RENCANA ANGGARAN BIAYA 1/1

PEKERJAAN SIPIL DAN ARSITEKTUR AREA MESIN LINE#2 & AREA UTILITIES
KONTRAK C-2102

NO JENIS PEKERJAAN VOL. SAT.

14 GANTRY HOIST CRANE CALENDER


a HB250x250 852.34 kg
b HB200x200 544.09 kg
c INP 250x125 1,127.96 kg
d WF 200x100 - kg
e Pipa SCH40 6" 332.40 kg
f Plat 16mm 45.22 kg
g Plat 12mm 15.07 kg
h UNP 150 224.00 kg
j Cat besi 3,141.08 kg