps and Operability
durations were defined which helped to identify the most critical steps for
hydrodynamic analysis.
Workability
• Three installation scenarios were then shortlisted based upon the clearances
and modelled through hydrodynamic analysis to assess their respective
operability and workability.
13
Find out more
Public resources and social media:
May 2018 June 2020 June 2021 July 2021 July 2022
15