Professional Documents
Culture Documents
INVESTMENT PROJECTS
2023
PORTFOLIO OF MINING
INVESTMENT PROJECTS
2023
OSCAR VERA GARGUREVICH
Minister of Energy and Mines
DOCUMENT PREPARED BY
THE MINING PROMOTION DIRECTORATE
STAFF
VICTOR CARRANZA AVELLANEDA
DEIVID RAMIREZ RAMIREZ
KIARA CAMPOS ROJAS
CARLOS ABANTO LEON
WWW.GOB.PE/MINEM
Central Phone: (+511) 4111100 This document is a translation of the original text in Spanish, made by the translator Teresa E.
Chumpitaz Garces (CTP N° 0246). It has been certified by the Association of Translators of Peru
(Registry N ° 0005-2023). This edition is for informational purposes only, it is not an official translation
and it is not valid for legal purposes in Peru.
INDEX
EXECUTIVE SUMMARY .................................................................. 5
I. INTRODUCTION .................................................. 7
V. ANNUALIZED PROJECTION
OF INVESTMENTS ............................................... 33
5.1. Investments Executed until 2020 ...................... 33
5.2. Projected investments 2023-2026 ................... 34
5.3. Projected investments after 2026 ..................... 35
In addition, the year of edition of the document has been changed to 2023, in
accordance with the deadlines for the execution of the mining projects that
are part of the portfolio. Therefore, the "Portfolio of Mining Investment Projects
2023" is the updated edition of the previous "Portfolio of Mine Construction
Projects 2021".
On the other hand, this document has been designed considering the funda-
mental characteristics that a mining project should comply with to carry out
its operations in the country, as detailed below:
Chapter II: This section contains the changes registered in the Portfolio with
respect to the previous version (November 2021) which are contained in 2
groups: a) Changes in the methodology, in order to standardize the terms and
definitions in accordance with the methodologies used by the main mining
countries in the region and the world; and b) Changes in the projects of the
Portfolio, referring to the update of characteristics of some projects, the entry
of 8 new projects and the exit of 4 projects from the portfolio.
Chapter III: This section describes the methodology used for the analysis of
the portfolio and the preparation of project files.
Chapter IV: Devoted to the analysis of the main characteristics of the projects
in the portfolio, such as the year of start of construction, location of the project,
country of origin of the main investor, type of project, stage of progress, source
of supply for water consumption, type of exploitation and the mineral to be
extracted, with Capex investment as the central axis.
In 2021, Peru was one of the largest mineral producers in the world, holding
7 of the most traded minerals (copper, gold, silver, zinc, lead, tin and
molybdenum). It is worth mentioning that this diversity is due to the
geographical conditions that make up the territory, making it a polymetallic
country. In addition, mining activities are developed in only 1.4% of the
national territory, which represents a great potential to be explored and
exploited.
In this regard, the Ministry of Energy and Mines (MINEM, by its acronym in
Spanish), through the General Directorate of Mining Promotion and
Sustainability, with the objective of encouraging and promoting mining
1 Mining Yearbook 2021. investment in the country, is pleased to present the new Portfolio of Mining
2 Source: Peruvian Institute of Investment Projects 2023, which consists of 47 mining projects and a
Economics (IPE, by its acronym
in Spanish). combined investment of US$ 53 715 million.
START
START OF MAIN PROGRESS GLOBAL
OF PROJECT OPERATOR REGION STAGE INVESTMENT
CONSTRUCTION PRODUCT
OPERATION US$ MILLION
2018 2024 Toromocho Expansion Minera Chinalco Peru S.A. Junin Copper CONSTRUCTION 1355
2019 2023 Santa Maria Expansion Compañia Minera Poderosa S.A. La Libertad Gold CONSTRUCTION 121
2021 2023 Shouxin Expansion Minera Shouxin Peru S.A. Ica Iron CONSTRUCTION 140
2022 2025 San Gabriel Compañia de Minas Buenaventura S.A.A. Moquegua Gold CONSTRUCTION 470
2023 2025 Romina Compañia Minera Chungar S.A.C. Lima Zinc FEASIBILITY 150
2023 2026 Corani Bear Creek Mining S.A.C. Puno Silver DETAIL ENGINEERING 700
2023 2026 Magistral Nexa Resources Peru. S.A.A. Ancash Copper FEASIBILITY 493
2023 2029** Antamina Replenishment Compañia Minera Antamina S.A. Ancash Copper FEASIBILITY 1604
2024 2027 Yanacocha Sulfides Minera Yanacocha S.R.L. Cajamarca Copper DETAIL ENGINEERING 2500
2024 2028 Zafranal Compañia Minera Zafranal S.A.C. Arequipa Copper FEASIBILITY 1473
TBD Bayovar Expansion Compañia Minera Miski Mayo S.R.L. Piura Phosphate FEASIBILITY 450
TBD Pachapaqui Expansion ICM Pachapaqui S.A.C. Ancash Zinc FEASIBILITY 117
TBD Ariana* Ariana Operaciones Mineras S.A.C. Junin Copper CONSTRUCTION 140
TBD Cañariaco Cañariaco Copper Peru S.A. Lambayeque Copper PRE-FEASIBILITY 1043
TBD Cañon Florida Nexa Resources Peru. S.A.A. Amazonas Zinc CONCEPTUAL 214
TBD Chalcobamba Phase I Minera Las Bambas S.A. Apurimac Copper DETAIL ENGINEERING 130
TBD Don Javier Junefield Group S.A. Arequipa Copper CONCEPTUAL 600
TBD Haquira Minera Antares Peru S.A.C. Apurimac Copper PRE-FEASIBILITY 1860
TBD Hierro Apurimac Apurimac Ferrum S.A.C. Apurimac Iron PRE-FEASIBILITY 2900
TBD Hilarion Nexa Resources Peru. S.A.A. Ancash Zinc PRE-FEASIBILITY 585
TBD Integracion Coroccohuayco Compañia Minera Antapaccay S.A. Cusco Copper PRE-FEASIBILITY 590
TBD La Granja Rio Tinto Minera Peru Limitada S.A.C. Cajamarca Copper CONCEPTUAL 5000
TBD Los Calatos Minera Hampton Peru S.A.C Moquegua Copper PRE-FEASIBILITY 655
TBD Pampa de Pongo Jinzhao Mining Peru S.A. Arequipa Iron PRE-FEASIBILITY 2344
TBD Rio Seco Copper Plant Procesadora Industrial Rio Seco S.A. Lima Copper FEASIBILITY 410
TBD Pukaqaqa Nexa Resources Peru. S.A.A. Huancavelica Copper PRE-FEASIBILITY 655
TBD Quechua Compañia Minera Quechua S.A. Cusco Copper PRE-FEASIBILITY 1290
TBD Inmaculada Replenishment Compañia Minera Ares S.A.C Ayacucho Gold FEASIBILITY 1319
TBD Raura Replenishment Compañia Minera Raura S.A. Huanuco Zinc FEASIBILITY 76
TBD Tantahuatay Replenishment Compañia Minera Coimolache S.A. Cajamarca Gold FEASIBILITY 194
TBD Rio Blanco Rio Blanco Copper S.A. Piura Copper FEASIBILITY 2500
TBD: To be defined
* The Ariana project owned by Ariana Operaciones Mineras S.A.C. is currently in a paralyzed construction stage [See sheet: Ariana].
** Year in which construction of all project components is completed
Developed by the Mining Promotion Department of the General Directorate of Mining Promotion and Sustainability.
PREVIOUS METHODOLOGY
Projects in the portfolio had to meet at least the following requirements
for inclusion:
UPDATED METHODOLOGY
For this new edition, a detailed analysis was carried out and some
requirements were adjusted as follows:
PROGRESS OF STAGES
The conceptual stage was added with the objective of identifying
projects that have preliminary economic studies and/or are developing
advanced exploration activities in order to define mineral resources.
Chart 02: Principal changes in the mining investment project portfolio 2023
1. Mining projects that started operations or left the portfolio are not considered in the summation for the number of projects
in this edition.
3.1. COVERAGE
The Mining Investment Project Portfolio 2023 is composed of projects
whose objectives include the execution of investments through the
construction of the necessary infrastructure in order to achieve the
operational start-up of mining activities such as exploitation and/or
beneficiation in accordance with current regulations. All the projects
are owned by private companies in the general regime stratum (large
and medium mining) and cover both metallic and non-metallic mineral
production.
Additionally, there are methodological criteria that have the purpose
of developing a portfolio of sustainable and feasible projects within an
established time horizon. Among these requirements are: a) the project
must have a Capex investment (in construction) equal to or greater
than US$ 70 million, b) the project must contemplate a tentative start-
up within the next twelve years and c) the project is at least at an
advanced exploration stage and has or is developing studies for its
start-up.
GREENFIELD PROJECTS
BROWNFIELD PROJECTS
• New: These include projects in current operations (brownfield),
but which contemplate a substantial change in the production
process, which implies the development and exploitation of a
new deposit.
• Expansion: These are projects that mainly seek to expand the
current processing capacity through the installation of new
components and/or technological improvements.
• Replenishment: Those projects that mainly seek to maintain the
current productive capacity through the development of new
exploitation areas, due to a drop in grades and/or depletion of
reserves in order to extend the useful life of the Mining Unit.
• Reuse: Projects whose main objective is the reuse of tailings
containing economically profitable minerals at present.
h^ΨϮϵϰϳŵŝůůŝŽŶ
ͻ ŽƌĂŶŝ
ͻDĂŐŝƐƚƌĂů
ͻZŽŵŝŶĂ
ͻŶƚĂŵŝŶĂZĞƉůĞŶŝƐŚŵĞŶƚ
h^ΨϯϵϳϯŵŝůůŝŽŶ
ͻĂĨƌĂŶĂů
ͻzĂŶĂĐŽĐŚĂ^ƵůĮĚĞƐ
4.2. INVESTMENTS BY
PROJECT LOCATION
BY REGION:
Regarding investments according to project location, these are located
in 18 regions nationwide, with the Cajamarca region standing out for
boasting the largest investment amount equivalent to US$ 18 494
million, a figure that represents 34.4% of the total investment in portfolio
with 6 projects. The project that stands out in this northern region for
its investment amount is La Granja (US$ 5000 million); on the other
hand, with respect to the nearest start of construction, Yanacocha
Sulfides stands out (US$ 2500 million), due to the fact that it plans to
start construction in 2024.
˟ʳˠ̇ ËȕŗȕNŷ
h^ΨϳϲŵŝůůŝŽŶ
ϭƉƌŽũĞĐƚ
ƻÝȕNJ ˤʳˤ̇
h^ΨϮϵϱϬŵŝůůŝŽŶ
ϮƉƌŽũĞĐƚƐ
˟ʳ˥̇ ƻǢNŷ
ĵōDɳrdžȕr ˠʳ˨̇ h^ΨϯϰϱŵŝůůŝŽŶ
ϮƉƌŽũĞĐƚƐ
h^ΨϭϬϰϯŵŝůůŝŽŶ
ϭƉƌŽũĞĐƚ
ŗNǢË ˤʳˣ̇
h^ΨϮϴϴϵŵŝůůŝŽŶ ˡʳˤ̇ ɳNȕNËŷ
ϱƉƌŽũĞĐƚƐ h^ΨϭϯϭϵŵŝůůŝŽŶ
ϭƉƌŽũĞĐƚ
BY MACROREGION:
Regarding investments according to macro-regions, the north stands
out for the largest investment, boasting an amount of US$ 23 972 million
and representing 44.6% of the overall investment in portfolio with 11
projects.
On the other hand, the southern and central macro-regions are in
second and third place respectively, together representing 55.0% of
participation, with a combined investment of US$ 29 529 million. It
should be noted that the southern macro-region includes 19 projects,
while the central macro-region has 16 projects, and the Huánuco region
is included for the first time.
Graph 04:
Investment by macro-region
^d
Ϭ͘ϰй
EKZd, ϭWƌŽũĞĐƚ
ϰϰ͘ϲй
ϭϭWƌŽũĞĐƚƐ
h^ΨϮϭϰ
ŵŝůůŝŽŶ
DKE^
h^ΨϮϯϵϳϮ
ŵŝůůŝŽŶ
:DZ
>DzYh
>>/Zd
W/hZ
EdZ ^Khd,
ϭϰ͘ϭй
ϭϲWƌŽũĞĐƚƐ
ϰϬ͘ϵй
ϭϵWƌŽũĞĐƚƐ
h^Ψϳϱϲϵ
ŵŝůůŝŽŶ
h^ΨϮϭϵϲϬ
ŵŝůůŝŽŶ
E^, WhZ/D
zh,K ZYh/W
,hEs>/ h^K
/ DKYh'h
:hE/E WhEK
>/D
W^K
,hEhK
ϭϯ͘ϲй ϭϵ͘ϳй
hE/d</E'KD ,/E
h^ΨϳϯϮϰŵŝůůŝŽŶ h^ΨϭϬϱϲϵŵŝůůŝŽŶ
ϲƉƌŽũĞĐƚƐ ϳƉƌŽũĞĐƚƐ
ϭϱ͘Ϯй
E Ϯ͘ϰй
h^ΨϴϭϳϲŵŝůůŝŽŶ
ϳƉƌŽũĞĐƚƐ :WE
ϭϰ͘ϲй ϰ͘ϰй h^ΨϭϮϵϬŵŝůůŝŽŶ
ϭƉƌŽũĞĐƚ
h͘^͘͘ ^t/dZ>E
h^ΨϳϴϰϬŵŝůůŝŽŶ h^ΨϮϯϰϰŵŝůůŝŽŶ
ϰƉƌŽũĞĐƚƐ ϯƉƌŽũĞĐƚƐ
ϭϲ͘ϱй Ϭ͘Ϯй
^Khd,<KZ
Dy/K h^ΨϭϭϳŵŝůůŝŽŶ
h^ΨϴϴϰϰŵŝůůŝŽŶ ϭƉƌŽũĞĐƚ
ϲƉƌŽũĞĐƚƐ
ϰ͘Ϯй
ϯ͘ϴй
WZh ϱ͘ϰй
h^ΨϮϮϳϰŵŝůůŝŽŶ Z/>
ϲƉƌŽũĞĐƚƐ h^ΨϮϬϯϴŵŝůůŝŽŶ h^dZ>/
ϱƉƌŽũĞĐƚƐ h^ΨϮϵϬϬŵŝůůŝŽŶ
ϭƉƌŽũĞĐƚ
Minerals Ltd. with the Cotabambas project (US$ 1486 million) and Teck
Resources Copper with the Zafranal project (US$ 1473 million). The latter
is expected to start construction in 2024.
