MATERIALES
MAT32 ABONO ORGANICO M3 $ 30,000.00
MAT24 ACERO DE REFUERZO f'y=60.000PSI KG $ 2,900.00
MAT480 ADAPTADOR HEMBRA DE 1/2" - PRESION SCH 40 UN $ 500.00
MAT471 ADAPTADOR MACHO DE 1/2" - PRESION SCH 40 UN $ 500.00
MAT1272 ALAMBRE DE PUAS GALVANIZADO - CALIBRE 12.5 ML $ 600.00
MAT26 ALAMBRE RECOCIDO NEGRO No. 18 KG $ 4,500.00
MAT206 ALFAJIA DE 2"x4" ML $ 3,000.00
MAT1254 ANGULO 6M 2-1/2 * 1/4 ML $ 20,000.00
MAT2588 ANGULO DE 1-1/2"X1-1/2"X1/8" ML $ 7,500.00
MAT1249 ANGULO METALICO DE 2x2" - 5/16" ML $ 8,500.00
MAT1250 ANGULO METALICO DE 1/2" ML $ 4,000.00
MAT1251 ANTICORROSIVO GAL $ 45,000.00
MAT1252 ANTISOL ROJO - SIKA KG $ 16,000.00
MAT57 ARBOL NATIVO - 3.0m UN $ 42,000.00
MAT18 ARENA M3 $ 40,000.00
MAT1258 ASPERSOR BOQUILLA 3/8 UN $ 20,000.00
MAT1245 Abrazaderas 10" UN $ 50,000.00
MAT1246 Abrazaderas 12" UN $ 55,000.00
MAT33 Abrazaderas 8" UN $ 40,000.00
MAT35 Acondicionador de superficie UN $ 84,500.00
MAT37 Adhesivo Epóxico (1/4 gl) UN $ 102,000.00
MAT41 Agua LT $ 50.00
MAT1256 BOMBA SUMERGIBLE 1 HP PARA AGUAS RESIDUALES TIPO PEDROLLO O SIMILAR UN $ 2,000,000.00
BOMBA SUMERGIBLE 2 HP PARA AGUAS RESIDUALES PARA EL SISTEMA DE
MAT1257 UN $ 4,610,000.00
AIREACION PROLONGADA
MAT465 BUJE ROSCADO DE 2" x 1/2" - PRESION SCH 40 UN $ 7,327.00
MAT30 CEMENTO GRIS TIPO 1 KG $ 550.00
MAT30 CEMENTO GRIS TIPO 5 KG $ 600.00
MAT357 CINTA PARA JUNTAS SIKA PVC O-22 ML $ 30,000.00
MAT1266 COALTAR EPOXICO COMPONENTE A GAL $ 160,000.00
MAT1267 COALTAR EPOXICO COMPONENTE B GAL $ 110,000.00
MAT523 CODO CxC 90° DE 3" SANITARIA UN $ 8,000.00
MAT524 CODO CxC 90° DE 4" SANITARIA UN $ 14,700.00
MAT383 CODO DE 90° DE 1/2" - PRESION SCH 40 UN $ 600.00
MAT132 CODO DE 90º 1-1/2" - PRESION UN $ 6,500.00
MAT1264 CORREAS PLASTICAS UN $ 100.00
MAT1120 ESMALTE DE PINTUCO GL $ 65,000.00
MAT993 ESTACAS DE MADERA UN $ 1,000.00
MAT1248 Escalones 3/4", pintados con aticorrosivo UN $ 15,000.00
MAT177 FORMALETA PARA ESTRUCTURAS EN CONCRETO M3 $ 200,000.00
MAT172 FORMALETA PARA COLUMNA UN $ 180,000.00
MAT178 FORMALETA PARA PEDESTALES UN $ 40,000.00
MAT1104 FORMALETA PARA VIGA DINTEL UN $ 140,000.00
MAT173 FORMALETA PARA VIGAS UN $ 150,000.00
MAT1900 Geomembrana 40 ml M2 $ 18,000.00
MAT1901 Geotextil NT 2000 M2 $ 8,000.00
MAT190 GRAMA NATURAL PARA ZONAS VERDES M2 $ 12,000.00
MAT17 GRAVILLA DE 1/4" - 1/2" M3 $ 62,000.00
INSUMOS DEL PRESUPUESTO
ALCALDÍA MUNICIPAL DE CHIRIGUANÁ
Entidad:
CONSTRUCCIÓN DE LOS SISTEMAS DE ALCANTARILLADO SANITARIO Y TRATAMIENTO DE LAS AGUAS
Proyecto:
RESIDUALES DEL CORREGIMIENTO DE POPONTE MUNICIPIO DE CHIRIGUANA DEPARTAMENTO DEL CESAR
Proponente:
EQUIPOS
EQU03 ANDAMIO TUBULAR 1.50x1.50m DIA $ 1,500.00
EQU06 CARRO TANQUE IRRIGADOR HORA $ 60,000.00
EQU07 CERCHAS METALICAS SEC $ 300.00
EQU117 COMPRESOR HORA $ 10,000.00
EQU151 Cargador HORA $ 120,000.00
EQU10 Compactador manual vibratorio - Tipo Canguro - Apisonadores. HORA $ 10,000.00
EQU115 DIFERENCIAL HORA $ 10,000.00
EQU116 EQUIPO DE OXICORTE HORA $ 15,000.00
EQU102 EQUIPO DE SOLDADURA HORA $ 15,000.00
EQU14 EQUIPO DE TOPOGRAFIA HORA $ 18,750.00
EQU55 FORMALETA PARA MUROS EN CONCRETO DIA $ 220,000.00
MAT1114 Formaleta metálica (concreto hidraulico) HORA $ 6,000.00
MAT174 Formaleta metálica (para pozos de inspección) HORA $ 12,500.00
EQU60 GUARDERAS 0.40x1.40m DIA $ 300.00
EQU01 Herramientas Menores GLOB $ 10,000.00
INSUMOS DEL PRESUPUESTO
ALCALDÍA MUNICIPAL DE CHIRIGUANÁ
Entidad:
CONSTRUCCIÓN DE LOS SISTEMAS DE ALCANTARILLADO SANITARIO Y TRATAMIENTO DE LAS AGUAS
Proyecto:
RESIDUALES DEL CORREGIMIENTO DE POPONTE MUNICIPIO DE CHIRIGUANA DEPARTAMENTO DEL CESAR
Proponente:
MANO DE OBRAS
MOB153 INGENIERO QUIMICO DIA $ 149,351.00
MOB154 AUXILIAR QUIMICO DIA $ 65,368.00
MOB152 (Cuadrilla tipo 5) Hr $ 44,048.38
MOB150 (Cuadrilla tipo 2) Hr $ 27,706.38
MOB151 (Cuadrilla tipo 4) Hr $ 35,877.38
MOB04 Cuadrilla topografica HORA $ 33,546.75
TRANSPORTES
TRA01 Transporte de material TF $ 10,000.00
TRA10 Transporte de material petreo M3-KM $ 1,100.00
ANALISIS DE PRECIOS UNITARIOS BASICOS
ALCALDÍA MUNICIPAL DE CHIRIGUANÁ
Entidad
CONSTRUCCIÓN DE LOS SISTEMAS DE ALCANTARILLADO SANITARIO Y TRATAMIENTO DE LAS AGUAS RESIDUALES DEL CORREGIMIENTO DE
Proyecto
POPONTE MUNICIPIO DE CHIRIGUANA DEPARTAMENTO DEL CESAR
Proponente
Código Descripción Unidad Rend./Cant. Vr. Unitario Vr. Parcial Vr. Rubro
Código Descripción Unidad Rend./Cant. Vr. Unitario Vr. Parcial Vr. Rubro
Código Descripción Unidad Rend./Cant. Vr. Unitario Vr. Parcial Vr. Rubro
Código Descripción Unidad Rend./Cant. Vr. Unitario Vr. Parcial Vr. Rubro
U1001 1.1 Localización, Replanteo, nivelación de tubería, incluye comision topografica permanente. UN: ML
MATERIALES
MAT27 PUNTILLA DE 1" - 3.1/2" LB 0.0300 4,500.00 135.00
MAT993 ESTACAS DE MADERA UN 0.1000 1,000.00 100.00 235.00
EQUIPOS
EQU01 Herramientas Menores GLOB 100.0000 10,000.00 100.00
EQU14 EQUIPO DE TOPOGRAFIA HORA 50.0000 18,750.00 375.00 475.00
MANO DE OBRA
MOB04 Cuadrilla topografica HORA 20.2600 33,546.75 1,655.81 1,655.81
Valor Costo Directo 2,365.81
Valor Aproximación 0.19
Costo Unitario Total 2,366.00
U211 2.1 Excavaciones mecanica para instalación de tubería en material comun y/o conglomerado de 0.00 a 1.50 m de profundidad UN: M3
EQUIPOS
EQU01 Herramientas Menores GLOB 1,000,000.00 10,000.00 100.00
EQU21 RETROEXCAVADORA HORA 14.0000 180,000.00 12,857.14 12,957.14
MANO DE OBRA
MOB150 Cuadrilla AA Hr 24.6600 27,706.38 1,123.54 1,123.54
Valor Costo Directo 14,080.68
Valor Aproximación 0.32
Costo Unitario Total 14,081.00
U501 2.2 Excavaciones mecanicas para instalación de tubería en material comun y/o conglomerado de 1.51 a 3.00 m de profundidad UN: M3
EQUIPOS
EQU01 Herramientas Menores GLOB 100.0000 10,000.00 100.00
EQU21 RETROEXCAVADORA HORA 13.0000 180,000.00 13,846.15 13,946.15
MANO DE OBRA
MOB150 Cuadrilla AA Hr 18.5100 27,706.38 1,496.83 1,496.83
Valor Costo Directo 15,442.98
Valor Aproximación 0.02
Costo Unitario Total 15,443.00
U502 2.3 Excavaciones mecanica para la instalación de tubería en material comun y/o conglomerado de 3.01 a 4.50 m de profundidad UN: M3
EQUIPOS
EQU01 Herramientas Menores GLOB 100.0000 10,000.00 100.00
EQU21 RETROEXCAVADORA HORA 13.0000 180,000.00 13,846.15 13,946.15
MANO DE OBRA
MOB150 Cuadrilla AA Hr 10.4800 27,706.38 2,643.74 2,643.74
Valor Costo Directo 16,589.89
Valor Aproximación 0.11
Costo Unitario Total 16,590.00
ANALISIS DE PRECIOS UNITARIOS
ALCALDÍA MUNICIPAL DE CHIRIGUANÁ
Entidad
CONSTRUCCIÓN DE LOS SISTEMAS DE ALCANTARILLADO SANITARIO Y TRATAMIENTO DE LAS AGUAS RESIDUALES DEL
Proyecto
CORREGIMIENTO DE POPONTE MUNICIPIO DE CHIRIGUANA DEPARTAMENTO DEL CESAR
Código Descripción Unidad Rend./Cant. Vr. Unitario Vr. Parcial Vr. Rubro
U537 2.4 Excavación en roca meteorizada UN: M3
EQUIPOS
EQU01 Herramientas Menores GLOB 100.0000 10,000.00 100.00
EQU21 RETROEXCAVADORA HORA 16.0000 180,000.00 11,250.00 11,350.00
MANO DE OBRA
MOB150 Cuadrilla AA Hr 37.0100 27,706.38 748.62 748.62
Valor Costo Directo 12,098.62
Valor Aproximación 0.38
Costo Unitario Total 12,099.00
U1042 2.5 Excavación manual para la instalación de tuberia de 6" para conexiones domiciliarias. UN: M3
EQUIPOS
EQU01 Herramientas Menores GLOB 10.0000 10,000.00 1,000.00 1,000.00
MANO DE OBRA
MOB150 Cuadrilla AA Hr 0.9620 27,706.38 28,800.81 28,800.81
Valor Costo Directo 29,800.81
Valor Aproximación 0.19
Costo Unitario Total 29,801.00
U575 3.1 SUMINISTRO Y COLOCACION DE ARENA GRUESA 1/8" - 1/4" para cimentacion o apayo de la tubería. UN: M3
MATERIALES
MAT18 ARENA M3 1.0000 40,000.00 40,000.00 40,000.00
EQUIPOS
EQU01 Herramientas Menores GLOB 10.0000 10,000.00 1,000.00 1,000.00
MANO DE OBRA
MOB150 Cuadrilla AA Hr 1.2300 27,706.38 22,525.51 22,525.51
TRANSPORTES
TRA01 Transporte de material M3-Km 30.0000 1,100.00 33,000.00 33,000.00
