What are the swords and shields in standard forms, in general, for Employers and Contractors?
Please discuss with examples from
any contract form. Please pick one form.
SIA, Lump Sum Contract,
“Swords & Shields” – Contract mechanisms for ensuring compliance and obligations are carried out. Clause Employer Contractor 1.(1) Written and Verbal Directions 1.1 Shield: Without the Architect’s written confirmation, and Instructions: The the Contractor shall not be entitled to Contractor shall always carry compensation or expense incurred by complying out the Works in accordance with any instructions of any Clerk-of-Works. with the Contract and all written directions and instructions by the Architect. Any verbal direction or instruction by the Architect shall be deemed to have been given in writing. Clause Employer Contractor 1.(7) Remedy on Non-compliance by Sword: Minimizes work disruption to project schedule Shield: In cases where Contractor does not have sufficient Contractor: If the Contractor while imposing additional cost onto defaulting resources to comply, having replacement contractors fails to comply with written Contractor. would potentially avert Liquidated Damages for late Architect’s direction/instruction completion. Financially, the Contractor does not within 7 days, Employer may suffer if no extra cost is incurred. employ other contractors. The extra costs (if any) to be deducted from monies otherwise due under the contract or recovered from the Contractor. Clause Employer Contractor 1.(8) Compensation to Contractor: If Shield: No additional cost or EOT will be granted for Shield: Provides assurance for Contractor to comply with Architect gives any any damage, liability, expenditure or cost any direction/instruction and to promptly execute direction/instruction which is incurred due to the Contractor’s default. obligations without raising “questionable subsequently found to have no direction/instruction from Architect” as a defense. power under contract or no justification, and Contractor duly compiled – then Contractor is entitled to additional payment or compensation, and extension of time if appropriate – except in cases where direction/instruction is reasonable consequence of negligence, defective work or breach of contract by Contractor. Clause Employer Contractor 2. Methods of Working and Sword: The Architect reserves the rights of issuing Shield: If any accidents, loss, liability, claim or damage Temporary Works: The change order, without any obligation to do so and subsequently occurs solely due to using the methods Architect may give a direction at his entire discretion, to ensure that the of working or temporary works ordered by a or an instruction requiring the Contractor applies appropriate construction direction or instruction of the Architect, the contractor to change his methods of working and temporary works. Employer will indemnify and if appropriate pay methods of working or compensation to the Contractor. temporary works. 3. Design and Completion Shield: The Contractor shall be entitled to additional Responsibilities: The Architect payment or compensation or extension of time on shall give the information about the like terms because of any act or neglect of the varied work to the Contractor Employer or of other contractors engaged by the when issuing relevant variation Employer, or due to an instruction or direction of the order Architect. Clause Employer Contractor 4. Programme: Disapproval of the Shield: Until the dispute of the program has been resolved, sufficiently detailed program by the contractor should be allowed to proceed with the the Architect shall not prevent work. This is so that contractor is able to safeguard the Contractor from starting his obligation to meet the contractual timeline. work, but may be considered in determining any dispute as to a reasonable sequence or order for affording possession of the Site of for supplying further information. Clause Employer Contractor 5. Make-up Contractor’s Prices: In Sword: Ensure Contractor provides detail breakdown Shield: The Contractor reserves the rights to adjust rates or the Schedule of Rates, the before commencement of work. prices, and to start work if he has submitted above Contractor shall submit required documents. breakdown of prices and indicate Letter Q, Letter T, and Letter F requiring adjustment. All categories of expenditure contemplated by those items not included in his other rates and prices shall also be indicated precisely. Preliminary items for which the Contractor has not given key letter indication shall be deemed to be fixed. Clause Employer Contractor 6.(3) Dismissal of Persons Sword: Ensures the compliance of all staff of the Employed: Architect may give Contractor in executing their obligations. directions requiring the dismissal from Works of any person employed whose continued employment by the Contractor may prejudice the satisfactory and expeditious completion of the Works. 7.(1) By-Laws and Regulations: Shield: Any delay in Architect’s direction/instruction to Shield: Entitled to claim for EOT, and compensation of fees Contractor can proceed with cover for the works to comply statutory and charges incurred as a result of complying with work conforming to statutory obligations does not prevent Contractor from statutory obligations. obligations even without executing statutory obligations. variation order by Architect within 7 days of the written notice, with EOT and monetary compensation as appropriate. Clause Employer Contractor 8. Setting Out: The Architect shall Sword: If any errors arise due to inaccurate setting out Sword: If the Architect fails to furnish the required accurate determine the levels for by the Contractor, the Architect reserves the right drawings, then the Contractor may be exempt from executing the Works and to decide either to amend them at the cost of the the errors and retain the right to claim for any loss. provide accurately dimensioned Contractor, or accept them without amendment, drawings for the Contractor to subject to reduction in the Contract Sum. set out the Works. 