CONCRETE POURING
Item Description 4000 Psi Ready Mix Concrete Estimated Quantity: 19 cum
CHECKLIST
Finishing Tools/ Equipment (Screeder, broom, etc.) Quality of Materials Used (Result of Design/Trial)
Line and Grade Alignment (Form setting, elev, etc.) Lighting System
Rebars size, spacing, and number Plumbing Layout (roughing -ins/ embedments)
Inspected by:
Project Inspector
Remarks
Approved by:
Municipal Engineer
Remarks
Republic of the Philippines
PROVONCE OF NEGROS ORIENTAL
OFFICE OF THE BUILDING OFFICIAL
MUNICIPALITY OF BACONG, NEGROS ORIENTAL
CONCRETE POURING
Item Description 4000 Psi Ready Mix Concrete Estimated Quantity: 37 cum.
Date of Pouring May 6, 2023 Upper viewdeck columns and portal slab
Requested by:
CHECKLIST
Finishing Tools/ Equipment (Screeder, broom, etc.) Quality of Materials Used (Result of Design/Trial)
Line and Grade Alignment (Form setting, elev, etc.) Lighting System
Rebars size, spacing, and number Plumbing Layout (roughing -ins/ embedments)
Inspected by:
Project Inspector
Remarks
Approved by:
Municipal Engineer
Remarks
Republic of the Philippines
PROVONCE OF NEGROS ORIENTAL
OFFICE OF THE BUILDING OFFICIAL
MUNICIPALITY OF VALENCIA, NEGROS ORIENTAL
CONCRETE POURING
Item Description 3000 Psi Ready Mix Concrete Estimated Quantity: 18 CUM
Requested by:
PROJECT ENGINEER
PHILSOUTH BUILDERS
CHECKLIST
Finishing Tools/ Equipment (Screeder, broom, etc.) Quality of Materials Used (Result of Design/Trial)
Line and Grade Alignment (Form setting, elev, etc.) Lighting System
Rebars size, spacing, and number Plumbing Layout (roughing -ins/ embedments)
Inspected by:
Project Inspector
Remarks
Approved by:
Municipal Engineer
Remarks
Republic of the Philippines
PROVONCE OF NEGROS ORIENTAL
OFFICE OF THE BUILDING OFFICIAL
MUNICIPALITY OF BACONG, NEGROS ORIENTAL
CONCRETE POURING
Item Description 3000 Psi Ready Mix Concrete Estimated Quantity: 6 CUM
Requested by:
CHECKLIST
Finishing Tools/ Equipment (Screeder, broom, etc.) Quality of Materials Used (Result of Design/Trial)
Line and Grade Alignment (Form setting, elev, etc.) Lighting System
Rebars size, spacing, and number Plumbing Layout (roughing -ins/ embedments)
Inspected by:
Project Inspector
Remarks
Approved by:
Municipal Engineer
Remarks
Republic of the Philippines
PROVONCE OF NEGROS ORIENTAL
OFFICE OF THE BUILDING OFFICIAL
MUNICIPALITY OF BACONG, NEGROS ORIENTAL
CONCRETE POURING
Item Description 4000 Psi Ready Mix Concrete Estimated Quantity: 24.34 CUM
Requested by:
CHECKLIST
Finishing Tools/ Equipment (Screeder, broom, etc.) Quality of Materials Used (Result of Design/Trial)
Line and Grade Alignment (Form setting, elev, etc.) Lighting System
Rebars size, spacing, and number Plumbing Layout (roughing -ins/ embedments)
Inspected by:
Project Inspector
Remarks
Approved by:
Municipal Engineer
Remarks
Republic of the Philippines
PROVONCE OF NEGROS ORIENTAL
OFFICE OF THE BUILDING OFFICIAL
MUNICIPALITY OF BACONG, NEGROS ORIENTAL
CONCRETE POURING
Item Description 4000 Psi Ready Mix Concrete Estimated Quantity: 24.24 m3
Requested by:
CHECKLIST
Finishing Tools/ Equipment (Screeder, broom, etc.) Quality of Materials Used (Result of Design/Trial)
