1 Introduction
Hanover is located on the North Western side of Jamaica and is bordered on the
east by St. James, and on the South by the parishes of Westmoreland; the
Caribbean Sea forms the northern and western boundary of the parish. The parish
has a mountainous terrain, with the coastline marked by coves and bays. Hanover
covers an area of 430 km2. The highest point in the parish is the Dolphin's Head,
which serves as a landmark for ships at sea. The parish has three small waterfalls,
several coves, such as the Davis Cove, named after a prominent Hanover family,
along its coastline and large caves. In the centre of Lucea stands a clock tower.
Though it was installed in 1817, it is still fully functional.
. Hanover is known for the production of yams, sugar cane, ginger, rice, pimento,
turmeric, breadfruit and arrowroot. Hanover is celebrated for its fine breeds of cattle.
The principal towns are Lucea, Green Island, Hopewell, and Sandy Bay.
The tourism industry has played a major role in the economic activity of the parish.
A deep-water pier was built, but this has been restricted only to the shipping of molasses. In
1983, the port was closed, but the old Fort Charlotte still stands at one side of the entrance
to the harbour. The major hotels are located along the coastline.
National Water Commission (NWC) produces some 635,457 m3/month of water per
month in Hanover through five (5) surface sources. The average billed volume from
16,813 accounts is only 275,695 m3/month which translates to average non-
revenue water (NRW) of 359,762 m3/month i.e. 57% of production. This
unacceptable level of NRW has had an adverse impact on the level of service
provided to the people of the parish, on its financial performance and that of NWC.
NWC now provides water to some 80.78% of the population in Hanover, which is a
marginal improvement over that in 2001 when the level of coverage was 74%. The
reliability of service to those who are served by NWC is estimated to average 18
hours per day. The average utilization rate of the parish is 79.70%. Total length of
pipeline within the parish is 455 km with varying material types from CI, AC, GI,
PVC, ST and DI.
A Water Supply Improvement plan has been prepared for the parish and is
presented in this document. The WSIP for the parish will involve an expenditure of
$5.4732 billion over the next twenty years in carrying out a number of water supply
rehabilitation and upgrading works. A substantial portion of the proposed works is
aimed at addressing the unacceptable level of NRW through the replacement of
major sections of the aged and undersized water supply infrastructure and
3|Page
Draft Hanover WS PPLan – October 12 2011
improvement in water supply pressure management. It is planned to increase water
supply coverage to 93% of the parish population by end 2030, reduction in NRW to
30% and service reliability to 24 hours per day at that time.
4|Page
Draft Hanover WS PPLan – October 12 2011
5|Page
Draft Hanover WS PPLan – October 12 2011
Table 2.1 – Summary Information on Hanover Pipe Network
Portion of
Pipe
Approximate the
Diameter
Length (km) Network
(inches)
(%)
0.50 5.77 1.30%
0.75 12.79 2.88%
1 44.13 9.94%
2 19.82 4.47%
2 111.68 25.16%
3 41.74 9.40%
4 80.61 18.16%
6 31.87 7.18%
8 15.35 3.46%
9 0.89 0.20%
10 19.78 4.46%
12 31.63 7.13%
14 0.90 0.20%
18 6.79 1.53%
20 20.10 4.53%
443.85
6|Page
Draft Hanover WS PPLan – October 12 2011
Revenue water in the parish is only 3.3 million cubic meters, which is 42.6% of the
water produced. The remaining 0.7 million cubic meters relate to commercial
losses.It would be noted that 0.61M cubic meters of water is attributed to
unauthorized consumption (i.e. 8.1% of production). This is largely due to illegal
connections to sections of the water transmission main for use in informal
settlements.
7|Page
Draft Hanover WS PPLan – October 12 2011
Figure 3.1 – Water Balance for Hanover
8|Page
Draft Hanover WS PPLan – October 12 2011
4 Water Requirement
Demand Centres
The enumeration districts (EDs) that were used in the 2001 population census was used
to establish priority areas that will be targeted to be provided with water supply. EDs
with population densities in excess of 150 persons per square kilometres were grouped
to form these demand centres.
