Project

Management
Class - 1
The following are the different steps involved in the completion of a project which is
divided into various tasks - A through G. The project is completed when all the
activities are completed.

Q1. What is the minimum duration in which all the activities can be completed?

Q2. What is the maximum duration in which all the activities can be completed
provided there is no day in which none of the activity was performed?
The following are the different steps involved in the completion of a project which is
divided into various tasks - A through J. The project is completed when all the
activities are completed.

Q1. What is the minimum duration in which all the activities can be completed?

Q2. What is the maximum duration in which all the activities can be completed
provided there is no day in which none of the activity was performed?
The following are the different steps involved in the completion of a project which is
divided into various tasks - A through F. The project is completed when all the
activities are completed.

Q1. What is the minimum duration in which all the activities can be completed?

Q2. What is the maximum duration in which all the activities can be completed
provided there is no day in which none of the activity was performed?
The following are the different steps involved in the completion of a project which is
divided into various tasks - A through K. The project is completed when all the
activities are completed.

Q1. What is the minimum duration in which all the activities can be completed?

Q2. What is the maximum duration in which all the activities can be completed
provided there is no day in which none of the activity was performed?
The following are the different steps involved in the completion of a project which is
divided into various tasks - A through K. The project is completed when all the
activities are completed.

Q1. What is the minimum duration in which all the activities can be completed?

Q2. What is the maximum duration in which all the activities can be completed
provided there is no day in which none of the activity was performed?
The following are the different steps involved in the completion of a project which is
divided into various tasks - A through I. The project is completed when all the tasks
are completed.

Q1. What is the minimum duration in which the task can be completed?

Q2. At most how many tasks can be completed in the first 9 hours from the start?

Q3. What is the shortest possible time from the start by when task F can be
completed?
The following are the details of different steps involved in the opening of a store after
finalization of the premises. More than one work can be calmed one simultaneously
as long as all work to be completed before it are over.

Q1) What is the earliest time, from the start, by which the false ceiling work can start?
a) 7th day b) 8th day c) 9th day d) 10th day
Q2 If the work is to be finished at the earliest, then the maximum number of days we
can wait to start the fire safety work is?
TITA( If you can start the work on the 9th day, then you will mention 8 as your
answer)
Q3) What is the least time from the start in which all the work can be completed?
a) 12 days b) 13 days c) 14 days d) None of these
Q4) If the work is to be done in the least possible time, what can be the maximum
time gap between the start of the networking work and the start of the flooring work?
a) 4 days b) 5 days c) 6 days d) 7 days