Professional Documents
Culture Documents
JKT05 SPC ARC 00001 C Architectural Specifications JKT05
JKT05 SPC ARC 00001 C Architectural Specifications JKT05
JKT05
Architectural & LEED General
Specifications
CLIENT X
Reference: 512127
Document No.:
512127-JKT05-SPC-ARC-00001
Revision: C
2021-10-15
Document control record
Document prepared by:
PT Aurecon Indonesia
Revenue Tower, 25th Floor,
Unit 25-113, District 8
Jenderal Sudirman Kav. 52-53,
SCBD Lot 13,
South Jakarta 12190
Indonesia
Document control
Client Client X
Current revision C
Approval
Title Title
Project number 512127 File Architectural & LEED General Specification 2021-10-15 Revision C
SS001_Contents
JKT05 SS1/1
OCTOBER 2021 ISSUED FOR PERMIT SECTION 1 - CONTENTS
SPECIFICATION
OCTOBER 2021
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
SS002_Suspended Ceiling
JKT05 SS2/1
OCTOBER 2021 ISSUED FOR PERMIT SECTION 2 - SUSPENDED CEILING
SECTION 2
2.1 GENERALLY
Suspended ceiling systems used in the Works shall be of proprietary design, proven
in use and erected to approval by the manufacturer/supplier's erection service.
Proprietary fire rated ceiling shall be constructed to specialist supplier’s
specifications.
All components shall be compatible with each other and when assembled, the
system shall form a functional and aesthetic whole.
Upon completion of the ceiling works, remove debris and excess materials, clean or
replace dirty or damaged material and leave the work clean and neat.
All components of ceiling panels and suspension systems in exterior, non air-
conditioned or exposed location to be external quality, humidity resistant and non-
ferrous.
The suspended ceiling includes the suspension system, acoustical materials, ceiling
boards, stainless steel trimmers/framing/lighting trough, egg crate diffusers and
aluminium trimmers/framing for the integration of lighting and ventilation
components.
The Contractor shall provide all penetrations for ducting, diffuser grilles, fire
protection services, cables etc trim and seal around all ducts and registers
penetrating the ceiling.
The Floor to ceiling heights shown on the drawings must be achieved and the
contractor will have allowed all necessary measures in the services and structure to
maintain the specified ceiling heights while meeting all other requirements of the
contract drawings and specifications.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS2/2
OCTOBER 2021 ISSUED FOR PERMIT SECTION 2 - SUSPENDED CEILING
At least 90% of all ceilings, by cost or surface area, meet the VOC emissions
evaluation, OR inherently nonemitting sources criteria, OR salvaged and reused
materials criteria.
2.2 STANDARDS
Unless otherwise agreed by Architect, ensure all of the works comply with the
relevant requirements of the Standards and Codes listed below or referenced in the
body of the Specification. Alternative Standards and Codes may be submitted to the
Architect provided it can be demonstrated that the alternative Standards and Codes
comply with the requirements of the standards specified. All standards and Codes
quoted are the current version, unless specific year references are noted.
Other Standards
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS2/3
OCTOBER 2021 ISSUED FOR PERMIT SECTION 2 - SUSPENDED CEILING
Co-ordinate the ceiling works particularly the interfacing with the following trades
c) The air-conditioning duct/grilles, light trunking/ fittings and other M&E services
will be done by other specialist contractors.
The Contractor will also have to liaise and co-ordinate with the other contractors on
the work sequence and structured cabling works, building construction works, etc.
The Contractor is required to submit shop and detailed drawings for the ceiling for
the Architect's approval before proceeding with the works.
Although the ceiling layout is indicated on drawing, this is only indicative and the
Contractor must submit a larger scale plan showing the exact layout after
coordination between MEP, structure and any specialist services and to indicate any
cutting of ceiling boards/panels.
2.5.1 Samples
Contractor to submit samples of part of each ceiling showing face materials, and
grid supports and technical data.
In addition, the contractor is required to submit fire and acoustic test certificates and
assessments for each type of ceiling assembly, where applicable.
2.5.2 Mock-ups
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS2/5
OCTOBER 2021 ISSUED FOR PERMIT SECTION 2 - SUSPENDED CEILING
2.6 TEST
Unless otherwise directed, conduct tensile pull out test for all ceiling works at one
location per 5 floors of building. At least one pull out test shall be conducted per
project. The location of pull out tests shall be selected by the Architect.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS2/6
OCTOBER 2021 ISSUED FOR PERMIT SECTION 2 - SUSPENDED CEILING
Conduct inspection of plasterboard ceiling after operating building M&E services for
48 hours to observe for wet or damp locations due to leakage or condensation.
Mark and annotate on a relevant reflected ceiling plan drawing with description of
causes for moisture or damp.
Suspended ceiling system(s) for the project may consist of one of the following types:
b) Metal ceiling: Modular, metal suspended ceiling either in tiles or as planks (strips)
on concealed suspension systems.
Where described in the schedule, mineral board ceiling shall be manufactured from
acoustic mineral fibre or high-density resin bonded glass fibre finished with
microporous white textured surface and fully sealed painted edges or equal and
approved.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS2/7
OCTOBER 2021 ISSUED FOR PERMIT SECTION 2 - SUSPENDED CEILING
The boards shall meet the Standard for Total Moisture Resistance (TMR) in
accordance with ISO 461 and shall withstand relative air humidity exposure of
b) Thermal Insulation
Fire resistance shall meet with FSSD or local Fire Bureau requirements.
Mineral wool wire reinforced mattress cavity barriers shall be installed where
necessary as per fire safety report/ local fire regulations.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS2/8
OCTOBER 2021 ISSUED FOR PERMIT SECTION 2 - SUSPENDED CEILING
d) Sound Absorption
The absorptive boards and reflective boards shall achieve sound absorption
Class A and C respectively tabulated below in accordance with the BS EN
20354, obtained by testing in accordance with the room method (EN ISO 354).
Boards shall be laid in accordance with the ceiling layout plans.
Absorptive Boards with 200mm Air Gap
The method of testing shall conform to EN ISO 354 and carried out by any of
the following accredited laboratories:
The performance of the combined absorptive and reflective ceiling system shall
meet the reverberation time (RT) criterion recommend by Acoustical society of
America or Building Bulletin 87 (UK). Contractor shall ensure that the RT does
not exceed 0.8 seconds (mean of 500Hz and 1000Hz) in an unoccupied
classroom.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS2/9
OCTOBER 2021 ISSUED FOR PERMIT SECTION 2 - SUSPENDED CEILING
f) Suspension System
[Applicable to proposed Ceiling Type 1 & 2]
Suspension system shall be of Armstrong Ceiling system Ultima+ Op or
approved equivalent, unless otherwise specified by Architect. The ceiling shall
conform to BS EN 13964.
Ceiling Type 1 :
Ceiling Type 2 :
• Suspension System: Prelude Grid Square Lay-in, 24mm exposed tee grid;
Colour to match
a) Joint-less systems
Exposed Ceiling grid & tee system colour shall match with selected ceiling
board colour, unless otherwise stated by Architect, to be submitted for
Architect’s approval.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS2/10
OCTOBER 2021 ISSUED FOR PERMIT SECTION 2 - SUSPENDED CEILING
The boards shall be suitable for clean and hygienic environment usage, tested
and achieve cleanroom class M3.5/100 according to US Federal Standard
209E. The boards shall also conform to the Swedish Asthma and Allergy
Association Certification, or equivalent local Standards.
h) Environmental Impact
At least 90% of all ceilings, by cost and surface area, meet the VOC emission
evaluation or inherently non-emitting source criteria.
The ceiling product category includes all ceiling panels, ceiling tile, surface
ceiling structures such as gypsum or plaster, suspended systems (including
canopies and clouds), and glazed skylights.
The board surface shall withstand and can easily be cleaned by dusting,
vacuum, dry cloth or damp sponge.
The fibrous plaster ceiling shall be 12.5 mm thick and to be moisture resistant and
external quality. Where ceiling is used externally, such as walkways, corridors or car
porches, submit waterproofing additives for water resistance.
a) General Composition
Fibreglass shall be Siland sized Type C glass, filament dia. 19 ±0.8 microns.
b) Perimeter Treatment
At all perimeter interfaces use aluminium profile to stiffen edge, either straight
or curved as necessary. Edging material shall be capable of receiving skim
coat in a manner consistent with a ceiling soffit.
Jointing of perimeter trims shall be carried out neatly without lipping and
twisted. Use mitred joints at all internal and external corners and the longest
lengths of trims available from the manufacturer to keep immediate butt joints
to a minimum. Coordinate joints of straight runs to coincide with grid locations.
Ignitability Index 0
Smoke Develop 0
Fire Rating 0
d) Workmanship
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS2/12
OCTOBER 2021 ISSUED FOR PERMIT SECTION 2 - SUSPENDED CEILING
Perimeters to have 50 x 50mm wall plate at joist ends power fixed to wall at
approximately 600mm centres.
i. Where fibrous plaster ceiling are fixed for ceiling by grouting over joists or
battens the background shall be substantially even and free from any
protrusions liable to adversely affect the fixing of the sheets.
ii. Fibrous plaster ceiling shall be fixed to joists or battens with 40mm
temporary pin-up nails, ensuring that each sheet finishes level with the
adjacent sheets. Perimeter of ceiling may be permanently nailed with
25mm galvanised clouts, ensuring such nailing points will be covered by
Plasterglass or other cornice moldings.
iii. Using approved Casting Plaster mixed with water at the ratio of two
plaster to one of clean water by volume and Fibreglass Strands, the
Plasterglass sheets are then grouted over joists or battens. Each grout to
be approximately 35mm wide and are to be spaced at approximately
450mm along each joist. Continuous grouts are to be applied to all joints.
g) Flush Joints
Where grouting is not applied at the back of the flush joint, the joint shall be
kept open 10mm to facilitate caulking with approved Bonding compound from
the face side. The joint is then trowelled with Stopping Compound to leave a
flush surface in true relationship to the adjacent surface.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS2/13
OCTOBER 2021 ISSUED FOR PERMIT SECTION 2 - SUSPENDED CEILING
Where described in the schedule, the ceiling system shall comprise of Firestop
boards suspended from hanger systems, cross rails, and furring channels. The fire
rating is provided by the complete system.
Ceiling Type 3 :
• Suspension System :
• Weight : 54kg/m2
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS2/14
OCTOBER 2021 ISSUED FOR PERMIT SECTION 2 - SUSPENDED CEILING
Ceiling Type 4 :
• Suspension System :
• Weight : 28.2kg/m2
Use premixed plastering compound to achieve level surface on the soffit of RC slabs
and beams where there is no suspended ceiling. Completed skim coat surface shall be
suitable to receive paint. Use proprietary edge beading to all corners and edges.
a) Material
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS2/15
OCTOBER 2021 ISSUED FOR PERMIT SECTION 2 - SUSPENDED CEILING
aggregates and/or fibres for added adhesion and bulk. Unless otherwise agreed
apply one finishing coat 3mm thick plaster conforming to BS 1191 class C & D.
b) Fire Performance
The suspended resin-bonded glass fibre acoustic ceiling board ceiling shall be semi-
concealed system. The ceiling boards shall be of 1200 x 600 x 20mm thick high
density (120kg/m3) resin-bonded glass fibre.
The boards must be able to withstand continuous exposure to high humidity without
causing visible sagging, warping or de-lamination under our extreme local conditions.
The visible surfaces and edges of the ceiling boards shall be factory painted finish in
White (F157) colour. The painted surface shall be partly porous giving good air
permeability for excellent sound absorption properties. The back of the boards shall
be faced with glass tissue.
When necessary, the surface of the boards can be easily cleaned using vacuum
cleaner, dry cloth or damp sponge.
a) Acoustic Performance
The sound absorption coefficient shall be in conformance with ISO 354 and are
measured as follows:
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS2/16
OCTOBER 2021 ISSUED FOR PERMIT SECTION 2 - SUSPENDED CEILING
b) Fire Characteristics
The ceiling boards shall achieve Class 0 (zero) rating tested in accordance
with BS 476: Part 6 & 7; or Surface Burning Characteristics of Maximum
25/450 flame spread/smoke developed index when tested in accordance with
ASTM E 84.
c) Suspension System
The suspension system shall be standard 15/24mm T-grid hot dip galvanised
steel or galvanised steel finish with pre-coated low sheen white colour capping
and shall be supported by 12/14 gauge hanger wires or other equal and
approved suspension system.
d) Installation System
e) Perimeter Trim
f) Accessibility
g) Installation
Examine the substrate and conditions under which work of this section will be
performed. Do not proceed until conditions detrimental to timely and proper
completion of the work have been rectified.
Confirm the positions of all exposed building services e.g. light fittings, fire
protection systems, speakers, air supply and exhaust grilles etc prior to setting
out the ceiling grid.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS2/17
OCTOBER 2021 ISSUED FOR PERMIT SECTION 2 - SUSPENDED CEILING
The ceiling panels shall be stored for at least 24 hours before installation in the
rooms in which they are to be installed to allow for temperature adjustment.
The relative humidity of the area to be installed shall not exceed 90%.
Ceiling panels shall be neatly and accurately cut. Panels shall be placed to fit
snugly into the main and cross tees, with no space between the bottom of the
panels and the grid system, and without gaps or panel edges showing in the
completed installation
Prior to commencement of ceiling works, the Contractor shall lodge with the
Architect a 5-year indemnity against defects in the ceiling works.
Under this indemnity, the Contractor will be required to make good any defects and
failure in the materials or installation and will be responsible for any consequential
loss attributable to any failure in the ceiling works during the warranty period.
If in the opinion of the Contractor, the Specifications are sufficient for him to give the
specified indemnity then the Contractor shall allow in his tender for upgrading the
Specifications as necessary to enable him to so indemnify.
Where a/c diffuser grilles, return air grilles and recessed light fittings etc, occurs,
provide recessed opening in suspended ceilings including all additional frames to
suit. These shall be included in the rates for the ceiling.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS2/18
OCTOBER 2021 ISSUED FOR PERMIT SECTION 2 - SUSPENDED CEILING
The Contractor shall co-ordinate with the ceiling specialist to ensure that the installed
suspended ceilings are not unnecessarily taken down, altered or damaged due to the
omission of work in the ceiling space.
The contractor shall verify all measurements and dimensions at the job site and shall
co-ordinate and schedule his work with the work of other specialist contractors
affected by his installation, with particular attention to the Mechanical and Electrical
Trades.
All access panels and inspection hatches shall be constructed by the Contractor as
required by the Architect/MEP drawings. Access panels/inspection hatches shall
have approved framing, ironmongeries and finished with matching colour of the
whole ceiling.
All ceiling panels to be covered by a foil protecting them during delivery, unpacking
and installation.
Ceiling panels and all components of the suspension system shall be delivered to the
job site in the original packages of the manufacturer.
All material shall be stored in dry areas where the temperature and humidity will be
maintained during the building occupancy.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS2/19
OCTOBER 2021 ISSUED FOR PERMIT SECTION 2 - SUSPENDED CEILING
2.13 INSTALLATION
The installer must examine the conditions under which the ceiling work is to be
performed and notify the contractor of any unsatisfactory conditions before
proceeding.
The Contractor shall maintain and provide sufficient protection for the completed
ceiling until handing over at completion. Until such time the Contractor shall be
responsible for and shall replace and/or make good any soils, dents or defacements
to the finished work at his own cost.
2.15 MAINTENANCE
The Contractor shall provide 5% spares of each of the ceiling type used in the project
for maintenance stock, and 2% of exposed suspension system components. It
should be delivered in manufacturer’s standard packages clearly marked with the
contents.
2.16.1 The metal ceiling panels to be used within corridors & specified areas are to be
Hunter Douglas Lay-in Panels or any other approved equivalent.
2.16.2 Specifications
The panels are simply laid on the exposed suspension grid system, allowing simple
and easy access to the plenum. This is especially useful for areas that require
frequent maintenance.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS2/20
OCTOBER 2021 ISSUED FOR PERMIT SECTION 2 - SUSPENDED CEILING
Architect)
Colour White and other colours to be approved by the Architect
2.16.3 Perforation
The back of the perforated panels come with acoustic material, SOUNDTEX C 1986
S/W. This material is non-flammable and meets the requirement of building material
class B1. This material has been approved by British (BS) and European (EN)
standards.
The Noise Reduction Coefficient (NRC) was calculated in accordance with ASTM
C423-90a. The degree of Sound Absorption was determined as follows for three
perforation patterns with a ceiling cavity of 400mm.
Ceiling panels shall be tested by PSB in accordance with British Standard 476, Pt 6 :
1989 "method of test for Fire Propagation for products" and BS 476, Pt : 1997 on
Flame Spread. They also meet the stringent requirements of Class O fire rating, or
equivalent local Authority/ Code requirements and FM Global Standards.
All main and cross carriers as well as brackets and clips are made of galvanized
steel.
Rod Hanger 4mm hanger with adjustable clip.
Angle Aluminium capping wall angle or painted steel wall angle.
Size 24mm x 24mm
Contractor is to ensure that the acoustic and other relevant qualities meet the client’s
requirements and Architect’s approval. The ceiling panels are to comply with Local
Code requirements and FM Global Standards.
2.16.8 Packing
Each panel is protected by an individual plastic cover. Each carton box contains 20
panels
Seismic design to specialist’s design & detail shall be included and provided as a
part of the Suspended Ceiling Grid system. In order to prevent damage and
reduce the risk of damage caused by within Data Hall/ critical M&E Room areas
(where applicable).
Seismic Design requirements shall be completed and comply with the following:
• The seismic restraints for the ceiling system shall be designed using ASCE 7
Chapter 13 or SNI1726 Chapter 9.
• The development is specified as Risk Category III (RC III).
• Soil class D at site location
• The peak ground acceleration, PGAM, shall be considered as 0.358g for the
project.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS2/22
OCTOBER 2021 ISSUED FOR PERMIT SECTION 2 - SUSPENDED CEILING
•
The ground motion (0.2s), SS, shall be considered as 0.729g.
•
The ground motion (1.0s), S1, shall be considered as 0.302g.
•
The short period spectral acceleration co-efficient, SDS, shall be considered as
0.591g for the project.
• The spectral response acceleration parameter at 1 second, SD1, shall be
considered as 0.403g for the project.
Seismic design, assessment & analysis (incl. necessary drawings, calculations,
simulation, etc) shall be submitted for Structural Engineer’s or Seismic Consultant’s
review & approval, prior fabrication & installation on Site.
The following components/ systems shall be included, but not limited to:
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
SS003_Drywall Partitions
JKT05 SS3/1
OCTOBER 2021 ISSUED FOR PERMIT SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
SECTION 3
3.1 GENERAL
The partitions shall generally be 150mm thick cavity type drywall partitions and shall
be constructed full height from floor level up soffit of the concrete slab above or to
200mm above suspended ceiling unless otherwise stated. The partitions shall be
installed on 100mm (H) concrete dike depth aligning with proposed partition depths
as included in details particularly to all ground structures and/ or adjacent to internal
space which potentially exposed to water ingress or moisture from floor slabs.
The construction of the partitions shall be made up of galvanised mild steel vertical
and horizontal studs spaces internally at 600mm centres erected on steel floor tracks
with 13mm gypsum plaster boards cladding on both faces of the partition. The
bottom track is made up of a steel floor tract and vinyl coving skirting.
The applied finish on the exposed surfaces of the gypsum plaster board shall be
selected and approved by the Architect and the Architect reserves the right to use on
or combination of the finishes at the rates priced for.
The internal hollow core of the partitions shall be filled up with min. 50mm thick
rockwool for 100mm thick partition or 75mm thick for 150mm thick partition as
described in the drawing.
The Contractor shall also guarantee that the demountable partition system including
doors shall achieve a sound absorption factor of at least 50 decibels.
The partition shall incorporate skirting, trim, fixing clip cover and adjusting pieces and
includes the provision for jointing to the floor, ceiling, column or other walls and to
form door openings complete with solid timber door jambs, etc.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/2
OCTOBER 2021 ISSUED FOR PERMIT SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
The Contractor must apply the relevant test certificate to substantiate that the
partition is non-combustible or other requirements as specified in this document.
The Contractor must provide 5 years of indemnity to the dry wall partitions against
defects, defects in installation and any related components.
3.2 STANDARDS
Unless otherwise agreed by Architect, ensure all of the works comply with the
relevant requirements of the Standards and Codes listed below or referenced in the
body of the Specification. Alternative Standards and Codes may be submitted to the
Architect provided it can be demonstrated that the alternative Standards and Codes
comply with the requirements of the standards specified. All standards and Codes
quoted are the current version, unless specific year references are noted.
Singapore Standards
Other Standards
BS EN10143 Specification for continuously hot-dip, metal coated steel sheet and
strip
BS 7364 Galvanised steel studs and channels for stud and sheet partitions and
linings using screw fixed plasterboard
BS 8212 Code of practice for dry lining and partitioning using gypsum
plasterboard
BS8110 Structural use of concrete (in particular Section 5 – Part 1 Design and
Detailing of Precast Composite Structures.
Part 108 Method for making test cubes from fresh concrete.
BS3148 Methods of test for water for making concrete (including notes on the
suitability of the water).
BS5328 Part 1 to 4
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/4
OCTOBER 2021 ISSUED FOR PERMIT SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
ASTM C475 Standard Specification for Joint Compound and Joint Tape for
Finishing Gypsum Board
ASTM C514 Standard Specification for Nails for the Application of Gypsum Board
ASTM C665 Standard Specification for Mineral-Fiber Blanket Thermal Insulation for
Light Frame Construction and Manufactured Housing
ASTM C840 Standard Specification for Application and Finishing of Gypsum Board
ASTM C1002 Standard Specification for Steel Drill Screws for the Application of
Gypsum Panel Products or Metal Plaster Bases
ASTM C1047 Standard Specification for Accessories for Gypsum Wallboard and
Gypsum Veneer Base
ASTM C1178 Standard Specification for Coated Glass Mat Water-Resistant Gypsum
Backing Panel
ASTM F 1667 Standard Specification for Driven Fasteners: Nails, Spikes, and
Staples
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/5
OCTOBER 2021 ISSUED FOR PERMIT SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
3.3 DEFINITIONS
High purity synthetic gypsum (HPSG) is fire resistant and moisture resistant
plasterboard consists of gypsum plaster core with vermiculite, fibre glass, silicon and
fly ash additives. Heavy impact board shall be 100% asbestos free, fire reinforced
boards having a density of not less than 925 kg/m3 and approved by Fire Safety
Bureau to be non-combustible/limited combustibility in accordance with the British
Standard 476 Part 22:1987.
The construction of the drywall solid partition shall be tested in accordance with BS
476.
For Conference Rooms and Meeting Rooms : STC shall achieve minimum acoustic
of STC53 on all walls, including walls adjoining private offices and/or any other room
space for teleconference/meeting room use.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/6
OCTOBER 2021 ISSUED FOR PERMIT SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
Breaking Strength
Transverse 734 N
Longitudinal 857 N
a) ASTM C1185
b) BS EN 1373
c) ASTM C109
a) General
One (1) layer of 16mm thick fire-rated gypsum fiber panel clad on both sides of
100mm studs system to form an overall wall thickness of approximately
132mm (without wall finishes). Cavity shall be filled with rockwool insulation for
enhanced STC.
Two (2) layers of 13mm thick fire-rated gypsum fiber panel clad on both sides
of 90mm studs system to form an overall wall thickness of approximately
142mm (without wall finishes). Cavity shall be filled with rockwool insulation for
enhanced STC.
Unless otherwise specified, the drywall framing shall be profiled steel studs &
runners. The studs shall have minimum 90mm deep of 22 gauge thick with
proprietary screw of lengths greater than 30 mm. The runners shall also be
90mm deep of 22 gauge thick. Self-bracket bearing and all necessary
accessories, method of fixing and installation shall be strictly in accordance
with manufacturer’s written instruction.
i. Attach top tracks and bottom runners to floor structure and structural
elements with suitable fasteners located 50mm from each end and
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/8
OCTOBER 2021 ISSUED FOR PERMIT SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
ii. Position studs vertically, engaging top tracks and bottom runners, spaced
at maximum 600mm on centre. At splice to bottom runners, place metal
stud section over splice between adjacent vertical studs. Secure splice
piece to each runner with 4 framing screws on each side of runners.
Place studs in direct contact with all doors frame jambs, abutting
partitions, partition corners and existing construction elements.
v. Provide horizontal bridging for all stud partitions over 2400mm high at
1200mm on centre maximum with 38mm rolled channels through studs
and screw attached in place. Lap channels by nesting one inside the
other at a depth of at least 200mm and secure with end angle clips.
vi. Provide all braced framing of steel stud framing as detailed in shop
drawings. Use only mechanical attachment or welding as required per
AISI Specification.
vii. Partition above ceiling shall allow for cut out opening service ducts,
trunking and cable trays. The Contractor shall co-ordinate with all sub-
contractors for the exact size and location of the openings. Any gaps
around any pipes, ducts, through the partition shall be properly sealed
with proprietary fire and smoke stop system.
viii. If full height partition had to be terminated below ventilation duct routed
parallel to the partition, the stud of the partition shall be secured to the
support frame of the duct. In such cases, space between the duct and
reinforced concrete soffit need not be sealed up.
ix. Steel stud framing system shall require to be provided taking into
consideration of load/ weight of proposed door, glazing, glass partition
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/9
OCTOBER 2021 ISSUED FOR PERMIT SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
The lining material shall be 13 mm thick, high abuse resistance, USG Boral
FIBEROCK® Board or approved equivalent.
Panel Composite 13mm thick fiber reinforced gypsum core, with 2.5mm
thick high strength cellulose surface, pre-coated and
ready to receive final finish
Strength (Annex A – L)
Weight 54 kg/m2
ii. Apply gypsum fiber board panel perpendicular to stud or framing with all
attachment to firm bearing surfaces over framing members. Install
panels in such a manner that panel joints do not align with edge of
opening. Staggered joints on the opposite side of panel. Tightly butt
tapered end board edge joints.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/10
OCTOBER 2021 ISSUED FOR PERMIT SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
iii. Treat cut edges, holes, fastener heads, and joints, including those at
angle intersections with partition paper tapes and All-Purpose Ready-
mixed joint compound.
iv. Place gypsum fibre board panels over supporting framing members with
panel ends aligning and parallel with framing members.
g) Insulation
All partition shall be filled with termite resistant Acoustical Fire Slab 100kg/m3
density, min. 50mm thick rockwool slab, to give an overall STC50 to the
Drywall system.
Frequency Hz
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/11
OCTOBER 2021 ISSUED FOR PERMIT SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
h) Compatibility
i. All partition shall be filled with termite resistant Acoustical Fire Slab
100kg/m3 density, min. 50mm thick rockwool slab; to give an overall
STC50 to the Drywall system.
ii. Seal all perimeter gaps of the wall frame system with acoustical sealant
prior to installation of gypsum panel, for maximum sound transmission
loss.
iii. Place acoustical insulation in partitions tight within spaces, around Cut
openings, behind and around electrical and mechanical items within or
behind partitions, and tight to items passing through partitions.
iv. Insure that all recessed panels, electrical outlets, light switch boxes, etc
are encased with fire-barrier seal wrap to seal all gaps and maintain
continuity in fire and smoke protection in all fire-rated assemblies.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/12
OCTOBER 2021 ISSUED FOR PERMIT SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
ii. Ceiling height door frames may be used as control joints. Less-than-
ceiling height frame shall have control joints extending to ceiling from
both corners.
iv. Place control joints consistent with lines of building spaces, with 12.5mm
between board. Apply Acoustical Sealant at base of space, apply control
joint accessory piece at face. Place joints vertically at jamb head of
double doors. Place vertical joint at jamb head, latch side, of doors set in
gypsum board walls, U.N.O. on the approved shop drawings.
i. Reinforced all vertical and horizontal exterior corners with corner beads
fastened with stainless steel stapled at 230mm o.c. on both flanges along
entire length of beads.
l) Joint Treatment
i. Reinforce all interior and exterior corners for both ceiling and wall
surfaces. Apply initial coating of joint compound about 76mm wide,
pressing tape firmly into compound, wipe off excess compound. Apply
second coat of compound with tools of sufficient width to extend beyond
joint centre approximately 100mm. Drawn compound down to a smooth
even plane.
ii. After drying or setting, sand or sponge joints, edges and corners,
eliminating high spot and excessive compound to produce smooth finish
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/13
OCTOBER 2021 ISSUED FOR PERMIT SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
iii. Sand after second and third applications of joint compound. Take
precautions not to raise nap of paper when sanding.
m) Gypsum Accessories
i. Corner Reinforcement
Paper faced metal tape corner bead with internal and external corner
beads in bull nose of various radius, or spray corner.
Material:
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/14
OCTOBER 2021 ISSUED FOR PERMIT SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
Material: Roll-formed zinc control joint with perforated flanges, 1-3/4 inch
wide, with ¼ inch wide center channel.
vi. Joint Tape - 50mm width fibreglass reinforced paper tape conforms to
requirements of ASTM C475.
3.6 CONSTRUCTION
Construction shall be carried out to the approval of the Architect under experiences
factory supervision and control. Only work which cannot be carried out in the
workshop or factory should be prefabricated and assembled quickly on site.
All joints shall be to the best trade practice type of joints. They should be cut and
assembled neatly and accurately and all joints, junctions and intersections shall have
neat hairline.
Butt joints shall be constructed between gypsum plaster board panels. Edges of
jointing panels shall be taped and plastered with approved jointing compound and
thereafter apply with sealant to receive wall covering.
Adequate allowance must be made for thermal movements of any aluminium frame
members.
All members shall be of sufficient strength and deflection shall be kept to maximum
of L/50 considering a distributed load of 5 Ibs per sq ft. The weight of the partition
shall not exceed 6 Ibs per sq ft
Accessories to be used to facilitate jointing and fixing may be connected to the edges
of adjacent spaces. He is to allow for in his pricing, methods of finishing above
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/15
OCTOBER 2021 ISSUED FOR PERMIT SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
finished ceiling level, below finished floor level and beyond grid lines against other
wall and windows elements all to the Architect’s satisfaction.
The deviation range to be allowed for on the floor to ceiling height shall be from 0 to
30mm. This includes an allowance of 6mm for variation in the horizontally of the floor
level, 20mm for deflection of ceiling and 6mm for variation sin horizontally of the
ceiling. The partition shall maintain this performance under the most adverse
condition of deviation.
The partition shall not show signs of deterioration which could be objectionable from
points of view of appearance, habitability or application of finishes. The installed
partitions and its component parts shall run straight to line and to be set vertical and
plumb.
3.7 SKIRTING
The partition shall incorporate homogeneous tile/ PU/ epoxy/ stainless steel skirting
as detailed in drawings.
Skirting should be provided on both sides of the partitions and shall be capable of
carrying electrical and telephone services and minor plumbing pipes.
The panels on both sides of the cavity type partition generally comprised of approved
quality 12.5mm thick plain gypsum plaster board.
The total thickness of the cavity type partition panel shall be 100mm thick and this
overall thickness should be flushed with the aluminium framing.
The partition panel shall be assembled neatly. All panels shall come one piece and
fixed between the aluminium frame members and no joint shall be exposed. No
cutting piece shall be allowed.
The sample of partition panel shall be submitted to the Architect for approval.
The panel shall be free from warps and other defects. Any replacement of defective
panels shall be at the expense of the Contractor.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/16
OCTOBER 2021 ISSUED FOR PERMIT SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
The fire resistant material for in in-fill must satisfy the local Building Authority and
Fire Service Bureau and comply with the specifications shown within the fire
protection drawings.
The gypsum plaster board panels for the partitions shall be finished with the wall
covering/ painting as specified.
Thickness of applied finishes to the gypsum plaster board panel shall require to
comply with requirements or standards stipulated by the Building Control Division
and Fire Service Bureau or any equivalent local authority Code and requirements
(where applicable).
The colour of the surface finish shall not appreciable fade or darken due to action of
natural or artificial light during the defects liability period.
Basic in-fill material in partition shall be 75mm rock wool material of not less than 1kg
or 2lbs density or other equivalent materials acceptable to Building Control Authority
or equivalent local authority Building Department. The panels shall be retained with
no fastening of fixing visible. All anchorages shall be concealed. Such sound proof
walls shall go all the way up to the soffit of the concrete floor above.
3.11 GLAZING
All glazed panels to the partitions shall have solid aluminium or stainless steel or
timber frame and glazing bars and are glazed in 8mm thick first quality coated or
patterned float glass or otherwise stated or shown on the drawings. All glass shall
conform to BS 952 and shall be free from blemishes, bubbles, air holes, specks,
scratches and other defects and samples shall be submitted for the approval of the
Architect.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/17
OCTOBER 2021 ISSUED FOR PERMIT SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
All glass delivered to site must be in its original packing showing the manufacturer’s
markings, guarantee, type of glass, etc attached to the outside of the container.
All broken, cracked or scratched glass must be removed and replaced with new
glass to satisfaction of the Architect.
All glass must be clean inside and outside after installation. On no account shall be
cleaned by scraping the glass.
All glass panels shall be fixed with neoprene or other approved gaskets and
aluminium fixing beads.
The Nominated Sub-Contractor is deemed to have allowed for in his unit rates for the
filling up of all cavities formed when his partition abuts the existing surfaces of walls,
ceiling and other adjoining structure. The fill used is to be approved by the Architect
and this may be in the manner of felt strips, neoprene strips or wet calcium plaster in
filling.
The Contractor is deemed to have allowed for in his unit rate for the erection of one
full and complete “mock-up” partition for the full storey height inclusive of security
screen and one double leaf door all as specified. The length of the partition shall
consist of three panels and totaling 12’0” long. Counter-proposed size of mock-up
partition shall obtain Architect’s clearance.
3.14 CO-ORDINATION
The Contractor shall co-ordinate with sub-contractors for all other trades in the
programming of his work, for example trades listed in the following but not limited to:
• Any door/ window/ louvre/ glass walls/ security mesh wall systems;
Notify Architect one week in advance of the date and the time when the Project, or
part of the Project, will be ready for an above-ceiling observation.
Promptly remove any residual joint compound from adjacent surfaces, and where
ever to the clean room standard.
3.17.1 The architectural drawings are diagrammatic and do not purport to identify or solve
the problems of thermal or structural movement, vapour barriers, fixings and
anchorage, flatness and stability of facing, and moisture disposal.
The drawings merely indicated the ‘profile, configurations and finishes required
together with the position relative to the structural frame and interior building
elements. The details contain therein serve merely as suggested directions for
solving some of the major design requirements. The Contractor may use these
details and develop them as he deems fit.
The Specification specifies the minimum requirements without limiting the Fabricator
as to the method of achieving such performance.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/19
OCTOBER 2021 ISSUED FOR PERMIT SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
The Contractor shall be deemed to have visited the site before submitting his Tender
and shall be wholly responsible for acquainting himself with the nature, position,
constraints of the site and the full extent and character of the works and all other
information relevant to the execution of the works.
The Contractor shall not be entitled to claim extra payment on the grounds of
insufficient or inaccurate tender information relating to propose or existing structures.
Preliminary design proposals must be submitted with the tender. Notwithstanding the
acceptance of the Contractor’s design recommendation/ proposals by the Architect,
Contractor shall be solely responsible for the adequacy of the works including design
and shall make good any damage or defects arising from inadequate design.
The Contractor shall submit for the consideration of the Architect preliminary design
drawings showing typical details fully dimensioned, showing finish, thickness,
profiles, jointing, welds, intersections and assembly; details of construction,
weatherproofing hardware and hardware schedules; reinforcement, anchorage and
structural supports; and such drawings and details (whichever applicable) as
required to fully illustrate all details of the work. The scale and detail of the drawings
are subject to Architect’s approval.
The Contractor shall outline details of his intended temporary works to the Architect
and incorporate his comments into the design. He shall then submit for the
Architect’s approval before the commencement of any on site construction, shop
drawings and calculations showing all details, manner and magnitude of the loading
on the structure. The Contractor shall be responsible for ensuring that the structural
elements to which the elements are to be fixed is adequate to support the load.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/20
OCTOBER 2021 ISSUED FOR PERMIT SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
3.21.1 Measurements
All true measurements of the building are to be in the metric system. The Contractor
shall be responsible for verifying all the dimensions and actual conditions on site.
These dimensions should be incorporated in the shop drawings prior to final
approval.
The Tenderer shall also submit a preliminary programme of the works showing the
various stages of design sampling, testing, fabrication, delivery and installation of the
works.
The Contractor shall submit with his Tender details of builder’s work and special
attendance required other than those already described in this Specification. Any
other items of work or facilities not so stated shall be deemed to be provided by the
Contractor when required.
3.22.1 Submittals
Within one month of award of the Contract, the Contractor shall submit updated
information as follows:-
i. Organization Chart.
Complete scaled construction detail drawings drawn to full scale. The drawings
shall fulfil all requirements made by the Architect during the technical
negotiation with the Contractor.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/21
OCTOBER 2021 ISSUED FOR PERMIT SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
3.23.2 Upon Architect’s approval of the shop drawings, four copies and one reproducible
print for each of the final approved drawings, plus four sets of the above reduce to
one-quarter of the original size shall be submitted for the Architect’s and Employer’s
use.
3.23.3 After the shop drawings and the structural calculation, etc. are approved, the
Contractor shall submit the following for the Architect’s approval before fabrication of
the bulk.
3.23.4 Should the Contractor consider it necessary to fabricate in bulk before approval in
order to meet completion date, it is entirely at his own risk and no compensation in
time and cost will be granted if the material and/or workmanship is eventually not
acceptable to the Architect.
3.23.5 Before the components are installed, the Contractor shall submit the following for the
Architect’s approval.
The Contractor shall monitor the site conditions constantly and report every
month the results of the inspection, in a deviation/defects list form to the
Architect. Format to be submitted for approval.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/22
OCTOBER 2021 ISSUED FOR PERMIT SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
Preliminary plan of the procedure for site inspection during installation stage
so as to maintain quality control on the site.
v. Plan of Protection –
3.23.6 Before the date of completion of the works, the contractor shall prepare and supply
to the Architect, record drawings and record photographs of the whole of the works
as installed and as requested by the Architect. These drawings and photographs
shall be specially prepared for record purpose
3.23.7 The Contractor shall submit a maintenance manual for all systems.
3.25 Guarantee
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/23
OCTOBER 2021 ISSUED FOR PERMIT SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
defects for which the causes cannot be determined. This guarantee and its
enforcement shall not deprive the Employer of other action, right or remedy
available to him.
b) The general guarantee shall cover a period of ten (10) years from the date of
issue of the Completion Certification of the Main contract by the Architect.
d) The guarantee shall cover structural failure and latent defects of the system in
compliance with the current and latest regulations and requirements stipulated
by the relevant local authorities.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
SS004_Steel & Metal Works
JKT05 SS4/1
OCTOBER 2021 ISSUED FOR PERMIT SECTION 4 - STEEL AND METAL WORKS
SECTION 4
All materials shall be of the best quality obtainable and shall be clean, straight and
free from twist before assembly. If straightening and flattening is necessary, it shall
be done in a manner that will not alter the integrity of the material.
All materials shall be subject to the approval of the Architect/Engineer, but the fact
that the contractor has used ‘approved’ materials will not absolve him of his
responsibility in respect of this section of the Works.
All steel and iron shall be approved origin and to comply with the relevant
requirements of British Standards Institution.
The costs of preparing materials for testing, and for all Site and laboratory tests
under this heading will be borne by the Contractor, who will also provide all
necessary apparatus and facilities, transportation, and pay all charges for such
tests.
The Contractor will, as directed, take and deliver samples of structural steel for
testing at an approved laboratory. Should the results of a test be unsatisfactory, the
whole consignment of steel that the sample represents will be rejected.
The Contractor is to provide and maintain all necessary equipment for tests, in a
satisfactory condition on Site, for as long as the Architect/Engineer may require.
The Contractor is to provide the Architect with copies of all test results.
Structural steel, steel tubes, rectangular hollow sections and testing is to comply
with the relevant British Standard.
4.1.1 Drawings
The Drawings prepared by the Architect/Engineer are layout drawings for the
purposes of tendering and contracting. The Contractor is to prepare his own shop
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS4/2
OCTOBER 2021 ISSUED FOR PERMIT SECTION 4 - STEEL AND METAL WORKS
drawings, showing sizes, dimensions of all members, and sizes and dimensions of
all bolts and rivets, complete with details of welds, type of electrodes, welding
procedures, whether welding is to be shop or Site executed, and the other details as
are required for the purposes of fabrication and erection.
Before fabrication is commenced, the Contractor is to submit two copies of his shop
drawings to the Architect/Engineer for approval. When approved, one set will be
returned to the Contractor signed as approved, upon receipt of which the Contractor
will be free to commence fabrication.
4.2 STANDARDS
Unless otherwise agreed by Architect, ensure all of the works comply with the
relevant requirements of the Standards and Codes listed below or referenced in the
body of the Specification. Alternative Standards and Codes may be submitted to the
Architect provided it can be demonstrated that the alternative Standards and Codes
comply with the requirements of the standards specified. All standards and Codes
quoted are the current version, unless specific year references are noted.
Singapore Standards
Other Standards
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS4/3
OCTOBER 2021 ISSUED FOR PERMIT SECTION 4 - STEEL AND METAL WORKS
BS EN 1461 Galvanising
fasteners
BS EN 10111 Low carbon steel sheet & strip for cold forming
BS EN 10130 Cold-rolled low carbon steel flat products for cold forming –
technical delivery conditions
BS EN 10139 Uncoated mild steel narrow strip (1) for cold forming
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS4/4
OCTOBER 2021 ISSUED FOR PERMIT SECTION 4 - STEEL AND METAL WORKS
BS EN 10142 Continuously hot dip zinc coated low carbon steels strip and
sheet for cold forming – technical delivery conditions
BS EN 10143 Continuously hot dip metal coated steel sheet and strip –
tolerances on dimensions and shape
BS EN 10147 Continuously hot dip zinc coated structural steel sheet & strip-
technical delivery conditions
BS EN 10152 Electrolytically zinc coated cold rolled steel flat products for
cold forming– Technical delivery conditions
BS EN 10258 Cold-rolled stainless steel and narrow strip and cut lengths -
tolerances on dimensions and shape
BS EN 10268 Flat products. High yield strength micro-alloyed steels for cold
forming
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS4/5
OCTOBER 2021 ISSUED FOR PERMIT SECTION 4 - STEEL AND METAL WORKS
BS 4604 The use of high strength friction grip bolts in structural steel
work.
Galvanized steel tubing shall comply with the requirements of BS:1387 medium
grade.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS4/6
OCTOBER 2021 ISSUED FOR PERMIT SECTION 4 - STEEL AND METAL WORKS
c. Mild steel shall be fabricated by workpeople skilled in this work and shall be
accurately manufactured and assembled to angles, curves and sizes as
specified, free from warps, hammer marks, burrs, distortion and other
imperfections.
f. Hot-rolled steel sections, including angles, shall comply and be made from
steel complying with British Standard.
h. Cold-rolled steel sections shall comply with relevant British Standard and be
made from steel complying with BS:1449.
j. Steel sheet and strip shall comply with relevant British Standard.
l. Welded wire mesh is to be made from wire complying with relevant British
Standard.
Cast iron shall be from the best quality tough gray pegs, and of not less quality than
the relevant British Standard.
Castings shall be sharp and of the exact form required, shaped to fit the parts truly
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS4/7
OCTOBER 2021 ISSUED FOR PERMIT SECTION 4 - STEEL AND METAL WORKS
and hold full dimensions. They shall be entirely free from air holes, scoriae, core
nails, flaws and defects of every kind. Holes shall be filled afterwards, all at the
Contractor’s expense.
4.5 TESTS
All wrought iron, steel and cast iron articles shall be submitted to a reasonable test
for strength, if so required by the Architect, at the Contractor’s expense.
a) All stainless steel shall be low carbon chromium nickel austenitic steel in
accordance with relevant BS. All exposed screws fastenings etc., shall be of
appropriate material, to the approval of the Architect.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS4/8
OCTOBER 2021 ISSUED FOR PERMIT SECTION 4 - STEEL AND METAL WORKS
action.
All stainless steel work shall be securely installed and anchored in position, set
plumb, square and level, and in proper alignment with other works.
Stainless Steel railings for internal use shall comply with relevant British Standard
containing Nickel and Chromium in the percentage of 18 and 8 respectively.
Stainless Steel railings for external use shall comply with relevant British Standard
containing Chromium, Nickel-molybdenum in the percentages of 18/10/3
respectively.
4.7 ALUMINIUM
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS4/9
OCTOBER 2021 ISSUED FOR PERMIT SECTION 4 - STEEL AND METAL WORKS
The finish shall described as either mill finish, rough textured finish, soft textured
finish, polished, or anodized clear or coloured.
Aluminium units shall be framed with corners of adequate strength and design to
prevent distortion, reinforced with steel as necessary and with hardwood cores
where required and factory welded, riveted or bolted. All bolts screws shall be of
stainless steel or approved alloy, anodized as a unit, countersunk flush where
practicable, or semi-countersunk round headed where it is not practicable to
countersunk fully.
4.8 ANODIZING
All aluminium surfaces shall be thoroughly cleaned and given a coating of clear
non-fading coloured anodizing of the hard inorganic type compatible with the alloy
use. The coating shall be applied over a caustic etched finished and sealed
effectively. The coating shall have a minimum film thickness of 0.02032 mm when
tested in accordance with ASIM and British Standards. Protect surfaces from
handling marks until sealers and protective coatings are applied.
Protective tapes and stripping shall be applied on all aluminium surfaces and shall
not be removed until the final cleaning down of the building.
Where aluminium comes into contact with concrete, brickwork or plaster, it shall be
coated with an insulating lacquer paint or tape etc., to ensure that electrolyte
corrosion is avoided.
4.9 BRASS
Brass for general use shall consist of 61.5% - 64% copper and 34% - 38.5% zinc.
Brass for all decorative work or external work such as handrails or brass in contact
with sea water shall consist of 70% copper, 29% zinc, 1% tin.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS4/10
OCTOBER 2021 ISSUED FOR PERMIT SECTION 4 - STEEL AND METAL WORKS
4.10 BRONZE
Bronze shall consist of 85% copper, 5% zinc, 5% tin, and unless otherwise specified
shall have a natural colour polished finish.
The Contractor is required to submit sample for the Architect's approval before
proceeding with the works.
All metal lath is to be fixed as taut as possible, with the largest dimension of the
mesh running between supports and with stiffening ribs uppermost in the same
direction. Cut ends are to be turned away from the plastered surface.
End laps are to be less than 25mm when the lap occurs at the bearer and otherwise
not less than 50mm. Side laps are to be not less than 25mm. All laps are to be
securely wired together with 18 gauge soft galvanized binding wire at intervals of
not more than 75 mm.
Chicken wire mesh for reinforcing screeds is to be galvanized, 18 SWG, with mesh
not longer than 19mm.
In all cases where chromium plated articles are specified to be provided by the
Contractor, the plating shall be on a base material of copper or brass.
The plating shall be of the quality described in relevant BS for service condition no.
3 - normal outdoor conditions and shall be free from visible defects, such as
blisters, pits, unplated areas, cloudy patches, cracks or stains.
Galvanized articles are to be thoroughly and evenly coated with zinc by the hot
dipped process and are to be free from stains, bare spots and other defects.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS4/11
OCTOBER 2021 ISSUED FOR PERMIT SECTION 4 - STEEL AND METAL WORKS
Galvanizing shall be carried out after fabrication, and articles shall be thorough
cleaned in caustic and acid solutions before the galvanizing process is carried out.
The minimum weight of zinc deposited by galvanizing shall be 300 g/m2 of surface.
The galvanizing shall comply with the requirements of relevant BS.
Any cutting, drilling abrasions or welding carried out after galvanizing must be
ground down to bare white metal and treated accordingly and approved cold
galvanizing paint. Wherever possible galvanizing is to be carried out after all
welding, cutting and drilling is to complete and the surface suitably protected.
Galvanizing to steel & metal works are to be guaranteed against defects and
workmanship for min. 10 years. In term of corrosion resistance, steel & metal works
shall not display more than 5% of surface rust after 10 years for pre-galvanizing
steel and 15 years for hot-dipped galvanized steel (performed after welding). Pro-
rated warranty schedule shall require to be submitted for Client’s acceptance should
there be any applicable.
Polyester powder finishes should comply with the requirements of relevant BS for
aluminium alloy components and relevant BS for steel components. The
components should be factory finished by applicators approved by the supplier of
the polyester powder. Where conditions allow, only one applicator should be used
for the whole of the works. One powder supplier only should be used for the whole
of the works.
The reference to one applicator is made to ensure the greatest control of colour
consistency throughout the production period. Al components should be control to
a minimum dry film thickness of 75 microns.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS4/12
OCTOBER 2021 ISSUED FOR PERMIT SECTION 4 - STEEL AND METAL WORKS
For architectural use, PVF2/acrylic blends should contain no less than 70% of
polyvinylidene fluoride resin.
The reference to one applicator is made to ensure the greatest control of colour
consistency throughout the production period.
All components should be coated on all significant surfaces with a spray primer coat
to a thickness recommended by the paint supplier and allowed to cure for the
interval recommended by the manufacturer before spray application of top coat to a
minimum dry film thickness of 25 microns.
The finish shall meet or exceed the requirements of AAMA 605.2 when tested by an
independent testing laboratory for the following properties:
a adhesion
c cupping
d Resistance to mortar
f resistance to humidity
g weathering
The coating system must be spray applied under factory conditions to pretreated
base metal in a three coat, three bake process (with a top coat of clear PVF2 resin),
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS4/13
OCTOBER 2021 ISSUED FOR PERMIT SECTION 4 - STEEL AND METAL WORKS
a. Colour uniformity
b. Specular gloss
d. Film adhesion
e. Chemical resistance
f. Abrasion resistance
g. Chemical test :
- mortar test
h. Corrosion test :
- humidity resistance
i. Weathering :
- color retention
- chalk resistance
The coating system must be applied by the coating system manufacturer. The
applicator shall propose a program of records and samples of the entire coating
production for approval by the Architect, and which records and samples shall be
made available to the Architect for approval upon request. The surface quality of
the coating must be smooth and free of flow lines, streaks, blistering or other
imperfections. The coating must be opaque and uniform, within the range of
approved upper and lower limit samples when viewed under a uniform light source,
such as north daylight.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS4/14
OCTOBER 2021 ISSUED FOR PERMIT SECTION 4 - STEEL AND METAL WORKS
Provide and furnish a compatible field touch-up PVF2 coating system formulated for
air-drying at ambient temperature, based on the “Kynar ADS” fluorocarbon resin, in
colour to match factory-applied finish. (Submit samples of the air dry system as well
as samples of actual touch-up work to factory-applied coating system).
