Professional Documents
Culture Documents
SPE Paper Swell Packer Case Histories
SPE Paper Swell Packer Case Histories
In each of the 3 zones, one packer was installed at the top A reservoir completion string consisting of 11 intervals
part of the permeable zone against early gas influx, one packer with intermittent Swell Packer, injection sliding sleeve (with
was installed in the bottom part of the zone against early water built in nozzles) sliding sleeves and blank was installed
influx and one in between the zones in barrier rock against efficiently. The well was completed to surface. The rig
crossflow between the zones. 8 packers in total were installed continued operations on the next well while the packers
with a downhole static temperature of 98°C. 7” slotted liner developed sealing through swelling in oil based mud for 2
with sized slots was selected for sand control. 7” liner was weeks and coiled tubing was mobilized. Simultaneous coiled
used to allow the concentric string with surface controlled tubing operations were commenced. The pressure in each
inflow. interval was measured by opening one and one zone
independently. A small stimulation operation was injected
Operationally, no challenges were experienced during through coiled tubing. A water fracturing operation with the
installation of the packers through a milled window and out water injection facility was injected at max rate. The
into the open hole. After installing the outer string with slotted differential pressures across intervals during operation was in
liner and packers, the smart well equipment was installed as an the range of 100bar. The completion method saved several
internal string. The smart well equipment consisted of weeks by eliminating cementing and running liner,
hydraulic on-off valves controlled from surface with fiberoptic perforating, cleanups, running of sliding sleeve assemblies .
gauges for pressure and temperature.
Eliminating cementing and perforating in slimhole
At initial testing of the downhole valves, 15 days after through tubing rotary drilling
installation of the packers isolation between the zones was
observed on the gauges. A through-tubing rotary-drilling campaign in a North Sea
targeted low cost development of marginal reserves. The
The well has at the time of writing has produced project was deemed very successful from a technical point of
selectively for 8 months with clear proof of isolation. view but was not on track to deliver economic targets. The
challenges that prevented the campaign's cost savings were
Selective stimulation of carbonate horizontal cleaning out of debris after the liner cement jobs, perforating
The operator of tight carbonate formation on a offshore the wells with coil tubing and achieving zonal isolation.
installation in the North Sea needed sequencial stimulation of Alternating zones of strong water drive and lower pressure oil
the formation. The requirement was to divert the treatment zones were anticipated and therefore zonal isolation was a
along the 1400m long wellbore and achieve a well distributed requisite for the economy of the projects. Precise depth
inflow profile. It was very important to control flow in the location of isolation was important to target the reserves.
reservoir.
A thorough and in-depth programme was completed to
Previous practice had been drilling long horizontal drainholes qualify the vendor quality system. A full scale test including
and cementing liners for zonal isolation. After cementing, a simulated washout was successfully executed to exceed the
process involving perforating, large volume pumping 2300psi open hole sealing requirement.
operations with boat based fracturing skids and running
packers with sliding sleeve assemblies. After running the The well was successfully drilled and the 2.875" liner with
sliding sleeve assemblies, the operation was repeated with new 12 Swell Packers with 4.2" outer diameter elements were run
perforations, new stimulation etc. This sequence may be through the 4.5" window without any weight indication going
repeated ten or even more times. The financial impact of this through the window or any other installation challenges. The
was that a coiled tubing spread, an expensive fracturing vessle well produced at a higher than predicted flowrate with low
and a rig was occupied for a long period with long inactive water cut and the sustained low water cut confirmed the
periods. functionality of the packers.
[Paper Number] [PAPER TITLE] 3
The well cost was within the cost target, with the main temperature of 170°C and initial pressure of 900bar. At about
difference in well cost attributed to reduced downtime, 450bar, compaction forces will cause sand control problems. 3
avoiding cementing, cleanout operations and perforating main zones exist. The bottom zone has the highest
including coiled tubing deployment. An improvement of zonal productivity while the top zone has the largest reserves..
isolation was seen compared to offset cemented wells. Between these two zones is an unstable shale interval of 30m
TVD thickness. After production startup it will become
Replacing gravel pack offshore Norway progressively more difficult (or impossible) to drill any new
A mature offshore field in the North Sea has many small wells in the area due to depletion. Interventions to internally
accumulations. Sidetracks and subsea tiebacks can extend the gravel pack will be complex or impossible and predicted to
field economic life significantly. The field was originally have unsatisfactory productivity performance.
completed with perforated liners and when sand production
occurred, the monobore completions were gravelpacked A qualification programme has been completed in
through tubing. Severe production impairment was conjunction with the operator for developing a packer suitable
experienced due to fines migration and scale deposition. For a for the downhole conditions with reservoir gas and the higher
period, open hole gravelpacking was therefore the preferred temperatures.
sand control method. Due to cost, operational complexity and
continued plugging challenges even in open hole, the practice The operator choses to install primary open hole screen
had limited application. Limiting production rates combined completions with isolation above and below the shale. The
with oriented perforation became the dominant sand control wells are drilled with brine based drilling fluids to be flowed
solution. back through the screen. These measures are used to minimize
Through 4D seismic and other methods, accumulations with plugging of the wire wrapped sand screens.
remaining reserves are identified. A reservoir segment was
identified in an interval that is prone to sand production. The For later well operations, shutting off the lower zone will
operator required demobilisation of fluid flow and particles in be performed by setting a plug across the interval of the shale
the annulus to avoid plugging of the screens with potential and Swell Packer.
production deferrment and screen failures. The slot size of the
wire wrapped screen was tailored according to the Rogaland
Research model. This model considers sieve analysis from all
available cores from different intervals to take into account the
heteregenity. The slot of the wire wrapped screen is designed
to let through the fines, but contain the coarse particles.
Multilateral
At the time of writing, these jobs are planned, but not yet
executed. An US operator is drilling and completing
multilateral wells in an enviromentally sensitive area. The
downhole temperature is slightly above 30°C and the oil is low
API. Each lateral is completed with slotted liner. To be
prepared for later interventions and setting of plugs in each
lateral to control water, the operator has chosen to apply Swell
Packers. The packer will be installed in the top end of the
lateral and at certain points in the horizontal section.
HPHT
A North Sea operator is developing a HPHT condensate field
with subsea installations. The field has an operating