Valor Costo Directo 96,525.51
Valor Aproximación 0.49
Costo Unitario Total 96,526.00
ANALISIS DE PRECIOS UNITARIOS
ALCALDÍA MUNICIPAL DE CHIRIGUANÁ
Entidad
CONSTRUCCIÓN DE LOS SISTEMAS DE ALCANTARILLADO SANITARIO Y TRATAMIENTO DE LAS AGUAS RESIDUALES DEL
Proyecto
CORREGIMIENTO DE POPONTE MUNICIPIO DE CHIRIGUANA DEPARTAMENTO DEL CESAR
Código Descripción Unidad Rend./Cant. Vr. Unitario Vr. Parcial Vr. Rubro
U1140 3.2 SUMINISTRO E ISNTALACIÓN GRAVILLA FINA DE 1/4" - 1/2" para cimentacion o apayo de la tubería. UN: M3
MATERIALES
MAT17 GRAVILLA DE 1/4" - 1" M3 1.0000 62,000.00 62,000.00
Desperdicio Ponderado % 5.00 62,000.00 3,100.00 65,100.00
EQUIPOS
EQU01 Herramientas Menores GLOB 5.0000 10,000.00 2,000.00 2,000.00
MANO DE OBRA
MOB150 Cuadrilla AA Hr 1.1100 27,706.38 24,960.70 24,960.70
TRANSPORTES
TRA01 Transporte de material M3-Km 30.0000 1,100.00 33,000.00 33,000.00
Valor Costo Directo 125,060.70
Valor Aproximación 0.30
Costo Unitario Total 125,061.00
4.1 Instalación de tubería de PVC con sistema de unión mecánica, campana espigo con hidrosello, de pared interior lisa y exterior corrugada, de
U503
diametro 8" (200 mm). UN: ML
MATERIALES
MAT1240 Hidrosello - 200MM UN 8,000.00 0.00
MAT219 Lubricantes 500 gramos UN 0.0300 24,000.00 720.00
MAT221 Limpiador PVC 1/4 Gal GAL 54,000.00 0.00 720.00
EQUIPOS
EQU01 Herramientas Menores GLOB 10.0000 10,000.00 1,000.00 1,000.00
MANO DE OBRA
MOB151 Cuadrilla BB Hr 2.3230 35,877.38 15,444.41 15,444.41
Valor Costo Directo 17,164.41
Valor Aproximación -0.41
Costo Unitario Total 17,164.00
4.2 Instalaciòn de tuberia de PVC con sistema de unión mecanica, campana espigo con hidrosello, de pared interior lisa y exterior corrugada, de
U505
diametro 10" (250 mm). UN: ML
MATERIALES
MAT1241 Hidrosello - 250MM UN 13,500.00 0.00
MAT219 Lubricantes 500 gramos UN 0.0500 24,000.00 1,200.00
MAT221 Limpiador PVC 1/4 Gal GAL 54,000.00 0.00 1,200.00
EQUIPOS
EQU01 Herramientas Menores GLOB 10.0000 10,000.00 1,000.00 1,000.00
MANO DE OBRA
MOB151 Cuadrilla BB Hr 1.7500 35,877.38 20,501.36 20,501.36
Valor Costo Directo 22,701.36
Valor Aproximación -0.36
Costo Unitario Total 22,701.00
ANALISIS DE PRECIOS UNITARIOS
ALCALDÍA MUNICIPAL DE CHIRIGUANÁ
Entidad
CONSTRUCCIÓN DE LOS SISTEMAS DE ALCANTARILLADO SANITARIO Y TRATAMIENTO DE LAS AGUAS RESIDUALES DEL
Proyecto
CORREGIMIENTO DE POPONTE MUNICIPIO DE CHIRIGUANA DEPARTAMENTO DEL CESAR
Código Descripción Unidad Rend./Cant. Vr. Unitario Vr. Parcial Vr. Rubro
4.3 Instalaciòn de tuberia de PVC con sistema de unión mecanica, campana espigo con hidrosello, de pared interior lisa y exterior corrugada, de
U507
diametro 12" (315 mm). UN: ML
MATERIALES
MAT1242 Hidrosello - 315MM UN 27,000.00 0.00
MAT219 Lubricantes 500 gramos UN 0.0500 24,000.00 1,200.00
MAT221 Limpiador PVC 1/4 Gal GAL 54,000.00 0.00 1,200.00
EQUIPOS
EQU01 Herramientas Menores GLOB 10.0000 10,000.00 1,000.00 1,000.00
MANO DE OBRA
MOB151 Cuadrilla BB Hr 1.4513 35,877.38 24,720.06 24,720.06
Valor Costo Directo 26,920.06
Valor Aproximación -0.06
Costo Unitario Total 26,920.00
4.4 Instalaciòn de tuberia de PVC con sistema de unión mecanica, campana espigo con hidrosello, de pared interior lisa y exterior corrugada, de
U509
diametro 16" (400 mm). UN: ML
MATERIALES
MAT1243 Hidrosello - 400MM UN 55,000.00 0.00
MAT219 Lubricantes 500 gramos UN 0.1000 24,000.00 2,400.00
MAT221 Limpiador PVC 1/4 Gal GAL 54,000.00 0.00 2,400.00
EQUIPOS
EQU01 Herramientas Menores GLOB 5.0000 10,000.00 2,000.00 2,000.00
MANO DE OBRA
MOB151 Cuadrilla BB Hr 1.1620 35,877.38 30,875.54 30,875.54
Valor Costo Directo 35,275.54
Valor Aproximación 0.46
Costo Unitario Total 35,276.00
5.1 Relleno con material clasificado de la misma excavación compactado al 95% del proctor modificado: Incluye herramientas menores, equipos de
U222
compactación y mano de obra. UN: M3
MATERIALES
MAT41 Agua LT 10.0000 50.00 500.00 500.00
EQUIPOS
EQU01 Herramientas Menores GLOB 10.0000 10,000.00 1,000.00
Compactador manual vibratorio - Tipo Canguro -
EQU10 HORA 1.5000 10,000.00 6,666.67 7,666.67
Apisonadores.
MANO DE OBRA
MOB150 Cuadrilla AA Hr 3.0822 27,706.38 8,989.16 8,989.16
Valor Costo Directo 17,155.83
Valor Aproximación 0.17
Costo Unitario Total 17,156.00
5.2 Relleno con material seleccionado de cantera, compactado al 95% del proctor modificado: incluye la explotación, cargue y transporte del
U514
material, herramientas menores, equipos de compactación y mano de obra. UN: M3
MATERIALES
MAT15 Material de relleno seleccionado M3 1.0000 24,000.00 24,000.00
MAT41 Agua LT 20.000 50.00 1,000.00
Desperdicio y compactación % 15.00 25,000.00 3,750.00 28,750.00
EQUIPOS
EQU01 Herramientas Menores GLOB 20.0000 10,000.00 500.00
Compactador manual vibratorio - Tipo Canguro -
EQU10 HORA 3.0000 10,000.00 3,333.33 3,833.33
Apisonadores.
MANO DE OBRA
MOB150 Cuadrilla AA Hr 4.9400 27,706.38 5,608.58 5,608.58
TRANSPORTES
TRA10 Transporte de material petreo M3-KM 30.0000 1,100.00 33,000.00 33,000.00
Valor Costo Directo 71,191.91
Valor Aproximación 0.09
Costo Unitario Total 71,192.00
ANALISIS DE PRECIOS UNITARIOS
ALCALDÍA MUNICIPAL DE CHIRIGUANÁ
Entidad
CONSTRUCCIÓN DE LOS SISTEMAS DE ALCANTARILLADO SANITARIO Y TRATAMIENTO DE LAS AGUAS RESIDUALES DEL
Proyecto
CORREGIMIENTO DE POPONTE MUNICIPIO DE CHIRIGUANA DEPARTAMENTO DEL CESAR
Código Descripción Unidad Rend./Cant. Vr. Unitario Vr. Parcial Vr. Rubro
5.3 Retiro de material sobrante de la excavación y escombros y limpieza general de obra, incluye: cargue, transporte, herramientas menores y
U1069
mano de obra. UN: M3
EQUIPOS
EQU01 Herramientas Menores GLOB 200.0000 10,000.00 50.00
EQU151 Cargador HORA 90.0000 120,000.00 1,333.33 1,383.33
MANO DE OBRA
MOB150 Cuadrilla AA Hr 37.0100 27,706.38 748.62 748.62
TRANSPORTES
TRA10 Transporte de material petreo M3-KM 18.0000 1,100.00 19,800.00 19,800.00
Valor Costo Directo 21,931.95
Valor Aproximación 0.05
Costo Unitario Total 21,932.00
6.1 Instalaciòn de tuberia de PVC con sistema de unión mecanica, campana espigo con hidrosello, de pared interior lisa y exterior corrugada, de
U515
diametro 6" (160 mm). UN: ML
MATERIALES
MAT1244 Hidrosello - 160MM UN 4,000.00 0.00
MAT219 Lubricantes 500 gramos UN 0.0200 24,000.00 480.00
MAT221 Limpiador PVC 1/4 Gal GAL 54,000.00 0.00 480.00
EQUIPOS
EQU01 Herramientas Menores GLOB 13.0000 10,000.00 769.23 769.23
MANO DE OBRA
MOB151 Cuadrilla BB Hr 2.9030 35,877.38 12,358.72 12,358.72
Valor Costo Directo 13,607.95
Valor Aproximación 0.05
Costo Unitario Total 13,608.00
U517 6.2 Instalación Silla Yee de 8"x6" (200 x160 mm) UN: UN
MATERIALES
MAT33 Abrazaderas 8" UN 40,000.00 0.00
MAT35 Acondicionador de superficie UN 0.0100 84,500.00 845.00
MAT37 Adhesivo Epóxico (1/4 gl) UN 0.3000 102,000.00 30,600.00 31,445.00
EQUIPOS
EQU01 Herramientas Menores GLOB 10.0000 10,000.00 1,000.00 1,000.00
MANO DE OBRA
MOB151 Cuadrilla BB Hr 5.8100 35,877.38 6,175.11 6,175.11
Valor Costo Directo 38,620.11
Valor Aproximación -0.11
Costo Unitario Total 38,620.00
U519 6.3 Instalación Silla Yee de 10"x6" (250 x160 mm) UN: UN
MATERIALES
MAT1245 Abrazaderas 10" UN 50,000.00 0.00
MAT35 Acondicionador de superficie UN 0.0100 84,500.00 845.00
MAT37 Adhesivo Epóxico (1/4 gl) UN 0.3500 102,000.00 35,700.00 36,545.00
EQUIPOS
EQU01 Herramientas Menores GLOB 10.0000 10,000.00 1,000.00 1,000.00
MANO DE OBRA
MOB151 Cuadrilla BB Hr 4.3600 35,877.38 8,228.76 8,228.76
Valor Costo Directo 45,773.76
Valor Aproximación 0.24
Costo Unitario Total 45,774.00
ANALISIS DE PRECIOS UNITARIOS
ALCALDÍA MUNICIPAL DE CHIRIGUANÁ
Entidad
CONSTRUCCIÓN DE LOS SISTEMAS DE ALCANTARILLADO SANITARIO Y TRATAMIENTO DE LAS AGUAS RESIDUALES DEL
Proyecto
CORREGIMIENTO DE POPONTE MUNICIPIO DE CHIRIGUANA DEPARTAMENTO DEL CESAR
Código Descripción Unidad Rend./Cant. Vr. Unitario Vr. Parcial Vr. Rubro
