You are on page 1of 8

VALORIZACION Nº 02

( ESTRUCTURAS )

PRESUPUESTO
DESCRIPCION Metrado Ejecutado
UNID. Metrado P. UNIT. P. TOTAL

01.00.00 OBRAS PROVISIONALES


01.01.00 OFICINAS EST 1.00 2,000.00 2,000.00 -
01.02.00 ALMACENES,GUARDIANIA,COMEDORES EST 1.00 1,500.00 1,500.00 -
01.03.00 VESTUARIO Y SERVICIOS HIGIENICOS EST 1.00 1,500.00 1,500.00 -
01.04.00 CARTEL DE OBRA EST 1.00 750.00 750.00 -
01.03.01 AGUA,DESAGUE Y FLUIDO ELECTRICO PARA LA OBRA EST 1.00 2,500.00 2,500.00 -
02.00.00 TRABAJOS PRELIMINARES
02.01.00 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS EST 1.00 1,500.00 1,500.00 0.50
02.02.00 LIMPIEZA DE TERRENO MANUAL M2 2,775.00 2.85 7,908.75 2,775.00
02.03.00 TRAZO Y REPLANTEO CON EQUIPO M2 2,775.00 1.69 4,689.75 -
03.00.00 MOVIMIENTO DE TIERRA
03.01.00 CORTE Y NIVELACION DE TERRENO
03.01.01 CORTE Y NIVELACION DE TERRENO H=0.20M M2 2,775.00 2.90 8,047.50 1,000.00
03.02.00 EXCAVACIONES
03.02.01 EXCV. ZANJAS P/CIMIENTOS MAT.SUELTO H=1.00M M3 435.29 24.86 10,821.31 435.29
03.02.01 EXCV. ZAPATAS MAT. SUELTO H=1.00M M3 181.32 24.86 4,507.62 116.32
03.02.03 EXCAVACION MASIVA C/RETRO EXCV. 58HP M3 274.31 3.14 861.33 -
03.03.00 RELLENO Y COMPACTACION -
03.03.01 RELLENO Y COMPACTADO C/EQUIPO - MAT. PRESTAMO (AFIRMADO) M3 786.61 39.94 31,417.20 783.50
03.03.02 REFINE,NIVEL Y COMPACT. C/ COMPACTADORA M2 2,529.00 3.48 8,800.92 2,535.00
03.04.00 ELIMINACION DE MATERIAL EXCEDENTE
03.04.01 ELIM. MAT. MANUAL, DH=30M (DIST.PROM) M3 1,807.40 10.88 19,664.51 907.40
04.00.00 OBRAS DE CONCRETO SIMPLE
04.01.00 SUB ZAPATAS
04.01.01 CONCRETO F*C=100 KG/CM2- SUB ZAPATAS M3 69.53 246.92 17,168.35 20.00
04.02.00 SOLADOS -
04.02.01 CONCRETO F*C=100 KG/CM2 - SOLADOS PARA CIMIENTOS M3 69.11 246.92 17,064.64 69.11
04.02.02 CONCRETO F*C=100 KG/CM2 - SOLADOS PARA ZAPATAS M3 29.72 246.92 7,338.46 19.72
04.03.00 CIMIENTOS CORRIDOS -
04.03.01 CONCRETO 1:10 + 30% P.G. PARA CIMIENTOS CORRIDOS M3 20.10 152.69 3,069.07 20.10
04.04.00 SOBRECIMIENTOS -
04.04.01 CONCRETO 1:8 +25% PM- SOBRECIMIENTOS M3 2.59 188.28 487.65 2.59
04.04.02 ENCOFRADO Y DESENCOFRADO NORMAL SOBRECIMIENTO M2 34.53 23.11 797.99 34.53
04.05.00 FALSO PISO -
04.05.01 CONCRETO F*C= 100 KG/CM2 - FALSO PISO E=4" M2 1,935.55 27.92 54,040.56 -
05.00.00 OBRAS DE CONCRETO ARMADO -
05.01.00 CIMIENTO REFORZADO -
05.01.01 CONCRETO F*C=140KG/CM2 - CIMIENTO REFORZADO M3 128.64 235.81 30,334.60 80.00
05.01.02 ENCOFRADO Y DESENCOFRADO NORMAL- CIMIENTO REFORZADO M2 402.12 17.83 7,169.80 350.00
05.01.03 ACERO FY= 4200 KG/CM2 - CIMENTO REFORZADO KG 1,754.58 3.41 5,983.12 1,685.00
05.02.00 ZAPATAS -
05.02.01 CONCRETO PREMEZCLADO F*C=210 KG/CM2 - ZAPATAS M3 56.88 281.95 16,037.32 20.00
05.02.02 ENCOFRADO Y DESENCOFRADO NORMAL - ZAPATAS M2 149.76 25.86 3,872.79 100.00
05.02.03 ACERO FY= 4200 KG/CM2 - ZAPATAS KG 771.92 3.41 2,632.25 550.00
05.03.00 SOBRECIMIENTOS REFORZADOS -
05.03.01 CONCRETO PREMEZCLADO F*C= 210 KG/CM2 - SOBRECIMIENTOS RE M3 72.03 286.49 20,635.87 -
05.03.02 ENCOFRADO Y DESENCOFRADO NORMAL - SOBRECIMIENTO REFOR M2 696.21 23.11 16,089.41 100.00
05.03.03 ACERO FY=4200 KG/CM2 - SOBRECIMIENTO REFORZADO KG 866.53 3.41 2,954.87 450.00
05.04.00 COLUMNAS
05.04.01 CONCRETO PREMEZCLADO F*C= 210 KG/CM2 - COLUMNAS M3 78.40 286.37 22,451.41 60.00
05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL - COLUMNAS M2 820.79 33.46 27,463.63 600.00
05.04.03 ACERO FY = 4200 KG/CM2 - COLUMNAS KG 15,550.75 3.41 53,028.06 ###
05.05.00 VI GAS
05.05.01 CONCRETO PREMEZCLADO F*C =210 KG/CM2 - VIGAS M3 113.15 298.60 33,786.59 -
05.05.02 ENCOFRADO Y DESENCOFRADO NORMAL - VIGAS M2 765.64 40.66 31,130.92 -
05.05.03 ACERO FY= 4200 KG/CM2 - VIGAS KG 13,939.91 3.41 47,535.09 -
05.06.00 LOSAS MACIZAS
05.06.01 CONCRETO PREMEZCLADO F*C = 210 KG/CM2 - LOSAS MACIZAS M3 17.56 286.37 5,028.66 -