With regard to investments from the United States, these reach an
investment of US$ 8176 million, reflecting a participation of 15.2% of
the total investment in the portfolio with 4 projects. It is worth noting
that 2 projects, Conga and Yanacocha Sulfides, belong entirely to
Newmont Goldcorp Corp. reflecting a combined investment of US$ 7300
million. The Bayovar Expansion project (US$ 450 million) belongs to the
majority investor The Mosaic Company, and the San Luis project (US$
90 million) belongs to SSR Mining Inc. with 100% participation.
Investments from the United Kingdom represent 13.6% of the total
investment portfolio, which are distributed in 6 projects, equivalent to
US$ 7,324 million. Of this group, Rio Tinto Plc. stands out with the La
Granja project (US$ 5000 million), Hochschild Plc. with the Inmaculada
Replenishment project (US$ 1319 million) and CD Capital Natural
Resources Fund III with Los Calatos (US$ 655 million). It is also important
to mention the investor Talingo Corporation with the largest
participation in the Santa Maria Expansion project (US$ 121 million),
which is in the construction stage and is expected to be commissioned
by 2023.
Australian investments represent 5.4% of the total investment portfolio
with US$ 2.9 billion and a single project. The project in question is Hie-
rro Apurimac, 100% owned by Strike Resources Limited.
Investments from Switzerland represent 4.4% of the total investment
portfolio with US$ 2344 million and 3 projects. Investors from this
country include Xstrata Glencore with the Antamina Replenishment
project, Glencore Plc. with Coroccohuayco Integration, and Volcan Com-
pañia Minera S.A.A. with the Romina project.
For its part, Peruvian investments represent 4.2% of the global
investment portfolio, with 6 projects and a combined investment amount
of US$ 2274 million. It is important to mention that 4 projects in the
portfolio (Rio Seco Copper Plant, San Gabriel, Trapiche, and Yumpag)
belong 100% to Grupo Buenaventura; while 1 project, Ayawilca, contains
a 19.3% participation of this same investor. The remaining project (Raura
Replenishment) has Brescia Group as the main investor with an overall
investment of US$ 76 million.
Finally, investments from Brazil (5 projects), Japan (1 project) and South
Korea (1 project) together represent a 6.4% share of total investments
with US$ 3444 million contained in 7 projects. The main investors in
each country are Hejoassu Administração S.A., Pan Pacific Copper Co.
Ltd. and Korea Zinc Company, respectively.
86
ϳϲй ŵŝůůŝŽŶ Ϯϰй
ƉƌŽũĞĐƚƐ
ϮϵWZK:d^ ϭϴWZK:d^
'ZE&/> ZKtE&/>
h^ΨϰϬϵϲϱ h^ΨϭϮϳϱϬ
ŵŝůůŝŽŶ ŵŝůůŝŽŶ
EtWZK:d^ yWE^/KEK&WZK:d^
ͻŶƟůůĂ ͻ>ŽƐŚĂŶĐĂƐ ͻĂLJŽǀĂƌdžƉĂŶƐŝŽŶ
ͻƌŝĂŶĂ ͻDĂŐŝƐƚƌĂů ͻƵĂũŽŶĞdžƉĂŶƐŝŽŶ
ͻLJĂǁŝůĐĂ ͻDŝĐŚŝƋƵŝůůĂLJ ͻ/ůŽdžƉĂŶƐŝŽŶ
ͻĂŹĂƌŝĂĐŽ ͻKůůĂĐŚĞĂ ͻWĂĐŚĂƉĂƋƵŝdžƉĂŶƐŝŽŶ
ͻĂŹŽŶ&ůŽƌŝĚĂ ͻWĂŵƉĂĚĞWŽŶŐŽ ͻ^ĂŶƚĂDĂƌŝĂdžƉĂŶƐŝŽŶ
ͻŽŶŐĂ ͻWƵŬĂƋĂƋĂ ͻ^ŚŽƵdžŝŶdžƉĂŶƐŝŽŶ
ͻŽƌĂŶŝ ͻYƵĞĐŚƵĂ ͻdŽƌŽŵŽĐŚŽdžƉĂŶƐŝŽŶ
ͻŽƚĂďĂŵďĂƐ ͻZŝŽůĂŶĐŽ
ͻŽŶ:ĂǀŝĞƌ ͻ^ĂŶ'ĂďƌŝĞů
ͻů'ĂůĞŶŽ ͻ^ĂŶ>ƵŝƐ WZK:d^K&ZW>E/^,DEd
ͻ,ĂƋƵŝƌĂ ͻ^ŚĂůŝƉĂLJĐŽ ͻŚĂůĐŽďĂŵďĂ^ƚĂŐĞ/
ͻ,ŝĞƌƌŽƉƵƌŝŵĂĐ ͻdŝĂDĂƌŝĂ ͻ/ŶƚĞŐƌĂĐŝŽŶŽƌŽĐĐŽŚƵĂLJĐŽ
ͻ,ŝůĂƌŝŽŶ ͻdƌĂƉŝĐŚĞ ͻŶƚĂŵŝŶĂZĞƉůĞŶŝƐŚŵĞŶƚ
ͻ>Ă'ƌĂŶũĂ ͻĂĨƌĂŶĂů ͻ/ŶŵĂĐƵůĂĚĂZĞƉůĞŶŝƐŚŵĞŶƚ
ͻ>ŽƐĂůĂƚŽƐ ͻZĂƵƌĂZĞƉůĞŶŝƐŚŵĞŶƚ
ͻdĂŶƚĂŚƵĂƚĂLJZĞƉůĞŶŝƐŚŵĞŶƚ
ͻZŽŵŝŶĂ
ͻzƵŵƉĂŐ
EtWZK:d^
ͻ>ĂƌĞŶĂ//
ͻZŝŽ^ĞĐŽŽƉƉĞƌWůĂŶƚ
ͻzĂŶĂĐŽĐŚĂ^ƵůĮĚĞƐ
d/>
KEWdh> WZͲ&^//>/dz &^//>/dz E'/EZ/E' KE^dZhd/KE
ƵĂũŽŶĞdžƉĂŶƐŝŽŶ
ŶƟůůĂ ĂLJŽǀĂƌdžƉĂŶƐŝŽŶ ŚĂůĐŽďĂŵďĂ^ƚĂŐĞ/ ^ĂŶƚĂDĂƌŝĂdžƉĂŶƐŝŽŶ
/ůŽdžƉĂŶƐŝŽŶ ĂŹĂƌŝĂĐŽ WĂĐŚĂƉĂƋƵŝdžƉĂŶƐŝŽŶ ŽƌĂŶŝ ^ŚŽƵdžŝŶdžƉĂŶƐŝŽŶ
LJĂǁŝůĐĂ ŽƚĂďĂŵďĂƐ ŽŶŐĂ dŝĂDĂƌŝĂ dŽƌŽŵŽĐŚŽdžƉĂŶƐŝŽŶ
ĂŹŽŶ&ůŽƌŝĚĂ ů'ĂůĞŶŽ DĂŐŝƐƚƌĂů zĂŶĂĐŽĐŚĂ^ƵůĮĚĞƐ ƌŝĂŶĂΎ
ŽŶ:ĂǀŝĞƌ ,ĂƋƵŝƌĂ ŶƚĂŵŝŶĂZĞƉůĞŶŝƐŚŵĞŶƚ ^ĂŶ'ĂďƌŝĞů
>ĂƌĞŶĂ// ,ŝĞƌƌŽƉƵƌŝŵĂĐ /ŶŵĂĐƵůĂĚĂZĞƉůĞŶŝƐŚŵĞŶƚ
>Ă'ƌĂŶũĂ ,ŝůĂƌŝŽŶ ZŝŽ^ĞĐŽŽƉƉĞƌWůĂŶƚ
DŝĐŚŝƋƵŝůůĂLJ /ŶƚĞŐƌĂĐŝŽŶŽƌŽĐĐŽŚƵĂLJĐŽ ZĂƵƌĂZĞƉůĞŶŝƐŚŵĞŶƚ
>ŽƐĂůĂƚŽƐ dĂŶƚĂŚƵĂƚĂLJZĞƉůĞŶŝƐŚŵĞŶƚ
>ŽƐŚĂŶĐĂƐ ZŝŽůĂŶĐŽ
KůůĂĐŚĞĂ ZŽŵŝŶĂ
WĂŵƉĂĚĞWŽŶŐŽ ^ĂŶ>ƵŝƐ
WƵŬĂƋĂƋĂ zƵŵƉĂŐ
YƵĞĐŚƵĂ ĂĨƌĂŶĂů
^ŚĂůŝƉĂLJĐŽ
SINGLE SOURCE
SURFACE WATER 16 20,232 37.70%
UNDERGROUND WATER 8 4,723 8.80%
SEAWATER 3 4,399 8.20%
MIXED SOURCE
SURFACE AND UNDERGROUND WATER 5 2,584 4.80%
SURFACE AND SEAWATER 1 450 0.80%
^hZ&tdZ
WĂĐŚĂƉĂƋƵŝdžƉĂŶƐŝŽŶ ŚĂůĐŽďĂŵďĂ^ƚĂŐĞ/ ŝĞƌƌŽƉƵƌŝŵĂĐ
, ĂƵƌĂZĞƉůĞŶŝƐŚŵĞŶƚ
Z
^ŚŽƵdžŝŶdžƉĂŶƐŝŽŶ ŽŶŐĂ zƵŵƉĂŐ ZŝŽůĂŶĐŽ
ŶƟůůĂ ŽƚĂďĂŵďĂƐ WƵŬĂƋĂƋĂ ^ĂŶ>ƵŝƐ
ĂŹĂƌŝĂĐŽ ,ĂƋƵŝƌĂ ŶƚĂŵŝŶĂZĞƉůĞŶŝƐŚŵĞŶƚ zĂŶĂĐŽĐŚĂ^ƵůĮĚĞƐ
hEZ'ZKhEtdZ
^ŝŶŐůĞƐŽƵƌĐĞ ͻ ƌŝĂŶĂ ͻ/ŶŵĂĐƵůĂĚĂZĞƉůĞŶŝƐŚŵĞŶƚ
ͻ/ŶƚĞŐƌĂĐŝſŶŽƌŽĐĐŽŚƵĂLJĐŽ ͻZŽŵŝŶĂ
ŽĨƐƵƉƉůLJ ͻDĂŐŝƐƚƌĂů ͻ^ĂŶ'ĂďƌŝĞů
ͻKůůĂĐŚĞĂ ͻĂĨƌĂŶĂů
^tdZ
ͻ>ŽƐĂůĂƚŽƐ
ͻWĂŵƉĂĚĞWŽŶŐŽ
ͻdşĂDĂƌşĂ
^hZ&tdZEhEZ'ZKhEtdZ
ͻ^ĂŶƚĂDĂƌŝĂdžƉĂŶƐŝŽŶ ͻŽƌĂŶŝ
ͻdŽƌŽŵŽĐŚŽdžƉĂŶƐŝŽŶ ͻdĂŶƚĂŚƵĂƚĂLJZĞƉůĞŶŝƐŚŵĞŶƚ
ͻĂŹŽŶ&ůŽƌŝĚĂ
DŝdžĞĚƐŽƵƌĐĞ
ŽĨƐƵƉƉůLJ
^hZ&tdZE^tdZ
ͻĂLJŽǀĂƌdžƉĂŶƐŝŽŶ
EŽŝŶĨŽƌŵĂƟŽŶ EKds/>>
ĂǀĂŝůĂďůĞŽŶ ͻƵĂũŽŶĞdžƉĂŶƐŝŽŶ ͻ>Ă'ƌĂŶũĂ ͻ>ŽƐŚĂŶĐĂƐ ͻ^ŚĂůŝƉĂLJĐŽ
ͻ/ůŽdžƉĂŶƐŝŽŶ ͻů'ĂůĞŶŽ ͻDŝĐŚŝƋƵŝůůĂLJ ͻdƌĂƉŝĐŚĞ
ƐŽƵƌĐĞŽĨƐƵƉƉůLJ ͻLJĂǁŝůĐĂ ͻ,ŝůĂƌŝŽŶ ͻZŝŽ^ĞĐŽŽƉƉĞƌWůĂŶƚ
ͻŽŶ:ĂǀŝĞƌ ͻ>ĂƌĞŶĂ// ͻYƵĞĐŚƵĂ
KWEW/dE
KWEW/d hEZ'ZKhE K^EKdWW>z
hEZ'ZKhE
ϰ ϳ
Ϯϰ ϭϮ
h^ΨϯϵϰϬϬ h^Ψϱϳϲϯ h^Ψϱϭϲϱ h^Ψϯϯϴϳ
ŵŝůůŝŽŶ ŵŝůůŝŽŶ ŵŝůůŝŽŶ ŵŝůůŝŽŶ
dŽƌŽŵŽĐŚŽdžƉĂŶƐŝŽŶ >Ă'ƌĂŶũĂ ƌŝĂŶĂ ,ĂƋƵŝƌĂ ĂLJŽǀĂƌdžƉĂŶƐŝŽŶ
ŶƟůůĂ >ŽƐŚĂŶĐĂƐ LJĂǁŝůĐĂ ZŽŵŝŶĂ ƵĂũŽŶĞdžƉĂŶƐŝŽŶ
ĂŹĂƌŝĂĐŽ DĂŐŝƐƚƌĂů ĂŹŽŶ&ůŽƌŝĚĂ zĂŶĂĐŽĐŚĂ^ƵůĮĚĞƐ /ůŽdžƉĂŶƐŝŽŶ
ŚĂůĐŽďĂŵďĂ^ƚĂŐĞ/ DŝĐŚŝƋƵŝůůĂLJ ,ŝůĂƌŝŽŶ >ŽƐĂůĂƚŽƐ WĂĐŚĂƉĂƋƵŝdžƉĂŶƐŝŽŶ
ŽŶŐĂ WƵŬĂƋĂƋĂ KůůĂĐŚĞĂ ^ĂŶƚĂDĂƌŝĂdžƉĂŶƐŝŽŶ
ŽƌĂŶŝ YƵĞĐŚƵĂ WĂŵƉĂĚĞWŽŶŐŽ ^ŚŽƵdžŝŶdžƉĂŶƐŝŽŶ
ŽƚĂďĂŵďĂƐ ŶƚĂŵŝŶĂ /ŶŵĂĐƵůĂĚĂZĞƉůĞŶŝƐŚŵĞŶƚ ZŝŽ^ĞĐŽŽƉƉĞƌWůĂŶƚ
ŽŶ:ĂǀŝĞƌ ZĞƉůĞŶŝƐŚŵĞŶƚ ZĂƵƌĂZĞƉůĞŶŝƐŚŵĞŶƚ
ů'ĂůĞŶŽ dĂŶƚĂŚƵĂƚĂLJ ^ĂŶ'ĂďƌŝĞů
,ŝĞƌƌŽƉƵƌŝŵĂĐ ZĞƉůĞŶŝƐŚŵĞŶƚ ^ĂŶ>ƵŝƐ
/ŶƚĞŐƌĂĐŝŽŶŽƌŽĐĐŽŚƵĂLJĐŽ ZŝŽůĂŶĐŽ ^ŚĂůŝƉĂLJĐŽ
>ĂƌĞŶĂ// dŝĂDĂƌŝĂ zƵŵƉĂŐ
dƌĂƉŝĐŚĞ
ĂĨƌĂŶĂů
As for gold projects, the portfolio contains 6 gold projects with a total
investment of US$ 6993 million, which represents 13.0% of the global
investment. The projects that stand out are: San Gabriel (US$ 470 million)
with an expected production of 180,000 fine ounces, and Santa Maria
Expansion (US$ 121 million), with an additional 36 000 fine ounces of
gold. It should be noted that both projects are in the construction stage.