U524 6.4 Instalación Sillas Yee de 12" x 6" (315 mm x 160 mm) UN: UN
MATERIALES
MAT1246 Abrazaderas 12" UN 55,000.00 0.00
MAT35 Acondicionador de superficie UN 0.0100 84,500.00 845.00
MAT37 Adhesivo Epóxico (1/4 gl) UN 0.5000 102,000.00 51,000.00 51,845.00
EQUIPOS
EQU01 Herramientas Menores GLOB 10.0000 10,000.00 1,000.00 1,000.00
MANO DE OBRA
MOB151 Cuadrilla BB Hr 4.3600 35,877.38 8,228.76 8,228.76
Valor Costo Directo 61,073.76
Valor Aproximación 0.24
Costo Unitario Total 61,074.00
U527 7.1.1 Construcción de pozo con altura menor de 1.80 m. Hprm. 1.38 m. UN: UN
MATERIALES
MAT1247 Tapa en ferroconcreto D= 0.60 m. UN 1.0000 225,000.00 225,000.00
MAT1248 Escalones 3/4", pintados con aticorrosivo UN 5.0000 15,000.00 75,000.00
CONCRETO ESTRUCTURAL f'c=28MPA (4.000 PSI),
U1048 M3 2.0000 546,192.00 1,092,384.00
impermeabilizado
U423 Acero de refuerzo PDR-60; f'y=420 Mpa KG 20.0000 5,592.00 111,840.00 1,504,224.00
EQUIPOS
EQU01 Herramientas Menores GLOB 0.5000 10,000.00 20,000.00
EQU25 Vibrador de concreto HORA 1.0000 9,000.00 9,000.00
MAT174 Formaleta metálica (para pozos de inspección) HORA 0.2000 12,500.00 62,500.00 91,500.00
MANO DE OBRA
MOB150 Cuadrilla AA Hr 0.0540 27,706.38 513,081.02 513,081.02
Valor Costo Directo 2,108,805.02
U528 7.1.2 Construcción de pozo con altura mayor de 1.80 m. Hprm. 2.35 m. UN: UN
MATERIALES
MAT1247 Tapa en ferroconcreto D= 0.60 m. UN 1.0000 225,000.00 225,000.00
MAT1248 Escalones 3/4", pintados con aticorrosivo UN 8.0000 15,000.00 120,000.00
CONCRETO ESTRUCTURAL f'c=28MPA (4.000 PSI),
U1048 M3 2.3000 546,192.00 1,256,241.60
impermeabilizado
U423 Acero de refuerzo PDR-60; f'y=420 Mpa KG 25.0000 5,592.00 139,800.00 1,741,041.60
EQUIPOS
EQU01 Herramientas Menores GLOB 0.4000 10,000.00 25,000.00
EQU25 Vibrador de concreto HORA 1.0000 9,000.00 9,000.00
MAT174 Formaleta metálica (para pozos de inspección) HORA 0.2000 12,500.00 62,500.00 96,500.00
MANO DE OBRA
MOB150 Cuadrilla AA Hr 0.0448 27,706.38 618,445.87 618,445.87
Valor Costo Directo 2,455,987.47
Valor Aproximación -0.47
Costo Unitario Total 2,455,987.00
ANALISIS DE PRECIOS UNITARIOS
ALCALDÍA MUNICIPAL DE CHIRIGUANÁ
Entidad
CONSTRUCCIÓN DE LOS SISTEMAS DE ALCANTARILLADO SANITARIO Y TRATAMIENTO DE LAS AGUAS RESIDUALES DEL
Proyecto
CORREGIMIENTO DE POPONTE MUNICIPIO DE CHIRIGUANA DEPARTAMENTO DEL CESAR
Código Descripción Unidad Rend./Cant. Vr. Unitario Vr. Parcial Vr. Rubro
U529 7.1.3 Construcción de pozo con altura mayor de 2.35 m. Hprm. 2.85 m. UN: UN
MATERIALES
MAT1247 Tapa en ferroconcreto D= 0.60 m. UN 1.0000 225,000.00 225,000.00
MAT1248 Escalones 3/4", pintados con aticorrosivo UN 10.0000 15,000.00 150,000.00
CONCRETO ESTRUCTURAL f'c=28MPA (4.000 PSI),
U1048 M3 2.8500 546,192.00 1,556,647.20
impermeabilizado
U423 Acero de refuerzo PDR-60; f'y=420 Mpa KG 30.0000 5,592.00 167,760.00 2,099,407.20
EQUIPOS
EQU01 Herramientas Menores GLOB 0.3000 10,000.00 33,333.33
EQU25 Vibrador de concreto HORA 1.0000 9,000.00 9,000.00
MAT174 Formaleta metálica (para pozos de inspección) HORA 0.2000 12,500.00 62,500.00 104,833.33
MANO DE OBRA
MOB150 Cuadrilla AA Hr 0.0363 27,706.38 763,261.02 763,261.02
Valor Costo Directo 2,967,501.55
Valor Aproximación 0.45
Costo Unitario Total 2,967,502.00
8.1 Construcción de cajas de inspección para conexiones domiciliarias, de sección interna 0.50 x 0.50 m, de 0.60 m de profundidad, con muros y placa de fondo en
U6110 concreto de 3000 PSI impermeabilizado de e = 0.10 m., reforzado con maya electroso UN: UN
MATERIALES
MAT51 Ángulo de 2"x2"x1/8" ML 4.0000 7,000.00 28,000.00
U1084 MORTERO 1:4 M3 0.0250 404,951.00 10,123.78
U1089 CONCRETO ESTRUCTURAL f'c=21MPA (3.000PSI). M3 0.2400 463,946.00 111,347.04
U423 Acero de refuerzo PDR-60; f'y=420 Mpa KG 7.0000 5,592.00 39,144.00
Desperdicio Ponderado % 3.88 188,614.82 7,318.26 195,933.08
EQUIPOS
EQU01 Herramientas Menores GLOB 2.5000 10,000.00 4,000.00
EQU25 Vibrador de concreto HORA 3.0000 9,000.00 3,000.00
MAT1114 Formaleta metálica (concreto hidraulico) HORA 0.5000 6,000.00 12,000.00 19,000.00
MANO DE OBRA
MOB150 Cuadrilla AA Hr 0.3336 27,706.38 83,052.68 83,052.68
Valor Costo Directo 297,985.76
Valor Aproximación 0.24
Valor Costo Directo 297,986.00
U533 9.2 Reparaciones de conexiones domiciliarias de acueducto en PVC de presion, Incluye tuberia de 1/2", accesorios y mano de obra UN: UN
MATERIALES
MAT220 Soldadura liquida PVC 1/4 Gal. UN 0.0200 91,861.00 1,837.22
MAT348 Tuberia PVC presión 1/2" RDE 9 ML 1.5000 3,562.00 5,343.00
MAT374 Union simple de 1/2" UN 2.0000 400.00 800.00
MAT423 Tapon Soldado 1/2" UN 2.0000 350.00 700.00 8,680.22
EQUIPOS
EQU01 Herramientas Menores GLOB 5.0000 10,000.00 2,000.00 2,000.00
MANO DE OBRA
MOB151 Cuadrilla BB Hr 0.8860 35,877.38 40,493.65 40,493.65
TRANSPORTES
TRA01 Transporte de material TF 0.5000 10,000.00 5,000.00 5,000.00
Valor Costo Directo 56,173.87
Valor Aproximación 0.13
Costo Unitario Total 56,174.00
ANALISIS DE PRECIOS UNITARIOS
ALCALDÍA MUNICIPAL DE CHIRIGUANÁ
Entidad
CONSTRUCCIÓN DE LOS SISTEMAS DE ALCANTARILLADO SANITARIO Y TRATAMIENTO DE LAS AGUAS RESIDUALES DEL
Proyecto
CORREGIMIENTO DE POPONTE MUNICIPIO DE CHIRIGUANA DEPARTAMENTO DEL CESAR
Código Descripción Unidad Rend./Cant. Vr. Unitario Vr. Parcial Vr. Rubro
U534 10.1 Excavación manual para zapata y pedestal. UN: M3
EQUIPOS
EQU01 Herramientas Menores GLOB 10.0000 10,000.00 1,000.00 1,000.00
MANO DE OBRA
MOB150 Cuadrilla AA Hr 0.9620 27,706.38 28,800.81 28,800.81
Valor Costo Directo 29,801.00
U1090 10.2 Concreto de f'c=2.500 PSI - Impermeabilizado, para solado e = 0.05m. UN: M3
MATERIALES
MAT3010 PLASTOCRETE DM GAL 2.0000 12,500.00 25,000.00
U1089 CONCRETO ESTRUCTURAL f'c=14MPA (2.500PSI). M3 1.0000 404,864.00 404,864.00
Desperdicio Ponderado % 3.00 429,864.00 12,895.92 442,759.92
EQUIPOS
EQU01 Herramientas Menores GLOB 10.0000 10,000.00 1,000.00 1,000.00
MANO DE OBRA
MOB150 Cuadrilla AA Hr 0.3194 27,706.38 86,745.07 86,745.07
TRANSPORTES
TRA01 Transporte de material TF 10,000.00 0.00 0.00
Valor Costo Directo 530,504.99
Valor Aproximación 0.01
Costo Unitario Total 530,505.00
U1141 10.3 Concreto de f'c=3.000 PSI - Impermeabilizado, para zapatas y pedestales UN: M3
MATERIALES
MAT1003 REPISA DE MADERA 4"x4" ML 4.0000 7,500.00 30,000.00
MAT178 FORMALETA PARA PEDESTALES UN 1.0000 40,000.00 40,000.00
MAT2585 SEPAROL (15KG) KG 1.0000 15,000.00 15,000.00
MAT27 PUNTILLA DE 1" - 3.1/2" LB 2.0000 4,500.00 9,000.00
MAT3010 PLASTOCRETE DM GAL 2.0000 12,500.00 25,000.00
U1048 CONCRETO ESTRUCTURAL f'c=21MPA (3.000 PSI). M3 1.0000 463,946.00 463,946.00
Desperdicio Ponderado % 3.00 582,946.00 17,488.38 600,434.38
EQUIPOS
EQU01 Herramientas Menores GLOB 10.0000 10,000.00 1,000.00
EQU24 VIBRADOR A GASOLINA SIN OPERADOR DIA 4.0000 45,000.00 11,250.00 12,250.00
MANO DE OBRA
MOB150 Cuadrilla AA Hr 0.1337 27,706.38 207,227.94 207,227.94
TRANSPORTES
TRA01 Transporte de material TF 2.0000 10,000.00 20,000.00 20,000.00
Valor Costo Directo 839,912.32
Valor Aproximación -0.32
Costo Unitario Total 839,912.00
ANALISIS DE PRECIOS UNITARIOS
ALCALDÍA MUNICIPAL DE CHIRIGUANÁ
Entidad
CONSTRUCCIÓN DE LOS SISTEMAS DE ALCANTARILLADO SANITARIO Y TRATAMIENTO DE LAS AGUAS RESIDUALES DEL
Proyecto
CORREGIMIENTO DE POPONTE MUNICIPIO DE CHIRIGUANA DEPARTAMENTO DEL CESAR
Código Descripción Unidad Rend./Cant. Vr. Unitario Vr. Parcial Vr. Rubro
10.6 Relleno con material clasificado de la misma excavación compactado al 95% del proctor modificado: Incluye herramientas menores, equipos
U222
de compactación y mano de obra. UN: M3
MATERIALES
MAT41 Agua LT 10.0000 50.00 500.00 500.00
EQUIPOS
EQU01 Herramientas Menores GLOB 10.0000 10,000.00 1,000.00
Compactador manual vibratorio - Tipo Canguro -
EQU10 HORA 1.5000 10,000.00 6,666.67 7,666.67
Apisonadores.