Página 1
VALORIZACION Nº 02
( ESTRUCTURAS )

PRESUPUESTO
DESCRIPCION Metrado Ejecutado
UNID. Metrado P. UNIT. P. TOTAL
05.06.02 ENCOFRADO Y DESENCOFRADO NORMAL - LOSAS MACIZAS M2 159.50 28.56 4,555.32 -
05.06.03 ACERO FY=4200 KG/CM2 - LOSAS MACIZAS KG 1,596.50 3.41 5,444.07 -
05.07.00 LOSAS ALIGERADAS
05.07.01 CONCRETO PREMEZCLADO F*C = 210 KG/CM2 - LOSAS ALIGERADAS M3 113.86 298.60 33,998.60 -
05.07.02 ENCOFRADO Y DESENCOFRADO NORMAL - LOSAS ALIGERADAS M2 1,314.60 23.64 31,077.14 -
05.07.03 LADRILLO P/TECHO 15X 30X30 CM - LOSAS ALIGERADAS PZAS 11,000.00 1.33 14,630.00 -
05.07.04 ACERO FY = 4200 KG/CM2 - LOSAS ALIGERADAS KG 7,107.51 3.41 24,236.61 -
05.08.00 ESCALERAS
05.08.01 CONCRETO PREMEZCLADO F*C =210 KG/CM2 - ESCALERAS M3 3.88 286.37 1,111.12 -
05.08.02 ENCOFRADO Y DESENCOFRADO NORMAL - ESCALERAS M2 18.20 41.40 753.48 -
05.08.03 ACERO FY = 4200 KG/CM2 - ESCALERAS KG 113.57 3.41 387.27 -
05.09.00 CISTERNA
05.09.01 CONCRETO PREMEZCLADO F*C= 210 KG/CM2 - CISTERNA M3 31.15 298.60 9,301.39 -
05.09.02 ENCOFRADO Y DESENCOFRADO NORMAL - CISTERNA M2 190.79 29.97 5,717.98 -
05.09.03 ACERO FY= 4200 KG/CM2 - CISTERNA KG 1,293.46 3.41 4,410.70 -
05.10.00 PAVIMENTOS RIGIDOS
05.10.01 CONCRETO PREMEZCLADO F*C = 210 KG/CM2 - PAVIMENTO RIGIDO M3 42.50 259.20 11,016.00 -
05.10.02 ACERO FY= 4200 KG/CM2 - PAVIMENTO RIGIDO KG 1,734.55 3.41 5,914.82 -
05.10.03 SELLO DE JUNTAS ML 176.00 3.66 644.16 -
06.00.00 ESTRUCTURAS METALICAS Y COBERTURAS
06.01.00 ESTRUCTURA METALICA GLB 1.00 30,000.00 30,000.00 -
06.02.00 COBERTURA M2 160 62.54 10,006.40 -