Warrant the organic coating will not peel, check, crack, chalk or change colour for a
period of ten years from the Completion Date in the Architect’s Completion
Certificate and that the finish exceed or meets the standards set out in relevant
AAMA and BS which include but are not limited to the following: -
a. Colour change must not exceed 5 NBS colour units, or 5 E units on a Hunter
Colour Difference Meter, when measured in accordance with relevant ASTM
after five years of 45o South Florida exposure or equivalent.
All surfaces exposed to view shall be finished. Surfaces shall match the
appearance, colour and texture of mock-up as approved by the Architect.
The Architect will inspect material prior to finishing and shall serve as sole judge
concerning the quality of material and its conformance to the drawings and
specifications. Colours shall be to the approval of the Architect. Colour range shall
not deviate from approved mock-up.
Complete certified inspection records for quality of finish and finish process records
shall be maintained.
At aluminium surfaces in contact with masonry, concrete to steel, prime paint steel
with zinc chromate or bituminous paint. Prime paint steel part of anchors, anchor
inserts, reinforcement and supports with zinc chromate. After field welding, remove
weld slag and touch up primed surface.
Provide minimum dry film thickness of one mil for zinc chromate and 30 mils for
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS4/15
OCTOBER 2021 ISSUED FOR PERMIT SECTION 4 - STEEL AND METAL WORKS
4.19 FASTENERS
Bolts screws and nuts are to comply with relevant British Standard.
All screwed work is projecting at least two threads through nuts, and all bolts are to
have hexagon heads and nuts with standard threads. All bolts are to be fitted with
washers that are to be splayed if necessary to give a level and even bearing for the
nuts.
4.20 FIXING
Install the work permanently and securely in place. Metalwork must not be allowed
to carry any structural loads unless specifically designed for that purpose. Railings
or balustrades must not be used as strutting or supports after fixing.
4.20.1 Workmanship
The fabrication and erection of steelwork shall comply with relevant BS.
Any part of the work that does not comply with the Drawings and/or the
Specification will be rejected, and shall be removed from the Site, if delivered, within
24 hours from receipt of such notice of rejection.
Ends of beams, channels and other parts abutting against or upon other parts, are
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS4/16
OCTOBER 2021 ISSUED FOR PERMIT SECTION 4 - STEEL AND METAL WORKS
to be cut to exact lengths, true and square, so as to provide a good bed or joint as
the case may be. Proper cover plates are to be provided where necessary and
covers to angles are to be diminished leg dimensions while maintaining at least the
same sectional area. Edges of web plates are to be flush with the faces of the
flange angles, and stiffeners are to fit closely against the flanges. Bolts heads and
ends of eye rods are not to be welded on but formed out of the solid metal.
c. Deviation from straight line, 6mm for beams & trusses + 3mm for ties & struts.
Welding shall be carried out by expert tradesmen in strict accordance with the
current Code of Practice.
No welding of members will be permitted except where shown on the Drawings. All
welding, where possible, is to be fillet welding.
Surfaces to be paint welded to be free from loose scale, slag, rust, grease, paint
and other deleterious materials. Surfaces are also be free from fins, tears and other
defects. Preparation of bevelled edges for welding is to be executed by planning or
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS4/17
OCTOBER 2021 ISSUED FOR PERMIT SECTION 4 - STEEL AND METAL WORKS
All members to be welded are to be accurately prepared so that components will fit
closely together. After assembly and before general welding commences, the parts
are to tack welded with small fillet welds about 50mm long made with 5mm
electrodes and a high current. The tack welds are to be of same quality and size as
the first run of the main weld. When the latter is deposited complete fusion with the
ends of the tack welds to form a final profile free from irregularities is required.
Any defective or unsound welds are to be cut out and replaced or suitably
corrected, as instructed by the Architect/Engineer.
Fire-rated roller shutters shall be approved by local fire regulations standards. Fire
shutter markings shall be etch, emboss, stamp or print onto identification tags, the
required information to comply with Clause 8.2 and Clause 8.3 of SS489, and fix
firmly to the bottom rail of the fire shutter. Fire-rated roller shutters shall be
manufactured from the following requirements:-
a. Curtain
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS4/18
OCTOBER 2021 ISSUED FOR PERMIT SECTION 4 - STEEL AND METAL WORKS
This shall be constructed from roll-formed galvanised steel shutter lath, 70mm
pitch 1.2mm thick. Lath shall be provided with end locks. It shall be finished
colourbond or power coated.
b. Roller Drum
This shall be constructed from mild steel tube of sufficient diameter to avoid
deflection of shutter curtain. It shall be finished with primer and rust-resistant
grey paint.
c. Roller Casing/Hood
d. Side Rails
This shall be constructed from 2mm mild steel profiles to be faced fixed to
concrete or masonry using 8mm diameter/50mm long expansion bolts at
532mm centres, and finished with primer and rust-resistant grey paint.
e. Bottom Rail
This shall be constructed from 2 numbers of (38 x 38 x 3)mm thick mild steel
angles bolted back to back to form a tee section, with primer and rust-
resistant grey paint.
f. Operation
g. Automatic Closing
All fire shutters shall be fitted with fusible link that breaks at 65oC and release
the brake to allow the shutters to descent at a controlled speed.
Connection to a fire alarm panel shall be provided and upon receipt of 24-volt
signal, the shutters shall close at a controlled speed.
A dual system option shall be provided whereby the shutters are required to
have a fusible link as well as connection to the fire alarm all as described.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS4/19
OCTOBER 2021 ISSUED FOR PERMIT SECTION 4 - STEEL AND METAL WORKS
h. Ironmongery
All ironmongery to be at least half hour fire rated. Where fire doors of a higher
rating are to be provided, the ironmongery must comply with this requirement.
i. Sealants
Insert intumescent sealant at the wall/roller shutter channel and head junction
of all fire rated shutters. Submit intumescent sealant to the Architect for
approval. Inset silicone sealant at junction of all external walls and roller
shutter channel and head.
PSB certify and fire test gasket and seals, where incorporated into fire rated
roller shutters, in conjunction with the roller shutter as an integral assembly.
Provide waterproof seals at the base of all external roller shutters.
Standard heavy duty roller shutter shall be manufactured from the following
requirements:-
a. Curtain
This shall be constructed from first grade high tensile galvanised or pre-
coated colour steel with carefully design interlocking groove, advance design
cut-off edge endlock to achieve maximum holding strength to each
interlocking lath. It shall be 1.5mm thick.
b. Bottom Bar
This shall be rolled-formed from high tensile steel of minimum 1.5m thick to
the shape of single angle design with mitred edge.
It shall be fabricated with hollow steel section with mild steel sheet covers to
be painted with one coat of anti-rust primer to factory standard.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS4/20
OCTOBER 2021 ISSUED FOR PERMIT SECTION 4 - STEEL AND METAL WORKS
e. Operation
All external roller shutters shall be powder coated with weather seal for bottom bar.
The colour shall be to Architect’s approval.
Prepare and submit shop drawings to enable the fabrication and installation of the
doors, including:
a. Elevation and section of all roller shutter doors together with head
shutter box. Clearance for opening the doors to be set out.
b. Section showing door jamb, head and floor junction with all fixing
positions.
Contractor to coordinate the roller shutter door works, particularly the interfaces with
the following packages and trades:
Liaise and coordinate with services engineer for location of all doors linked to
security or fire system.
All roller shutters should be provided with 5 years warranty. This is to be provided
against any defects, installation defects and defects against any related equipment
or components.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS4/21
OCTOBER 2021 ISSUED FOR PERMIT SECTION 4 - STEEL AND METAL WORKS
All fusible links are to comply with FSSD requirements and comply with SS 489.
Shop drawings and mechanism specifications to be submitted for Architect’s
approval.
Check all dimensions, both on drawings and on site before starting fabrication.
Prevent distortion of components during transit, handling and storage and prevent
finished surfaces from rubbing together.
Install components securely in place, plumb, square, level and in proper alignment
with other work.
Pack joints to maintain specified widths especially at positions where fixings tighten
frame against the structure.
Keep opening lights of window closed and secured during all operations until fixed.
Retain any clamping devices in position. Pack between light and frame to maintain
correct clearances.
Bed mating surfaces of composite assemblies with metal to metal joints in bedding
compound.
Assemble and fix ironmongery using fastenings with matching finish supplied by the
ironmongery manufacturer.
On completion, check and adjust all moving parts and ironmongery, lubricating as
necessary to ensure correct functioning.
The whole of the fabrication, welding, bolting, priming and installation shall be
carried out by skilled tradesmen in accordance with the best trade practice.
All joints and mitres shall be carefully and accurately assembled and machined so
as to provide close smooth connections that will be weather and water-tight and not
noticeable.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS4/22
OCTOBER 2021 ISSUED FOR PERMIT SECTION 4 - STEEL AND METAL WORKS
Faces of metal in contact shall have hairline joints. Work shall be assembled with
concealed fittings insofar as practicable. Mouldings shall be in true alignment at
joints, straight, tightly and neatly fitted. Junctions of identical sections shall be
mitred. When assembled, all moving parts shall move freely without binding.
Remove all burrs and sharp arises which would be visible after fixing or a hazard to
the user.
4.26 RATES
The description of and rate for each item of ‘Metalworker’ etc., will be held to
include for taking delivery, unloading, carrying in, sorting, stripping or removing
protective wrapping or coverings, checking, assembling, returning packages,
handling, hoisting and placing and lowering, or fitting and fixing materials and goods
in position, adjusting, re-fixing, and for cutting away and making good, levelling,
packing, grouting, providing templates and plugged grounds, and touching up all in
accordance with the generally accepted requirements of the specific item, including
protecting and safeguarding until the issue of the Completion Certificate.
The description of and rate for each item of ‘Metalwork’ included will be held to
include for all straight, skew and circular cutting etc., and all holes for pipes, etc.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS4/23
OCTOBER 2021 ISSUED FOR PERMIT SECTION 4 - STEEL AND METAL WORKS
Panel Properties
4.21.2 Accessories
a) EBS1 Z Base support 2450mm long laid continuously to locate bottom panel
for Horizontally laid panels only)
b) 200m long EBS2 Z edge clip for Vertically laid panels only.
c) 12mm x 6mm x 10m Rear Air Seal to air seal openings and junctions
including windows and doors
d) 95mm x 10mm Structural Rear Air Seal applied continuously up the vertical
steel support, for Horizontal panel instillation only
e) 9mm x 3mm Butyl Mastic Strip to be used between the panel face and the
proposed flashings / omega sections
g) 1200mm long Rockwool infill (depth to match panel thickness) fitted behind
Omega Section
h) 3656mm and 6000mm long flush Omega Section & Cap insert at each vertical
joint location
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS4/24
OCTOBER 2021 ISSUED FOR PERMIT SECTION 4 - STEEL AND METAL WORKS
a) Design
- Standard: To BS 5427-1.
Paper 1/06.
c) Product Samples
- Panels
- Fasteners
a) Performance Compliance
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS4/26
OCTOBER 2021 ISSUED FOR PERMIT SECTION 4 - STEEL AND METAL WORKS
d) Water Penetration
f) Fire Performance
building elements
a) Painting Structure
b) Fasteners
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS4/27
OCTOBER 2021 ISSUED FOR PERMIT SECTION 4 - STEEL AND METAL WORKS
positively fixed.
• Material:
- Manufacturer:
- Product reference:
• Recycled content:
• Panel and sheet ends, laps and raking cut edges: Fully supported and
with fixings at top of lap.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS4/28
OCTOBER 2021 ISSUED FOR PERMIT SECTION 4 - STEEL AND METAL WORKS
• Debris: Remove dust and other foreign matter before finally fixing panel
and sheets.
• Type: Cover flashing fixed on one side over gap between panels.
• Requirement: Weathertight.
i) Abutments
4.21.6 Testing
Panel cladding and covering to pass Ash, Combustion and Heat tests. Fire
resistance tested from both sides, of up to 120 minutes. Integrity & 120 minutes
Insulation when tested to EN1364-1:1999.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS4/29
OCTOBER 2021 ISSUED FOR PERMIT SECTION 4 - STEEL AND METAL WORKS
All penetrations through the panels must be filled tightly with stonewool insulation
(or similar) with a minimum density of 23kg/m3 and weather proof sealant and must
be capped off with stainless steel flashing to colour and finish to match the cladding
panels unless mentioned otherwise. The detail must be verified and approved by
the manufacturer before execution at site. The joints must be tested on their water
indemnity upon completion of works.
• Multiple 300mm x 300mm penetrations linearly aligned along the length of the
panels
• Load and penetration sizes can be shared across panels to make larger sized
opennings.
• Multiple punctures that cover more than an approved extent of the panels
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
SS005_Waterproofing
JKT05 SS5/1
OCTOBER 2021 ISSUED FOR PERMIT SECTION 5 – WATERPROOFING
SECTION - 5
5.0 WATERPROOFING
5.1 GENERALLY
The Contractor shall arrange for an approved Specialist Contractor acceptable to the
Architect to carry out all the waterproofing works. On completion of the whole
Contract, the Contractor shall jointly and severally with the Specialist Contractor
furnish a ten-year guarantee against leakage, faults in installation, workmanship,
premature deterioration of the waterproofing, etc.
Supply and install bonded insulated roof waterproofing system as shown on the
drawings or specified herein consisting of:
b) Separation layer
c) Insulation
e) Waterproofing membrane
COPYRIGHT BY M/S AWPPTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS5/2
OCTOBER 2021 ISSUED FOR PERMIT SECTION 5 – WATERPROOFING
Substations, Pump House, Bin Centre, etc.. wherever applicable. Refer drawings &
schedules.
The contractor may select one of the following systems or approved equivalent. The
installation must strictly comply with the specifications and application procedure of
the manufacturer of the system selected.
c) Sub-soil drainage
d) Waterproofing membrane
Wet areas include toilets, kitchen/ kitchennette or pantry, refuse compactor room, bin
centre, bin room, janitor/ cleaner’s room, AHU rooms, pump sump room, bulk refuse
room, sprinkler tank room, potable water pump/tank room, Chiller rooms, unloading
bay, areas open to the exterior, etc. shall be treated with waterproofing system.
The waterproofing will extend up to 1800mm up the vertical surfaces of walls in wet
areas unless stated otherwise.
General Areas: Toilets, Janitor/ cleaner’s room, pantries, refuse collection points, bin
centre, pump rooms, etc.
The contractor may select one of the following systems or approved equivalent. The
installation must strictly comply with the specifications and application procedure of
the manufacturer of the system selected. The application must be carried out by a
specialist contractor, licensed by the product manufacturer and by trained personnel.
COPYRIGHT BY M/S AWPPTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS5/4
OCTOBER 2021 ISSUED FOR PERMIT SECTION 5 – WATERPROOFING
The full extent of the Ground Floor inclusive of lift pits, water tanks and cable
chambers etc…are to be waterproofed as follows to prevent the ingress of rising
damp.
The Exposed external areas will have structural slabs laid to fall.
ii. a surface applied system which will be topped with screed and respective
floor finish
The contractor may select one of the following systems or approved equivalent. The
installation must strictly comply with the specifications and application procedure of
the manufacturer of the system selected. The application must be carried out by a
specialist contractor, licensed by the product manufacturer and by trained personnel.
A method statement must be submitted by the contractor seeking the approval of the
Architect before proceeding with relevant works.
Sika Indonesia
General Areas: water tanks, sprinkler tanks, underground trenches, pump rooms,
etc.
Supply and install waterproofing system or blind side waterproofing as shown on the
drawings or specified herein.
Sika Indonesia
Areas: all structures below ground and in contact with the earth. [To be read in
conjunction of Consultants’ drawings & schedules]
Supply and install protection cum drainage to external surfaces of walls in contact
with the earth as shown on the drawings or specified herein.
COPYRIGHT BY M/S AWPPTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS5/6
OCTOBER 2021 ISSUED FOR PERMIT SECTION 5 – WATERPROOFING
Supply and lay cast-in-situ cement/sand panel topping on the separation felt to fall
with minimum thickness of 40mm in bay of 1m x 1m (panel size depending on site
condition) with joint size of 12mm and filled with hot bitumen.
5.10 VENT PIPE, RAINWATER DOWNPIPE, DUCT AND OTHER PENETRATION FROM
ROOF SLAB
The waterproofing system must be turned up along skirting, vent pipes, etc to a level
of at least up to the top of the parapet wall above the roof surface. All rain water
outlets must be similarly dressed down.
The entire system of waterstop at construction joints and expansion joints shall be
compatible with the waterproofing system approved and they shall be carried out
strictly in accordance with the manufacturer's recommendations.
COPYRIGHT BY M/S AWPPTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS5/7
OCTOBER 2021 ISSUED FOR PERMIT SECTION 5 – WATERPROOFING
The grease traps are located at the first storey area. The Contractor shall take all
measures (if necessary, grout the perimeter joints) in ensuring that the grease trap
base and perimeter is waterproofed. Internal waterproofing of the grease trap shall
be carried out by the Contractor who shall submit their type/details for approval. Such
waterproofing shall be durable to food acids, heat and other food wastes produced.
The Contractor is to consider carefully details concerning the grease trap (i.e.
internal & external waterproofing, compartmentalisation, dust screw area, etc.)
before commencing works in this area.
The waterproofing membrane shall have been used under the same name and
composition in Singapore for at least 15 years. The waterproofing membrane shall
possess a British Board of Agrément (“BBA”) or European (“UEAtc”) Agrément
certificate with durability rating of at least 30 years. Where the membrane is to be
COPYRIGHT BY M/S AWPPTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS5/8
OCTOBER 2021 ISSUED FOR PERMIT SECTION 5 – WATERPROOFING
exposed, it shall be according to the RAL colour specified. For areas where the
waterproofing membrane is to be fully adhered, the cold applied adhesive shall be
according to the manufacturer's recommendations. The waterproofing membrane
shall be manufactured to ISO 9001 quality assurance.
COPYRIGHT BY M/S AWPPTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS5/9
OCTOBER 2021 ISSUED FOR PERMIT SECTION 5 – WATERPROOFING
The waterproofing coating shall provide an effective waterproofing coating for floors,
walls and water retaining structures and as a damp-proof membrane in sandwich
constructions in accordance with BS 8102:2009 (Code of Practice for protection of
below ground structures against water from the ground). The waterprrof coating shall
be applied at a rate of 0.75 litre/m2/coat. Two coats are recommended, allowing the
first to fully dry prior to application of the second. A dry film thickness of 1.0 mm to
1.2 mm is recommended.
COPYRIGHT BY M/S AWPPTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS5/10
OCTOBER 2021 ISSUED FOR PERMIT SECTION 5 – WATERPROOFING
COPYRIGHT BY M/S AWPPTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS5/11
OCTOBER 2021 ISSUED FOR PERMIT SECTION 5 – WATERPROOFING
GENERIC SPECIFICATION
COPYRIGHT BY M/S AWPPTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS5/12
OCTOBER 2021 ISSUED FOR PERMIT SECTION 5 – WATERPROOFING
The drainage sheeting to all vertical surfaces shall be DELTA MS sheeting supplied
by Elmich Pte Ltd or approved equivalent.
The drainage sheeting shall be a dimpled sheet manufactured from high density
polyethylene and without any recycled materials. It shall have excellent resistance to
puncture and decay. It shall meet/exceed the requirements of DIN 4095 and DIN
18195 for protection and drainage applications. The sheeting shall be mechanically
fastened to the substrate using proprietary studs from the same manufacturer to
ensure water-tightness.
The Performance Standards of the drainage sheeting shall match or surpass the
following tested according to DIN 53576:
COPYRIGHT BY M/S AWPPTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS5/13
OCTOBER 2021 ISSUED FOR PERMIT SECTION 5 – WATERPROOFING
The sub-soil protection cum drainage system to all waterproofing applied on vertical
surfaces shall be VERSICELL interlocking cellular drainage modules (‘draincells’)
with non-woven geotextile filter fabric supplied by Elmich Pte Ltd or equivalent. The
sub-soil protection cum drainage modules (‘draincells’) shall have a compressive
strength of at least 100 tonne/m2 to accommodate both static and dynamic loads
during and after installation. It shall have good resistance to petroleum-based
chemicals and naturally occurring soil chemicals.
The draincells shall have surface perforations each not exceeding 350 mm2 to
prevent entry of large fill aggregates. The openings on the horizontal surfaces shall
be at least 65% of the total surface area to provide optimum flow rate. The draincells
shall be at least 30 mm high and shall be interlocked with adjacent draincells along
connecting edges to form a continuous entity whether as panels, conduits or tanks.
The draincells shall comprise of one or more layers to ensure a total flow rate of at
least 16.5 l/m.s for maximum rainfall under Singapore Code of Practice SS 525 :
2006 (or equivalent local Standards/ Code Requirements).
The under-screed drainage mat shall be VERSIDRAIN 6P supplied by Elmich Pte Ltd
or approved equivalent.
COPYRIGHT BY M/S AWPPTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS5/14
OCTOBER 2021 ISSUED FOR PERMIT SECTION 5 – WATERPROOFING
Property Value
Overall height 6 mm
COPYRIGHT BY M/S AWPPTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS5/15
OCTOBER 2021 ISSUED FOR PERMIT SECTION 5 – WATERPROOFING
Property Value
Water permeability
The sealing tape shall be ELMICH SEALING TAPE P50 tape supplied by Elmich Pte
Ltd or approved equivalent.
The sealing tape shall be a self-adhesive butyl sealing tape protected by a strong,
high-density, cross-laminated, white creped polyethylene film. It is ideal for the
sealing of connections and moulds perfectly to irregular structures. Elmich Sealing
Tape P50 is highly adhesive to steel, concrete, bricks, glass and most other
substrates.
PROPERTY VALUE
Solids 100%
COPYRIGHT BY M/S AWPPTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS5/16
OCTOBER 2021 ISSUED FOR PERMIT SECTION 5 – WATERPROOFING
The sealing tape shall be ELMICH REINFORCEMENT TAPE F100 tape supplied by
Elmich Pte Ltd or approved equivalent.
Property Value
Solids 100%
COPYRIGHT BY M/S AWPPTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS5/17
OCTOBER 2021 ISSUED FOR PERMIT SECTION 5 – WATERPROOFING
thermal jointing.
Property Value
COPYRIGHT BY M/S AWPPTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS5/18
OCTOBER 2021 ISSUED FOR PERMIT SECTION 5 – WATERPROOFING
Property Value
Prior to commencement of waterproofing works, the Contractor shall lodge with the
Architect a 10-year indemnity against leaks and any failure of the waterproofing and
watertightness and waterproofing additives of the following:
iii) Toilets, Wet areas, Water Contained Structures and chemical contained
structures
vi) Other external structures such as grease trap, receptors and Bin centre
Under these indemnities, the Contractor will be required to make good any defects to
keep the whole works perfectly watertight and will be responsible for any
consequential loss attributable to leakage during the warranty period.
If in the opinion of the Contractor, the Specification, the Specifications are insufficient
COPYRIGHT BY M/S AWPPTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS5/19
OCTOBER 2021 ISSUED FOR PERMIT SECTION 5 – WATERPROOFING
for him to give the specified indemnity then the Contractor shall allow in his tender for
upgrading the Specifications as necessary to enable him to so indemnify.
5.15.1 Submissions
a Waterproofing System
b Membrane Applicator
i Name
a Sequence of Construction
COPYRIGHT BY M/S AWPPTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS5/20
OCTOBER 2021 ISSUED FOR PERMIT SECTION 5 – WATERPROOFING
ii Layout of membrane
ii Surface finishes
ii Flashing at upstands
Do not commence installation until shop and installation drawings have been reviewed
and permission to proceed has been obtained
a Waterproofing membrane
b Sealant materials
5.15.5 Procedure
COPYRIGHT BY M/S AWPPTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS5/21
OCTOBER 2021 ISSUED FOR PERMIT SECTION 5 – WATERPROOFING
5.15.6 Execution
a) Prior to commencing waterproofing, all dust, dirt and foreign matter, shall
be removed and the substrate shall be inspected and approved by
waterproofing manufacturer's representative.
i) Brand Name
ii) Manufacturer
COPYRIGHT BY M/S AWPPTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS5/22
OCTOBER 2021 ISSUED FOR PERMIT SECTION 5 – WATERPROOFING
e) For the roof, at the conclusion of the waterproofing treatment but prior to
the installation of the other components forming the roofing system, the
waterproofed area shall be tested by ponding either entirely or in
sections for at least 48 hours.
5.16 STANDARDS
Unless otherwise agreed with the architect, ensure all works comply with the relevant
requirements of the Standards and Codes listed below or referenced in the body of
the Specification. Alternative Standards and Codes may be proposed for approval by
the architect, provided it can be demonstrated that the alternative Standards and
Codes comply with the requirements of the standards specification. All Standards
and Codes quoted refer to the current version
5.17.1 Mock-ups
Prepare 1 x 1 metre panel sample of each internal floor and wall waterproofing type,
clearly showing compositional materials and components from structural slab to
COPYRIGHT BY M/S AWPPTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS5/23
OCTOBER 2021 ISSUED FOR PERMIT SECTION 5 – WATERPROOFING
finished surface. Include a sample of the floor/wall junction, the flashing around a
50mm diameter pipe and the drain outlet. Keep at least one panel of each respective
sample on site, for use as a site quality standard for the remainder of the works.
Provide additional mock-ups for the project as required by the architect.
5.18 TESTING
5.18.1 Inspections
Carry out inspections at the following stages, ensuring that the work is carried out in
a proper and orderly manner:
Carry out on site water tests at the following stages to verify serviceability and water-
tightness, in accordance with the membrane manufacturer’s recommendations and
specifications.
Do not conduct on-site water test until the membrane is cured and set.
Inform the architect 5 days prior to the tests being carried out
Carry out the water tests by blocking up the drain holes and flooding the floor to a
depth of 25mm above the highest point of the floor for 24 hours and the running of
the shower head onto each of the tiled walls for 15minutes.
Any areas showing water penetration through the floor, signs of seepage or other
defects, shall be made good. Submit a method statement and remedial measures to
the SO. Re-test the area after the remedial works have been completed.
COPYRIGHT BY M/S AWPPTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
SS006_External & Internal Aluminium Works
JKT05 SS6/1
OCTOBER 2021 ISSUED FOR PERMIT SECTION 6 - ALUMINIUM WORKS
SECTION 6
The Specialist’s Contractor shall design, engineer, test, fabricate, deliver, install and
guarantee all construction necessary to provide the External and Internal Aluminium
Works, complete with all accessories and components, in conformance with the
requirements of the drawings and specifications. The work shall be carried out under
the direction of the Main Contractor.
The references made under the specification ‘Metalworker’ applies equally to this
section.
Without limiting the generalities of the foregoing, the works shall include, without being
limited to:
i. Aluminium windows and glazing, curtain walling, aluminium letterbox and trap
door.
ii. Bolts, fasteners and secondary metal work connecting the Aluminium Works to
the structure.
iii. All anchors, attachments and reinforcements for mullions and transoms as
required for a complete installation.
vi. All caulking, polyurethane sealing and flashing as required for a watertight
assembly.
x. Shop drawings.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS6/2
OCTOBER 2021 ISSUED FOR PERMIT SECTION 6 - ALUMINIUM WORKS
Other Standards
Aluminum
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS6/3
OCTOBER 2021 ISSUED FOR PERMIT SECTION 6 - ALUMINIUM WORKS
ASTM E 283 Standard Test Method for Determining the Rate of Air
Specimen
Pressure Difference
Pressure Differentials
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS6/4
OCTOBER 2021 ISSUED FOR PERMIT SECTION 6 - ALUMINIUM WORKS
ASTM F 1450 Standard Test Methods for Hollow Metal Swinging Door
Factors
Organic)
SSPC Paint 25 Red Iron Oxide, Zinc Oxide, Raw Linseed Oil, and Alkyd
Primer
The tender drawings do not purport to identify or solve completely the problems of
thermal or structural movement, pressure equalization, vapor barriers, fixings and
anchorage, flatness and stability of facing, moisture disposal, etc. The drawings also
do not purport to solve problems at the glass line associated with glass movement,
pressure factor or thermal shock.
The tender drawings only indicate profile and configuration required together with
relationship to structural frame and interior building elements.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS6/5
OCTOBER 2021 ISSUED FOR PERMIT SECTION 6 - ALUMINIUM WORKS
The Sub-Contractor shall be responsible for the design of all components of the
External and Internal Aluminium works installation, including (but not by way of
limitation) frame sections and sizes, catches, locks, rating gears, glass thickness,
glass location, weather stripping and neoprene gaskets, to meet all performance
requirements and shall be subject to the approval of the Architect.
The design drawings of the Sub-Contractor will be subject to the inspection and
acceptance of the Architect and Contractor, and will subsequently form part of the
Contract Documents.
Shop drawings, samples, etc. shall be submitted to the Architect for approval before
the Sub-Contractor is allowed to proceed with the fabrication. However, the approval
of the drawings by the Architect shall not absolve the Sub-Contractor from all
responsibilities and liabilities as to performance and the efficiency of the External and
Internal Aluminium Works.
Aluminium sections, assemblies, sealants and glass samples are to be submitted for
Architect’s approval prior to fabrication.
Mock-up unit of typical open able and fixed units to be submitted to for approval prior
to fabrication.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS6/6
OCTOBER 2021 ISSUED FOR PERMIT SECTION 6 - ALUMINIUM WORKS
All assemblies shall comply with relevant CP. The arithmetic mean of the sound
transmission loss at 1/3 active bands over frequency bands from 125 Hz shall not be
less than 40 dB for fixed panels and 36 dB for operable windows.
The whole External and Internal Aluminium Works assemblies and their individual
components shall comply with all local or other statutory requirements. The Sub-
Contractor will be fully responsible for any submissions to the relevant authorities as
may be necessary to demonstrate the compliance with statutory requirements of any
material used in the assemblies.
All window and doorframes shall be Polyester Powder-Coated treated and shall be
designed, fabricated, supplied and installed as manufacturer’s recommendations and
to the approval of the Architect. Colour is to be determined only after the
submissions of the relevant sample by the contractor and approved by the Architect.
Aluminium unit shall be framed with corners of adequate strength and design to
prevent distortion, reinforced with steel as necessary and with hardwood cores where
required and factory welded, riveted or bolted. All units countersunk flush where
practicable or semi-countersunk round headed where it is not practicable to
countersink fully.
Mullions, transoms and other sections are to be submitted to Architect for approval
prior to fabrication.
The Contractor shall provide all necessary accessories and fixings for proper
completion of the Works.
Frames shall be fixed in structural drawing openings using appropriate fixing lugs
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS6/7
OCTOBER 2021 ISSUED FOR PERMIT SECTION 6 - ALUMINIUM WORKS
Aluminium doors and windows shall be installed complete with all operating
ironmongery, locks, keys, etc. to the Architect’s approval.
Protective tapes, strippings, etc. shall be provided for all aluminium surfaces and
shall not be removed until final cleaning down of the building.
6.1.8 Installation
All joints between masonry and concrete shall be fully caulked with polyurethane
sealant or equivalent, a non-staining, permanently elastic and waterproof sealant.
6.1.9 Other
Requirements for warranties are given in the Contract Document. The expected life
of products used in the façade shall be confirmed by providing at least the
information below:
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS6/8
OCTOBER 2021 ISSUED FOR PERMIT SECTION 6 - ALUMINIUM WORKS
All materials that are exposed to sunlight, including materials exposed through glass,
shall not be affected due to exposure to heat or ultraviolet radiation such that the
material can no longer perform as intended, for a period of 20 years.
EQUIVALENT
6.2.1 SCOPE
A. SECTION INCLUDES
1. The extent of panel system work is indicated on the drawings and in these
specifications.
b. Parapet coping, column covers, soffits, sills, border, and filler items
indicated as integral components of the panel system or as designed.
c. Interior panel system work that basically matches exterior panel system
work.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS6/9
OCTOBER 2021 ISSUED FOR PERMIT SECTION 6 - ALUMINIUM WORKS
6. Shop drawings shall show the preferred joint details providing a watertight and
structurally sound wall panel system that allows no uncontrolled water
penetration on the inside face of the panel system as determined by ASTM E
331. Systems not utilizing a construction sealant at the panel joints (i.e. Rout
and Return Dry and Rear Ventilated System) shall provide a means of
concealed drainage with baffles and weeps for water which may accumulate in
members of the system.
6.2.3 REFERENCES
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS6/10
OCTOBER 2021 ISSUED FOR PERMIT SECTION 6 - ALUMINIUM WORKS
All window and door frames shall be either Polyester Powder-Coated treated
aluminium and shall be designed, fabricated, supplied and installed as
manufacturer’s recommendations and to the approval of the Architect.
Aluminium unit shall be framed with corners of adequate strength and design to
prevent distortion, reinforced with steel as necessary and with hardwood cores where
required and factory welded, riveted or bolted. All units countersunk flush where
practicable or semi-countersunk round headed where it is not practicable to
countersink fully.
Mullion, transom and other sections to be submitted to Architect for approvals prior to
fabrication.
The Contractor shall provide all necessary accessories and fixings for proper
completion of the Works.
Frames shall be fixed in structural drawing openings using appropriate fixing lugs
and properly bolted to the structure.
Fixed louvres shall be of weatherproof type suitable for overcoming water carry-over
by wind up to a velocity of 161 kph and have a pressure drop of not more than 40 Fa
when subjected to a gross face velocity of 150m/min for airflow directions normal to
the louvre blades.
Aluminium doors and windows shall be installed complete with all operating
ironmongery, locks, keys, etc. to the Architect’s approval.
Protective tapes, strippings, etc. shall be provided for all aluminium surfaces and
shall not be removed until final cleaning down of the building.
All aluminium façade details are to be captured within a mock up extending a min. of
1m in height and 4m in width.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS6/11
OCTOBER 2021 ISSUED FOR PERMIT SECTION 6 - ALUMINIUM WORKS
6.2.4 SUBMITTALS
A. SAMPLES
2. Two samples of each color or finish selected, 76mm (3”) x 102mm (4”)
minimum.
B. SHOP DRAWINGS
Submit shop drawings showing project layout and elevations; fastening and anchoring
methods; detail and location of joints, sealants, and gaskets, including joints
necessary to accommodate thermal movement; trim; flashing; and accessories.
E. CODE COMPLAINCE
Documents showing product compliance with the national and local building code shall
be submitted prior to the bid. These documents shall include, but not be limited to,
appropriate Evaluation Reports and/or test reports supporting the use of the product.
PRODUCTS
6.2.6 PANELS
G. COMPOSITE PANELS
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS6/12
OCTOBER 2021 ISSUED FOR PERMIT SECTION 6 - ALUMINIUM WORKS
2. Items of the same function and performance, which have received prior
approval from the architect, shall be allowed for this project. Approval shall
be based on documentation submitted showing the adequacy of the material.
I. PRODUCT PERFORMANCE
1. Bond Integrity
When tested for bond integrity, in accordance with ASTM D1781 (simulating
resistance to panel delamination), there shall be no adhesive failure of the
bond a) between the core and the skin nor b) cohesive failure of the core itself
below the following values:
2. Fire Performance
ASTM E 84 Flame Spread Index must be less than 25, Smoke Developed
Index must be less than 450.
Panel must comply with one of the following BS 476 Part 4 or BS 476 part 11
or BS 476 Part 6+7 or EN 13501-1 or NFPA 285. Panel must not have
flammable core (plastic or polyethylene core is not permitted).
J. FINISHES
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS6/13
OCTOBER 2021 ISSUED FOR PERMIT SECTION 6 - ALUMINIUM WORKS
b. Coating Thickness:
d. Impact:
e. Adhesion:
f. Humidity Resistance
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS6/14
OCTOBER 2021 ISSUED FOR PERMIT SECTION 6 - ALUMINIUM WORKS
h. Weather Exposure
1) Outdoor:
i. Chemical Resistance:
3) AAMA 2605 utilizing 70% reagent grade Nitric Acid vapor for an
exposure time of 30 minutes. Maximum color change of 5 Delta E
units as calculated in accordance with ASTM D-2244.
2. Anodized:
Color (Clear): AA-C22-A41 Architectural Class I Color Coating: AA-C22-A44,
light bronze, medium bronze, dark bronze and black.
Architectural Class I/II
3. Urethane Coating:
For small quantity aluminum accent panels or custom color applications,
provide a multi coat urethane finish in accordance with the paint
manufacturer’s requirements.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS6/15
OCTOBER 2021 ISSUED FOR PERMIT SECTION 6 - ALUMINIUM WORKS
A. COMPOSITION:
C. PANEL WEIGHT:
D. TOLERANCES
3. Panel lines, breaks, and angles shall be sharp, true, and surfaces free from
warp and buckle.
E. SYSTEM CHARACTERISTICS
3. System shall comply with the applicable provisions of the “Metal Curtain Wall,
Window, Storefront, and Entrance Guide Specifications Manual” by AAMA
and ANSI/AAMA 302.9 requirements for aluminum windows.
6. The finish side of the panel shall have a removable plastic film applied prior
to fabrication, which shall remain on the panel during fabrication, shipping,
and erection to protect the surface from damage.
F. SYSTEM TYPE
G. SYSTEM PERFORMANCE
a. Wind Load
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS6/17
OCTOBER 2021 ISSUED FOR PERMIT SECTION 6 - ALUMINIUM WORKS
Normal to the plane of the wall, the maximum panel deflection shall not
exceed L/60 of the full span.
c. Pressure Equalized Rain Screen Systems shall comply with AAMA 508-
05 Voluntary Test Method and Specification for Pressure Equalized
Rain Screen Wall Cladding Systems
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS6/18
OCTOBER 2021 ISSUED FOR PERMIT SECTION 6 - ALUMINIUM WORKS
6.2.8 ACCESSORIES
1. Extrusions, formed members, sheet, and plate shall conform with ASTM
B209 and the recommendations of the manufacturer.
3. Sealants and gaskets within the panel system shall be as per manufacturer's
standards to meet performance requirements.
6.3 EXECUTION
6.3.1 INSPECTION
1. Surfaces to receive panels shall be even, smooth, sound, clean, dry and free
from defects detrimental to work. Notify contractor in writing of conditions
detrimental to proper and timely completion of the work. Do not proceed with
erection until unsatisfactory conditions have been corrected.
6.3.2 INSTALLATION
2. Attachment system shall allow for the free and noiseless vertical and
horizontal thermal movement due to expansion and contraction for a material
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS6/19
OCTOBER 2021 ISSUED FOR PERMIT SECTION 6 - ALUMINIUM WORKS
7. Do not cut, trim, weld, or braze component parts during erection in a manner
which would damage the finish, decrease strength, or result in visual
imperfection or a failure in performance. Return component parts which
require alteration to shop for refabrication, if possible, or for replacement with
new parts.
1. Remove and replace panels damaged beyond repair as a direct result of the
panel installation. After installation, panel repair and replacement shall become
the responsibility of the General Contractor.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS6/20
OCTOBER 2021 ISSUED FOR PERMIT SECTION 6 - ALUMINIUM WORKS
5. Make sure weep holes and drainage channels are unobstructed and free of dirt
and sealants.
The aluminium ventilation and double bank louvres to be used for the building shall be
weather-tight with virtually 100% efficient at rain defense. The louvres shall be double
bank shallow section louvres. 2UL/SH louvres offer the same airflow as conventional
louvre but, in rainy weather, is five and a half times more effective at keeping rain out
with front louvres at 50mm pitch. The interval gaps between the louvers shall be
25mm.
The double bank louvre system, 2UL/SH, must be tested complying to the following:
2UL/SH offers the same airflow as conventional ‘Z’ section louvre, with tangential
separation, 50mm pitch.
Materials
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS6/21
OCTOBER 2021 ISSUED FOR PERMIT SECTION 6 - ALUMINIUM WORKS
Sealants and gaskets are used between materials that can have an adverse reaction
when in contact with each other.
Finishes
The finishes of the louvres shall be PPC -Polyester powder-coated finish to a RAL
colour to match external finishes; Colour to Architect’s selection & approval.
The ventilator is designed to be fitted into an opening and/or onto supporting members
supplied and fitted by others. Details of supports required depend upon the size of
opening and design wind load. Ventilators fitted into sheeting require a framework
round the opening.
Care must be taken to ensure that 2UL will be flushed with the wall when fitting the
framework.
Drainage
Special drainage systems are to be incorporated into each ventilator. Water is drained
down to the bottom frame, directly from the outer surface and via a system of internal
channels.
The bottom frame of 1UL and 2UL ventilators forms a cill preventing re-entainment.
Water collected on the inner louvres of 2UL is drained internally via hollow box
sections. Water is discharged from 2.5”D outlets for connection to PVC pipes
(BS4576). They should be spaced evenly along the width of the unit and fitted, if
possible, at mullion positions.
On 2UL/SH it is possible to specify the outlet with the pipe connection at the front or
rear of the ventilator. The drainage capacity of the ventilator has been calculated in
accordance with CP.308 based on rainfall of 76mm per hour. The wall area above 2UL
must be included in the calculations for drainage purposes. When exposure to gale
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS6/22
OCTOBER 2021 ISSUED FOR PERMIT SECTION 6 - ALUMINIUM WORKS
force winds and rain is expected, a gutter should be fitted to divert extra rainwater
away. In this instance the wall area would not be included in the calculations.
If the size of a single ventilator panel exceeds these limits, more than one ventilator
must be used, fitted side by side and/or one above the other.
Testing
Performance data in the Louvre Specifiers Manual is taken from tests using two test
methods.
Where possible, data has been included from tests carried out by BSRIA using the
1988 HEVAC standard ‘Method of test for water rejection performance of Lourdes
subjected to simulated rainfall’. All other data is the result of extensive testing carried
out to our own exacting standards.
Both tests are similar in concept, the HEVAC method being developed partly from the
Colt test method. The tests simulate, as far as possible, typical UK site conditions.
The HEVAC method uses a single rig, to assess both the louvre coefficient and its
rainfall rejection efficiency, simulating wind at 0 and 13m/s, rain at 75mm per hour,
and inlet airflows between 0 and 3.5m/s. The Colt test for weathering performance is
similar, but utilises a different test-rig configuration. Colt louvre coefficient tests are
carried out on a separate wind tunnel.
All tests are carried out on louvre panels of nominal face area 1m x 1m and panel area
1.2m x 1.2m.
Mock Up
Full height louvre panel with a min. of 1.5m in width (to Architect’s approval).
Guarantee/Warranty
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS6/23
OCTOBER 2021 ISSUED FOR PERMIT SECTION 6 - ALUMINIUM WORKS
The louvre systems are to be guaranteed against faulty materials and workmanship
for 10 years.
Shop drawings and approved test reports are to be submitted for approval before
installation.
All Louvres profiles into mechanical ventilation ducts, flue ducts etc on the wall or roof
level, are to be weatherproof to prevent the entry of rain or other elements into the
ducts and come with bird or insect screen installed on the interior face of the louvres
properly secured to louvre frames with stainless steel sheet metal screws located at
each corner and spaced approximately 300mm c/c around the screen perimeter.
Fabricate screen frames from the same material as louvres and join by welding or
mechanical fasteners.
Offset flush glazed, jambs and vertical mullions with continuous, head and sill
members attached by screw spline method; or continuous head and sill members with
intermediate horizontals attached by shear clips. Manufacturer's standard extruded
aluminum mullions and indicated shapes.
The thermal barrier shall consist of a single durometer EPDM glazing gasket/isolator
and isolator clips at the perimeter that minimize all metal to metal contact between the
exterior and interior. Systems employing non-structural type thermal barriers are not
acceptable.
b. Aluminum Sheet:
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS6/24
OCTOBER 2021 ISSUED FOR PERMIT SECTION 6 - ALUMINIUM WORKS
C. Glass & Glazing – Double glazed laminated glass panels with 4mm thick
polyester safety and security film (on the interior side). U-value and shading
coefficient to comply with LEED Gold Certification and MEP requirements
Setting blocks, edge blocks, and spacers in accordance with ASTM C 864,
shore durometer hardness as recommended by manufacturer; Glazing gaskets
in accordance with ASTM C 864.
6.5.1 Fabrication
A. Shop Assembly : Fabricate and assemble units with joints only at intersection of
aluminium members with uniform hairline joints; rigidly secure, and sealed in
accordance with manufacturer's recommendations.
a. Hardware: Drill and cut to template for hardware. Reinforce frames and door
stiles to receive hardware in accordance with manufacturer's
recommendations.
B. Anodized Finishing
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS6/25
OCTOBER 2021 ISSUED FOR PERMIT SECTION 6 - ALUMINIUM WORKS
D. Finishes Testing:
6.5.3 Testing
A. Air Filtration
Completed window systems shall have 0.06 CFM/FT² (1.10 m³/h·m²) maximum
allowable infiltration when tested in accordance with ASTM E 283 at differential static
pressure of 6.24 PSF (299 Pa).
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS6/26
OCTOBER 2021 ISSUED FOR PERMIT SECTION 6 - ALUMINIUM WORKS
B. Water Infiltration
Conduct field test to determine water tightness of entrance system. Conduct test in
accordance with AAMA 501.2.
C. Wind Loads
Completed window wall system shall withstand wind pressure loads normal to wall
plane indicated for both exterior and interior walls, value of which shall comply with
local standard requirements.
D. Deflection
Maximum allowable deflection in any member when tested in accordance with ASTM
E 330 with allowable stress in accordance with AA Specifications for Aluminum
Structures.
b. With Horizontals: L/175 or L/240 + 1/4" (6.4mm) for spans greater than 13'-6"
(4.1m) but less than 40'-0" (12.2m).
E. Thermal Movement:
Provide for thermal movement caused by 180 degrees F. (82.2 degrees C.) surface
temperature, without causing buckling stresses on glass, joint seal failure, undue
stress on structural elements, damaging loads on fasteners, reduction of performance,
or detrimental effects.
F. Thermal Performance for YWE 60 T when tested in accordance with AAMA 1503 and
NFRC 102:
Note: The CRF for the glazed system as a whole will be affected by the
characteristics of the glass specified.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS6/27
OCTOBER 2021 ISSUED FOR PERMIT SECTION 6 - ALUMINIUM WORKS
a. Sound Transmission Class (STC) shall not be less than: 1" IGU; 31, laminated;
34.
b. Outdoor–Indoor Transmission Class (OITC) shall not be less than: 1" IGU; 26,
laminated; 28.
6.5.4 Submittals
B. Product Data: Submit product data for each entrance series specified.
D. Shop Drawings: Submit shop drawings showing layout, profiles, and product
components, including anchorage, accessories, and finish colours.
E. Samples: Submit verification samples for colours. Minimum 2-1/2 inch by 3 inch (61
mm by 73 mm) samples on actual aluminium substrates indicating full color range
expected in installed system.
a. Test Reports: Submit certified test reports showing compliance with specified
performance characteristics and physical properties.
G. Closeout Submittals:
Install at project site a job mock-up using acceptable products and manufacturer
approved installation methods. Obtain Owner's and Architect's acceptance of finish
color, and workmanship standard.
A. Visual Mock-Up: The visual mock-up should feature full size glass panels following the
production methods and specifications of that proposed for the typical panels. The
visual acceptance of the glass is to be assessed using the visual mock-up.
6.5.6 Warranty
B. Cleaning: The General Contractor shall clean installed products in accordance with
manufacturer's instructions prior to owner's acceptance and remove construction
debris from project site. Legally dispose of debris.
C. Protection: The General Contractor shall protect the installed product's finish surfaces
from damage during construction.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
SS007_Glass & Glazing
JKT05 SS7/1
OCTOBER 2021 ISSUED FOR PERMIT SECTION 7 - GLASS AND GLAZING
SECTION 7
7.1 GENERALLY
This section describes the requirements for providing glass and glazing and specified
to include:
a. Curtain Wall, Aluminium window system, entrances and shop front, if any.
c. Glass Screens
e. Joint Sealers
External glazing selection & details shall comply with requirements to design
standards/ performance which equivalent to LEED Gold Certification standards.
7.2 STANDARDS
Unless other wise agreed by Architect, ensure all of the works comply with the
relevant requirements of the Standards and Codes listed below or referenced in the
body of the Specification. Alternative Standards and Codes may be submitted to the
Architect, provided it can be demonstrated that the alternative Standards and Codes
comply with the requirements of the standards specified. All standards and Codes
quoted are the current version, unless specific year references are noted.
Other Standards
ASTM C 1048 Standard Specification for Heat-Treated Flat Glass-Kind HS, Kind FT
Coated and Uncoated Glass
ASTM E 773 Test Method for Seal Durability of Sealed Insulating Glass Units
ASTM F 1450 Standard Test Methods for Hollow Metal Swinging Door Assemblies
for Detention Facilities
ASTM E 1886 Standard Test Method for Performance of Exterior Windows, Curtain
Walls, Doors, and Impact Protective Systems Impacted by Missile(s)
and Exposed to Cyclic Pressure Differentials
GSA-TS01 Standard Test Method for Glazing and Window Systems Subject to
Dynamic Overpressure Loadings
NFRC 200 Procedure for Determining Fenestration Product Solar Heat Gain
Coefficient and Visible Transmittance at Normal Incidence
NFRC 300 Test Method for Determining the Solar Optical Properties of Glazing
Materials and Systems
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS7/3
OCTOBER 2021 ISSUED FOR PERMIT SECTION 7 - GLASS AND GLAZING
BS 6206 British standard impact testing for annealed glass with applied safety
film
BS 6399-1 Loading for buildings – Part 1: Code of practise for dead and
imposed loads
Provide glass and glazing that has been produced, fabricated and installed to
withstand normal thermal movement, wind loading and impact loading (where
applicable), without failure including loss or breakage of glass, failure of sealants or
gaskets to remain watertight and airtight, deterioration of glass and glazing materials
and other defects in the work.
7.4 SUBMITTALS
Submit manufacturer's technical data for each glazing material and fabrication glass
product required, including installation and maintenance instructions.
7.4.2 Samples
Submit, for verification purposes, 600-mm square samples of each type of glass
indicated except for clear single pane units, and 600-mm long samples of each colour
required (except black) for each type of sealant or gasket exposed to view. Install
sealant or gasket sample between two strips of material representative of adjoining
framing system in colour.
The Architect will be concerned about the ‘Flatness’ of the proposed glass panels. The
Contractor will provide manufacturers data relating to Flatness and arrange for a visit
by the Architect to a completed example of the proposed glass in a curtain wall floor to
floor glass installation.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS7/4
OCTOBER 2021 ISSUED FOR PERMIT SECTION 7 - GLASS AND GLAZING
7.4.3 Certificate
Submit certificates from respective manufacturers attesting that glass and glazing
materials furnished for project comply with requirements
Submit statement from sealant manufacturer indicating that glass and glazing
materials have been tested for compatibility and adhesion with glazing sealants and
interpreting test results relative to material performance, including recommendations
for primers and substrate preparation needed to obtain adhesion.
a Glazing Standards
iv Except where permanent labels are required, each glass lite shall have
a removable label which will be removed only after acceptance of glass.