Line and Grade Alignment (Form setting, elev, etc.) Lighting System
Rebars size, spacing, and number Plumbing Layout (roughing -ins/ embedments)
Inspected by:
Project Inspector
Remarks
Approved by:
Municipal Engineer
Remarks
Republic of the Philippines
PROVONCE OF NEGROS ORIENTAL
OFFICE OF THE BUILDING OFFICIAL
MUNICIPALITY OF BACONG, NEGROS ORIENTAL
CONCRETE POURING
Item Description 4000 Psi Ready Mix Concrete Estimated Quantity: 6.59 cum
Requested by:
CHECKLIST
Finishing Tools/ Equipment (Screeder, broom, etc.) Quality of Materials Used (Result of Design/Trial)
Line and Grade Alignment (Form setting, elev, etc.) Lighting System
Rebars size, spacing, and number Plumbing Layout (roughing -ins/ embedments)
Inspected by:
Project Inspector
Remarks
Approved by:
Municipal Engineer
Remarks
Republic of the Philippines
PROVONCE OF NEGROS ORIENTAL
OFFICE OF THE BUILDING OFFICIAL
MUNICIPALITY OF BACONG, NEGROS ORIENTAL
CONCRETE POURING
Item Description 4000 Psi Ready Mix Concrete Estimated Quantity: 21.14 cum
Requested by:
CHECKLIST
Finishing Tools/ Equipment (Screeder, broom, etc.) Quality of Materials Used (Result of Design/Trial)
Line and Grade Alignment (Form setting, elev, etc.) Lighting System
Rebars size, spacing, and number Plumbing Layout (roughing -ins/ embedments)
Inspected by:
Project Inspector
Remarks
Approved by:
Municipal Engineer
Remarks
Republic of the Philippines
PROVONCE OF NEGROS ORIENTAL
OFFICE OF THE BUILDING OFFICIAL
MUNICIPALITY OF BACONG, NEGROS ORIENTAL
CONCRETE POURING
Item Description 4000 Psi Ready Mix Concrete Estimated Quantity: 55.97 CUM
Requested by:
CHECKLIST
Finishing Tools/ Equipment (Screeder, broom, etc.) Quality of Materials Used (Result of Design/Trial)
Line and Grade Alignment (Form setting, elev, etc.) Lighting System
Rebars size, spacing, and number Plumbing Layout (roughing -ins/ embedments)
Inspected by:
Project Inspector
Remarks
Approved by:
Municipal Engineer
Remarks
Republic of the Philippines
PROVONCE OF NEGROS ORIENTAL
OFFICE OF THE BUILDING OFFICIAL
MUNICIPALITY OF BACONG, NEGROS ORIENTAL
CONCRETE POURING
Item Description 4000 Psi Ready Mix Concrete Estimated Quantity: 19.99 CUM
Date of Pouring January 31, 2022 COLUMNS AND TIE BEAM (RETAIL BUILDING)
Requested by:
CHECKLIST
Finishing Tools/ Equipment (Screeder, broom, etc.) Quality of Materials Used (Result of Design/Trial)
Line and Grade Alignment (Form setting, elev, etc.) Lighting System
Rebars size, spacing, and number Plumbing Layout (roughing -ins/ embedments)
Inspected by:
Project Inspector
Remarks
Approved by:
Municipal Engineer
Remarks
Republic of the Philippines
PROVONCE OF NEGROS ORIENTAL
OFFICE OF THE BUILDING OFFICIAL
MUNICIPALITY OF BACONG, NEGROS ORIENTAL
CONCRETE POURING
Item Description 4000 Psi Ready Mix Concrete Estimated Quantity: 24.347 cum
Date of Pouring February 16, 2022 PEDESTALS & FOOTINGS (RETAIL BUILDING)
Requested by:
CHECKLIST
Finishing Tools/ Equipment (Screeder, broom, etc.) Quality of Materials Used (Result of Design/Trial)
Line and Grade Alignment (Form setting, elev, etc.) Lighting System