COSTO DIRECTO S/. 725,775.06


GASTOS GENERALES Y DIRECCION TECNICA (10%) S/. 72,577.51

SUB-TOTAL S/. 798,352.57


FACTOR RELACION 1.0000000
VALORIZACION BRUTA S/. 798,352.57

Página 2
VALORIZACION N° 02
( ARQUITECTURA )

PRESUPUESTO
DESCRIPCION Metrado Ejecutado
UNID. Metrado P. UNIT. P. TOTAL

01.00.00 MUROS Y TABIQUES


01.01.00 MURO DE LADRILLO KK DE SOGA M2 1,392.90 36.10 50,283.69 500.00
01.02.00 MURO DE LADRILLO KK DE CABEZA M2 1,474.55 55.71 82,147.18 600.00
02.00.00 REVOQUES Y ENLUCIDOS
02.01.00 TARRAJEO DE MURO PRIMARIO Y RAYADO m2 73.71 19.17 1,413.02 -
02.02.00 TARRAJEO DE MURO INTERIOR m2 2,655.14 16.29 43,252.23 -
02.03.00 TARRAJEO DE MURO EXTERIOR m2 1,950.39 18.44 35,965.19 -
02.04.00 TARRAJEO DE COLUMNAS m2 488.48 23.93 11,689.33 -
02.05.00 TARRAJEO DE VIGAS m2 470.15 31.35 14,739.20 -
02.06.00 VESTIDURA DE DERRAMES ml 975.41 11.38 11,100.17 -
02.07.00 TARRAJEO CON IMPERMEABILIZANTE m2 192.00 22.49 4,318.08 -
03.00.00 CIELORRASOS
03.01.00 CIELORASO CON MEZCLA C:A 1:4 m2 1,483.33 25.05 37,157.42 -
03.02.00 VESTIDURA DE FONDO DE ESCALERAS m2 8.00 21.45 171.60 -
04.00.00 PISOS Y PAVIMENTOS
04.01.00 CONTRAPISO FROTACHADO DE 2" m2 170.07 22.18 3,772.15 -
04.02.00 PISO DE CEMENTO PULIDO Y BRUÑADO m2 1,239.78 35.16 43,590.66 -
04.03.00 VEREDA DE CONCRETO m2 706.41 31.71 22,400.26 -
04.04.00 PISO CERAMICO DE 30x30 CM m2 50.43 56.89 2,868.96 -
05.00.00 ZOCALOS Y CONTRAZOCALOS
05.01.00 ZOCALO CERAMICO DE 30x30 m2 165.69 67.34 11,157.56 -
06.00.00 COBERTURAS
06.01.00 COBERTURA DE LADRILLO PASTELERO HECHO A MAQUINA ASENTADO m2 1,483.33 24.27 36,000.42 -
07.00.00 CARPINTERIA DE MADERA
07.01.00 PUERTA P2 (0.75x2.10) und 1.00 707.00 707.00 -
07.02.00 PUERTA P3 (0.90x2.10) und 2.00 798.00 1,596.00 -
07.03.00 PUERTA P5 (0.80x2.95) und 3.00 934.00 2,802.00 -
07.04.00 PUERTA P6 (2.00x2.95) und 4.00 1,571.00 6,284.00 -
07.05.00 PUERTA P7 (2.00x2.00) und 1.00 1,120.00 1,120.00 -
08.00.00 CARPINTERIA METALICA
08.01.00 DIVISIONES METALICAS PARA BAÑOS m 2.40 603.00 1,447.20 -
08.02.00 PUERTAS METALICAS P1 und 7.00 2,200.00 15,400.00 -
08.03.00 PUERTA METALICA P4 und 6.00 1,256.00 7,536.00 -
08.04.00 PUERTAS METALICAS 6.0X3.0 und 1.00 4,500.00 4,500.00 -
08.05.00 PUERTAS METALICAS 1.20X2.85 und 1.00 1,325.00 1,325.00 -
09.00.00 CERRAJERIA
09.01.00 CERRADURA PUERTA MADERA und 14.00 102.00 1,428.00 -
09.02.00 CERRADURA PUERTA METALICA und 8.00 180.00 1,440.00 -
10.00.00 VIDRIOS, CRISTALES Y SIMILARES
10.01.00 VENTANAS V1 (2x1) und 14.00 588.22 8,235.08 -
10.01.01 VENTANAS V1´ (2x1) und 8.00 368.22 2,945.76 -
10.02.00 VENTANAS V2 (2x2) und 1.00 778.00 778.00 -
10.02.01 VENTANAS V2´ (2x2) und 1.00 538.00 538.00 -
10.03.00 VENTANAS V3 (0.60x0.60) Apercianado und 9.00 766.15 6,895.35 -
10.04.00 VENTANAS V4 (0.60x1.20) Apercianado und 2.00 853.25 1,706.50 -
10.05.00 VENTANAS V5 (2.00x1.75) und 2.00 1,027.16 2,054.32 -
10.06.00 VENTANAS V6 (Diametro 0.60) und 1.00 352.44 352.44 -
10.07.00 VENTANAS V7 (3.75x0.85) und 7.00 766.40 5,364.80 -
10.07.01 VENTANAS V7´ (3.75x0.85) und 3.00 646.00 1,938.00 -
10.08.00 VENTANAS V8 (1.50x1.50) und 3.00 610.00 1,830.00 -
10.09.00 VENTANAS V9 (1.20x0.90) und 1.00 560.00 560.00 -
10.10.00 VENTANAS V10 BLOKS DE VIDRIO und 24.00 140.00 3,360.00 -
11.00.00 PINTURA
11.01.00 PINTURA LATEX EN MUROS INTERIORES m2 1,949.00 7.04 13,720.96 -
11.02.00 PINTURA EN MUROS EXTERIORES m2 2,441.96 7.04 17,191.40 -
11.03.00 PINTURA LATEX CON ACABADO m2 396.06 10.04 3,976.44 -
11.04.00 PINTURA EN CIELORASO CON LATEX m2 1,950.39 12.01 23,424.18 -
12.00.00 APARATOS SANITARIOS Y ACCESORIOS
12.01.00 INODORO DE LOSA VITRIFICADA BLANCA MODELO TORNADO C/TANQ und 2.00 730.00 1,460.00 -
12.02.00 OVALIN LOSA VITRIFICADA TIPO SONET CON GRIFERIA A PRESION pza 2.00 277.00 554.00 -
12.03.00 LAVATORIO DE LOSA VITRIFICADA BLANCA FONTSANA C/GRIFERIA A und 1.00 177.00 177.00 -
12.04.00 URINARIO DE LOSA VITRIFICADA BLANCA TIPO CADET CON VALVUL und 2.00 580.00 1,160.00 -
12.05.00 LAVADERO DE UNA POZA DE ACERO SATINADO INC. ACCESORIOS Y G pza 2.00 382.00 764.00 -
12.06.00 PAPELERA DE LOSA ADOSADA und 2.00 50.00 100.00 -
12.07.00 PAPELERA PARA TIPO TOALLA und 1.00 50.00 50.00 -