MANO DE OBRA
MOB150 Cuadrilla AA Hr 3.0830 27,706.38 8,986.82 8,986.82
Valor Costo Directo 17,153.49
Valor Aproximación -0.49
Costo Unitario Total 17,153.00
ANALISIS DE PRECIOS UNITARIOS
ALCALDÍA MUNICIPAL DE CHIRIGUANÁ
Entidad
CONSTRUCCIÓN DE LOS SISTEMAS DE ALCANTARILLADO SANITARIO Y TRATAMIENTO DE LAS AGUAS RESIDUALES DEL
Proyecto
CORREGIMIENTO DE POPONTE MUNICIPIO DE CHIRIGUANA DEPARTAMENTO DEL CESAR
Código Descripción Unidad Rend./Cant. Vr. Unitario Vr. Parcial Vr. Rubro
U535 10.7 Suministro e instalación cercha metálica ángulo L 2"X2"X5/16". UN: ML
MATERIALES
MAT1120 ESMALTE DE PINTUCO GL 0.3000 65,000.00 19,500.00
MAT1249 ANGULO METALICO DE 2x2" - 5/16" ML 14.0000 8,500.00 119,000.00
MAT1250 LAMINA 35x35x1/2" UN 0.0650 1,500,000.00 97,500.00
MAT1251 ANTICORROSIVO GAL 0.3000 45,000.00 13,500.00
MAT270 SOLDADURA WEST ARCO E:60-11 KG 0.3000 8,000.00 2,400.00
MAT38 THINNER ADITIVOS PARA PINTURAS GAL 0.3000 20,000.00 6,000.00 257,900.00
EQUIPOS
EQU01 Herramientas Menores GLOB 2.0000 10,000.00 5,000.00
EQU102 EQUIPO DE SOLDADURA HORA 2.5000 15,000.00 6,000.00
EQU104 PULIDORA CON DISCO DIAMANTADO HORA 2.0000 8,500.00 4,250.00
EQU115 DIFERENCIAL HORA 2.0000 10,000.00 5,000.00
EQU116 EQUIPO DE OXICORTE HORA 2.0000 15,000.00 7,500.00
EQU117 COMPRESOR HORA 2.0000 10,000.00 5,000.00 32,750.00
MANO DE OBRA
MOB150 Cuadrilla AA Hr 0.2470 27,706.38 112,171.56 112,171.56
TRANSPORTES
TRA01 Transporte de material TF 5.0000 10,000.00 50,000.00 50,000.00
Valor Costo Directo 452,821.56
Valor Aproximación 0.44
Valor Costo Directo 452,822.00
Código Descripción Unidad Rend./Cant. Vr. Unitario Vr. Parcial Vr. Rubro
U539 13.1 Concreto de f'c=2.500 PSI - Impermeabilizado, para solado e = 0.05m. UN: M3
MATERIALES
MAT3010 PLASTOCRETE DM GAL 2.0000 12,500.00 25,000.00
U1089 CONCRETO ESTRUCTURAL f'c=14MPA (2.500PSI). M3 1.0000 404,864.00 404,864.00
Desperdicio Ponderado % 3.00 429,864.00 12,895.92 442,759.92
EQUIPOS
EQU01 Herramientas Menores GLOB 10.0000 10,000.00 1,000.00 1,000.00
MANO DE OBRA
MOB150 Cuadrilla AA Hr 0.3200 27,706.38 86,582.42 86,582.42
TRANSPORTES
TRA01 Transporte de material TF 10,000.00 0.00 0.00
Valor Costo Directo 530,342.34
Valor Aproximación -0.34
Costo Unitario Total 530,342.00
ANALISIS DE PRECIOS UNITARIOS
ALCALDÍA MUNICIPAL DE CHIRIGUANÁ
Entidad
CONSTRUCCIÓN DE LOS SISTEMAS DE ALCANTARILLADO SANITARIO Y TRATAMIENTO DE LAS AGUAS RESIDUALES DEL
Proyecto
CORREGIMIENTO DE POPONTE MUNICIPIO DE CHIRIGUANA DEPARTAMENTO DEL CESAR
Código Descripción Unidad Rend./Cant. Vr. Unitario Vr. Parcial Vr. Rubro
U1092 13.2 Concreto f'c=3.500 PSI impermabilizado para placa de fondo. UN: M3
MATERIALES
MAT1003 REPISA DE MADERA 4"x4" ML 4.0000 7,500.00 30,000.00
Código Descripción Unidad Rend./Cant. Vr. Unitario Vr. Parcial Vr. Rubro
U543 13.4 Concreto f'c=3.500 PSI impermabilizado para vigas de riostras muros. UN: M3
MATERIALES
MAT1003 REPISA DE MADERA 4"x4" ML 6.0000 7,500.00 45,000.00
MAT173 FORMALETA PARA VIGAS UN 1.0000 150,000.00 150,000.00
MAT2585 SEPAROL (15KG) KG 1.0000 15,000.00 15,000.00
MAT27 PUNTILLA DE 1" - 3.1/2" LB 2.0000 4,500.00 9,000.00
MAT3010 PLASTOCRETE DM GAL 2.0000 12,500.00 25,000.00
U2000 CONCRETO ESTRUCTURAL f'c=24.5MPA (3.500PSI) M3 1.0000 472,978.00 472,978.00
Desperdicio Ponderado % 3.00 716,978.00 21,509.34 738,487.34
EQUIPOS
EQU01 Herramientas Menores GLOB 2.0000 10,000.00 5,000.00
EQU03 ANDAMIO TUBULAR 1.50x1.50m DIA 0.2000 1,500.00 7,500.00
EQU19 PARAL TELESCOPICO SEC 0.1000 400.00 4,000.00
EQU24 VIBRADOR A GASOLINA SIN OPERADOR DIA 2.0000 45,000.00 22,500.00 39,000.00
MANO DE OBRA
MOB150 Cuadrilla AA Hr 0.1050 27,706.38 263,870.24 263,870.24
TRANSPORTES
TRA01 Transporte de material TF 2.0000 10,000.00 20,000.00 20,000.00
Valor Costo Directo 1,061,357.58
Valor Aproximación 0.42
Costo Unitario Total 1,061,358.00
U544 13.5 Concreto f'c=3.000 PSI impermabilizado para plataforma de operación y repaleo. UN: M3
MATERIALES
MAT1003 REPISA DE MADERA 4"x4" ML 6.0000 7,500.00 45,000.00
MAT177 FORMALETA PARA ESTRUCTURAS EN CONCRETO M3 1.0000 200,000.00 200,000.00
MAT2585 SEPAROL (15KG) KG 1.0000 15,000.00 15,000.00
MAT27 PUNTILLA DE 1" - 3.1/2" LB 2.0000 4,500.00 9,000.00
MAT3010 PLASTOCRETE DM GAL 2.0000 12,500.00 25,000.00
U1048 CONCRETO ESTRUCTURAL f'c=21MPA (3.000 PSI). M3 1.0000 463,946.00 463,946.00
Desperdicio Ponderado % 3.00 757,946.00 22,738.38 780,684.38
EQUIPOS
EQU01 Herramientas Menores GLOB 2.0000 10,000.00 5,000.00
EQU03 ANDAMIO TUBULAR 1.50x1.50m DIA 0.2000 1,500.00 7,500.00
EQU19 PARAL TELESCOPICO SEC 0.1000 400.00 4,000.00
EQU24 VIBRADOR A GASOLINA SIN OPERADOR DIA 2.0000 45,000.00 22,500.00 39,000.00
MANO DE OBRA
MOB150 Cuadrilla AA Hr 0.1060 27,706.38 261,380.90 261,380.90
TRANSPORTES
TRA01 Transporte de material TF 2.0000 10,000.00 20,000.00 20,000.00
Valor Costo Directo 1,101,065.28
Valor Aproximación -0.28
Costo Unitario Total 1,101,065.00
ANALISIS DE PRECIOS UNITARIOS
ALCALDÍA MUNICIPAL DE CHIRIGUANÁ
Entidad
CONSTRUCCIÓN DE LOS SISTEMAS DE ALCANTARILLADO SANITARIO Y TRATAMIENTO DE LAS AGUAS RESIDUALES DEL
Proyecto
CORREGIMIENTO DE POPONTE MUNICIPIO DE CHIRIGUANA DEPARTAMENTO DEL CESAR
Código Descripción Unidad Rend./Cant. Vr. Unitario Vr. Parcial Vr. Rubro
U5440 13.7 Concreto f'c=3.000 PSI impermabilizado para cajillas de distibución y salida. UN: M3
MATERIALES
MAT1003 REPISA DE MADERA 4"x4" ML 3.0000 7,500.00 22,500.00
MAT177 FORMALETA PARA ESTRUCTURAS EN CONCRETO M3 0.5000 200,000.00 100,000.00
MAT2585 SEPAROL (15KG) KG 1.0000 15,000.00 15,000.00
MAT27 PUNTILLA DE 1" - 3.1/2" LB 2.0000 4,500.00 9,000.00
MAT3010 PLASTOCRETE DM GAL 2.0000 12,500.00 25,000.00
U1048 CONCRETO ESTRUCTURAL f'c=21MPA (3.000 PSI). M3 1.0000 463,946.00 463,946.00
Desperdicio Ponderado % 3.00 757,946.00 22,738.38 658,184.38
EQUIPOS
EQU01 Herramientas Menores GLOB 2.0000 10,000.00 5,000.00
EQU03 ANDAMIO TUBULAR 1.50x1.50m DIA 0.2000 1,500.00 7,500.00
EQU19 PARAL TELESCOPICO SEC 0.1000 400.00 4,000.00
EQU24 VIBRADOR A GASOLINA SIN OPERADOR DIA 4.0000 45,000.00 11,250.00 27,750.00
MANO DE OBRA
MOB150 Cuadrilla AA Hr 0.1200 27,706.38 230,886.46 230,886.46
TRANSPORTES
TRA01 Transporte de material TF 2.0000 10,000.00 20,000.00 20,000.00
Valor Costo Directo 936,820.84
Valor Aproximación 0.16
Costo Unitario Total 936,821.00
U5441 13.8 Concreto f'c=3.000 PSI impermabilizado para cunetas de drenaje. UN: M3
MATERIALES
MAT1003 REPISA DE MADERA 4"x4" ML 2.0000 7,500.00 15,000.00
Código Descripción Unidad Rend./Cant. Vr. Unitario Vr. Parcial Vr. Rubro
Costo Unitario Total 879,321.00
ANALISIS DE PRECIOS UNITARIOS
ALCALDÍA MUNICIPAL DE CHIRIGUANÁ
Entidad
CONSTRUCCIÓN DE LOS SISTEMAS DE ALCANTARILLADO SANITARIO Y TRATAMIENTO DE LAS AGUAS RESIDUALES DEL
Proyecto
CORREGIMIENTO DE POPONTE MUNICIPIO DE CHIRIGUANA DEPARTAMENTO DEL CESAR
Código Descripción Unidad Rend./Cant. Vr. Unitario Vr. Parcial Vr. Rubro
U547 14.1 Acero de refuerzo PDR-60; f'y=420 Mpa UN: KG
MATERIALES
MAT24 ACERO DE REFUERZO f'y=60.000PSI KG 1.0000 2,900.00 2,900.00
MAT26 ALAMBRE RECOCIDO NEGRO No. 18 KG 0.1000 4,500.00 450.00
MAT29 HOJA DE SEGUETA NICHOLSON UN 0.1000 4,000.00 400.00
Desperdicio Ponderado % 3.00 3,750.00 112.50 3,862.50
EQUIPOS
EQU01 Herramientas Menores GLOB 100.0000 10,000.00 100.00 100.00
MANO DE OBRA
MOB150 Cuadrilla AA Hr 20.9700 27,706.38 1,321.24 1,321.24
Valor Costo Directo 5,283.74
Valor Aproximación 0.26
Costo Unitario Total 5,284.00
U548 14.2 Rejilla para cribado en varillas de 1/2", Medidas 0.40 x 1.00m. UN: UN
MATERIALES
