MINUTES OF MEETING

Date: 02-Dec-22
Project: STYLE TEXTILE (PVT) LIMITED. Time: 12:00 AM
Subject: MINUTES OF MEETING
Agenda: Site Related Issues
Venue GM Engineering/ Projects Office.

Participants
Style Textile (STM) A.S Enterprises (ASE)

Mr. Zulfiqar Ali HOD (Civil) Malik Adnan Ashraf DPM

Husnain Raza GM Projects


Riasat Ali PM

Aadil Noshairwan DGM

S.
Building Description Reply Remarks
No.

Hardonat flooring is on hold 02x pannels due to


Client did not commited any time line regarding the
1 FF-2 incomplete work by M/s ISPL since November 27,
completion of M/s ISPL scope of work.
2022.

It commited by the client that first floor will be


ASE required work space/ Approval for the floor polish
handedover on 31/12/2022 and Ground Floor will
2 P-3 of P-3 & P-2 by the client, as all internal activities are
hadedover on 31/1/2022 to A.S for floor polishing
completed.
activity.

Purchaseorder was issued to Agha steel Karachi,


3 Sky Bridge Supply of Steel for the Sky bridge foundations.
Delivery still awaited.

4 External Roads Development. Following dates are commited for road completion.

i) Yarn to Ecru Road 25/01/2023


S.
Building Description Reply Remarks
No.

ii) Ecru to FF-2 15/02/2023

No date is committed subject to completion of sky


iii) P-2 to FF-2 ETP Side Road
bridge.

iv) P-2 to FF-2 Admin Side Road 28/02/2023

P-3 Lift well finishing required H Line / 34 grid Lifts will be hadedover to Mr. Aadil till 12/12/2022

ASE requested for the release of revised issued for


construction drawings of all the office areas as Client did not commited any time line regarding the
P-3
construction work in all offices is on hold at clients's issue.
end.

P-3 Raising machine foudations Between P-3 & FF-2 5/1/2023

P-3 Heat Recovery Pump room masonry and plaster 30/12/2022

On hold due to erection/ Fabrication of Pipe bridge.


P-2 P-2, CS to P-3 link at 17 grid
No work space is available.

P-3 P-3 washrooms Admind Side 31/01/2023

P-3 P-3 washrooms ETP Side 28/02/2023 subject completion of sky bridge

P-3 P-3 Compactor Drains inside area cleaning 15/12/2022

Mecanical work shop Dismanting / reconstruction


P-3 25/12/2022
according to revised plan
All walls Opening need to be closed for security
P-3 20/12/2022
pupose

P-2 Engineering office Extension 3/1/2023


S.
Building Description Reply Remarks
No.
Cleaning of area at +107.550 level where floor is on
P-2 26/12/2022
hold by client

P-2 Louver Marbal sill at +107.550 25/12/2022