Página 3
VALORIZACION N° 02
( ARQUITECTURA )

PRESUPUESTO
DESCRIPCION Metrado Ejecutado
UNID. Metrado P. UNIT. P. TOTAL
12.08.00 DISPENSADOR DE JABON LIQUIDO MODELO PD-050 und 3.00 70.00 210.00 -
12.09.00 JABONERA und 2.00 35.00 70.00 -
13.00.00 VARIOS
13.01.00 TABLEROS CORIAN m 7.20 1,100.00 7,920.00 -
13.02.00 JARDINERIA m2 270.00 20.00 5,400.00 -
13.03.00 SARDINEL m 83.00 32.75 2,718.25 -
13.04.00 ESPEJO 0.60X0.75 und 1.00 120.00 120.00 -
13.05.00 ESPEJO 0.90X0.75 und 2.00 150.00 300.00 -
14.00.00 EQUIPAMIENTO EN CAMARAS FRIAS
14.01.00 ESTRUCTURA MINIRACK TIPO "A" UND 6.00 3,883.32 23,299.92 -
14.02.00 ESTRUCTURA MINIRACK TIPO "B" UND 3.00 5,204.31 15,612.93 -

COSTO DIRECTO S/. 612,399.65


GASTOS GENERALES Y DIRECCION TECNICA (10%) S/. 61,239.97

SUB-TOTAL S/. 673,639.62


FACTOR RELACION 1.0000000
VALORIZACION BRUTA S/. 673,639.62

Página 4
VALORIZACION N° 02
( INST. SANITARIAS )

PRESUPUESTO
DESCRIPCION Metrado Ejecutado
UNID. Metrado P. UNIT. P. TOTAL

01.00.00 OBRAS PRELIMINARES


01.01.00 TRABAJO PRELIMINAR GLB 1.00 862.77 862.77 1.00
01.02.00 TRAZO Y REPLANTEO ML 240.00 0.69 165.60 240.00
01.03.00 EXCAVACION Y RELLENO DE ZANJAS 0.60X0.60 M ML 240.00 18.04 4,329.60 240.00
01.04.00 ELIMINACION DE MATERIALES EXCEDENTE M3 18.00 42.86 771.48 18.00
02.00.00 RED PRINCIPAL DE AGUA FRIA
02.01.00 TUBERIA
02.01.01 TUBERIA C-10 1-1/2´´ S/P ML 13.00 10.18 132.34 13.00
02.01.02 TUBERIA C-10 1 1/4´ S / P ML 3.00 7.60 22.80 3.00
02.01.03 TUBERIA C-10 1´´ S / P ML 56.00 6.11 342.16 56.00
02.01.04 TUBERIA C-10 3/4´´ S/P ML 40.00 4.62 184.80 40.00
02.01.05 TUBERIA C-10 1/2´´ S/P ML 20.00 5.92 118.40 20.00
02.02.00 VALVULAS
02.02.01 VALVULA ESFERICA DE 1 1/2´´ UND 1.00 85.06 85.06 -
02.02.02 VALVULAS ESFERICAS DE 3/4´´ UND 1.00 49.55 49.56 -
02.02.03 VALVULAS ESFERICAS DE 1/2´´ UND 5.00 39.24 196.20 -
02.03.04 CAJUELA PARA ARROJAR VALVULAS UND 10.00 56.10 561.00 -
02.03.00 SALIDAS DE AGUA FRIA
02.03.01 SALIDAS DE GRIFOS DE 3/4´´ PTO 3.00 38.57 115.71 -
02.03.02 SALIDAS DE AGUA FRIA DE 1/2´´ PTO 9.00 43.66 392.94 -
