COCOMO Model
COCOMO Model
are also an outcome of the Cocomo are primarily Effort & Schedule:
Software Project ab bb cb db
Effort = ab(KLOC)bb
Duration = cb(Effort)db
Therefore, KLOC = 4
Effort
= 2.4(KLOC)1.05 person/month
= 2.4(4)1.05 person/month
= 10.28 person/month
Duration
= 2.5(Effort)0.38 months
= 2.5(10.28)0.38 months
= 6.06 months
People required
= effort/duration
= 10.28/6.06
= 1.7