Item Insumo Unidad Cantidad PU Parcial 01-05-2023 01-06-2023 01-07-2023


1 OPERARIO HH 2,338.43 26.40 61,734.53 3,909.85 37,613.87 20,210.81
2 PEON HH 8,219.12 18.75 154,108.52 19,361.12 72,410.31 62,337.09
3 OFICIAL HH 1,305.17 20.74 27,069.28 3,147.69 11,064.77 12,856.83
4 CAPATAZ HH 0.49 21.79 10.59 10.59 0.00 0.00
5 OPERADOR DE EQUIPO PESADO HH 130.06 27.40 3,563.74 3,415.14 148.60 0.00
6 OPERADOR DE EQUIPO LIVIANO HH 170.09 27.20 4,626.46 0.00 4,626.46 0.00
7 ALQUILER DE OFICINA, ALMACÉN Y CASETA DE GUARDIANÍA MES 3.00 1,400.00 4,200.00 4,200.00 0.00 0.00
8 ALQUILER SE SERVICIOS HIGIÉNICOS PORTÁTILES MES 3.00 520.00 1,560.00 1,560.00 0.00 0.00
9 GIGANTOGRAFIA IMPRESA A COLORES PARA CARTEL DE OBRA M2 17.28 54.00 933.12 933.12 0.00 0.00
10 MADERA TORNILLO P2 6,836.65 5.50 37,601.58 1,808.47 29,039.81 6,753.30
11 TRIPLAY LUPUNA 1.20 x 2.40m x 4mm PLN 4.00 41.90 167.60 167.60 0.00 0.00
12 CLAVOS KG 392.55 6.90 2,708.58 101.26 2,176.75 430.57
13 CEMENTO PORTLAND TIPO I (42.5KG) BLS 9,390.06 30.00 281,701.87 712.26 80,996.29 199,993.32
14 ARENA GRUESA M3 609.53 43.00 26,209.95 124.29 7,723.29 18,362.37
15 PIEDRA CHANCADA DE 1/2" M3 0.27 58.00 15.37 15.37 0.00 0.00
16 AGUA PARA LA OBRA M3 206.55 5.00 1,032.75 5.01 296.25 731.49
17 CARTEL DE DESVIO DE TRANSITO UND 10.00 60.00 600.00 600.00 0.00 0.00
18 CARTEL DE FIN DE DESVIO DE TRÁNSITO UND 5.00 60.00 300.00 300.00 0.00 0.00
19 CARTEL DE INICIO DE ZONA DE TRABAJO UND 5.00 60.00 300.00 300.00 0.00 0.00
20 CARTEL DE FIN DE ZONA DE TRABAJO UND 5.00 60.00 300.00 300.00 0.00 0.00
21 TRANQUERA DE MADERA UND 5.00 103.00 515.00 515.00 0.00 0.00
22 ALAMBRE NEGRO N° 8 KG 381.70 8.20 3,129.91 110.98 2,523.76 495.17
23 CLAVOS C/CABEZA PARA MADERA (PROMEDIO) KG 0.54 6.90 3.71 3.71 0.00 0.00
24 TRIPLAY LUPUNA 1.20 x 2.40m x 18mm PLN 0.32 170.90 55.13 55.13 0.00 0.00
25 GASOLINA GLN 688.10 18.20 12,523.41 483.16 3,675.29 8,364.96
26 PIEDRA CHANCADA DE 3/4" M3 613.96 55.00 33,767.65 157.76 9,688.18 23,921.71
27 CHALECO REFLECTIVO UND 30.00 15.90 477.00 429.30 47.70 0.00
28 RESPIRADOR CONTRA POLVO - UNA VIA UND 30.00 65.90 1,977.00 1,779.30 197.70 0.00
29 CASCO DE SEGURIDAD UND 30.00 15.90 477.00 429.30 47.70 0.00
30 ZAPATOS DE SEGURDAD PAR 30.00 55.00 1,650.00 1,485.00 165.00 0.00
31 LENTES DE SEGURIDAD UND 30.00 15.00 450.00 405.00 45.00 0.00
32 OVEROLES UND 30.00 73.90 2,217.00 1,995.30 221.70 0.00
33 CINTA DE SEÑALIZACION DE 350m (PELIGRO OBRAS) UND 15.00 53.90 808.50 808.50 0.00 0.00
34 ALARMAS AUDIBLES UND 5.00 100.00 500.00 500.00 0.00 0.00