10. Possession of Site and Shield: The Architect may set restrictions upon Sword: If no expressly agreed date by the parties, the Commencement of Work: If no possession of the whole of the Site in the Contractor shall be entitled to freely and Contract Commencement Date Appendix to these Conditions or in the uninterruptedly possess the whole area of the Site is stated in the Appendix, or if Specifications. regardless of Specifications or Drawings and be such date in the Appendix entitled to Special Access to the Site which the becomes invalid due to some Employer is responsible to provide. reasons not responsibility of the Contractor, then such date shall be deemed to be such other date agreed by the parties or be a reasonable date. Clause Employer Contractor 11. Quality of Material and Sword: Architect may ask for removal or demolition of Shield: Contractor is entitled compensation for additional Workmanship: Architect may work/goods/material which is not in accordance expenditure or delay resulting if test or request to be furnished with with the contract with reconstruction and investigations find no evidence of defective work by proof of quality of replacement in accordance with contract. the contractor. material/goods/workmanship Shield: Ensures quality of materials/goods/workmanship from the contractor. Architect provided by the contractor. may request for test or investigations to be carried out to verify quality of material/goods/workmanship. 12. Variation and Valuation of Sword: Architect may sanction and variation by the Sword: Contractor is entitled to additional payment, Additional Payments: Architect contractor without input from Architect or compensation and/or extension of time for has the power to at any time Employer with no entitlement to the Contractor variations by the contractor that was made in an give directions or instructions to additional payment, compensation and/or emergency or in the case it was not practical to for a variation to be made in the extension of time. obtain instructions from the Architect. original contract work. Clause Employer Contractor 13. Schedule of Rates: This clause Shield: Prevent the contractor to amend the rates as specifies that the schedule of specified due to any cost incurred by the rates shall be inclusive of all Contractor that was previously not taken into work, material and expenditure account to bring the work to completion. required to bring the works to completion. 14. Discrepancy or Divergence: In Shield: Protects the employer to unfavorable works that Shield: If due to the discrepancy or divergence, the the event there is discrepancy or are not of employer’s intention when there is a Architect were to give instruction that differs from divergence in the contract divergence in the contract. the interpretation of the Contract as a whole, or if document to the exact nature of the Contractor has been reasonably misled to his work to be carried out, it is the detriment when pricing, the Contract sum may be contractor’s responsibility to increased and if necessary an appropriate extension notify the Architect for further of time will be granted. instructions. Clause Employer Contractor 15. Assignment and Sword: Employer is protected from damage or loss due Sword: Employer shall not withhold consent for the Sub-Contracting: Defines the to the action of the subcontractor and in this is engagement of subcontractor if the subcontractor is scope allowable to be treated as an agent of the Contractor. of a class and good standing and appropriate for the subcontracted out and the Shield: Makes contractor solely responsible for own type of work to be carried out. conditions around actions and obligations, instead of blaming third subcontracting. Contractor parties not privy to the contract. cannot assign or make arrangement for vicarious performance of main contractor’s functions – such as controlling site with own site staff, coordinating work of any sub-contractor and ordering materials for the Works. Clause Employer Contractor 16. Plant and Materials: All plant Sword: Employer has the right to keep on site plants, Shield: Consent for the removal of plant or facility cannot and temporary buildings temporary buildings, unfixed material and be unreasonably withheld if no further work brought onto the site be deemed delivered goods that is required for ongoing appropriate to the plant or facility remains. to be the property of the works that has yet to be completed. Employer and consent of the employer is required before these are removed from the site. Similar consent is required for any unfixed material and goods delivered on site. 17. Artist, Tradesmen and Other Shield: Employer is able to hire other skilled Contractor: The contractor is professional and grant them access to the site unable to refuse entry to during which time works are being carried out by artist/tradesmen/other the Contractor. contractors engaged by the employer. Clause Employer Contractor 18. Indemnities to Employer: The Shield: Employer is protected from liability from Shield: Contractor is released from liability of loss arising Contractor is liable for and personal injury or damage to property in regards due to the willful neglect of the Employer. shall indemnify the Employer to completion of work by the Contractor. from losses arising when Works are carried out as part of the Contract. 