There are 3 ferrous projects in the portfolio, reflecting a combined
investment of US$ 5384 million, which represents 10.0% of the overall
budget in the portfolio. This group is composed of the Hierro Apurimac
project (US$ 2900 million) with an estimated production of 20 million
MTF per year, Pampa de Pongo (US$ 2344 million) with an estimated
production of 23.4 million MTF, and Shouxin Expansion (US$ 140 million)
with a projected production of 400 000 additional MTF of iron per year,
the latter is in the construction stage.
WKZd&K>/KK&D/E/E'/Es^dDEdWZK:d^
ĂLJŽǀĂƌ
džƉĂŶƐŝŽŶ
ŽƌĂŶŝ͕^ĂŶ>ƵŝƐĂŶĚzƵŵƉĂŐ
WĂĐŚĂƉĂƋƵŝdžƉĂŶƐŝŽŶ͕LJĂǁŝůĐĂ͕ĂŹŽŶ&ůŽƌŝĚĂ͕,ŝůĂƌŝŽŶ͕
ZĂƵƌĂZĞƉůĞŶŝƐŚŵĞŶƚ͕ZŽŵŝŶĂĂŶĚ^ŚĂůŝƉĂLJĐŽ͘
^ŚŽƵdžŝŶdžƉĂŶƐŝŽŶ͕,ŝĞƌƌŽƉƵƌŝŵĂĐĂŶĚWĂŵƉĂĚĞWŽŶŐŽ͘
^ĂŶƚĂDĂƌŝĂdžƉĂŶƐŝŽŶ͕ŽŶŐĂ͕KůůĂĐŚĞĂ͕/ŶŵĂĐƵůĂĚĂZĞƉůĞŶŝƐŚŵĞŶƚ͕dĂŶƚĂŚƵĂƚĂLJZĞƉůĞŶŝƐŚŵĞŶƚĂŶĚ^ĂŶ'ĂďƌŝĞů͘
ƵĂũŽŶĞdžƉĂŶƐŝŽŶ͕/ůŽdžƉĂŶƐŝŽŶ͕dŽƌŽŵŽĐŚŽdžƉĂŶƐŝŽŶ͕ŶƟůůĂ͕ƌŝĂŶĂ͕ĂŹĂƌŝĂĐŽ͕ŚĂůĐŽďĂŵďĂ^ƚĂŐĞ/͕ŽƚĂďĂŵďĂƐ͕ŽŶ:ĂǀŝĞƌ͕
ů'ĂůĞŶŽ͕,ĂƋƵŝƌĂ͕/ŶƚĞŐƌĂĐŝŽŶŽƌŽĐĐŽŚƵĂLJĐŽ͕>ĂƌĞŶĂ//͕>Ă'ƌĂŶũĂ͕>ŽƐĂůĂƚŽƐ͕>ŽƐŚĂŶĐĂƐ͕DĂŐŝƐƚƌĂů͕DŝĐŚŝƋƵŝůůĂLJ͕
ŶƚĂŵŝŶĂZĞƉůĞŶŝƐŚŵĞŶƚ͕ZŝŽ^ĞĐŽŽƉƉĞƌWůĂŶƚ͕WƵŬĂƋĂƋĂ͕YƵĞĐŚƵĂ͕ZŝŽůĂŶĐŽ͕dŝĂDĂƌŝĂ͕dƌĂƉŝĐŚĞ͕zĂŶĂĐŽĐŚĂ^ƵůĮĚĞƐĂŶĚĂĨƌĂŶĂů͘
h^Ψϰϲϲϱϳ
ŵŝůůŝŽŶ
h^ΨϲϯϬϰ
ŵŝůůŝŽŶ
h^Ψϳϱϯ
ŵŝůůŝŽŶ
At the end of 2022, it is estimated that US$ 147 million will be invested,
which represents 2.3% of the total investments to be made in the 2022
- 2026 period. It is worth mentioning that this amount does not include
the investment executed in Quellaveco, since the project started up at
the end of the third quarter of this year, so it is not included in the
current portfolio. However, the amount includes the estimated
investment for the San Gabriel project, which started construction in
the first quarter of 2022, in addition to what has been executed for the
Toromocho Expansion, Santa Maria Expansion and Shouxin Expansion.
Thus, the current estimated amount shows a contraction of 90.5%
compared to the investment executed in 2021 (US$ 1555 million) due
to the fact that 6 of the 7 projects that had planned to start construction
in 2022 did not do so due to various factors such as: administrative
issues (delay in the approval terms of their different studies), financing,
social issues, among others.
Lastly, for the year 2026 an investment of US$ 1411 million is projected,
showing a reduction of 22.2% compared to the estimate for 2025.
However, during this period the Corani and Magistral projects are
expected to come on stream, the latter contributing an estimated annual
production of 55,000 fine metric tons of copper over an 11-year life.
h^ΨϭϵϮϴ h^Ψϭϴϭϯ
ŵŝůůŝŽŶ
ŵŝůůŝŽŶ h^Ψϭϰϭϭ
h^ΨϭϬϬϱ ŵŝůůŝŽŶ
ŵŝůůŝŽŶ
h^Ψϭϰϳ
ŵŝůůŝŽŶ
5.3. PROJECTION OF
INVESTMENTS AFTER 2026
Regarding investments after 2026, the estimated projection amounts
to US$ 46 657 million, which represents 86.9% of the global amount of
investments.
WŽƐƐŝďůĞƉƌŽũĞĐƚƐ
WƌŽďĂďůĞƉƌŽũĞĐƚƐ
ĂƐĞĐĂƐĞƉƌŽĚƵĐƟŽŶĐĂƉĂĐŝƚLJ
WƌŝŵĂƌLJĚĞŵĂŶĚ
Graph 13: Mining projects under construction and possible start-up in 2023
ǻŷNJŷōŷNËŷrɭƻŗǢÝŷŗ
dŽƚĂů/ŶǀĞƐƚŵĞŶƚ͗h^ΨϭϯϱϱŵŝůůŝŽŶ
:ŽďƉŽƐŝƟŽŶƐĞdžƉĞĐƚĞĚ͗
^ƚĂŐĞ/͗
ϯϮϬϬŝŶĐŽŶƐƚƌƵĐƟŽŶ
ϭϱϬϬŝŶŽƉĞƌĂƟŽŶ
ǢŗǻōNJÝrɭƻŗǢÝŷŗ ^ƚĂŐĞ//͗
dŽƚĂů/ŶǀĞƐƚŵĞŶƚ͗h^ΨϭϮϭŵŝůůŝŽŶ ϮϱϵŝŶĐŽŶƐƚƌƵĐƟŽŶ
:ŽďƉŽƐŝƟŽŶƐĞdžƉĞĐƚĞĚ͗ ϰϭŝŶŽƉĞƌĂƟŽŶ
ϭϬϯŝŶĐŽŶƐƚƌƵĐƟŽŶ
ϭϭϳϯŝŶŽƉĞƌĂƟŽŶ
ōµÝǢǻNJĵ
dŽƚĂů/ŶǀĞƐƚŵĞŶƚ͗h^ΨϰϵϯŵŝůůŝŽŶ
:ŽďƉŽƐŝƟŽŶƐĞdžƉĞĐƚĞĚ͗
ϭϴϴϯŝŶĐŽŶƐƚƌƵĐƟŽŶ
ϵϭϰŝŶŽƉĞƌĂƟŽŶ
ŗǻōÝŗ
NJrƻĵrŗÝǢËōrŗǻ NŷNJŗÝ
dŽƚĂů/ŶǀĞƐƚŵĞŶƚ͗h^ΨϭϲϬϰŵŝůůŝŽŶ dŽƚĂů/ŶǀĞƐƚŵĞŶƚ͗h^ΨϳϬϬŵŝůůŝŽŶ
:ŽďƉŽƐŝƟŽŶƐĞdžƉĞĐƚĞĚ͗ :ŽďƉŽƐŝƟŽŶƐĞdžƉĞĐƚĞĚ͗
ϮϱϬϬŝŶĐŽŶƐƚƌƵĐƟŽŶ ϭϱϬϬŝŶĐŽŶƐƚƌƵĐƟŽŶ
ϮϰϬϰŝŶŽƉĞƌĂƟŽŶ ϰϰϬŝŶŽƉĞƌĂƟŽŶ
NJŷōÝŗ
dŽƚĂů/ŶǀĞƐƚŵĞŶƚ͗h^ΨϭϱϬŵŝůůŝŽŶ
:ŽďƉŽƐŝƟŽŶƐĞdžƉĞĐƚĞĚ͗ džȕrĵĵərNŷ
ϯϳϴŝŶĐŽŶƐƚƌƵĐƟŽŶ dŽƚĂů/ŶǀĞƐƚŵĞŶƚ͗h^ΨϱϯϬϬŵŝůůŝŽŶ
ϰϱϬŝŶŽƉĞƌĂƟŽŶ :ŽďƉŽƐŝƟŽŶƐĞdžƉĞĐƚĞĚ͗
ϭϱϬϬϬŝŶĐŽŶƐƚƌƵĐƟŽŶ
ϮϱϬϬŝŶŽƉĞƌĂƟŽŶ
ǢËŷȕɭÝŗrɭƻŗǢÝŷŗ ǢŗµDNJÝrĵ
dŽƚĂůŝŶǀĞƐƚŵĞŶƚ͗h^ΨϭϰϬŵŝůůŝŽŶ dŽƚĂů/ŶǀĞƐƚŵĞŶƚh^ΨϰϳϬŵŝůůŝŽŶ
:ŽďƉŽƐŝƟŽŶĞdžƉĞĐƚĞĚ͗ :ŽďƉŽƐŝƟŽŶƐĞdžƉĞĐƚĞĚ͗
ϭϬϮϱŝŶĐŽŶƐƚƌƵĐƟŽŶ ϮϬϬϬŝŶĐŽŶƐƚƌƵĐƟŽŶ
ϭϴϰŝŶŽƉĞƌĂƟŽŶ ϱϬϬŝŶŽƉĞƌĂƟŽŶ
6.1. ESTIMATED
MINING PRODUCTION
The start-up of the 8 projects in the portfolio, among which copper and
gold are the main products, added to the expected copper production of
Quellaveco, will generate an increase in national production, favoring Peru's
position in the world ranking, as well as the improvement of the national
Gross Domestic Product (GDP).
By 2023, the positive evolution of mining in Peru would be led by the increase
in copper production, especially because it will be the first full year of
commercial operation of Quellaveco, which will produce 300 000 fine metric
tons (FMT) of copper per year.
In this sense, based on 2021 copper and gold production, the start of
operations of the 8 projects would increase domestic copper production by
13.0% and domestic gold production by 6.3%.
PRODUCTION
2019 2021 2026 VAR%
42 Bayovar Expansion
43 Cuajone Expansion
44 Ilo Expansion
45 Pachapaqui Expansion
46 Santa Maria Expansion
47 Shouxin Expansion
48 Toromocho Expansion
49 Antilla
50 Ariana
51 Ayawilca
52 Cañariaco
53 Cañon Florida
54 Chalcobamba Phase I
55 Conga
56 Corani
57 Cotabambas
58 Don Javier
59 Galeno
60 Haquira
61 Hierro Apurimac
62 Hilarion
63 Integration Coroccohuayco
64 La Arena II
65 La Granja
66 Los Calatos
67 Los Chancas
68 Magistral
69 Michiquillay
70 Ollachea
71 Pampa de Pongo
72 Rio Seco Copper Plant
73 Pukaqaqa
74 Quechua
75 Antamina Replenishment
76 Inmaculada Replenishment
77 Raura Replenishment
78 Tantahuatay Replenishment
79 Rio Blanco
80 Romina
81 San Gabriel
82 San Luis
83 Shalipayco
84 Tia Maria
85 Trapiche
86 Yanacocha Sulfides
87 Yumpag
88 Zafranal
Region Piura
Province Sechura
District Sechura
Project is located in the north of Peru, 1000 km from Lima city, 110 km south from Piura and 30 km from
the Pacific Ocean
Bayovar is one of the largest phosphate deposits in the world, the project area contains phosphate rocks, diatomites, brines, and other minerals. The Bayovar mine is currently in
operation, which began in 2010. The project consists of the expansion of the Bayovar I and Bayovar II Concentrator Plant from 54,089 to 81,079 tpd through the implementation
of a new line 3 and other components, as well as areas within the mining unit.
The approval of the First Modification of the Detailed Environmental Impact Assessment (1st MEIA-d) of the Bayovar Phosphates project is registered by R.D. No. 070-2013-
MEM/AAM dated March 7, 2013.
Without registration.
Resolution No. 384-2013-MEM-DGM/V approved the modification project and authorized the construction of 31 additional facilities at the Bayovar I Plant, 12 additional facilities
at the Bayovar II Plant, as well as storage and protection structures to increase the capacity of the "Bayovar I and Bayovar II" beneficiation concession to 81,079 metric tons per
day.
1 Compañia Minera Miski Mayo: Shareholders - http://www.miskimayo.com/Who_We_Are/accionistas.htm. Consultation date: December 18, 2022.
2 Compañia Minera Miski Mayo: Request for modification of "Bayovar I and Bayovar II" Beneficiation Concession. Approved in September 2013.