All glass panels within 1000mm of adjacent floor levels, where safety glass is
indicated or required by authorities having jurisdiction, provide type of products
indicated which comply with relevant ANSI and testing requirements of 16 CFR
Part 1201 for category II materials.
c Fire Resistance Glass as specified shall meet with the fire rating required and
tested in recognised laboratory and have the test certificate recognised and
acceptable by the Singapore Fire Authority or local Fire Authority.
Submit samples of all glass, gaskets, glazing accessories, and glass framing
members proposed for use in contact with, or proximity of, glazing sealants, to
sealant manufacturer for compatibility and adhesion testing in accordance with
sealant manufacturer’s standard testing methods and the following
requirements:
i Submit not less than 9 pieces of each type and finish of glass framing
member and of each type, class, kind, condition, and form (monolithic,
laminated, insulating units) of glass for adhesion testing and one
sample of substrates (gaskets, setting blocks and spacers) for
compatibility testing.
iii. Direct water spray primarily at aluminum head, jamb, and sill
sections for no less than 10 minutes.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS7/6
OCTOBER 2021 ISSUED FOR PERMIT SECTION 7 - GLASS AND GLAZING
Protect glass and glazing materials during delivery, storage and handling to comply
with manufacturers’ directions and as required to prevent edge damage to glass, and
damage to glass and glazing materials from effects of moisture including
condensation, of temperature changes, of direct exposure to sun, and from other
causes.
Environmental Conditions: Do not proceed with glazing when ambient and substrate
temperature conditions are outside the limits permitted by glazing material
manufacturer or when joint substrates are wet due to rain, frost, condensation or other
causes.
The contractor shall identify the manufacturer for the glass and glazing materials for
Architect’s approval.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS7/7
OCTOBER 2021 ISSUED FOR PERMIT SECTION 7 - GLASS AND GLAZING
ASTM C 1036 Type I, (transparent glass, flat) Class 2 (tint heated absorbing
and light reducing), Quality q3 (glazing select)
a By horizontal (roller hearth) process with roll wave distortion parallel with
bottom edge of glass as installed, unless otherwise indicated.
7.12.1 General
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS7/8
OCTOBER 2021 ISSUED FOR PERMIT SECTION 7 - GLASS AND GLAZING
b Provide polyvinyl butyral interlayer, not less than 30 mil thickness, for
laminating panes of glass, with a proved record of showing no tendency to
bubble, discolour or lose physical or mechanical properties after laminating and
installation, in clear or colours and of thickness indicated; "Saflex"; Monsanto
co. or equal.
Polyvinyl butyral interlayer for laminating panes of glass, with a proved record
of showing no tendency to bubble, discolour or lose physical or mechanical
properties after laminating and installation
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS7/9
OCTOBER 2021 ISSUED FOR PERMIT SECTION 7 - GLASS AND GLAZING
Fire resistance glass shall be a multi-ply sheet glass with special intumescent and
armour shield interlayer. The glass shall be manufactured with an extremely light
“whisky” tint.
The fire rating of the glass shall be 2 hours and tested successfully according to the
relevant International ISO Standard and several national standards. The glass shall
also be designed to safety behaviour according to relevant BS impact test standards.
This standard details the impact performance requirements for flat safety glass. When
a 12mm glass is submitted to an impact of 540 Joule (about 400 lbs-ft):
a there is no perforation
The fire resistance glass shall transforms itself into the complete protective barrier
when exposed to fire as follows:
a For the first few minutes of the fire, the transparency of glass is preserved,
allowing occupants and firemen the opportunity to see through the glass and
evaluate the severity of the outbreak.
b As the heat intensity increases, the special in tumescent interlayer expand, and
the glass becomes completely opaque:
ii ensures that bystanders do not see any flames, nor feel any heat,
thereby reducing the danger of panic during evacuation
c Even when a fire develops temperatures of 850°C and over the glass
maintains constant and complete protection :
i as the heat of the fire increases, the temperature on the side opposite the
fire remains very low (about 100°C) as there is little heat transfer by
conduction or convection
d The special structure of glass ensures that no heat-radiation passes from the
fire-side to the other side. This complete elimination of heat-radiation is of the
utmost importance in the effective containment of fire.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS7/10
OCTOBER 2021 ISSUED FOR PERMIT SECTION 7 - GLASS AND GLAZING
a Elastomer strip (elastozel tape T1). Any foam strip with closed cells can
be used.
d Fiberfraz Tape – to be used at top side only, for 17mm and 19mm
glass unit
7.15.1 General
Provide products of type indicated and complying with the following requirements:
a Compatibility
Select glazing sealants and tapes of proven compatibility with other materials with
which they will come into contact, including glass products, seals of insulating glass
units, and glazing channel substrates, under conditions of installation and service, as
demonstrated by testing and field experience.
b Suitability
d Colours
Provide colour of exposed sealants indicated or, if not otherwise indicated, as selected
by architect from manufacturer's standard colours.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS7/11
OCTOBER 2021 ISSUED FOR PERMIT SECTION 7 - GLASS AND GLAZING
Type S; Grade NS, Glass 25; Uses NT, G. A, and, as applicable to uses indicated, O;
and complying with the following requirements for modulus and additional joint
movement capability.
a Medium Modulus
Tensile strength of not less than 45 nor more than 52,730 kg/m2 at 100
percent elongation when tested per relevant ASTM after 14 days at 20 deg. C
and 50 percent relative humidity.
b Additional capability
When tested per relevant ASTM for adhesion and cohesion under maximum
cyclic movement, to withstand the 40% increase and decrease of joint width,
as measured at time of application, and remain in compliance with other
requirements of relevant ASTM.
c Manufacturer
c Dense gaskets of EPDM are also acceptable, provided the material conforms
to all requirements of relevant ASTM, except for flame propagation.
d Mould all corners of all interior gaskets where compatible with installation
procedure.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS7/12
OCTOBER 2021 ISSUED FOR PERMIT SECTION 7 - GLASS AND GLAZING
7.17.1 Compatibility
a Setting blocks and setting block chairs shall be secured against migration.
b Setting blocks and edge blocks shall be sized and located in accordance with
FGMA Glazing Manual.
7.17.4 Spacers
4mm thick film polyester passing ANSI Z97.1 or BS 6206 or EN12600 at 150 ft. lb.
impact, tear resistant, penetration resistant with an acrylic, abrasion resistant
coating, able to reduce UV through glass and tested in accordance with ASTM D
1004.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS7/13
OCTOBER 2021 ISSUED FOR PERMIT SECTION 7 - GLASS AND GLAZING
One-Way Vision Glazing Films, where necessary, shall be installed as per the
manufacturer’s instructions and specifications. The applied material shall be as
follows :
• Internal Film
Opacity – Opaque
Colour – Black
• External Film
7.18 EXAMINATION
Require Glazier to inspect work of glass framing erector for compliance with
manufacturing and installation tolerances, including those for size, squareness, offsets
at corners; for presence and functioning of weep system; for existence of minimum
required face or edge clearances; and for effective sealing of joinery. Obtain Glazier's
written report listing conditions detrimental to performance of glazing work. Do not
allow glazing work to proceed until unsatisfactory conditions have been corrected.
7.19 PREPARATION
a Pre-installation Meeting
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS7/14
OCTOBER 2021 ISSUED FOR PERMIT SECTION 7 - GLASS AND GLAZING
Protect glass from edge damage during handling and installation; use a rolling block in
rotating glass units to prevent damage to glass corners.
b Use suction cups to shift glass units within openings; do not raise or drift glass
with a pry bar.
c Rotate glass with flares or bevels along one horizontal edge which would occur
in vicinity of setting blocks so that these are located at top of opening.
d Remove from project and dispose of glass units with edge damage or other
imperfections of kind that, when installed, weakens glass and impairs
performance and appearance.
Apply primers to joint surfaces where required for adhesion of sealants, as determined
by pre-construction sealant-substrate testing.
7.21 GLAZING
Install setting blocks of proper size in sill rabbet, located one quarter of glass width
from each corner, but with edge nearest corner not closer than 150-mm from corner
unless otherwise required. Set blocks in thin course of sealant that is acceptable for
heel bead use.
Provide spacers inside and out, of correct size and spacing to preserve required face
clearances, for glass sizes larger than 1270 united mm (length plus height), except
where gaskets or glazing tapes with continuous spacer rods are used for glazing.
Provide 3.2-mm minimum bite of spacers on glass and use thickness equal to sealant
width, except with sealant tape use thickness slightly less than final compressed
thickness of tape.
Set units of glass in each series with uniformity of pattern, draw, bow and similar
characteristics.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS7/15
OCTOBER 2021 ISSUED FOR PERMIT SECTION 7 - GLASS AND GLAZING
Force sealants into glazing channels to eliminate voids and to ensure complete
"wetting" or bond of sealant to glass and channel surfaces.
Tool exposed surfaces of sealants to provide a substantial "wash" away from glass.
Install pressurised tapes and gaskets to protrude slightly out of channel, so as to
eliminate dirt and moisture pockets.
Where wedge-shaped gaskets are driven into one side of channel to pressurise
sealant or gasket on opposite side, provide adequate anchorage to ensure that gasket
will not "walk" out when installation is subjected to movement.
Protect exterior glass from breakage immediately upon installation by use of crossed
streamers attached to framing and held away from glass. Do not apply markers to
surfaces of glass. Remove non-permanent labels and clean surfaces.
Protect glass from contact with contaminating substances resulting from construction
operations. If, despite such protection, contaminating substances do come into
contact with glass, remove immediately by method recommended by glass
manufacturer.
Examine glass surfaces adjacent to or below exterior concrete and other masonry
surfaces at frequent intervals during construction, but not less often than once a
month, for build-up of dirt, scum, alkali deposits or staining. When examination reveals
presence of these forms of residue, remove by method recommended by glass
manufacturer.
Remove and replace glass which is broken, chipped, cracked, abraded or damaged in
other ways during construction period, including natural causes, accidents and
vandalism.
Wash glass on both faces not more than 4-days prior to date scheduled for
inspections intended to establish date of Completion in each area of Project. Wash
glass by method recommended by glass manufacturer.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS7/16
OCTOBER 2021 ISSUED FOR PERMIT SECTION 7 - GLASS AND GLAZING
Functional liquid crystal film is a film which is able to transform between a transparent
state and an opaque state with a flick of a switch. This product is designated to be
used on the glass separating the L1 NOC Command Centre with corridor along GL-3.
The extent of this product should be read in conjunction with the related drawings.
This should be a product supplied by Seiko Innovative Light film or any other
approved equivalent products by the Architect. The crystal film chosen shall be the
‘sticking type’. It is a layer of ‘functional Liquid Crystal film with transparent and
opaque capabilities to be stuck onto the glass.
Features:
• High Permeability
• Low Voltage Drive – Energy saving low rated voltage of AC50V is used.
Voltage used is not large enough to risk harm to humans and electricity fees
are not charged when it is opaque.
Application methods:
The Functional Liquid Crystal Film is to be stuck onto the designated glass. This glass
Is to be stuck on via an adhesive layer/sticking film which is connected to an exclusive
control box with voltage below AC50V. The application of the film should be carried
out by the relevant designated sub-contractor who is approved by the supplier for
carrying out the task.
This includes the sticking on of the film to the connection of the electrical wiring
between the film and the exclusive control box. A proper plan of work has to be
submitted to the Architect before any work is to be carried out. A licensed electrician is
to be present to carry out any relevant electrical work.
The work done must 1) guarantee the implementation of a protective function to the
exclusive control box and 2) provide a low voltage drive (50V).
a) The value of the current that goes through the human body
The size of the current and the time that the current might pose a danger here will be
reduced with the exclusive control box of the sticking tppe. This implementation will
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS7/17
OCTOBER 2021 ISSUED FOR PERMIT SECTION 7 - GLASS AND GLAZING
provide a safe protective function that can detect an electric leakage of 1mA
(minimum of detective current) and disconnection within 0.5 seconds.
The time in which the current goes through someone must fall within AC2 category of
the response curve of humans to an alternating current. This category demonstrates
that the response time of the human body to different current and the period of time
must have ‘no harmful psychological effect’.
When a person standing on the earth touches a live part gets an electric shock, we
call the voltage that applies to human as contact voltage. Depending on various
contact condition (including it’s possibility), allowable contact voltage is different.
The contact condition and voltage reference value that this falls within with reference
to the ‘Guide of protection from earth leakage in low voltage circuit by the Japan
Electric Association’ should fall within the category of ‘Type 3’. The contact condition
for this category states that except for type 1 and 3, there is high possibility that
electric voltage applies to someone at all times. The electric circuit where humans
have easy access to (For example, electric tools which may easilty be touched by
humans, in houses, factory, offices and such usual places,). This Contact Voltage
should be lower than 50V.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS7/18
OCTOBER 2021 ISSUED FOR PERMIT SECTION 7 - GLASS AND GLAZING
o In the case of reinstallation or reuse after being taken off, it will not be
guaranteed.
o Ununiformity of opaqueness may appear, which does not influence its use.
Depending on the surrounding environment of functional liquid crystal film
which includes the condition of sunshine and lighting, cases of spotting or
being seen through may appear.
o Since influence such as pressure or twisting from the ambient set or frame,
etc., when installing it, can decreases the degree of opaque, cases of spotting
or being seen through may happen.
o When using sticking type consequently, please make sure the distance
between the different pieces of film to be 1mm. at minimum, and to insert
insulated calking compound in between.
o Be careful not to use conductive calking compound.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS7/19
OCTOBER 2021 ISSUED FOR PERMIT SECTION 7 - GLASS AND GLAZING
o After functional liquid crystal film is delivered to the customer, requests for size
modification (cutting work and dimension adjustment) are not accepted.
o Make sure to connect an ground wire to the exclusive control box (power
source).
7.24 INDEMNITIES
All glazing related works and glass installed onsite shall be lodged with the Architects
by the Contractor with 10 years indemnity against any glazing related defects, seal
failures, and interpane dusting and misting.
Under this indemnity, the Contractor will be required to replace, make good any
defects and failure in the glazing, glazing related works and any defects arising from
installation. The contractor will be responsible for any consequential loss attribute to
any failure in the glazing and glazing related works during the warranty period.
1. Provide new conforming glass units to replace glass units which break for a
period of one year.
2. Units broken by impact, fire, earthquake, or similar events which exceed the
design loads and conditions are not subject to this requirement.
4. Include all labor and materials for replacement of failed unit(s). Replacement
shall include coordination with the Owner, immediate provision for maintaining
openings secure and weather tight, timely ordering and fabrication of
replacement items as required, installation, and cleaning.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
SS008_Epoxy Flooring
JKT05 SS8/1
OCTOBER 2021 ISSUED FOR PERMIT SECTION 8 – EPOXY FLOORING
SECTION 8
8.1 GENERAL
8.1.1 Summary
A. Scope of Specification
8.1.2 References
Referenced publication within this specification shall be the latest revision, unless
otherwise specified, and applicable parts of the referenced publication shall become a
part of this specification as is fully included.
8.1.3 Submittals
A. General: Submit the following items to the Architect/ Engineer for review in
accordance with the Contract requirements.
B. Product Data: For each type of product specified, include manufacturer’s technical
data, installation instructions, and recommendations for each resinous terrazzo
flooring component required.
C. Sample for Initial Selection: Manufacturer’s colour charts showing the full range of
colours, textures, and patterns available for each resinous terrazzo flooring system
indicated.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS8/2
OCTOBER 2021 ISSUED FOR PERMIT SECTION 8 – EPOXY FLOORING
a. Work shall not proceed without proper results from moisture testing for
each flooring system and area of Work.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS8/3
OCTOBER 2021 ISSUED FOR PERMIT SECTION 8 – EPOXY FLOORING
C. Close spaces to traffic during resinous terrazzo flooring application and for not less
than 24 hours after application, unless manufacturer recommends a longer period.
8.1.7 Warranty
The Owner shall receive a written guarantee against defects due to improper material
and installation for a period of 10 years following the completion of installation.
8.2 PRODUCTS
a. Flowcrete
b. Approved equivalent.
8.2.2 Materials
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS8/4
OCTOBER 2021 ISSUED FOR PERMIT SECTION 8 – EPOXY FLOORING
D. Metal Edge Strips: Provide Zinc Alloy or Aluminium edge strips, 14B & S gauge, of
depth to suite flooring.
8.3. EXECUTION
8.3.1 Inspection
C. Moisture test – additional means ---- Perform polyethylene sheet cover test for
excessive moisture in each area prior to starting Work. Test shall conform to
ASTM D- 4263, as follows:
a. Securely tape heavy gauge clear plastic film to concrete floor. The sheet
shall remain undisturbed for a period of 24 hours, and then inspected. The
presence of condensation, moisture, or dampness on the concrete or
plastic sheet indicates excessive moisture in the concrete slab.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS8/5
OCTOBER 2021 ISSUED FOR PERMIT SECTION 8 – EPOXY FLOORING
b. Sheet film shall be 18 inches square and 4 mils thick. Duct tape shall be
used for fastening plastic sheet to substrate.
8.3.2 Preparation
C. Substrate Level: The level of the floor substrate for receiving resinous terrazzo
flooring shall be not more than 3mm deviation over 3 metres straight edge
(BS8204; SR1).
E. Use patching and fill material to fill holes and depressions in substrates according
to manufacturer’s written instructions.
F. Protect adjacent surfaces from damages resulting from work of this trade.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS8/6
OCTOBER 2021 ISSUED FOR PERMIT SECTION 8 – EPOXY FLOORING
8.3.3 Installation
A. GENERAL
B. SURFACE PREPARATION
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS8/7
OCTOBER 2021 ISSUED FOR PERMIT SECTION 8 – EPOXY FLOORING
d. Within 24 hours of the application of primer, mix & spread the epoxy
terrazzo screed at manufacturer’s recommended coverage rate by using
hand trowel or screed box slightly thicker than the required thickness and
compact to the required thickness using a steel bladed trowel.
D. TRAFFICKING
A. Retain the empty product containers for the purpose of determining the actual
average coating thickness.
A. Protect resinous terrazzo flooring from damage and wear during the remainder of
construction period. Use protective methods and materials, including temporary
covering, recommended in writing by resinous terrazzo flooring manufacturer.
B. Clean resinous terrazzo flooring not more than 4 days before dates scheduled for
inspections intended to establish date of Substantial Completion in each Project
area. Use cleaning materials and procedures recommended in writing by resinous
flooring manufacturer.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS8/8
OCTOBER 2021 ISSUED FOR PERMIT SECTION 8 – EPOXY FLOORING
Slip Resistance : TRRL Pendulum Slip Test Dry >40 low slip potential
8.3.6 Mock-Up
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
SS009_Mock-ups & Tests
JKT05 SS9/1
OCTOBER 2021 ISSUED FOR PERMIT SECTION 9 – MOCK-UPS AND TEST
SECTION 9
9.1 GENERAL
9.2 SUMMARY
9.2.1 This Section describes the requirements for testing mock-ups of exterior façade,
wall elements and visual mock ups of exterior façade, wall elements and of interior
building and finishes elements. There may be requirements for additional mock-
ups stated in the various sections of this specification.
9.2.2 Testing Mock-ups: Provide full-scale mock-ups of exterior façade, wall for
evaluation of colour, texture, alignment, general appearance and quality of
workmanship, and for specified performance tests.
b. Façade: Metal Roof & Walling, Curtain Wall, ACP Cladding & Fixed/
Removable Alum. Louvre systems.
Exterior Visual Mock-ups (Located off site) shall be provided for the
following components & systems:
i. Pre-Cast Wall System (including sealants, pre-cast off form wall, etc)
ii. Façade system: Metal Roof & Walling, Window Wall Glazing System,
ACP Cladding, Fixed/ Removable Alum. Louvre, Alum. Louvre
screening systems
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS9/2
OCTOBER 2021 ISSUED FOR PERMIT SECTION 9 – MOCK-UPS AND TEST
iii) Masonry –
b. A wall including window set into each of the masonry wall types.
The windowis to include the lintel, DPCs, weepholes, sill and
sealant. The sample can form part of the final construction
a. One wall, location to be agreed upon with the Owner, shall be used
for the mock-up of all render finishes for approval
vi) Façade & Glazing Works: external Alum. Window & Glazing System.
vii) External Alum & Steel Works: Fixed/ Removable Alum. Louvre system,
fixed Alum. Louvre Screen system (double bank louvre), external alum.
& steel doors.
viii) Fencing works – 2-3 modules with connection system and termination
details
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS9/3
OCTOBER 2021 ISSUED FOR PERMIT SECTION 9 – MOCK-UPS AND TEST
a. Typical Corridor
c. Typical Toilet
iii) Internal Drywall system (incl. finishing & typical details) and Internal
Masonry
b. A wall including window set into each of the masonry wall types.
The window is to include the lintel, DPCs, weepholes, sill and
sealant. The approved sample shall become the control sample
and can form part of the final construction.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS9/4
OCTOBER 2021 ISSUED FOR PERMIT SECTION 9 – MOCK-UPS AND TEST
d. Carpet Tiles
viii) Colo (Data Hall) racking and Hot Aisle Containment systems consisting
of the following
a. Server Row
b. IDF Row
c. RNG Row
d. Flex Row
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS9/5
OCTOBER 2021 ISSUED FOR PERMIT SECTION 9 – MOCK-UPS AND TEST
x) Signage
xiv) Waterproofing
c. 50mm diameter pipe and drain outlet with flashing sample mock-up
Contractor to review project Construction schedule and propose Mock-up list &
schedule to determine interior mock-up items which shall be remained as control
samples for the duration of work, for Client’s & Architect’s review & approval.
Contractor shall also require to submit schedule for submission of samples at the
earliest practical time.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS9/6
OCTOBER 2021 ISSUED FOR PERMIT SECTION 9 – MOCK-UPS AND TEST
9.2.6 Responsibility: Where required the Contractor shall engage the services of an
independent testing Laboratory to administer the required testing and issue the
test report to certify whether the components of the mock-up pass the prescribed
test criteria, re-test of the mock-up or components will be required until they pass
the test.
9.4.1 Allow sufficient time in the schedule to accommodate failures of tests and
necessity to modify and re-test. The mock-up shall be erected in sufficient time to
allow final approval of window frame colour, glass selection, sealant colours, and
panel finish. Allow sufficient time to accommodate adjustments in colours and
design profiles without detrimental effects on the Project Schedule.
9.4.2 Specialist Installers approved for the project shall install the mock-ups. Personnel
representing manufacturers, fabricators, and installers of exterior wall components
shall be present during mock-up construction and testing as appropriate for
efficient evaluation and revision if required.
9.5.1 Location of Tests: Test mock-up shall be assembled at the testing facilities with
proper testing equipment and approved by the Architect: In the case where the
mock-ups are located outside Singapore and/or Jakarta, the Contractor shall be
responsible to arrange, at his own cost, for the Architect and his representatives
(total 4 persons) to witness the tests.
General: Before testing, mock-up will be evaluated for type of glass, window
frame colour, sealant colour, and metal panel finishes.
9.5.3 Glass Aesthetic Requirements: Mock-up will be used to establish the maximum
permissible roller mark distortion in the glass. Final approved mock-up glass shall
serve as a standard for the Project.
9.5.4 Test Methods: The mock-up shall be tested at the Laboratory in accordance with
the following AAMA and ASTM test procedures:
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS9/7
OCTOBER 2021 ISSUED FOR PERMIT SECTION 9 – MOCK-UPS AND TEST
1. ASTM Test Method for Rate of Air Leakage through Exterior Windows,
Curtain Walls and Doors.
9.5.6 Where tests to failure occur, furnish number of duplicate components necessary
for all tests.
9.5.7 Wind Design Pressures: As specified in Specification and the wind tunnel test
report.
1. Pre-test.
6. Repeat Test 3.
8. Repeat Test 3.
9.5.9 Pressure Tests: As specified in Specification and wind tunnel test report.
1. Pressure shall be positive and negative per code calculations for wind
pressure tests, with a limiting deflection of l/300L or 12.7-mm maximum
from resting position.
2. Tests per relevant ASTM shall show no air infiltration in excess of values
specified. Tests per the relevant ASTM shall show no leakage - defined as
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS9/8
OCTOBER 2021 ISSUED FOR PERMIT SECTION 9 – MOCK-UPS AND TEST
5. In the plane of the wall, deflection of framing members shall not reduce the
glass or panel bite below 75% of the design dimension, and shall not reduce
the glass or panel edge clearance below 25% of the design dimension or 3-
mm, whichever is greater. Restrict deflection further if required for assembly
and fit of components.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS9/9
OCTOBER 2021 ISSUED FOR PERMIT SECTION 9 – MOCK-UPS AND TEST
Incorporate approved corrective changes in the final shop drawings and the
Work
Acceptance: Installation of wall and window elements on the building shall not
proceed until mock-up testing and evaluation are finished and accepted by the
Architect.
Schedule site visual mock-up after aluminium window wall components have been
reviewed at fabrication facility.
Evaluation mock-up shall be built of the same materials, components and using the
construction procedures and subcontractors proposed for the Work.
Modifications to the Work, if needed, to obtain the quality of workmanship and finish
required in the finished structure shall be made during construction of the mock-up.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
SS010_Roofing
JKT05 SS10/1
OCTOBER 2021 ISSUED FOR PERMIT SECTION 10 - ROOFING
SECTION 10
10.0 ROOFING
10.1 GENERALLY
The whole of the roofing works are to be carried out by the Roofing Specialist
approved by the Architect.
Roof should also be suitable for fixing array of solar panels and accessible from
ground level via catladder or internal staircase.
Spit-outs are to be provided for all flat roofs with upturn beams or parapet walls
(incl. RC flat roof layer below metal roof liner system proposed at Main Building).
These spit-outs are to be located at 6000mm intervals, 50mm above the roof level,
unless otherwise indicated. Spit-outs are to be 50mm diameter, with a drip, with an
overhang from the building of 25mm, unless otherwise directed by the Architect.
Fall arrest system or maintenance safety lifeline system shall be deem provided
along with Aluminium Standing Seam Roofing & Façade Cladding system as a
part of “complete” system for used of maintenance and access purpose.
b) All surfaces to be covered with screed are to be brushed clean and well
wetted before screed is applied. All screeds shall be kept damp and
adequately cured to prevent shrinkage and cracking.
d) The 25mm thick cement screed shall be composed of one part of cement to
three parts of sand and laid to falls on concrete roof slab. Form (25 x 25)mm
angle filler at all junctions with vertical surfaces.
g) Waterproofing Membrane
l) Ballast
50mm thick (600 x 600)mm concrete slabs to be laid over insulation and
supported by appropriate underlay pads.
Sheets to be of Z55 high strength steel with 350g/m2 zinc galvanizing and
minimum 25 micron thick polyvinylidene Fluoride Coating or equivalent finish.
Galvanized steel panel clips fastened to steel purlins from ridge to eaves.
Clips should be fixed one row at a time and sheet snapped into position. The
subsequent rows of clips located so as to fit into groove of the proceeding sheet. A
spacer gauge should be used to ensure precise alignment.
All clips, starter Trims, End Trims, Ridge Capping, Ridge Closure Flashing, Fillers,
Fixing Straps, Eaves Closures and Barge Board details to be proprietary to system
unless otherwise indicated on architectural Drawings and shop drawings as
approved by Architect.
10.4.1 STANDING SEAM ROOF & WALL CLADDING SYSTEM – STANDING SEAM
ROOFING AND WALLING SYSTEM LYSAGHT LOCKSEAM™ 0.8MM BMT
COLOURBOND ® XAL or approved equivalent
Aluminium standing seam roof system manufactured from aluminium alloy (Al-Mg-
Ti) as specified in DIN 1725, material thickness min 0.80mm, 330mm cover width,
25mm deep ribs c/c spanning 600mm. Pre-treatment is a corrosion resistant
conversion coating. The primer is a corrosion inhibitive primer, nominal thickness
of 5µm. The finish exposed surface of the liner will be a PVDF finish coating with a
nominal film thickness of 20µm. The backing coat is custom formulated Shadow
Grey with film thickness 5µm.
Unless otherwise indicated in drawings or agreed by the Architect the finish colour
shall be Silver Metallic or alternative selected colour to shade and tone approved
by Architect. Stucco-embossed surface finish maybe required and should be
option available to Architect for selection.
The substrate is aluminium alloy 3105 H16, Yield Strength min 210Mpa, Tensile
Strength 250-320 Mpa, elongation >3%.
aluminium insulation foil should be laid to roof mesh with diameter 1,5mm @ 3”x3”
or as per manufacturers’ written instructions.
Note. i. The roof panels spanning the width of the building shall be continuous
with no joints and no ridge cap to avoid water permeability through the
joints.
The roofing system shall be provided with an integrated hands free fall
arrest system for upto three persons, which shall be fixed onto the standing
seam in order to avoid roof penetrations.
Aluminium standing seam roof system manufactured from aluminium alloy (Al-Mg-
Ti) as specified in DIN 1725, material thickness min 0.50mm, 400mm cover width,
65mm deep ribs c/c spanning 400mm, with a minimum 2o roof slope. Pre-
treatment is a corrosion resistant conversion coating. Roof shall be fixed with a
concealed fix system that requires no piercing fasteners and helps provide
weather tightness and superior resistance to wind uplift.
Coating Class (min.) ZINCALUME AZ150 (150g/m2) (55% Aluminium, 43.5% Zinc,
1.5% Si) as per AS1397 / IS15961 – with Super Durable Polyester
Unless otherwise indicated in drawings or agreed by the Architect the finish colour
shall be Silver Metallic or alternative selected colour to shade and tone approved
by Architect. Stucco-embossed surface finish maybe required and should be
option available to Architect for selection.
The roofing system shall be designed, fabricate and installed so that the complete
Work shall merge perfectly with the overall building architectural and present a
uniform and smooth appearance.
All flashing and capping to the roof will be manufactured from the same quality
grade and colour of material as the roofing elements.
b) Fasteners
Fasteners such as screws and other fastening devices shall be suitable for the
conditions of each application and shall be of austenitic stainless steel to prevent
galvanic action with the components fastened. Where fasteners are not
manufactured in stainless steel, then fasteners of metal compatible with adjoining
materials and having a permanent corrosion resistant finish will be used.
All external fascias, Eaves and Verges shall be manufactured from minimum
3.0mm thick aluminium, workshop fabricated to required curvature and supplied
complete with required supports. An approved non-staining silicone sealant should
be used on all joins. The fascia will be finished in a two coat PvF2 paint finish. The
colour shall match main panel colour or alternative selected colour to shade and
Tone approved by Architect. Stucco-embossed surface finish maybe required and
should be option available to Architect for selection.
Unless otherwise indicated by Architectural design intent all Verges shall be closed
by an Aerofoil profile cover plates nested over expansion joint and zipped up to
roof / wall panel (sheet). Soffit-face to be of required length and support with return
to mechanically fix or tack weld back to cantilever overhang or wall face. Detail by
manufacturer to Architect approval.
The aluminium standing seam roofing and wall cladding system will be guaranteed
for 10 years with regards to its composition, surface and tensile strength. In
addition, the Contractor and his Roofing Specialist (Manufacturer and or Supplier)
are to severally and jointly furnish a 10 years warranty that the above roofing
system shall be waterproof and watertight in terms acceptable to the Client.
10.5.1 Before commencing roof coverings, the contractor shall lodge with the Architect a
10 or 15 (dependent on roof type) years indemnity against roof leaks, after the
issue of the Completion Certificate (in the joint name of the Specialist and the
Contractor) in favour of the Employer and assigned against faulty workmanship
and premature breakdown of materials in a format approved by the Architect.
Under this indemnity the contractor will be required to make good any defects and
to keep the roofs perfectly watertight and will be responsible for any consequential
loss directly attributable to any roof leakage during the warranty period.
10.5.2 If, in the opinion of the contractor, the forgoing Specifications are insufficient for
him to give the Indemnity then he shall allow for upgrading as he shall deem
necessary to enable him to so indemnify.
10.6 RATES
10.6.1 The description of and rate for each item of ‘Roofing’, will be held to include for
taking delivery, unloading carrying in, sorting, storing, stripping or removing
protective wrapping or coverings, checking, assembling, returning packages,
handling, hoisting and placing and lowering, or fitting and fixing materials and
goods in position, adjusting, re-fixing, and for cutting away and making good,
levelling, and touching up all in accordance with the generally accepted
requirements of the specific item, including protecting and safeguarding until the
issue of the Completion Certificate.
10.6.2 The description of and rate for each item of ‘Roofing’, shall be held to include for
the cost of all tests required by the Specifications.
10.6.3 The description of and rate for each item of ‘Roofing’, shall be held to have
complied with all the foregoing requirements of the specification and drawings,
referred therein.
10.7.1 Samples
For each system type specified provide samples of each component to permit
approval of material quality, thickness, finishes and profile. Submit samples of
fasteners for approval.
10.7.2 Mock-Ups
a. Eaves
b. Ridge
c. Edge/gutter
d. Upstand
If approved, this sample mock-up panel may form part of the works.
Carry out on site water tests, upon completion of a part of the works, in
accordance with the following procedure:
a. Spray with a continuous water jet from a water hose with normal tap pressure.
Hold the hose at 1.2 m away from the roof surface. Place the hose at the level of
horizontal joints so that the jet cone scatter will cover the joints.
c. Any areas showing water seepage or other defeats shall be made good after a
method statement for reinstatement has been accepted by the SO.
d. Use tested areas as a site quality standard for the remainder of the project.
Upon completion of the roofing works and installation of rain water goods, carry
out on site drainage test to verify proper functioning and performance of the roof
drainage system, in accordance with SS CP 26.
In addition, inspections on the joints and roof sheeting shall be inspected annually.
SECTION 11
11.1 GENERAL
Read with the General Requirements section, and all other contract documents.
11.2 SCOPE
This section covers the requirements for common floor screeds applied in buildings,
including bonded and un-bonded cement sand screeds, polymer modified toppings
and resin flooring. It also covers the requirement for common floor hardeners.
Read this work section in conjunction with the relevant requirements of the other
work sections including the following:
• Waterproofing Series
• Finishes Series
11.4 STANDARDS
Unless otherwise agreed by the Architect, ensure all of the Works comply with the
relevant requirements of the Standards and Codes listed below or referenced in the
body of the Specification. Alternative Standards and Codes may be submitted to the
Architect, provided it can be demonstrated that the alternative Standards and Codes
comply with the requirements of the standards specified. All Standards and Codes
quoted are the current version, unless specific year references are noted.
SS 78 Testing of concrete
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS11/2
OCTOBER 2021 ISSUED FOR PERMIT SECTION 11 - FLOOR SCREED & HARDENERS
SS 289 Concrete
Other Standards
BS 4841 Rigid polyurethane (PUR) and polyisocyanurate (PIR) foam for building
Part 3: Code of practice for the design and installation of ceramic floor
tiles and mosaics
Part 5: Code of practice for the design and installation of terrazzo tile
and slab, natural stone and composition block flooring
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS11/3
OCTOBER 2021 ISSUED FOR PERMIT SECTION 11 - FLOOR SCREED & HARDENERS
The intended types of floor screed for the project are set out in clause 3.1 and
locations are indicated in the drawings. Base on the information; submit the following
items to the Architect.
B. Submit suitable mix and application methods taking into account of the
performance requirements as set out in clause 2.1.
Co-ordinate the screeding works particularly the interfacing with the following trades:
a. Floor finishes
b. Floor waterproofing
c. Dry walls
d. Internal masonry
Liaise and coordinate with services engineer for location of services perforations in
the floor.
Deliver to site in strong protective packages marked for identification, and store
where directed, components and materials for future replacement and repair.
11.6 WARRANTY
Provide a ten-year indemnity in accordance with contract conditions for the floor
hardeners where specified in the project.
When carrying out the proposals as set out in clause 1.4.1, take account of the
following performance requirements:
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS11/4
OCTOBER 2021 ISSUED FOR PERMIT SECTION 11 - FLOOR SCREED & HARDENERS
Take into account, that performance, appearance and proper functioning of the
screeding Works are not affected by any movements, settlement, deflection,
expansion or contraction which can be expected to occur in the building or the
construction process.
Junction between the screeding Works and adjacent work by others shall be formed
to take into account, possible structural deflections or movement in that adjacent
element without distortion to the Works, or disintegration of joints between works.
11.7.3 Environmental
Take cognisance to the environment for which the Works are to be applied, paying
particular attention to the following environmental effects:
b. For non air-conditioned areas, daily and seasonal variations in humidity and
temperature in the Tropics.
11.7.4 Appearance
Include any measures necessary to take into account, that the surface finishes are
uniform in colour and texture and appearance throughout. Achieve surface level
tolerance as set out in BS 8204.
A. Base
B. Thickness
C. Mix
Sand/Fine aggregate: To SS 31, grading limit M, but with not more than 10%
passing sieve size 150 microns.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS11/5
OCTOBER 2021 ISSUED FOR PERMIT SECTION 11 - FLOOR SCREED & HARDENERS
Mix proportions: 1:3 for flexible floor finishes and/or 1:4~4.5 for thick or rigid floor
finishes.
D. Finish
E. Soundness
3mm for areas expected to take very heavy traffic and/or where disruption, dust
or pollution may occur. 4mm for areas expected to take heavy traffic including
heavy trolleys e.g. public areas and main corridors. 5mm for other areas subject
to mainly foot traffic and light trolleys.
A. Base
Separating Layer or DPM on concrete that will not provide a good bond e.g.
smooth high strength concrete.
B. Thickness
D. Mix
Mix proportions: 1:3 for flexible floor finishes and 1:4~4.5 for thick or rigid floor
finishes.
E. Finish
F. Soundness
A. Base
B. Thickness
D. Mix
b. Sand/Fine aggregate: To SS 31, grading limit M, but with not more than 10%
passing sieve size 150 microns.
c. Mix proportions: 1:3 for flexible floor finishes and 1:4~4.5 for thick or rigid floor
finishes.
E. Finish
F. Soundness
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS11/7
OCTOBER 2021 ISSUED FOR PERMIT SECTION 11 - FLOOR SCREED & HARDENERS
A. Base
B. Thickness
D. Mix
b. Sand/ Fine Aggregate: To SS 31, grading limit M, but with not more than 10%
passing sieve size 150 microns.
E. Finish
A. Construction
a. 40-50 mm Bonded
b. 50-65 mm Unbonded
c. 65-75 mm Floating
D. Insulation
E. Manufacturer
F. Mix
b. Sand/Fine aggregate: To SS 31, grading limit M, but with not more than
10% passing sieve size 150 microns.
G. Finish
H. Soundness
PVA materials are water sensitive. Do not use in areas where permanent dampness
is expected.
A. Base
B. Construction
Bonded.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS11/9
OCTOBER 2021 ISSUED FOR PERMIT SECTION 11 - FLOOR SCREED & HARDENERS
D. Manufacturer
E. Mix
F. Finish
G. Soundness
A. Base
B. Construction
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS11/10
OCTOBER 2021 ISSUED FOR PERMIT SECTION 11 - FLOOR SCREED & HARDENERS
D. Mix
d. Proportions: 1:1:2
E. Finish
A. Base
B. Construction
Bonded.
C. Manufacturer
D. Mix
E. Finish
F. Surface Hardness
G. Slip Resistance
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS11/11
OCTOBER 2021 ISSUED FOR PERMIT SECTION 11 - FLOOR SCREED & HARDENERS
A. Base
B. Construction
Fully Bonded. This type of topping should fully reflect any movement joints within
the structural base
C. Manufacturer
D. Mix
E. Finish
Refer to clause 3.1 for selected proprietary product to be used for movement joint.
Bed in 1:3 cement/sand centred over joint and to finished floor level. Mechanically fix
with stainless steel screws to base.
Closed cell polyethylene filler, bond breaking tape and sealant as noted in clause 3.1.
Proprietary water based metallic fluorosilicate and wetting agents solution designed
for the hardening of concrete surfaces. Submit suitable product to the SO. If no
metallic hardener is specified, proprietary non-metallic hardener may be submitted to
the SO.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS11/12
OCTOBER 2021 ISSUED FOR PERMIT SECTION 11 - FLOOR SCREED & HARDENERS
11.11 WORKMANSHIP
Before starting work ensure that Bases are sufficiently flat to permit specified levels
and flatness of finished surfaces, bearing in mind the permissible minimum and
maximum thicknesses of the screed/topping. Bases are clean and free from plaster,
dirt, dust and oil.
Shortly before laying screed/topping completely remove mortar matrix from surface
to expose coarse aggregate over entire area of hardened base slab using abrasive
blasting or, for in situ slabs only, pneumatic scabbling. Remove all dust and debris.
Keep base slab well wetted for several hours before laying screed/topping. Remove
free water then brush in recommended bonding agent: cement slurry. Lay
screed/topping while slurry is still wet to ensure a good bond.
Before surface of base slab has completely hardened brush off all surface laitance
with a stiff broom. Thoroughly clean base slab and keep well wetted for several
hours before laying screed. Remove free water then brush in recommended bonding
agent: cement slurry. Lay screed/topping while slurry is still wet to ensure a good
bond.
Lay separating sheet of polythene not less than 65 microns thick (250 gauge) on
base and lap all joints not less than 50 mm.
Lay insulation with tight butt joints and turn up for full depth of screed at all wall
abutments.
Lay separating sheet of polythene not less than 125 microns thick (500 gauge) with
50 mm laps. Lay wire netting to BS 1521, mesh size 50 mm, wire designation 19
over separating sheet with 50 mm laps tied securely with tying wire at 300 mm
centres.
11.11.6 Conduits
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS11/13
OCTOBER 2021 ISSUED FOR PERMIT SECTION 11 - FLOOR SCREED & HARDENERS
11.12.1 Batching
11.12.2 Mixing
Keep water content of mixes to the minimum, slump not exceeding 25 mm,
necessary to achieve full compaction, low enough to prevent excessive water being
brought to the surface during compaction. Mix materials thoroughly to a uniform
consistency. Mixes other than no-fines must be mixed in a suitable forced action
mechanical mixer: do not use a free fall type (drum) mixer.
Use all mixes within 2 hours or time limit set out by supplier / manufacturer. Discard
all left over mixes. Use while sufficiently plastic for full compaction.
11.13 LAYING
Fully compact by double beam vibrator or plate vibrator or, where this is not
practicable, by hand.
Ensure that movement joints are taken through the full depth of the screed and are
clean prior to the insertion of the filler strip.
Unless otherwise specified, bay sizes to be not more than 16m², ratio of length to
breadth not more than 3:2, a joint occurring over every construction joint in the base
slab. Where location of bay joints is not shown on drawings obtain approval before
starting work.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS11/14
OCTOBER 2021 ISSUED FOR PERMIT SECTION 11 - FLOOR SCREED & HARDENERS
Forms to be square edged with steel top surfaces, securely fixed. Compact
thoroughly at edges to give level, closely abutted joints with no lipping. Alternatively,
toppings may be cast continuously, bay joints being formed with approved plastics or
metal dividing strips.
11.14 FINISHING
11.14.1 Timing
Carry out all finishing operations at optimum times in relation to the setting and
hardening of the material. Do not wet surfaces to assist surface working. Do not
sprinkle cement onto surface.
Use a wood float to give an even slightly coarse texture with no ridges or steps.
Trowelled finish to receive applied floor finishes. Float to an even surface with no
ridges or steps.
Hand or power trowel to give a uniform smooth but not polished surface free from
trowel marks and other blemishes, and suitable to receive the specified flooring
material.
11.15 PROTECTION
Adequately protect the surface from construction traffic. If, because of inadequate
finishing or protection, the surface of the screed is not suitable to receive the
specified flooring material, submit to the SO and carry out remedial measures.
11.16 HARDENERS
11.16.1 Application
Allow concrete floor to cure for 14 days prior to treatment. Remove all loose material,
laitance or grease contamination. Prepare solution of hardener strictly in accordance
with manufacturer’s instructions. Apply only to dry surfaces. Brush out to prevent
ponding, allow the solution to be absorbed for two hours, do not let the floor dry out
during this period. While the floor is still damp wash with clean water and dispose of
surplus solution. Re-Apply further coat to dry surface after 24 hours ensuring the
floor is dry.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS11/15
OCTOBER 2021 ISSUED FOR PERMIT SECTION 11 - FLOOR SCREED & HARDENERS
11.17 CURING
a. Immediately after laying, protect surface from wind, draughts and strong
sunlight.
b. As soon as screed/topping has set, closely cover with polythene sheeting and
keep in position for not less than 7 days.
A. Submissions
B. Work Submissions
a. Sequence of construction
b. Method statements
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS11/16
OCTOBER 2021 ISSUED FOR PERMIT SECTION 11 - FLOOR SCREED & HARDENERS
11.19.1 Mock-ups
Each sample to be no smaller than 2mx2m and to include movement joint and
skirting when the latter is formed from the screed material.
11.20 TESTS
A. Tap Tests
Tap test all screeded areas four weeks after laying at intervals at 1m intervals
and submit a report to the Architect. There shall be no hollows in the completed
screed.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
SS012_Bricklayer, Blockwork & Plaster
JKT05 SS12/1
OCTOBER 2021 ISSUED FOR PERMIT SECTION 12 – BRICKLAYER, BLOCKWORK & PLASTERING
SECTION 12
12.1 GENERALLY
This section covers requirements for the erection of masonry walls, including
common clay bricks, concrete blocks and Autoclave Aerated blocks. Whenever a
material, item, article or product is specified by trade/brand name, manufacturer's
name or catalogue reference, the Contractor propose to use its equivalent in the
Works, subject to the written confirmation of the Architect.
12.2 STANDARDS
Unless otherwise agreed by Architect, ensure all of the works comply with the
relevant requirements of the Standards and Codes listed below or referenced in the
body of the Specification. Alternative Standards and Codes may be submitted to the
Architect provided it can be demonstrated that the alternative Standards and Codes
comply with the requirements of the standards specified. All standards and Codes
quoted are the current version, unless specific year references are noted.
SS 26 Portland Cement
Other Standards
Concrete
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS12/2
OCTOBER 2021 ISSUED FOR PERMIT SECTION 12 – BRICKLAYER, BLOCKWORK & PLASTERING
12.3 BRICKS
All common bricks shall be of a standard size of even shape, hard, well burnt,
machine-made pressed bricks with true arises. Bricks to be regular in shape and
meet the requirements of relevant BS and PSB. Bricks will have a minimum
compressive strength of 35MN/mm2.
Bricks shall be delivered to the Site by the supplier and shall be carefully stacked in
convenient positions on arrival. All bricks shall give a clear ring when struck with a
trowel or another brick. No soft or defective bricks are allowed and no bats or broken
bricks shall be used except for closers.
12.4 SAMPLES
The Contractor shall supply sample bricks and blocks for the approval of the
Architect before delivery to the Site and all bricks and blocks delivered must not fall
below the standard of the approved samples.
Further samples of bricks and blocks taken at random from the load shall be
deposited with and be approved by the Architect before being used and all
subsequent deliveries shall be up to the standard of that approved.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS12/3
OCTOBER 2021 ISSUED FOR PERMIT SECTION 12 – BRICKLAYER, BLOCKWORK & PLASTERING
The removal of bricks and blocks not up to the standard of the approved samples
shall be at the expense of the Contractor as it shall be his responsibility to accept
from the suppliers’ bricks or blocks of the approved standard only.
12.5 MORTAR
The sand for mortar is to comply with relevant British Standard and is to be clean,
sharp fresh water river or naturally occurring sand free of organic impurities to be
washed and screened if so directed by the Architect.
Mortar shall consist of cement and sand in the proportions of one part Portland
cement to six parts sand, by volume, with an approved plasticiser added, in
accordance with the manufacturer’s printed instructions.
The use of plasticiser or other additives may be allowed upon application being
made to the ARCHITECT. Any such plasticiser or additives that are permitted shall
be used strictly in accordance with the manufacturer’s printed instructions.
All mixing boards and boxes are to be cleaned at the end of each day’s work, and all
unused mortar is to be removed from the Site.
The Contractor shall provide proper setting out rods and shall set out on the same
all works showing openings, heights, sills and lintels and shall build the various walls
and piers to the thickness, widths and heights as shown in the drawings. No part of
the walling shall be constructed more than one meter higher than any other part at
any one time and in such cases the jointing shall be made in long steps and not by
toothing so as to prevent cracks arising. All walls shall be levelled around at floors
and all brickwork must be built in level courses, no four courses of brickwork to rise
more than 300mm.
Proper plumbing must be carried out to ensure those brick walls constructed are
perpendicular to the floor throughout its height and length. Brick walls that are not
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS12/4
OCTOBER 2021 ISSUED FOR PERMIT SECTION 12 – BRICKLAYER, BLOCKWORK & PLASTERING
Before commencing any brickwork, the Contractor shall confer with other specialist
contractors to ensure that all pipes, conduits, drains, sleeves, bolts, hangers, door
and window fixing lugs or timber pellets or any other materials necessary to be
installed in the brickwork at the time it is built have been fixed or provided for.
All bricks shall be well wetted by being soaked in clean water for at least half an hour
before use and tops of walls where left off shall be wetted before re-commencing
building. Clean all supporting surfaces and remove loose mortar before laying units
All joints shall be 10mm thick and flushed up and grouted in solid as the work
proceeds.
All constructed brickwork and block work must be cured with water for 5 days and
protected from sun rays 2 days after laying.
Except where specified to be fair face, all faces of brickwork and walling shall be left
rough and the joints raked out to a depth of 10mm whilst the mortar is green to form
adequate key for plaster.
Tops of walls where built to underside of soffits to be pointed up with 25mm layer of
‘Flexell’ or similar approved expansion jointing material. In the case of fire resisting
walls, the walls including associated steelwork must provide fire separation and
smoke sealing between rooms/compartments to the fire rating as indicate in the
drawings. Where noted on drawings install fire sealants to vertical and horizontal
joints and intumescent paint to the steelwork to achieve the required fire
performance.
Frames, grounds, bearers etc. to be fixed to walls to be built in as the work proceeds
and are to be bedded solidly at the back in cement mortar and pointed.
Mesh Reinforcement is to be laid, every fourth course (Every course for walls less
than 100mm thk.). Mesh to be galvanised steel or Grade 1.4401 stainless steel
0.3mm thick.
Walls on ground floors, roof, carparking floors, external wall or party to a ‘wet’ room
etc, to be built off a DPC at slab level. Damp proof course to be in accordance with
BS:743.
Where brick units occur on sloped ramps, cut bottom course to maintain horizontal
jointing.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS12/5
OCTOBER 2021 ISSUED FOR PERMIT SECTION 12 – BRICKLAYER, BLOCKWORK & PLASTERING
All half-brick thick walls throughout the work shall be built entirely in stretchers and
shall be laid so that there is always a lap of one brick over another of half a brick. All
one brick walls and over throughout the works shall be built in English Bond in the
best-approved manner. All piers and intersections and angles of walls shall be
properly bonded together. All must be built in level courses; no four courses to rise
more than 300mm.
All perpends, reveals, quoins and other angles of the walls, etc. shall be built strictly
true and square.