19. Insurance against Injury to Sword: If the Contractor defaults on payment of the Persons and Property and Work premium of the insurance, the Employer may Injury Compensation: The exercise the right to pay the premium on the Contractor is to maintain Contractor’s behalf and subsequently deduct the insurance. To cover liability due cost of which from the sum due to the to personal injury and loss due Contractor. to the works being carried. Clause Employer Contractor 20. Insurance of Works: Covers the Sword: Ensure contractor carry out work as directed by extent of insurance and to Architect. whom payment is to be made in Shield: Contractor to maintain insurance protecting the the event of claim. Upon interest of the Employer to the full value of the occurrence of any loss or works and all unfixed goods and materials damage to the Works, the delivered. payment from the insurer is to be made to Employer and payment by the Employer is to be made to the Contractor as repair/restoration/replacement of the damage has been carried out. Clause Employer Contractor 23. Extension of Time: To be entitled Shield: Retains employer’s right to liquidated damages Shield: Grants reasonable time extension and monetary for EOT, the Contractor must by mitigating the possibility of rendering time “at reimbursement, should delays be due to neutral have been carrying out the works large” for delays caused by employers. events or employer-caused events – rather than with due diligence and must have undue financial burden or bankruptcy due to heavy taken all reasonable steps to imposition of such LDs. avoid or reduce any delay due to neutral events and/or employer’s default/ delay. 23.(2) Notice (condition precedent to Sword: If Contractor fails to comply with the EOT): Contractor to notify notification period and/or fails to furnish Architect within 28 days in sufficient explanation to justify for the EOT, then writing of any event or the Architect as the administrator the contract is direction/instruction which he not obliged to grant any EOT. This minimizes considers entitles him to EOT, indiscriminate and unsubstantiated claims for together with sufficient EOT from the contractor. explanation why delay to completion will result. Clause Employer Contractor 24. Liquidated Damages: Upon Sword: Ensures Contractor strives to complete Shield: The LD amount being known at the point of tender, receipt of Delay Certificate, obligations on time. will allow the Contractor to price for the risk of Employer can recover from non-compliance to the contractual completion date. Contractor liquidated damages If the LD is too low, the contractor may choose to calculated at the rate stated in pay the LD amount as oppose to incurring additional the Appendix from date of cost to expedite the works to complete the works by default certified by Architect. the contract completion date. On the other hand, if The LD amount may be the LD amount is too high, it would be considered deducted in whole or part from as a penalty, and thus, be not enforceable in court. any monies due under the Contract at any time. Clause Employer Contractor 26. Partial Re-Occupation: Upon Shield: Reduces the financial burden of the Contractor. issuance of Certificate of Partial Occupation, a proportion of the first half of the Retention Monies in respect of the Occupied Part shall be released to the Contractor within 14 days of re-entry by the Employer. Similar approach would apply to release of the second half of the Retention Monies on the same basis. In addition, the maintenance of the occupied part would commence upon the re-entry. Contractor can also apply for reduction in the value of Works insured. Contractor’s liability shall also be reduced proportionately. Clause Employer Contractor 27. Maintenance Period: Any defects Sword: Failure to comply with the contract on the due to failure of Contractor quality of materials and workmanship, results in (including subcontractor or the Contractor having to remedy at his own supplier) to comply with his expense and without EOT entitlement. If obligations under the contract defects are accepted, then contract sum is shall be made good by the reduced. contractor at no cost to the Employer. Default period of 6 months from Completion Certificate if not stated in the Appendix. - Allowance for Defect: Architect may give directions for the removal or demolition of any work, goods or materials, whether fixed or unfixed, which are not in accordance with the Contact, and for the reconstruction or replacement in exact accordance with the Contract.
If Architect accepts defective work,
Clause Employer Contractor 29.(2) Objections to Nomination: Shield: Grants Contractor the right to protect himself from The Contractor is entitled to potential damages incurred from default or object to a Nomination incompetence of Nominated Sub-Contractor or Instruction when Nominated Suppliers or Designated Sub-Contractor or Sub-Contractor or Suppliers’ Suppliers. financial standing or solvency or technical competence or reliability is not qualified, as well as the terms of subcontract offered by Nominated Sub-Contractor or Suppliers, or Designated Sub-Contractor or Suppliers are unsatisfactory. Clause Employer Contractor 29.(3)(a) Powers following Shield: Prevents delay to work due to non-appointment Shield: Contractor can carry out related works by himself to Objection: After Contractor of subcontractor. prevent potential damages brought by Nominated raises a valid objection to a Sub-Contractor or Suppliers or Designated Nomination Instruction, Contractor or Suppliers. If Architect instructs Architect can instruct Contractor to enter into the sub-contract, according Contractor to carry out related to the clause, Employer will guarantee the works by himself, or instruct Contractor against any loss, damage, claim or Contractor to enter into a expense. Moreover, Contractor can be granted with sub-contract notwithstanding EOT where necessary. the valid objection. Provide assurance that Contractor will be paid for the work carried out with the Architect’s instruction; or Contractor will not be held responsible for default of the nominated subcontractor for matters validly objected by the Contractor Clause Employer Contractor 30.