Figure 4.1 – Demand Centres
9|Page
Draft Hanover WS PPLan – October 12 2011
Pipeline
TYPES OF DATA
Subdivision
Enumeration
District (ED)
- Population Data
As far as possible, each demand centre (DC) is linked to a water supply system. It is
related to a water distribution system that now serves it or has the potential to serve by
it.
Set out in table 4.1 is information showing the population in each DC, indicating
estimates for 2010, 2015, 2030.
The estimated total 2010 population in the DCs is shown to be 6,374 (9.4% of parish
population)
10 | P a g e
Draft Hanover WS PPLan – October 12 2011
4.2 Current Water Requirement
Domestic Commercial &
Water Other Water Technical Total Water Supply
Supply Production Requirement Requirement Losses Requirement Surplus/Deficit
System gal/day) Population (gal/day) (gal/day) (gal/day) (gal/day) (gal/day)
Cascade 28,650 3,100 124,000 13,778 13,179 150,957 (122,307)
Kendal 41,600 2,555 102,200 11,356 19,136 132,692 (91,092)
New Milns 106,400 6,550 262,000 29,111 48,944 340,055 (233,655)
Shettlewood 567,721 14,096 563,840 62,649 261,151 887,640 (319,920)
Logwood 5,408,083 57,285 2,291,400 1,659,290 2,487,718 6,438,408 (1,030,325)
TOTAL 6,152,453 83,586 3,343,440 1,776,183 2,830,128 7,949,751 (1,797,298)
The current water supply situation in Hanover is that, overall, there is insufficient
water in the parish to meet the water requirement, even with the existing technical
losses (leaks, tank overflows, etc). There is a current water supply shortfall of some
2.7 mgd based on the existing water production levels and the water requirement in
the Demand Zones combined.
The average daily water production in the parish is 5.7 mg; the average day water
requirement (domestic, commercial, institutional, etc) in the Demand Zones is
estimated to be 5.8 mgd. Technical losses estimated to be 2.7 mgd.
Set out in the tables below are water supply scenarios based on whether the level
of technical losses are addressed and reduced to 30% at most or the conditions
remain the same. It would be noted that the deficit would increase to 3.8 mgd.
HANOVER - YR 2030
Domestic Commercial &
Water Other Water Technical Total Water Supply
Supply Production Requirement Requirement Losses Requirement Surplus/Deficit
System gal/day) Population (gal/day) (gal/day) (gal/day) (gal/day) (gal/day)
Cascade 28,650 3,708 148,335 16,482 13,179 177,996 (149,346)
Kendal 41,600 3,056 122,257 13,584 19,136 154,977 (113,377)
New Milns 106,400 7,835 313,418 34,824 48,944 397,187 (290,787)
Shettlewood 567,721 16,862 674,496 74,944 261,151 1,010,591 (442,871)
Logwood 5,408,083 68,527 2,741,096 1,984,932 2,487,718 7,213,745 (1,805,663)
11 | P a g e
Draft Hanover WS PPLan – October 12 2011
TOTAL 6,152,453 99,990 3,999,603 2,124,766 2,830,128 8,954,497 (2,802,044)
12 | P a g e
Draft Hanover WS PPLan – October 12 2011
Water Requirement in 2015 - NRW reduced to 30% of Production
13 | P a g e
Draft Hanover WS PPLan – October 12 2011
5 Water Supply Improvement Plans
The improvement to the water supply in Hanover will be based on
(a) Reducing the level of technical losses due to the aged water supply network;
(b) Rehabilitating the water facilities to increase output.
NWC has committed to significantly reduce the high level of NRW in the parish of
Hanover. This will include pipeline replacement works and improved pressure
management.
The Logwood Water Treatment Plant is the major plant in the parish, with an installed
treatment capacity of 7.5 mgd. Its average production in recent years has been 5.4 mgd.
The projects will be packaged as presented below. Details on the undertakings are
provided in section 6.