Bonding ties shall be 6mm diameter mild steel rods, galvanised once kneed, not less
than 450mm long, hooked both ends, one cast into concrete columns and the other
built into the brickwork at every fourth course, where brickwork or blockwork abuts
concrete columns.
Start joint reinforcing 225mm above supporting floor slab or first course above
supporting floor slab. Stagger ends of joint reinforcing in jointing courses and lap
150mm. Provide joint reinforcing in 2 horizontal mortar joints 75mm and 150mm
above and below wall openings, extending beyond each side of opening. Terminate
joint reinforcing not more than 50mm from openings, expansion joints and control
joints. Longitudinal wires of joint reinforcing not to be less than 18mm or more than
25mm from each face, woth longitudinal wires fully embedded in mortar.
Where brickwork or blockwork abuts steel stanchions, the bonding ties shall be
welded for a length of 75mm, to the steelwork.
Rake out joints of brickwork or cut grooves for turn-in of flashings, wedge with
hardwood wedges and point in cement mortar (1:3) where required.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS12/6
OCTOBER 2021 ISSUED FOR PERMIT SECTION 12 – BRICKLAYER, BLOCKWORK & PLASTERING
(ii) Lightweight blocks shall be laid with cement and lime mortar of 1:6 mix with
approved plasticiser. Horizontal and vertical joints should be 10mm thick.
Lightweight concrete blocks or foam concrete should satisfy the following technical
specifications.
Thickness : ± 2mm
The blockwork shall be laid in stretcher bond. Lay first course on DPC with sand
cement bed so that the first course is level and plump. Lay subsequent courses on
thin bed adhesive, tapping the blocks with a rubber mellet to achieve level. Walls
shall be carried up in a uniform carefully levelled every second course and
reinforced with ‘Exmet’ every forth course, maximum at 1m high interval, and on one
portion raised more than 800mm above another at any time. Corners shall be well
bonded, plumbed and all perpendicular and quoins kept true and square.
Broken or cracked blocks shall not be used. Face of blocks shall not vary from the
general vertical face of wall by more than 3mm. The cement mortar joint thickness
shall be approximately 10 mm thk. Blocks should be bedded and jointed in cement
and sand mix of 1:4 with approved plasticiser. All fair face internal and external
concrete blocks walls shall be flushed pointed in 1:3 (Masonry Cement: Sand Mix or
Ordinary Portland Cement: Sand Mix with approved plasticiser) at least three days
after the blocks have been laid.
The work shall be executed course by course and every third course shall be
levelled.
Steam cure all concrete block, air dry for not less than 30 days before delivery. All
blocks shall be well wetted before being laid.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS12/7
OCTOBER 2021 ISSUED FOR PERMIT SECTION 12 – BRICKLAYER, BLOCKWORK & PLASTERING
All walls and corners shall be well bonded, plumb and true, and all perpends and
quoins shall be kept strictly true and square. No broken or cut blocks shall be used
in the work.
Except where specified to be fair faced, all faces of blockwork and walling shall be
left rough and the joints raked out to a depth of 13mm whilst the mortar is green to
form adequate key for plaster.
Openings for doors, windows and ventilators, etc shall be properly marked out and
left unbuilt until the wooden frames have been fixed in position. All timber frames
shall be built in as the work proceeds.
All door frames, window frames and vent frames, plates, etc. shall be bedded in
13mm thick cement mortar (1:6 incorporating plasticiser).
All door frames shall be carefully fixed and stayed in position and shall be anchored
into walls with 38 x 3mm galvanised m.s. holdfasts of 225mm girth, one end turned
up 75mm and twice countersunk drilled and screwed to frame and other end
swallow-tailed and built into joints of walling at approximately 600mm centres.
All putlog holes shall be carefully, properly and completely filled up on completion of
walling work and before any plastering work commences.
Cut out any defective bricks found in the work after completion and replace with
sound ones at the Contractor's expense.
Cut and pin or build in ends of bars, railings and the like and make good in cement
mortar. Leave or form all holes, mortices, openings and the like in brick walls for
fittings, pipes and the like and make good in cement mortar (1:6 incorporating
plasticiser) to the satisfaction of the ARCHITECT
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS12/8
OCTOBER 2021 ISSUED FOR PERMIT SECTION 12 – BRICKLAYER, BLOCKWORK & PLASTERING
12.17 LINTELS/STIFFENERS
Provide masonry lintels where shown and where openings of more than 300mm for
brick size units and 600mm for block size units are shown without structural steel or
other supporting lintels.
Provide precast lintels made from concrete matching concrete masonry units in
color, texture, and compressive strength and with reinforcement bars indicated or
required supporting loads indicated.
Joint reinforcing shall comprise 6mm diameter galvanised steel double wire mesh
formed of two parallel wires 50mm on centres with electrically welded cross wires at
regular intervals. Panel anchors shall be 38mm wide x 1mm thick x 600mm long
galvanised steel perforated strips.
Bed blocks on mortar mixed in the ration of 1:3 by volume. All mortar joints shall be
full and not furrowed. Steel tools shall not be used to tap glass blocks.
Unless otherwise indicated on the drawings, joint width shall generally be 10mm.
Lay Glass Blocks complete with sealant joints, expansion strips, panel anchors and
reinforcing wires and separate from any adjoining masonry by expansion and gliding
joints. Expansion and gliding joints to consist of compressible filler and sealant.
Provide metal reinforcement and flashing of the types recommended by the
manufacturer of the sill. Lay the glass block in strict compliance with manufacturer’s
recommendation.
Where glass block panels abut dissimilar elements such as walls, slab soffits, etc.,
install panel anchors at 600mm centres anchored to the adjoining element in a
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS12/9
OCTOBER 2021 ISSUED FOR PERMIT SECTION 12 – BRICKLAYER, BLOCKWORK & PLASTERING
suitable manner and extending into the glass block mortar joints that contain the
reinforcing.
Place succeeding courses of blocks in a similar fashion, striking joints smooth while
the mortar is still plastic and before final set. Tool joints to be concave.
Surplus mortar shall be removed and faces of the blocks wiped dry at the time the
joints are tooled.
Final cleaning shall be carried out after the mortar has attained final set but before
becoming dry on the block surfaces. Clean with water and glass-cleaning detergent
specifically recommended for such purpose. Do not use abrasive cleaners, such as,
steel wool, wire brushes or acid.
12.19 CEMENT
All cement used in the works to be as specified in Engineer's Specification for Concrete
Works.
All sand used in the works to be as specified in Engineer's Specification for Concrete
Works but is to be fine sand of light colour and to be approved by the Architect.
The clay-plus-fine silt cement shall not exceed 5% by weight and 15% by volume as
specified in BS 1199.
Where there is a suspended false ceiling all wall finishes shall rise a minimum of 50mm
above the height of the suspended ceiling and be finished off in a neat straight line.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS12/10
OCTOBER 2021 ISSUED FOR PERMIT SECTION 12 – BRICKLAYER, BLOCKWORK & PLASTERING
All arrises, internal angles, external angles, etc shall be straight plumbed and slightly
rounded.
When concrete occurs in a brick or block background, allow for differential movement as
follows: fix expanded metal lathing over to walls on each side; apply first coat to lathing
and cut through on both sides, before first coat has set, apply second coat. Use
Expamet Strip Mesh (ref. 779-100) 100mm wide tight coat galvanized steel.
Securely fix with plaster dabs reinforced with galvanised nails plugged. Coat nails and
cut ends with bitumen.
All making good is to be cut out to a rectangular shape, the edges undercut to form
dovetailed key and finished flush with face of surrounding plaster.
Cut out and make good all cracks, blisters and other defects and leave the whole of the
work perfect on completion.
No partially or wholly set plaster or paving will be allowed to be used or re-mixed and
must be removed from the site.
Plastering may not be required to concrete soffits should the concrete surfaces be
smooth and even. However, should the concrete surfaces of concrete walls, columns,
beams and other concrete works be smooth and true to plane and shape a skim coat
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS12/11
OCTOBER 2021 ISSUED FOR PERMIT SECTION 12 – BRICKLAYER, BLOCKWORK & PLASTERING
to even but minor defects is acceptable. The skim coat shall be pure masonry cement
slurry.
The Architect shall decide whether wall surfaces are sufficiently smooth and true to
plane. Refer also to Accuracy in Plastering.
Drips and grooves should be formed to give a clean clear and straight surface free
from loose sandy mortar.
The plane of any smooth untextured finished surface of plaster, which is at least 13mm
thick, is to be controlled to within 3mm. Measure between the face and any point along
a 1.8m straight edge placed against it.
For plastering to receive wall tiling, finish the surface accurately so that any gap under
a 2m straight edge laid on the surface is not greater than 3mm for tiling to be fixed with
adhesive, or 6mm for tiling to be fixed with sand cement.
Minimum thickness of plaster shall be maintained by forming thickness markers of
backing coat plaster during application at approximately 1m centres both ways.
Finishing coat shall be applied to at least the outer surface of these markers to ensure
minimum thickness.
All mortars for plastering are to be mechanically or hand mixed as directed by the
Architect, and the Contractor is to make allowance for the use of additional cement
necessitated by the method of mixing instructed. Only whole bags of cement are to be
used in any one batch of mix.
12.28.7 SAMPLES
The Contractor is to prepare, demolish and amend a sample three square metres of
such type of plastering as directed until the quality, texture and finish required is
obtained and approved by the Architect after which all plastering executed is to equal
the approved samples.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS12/12
OCTOBER 2021 ISSUED FOR PERMIT SECTION 12 – BRICKLAYER, BLOCKWORK & PLASTERING
ITEM DESCRIPTION
Cement and sand (1:3) plaster shall be mixed on clean boards in a sheltered place in a
batch mixer and shall consist of one part of cement to three parts of sand and be applied
in two coats to a total thickness of 20mm as specified.
The first coat to be 10mm or 13mm thick rough plastering and shall be cross scored to
receive the second coat which shall be 3mm or 7mm thick finished with a steel trowelled
smooth finish internally and wood float finish externally.
External plastering shall be mixed with an approved plasticiser used strictly in
accordance with the manufacturer's printed instructions.
Cement and sand (1:4) plain face plaster shall be mixed on clean boards in a sheltered
place in a batch mixer and shall consist of one part of cement to four parts of sand and
be applied in two coats to a total thickness of 20mm as specified.
The first coat to be 10mm or 13mm thick rough plastering and shall be cross scored to
receive the second coat which shall be 3mm or 7mm thick finished with a steel trowelled
smooth internally and wood float finish externally.
External plastering shall be mixed with an approved plasticiser used strictly in
accordance with the manufacturer's printed instructions.
Unless otherwise stated, all internal and external brick walls and concrete surfaces flush
with brick walls are to have 20mm thick cement and sand plain face plaster.
Unless otherwise stated, all internal exposed concrete soffits and sides and soffit of
beams are to have 15mm thick cement and sand plain face plaster.
Unless otherwise stated, all external exposed concrete soffits and sides and soffit of
beams are to have 20mm thick cement and sand plain face plaster.
Provide cement and sand plastering to areas as indicated on the Architect's drawings
and the Schedule of Finishes.
ITEM DESCRIPTION
A WALL TILING
The tiles are to be bedded in cement mortar (1:3) with mortar buttered on to the back of
the tiles to give a bed of 3mm, after which the tiles are to be pressed and tapped home
on and including cement and sand backing (1:3) mix overall 20mm thick taking care to
keep the joints as recommended by the tile manufacturer.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS12/13
OCTOBER 2021 ISSUED FOR PERMIT SECTION 12 – BRICKLAYER, BLOCKWORK & PLASTERING
The joints are to be pointed with approved neat white or coloured cement.
The tiles shall be thoroughly soaked in clean water before fixing.
Erect the wall tiles to areas as indicated in the Architect's Schedule of Finishes.
Overall thickness of the ceramic wall tiles and cement and sand backing shall be
minimum 20mm thick.
The wall tiling is to be neatly cut at all junctions with walls, etc. and to be neatly fitted
around all obstructions such as pipes, etc. and laid strictly in accordance with the
manufacturer's printed instructions.
Tiling works are to include for all internal and external angles.
Clean off all dirt, stains, etc. replace all damaged and defective tiles and leave tiling
perfect on completion.
B SHOP DRAWINGS
Submit shop drawings indicating the layout of special tile patterns for the approval of the
Architect.
C PRODUCT DATA
Submit manufacturer's printed instructions for mixing and installation of all materials
used in this section of the Specification.
D PRODUCT HANDLING
Deliver materials, other than bulk items, in manufacturer's unopened containers fully
identified with grade labels, brand name, type, class, size, colour, pattern, etc. Store all
materials in suitable conditions and protect from weather and damage from any source.
Store in accordance with manufacturers printed instructions.
E EXTRA STOCK
Deliver to the Owner, at the Project Site, ten (10) unopened boxes of each type of tile
installed and 2 litre can of each type of factory prepared dry set mortar, grout and
adhesive.
ITEM DESCRIPTION
Conditions of surfaces to receive tile shall be firm, dry, clean and free of oil or waxy
films.
Grounds, anchors, plugs, hangers, bucks, electrical and mechanical work in or behind
tile shall be installed prior to proceeding with tile work.
Ensure that the substrates to receive tile are free of any defects detrimental to the work.
Do not proceed with the work until defects are corrected. Commencement of work
indicates acceptance of substrates.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS12/14
OCTOBER 2021 ISSUED FOR PERMIT SECTION 12 – BRICKLAYER, BLOCKWORK & PLASTERING
All toilet rooms have been designed and dimensioned for full tile size. Tile cutting will not
be permitted unless otherwise approved by the Architect.
Lay out tile work in pattern shown using field tile and trim shapes as shown or as
required. Centre tile fields in both directions in each space or on each wall and adjust to
wall dimensions.
Extend tile work into recesses and under or behind equipment and fixtures, to form a
complete covering without interruptions, except as otherwise shown. Terminate work
neatly at obstructions, edges and corners without disrupting pattern or joint alignments.
Accurately form intersections and returns. Perform cutting and drilling of tile without
marking visible surfaces. Carefully grind cut edges of tile abutting trim, finish or built-in
items for straight aligned joints. Fit tile closely to electrical outlets, piping, fixtures and
other penetrations so that plates, collars, or covers overlap tile.
Use uniform joint widths of 1.5mm for homogeneous/ ceramic/ porcelain tile (whichever
applicable) to wall (or as recommended by the tile manufacturer).
Surface Preparation
Allow render to cure for at least 7 days prior to tiling. Do not apply rendering over
existing structural or movement joint. The render should consist of 3 or 4 parts (by
volume) suitable sand to one part cement mixed with clean drinkable water. The render
should be left with a wood float finish at approximately 10mm in thickness.
Surface to receive tiles must be clean and free from dust, oil, grease and all loose
contaminating materials. Ensure surfaces are dry before tiling with no residue or
permanent dampness. Do not wet the tiles before laying, if the back of tiles are very
dusty, remove dust with a damp sponge.
ITEM DESCRIPTION
Provide horizontal and vertical joints at every 5 metre centres and at every internal
corner unless otherwise stated the width of expansion joints shall match the tile joints.
The joints must be kept free of adhesive and grout dropping during the progress of
works.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS12/15
OCTOBER 2021 ISSUED FOR PERMIT SECTION 12 – BRICKLAYER, BLOCKWORK & PLASTERING
Provide pointing with approved silicone sealant to all internal expansion joints and
approved polysulphide sealant to all external expansion joints, all in strict accordance
with the manufacturer's printed instructions.
The tiles of approved size, thickness, colour and pattern are to be bedded in cement
mortar (1:3) with approved mortar adhesive on to the back of the tiles on and including
cement and sand backing (1:3) mix taking care to keep the joints as thin as possible all
in accordance with the manufacturer's printed instructions.
Tile setting and grouting materials for wall tiling works shall be as described in 'PAVIOR'.
Clean off all dirt, stains, etc. replace all damaged and defective tiles and leave tiling
perfect on completion.
The homogeneous/ ceramic/ porcelain (whichever applicable) floor tiles are to be
supplied and installed by the Contractor to respective areas as shown in the Schedule of
Finishes.
The Contractor is required to furnish a Warranty and Indemnity for tile adhesive to the
Employer against any defects, failures, etc for a period of ten (10) years.
ITEM DESCRIPTION
The marble or granite wall slab/tiles used in the works shall be as described under
"Pavior", where applicable.
The marble or granite slab/tiles are to be laid to patterns/designs and including jointing
with cement and sand (1:3) mix with approved tile adhesive in the appropriate mix
proportions and all necessary fixing accessories, wastage of materials in handling and
cutting, laying of tiles, supervision and profit and everything else necessary for the
completion of the respective items.
All marble/granite slab shall be from an approved source and shall be of best quality
sound stock, carefully selected, uniform in colour, pattern, markings, texture and finish,
free from defects impairing strength, durability or appearance such as cracks, seams,
mineral stains, quarry sap, holes, flaws, imperfections, or unusual accumulation of
discolouration in any area. Patching or filling is not permitted. All units shall be examined
to ensure uniformity and matching of colour, pattern, markings, texture, finish, etc. to
that of the approved unit. Delivered stone shall match the approved samples and any
stone not matching the approved samples may be rejected by the Architect. All
necessary arrangement must be made to match the texture, vein and colour of
marble/granite slabs before installation.
The wall tiling is to be neatly cut and mitred at all junctions with walls, etc. and to be
neatly fitted around all obstructions such as pipes, etc. and laid strictly in accordance
with the manufacturer's printed instructions.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS12/16
OCTOBER 2021 ISSUED FOR PERMIT SECTION 12 – BRICKLAYER, BLOCKWORK & PLASTERING
Before polishing of granite or marble, all blemishes and holes of the granite or marble
shall be filled with approved filler consisting of matching granite/marble chips and hand-
polished where applicable and as directed by the Architect.
All corners shall be mitred with matching finishes. All joints and gaps shall be sealed with
approved tinted cement grout with neat flush pointing.
Clean off all dirt, stains, etc. replace all damaged and defective tiles and leave tiling
perfect on completion.
The Contractor and the Manufacturer/Agent are required to furnish a Joint Warranty and
Indemnity for tile adhesive to the Employer against any defects, failures, etc. for a period
of ten (10) years.
Generally granite skirting shall be 15mm x 100mm high x 600mm length, mitred at
corners.
Generally compressed marble skirting shall be 12mm x 100mm x 600mm long mitred at
corners.
Compressed marble skirting to curved walls shall be 12mm x 100mm high in equal
segments of wedges to suit the curvature of the wall. Segments shall be max. 150mm
long.
All skirting’s shall be bull nosed as shown.
12.29 MOCK-UPS
A 1m x 1m panel of each of the masonry types shall be set up at a location agreed with
the SO/CM.
A wall including window set into each of the masonry wall types. The window is to
include the lintel, DPCs, weepholes, sill and sealant. The sample can formpart of the
final construction.
Masonry works shall not proceed until SO/CM has approved the mock-ups.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
SS013_Concrete Wall Panels
JKT05 SS3/1
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
SECTION 13
13.1 GENERAL
13.2 STANDARDS
Unless otherwise agreed by Architect, ensure all of the works comply with the
relevant requirements of the Standards and Codes listed below or referenced in the
body of the Specification. Alternative Standards and Codes may be submitted to the
Architect provided it can be demonstrated that the alternative Standards and Codes
comply with the requirements of the standards specified. All standards and Codes
quoted are the current version, unless specific year references are noted.
Other Standards
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/2
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
Part 108 Method for making test cubes from fresh concrete.
BS3148 Methods of test for water for making concrete (including notes on
the suitability of the water).
BS5328 Part 1 to 4
Panel to be Dowel Bar fixed to 250mm high, 100mm wide RC kerb. RC kerb to have
(75x50x2)mm thick MS perforated continuous angle support.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/3
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
13.4 SPECIFICATIONS
a) 600mm width
b) 100-150 mm thickness
a) Test result of the panel must be in accordance with British Standard BS 476:
Part 20 and 22 (Fire Resistance Test).
a) 100mm thick wall panel shall not be less than STC 40 rating when tested to
ASTM E90.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/4
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
13.4.10 Non-Combustible
• Test result of the panel must be in accordance with American Standard ASTM
C236 and shall not exceed 0.50W/mC
The panel shall manufactured by the process of extrusion with sanding of both
surfaces of the panel process. The manufacturing process shall be as follows:
A.Ensure that the workers have been properly trained to handle and erect the panel.
C.The panels can be laid horizontally above door or window openings not more that
5000mm wide and 2000mm high. Provided the manufactures guidelines are
strictly adhered to.
D.The opening the M&E services can be cut with timber working tools and joined as
specified in the manufactures guidelines.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/6
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
Weight 75kg/ m2
Non-Combustibility
Pass
BS 476: Pt 4
Fire Rating
75 mins
BS 476: Pt 20
Sound Insulation 40 dB
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/7
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
13.21.1 Specification:
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/8
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/9
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/10
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/11
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
The tolerance in manufacture for units will be generally in accordance with BS 8110
Part 1: 1985: Section 6: Subsection 11.3 except that the permissible deviations from
designed dimensions will be as follows:
13.22.2 Overall length and width (measured at neutral axis of ribbed members)
3m or under : 3mm
3 - 6m : +3mm, - 4mm
6m - 12m : 6mm
Each additional 3m : 1.5mm
Total thickness or flange thickness : -3mm,+ 6mm
Rib thickness : 3mm
Distance between ribs : 3mm
Angular variation of plane of side mould : 0.5mm per 75 mm of depth or
1.5mm, whichever is greater
Variation from square or designated skew : 1.5mm per 2.0m diagonal or
(difference in length of the two diagonal measurements) : 10mm, whichever is greater.
Length and width of blockouts and openings within : 6mm one unit
Location and dimensions of blockouts hidden from : 18mm view and used for HVAC
and utility penetrations
Dimensions of haunches : 6mm
Haunch bearing surface deviation from specified plane : 3mm
Difference in relative position of adjacent haunch : 6mm bearing surfaces from
specified relative position
Bowing : L/360, max. 18mm
Differential bowing between adjacent panels of the :12mm
same design
Local smoothness : 6mm in 3m
Warping : 1.5mm per 300mm of
distance from the nearest
adjacent corner
Location of window opening within panel : 6mm
Position of plates : 18 mm
Tipping and flushness of plates : 6mm
Position tolerances. For cast-in items measured from datum line location as shown on
approved erection drawings:
Weld plates : 18mm
Inserts : 9mm
Handling devices : 50mm
Reinforcing steel and welded wire fabric : 6mm
Where position has structural implications or affects concrete cover, otherwise 9mm
Tendons : 3mm
Flashing reglets : 6mm
Flashing reglets at edge of panel : 3mm
Reglets for glazing gaskets : 1.5mm
Groove width for glazing gaskets : 1.5mm
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/12
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
13.23.1 The pre-cast panels to be used are Autoclaved Lightweight Aerated Concrete Panel
(ALC), a product of FBM Engineering Pte Ltd or any other approved equivalent.
13.23.2 Introduction
The ALC panel is made by raw materials such as cement, lime and silica sand. This
panel will be made to form partition panels for this building’s usage.
13.23.3 Specification
Width : 600mm
Length : 6000mm
The ALC panels are in organic non-combustible materials and have absolute
incombustibility properties. At up to 700 degrees Celsius, the ALC panels should not
experience any strength loss and a 15 cm thick wall should be able to resist fire for
as long as 4 hours. This should be a Class A fireproof construction material.
No smoke or toxic gas should be released from the ALC panels during fire. The ALC
panels should effectively resist fire, spread of fire and protect the internal from the
impact of fire.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/13
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/14
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/15
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
ALC absolute dry densities of different grade products are 400-600 kg/sqm. This is a
lightweight product which reduces labour intensity during construction. ALC panels
can be used with reinforcing bar according to the design to meet a variety of load-
bearing requirements. Reinforcing bar in the panels perform stabilized, toughening
and impact resistance functions. Before producing panels, it is necessary to rationally
design the plate reinforcement (including structure and size of reinforcing bar)
according to the load requirements of the specific projects, making bearing capacity,
shear resistant, stiffness and deflection indicators to meet the requirements. After
production, the panels muste be tested through sampling to review whether the
structure performance meets the load requirements.
ALC Panel
Fire Resistance
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/16
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
1) No surface treatment 40
3 1) No surface treatment 42
1) No surface treatment 44
8.33 pc/m2
77kg/m2
Noise insulation of the ALC Panels are between 40-60DB. ALC has a dual nature,
soud absorption and sound resistance.
Study shows that besides structural reasons, the seepage of external walls is
generally infiltrated from the masonry mortar joint, but ALC panels mainly use special
adhesive mortar joint denser than ordinary masonry mortar joint, thus they greatly
reduce the seepage probability. The technical ability ensures that the inside holes of
ALC products are independent closed holes, and their diameter is about 1-2mm, so
that they can prevent the moisture diffusion effectively.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/17
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
Precise Size
ALC products are of precise sizes and the tolerance of length, height and width is
+1.0mm. Precise sizes make it possible to avoid cracking by the way of coating thin
mortar and putty.
Dry Construction
This aerated concrete products can be installed by the way of dry masonry
continuous operation. They are not restricted from the height of one time masonry, so
they can highly improve the speed of construction. When special adhesive is used to
dry masonry installing our blocks, it does not need watering in the surface of blocks
to be wet. After installation, the surface ALC product walls can be directly coated with
putty. Without watering and heat conservation, it effectively reduces cracks caused
by masonry wall shrinkage as a result of expansion and contraction due to change of
water content. It not only reduces the construction difficultly, but also is conducive to
the quality of the project and shortens project period.
Easier to process than wooden products, these ALC products can be processed
simply into different shapes as per your demand. They are easy to groove and do not
need much time spent in cutting. Various processing methods like sawing, drilling,
nailing, hanging, craving and coating thin-layer mortar make it easier and more
flexible to bury pipeline and do second decoration.
ALC Panels are lightweight and easy-processed, which may ease labour intensity.
Internal and external walls can be constructed at the same time, so construction
speed is faster and labour costs are reduced. ALC panels are masoned and coated
by dry powder mortar. Heat insulation time is reduced, project time is shortened by
about 2/3.
Shrinkage rate of ALC products is much smaller than national standard 0.5mm/m and
other wall materials. The smaller the dry shrinkage rate, the better the anti-cracking
ability. Moreover, dry construction avoids wall cracking because of dry shrinkage.
ALC panel is masoned by special mortar whose thickness is only 3mm, so cracking
possibility of the gap is greatly lowered. Wall is elastically connected, which is
beneficial to avoid cracking even if the base subsides
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/18
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
ALC panels can be used directly in internal wall of concrete structures and steel
structures, such as in hotels, schools, offices, market places and houses etc. The
internal walls such as household walls, separating walls, partition walls in bathroom
and kitchens etc, conform to hang various things such as air conditioning, water
heater, radiator, hanging cases, etc. Compared with traditional internal wall partition
materials, ALC internal panels have obvious advantages in various technical
performances; lightweight, high strength, thermal insulation, fire resistance, sound
insulation, seepage prevention, frost resistance, durability, anti-seismic, high
softening coefficient, no radiation, good creativity, scientific installing method,
convenient and quick construction.
ALC internal panels are reinforced by antirust double-layer and two way steel mesh.
They have good load-bearing capacity, the static hanging weight in a single point
being 120kgs. They are produced in high temperature, high pressure and steam
curing, with the minimum shrinkage ratio in the inorganic materials, caulked with
special polymer binders, which can effectively prevent cracking.
Specifications
ALC panels can be used directly in exterior walls of concrete structures and steel
structures. As an excellent heat insulator, they surpass most other similar building
materials. They are also guarantee of a comfortable and pleasant environment inside
the buildings, with lower heating and cooling costs throughout the lifespan of a
building.
ALC panels improve the reliability and security of node strength in external walls.
During the rotation and extension in plane of the connecting nodes of wallpanels,
ALC panels ensure that the walls can be adapted to the interlayer displacement in
different directions of the main structure and satisfies the need for the interlayer
deformation of the main structure conforming to the seismic design intensity.
The installation nodes of ALC panels are scientifically designed, with high strength
and a certain amount of rotating performance. It can bear an interlayer displacement
of between 1/200 to 1/50 without damage or only a minor damage.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/19
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
ALC panels are regarded as constructional elements with flexible connection in terms
of seismic design, so their stiffness and seismic bearing capacity are not counted.
Structure members supporting the ALC external panels can count the effect of
seismic action of ALC wall panels as an additional effect and meet the anchoring
requirement of connecting accessories.
Preparation
1. Check the drawing before construction, and compose on designing, the width of
partition wall should fit multiples of 600mm, we should better arrange the rest near
the concrete column or the side of wall. It's inadvisable to arrange it near the
windows and doors.
2. Clean up the joint part between panels and roofs, sand, soil and so on. All the
mortar and concrete which are bulged out over the walls should be cleaned up.
3. According to the drawing, mark the columns, beams, floor which is connected with
Panel, and pop the two-side upper and lower line of control by using ink fountain.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/20
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
METHOD OF STATEMENT
On-site.
While composing and the 600mm modulus. If the width can't fit the multiples of
600mm, we should better arrange the rest near the concrete column or the side of
the walls. Its inadvisable to arrange it near the windows and doors.
Clean up the joint part between panels and roofs, floors and walls. Clean the floating
ash, sand, soil and so on. All the mortar which are bulged out over the walls should
be cleaned out.
According to the drawing, mark the columns, beams, floor which is connected with
ALC Panel, and pop the two-side upper and lower line of control by using ink
fountain.
4-5 workers form a group. Use hydraulic trolley for transportation. Panels should be
kept flat during the transportation. Pulling on the floor or unilateral support is forbidden
during transportation.
Use special fixture when lifting. Hoisting belt should be flexible nylon tie belt. Use 1:3
cement mortar on the bottom of the panel to make level, mortar thickness is 10 to
20mm.
While installation, one worker uses a chain hoist to make the panel stand up, other
workers stabilize the panel to the corresponding location.
Each panel should be connected to major structure by special U panels by nail gun.
After panel is upright, adjust the verticality by a wadge stuffed on the bottom of the
panel.
U-Card which is shot on the panels by a nail gun. After panel is upright, adjust the
verticality by a wadge stuffed on the bottom of the panel.
Pay attention to control the verticality during the installation, and check-up carefully
after installation.
Gap between panels to be caulked by special mortar, and extra mortar should be
pushed out while connecting panels.
Then clean up adhesive cracks between panels, and use specialized pointing mortar
to fill up gaps and level out.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/21
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
To avoid cracking on gaps between panels, cover the adhesive gap with a layer of
200mm wide alkali-resistance fibre mesh.
13.23.13 Submittal
Samples
Mock Ups
Contractor is to provide for a single story full height mock-up with a width of 8m as
part of the submission for approval
Shop Drawing
Code of Compliance Certificates
Submit shop drawings showing project layout and elevations; fastening and
anchoring methods; detail and location of joints, sealants, and gaskets, including
joints necessary to accommodate thermal movement; trim; flashing; and
accessories.
Code Compliance
Documents showing product compliance with the national and local building code
shall be submitted prior to the bid. These documents shall include, but not be limited
to, appropriate Evaluation Reports and/or test reports supporting the use of the
product.
Alternate materials must be approved by the architect prior to the bid date.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/22
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
13.24.1 Natural stone for casting on to concrete units to be supplied by the Contractor in
accord with BS 8298 1989.
13.24.2 Colour, Graining & Matching of Stone Applied Finishes. Naturally occurring granites,
marbles and other stone are subject to variations in colour, shade, texture and
graining.
i) Provide fine and coarse aggregate for each type of exposed finish required
from a single source for entire job.
ii) Aggregates shall be clean, hard, strong, durable, and inert, free of staining or
deleterious material.
13.25.1 Bricks or brick tiles used for casting on to precast units must be:
13.25.2 An allowance of +15% on the calculated nett brick quantities is required for size and
shape selection. Bricks received to be checked to ensure sufficiently sharp arises
and uniform shape. Where insufficient, additional bricks are to be supplied foc or an
exchange of “rejects” for new supplies made.
13.25.2 Panels rejected by the Architect due to brick quality to be replaced at no extra cost
by Contractor.
13.25.3 Fabricator to ensure placement of brick order upon confirmation of shape, sizes and
quantities approved by Architect. The delivery of sufficient quantity of bricks required
for the completion of the pre-cast panels in accordance to the construction schedule
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/23
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
i) Unless agreed by Architect, all brick pointing to be “Pointing in the mould” not
hand pointing after casting.
ii) The minimum joint width that can be used is 9mm and therefore subject to the
bricks being supplied/used to the tolerances quoted above the minimum
nominal design joint width will be 10 mm.
iii) Joint to be either recessed/raked to a depth of 9mm or struck at 45 degrees.
Architect to approve.
iv) Unless otherwise indicated drawings, courses to be ‘Running Bond’ (Stretcher)
with course stating and finishing on half or full bricks to avoid cutting and to
match adjacent spandrels or column covers.
v) Alternate course vertical joints to align.
vi) Stretcher, corner, edge corner and 3-sided corner brick facing modules to be
used.
13.25.5 Contractor must consider the following in design and production in order to minimize
or eliminate panel bowing:
13.25.6 Exposed horizontal bottom panel edges and soffits to have drip/groove.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/24
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
Typical dimensions:
Length : 230mm
Width : 70mm
Depth : 20 – 30mm
Dimensional Category:
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/25
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
i) General
3. Concrete mix design to combine minimum cement content and a constant low
water-cement ratio with high density.
ii) Specification
2. Full scale mockup of one typical panel to be made for Architect review and
subsequent mock-ups prepared until colour and standard of finish acceptable
to Architect is achieved.
3. Approved mock up finish to be accepted standard of finishes for all panels and
will form basis of comparison. Panels failing to meet the standard of mock up
sample may be rejected at the discretion of the Architect.
Cement : white
Fine aggregate : 80% - Crushed grey granite
20% - Crushed black obsidian
Coarse aggregate : 7mm white marble
Pigment : Dark Grey
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/26
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
iv) Architect Approved full scale mock up to be datum standard of finish for
production panels.
Coarse and fine aggregate of Ashton Keynes gravel (or equivalent single
source), white cement with acid etched and rubbed finish to achieve Bath
sandstone appearance.
iv) Architect Approved full scale mock up to be datum standard of finish for
production panels.
All panels to be treated with fluorosilane or equivalent for dirt, mould and graffiti
resistance.
13.27 REINFORCEMENT
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/27
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
13.28 MOULDS
13.28.1 Fabricated in stout seasoned timber, fibreglass lined or treated where necessary to
produce true matt faces and made accurately to full size templates and length rods.
13.28.2 Of such construction that casting deviations may be readily controlled to give
compliance with the manufacturing tolerances outlined above.
13.28.3 Maintained in clean sound condition and inspected carefully for accuracy and
surface defects before reuse.
13.28.4 Reused only if any damage can be reasonably repaired and if this would not impair
the surface appearance of the unit.
13.28.6 Where specially textured surfaces to the units are required the mould faces will be
lined with either fibreglass or polyurethane or silicone rubber. These linings having
been reproduced from hand finished master casts.
13.28.7 Moulds for containing bricks, natural stone or other cast on materials will be pre-
guided using rubber, steel or timber grids to standard sizes in order to retain the
applied materials. (See also section on tolerances).
13.28.8 Where deemed necessary by Fabricators, mould release agents, face retarders and
other mould treatments may be used strictly in accordance with manufacturer’s
instruction to assist in producing the various finishes and effects and as dictated by
the sample selected and the practical requirements of casting.
13.28.9 Complex moulds/ artwork and special architectural features shall be based upon
the intent of the Architect’s drawings. Detailed shop drawings and models to be
submitted by Fabricator to the Architect for approval.
13.28.10 When the shop drawings and models are completed the Architect will be requested
to view them and if necessary attend whilst any minor modifications are carried out.
13.28.11 Unless otherwise stipulated moulds remain the property of the Fabricator. However
the Architect’s copyright must be respected. No mould may be destroyed without
the consent of the Architect and Employer.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/28
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
13.29.1 All concrete mixes used must be generally in accord with BS5328. All materials
used will comply with the relevant British Standards and concrete mixes will attain a
characteristic compressive strength of 40N/mm2 at 28 days. (C40)
13.29.2 However as well as crushing strengths the mixes must be designed specifically to
produce colours and finishes as represented by the sample finishes selected by the
Architect and to enable units to be produced taking account of shapes, casting
attitudes etc.
Such mortar mixes will consist of a 6:1 by weight. Sand/cement mix with an
appropriate additive used in accordance with the Manufacturers’ instructions.
13.30.1 Admixtures
13.30.2 Pigments
Dry inorganic powder pigments used to be in accordance with BS 1014 where tinted
finishes are required. The pigments are to be weight batched and dry blended with
the appropriate cement before the combined materials are used in a wet mix.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/29
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
13.31.1 Fixings will be cast into units for the purposes of lifting and for attaching units to the
structure via loose metal fixings etc. as appropriate.
13.32 Lifting
All lifting sockets cast into units whether for works lifting or for site lifting to be in
galvanised mild steel. Where these occur on an exposed face or on a face covered
by other works, they are to be sunk at least 25mm below the finished face and
grouted in solid and where they occur on an exposed face, filled on site to match as
closely as possible the finish of the panel.
13.32.1 Where these sockets are on an internal face protected from weathering, they are not
required to be filled.
13.32.2 Site lifting should be via proprietary wire loops, screwed into lifting sockets, or similar
connections located approximately on the centres of gravity of the individual unit,
where possible. Alternative methods of lifting, such as slinging, using flat plait nylon
slings, or via cast in nylon rope lifters, may be used where appropriate.
13.32.4 Fixings etc cast in the unit to have a tolerance on positioning when measured from
the appropriate faces on the unit of + or – 6mm and generally in accord with BS8810.
13.32.5 All cast in items within the unit for the purposes of fixing securely to the building
must be in stainless steel.
13.32.1 Units must not be de-moulded prematurely and in no instance should they be de-
moulded less than 18 hours after casting or until the concrete within the unit has
achieved a compressive strength of 20 N/mm as determined by Schmidt hammer
testing. Damage to and distortion to immature units due to movement, vibration,
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/30
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
overloading, physical shock, rapid cooling and thermal shock must be prevented and
is the sole responsibility of the manufacturer.
13.32.2 Following de-moulding, units to be cured in air under cover generally for a minimum
of 5 days and therefore protected from the effects of sun and drying winds.
Following finishing of the units they may be removed to a covered stacking area
where they must be stacked on non-staining bearers as appropriate for the type of
unit.
13.32.3 No units to be delivered to site until they have reached 14 to 21 days old or have
attained their designed strength by comparison with the normal 7 and 28 day cube
strength results and if necessary confirmed by an in-house test with a Schmidt
hammer.
13.33 FINISHING
13.33.1 When sufficiently hardened the exposed surfaces of the units to be treated to
achieve the finish as selected by the Architect and as represented by the approved
sample. The finished surfaces of the units to be then cleaned with a dilute acid
solution and clean water.
ii) The mock-up will determine the range of acceptability with respect to colour and
texture variations, surface defects, and overall appearance.
iii) Precast concrete products that do not meet the colour and texture range or the
dimensional tolerances of this specification may be rejected at the option of the
Architect, if they cannot be satisfactorily corrected, as determined by the
Architect.
13.34.1 The Contract is deemed to be ‘Delivered and Fixed’ where cleaning is a normal part
of the fixing service and together with the making good of any minor damage caused
during delivery of fixing and the undertaking of minor final finishing, works be
undertaken towards the end of the on site period, just prior to final
inspection/handover.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/31
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
13.34.2 Potential problems associated with obtaining the colour, grading, texture and profile
of the precast units should be highlighted by the Fabricator prior to fabrication.
13.34.3 A mild hydrochloric acid wash or equivalent suitable cleaning agent should be used
to remove efflorescence or ‘lime bloom’.
13.35.1 General
i) General
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/32
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
b) Horizontal joint
i) Horizontal joint to be a shiplap joint with gasket sealant air seal at the internal
edge face. Exterior face to be open to vent air chamber to form pressure qualized
space. Open joint width to be 12 -20mm, or as otherwise indicated in drawings.
ii) Air tight interior seal to be prime seal preventing warm, moist air movement.
iii) Water from penetration or condensation, should be drained from the joint by
proper flashing installations.
iv) Flashing using electrometric sheet at each 2nd floor level to be used.
v) Vent or drain tubes should be a minimum 7mm inside diameter polyvinyl chloride
or other non-staining materials. Vents should be located at the junction of horizontal
and vertical joints.
vi) Drip groove to be cast into bottom horizontal outer edge panel.
c) Vertical joint
i) Vertical joint to be two stage joint with gasket/sealant air seal at the internal
edge face.
13.35.4 Shop drawings to be reflect full-scale details and mock-up of joint detail to be tested
prior to fabrication and installation.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/33
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
(a) General
i) All sealants and gaskets to be fit for purpose and detail proposed and to be
applied/fixed in accordance to manufacturer’s instructions and good
international building practice.
v) Edges of the precast concrete units and the adjacent materials must be
sound, smooth, clean and dry. Edges must be free of frost, dust, loose
mortar or any other contaminants that may affect adhesion.
(b) Sealant
i) Joint to consist of sealant, band breaker (if required) and pre-formed rod or
tubular backing.
ii) Joints to be completely filed and neatly tooled slightly concave, to eliminate
air pockets or voids.
iii) Surface of sealant should be full, smooth bead, free of ridges, wrinkles,
gags, air pockets and embedded impurities.
iv) Back up material must not stain sealant and be of suitable size and shape
for compression to provide watertight joints.
v) Primers may be used if recommended by sealant manufacturer, but must be
non-staining.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/34
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
9. Ease of application.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/35
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
13.36.1 Cement
Were in receipt of manufacturer’s test certificates for cement on a weekly basis and
these certificates show details as follows:
13.36.2 Aggregates
All aggregates delivered load by load to be subject to sieve analysis and silt content
tests and visually inspected against control samples for both colour and grading. In
addition physical and chemical properties as provided by the various specialist
aggregate suppliers are as stable.
No. OF SETS
Up to 2 cubic metres 1
2 –5 cubic metres 2
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/36
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
From each of the above sets of cubes one will be tested at 7 day, and two at 28
days.
Where the sample elected is a new mix design the suitability of the mix must be
assessed in accordance with B.S. 5328 and B.S. 8110 and ISAT performance
assessed by (in house) trial mixes. Details to be made available on request.
Tests may be carried out independently and therefore the Fabricator must include
for making an additional set of three cubes, once per month, as and when directed
by the Architect for testing by an independent testing house to be agreed.
13.36.5 Reinforcement
Up to 20% of all units cast must have reinforcement cover checked by means of a
cover meter survey, details of which are to be recorded.
All units manufactured to be identified by the unit number related to Fabricators key
elevation drawings and must be marked with the date of casting and issued to
Architect.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/37
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
13.37.1 Programme
Prior to commencement of Main Contract work Contractor must submit a
programme of work which must include but not limited to the following:-
iii) Mock up preparation, submission, period for revision and required approval
date.
13.37.2 Samples
ii) A sample of every proposed finish, joint details and sealant/gasket must be
submitted in a size not less than 300 x 300mm.
Contractor to expedite submittal of full shop drawings to the Architect for approval.
The content of these drawings should include but not limited to the following:-
b) Handling procedure, plans and elevations showing panel location, and sequence
of erection.
c) Finishes
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/38
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
13.37.4 Testing
ii) All statutory submissions required for the completion and installation of the
system to be made by the Contractor/Contractors appointed Consultants.
iii) Calculations must include although limited to all design calculations for precast
concrete products not defined or completed on the drawings and for steel
reinforcement required for handling and erection loads.
vi) All design modifications necessary to meet performance requirements and held
coordination to be submitted.
iii) Variations in details or materials shall not adversely affect the appearance,
durability or strength of units.
iv) General design concept must be maintained without altering size of members,
profiles and alignment.
13.38.1 Contractor should coordinate arrival of precast concrete units and provide for
possible storage and for erection in a safe manner within the agreed schedule and
with due consideration for other trades. Handling procedures, including type and
location of fastenings. The Contractor shall:-
a) Deliver all architectural precast concrete units to project site in such quantities
and at such times to assure continuity of erection.
b) Handling and transport units in a position consistent with their shape and design
in order to avoid stresses which would cause cracking or damage.
c) Lift or support units only at the point shown on the shop drawings.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/39
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
g) Store and protect units to prevent contact with soil, staining, and physical
damage.
i) Store units on firm, level, and smooth surfaces to prevent cracking, distortion,
warping or other physical damage.
j) Place stored units so that identification marks are discernible, and so that
product can be inspected.
13.38.2 Damage
13.39.1 The architectural drawings are diagrammatic and do not purport to identify or solve
the problems of thermal or structural movement, vapour barriers, fixings and
anchorage, flatness and stability of facing, and moisture disposal.
The drawings merely indicated the ‘profile, configurations and finishes required
together with the position relative to the structural frame and interior building
elements. The details contain therein serve merely as suggested directions for
solving some of the major design requirements. The Contractor may use these
details and develop them as he deems fit.
The Specification specifies the minimum requirements without limiting the Fabricator
as to the method of achieving such performance.
The Contractor shall be deemed to have visited the site before submitting his Tender
and shall be wholly responsible for acquainting himself with the nature, position,
constraints of the site and the full extent and character of the works and all other
information relevant to the execution of the works.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/40
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
The Contractor shall not be entitled to claim extra payment on the grounds of
insufficient or inaccurate tender information relating to propose or existing
structures.
Preliminary design proposals must be submitted with the tender. Notwithstanding the
acceptance of the Contractor’s design recommendation/ proposals by the Architect,
Contractor shall be solely responsible for the adequacy of the works including design
and shall make good any damage or defects arising from inadequate design.
The Contractor shall submit for the consideration of the Architect preliminary design
drawings showing typical details fully dimensioned, showing finish, thickness,
profiles, jointing, welds, intersections and assembly; details of construction,
weatherproofing hardware and hardware schedules; reinforcement, anchorage and
structural supports; and such drawings and details as required to fully illustrate all
details of the work. The scale and detail of the drawings are subject to Architect’s
approval.
The Contractor shall outline details of his intended temporary works to the Architect
and incorporate his comments into the design. He shall then submit for the
Architect’s approval before the commencement of any on site construction, shop
drawings and calculations showing all details, manner and magnitude of the loading
on the structure. The Contractor shall be responsible for ensuring that the structural
elements to which the elements are to be fixed is adequate to support the load.
Within four weeks of the acceptance of the tender, modify the preliminary drawings
to full working shop drawings complying with the Architect’s instructions and
requirements. Supply to the Architect for distribution to those connected with this
project, four copies each of the final approved drawings.
13.43 Measurements
All true measurements of the building are to be in the metric system. The Contractor
shall be responsible for verifying all the dimensions and actual conditions on site.
These dimensions should be incorporated in the shop drawings prior to final
approval.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/41
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
The Contractor shall submit with his Tender details of builder’s work and special
attendance required other than those already described in this Specification. Any
other items of work or facilities not so stated shall be deemed to be provided by the
Contractor when required.
Within one month of award of the Contract, the Contractor shall submit updated
information as follows:-
i. Organization Chart.
ii. Detailed programme of the Works.
iii. Shop Drawings:-
Complete scaled construction detail drawings drawn to full scale. The
drawings shall fulfil all requirements made by the Architect during the
technical negotiation with the Contractor.
(b) Upon Architect’s approval of the shop drawings, four copies and one
reproducible print for each of the final approved drawings, plus four sets of the
above reduce to one-quarter of the original size shall be submitted for the
Architect’s and Employer’s use.
(c) After the shop drawings and the structural calculation, etc. are approved, the
Contractor shall submit the following for the Architect’s approval before
fabrication of the bulk.
i. Plan of Inspection of Component –
Material specification, supply source, and procedure for inspection of the
quality of the components of the systems during the manufacturing and
fabricating process.
(e) Before the components are installed, the Contractor shall submit the following
for the Architect’s approval.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/42
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
v. Plan of Protection –
Preliminary plan of the method of protecting the works with description as to
when the protection can be removed. The plan to consider effect on other
trades.
(f) Before the date of completion of the works, the contractor shall prepare and
supply to the Architect, record drawings and record photographs of the whole
of the works as installed and as requested by the Architect. These drawings
and photographs shall be specially prepared for record purpose and the copies
as finally provided to the Architect shall consist of (four) sets of reduced size
prints together with its corresponding (drawings) and (two) sets of
photographs.
(g) The Contractor shall submit a maintenance manual for all systems.
13.47 Guarantee
(a) Submit written guarantee agreeing to repair or replace defective materials and
workmanship during the guarantee period. The Contractor shall be responsible
for damages to building and furnishings caused by defective materials and
workmanship including water leakage during the guarantee period.
Defective materials and workmanship of the work shall include abnormal
deterioration, aging or weathering of the work, leakage of water or air
pressures and forces, failure of operating parts to function normally,
deterioration or discolouration of finishes in excess of normal weathering and
aging, glass breakage, secondary glass damage or breakage due to falling
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS3/43
OCTOBER 2021 ISSUED FOR PERMIT SECTION 13 - SUPPLY AND INSTALLATION OF CONCRETE WALL PANELS
(b) The general guarantee shall cover a period of ten years from the date of issue
of the Completion Certification of the Main contract by the Architect.
(d) The guarantee shall cover structural failure and latent defects of the system in
compliance with the current and latest regulations and requirements stipulated
by the relevant local authorities.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
SS014_Handrails, Guardings & Railings
JKT05 SS14/1
OCTOBER 2021 ISSUED FOR PERMIT SECTION 14 – HANDRAILS, GUARDINGS AND RAILINGS
SECTION 14
14.1 GENERALLY
The Works includes the design, engineering and fabrication of the following:
14.2.1 General
Design and engineering the handrail, railing and Catwalk systems to withstand
structural loads indicated and coordinate as required, determine allowable design
working stresses of railing materials based on the following:
Engineer, fabricate, and install handrails and railing systems to comply with applicable
code requirements.
Allow for thermal movement resulting from the following maximum change (range) in
ambient temperature in engineering, fabricating, and installing handrails and railing
systems to prevent buckling, opening of joints, overstressing of components and
connections, and other detrimental effects. Base engineering calculation on actual
surface temperatures of materials due to both solar heat gain and night time sky heat
loss.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS14/2
OCTOBER 2021 ISSUED FOR PERMIT SECTION 14 – HANDRAILS, GUARDINGS AND RAILINGS
14.3 SUBMITTALS
14.3.1 General
Submit each item in accordance to the Conditions of the Contract and Specification.
Product data for manufacturer's product lines of handrails and railing systems
assembled from standard components. Submit product data for grout, anchoring
cement, and paint products.
Shop drawings showing fabrication and installation of handrails and railings, including
plans, elevations sections, details of components, and attachments to other units of
Work.
