Professional Documents
Culture Documents
05 Raceway and Boxes 26 05 33 09022022011344
05 Raceway and Boxes 26 05 33 09022022011344
26 05 33
Contents
1.0 GENERAL
1.1 Reference
1.2.1 Refer to and co-ordinate with sections on Excavation and Backfill, and
Concrete Work, and refer to details of duct/pipe enclosures indicated on
structural and electrical drawings.
2.0 PRODUCTS
2.1.1 Design, Supply, Installation, Testing and Commissioning of UPVC duct banks
as shown on the drawings and as specified hereunder for the following systems:
Size and type of ducts shall be as indicated in the related electrical system
drawings.
2.1.4 Submittals
2.1.5 Ducts shall be Type heavy duty UPVC complete with associated couplings,
spacers and all required accessories. Duct shall be suitable to withstand a
minimum pressure of 6 bar.
2.2.3 Accessories
The system shall have a comprehensive range of couplers, end plates, inside
and outside corners, both horizontal and vertical. The Accessories shall have a
finish compatible to the main trunking.
The accessories shall be manufactured from uPVC to facilitate easy fitment and
alignment with the straight lengths.
There shall be a complementary range of Flat angles and Tees to allow the
trunking to follow its profile along the vertical face.
2.2.5 Dimensions
The system must be non corrosive and not affected by sea water. It should be
resistant to mineral acid, alkalis and detergents.
2.2.9 Thermal
2.3.1 Materials
c) Use flexible steel conduit with ground conductor for final connections
to motors. Lengths shall not exceed 500 mm.
2.4.1 Materials
g) Provide combination boxes with barriers for wiring of more than one
system.
h) Provide panel mounted fixing frames where outlet boxes are installed in
paneling.
i) Brass earth lead shall be provided for the outlet box to allow connection
of earth wire.
k) All circular PVC boxes where used to support light fittings shall be
provided with steel insert clips.
2.5.1 Materials
b) Junction and pull boxes shall be of steel with covers attached by screws
and shall be provided with earth terminal and screws.
2.6.1 Materials
a) The cable tray system shall be complete with all necessary trays, risers,
elbows, supports, end plates, drop outs and fittings required for the
installation.
b) Cable trays shall be heavy duty perforated sheets to BS 1449, Hot dip
galvanized after manufacture to BS 729. All heavy duty trays
supporting power cables shall be of folded each with return flang.
Thickness of tray shall not be less than:
d) All supports and fixings shall be hot dip galvanized after manufacture to
BS 729.
f) Cable ladder shall be produced of 2mm hot dip galvanized mild steel.
3.0 EXECUTION
3.1.1 Construction
a) Build duct banks on undisturbed soil or well compacted granular fill not
less than 150 mm thick, compacted to 95% of modified Proctor.
f) Prior to laying ducts, construct a concrete skim slab not less than 50
mm thick. Provide base spacers across the skim slab at 1500 mm
intervals, levelled to the grades indicated for the bottom layer of ducts.
g) Construct a dry well of crushed stone at the low points of the ductbank,
and where indicated at manholes. Dry wells shall be pits not smaller
than 500 mm square x 1200 mm deep below the invert elevations of the
low points of the duct banks or manholes.
i) Install ducts at the elevations and slopes indicated on the drawings, with
a uniform grade of not less than 250 mm per 100 m. The top of any duct
bank shall not be less than 700 mm below finished grade unless
specifically indicated.
k) Reinforcing steel and metal ties may encircle all ducts, but shall not
encircle any duct or group of ducts in the duct bank.
m) This Division shall ensure that not less than 75 mm of concrete are
placed at the top, bottom and sides of the duct bank.
o) Cut, ream and taper ends of ducts in the field in accordance with the
manufacturer's recommendations, so that duct ends are equal to factory-
made ends.
q) Use rigid aluminium or galvanized steel conduit for bends and for all
sections extending above finished grade level. For ducts carrying single
conductor cable, use only aluminium conduit.
v) Ensure that concrete has attained 50% of its specified strength before
backfilling.
x) Back opening in ducts with asbestos, braid packing and seal the
asbestos packing with permanently resilient silicon base non
inflammable water proof compound.