(2) Early Final Payment: If the Shield: Early Final Payment can only be issued when Architect wishes to secure final Sub-Contractor or Supplier has satisfactorily payment to any Designated or indemnified the Contractor against any defect or Nominated Sub-Contractor or unsuitability subsequently appearing in his work. Supplier before final payment is Moreover, if there are defects or unsuitability of the due to the Contractor, then the work not apparent at the relevant date to which the Architect may in an Interim Certificate relates, the Contractor shall be Certificate include an amount discharged from any further liability for the to cover such final payment. maintenance of the work during the Maintenance Period. 31.(2) Payment Claim: The Sword: Contractor should submit a payment claim to the Employer on the stipulated date. 31.(8) Retention Monies: Part of Shield: Compensate the Employer’s loss from potential progress payments not paid to defects found during Maintenance Period. the Contractor. Clause Employer Contractor 31.(12)(a) Final Certificate: Sword: Grants the Contractor with the right to get money Indicates final balance due due from the Employer. from the Employer to the Shield: Secures the Contractor to get money due from the Contractor or from the Employer. Contractor to the Employer. 31.(12)(b) Outstanding Balance of Shield: The Employer pays any such sum into a special Nominated Sub-Contractors bank account in the case of dispute about and Suppliers: The Architect balances of Nominated Subcontractors or may certify direct payment by Suppliers. The Employer can deduct this from the Employer to any Nominated any sums then certified as payable by him or Sub-Contractor or Supplier and recovered this from the Contractor. unpaid. Clause Employer Contractor o 32.(1) Termination without Shield: Reserve compensation rights in the event of Default: The Employer may at termination without Termination Certificate. any time and for any reason give the Contractor written Notice of Termination which shall have the effect of immediately terminating the employment of the Contractor. Contractor is entitled to compensation for all damage and loss suffered by him as a consequence of the termination of his employment. Clause Employer Contractor 32.(2) Termination for Default: If Sword: Ensure the Contractors comply with the contract final Contract Sum in Cost of provisions so as the project can proceed with Termination Certificate less diligence and due expedition. Failing to do so than Completion Cost certified, enable the Employers to terminate the contract then difference is the sum due without any compensation to the Contractors. from Contractor to Employer. 32.8 (g)(i)Ensures that Contractor carries out due Furthermore, if final completion diligence to fulfill contract obligations by having the by replacement contractors is mechanism to recover cost for engaging replacement delayed beyond the Contract contractor as well as imposing LDs should there be Completion Date, then the delay in completion of the works following the damages certified in termination. Termination Delay Certificate would be payable by the Contractor to Employer. Clause Employer Contractor 33. Termination by Contractor: The Shield: Entitle to suspend any work and claim for contractor shall be entitled by a compensations for works already completed, losses written Notice of Termination and expenses, damages incurred as a result of the given to terminate his termination. in the event of where Employers are not employment under the Contract able to comply with regulations based on the grounds on any of the following grounds in 33-1. in clause 33-1. 34. Outbreak of War: In the outbreak Sword: Contractors still must comply with the Shield: Subjected to payment claims from the Employer for of war, either the Employer or instructions given by Architect to execute the the extended protection works Contractor may at any time by protection work after the notice of termination notice, by registered post or Shield: Entitled to any work compensation due to war recorded delivery forthwith damages which is payable by the Government terminate the employment of the Contractor under this Contract. Clause Employer Contractor 36. Antiquities: All fossils, Shield: Secure potential value for the Employer. Shield: If such findings involve the Contractor in any loss antiquities and other objects of or expense or expense, the Contractor can be interest or value which may be entitled to additional payment, and EOT where found on the Site or excavating applicable. the same during the progress of the Works. 37. Arbitration: Any disputes Shield: Both Employer and Contractor can defend their Shield: Both Employer and Contractor can defend their between the Contractor and the right and benefit or attack the other party to fight right and benefit or attack the other party to fight for Employer in relation to the for their right and benefit through arbitration. their right and benefit through arbitration. Contract, or carrying out of the Works, or direction or instruction or certificate, arbitration can be required. Clause Employer Contractor 39. Additional Optional Clause for Shield: Prevent excessive pricing by Contractor to Shield: Enable Contractor to better manage risks of material Fluctuations: The Contract Sum account for risk of fluctuations in material prices. price fluctuations and provides assurance of being shall be adjusted upwards or Employer can also save cost in the event of a fall compensated in the event of a hike in material price. downwards to take account of in material prices. any rise or fall of specified material prices during the Contract 40. Additional Optional Clause Shield: The Contractor can apply insurance excess in any Permitting Insurance Excess: event as are stipulated in Specification or other Insurance excess can be Contract Document and may at the Contractor’s applied. discretion to do so.