02.03.03 VALAVULAS ESFERICAS DE 1/2´´ UNID 3.00 39.24 117.72 -
03.00.00 RED DE AGUA CALIENTE
03.01.00 SALIDAS
03.02..00 SALIDAS DE AGUA CALIENTE DE 1/2´´ PTO 3.00 47.26 141.78 -
03.03.00 VALVULA ESFERICA DE 1/2´´ UNID 1.00 39.24 39.24 -
04.00.00 CALENTADOR DE AGUA 80 LTS UNID 1.00 1,202.09 1,202.09 -
04.01.00 RED DE DESAGUE
04.01.00 TUBERIA
04.01.01 TUBERIA PVC - SAL DE 6´´ ML 25.00 39.44 986.00 25.00
04.01.02 TUBERIA PVC - SAL DE 4´´ ML 68.00 27.23 1,851.64 68.00
04.01.03 TUBERIA PVC - SAL DE 3´´ ML 125.00 19.44 2,430.00 125.00
04.01.04 TUBERIA PVC - SAL DE 2´´ ML 32.00 17.71 566.72 32.00
04.02.00 CAJA DE REGISTRO
04.02.01 CAJA DE REGISTRO DE 24´´ X 24 ´´ UNID 3.00 95.22 285.66 -
04.02.02 CAJA DE REGISTRO DE 12´´ X 24 ´´ UNID 2.00 70.17 140.34 -
04.03.00 SALIDAS
04.03.01 SALIDAS PARA DESAGUE DE 4´´ PTO 2.00 52.76 105.52 -
04.03.02 SALIDAS PARA DESAGUE DE 2´´ PTO 3.00 37.27 111.81 -
04.03.03 SALIDAS PARA REGISTRO DE BRONCE DE 4´´ PTO 1.00 42.50 42.50 -
04.03.04 SALIDAS PARA REGISTRO DE BRONCE DE 3´´ PTO 6.00 41.18 247.08 -
04.03.05 SALIDA PARA SUMIDERO DE 3´´ PTO 10.00 46.21 462.10 -
04.03.06 SALIDA PARA TRAMPA DE 2´´ PTO 3.00 32.67 98.01 -
04.03.07 SALIDA DE VENTILACION 2´´ PTO 5.00 47.06 235.30 -
04.03.08 SALIDA DE SUMIDERO PTO 1.00 37.26 37.26 -
05.00.00 VARIOS
05.01.00 CISTERNA
05.01.01 TUBERIA PVC SAL DE 2´´ ML 15.00 17.71 265.65 -
05.01.02 TUBERIA C- 10 DE 1´´ ML 5.00 6.14 30.70 -
05.01.03 VALVULA FLOTADOR DE 1´´ UNID 1.00 69.52 69.52 -
05.01.04 ROMPE AGUA DE 2´´ UNID 1.00 73.03 73.03 -
05.01.05 VALVULA CHECK DE 2´´ UNID 2.00 192.97 385.94 -
05.01.06 VALVULA ESFERICA DE 2´´ UNID 2.00 221.48 442.96 -
05.01.07 SOMBREROS DE VENTILACION UNID 9.00 25.72 231.48 -
05.02.00 BOMBA DE AGUA Y DESAGUE
05.02.01 BOMBA CONTRAINCENDIO Y BOMBA JOCKEY + ACCESORIOS GLB 1.00 49,800.00 49,800.00 -
05.02.02 BOMBA DE DESAGUE Y ACCESORIOS GLB 1.00 1,575.00 1,575.00 -
05.02.03 INSTALACION DE EQUIPOS DE BOMBEO (MANO DE OBRA + ACCESORI GLB 1.00 18,647.90 18,647.90 -
05.03.00 PRUEBAS GENERALES
05.03.01 PRUEBA DE RED AGUA Y DESAGUE GLB 1.00 600.00 600.00 -