3 Compañia Minera Miski Mayo: Third Technical Supporting Report of the Second Modification of the Detailed Environmental Impact Study of the Bayovar Phosphate Mine. Approved in November 2021.
Cuajone Expansion
Southern Peru Copper Corporation, Peru Branch
Operator Investor4 100%: Grupo Mexico S.A.B. de C.V. (Mexico)
Office
Region Moquegua
District Torata
Plant capacity6 120 000 tons per day Estimated annual production Not available
The owner plans to expand the capacity of the Cuajone mining unit's concentrator plant to 120 thousand tons per day. The company will present the expansion project to the
board of directors of the head office in 2023.
Without registration.
Without registration.
Without registration.
4 Standard and Poor's (S&P Global): Southern Peru Copper Corporation, Peru Branch Office - Ownership Information [Market Intelligence from the Official Website]. Consultation date: December 13, 2022.
5 El Comercio: “Thinking about an expansion of Cuajone in this situation does not make much sense.” [Web publication]. April 2022.
6 El Comercio: "Southern awaits green light for Cuajone expansion". [Web publication]. January 2022.
Ilo Expansion
Southern Peru Copper Corporation, Peru Branch
Operator Investor7 100%: Grupo Mexico S.A.B. de C.V. (Mexico)
Office
Region Moquegua
Province Ilo
On August 20, 2022, the owner submitted to SENACE, the request for approval of the Citizen Participation Plan corresponding to the "Modification of the Detailed Environmental
Impact Study of the Ilo mining unit".
Without registration.
Without registration.
7 Standard and Poor's (S&P Global): Southern Peru Copper Corporation, Peru Branch Office - Ownership Information [Market Intelligence from the Official Website]. Consultation date: December 13.
8 Gestion: "Southern Peru moves forward with studies for new smelter in Ilo" [Web publication]. May 2022. / Grupo Mexico: "3Q22 RESULTS" [Corporate web presentation]. October 2022.
9 Grupo Mexico: "3Q22 RESULTS" [Corporate web presentation]. October 2022.
10 Southern Peru Copper Corporation, Peru Branch Office: Citizen Participation Plan of the MEIA Ilo. August 2022.
Pachapaqui Expansion
Operator ICM Pachapaqui S.A.C. Investor11 100%: Korea Zinc Company (South Korea)
Region12 Ancash
Province12 Bolognesi
District12 Aquia
Plant capacity12 Expansion from 800 to 3300 tons per day Estimated annual production Not available
The project has a Modification to its Detailed Environmental Impact Assessment (MEIA-d) for exploitation activities, approved by Resolution No. 023-2017-SENACE-JEF-DEAR on
December 1, 2017.
Without registration.
Without registration.
11Standard and Poor’s (S&P Global): Pachapaqui – Ownership Information [Market Intelligence from the official Web site]. Consultation date October 21, 2022.
12ICM Pachapaqui: Modification of the Detailed Environmental Impact Assessment (EIA-d), of the Expansion Project to 3300 tons per day UM Pachapaqui. Approved by Resolution No. 023-2017-SENACE-JEF/DEAR,
on December 01, 2017.
Santa Maria Expansion
18.50%: Talingo Corporation (United Kingdom);
Operator Compañia Minera Poderosa S.A.
16.05%: Arias Vargas Victoria Isabel (Peru);
15.22%: Arias Vargas de Sologuren (Peru);
13.96%: Cori Apu SAC (Peru);
Investor13
10.46%: South America Mining Investment (United Kingdom);
9.63%: Xelor Shipping Limited (United Kingdom);
9.63%: Zulema Invest Limited (United Kingdom);
6.55%: Common stock
Region La Libertad
Province Pataz
District Pataz
The project is located in the Hualanga‐Francés ravine basin between 1200 and 4350 m.a.s.l.
Water source15 Surface water and underground water Life of mine15 22 years
Plant capacity15 Expansion from 600 to 1000 tons per day Estimated annual production 36,000 fine ounces of gold (additional)
The project has the Modification of its Detailed Environmental Impact Assessment (MEIA-d) for exploitation activities, approved by Resolution No. 011-2017-SENACE-JEF/DEAR
on November 24, 2017. Furthermore, on November 19, 2020, Resolution No. 0141-2020-SENACE-PE/DEAR approved the specific terms of reference for the Second Modification
of the Integrated Environmental Impact Assessment of the Santa Maria Production Unit. In addition, by means of Resolution No. 012-2022-SENACE-PE/DEAR, the Second Technical
Supporting Report of the Modification to its Detailed Environmental Impact Assessment (2nd ITS of the MEIA-d) of the project was approved on January 18, 2022.
Without registration.
The authorization to expand the capacity of the "Santa Maria I" mill from 600 TM/day to 1000 TM/day and to operate 26 additional pieces of Stage 1 equipment was authorized
by Resolution No. 0591-2019-MINEM-DGM/V on December 5, 2019.
13 Compañia Minera Poderosa S.A.: "Sustainability Report 2021" (Sustainability Report 2021).
14 Compañia Minera Poderosa S.A.: “Santa Maria Project” [Corporate Presentation]. October 08, 2021.
15 Compañia Minera Poderosa S.A.: Modification of the Environmental Impact Assessment (EIA) for the expansion of the Santa Maria I operation and processing plant from 600 to 1000 tons per day (tpd). Approved
Region Ica
Province Nazca
District Marcona
The project has a Modification to its Detailed Environmental Impact Assessment (MEIA-d) for exploitation activities, approved by Resolution No. 010-2020-SENACE-PE/DEAR on
January 16, 2020.
Without registration.
On October 23, 2020, Resolution No. 292-2020-MEM/DGM/V approved the first stage of the project to modify the "Planta Concentradora Polimetalica MSP" (Polymetallic
Concentrator Plant MSP) beneficiation concession to increase its installed capacity to 48,484.84 tons per day, without increasing the area, and authorized the construction of civil
works and installation of equipment for this first stage of the project. On July 26, 2022, Resolution No. 291-2022-MINEM-DGM/V approved the second stage of the project,
including the installation of the final tailings transport system from the processing plant to DR Choclon 2 and the expansion of the area for the respective beneficiation concession;
and authorized the construction of civil works and installation of equipment corresponding to the second stage. On November 7, 2022, Minera Shouxin Peru S.A. announced the
completion of the construction of the project and requested the operating license, which is currently under evaluation.
16 Wood Mackenzie: “Shouxin Tailing copper mine project” [Asset report]. February 2021.
17 Minera Shouxin Peru S.A.: Modification of the Detailed Environmental Impact Assessment [Executive Summary]. November 2019.
18 Minera Shouxin Peru S.A.: Mining Plan Schedule. Consultation date: October 18, 2021.
19 Minera Shouxin Peru S.A.: Application for Modification of Concession and Beneficiary Authorization. January 2020.
20 Official Website of the Ministry of Energy and Mines [Intranet] - Monthly Statistical Statement (ESTAMIN): " Estimation according to the current production reported by Minera Shouxin Peru S.A. in its Monthly
Statistical Statement and the Modification of the Detailed Environmental Impact Assessment (MEIA-d) approved on January 16, 2020".
Toromocho Expansion
100%: Aluminum Corporation of China Overseas Holdings
Operator Minera Chinalco Peru S.A. Investor21
Limited (China)
Region Junin
Province Yauli
District Morococha
Stage I: 3200
Jobs in construction24 Type of exploitation24 Open pit
Stage II: 1500
Stage I: 259
Jobs in operations24 Ore Resources/Reserves Not applicable
Stage II: 41
Water source24 Surface water and underground water Life of mine24 25 years
The project has a Detailed Environmental Impact Assessment (EIA-d) for exploitation activities, approved by Resolution No. 411-2010-MEM/AAM on December 14, 2010.
Furthermore, considering the development of the project by stages, on December 29, 2015 the Second Technical Supporting Report of the Detailed Environmental Impact
Assessment (2nd ITS of the EIA-d) was approved by Resolution No. 504-2015-MEM-DGAAM, which includes Stage I of the project. Regarding the development of Stage II, on June
3, 2021 the "Modification of the Detailed Environmental Impact Study (MEIA-d) for the Toromocho M.U. Expansion Project to 170,000 tons per day (tpd)" was approved. On
September 22, 2022, the owner submitted to SENACE the First ITS of the MEIA-d (1st ITS of the MEIA-d) of the Toromocho mining unit.
Without registration.
On January 31, 2017, the Mining Technical Report for the project "Optimization for Expansion of the Toromocho Concentrator Plant of Minera Chinalco Peru S.A., where is
considered the expansion of installed capacity from 117 200 tons per day to 140 640 tons per day" without expansion of area, due to the incorporation of new components. On
July 27, 2022, Minera Chinalco Peru S.A. submitted the application for the modification of the "Toromocho Project" beneficiation concession to increase the installed capacity to
170,000 tons per day, taking into consideration the start of operations in the year 2024.
21 Standard and Poor’s (S&P Global): Toromocho – Ownership Information [Market Intelligence from the Official Website]. Consultation date: October 12, 2022.
22 Tv Peru (canal #7): “Head of State announces expansion of Toromocho project with investment of US$ 1355 million". [Broadcast] October 01, 2018.
23 Minera Chinalco Peru S.A.: “Modification of the Beneficiation Concession of the Toromocho Mill Expansion Project to 170,000 tpd". July 2022.
24 Minera Chinalco Peru S.A.: “Modification of the Detailed Environmental Impact Assessment for the Toromocho unit expansion project to 170,000 tpd". Approved on June 03, 2021.
Antilla
90%: Heeney Capital Acquisition Company Inc. (Canada);
Operator Panoro Apurimac S.A. Investor25
10%: Panoro Minerals Ltd. (Canada)
Region Apurimac
Province Antabamba
District Sabaino
Project is located at 3400 to 4100 m.a.s.l., approximately 150 km southwest from Cusco and 500
kilometers southeast from Lima.
Jobs in operations To be defined Ore reserves26 291.8 Mt @ 0.34% Cu, 0.01% Mo - (Indicated)
The project has a Technical Report of Resources Estimation on December 16, 2013. Additionally, the project has a Preliminary Economic Assessment (PEA) optimized as of
June 11, 2018. On December 6, 2021, Panoro Minerals Ltd. announced the closing of the sale of the project to Heeney Capital Acquisition Company Inc. (HCAC), a mineral
exploration and development company. Upon closing of the transaction, Panoro received the first scheduled prepayment of $10 million CA.
The project does not yet have a Detailed Environmental Impact Assessment (EIA-d) for exploitation activities.
Without registration.
Without registration.
25 Standard and Poor’s (S&P Global): Antilla – Ownership Information [Market Intelligence from the official Web site]. Consultation date October 12, 2022.
26 Panoro Minerals LTD.: "Corporate Presentation - September 2021".
27 Panoro Minerals LTD.: “Technical report on the PEA for the Antilla Copper Project heap leach and sx/ew operation” [Technical report]. June 11, 2018.
Ariana
Operator Ariana Operaciones Mineras S.A.C. Investor28 100%: Southern Peaks Mining LP. (United Kingdom)
Region Junin
Province Yauli
District Marcapomacocha
Project in at the west side of La Viuda Western Mountain Range in the central Andes
of Peru, at 4700 m.a.s.l.
Jobs in operations30 800 Ore reserves31 6.2 Mt @ 1.14% Cu, 18.04 g/t Ag, 0.84 g/t Au, 1.79% Zn
The project began its construction stage in 2018. However, on April 25, 2019, a citizen's group filed an action of protection before the Sixth Constitutional Court of the Superior
Court of Justice of Lima, demanding the definitive halt of the project due to the alleged threat of contamination of water sources. On August 27, 2020, representatives of Ariana
Mining attended the second hearing of the appeal process, where the suspension of the mining project was evaluated. To date, no decision has been issued.
The project has a Detailed Environmental Impact Assessment (EIA-d) approved by Resolution No. 127-2016-MEM/DGAAM on April 29, 2016. Furthermore, on March 4, 2020, Ariana
Operaciones Mineras S.A.C. obtained the approval of the Second Technical Supporting Report (2nd ITS) of the project, through Resolution R.D. No. 0041-2020-SENACE-PE/DEAR.
It is recorded that the project has a Mining Plan approved by Resolution No. 0137-2018-MEM-DGM on May 31, 2018.
It is recorded the approval of the Beneficiation Concession project file approved for a plant capacity of 2000 MT/day and an authorization for the construction of the Metallurgical
Process Plant, among other components, by Resolution No. 0602-2018-MEM-FGM/V on July 10, 2018.
28 Southern Peaks Mining: "Ariana" [Official Web site] - https://southernpeaksmining.com/ariana/. Consultation date: December 18, 2022.
29 Ariana Operaciones Mineras S.A.C: Detailed Environmental Impact Assessment. Approved on April 29, 2016.
30 College of Engineers of Peru - Mining Engineering Tuesday Conference: "Ariana Project and its commitment to the environment" [Corporate Presentation of Ariana Operaciones Mineras S.A.C]. November 10,
2020.
31 Ariana Operaciones Mineras S.A.C.: Detailed Mining Plan. Approved May 31, 2018.
32 Ariana Operaciones Mineras S.A.C.: Second Technical Report of the Ariana mining unit. Obtained conformity through Resolution No. 0041-2020-SENACE-PE/DEAR on March 04, 2020.
Ayawilca
19.3%: Compañia de Minas Buenaventura S.A.A. (Peru);
Operator Tinka Resources S.A.C.
18.8%: Sentient Group Ltd. (United Kingdom);
Investor33
18.2%: Hejoassu Administração S.A. (Brazil);
43.7%: Other shareholders
Region Pasco
Jobs in operations To be defined Ore reserves36 19.0 Mt @ 7.2% Zn, 0.2% Pb, 16.8 g/t Ag - (Indicated)
Estimated annual
Plant capacity33 8500 tons per day 155 000 FMT of zinc
production33
As part of the exploration work, on November 21, 2022, Tinka Resources reported the results of its 2022 drilling program to expand the measured and indicated zinc mineral
resource by press release.
The project does not yet have a Detailed Environmental Impact Assessment (EIA-d) for exploitation activities. However, the project has the Modification of the Semi-Detailed
Environmental Impact Study (1st MEIA-sd) submitted on July 27, 2021, which is currently under evaluation.
Without registration.
Without registration.
33 Tinka Resources Limited: "Advancing Ayawilca towards development” [Corporate Presentation]. August 2022.
34 Tinka Resources Limited: "Ayawilca Polymetallic Project Central Peru NI 43‐101 Technical Report on Updated Preliminary Economic Assessment". November 2021.