Rebars size, spacing, and number Plumbing Layout (roughing -ins/ embedments)
Inspected by:
Project Inspector
Remarks
Approved by:
Municipal Engineer
Remarks
Republic of the Philippines
PROVONCE OF NEGROS ORIENTAL
OFFICE OF THE BUILDING OFFICIAL
MUNICIPALITY OF BACONG, NEGROS ORIENTAL
CONCRETE POURING
Item Description 4000 Psi Ready Mix Concrete Estimated Quantity: 28.99 cum
Date of Pouring February 23, 2022 TIE BEAM AND COLUMN (RETAIL BUILDING)
Requested by:
CHECKLIST
Finishing Tools/ Equipment (Screeder, broom, etc.) Quality of Materials Used (Result of Design/Trial)
Line and Grade Alignment (Form setting, elev, etc.) Lighting System
Rebars size, spacing, and number Plumbing Layout (roughing -ins/ embedments)
Inspected by:
Project Inspector
Remarks
Approved by:
Municipal Engineer
Remarks
Republic of the Philippines
PROVONCE OF NEGROS ORIENTAL
OFFICE OF THE BUILDING OFFICIAL
MUNICIPALITY OF BACONG, NEGROS ORIENTAL
CONCRETE POURING
Item Description 4000 Psi Ready Mix Concrete Estimated Quantity: 15.808 cum
Requested by:
CHECKLIST
Finishing Tools/ Equipment (Screeder, broom, etc.) Quality of Materials Used (Result of Design/Trial)
Line and Grade Alignment (Form setting, elev, etc.) Lighting System
Rebars size, spacing, and number Plumbing Layout (roughing -ins/ embedments)
Inspected by:
Project Inspector
Remarks
Approved by:
Municipal Engineer
Remarks
Republic of the Philippines
PROVONCE OF NEGROS ORIENTAL
OFFICE OF THE BUILDING OFFICIAL
MUNICIPALITY OF BACONG, NEGROS ORIENTAL
CONCRETE POURING
Item Description 4000 Psi Ready Mix Concrete Estimated Quantity: 29.07 cum
Date of Pouring March 9, 2022 COLUMN, FOOTING AND TIE BEAM (RETAIL BUILDING)
Requested by:
CHECKLIST
Finishing Tools/ Equipment (Screeder, broom, etc.) Quality of Materials Used (Result of Design/Trial)
Line and Grade Alignment (Form setting, elev, etc.) Lighting System
Rebars size, spacing, and number Plumbing Layout (roughing -ins/ embedments)
Inspected by:
Project Inspector
Remarks
Approved by:
Municipal Engineer
Remarks
Republic of the Philippines
PROVONCE OF NEGROS ORIENTAL
OFFICE OF THE BUILDING OFFICIAL
MUNICIPALITY OF BACONG, NEGROS ORIENTAL
CONCRETE POURING
Item Description 4000 Psi Ready Mix Concrete Estimated Quantity: 15 cum
Date of Pouring March 26, 2022 COLUMN AND TIE BEAM (RETAIL BUILDING)
Requested by:
CHECKLIST
Finishing Tools/ Equipment (Screeder, broom, etc.) Quality of Materials Used (Result of Design/Trial)
Line and Grade Alignment (Form setting, elev, etc.) Lighting System
Rebars size, spacing, and number Plumbing Layout (roughing -ins/ embedments)
Inspected by:
Project Inspector
Remarks
Approved by:
Municipal Engineer
Remarks
Republic of the Philippines
PROVONCE OF NEGROS ORIENTAL
OFFICE OF THE BUILDING OFFICIAL
MUNICIPALITY OF BACONG, NEGROS ORIENTAL
CONCRETE POURING
Item Description 4000 Psi Ready Mix Concrete Estimated Quantity: 60 cum
Requested by:
CHECKLIST
Finishing Tools/ Equipment (Screeder, broom, etc.) Quality of Materials Used (Result of Design/Trial)
Line and Grade Alignment (Form setting, elev, etc.) Lighting System
Rebars size, spacing, and number Plumbing Layout (roughing -ins/ embedments)