For installed handrails and railing systems indicated to comply with certain design
loading include structural analysis data sealed and signed by the qualified professional
engineer who was responsible for their preparation.
c. Welded connections.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS14/3
OCTOBER 2021 ISSUED FOR PERMIT SECTION 14 – HANDRAILS, GUARDINGS AND RAILINGS
14.4.2 Mock-ups
Prior to installing railings, construct mock-ups for each form of railing system and
finish required to verify selections made under sample submittals and to demonstrate
aesthetic effects as well as qualities of materials and execution. Build mock-ups to
comply with the following requirements, using materials indicated for final unit of Work.
b. Notify Architect one week in advance of the dates and times when mock-ups
will be constructed.
14.5 STORAGE
Store handrails and railing systems inside a well-ventilated area, away from uncured
concrete and masonry and protected from weather, moisture, soiling, abrasion,
extreme temperatures, and humidity.
Where handrails and railings are indicated to fit to other construction, check actual
dimensions of other construction by accurate field measurements before fabrication;
show recorded measurements on final shop drawings. Co-ordinate fabrication
schedule with construction progress to avoid delaying the Work.
14.8 METALS
14.8.1 General
Provide metal free from surface blemishes where exposed to view in the finished unit.
Exposed-to-view surfaces exhibiting pitting, seam marks, roller marks, stains,
discolourations, or other imperfections on finished units are not acceptable.
Provide steel and iron in the form indicated complying with the following requirements:
ii For exterior installations and where indicated, provide tubing with hot-
dip galvanised coating per ASTM A 53.
Brackets, Flanges, and Anchors: Cast or formed metal of the same type material and
finish as supported rails, unless otherwise indicated.
Provide type and alloy of filler metal and electrodes as recommended by producer of
metal to be welded or brazed and as required for colour match, strength, corrosion
resistance, and compatibility in fabricated items.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS14/5
OCTOBER 2021 ISSUED FOR PERMIT SECTION 14 – HANDRAILS, GUARDINGS AND RAILINGS
14.10 FASTENERS
Select fasteners of the type, grade, and class required to produce connections that
are suitable for anchoring railing to other types of construction indicated and capable
of withstanding design loading.
a. For stainless-steel railings, provide fasteners fabricated from Type 316 stainless
steel.
b. For steel fittings, use plated fasteners complying with ASTM B 633, Class Fe/Zn
25 for electro-deposited zinc coating.
Use fasteners of same basic metal as the fastened metal, unless otherwise indicated.
Do not use metals that are corrosive or incompatible with materials joined.
Provide concealed fasteners for interconnecting handrail and railing components and
for attaching them to other work, except where otherwise indicated.
Anchors of type indicated below, fabricated from corrosion resistant materials with
capability to sustain, without failure, a load equal to 6 times the load imposed when
installed in unit masonry and equal to 4 times the load imposed when installed in
concrete, as determined by testing per relevant ASTM conducted by a qualified
independent testing agency.
a. Cast-in-place anchors.
b. Expansion anchors.
14.11 PAINT
a. Exterior Assemblies
b. Interior Assemblies
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS14/6
OCTOBER 2021 ISSUED FOR PERMIT SECTION 14 – HANDRAILS, GUARDINGS AND RAILINGS
High-zinc-dust-content paint for re-galvanising welds in galvanised steel, with dry film
containing not less than 94 percent zinc dust by weight, and complying with DOD-P-
21035 or SSPC-Paint 20.
14.13 FABRICATION
14.13.1 General
Fabricate handrails and railing systems to comply with requirements indicated for
design, dimensions, details, finish, and member sizes, including wall thickness of
hollow members, post spacing and anchorage, but not less than that required to
support structural loads.
Assemble railing systems in shop to the greatest extent possible to minimise field
splicing and assembly Disassemble units only as necessary for shipping and handling
limitations- Clearly mark units for re-assembly and co-ordinated installation Use
connections that maintain structural value of joined pieces.
Form simple and compound curves by bending members in jigs to produce uniform
curvature for each repetitive configuration required; maintain profile of member
throughout entire bend without buckling twisting, cracking, or otherwise deforming
exposed surfaces of handrail and railing components.
Fabricate railing systems and handrails for connecting members by welding. For
connections made during fabrication, weld corners and seams continuously to comply
with the following:
a. Use materials and methods that minimise distortion and develop strength and
corrosion resistance of base metals.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS14/7
OCTOBER 2021 ISSUED FOR PERMIT SECTION 14 – HANDRAILS, GUARDINGS AND RAILINGS
Fabricate splice joints for field connection using epoxy structural adhesive where this
represents manufacturer's standard splicing method.
Provide inserts and other anchorage devices to connect handrails and railing systems
to concrete or masonry work. Fabricate anchorage devices capable of withstanding
loads imposed by handrails and railing systems. Co-ordinate anchorage devices with
supporting structure.
For railing posts set in concrete, provide pre-set sleeves of steel not less than 150mm
long with inside dimensions not less than 12.7mm greater than outside dimensions of
post, and steel plate forming bottom closure.
Shear and punch metals cleanly and accurately. Remove burrs from exposed cut
edges.
Cut, reinforce, drill, and tap components, as indicated, to receive finish hardware,
screws, and similar items.
Provide weep holes or another means to drain entrapped water in hollow sections of
railing members that are exposed to exterior or to moisture from condensation or other
sources.
Close exposed ends of handrail and railing members with prefabricated end fittings.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS14/8
OCTOBER 2021 ISSUED FOR PERMIT SECTION 14 – HANDRAILS, GUARDINGS AND RAILINGS
14.13.5 Fillers
Provide steel sheet or plate fillers of thickness and size indicated or required to
support structural loads of handrails where needed to transfer wall bracket loads
through Wall finishes to structural supports. Size fillers to suit wall finish thickness’
Size fillers to produce adequate bearing to prevent bracket rotation and over-stressing
of substrate.
Remove or blend tool and die marks and stretch lines into finish. Mirror-like Reflective,
Non-directional Polish: Match AISI No. 8 finish.
14.16.1 Galvanising
b. ASTM A 123 for galvanising iron and steel products made from rolled, pressed,
and forged steel shapes, castings, plates, bars, and strips.
Fill vent and drain holes that will be exposed in the finished work, unless indicated
to remain as weep holes, by plugging with zinc solder and filing off smooth.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS14/9
OCTOBER 2021 ISSUED FOR PERMIT SECTION 14 – HANDRAILS, GUARDINGS AND RAILINGS
For galvanised handrails and railing systems, provide galvanised fittings, brackets,
fasteners, sleeves, and other ferrous components.
Cutting, Fitting, and Placement: Perform cutting, drilling, and fitting required for
installing handrails and railings. Set handrails and railings accurately in location,
alignment, and elevation, measured from established lines and levels and free from
rack.
Do not weld, cut, or abrade surfaces of handrails and railing components that have
been coated or finished after fabrication and are intended for field connection by
mechanical or other means without further cutting or fitting.
Align rails so that variations from level for horizontal members and from parallel with
rake of steps and ramps for sloping members do not exceed 2-mm in 1-m.
a. Use materials and methods that minimise distortion and develop strength and
corrosion resistance of base metals.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS14/10
OCTOBER 2021 ISSUED FOR PERMIT SECTION 14 – HANDRAILS, GUARDINGS AND RAILINGS
Coat concealed surfaces of the following that will be in contact with grout, concrete
masonry, wood, or dissimilar metals, with a heavy coat of bituminous paint.
14.18.3 Alignment
Adjust handrails and railing systems prior to anchoring to ensure matching alignment
at abutting joints. Space posts at interval indicated but not less than that required by
structural loads.
Use anchorage devices and fasteners where necessary for securing handrails and
railings systems and for properly transferring loads to in-place construction.
Welded Connections: Use fully welded joints for permanently connecting railing
components by welding. Cope or butt components to provide 100 percent contact, or
use fittings designed for this purpose.
Anchor posts in concrete with pipe sleeves pre-set and anchored into concrete. After
posts have been inserted into sleeves, solidly fill annular space between post and
sleeve with the following anchoring material, mixed and placed to comply with
anchoring material manufacturer's directions.
Leave anchorage joint exposed, wipe off surplus anchoring material, and leave 3-mm
build-up, sloped away from post.
Anchor posts to metal surfaces with oval flanges, angle type or floor type as required
by conditions, connected to posts and to metal supporting members as follows:
For stainless-steel railings, weld flanges to post and bolt to metal supporting surfaces.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS14/11
OCTOBER 2021 ISSUED FOR PERMIT SECTION 14 – HANDRAILS, GUARDINGS AND RAILINGS
Anchor rail ends into concrete and masonry with round flanges connected to rail ends
and anchored into wall construction with post-installed anchors and bolts.
Anchor rail ends to metal surfaces with oval or round flanges. Weld flanges to rail
ends.
Attach handrails to wall with wall brackets and end fittings. Provide bracket with 38-
mm clearance from inside face of handrail and finished wall surface.
Secure wall brackets and wall return fittings to building construction as follows: Use
type of bracket with flange tapped for concealed anchorage to threaded hanger bolt.
a. For concrete and solid masonry anchorage, use drilled-in expansion shield and
either concealed hanger bolt or exposed lag bolt, as applicable.
b. For hollow masonry anchorage, use toggle bolts with square heads.
Testing Agency: Contractor shall employ and pay a qualified independent testing
agency to perform field quality control testing.
Extent and Testing Methodology: The testing agency will randomly select completed
railing assemblies for testing that are representative of the different railing designs and
conditions in the completed Work. Railings will be tested for compliance according to
relevant ASTM.
Testing agency will report test results promptly and in writing to Architect.
Remove and replace railings where test results indicate that they do not comply with
specified requirements, unless they can be repaired in a manner satisfactory to the
Architect, so that they will comply with specified requirements.
Additional Testing: Where railings are removed and replaced or is repaired, additional
testing will be performed to determine compliance with specified requirements.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS14/12
OCTOBER 2021 ISSUED FOR PERMIT SECTION 14 – HANDRAILS, GUARDINGS AND RAILINGS
Clean the stainless steel by washing thoroughly with clean water and soap, followed
by rinsing with clean water.
Touch-up Painting: Immediately after erection, clean field welds, bolted connections,
and abraded areas of shop paint, and paint exposed areas with same material.
For galvanised surfaces: Clean field welds, bolted connections, and abraded areas
and apply galvanising repair paint to comply with relevant ASTM.
14.25 PROTECTION
Protect finishes of railing systems and handrails from damage during construction
period with temporary protective coverings approved by railing manufacturer Remove
protective coverings at the time of Completion.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
SS015_Cement Paving
JKT05 SS15/1
OCTOBER 2021 ISSUED FOR PERMIT SECTION 15 - CEMENT PAVING
SECTION 15
15.1 GENERALLY
All making good of cement paving shall be cut out to a rectangular shape, the
edges undercut to form dovetailed key and finished flush with face of
surrounding paving. Cut out and make good all cracks, blisters and other
defects and leave the whole of the work perfect on completion.
All mortars for paving shall be mechanically or hand mixed as directed by the
Architect and the Contractor shall make allowance for the use of additional
cement, necessitated by the method of mixing instructed. Only whole bags of
cement shall be used in any one batch of mix.
The ingredients for all paving mixes shall be accurately gauged in approved
boxes and mixed on proper watertight boarded platforms. Mixes containing
cement shall be used up within two hours of the first contact of the cement with
water.
The skirtings and risers shall be the heights and thickness shown in the
drawings or as directed. Junction with paving at bottom shall be covered and
paving at top shall have a rounded edge. All vertical angles shall be covered
and vertical material angles shall be rounded.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS15/2
OCTOBER 2021 ISSUED FOR PERMIT SECTION 15 - CEMENT PAVING
If in the opinion of the Contractor, the Specifications are insufficient for him to
give the specified indemnity then the Contractor shall allow in his tender for
upgrading the Specifications as necessary to enable him to do so indemnify.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
SS016_Tiles & Tiling Adhesives
JKT05 SS16/1
OCTOBER 2021 ISSUED FOR PERMIT SECTION 16 - TILING AND TILING ADHESIVES
SECTION 16
16.1 GENERALLY
At least 90% of all flooring, by cost or surface area, meets the VOC emissions
evaluation OR inherently non emitting sources per LEED Gold Standards
At least 75% of all adhesives and sealants, by volume or surface area, meet the VOC
emissions evaluation AND 100% meet the VOC content evaluation as per LEED Gold
Standards
Are sufficiently flat to permit specified flatness of finished surfaces, bearing in mind
the permissible minimum and maximum thickness of the bedding material.
Have been allowed to dry out by exposure to the air for not less than the following:
Rendering : 2 weeks
16.1.2 Samples
Before placing orders submit full sets of samples of all tiles or panels specified to the
Architect for selection of patterns, and all deliveries to the Site shall be equal to these.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS16/2
OCTOBER 2021 ISSUED FOR PERMIT SECTION 16 - TILING AND TILING ADHESIVES
On colours and patterns being selected, the Contractor shall place his orders for the
total requirements to ensure conformity in the colour and texture of the tiles or panels.
In the event of under-ordering, the Contractor will be responsible for ensuring that the
further orders conform entirely to the colouring and specification of the tiles or panels
previously supplied.
Samples of all floor finishes shall be laid in representative areas not less than 2000 x
2000mm, and in the case of stonework in such areas as the Architect may direct.
Such sample areas shall be subjected to the approval of the Architect, and following
any such approval, all finishes subsequently laid shall be equal to the approved areas.
A mock-up floor will be used for the majority of sample finishes, but other sample
areas of non-typical finishes will be laid in locations as directed by the Architect.
Particular care to be taken in sorting and preparing tiles, with all special pieces for
matching.
All tiling is to be carried out by trades people experienced in this specialist work. All tiling
is to be laid strictly in accordance with approved shop drawings.
All Tile beddings, adhesives and grouts to Architect’s approval and strictly in accordance
with manufacturer’s instructions and recommendations.
Tiles to wet areas to be laid neatly to falls to ensure no standing water. Falls should be
dished from perimeter of room to maintain a horizontal skirting.
All items suffering damage in transit prior to acceptance shall be rejected, and
replaced at the Contractor’s cost, and the Contractor to hold sufficient stocks of the
specified materials for such replacements.
After confirmation of tiles by the Architect the contractor is to have the tiles tested by
SESCO (or equivalent local Standards) to ensure compliance with specification
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS16/3
OCTOBER 2021 ISSUED FOR PERMIT SECTION 16 - TILING AND TILING ADHESIVES
Properties :
Minimum thickness : 10 mm
Thermal expansion : 9 x 10
Resistance to chemical :
Properties :
Minimum thickness : 10 mm
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS16/4
OCTOBER 2021 ISSUED FOR PERMIT SECTION 16 - TILING AND TILING ADHESIVES
Thermal expansion : 9 x 10
Properties:
Minimum thickness : 7 mm
Thermal expansion : 9 x 10
16.2 PREPARATION
Scrub with water containing detergent to ensure complete removal of mould, oil,
surface retarders and other materials incompatible with the bedding. Rinse with
clean water and allow to dry unless specified otherwise.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS16/5
OCTOBER 2021 ISSUED FOR PERMIT SECTION 16 - TILING AND TILING ADHESIVES
b New Plaster
Ensure plaster is dry, solidly bedded, free from dust and friable matter. Apply
plaster primer recommended by the adhesive manufacturer and allow to dry
before tiling.
c Keying
Rake out soft joints in existing brickwork to a depth of not less than 13mm.
Brush out joints to remove dust.
Check that there are no unintended colour/shade variations within the tiles for use in
each area/room. Thoroughly mix variegated tiles.
All surfaces on which tiling is to be laid shall be suitable for that purpose, and the
Contractor shall report any factors that may affect the execution of satisfactory tiling to
the Architect. The Architect will issue necessary instructions with regard to any action
required to be taken in this respect.
Tiles are to be laid in accordance with good practice, and the written instructions of the
manufacturer.
c. Fix tiles so that there is adhesion over the whole of the background/base and tile
backs.
d. Before bedding material sets, make adjustments necessary to give true, regular
appearance to tiles and joints when viewed under final lighting conditions.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS16/6
OCTOBER 2021 ISSUED FOR PERMIT SECTION 16 - TILING AND TILING ADHESIVES
e. Clean surplus bedding material from joints and face of tiles without disturbing
tiles.
All tiles in this project are to be set-out in accordance with approved shop drawings by
the contractor. Shop drawings need to be co-ordinated with M&E at an early stage to
ensure that all fittings align with the tile grids. Falls in floor are to be formed by dishing
away from wall to maintain horizontal floor/wall interface.
Joints to be true to line, continuous and without steps. Joints on walls to be truly
horizontal, vertical and in alignment round corners. Joints in floors to be parallel to the
main axis of the space or specified features.
Where positions of movement joints are not specified they are to be agreed with the
Architect.
Sudden irregularities not permitted. When measured with a slip gauge to relevant BS
or equivalent, the variation in gap under a 2m straight edge (with feet) placed
anywhere on the surface to be not more than 2mm.
Sudden irregularities not permitted. When measured with a slip gauge to relevant BS
or equivalent, the variation in gap under a straight edge (with feet) placed anywhere
on the surface to be not more than:
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS16/7
OCTOBER 2021 ISSUED FOR PERMIT SECTION 16 - TILING AND TILING ADHESIVES
Sand for floors :To relevant BS, grading limit M but where fine sand is
specified grading limit F.
b. Batch by volume. Specified proportions are for dry sand, allow for bulking if
damp
d. Use mortar within two hours of mixing at normal temperatures. Do not use after
the initial set has taken place and do not re-tempered.
If to be bedded in cement and sand screed, soak in clean water for at least 30
minutes, and fix as soon as surface water has drained.
Bed solid to wall with cement based adhesive after laying floor tiles. Ensure joints in
skirtings match and align with joints in floor tiling.
Apply floated coat of adhesive to dry base and comb the surface with the
recommended solid bed trowel. Apply adhesive to backs of tiles as necessary to fill
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS16/8
OCTOBER 2021 ISSUED FOR PERMIT SECTION 16 - TILING AND TILING ADHESIVES
any depressions or keys. Press tiles firmly into position to give finished bed thickness
within the range recommended by the tile manufacturer.
As work proceeds and before the bedding has set, carefully remove random tiles as
directed and in the presence of the Architect to verify that there is adhesion over the
whole area. Remove the initial adhesive, butter the removed tiles with fresh adhesive
and re-fix.
16.13 GROUTING/COMPLETION
a. Grouting Mix
b. Grouting
Ensure that joints are 6mm deep (or the depth of the tile if less), and are free
from dust and debris.
Fill joints completely, tool to an approved profile, clean off surface and leave
free from blemishes.
Polish wall tiling with a dry cloth when joints are hard.
c. Tiling Joint
All tiling joints of maximum 3mm width to be maintained throughout all tiling
areas unless it is contrary to the tile manufacturer's recommendation. In which
case, the Architect's approval is to be obtained prior to execution of any work.
d. Movement Joints
Movement joints shall be formed at not more than 4.5 metre centres in both
directions, unless otherwise shown or described, and shall be taken through
the full depth of the cement screed to substrate. Ensure that joints coincide
with any movement joints left for the purpose in the substrate. Joints shall be
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS16/9
OCTOBER 2021 ISSUED FOR PERMIT SECTION 16 - TILING AND TILING ADHESIVES
filled with a polyethylene backer rod and finished with a modified polyurethane
sealant in selected colours, all to match floor finish.
Joints must extend through tiles and bedding to substrate. Ensure that joints
coincide with any movement joints left for the purpose in the substrate.
All sealants used shall not through position/location or innate material attracts
staining or cause stains to adjacent materials.
Bed in 1:3 cement and sand screed centred over joint and to finished floor
level. Fix to base in accordance with the manufacturer's instruction.
16.14 PROTECTION
The floor finishes are to be carefully and adequately protected with rigid board and
polythene and kept clean all completed areas until completion of the works. The
protection provided shall be suitable for each type of finish and shall be subject to the
approval of the Architect.
Clean off any droppings immediately. Tiles/slabs to all areas to be kept dry and not
brought into service for at least three weeks after grouting/jointing.
16.15 TRAFFICKING
Keep floors clear of traffic for at least four days and permit only light traffic for the next
10 days.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS16/10
OCTOBER 2021 ISSUED FOR PERMIT SECTION 16 - TILING AND TILING ADHESIVES
Prior to commencement of tiling works, the Contractor shall, jointly with the supplier of
the polyester liquid latex admixture and colour grout, lodge with the Architect a 5-year
indemnity against defects in the tile adhesive works.
The defects shall include but not limited to tiles falling off, cracking of colour grout,
efflorescence, staining of tiles and discolouration of colour grout.
Under this indemnity, the Contractor will be required to make good any defects and
failure in the materials or installation and will be responsible for any consequential loss
attributable to any failure in the tile adhesive works during the warranty period.
If in the opinion of the Contractor, the Specifications are insufficient for him to give the
specified indemnity then the Contractor shall allow in his tender for upgrading the
Specifications as necessary to enable him to so indemnify.
The Contractor shall be deemed to have allowed in his Tender for the supply of wall
and floor tiles to be used by the Employer for future maintenance purposes, and the
quantities to be allowed shall be pegged at 3% of each type of wall and floor tiles used
in the Contract.
These tiles for maintenance purposes shall be carefully stored and protected, and
handed over to the Employer's Property Management Department upon completion of
the Contract or when instructed by the Architect. If these tiles are found to be of the
type and/or quality which are inconsistent or do not match those used in the Contract,
the Architect reserves the right to reject them and the Contractor shall then deliver the
required tiles without undue delay.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
SS017_Stoneworks
JKT05 SS17/1
OCTOBER 2021 ISSUED FOR PERMIT SECTION 17 - STONE WORK
SECTION 17
17.1 GENERALLY
The Contractor shall jointly and severally with the Specialist Contractor furnish
a ten (10) years guarantee for the works.
For location of stone, see Schedule of Finishes. Stonework shall include, but is
not necessary limited to the following:-
c. Vanity counters.
d. Provide sealant system for all interior and exterior stonework joints
except for interior floor paving.
e. Provide mortar bed as necessary to bed all large solid pieces, pavers,
etc. whether sealant or mortar joints.
h. Fabricate, cut, finish and install each type of stone in accordance with
approved shop drawings. Provide all slots in stone required for
mechanical/electrical trades, co-ordinate with same.
k. Provide mortar joints for all interior stonework at floors. All other joints
shall be sealant types as specified herein.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED
PARTLY OR WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS17/2
OCTOBER 2021 ISSUED FOR PERMIT SECTION 17 - STONE WORK
n. Provide one piece solid shaped stones without joint for all shaped
pieces.
The stone shall have a low water absorption coefficient, suitable for external
use, and shall be free from iron (which may cause staining to the stone).
Full technical data of the stone must be submitted by the contractor and shall
include the following information:
a. Country of origin
b. Location of quarry
f. Mineral composition
g. Compressive Strength
h. Tensile Strength
i. Impact Strength
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED
PARTLY OR WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS17/3
OCTOBER 2021 ISSUED FOR PERMIT SECTION 17 - STONE WORK
j. Density
k. Abrasion Resistance
All stones of a particular type shall be obtained from one quarry and shall be
free from all flaws, defects, disfigurations and discoloration.
All mitred joints shall be formed by factory made mitres, securely bonded with
epoxy resin and reinforced where necessary with stainless steel cramps,
dowels, etc.
All stone shall be subject to Architect’s review. Stone rejected for non
conformance to the agreed samples or confirmed shop drawings shall be
removed from the site and replaced with material meeting the Architect’s
requirement and all of the specified requirements at no additional cost or time.
The Architect will reject any materials that, in his opinion, do not reasonably
comply with the requirements of the specification.
All full size sample panels will be required for those special areas of the work
defined herein.
The sample panels shall be erected with adequate foundation supports and
provision for bracing, at a site provided by the Contractor, as agreed with the
Architect in Singapore, unless otherwise agreed by Architect.
Sample panels for stone at walls shall provide actual stone support and
anchoring system, on block or concrete back up as shown on the drawings
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED
PARTLY OR WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS17/4
OCTOBER 2021 ISSUED FOR PERMIT SECTION 17 - STONE WORK
17.4 CO-ORDINATION
Contractor to ensure that all requirements due to this specialist work are made
known to the respective affected sub-contractors and vice-versa
17.5.1 General
As part of the Contract for furnishing and installing stonework, the Contractor
will be required to engage the services of a Professional Engineer, herein after
referred to as the "Contractor's Engineer", who will be required to provide
review and oversee all other services specified herein. The said Engineer's
credentials shall be offered to the Architect for review, prior to acceptance.
Once engaged, the Contractor will be required to pay all fees relevant to the
services of the Engineer, at no additional cost to the Employer.
17.5.2 Requirements
It is not the intention of the Contract Documents, including drawings and these
Specifications, to determine for the Contractor the means and/or methods for
the fabrication, delivery and installation of all stonework. The drawings and
specifications are provided to convey to the Contractor the desired design
intent and quality of workmanship. The means and methods to achieve same
shall be the total responsibility of the Contractor, including testing for same as
specified herein.
The typical details shown on the drawings, and the criteria set forth herein is
provided to the Contractor to assist in achieving the best workmanship in strict
adherence to architectural design, a stonework installation consistent with
superior structural design procedures, and assurance that all work is designed
and installed in accordance with the best trade practices, the "Standards"
specified herein. The Contractor in co-ordination with said Engineer shall be
responsible for the following:
The Contractor shall prepare a detailed stonework phasing schedule for review
and approval prior to commencement of any stone quarry work, fabrication or
delivery. Said schedule to be reviewed by the Contractor's Engineer and the
Architect concurrently. Schedule shall be revised as required and re-submitted.
Preparation of schedule shall commence immediately upon award of Contract.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED
PARTLY OR WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS17/5
OCTOBER 2021 ISSUED FOR PERMIT SECTION 17 - STONE WORK
Based on the conceptual drawings in the tender document, which show the
overall dimensions of the Building and the control joints, as well as the general
layout of the stones.
The Contractor shall supply, with his tender, details of projects where the same
or similar designs of stonework, joints, fixings and the like have been utilised.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED
PARTLY OR WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS17/6
OCTOBER 2021 ISSUED FOR PERMIT SECTION 17 - STONE WORK
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED
PARTLY OR WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS17/7
OCTOBER 2021 ISSUED FOR PERMIT SECTION 17 - STONE WORK
tolerances, deflection criteria, etc. Shop drawings for stonework shall provide
the following information:
b. Large scale details of all special shaped and fitted pieces including
specification and test reports on jointing compounds used in shop
executed jointing.
c. Typical joint details showing sealant, backer rod, anchors, ties, etc. and
mortar beds where required.
e. Large scale details of anchoring and support for all special pieces.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED
PARTLY OR WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS17/8
OCTOBER 2021 ISSUED FOR PERMIT SECTION 17 - STONE WORK
17.9 CERTIFICATION
Submit certifications stating that all work has been designed, fabricated and
installed in compliance with the Local Authorities' requirements.
Metal parts: the requirements of relevant BS, taken without stress increase for
the loading case of self-weight plus wind
a. Stones shall hold out square at the back, i.e. without corners broken
away whereby the strength of the cramp fixing is impaired.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED
PARTLY OR WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS17/9
OCTOBER 2021 ISSUED FOR PERMIT SECTION 17 - STONE WORK
e. Variation from level: max. 3mm in 6m line and 6mm in 12m or more
Any bow or twist on finished faces of any stone should not vary from the
planes by a dimension exceeding 1mm in 1200mm.
All stones, unless otherwise designed, shall stand up square at all face
corners, so that any deviations in length or height dimensions are reasonably
uniform.
The mortises, sinking, perforations and notches for cramps, dowels and corbel
plates for supporting nibs, shall be formed in accordance with the approved
drawings, and in the factory prior to delivery to site.
Before approval of shop drawings the Contractor shall confirm that the limits of
in-service lateral and vertical deflections which the installation has been
designed to accommodate are according to these specifications.
a. All stone shall be carefully selected, from sound stock, and free from
defects impairing strength, durability or appearance, such as cracks,
seams, starts, holes, flaws or imperfections which have been patched
or filled.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED
PARTLY OR WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS17/10
OCTOBER 2021 ISSUED FOR PERMIT SECTION 17 - STONE WORK
d. The granite shall be the best grade or type within the quarries and shall
have no large-scale veining or any inclusions.
a. General
All stone, interior and exterior to the structure, are selected as provided
herein by the Architect from selected sources.
b. Physical Properties
c. Samples
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED
PARTLY OR WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS17/11
OCTOBER 2021 ISSUED FOR PERMIT SECTION 17 - STONE WORK
All stone shall be cut to sizes, shapes, dimensions, and details as shown on
reviewed shop drawings. There shall be no deviation from jointing shown or
specified thereon. If pre-assembled pieces are proposed, techniques of pre-
assembly and sample where required by the Architect are to be submitted for
review. Adhesives used to be highest quality type.
Exposed surfaces and edges of stone units shall be free from cracks, broken
corners, chipped edges, scratches, or other defects affecting appearance. No
patching or hiding of defects will be permitted. Stone units having flaws or
imperfections are not acceptable and will be rejected, and shall be replaced
with approved material at Contractor's expense.
17.14.1 Thickness
a. Maximum variation in thickness shall be 3mm for stone less than 50mm
thick.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED
PARTLY OR WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS17/12
OCTOBER 2021 ISSUED FOR PERMIT SECTION 17 - STONE WORK
f. Toilet counter vanity tops wash basin openings are to be cut through on
faces and polished finish to receive under-counter mounted wash basin
according to the drawings. Provide for openings as required to suit the
specified toilet accessories and sanitary fittings.
Cut all stone full and true on faces, reveals, beds, joints, and top to the full
dimensions required by drawings. All sawn edges shall be straight and true.
Maximum deviation from straight line or radii indicated shall not exceed 1.5mm
when measured with a 3 metres straight edge or radial template, or plus or
minus one-fourth the width of joints, whichever is more stringent. All units shall
fit together accurately.
Fabricate all stone work so that joints between units shall be as shown on
drawings.
Make faces of stone work in same plane flush at joints. All finished surfaces
shall be true.
Include all cutting, drilling, and fitting of stone work required to accommodate
the work of other trades. In cutting and fitting, carefully cut and grind edges to
a neat, tight fit, cutting in such a manner so as not to impair strength,
appearance or architectural design of stone work. Use physical templates and
accurate site measurements for all cutting and drilling. Obtain required
templates from proper trades.
The Contractor will complete all shop drawings showing panel sizes, any joints
required, sealants and support fixings.
All wash hand basins to be 'under counter' type. Contractor to allow for forming
bullnose finish around wash hand basin openings and front edge of panel as
shown on drawings.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED
PARTLY OR WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS17/13
OCTOBER 2021 ISSUED FOR PERMIT SECTION 17 - STONE WORK
Wind load shall be calculated accordingly to relevant CP. Basic wind speed
shall be taken as 30 m/s for a 3-second gust, at a height of 10m above
ground.
The following values of lateral drift shall be used for the cladding design:
Mortar packing required behind granite cladding shall compose of one part
cement to three parts sand (1:3) thoroughly mixed. Mortar if not mixed by a
mechanical mixer shall be thoroughly mixed twice after adding water on a
clean watertight platform. Mix shall be done in small quantities and used fresh.
Mortar that has begun to set or which has been mixed more than 30 minutes
shall not be used or re-mixed.
All metals and materials selected for the fixing of granite cladding shall comply
with the requirements of the British Standards Institution.
The tying back fixings and load bearing fixings shall be of either:
a. phosphor bronze
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED
PARTLY OR WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS17/14
OCTOBER 2021 ISSUED FOR PERMIT SECTION 17 - STONE WORK
The form of the building and of the surrounding buildings should be considered
in detail when designing the restraint and load bearing fixings. Higher
pressures will be encountered at the corners thereof. The fixings selected
must be capable of being used at any location on any elevation of the building.
The Contractor shall include against the following in the design consideration
for fixings:
b. movement characteristics;
c. thermal expansion;
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED
PARTLY OR WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS17/15
OCTOBER 2021 ISSUED FOR PERMIT SECTION 17 - STONE WORK
The Contractor will be entirely responsible for the attachment of the stones to
the structure.
All fixings should be designed to the appropriate working stresses and all
metals should be of approved type. The suitability of the fixings is to be
supported by detailed calculations by a Registered Engineer in Singapore,
substantiated to the satisfaction of the Architect by tests.
Whenever anchor slot fixings, inserts or fixings of any kind are cast integrally
with the structure, accuracy in setting out is of the utmost importance.
The mortar used for bedding the fixings in place in the stone or in the concrete
structure shall consist of 1 part ordinary or rapid hardening cement to relevant
BS of clean sharp sand.
The mortar should be mixed to a fairly dry consistency and well tamped into
the aperture around the fixing, and allowed to cure for 48 hours before being
subjected to stress.
The tieback or restraint fixings are generally located near the top or side edges
of the stone.
17.22 JOINTS
The Contractor shall be responsible for the accuracy of all setting out of joints
and the proper fitting-in of the stones.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED
PARTLY OR WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS17/16
OCTOBER 2021 ISSUED FOR PERMIT SECTION 17 - STONE WORK
Expanded polyethylene or similar closed cell separator may be used for the
entire depth of the joint. The polyethylene may be removed, the joint checked,
before pointing commences.
Part of the sealant on the face of the building may be extruded as the building
shrinks, and this projection shall require to be trimmed. The sealant must be
compatible with the polyethylene.
Joints should be provided within 1.5m to 3m of each corner of the building, and
it is at such locations that the effect of moisture and thermal movements are
most likely to be pronounced.
17.25 SEALANTS
knife or gun or available as a pre-formed strip or tape used for providing a seal
between stones or between stones and a window unit or structure.
The properties of the selected sealant should comply with the requirements of
relevant JIS, or of the ASTM or of the British Standards Institution.
c. extrusion facility;
d. waterproof;
f. non-staining;
g. be of suitable colour;
h. self-levelling;
i. stability.
Sealants must be applied under the correct weather conditions and should
conform to all the manufacturer's instructions. The sealant should be applied
by experienced persons with professional supervision of an experienced
person approved by the manufacturer.
All stone is to be treated with a proprietary sealant to all faces. The contractor
is to propose a sealant that is suitable and appropriate in the case of each
stone specified.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED
PARTLY OR WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS17/18
OCTOBER 2021 ISSUED FOR PERMIT SECTION 17 - STONE WORK
The colourless waterproof sealant liquid which will not stain, discolour,
disfigure or cause any chemical reactions to the stones but which will prevent
moisture penetration to the stone cladding.
Stones shall be transported in the plane on which the stones are to be fixed in
the Building. Anchorage points should be provided for straps and frames to
hold the units safely in position during transport. Consideration should be given
to the design of racks and other equipment for transportation.
The material selected from the quarry shall be equal to the approved samples
in all respects. The exposed faces and all edges shall be polished and all
special shaping is to be accurately worked before delivery to site, apart from
exceptional circumstances where the work requires to be carried out on site.
Care shall be taken to prevent chipping or damage to arises. All damaged
units will be rejected by the Architect and shall be replaced entirely at the
Contractor's own expense. In this respect no extension of time shall be given
and the Contractor shall be responsible for any delay to the project in the
cause of replacing the damaged or rejected unit.
17.29 EXECUTION
17.29.1.1 General
a. Engineering Development
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED
PARTLY OR WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS17/19
OCTOBER 2021 ISSUED FOR PERMIT SECTION 17 - STONE WORK
f. Sample Submissions
j. Stone Delivery
k Control Panels
l. Stone Erection
17.29.2 Preparation
17.29.3 Installation
17.29.3.1 General
a. Stone with chips, cracks, voids, stains or other defects that are visible
shall not be used in the finished work. Any stone, so installed, shall be
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED
PARTLY OR WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS17/20
OCTOBER 2021 ISSUED FOR PERMIT SECTION 17 - STONE WORK
e. Erect walls plumb and true with joints uniform in width and accurately
aligned.
f. Include all cutting, drilling and fitting of stone work not performed in the
shop and required to accommodate the work of other trades. In cutting
and fitting, carefully cut and grind edges to a neat tight fit. Do cutting in
such manner as not to impair strength or appearance of stone. Use
physical templates and accurate site measurements for all cutting and
drilling. Obtain required templates from proper trades.
a. Install stone work support systems and set stone in accordance with
final reviewed shop drawings. Furnish and install anchors, supports,
fasteners and other attachments shown, or necessary to secure stone
work in place. Shim and adjust accessories as required for proper
setting.
b. Erect walls plumb and true with joints as detailed, uniform in width and
accurately aligned.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED
PARTLY OR WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS17/21
OCTOBER 2021 ISSUED FOR PERMIT SECTION 17 - STONE WORK
e. Maintain cavity space between back of stone wall panels and face of
back-up. Do not fill cavity space with mortar or grout or any other
materials except to the lower 1,000mm that is to be filled with mortar
f. Apply to the back and sides of stone Elastiment seal and glaze sealer
to the lower 1.5m of stone wall panels.
d. Mixing
Add cement just before mixing and mix dry. use as little water as necessary
to produce a workable mix.
a. Setting Procedure
b. Pattern
d. Setting Bed
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED
PARTLY OR WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS17/22
OCTOBER 2021 ISSUED FOR PERMIT SECTION 17 - STONE WORK
e. Any stone unit having a hollow sound after being laid shall be reset to
provide solid backing
f. All interior granite paving units shall be kept perfectly clean. Mortar
joints between stone shall be raked out 12mm for coloured joint grout.
All joints to receive sealant shall be left open, trowel separated through
setting bed. Sealant to be installed as part of this Contract.
i. Anchoring
After all stone units have been set and setting bed is thoroughly cured,
brush joints clean. Thoroughly wet raked out portion of mortar joint and
then fill solid with coloured joint grout. Strike joint neatly and tool to a
dense, slightly concave surface, flush with stone surface. Control joints
in interior paving shall be spaced to Sub-Contractor's recommendation
and be 6mm wide and located to Architect's approval.
k. Provide all anchors, dowels, cramps, wires, etc. where approved shop
drawings for setting all steps and copings. It shall be the responsibility
of the Sub-Contractor to design anchoring system and materials for all
paving and related work.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED
PARTLY OR WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS17/23
OCTOBER 2021 ISSUED FOR PERMIT SECTION 17 - STONE WORK
All access should be safe and adequate to comply with the Factories
Act and other statutory Acts and Laws of Singapore.
All temporary supports, jointing and bedding materials, fixings and tools
and equipment shall be pre-positioned at the fixing point.
All temporary wedges, shims, spacers, and other devices not designed
for permanent inclusion in the structure shall be removed and spaces
made good before fixing.
Apart from normal co-operation with other trades and Contractors, the
Contractor shall liase closely with the aluminium window specialist
contractor, in co-ordinating the weather tightness of the works.
When fixed in position, all stones shall have their faces in exact planes
and be truly vertical. All joints shall be truly horizontal and vertical, as
required.
Before any erection and fixing of stones, vertical and horizontal datum
lines shall be set out, using piano wires or other approved methods.
All joint surfaces shall be cleaned free of dirt, dust, grease or other
deleterious material before sealants are applied.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED
PARTLY OR WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS17/24
OCTOBER 2021 ISSUED FOR PERMIT SECTION 17 - STONE WORK
17.29.9 Prototype
The Contractor shall erect a prototype for testing for wind, water
penetration and other tests to be determined by the Architect.
All stonework shall be protected from the weather elements, and kept
clear of all other building operations. For work involving highly finished or
polished stones, it is essential to provide safe, dry internal storage, away
from main traffic runs.
Hooks, crow-bars, oils, grease, paints, cement slurry and liquid agents
liable to cause staining shall not be used in close proximity to the area in
which stones are stacked.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED
PARTLY OR WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS17/25
OCTOBER 2021 ISSUED FOR PERMIT SECTION 17 - STONE WORK
The Contractor shall take extreme care that all adjoining surfaces such as
window frames, glass panes, etc. are not damaged or stained with mortar
or acids during installation. All stains shall be cleaned immediately.
The Contractor shall be responsible and shall pay all costs for cleaning
and/or replacing frames or glass if they have been damaged or defaced by
mortar or chemicals used for cleaning facings.
17.32 COMPLETION
Clean down all facings remove dirt, mortar, stains, efflorescence or other
harmful material. Use cleaners and procedures recommended by stone
quarry and fabricator. Protect adjacent surfaces from damage during
cleaning operations.
Brush all joints clean, drench and point with tinted mortar. Do not use wire
brushes or acids.
Under this indemnity, the Contractor will be required to make good any
defects and failure in the materials or installation and will be responsible
for any consequential loss attributable to any failure in the stonework
during the warranty period.
If in the opinion of the Contractor, the Specifications are insufficient for him
to give the specified indemnity then the Contractor shall allow in his tender
for upgrading the Specification as necessary to enable him to so
indemnify.
The Contractor shall comply with the building control regulations or local
authority requirement & standards..
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED
PARTLY OR WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS17/26
OCTOBER 2021 ISSUED FOR PERMIT SECTION 17 - STONE WORK
a. All panels used for claddings and their system of fixing shall be
designed to take into account wind load, deflection, relative movements
of the panels and the building frame as well as long term durability and
integrity of the panels and the fixing system.
b. All fixings for securing the cladding to the main structure shall be of
stainless steel, phosphor bronze, aluminium, bronze or other materials
that may be approved by the Building Authority.
Sand shall be clean, sharp, free from salts, vegetable or other deleterious
matter. It shall be gauged as required for the various works. Sand for
pointing shall pass a No. 12 mesh sieve.
Water shall be clean obtained from the PUB mains and shall be free from
any harmful matter whether in suspension or solution at the time when it is
used.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED
PARTLY OR WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
SS018_Painting and Texture Coating
JKT05 SS18/1
OCTOBER 2021 ISSUED FOR PERMIT SECTION 18 - PAINTING AND TEXTURE COATING
SECTION 18
18.1 GENERALLY
The Paintwork and Texture Coating Work, generally, shall be carried out in
conjunction with relevant BS "Code of Practice for Painting of Buildings" and
relevant JIS for texture coating.
All texture coating shall be ceramic quartz and acrylic texture coating or
equivalent.
During the execution of the Works, further samples of all or any of the materials
may be taken by the Architect, and the Contractor is to provide the containers with
necessary seals and all samples at his own expense. The sample may be taken
from sealed or open containers or from the work peoples' pails on the Works.
All material shall be of approved manufacture suitable for the particular purpose
for which to be used, and applied in accordance with the manufacturer's printed
instructions.
All materials for multiple coat work, e.g. priming, undercoat and finishing coats are
to be obtained from the same manufacturer, and to be those recommended by the
manufacturer as suitable for use together, and for the surfaces concerned.
At least 75% of all paints and coatings wet-applied on site , by volume or surface
area, meet the VOC emissions evaluation AND 100% meet the VOC content
evaluation as per LEED Gold Standards
18.2 STANDARDS
Unless other wise agreed by Architect, ensure all of the works comply with the
relevant requirements of the Standards and Codes listed below or referenced in
the body of the Specification. Alternative Standards and Codes may be submitted
to the Architect, provided it can be demonstrated that the alternative Standards
and Codes comply with the requirements of the standards specified. All standards
and Codes quoted are the current version, unless specific year references are
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS18/2
OCTOBER 2021 ISSUED FOR PERMIT SECTION 18 - PAINTING AND TEXTURE COATING
noted.
Singapore Standards (or equivalent local Standards)
Other Standards
All materials are to be delivered to the Site fresh and in the original sealed
containers, bearing the manufacturer's name. The containers are to be clearly
marked with a description of the contents.
All materials are to be stored on the Works, and precautions taken to minimise
exposure to high temperatures and in accordance with manufacturer’s
recommendation. Use in order of delivery and before service life expiry date.
After stoppage of work and when containers are not in use, close the containers
(empty or otherwise) and remove to the designated storage area.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS18/3
OCTOBER 2021 ISSUED FOR PERMIT SECTION 18 - PAINTING AND TEXTURE COATING
18.4 TEST
All materials for paint and film and coating finishes may be subjected to tests,
including, but not limited to, the following:
Samples of testing shall be supplied without charge. The costs of testing shall be
borne by the Contractor.
The Contractor shall allow for applying a test colour patch over the appropriate
undercoat of the various surfaces specified to be coated, and for obtaining the
Architect's approval before proceeding with the painting and coating work.
Colours will be selected from the British Standard range of colours, and shall be
mixed as necessary to the instructions of the manufacturer. The Contractor shall
allow for any special colour mixing and/or blending required.
The Contractor shall keep, on site, British Standard Colour Charts of the selected
colours, to relevant BS. Standard colour charts will be used for comparison, and
colours that do not match will be rejected.
Colours for other materials will be selected from the range of colours supplied by
the manufacturer.
Any work executed with material found on test not to fulfil the necessary
requirements, is to be burnt off, or otherwise removed and made good.
The mixing of paints and coatings of different types and brands will not be
permitted.
All decorative finishes are to be applied with proper brushes or as directed by the
manufacturer. The use of coarse brushes and rags is prohibited.
Unless otherwise instructed by the Architect, all materials shall be evenly spread
and shall be finished uniform in colour free from runs, brush marks or roller marks,
to a high gloss finish. Each coat, prior to the finishing coat, including sealer,
primers, etc. shall be properly rubbed down with pumice, steel-wool, glass-paper,
emery paper, waterproof garnet paper or cutting compound, whichever is the most
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS18/4
OCTOBER 2021 ISSUED FOR PERMIT SECTION 18 - PAINTING AND TEXTURE COATING
suitable for the particular surface, to produce the highest quality finish. Wherever
practicable rubbing shall be wet, using one (1) of the above, in combination with
water, lime water, turpentine or benzene.
The Contractor shall allow the minimum drying time between coats as
recommended by the manufacturer.
All ironmongery & electrical cover plates, shall be removed before painting and
coating, and shall be replaced after the final coats have been applied and
approved.
Floors and other work and fittings are to be properly covered up and protected,
and painting pots, etc. are not to be placed on impervious coverings, window cills,
etc.
The Contractor shall allow for painting walls or panels in different tints or colours,
as samples. Subsequent work shall be identified to be sample of colours
approved by the Architect.
The number of coats indicated is in addition to the sealer or priming coat. Each
undercoat shall be in a visibly different tint from the preceding coat, and coloured
to suit the finishing coat.
Where the number of coats specified does not result in an uniformly solid
appearance, and is due to the faulty materials or application, the Contractor will be
required to apply further coats to arrive at a satisfactory appearance, entirely at
his own expense.
Where in the opinion of the Architect, such faulty appearance is due solely to the
selection of the colour and texture; the Contractor must refer to the Architect and
await his instructions before proceeding with further coats.
No painting and coating work shall be carried out before the work of all specialist’s
contractor has been substantially completed, and the areas concerned thoroughly
cleaned. Clean conditions shall be maintained during all painting work.
No paint and coating shall be applied to surfaces that are damp or dusty, and
immediately prior to painting and coating, recipient surfaces are to be inspected
by the Architect for approval.
Inform the architect when the first section of paint has cured. Undertake a pull off
test by complying with ASTM D3359-02.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS18/5
OCTOBER 2021 ISSUED FOR PERMIT SECTION 18 - PAINTING AND TEXTURE COATING
Carry out adhesion test when directed by the architect. Adhesion tests are to be
carried out in accordance with SS 5
Remove form oil. Mould release oil, laitance, grease, dirt and debris from concrete
surfaces using a suitable solvent and then neutralize. Remove grit, dirt, loose
materials, mortar drippings and the like; remove all nibs, projections and
protuberances.
Patch concrete surfaces with a non shrink cementitious grout, or filler compound,
suitable for such use filling all cracks, depressions, and voids to provide smooth
surfaces. Refer any defects other than surface imperfections to the Architect
before patching.
Prior to application, allow the concrete to cure for a minimum of 30 days. Test the
concrete surfaces for moisture content and ensure that the moisture content is
below 15% of a Protimeter scale is used and below 6% if a Kett meter is used.
Plastered surfaces are to be allowed to dry out not less than 14 days. All dust,
dirt, plaster splashes or efflorescence is to be brushed off or removed by wiping
first with a dry coarse cloth and then with a damp clothe. The surface is then to be
left for forty-eight (48) hours to ascertain if further efflorescence occurs.
All cracks, holes, crevices, etc. shall be filled with approved filler for e.g. Din Filler
patty or equivalent before any coating commences.
Primer
Apply 1-2 coats of a deeply penetrative silicone primer with intense infiltration and
breathability properties that is highly water repellent, by roller/ brush to achieve a
spreading rate of 0.10 - 0.15 kg/ m2/coat. Allow 2 hours drying time.
Texture Coat:
Apply 1 coat of a water-reducible modified acrylic resin reinforced spray body
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS18/6
OCTOBER 2021 ISSUED FOR PERMIT SECTION 18 - PAINTING AND TEXTURE COATING
texture, by spray to achieve a spreading rate of 1.00 –1.70 kg/ m2/coat. Allow 24
hours over-coating interval.
Top Coat
Apply 2 coats of a super-durable water-based acrylic silicone resin paint, by roller/
brush to achieve a spreading rate of 0.15 - 0.20 kg/ m2/coat. Allow 2 hours
drying time before re-coating. Allow 24 hours for final curing.
The specified paint shall fulfil the Japanese Industrial Standard for silicone resin
paint under JIS 5660 test.
a. The said paint system shall possess the following technical test data: -
b. The said paint system shall possess the following performance test data: -
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS18/7
OCTOBER 2021 ISSUED FOR PERMIT SECTION 18 - PAINTING AND TEXTURE COATING
i) Substrates receiving paint should be sufficiently cured, sound and free from
foreign substances, surface stresses and cracks.
ii) Remove thoroughly sandy and chalky layers that are incapable of receiving
paint by cleaning with water jets.
iii) Heavily soiled surfaces must be properly treated.
iv) Any damaged receiving substrate shall be leveled and repaired prior to
application of the paint.
v) Preparation of substrate, priming and painting shall be carried out in
accordance with the manufacturer’s recommended instructions.
After the plastering of the fibrous plaster surface to remove all the uneven
surface, apply one coat of sealer and finish with two (2) coats emulsion paint.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS18/8
OCTOBER 2021 ISSUED FOR PERMIT SECTION 18 - PAINTING AND TEXTURE COATING
a. The ceramic silicone type enamel painting system shall comply with the
following application specification: -
Surface Preparation
The mild steel surface has to be shop-primed and applied with epoxy-based anti-rust
primer by the Steel Supplier prior to application of the coating systems.
b. The coating system shall comply with the following application specifications: -
Anti-rust primer
Apply 1 coat of a high-build epoxy/ polyamide rust-preventing primer, by spray to
achieve a spreading rate of 0.14 - 0.16 kg/m2. Allow minimum 16 hours over-coating
interval.
Undercoat
Apply 1 coat of a two-component high build epoxy-polyamide cured primer, by brush/
roller to achieve a spreading rate of 0.15- 0.25 kg/m2. Allow minimum 8 hours over-
coating interval.