MAT5860 VARILLA CORRUGADA DE 1/2" ML 8.0000 2,500.00 20,000.00
MAT1250 ANGULO METALICO DE 1/2" ML 3.0000 4,000.00 12,000.00
MAT270 SOLDADURA WEST ARCO E:60-11 KG 4.0000 8,000.00 32,000.00
U1084 MORTERO 1:4 M3 0.1000 404,951.00 40,495.10
Desperdicio Ponderado % 5.00 104,495.10 5,224.76 109,719.86
EQUIPOS
EQU01 Herramientas Menores GLOB 0.2500 10,000.00 40,000.00
EQU100 PLANTA ELECTRICA 6.5 KW Hr 0.1500 30,000.00 200,000.00
EQU102 EQUIPO DE SOLDADURA HORA 0.1500 15,000.00 100,000.00
EQU116 EQUIPO DE OXICORTE HORA 0.1500 15,000.00 100,000.00 440,000.00
MANO DE OBRA
MOB150 Cuadrilla AA Hr 0.0740 27,706.38 374,410.47
MOB152 Cuadrilla DD Hr 0.0740 44,048.38 595,248.31 969,658.78
TRANSPORTES
TRA01 Transporte de material TF 5.0000 10,000.00 50,000.00 50,000.00
Valor Costo Directo 1,569,378.64
Valor Aproximación 0.36
Costo Unitario Total 1,569,379.00
14.3 Suministro e instalacion de compuertas planas deslizantes de 0.40 X 0.40 m, con vastago de extensión de L = 1.50 m y rueda de manejo
U5490
UN: UN
MATERIALES
MAT1280 Compuerta Plana de 0.40 x 0.40 m Und 1.0000 1,800,000.00 1,800,000.00
MAT1281 Vastago de extensión L = 1.50 m Und 1.0000 350,000.00 350,000.00
MAT1282 Rueda de manejo Und 1.0000 120,000.00 120,000.00
MAT1283 Pernos de anclaje Und 6.0000 20,000.00 120,000.00
U1084 MORTERO 1:4 M3 0.1500 404,951.00 60,742.65 2,450,742.65
EQUIPOS
EQU01 Herramientas Menores GLOB 0.5000 10,000.00 20,000.00 20,000.00
MANO DE OBRA
MOB150 Cuadrilla AA Hr 0.2300 27,706.38 120,462.50 120,462.50
TRANSPORTES
TRA01 Transporte de material TF 5.0000 10,000.00 50,000.00 50,000.00
Valor Costo Directo 2,641,205.00
ANALISIS DE PRECIOS UNITARIOS
ALCALDÍA MUNICIPAL DE CHIRIGUANÁ
Entidad
CONSTRUCCIÓN DE LOS SISTEMAS DE ALCANTARILLADO SANITARIO Y TRATAMIENTO DE LAS AGUAS RESIDUALES DEL
Proyecto
CORREGIMIENTO DE POPONTE MUNICIPIO DE CHIRIGUANA DEPARTAMENTO DEL CESAR
Código Descripción Unidad Rend./Cant. Vr. Unitario Vr. Parcial Vr. Rubro
16.1 Instalaciòn de tuberia de PVC con sistema de unión mecanica, campana espigo con hidrosello, de pared interior lisa y exterior corrugada, de
U515
diametro 6" (160 mm). UN: ML
MATERIALES
MAT1244 Hidrosello - 160MM UN 4,000.00 0.00
MAT219 Lubricantes 500 gramos UN 0.0200 24,000.00 480.00
MAT221 Limpiador PVC 1/4 Gal GAL 54,000.00 0.00 480.00
EQUIPOS
EQU01 Herramientas Menores GLOB 13.0000 10,000.00 769.23 769.23
MANO DE OBRA
MOB151 Cuadrilla BB Hr 2.9100 35,877.38 12,328.99 12,328.99
Valor Costo Directo 13,578.22
Valor Aproximación -0.22
Costo Unitario Total 13,578.00
16.2 Instalaciòn de tuberia de PVC con sistema de unión mecanica, campana espigo con hidrosello, de pared interior lisa y exterior corrugada, de
U509
diametro 16" (400 mm). UN: ML
MATERIALES
MAT1243 Hidrosello - 400MM UN 55,000.00 0.00
Código Descripción Unidad Rend./Cant. Vr. Unitario Vr. Parcial Vr. Rubro
U222 17.1 Relleno con material de excavación para tape de zanja de tuberias. UN: M3
MATERIALES
MAT41 Agua LT 10.0000 50.00 500.00 500.00
EQUIPOS
EQU01 Herramientas Menores GLOB 10.0000 10,000.00 1,000.00
Compactador manual vibratorio - Tipo Canguro -
EQU10 HORA 1.5000 10,000.00 6,666.67 7,666.67
Apisonadores.
MANO DE OBRA
MOB150 Cuadrilla AA Hr 3.0900 27,706.38 8,966.46 8,966.46
Valor Costo Directo 17,133.13
Valor Aproximación -0.13
Costo Unitario Total 17,133.00
U5141 17.3 Conformacion de dique perimetral con material de excavación (Terraplen). UN: M3
EQUIPOS
EQU01 Herramientas Menores GLOB 100.0000 10,000.00 100.00
Compactador manual vibratorio - Tipo Canguro -
EQU10 HORA 2.5000 10,000.00 4,000.00
Apisonadores.
EQU27 VOLQUETA 6 m3 CON CARGUE VIAJE 40.0000 120,000.00 3,000.00
EQU06 CARRO TANQUE IRRIGADOR HORA 30.0000 60,000.00 2,000.00 9,100.00
MANO DE OBRA
MOB150 Cuadrilla AA Hr 3.0900 27,706.38 8,966.46 8,966.46
TRANSPORTES
TRA10 Transporte de material petreo M3-KM 0.0000 1,100.00 0.00 0.00
Valor Costo Directo 18,066.46
Valor Aproximación -0.46
Costo Unitario Total 18,066.00
U5142 17.4 Suministro, colocación y compactación de material granular, e = 0.20 m, en la corona de los diques de la PTAR. UN: M3
MATERIALES
MAT150 Material de relleno Granular M3 1.0000 24,000.00 24,000.00
MAT41 Agua LT 20.000 50.00 1,000.00
Desperdicio y compactación % 10.00 25,000.00 2,500.00 27,500.00
EQUIPOS
EQU01 Herramientas Menores GLOB 20.0000 10,000.00 500.00
EQU06 CARRO TANQUE IRRIGADOR HORA 50.0000 60,000.00 1,200.00
Compactador manual vibratorio - Tipo Canguro -
EQU10 HORA 3.0000 10,000.00 3,333.33 5,033.33
Apisonadores.
MANO DE OBRA
MOB150 Cuadrilla AA Hr 4.9400 27,706.38 5,608.58 5,608.58
TRANSPORTES
TRA10 Transporte de material petreo M3-KM 30.0000 1,100.00 33,000.00 33,000.00
Valor Costo Directo 71,141.91
ANALISIS DE PRECIOS UNITARIOS
ALCALDÍA MUNICIPAL DE CHIRIGUANÁ
Entidad
CONSTRUCCIÓN DE LOS SISTEMAS DE ALCANTARILLADO SANITARIO Y TRATAMIENTO DE LAS AGUAS RESIDUALES DEL
Proyecto
CORREGIMIENTO DE POPONTE MUNICIPIO DE CHIRIGUANA DEPARTAMENTO DEL CESAR
Código Descripción Unidad Rend./Cant. Vr. Unitario Vr. Parcial Vr. Rubro
Valor Aproximación 0.09
Costo Unitario Total 71,142.00
ANALISIS DE PRECIOS UNITARIOS
ALCALDÍA MUNICIPAL DE CHIRIGUANÁ
Entidad
CONSTRUCCIÓN DE LOS SISTEMAS DE ALCANTARILLADO SANITARIO Y TRATAMIENTO DE LAS AGUAS RESIDUALES DEL
Proyecto
CORREGIMIENTO DE POPONTE MUNICIPIO DE CHIRIGUANA DEPARTAMENTO DEL CESAR
Código Descripción Unidad Rend./Cant. Vr. Unitario Vr. Parcial Vr. Rubro
U5270 18.1 Construcción de pozo con altura menor de 1.80 m. Hprm. 1.65 m. UN: UN
MATERIALES
MAT1247 Tapa en ferroconcreto D= 0.60 m. UN 1.0000 225,000.00 225,000.00
MAT1248 Escalones 3/4", pintados con aticorrosivo UN 8.0000 15,000.00 120,000.00
CONCRETO ESTRUCTURAL f'c=28MPA (4.000 PSI),
U1048 M3 2.3000 546,192.00 1,256,241.60
impermeabilizado
U423 Acero de refuerzo PDR-60; f'y=420 Mpa KG 25.0000 5,592.00 139,800.00 1,741,041.60
EQUIPOS
EQU01 Herramientas Menores GLOB 0.4000 10,000.00 25,000.00
EQU25 Vibrador de concreto HORA 1.0000 9,000.00 9,000.00
MAT174 Formaleta metálica (para pozos de inspección) HORA 0.2000 12,500.00 62,500.00 96,500.00
MANO DE OBRA
MOB150 Cuadrilla AA Hr 0.0450 27,706.38 615,697.22 615,697.22
Valor Costo Directo 2,453,239.00
U5360 20.1 Localización, Replanteo, nivelación de tubería, incluye comision topografica permanente. UN: ML
MATERIALES
MAT27 PUNTILLA DE 1" - 3.1/2" LB 0.0300 4,500.00 135.00
MAT993 ESTACAS DE MADERA UN 0.1000 1,000.00 100.00 235.00
EQUIPOS
EQU01 Herramientas Menores GLOB 100.0000 10,000.00 100.00
EQU14 EQUIPO DE TOPOGRAFIA HORA 50.0000 18,750.00 375.00 475.00
MANO DE OBRA
MOB04 Cuadrilla topografica HORA 20.2600 33,546.75 1,655.81 1,655.81
Valor Costo Directo 2,365.81
Valor Aproximación 0.19
Costo Unitario Total 2,366.00
ANALISIS DE PRECIOS UNITARIOS
ALCALDÍA MUNICIPAL DE CHIRIGUANÁ
Entidad
CONSTRUCCIÓN DE LOS SISTEMAS DE ALCANTARILLADO SANITARIO Y TRATAMIENTO DE LAS AGUAS RESIDUALES DEL
Proyecto
CORREGIMIENTO DE POPONTE MUNICIPIO DE CHIRIGUANA DEPARTAMENTO DEL CESAR
Código Descripción Unidad Rend./Cant. Vr. Unitario Vr. Parcial Vr. Rubro
MANO DE OBRA
MOB150 Cuadrilla AA Hr 24.6600 27,706.38 1,123.54 1,123.54
Valor Costo Directo 14,080.68
Valor Aproximación 0.32
Costo Unitario Total 14,081.00
U528 20.7 Construcción de pozo con altura mayor de 1.80 m. Hprm. 2.35 m. UN: UN
MATERIALES
MAT1247 Tapa en ferroconcreto D= 0.60 m. UN 1.0000 225,000.00 225,000.00
MAT1248 Escalones 3/4", pintados con aticorrosivo UN 8.0000 15,000.00 120,000.00
CONCRETO ESTRUCTURAL f'c=28MPA (4.000 PSI),
U1048 M3 2.3000 546,192.00 1,256,241.60
impermeabilizado