COSTO DIRECTO S/. 89,553.37


GASTOS GENERALES Y DIRECCION TECNICA (10%) S/. 8,955.34

Página 5
VALORIZACION N° 02
( INST. SANITARIAS )

PRESUPUESTO
DESCRIPCION Metrado Ejecutado
UNID. Metrado P. UNIT. P. TOTAL
SUB-TOTAL S/. 98,508.71
FACTOR RELACION 1.0000000
VALORIZACION BRUTA S/. 98,508.71

Página 6
VALORIZACION N° 02
( INST. ELECTRICAS )

PRESUPUESTO
DESCRIPCION Metrado Ejecutado
UNID. Metrado P. UNIT. P. TOTAL

01.00.00 ALMACEN DE DISTRIBUCION (incluye almacen y oficinas )


01.01.00 ALIMENTADORES :
01.01.01 TABLERO GENERAL T.G. NEMA 1
01.01.02 2 ( 3-1x 70 MM2 THW + 1X35 MM 2/T ) m 63.00 198.15 12,483.45 63.00
01.02.00 TUBERIA PVC - SAP DE 80 MM + DADO DE CONCRETO m 59.00 22.51 1,328.09 59.00
01.02.00 TABLERO DE DISTRIBUCION AIRE ACONDICI. T -AA NEMA12
01.02.02 2 ( 3 - 1 x 50 mm2 THW +1x25 mm2 TW/T ) m 28.00 99.93 2,798.04 28.00
01.02.03 TUBERIA PCV - SAP DE 80 MM m 21.00 22.51 472.71 21.00
01.03.00 TABLERO DE DISTRIBUCION T - 1
01.03.01 3-1 x 10 MM2 THW + 1X 6 MM 2 TW / T m 59.00 16.87 995.33 59.00
01.03.02 TUBERIA PVC - SAP DE 25 MM m 54.00 7.50 405.00 54.00
01.04.00 TABLERO DE DISTRIBUCION T - 2
01.04.01 3-1 x 16 MM 2 THW + 1X 10 MM 2 TW / T m 9.00 27.70 249.30 9.00
01.04.021 TUBERIA PVC - SAP DE 35 MM m 2.00 11.94 23.88 2.00
01.05.00 TABLERO DE BOMBA DE DESAGUE
01.05..01 3-1x10 mm2THW +1X 6TW/T m 22.00 16.87 371.14 22.00
01.05.02 TUBERIA PVC - SAP DE 25 MM m 12.00 7.50 90.00 12.00
01.05.03 CAJA DE F.o Go de 150 x150 x100 MM und 1.00 37.64 37.64 1.00
01.05.04 TUBERIA 25 MM FoGo m 8.00 33.82 270.56 8.00
01.06.00 TABLERO DE BOMA CONTRA INCENDIO
01.06.01 3 - 1X 35 MM 2 THW + 1 X 10 MM 2 /T m 27.00 33.93 916.11 27.00
01.06.02 TUBERIA PVC - SAP DE 50 MM 2 m 15.00 18.45 276.75 15.00
01.06.03 TUBERIA 50 MM 2 Fo Go m 8.00 39.84 318.72 8.00
01.06.04 CAJA DE PASE 200 X 200 X 150 MM und 1.00 49.50 49.50 1.00
01.07.00 TABLERO ESTABILIZADO
01.07.01 2 - 1 X 4 MM 2 THW + 1X 4 MM 2 TW /T m 15.00 5.65 84.75 15.00
01.07.02 TUBERIA PVC - SAP DE 20 MM m 15.00 7.93 118.95 15.00
01.08.00 TRANSFORMADOR DE AISLAMIENTO DE
01.08.02 CABLE 2 1X35 MM2 THW m 15.00 31.33 469.95 15.00
01.08.02 TUBERIA DE ..25.. MM FoG m 15.00 33.82 507.30 15.00
01.09.00 Tableros de Distribución
01.09.01 TABLERO GENERAL T.G. und 1.00 5,268.26 5,268.26 -
01.09.02 TABLEREO DE DISTRIBUCION AIRE ACONDICIONADO T. AA und 1.00 8,141.40 8,141.40 -
