Professional Documents
Culture Documents
712201
Philips contact
Telephone
e-mail
Important information
Important!
This package provides only indicative information intended for use in very early project phases to
provide an impression of room set ups and required site preparation. Any information, figure or value
shown is not necessarily applicable, accurate and/or up-to-date. Your Philips contact can arrange
Room Designs and Site preparation specifications for your specific situation.
1.1 Purpose
The Site preparation specifications should provide all required information to the customer and relevant
contractors to enable the site to be prepared to the necessary quality and timescales ready for delivery and
installation of the equipment.
1.2 Roles
Within this document the following groups are referred to:
• Philips: Equipment manufacturer, equipment supplier
• Customer: Purchaser, end user
• Contractor / Third party: member of the Architect, Engineers & Contractors (AEC) community, hired
by either the customer or Philips
1.4 Responsibilities
The customer is responsible for any classification of the room in relation to its intended use, and must notify
Philips Healthcare project manager and the contractors of any additional specifications this may include.
The customer remains responsible for all works that are necessary for site preparation, unless works that
are included in the Philips contract, in which case the term "customer" can be read as "Philips contractor".
The customer should ensure that the work areas are lockable with limited access. Philips Healthcare should
have access to the areas (via keys / access codes) prior to the start and during the installation.
The customer shall advise Philips of conditions at or near the site which could adversely affect the carrying
out of the installation work and shall ensure that such conditions are corrected and that the site is fully
prepared and available to Philips before the installation work is due to begin.
The contractor and or architect must ensure that the works carried out in line with this document comply
with local regulations unless more strict requirements are set out by this document or defined by the
customer.
General Page 2 of 21
1.5 Site readiness
We expect the site of the installation to be completely finished, clean, dry, and clear of contractors and
meet the requirements defined in this document before the equipment delivery / start of the installation.
Failure to meet these requirements could result in delays to the timelines, additional charges etc.
Note!
Equivalents for lead (1 mm Pb)
There are other materials which can be used for protection as an alternative to lead (however this
must be specified by the local radiation protection authority)
• 8 cm concrete: 2.2 g/cm3
• 11 cm brick: 1.6 g/cm3
General Page 3 of 21
1.7 Equipment details
1.7.1 Equipment and delivery specifications
The table lists the basic specifications for the ordered equipment.
a
IC N - 1403- 712- GG -01- 01-A
W D
General Page 4 of 21
Vertical stand 2 (VS2) tilted
Other equipment
Width (W) Depth (D) Height (H) Weight Notes
[mm] [mm] [mm] [kg]
Generator (M-cabinet CXA Pro)
Packed 631 843 1274 205 Generator
Packed 495 140 1000 34 Wall box
Installed 702 488 980 136 Generator
Installed 488 135 1900 20 Wall box
Operator' s console
Packed 630 565 370 17.5 Eleva Examination Control A
Packed 555 465 358 16.0 AWS-TX
Installed 529 207 359 8.4 Eleva Examination Control A
Installed 215 276 449 14.1 AWS-TX
Varian (PaxScan) detector
Packed - - - - -
Installed 460 16 385 3.6 Varian Detector
Installed 220 160 34 1.0 Varian Battery charger
Installed 175 205 65 1.1 Wireless access point
General Page 5 of 21
Delivery details
The delivery routes will be checked in advance by the Philips Healthcare project manager.
Requirement
The table lists the critical requirements for delivery. In case of any potential problems with these
requirements please contact Philips Healthcare project manager.
Requirement Specification
A
Y
IC N - V -1403- 000-GG-01- 01-A
General Page 6 of 21
Equipment Noise level [d B(A)]
(operational) (standby)
Ceiling suspension (CSV2) ≤ 55 ≤ 55
with longitudinal carriage
Patient table (DiDi TH 750mm) - -
Vertical stand 2 (VS2) ≤ 55 ≤ 55
X-ray generator (M-cabinet CXA Pro) < 52 -
(at 1 m distance 1 m above
floor)
General Page 7 of 21
2 Building
Building Page 8 of 21
2.2.2 Floor requirements illustrations
Illustration(s)
Refer to the chapter Drawings, sheet Floor provisions for the site specific drawings.
Ceiling clearance
Lighting fixtures must be placed in such a position that they are not obscured by equipment or its
movement, or interfere with the movement of Philips equipment (e.g. monitor suspensions) or otherwise
adversely affect the equipment.
C
IC N - V -1403- 746-GG- 02-01- A
Building Page 9 of 21
2.3.2 Ceiling requirements illustrations
Illustration(s)
Refer to the chapter Drawings, sheet Ceiling provisions for the site specific drawings.
ICN-V-1403-000-GG-02-02-A
A B
A complete set of fixing material to mount the Philips equipment to the anchor rails (including isolation /
installation / insulation plates and shims) is part of the delivery. Further details can be seen in the drawings.
If Beam Clamps are used to fix Unistruts/Marstrut to steelwork, a suitable shake proof type must be used.
The load bearing struts are indicated in the drawings. When applicable extra struts/profiles are indicated to
serve as frame work for suspended ceiling tiles.
The contractor must take measures (like tagging) to prevent drilling and/or screwing in the lower metal
framing channels.