U423 Acero de refuerzo PDR-60; f'y=420 Mpa KG 25.0000 5,592.00 139,800.00 1,741,041.60
EQUIPOS
EQU01 Herramientas Menores GLOB 0.4000 10,000.00 25,000.00
EQU25 Vibrador de concreto HORA 1.0000 9,000.00 9,000.00
MAT174 Formaleta metálica (para pozos de inspección) HORA 0.2000 12,500.00 62,500.00 96,500.00
MANO DE OBRA
MOB150 Cuadrilla AA Hr 0.0450 27,706.38 615,697.22 615,697.22
Valor Costo Directo 2,453,238.82
Valor Aproximación 0.18
Costo Unitario Total 2,453,239.00
ANALISIS DE PRECIOS UNITARIOS
ALCALDÍA MUNICIPAL DE CHIRIGUANÁ
Entidad
CONSTRUCCIÓN DE LOS SISTEMAS DE ALCANTARILLADO SANITARIO Y TRATAMIENTO DE LAS AGUAS RESIDUALES DEL
Proyecto
CORREGIMIENTO DE POPONTE MUNICIPIO DE CHIRIGUANA DEPARTAMENTO DEL CESAR
Código Descripción Unidad Rend./Cant. Vr. Unitario Vr. Parcial Vr. Rubro
U579 21.2 Concreto de f'c=2.500 PSI impermeabilizado, para solado e= 0.05 m. UN: M3
MATERIALES
MAT3010 PLASTOCRETE DM GAL 2.0000 12,500.00 25,000.00
U1089 CONCRETO ESTRUCTURAL f'c=14MPA (2.500PSI). M3 1.0000 404,864.00 404,864.00
Desperdicio Ponderado % 9.38 429,864.00 40,321.24 470,185.24
EQUIPOS
EQU01 Herramientas Menores GLOB 5.0000 10,000.00 2,000.00 2,000.00
MANO DE OBRA
MOB150 Cuadrilla AA Hr 0.2900 27,706.38 95,539.22 95,539.22
TRANSPORTES
TRA01 Transporte de material TF 1.0000 10,000.00 10,000.00 10,000.00
Valor Costo Directo 577,724.46
Valor Aproximación -0.46
Costo Unitario Total 577,724.00
U581 21.3 Concreto de f'c=3.000 PSI impermeabilizado, para losa y muros. UN: M3
MATERIALES
MAT1003 REPISA DE MADERA 4"x4" ML 6.0000 7,500.00 45,000.00
MAT173 FORMALETA PARA VIGAS UN 1.0000 150,000.00 150,000.00
MAT2585 SEPAROL (15KG) KG 1.0000 15,000.00 15,000.00
MAT27 PUNTILLA DE 1" - 3.1/2" LB 2.0000 4,500.00 9,000.00
MAT3010 PLASTOCRETE DM GAL 2.0000 12,500.00 25,000.00
U1048 CONCRETO ESTRUCTURAL f'c=21MPA (3.000 PSI). M3 1.0000 463,946.00 463,946.00
Desperdicio Ponderado % 3.68 707,946.00 26,052.41 733,998.41
EQUIPOS
EQU01 Herramientas Menores GLOB 2.0000 10,000.00 5,000.00
EQU03 ANDAMIO TUBULAR 1.50x1.50m DIA 0.2000 1,500.00 7,500.00
EQU19 PARAL TELESCOPICO SEC 0.1000 400.00 4,000.00
EQU24 VIBRADOR A GASOLINA SIN OPERADOR DIA 2.0000 45,000.00 22,500.00 39,000.00
MANO DE OBRA
MOB150 Cuadrilla AA Hr 0.1060 27,706.38 261,380.90 261,380.90
TRANSPORTES
TRA01 Transporte de material TF 2.0000 10,000.00 20,000.00 20,000.00
Valor Costo Directo 1,054,379.31
Valor Aproximación -0.31
Costo Unitario Total 1,054,379.00
Código Descripción Unidad Rend./Cant. Vr. Unitario Vr. Parcial Vr. Rubro
U588 22.3 Cerramiento en alambre pua Calb. 12.5-5 Hilos, Postes en concreto f'c=3.000PSI de 0.10 x 0.10 x 2.50 - cada 2.00 m. UN: ML
MATERIALES
MAT1272 ALAMBRE DE PUAS GALVANIZADO - CALIBRE 12.5 ML 5.0000 600.00 3,000.00
MAT2588 POSTE CERCCA 10x10cm - N 0.5000 43,500.00 21,750.00
U1048 CONCRETO ESTRUCTURAL f'c=21MPA (3.000 PSI). M3 0.0500 463,946.00 23,197.30
Desperdicio Ponderado % 5.00 47,947.30 2,397.37 50,344.67
EQUIPOS
EQU01 Herramientas Menores GLOB 20.0000 10,000.00 500.00 500.00
MANO DE OBRA
MOB150 Cuadrilla AA Hr 6.7500 27,706.38 4,104.65 4,104.65
TRANSPORTES
TRA01 Transporte de material TF 0.1000 10,000.00 1,000.00 1,000.00
Valor Costo Directo 55,949.32
Valor Aproximación -0.32
Costo Unitario Total 55,949.00
Código Descripción Unidad Rend./Cant. Vr. Unitario Vr. Parcial Vr. Rubro
U581 22.5 Concreto de f'c=3.000 PSI Impermeabilizado, para viga de cimentación. UN: M3
MATERIALES
MAT1003 REPISA DE MADERA 4"x4" ML 6.0000 7,500.00 45,000.00
MAT173 FORMALETA PARA VIGAS UN 1.0000 150,000.00 150,000.00
MAT2585 SEPAROL (15KG) KG 1.0000 15,000.00 15,000.00
MAT27 PUNTILLA DE 1" - 3.1/2" LB 2.0000 4,500.00 9,000.00
MAT3010 PLASTOCRETE DM GAL 2.0000 12,500.00 25,000.00
U1048 CONCRETO ESTRUCTURAL f'c=21MPA (3.000 PSI). M3 1.0000 463,946.00 463,946.00
Desperdicio Ponderado % 3.68 707,946.00 26,052.41 733,998.41
EQUIPOS
EQU01 Herramientas Menores GLOB 2.0000 10,000.00 5,000.00
EQU03 ANDAMIO TUBULAR 1.50x1.50m DIA 0.2000 1,500.00 7,500.00
EQU19 PARAL TELESCOPICO SEC 0.1000 400.00 4,000.00
EQU24 VIBRADOR A GASOLINA SIN OPERADOR DIA 2.0000 45,000.00 22,500.00 39,000.00
MANO DE OBRA
MOB150 Cuadrilla AA Hr 0.1060 27,706.38 261,380.90 261,380.90
TRANSPORTES
TRA01 Transporte de material TF 2.0000 10,000.00 20,000.00 20,000.00
Valor Costo Directo 1,054,379.31
Valor Aproximación -0.31
Costo Unitario Total 1,054,379.00
Código Descripción Unidad Rend./Cant. Vr. Unitario Vr. Parcial Vr. Rubro
MATERIALES
MAT1120 ESMALTE DE PINTUCO GL 0.1000 65,000.00 6,500.00
MAT1251 ANTICORROSIVO GAL 0.1000 45,000.00 4,500.00
MAT270 SOLDADURA WEST ARCO E:60-11 KG 0.1500 8,000.00 1,200.00
MAT38 THINNER ADITIVOS PARA PINTURAS GAL 0.1000 20,000.00 2,000.00
MAT908 TUBO GALVANIZADO TIPO CERRAMIENTO 1.5mm x 2" ML 3.0000 17,000.00 51,000.00 65,200.00
EQUIPOS
EQU01 Herramientas Menores GLOB 10.0000 10,000.00 1,000.00
EQU102 EQUIPO DE SOLDADURA HORA 4.0000 15,000.00 3,750.00
EQU104 PULIDORA CON DISCO DIAMANTADO HORA 2.5000 8,500.00 3,400.00
EQU117 COMPRESOR HORA 3.3333 10,000.00 3,000.03 11,150.03
MANO DE OBRA
MOB152 Cuadrilla DD Hr 2.0500 44,048.38 21,487.01 21,487.01
TRANSPORTES
TRA01 Transporte de material TF 0.2000 10,000.00 2,000.00 2,000.00
Valor Costo Directo 99,837.04
Valor Aproximación -0.04
Costo Unitario Total 99,837.00
ANALISIS DE PRECIOS UNITARIOS
ALCALDÍA MUNICIPAL DE CHIRIGUANÁ
Entidad
CONSTRUCCIÓN DE LOS SISTEMAS DE ALCANTARILLADO SANITARIO Y TRATAMIENTO DE LAS AGUAS RESIDUALES DEL
Proyecto
CORREGIMIENTO DE POPONTE MUNICIPIO DE CHIRIGUANA DEPARTAMENTO DEL CESAR
Código Descripción Unidad Rend./Cant. Vr. Unitario Vr. Parcial Vr. Rubro
U587 22.11 Panel en malla eslabonada calibre 12 2 1/4" X 2 1/4" de 2.5 m de Long. Para cerramiento frontal. UN: UN
MATERIALES
MAT1120 ESMALTE DE PINTUCO GL 0.2000 65,000.00 13,000.00
MAT1251 ANTICORROSIVO GAL 0.2000 45,000.00 9,000.00
MALLA ESLABONADA CAL. 12, HUECO 2.1/4x2.1/4" -
MAT1271 M2 5.0000 18,000.00 90,000.00
ALTURA H=2.5m
MAT2588 ANGULO DE 1-1/2"X1-1/2"X1/8" ML 40.0000 7,500.00 300,000.00
MAT270 SOLDADURA WEST ARCO E:60-11 KG 0.3000 8,000.00 2,400.00
MAT38 THINNER ADITIVOS PARA PINTURAS GAL 0.2000 20,000.00 4,000.00
Desperdicio Ponderado % 5.00 418,400.00 20,920.00 439,320.00
EQUIPOS
EQU01 Herramientas Menores GLOB 5.0000 10,000.00 2,000.00
EQU102 EQUIPO DE SOLDADURA HORA 4.0000 15,000.00 3,750.00
EQU104 PULIDORA CON DISCO DIAMANTADO HORA 3.3333 8,500.00 2,550.03
EQU115 DIFERENCIAL HORA 3.3333 10,000.00 3,000.03
EQU117 COMPRESOR HORA 3.3333 10,000.00 3,000.03 14,300.09
MANO DE OBRA
MOB152 Cuadrilla DD Hr 0.8200 44,048.38 53,717.53 53,717.53
TRANSPORTES
TRA01 Transporte de material TF 1.5000 10,000.00 15,000.00 15,000.00
Valor Costo Directo 522,337.62
Valor Aproximación 0.38
Costo Unitario Total 522,338.00
U589 22.12 Porton en tubo galvanizado y malla eslabonada de 4.00 x 3.00 m. UN: UN
MATERIALES
MAT1120 ESMALTE DE PINTUCO GL 1.5000 65,000.00 97,500.00
MAT1251 ANTICORROSIVO GAL 1.5000 45,000.00 67,500.00
MALLA ESLABONADA CAL. 12, HUECO 2.1/4x2.1/4" -
MAT1271 M2 12.0000 18,000.00 216,000.00
ALTURA H=2.5m
MAT270 SOLDADURA WEST ARCO E:60-11 KG 8.0000 8,000.00 64,000.00
MAT38 THINNER ADITIVOS PARA PINTURAS GAL 1.5000 20,000.00 30,000.00
MAT908 TUBO GALVANIZADO TIPO CERRAMIENTO 1.5mm x 2" ML 48.0000 17,000.00 816,000.00 1,291,000.00
EQUIPOS
EQU01 Herramientas Menores GLOB 0.5000 10,000.00 20,000.00
EQU102 EQUIPO DE SOLDADURA HORA 0.0750 15,000.00 200,000.00
EQU104 PULIDORA CON DISCO DIAMANTADO HORA 0.0650 8,500.00 130,769.23
EQU115 DIFERENCIAL HORA 0.0650 10,000.00 153,846.15