Mid Coat
Apply by roller/ brush 1 coats of an acrylated polyol/ isocyanate cured two pack
polyurethane resin enamel incorporating premium grade weather resistant pigments,
to achieve a spreading rate of 0.125 – 0.15kg/m2/coat. Allow 24 hours for final curing.
Finishing
Apply by roller/ brush 1 coat of a special modified ultra-antipollution, super durable,
two component reactive type curing enamel coating combining special ceramic
elements (inorganic base) and acrylic-silicon resin film (organic base), to achieve a
spreading rate of 0.13 – 0.15kg/m2/coat. Allow 24 hours for final curing.
- Excellent adhesion and bonding strength onto substrate due to its special
molecular structure by Siloxane Bond (-Si-O-Si-)
- Easy cleaning function due to its ceramic film
- Excellent weathering performance
- Heat resistance and incombustible
- Outstanding chemical and solvent resistance
- Excellent mould and fungus resistance
- Forms a strong and hard density film which shuts out water and carbon
dioxide penetration, hence excellent against carbonation and neutralization
- Good abrasion and scratch resistance
- Stain resistance
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS18/9
OCTOBER 2021 ISSUED FOR PERMIT SECTION 18 - PAINTING AND TEXTURE COATING
d. The said paint system shall possess the following technical data: -
18.9.1 The ceramic silicone type enamel painting system shall comply with the following
application specification: -
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS18/10
OCTOBER 2021 ISSUED FOR PERMIT SECTION 18 - PAINTING AND TEXTURE COATING
18.9.2 The said paint system shall possess the following characteristic: -
- Excellent adhesion and bonding strength onto substrate due to its special
molecular structure by Siloxane Bond (-Si-O-Si-)
- Easy cleaning function due to its ceramic film
- Excellent weathering performance
- Heat resistance and incombustible
- Outstanding chemical and solvent resistance
- Excellent mould and fungus resistance
- Forms a strong and hard density film which shuts out water and carbon dioxide
penetration, hence excellent against carbonation and neutralization
- Good abrasion and scratch resistance
- Stain resistance
- Excellent gloss retention
The said paint system shall possess the following technical data: -
Large or loose-knots are to be cut, and replaced with sound wood or cut back and
the surface made good with filler. Smaller knots are to be treated with two (2) thin
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS18/11
OCTOBER 2021 ISSUED FOR PERMIT SECTION 18 - PAINTING AND TEXTURE COATING
coats of knotting. Open grains shall be surface filled. The surfaces to be then
primed with one (1) coat of wood primer, well brushed on.
18.10.1 Polyurethane coating for timber coating. The clear coating system shall
comply with the following application specifications: -
Finishing
Apply by roller 2-3 coats of a one pack modified polyurethane clear coating for
old and new surfaces of timber to enhance the natural beauty of the wood, to
achieve a spreading rate of 6 sq m/litre/coat. Allow within 3hour over-coating
interval and 24 hours for final curing.
The said paint system shall possess the following technical data: -
External varnishing shall consist of two(2) coats of wood stain and two(2) coats of
satin clear finish, or equivalent resin based varnish.
Internal varnishing shall consist of one(1) coat of wood stain and two(2) coats of
clear finish eggshell finish, one(1) pack polyurethane varnish.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS18/12
OCTOBER 2021 ISSUED FOR PERMIT SECTION 18 - PAINTING AND TEXTURE COATING
Unless otherwise specified, apply one coat of polyamide epoxy primer followed by
two coats of enamel paint.
Apply two (2) coats Chlorinated Rubber Base Roadline Paint. Application shall be
by brush or spray.
18.14 APPLICATION
The Contractor to observe the following sequences in the carrying out of the
painting and coating works.
a. Colour
b. Porosity Sealing
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS18/13
OCTOBER 2021 ISSUED FOR PERMIT SECTION 18 - PAINTING AND TEXTURE COATING
c. Priming Generally
Apply in a wet even film over all surfaces, ensuring adequate thickness at
edges and angles, and avoiding excessive brush marks, sags, runs, orange-
peel and other defects.
e. Brush Painting
Lay off all areas evenly and ensure that brush marks have been minimised.
f. Roller Painting
Use foamed plastic or short pile sheepskin rollers. Use brushes for cutting-
in. The following must not be applied with rollers:
1 External paintwork
2 Priming coats
3 Work not of a simple character
4 Where specifically described to be brush or spray painted
g. Spray Painting
Use approved equipment with airless spray methods. Do not spray where
soiling of adjacent surfaces cannot be prevented. Spray painting must be
utilised to all doors, and where shown on the Drawings.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS18/14
OCTOBER 2021 ISSUED FOR PERMIT SECTION 18 - PAINTING AND TEXTURE COATING
Mask all adjoining surfaces and take all necessary precautions to prevent
contamination of adjoining areas by spray mist, and accumulation of vapour.
Before commencing any work, adjoining areas that are not to be painted, or have
been already painted, shall be properly protected.
Any finished surfaces which are stained or blemished, to be cleaned and made
good by the Contractor, to the satisfaction of the Architect, entirely at the
Contractor's expense.
The whole of the work is to be left in a clean and totally satisfactory condition on
completion, with all runs, splashes, etc cleaned off and made good to the
Architect's satisfaction. Provide adequate signage and barriers to protect the
general public, and to prevent damage to freshly applied coatings.
The aluminium finish shall be unless specifically stated as other, a PVDF 4 coat
(Polyvinylidene Flouride) system colour as stated in the finishes schedule and as
approved by the Architect. High performance organic coatings to relevant BS &
AAMA and paint manufacturer’s specifications.
The application of the selected finishes may either be carried out at the
Contractor's plant or by an approved Applicator. Any application shall be an
accredited Applicator for the paint system and materials being applied. All
applications are to be made by the same applicator.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS18/15
OCTOBER 2021 ISSUED FOR PERMIT SECTION 18 - PAINTING AND TEXTURE COATING
The approved paint system will comprise products of one (1) manufacturer
selected for suitability for the particular application and shall include all preparatory
and or priming coats, conforming to relevant AAMA.
The finish shall meet or exceed the requirements of relevant AAMA when tested
by an independent testing laboratory for the following properties:
a. adhesion
b. scratch resistance impact
c. cupping
d. resistance to mortar
e. resistance to acetic acid/salt spray
f. resistance to humidity
g. weathering
The mild steel surface has to be shop-primed and applied with epoxy-based anti-
rust primer by the Steel Supplier prior to application of our coating systems.
To establish the DFT required for the specified time period of fire resistance, it is
necessary to correlate the Hp/A values with the DFT from the “Size of steel material
and film thickness” chart
The coating system shall comply with the following application specifications: -
Undercoat:
Apply 1 coat of SK Tighca Coat Primer OR APPROVED EQUIVALENT, a two-
component high build epoxy-polyamide cured primer, by brush/ roller to achieve a
spreading rate of 0.15- 0.25 kg/m2.
Base coat:
Apply 2-3 coats of SK Tighca Coat Base OR APPROVED EQUIVALENT, a low
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS18/16
OCTOBER 2021 ISSUED FOR PERMIT SECTION 18 - PAINTING AND TEXTURE COATING
Topcoat:
Apply 2 coats of SK Tighca Topcoat OR APPROVED EQUIVALENT, an
environmental-friendly water-based acrylic reactive type paint forming by chemical
cross-linking structure, by roller to achieve a spreading rate of 0.25 – 0.35 kg/ m2.
The said paint system shall possess the following technical data: -
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS18/17
OCTOBER 2021 ISSUED FOR PERMIT SECTION 18 - PAINTING AND TEXTURE COATING
Prior to commencement of external painting works, the Contractor shall lodge with
the Architect a 5-year indemnity against defects in the external painting works and
10-year indemnity against defects in intumescent coating to steel structures.
The defects shall include but not limited to watertightness, peeling, bubbling,
cracking, disintegration of materials, patchy discolorationn, flakey or powdery
surfaces, uneven loss in gloss or brightness or colour fade.
Under this indemnity, the Contractor will be required to make good any defects
and failure in the materials or installation and will be responsible for any
consequential loss attributable to any failure in the external painting works during
the warranty period.
If in the opinion of the Contractor, the Specifications are insufficient for him to give
the specified indemnity then the Contractor shall allow in his tender for upgrading
the Specifications as necessary to enable him to so indemnify.
18.20 RATES
The description of and rate of each item of painting and coating work included in
the Supplementary Schedule of Rates will be held to include for preliminary
preparatory work to the surface required before the application of any material, all
multi-coloured work and cutting to line and rubbing down between coats, the
provision, erection and removal of scaffolding, the protection and/or masking of
floors, fittings and the like, removing and replacing door and window furniture and
removing splash and spray marks, and for painting and coating in different tints
from wall to wall and/or room to room.
The description of and rate of each item of painting and coating to piping, included
in the Supplementary Schedule of Rates will be held to include for painting on all
fittings, stop-cocks, clips, brackets, grounds, etc. and for painting colour bands.
18.21 FOR ALL INTERNAL WALLS AND CEILING – WITH GREEN LABEL
CERTIFICATION
Low VOC, low odour, stain resistant and anti-bacterial property water based silicon
emulsion paint
The painting system shall comply with the following application specifications: -
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS18/18
OCTOBER 2021 ISSUED FOR PERMIT SECTION 18 - PAINTING AND TEXTURE COATING
Primer
Apply 1 coat of a water-based, low VOC low odour acrylic sealer/ primer designed
for application to both exterior and interior of old and new masonry, plastered
painted surfaces, by roller/ brush to achieve a spreading rate of 0.15 – 0.20 kg/
m2/coat. Allow 2 hours drying time.
Top Coat
Apply 2 coats of a water-based, low VOC, excellent staining resistant, dirt
resistant emulsion paint of less than 1% (Volatile Organic Content) low odour
environmental-friendly coating incorporating special silicon resin, by roller/ brush
to achieve a spreading rate of 0.25 – 0.30 kg/ m2/coat. Allow 2 hours drying time
before re-coating. Allow 24 hours for final curing.
The said paint system shall possess the following performance test data: -
At least 75% of all paints and coatings, by volume or surface area, meet the VOC
emissions evaluation and 100% meet the VOC content evaluation as per LEED
Gold Standard requirements
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS18/19
OCTOBER 2021 ISSUED FOR PERMIT SECTION 18 - PAINTING AND TEXTURE COATING
Every coat of paint must be thoroughly dry and rubbed down with fine sand paper
where necessary before any subsequent coat is applied.
The description of preparation and painting hereunder is for general guidance but
the Contractor will be expected to comply with the detailed recommendations of
the manufacturer and his prices will be deemed to include for this.
Plastered surfaces are to be carefully rubbed down smooth to remove all loose
particles and efflorescence. All cracks and other imperfections shall be cut out
and make good with suitable plaster and painted. The first coat is sealing coat
and shall be thinned in strict accordance with the manufacturer’s
recommendations and the remaining coats applied neat. Paint one coat alkali
resisting primer, one undercoat and two coats emulsion paint.
Generally, all internal wood work including external doors and windows are to
be stained and applied with three coats polyurethane varnish.
Preparation:
New unprimed wood work shall be clean from dirt, grease, etc rubbed down or
scraped smooth and dusted off.
Priming:
A think coat of best patent knotting shall be applied to all knots and allowed to
harden. The surface shall then be primed.
Stopping :
When the primer is hard all cracks, holes, open joints and other imperfections
shall be made good with hard stopping of the following type :-
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS18/20
OCTOBER 2021 ISSUED FOR PERMIT SECTION 18 - PAINTING AND TEXTURE COATING
- Best washed whiting and boiled linseed oil, well kneaded together with at
least 10% ground white lead in oil worked into;
All wood work shall be carefully sanded down after filling and stopping.
Internal woodwork requiring a clear finish shall be filled with an approved filler
coloured to match the natural wood colour. The following finishes shall be
applied as required by the particular specification.
- Prime with 1 coat of uncoloured shellac, sand lightly and wax polish with 2
coats applied at 4 hour intervals using a soft line free cloth and finish to an
eggshell finish with a soft bristled brush.
All mortar or plaster splashes, etc shall be removed from the plasterboard by
careful scraping, any oil or grease spots shall be removed with white spirit, all
holes shall be filled with gypsum plaster and the whole surfaces brushed down
to remove dust and other loose materials.
Prepare and apply two coats of Hi-pac P510 or other approved polyurethane
coating to walls and must be carried out by a Specialist approved by the Architect
and in accordance with the manufacturer’s printed instructions.
Samples of the polyurethane finish works must be submitted to the Architect for
approved prior to the commencement of the works, The spray coat is to have
complete anti-fungal and weather resistant properties.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS18/21
OCTOBER 2021 ISSUED FOR PERMIT SECTION 18 - PAINTING AND TEXTURE COATING
18.25 RATES
Rates for painting are to include for all necessary preparation of the surfaces
including cleaning off, and sand papering wood wok, wire brushing metal and
leaving all surfaces free from dust, rust, grease and oil before painting. In addition
rates shall include for additional scaffolding required, all extra labour involved in
external or internal work and all cutting in to line narrow widths and girths.
Rates shall also include for carrying out all works in accordance with the
manufacturer’s instructions and for using the correct undercoat and the correct
shades.
Rates for painting to walls, soffits, etc are to include for painting two finishing coats
to all electrical cables, battens, roses, etc to match the colour of the surface to
which they are fixed.
18.26 PROTECTION
Display “WET PAINT” signs and provide adequate protective barriers whenever
and wherever necessary.
Provide portable extract fans to ventilate the area while spray painting is carried
out and to prevent spray painting from emitting into air-con diffuser or exhaust
grille.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS18/22
OCTOBER 2021 ISSUED FOR PERMIT SECTION 18 - PAINTING AND TEXTURE COATING
All paint and paint work shall have a 5 years warranty against discoloration
peeling, blistering, flaking, cracking and any other forms of unacceptable defects
except general wear and tear. If such defects are detected, the contractor shall
scrape off the all faulty paint and reprime and repaint the areas involved as in
accordance with the specification. Upon completion of the remedial works, the
new repainted area shall have a 5 years warranty dated from the day of
completion of the remedial painting.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
SS019_Siphonic Roof Drainage System
JKT05 SS19/1
OCTOBER 2021 ISSUED FOR PERMIT SECTION 19 - SIPHONIC ROOF DRAINAGE SYSTEM
SECTION 19
19.1 GENERALLY
All materials and workmanship the best of their respective kinds subject to the
inspection by the Architect at any stage shall be of manufacture or erection and shall
comply with the latest relevant Singapore Standard unless otherwise stated and the
relevant Singapore Standard Code of Practice or equivalent British Standards and
codes. All samples shall be supplied free of charge.
This section specifies the requirements necessary for the design, manufacture,
supply, installation, testing & commissioning, warranty of Siphonic Roof Drainage
System for the conveyance of rainwater from the roof to ground discharge point via
connection to the drainage system for the whole project.
The Siphonic Specialist shall be responsible to design, supply and install the complete
Siphonic Roof Drainage System. The Specialist shall do the installation of the
complete Siphonic Roof Drainage System where no sub-letting of installation works is
allowed in this system.
All Siphonic systems must carry an international recognized certificate (e.g. British
Board of Agreement Certificates or PSB Test Certificate) or equivalent local
Standards.
Location of application: Siphonic system shall be applicable to Main building block and
ancillary buildings with building height more than 6m.
19.2 PRODUCTS
19.2.1 Standard
The Siphonic system shall generally be designed and installed in accordance with
Singapore Standard SS 525 (Code of Practice for Roof Drainage) and relevant British
/ local Standards.
Siphonic system shall be Fast Flow Siphonic system or approved equivalent system.
The system shall be designed and manufactured to meet the specified performances
and requirements on dimension, thickness and visual appearance, and fit for the
prevailing local weather conditions. The roof rainwater shall discharge effectively from
the collection points to the discharge points upon completion. Pipes and fittings must
meet the local manufacturer’s performance specification.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS19/2
OCTOBER 2021 ISSUED FOR PERMIT SECTION 19 - SIPHONIC ROOF DRAINAGE SYSTEM
The Siphonic Roof Drainage System proposed by the Specialist must have a track
record of system design, supply and install in Singapore for at least 10 years c/w job
reference in Singapore and have a track record in the world market for more than 10
years.
The minimum flow velocity in the system shall not be less than 0.7 m/s for horizontal
pipes and 2.2 m/s for vertical pipes.
When the system is operating at its design intensity, the high velocity of the water will
ensure the system is performing self-cleansing inside the pipeline.
Self-cleansing shall also occur at the rainfalls as low as 50% of the design intensity. At
rainfalls less than the Siphonic roof drainage system shall operate under vented
gravity flow conditions.
The Siphonic outlet shall be the proven product evident with design technical data (ref
BBA Certificate or PSB Certificate), performance graph, test certificate, etc for primary
acceptance.
The system design shall also ensure that the outlets eliminate the intake of air into the
system. This set up full-bore flow and maximizes the capacity of the pipe work. All
exposed to weather component of the rain water outlet shall be of full metallic
construction for good weathering & durability.
The Siphonic outlet base plate shall be of stainless steel body complete with
aluminium alloy leaf guard & air baffle. The siphonic outlet stainless steel base plate
shall not have a recess of more than 20mm into the roof slab/metal gutter in order not
to interfere with the structure element.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS19/3
OCTOBER 2021 ISSUED FOR PERMIT SECTION 19 - SIPHONIC ROOF DRAINAGE SYSTEM
The Siphonic outlets shall come complete with stainless steel water proofing clamp
ring for water-tight interfacing with waterproofing material on RC roof/ scupper
construction.
Water-proofing material shall terminate within the base plate unit of the Siphonic outlet
and properly secured by the stainless steel water proofing clamping ring complete with
stainless steel bolts and nuts for water-tightness construction. Water proofing
membrane shall not rap into the outlet spigot as this will reduce the effective bore of
the siphonic outlet.
Siphonic outlets shall come complete with aluminium counter flange and EPDM water
seal for outlet installation on metal gutter for water-tightness requirement on Metal
roof/ gutter construction. Silicon joint as primary with tightness barrier for outlet
installation on metal gutter is not acceptable.
All aluminium flanges and EPDM insulation should be properly secured with the base
plate unit of the Siphonic outlet complete with stainless steel bolts and nuts for water-
tightness construction.
System design shall be supported by calculation report generated for each designed
system. Details of in-line components contained within each system shall also be
clearly indicated. The calculation report shall show clearly the following:
• Drainage capacity
• Velocity
• Upstream pressure
• Downstream pressure
• Headloss
The calculation report must clearly indicate the system imbalance in separate
sections. In system more than one outlet, the imbalance in the system should not
exceed 10% of the hydraulic head (m) or 0.5m, whichever the smaller.
The Siphonic system shall be designed by selecting suitable size and quantity of outlet
to accommodate the computed rainfall. The computed flow from an individual outlet
shall not exceed the specified maximum capacity for each outlet type size.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS19/4
OCTOBER 2021 ISSUED FOR PERMIT SECTION 19 - SIPHONIC ROOF DRAINAGE SYSTEM
The pipe material shall be of cast iron pipe to comply with the performance
specification for DIN 1691 or EN877 standard and carry a British Board of Agreement
Certificates for the total pipe system. All cast iron pipes and fittings are finished
externally with red oxide primer. Internally, pipes and fittings are finished with
corrosion resistant epoxy coating. The pipe material should also meet the requirement
as stated by the System Technical Manual of Siphonic Roof Drainage System.
The selection of pipes & fittings must be able to withstand a working sub atmospheric
pressure of –0.9bar.
Siphonic System moulded or fabricated pipe fittings must be capable of either resisting
longitudinal forces without sliding apart or must be restrained to prevent relative
movement to the Siphonic Specialist’s requirement.
Sharp radius bends in excess of 45 degrees deviation from the direction of flow should
not be used.
The Siphonic Roof Drainage System shall be designed to use Cast Iron pipe and
fittings subject to withstand both positive and negative pressure required by the
system.
19.9.1 Sample
The Specialist shall submit sample of all major and minor material classified under
the Siphonic Roof Drainage system scope of supply. Sample submits shall be
accompanied with relevant Product data, such as catalogue, technical data as the
supporting documents for review & approval.
The Contractor shall submit 3 sets of Shop drawings & Typical Installation Details
showing outlets position, pipe routes, location and length of each pipe size, including
all relevant details of accessories and assemblies complete with Engineering
Calculation with PE Endorsement for approval before construction.
The Specialist shall submit a detail Work Program with referenced to Master Work
Program depicts the interfacing works elaborated with the Builder and their scope of
works.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS19/5
OCTOBER 2021 ISSUED FOR PERMIT SECTION 19 - SIPHONIC ROOF DRAINAGE SYSTEM
The Specialist shall submit the As-Built Shop drawings upon the completion of
installation and handing over of the system for permanent operation.
19.10 INSTALLATION
All pipe works shall be fabricated, assembled, jointed and supported as per pipe
manufacturer’s recommendation & requirements subject to the material chosen and
confirmed by the Architect.
The contractor shall maintain all pipes installation is as per system designed. Any
changed of piping re-route, level, dimension deviated from the approved shop
drawings which might be significantly affected the performance shall be reconfirm by
System calculation and gain approval by the System designer and Architect.
The Siphonic Specialist must have its own in-house Design and Operation
Department based in Singapore or Indonesia. The specialist must submit its
company profile and CV of staffs within Singapore or Indonesia to facilitate the
design and installation of the project.
The system shall not be utilized as temporary roof drainage system during the
construction period.
The Specialist shall conduct the Leak Check to the outlet during the roof water
proofing ‘Ponding Test’ by ensuring proper jointing and water tightness around
outlets.
The Specialist shall conduct flow test to all pipe works and visual inspection to
ensure proper jointing at all joints is maintained.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS19/6
OCTOBER 2021 ISSUED FOR PERMIT SECTION 19 - SIPHONIC ROOF DRAINAGE SYSTEM
The Specialist shall conduct at least one dynamic flow test to ensure proper
discharging from collection points to discharge points.
The Specialist shall conduct visual inspection at no additional cost to ensure proper
performance of the Siphonic Roof Drainage. The Specialist shall inspect and
maintain all Siphonic roof outlets installed in the building including cleaning of outlet
surface caused by build-up of debris, where necessary. Water flow test will be
conducted for the pipe works where water point is available on the respective roof.
The Specialist shall be able to gain access to all RC flat roof / metal gutter to
conduct visual inspection and maintenance of the roof outlets.
The roof drain to be covered with removable wire mesh to control Birds harborage
This section specifies the requirements necessary for the design, supply and
installation of the Pressurised Drainage System for the conveyance of rainwater
from the terraces, balconies, corridors, planters, lobby etc to ground discharge point
via connection to the drainage system for the whole project.
The Contractor shall carry out the installation of the complete Pressurized Drainage
System to be in accordance to the Manufacturer’s design requirement /
recommendation.
This section shall be used in conjunction with, but not limited to, the other relevant
specifications, the Drawings and Contract Documents to establish the total
requirements for the installation of the Pressurised Drainage System.
In the event of conflict regarding the roof drainage system requirements between
this section and any other document, the more stringent requirement shall apply,
unless otherwise specifically instructed by the Architect.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS19/7
OCTOBER 2021 ISSUED FOR PERMIT SECTION 19 - SIPHONIC ROOF DRAINAGE SYSTEM
The Siphonic system shall generally be designed and installed in accordance with
Singapore Standard SS 525 (CP for Roof Drainage) or equivalent local Standards.
The effective catchment area for the covered balcony should be taken as half the
exposed vertical area of the wall up to a maximum height of 10m at a dimensional
rainfall intensity of 165mm/hr in compliance with SS525 : Code of Drainage Practice
(or equivalent local Standards).
The Contractor shall produce Schematic Design diagram for the Pressurised
Drainage System complete with PE Endorsement for approval before construction to
verify that the drainage capacity of each System is in accordance to the
Manufacturer’s recommendation.
All open to sky area shall be provided with siphonic terrace outlet. The outlet
consists of epoxy coated aluminum alloy body, stainless steel edging frame and
epoxy coated aluminum alloy air baffle to the Manufacturer’s details.
All balcony shall be provided with siphonic balcony outlet. The outlet consists of
epoxy coated aluminium alloy body, stainless steel edging frame and stainless steel
tile tray to the Manufacturer’s details.
The above components shall be hydraulically tested and validated by PSB, complete
with are port that verify the drainage capacity of each component.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS19/8
OCTOBER 2021 ISSUED FOR PERMIT SECTION 19 - SIPHONIC ROOF DRAINAGE SYSTEM
The pipe material to be used in this project for Pressurised Drainage System shall
be UPVC pipes material (external & underground in cast iron material) in
accordance to SS525 (CP for Roof Drainage) standard or equivalent local Standards
to be approved by the Architect.
Pipe joints must be capable of either resisting longitudinal forces without sliding
apart or must be restrained to prevent relative movement.
19.20.1 Sample
The Contractor shall submit sample of all Components. Sample submits shall be
accompanied with relevant Product data, such as catalogue, PSB Report as the
supporting documents for review & approval before installation works commence on
site.
The Contractor shall submit 3 sets of Shop drawings, Schematic Design Diagram &
Typical Installation Details showing outlets position, pipe routes, location and length
of each pipe size, including all relevant details of accessories and assemblies.
The Contractor shall submit the As-Built Shop drawings upon the completion of
installation and handing over of the system for permanent operation.
19.21 INSTALLATION
All pipe works shall be fabricated, assembled, jointed and supported as per pipe
manufacturer’s recommendation & requirements subject to the material chosen and
recommended by the Manufacturer to be approved by the Architect.
The Contractor shall submit method of statement to ensure any possible entries of
debris and foreign material likely to affect the system performance during the
construction period.
The system shall not be utilized as temporary roof drainage system during the
construction period unless otherwise obtained written approval from the Architect
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS19/9
OCTOBER 2021 ISSUED FOR PERMIT SECTION 19 - SIPHONIC ROOF DRAINAGE SYSTEM
The Contractor shall conduct flow test to all pipe works and visual inspection to
ensure proper jointing at all joints is maintained.
The Contractor shall conduct at least one dynamic flow test to ensure proper
discharging from collection points to discharge points.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
SS020_Signage
JKT05 SS20/1
OCTOBER 2021 ISSUED FOR PERMIT SECTION 20 - SIGNAGE
SECTION 20
20.0 SIGNAGES
20.1 GENERALLY
b. All Code Compliant and Cautionary signages shall be bilingual (English and
Bahasa) unless specified otherwise.
c. Font to be SEGOE (07-03) as per Owner’s Standards. The font size may
vary as per signage type.
e. Where indicated, the company logo shall be the official company logo, as
provided by the Owner in camera ready or digital medium
Contractor shall review the Signage Schedule for correct copy context and
directional arrows in relationship to floor plan. Note recommended changes in
shop drawing submittals.
The Contractor shall erect full size mock up samples of all signage’s and obtain
approval before proceeding with the rest of the works.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS20/2
OCTOBER 2021 ISSUED FOR PERMIT SECTION 20 - SIGNAGE
The Architect reserves right to instruct the demolition and reproduction of all
signage’s considered substandard or wrongly produced as determined from
design, drawings, visual inspection, etc.
If for any reason in the opinion of the Architect these defective works are not
practical or convenient to remedy, the Architect shall ascertain the diminution in
the value of the Works due to the existence of such defects and deduct such
amounts from monies due to the Contractor or he may choose to impose an
amount as penalty.
20.4 REQUIREMENTS
All signage’s shall be carried out according to the specified Standards and Codes
of Practice and shall comply with all Building and Safety Regulations including
latest Building Control Act (or equivalent local authority Regulations/ Standards).
The Contractor shall liable for any defects/damages arising out of non-conformity
and all necessary remedial works shall be carried out at Contractor’s own cost
and time.
The Contractor shall take into account any constraints or effects imposed by the
existing works and services in the surrounding areas and works of other nearby
contractors.
The Contractor shall also submit the necessary shop drawings and obtained
approval from the Architect prior to order, fabrication and installation.
The Contractor shall co-ordinate and work closely with the Architect.
The Contractor shall submit 3 sets of paper prints and 1 set of re-producible of
complete shop drawings of all signs to Architect for approval before fabrication.
Full size details of all exposed edges, joints between materials and details which
affect the appearance shall be included. Prints of copy layouts with white
letterings on black background shall also be provided.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS20/3
OCTOBER 2021 ISSUED FOR PERMIT SECTION 20 - SIGNAGE
d. Type of finish;
f. Mounting details of sign units to the door, floor, ceiling or wall where
appropriate.
The shop drawings shall include instructions and explanatory details for the
sequence of fabrication, assembly, erection and the installation of all materials
and elements.
20.5.2 Sample
The Contractor shall submit mock-up samples of layout and choice of colours for
each sign for approval before commencement of fabrication. If the Contractor fails
to comply with the above, the Architect reserves the right to either reject the
whole or part of the works and he shall not be granted any extension of time and
compensation whatsoever to that respect.
All samples shall be labelled, tagged or otherwise clearly identified and each label
shall have sufficient clear space to permit the application of any approval stamp
by the Architect.
Before mass production of the signs, samples of each sign shall be put up on
Sites for actual viewing and inspection of the Architect. The Contractor shall allow
for modification and adjustment of sample and in advance cases rejection of the
sample in his tender price. No mass production is allowed until the sample is
approved. Any relay in approval due to the sample not being to the satisfaction of
the Architect will be responsibility of the Contractor.
20.5.3 Erection
Signage works shall be installed and erected in accordance with the approved
shop drawings. All signs shall be fastened securely in correct vertical and
horizontal alignment.
The Contractor shall use fixing and jointing methods, types and spacings of
fastening which are suitable having regard to : -
a. Nature of and compatibility with product / material being fixed and fixed to;
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS20/4
OCTOBER 2021 ISSUED FOR PERMIT SECTION 20 - SIGNAGE
No short-fired fixing shall be allowed. Power actuated fasteners shall not be used
unless approved by the Architect.
All work shall be installed square, plumb, straight, true to line or radius, accurately
fitted and located, with flush type hairline joints (except as indicated otherwise or
to allow for thermal movement), with provisions for specialist’s contractor, thermal
movement and exclusion of water as required for a secure and rigid installation,
all in accordance with the approved shop drawings.
The Contractor shall protect all metalwork and subsequently remove all protective
applications and clean prior to completion of the works.
The Contractor shall be solely responsible for ensuring total co-ordination of all
work and shall take site measurements prior to preparation of any shop drawings
or before commencing fabrication.
The Contractor shall work out precisely the location of signs to be installed, with
reference to the drawings and Owner’s Signage Guidelines and allow ample time
for verification and confirmation of locations, positions and methods of display
before commencement of installation of signs on Sites.
Unless otherwise agreed to in writing by the Architect, all sign units which are to
be floor, ceiling mounted or wall projected shall be mounted with fixing-screws of
corrosion resistant material, in sufficient numbers as to render the structure firmly
held in place, stable and free from being toppled. In this regard, all exposed or
visible screws and other fasteners shall be steel or heavily chromed brass or
galvanised steel. Ordinary mild steel screws, bolts and nuts and such like
fasteners that are not corrosion resistant shall not be permitted.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS20/5
OCTOBER 2021 ISSUED FOR PERMIT SECTION 20 - SIGNAGE
a. Nails are to be not less than 25mm or 2½ times the thickness of the
member through which nails are being driven, whichever the greater.
b. Screws are to be not less than 12mm or twice the thickness of the member
through which the screws are being driven whichever is the greater.
Unless otherwise directed by the Architect, all joints and edges shall be pointed
with an approved coloured silicone sealant. Sealants shall be applied in
accordance with the manufacturer’s instructions with backer rods where
necessary. All surfaces to receive sealant shall be thoroughly cleaned; excess
material and spillage shall be cleaned and removed.
The joints for each and every material shall be accurately set, cut and neatly
executed and finished with no protrusion, gaps or misalignment. The joints shall
be of stout and sturdy construction to match the purpose for which it is intended.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS20/6
OCTOBER 2021 ISSUED FOR PERMIT SECTION 20 - SIGNAGE
20.6.1 Materials
Silk screen inks shall be of an appropriate quality for the material and finish on
which they are applied. The finish for inks on face-screened surfaces shall be
semi-matt (egg shell).
Where a specified hue is applied for translucent illumination, the ink must match
that hue when lit.
b. Hue-Face Illumination
i. Where a specified hue is applied for face illumination, the ink shall
match that hue for daylight and colour-corrected ambient lighting
conditions.
ii. Ink hue shall not be affected adversely by the presence or lack of ultra-
violet radiation or of other rays in the spectrum.
iii. There inks are screened onto acrylic to an exact match in hue and
finish with other surface coatings, the resistance to weathering of both
coatings must be consistent in order to retain the match of hue and
finish.
iv. Inks, shall withstand detergent cleaning, rain, humidity, heat and other
ambient conditions.
20.6.2 Workmanship
a. Preparation of Surfaces
Ensure that all surfaces to be screened shall be free from imperfections. Remove
dirt, dust and grease and treat acrylic materials with anti-static cleaner.
b. Application
i. Ink application shall be flat, evenly distributed over the printed area and
free from spotting, marks or imperfections.
iii. Light colours shall not be printed over dark colours. In the case of face
screening, the light colour shall be block-printed and dark colour stencil-
screened on top. For reverse screening, the dark colour is stencil-
screened first and the light colour behind.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS20/7
OCTOBER 2021 ISSUED FOR PERMIT SECTION 20 - SIGNAGE
20.6.3 Registration
All printing, in particular multiple colour printing shall be carried out with true
registration.
20.6.4 Maintenance
During the Period of Maintenance, the Contractor shall ensure that all sign
system and all sign boxes are kept in good working condition and that at any time
when called upon shall replace all defective parts.
20.6.5 Acrylic
a. Submittal
i. Shop drawings, where required for relevant sign types shall show sizes,
dimensions, and profiles of acrylic sheet or block work.
ii. Samples displaying the available colour range and quality of the acrylic
sheets shall be submitted to Architect for approval before mass
production.
b. Materials
i. The acrylic supplied shall be free from specks, air bubbles, waves,
scratches, air-holes and other defects.
d. Hardware
Provide and install all incidental hardware necessary for the proper functioning of
the signs which shall be in stainless steel unless otherwise approved by the
Architect.
Upon completion of works and handover, the Contractor shall provide the
following items :
a. Reorder Forms – Provide complete reorder form in Excel format per the
Microsoft Standards; Building and Signage Guidelines for New
Construction, dated June 2013, including prices with types and
description to aid reorders after the date of Practical Completion.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS20/8
OCTOBER 2021 ISSUED FOR PERMIT SECTION 20 - SIGNAGE
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
SS021_Termite Control Treatment
JKT05 SS21/1
OCTOBER 2021 ISSUED FOR PERMIT SECTION 21 – TERMITE CONTROL TREATMENT
SECTION 21
21.1 GENERALLY
The Contractor shall employ specialist pest control operator to carry out the anti-
termite soil treatment. The Contractor to note the requirements as stipulated by the
relevant Authorities for the protection of water catchments and the prevention of water
pollution when chlordane is used in soil treatment against termite.
All materials proposed and supplied must possess environmentally friendly attributes
and comply to the Green label product requirements with relevant certifications.
a Areas to be Treated
ii. The area surrounding all sides of column stumps extending to one
metre below the soil surface or to the top of the pile cap, whichever
is shallower.
iii. Two metres all round the building perimeter prior to concreting of
the apron area;
21.3 CLEARANCE
The pest control operators (PCOs) shall seek clearance from the Ministry of
Environment (ENV) before soil treatment is carried out. The PCOs must certify in
writing that the requirements as stipulated below can be complied with when they
apply to the Department for clearance or whichever requirement as imposed by the
ENV.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS21/2
OCTOBER 2021 ISSUED FOR PERMIT SECTION 21 – TERMITE CONTROL TREATMENT
i. The address or lot number of the site together with a site plan showing area
to be treated.
iii. The estimated amount (litre) of chlordane used and its application rate
(dosage)
Water Table Test shall be carried out at site to determine ground water table. Soil
treatment shall not be carried out if the ground water table is less than 0.5m below
soil level.
b A sampling sump shall be provided at the outlet drain for the monitoring of
chlordane in the run-off.
When it rains during the course of soil treatment, all treated soil shall be covered
immediately with polythene sheet. The coverage shall extend one metre onto the
untreated area The polythene sheets especially their overlapping parts shall be
properly secured by heavy objects to ensure that all rain water runs into the
surrounding temporary drains.
When treating the soil, special care must be taken out to spray the chemical onto
the temporary drains.
When soil treatment is completed, the treated soil shall be immediately covered
securely with the polythene sheet. As soon as practical, a layer of 50mm lean
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS21/3
OCTOBER 2021 ISSUED FOR PERMIT SECTION 21 – TERMITE CONTROL TREATMENT
Soil treatment and concreting shall preferably be carried out on the same day or
on the following day, latest.
Soil treatment shall not be carried out when the soil is saturated or excessively
wet (e.g. during or after a rain) or when it is likely to rain. No soil treatment shall
be carried out after 6.00 PM.
Preparation of the chlordane shall be carried out within a kerb area under a roof
with no outlet to the open drain or a public sewer. All spillage shall be mopped up
with soil and the affected soil shall be added into the treated area.
All equipment used in soil treatment shall be in good order and in serviceable
condition
Uncovered chemicals shall not be left unattended at the worksite. All unwanted
chemicals and containers shall be disposed of at the Ministry's dumping ground.
When the treatment has been completed, the pest control operator responsible for
the treatment shall inform ENV, Head (Sewerage Department) in writing of the
following:
a A statement that treatment has been carried out in accordance with the
requirements as stipulated by the Department
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS21/4
OCTOBER 2021 ISSUED FOR PERMIT SECTION 21 – TERMITE CONTROL TREATMENT
b The address or lot number of the site together with a site plan.
The chemical to be used for the pre-treatment of the soil shall be the following:
a Chemical Dilution
b The prescribed dosage will be 5 litres to 1 sq.metre of soil surface for the
ground level portion of the barrier while the vertical barrier must provide a
continuous cover (5cm deep against the wall to be protected and either
joined up with the horizontal barrier at the upper and lower limits).
If in the opinion of the Contractor, the Specifications are insufficient for him to give
the specified indemnity then the Contractor shall allow in his tender for upgrading
the specifications as necessary to enable him to so indemnify.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
SS022_Ironmongery
JKT05 SS22/1
OCTOBER 2021 ISSUED FOR PERMIT SECTION 22 - IRONMONGERY
SECTION 22
22.0 IRONMONGERY
22.1 GENERALLY
a. Ironmongery shall be approved satin stainless steel finish unless otherwise stated.
c. All locks shall be furnished with temporary cylinder at FOC during the construction
period and to be replaced and fixed with the permanent cylinder by the
manufacturer prior to handing over without additional cost.
d. No individual keys are to be released to any person without prior approval from
the Client.
e. All keys herein above mentioned must be systematically label with door locations
and submitted in sealed envelopes.
f. Contractor shall include approved rubber stopper to all toilet entrance doors and
glass doors. Contactor shall include approved magnetic doorstopper to all doors
except toilet entrance doors, glass doors and water closet cubicles.
h. All Locks, Cylinders and Lever Handles including Exit Device supplied shall be
under the same manufacturer carrying one warranty package from the same
group of companies.
i. The Contractor shall comply with the below listed regulatory requirements and
standards, and also submit valid certificates or approval list for the respective
products:
Carefully check and verify Ironmongery Schedule against all drawings to ensure the
ironmongery listed can function as specified. Inform the Architect of any
recommendations concerning quality, quantity, operation or function of ironmongery
selected, prior to submission of tender.
Ironmongery Schedule is a guide for location and type of ironmongery to be used and
is not necessarily an exact list of quantities or qualities required to complete the entire
project. The contractor shall complete, for review, a separate schedule based upon his
own assessment of the requirements.
Ironmongery on doors that are exposed to weathering shall be of outdoor quality, fully
weather resistant type. Ironmongery on all fire rated doors shall have the appropriate
fire rating to comply fully with the requirements of the Fire Safety Bureau.
Any ironmongery for public communal areas and other specific locations is to comply
with the Code on Barrier Free Accessibility in Buildings or local equivalent authority
requirements.
Ironmongery provision related to security services system: electronic control & alarm
system and emergency exit system (to local Fire Code compliance) i.e. Card access,
electric locks, exit devices, over-riding break glass control panel, panic exit, etc...,
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS22/3
OCTOBER 2021 ISSUED FOR PERMIT SECTION 22 - IRONMONGERY
shall refer to M&E, Security Services drawings incl. that of specifications & schedules
as well as to be read in conjunction with Architectural Specifications Section 22 -
Ironmongery.
Panic exit device/ push bar system & associated accessories shall applicable to all fire
escape doors for emergency exit purposes unless otherwise stated in M&E or Security
Services drawings and specifications i.e. in replacement with/ of electromechanical
lock etc.
• Heavy-duty 2-stage Door Dlosers (both active and passive leaves for
double leaves door) & Standard Arm
• Cable Pass
• Lead cover
• Strike Plate
• Flush Bolt & extension rod (where reachable height <2100mm AFFL)
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS22/4
OCTOBER 2021 ISSUED FOR PERMIT SECTION 22 - IRONMONGERY
• Strike Latch Guard (for external outswing doors with electric strike lock
system)
Delayed egress door system or intuitional lock system shall be provided to all main
entrance doors of each security zoning unless otherwise stated.
The actual quantities shall be based on the tender drawings, the Contractor shall allow
for such in his Tender Sum as no claims for extra on grounds of lack of knowledge will
be entertained by the Employer.
22.2 QUALITY
All ironmongeries shall be of first class quality, heavy duty durable, aesthetically
pleasing and suitable for the specific function for which it is intended. All ironmongery
shall be approved by the Architect who shall be the sole judge as to the brand, quality,
function and suitability.
All ironmongery items shall be complete with screws, bolts, nuts, brackets, striking
plates and the like, necessary for their proper installation. All accessories shall,
preferably, be the products of one manufacturer and with matching surface finish.
Non-ferrous components only to be used.
The Contractor shall submit the Architect with two sets of relevant brochures/
pamphlets in which the specified ironmongery items are clearly marked out for easy
reference. An ironmongery schedule shall be prepared and submitted to the Architect
for approval before ordering of the materials.
The schedule will include for ironmongery for all doors indicated on the drawings. The
ironmongery provisions to each door will be as set out in the ironmongery lists
attached to this section and any relevant authorities’ requirements. The contractor will
point out to the Architect, any doors which have ironmongery requirements not
covered in the lists, and confirm the proposed ironmongery provisions that have been
made for those doors.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS22/5
OCTOBER 2021 ISSUED FOR PERMIT SECTION 22 - IRONMONGERY
22.4 LOCKSET
a. Locksets will normally be mortise type, ANSI A156.13, Grade 1 with above 1.5
million Cyclic test. All locks must be FULLY REVERSIBE without opening the
lock case and must be available with non-handed guardbolt, unless otherwise
stated in drawings.
b. Locks shall have all functions available in one size case manufactured from 0.125”
heavy gauge steel, completely chrome plated for corrosion resistance and lubricity
of parts. Cases are to be closed on all sides to protect internal parts. Locks are to
have adjustable and normal fronts 70mm backset, convertible from one function to
another, a full ¾" throw one piece anti-friction reversible latchbolt and 1"
throw solid stainless steel deadbolt, with two enclosed hardened-steel roller
armor pin. The fastening should be strictly thru-bolt fixing.
c. Locks shall have all functions available in one size case, for heavy duty usage.
They should have the ability to change lock function and handing without removing
the lock from the door.
d. All latch bolt lock cases must have Anti-thrust feature as required depending on
the location used
I. Night Latch
f. All locksets and lever handle trims to be UL Listed and strictly without any
modification for fire door application. The dimension for the thru-bolt fixing position
on the lockbody is 38mm CTC strictly without any modification.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS22/6
OCTOBER 2021 ISSUED FOR PERMIT SECTION 22 - IRONMONGERY
g. Trim Alignment for lockbody to ensure threaded case and trim aligners properly
secure the lockbody on the door centerline. Rigid mounting prevents rocking of the
lockbody when loads apply to the door.
h. Split spindle for lever on both side of door shall operate independently. Spindle
design shall be durable to provide security and integrity of the lockbody by
shearing off under extreme loads while preventing any damage to the lockbody.
i. Cylinder s with the two cone-point cylinder clamp screws are made of hardened
steel and will cut groove in the cylinder if attacked by wrenching.
j. All lock case posts and screws are cold headed into case or cap, and pan head
screws are used to secure the cap to the case. This prevents the spreading of the
lockbody when an excess load to the bolts.
k. All case and cap is heavy gauge of 0.109” steel. The inside front 0.125” steel and
the lockbody’s interlocking construction features provide a rigid assembly. It also
assured proper interaction of all parts while providing a smooth operation during
continuous lockset operation.
l. Hubs are made of 10mm thick copper infiltrated sintered iron for strength and
positive latch retraction. Hub is designed to be stronger than the spindle, yet
weaker than the stop work thus creating a specific failure sequence during attack
on the lock case.
m. Stop work button is guarded with a heat-treated button tail. This tail is the
strongest member in the spindle hub-tail security chain. Tail is always guided in
the case and the cap to ensure proper engagement when projected into the
locking hub.
n. The latchbolt and dead bolt can withstand substantial loads without any permanent
distortion. Then a load is applied to the door, the latch bolt absorbs the load first,
leaving the dead bolt free to move. The guard bolt is not subject to loads or wear,
and automatically retract with the latch bolt.
p. All lockset with deadbolt and latchbolt (dormitory function) shall have an anti-panic
feature.
q. The product warranty is 5 years against manufacturing defects. The warranty must
be issued with the own groups of companies.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS22/7
OCTOBER 2021 ISSUED FOR PERMIT SECTION 22 - IRONMONGERY
22.5 CYLINDER
(a) Cylinders shall comply with Keying Security for Cylinders AS4145.2-1993 K3
and Physical Security for Cylinders AS4145.2-1993 K3K4 or its equivalent.
(b) All cylinders proposed shall meet the degree of security desired for the
installation.
(c) The plug shall be made of solid brass. Cylinder housing shall be made of solid
brass and finish to match the appearance of the lock which the cylinder is
fitted.
(d) All cylinders shall be available in at least 6 pins tumbler system with a series of
different key profiles. Each of the 6 positions consists of a security pin, a
security tumbler and a spring. For added security the cylinder shall possess
multi-part construction of the pin mechanism coupled with the rotation factor
and off centre pin to key alignment features, and in 4 multiple rows for security
reasons.
(e) The cylinders shall have detainer pins to protect against picking.
(f) Cylinders shall be designed for tensile loading of 12800 Newton against
wrenching and pulling of the plug within the cylinder.
(g) The cylinder shall suit regular door thickness of 32 - 50 mm but incremental
increases shall be available for doors of thickness more than 60mm.
(h) The cylinder's bodies and plugs are machined from extruded brass to a
diameter of 17mm or 22mm round profile unique as compared to the
conventional cylinder.
(i) It is finished in nickel silver plating as standard to match most door furniture;
however, other finishes are available upon request.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS22/8
OCTOBER 2021 ISSUED FOR PERMIT SECTION 22 - IRONMONGERY
(j) The standard length of a double cylinder shall suits most doors up to 50mm
thick. Extended length is available upon request for extra thick doors.
(k) Where external security is vital, cylinder can be surface hardened to prevent
drilling. The pins in such cylinders are also hardened.
(l) The range of cylinders must be very wide. A cylinder can be found to suit most
applications from door locks, roller shutter locks, furniture locks, key switches,
or in certain cases special application.
(m) All cylinders are factory sealed making it impossible to tamper with the
permutation inside the cylinder.
(o) All cylinders supplied shall be under grand master key complete with optional
construction key system. The Contractor shall liaise with his sub-contractor
responsible for producing a key chart in master key system for S.O.'s approval
prior to installation.
(q) The inserts of the master keyed cylinders should be interchangeable for
replacement and security purposes.
(r) The inserts of the master keyed cylinders must be suited to other cylinder
types, namely rim cylinder, 17 mm profile cylinder, 22 mm profile cylinder, 36
mm profile cylinder, etc.
(s) The housing of the cylinder shall be recyclable and interchangeable. These as
well as other components could be kept by the user for maintenance purposes.
(t) The listed security patented cylinders and padlock would be:
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS22/9
OCTOBER 2021 ISSUED FOR PERMIT SECTION 22 - IRONMONGERY
(v) Restricted key profile and keying for legal protection against unauthorised
duplication of keys.
a. All cylinders shall be of Pin Tumblers mechanism with seven levels Master Key
levels with Multi-key profile. Plug to be 0.51 diameter pin tumbler type, made of
brass. Cylinder shall be made of solid brass and finishes to match the appearance
of the lock, which the cylinder is fitted.
b. All Cylinders provided must complete with 3 keys incorporate under one Grand
Master Key for all doors. Eg.Glass Doors, Aluminum Doors, Cladded doors and
Gates, etc.
c. Cylinders & Keys provided must carry Patent Rights, with the direct back-up
supports from Manufacturer.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS22/10
OCTOBER 2021 ISSUED FOR PERMIT SECTION 22 - IRONMONGERY
22.6 HANDLE
a. All Cylinder Accessories, Lever Handles, Knobs and Pull Handles shall be from the
same manufacturer and these products must be proven to operate together with
the chosen lockcase.
b. The Lever Handles shall be hollow, by the principle of welding two stamped halves
together, as bended hollow tubes have cracks in the material or in the finish. This
ensures light Lever Handles with long lifetime on the return spring in the Lockcase.
c. The Lever Handles shall have a patented needle bearing system with 18 needles,
which ensure optimum function with the Lockcase.
d. All visible parts shall be made of AISI 316L acid-proof satin stainless steel, which
is bacteria repellent and maintenance free.
e. The required products shall be approved for MPA NRW DIN 18273, with fusing
point of fire handle is 1,450 degree Celsius.
f. Modular and flexible concept, where all types of Lever Handles, Knobs, Roses or
Back plates in the same series can be inter-mixed freely on both the outside and
the inside. All parts have concealed screw fixing with through bolt fixing.
h. Contractor shall submit minimum 5 designs of the handles to Architect for approval.
a. Pins stems in all non-ferrous bearing hinges are SS 316 stainless steel.
b. Base material must be solid stainless steel. Finish shall be in satin stainless steel.
d. All hinges have template screw hole location conform to relevant ANSI/BHMA and
U.S government standard for use on either wood or hollow metal doors and
frames.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS22/11
OCTOBER 2021 ISSUED FOR PERMIT SECTION 22 - IRONMONGERY
22.8 EXPOSED DOOR CLOSER WITH BACK CHECK & DOOR SELECTOR
a. All door closers must be installed at the secure side; parallel arm to be
provided where necessary
c. Must be able to carry up to the maximum door width of 1250mm with the
maximum Weight of 100kg.
e. Build-in thermostat and special hydraulic fluid to ensure constant closing speed
even during varying temperature.
h. Adjustable latching force to ensure that the door is properly closed and
latched.
i. Door closer shall be totally reversible without adjustment and have power
adjustment for relevant EN.
j. Delay action must be available as an option from the same model of Door
Closer.
k. Door closer must comply with all the quality assured manufacture to relevant
ISO, EN, BS. Under the same manufacturer with Lockset specified.
m. Hold open arm available (unless otherwise stated) without back check feature.
n. The listed door selector would be: Stainless steel door selector
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS22/12
OCTOBER 2021 ISSUED FOR PERMIT SECTION 22 - IRONMONGERY
p. All door closers shall be equivalent to Assa Abloy, Dormakaba, Sargent, d-line,
Dorma or contractors proposal to the approval of the Architect.
q. Heavy-duty 2-stage door closers (both active and passive leaves for double
leaves door) shall be applicable to all access-controlled & security-monitored
doors. Location for access-controlled & security-monitored doors shall refer to
MEP and/or Security drawings whichever applicable.
b. Floor Spring must be versatile during installation, be able to adjust 6 horizontal & 6
vertical position even after installation or floor spring housing are being cast onto
concrete floor.
g. Full range of accessories suitable for aluminium, tempered glass, hollow steel or
wood door.
i. Floor check shall seal with hermetical seal to prevent water penetration as well as
oil leakage.
j. Floor spring body is cast-iron block, rugged and able to withstand heavy weight
wear & tear. Tested up to 1 million floor checks.
k. Decrease opening stress after 20 degree opening, user friendly idea for children &
elderly.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS22/13
OCTOBER 2021 ISSUED FOR PERMIT SECTION 22 - IRONMONGERY
Mortise latch/bolt for doors with card reader & wave sensor and/or iris reader
mechanism needs to be automatically retract upon activation and to be provided with
automatic operator with time delay.