Building Page 10 of 21
2.4.2 Wall requirements illustrations
Illustration(s)
Refer to the chapter Drawings, sheet Wall provisions for the site specific drawings.
IC N - 1403- 742- GG -02- 01-A
Building Page 11 of 21
3 Electrical
3.2 Power
3.2.1 Power specifications
The power specifications are determined by the X-ray generator which generates high voltage for the X-
ray tube in the equipment.
3.2.2 Power quality
The power supply to the system must meet the following voltage quality and frequency requirements.
Requirement Specification
Electrical Page 12 of 21
3.2.5 Earthing
Note!
The earth connection requirements for medical equipment exceed those for ordinary electrical
installations. The contractor must ensure that local regulations are followed closely.
In all situations, the contractor must ensure that there is one (1!) earth reference terminal (ERT) for all
Philips supplied equipment, and it should be connected via a removable link (A) to the customer earth.
A
ERT
Philips
ICN-V-1103-000-GG-03-C
Typicallayout of an EarthReferenceTerminal
3.2.6 Lighting & Small Power
The contractor must ensure that sockets for the Philips equipment only are provided as per the drawings.
3.2.7 Safety mechanism requirements
The Philips system is equiped with several additional safety provisions. The use of these provisions is
regulated by local legislation. Philips Healthcare advises to install the safety provisions at all times to reach
maximum safety for personnel and patient.
B D C
+24 V
+24 V
A
ICN-V-1403-742-GG-03-01-A
230 Vac
Electrical Page 13 of 21
X-ray ON warning lights
For the X-ray on warning light(s) (A), the system is provided with a relay contact in the generator which
can switch a maximal 6 A and can be connected to maximum 230 V as shown in the illustration above.
The contractor must ensure that the lamp provided has a response time between 1 - 1000 msec.
The contractor must ensure that the X-ray on warning lights are mounted as per the drawings and cables
are routed to the X-ray generator. It is allowed to use Philips dedicated cable ducting for this purpose.
The Philips engineer will connect the cables to the X-ray generator (D).
Electrical Page 14 of 21
3.4 Networking specifications
3.4.1 Local Area Network (LAN)
The contractor must ensure that the network connection points are supplied, fitted and connected as per
the drawings.
The contractor must work with the customer to ensure that a connection to the hospital network is
available, prior to the start of installation, at the network connection points as shown in the drawings.
The customer must allocate an IP address and other network specific information requested by Philips, for
each network connection shown in the drawings.
Further information and guidance on LAN setup and requirements will be provided by the Philips
Healthcare project manager.
3.4.2 Remote Service Network (RSN)
The system needs one or more Ethernet RJ-45 wall sockets with connection to the hospital network as per
the drawings. This connection needs to be setup according to the following specifications.
Important!
RSN Details
Please provide the Philips project manager in advance with the details.
• Full duplex network connection, 10BASE-T, 100BASE-T or 1000BASE-T
• Local f ixed IP address
• Corresponding subnet mask
• Corresponding gateway
• Minimum required speed: 128 Kbit/s
Electrical Page 15 of 21
4 Mechanical
Requirement Specification
Examination room
Temperature +18 to +30 °C
Relative humidity 30 - 75% (non-condensing)
Control room
Temperature +18 to +35 °C
Relative humidity 20 - 75% (non-condensing)
Technical room
Temperature +10 to +40 °C
Relative humidity 30 - 75% (non-condensing)
The following heat outputs of the Philips equipment must be taken into account, please refer to the
drawings for the precise locations.
(operational) (standby)
Ceiling suspension (CSV2) 425 (incl. tube) 50 (CSV2)
with longitudinal carriage
Patient table (DiDi TH 750mm) 150 (excl. detector) -
Vertical stand (VS2) wall mounted 180 130
X-ray generator (M-cabinet CXA Pro 50/65 kW) < 100 60
Eleva Workspot (AWS-TX + EEC-A) 230 (max) 20
4.4 Water
The Philips equipment has no requirements in this discipline.
Mechanical Page 16 of 21
4.5 Sewerage
The Philips equipment has no requirements in this discipline.
4.6 Sprinkler
The Philips equipment has no requirements in this discipline.
4.8 Gases
The Philips equipment has no requirements in this discipline.
Mechanical Page 17 of 21
5 Environmental protection
5.1 X-ray
5.1.1 X-ray energy
The local radiation protection authority can use the following data to determine the correct
protection requirements.
Parameter Specification
Tube current 1 - 900 mA
Tube voltage 40 - 150 kV
mAs product 0.5 - 850 mAs
Exposure time 1 ms - 6 s / 16 s
Exposure frequency ≤ 12 exp./s
Drawings Page 19 of 21
7 Annex
Philips
Customer
PPCB
PCB
RCD2
F4
Spare
ECB
Incoming power
L1,L2,L3,N
RCD1
M-CXA Pro
Generator
cabinet
GS1
F3
K1
L3
F2
L2
L1
K1
F1
Electrical panel
PE
EPO
EPO
ON/OFF
pushbutton
Requirement Specification
Annex Page 20 of 21
Colophon
Philips Healthcare
A business of Royal Philips N.V.
www.philips.com/healthcare
healthcare@ philips.com
www.healthcare.philips.com/main/support/support-for-your-site/site-planning/index.wpd
Page 21 of 21