35 Tinka Resources Limited: "Tinka Reports updated PEA for Ayawilca project: Highlights potential to become top - 10 global zinc producer” [Technical Report]. October 14, 2021.
36 Tinka Resources Limited: "Tinka drills 6 meters grading 19% zinc at Ayawilca, expands tin zone” [Press Release]. October 11, 2022.
Cañariaco
Operator Cañariaco Copper Peru S.A. Investor37 100%: Candente Copper Corp. (Canada)
Region Lambayeque
Province Ferreñafe
District Cañaris
Cañariaco is a potential copper project that includes the Cañariaco north deposit, the Cañariaco South deposit and the Quebrada Verde prospect. On February 08, 2022, the "NI
43-101 Technical Report on Preliminary Economic Assessment" was presented which optimizes different aspects of the project. The company is currently arranging working capital
financing in order to continue advancing the Cañariaco project, including community relations and exploration authorization, which are targets for 2023.
Without registration.
Without registration.
Without registration.
37 Standard and Poor's (S&P Global): Cañariaco - Ownership Information [Market Intelligence from the Official Website]. Consultation date: October 19, 2022.
38 Candente Copper Corp.: “NI 43-101 Technical Report on Preliminary Economic Assessment”. Published on February 8, 2022.
39 Candente Copper Corp.: “Cañariaco Copper with ESG and Valor C”. [Corporate Presentation]. September 2022.
Cañon Florida
70%: Hejoassu Administração S.A. (Brazil);
Operator Nexa Resources Peru S.A.A. Investor40
30%: Solitario Zinc Corp. (U.S.A.)
Region Amazonas
Province Bongara
Jobs in operations To be defined Ore reserves42 2.4 Mt @ 10.6% Zn, 1.3% Pb, 15.0 g/t Ag - (M&I)
Water source41 Surface water and underground water Life of mine44 12.5 years
During 2022, the company mentions that work continued on the opening and maintenance of accesses, compliance with maintenance requirements and the obtaining of new
environmental permits necessary to enable new exploratory drilling programs, scheduled to begin in 2023.
The project does not yet have a Detailed Environmental Impact Assessment (EIA-d) for exploitation activities. However, the project has the Fifth Modification of the Semi-Detailed
Environmental Impact Study (5th MEIA-sd) for exploration activities, submitted on August 31, 2022, and is currently under evaluation.
Without registration.
Without registration.
40 Standard and Poor's (S&P Global): Cañon Florida - Ownership Information [Market Intelligence from the Official Website]. Consultation date: October 20, 2022.
41 Nexa Resources S.A.: “Technical Report Preliminary Economic Assessment Florida Canyon Zinc Project”. August 02, 2017.
42 Nexa Resources Peru S.A.A.: " Annual Report 2021". Mars 29, 2022.
43 Nexa Resources S.A.: “Earnings Release - 1Q22”. Published on April 25, 2022.
44 Solitario Zinc Corp.: "NI 43-101 Technical Report for Its Florida Canyon Zinc Project Detailing a Significant Increase in Mineral Resources". April 07, 2021.
Chalcobamba Stage I
62.5%: MMG limited (China);
Operator Minera Las Bambas S.A.
Investor45 22.5%: Guoxin International Investment Co. Ltd. (China);
15.0%: Citic Metal Company Limited (China)
Region Apurimac
Project is located between the basins of Vilcabamba and Santo Tomás rivers, at,
approximately 3800 to 4660 m.a.s.l.
Jobs in operations48 No extra workforce required Ore reserves49 176.4 Mt @ 0.67% Cu, 134.96 ppm Mo, 2.50 g/t Ag
At the Las Bambas mining unit, exploitation activities are currently being carried out at the Ferrobamba ore deposit and subsequently exploitation activities will be carried out at
the Chalcobamba and Sulfobamba deposits, with the objective of maintaining production levels. The Chalcobamba pit will be developed in two stages. For this first stage, the
exploitation of the south and central sector of the Chalcobamba pit is considered.
The project has the Third Modification of the Detailed Environmental Impact Assessment (3rd MEIA-d) for exploitation activities, approved by Resolution No. 016-2018-SENACE-
PE-DEAR on October 5, 2018. Furthermore, on October 16, 2020, the Second Technical Supporting Report of the Third Modification of the Detailed Environmental Impact
Assessment (2nd ITS of the 3rd MEIA-d) was approved by Resolution No. 126-2020-SENACE-PE/DEAR. Subsequently, on February 18, 2022 the Third Technical Supporting Report
of the Third Modification of the Detailed Environmental Impact Study (3rd ITS of the 3rd MEIA-d) was approved by Resolution No. 00033-2022-SENACE-PE/DEAR. It is worth
mentioning that on September 16, 2022 the Fourth Technical Report of the Third Modification of the Detailed Environmental Impact Assessment (4th ITS of the 3rd MEIA-d) was
approved by Resolution No. 00135-2022-SENACE-PE/DEAR.
A modification of the authorization to start exploitation activities is registered, which includes the engineering design for the start of exploitation activities of the "Chalcobamba"
project, including the Chalcobamba Pit - Stage 1 and the Chalcobamba Deposit - Stage 1 in the Las Bambas mining unit (2019).
Without registration.
45 Minera Las Bambas S.A.: “2021 Annual Report”. April 26, 2022.
46 Minera Las Bambas S.A.: “Submission of the mining titleholder to the Ministry of Energy and Mines (MINEM))”. September, 2022.
47 Minera Las Bambas S.A.: "Second quarter 2022 production report". June 30, 2022.
48 Regarding the current operation of the Las Bambas mining unit.
49 Minera Las Bambas S.A.: “Authorization of Exploitation Activities of the Chalcobamba pit, Stage I” [Technical Report]. February 18, 2022.
Conga
Operator Minera Yanacocha S.R.L. Investor50 100%: Newmont Goldcorp Corp. (U.S.A.)
Region Cajamarca
Jobs in operations53 1660 Ore reserves55 356 Mt @ 0.56% Au, @2.06 g/t Ag, @0.26% Cu - (M&I)
The project includes the exploitation of the Perol and Chaihuagon porphyry deposits. The project is currently in the suspended feasibility stage.
It is recorded that the project has a Second Modification to its Detailed Environmental Impact Assessment (2nd MEIA-d) for exploitation activities, approved by Resolution No.
228-2015-MEM/DGAAM on May 29, 2015.
The project has a Mining Plan approval and the Authorization to Start Mining Activities for the "Conga" mining project approved by Resolution N° 035-2012-MEM-DGM on March
9, 2012.
The approval of the Beneficiation Concession project and the authorization for the construction of the concentrator plant, the tailings deposit and other components for an
operating capacity of 92,000 MT/day was registered by Resolution No. 078-2012-MEM-FGM/V on March 1, 2012.
53 Minera Yanacocha S.R.L.: Second Modification of the Environmental Impact Assessment of the Conga project. May 29, 2015.
54 Minera Yanacocha S.R.L.: Mining Plan for the Conga project. Approved on March 09, 2012.
55 Newmont Corp.: Press Release (PR) - "Newmont Reports 2021 Mineral Reserves of 93 million Gold Ounces and 65 million Gold Equivalent Ounces". February 2022.
Region Puno
Province Carabaya
District Corani
Jobs in operations59 440 Ore reserves60 138.6 Mt @ 51.3 g/t Ag, 0.90% Pb, 0.55% Zn (P&P)
Water source57 Surface water and underground water Life of mine57 15 years
The project has a Detailed Environmental Impact Assessment (EIA-d) for exploitation activities, approved by Resolution No. 355-2013-MEM/AAM on September 20, 2013.
Furthermore, on November 2, 2017, the Second Sustaining Technical Report (2nd ITS) was approved by Resolution No. 340-2017-SENACE-DCA, including changes in the open pit
design, rearrangement of components in the process facilities, change in the engineering design of the mine waste deposit, among others.
Approval of the Mining Plan and Authorization to Start Mining Activities for the "Corani" mining project corresponding to the East Pit, Main and Mine, by means of Resolution No.
0119-2018-MEM-DGM dated May 09, 2018.
An approval of the Beneficiation Concession file named "Processing Plant of the Corani Metallurgical Mining Project" and Authorization for the construction of the Metallurgical
Processing Plant, among others, is recorded by means of R.D. No. 0570-2018-MEM-DGM/V dated June 25, 2018.
57 Bear Creek Mining Corporation: “Corani Project Report NI43-101” [Technical Report]. December 17, 2019.
58 Bear Creek Mining Corporation: Annual Letter to Shareholders. April 26, 2022.
59 Bear Creek Mining Corporation: “Corani Project Environmental Impact Assessment Executive Summary”. February 2013.
60 Bear Creek Mining Corporation: Precious Metals Summit [Corporate Presentation]. September 2022.
61 Bear Creek Mining S.A.C.: Beneficiation Concession Project File " Process Plant of Corani Metallurgical Mining Project ". December 2017.
62 Bear Creek Mining S.A.C.: Technical file for obtaining authorization to start exploration, development, preparation and exploitation activities, including mining plan and dumps, in metallic mining concessions.
Region Apurimac
Province Cotabambas
District Cotabambas
The project is located 545 km southwest of the city of Lima and 50 km southwest of Cusco, at an
altitude of approximately 3000 m.a.s.l. - 4000 m.a.s.l.
Estimated annual
Plant capacity64 80 000 tons per day 270 000 FMT of copper
production65
The project has an Ore Resource Estimate Technical Report dated July 24, 2012. Additionally, on April 9, 2015, the company submitted a Preliminary Economic Assessment (PEA)
Technical Report, which was updated on September 22, 2015. On February 22, 2018, Panoro Minerals restarted the drilling program, same which as of July 2019, released a high
grade of mineralization for both Chaupec Target and Guaclle Target. Panoro Minerals Ltd. is currently seeking to complete a Pre-Feasibility Study in 2023 through work programs.
The project does not yet have a Detailed Environmental Impact Assessment (EIA-d) for exploitation activities. However, it has a Second Modification of the Semi-Detailed
Environmental Impact Study (2nd MEIA-sd) for exploration activities of the project, approved by Resolution No. 147-2018-MEM/DGAAM on August 2, 2018. Also, on May 25, 2022
by Resolution No. 155-2022/MINEM-DGAAM the First Technical Supporting Report of the Second Modification of the Semi-Detailed Environmental Impact Study (1st ITS of the
2nd MEIA-sd) was approved. It is worth mentioning that on September 14, 2022, the company submitted to MINEM the 2nd ITS of the 2nd MEIA-sd of the project, which is
currently under evaluation.
Without registration.
Without registration.
63 Standard and Poor’s (S&P Global): Cotabambas – Ownership Information [Market Intelligence from the official Web site]. Consultation date October 12, 2022.
64 Panoro Minerals LTD.: "Corporate Presentation - September 2022".
65 Panoro Minerals Limited: “NI 43-101 Technical Report on Updated Preliminary Economic Assessment” [Technical Report]. September 22, 2015.
Don Javier
Operator Junefield Group S.A. Investor66 100%: Junefield Mineral Resources Holding Limited (China)
Region Arequipa
Province Arequipa
District Yarabamba
Estimated annual
Plant capacity To be defined 34 425 FMT of copper
production71
The owner would continue to be interested in developing exploratory activities within the project area in order to obtain more information regarding the geological characteristics.
The project does not yet have a Detailed Environmental Impact Assessment (EIA-d) for exploitation activities. However, the project has the conformity of the 2nd Technical
Supporting Report of the Second Modification of the Semi-Detailed Environmental Impact Study (2nd ITS of the 2nd MEIA-sd) for exploration activities, by Resolution No. 054-
2019-MEM-DGAAM on April 16, 2019.
Without registration.
Without registration.
66 Revista Energiminas: “Arequipa: Hongkonesa Junefield Group processes ITS to continue with exploration at Don Javier 79". November 15, 2018.
67 Junefield Group S.A.: “Informe Tecnico NI-43-101 of the copper-molybdenum mining project Don Javier, Arequipa” [MINEM Intranet System]. August 2014.
68 Junefield Group S.A.: Environmental Assessment - First Modification of the Semi-Detailed Environmental Impact Assessment (1st MEIA-sd) of the Don Javier exploration project.
69 Junefield Mineral Resources Holding Limited: “Mining Method”. [Official company website]. Consultation date November 28, 2022.
70 Junefield Group S.A.: “Technical Report” [Prepared by AMC Consultants Ltd.]. November 15, 2013.
71 Revista Rumbo Minero: “Measures for Don Javier's closure stage evaluated” [Web Publication]. 10 Dec. 2018.
El Galeno
60%: China Minmetals Corporation (China);
Operator Lumina Copper S.A.C. Investor72
40%: Jiangxi Copper Ltd. (China)
Region Cajamarca
The project is located 30 km northeast of the city of Cajamarca, at an altitude of approximately 3800 to
4200 m.a.s.l.
803 Mt @ 0.48% Cu, 0.014% Mo, 0.11 g/t Au, 2.6 g/t Ag
Jobs in operations To be defined Ore reserves72
– (M&I)
The company developed the pre-feasibility study in February 2007, which was reviewed on April 30, 2007. On the other hand, the company evaluated the possibility of developing
a mining cluster in conjunction with adjacent mining units.
The project does not yet have a Detailed Environmental Impact Assessment (EIA-d) for exploitation activities. However, the project has a Fifth Modification of its Semi-Detailed
Environmental Impact Study (5th MEIA-sd) for exploration activities, approved by Resolution No. 094-2019-MINEM/DGAAM on June 18, 2019. Also, on June 28, 2022, the company
submitted to MINEM the Sixth Modification of its Semi-Detailed Environmental Impact Study (6th MEIA-sd) in order to extend its schedule of activities for an additional three
years, which is currently under evaluation.
Without registration.
Without registration.
72 Standard and Poor’s (S&P Global): El Galeno – Ownership Information [Market Intelligence from the official website]. Consultation date: October 12, 2022.
73 Official Website of the Ministry of Energy and Mines [Intranet]: "Monthly Statistical Statement (ESTAMIN)". August 02, 2019.
74 northern Peru Copper Corp.: "Pre-feasibility Assessment”. [Technical Report]. February 19, 2007.
Haquira
Operator Minera Antares Peru S.A.C. Investor75 100%: First Quantum Minerals Ltd. (Canada)
northern Peru Copper Corp.: "Pr e-fea sibility A ssessment Region Apurimac
The project is in the south of Peru on the western side of Peruvian Andes, approximately
3500 to 4400 m.a.s.l.