EQU117 COMPRESOR HORA 0.0650 10,000.00 153,846.15 658,461.53
MANO DE OBRA
MOB152 Cuadrilla DD Hr 0.0580 44,048.38 759,454.74 759,454.74
TRANSPORTES
TRA01 Transporte de material TF 4.0000 10,000.00 40,000.00 40,000.00
Valor Costo Directo 2,748,916.27
Valor Aproximación -0.27
Costo Unitario Total 2,748,916.00
ANALISIS DE PRECIOS UNITARIOS
ALCALDÍA MUNICIPAL DE CHIRIGUANÁ
Entidad
CONSTRUCCIÓN DE LOS SISTEMAS DE ALCANTARILLADO SANITARIO Y TRATAMIENTO DE LAS AGUAS RESIDUALES DEL
Proyecto
CORREGIMIENTO DE POPONTE MUNICIPIO DE CHIRIGUANA DEPARTAMENTO DEL CESAR
Código Descripción Unidad Rend./Cant. Vr. Unitario Vr. Parcial Vr. Rubro
U1142 22.13 Muro en Ladrillo a la vista - E=0.15m, Ladrillo 0.07x0.12x0.24m - Mortero de pega a la vista y ranurado. UN: M2
MATERIALES
MAT1273 LADRILLO A LA VISTA DOS CARAS - 7x12x24cm UN 50.0000 1,500.00 75,000.00
U1084 MORTERO 1:4 M3 0.0300 404,951.00 12,148.53
Desperdicio Ponderado % 5.00 87,148.53 4,357.43 91,505.96
EQUIPOS
EQU01 Herramientas Menores GLOB 5.0000 10,000.00 2,000.00
EQU03 ANDAMIO TUBULAR 1.50x1.50m DIA 0.4000 1,500.00 3,750.00
EQU104 PULIDORA CON DISCO DIAMANTADO HORA 8.5000 8,500.00 1,000.00
MAT3011 TABLONES DE MADERA DIA 10.0000 10,000.00 1,000.00 7,750.00
MANO DE OBRA
MOB150 Cuadrilla AA Hr 1.2600 27,706.38 21,989.19 21,989.19
TRANSPORTES
TRA01 Transporte de material TF 0.5000 10,000.00 5,000.00 5,000.00
Valor Costo Directo 126,245.15
Valor Aproximación -0.15
Costo Unitario Total 126,245.00
MANO DE OBRA
MOB150 Cuadrilla AA Hr 45.4800 27,706.38 609.20 609.20
TRANSPORTES
TRA01 Transporte de material M3 30.00 1,100.00 6,600.00 6,600.00
Valor Costo Directo 23,594.65
Valor Aproximación 0.35
Costo Unitario Total 23,595.00
ANALISIS DE PRECIOS UNITARIOS
ALCALDÍA MUNICIPAL DE CHIRIGUANÁ
Entidad
CONSTRUCCIÓN DE LOS SISTEMAS DE ALCANTARILLADO SANITARIO Y TRATAMIENTO DE LAS AGUAS RESIDUALES DEL
Proyecto
CORREGIMIENTO DE POPONTE MUNICIPIO DE CHIRIGUANA DEPARTAMENTO DEL CESAR
Código Descripción Unidad Rend./Cant. Vr. Unitario Vr. Parcial Vr. Rubro
25.1 Suministro de tuberia de PVC con sistema de unión mecanica, campana espigo con hidrosello, de pared interior lisa y exterior corrugada, de
U504
diametro 8" (200 mm). UN: ML
MATERIALES
MAT785 TUBERIA de P.V.C. SANITARIA x 200mm - 8" ML 1.0000 36,235.00 36,235.00
Desperdicio Ponderado % 5.00 36,235.00 1,811.75 38,046.75
TRANSPORTES
TRA01 Transporte de material TF 0.4312 10,000.00 4,312.00 4,312.00
Valor Costo Directo 42,358.75
Valor Aproximación 0.25
Costo Unitario Total 42,359.00
25.2 Suministro de tuberia de PVC con sistema de unión mecanica, campana espigo con hidrosello, de pared interior lisa y exterior corrugada, de
U506
diametro 10" (250 mm). UN: ML
MATERIALES
MAT783 TUBERIA de P.V.C. SANITARIA x 250mm - 10" ML 1.0000 52,923.00 52,923.00
Desperdicio Ponderado % 5.00 52,923.00 2,646.15 55,569.15
TRANSPORTES
TRA01 Transporte de material TF 0.6298 10,000.00 6,298.00 6,298.00
Valor Costo Directo 61,867.15
Valor Aproximación -0.15
Costo Unitario Total 61,867.00
25.3 Suministro de tuberia de PVC con sistema de unión mecanica, campana espigo con hidrosello, de pared interior lisa y exterior corrugada, de
U508
diametro 12" (315 mm). UN: ML
MATERIALES
MAT781 TUBERIA de P.V.C. SANITARIA x 315mm - 12" ML 1.0000 78,248.00 78,248.00
Desperdicio Ponderado % 5.00 78,248.00 3,912.40 82,160.40
TRANSPORTES
TRA01 Transporte de material TF 0.9312 10,000.00 9,312.00 9,312.00
Valor Costo Directo 91,472.40
Valor Aproximación -0.40
Costo Unitario Total 91,472.00
25.4 Suministro de tuberia de PVC con sistema de unión mecanica, campana espigo con hidrosello, de pared interior lisa y exterior corrugada, de
U510
diametro 16" (400 mm). UN: ML
MATERIALES
MAT777 TUBERIA de P.V.C. SANITARIA x 400mm - 16" ML 1.0000 137,138.00 137,138.00
Desperdicio Ponderado % 5.00 137,138.00 6,856.90 143,994.90
TRANSPORTES
TRA01 Transporte de material TF 1.6319 10,000.00 16,319.00 16,319.00
Valor Costo Directo 160,313.90
Valor Aproximación 0.10
Costo Unitario Total 160,314.00
25.5 Suministro de tuberia de PVC con sistema de unión mecanica, campana espigo con hidrosello, de pared interior lisa y exterior corrugada, de
U516
diametro 6" (160 mm). UN: ML
MATERIALES
MAT787 TUBERIA de P.V.C. SANITARIA x 160mm - 6" ML 1.0000 26,532.00 26,532.00
Desperdicio Ponderado % 5.00 26,532.00 1,326.60 27,858.60
TRANSPORTES
TRA01 Transporte de material TF 0.3157 10,000.00 3,157.00 3,157.00
Valor Costo Directo 31,015.60
Valor Aproximación 0.40
Costo Unitario Total 31,016.00
ANALISIS DE PRECIOS UNITARIOS
ALCALDÍA MUNICIPAL DE CHIRIGUANÁ
Entidad
CONSTRUCCIÓN DE LOS SISTEMAS DE ALCANTARILLADO SANITARIO Y TRATAMIENTO DE LAS AGUAS RESIDUALES DEL
Proyecto
CORREGIMIENTO DE POPONTE MUNICIPIO DE CHIRIGUANA DEPARTAMENTO DEL CESAR
Código Descripción Unidad Rend./Cant. Vr. Unitario Vr. Parcial Vr. Rubro
U518 25.6 Suministro Silla Yee de 8"x6" (200 x160 mm) UN: UN
MATERIALES
MAT805 Sillas Yee de 8" x 6" (200 mm x 160 mm) UN 1.0000 106,027.00 106,027.00
Desperdicio Ponderado % 0.00 106,027.00 0.00 106,027.00
TRANSPORTES
TRA01 Transporte de material TF 1.2617 10,000.00 12,617.00 12,617.00
Valor Costo Directo 118,644.00
Valor Aproximación 0.00
Costo Unitario Total 118,644.00
U523 25.7 Suministro Silla Yee de 10"x6" (250 x160 mm) UN: UN
MATERIALES
MAT807 Sillas Yee de 10" x 6" (250 mm x 160 mm) UN 1.0000 119,862.00 119,862.00
Desperdicio Ponderado % 0.00 119,862.00 0.00 119,862.00
TRANSPORTES
TRA01 Transporte de material TF 1.4264 10,000.00 14,264.00 14,264.00
Valor Costo Directo 134,126.00
Valor Aproximación 0.00
Costo Unitario Total 134,126.00
U526 25.8 Suministro Sillas Yee de 12" x 6" (315 mm x 160 mm) UN: UN
MATERIALES
MAT810 Sillas Yee de 12" x 6" (315 mm x 160 mm) UN 1.0000 180,227.00 180,227.00
Desperdicio Ponderado % 0.00 180,227.00 0.00 180,227.00
TRANSPORTES
TRA01 Transporte de material TF 2.1447 10,000.00 21,447.00 21,447.00
Valor Costo Directo 201,674.00
Valor Aproximación 0.00
Costo Unitario Total 201,674.00
25.9 Suministro de tuberia de PVC con sistema de unión mecanica, campana espigo con hidrosello, de pared interior lisa y exterior corrugada, de
U516
diametro 6" (160 mm). UN: ML
MATERIALES
MAT787 TUBERIA de P.V.C. SANITARIA x 160mm - 6" ML 1.0000 26,532.00 26,532.00
Desperdicio Ponderado % 5.00 26,532.00 1,326.60 27,858.60
TRANSPORTES
TRA01 Transporte de material TF 0.3157 10,000.00 3,157.00 3,157.00
Valor Costo Directo 31,015.60
Valor Aproximación 0.40
Costo Unitario Total 31,016.00
25.10 Suministro de tuberia de PVC con sistema de unión mecanica, campana espigo con hidrosello, de pared interior lisa y exterior corrugada, de
U510
diametro 16" (400 mm). UN: ML
MATERIALES
Código Descripción Unidad Rend./Cant. Vr. Unitario Vr. Parcial Vr. Rubro
#REF!
ITEM: TRANSICIÓN AEREA SUBTERRRANEA EN TUBO GALVANIZADO DE 1", CAPACETE, CABLE DE COBRE THHN 3 No. 4
MEDIDA: UND
A. MATERIALES UNIDAD CANTIDAD V/UNITARIO V/PARCIAL
1 TUBERIA GALVANIZADA DE 1-1/2" ML 6.00 $ 29,745.00 $ 178,470.00
2 ADAPTADOR GALVANIZADO DE 1-1/2" UND 1.00 $ 3,640.00 $ 3,640.00
3 UNION GALVANIZADA TIPO IMC DE 1-1/2" UND 1.00 $ 4,060.00 $ 4,060.00
4 CURVA GALVANIZASDA TIPO IMC DE 1-1/2" UND 1.00 $ 13,200.00 $ 13,200.00
5 CABLE COBRE THNN No. 4 ML 24.00 $ 8,680.00 $ 208,320.00
6 CINTA BANDIT DE 3/4" ML 6.00 $ 4,300.00 $ 25,800.00
7 HEBILLAS PARA CINTA BANDIT DE 3/4" UND 3.00 $ 1,450.00 $ 4,350.00
8 CAPACETE DE 1-1/2" UND 1.00 $ 5,670.00 $ 5,670.00
9 CONECTOR PONCHABLE CABLE 4 UND 4.00 $ 4,650.00 $ 18,600.00
SUBTOTAL MATERIALES $ 462,110.00
#REF!