35 LETREROS DE SEGURIDAD CON SOPORTE UND 10.00 82.00 820.00 820.00 0.00 0.00
36 CAMILLA DE PRIMEROS AUXILIOS UND 1.00 240.00 240.00 240.00 0.00 0.00
37 EXTINTOR PQS 6KG UND 4.00 120.90 483.60 483.60 0.00 0.00
38 BOTIQUIN DE PRIMEROS AUXILIOS UND 4.00 400.00 1,600.00 1,600.00 0.00 0.00
39 YESO BOLSA 28 kg BLS 28.01 25.00 700.26 214.73 384.77 100.76
40 PETROLEO GAL 2,094.67 19.60 41,055.56 38,915.49 1,997.41 142.66
41 MATERIAL CLASIFICADO GRANULAR # 1 M3 623.82 40.00 24,952.96 24,952.96 0.00 0.00
42 TRIPLAY DE 19 MM PARA ENCOFRADO PLN 47.17 155.90 7,354.52 0.00 7,354.52 0.00
43 DESMOLDANTE GAL 33.99 135.50 4,605.30 0.00 4,605.30 0.00
44 ADITIVO CURADOR DE CONCRETO GAL 269.18 44.90 12,086.37 0.00 9,249.82 2,836.55
45 ASFALTO RC-250 GAL 204.99 20.40 4,181.72 0.00 2,966.02 1,215.71
46 TECNOPORT DE 1" M2 238.15 10.50 2,500.54 0.00 2,467.61 32.94
47 ACERO LISO, GRADO 60, PROMEDIO KG 2,031.14 4.60 9,343.25 0.00 9,343.25 0.00
48 GRASA %MT 0.00 0.00 644.69 0.00 644.69 0.00
49 TUBERIA PVC SAP CLASE 10 3/4" M 1,160.65 2.97 3,447.14 0.00 3,447.14 0.00
50 ACERO CORRUGADO F'Y 4,200 KG/CM2 KG 2,318.81 4.60 10,666.54 5,274.38 5,364.36 27.81
51 PINTURA ESMALTE GAL 7.18 102.00 732.83 79.12 518.05 135.66
52 MATERIAL GRANULAR PARA AFIRMADO M3 162.86 48.00 7,817.47 0.00 7,817.47 0.00
53 ARENA FINA M3 3.88 80.00 310.03 0.00 166.65 143.38
54 CAJA DE CONCRETO PARA DESAGÜE 12"x24", PESTAÑA UND 85.00 47.00 3,995.00 0.00 3,995.00 0.00
55 CAJA PARA MEDIDOR DE AGUA DE 1" A 2" UND 85.00 45.00 3,825.00 0.00 3,825.00 0.00
56 GRASS M2 60.27 6.00 361.62 0.00 0.00 361.62
57 TIERRA DE CHACRA M3 13.78 36.30 500.07 0.00 0.00 500.07
58 PLANTAS NATIVAS UND 25.00 15.00 375.00 0.00 0.00 375.00
59 PLANTAS ORNAMENTALES UND 25.00 15.00 375.00 0.00 0.00 375.00
60 ALAMBRE NEGRO N° 16 KG 108.86 8.20 892.69 446.35 446.35 0.00
61 DISOLVENTE XILOL GLN 1.34 60.90 81.90 0.00 0.00 81.90
62 PINTURA PARA TRAFICO GAL 34.02 93.50 3,180.79 0.00 0.00 3,180.79
63 ADITIVO DISOLVENTE DISOLKRET DS-50 GL 15.20 69.32 1,053.56 0.00 0.00 1,053.56
64 SEÑALIZACION INFORMATIVA UND 6.00 555.02 3,330.12 0.00 3,330.12 0.00
65 SERVICIO PARA PLAN DE MITIGACIÓN AMBIENTAL EST 1.00 2,500.00 2,500.00 2,500.00 0.00 0.00
66 MANEJO DE RESIDUOS SÓLIDOS EST 1.00 1,800.00 1,800.00 1,800.00 0.00 0.00
67 MATERIALES Y MANO DE OBRA GLB 3.00 750.00 2,250.00 2,250.00 0.00 0.00
68 TACHOS ECOLÓGICOS SEGUN DISEÑO UND 15.00 418.00 6,270.00 0.00 0.00 6,270.00
69 PLACA RECORDATORIA GLB 1.00 850.00 850.00 0.00 0.00 850.00
70 HERRAMIENTAS MANUALES %MO 0.00 0.00 9,041.99 851.19 4,965.65 3,225.15