Inspected by:
Project Inspector
Remarks
Approved by:
Municipal Engineer
Remarks
Republic of the Philippines
PROVONCE OF NEGROS ORIENTAL
OFFICE OF THE BUILDING OFFICIAL
MUNICIPALITY OF BACONG, NEGROS ORIENTAL
CONCRETE POURING
Item Description 4000 Psi Ready Mix Concrete Estimated Quantity: 140.85 cum
Date of Pouring April 21, 2022 Food and Beverage Suspended Slab
Requested by:
CHECKLIST
Finishing Tools/ Equipment (Screeder, broom, etc.) Quality of Materials Used (Result of Design/Trial)
Line and Grade Alignment (Form setting, elev, etc.) Lighting System
Rebars size, spacing, and number Plumbing Layout (roughing -ins/ embedments)
Inspected by:
Project Inspector
Remarks
Approved by:
Municipal Engineer
Remarks
Republic of the Philippines
PROVONCE OF NEGROS ORIENTAL
OFFICE OF THE BUILDING OFFICIAL
MUNICIPALITY OF BACONG, NEGROS ORIENTAL
CONCRETE POURING
Item Description 3000 Psi Ready Mix Concrete Estimated Quantity: 25 cum
Requested by:
CHECKLIST
Finishing Tools/ Equipment (Screeder, broom, etc.) Quality of Materials Used (Result of Design/Trial)
Line and Grade Alignment (Form setting, elev, etc.) Lighting System
Rebars size, spacing, and number Plumbing Layout (roughing -ins/ embedments)
Inspected by:
Project Inspector
Remarks
Approved by:
Municipal Engineer
Remarks
Republic of the Philippines
PROVONCE OF NEGROS ORIENTAL
OFFICE OF THE BUILDING OFFICIAL
MUNICIPALITY OF BACONG, NEGROS ORIENTAL
CONCRETE POURING
Item Description 3000 Psi Ready Mix Concrete Estimated Quantity: 73.05 cum
Requested by:
CHECKLIST
Finishing Tools/ Equipment (Screeder, broom, etc.) Quality of Materials Used (Result of Design/Trial)
Line and Grade Alignment (Form setting, elev, etc.) Lighting System
Rebars size, spacing, and number Plumbing Layout (roughing -ins/ embedments)
Inspected by:
Project Inspector
Remarks
Approved by:
Municipal Engineer
Remarks
Republic of the Philippines
PROVONCE OF NEGROS ORIENTAL
OFFICE OF THE BUILDING OFFICIAL
MUNICIPALITY OF BACONG, NEGROS ORIENTAL
CONCRETE POURING
Item Description 4000 Psi Ready Mix Concrete Estimated Quantity: 23 cum
Requested by:
CHECKLIST
Finishing Tools/ Equipment (Screeder, broom, etc.) Quality of Materials Used (Result of Design/Trial)
Line and Grade Alignment (Form setting, elev, etc.) Lighting System
Rebars size, spacing, and number Plumbing Layout (roughing -ins/ embedments)
Inspected by:
Project Inspector
Remarks
Approved by:
Municipal Engineer
Remarks
Republic of the Philippines
PROVONCE OF NEGROS ORIENTAL
OFFICE OF THE BUILDING OFFICIAL
MUNICIPALITY OF BACONG, NEGROS ORIENTAL
CONCRETE POURING
Item Description 4000 Psi Ready Mix Concrete Estimated Quantity: 98 cum
Date of Pouring May 17, 2022 Suspended Slab (Food and Beverage)
Requested by:
CHECKLIST
Finishing Tools/ Equipment (Screeder, broom, etc.) Quality of Materials Used (Result of Design/Trial)
Line and Grade Alignment (Form setting, elev, etc.) Lighting System
Rebars size, spacing, and number Plumbing Layout (roughing -ins/ embedments)
Inspected by:
Project Inspector
Remarks
Approved by:
Municipal Engineer
Remarks
44.6 356.8
7.5 40 300
9 44 396
12 8 96
792
\
9.45