5.2.1 Component A
5.2.2 Component B
14 | P a g e
Draft Hanover WS PPLan – October 12 2011
5.2.3 Component C
5.2.4 Component D
15 | P a g e
Draft Hanover WS PPLan – October 12 2011
5.2.5 Component E
5.2.6 Component F
5.2.7 Component G
16 | P a g e
Draft Hanover WS PPLan – October 12 2011
5.1 Expected Benefits
The detailed audit of the Hanover Supply system will provide information that will be
used to help in defining detailed NRW reduction intervention activities. The results
of the audit will be used to target the most critical sections of the parish water
supply system that require attention and assist in scheduling of the required works.
The information will be used to populate the asset database for the parish which will
form a critical part of the asset management system (AMS) that will be established
for Hanover. A fully functional AMS will be a valuable operational tool that can be
used to sustain the benefits that will be derived from the various projects and
activities that are set out in this document.
Improved network infrastructure
• DMAs, pressure zones, SCADA etc.
Improved network data quality (GIS)
Improved asset management planning
High quality and continuous water supply service
Hydraulic network model
Extension of Service areas
Operational Improvements and Energy savings
Utility staff development
• Specialist technical and managerial know-how
• New technology and the know-how to use it efficiently
17 | P a g e
Draft Hanover WS PPLan – October 12 2011
5.1.1 Cost for Improvements - Summary
Budget Cost
Item No. Proposed Project for NRW Reduction in Hanover
in $JB
Component A
1 0.3
Water Treatment Plant and Intake Works Rehabilitation
Component B
Rehabilitation, Construction and Expansion of
2 0.27
Reservoir
Component C
3 Water Supply Enhancement 1.63
Component D
4
Supply of materials and Equipment and do General
0.41
NRW reduction
Component E
5 Pipeline Replacement Plan 1.826
Component F
6 0.045
Low Income Settlement Improvement
Component G
7 Pumping Station and Well Rehabilitation 0.08
4.561
Sub-Total - Works
18 | P a g e
Draft Hanover WS PPLan – October 12 2011
5.1.2 Economic Assessment
19 | P a g e
Draft Hanover WS PPLan – October 12 2011
6 Water Supply Projects
6.1 Cascade Demand Zone (H-1)
20 | P a g e
Draft Hanover WS PPLan – October 12 2011
Miscellaneous Non-Revenue Water Reduction NRW
It is planned to carry out miscellaneous non-revenue water activities on the Cascade water
supply system to include:
• Creation of new flow/pressure zones and installation of gate valves, check valves,
flow control valves, pressure sustaining valves, control mate, air valves throughout
distribution
• Controls for all pumps within the distribution with pressure switch, timer, surge
vessel to reduce energy and water loss
• Installation of a new telemetry system for flow, level, pressure and water quality
and to create an electronic library including flow, level and pressure data collected
in the past years
21 | P a g e
Draft Hanover WS PPLan – October 12 2011
6.1.5 Cost for Improvements
The estimated total cost for the improvement works is $234M as shown below.
TOTAL 234,000,000
22 | P a g e
Draft Hanover WS PPLan – October 12 2011
6.2 Kendal Demand Zone (H-2)
23 | P a g e
Draft Hanover WS PPLan – October 12 2011
Pipeline Replacement/Upgrading
Pipeline replacement will be undertaken as follows:
24 | P a g e
Draft Hanover WS PPLan – October 12 2011
6.2.2 Cost for Improvements
The estimated total cost for the improvement works is $118.7M as shown below.
25 | P a g e
Draft Hanover WS PPLan – October 12 2011
6.2.1 Economic Assessment
26 | P a g e
Draft Hanover WS PPLan – October 12 2011
Logwood Demand Zone (H-3)
• Reduction in flow through the intake to the Logwood plant by up to 20% during
periods of drought
• There is need to provide the additional two raw water pumps for which
provision was made
• The treatment plant is not capable of producing water at its designed 7.5mgd
capacity because only three of eight pumps at clear water well are operational.
27 | P a g e
Draft Hanover WS PPLan – October 12 2011
• Sections on the distribution to Lucea and Negril experience excessively high
pressures and there are losses primarily from the aged asbestos cement and cast
iron type distribution network.
The planned works are presented below.