3.2.1 Installation
d) Provide expansion couplings with bonding jumpers and clamps for all
conduits crossing building expansion joints. Expansion couplings shall
be Crouse-Hinds Type XJ. or equivalent Bonding jumpers and earthing
clamps shall be Crouse-Hinds Type GC or equivalent.
f) Running couplers with lock nuts shall not be permitted only three piece
conduit unions shall be accepted.
h) Install conduits in block walls as the walls are being erected and not by
cutting after erection of the walls.
i) Conduits shall not run exposed in any finished area. All areas shall be
considered finished unless indicated otherwise. Electrical Rooms and
Mechanical rooms shall be classed as unfinished areas.
q) Protect conduit stub-ups from damage during construction, and seal the
ends to prevent the entrance of foreign material with plastic plugs or
other approved devices. Taping or similar protection is not acceptable.
s) Where conduits pass through other floor slabs or fire walls, seal into the
concrete or pass through a sleeve. Sleeves shall be high density plastic,
with flange for attaching to form work or structure. Pack the sleeve
with fireproof packing and seal approved by THE CONSULTANT
safety department.
t) Where runs of conduit are shown, only the general routing and location
are indicated. Install all conduits so as to provide a maximum head
room and minimum interference with the space. Install conduits as
close to the structure as possible, so that furring can be kept to a
minimum.
u) Take out and replace at no change to the contract price any conduit or
cable which is not installed properly.
v) Install a nylon fish cord in each empty conduit, complete with cap and
bushing at each end.
For the purposes of this Specification a double set constitutes the equivalent of
one right-angled bend.
Not more than two right-angled bends or 10m length of conduit shall be
permitted between draw boxes, and vertical conduit runs more than 3.0m shall
provide cable support using a draw-in box.
Each bend, set, adaptable box, conduit box, etc, shall be supported at 150 mm
(approx) from each side.
Saddles and boxes shall be secured by stainless steel screws of a minimum size
of 30mm x No.8 or equal.
Separate conduit shall be provided for each circuit and for each system wire.
3.3.1 Installation
f) In the situations where tees and junctions are encountered, the multi-
compartment fittings shall be of such a depth as to allow for suitable
pass-over connections.
j) Trunking shall Lie securely fixed to the building fabric at intervals not
exceeding 1.5 meters.
k) Trunking up to 50mm wide shall have only one screw at each fixing
point, trunking over this width shall have two screws. Screws shall be
sheradised Class 1 or stainless steel, No. 12 for up to 75mm width, No.
14 for larger sizes.
o) The cover shall be removable over the whole length of the trunking.
Where trunking passes through walls or floors a small length of cover
must be provided on the section passing through to form a sleeve for 25
mm on each side.
3.4.1 Installation
c) Locate boxes in hung ceiling spaces so that they do not interfere with
the removal of ceiling tiles or equipment.
e) Do not mount boxes between the same pair of studs, on opposite sides
of sound-rated partitions. Seal spaces between boxes and gypsum board
with acoustical sealant.
f) Adjust floor boxes so that closure plates are flush with the surface of the
floor tile, or the floor if carpeting is specified. Provide under floor duct
fittings and outlets or single flush outlets with waterproof covers, as
indicated on the drawings.
3.5.1 Installation
e) Terminal strips may be omitted where there are less than 3 connections
in a junction box, but all conductors shall be identified by cable
markers.
f) Terminals may be omitted for through cables which are not broken at a
junction box.
3.6.1 Installation
b) Sizing of cable trays shall allow 30% spare capacity for future cables.
c) All cables inside buildings shall run in cable trays whether or not shown
in the related drawings. Cable trays shall be segregated for each
system.
e) Sets and bends shall be sized to allow for the minimum permissible
radius of the largest cable on the tray. Cables shall retain their relative
positions on bends and sweeps.
g) Cable trays shall be cut along a line of plain metal and not through
perforations. Burrs or sharp edges shall be removed prior to the
installation of tray sections or accessories.
Bushes shall be provided through all holes cut in the body of the tray.
The cable tray shall be made good at all joints or holes by first treating
the surfaces with a suitable rust proofing agent, then applying finishes
comparable to the remainder of the surface.
i) All metal work, fixing bolts, etc., shall be suitably primed and painted
with two coats of zinc-enriched paint.
Not more than four cables shall be secured by a single clip or saddle.
Binding tape fixings must not be used. On vertical tray installations
load-bearing cleats or saddles shall be used and securely fixed to the
tray.
k) Provide cable tray expansion joints at all locations where the tray
crosses a building expansion joint and at other locations recommended
by the manufacturer.
l) Where cables in tray pass through a floor or fire barrier, interrupt the
tray and provide an Electro tray cable transit with openings sized for the
cables.
m) Cable trays shall be provided with standard stand and ventilated cover
to protect cables from sun radiation when installed outdoors and to
protect cables form mechanical damage where damage is likely to occur
during maintenance activities. Also, wherever applicable indoor and
subject to the consultant.
END OF SECTION