All doors with electric mortise to be equipped with transfer hinge for electrical mortise
cable to go through.
22.11 SAMPLES
Before placing any orders with the manufacturer, the Contractor shall furnish the
Architect with an ironmongery sample board that illustrates a properly assembled set
from each different item described in the hardware legend, for approval.
The sample board shall be properly labeled and kept at the Site for reference as well
as for comparison with subsequent deliveries.
Contractor to allow for a grand master keying system. Same grand master keying
system shall be applicable to all phases (for phasing development), unless otherwise
stated.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS22/14
OCTOBER 2021 ISSUED FOR PERMIT SECTION 22 - IRONMONGERY
Wave to open (WTO) complete system must be provided for all toilet doors and other
doors as indicated in A-500 Series drawing. WTO shall be in BEA MS41 or approved
equivalent, complete with red-green-display indicators and swing door operators and
must be compatible for barrier-free toilet and touchless function.
During the construction period, all installed ironmongery shall be protected with plastic
cover properly secured, and removed only after the interiors are finish and ready for
cleaning up. Any damaged or scratched ironmongery shall be replaced.
During construction, the contractor shall only use a construction key to operate and
secure the site, for the locksets installed. No permanent keys are permitted to be used
during the construction. Upon handing over of the building to the employer the
contractor shall arrange to convert the construction locks to the permanent state in the
presence of representatives of the employer, as directed by the Architect.
The contractor shall hand over to the employer, upon completion a minimum of three
sets of keys for each lock set clearly marked with labels. Contractor shall supply a
metal cabinet to house and hang all the keys with identification, to the employer
22.16 SPARES
All ironmongery shall be supplied with spares of 10% for each item and such shall be
delivered to the Employer as directed by the Architect.
22.17 WARRANTY
In addition to, and not precluding, other warranty requirements in the Contract
Documents, the following items are to be covered by extended minimum warranties as
indicated:
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
SS023_Acoustical Design
JKT05 SS23/1
OCTOBER 2021 ISSUED FOR PERMIT SECTION 23 - ACOUSTICAL DESIGN
SECTION 23
23.1 GENERAL
The Contractor shall exercise due care in ensuring design co-ordination and
integration among architectural, M&E services and other performance requirements.
The following are some suggested acoustic criteria for the building. The criteria given
are relevant mainly for noise vibration control.
Noise emitted from the proposed buildings by way of air discharge, cooling towers,
fresh air intake, generator etc, shall be reduced to an appropriate level at the
boundary of the proposed building. The specialist consultant shall evaluate all the
relevant equipment, materials and methods of installation against noise and vibration
control specification.
Where either design values (or measurements) of one or both (noise and vibration)
are exceeded, the Contractor shall at his own cost carry out all necessary works to
rectify the situation to ensure compliance with the criteria.
The permissible indoor noise levels for different accommodation types are as given
in the Table below. These indoor noise criteria refer to resultant noise level in
different spaces measured with the space fully completed and with all equipment
and services fully installed and operating.
For noise or noise sources which exhibit tonal characteristic in a very narrow band of
frequencies, or in pure tone, the Contractor shall exercise specific care to eliminate
such tonal response where practicable. Alternatively, the Contractor may lower the
general noise level of the affected source to a level where the tone is not clearly
perceptible.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS23/2
OCTOBER 2021 ISSUED FOR PERMIT SECTION 23 - ACOUSTICAL DESIGN
Any remedial works required to comply with the required NC level shall be at the
Contractor's own costs.
d. The entire air conditioning and mechanical ventilation system shall be carefully
designed and installed to ensure compliance with the noise criteria spelt out
above. The Contractor shall take all necessary design measures to ensure that
the stipulated criteria are met.
All equipment and noise control appliances shall be compatible with the specified
noise criteria. The Acoustic performance of such equipment and appliances are
to be supported by independent test certificates issued by approved laboratories.
All noisy mechanical plants equipment eg chillers, pumps, fans, etc are to be
supplied and installed with anti-vibration equipment as provided by the
manufacturer. The final transmitted vibration levels shall not exceed the "Design
Criteria" as shown in the Reiher-Meister vibration sensitivity curves. Acoustical
Design And Noise And Vibration Control consideration. Where necessary, the
Contractor shall provide additional controls to ensure that the specified criterion is
met.
Where the resultant noise exhibits tonal characteristics (the sound spectrum
shape exhibits sharp peak(s) of 5 dB or more above the adjacent frequency
bands), control measures shall be implemented to reduce the tonal
characteristic. Otherwise, the prevailing acoustic criterion (NC curve) specified
shall be reduced by 5 dB.
To minimise noise radiation and noise control requirements as far as possible all
noisy plants and equipment shall be supplied and installed complete with
acoustic enclosure or jacket.
Prior to Building completion, the Contractor shall carry out tests to each of the
areas (at his own costs and witnessed by the Architect or his representative. It is
the Contractor's responsibility to ensure that the installations have fulfilled the
stipulated requirements and approval shall be lodged with all calibration
certificates.
Should any installation fail the commissioning test, the Contractor shall be
required to rectify and/or modify the installation to meet the specified criteria. All
further works and additional testing, where necessary, shall be conducted at the
Contractor's own cost. A final test report shall be submitted for final approval by
the Architect.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
SS024_External Works
JKT05 SS24/1
OCTOBER 2021 ISSUED FOR PERMIT SECTION 24 - EXTERNAL WORKS
SECTION 24
24.1 GENERALLY
The contractor shall carry out all the necessary earth filling, cutting and trimming
works to the existing ground to the proposed levels shown as well as forming slopes to
match the surrounding area. Clear site of all rubbish, obstructions, shrubs, undesirable
growth, etc. for proper execution of the entire works and remove all debris off site.
The contractor shall note that the existing ground levels wherever indicated serve as a
guide only, and will check the actual ground levels on site prior to submission of his
tender. No compensation will be paid to the contractor for any work resulting from the
difference in existing levels indicated on the drawings and the actual site condition.
Levels will be made up and mechanically compacted where required with selected
approved fill to the Employers standard technical specification.
The proposed levels of the works shown on drawings may be varied by the Architect
to tie in with the existing surrounding levels. The contractor shall determine the actual
surrounding levels and make provision in his lump sum tender price to allow for these
adjustments to be made, and also any adjustments necessary to maintain effective
falls and drainage.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS24/2
OCTOBER 2021 ISSUED FOR PERMIT SECTION 24 - EXTERNAL WORKS
The contractor following the intent concept indicated on the drawings will prepare the
detail design of the drainage system. The contractor will allow for all temporary works
involved in upgrading and construction of drains including temporary or permanent
diversions of services or road crossings etc.
All work to drains to comply in all respects with the requirements to relevant
authorities. The submission of the proposed drainage system for authority approval
will be prepared by and submitted by the contractors PE.
Contractor to allow for all works connected with the PE’s LTA & SWA OR any local
equivalent authorities submission.
All metal gratings to the external Drains are to be Hot Dipped Galvanised and Heavy
duty. Pavings to be taken up to the back of the grating frame. They shall be able to
withstand the working loads of a Fire engine truck. No Concrete/Cement screed
margins to gratings, I.C.’s etc. will be accepted.
All external walkways, driveways and paved areas are to be laid to falls (min 1in100)
to floor outlets, locations to be agreed with the Architect. Outlets to be fitted with
stainless steel heavy duty cover.
The drains within the site boundary will be suspended beneath the floor slab to
contractors detail. Drains with in the road reserve area will be to contractors PE detail,
forming part of the SWA submission and compliant in all respects with relevant
authorities requirements.
Where proposed drains are to be connected to the existing drains the points of
transition are to be designed by the contractors PE, and constructed to suit site
conditions and to provide and maintain a smooth flow within the drain.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS24/3
OCTOBER 2021 ISSUED FOR PERMIT SECTION 24 - EXTERNAL WORKS
If back filling is required behind retaining walls it is to be carried out in accordance with
method statement approved by contractors PE.
24.8 HARDSCAPING/PAVINGS/FINISHES
All external areas to be paved in accordance with the drawings and finishes schedule.
All aprons within the site boundary to be suspended to contractors detail, and laid to
sufficient falls to prevent the ponding of water.
Kerbs - All kerbs within the site/building boundary to be stone to match adjacent
pavings.
Kerbs to be constructed with expansion joint at max. 18m intervals to extend into
base.
Contractor to allow for the adequate protection of existing trees to be retained within
the road reserve and adjacent to the site. The contractor is to allow for the removal of
existing trees as necessary by appropriately qualified and licensed contractors.
The contractor is to propose for Architects approval a planting scheme for those
planted areas indicated on the drawings, or additional planted areas required by the
authorities. Contractor’s proposal to include;
j) All other requirements for the planting and continued well being of the
completed scheme.
Contractor to allow in his price for applying coloured decorative graphic to the
hoarding. The contractor will take over responsibility for the removal of the existing
hoarding as necessary. Contractor to arrange approvals as necessary with relevant
authorities to establish temporary works access as necessary.
The contractor will liaise with the authorities and take extra care to ensure the safety
and minimise inconvenience to members of the public and neighbours at all times.
24.11 TURFING
Spot turf all external unpaved areas including all necessary trimming, leveling, 50mm
thick approved loamy topsoil treated with weed killer, well mixed with sludge, watering,
rolling, weeding, maintenance, etc. as specified. Spot turf should not be more than
300mm centre to centre. Close turf all embankments, slopes formed and playfield all
as before for spot turf.
Loamy soil to allow for sub soil drainage in order to avoid ponding in case of heavy
rains.
Construct reinforced / precast concrete (Grade 20) surface water channels minimum
300mm width and cascade steps including fabric reinforcement and 65mm diameter
PVC weepholes. The width of the drain to be varied according to the depth in
accordance to Ministry of Environment Code of Practice.
Construct concrete u-drains with 50mm thick lean concrete and 100mm thick
compacted hardcore bed.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS24/5
OCTOBER 2021 ISSUED FOR PERMIT SECTION 24 - EXTERNAL WORKS
Supply and lay 75mm thick precast concrete (Grade 20) removable cover slab with
notch handle hole at ends including setting slabs over channel.
Supply and lay hot-dip galvanised mild steel grating and hinged grating and angle
seating to all open drains including setting grating over channel.
Break into sides of existing drains to connect surface water channel to existing.
Supply and drive bakau piles for concrete covered drains and surface water channels
including bringing piling rig into site, moving rig around site and removing from site on
completion.
Construct stopcock pit including precast concrete (Grade 20) cover slab and
galvanised cast iron hinged cover and frame to pit.
Construct sluice valve pit and chamber including removable aluminium chequered
plate cover to pit and chamber.
Supply and lay cement lined coated ductile iron pipe in trench with spigot and socket
joints with rubber ring and fittings to relevant BS including all necessary excavation
and backfilling.
Supply and fix cast iron double flanged sluice valve to relevant BS complete with
wrought iron tee key and bolted flanged joints to ductile iron pipes at both ends.
Supply and fix cast iron horizontal type check valve to relevant BS with flanged ends,
globe shaped body with flow direction arrow cast on and with hexagonal headed
inspection cap and swing check with limit stop cast on including approved drain out
test cock.
Supply and lay heavy duty galvanised steel pipe epoxy lined and fittings to relevant BS
in trench including all necessary excavation and backfilling.
Supply and fix high pressure screw down underground pattern brass stop cock to
relevant BS with square head complete with loose key and screwed joints to
galvanised steel pipe.
Supply and fix spindle screw down type fire hydrant point with double screw outlet
complete with flange ends and necessary painting.
Test the whole of the external water supply and fire hydrant installation to the
satisfaction of the Architect.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS24/6
OCTOBER 2021 ISSUED FOR PERMIT SECTION 24 - EXTERNAL WORKS
The foul drainage and minor sewer works shall be executed by a licensed plumber
and shall be in full accordance with the requirements of the ENV. If the work is not
satisfactory in any respect, the Contractor shall rectify the defects at his own expense.
The Contractor shall include in his pricing for the length of the minor sewer from last
manhole within the boundary of the school site to the existing public sewer. The
connection to the public sewer shall be executed under the supervision of ENV.
Connect the foul drainage system to the existing manhole by breaking into side for
entry, breaking existing benching and making good all works disturbed.
Supply and lay all drain pipes consisting of vitrified clay pipes to relevant BS and
heavy duty cast iron drain pipes to relevant BS and including all appropriate fittings,
trench excavation and backfilling, concrete bed, surround and haunchings.
Construct backdrop and tumbling bays. Construct concrete sumps and gully sumps
precast concrete cover slabs.
Supply and drive where necessary 150mm x 150mm tanalised timber piles at 4m
centres for all sewer lines, inspection chambers and external drains, including bring
piling rig onto the site, moving rig around site and removing from site on completion.
The sewer lines will be supported by capping beam of size, 400mm width by 400mm
depth (width 4Y16m and links Y10mm at 200mm spacing). Only installation of piles
will be considered as provisional item.
The Contractor shall test the whole of the foul drainage system with water to the
satisfaction of the Architect both before and after covering in and flushing out at
completion of work.
Construct concrete sumps and gulley sumps including hot-dip galvanised mild steel
grating and angle seating and purpose made galvanised wire mesh basket to sump.
Supply and drive where necessary 150mm x 150mm tanalised timber piles including
piling rig, mild steel connector and cutting off piles to receive concrete.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS24/7
OCTOBER 2021 ISSUED FOR PERMIT SECTION 24 - EXTERNAL WORKS
Construct grease trap consisting of precast concrete (Grade 20) chamber rings,
standard aluminium alloy strainer bucket, aluminium alloy removable fan shape plate,
prefabricated glassfibre reinforced plastic cover including all necessary excavation and
backfilling, reinforced concrete base, brickwalls and finishes.
Flag posts shall be proprietary stainless steel complete with belaying cleat, brass
gulley and approved woven nylon halyard and setting flag post in concrete base.
Contractor to allow for the project signboard/s for the duration of the construction
works.
Contractor to allow for a specialist signage contractor to supply and install graphics
and perspective.
Contractor to allow for effective lighting of project sign board. Contractor will carry out
all necessary authority clearances involved including TOL if on State Land.
24.19 ROADWORKS
Contractor to allow for rebuilding road edge, side table as necessary on the Service
Road Frontage. This includes all road works, diversions of services, new drains, sewer
connection, culverts and any other works required further to the contractors P.E.
submissions to the Authorities and compliance with The Street Works Act.
The sub-soil drainage system shall be interlocking cellular drainage modules with non-
woven geotextile filter fabric.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS24/8
OCTOBER 2021 ISSUED FOR PERMIT SECTION 24 - EXTERNAL WORKS
The permeability of the soil must be ensured for areas requiring sub-soil drainage.
This is to ensure that water passes though the soil to the drainage, in order avoid
ponding.
The sub-soil drainage modules (‘draincells’) shall be high strength modules of UV-
stabilised polypropylene with compressive strength of at least 100 tonne/m2 to
accommodate both static and dynamic loads during and after installation. It shall have
good resistance to petroleum-based chemicals and naturally occurring soil chemicals.
The draincells shall have a horizontal surface made up of circular perforations, each
not exceeding 350 mm2, to provide optimum water flow with minimum risk of
obstruction by larger fill aggregates.
The draincells shall be at least 30 mm high and the ratio of opening to solid at the
horizontal surface shall be at least 62% of the total surface area. Each drainage cell
shall be interlocked with adjacent drainage cells along connecting edges to form a
continuous entity whether as panels, conduits or tanks.
The draincells shall comprise of one or more layers to ensure a total flow rate of at
least 16.5 l/m.s for maximum rainfall under Singapore Code of Practice or local
equivalent authority requirements.
PROPERTY VALUE
Material PP or HDPE
Height 30 mm
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
SS025_Carpet Finishes
JKT05 SS25/1
OCTOBER 2021 ISSUED FOR PERMIT SECTION 25 - CARPET FINISHES
SECTION 25
25.1 GENERALLY
25.2 STANDARDS
Unless other wise agreed by Architect, ensure all of the works comply with the
relevant requirements of the Standards and Codes listed below or referenced in the
body of the Specification. Alternative Standards and Codes may be submitted to the
Architect, provided it can be demonstrated that the alternative Standards and Codes
comply with the requirements of the standards specified. All standards and Codes
quoted are the current version, unless specific year references are noted.
Other Standards
A. Qualifications :
3. Submit a list of at least five (5) installations that have been in use for a
minimum of three (3) years using carpet tile similar to what is specified
in this document. Provide contact name and numbers.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS25/2
OCTOBER 2021 ISSUED FOR PERMIT SECTION 25 - CARPET FINISHES
6. All products must comply with Carpet & Rug Institute “Green Label
Plus” or equivalent local Standards.
8. The average quantity of green house gas emissions associated with the
life cycle of the product, a description of the green house offsets used
to make the product green house gas neutral, and the name of the 3rd
party organization certifying such offsets must be submitted for
verification.
10. Finished product must have recycled content and is able to contribute
to the attainment of design standards of the Green Mark (DC) Platinum,
to Consultants’ selection & approval.
C. Tests : Carpet furnished under this section shall comply with the following test
requirements :
a. VOCs not to exceed 0.5 milligrams per square metre per hour.
b. Styrene not to exceed 0.4 milligrams per square metre per hour.
c. Formaldehyde not to exceed 0.5 milligrams per square metre
per hour.
3. ASTM E 648, Critical Radiant Panel Flux : Class I, greater than 0.45
watts per square centimetre.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS25/3
OCTOBER 2021 ISSUED FOR PERMIT SECTION 25 - CARPET FINISHES
5. ASTM 662 (NFPA 258) : Smoke density less 450 optical density.
B. Carpet tiles shall be stored between 40o F and 100o F and shall be conditioned
between 60o F and 90o F for 48 hours prior to installation.
B. Floor pH shall not exceed 10.0 (acid etch using a 50/50 vinegar and water or a
1/20 muriatic acid and water solution if greater than 10.0).
C. Water vapour transmission of sub-floor shall not exceed 3 lbs. per 1000 sq.
feet per 24-hour period as determined by the # 625 Calcium Chloride Test.
25.6 WARRANTY:
Provide 5%, but not less than one box/bundle of each colour and pattern.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS25/4
OCTOBER 2021 ISSUED FOR PERMIT SECTION 25 - CARPET FINISHES
25.8 MATERIALS:
Tufted textured loop pile, CRI Indoor Air Quality Testing Program certified, with non-
woven primary backing and PVC-Free secondary backing. Wet dye injection pattern
application to match approved design, conforming to the following criteria.
1. Yarn System: Type 6.6 nylon with up to 100% post industrial recycled nylon
3. Construction: Tufted
13. Mergeability: Carpet that is of the same style/color, but from different dyelots
and/or manufacturing dates, may be merged and used interchangeably, both at
initial installation and at later selective replacement, to create a continuous
carpeted surface with no tile appearing out of place
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS25/5
OCTOBER 2021 ISSUED FOR PERMIT SECTION 25 - CARPET FINISHES
14. Backing: Free Lay Modular Fiberglass Reinforced Thermoplastic Composite with
minimum 40% of recycled material content and must be 100% recyclable at the
end of its useful life.
17. Installation method: Tactile ( 100% glue free ) or equivalent – full spread adhesive
installation not allowed.
25.11 ACCESSORIES:
A. Adhesive: Non Releasable water based adhesive (CRI Green Label Certified or
equivalent local Standards)
Submit samples that meet or exceed the attached specifications. Installer must
provide samples suitable for specific application and quantify each area.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS25/6
OCTOBER 2021 ISSUED FOR PERMIT SECTION 25 - CARPET FINISHES
A. The sub-floor shall be structurally sound, clean, dust free, smooth and level.
B. Holes and Protrusions : Any holes greater than 1/8" (3 mm) in diameter must
be patched regardless of floor surface. All protrusions in excess of 1/32"
(0.8 mm) must be smoothed.
25.14 INSTALLATION:
C. Adhesive application: Carpet tiles must be installed with a full spread water
based adhesive in case of cushioned carpet tiles. Apply adhesive using a
paint roller with a 0.75 - 1.0 inch nap.
Allow releasable adhesive to fully dry so it does not transfer to the module
backing.
25.15 CLEANING:
A. Remove excess adhesive from the floor, base and wall surfaces without any
damage.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS25/7
OCTOBER 2021 ISSUED FOR PERMIT SECTION 25 - CARPET FINISHES
25.16 PROTECTION:
25.17 WARRANTY
Provide 5%, but not less than one box/bundle of each colour and pattern.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
SS026_Acoustic Wall Lining System
JKT05 SS26/1
OCTOBER 2021 ISSUED FOR PERMIT SECTION 26 - ACOUSTIC WALL LINING SYSTEM
SECTION 26
26.1 GENERALLY
The fabric acoustic wall lining system shall be installed in strict accordance with
the manufacturer's instruction.
The fabric acoustic wall lining system is a versatile fabric wall covering system
that combines high performance acoustic control with a crisp, even fabric finish,
suitable for all internal walls and ceilings.
26.2 DESCRIPTION
The fabric acoustic wall lining system consists of perimeter UPVC frame, acoustic
linings and fabric.
The acoustic linings are normally of 50 mm standard thickness high density glass
fibre panels of density between 50 kg/m3 to 60 kg/m3 to provide good acoustic
performances and the required strength to withstand direct impact especially in
heavy traffic areas.
Fabrics, normally woven and acoustically transparent, must be the type approved
for use in acoustic panel/wall installations.
The following are some suggested acoustic criteria for the building. The criteria
given are relevant mainly for noise vibration control.
Noise emitted from the proposed buildings by way of air discharge, cooling towers,
fresh air intake, generator etc, shall be reduced to an appropriate level at the
boundary of the proposed building. The specialist consultant shall evaluate all the
relevant equipment, materials and methods of installation against noise and
vibration control specification.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS26/2
OCTOBER 2021 ISSUED FOR PERMIT SECTION 26 - ACOUSTIC WALL LINING SYSTEM
Where either design values (or measurements) of one or both (noise and vibration)
are exceeded, the Contractor shall at his own cost carry out all necessary works to
rectify the situation to ensure compliance with the criteria.
The permissible indoor noise levels for different accommodation types are as given
in the Table below. These indoor noise criteria refer to resultant noise level in
different spaces measured with the space fully completed and with all equipment
and services fully installed and operating.
Required Range
Area
(NC)
For noise or noise sources which exhibit tonal characteristic in a very narrow band
of frequencies, or in pure tone, the Contractor shall exercise specific care to
eliminate such tonal response where practicable. Alternatively, the Contractor may
lower the general noise level of the affected source to a level where the tone is not
clearly perceptible.
The entire air conditioning and mechanical ventilation system shall be carefully
designed and installed to ensure compliance with the noise criteria spelt out above.
The Contractor shall take all necessary design measures to ensure that the
stipulated criteria are met.
All equipment and noise control appliances shall be compatible with the specified
noise criteria. The Acoustic performance of such equipment and appliances are to
be supported by independent test certificates issued by approved laboratories.
All noisy mechanical plants equipment e.g. chillers, pumps, fans, etc are to be
supplied and installed with anti-vibration equipment as provided by the
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS26/3
OCTOBER 2021 ISSUED FOR PERMIT SECTION 26 - ACOUSTIC WALL LINING SYSTEM
manufacturer. The final transmitted vibration levels shall not exceed the "Design
Criteria" as shown in the Reiher-Meister vibration sensitivity curves. Acoustical
Design and Noise and Vibration Control consideration. Where necessary, the
Contractor shall provide additional controls to ensure that the specified criterions
are met.
Where the resultant noise exhibits tonal characteristics (the sound spectrum shape
exhibits sharp peak(s) of 5 dB or more above the adjacent frequency bands),
control measures shall be implemented to reduce the tonal characteristic.
Otherwise, the prevailing acoustic criterion (NC curve) specified shall be reduced by
5 dB.
To minimize noise radiation and noise control requirements as far as possible all
noisy plants and equipment shall be supplied and installed complete with acoustic
enclosure or jacket.
Prior to Building completion, the Contractor shall carry out tests to each of the areas
(at his own costs and witnessed by the Architect or his representative. It is the
Contractor's responsibility to ensure that the installations have fulfilled the stipulated
requirements and approval shall be lodged with all calibration certificates.
Should any installation fail the commissioning test, the Contractor shall be required
to rectify and/or modify the installation to meet the specified criteria. All further
works and additional testing, where necessary, shall be conducted at the
Contractor's own cost. A final test report shall be submitted for final approval by the
Architect.
26.5 PERFORMANCE
a) Fire
The fabric and the acoustic linings can be supplied to meet Class 1 or Class
0 fire requirements of the Building Regulations or equivalent local authority
requirements.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS26/4
OCTOBER 2021 ISSUED FOR PERMIT SECTION 26 - ACOUSTIC WALL LINING SYSTEM
b)
Sound
Sound absorption coefficients for typical 50 mm linings are shown in the
table below.
________________________________________________________________________
Frequency (Hz)
Application 125 250 500 1000 2000 4000 NRC
________________________________________________________________________
Without air gap 0.17 0.75 0.98 0.93 0.94 0.96 0.90
With air gap 0.46 0.73 0.87 0.93 0.96 0.97 0.90
________________________________________________________________________
Where specialised acoustic control is required, the acoustics specialist can advise
on the extent of treatment to achieve a particular performance.
26.6 INSTALLATION
The acoustics lining is cut to the size of the panel and fix in place with the
perimeter frame. If the panels are too large, the linings can be held in place by
means of glue or hold-down pins.
The fabric is mounted by use of a special application tool that inserts the fabric
into the jaws of the track. Once fitted, the fabric completely covers the area and
no braiding or cover strips are required. The fabric should not be installed until:
c) painting is completed and wall base and floor covering are installed;
d) all adjacent and related work of other trades has been completed;
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
SS027-Sealant
JKT05 SS27/1
OCTOBER 2021 ISSUED FOR PERMIT SECTION 27 - SEALANT
SECTION 27
27.0 GENERAL
All Work in this Section shall comply with the requirement of the Contract
Documents for the Main Building works, with the Drawings, Schedules and with
all other Contract Documents.
(a) Sealant work for control joints, expansion joints, and other joints at the
following:
i. Concrete work
x. Between grilles
(b) Provide fire rated sealant assemblies at all through openings in fire
rated masonry, concrete partitions or partitions.
Sealants must comply with the latest version of the following British Standards:
Part 2 Methods of test for seepage, staining, shrinkage, shelf life and
paintability
Part 1 Code of practice for internal ceramic wall tiling and mosaics in
normal conditions
Part 2 Code of practice for external ceramic wall tiling and mosaics
(b) Submittals
(ii) Samples
Submit :
i. Samples of each type of sealants for custom colour appraisal (where
exposed) and compliance with Specifications
ii. Complete sealant assembly for fire rated sealants
(v) Sample
See respective Trade Sections for Sample requirements. Provide all sealing
as necessary to complete same.
(i) Temperature
(ii) Moisture
Do not apply work of this Section on surfaces which are wet or damp.
27.5 PRODUCTS
i. Expandite Ltd, UK
iv. Bostik
(ii) Sealants
Shall be approved equal to those types and products specified herein. Other
manufacturers, providing similar materials will be given equal consideration.
All sealants shall be custom coloured, unless otherwise approved. Silicone-
based sealant shall not be used where sealant is in contact with mirror or
porous stone.
1. Polyurethane Sealant
Vulkem 116
Bostik 2637
Tremco Dymeric
Vulkem 255
Bostik 2655P
Tremco Tremsil
Vulkem 227
4. UV resistance sealant
Vulkem 116
Bostik 2638
1. Grade
4. Color’s
of the sizes and shapes to suit the various conditions, and shall be 30% wider
than the joint width. Joint backing shall be compatible with sealant and
primers. Backing at paving joints and the traffic bearing joints shall be sponge
rubber, conforming to ASTM D-1752, Type I, Sponge Rubber; “Cementone
Sponge Rubber No. 3329” by Serviced Products, Division of Grace
Construction Materials or approved equal.
As specified herein.
27.6 EXECUTION
(i) Supervision
The Contractor shall submit to the Architect written certification from the
sealant manufacturer that the applicators are approved by the manufacturer
and have been instructed in the proper application of their materials. The
Contractor shall use only skilled and experienced workmen for installation of
sealant.
(ii) Preparation
Joint surfaces to receive sealant shall be sound, smooth, clean, dry and free
of all contaminants. Factory or site applied coatings shall be removed with a
COPYRIGHT BY M/S AWPPTE LTD.
THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR WHOLLY WITHOUT THE WRITTEN
PERMISSION OF M/S AWP PTE LTD.
JKT05 SS27/8
OCTOBER 2021 ISSUED FOR PERMIT SECTION 27 - SEALANT
i. General
ii. Primer
Thoroughly clean joints and apply primer to surfaces that will receive sealant.
Apply primer on clean, dry surfaces, and prior to installation of joint backing.
Completely wet both inner faces of the joint with primer. Mask adjacent
surfaces of joint with non-staining masking tape prior to priming. Allow primer
to dry prior to application of joint backing, bond breaker or sealant. All joints
must be primed prior to application of sealant in accordance with
manufacturer’s instructions.
In joints where depth of joint exceeds required depth of sealant, install joint
backing (after primer is dry) in joints to provide backing and proper joint
shape for sealant. Proper shape for sealant is a very slight “hourglass” shape,
with back and front face having slight concave curvature. Use special blunt T-
shaped tool or roller to install joint backing to the proper and uniform depth
required for the sealant. Joint backing shall be installed with approximately
30% compression. Do not stretch, twist, braid, puncture or tear joint backing.
Butt Joint backing at intersections, to be cemented.
Install bond breaker smoothly over joint backing that would bond to sealant
and at back of joints where joint backing is not required, so that sealant
adheres only to the sides of the joint and not to backing.
v. Sealant Application
tape. Force sealant into joint in front of the tip of the “caulking gun” (not pulled
after it) and force sealant against sides to make uniform, contact with sides of
joint and to prevent entrapped air or pulling of sealant off of sides. Fill sealant
space solid with sealant.
vi. Tooling
Tool exposed joints to form smooth and uniform bends, with slightly concave
surface. Finished joints shall be straight, uniform, smooth, and neatly finished.
Sealant to finish flush with adjacent surfaces, except where otherwise
indicated on Drawings. Remove masking tape immediately after tooling of
sealant and before sealant face starts to “skin” over. Neatly remove any
excess sealant from adjacent surfaces of joint, leaving the work in a neat,
clean condition.
SECTION 28
28.0 DOORS
28.1. GENERAL
Read with the General Requirements section, and all other contract documents.
28.1.1 Scope
This section covers the requirements for external doors including fire doors and their
associated ironmongery.
Read this work section in conjunction with the relevant requirements of the other work
sections including the following:
- External Render
- Wall Tiling
- Painting
28.1.3 Standards
Unless otherwise agreed by the Architect, ensure all of the Works comply with the relevant
requirements of the Standards and Codes listed below or referenced in the body of the
Specification. Alternative Standards and Codes may be submitted to the Architect, provided
it can be demonstrated that the alternative Standards and Codes comply with the
requirements of the standards specified. All Standards and Codes quoted are the current
version, unless specific year references are noted.
SS 1 Plywood
SS 71 Nomenclature of commercial timbers
SS 72 Treatment of timber and plywood with copper/chrome/arsenic wood preservative
SS 91 Solvent-based paint remover
SS 173 Glossary of terms relating to timber and woodwork
SS 332 Fire doors
SS 341 Safety glazing materials for use in buildings (human impact considerations)
SS 347 Timber doors
Code of Barrier Free Accessibility in Buildings
Other Standards
The intended type of external doors and their associated ironmongery are set out in relevant
clauses and locations are indicated in the drawings and / or door schedules.
Engage qualified and experienced personnel to carry out and submit the following items to
the Architect.
28.1.4.1.1 Develop all necessary details for the doors based on the design drawings.
28.1.4.1.2 Submit names of manufacturer’s for door leaves, door sets (if specified) and
ironmongery.
Prepare and submit shop drawings to enable the fabrication and installation of the doors.
Co-ordinate the external door works, particularly the interfaces with the following work
packages and trades:
a. External walls including masonry, in-situ concrete and glazing.
b. External finishes
Liaise and coordinate with M & E engineer for location of all doors linked to security or fire
systems.
Deliver to site in strong protective packages marked for identification, and store where
directed, components and materials for future replacement and repair.
Supply the following spare materials and stored in an area agreed with the Architect
28.2 GENERAL
Doors shall be of 40mm thick skeleton framed plywood faced flush with 38 x 12mm
timber lipping all around or as shown in the drawings.
Where doors are in two leaves, they shall have 38 x 25mm timber rebated meeting
stiles.
The door frames shall be in solid moulded timber sections to suit the profile of
partition of folded m.s. sections as shown in the drawings.
All timber doors are to be finished with laminated plastic finish unless otherwise
indicated.
Where required, provide observation panels on the doors glazed with 6mm clear
float glass with timber glazing beads on both sides and bed edge of glass in
neoprene as detailed in the drawings.
For framed glazed doors, install 9mm toughened glass with one side colour
chemically coated to manufacturer’s specification and architect’s selection.
The Contractor is to provide opening in the framing for housing of electrical wiring
for contract alarms and door opening electrical controls.
Materials and construction of fire doors shall comply with the Fire Safety Bureau’s
(FSB) requirements and be delivered to site tested, permanently labelled and
approved by the PSB or equivalent authority requirements/ Regulations. All solid
core fire doors shall be guaranteed to be to the approval of the Authorities.
Where fire doors are indicated in the Contract Documents, all door frames and
ironmongery thereto shall also conform to the requirements in this respect.
Vision Panels to be provided in fire doors as required in the FSB Code of Practice
for Fire Precautions in Buildings 1997 (or latest edition) or equivalent authority
requirements/ Regulations.
Door frames to be solid timber to match door leaf finish. Door frames to wet areas
to have 100mm high heel stone profiled to match door frame.
The widths, heights and thickness of doors and panels specified are the finished
sizes. Likewise, the thickness specified for the component members of flush doors
and panels are the finished thickness required.
All doors and panels shall be provided with accessories such as mohair/brush
seals, weather-sealing strips, dampeners, felts, etc. where deemed necessary.
Hollow core doors shall be 50mm thick constructed of Kapor cores with 6mm
plywood facing to both sides. The core shall consist of 76 x 38mm top rail and
stiles, 150 x 38mm middle and bottom rails, 75 x 38mm intermediate rails and with
10 x 50mm Kapor lipping tongued on to all four edges. Rebated lippings to stiles
shall be 20 x 50mm.
Glazing openings shall be trimmed with 75 x 38mm core framing and fitted with 20
x 12mm Kapor glazing beads loosely pinned in all round on both sides.
Hollow core panels shall be 50mm thick constructed of Kapor cores with 6mm
plywood facing to both sides. The core shall consist of 100 x 6mm plywood facing
to both sides.
Solid core doors shall be 50mm thick constructed of Kapor cores with 6mm
plywood facing to both sides. The core shall consist of 75 x 38mm top rail and
stiles, 150 x 38mm bottom rail and in-filled with 76 x 38mm vertical battens glued
and well cramped together and with three 10mm diameter mild steel bars passing
horizontally through the width of the door with nuts and washers at each end sunk
into stiles and with 10 x 50mm Kapor lipping tongued on to all four edges. Rebated
lippings to stiles shall be 20 x 50mm.
Glazing openings shall be fitted with 20 x 12mm Kapor glazing beads loosely
pinned in all round on both sides.
Solid core panels shall be 50mm thick constructed of Kapor cores with 6mm
plywood facing to both sides. The Core shall consist of 100 x 38mm muntin and
framing, in-filled with 75 x 38mm vertical battens glued and well clamped together
and with one 10mm diameter mild steel bar passing horizontally through the width
of the panel with nuts and washers at each end sunk into the framing and with 10 x
50mm Kapor lipping tongued on to all four edges.
Glazed panelled doors shall be PSB/FSB approved & 50mm thick constructed of
Kapor 100 x 50mm top rails and stiles, 150 x 50mm bottom rails and in-filled with
6mm thick clear tempered glass. Glazing shall be fitted with 20 x 12mm Kapor
glazing beads loosely pinned in all round on both sides.
Glazed paneled doors must also be equipped with mohair brush around the door
leaf or door frame for draught and sound proofing.
Materials and construction of rated doors shall comply with the Building Authority’s
requirement and be delivered to the site labelled and approved by PSB or
equivalent authority requirements/ Regulations.
Architraves, Frames, Lippings Beadings etc. to doors will match the facing to the
door as indicated on the drawings.
For framed glazed doors, install 9mm thick toughened glass with one side colour
chemically coated to manufacturer’s specifications and architect’s selection.
Framed glazed door must also be equipped with mohair brush around the door leaf
or door frame for draught and sound proofing.
The Contractor is to provide opening in the framing for housing of electrical wiring
for contract alarms and door opening electrical controls.
Materials and construction of fire doors shall comply with the Fire Safety Bureau.
All framed glazed doors shall be equipped with alumunium metal plate (to match
the finish of the door/door frame unless mentioned otherwise) on the internal &
external sides to mount card reader and other controllers/services as indicated in
drawings or where deemed necessary (to be read in conjunction with Security &
MEP drawings).
The door frame shall allow for cable pass routing within the frames to conceal all
cables.
All mesh doors and BRC doors are to be equipped with alumunium metal plate on
the internal & external sides to mount card reader and other controllers/services as
indicated in drawings or where deemed necessary; necessary (to be read in
conjunction with Security & MEP drawings).
The door frame shall allow for cable pass routing within the frames to conceal all
cables.
The auto sliding glass door shall be DORMA INDUSTRIES EL300/EZYFIT SERIES,
BWN or BESAM Approved Equivalent auto sliding door operator or approved
equivalent.
28.4.1 Specification
Constant rated 7kg torque capacitor start and run squirrel cage motor. No thermal
overload is permitted. The motor to have operational rating of 60 minutes in the
hour, 24 hours per day. It is a self-lubricating planetary gearbox with spiral bevel
drive. No intermediate belts, pulleys or couplings which are subject to failure,
breakage, slippage, shearing or loss of tension.
Chain drive with average tensile strength of 1950kg and a 12.7 minimum pitch. Belts
or chains of lesser strength and average tensile strength shall not be considered.
The track is to be hard coated anodised aluminium track fully replaceable carrying
hanger bars supported by fully fibre-glass reinforced nylon track wheels (min. 50mm
diameter) for smoother wear and increased life. No external lubricant required.
COPYRIGHT BY M/S AWPPTE LTD.
THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR WHOLLY WITHOUT THE WRITTEN
PERMISSION OF M/S AWP PTE LTD.
JKT05 28/8
OCTOBER 2021 ISSUED FOR PERMIT SECTION 28- DOORS
Dual sets of jamb fitting sun resistant light cells flush mounted in door jamb that will
prevent the door from closing if threshold area is obstructed. Located at
approximately 150 mm and 600 mm from finished floor level. In the event that there
is no door jamb, Activ.8 sensor shall be used as a normal and safety sensor to
prevent doors from closing when there’s obstruction in the middle of the doors.
28.4.2 Actuation
The Operator is to be actuated by two (2) BWN sensor or Activ.8 sensors or kick
button.
As per regulations, doors drive fully open automatically on power failure/fire alarm.
Failsafe consists of a 12VDC/110VAC invertor also incorporating battery
alarm/monitor to alert, if power is low. Doors automatically return to original function
mode when power is returned or fire signal is deactivated.
The sliding door system shall include safety sensors located at overhead or side of
entry opening for restraining door closure when the opening is obstructed. Safety
system performance specifications shall be submitted to Architects for comments
before installation.
28.4.4 Warranty
Motor to have an electric lock fitted between the motor and the gearbox. Breaking
strength of electric lock shall be 2000kg. Solenoid locks will not be considered.
Electric lock to incorporate battery reserve, rechargeable circuits and all associated
wiring, battery and charger monitor.
Opening width for single leaf shall be from 700mm to 3000mm and 700mm to
4000mm for double leaf. Maximum loading capacity for single leaf shall be 150kg
and double leaf at 250kg. Adjustable maximum opening and closing speed at
700mm/sc. Dwell time 0-12secs. Glass to be used shall be 12-15mm thick tempered.
28.5.1 Specification
b) The drive unit must be small and compact with dimensions not exceeding
530(W) x 100(H) x 104(D), appropriate for all the installation positions
according to DIN 3-5 standard.
c) The drive unit must be able to be installed on both sides of the hinges or on
the opposite side and able to be connected with the appropriate rod (normal
rotating arm, parallel, or sliding), guarantees a trouble free opening and
closing of the door.
g) The opening angle must not be less than 60° and not greater than 95°.
h) The drive unit must be able to drive a max. weight of 350 kg panel with a
max. door width not greater than 700 mm and min. weight of 85 kg panel with
a max. door width not greater than 1400 mm.
i) The basic drive unit must have a min. integrated functions to allow the drive
unit to function in the following mode:-
• Automatic
• Manual
• Open
j) The drive unit must also come with an option of remote control switch to allow
a wide choice of on-line options for the selection of programs, adjustment of
functions and self-diagnostic display (see Table A):-
• To set the opening width of the automatic as well as the opening and
closing speeds, and holding time.
k) The drive unit must be capable of providing at least 4 potential free signal for
subsequent data processing or building management functions such as:-
• Error message
• Audio signal
l) The unit must have a provision for optional features to handle fire protection
and smoke control application especially for units that are linked to a building
management system.
Normal Mode
Note : All above functions can be changed when the drive unit is in operation.
i) The manual sliding door gear shall be “Dorma Agile 150 Sliding Gear”, Hafele,
Dormakaba or approved equivalent. It shall be designed and engineered from
quality materials to provide a robust sliding system that meets the highest
standards of reliability and durability. The complete system comes with a full 2
years warranty against manufacturing defects.
ii) The system shall be frameless in design with modular track section with 63mm
height. System shall have two clamps and each clamp shall have only two
rollers on one side. Completely top hung system without bottom track.
iii) The gear must be suitable for normal solid timber door as shown in the drawings
and able to carry door panel weight up to 150kg.
v) Clip-on cover is to be provided to cover the exposed side. End stop and holder
in the track shall operate as a cushioned end stop for retaining the door securely
in the end positions.
System shall be tested to EN 1527 standard with 100,000 motion cycles. It shall be
built to last salt spray tests as per EN 1670 standard.
Turnstile
Full height turnstile constructed from tubular stainless steel, 2270mm high and
1300mm diameter, (Kentaur FTS-E04 by Dormakaba Singapore Pte Ltd or approved
equivalent). Manual motion, both directions of travel electronically controlled via link
to security office, with card reader access and intercom link to security office. Free
rotation in event of power failure.
Full height gate (suitable for barrier free access) constructed from tubular stainless
steel, 2270mm high and 1370mm wide (portal width), (Kentaur FGE-M01 by
Dormakaba Singapore Pte Ltd or equal and approved). Power assisted motion, both
directions of travel electronically controlled via link to security office at north gate,
with card reader access and intercom link to security office. Free opening in event of
power failure.
28.8 FITTINGS
All fittings shall be in accordance with the relevant requirements of the British
Standards Institution, with regards to general construction, quality and
workmanship for fittings.
28.12 RATES
The description of and rate for each item of ‘Carpenter’ will be held to include for all
cutting, knotting, boring, sinking, pelleting, fitting, trimming, mitering, halving,
morticing, tenoning, dovetailing, scarfing and wedging, and all ends, splayed
edges, short lengths and temporary supports, rebating for plaster, and other sundry
items of a like nature, nails, spikes, pins and brads required.
The description of and rate of each item of ‘Joiner’ will be held to include for all
cutting, notching, holes, housing ends, mitering ends and shaped ends, angles,
junctions, heading joints, short lengths and any sundry items of a like nature, labour
to stops or cross grains, nails, spikes, pins and brads and for all testing.
The description of each item of ‘Joiner’ will be held to include for screws, gluing and
any other fixing.
SECTION 29
29.1.1 The terms "general repairs" ‘to be made good’ or ‘make good’ shall mean to
include the following items including removing debris and unwanted materials off
site, taking down to facilitate repairs/replacement works where required,
subsequent re-fixing and making good works disturbed (whether specifically
mentioned or not), etc.
29.1.2 Taking out silt, loose muddy soil or other materials from existing gullies, traps,
running storm water channels, drains, grease traps or sump pits, where necessary
or as directed by Architect.
29.1.3 Cutting out cracks in paved floors, aprons, channels, junctions between channels
and aprons, curbs, etc. (irrespective whether cast in-situ or precast) to a width of
at least 15mm, form undercut edges, diamond cutting where required, making
good to match existing and removing debris off site.
29.1.4 Hacking off defective/damaged cement paving including diamond cutting where
required, patching up with materials to match, and making good to floors, aprons,
channels, curbs, dapor slabs, concrete worktops/tables, etc., and where necessary
re-rendering and regarding surfaces to required falls and gradients (irrespective of
cast in-situ or precast).
29.1.5 Taking up, regarding and re-cementing in-situ or precast concrete inverts and side
slabs of surface and scupper drains.
29.1.6 Renewing existing sealant in expansion joints in aprons, floors, roofs, etc.
(excluding expansion joints in panel roofs and main structures).
29.1.7 Clearing all chokes and debris in weep pipes, water sprouts, rain water downpipes,
gutters, etc. and replacing defective/damaged/missing weep pipes, water sprouts,
rain water downpipes, gutters, rainwater heads, balloon gratings to rain water
outlets, etc. to match existing. Existing galvanised iron rainwater goods shall be
replaced with UPVC type.
29.1.8 Making good all damaged concrete vents and replaces missing/defective vents to
match existing.
29.1.9 Making good damaged and replaces missing/defective brick, quarry tile or other
material copings, cills, steps, arches, kerbs, etc.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS29/2
OCTOBER 2021 ISSUED FOR PERMIT SECTION 29 – GENERAL REPAIRS
29.1.10 Replacing all broken or missing precast concrete slabs within the complex, such
as to footpaths, aprons, over drains, etc. with new slabs reinforced with suitable
reinforcement, including levelling of sunken areas, to match the existing.
29.1.11 Make good/reconstruct sunken concrete floors, aprons, steps, footpaths, ramps,
surface water drains and the, like including suitable reinforcement, and levelling
sunken areas, to match existing.
29.1.12 Investigating and curing all roof leaks in roof coverings (any type) including
providing new to match existing tiling, or the like; replacing metal hook bolts, drive
screws or tying wires or the like; sealing existing nail, screw or bolt heads, flashing
and roof ridge joints, side and end laps with approved liquid-applied membrane of
heavy duty acrylic polymer reinforced with fibreglass as instructed; replacing
damaged/defective/missing tiles, roof sheeting’s and accessories, fittings such as
capping, fascia, roof insulation, etc. (but not amounting to total replacement).
29.1.13 Provide all necessary protection to existing lightning conductors, fittings, etc. and
clean all existing profile/corrugated metal and/or cement roofs and the like with
water jet to remove dust, dirt, grease, contaminants, etc.
29.1.14 Cutting out and replacing damaged/defective and missing styles, rails, ledges,
braces and the like to timber doors, windows, and fitment doors etc. (any type and
thickness) with new to match existing.
29.1.15 Cutting out and replacing damaged/defective and missing boarding or panelling in
doors, windows, fitment doors etc. (any type and thickness) with new to match
existing including taking down doors/windows and rehang.
29.1.16 Cutting out and replacing damaged/defective frames to doors, windows, vents,
fanlights, partitions, fitments, etc. with new to match existing including taking down
doors, windows, infill panels, etc. and refix.
29.1.17 Fixing back all loose and replacing damaged/defective and missing lengths of
beads, lippings, picture rails, skirting, and architrave’s, etc. with new to match
existing including making good all round.
29.1.18 Taking out where necessary loose boarding, treads, risers, nosing, strings,
balusters, handrails, newels, ramps, wreaths or staircases, framing and the like
(any design and size) and refix and re-cramp including providing new wedges,
nails, screws, etc. including replacing any damaged/defective and missing portion
with new to match existing.
29.1.19 Replacing all damaged/defective and missing handrails (any type and size) to
steps, ramp areas, corridors, etc. to match existing.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS29/3
OCTOBER 2021 ISSUED FOR PERMIT SECTION 29 – GENERAL REPAIRS
29.1.20 Taking out where necessary loose fibreboard’s, cement boards, hardboards,
plywood, signboards and the like including all fillets (any type and size) and refix
including providing new nails, screws or other fixtures. Damaged/defective and
missing fillets shall be replaced to match existing.
29.1.21 Taking out all damaged, badly stained and missing ceiling boards, notice boards,
partition/fitment/door linings, laminated plastic/decorative vinyl or veneer, wall
paper, etc.
29.1.22 Cutting spall or loose concrete and make good defective areas with approved non-
shrink cementitious mortar. Unless otherwise approved by the Architect, areas of
spall concrete with exposing reinforcement shall be made good with approved
epoxy mortar. All repairs including non-shrink cementitious/epoxy resin grouting if
so instructed by the Architect to spall or loose concrete shall be carried out by an
approved specialist firm and in accordance to manufacturer’s recommendations.
29.1.23 Cutting well-defined cracks to form ‘V’ groove and refill cracks with approved non-
shrink cementitious mortar to the approval of the Architect All repairs including
non-shrink cementitious/epoxy resin grouting if so instructed by the Architect, to
well-defined cracks shall be carried out by an approved specialist firm and in
accordance to the manufacturer’s recommendations.
