5
area de influencia x1 x2 y1 y2 Fc 21
2.45 0 2.1 1.95 Fy 420
Volcol 0.12
Volviga 0.29375
Vollosa 1.5827
Pp 47.9148
Cv 2.5
Cm 4.5
CVtotal 24.80625
Cmtotal 44.65125
u 753.8463 KN/M
B1 B2 B3 B4 B5
PISO
6 160.77 298.68 271.56 193.2 73.37
5 321.55 597.3786 543.13 386.41 146.75
4 COL 482.33 896.06 814.69 579.62 230.13
3 643.1 1194.7572 1086.26 772.83 293.51
2 803.88 1493.4465 1357.82 966.04 366.89
1 992.31 1819.7838 1657.04 1186.89 467.92
SECCIONES
PISO B1 B2 B3 B4 B5
6
5
4
3
2
1
Secciones
diametro de acero 10 Num de barras 8 40X40
d= 0.01 40X35
As= 0.000628319 cm 40X30
Ag= 0.04 30X30
ρ= 1.570796327 35X35
Ac= 0.039371681 30X25
ØPn 0.502672715 MN 30X20
ØPn 502.6727145 KN 20X20
No cumple 25X25
0.25 espesor losa 0.17 NUM DE PISOS 5
Mpa