Note: Operation hours/Manhours includes excavation and loading onto truck/hauler.
Soil Type Excavator Bucket Size Operation Hours per 100m3 of excavation
Excavator Operator Mechanic Laborer
Light 0.75 m3 Bucket 1.84 1.84 1.84 1.84
0.5 m3 Bucket 1.97 1.97 1.97 1.97
0.3 m3 Bucket 2.62 2.62 2.62 2.62
Medium 0.75 m3 Bucket 3.41 3.41 3.41 3.41
0.5 m3 Bucket 4.98 4.98 4.98 4.98
0.3 m3 Bucket 5.76 5.76 5.76 5.76
Heavy 0.75 m3 Bucket 4.58 4.58 4.58 4.58
0.5 m3 Bucket 5.24 5.24 5.24 5.24
0.3 m3 Bucket 6.41 6.41 6.41 6.41
Hard Pan 0.75 m3 Bucket 5.76 5.76 5.76 5.76
0.5 m3 Bucket 6.02 6.02 6.02 6.02
0.3 m3 Bucket 7.98 7.98 7.98 7.98
Rock 0.75 m3 Bucket 5.76 5.76 5.76 5.76
0.5 m3 Bucket 6.02 6.02 6.02 6.02
0.3 m3 Bucket 7.98 7.98 7.98 7.98
EXCAVATION MAN HOURS - MANUAL LABOR Note: Man hours includes excavation and loading onto truck/hauler. Soil Type Soil Condition Manhours per one (1) cubic meters of excavation
First Lift 2nd Lift Third Lift
Light Dry 1.4 1.84 1.84
Wet 2.1 1.97 1.97
Medium Dry 2.1 3.41 3.41
Wet 2.8 4.98 4.98
Heavy Dry 3.5 4.58 4.58
Wet 4.2 5.24 5.24
Hard Pan Dry 4.9 5.76 5.76
Wet 5.6 6.02 6.02
DISPOSAL OF HAULED MATERIALS
Note: Driver Manhours will be equal to the operation hour of the Truck / Dump Truck / Hauler
Manhours per 100 cubic meter of hauled materials
Truck Capacity Distance of Hauling Average Speed 10 KPH Average Speed 20 KPH