01.09.03 TABLERO DE DISTRIBUCION T - 1 und 1.00 1,863.01 1,863.01 -
01.09.04 TABLERO DE DISTRIBUCION T - 2 und 1.00 2,554.92 2,554.92 -
01.09.05 TABLERO DE BOMBA DE DESAGUE und 1.00 2,609.04 2,609.04 -
01.09.06 TRANSFORMADOR DE AISLAMIENTO und 1.00 1,304.52 1,304.52 -
01.10.00 CAJAS DE Fo Go PESADAS
01.10.01 Caja tipo 1: 300x300x100 mm c/tapa ciega und 2.00 74.33 148.66 -
.01.10.02 Caja tipo 2: 200x200x100 mm c/tapa ciega und 4.00 49.50 198.00 -
01.10.03 Caja tipo 3: 150x150x100 mm c/tapa ciega und 5.00 37.64 188.20 -
01.10.04 Caja tipo 4: 100x10x50 mm c/tapa ciega und 13.00 13.68 177.84 -
02.01.00 SISTEMA DE TIERRA
02.01.01 EXCAVACION DE POZO DE PUESTA DE TIERRA und 2.00 134.98 269.96 -
02.01.02 RELLENO - COMPACTACION Y APLICACIÓN DEL GEL , POZO TIERRA und 2.00 965.52 1,931.04 -
02.01.03 TUBERIA PVC -SAP DE 25 MM und 20.00 37.64 752.80 -
02.01.04 TUBERIA PVC- SAP DE 20 MM und 7.00 7.93 55.51 -
02.01.05 CABLE TW 1X35 MM 2 m 23.00 20.40 469.20 -
02.01.06 CABLE TW 1X16 MM 2 m 10.00 9.99 99.90 -
02.01.07 CABLE DESNUDO COBRE DE 1X 10 MM 2 m 12.00 5.34 64.08 -
03.00.00 CIRCUITOS DE DISTRIBUCION
03.01.00 Circuitos de distribucion en la nave
03.01.01 Salida de alumbrado en el techo almacen ,cuarentena ,administrativa e insumo y otros pto 87.00 65.07 5,661.09 -
03.01.02 Salida de alumbrado en el exterior braquetes incluye : tuberia de fo.go. Y pvc - sap pto 20.00 66.24 1,324.80 -
03.01.03 Salida de alumbrado en el exterior , poste incluye : tuberia de pvc - sap 35 mm ,acce pto 9.00 60.39 543.51 -
03.01.04 Tomacorriente monofasico industrial de 16 A (2P + T - 250 ) para adosar a la pared ma pto 10.00 70.66 706.60 -
03.01.05 Salida de luz de emergencia pto 10.00 53.41 534.10 -
03.01.06 Equipo de luz de emegencia con bateria pto 10.00 505.96 5,059.60 -
03.01.07 Salida de equipo de desague pto 1.00 133.53 133.53 -
03.01.08 Tomacorriente bipolar dobles c/ linea de tierra 220 V - 15 A , C/ placa metalica tipo am pto 55.00 50.82 2,795.10 -
03.01.09 Tomacorriente bipolar dobles c/ linea de tierra 220 V - 15 A , C/ placa metalica tipo ameri pto 9.00 50.82 457.38 -
04.00.00 AIRE ACONDICIONADO
04.01.01 Salida de camara fria , 35kw,6kw y 4 kw pto 4.00 814.66 3,258.64 -
04.01.02 Salida de cortina de aire 1.5 kw pto 2.00 188.54 377.08 -
04.01.03 Salida de sensores pto 5.00 35.00 175.00 -