Jobs in operations To be defined Ore reserves77 703.7 Mt @ 0.51% Cu 0.03 g/t Au – (M&I)
In early 2020, the company initiated actual land rights and resettlement discussions with the communities of Huanacopampa, Ccahuanhuire, Lahuani, Cconchaccota, Llamahuire,
Ccarayhuacho and Pararani. Currently, the company is continuing with resettlement negotiations with the communities and then focusing on the preparation of its Detailed
Environmental Impact Assessment (EIA-d).
The project does not yet have a Detailed Environmental Impact Assessment (EIA-d) for exploitation activities. However, the project has the Second Technical Supporting Report of
the Second Modification of the semi-detailed Environmental Impact Study (2nd ITS of the 2nd MEIA-sd) for exploration activities approved by Resolution No. 141-
2019/MINEM/DGAAM on September 13, 2019.
Without registration.
Without registration.
75 Standard and Poor’s (S&P Global): Haquira – Ownership Information [Market Intelligence from the official website]. Consultation date: October 13, 2022.
76 Antares Minerals Inc.: “Preliminary Economic Evaluation Update NI 43-101 Technical Report” [Technical Report]. September 02, 2010.
77 First Quantum Minerals Ltd.: "Annual Information Form". March 28, 2022.
Hierro Apurimac
Operator Apurimac Ferrum S.A.C. Investor78 100%: Strike Resources Limited (Australia)
Region Apurimac
Province Andahuaylas
District Andahuaylas
The project is located at an altitude of approximately 3500 m.a.s.l., 20 km from the city of Andahuaylas,
with a total concession area of 7500 hectares.
Estimated annual
Plant capacity To be defined 20 million FMT of iron
production79
A Detailed Environmental Impact Assessment (EIA-d) for mining activities has not yet been filed.
Without registration.
Without registration.
78 Strike Resources Limited: “Full Year Report: Director’s report” [Financial Report]. June 30, 2022.
79 Strike Resources Limited: “Pre-feasibility results confirm world class prospects for Apurimac Project in Peru” [Market Announcement]. July 23, 2008.
80 Standard and Poor's (S&P Global): Hierro Apurimac - Ownership Information [Market Intelligence from the Official Website]. Consultation date: October 24, 2022.
Hilarion
Operator Nexa Resources Peru S.A.A. Investor81 100%: Hejoassu Administração S.A. (Brazil)
Region Ancash
Province Bolognesi
Jobs in operations To be defined Ore reserves84 59 Mt @ 3.5% Zn, 0.6% Pb, 28.7 gr/t Ag - (M&I)
In the third quarter of 2022, the company mentions that exploration drilling was completed 4630 meters of drilling. This exploration was to test the Hilarion West and San Martin
resources with two rigs over outcropping vein systems, these new deposits are for resource expansion.
The project does not yet have a Detailed Environmental Impact Assessment (EIA-d) for exploitation activities. However, it has the Fifth Modification of the semi-Detailed
Environmental Impact Study (5th MEIA-sd) for exploration activities approved by Resolution No. 0159-2020-MINEM/DGAAM on November 20, 2020.
Without registration.
Without registration.
81 Standard and Poor's (S&P Global): Nexa Resources S.A. - Corporate Structure [Market Intelligence from the Official Website]. Consultation date December 19, 2022.
82 Nexa Resources S.A.: “Nexa announces PEA for potential annual production of 150kt of zinc equivalent - Hilarion project”. [Press Release]. March 5, 2020.
83 Nexa Resources S.A.: “Earnings Release - 1Q22”. April 28, 2022.
84 Nexa Resources Peru S.A.A.: “Annual Report 2021”. February 24, 2022.
85 Nexa Resources Peru S.A.A.: “Annual Report 2020”. February 25, 2021.
Integracion Coroccohuayco
Operator Compañia Minera Antapaccay S.A. Investor86 100%: Glencore Plc. (Switzerland)
Region Cusco
Province Espinar
District Espinar
Type of mineral deposit Copper (Cu) and Gold (Au) Skarn/ Porphyry of Copper (Cu) and Gold
and/or mineralization88 (Au)
Jobs in operations89 1092 Ore reserves86 643 Mt @ 0.6% Cu, 0.08 g/t Au, 2.33 g/t Ag - (M&I)
Compañia Minera Antapaccay S.A. decided to reformulate the "Antapaccay Expansion Tintaya Integracion Coroccohuayco" project by returning to the pre-feasibility stage, expected
to be completed by the end of 2022.
The project has a Modification of the Detailed Environmental Impact Assessment (MEIA-d) for exploitation activities, approved by Resolution No. 196-2019-SENACE-PE/DEAR on
December 17, 2019. In addition, the approval of a "First Technical Supporting Report of the Modification of the Detailed Environmental Impact Assessment (1st ITS of the MEIA-d)
of the Antapaccay Expansion Tintaya - Coroccohuayco Integration Project" was approved by Resolution No. 00040-2022-SENACE-PE/DEAR on March 09, 2022.
Without registration.
Without registration.
86 Standard and Poor's (S&P Global): Antapaccay - Ownership Information [Market Intelligence from the Official Website]. Consultation date November 29, 2022.
87 Official Website of the Ministry of Energy and Mines [Intranet] - Online Environmental Assessment System (SEAL): “Modification of the Environmental Impact Assessment (EIA) for the Antapaccay Tintaya Expansion
Project - Coroccohuayco Integration”. Consultation date: August 28, 2019.
88 Compañia Minera Antapaccay S.A.: Modification of the Environmental Impact Study (MEIA) of the Antapaccay Tintaya Expansion Project Coroccohuayco Integration.
Region La Libertad
Jobs in operations To be defined Ore reserves92 742.4 Mt @0.24 g/t Cu, @0.35% Cu - (M&I)
La Arena II is a copper/gold sulphide deposit located below and adjacent to the gold oxide deposit called La Arena that Pan American currently mines. In February 2018, a
Preliminary Economic Assessment (PEA) on La Arena II was released.
Without registration.
Without registration.
Without registration.
91 Standard and Poor’s (S&P Global): La Arena – Property Profile [Market Intelligence from the Official Website]. Consultation date December 13, 2022.
92 Technical Report on the La Arena Project, Peru. February 2018.
La Granja
Operator Rio Tinto Minera Peru Limitada S.A.C. Investor93 100% Rio Tinto Plc. (United Kingdom)
Region Cajamarca
Province Chota
District Querocoto
The project is located approximately 670 km northwest of the city of Lima and at an altitude between
2000 and 2800 m.a.s.l.
Estimated annual
Plant capacity Not available 500 000 FMT de copper
production97
Rio Tinto Minera Peru Limitada S.A.C. continues to carry out exploration activities in the project area in order to obtain more information regarding the geological characteristics
of the project. In addition, it is important to mention that they will continue with the exploration programs due to the compliance of the Second Technical Supporting Report of
the Twelfth Modification of the Semi-Detailed Environmental Impact Study (2nd ITS of the 12th MEIA-sd).
The project does not yet have a Detailed Environmental Impact Assessment (EIA-d) for exploitation activities. However, the project has the conformity to the Second Technical
Supporting Report of the Twelfth Second Modification of the semi-Detailed Environmental Impact Study (2nd ITS of the 12th MEIA-sd) for exploration activities, approved by
Resolution No. 202-2022/MINEM-DGMM dated July 7, 2022. Additionally, the company has submitted its Thirteenth Modification of the semi-Detailed Environmental Impact Study
(13th MEIA-sd) on October 20, 2022 and is currently under evaluation.
Without registration.
Without registration.
93 Standard and Poor's (S&P Global): La Granja - Ownership Information [Market Intelligence from the Official Website]. Consultation date: October 20, 2022.
94 Rumbo Minero: “La Granja mining project, the largest copper deposit in Cajamarca” [Interview of the Rio Tinto company’s representatives]. Edition No. 129. August 2020.
95 INGEMMET: "Compendium of Peruvian Mineral Deposits” (Newsletter No. 10 Series B: Economic Geology). February 2003.
96 Rio Tinto Minera Peru Limitada S.A.C.: “Rio Tinto Annual Report 2021”.
97 Rio Tinto Plc.: “La Granja project is one of the largest undeveloped greenfield cooper projects in Latin America”. [Corporate Presentation]
Los Calatos
100%: CD Capital Natural Resources Fund III (United
Operator Minera Hampton Peru S.A.C. Investor98
Kingdom)
Region Moquegua
The project is located at an average altitude of 2950 m.a.s.l., between the Los Calatos hills, from which
the project receives its name.
Jobs in operations To be defined Ore reserves101 136.5 Mt @ 0.73% Cu, 434 ppm Mo - (M&I)
The company plans exploration programs according to the Third Modification of its semi-Detailed Environmental Impact Assessment (3rd MEIA-sd) for exploration activities.
The project does not yet have a Detailed Environmental Impact Assessment (EIA-d) for exploitation activities. However, it has the Third Modification of the semi-Detailed
Environmental Impact Study (3rd MEIA-sd) for exploration activities approved by Resolution No. 035-2021-MINEM/DGAAM dated February 24, 2021, which aims to improve the
technical knowledge of the deposit to facilitate its exploitation, as well as to define the location of future components.
Without registration.
Without registration.
98 Standard and Poor's (S&P Global): Los Calatos - Ownership Information [Market Intelligence from the Official Website]. Consultation date: October 19, 2022.
99 Minera Hampton Peru S.A.C.: " Request for an extension of the deadline for the reservation of surface land for the implementation of the National Interest Project called “Los Calatos”. January 2020.
100 Metminco Limited: “Los Calatos: High Grade Development Option”. [Investor presentation]. September 2015.
101 Metminco Limited: Director's report. [Press release]. June 27, 2017.
Los Chancas
Southern Peru Copper Corporation, Peru Branch
Operator Investor102 100%: Grupo Mexico S.A.B. de C.V. (Mexico)
Office
Region Apurimac
Province Aymaraes
The project is located in the Pachachaca basin on the Pacific slope at an average elevation of 2279 m.a.s.l.
During 2022, the company continued to develop complementary activities with the objective to complete the evaluation of the Detailed Environmental Impact Assessment (EIA-
d) for the project. The company also plans to continue developing social and environmental improvements for the local communities.
SENACE resolved to approve the Specific Terms of Reference for the preparation of the Environmental Impact Study for the Los Chancas project through Resolution No. 00111-
2022-SENACE-PE/DEAR on July 21, 2022.
Without registration.
Without registration.
102 Standard and Poor's (S&P Global): Los Chancas - Ownership Information [Market Intelligence from the Official Website]. Consultation date: October 14, 2022.
103 Southern Peru Copper Corporation: “Third Quarter and Nine Months Results 2022”. October 2022.
104 Southern Peru Copper Corporation: “Evaluation of the Terms of Reference for the preparation of the Modification of the Detailed Environmental Impact Assessment of Los Chancas”. Approved on July 21, 2022,
Region Ancash
Province Pallasca
District Conchucos
The project is located at an altitude between 3300 m.a.s.l. and 4875 m.a.s.l., approximately 450 km
northwest of the city of Lima.
Jobs in operations107 914 Ore reserves108 189.4 Mt @0.48% Cu, 2.8 g/t Ag, 0.046% Mo - (M&I)
On December 17, 2016, Milpo and Activos Mineros S.A.C., with the intervention of Proinversion, signed the Transfer Agreement for the Mining Concessions that make up the
Magistral project. The company mentions that the feasibility studies for the Magistral project continue to advance.
The project has an Environmental Impact Assessment (EIA-d) approved by Resolution No. 278-2016-MEM-DGAAM dated September 15, 2016. On December 23, 2021, the mining
company submitted to SENACE the Modification of the Detailed Environmental Impact Assessment (MEIA-d) of the Magistral project, currently still under evaluation. However, the
project has the conformity to the Fourth Technical Supporting Report of the Detailed Environmental Impact Study (4th ITS of the EIA-d) through Resolution No. 158-2022-SENACE-
PE/DEAR.
On February 27, 2021, the project owner submitted the request for the Authorization to Start Mining Activities (Mining Plan). It should be noted that this study contemplates 2
stages; precisely, the application refers to Stage I of the Magisterial pit (Pre-mining). Currently, it is still under evaluation.
Without registration.
105 Standard and Poor's (S&P Global): Magistral - Ownership Information [Market Intelligence from the Official Website]. Consultation date: October 14, 2022.
106 National Service of Environmental Certification for Sustainable Investments (SENACE): EVA Information Platform "Project Description - Magistral". Consultation date: October 12, 2022.
107 Nexa Resources Peru S.A.: Modification of the Detailed Environmental Impact Assessment [Executive Summary]. January 2022.
108 Nexa Resources Peru S.A.A.: "Annual Report”. Published on February 24, 2022.
109 Nexa Resources Peru S.A.A.: “Project Technical Data Sheet submitted to MINEM”. October 08, 2020.
Michiquillay
Southern Peru Copper Corporation, Peru Branch
Operator Investor110 100%: Grupo Mexico S.A.B. de C.V. (Mexico)
Office
Region Cajamarca
Province Cajamarca
District La Encañada
It is located approximately 900 km northeast of the city of Lima and 45 km from the city of Cajamarca,
at an altitude that varies between 3275 and 4000 m.a.s.l.
Estimated annual
Plant capacity Not available 225 000 FMT of copper
production111
In June 2018, Southern Copper signed a lease for the acquisition of the Michiquillay project in Cajamarca. Also, in 2021, the company signed a Social Agreement with the Michiquillay
and La Encañada communities. In 2022, the company obtained the required permits to initiate an exploration program in the project's direct area of influence.
The project does not yet have a Detailed Environmental Impact Assessment (EIA-d) for exploitation activities. However, on October 1, 2021 the semi-Detailed Environmental Impact
Assessment (EIA-sd) was approved by Resolution No. 190-2021/MINEM-DGAAM, in order to continue with the exploration programs.
Without registration.
Without registration.
110 Standard and Poor's (S&P Global): Michiquillay - Ownership Information [Market Intelligence from the Official Website]. Consultation date: October 14, 2022.
111 Southern Peru Copper Corporation: "Third Quarter and Nine Months Results 2022”. October 2022.
112 INGEMMET: “Newsletter No. 10 Series B: Economic Geology”. February 2003.
Ollachea
Operator Minera Kuri Kullu S.A. Investor113 100%: Minera IRL Limited (United Kingdom)
Region Puno
Province Carabaya
District Ollachea
The project is located south of Puno, approximately 250 km from Lake Titicaca and at an altitude between
2900 and 3850 m.a.s.l..