29.1.24 Fixing back all loose lengths of metal, plastic and other materials, dividing strips,
edges, nosings and the like to floor, wall, doorway, step, and the like including
replacing damaged/defective and missing ones with new to match existing.
29.1.25 Taking out loose and damaged/defective and missing putty or sealant from glazed
windows, doors, vents, fanlights, partitions and the like and reputty or refilled with
approved sealant to match existing.
29.1.26 Taking out and replacing all broken and missing glass louvres and panels to match
the existing including replacing sealant, putty or gasket and glazing.
29.1.27 Taking out windows and doors, re-dowelling, re-wedging, recramping, rehinge,
easing and adjusting, planning and smoothening out rough projects, replacing
damaged/defective and missing glazing beads, lippings, fillets, hinges and refixing
to smooth working condition.
29.1.28 Repairing and where necessary replacing all damaged/defective and missing
ironmongery such as door closers, hinges, hooks and eyes, door catch, casement
fasteners, handles, bolts, drawers and cabinet sliding and quiding tracks, to match
existing.
29.1.29 Oiling of hinges to smooth working condition and where necessary renewing
hinges.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS29/4
OCTOBER 2021 ISSUED FOR PERMIT SECTION 29 – GENERAL REPAIRS
29.1.30 Replace parts and accessories such as rollers, clips, brackets, etc. to existing
collapsible gates, roller shutters, roller grilles, folding and sliding doors, adjustable
metal louvred frames and the like and put them in smooth running condition.
29.1.31 Refix and adjust dislodged grilleworks such grilled doors/windows, railings, etc
including cutting out and replacing defective grilleworks and frames, all necessary
welding, replacing hinges, stops, bolts, etc., taking down doors, windows, railings,
etc. and refix.
29.1.32 Spot welding any loose metal joint in window, door, grillework, and the like
including taking down and refixing if necessary.
29.1.33 Argon welding or other approved methods to loose joints in stainless steel flashing,
gutter, rainwater downpipes, and the like.
29.1.34 Replacing all damaged and missing gratings to gullies and floor traps/waste to
match existing.
29.1.35 Testing before and after for the whole plumbing system to detect pipe leakage,
chokages and other defective works and fittings and submit reports to the
Architect. Curing pipe leaks, clearing of chokages and repairing defective works
and fittings of the plumbing system.
29.1.36 Testing before and after for the whole drainage system to detect chokages and
repairing defective works of the drainage systems. The drainage system shall
include sandpits, grease traps, inspection chambers, cesspits, and the like located
within the boundary of the building or structure and not under the control of the
Ministry of the Environment (or equivalent authority requirements/ Regulations).
29.1.37 Replacing all damaged and missing roof fascia and soffit boards to match the
existing.
29.1.38 All works in preparing surfaces of new and old substrates for painting including
making good holes and other blemishes affected by removal of existing wiring and
electrical battens and fittings and the like.
29.1.39 All new timber used in replacement work shall be held to include pressure
impregnation with solignum preservative unless chengal, balau or teak is used or
unless otherwise approved by the Architect.
29.1.40 Making good walls, columns, ceilings, etc. affected by rewiring by removing all
unwanted nails, battens, plug and the like and the refilling with non-shrink mortar.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS29/5
OCTOBER 2021 ISSUED FOR PERMIT SECTION 29 – GENERAL REPAIRS
29.1.41 Engaging an experienced general foreman to inspect the condition of the building
or structure to detect any signs of defective works such as rotten timber, rusty
hinges, water seepage, sagging beams, leaks, corroded rainwater goods, cracks
etc and report the defects to the Architect before commencement of the remedial
work.
29.1.43 For work involving ceiling boards, the Contractor shall remove and reinstall the
lighting fittings and any other fixtures attached to the ceilings boards. This shall
also include rewiring of the existing circuits if necessary.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
SS030_Sanitary Fittings and Accessories
JKT05 SS30/1
OCTOBER 2021 ISSUED FOR PERMIT SECTION 30 - SANITARY FITTINGS AND ACCESSORIES
SECTION 30
30.1 GENERALLY
Materials and workmanship of Sanitary Wares and Fittings supplied and installed
shall be similar to the respective manufacturer's printed catalogues. The
Contractor shall be deemed to have included provision for carriage, unloading,
placing orders, delivery to site, custom duties, insurance and all other labour costs
and expenses required in and for the proper completion of each item together with
all risks, liabilities and obligations set forth or implied.
The Contractor is to have included costs for all necessary insurance policies
against all and every risk whatever and however arising extended to cover the
fittings up to delivery to site and put in store. The contractor may propose an
equivalent alternative to proprietary items specified, subject to the written approval
of the ARCHITECT.
The Contractor shall ensure at his own expense that the Sanitary Wares and
Fittings, etc. offered are approved and accepted by the relevant authorities in
Singapore or equivalent local Standards. All sanitary wares and fittings delivered to
the site shall bear the indelible brand markings of the manufacturers approved by
the Public Utility Board (PUB) and Ministry of Environment (ENV) or the relevant
Approving Authority and accompanied with ENV serial numbers. Any sanitary
wares and fittings that do not have the above said marking shall be rejected and
removed from the site. Contractor to note that Auto sensor operated flush valves
may be required to be limited capacity (6 litres) and require clearance from PUB.
Contractors PE will liaise with authorities as necessary ensure all appropriate
provisions are included.
For water fittings, selection should be based on LEED Gold requirements. For the
fixtures and fittings listed , as applicable to the project scope, reduce aggregate
water consumption by 20% from the baseline. Base calculations on the
volumes and flow rates shown in the table below.
All newly installed toilets, urinals, private lavatory faucets, and showerheads that
are eligible for labeling must be WaterSense labeled (or a local equivalent for
projects outside the U.S.).
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS30/2
OCTOBER 2021 ISSUED FOR PERMIT SECTION 30 - SANITARY FITTINGS AND ACCESSORIES
IP Units SI Units
Public Lavatory Faucet 0.5 gallon/minute at 60psi 1.9 litre/minute at 415 kPa
Private Lavatory Faucet 2.2 gallon/minute at 60psi 8.3 litre/minute at 415 kPa
Legend
30.3 SAMPLES
30.4 DEFECTS
All sanitary wares and fittings shall be free from defects and in good working
condition. All sanitary wares and fittings shall be suitably packed to ensure
protection against handling or breakage during delivery.
30.5 GUARANTEE
The supplier of the sanitary wares and fittings shall rectify faults which may arise in
the sanitary wares and fittings for a period of 12 months from the date shown in
the Completion Certificate of the whole project and replace any defective sanitary
wares and fittings at his own expense if these defects were caused by a
manufacturing malfunction or if the materials do not conform to specification.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS30/3
OCTOBER 2021 ISSUED FOR PERMIT SECTION 30 - SANITARY FITTINGS AND ACCESSORIES
30.6 SPARES
The contractor shall provide a 5% (five percent spare) for all fittings and
accessories to the Employer upon the completion of the Project, to be handed over
the Maintenance Department’s representatives as directed by the ARCHITECT, for
future maintenance works.
The Contractor shall, as directed by the ARCHITECT, provide any item for the
supply and delivery of sample units and for all arrangements necessary for the
tests thereof by a recognised testing authority such as PSB or other approved
authorities.
The whole of the works for the Supply of Sanitary Wares and Fittings shall come
complete with matching chromium plated wall plates and brackets, backnuts,
washers, unions, bolts, screws, adaptors, connectors, hangers, chairs, back
plates, holding down or expansion bolts, capping pieces, and all associated
accessories, etc., for the fixing and complete functioning of the Sanitary Wares
and Fittings.
The Contractor shall submit to the ARCHITECT for approval, the trade literature,
catalogues, etc. of the fittings offered. All catalogues, etc. shall be properly filled
with pages numbered and cross-references shall be given. Catalogues for the
Sanitary Wares and Fittings shall be kept in separate files.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS30/4
OCTOBER 2021 ISSUED FOR PERMIT SECTION 30 - SANITARY FITTINGS AND ACCESSORIES
The sanitary wares and fittings shall be white. In the event of delay in the delivery
schedule, the sanitary wares and accessories shall be airfreight without any
additional cost charged to the Employer.
30.11 P, Q OR S TRAPS
The price for traps shall be deemed to include for left or right handed P, Q or S
traps. The Contractor to include for use of 'P' strap and highlight if 'P' trap cannot
be used. The Contractor shall be deemed to have checked the installation and
supervision of the hydraulics and sanitary work are appropriate for the
requirements of the traps to suit each piece of sanitary wares and its location in
relation to structural members and supply/ discharge piping.
The quantities will be as indicated on the schedules and/or the drawings. The
Contractor shall be deemed to have re-checked the numbers and types of sanitary
wares and fittings required prior to placing of order and all costs due to shortage,
wrong orders, etc. shall be borne solely by him.
Squatting pans shall be white vitreous china with integral PVC P or S traps,
screws, inlet spud, approved concealed flush valve with sensor device,
photoelectric sensor, stainless steel extension pipe with anti-siphonic arms. All
shall be supplied with provision for venting. Water inlets shall be at the back.
Sanitary wares shall be at least equal in standard to Armitage Shanks Claywood
squatting WC pan.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS30/5
OCTOBER 2021 ISSUED FOR PERMIT SECTION 30 - SANITARY FITTINGS AND ACCESSORIES
30.15 PEDESTALS
Pedestal W.C. shall be wall-mounted and white vitreous china with double or
single PVC P traps as required and provisions for venting. The following
accessories shall be supplied:
Basins shall be wall-mounted with backing and over counter type in white vitreous
china as shown in the detail drawings. Basins shall have built-in overflows and be
supplied with the following accessories:
Wall hung urinal shall be white vitreous china and shall come with the following
accessories:
(c) Flange
(d) Breaker
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS30/6
OCTOBER 2021 ISSUED FOR PERMIT SECTION 30 - SANITARY FITTINGS AND ACCESSORIES
Sink shall be stainless steel with single bowl and single drainer complete with
stainless steel bottle trap, extension tube, grating, brackets with bolts and nuts.
Sink shall be equal in standard to Kohler 'Ballad' Utility Sink Model K-3261 19" x
19". Sink to be able to fit into structural opening of the Mop sink Closets indicated
on the drawings. Sink will be fitted with a heavy duty faucet configured to facilitate
the filling of buckets or similar. All fittings/faucets to comply with local codes.
Toilet tissue holder (to hold 2 rolls at one time) shall include all fixing accessories.
Automatic electrical hand dryer to include 3 pins square plug and electric cord of
about 2,200mm long in locations (if any) noted on the drawings
Liquid soap dispenser of chrome plated stainless steel in base and cap complete
with concealed mounting bracket to be plugged and surface mounted to vanity
counter. One dispenser will be supplied for each basin.
Before commencing the installation works, the Contractor shall submit a full
sanitary ware and accessories schedule for each item listed.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS30/7
OCTOBER 2021 ISSUED FOR PERMIT SECTION 30 - SANITARY FITTINGS AND ACCESSORIES
The colour of all sanitaryware, unless stated as otherwise on the drawings will be
white. The finish of all sanitary accessories will be polished chrome-on stainless
steel
30.24 GLASS
All glass is to be from a manufacturer approved by the S.O. and complying with
relevant B.S. and to be of the qualities specified, free from bubbles, smoke wanes,
air holes and other defects for the full weight and thickness specified and to be
bedded in putty, back puttied and sprigged as required.
Glazer Generally
Rates for glass are to include for all raking, circular cutting and risks and for glazing
with "Arbolite" or other equal and approved special tropical glazing putty. Rates for
glass are to include for cleaning all glass inside and out, replacing all cracked or
broken panes and leaving in good condition on completion.
30.25 MIRRORS
All mirrors shall be 6mm thick "Pilkington's" polished plate glass mirrors with
polished bevelled edges all round.
All mirrors are to be in one piece with 15mm bevelled edge and back with 6mm
thick waterproofed marine plywood. Provide stainless steel framing around
perimeter of mirror.
30.26 PUTTY
All putty is to be hard and quick setting tropical putty specially manufactured and
shall receive one coat of paint ten days after glazing. Putty to be ".Arbolite" special
tropical putty or other equal and approved.
General
The Contractor to supply and install solid phenolic toilet partitions, shower stalls and
urinal screens, top hung, as shown in the architectural drawings. The proprietary
toilet cubicles shall include all the manufacturer’s fittings and accessories.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS30/8
OCTOBER 2021 ISSUED FOR PERMIT SECTION 30 - SANITARY FITTINGS AND ACCESSORIES
Shop Drawings
The contractor shall provide shop drawings of the toilet cubicles and the name and
country of the manufacturer for the Architects’s approval prior to the order for the
works. They shall also submit the full range of manufacturer’s complete range of
standard colour for the Architects’s selection and confirmation.
Toilet Partition
Doors - shall be nominal 25mm thick & of the same design and construction as
specified for dividing panels.
Pilasters - shall be nominal 25mm thick and of the same design and construction
as specified for dividing panels and doors. Pilaster shall be secured to floor to
proprietary detail. Pilaster shall be rebated 13mm x 9.5mm x 1423mm to permit
doors to overlap with flush front appearance.
Hardware - compartments shall be supplied with all hardware and fasteners for a
complete installation. Doors shall be hung on a continuous contact piano-type
hinge, made of extruded brite anodized aluminium and shall weigh not less than 1.5
pounds per foot. Knuckles shall have nylon separators. Pivot pin shall be 6mm type
304 stainless steel.
All fasteners shall be 6mm type 304 stainless steel. All fasteners shall be 19mm
“Pro-Star” tamper-proof screws located 200mm on centre on door and pilaster.
Fasteners shall be concealed under a snap-on cover.
Cover shall be fastened top and bottom with 16mm stainless steel “Pro-Star”
tamper-proof screws. Hinge shall have internal spring which is adjustable to hold
door open or closed as shown on drawings.
Strike-keeper and throw latch shall be heavy extruded brite anodized type 6463T5
aluminium. Coat hook and wall bumper shall be heavy chrome-plated Zamac and
fastened with 16mm “Pro-Star” tamper-proof screws.
Ducts to Urinals to have post formed roll fronted laminate tops cupped, screwed &
grommeted for maintenance access. Laminate to be Formica Colour portfolio range
or approved equivalent. Colour of laminate to ARCHITECT’s selection
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS30/9
OCTOBER 2021 ISSUED FOR PERMIT SECTION 30 - SANITARY FITTINGS AND ACCESSORIES
The polymer material shall be tested for its chemical resistance to the following
materials. Test result data confirms the material will not show any sign of
deterioration when immersed in the following chemicals and maintained at a
temperature of 80 degrees for a minimum of 30 days.
*Brine *Nicotine
The Contractor will complete all shop drawings showing panel sizes, any joints
required, sealants and support fixings.
All wash hand basins to be 'under counter' type. Contractor to allow for forming
bullnose finish around wash hand basin openings and front edge of panel as shown
on drawings.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS30/10
OCTOBER 2021 ISSUED FOR PERMIT SECTION 30 - SANITARY FITTINGS AND ACCESSORIES
30.31 SHOWER
Showers shall be wall mounted, and shall be complete with accessories including
and not restricted to the following :
c. Approved and painted mounting brackets, nuts, bolts, and screws required
for fixing.
Handrails and grab bars shall be placed to be ADA compliant. They shall be
cylindrical profiled in wood/stainless steel hairline finish, attached to wall, floor or
other stable structure that provides the means to support one person.
Grab bars shall include and not be restricted to swing-up grab bars, vertical and
horizontal grab bar, and L-shaped grab bars.
Wall mounted bib taps to be provided where specified with floor scupper drains to
allow for immediate drainage. Floor drains to be provided with mosquito/insect
traps.
Bidet hand sprays shall be provided with metallic hose complete with wall mounted
angle stop valve with lever handle.
Stainless steel in hairline finish robe hooks and clothes hanging rods to be
provided where highlight in drawings.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
SS031_Carpentry & Joinery
JKT05 SS31/1
OCTOBER 2021 ISSUED FOR PERMIT SECTION 31 - CARPENTRY AND JOINERY
SECTION 31
31.1 GENERALLY
All timber shall be best quality well seasoned, sawn die square, free from sap, shakes,
wavy edges, loose or dead knots and other defects.
Timber shall comply with the general requirements of the Malayan Grading Rules for
Scantlings, Baulks and Boards, with particular reference to Scantlings for joinery and
dressing.
Full cut timber must be used to ensure that the finished thickness and sizes shown on the
drawings are obtained, except where sizes are shown on drawings to be ‘nominal’, in
which instances the finished sizes may be up to 2mm less for each surface dressed.
The Contractor is to verify all finished sizes with the Architect, before putting the work in
hand, as the contractor will be held responsible for ensuring that all timbers are of the size
required by the Architect.
All timber is to be stored under cover and properly stacked, to enable air to circulate freely
around all faces.
Where timber is described as ‘plugged’, each item so described will be held to include for
plugging to concrete or brickwork and the plugging will be executed at not more than
450mm centres, unless otherwise described.
Where timber is described as ‘Ramset’, or the like, the gun fixing apparatus will be an
approved type of cartridge powered for fixing gun, firing steel fasteners, and the gun fixing
will executed at not more than 450mm centres, unless otherwise described.
31.2 STANDARDS
Unless other wise agreed by Architect, ensure all of the works comply with the relevant
requirements of the Standards and Codes listed below or referenced in the body of the
Specification. Alternative Standards and Codes may be submitted to the Architect,
provided it can be demonstrated that the alternative Standards and Codes comply with the
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR WHOLLY
WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS31/2
OCTOBER 2021 ISSUED FOR PERMIT SECTION 31 - CARPENTRY AND JOINERY
requirements of the standards specified. All standards and Codes quoted are the current
version, unless specific year references are noted.
Proposed specifications, selection of materials and proposal of Cabinetry and Joinery shall
comply with requirements/ achieve design standards matching LEED Gold Certification
standards/ provisions
SS 1 Plywood
SS 341 Safety glazing materials for use in buildings (human impact consideration)
Other Standards
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR WHOLLY
WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS31/3
OCTOBER 2021 ISSUED FOR PERMIT SECTION 31 - CARPENTRY AND JOINERY
VOCs not to exceed 0.5 milligrams per square metre per hour.
Styrene not to exceed 0.4 milligrams per square metre per hour.
All HPD laminates shall be manufactured in accordance with ISO 9002 criteria and meet or
exceed the performance requirements of European National Standard and International
Standards for high pressure decorative laminates. They should conform to the following:-
Dimensional
Change
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR WHOLLY
WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS31/4
OCTOBER 2021 ISSUED FOR PERMIT SECTION 31 - CARPENTRY AND JOINERY
Stain Resistance
No Effect No Effect No Effect
(1 – 23)
No Effect No Effect No Effect
(24 – 29)
All timber for carpentry and joinery work, except where otherwise described shall be
equivalent to first quality selected Teak or Birch.
All timber for joinery work shall be kiln dried. All timber exposed to air-conditioning shall
have a maximum moisture content of 12%.
All timber used on the works shall be supplied with a Certificate from the Kiln drying plant in
accordance with Appendix D of CP1-1966 the Code of Practice for the use of timber in
Building Construction.
The Contractor shall allow for tests to be made on samples of timber, as required by the
Architect, by an approved testing authority.
All timber used in the permanent works is to be treated with preservative, the timber is to be
vacuum/pressure treated, with preservative in accordance with SS 72 after machining. The
Contractor is to produce certificates to this effect, showing the quantities and sizes of timber
treated. Cut ends and saw cuts are to be swabbed with preservative to the satisfaction of
the Architect.
The timber preservatives shall be Tanalith C or Celcure A or other equal and approved.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR WHOLLY
WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS31/5
OCTOBER 2021 ISSUED FOR PERMIT SECTION 31 - CARPENTRY AND JOINERY
The following table sets down the recommended amount of approved preservative material
for use per m³ of timber.
The Contractor shall ensure that all treated timber shall be air dried for three (3) weeks
before being used in the Works.
The Contractor shall obtain from the treating firm a certificate of each consignment of
timber received for treatment to the effect that the timber has been impregnated in
accordance with this Specification, and that of the treating firm.
At all reasonable times, the Architect may visit any impregnation plant and may carry out
such tests and such inspections, as he may consider necessary. To facilitate this, the
Contractor shall lodge with the Architect, copies of all invoices and orders on the treating
firm at the time of dispatch.
31.7 PLYWOOD
Plywood is to be one of the grades specified in BS: 1455 and BS: 1088 and must comply
with Singapore Standard SS1:1984 (or equivalent local Standards) for Plywood
Specifications or which, in the opinion of the Architect, is appropriate to the work as
follows:-
a Grade 1
For in its natural state. The veneer shall be free from knots, worm and beetle
holes, glue stains or other defects.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR WHOLLY
WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS31/6
OCTOBER 2021 ISSUED FOR PERMIT SECTION 31 - CARPENTRY AND JOINERY
b Grade 2
For use where subsequent painting or similar treatment is required. The veneer
on the face side may have a few sound knots, occasional minor discoloration or
stains and small inlay repairs.
c Grade 3
For use where the plywood is not normally visible. The veneer may have defects
other than those specified above, provided that its serviceability is not affected.
Each sheet of plywood delivered to the Site shall bear the following markings :-
b BS No.
c WBP or MR
d Grade of finish
e Thickness
Woods used must be from sustainable managed forest face/back red species tropical
wood, long core tropical hardwood & short core tropical hardwood. Registration Certificate
for the statement of wood sources must be submitted.
Unless otherwise specified, plywood for internal use shall be Grade 2 with Type 2
adhesive, and plywood for external use shall be Grade 2 with Type 1 adhesive, the
veneers being rotary cut Luan unless otherwise indicated. Marine ply shall conform in all
respects to BS: 1088.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR WHOLLY
WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS31/7
OCTOBER 2021 ISSUED FOR PERMIT SECTION 31 - CARPENTRY AND JOINERY
5 (min) - (Reagent
1+2)
Stain Resistance
4 (min) – (Reagent
3+4)
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR WHOLLY
WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS31/8
OCTOBER 2021 ISSUED FOR PERMIT SECTION 31 - CARPENTRY AND JOINERY
31.9 VENEERS
Veneers shall be specifically selected and of the timber specified, not less than 1.50mm
thick. Veneers shall be properly bonded to prepared surfaces using approved adhesive, in
accordance with the manufacturer’s printed instruction.
Veneers to be on non-combustible backing where required under Section 3.13 of the FSB
Code of Practice for Fire Precautions in Buildings 1997 (or latest edition)
31.10 FIXINGS
Nails shall be the wire cut type of mild or black rolled steel, complying with the
requirements of BS: 1202, and unless otherwise specified shall be ‘bright finish’.
Galvanised, sherardised or cadmium plated nails shall also comply with BS: 1201.
Nails and spikes are to enter the second timber not less than 1½ times the thickness of
the first timber penetrated, where practical.
Nuts and bolts shall be mild steel. Expansion bolts shall be of approved manufacture.
Bolts connecting timbers loaded parallel to the grain shall be spaced a minimum of eight
(8) diameters from the end of the timber.
Bolts connecting timber loaded perpendicular to the grain shall be spaced a minimum of
four (4) times the diameter of the bolt from the loaded edge.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR WHOLLY
WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS31/9
OCTOBER 2021 ISSUED FOR PERMIT SECTION 31 - CARPENTRY AND JOINERY
Wood screws shall comply with BS: 1210. Unless otherwise described, brass screws shall
be used.
Exposed screws in public areas shall be the ‘Philips’ head type. Screws will be
countersunk where possible, dome headed where not. Screws to be stainless steel.
Positions and alignment of exposed screws is to be neat and regular, and to Architects
approval.
Screws that have to be removed and replaced periodically shall be fitted with satin
chromium/brass plated cups.
Coach screws shall be first quality mild steel, of approved manufacture, with hexagonal
heads. Each coach screws shall be fitted with a soft aluminium washer 3mm thick.
31.11 CARPENTRY
All carpentry is to be left with a sawn surface, except where particularly described as wrot.
31.12 JOINERY
Before the commencement of any joinery work, the Contractor shall submit for approval,
three samples of the timbers and plywood that it is proposed to use in the Works. All
timber and plywood subsequently used in the works shall be equal to the approved
samples.
When delivered to the Site, joinery shall be stored in dry conditions, and protected from
damp, the weather and any other damaging influences.
All joinery work is to be accurately set out, framed, and executed in strict accordance with
the detail drawings, and finished in a proper and workmanlike manner.
Running bonded joints are to be cross-tongued with Teak tongues and where over 38mm
thick, double cross tongued.
Joinery shall not be fixed until the plaster, etc., has completely dried out. Should it be
necessary for any tucking in or pointing to be undertaken, after joinery is in position, this
shall be kept to a minimum.
All joinery shall conform to the relevant requirements of BS: 1186 with regards to quality
and workmanship.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR WHOLLY
WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS31/10
OCTOBER 2021 ISSUED FOR PERMIT SECTION 31 - CARPENTRY AND JOINERY
All surfaces are to be wrot and glass papered to the Architect’s approval.
All window and door frames, stiles, rails, mullions, and framing of a like nature, are to be
rigidly framed together, with mortice and tenon joints, in accordance with BS: 1186.
All joinery work including plywood, which is to be stained, waxed etc., is to be of full,
matching and selected grains, without streaks. Timber is to be delivered to the Works in
sufficient time, to allow for replacement of any timber rejected by the Architect.
Any defects caused by non-compliance with the foregoing shall be remedied entirely at the
Contractor’s own expenses.
31.13 ADHESIVE
Adhesive used for carpentry and joinery work are to be cold setting case in glue in
accordance with BS: 1444 or cold setting synthetic resin adhesive of the moisture
resistant, gap filling type, complying with BS: 1204. The use of animal glue will not be
permitted.
a Phenol formaldehyde resin adhesive classified as weather and boil proof (W.B.P) to
BS: 1203.
b Urea formaldehyde resin adhesive classified as moisture and weather resistant (M.R.).
c. Low V.O.C
The adhesive for bonding plastic sheeting is to be an approved synthetic resin adhesive
used strictly in accordance with the manufacturer’s instructions. Plastic sheeting shall not
be applied to timber at a temperature less than 60°F or with a moisture content of more
than 15%.
31.14 PLUGS
All plugs described as fixing for joinery shall be stout hardwood dovetailed plugs dipped in
wood preservative before fixing and built into walls or bedded in cement mortar (1:6) in
mortices cut to same, at centres not exceeding 450mm.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR WHOLLY
WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS31/11
OCTOBER 2021 ISSUED FOR PERMIT SECTION 31 - CARPENTRY AND JOINERY
Alternatively, approved patent plugs may be used. Holes to receive these shall be drilled.
Any Joiner’s work which may show flaws or defects arising from unsound materials or
defective workmanship shall be removed, on the instructions of the Architect, and replaced
with new, all at the Contractor’s expense.
The Contractor is responsible for the protection of all Joiner’s work arising from
subsequent operations by his own or other tradesmen. The protection is to be rigid sheets
of a suitable material extending over all exposed surfaces. External corners will need to be
reinforced
Fixed Joiner’s work that in the opinion of the Architect, is liable to become bruised or
damaged in any way is to be properly cased and protected by the Contractor, until the
completion of the Work.
31.17 DOORS
Doors shall be in accordance with BS: 459, with regard to workmanship. To be effectively
kiln dried to prevent future warping.
The Contractor shall supply samples of all doors for the approval of the Architect, before
commencing the manufacture of doors. In the case of flush doors, the Contractor shall
supply, in addition, a sample section of the door showing the internal construction.
Materials and construction of fire doors shall comply with the Fire Safety Bureau’s (FSB)
requirements and be delivered to site tested, permanently labelled and approved by the
PSB. All solid core fire doors shall be guaranteed to be to the approval of the Authorities.
Where fire doors are indicated in the Contract Documents, all door frames and
ironmongery thereto shall also conform to the requirements in this respect.
Vision Panels to be provided in fire doors as required in the FSB Code of Practice for Fire
Precautions in Buildings 1997 (or latest edition)
Door frames to be solid timber to match door leaf finish. Door frames to wet areas to have
100mm high heel stone profiled to match door frame.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR WHOLLY
WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS31/12
OCTOBER 2021 ISSUED FOR PERMIT SECTION 31 - CARPENTRY AND JOINERY
The widths, heights and thickness of doors and panels specified are the finished sizes.
Likewise, the thickness specified for the component members of flush doors and panels
are the finished thickness required.
Hollow core doors shall be 50mm thick constructed of Kapor cores with 6mm plywood
facing to both sides. The core shall consist of 76 x 38mm top rail and stiles, 150 x 38mm
middle and bottom rails, 75 x 38mm intermediate rails and with 10 x 50mm Kapor lipping
tongued on to all four edges. Rebated lippings to stiles shall be 20 x 50mm.
Glazing openings shall be trimmed with 75 x 38mm core framing and fitted with 20 x
12mm Kapor glazing beads loosely pinned in all round on both sides.
Hollow core panels shall be 50mm thick constructed of Kapor cores with 6mm plywood
facing to both sides. The core shall consist of 100 x 6mm plywood facing to both sides.
Solid core doors shall be 50mm thick constructed of Kapor cores with 6mm plywood facing
to both sides. The core shall consist of 75 x 38mm top rail and stiles, 150 x 38mm bottom
rail and in-filled with 76 x 38mm vertical battens glued and well cramped together and with
three 10mm diameter mild steel bars passing horizontally through the width of the door
with nuts and washers at each end sunk into stiles and with 10 x 50mm Kapor lipping
tongued on to all four edges. Rebated lippings to stiles shall be 20 x 50mm.
Glazing openings shall be fitted with 20 x 12mm Kapor glazing beads loosely pinned in all
round on both sides.
Solid core panels shall be 50mm thick constructed of Kapor cores with 6mm plywood
facing to both sides. The Core shall consist of 100 x 38mm muntin and framing, in-filled
with 75 x 38mm vertical battens glued and well clamped together and with one 10mm
diameter mild steel bar passing horizontally through the width of the panel with nuts and
washers at each end sunk into the framing and with 10 x 50mm Kapor lipping tongued on
to all four edges.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR WHOLLY
WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS31/13
OCTOBER 2021 ISSUED FOR PERMIT SECTION 31 - CARPENTRY AND JOINERY
Glazed panelled doors shall be PSB/FSB approved & 50mm thick constructed of Kapor
100 x 50mm top rails and stiles, 150 x 50mm bottom rails and in-filled with 6mm thick clear
tempered glass. Glazing shall be fitted with 20 x 12mm Kapor glazing beads loosely
pinned in all round on both sides.
Materials and construction of rated doors shall comply with the Building Authority’s
requirement and be delivered to the site labelled and approved by PSB or equivalent local
authorities.
Architraves, Frames, Lippings Beadings etc. to doors will match the facing to the door as
indicated on the drawings
31.26 FITTINGS
All fittings shall be in accordance with the relevant requirements of the British Standards
Institution, with regards to general construction, quality and workmanship for fittings.
The contractor is required to prepare shop drawings of all exposed carpentry, joinery and
doors for architect’s approval.
31.28 MOCK-UPS
The contractor is required to prepare sample/mock-ups of all the various doors in the
project for Architects approval including Frame, Door leaf, Architrave, Ironmongery,
overpanel etc. Mock ups are to be done for one door type each as shown within the door
schedule.
The storage of doors in areas exposed to moisture or excessive humidity is not acceptable
and the contractor will be directed to remove such items from the site.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR WHOLLY
WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
JKT05 SS31/14
OCTOBER 2021 ISSUED FOR PERMIT SECTION 31 - CARPENTRY AND JOINERY
31.30 RATES
The description of and rate for each item of ‘Carpenter’ will be held to include for all
cutting, knotting, boring, sinking, pelleting, fitting, trimming, mitering, halving, morticing,
tenoning, dovetailing, scarfing and wedging, and all ends, splayed edges, short lengths
and temporary supports, rebating for plaster, and other sundry items of a like nature, nails,
spikes, pins and brads required.
The description of and rate of each item of ‘Joiner’ will be held to include for all cutting,
notching, holes, housing ends, mitering ends and shaped ends, angles, junctions, heading
joints, short lengths and any sundry items of a like nature, labour to stops or cross grains,
nails, spikes, pins and brads and for all testing.
The description of each item of ‘Joiner’ will be held to include for screws, gluing and any
other fixing.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR WHOLLY
WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
SS032-Others Misc
JKT05 SS32/1
OCTOBER 2021 ISSUED FOR PERMIT SECTION 32 - OTHERS AND MISCELLANEOUS ITEMS
SECTION 32
32.1 GENERALLY
The miscellaneous specifications are for items that have not been covered under
the other specifications and relate more to the specific items as described.
All fire doors must be labelled by Singapore Institute of Standards and Industrial
Research to comply with fire regulation and approved by the Fire Safety Bureau.
Single and Double leave doors shall be flush type, with door leaf made of two
1mm electro-galvanised steel sheets made in pair as open boxes in a
mechanically fully automatic production line designed to give a modern high
quality flush door with a very high level of smoothness. The door in-fill shall be
insulated with in-combustible glass wool 20 kilos/m³ with (sound reduction of RW
= 34db). This is to be applied not only to the internal fire doors also to the external
facing fire doors and all external facing doors unless specified otherwise by the
Architect.
The door leaf shall have internal steel reinforcements for hinges, lock and door
closer (min 400 x 1200mm WxH at upper hinge corner).
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR WHOLLY WITHOUT THE WRITTEN
PERMISSION OF M/S AWP PTE LTD.
JKT05 SS32/2
OCTOBER 2021 ISSUED FOR PERMIT SECTION 32 - OTHERS AND MISCELLANEOUS ITEMS
Doors shall have heat bonded laminate finish both sides using approved plastic
laminate. All exposed edges of steel doors and steel frames shall be sprayed
painted with Hipac P520 high performance polyurethane coating as specified or
other equivalent.
All ironmongery to doors shall factory fitted to the Architect’s approval and
selection. Shop drawings of all doors types of adequate detail to explain
installation shall be provided for approval prior to fabrication.
Fire door frame shall be of single (or twice) rebated made from 1.6mm thick
nominal of electro-galvanised steel sheet and are available up to finished
thickness of 290mm wide with a rebated depth of 25mm or 15mm for 1-2 hour fire
rated doors.
All door frames shall be reinforced to receive door closer arms, and suitable look
striker fixing plate with mortar guard behind lock plates and reinforced pockets for
fixing of hinges. A steel spreader is to be fitted to the bottom of each door frame
and can be fixed or removed after installation subject to requirements.
All fire door frames shall be installed true and plumb into door openings and must
be grouted solid with cement mortar. All frames shall also be provided with
“fishtail” cross brackets to be built into mortar joints to at least 75mm in depth at
vertical spacing along the jambs.
The number of cross brackets used is subject to the height of each door frame
and shall follow the original manufacturer’s installation instruction.
Although the doors and rollers shutters have been measured, the Contractor is
deemed to have checked the rated requirements of these doors and roller
shutters. The Contractor is to have allowed for at his own cost all cost incurred in
the use of other standard equivalent doors including extra structural supports, etc
to comply with the latest requirements of the Singapore Fire Authorities.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR WHOLLY WITHOUT THE WRITTEN
PERMISSION OF M/S AWP PTE LTD.
JKT05 SS32/3
OCTOBER 2021 ISSUED FOR PERMIT SECTION 32 - OTHERS AND MISCELLANEOUS ITEMS
Engineered Reliability
a) Constant-rated, stall-proof 5 kg torque capacitor start and run squirrel cage
motor
b) Chain drive, with average tensile strength of 1950 kg and 12.7 minimum
pitch
c) Self-lubricating planetary gear box
d) Adjustable hanger bars
Engineered Security
a) Selectable fire alarm interface
b) Compatible wit and data provider for automatic building systems
c) Sophisticated security control interface
d) Climate control, variable to suit conditions
e) Five selectable mode functions
The Operator shall work through logic controller programmable
microprocessor and any function can be adjusted through a hand-held plug-
in control pad.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR WHOLLY WITHOUT THE WRITTEN
PERMISSION OF M/S AWP PTE LTD.
JKT05 SS32/4
OCTOBER 2021 ISSUED FOR PERMIT SECTION 32 - OTHERS AND MISCELLANEOUS ITEMS
The equipment shall incorporate, but not limited to the following, as a complete
system:
a) Chain drive with automatic tensioner for smooth, quiet, positive operation.
b) High torque 5kg. Squirrel cage motor using 2 AC windings of 100V AC which
shall not consume more than 1/3 AMP under normal operating conditions
and be capable of successfully opening and closing a pair of 150 kg door
leaves.
c) Self lubricating gear box.
d) The operator shall be directed by a solid state electronics system
comprising; logic control, by the use of reed switches providing logic signals
for door positioning.
e) The operator must have positive electric braking without the use of
compressible cylinders.
f) The operator shall provide a force of 1kg. for 0.5 seconds closing, to ensure
full closure of the doors.
g) The track to be replaceable, made of steel curved to the desired radius,
carrying adjustable hanger bars supported by fully sealed raced fibreglass
reinforced nylon track wheels.
h) Adjustable dwell time (0-12 seconds). Pre-set dwell time will not be
accepted.
The contractor must provide a warranty of 5 years for the guarantee for the
operations of the system including the replacement of parts.
32.4 PATCHING UP
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR WHOLLY WITHOUT THE WRITTEN
PERMISSION OF M/S AWP PTE LTD.
JKT05 SS32/5
OCTOBER 2021 ISSUED FOR PERMIT SECTION 32 - OTHERS AND MISCELLANEOUS ITEMS
32.5.1 Generally
32.5.2 Material
Floor mats shall be roll-out type and shall be able to withstand heavy entrance
traffic.
Tread shall be securely locked into tread rails, yet remain easily accessible for
in-field replacement in the event of excessive wear or damage. Tread rails to
be fabricated from 6063-T52 aluminium alloy, and shall be continuously
hinged at each tread connection to permit cleaning. Tread rail finish shall be
standard medium bronze.
Recessed frame along the edge shall be a continuous stainless steel frame in
hairline finish.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR WHOLLY WITHOUT THE WRITTEN
PERMISSION OF M/S AWP PTE LTD.
JKT05 SS32/6
OCTOBER 2021 ISSUED FOR PERMIT SECTION 32 - OTHERS AND MISCELLANEOUS ITEMS
All openings in floors, walls and in duct spaces which need to be sealed shall
be fire-stopped with fire stopping system of 2 hours rating.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR WHOLLY WITHOUT THE WRITTEN
PERMISSION OF M/S AWP PTE LTD.
JKT05 SS32/7
OCTOBER 2021 ISSUED FOR PERMIT SECTION 32 - OTHERS AND MISCELLANEOUS ITEMS
32.9.1 General
Loading dock bumpers shall be provided in the loading and unloading area.
32.9.2 Material
Loading dock bumpers shall be heavy duty EPDM bumpers, and shall confirm
to the following sizes:
Height - 200mm
Thickness - 80mm
32.9.3 Specification
Durometer - 70 ±5
Elongation - 27%
Tolerance - ±¼"
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR WHOLLY WITHOUT THE WRITTEN
PERMISSION OF M/S AWP PTE LTD.
JKT05 SS32/8
OCTOBER 2021 ISSUED FOR PERMIT SECTION 32 - OTHERS AND MISCELLANEOUS ITEMS
Loading dock bumpers shall be installed onto the face of the dock or designated
walls according to the Manufacturer's printed instructions and to the Architect's
approval.
32.10.1 All walls and columns at all service areas shall be fixed with wall and column
guards manufactured under an ISO 9002 Quantity Management System, of
1200mm length corner guards. Walls and column guards shall be provided to all
external areas.
The Corner Guard shall be installed in wall corners and pillars at a height of not
more than 100mm from the floor level. Drill 5mm diameter pilot holes in the wall
where the profiles is to be attached using a 2mm(T) x 12.5mm(W) x1200mm(L)
Aluminium Pressure Strip. Install the Corner Guard Profile with 5mm (D) x
45mm(L) nail plugs.
Stainless steel used shall be classified under austenitic 18% chromium and 10%
nickel type 316 conforming to the relevant British Standard. Unless specifically
stated as otherwise. Strippable protective membrane shall be used to prevent
damage to surfaces during fabrication and erection.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR WHOLLY WITHOUT THE WRITTEN
PERMISSION OF M/S AWP PTE LTD.
JKT05 SS32/9
OCTOBER 2021 ISSUED FOR PERMIT SECTION 32 - OTHERS AND MISCELLANEOUS ITEMS
The Architect reserves the right to replace the length, part or whole of the
stainless steel works if it is found that the above precautionary steps are not
carried out by the Contractor.
The drum assembly shall consist of suitably graded oil-tempered torsion springs
secured to drumwheels moulded from engineering plastics, with a corrugated
sheet metal wrap-around to form a cylindrical torque tube.
The door curtain shall consist of HD interlocking slate with a matching bottom rail
complete with PVC weatherseal. The edges of the curtain shall be fitted with self-
lubricating nylon end-clips secured to alternate slats to prevent lateral movement.
The slats shall be perforated throughout with 225 x 40mm slots spaced at 20mm
apart to achieve a lattice grille appearance, with exception of the shutter to Bin
centre which is to be fitted with solid slats.
The guide channels shall have PVC inserts on both lips to prevent metal-to-metal
contact with the curtain. The door shall be push-pull hand operated, with a hook
handle provided to assist operation beyond arm's reach.
The whole door curtain including the guides shall be powder-coated to the
approved colour.
The Electrical Operated system shall include the motor and electrical accessories,
properly earthed, with approval by the relevant Electrical Authority. Manual over-
ride system for operating the roller shutter shall be provided in the event of power
failure.
Guarantee/Warranty
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR WHOLLY WITHOUT THE WRITTEN
PERMISSION OF M/S AWP PTE LTD.
JKT05 SS32/10
OCTOBER 2021 ISSUED FOR PERMIT SECTION 32 - OTHERS AND MISCELLANEOUS ITEMS
1. 1800mm high x 300mm wide x 500mm deep complete with 8mm thick solid
compact laminate doors (phenolic core board) in a choice of standard colours
from Trespa.
3. Full height aluminium locker bodies with radiused back corners for ease of
cleaning.
4. Injection moulded plastic tops, shelves and bases with ventilation slots and
drainage holes.
5. Locker base unit to have 3 degree slope to facilitate cleaning or hosing out.
6. Full height extruded aluminium (door and latch) frame sections, fitted with
double unsprung hinges and door stops, trapped within the extrusion to ensure
maximum strength.
7. Full height extruded aluminium (door and latch) frame sections, fitted with
double unsprung hinges and door stops, trapped within the extrusion to ensure
maximum strength.
8. 8mm solid laminate door bonded and mechanically fixed to the hinges with
aluminium rosettes to the outside.
10. The locks shall be in ‘Prospec’ cam lock supplied with 2 keys each.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR WHOLLY WITHOUT THE WRITTEN
PERMISSION OF M/S AWP PTE LTD.
JKT05 SS32/11
OCTOBER 2021 ISSUED FOR PERMIT SECTION 32 - OTHERS AND MISCELLANEOUS ITEMS
The Fire Roller Shutters to be installed at the loading bay are to be GDS Global
Limited’s IFS 50/240 2 hr fire rated roller shutter or any other approved equivalent.
All proposed fire roller shutters by contractor must perform and excel in the
international test criteria. for such shutters set internationally are extremely
stringent.
The Fire Insulated shutter has to undergo a fire test to determine its fire insulation
capabilities. Failure is deemed to have occurred once the surface temperature of
the unexposed side of the test specimen exceeds a mean temperature rise of
140°C. This is measured by the 5 main thermocouples, one placed at the center of
the curtain and the remaining four at the centers of each quadrant of the curtain.
Three additional thermocouples are placed at the right, center and left of the top of
the curtain.
Drum Assembly
The barrel assembly consists of an extremely rigid steel tube sheathed over a pair
of drive shaft assemblies fitted to heavy duty bearing sets and supported at both
ends by steel head plates. The drive shaft is a solid polished-steel round bar
incorporating key ways to accept the drive sprocket. Corresponding to the size of
the shutter, the head plates are either 6mm or 8mm thick with shafts of either
38mm or 50mm diameter.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR WHOLLY WITHOUT THE WRITTEN
PERMISSION OF M/S AWP PTE LTD.
JKT05 SS32/12
OCTOBER 2021 ISSUED FOR PERMIT SECTION 32 - OTHERS AND MISCELLANEOUS ITEMS
Door Curtain
Material
The door curtain consists of 2 layers of double-walled cavity interlocking slats
overall size 80mm x 20mm thick, thus forming an air gap. Located within this air
gap is an additional insulation barrier of silica fabric which is rolled up into a
deployable package. This barrier will be deployed by a separate fusible link in the
event of a fire. The cavity of the slat is filled with insulation material consisting of a
combination of Ceramic Fibre and Gypsum.
End Clips
Custom-shaped steel end-clips are secured to each end of every slat to prevent
lateral movements
Bottom Rail
A notional bottom rail is formed by bottom-most slat linking the two walls of curtain
when the shutter is in the fully closed position.
Door Guides
The door guides are a pair of box module of overall dimensions 250mm wide x
265mm deep. Each module contains a mechanically retractable guide channel that
will automatically latch between the two walls of curtains when the door reaches its
fully closed position. In the opening sequence, the guide channels will automatically
retract to allow the curtains to travel upwards to roll up. The retractable guide
channels are secured to a pair of 100 x 50 x 5mm thick 'C' channel post via
purpose-made linkages. The box module is finished with an external 1.0mm thick
galvanized steel sheet cladding, with the voids packed with Ceramic Fibre blanket
for fire insulation.
Door Operation
Motor Drive
The drive unit consists of a suitably-sized linear drive motor operator mounted
parallel to and behind the door roll. It has an integrated gearbox and a chain-
operated sheave wheel for manual operation in case of power failure.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR WHOLLY WITHOUT THE WRITTEN
PERMISSION OF M/S AWP PTE LTD.
JKT05 SS32/13
OCTOBER 2021 ISSUED FOR PERMIT SECTION 32 - OTHERS AND MISCELLANEOUS ITEMS
The control box is lockable, housing a set of push buttons for Up', 'Down' and 'Stop'
operations. The door operation shall automatically stop at the desired upper and
lower limits via adjustable limit switches.
For safety reasons, the 'DOWN' button shall require the operator to push and hold
when closing the shutter. This is to ensure the closing operation is being
supervised. Upon sighting an obstruction, the operator will automatically release the
push button by reflex. This will instantly stop the downward travel of the shutter and
prevent accidents.
Power supply shall be either Single Phase 230V x 15amp or 3 Phase 415V x
20amp, depending on the size of the shutter.
Submittals
The contractor is to submit a method statement when proposing the fire roller
shutters. The construction methods and relevant test results have to be provided to
verify the product’s capabilities and compliance to the specifications. No fabrication
is to take place without the Architect’s approval. The contractor is to provide an
indemnity of 5 years of warranty to the client.
The acoustic quality and STC rating for enclosure of spaces in accordance to the
chart below
NO ROOM STC
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR WHOLLY WITHOUT THE WRITTEN
PERMISSION OF M/S AWP PTE LTD.
JKT05 SS32/14
OCTOBER 2021 ISSUED FOR PERMIT SECTION 32 - OTHERS AND MISCELLANEOUS ITEMS
The following are Physical Security Product Selection required to be included in the
Project. Counter-proposal should there be any shall require to be submitted for Client &
Security Consultant’s clearance.
[Provision of security related items shall be read in conjunction with design and
schedules]
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR WHOLLY WITHOUT THE WRITTEN
PERMISSION OF M/S AWP PTE LTD.
JKT05 SS32/15
OCTOBER 2021 ISSUED FOR PERMIT SECTION 32 - OTHERS AND MISCELLANEOUS ITEMS
6 Sliding Gate Securitex FAAC For gate length – max.10m (single side)
Operator 994/884T
Location – Toilets
Security Hardlines
Loading Dock equipment shall be procured and installed in compliance with owner’s and
local requirements. The items include, however are not restricted to, the following :
a. Dock Levelers
• Features: Include a bellows type skirt to close off the pit from debris.
Provide gasketing/weathersealing to prevent air infiltration. Refer to
drawings for additional details.
• Description:
b. Dock Bumpers
• Construction:
ii. Enclose ends of bumpers with metal angles under 1,500 pounds
pressure and weld to supporting rods.
• Installation: Install level with dock, plug welded to steel corner angle, or
use 5/8 inch by 3 inches minimum, lag bolts with a minimum length of 3
inches and corresponding
c. Dock Shelter
• Construction:
d. Truck Restraints
• Operation:
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR WHOLLY WITHOUT THE WRITTEN
PERMISSION OF M/S AWP PTE LTD.
JKT05 SS32/17
OCTOBER 2021 ISSUED FOR PERMIT SECTION 32 - OTHERS AND MISCELLANEOUS ITEMS
ii. Dual locking positions at 7 inches and 11 inches from face of 4 inch
bumper.
iii. Horizontal hooking range up to 12" (305mm) beyond the face of the
dock.
• Hardware:
iv. Housing profile: 11-5/8" (295mm) above grade and complies with
NHTSA guidelines.
v. High Visibility Barrier Arm: Hydraulic arm secures ICC bars from
12" to 26" (305mm to 660mm) above grade.
• Electrical: 120 volt, single phase supply; 24 volt control and lighting circuit.
• Exterior Lights: Low profile flashing green and red LED signals indicate
safe or unsafe conditions for vehicle movement. Caution sign with standard
reversed lettering.
e. Scissors Lifts
• Capacity: 10,000 lbs minimum to take forklift load (MHE Electric Forklift 3-
wheel 1.5t – service weight (incl. battery): 3,050kg)
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR WHOLLY WITHOUT THE WRITTEN
PERMISSION OF M/S AWP PTE LTD.
JKT05 SS32/18
OCTOBER 2021 ISSUED FOR PERMIT SECTION 32 - OTHERS AND MISCELLANEOUS ITEMS
• Platform:
• Hinged Bridge:
ii. Construction:
o Spring-assisted bridge
• Safety Devices:
f. Dock Lights
• Die cast aluminum control box, surface mount, polyester powder coated
finish, yellow color.
• UL listed.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR WHOLLY WITHOUT THE WRITTEN
PERMISSION OF M/S AWP PTE LTD.
JKT05 SS32/19
OCTOBER 2021 ISSUED FOR PERMIT SECTION 32 - OTHERS AND MISCELLANEOUS ITEMS
h. Electrical Requirements
Warranty
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR WHOLLY WITHOUT THE WRITTEN
PERMISSION OF M/S AWP PTE LTD.
Document prepared by
PT Aurecon Indonesia
Revenue Tower, 25th Floor,
Unit 25-113, District 8
Jenderal Sudirman Kav. 52-53,
SCBD Lot 13,
South Jakarta 12190
Indonesia