• Interconnection from the 18" (coming from Logwood, reaching the Highway) at
the taxi stop in the highway towards Savanna, near to Negril Spots, with the 8"
pipeline that was started four years ago. Interconnection should be provided
with a PRV because the pressure is about 15 bar from the main.
• Basic Telemetry system connecting Red Ground with Logwood WTP. The
system shall be able to show 5 different levels of the reservoir to the operator in
order to decide when to stop 2 pumps and keep running one for network
balanced operation.
• At Negril area, to interconnect and install a 150mm pipeline from the 18" main at
Sweet Spice restaurant with meter and PRV supplying White Hall and the road
towards Orange Hill. This will involve the use of the Redground and Westland
water storage tanks.
28 | P a g e
Draft Hanover WS PPLan – October 12 2011
• Extension of 4.5 km of new 100mm pipe from Keep Left in Lucea to Dry Hill
29 | P a g e
Draft Hanover WS PPLan – October 12 2011
General Non-Revenue Water Reduction NRW
• Active leak detection and Repair of detected leaks
• Controls for all pumps within the distribution with pressure switch, timer, surge
vessel to reduce energy and water loss
• Metering and Geo referencing of all customers. Macro and micro metering,
sizing, maintenance and replacement
• CS Analysis
Rehabilitation and Reinforcement of Small, Medium and Large Diameter Pipe Network
• Replacement of 16 km of Pipe 12’’ CI & AC with 250mm From Orange Bay PRV
to Negril PRV
• (Prospect): 2.3 km of Replacement of the 6" AC line that runs from the highway
towards Prospect and Kendall
• Replacement of 4 km of Pipe 12’’ AC with 300mm From Keep Left to Lucea PRV
at Molasses Tank
30 | P a g e
Draft Hanover WS PPLan – October 12 2011
• Replacement and upgrading of 0.6 km of Pipe 3’’ GI with 100mm From
Cambleton to March Town intersection
31 | P a g e
Draft Hanover WS PPLan – October 12 2011
Low Income Settlement Environmental Improvement
32 | P a g e
Draft Hanover WS PPLan – October 12 2011
6.2.6 Cost for Improvements
The estimated total cost for the improvement works is $3,781.2.7M as shown below.
33 | P a g e
Draft Hanover WS PPLan – October 12 2011
C. General Non-Revenue Water Reduction
NRW activities
Sub-Total C 300,000,000
D. Pipeline Replacement
Sub-Total D 1,393,300,000
Sub-Total E 20,000,000
Sub-Total A to E 3,150,970,000
TOTAL 3,781,164,000
34 | P a g e
Draft Hanover WS PPLan – October 12 2011
6.3 New Milns Demand Zone (H-1)
35 | P a g e
Draft Hanover WS PPLan – October 12 2011
An active leak detection campaign and repair of identified leaks will be undertaken.
There will also be the establishment of appropriate flow/pressure zones and installation
of gate valves, check valves, flow control valves, pressure sustaining valves, control
mate, air valves throughout distribution
Pipeline Replacement
It is planned to replace about 1 km of the leaking 4 inch diameter galvanized iron
pipeline from the New Milns Pump Station with 150 mm of PVC. In addition, provision
has been made to replace other sections of the water supply network..
36 | P a g e
Draft Hanover WS PPLan – October 12 2011
6.3.1 Cost for Improvements
The estimated total cost for the improvement works is $106.8M as shown below
37 | P a g e
Draft Hanover WS PPLan – October 12 2011
6.4 Shettlewood Demand Zone (H-1)
• Supply of Spare parts and materials to sustain production efficiency capacity and Preventative
maintenance
o Controls for all pumps within the distribution with pressure switch, timer, surge vessel to reduce
energy and water loss
Rehabilitation and Reinforcement of Small, Medium and Large Diameter Pipe Network
Replacement of 1’’ GI pipeline with 150mm to 100m from Axe and Daze to Chigwell
39 | P a g e
Draft Hanover WS PPLan – October 12 2011
6.4.1 Cost for Improvements
The estimated total cost for the improvement works is $473.1M as shown below
Sub-Total 394,220,000
40 | P a g e
Draft Hanover WS PPLan – October 12 2011
TOTAL
473,064,000
41 | P a g e