On September 16, 2019 the arbitration award ordered the payment of US$ 34.2 million by COFIDE to the company, as well as the repayment of the bridge loan. In December 2019
Minera IRL and COFIDE signed a Memorandum of Understanding, which was successively extended until November 7, 2020. Finally, on November 12, 2020, the holder announced
the resolution of its dispute with COFIDE, having up to 36 months to fulfill the agreed commitments.
The project has a Detailed Environmental Impact Assessment (EIA-d) for exploitation activities, approved by Resolution No. 363-2013-MEM-AAM on September 25, 2013.
Subsequently, on December 18, 2014, the First Technical Supporting Report of the Detailed Environmental Impact Study (1st ITS of the EIA-d) was approved by Resolution No.
615-2014-MEM-DGAAM.
On April 28, 2017, the company requested the authorization to start exploitation activities. However, on February 7, 2020, through Resolution No. 0074-2020-MINEM-DGM/V, the
General Directorate of Mining declared the request for authorization to start exploitation activities ineffective due to non-compliance with the deadline granted for correction.
Later, on January 6, 2022, the company resubmitted the request for Authorization to Commence Exploitation Activities for the Ollachea project, which is currently under evaluation.
The approval of the Beneficiation Concession project is registered for the installation of a 3000 tons per day processing plant and the authorization of the construction of the
project by means of Resolution No. 0235-2014-MEM-DGM/V on June 25, 2014.
113 Standard and Poor’s (S&P Global): Minera IRL – General Comments. [Market Intelligence from the Official Website]. Consultation date: October 19, 2022.
114 Minera Kuri Kullu S.A.: “Ollachea Gold Project – Peru, NI 43‐101 Technical Report" [Preliminary Technical Report]. August 27, 2021.
115 Minera Kuri Kullu S.A.: Corporate Presentation. February 2022.
Pampa de Pongo
49%: Zhongrong Xinda Group Co. Ltd. (China);
Operator Jinzhao Mining Peru S.A. Investor116
51%: Jiangtong Group (China)
Region Arequipa
Province Caraveli
Estimated annual
Plant capacity Not available 22.5 million FMT of iron
production120
The project has a Detailed Environmental Impact Assessment (EIA-d) approved by Resolution No. 044-2015-MEM-DGAAM dated January 22, 2015. On October 14, 2021, the owner
submitted to SENACE the Modification of the Detailed Environmental Impact Assessment (MEIA-d) of the Pampa de Pongo project, which was declared inadmissible by Resolution
No. 000160-2021-SENACE-PE/DEAR dated December 9, 2021.
The approval of the Mining Plan and its Authorization to Begin Exploitation Activities for stage I of the "Pampa de Pongo" metallic mining project was approved by Resolution No.
0084-2018-MEM-DGM on March 26, 2018.
Without registration.
116 Standard and Poor’s (S&P Global): Pampa de Pongo – Ownership Information [Market Intelligence from the Official Website]. Consultation date: October 19, 2022.
117 Jinzhao Mining Peru S.A.: Information requested from the company, 2022.
118 Jinzhao Mining Peru S.A.: Stage I Mining Plan. February 2018.
119 Jinzhao Mining Peru S.A.: Citizen Participation Plan for the Modification of the Detailed Environmental Impact Assessment (MEIA-d). August 2022.
120 Jinzhao Mining Peru S.A.: Summary sheet submitted to the Ministry of Energy and Mines (MINEM). September 18, 2020.
Rio Seco Copper Plant
Operator Procesadora Industrial Rio Seco S.A. Investor121 100%: Grupo Buenaventura (Peru)
Region Lima
Province Huaral
The project is located approximately 96 and 17.5 km north of the cities of Lima and Huaral, respectively.
Estimated annual
Plant capacity122 Not available 40 000 MT of copper in cathodes
production122
On November 11, 2020, the owner submitted the request for the evaluation of the "Detailed Environmental Impact Assessment of the Planta de Cobre Rio Seco" in the framework
of the Global Environmental Certification - IntegrAmbiente. Furthermore, on December 11, 2020, SENACE declared the project admissible, as well as the mechanisms proposed in
the Citizen Participation Plan and the Rio Seco EIA Executive Summary, through A.D. No. 201-2020-SENACE-PE/DEAR. On January 31, 2022, SENACE approved the Detailed
Environmental Impact Assessment for the Planta de Cobre Rio Seco project through Resolution No. 020-2022-SENACE-PE/DEAR dated January 31, 2022.
Without registration.
Without registration.
121 Compañia de Minas Buenaventura S.A.A.: Annual Report 2021. February 18, de 2022.
122 Industrial Processor Rio Seco: Detailed Environmental Impact Assessment (EIA-d) for the Rio Seco Copper Plant.
Pukaqaqa
83.55%: Hejoassu Administração S.A. (Brazil);
Operator Nexa Resources Peru S.A.A. Investor123
16.45%: Other shareholders
Region Huancavelica
Province Huancavelica
Estimated annual
Plant capacity126 30 000 tons per day 5000 FMT of copper
production124
The pre-feasibility study progressed all the way to the end of the FEL2-A stage. It should be noted that the metallurgical results indicated the need to further explore copper and
molybdenum recoveries and grades before moving forward with the pre-feasibility study.
The project has a Detailed Environmental Impact Assessment (EIA-d) approved by Resolution No. 130-2015-MEM/DGAAM on March 9, 2015. It also has the Third Technical
Supporting Report (3rd ITS, for its acronym in Spanish) to enable the main components of the Pukaqaqa mining unit, which was approved on February 17, 2020 through Resolution
No. 32-2020-SENACE-PE/DEAR.
Without registration.
Without registration.
123 Standard and Poor's (S&P Global): Pukaqaqa - Ownership Information [Market Intelligence from the Official Website]. Consultation date: October 19, 2022.
124 Nexa Resources Peru. S.A.A.: “Project Technical Data Sheet submitted to MINEM”. October 18, 2020.
125 Nexa Resources S.A.: “Earnings Release - 1Q22”. October 19, 2022.
126 Compañia Minera Milpo S.A.A. (Actual Nexa Resources S.A.A.): "Detailed Environmental Impact Assessment for the Pukaqaqa Mining Project”. Approved on March 09, 2015.
127 Nexa Resources Peru S.A.A.: Annual Report 2021. October 19, 2022.
Quechua
Operator Compañia Minera Quechua S.A. Investor128 100%: Pan Pacific Copper Co. Ltd. (Japan)
Region Cusco
Province Espinar
District Espinar
Estimated annual
Plant capacity Not available 76 000 FMT of copper
production130
The project does not yet have a Detailed Environmental Impact Assessment (EIA-d) for exploitation activities. However, the project has the Second Modification of the semi-
Detailed Environmental Impact Assessment (2nd MEIA-sd) for exploration activities, approved by Resolution No. 075-2010-MEM/AAM on March 3, 2010.
Without registration.
Without registration.
128 Standard and Poor’s (S&P Global): Quechua – Ownership Information [Market Intelligence from the Official Website]. Consultation date: October 13, 2022.
129 Official Website of the Ministry of Energy and Mines [Intranet] - Monthly Statistical Statement (ESTAMIN): Investment Program. Consultation date: September 10, 2018.
130 Pan Pacific Copper Co.: “Pan Pacific Copper gears up to feasibility study stage in development project of Quechua Copper”. [Press Release]. November 30, 2009.
Antamina Replenishment
33.75%: Xstrata Glencore (Switzerland);
Operator Compañia Minera Antamina S.A.
33.75%: BHP Billiton (Australia);
Investor131
22.50%: Teck Base Metals Ltd. (Canada);
10.00%: Mitsubishi Corporation (Japan)
Region Ancash
Province Huari
The project is located at 4300 m.a.s.l., approximately 100 km east of the city of Huaraz.
Plant capacity132 208 000 tons per day Estimated annual production Not available
The project aims to modify components approved and add auxiliary components in the mine area of the Antamina mining unit, to provide continuity to current operations and
expand the mine until 2036.
On April 12, 2022, the project owner submitted the request for the evaluation of the Modification of the Detailed Environmental Impact Assessment (MEIA-d), which is currently
under evaluation.
The mining unit associated with the project is classified as a continuous mining activity that began prior to the enactment of Supreme Decree No. 046-2001-EM and in accordance
with Article 29 of the Regulation of Occupational Safety and Health in Mining Supreme Decree No. 024-2016-EM, as amended.
Without registration.
131 Standard and Poor’s (S&P Global): Antamina – Equity & Controlling Owner(s)/Operator [Market Intelligence from the Official Website]. Consultation date: October 13, 2022.
132 Compañia Minera Antamina S.A.: Modification of the Detailed Environmental Impact Assessment (MEIA-d) of the Antamina mining unit. June 2022.
Inmaculada Replenishment
Operator Compañia Minera Ares S.A.C. Investor133 100%: Hochschild Plc. (United Kingdom)
Region Ayacucho
On July 26, 2021, Compañia Minera Ares S.A.C. submitted to SENACE the Second Modification of the Detailed Environmental Impact Assessment (2nd MEIA-d) of the project, which
is currently under evaluation.
Without registration.
Without registration.
133 Standard and Poor’s (S&P Global): Inmaculada – Ownership Information [Market Intelligence from the Official Website]. Consultation date: October 18, 2022.
134 Compañia Minera Ares S.A.C.: Second Modification of the Environmental Impact Study (2nd MEIA) of the Inmaculada mining unit. September 2022.
Raura Replenishment
Operator Compañia Minera Raura S.A. Investor135 100%: Brescia Group (Peru)
The Raura Mining Unit is located in the western chain of the central Andes to the southeast of the
Huayhuash Cordillera, at an altitude that varies between 4300 and 5700 m.a.s.l.
The project aims to expand the operations of the Raura mining unit by approximately 14 years, mainly through the deepening of the mine's underground workings, the continued
operation of the Nieve Ucro II tailings deposit and the construction of a new tailings deposit (Niño Perdido).
On July 20, 2022, the project owner submitted the request for the evaluation of the Modification of the Detailed Environmental Impact Assessment (MEIA-d), which is currently
under evaluation.
The mining unit associated with the project is considered a continuous mining activity initiated before the enactment of Supreme Decree No. 046-2001-EM and in accordance with
Article 29 of the Regulation of Occupational Safety and Health in Mining D.S. No. 024-2016-EM and amendments.
Without registration.
135 Standard and Poor’s (S&P Global): Compañia Minera Raura S.A. – Corporate Structure [Market Intelligence from the Official Website]. Consultation date: October 18, 2022.
136 Compañia Minera Raura S.A.: Second Modification of the Environmental Impact Study (2nd MEIA) of the Raura mining unit. [Executive summary]. September 2022.
Tantahuatay Replenishment
44.2%: Grupo Mexico S.A.B de C.V. (Mexico);
Operator Compañia Minera Coimolache S.A.
Investor137 40.1%: Compañia de Minas Buenaventura S.A.A. (Peru);
15.7%: Regal Ware, Inc. (U.S.A.)
Region Cajamarca
Province Hualgayoc
The project is located in the region of Cajamarca, province of Hualgayoc, districts of Chugur and
Hualgayoc at an altitude that varies between 3600 and 4050 m.a.s.l.
Tantahuatay Pit:
103.4 Mt @0.306 g/t Au; @13.879 g/t Ag
Pit Cienaga north:
Jobs in operations139 800 Ore reserves139
15.9 Mt @0.656 g/t Au; @1.137 g/t Ag
Pit Mirador north:
21.3 Mt @0.402 g/t Au; @0.489 g/t Ag
Water source139 Surface water and underground water Life of mine139 8 years
The project contemplates the expansion of major components such as the Tantahuatay 02 and Cienega north pits, leaching PAD's, auxiliary facilities, as well as the installation of
new components, in order to maintain the continuity and production level of 72,000 metric tons/day at the Tantahuatay mining unit and extend its useful life.
On December 28, 2021, the owner submitted to SENACE the request for evaluation of the Third Modification of the Detailed Environmental Impact Assessment (3rd MEIA-d)
Tantahuatay.
Without registration.
Without registration.
137 Standard and Poor’s (S&P Global): Tantahuatay – Ownership Structure [Market Intelligence from the Official Website]. Consultation date: December 13, 2022.
138 Energiminas: "Minera Coimolache's US$ 621 million plan to revitalize Tantahuatay mine in Cajamarca”. January 13, 2022.
139 Compañia Minera Coimolache S.A.: "Third Modification of the Environmental Impact Assessment of Tantahuata UP”. December 2021.
Rio Blanco
51%: Zijin Mining Group Co. Ltd. (China);
Operator Rio Blanco Copper S.A.
35%: Tongling Non-Ferrous Metals Group Holding Co. Ltd.
Investor140
(China);
14%: Xiamen C&D Co. Ltd. (China)
Region Piura
Province Huancabamba
The project is located on Henry Hill, on the border between Peru and Ecuador, at an altitude of 2200 to
2800 m.a.s.l.
The company is currently updating the feasibility study and is in the process of preparing the Detailed environmental impact assessment (EIA-d). It is in the last stage of the pre-
operational stage, defining the final technical studies of the mine's modern components, technological processes, and mitigation plans. It is also working on community relations.
The company is in the process of preparing a Detailed Environmental Impact Assessment (EIA-d) for exploitation activities. However, it has a Modification of the Update of the
Rehabilitation Plan of the project, approved through Resolution No. 274-2016-MEM-DGAAM on September 14, 2016.
Without registration.
Without registration.
140 Standard and Poor’s (S&P Global): Rio Blanco – Ownership Information [Market Intelligence from the Official Website]. Consultation date: October 13, 2022.
141 Rio Blanco Copper S.A.: “Information submitted by the mining owner to the Ministry of Energy and Mines (MINEM))”. [Corporate Presentation]. September 23, 2020.
142 Rio Blanco Copper S.A.: “Proyecto Rio Blanco”. [Official company website]. Consultation date: October 13, 2022.
Romina
63%: Glencore Plc. (Switzerland);
Operator Compañia Minera Chungar S.A.C. Investor143
37%: Other shareholders (Peru)
Region Lima
Province Huaral
Jobs in operations144 450 Ore reserves144 14,5 Mt @ 4,63% Zn; 2,72% Pb; 1,23 oz/t Ag - (M&I)
The objective of the project is the construction and operation of an open pit and underground works for the extraction of polymetallic minerals (zinc, lead and silver, with copper
and iron contents). This material will be transported to the Alpamarca mining unit for beneficiation. The open pit will have a maximum production rate of 28,500 tons per day,
while the underground works will have a maximum production rate of 5,000 tons per day.
