CSMT P.F EXTENSION WORK Date :14.05.

2023
Section
S.no. Activity UNIT Total Execution Total Remarks/
Scope Balance Details
1 Foundation Nos. 135 132 3
2 Mast /Upright Erection Nos. 135 125 10
3 Mast /Upright Grouting Nos. 135 125 10
4 Feeder Foundation Nos. NIL NIL NIL
5 Feeder mast Erection Nos. NIL NIL NIL
6 Feeder mast Grouting Nos. NIL NIL NIL
7 TTC erection Nos. 16 12 4
8 Portal & Boom Nos. 13 7 6
9 Bracket erection Nos. 258 130 128
10 Wiring P.F 10&11(Catenary) Shots/KM 2/2.2 nil 2/2.2 10Tkm(Do
10A Wiring SDG 1&14(Catenary) Shots/KM 2/1.5 nil 2/1.5 ne-1.2. Bal
10B wiring (X/O AND O/LAP) Shots/KM 14/6.3 4/1.2 10/5.1 8.8tkm)
caternary
11 Wiring P.F 10&11(Contact) Shots/KM 2/2.2 nil 2/2.2
11A Wiring SDG 1&14(Contact) Shots/KM 2/1.5 nil 2/1.5
11B wiring (X/O AND O/LAP) contact Shots/KM 14/6.3 4/1.2 10/5.1
12 ATD Erection Nos. nil nil nil
13 Droppering & Clipping Span 410 182 238
14 SED Checking Nos. NIL NIL NIL
15 ATD Adjustment Nos. NIL NIL NIL
16 Isolator Erection Nos. 14 3 11
17 Section Insulator Nos. 12 3 9
18 TW checking Nos. NIL NIL NIL
19 Bond Erection Nos. 135 110 25
20 AT Erection Nos. 4 NIL 4
21 SPL PORTAL Nos 4 NIL 4
22 SPL FOUNDATION Nos 8 NIL 8
23 formation of overlap Nos 9 3 6
24 dismantling of portals+TTC Nos 23+9 11+5 12+4

CSMT END BLOCK


Erection=2 foundation, four portal and six TOTAL BLOCKS REQUIRED 40 BLOCKS OF 2HRS EACH
mast,2TTC
Dismantle=4 portal, 2TTC ,4 mast DISMANTLE,

MAJID END BLOCK


Overlap formation of nine line (3 completed), SPECIAL BLOCK required 4 BLOCKS OF 6HRS EACH
Erection= 4special portal of 52m span and two nos AND 6 BLOCKS OF 4HRS EACH.
portal,2TTC. corridor 20 blocks of 2hrs each
Dismantle=2nos special anchor portal and 5 nos 15 blocks 3hrs (crossover)
D portal,2TTC