Página 7
VALORIZACION N° 02
( INST. ELECTRICAS )

PRESUPUESTO
DESCRIPCION Metrado Ejecutado
UNID. Metrado P. UNIT. P. TOTAL
04.01.04 Salida de temperatura pto 1.00 35.00 35.00 -
04.01.05 Alimentacion electrica a la central de control de monitoreo pto 1.00 60.00 60.00 -
04.01.06 Cajas de f. G. Pesadas de 100 x 100 x 50 mm und 16.00 13.68 218.88 -
04.01.07 Pases atravez de loza und 3.00 20.00 60.00 -
05.00.00 Punto de interruptor incluye tuberia ,cable caja de fo.go. De las siguientes caracteristicas :
05.00.01 Interruptor unipolar simple pto 28.00 49.43 1,384.04 -
05.00.02 Interruptor unipolar doble pto 2.00 49.43 98.86 -
05.00.03 Interruptor unipolar de tres vias pto 4.00 49.43 197.72 -
06.00.00 Alumbrado exterior con poste de concreto
06.00.01 Poste de concreto de 7/200/ , C / pastoral recortado pto 7.00 894.32 6,260.24 -
06.00.02 Poste de concreto de 9/200 pto 2.00 1,042.00 2,084.00 -
06.00.03 Izamiento de poste de concreto und 9.00 50.00 450.00 -

07.00.00 Salida de comunicación y señales


07.00.01 Salida de voz y data , incluye tuberia de 25 mm de diametro de PVC SAP y caja cuad pto 5.00 35.00 175.00 -
07.00.02 Salida de telefono pto 4.00 35.00 140.00 -
07.00.03 Salida de TV pto 1.00 35.00 35.00 -
08.00.00 Artefacto de iluminacion
08.00.01 Reflector tipo ZORUS 400 W SODIO und 4.00 512.00 2,048.00 -
08.00.02 Luminaria con lampara astro 70 w und 7.00 259.00 1,813.00 -
08.00.03 Artefacto en camara y antecamara similar al modelo FV - 1X50 W und 10.00 98.60 986.00 -
08.00.04 Artefacto en almacen similar al modelo MER - 250 DE JOSFEL und 43.00 296.00 12,728.00 -
08.00.05 Artefacto p/ laboratorio similar al modelo AHR - 236 de JOSFEL und 14.00 176.00 2,464.00 -
08.00.06 Artefacto p/ oficina similar al modelo NVR - 236 DE JOSFEL und 8.00 165.00 1,320.00 -
08.00.07 Braquete en la sala de recepcion , similar BJ - 300 , c / lamapara halogena 150 w und 1.00 153.00 153.00 -
08.00.08 Braquete exterior , similar modelo BTL - 136 CON lamapara compacta und 19.00 136.00 2,584.00 -
08.00.09 Artefacto Galaxie 2x18 w und 7.00 174.90 1,224.30 -
09.00.00 VARIOS
09.00.01 Excavación de zanja 500 x 600 mm m 60.00 16.01 960.60 -
09.00.02 Buzones electricos marco de fierro fdo. Y tapa de concreto ,600 mm diametro und 1.00 119.98 119.98 -
10.00.00 INSTALACION ELECTROMECANICA
10.00.01 Sistemas de camara fria glb 1.00 175,523.70 175,523.70 -
10.00.02 Sistema de aire acondicionado glb 1.00 97,020.00 97,020.00 -
10.00.03 Medicion y monitoreo de temperatura glb 1.00 23,100.00 23,100.00 -

COSTO DIRECTO S/. 402,633.26


GASTOS GENERALES Y DIRECCION TECNICA (10%) S/. 40,263.33

SUB-TOTAL S/. 442,896.59


FACTOR RELACION 1.0000000
VALORIZACION BRUTA S/. 442,896.59