On June 11, 2022, the project owner submitted the Detailed Environmental Impact Assessment (EIA-d) of the Romina project to SENACE, which is currently under evaluation.
Without registration.
Not applicable.
143 Standard and Poor’s (S&P Global): Volcan Compañia Minera S.A.A. – Corporate Structure [Market Intelligence from the official Web site]. Consultation date: October 13, 2022.
144 Compañia Minera Chungar S.A.C.: Detailed Environmental Impact Assessment (EIA-d) of the Romina Project [Project Description]. June 2022.
145 Revista Rumbo Minero: “Volcan could start construction of the Romina project in 2023" [Volcan CEO interview]. November 2022.
San Gabriel
Operator Compañia de Minas Buenaventura S.A.A. Investor146 100%: Grupo Buenaventura (Peru)
Region Moquegua
District Ichuña
The project is located at an altitude between 4450 and 5000 m.a.s.l., 837 km from Lima and 115.5 km
from the city of Moquegua.
Jobs in operations149 500 Ore reserves148 14.9 Mt @ 4.04 g/t (1.94 Moz Au), 6.43 g/t de Ag
Estimated annual
Plant capacity150 3000 tons per day 125 000 ounces of fine gold.
production147
In March 2022, Compañia de Minas Buenaventura S.A.A. announced the start of the construction stage of its San Gabriel project. However, on June 15, 2022, construction was
suspended due to the social context in the area of direct influence. On October 28, 2022, the company announced the progressive return of preparatory work for the construction
of the project, as a result of multiple meetings held with authorities and communities. As of November 2022, the project has a financial progress of 5.8%.
The project has a Detailed Environmental Impact Assessment (EIA-d) for exploitation activities, approved by Resolution No. 099-2017-MEM/DGAAM on March 31, 2017. Likewise,
the owner submitted to SENACE the Third Technical Supporting Report of the Detailed Environmental Impact Study (3rd ITS of the EIA-d) which was approved on February 4, 2022
by Resolution No. 00025-2022-SENACE-PE/DEAR.
Through Resolution No. 0257-2022-MINEM/DGM, dated March 23, 2022, the Mining Plan was approved and the Start of Mining Activities of the San Gabriel project was authorized.
It should be noted that on June 7, 2022, through Resolution No. 0229-2022-MINEM-DGM/V, corrections were made to Resolution No. 0257-2022-MINEM/DGM.
The application of the "San Gabriel" Beneficiation Concession for the construction of the main components was approved and the Beneficiation Concession title was granted for a
plant capacity of 3000 tons per day by Resolution No. 0298-2022-MINEM/DGM dated March 29, 2022.
146 Compañia de Minas Buenaventura S.A.A.: San Gabriel Project [Official company website]. Consultation date: October 17, 2022.
147 Compañia de Minas Buenaventura S.A.A.: Presentation at the Investor Day event organized by the Lima Stock Exchange. [Corporate Presentation]. August 29, 2022.
148 Compañia de Minas Buenaventura S.A.A.: 2021 Annual Report. February 18, 2022.
149 Perumin 35: Presentation of the status of the San Gabriel project [Corporate Presentation]. September 28, 2022.
150 Compañia de Minas Buenaventura S.A.A.: Beneficiation Concession approved for a plant capacity of 3000 tons per day. Approved on March 29, 2022.
San Luis
Operator Reliant Ventures S.A.C. Investor151 100%: SSR Mining Inc. (USA)
Region Ancash
Province Yungay
District Shupluy
Jobs in operations To be defined Ore reserves153 484 Kt @ 578 g/t Ag, 22.4 g/t Au - (M&I)
During 2021, the company developed activities to provide information about the San Luis project to the community members of the Ecash Rural Community, which includes the
districts of Shupluy, Cascapara, Ataquero, Carhuaz, Marcara and Anta, located in the provinces of Yungay and Carhuaz in the regionof Ancash. Furthermore, the head of the
company held meetings to reinforce the relationship with the community in order to obtain the permit for the construction of the project.
The project has a Detailed Environmental Impact Assessment (EIA-d) for exploitation activities, approved by Resolution No. 289-2012-MEM/AAM dated September 10, 2012.
Without registration.
Without registration.
151 Standard and Poor's (S&P Global): San Luis - Ownership Information [Market Intelligence from the Official Website]. Consultation date: October 20, 2022.
152 Reliant Ventures S.A.C.: Environmental Impact Assessment (EIA) of the “Ayelen Vein Exploitation Project and San Luis gold and silver processing”. Approved on September 10, 2012.
153 SSR Mining.: Reserve and Resource tables. December, 2021.
154 Reliant Ventures S.A.C.: San Luis Project [Company's oficial Web page]. Consultation date: October 21, 2022.
155 Reliant Ventures S.A.C.: Technical Report for the San Luis Project Feasibility Study. Published on June 4, 2010.
Shalipayco
75%: Hejoassu Administração S.A. (Brazil);
Operator Nexa Resources Peru S.A.A. Investor156
25%: Pan American Silver Peru (Canada)
Region Junin
Province Junin
District Carhuamayo
The project is located at an altitude between 4000 and 4800 m.a.s.l., the closest town to the project is the
city of Carhuamayo located 11 km away.
Jobs in operations To be defined Ore reserves158 9.4 Mt @ 4.4%Zn, 0.4%Pb, 31.1 g/t Ag - (M&I)
The project does not yet have a Detailed Environmental Impact Assessment (EIA-d) for exploitation activities. However, the company has the Second Modification of the semi-
Detailed Environmental Impact Assessment (2nd MEIA-sd) for exploration activities, approved by Resolution No. 020-2019-MEM/DGAAM on February 08, 2019.
Without registration.
Without registration.
156 Standard and Poor's (S&P Global): Shalipayco - Ownership Information [Market Intelligence from the Official Website]. Consultation date: October 19, 2022.
157 Nexa Resources S.A.: “Technical Report NI 43-101” [Technical report]. July 26, 2017.
158 Nexa Resources Peru S.A.A: Annual Report 2021. October 19, 2022.
159 Nexa Resources S.A.: “Earnings Release - 2Q21”. October 19, 2022.
160 Nexa Resources Peru S.A.A.: “Presentation of the mining owner to the Ministry of Energy and Mines (MINEM)". September 2020.
Tia Maria
Operator Southern Peru Copper Corporation, Peru Branch Investor161 100%: Grupo Mexico S.A.B. de C.V. (Mexico)
Region Arequipa
Province Islay
Jobs in construction164 9000 jobs: 3600 directs and 5400 indirects Type of exploitation163 Open pit
Estimated annual
Plant capacity163 100 000 tons per day 120 000 FMT of copper
production162
A Detailed Environmental Impact Assessment (EIA-d) for exploitation activities was approved by Resolution No. 392-2014-MEM/DGAAM on August 1, 2014. Likewise, the project
registers a First Technical Supporting Report of the Detailed Environmental Impact Study (1st ITS of the EIA-d) to which conformity was given by Resolution No. 030-2018-SENACE-
JEF/DEAR on February 19, 2018.
Without registration.
The Beneficiation Concession file was approved for an installed capacity of 100,000 metric tons/day and the construction of components in the dry and wet areas was authorized
by Resolution No. 0328-2019-MINEM-DGM/V on July 8, 2019.
161 Standard and Poor's (S&P Global): Tia Maria - Ownership Information [Market Intelligence from the Official Website]. Consultation date: October 19, 2022.
162 Southern Copper Corporation: “Results Second Quarter 2022”. Publication date: August 24, 2022.
163 Southern Peru Copper Corporation: Information submitted by the mining owner to the Ministry of Energy and Mines (MINEM). October 08, 202.
164 Southern Copper Corporation: “Results Second Quarter 2022”. Publication date: May 14, 2022.
165 Southern Peru Copper Corporation: "Environmental Impact Assessment for the Tia Maria mining exploitation and beneficiation Project”. Approved on August 01, 2014.
Trapiche
Operator El Molle Verde S.A.C. Investor166 100%: Grupo Buenaventura (Peru)
Region Apurimac
Province Antabamba
During 2021, the company completed construction of the on-site metallurgical laboratory and began 36 of the 100 column tests scheduled as part of the feasibility study. The
environmental baseline was completed and the first of two citizen participation workshops were scheduled for the end of the year. Also the Company updated the pre-feasibility
study and planned a drilling program of 18,000 m by 2022 to continue in-situ column testing and improve the certainty of the mineral resource.
On November 5, 2021, the Citizen Participation Plan was approved prior to the submission of the Detailed Environmental Impact Assessment (EIA-d) of the Trapiche project by
Resolution No. 00144-2021-SENACE-PE/DEAR. On November 8, 2022, the owner submitted to SENACE, the request for modification of the Citizen Participation Plan for the
"Detailed Environmental Impact Study of the Trapiche project" and is currently under evaluation.
Without registration.
Without registration.
166 Compañia de Minas Buenaventura S.A.A.: Trapiche [Official company website]. October 18, 2022.
167 Compañia de Minas Buenaventura S.A.A.: Presentation of the "Buenaventura Project Portfolio" to the Ministry of Energy and Mines (MINEM). August 2020.
168 Compañia de Minas Buenaventura S.A.A.: Annual Report 2021. February 18, 2022.
169 Compañia de Minas Buenaventura S.A.A.: Presentation at the Investor Day event organized by the Lima Stock Exchange. [Corporate Presentation]. August 29, 2022.
170 Compañia de Minas Buenaventura S.A.A.: Second quarter 2022 corporate results [Corporate Presentation]. October 18, 2022.
Yanacocha Sulfides
Operator Minera Yanacocha S.R.L. Investor171 100%: Newmont Goldcorp Corp. (U.S.A.)
Region Cajamarca
Province Cajamarca
The project is located at a distance approximately 20 km north from the city of Cajamarca
and 583 km from the city of Lima, at 3600 to 4200 m.a.s.l..
Estimated annual
Plant capacity Not available 525 000 equivalent ounces of gold
production176
The Yanacocha Sulfides project is located within the current operating zone and involves the processing of sulfide ores to produce copper and gold, which would substantially
extend the life of the mine. In September 2022, Newmont announced that following the decision to invest full funding by the second half of 2024, the advanced engineering
activities will continue.
The project has the Second Modification of the Detailed Environmental Impact Assessment (2nd MEIA-d) of the Yanacocha Sulfides project, approved by Resolution No. 154-2020-
SENACE-PE/DEAR on December 21, 2020, which seeks to increase the extraction of material from the Chaquicocha Stage 3 pit to increase the average annual production of gold,
in addition to improving operational efficiency through the mixing of tailings and their subsequent sequential disposal. It should be noted that a Third Technical Supporting Report
of the Second Modification of the Detailed Environmental Impact Study (3rd ITS of the 2nd MEIA-d) is registered, which was approved by Resolution No. 0145-2022-SENACE-
PE/DEAR on September 30, 2022.
Without registration.
Without registration.
174 Minera Yanacocha S.R.L.: "Results Second Quarter 2022”. September, 2022.
175 Newmont Corporation: "Newmont Reports 2021 Mineral Reserves of 93 million Gold Ounces and 65 million Gold Equivalent Ounces". February 2022.
176 Minera Yanacocha S.R.L.: Newmont delays Yanacocha Sulfides project and names Dean Gehring to lead Peruvian assets [Press Release]. September 2022.
Yumpag
Operator Compañia de Minas Buenaventura S.A.A. Investor177 100%: Grupo Buenaventura (Peru)
Region Pasco
District Yanahuanca
The project is located on the eastern flank of the Cordillera Occidental of the Peruvian Andes, at an
altitude between 3750 and 5150 m.a.s.l.
On July 1, 2021, the owner submitted to SENACE its Detailed Environmental Impact Assessment (EIA-d) for evaluation. Subsequently, on August 17, 2021, through Directorial Order
No. 00165-2021-SENACE-PE/DEAR, the Detailed Environmental Impact Assessment (EIA-d) of the Yumpaq-Carama Project was declared admissible, as well as the conformity of
the Citizen Participation Plan and the Executive Summary of the aforementioned assessment. Currently, it is under evaluation.
On July 1, 2021, Compañia de Minas Buenaventura S.A.A. submitted to SENACE the request for evaluation of its Detailed Environmental Impact Assessment (EIA-d) of the Yumpag
mining project, which is currently under evaluation..
Without registration.
Without registration.
177 Compañia de Minas Buenaventura S.A.A.: Annual Report 2021. February 18, de 2022.
178 Compañia de Minas Buenaventura S.A.A.: Detailed Environmental Impact Assessment (EIA-d) of the Yumpag Carama project [Executive Summary]. July 2021.
179 Compañia de Minas Buenaventura S.A.A.: Company Web Portal [Yumpag Project]. Consultation date: November 30, 2022.
Zafranal
80%: Teck Resources Copper (Canada);
Operator Compañia Minera Zafranal S.A.C. Investor180
20%: Mitsubishi Materials Corporation (Japan)
Region Arequipa
The project is located at an altitude range of 1444 to 2900 m.a.s.l., approximately 90 km in a straight line
to the northwest of the city of Arequipa.
Jobs in operations181 1210 Ore reserves181 440.7 Mt@ 0.38% Cu, 0.07 g/t Au. - (P&P)
The Zafranal project aims to extract copper sulfides with gold content. In addition, it seeks to obtain water use permits and build infrastructure related to water management, to
which end it must first demonstrate that there is an available volume that can be used in the project.
On December 21, 2021, Compañia Minera Zafranal S.A.C. submitted to SENACE the request for evaluation of its Detailed Environmental Impact Assessment (EIA-d) of the Zafranal
mining project, currently under evaluation.
Without registration.
Without registration.
180 Standard and Poor’s (S&P Global): Zafranal – Ownership Information [Market Intelligence from the Official Website]. Consultation date: October 17, 2022.
181 Compañia Minera Zafranal S.A.C.: Detailed Environmental Impact Assessment for the Zafranal Mining Project [Project Description]. December 2021.
182 Perumin 35: Presentation of the Zafranal project status [Corporate Presentation]. September 28, 2022.
183 Revista Rumbo Minero:“ Zafranal mining project, estimated to generate 3,000 direct jobs and about 1,000 indirect jobs at the peak of the mine's construction". [Interview with Zafranal company representatives].
August 2022.
184 Compañia Minera Zafranal S.A.C.: “Information presented by the mining owner to the Ministry of Energy and Mines (MINEM)” September, 2020.
2023
PORTFOLIO OF MINING
INVESTMENT PROJECTS
DIGITAL VERSION
WWW.GOB.PE/MINEM