Mfg.
Location
Voltage Class
Main Bus Current Rating
Total Breakers and Types
Total Relays and Types
VISUAL INSPECTION
Yes No
1. General inspection of exterior of equipment.
2. Check panel lights for operation, burned out or missing bulbs LED's and
covers.
3. Inspect for damaged, bent, or twisted doors and verify ground bonding.
4. Inspect for broken instrument, relay cover glass and damaged phase
indicator lights.
5. Inspect bus for physical damage, missing insulation, connections at joints,
confirm plating is acceptable.
6. Check cleanliness of interior of cubicle
7. Inspect insulation, stand-off insulators, and bus separators for damage or
clearance problems.
8. Inspect for proper compartmentalization as required.