71 MEZCLADORA DE CONCRETO 18 HP 11-12 P3 HM 406.66 25.00 10,166.60 66.98 2,911.25 7,188.37
72 VIBRADOR DE CONCRETO 4 HP 1.50" HM 489.20 8.00 3,913.59 1.60 1,611.71 2,300.28
73 BARRENOS HM 0.70 398.00 277.72 277.72 0.00 0.00
74 COMPRESORA NEUMATICA 76 HP 125-175 PCM HM 0.24 74.00 17.76 17.76 0.00 0.00
75 CORTADORA DE PAVIMENTO, INC. DISCO HM 59.91 7.50 449.33 12.00 437.33 0.00
76 MARTILLO NEUMATICO 21-24 KG HM 14.42 5.70 82.18 82.18 0.00 0.00
77 VIBRADOR DE CONCRETO 4 HP 1.25" HM 0.35 7.00 2.46 2.46 0.00 0.00
78 GENERADOR ELECTRICO 2000W HM 13.94 60.00 836.21 836.21 0.00 0.00
79 PRISMAS HM 302.14 7.00 2,114.98 1,825.42 229.47 60.09
80 ESTACION TOTAL HM 151.18 15.00 2,267.69 1,955.98 247.02 64.69
81 TRACTOR SOBRE ORUGAS 190-240 HP HM 22.24 195.00 4,337.54 4,337.54 0.00 0.00
82 PLANCHA COMPACTADORA 7 HP HM 27.63 30.00 828.86 557.28 271.58 0.00
83 RODILLO LISO VIBRATORIO MANUAL 10.8 HP 0.8-1.1 TN HM 9.29 31.76 294.99 294.99 0.00 0.00
84 CAMION CISTERNA AGUA 4X2 145-165 HP 2000 GAL HM 0.53 128.96 67.81 67.81 0.00 0.00
85 CARGADOR SOBRE LLANTAS 125-155 HP 3 YD3 HM 146.43 170.08 24,905.12 23,693.13 1,177.77 34.22
86 ZARANDA ESTATICA HM 0.97 10.00 9.65 9.65 0.00 0.00
87 VOLQUETE 6X4 330HP 15M3 HM 191.42 150.00 28,712.39 26,881.62 1,710.56 120.21
88 RODILLO LISO VIBRATORIO AUTOPROPULSADO 101-135 HP 10-12 TN HM 28.07 150.00 4,210.82 4,210.82 0.00 0.00
89 MOTONIVELADORA 125 HP HM 28.07 180.00 5,052.98 5,052.98 0.00 0.00
90 CAMION CISTERNA AGUA 4X2 178-210 HP 3000 GAL HM 29.49 135.00 3,980.72 3,818.50 154.28 7.94
91 BOMBA PULVERIZADORA HM 36.07 7.50 270.54 0.00 207.05 63.49
92 NIVEL TOPOGRAFICO HM 23.30 15.00 349.43 37.72 247.02 64.69
93 MIRA TOPOGRAFICA HM 23.30 7.00 163.08 17.61 115.28 30.19
94 MAQUINA PARA PINTAR MARCAS EN EL PAVIMENTO HM 2.47 60.00 148.34 0.00 0.00 148.34
95 MAQUINA PARA MARCAS EN EL PAVIMENTO HM 1.78 60.00 106.59 0.00 0.00 106.59
96 MAQUINARIA PARA PINTADO DE SARDINEL HM 15.20 35.00 531.95 0.00 0.00 531.95
97 REHUBICACIÓN DE POSTES DE CONCRETO GLB 10.00 1,400.00 14,000.00 14,000.00 0.00 0.00
98 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS GLB 1.00 4,000.00 4,000.00 4,000.00 0.00 0.00
99 PAGO DE TRAMITE AL MINISTERIO DE CULTURA EST. 1.00 2,000.00 2,000.00 2,000.00 0.00 0.00
100 ELABORACION DEL PMA GLB 1.00 4,000.00 4,000.00 4,000.00 0.00 0.00
101 ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE SEGUR GLB 1.00 4,100.00 4,100.00 4,100.00 0.00 0.00
102 CAPACITACION DE SEGURIDAD Y SALUD GLB 1.00 2,500.00 2,500.00 2,500.00 0.00 0.00
103 CONCRETO PREMEZCLADO F'C=210 KG/CM2 M3 669.65 380.00 254,466.24 0.00 254,466.24 0.00