ITEM: ACOMETIDA SUBTERRANEA EN TUBERIA PVC DE 1-1/2", EN CABLE DE COBRE THHN EN 3 No. 4 AWG
MEDIDA: ML
A. MATERIALES UNIDAD CANTIDAD V/UNITARIO V/PARCIAL
1 TUBERIA PVC CONDUIT DE 1-1/2" ML 1.00 $ 4,083.00 $ 4,083.00
2 ADAPTADOR TERMINAL PVC 1-1/2" UND 0.15 $ 2,650.00 $ 397.50
3 UNION PVC CONDUIT 1-1/2" UND 0.20 $ 1,450.00 $ 290.00
4 CURVA PVC CONDUIT DE 1-1/2" UND 0.10 $ 2,450.00 $ 245.00
5 CABLE COBRE THNN No. 4 ML 3.09 $ 8,680.00 $ 26,821.20
7 PEGANTE, CINTA, OTROS GLB 1.00 $ 450.00 $ 450.00
SUBTOTAL MATERIALES $ 32,286.70
#REF!
ITEM: ACOMETIDA SUBTERRANEA EN TUBERIA PVC DE 3/4", EN CABLE DE COBRE THHN EN 2 No. 10 + 1 No. 12
MEDIDA: ML
A. MATERIALES UNIDAD CANTIDAD V/UNITARIO V/PARCIAL
1 TUBERIA PVC CONDUIT DE 3/4" ML 1.00 $ 1,565.00 $ 1,565.00
2 ADAPTADOR TERMINAL PVC 3/4" UND 0.15 $ 302.00 $ 45.30
ANALISIS DE PRECIOS UNITARIOS ELÉCTRICOS
#REF!
ITEM: ACOMETIDA SUBTERRANEA EN TUBERIA PVC DE 1", EN CABLE DE COBRE THHN EN 2 No. 8 + 1 No. 10
MEDIDA: ML
A. MATERIALES UNIDAD CANTIDAD V/UNITARIO V/PARCIAL
1 TUBERIA PVC CONDUIT DE 1" ML 1.00 $ 2,195.00 $ 2,195.00
2 ADAPTADOR TERMINAL PVC 1" UND 0.15 $ 530.00 $ 79.50
3 UNION PVC CONDUIT 1" UND 0.20 $ 450.00 $ 90.00
4 CURVA PVC CONDUIT DE 1" UND 0.10 $ 910.00 $ 91.00
5 CABLE COBRE THNN No. 8 ML 2.06 $ 3,710.00 $ 7,642.60
6 CABLE COBRE THNN No. 10 ML 1.03 $ 2,310.00 $ 2,379.30
7 PEGANTE, CINTA, OTROS GLB 1.00 $ 450.00 $ 450.00
SUBTOTAL MATERIALES $ 12,927.40
#REF!
ITEM: TUBERIA PVC DE 3/4", DUCTO DE RESERVA
MEDIDA: ML
A. MATERIALES UNIDAD CANTIDAD V/UNITARIO V/PARCIAL
1 TUBERIA PVC CONDUIT DE 3/4" ML 1.00 $ 1,565.00 $ 1,565.00
2 ADAPTADOR TERMINAL PVC 3/4" UND 0.15 $ 302.00 $ 45.30
3 UNION PVC CONDUIT 3/4" UND 0.20 $ 350.00 $ 70.00
4 CURVA PVC CONDUIT DE 3/4" UND 0.10 $ 530.00 $ 53.00
5 PEGANTE, CINTA, OTROS GLB 1.00 $ 450.00 $ 450.00
6
SUBTOTAL MATERIALES $ 2,183.30
#REF!
ITEM: TUBERIA PVC DE 1", DUCTO DE RESERVA
MEDIDA: ML
A. MATERIALES UNIDAD CANTIDAD V/UNITARIO V/PARCIAL
1 TUBERIA PVC CONDUIT DE 1" ML 1.00 $ 2,195.00 $ 2,195.00
2 ADAPTADOR TERMINAL PVC 1" UND 0.15 $ 530.00 $ 79.50
3 UNION PVC CONDUIT 1" UND 0.20 $ 450.00 $ 90.00
4 CURVA PVC CONDUIT DE 1" UND 0.10 $ 910.00 $ 91.00
5 PEGANTE, CINTA, OTROS GLB 1.00 $ 450.00 $ 450.00
6
7
SUBTOTAL MATERIALES $ 2,905.50
#REF!
ITEM: ACOMETIDA AEREA EN CABLE TRENZADO TRIPLEX No. 4
MEDIDA: ML
A. MATERIALES UNIDAD CANTIDAD V/UNITARIO V/PARCIAL
1 CABLE TRENZADO TRIPLEX AAAC No. 4 ML 1.00 $ 7,140.00 $ 7,140.00
#REF!
ITEM: LAMPARA CERRADA DE ALUMBRADO TIPO LED DE 60W- ORION DE SYLVANIA DE 6000 LUMENS 198/242V, INCLUYE BASE Y FOTOCELDA, BRAZO
CON ABRAZADERAS DE 1,5M X 1-1/2" , CABLEADA CON CABLE No. 12.
MEDIDA: UND
A. MATERIALES UNIDAD CANTIDAD V/UNITARIO V/PARCIAL
LAMPARA CERRADA DE ALUMBRADO TIPO ORION DE SYLVANIA
1 UND 1.00 $ 599,277.00 $ 599,277.00
60W TIPO LED
2 BRAZO CON ABRAZADERAS DE 1.5MX1-1/2" UND 1.00 $ 48,600.00 $ 48,600.00
3 BASE Y FOTOCELDA DE 1000W UND 1.00 $ 26,400.00 $ 26,400.00
4 CABLE DE COBRE THNN No. 12 ML 6.00 $ 1,750.00 $ 10,500.00
5 CONECTOR DE RED TRENZADA 2-12 UND 2.00 $ 13,600.00 $ 27,200.00
6 ACCESORIOS MENORES DE MONTAJE GLB 1.00 $ 300.00 $ 300.00
SUBTOTAL MATERIALES $ 712,277.00
#REF!
ITEM: POSTE DE CONCRETO DE 12 MTS X 750 KGR
MEDIDA: UND
A. MATERIALES UNIDAD CANTIDAD V/UNITARIO V/PARCIAL
1 POSTE DE CONCRETO DE 12 MTS X 750 KGR UND 1.00 $ 870,500.00 $ 870,500.00
SUBTOTAL MATERIALES $ 870,500.00
#REF!
ITEM: POSTE DE CONCRETO DE 10 MTS X 510 KGR
MEDIDA: UND
A. MATERIALES UNIDAD CANTIDAD V/UNITARIO V/PARCIAL
1 POSTE DE CONCRETO DE 10 MTS X 510 KGR UND 1.00 $ 596,500.00 $ 596,500.00
SUBTOTAL MATERIALES $ 596,500.00
#REF!
ITEM: ESTRUCTURA DE M.T. TIPO ANCLAJE EN ANGULO DE 90° BIFASICA CON CRUCETA METALICA DE 1,4M
MEDIDA: UND
A. MATERIALES UNIDAD CANTIDAD V/UNITARIO V/PARCIAL
1 CRUCETA METALICA DE 1,4 M AUTOSOPORTADA UND 4.00 $ 146,500.00 $ 586,000.00
2 ESPARRAGO DE 5/8X12" UND 5.00 $ 8,500.00 $ 42,500.00
3 PERNO DE 5/8X12" UND 1.00 $ 3,500.00 $ 3,500.00
4 ABRAZADERA DOBLE DE 7-8" UND 2.00 $ 21,350.00 $ 42,700.00
5 AISLADOR SINTETICO DE 15 KV UND 4.00 $ 45,000.00 $ 180,000.00
6 TUERCA DE OJO ALARGADO DE 5/8" UND 4.00 $ 8,500.00 $ 34,000.00
7 GRAPA TIPO PISTOLA DE 2 UES UND 4.00 $ 21,450.00 $ 85,800.00
8 AISLADOR DE PIN DE 15 KV UND 1.00 $ 54,350.00 $ 54,350.00
9 PIN PARA CRUCETA METALICA UND 1.00 $ 8,650.00 $ 8,650.00
10 AMARRA PREFORMADA PARA AISLADOR DE PASO UND 1.00 $ 12,350.00 $ 12,350.00
11 ACCESORIOS MENORES GLB 1.00 $ 4,500.00 $ 4,500.00
SUBTOTAL MATERIALES $ 1,054,350.00
#REF!
ITEM: ESTRUCTURA DE M.T. TIPO FIN DE LINEA BIFASICA CON CRUCETA METALICA DE 1,4M
MEDIDA: UND
A. MATERIALES UNIDAD CANTIDAD V/UNITARIO V/PARCIAL
1 CRUCETA METALICA DE 1,4 M AUTOSOPORTADA UND 2.00 $ 146,500.00 $ 293,000.00
2 ESPARRAGO DE 5/8X12" UND 3.00 $ 8,500.00 $ 25,500.00
3 PERNO DE 5/8X12" UND 1.00 $ 3,500.00 $ 3,500.00
4 AISLADOR SINTETICO DE 15 KV UND 2.00 $ 45,000.00 $ 90,000.00
5 TUERCA DE OJO ALARGADO DE 5/8" UND 2.00 $ 8,500.00 $ 17,000.00
6 GRAPA TIPO PISTOLA DE 2 UES UND 2.00 $ 21,450.00 $ 42,900.00
7 ACCESORIOS MENORES GLB 1.00 $ 4,500.00 $ 4,500.00
SUBTOTAL MATERIALES $ 476,400.00
#REF!
ITEM: ESTRUCTURA DE M.T. TIPO ALINEACION BIFASICA CON CRUCETA METALICA DE 1,4M
MEDIDA: UND
A. MATERIALES UNIDAD CANTIDAD V/UNITARIO V/PARCIAL
1 CRUCETA METALICA DE 1,4 M AUTOSOPORTADA UND 1.00 $ 146,500.00 $ 146,500.00
2 PERNO DE 5/8X12" UND 2.00 $ 3,500.00 $ 7,000.00
ANALISIS DE PRECIOS UNITARIOS ELÉCTRICOS
#REF!
ITEM: ESTRUCTURA DE M.T. TIPO ALINEACION BIFASICA EN ANGULO CON CRUCETA METALICA DE 1,4M
MEDIDA: UND
A. MATERIALES UNIDAD CANTIDAD V/UNITARIO V/PARCIAL
1 CRUCETA METALICA DE 2,4 M AUTOSOPORTADA UND 2.00 $ 186,500.00 $ 373,000.00
2 ESPARRAGO DE 5/8X12" UND 3.00 $ 8,500.00 $ 25,500.00
3 PERNO DE 5/8X12" UND 1.00 $ 3,500.00 $ 3,500.00
4 AISLADOR LINE POST DE 15 KV UND 4.00 $ 54,350.00 $ 217,400.00
5 PIN PARA CRUCETA METALICA UND 4.00 $ 8,650.00 $ 34,600.00
6 AMARRA PREFORMADA PARA AISLADOR DE ANGULO UND 2.00 $ 16,450.00 $ 32,900.00
7 ACCESORIOS MENORES GLB 1.00 $ 4,500.00 $ 4,500.00
SUBTOTAL MATERIALES $ 691,400.00
#REF!
ITEM: TRANSFORMADOR MONOFASICO DE 15 KVA; 13200/240/120V
MEDIDA: UND
A. MATERIALES UNIDAD CANTIDAD V/UNITARIO V/PARCIAL
1 TRANSFORMADOR MONOFASICO DE 15 KVA -13200/240/120 VOLTIO UND 1.00 $ 2,730,630.00 $ 2,730,630.00
2 COLLARIN PARA TRANSFORMADOR DE 15 CMS UND 2.00 $ 28,500.00 $ 57,000.00
SUBTOTAL MATERIALES $ 2,787,630.00
B. TRANSPORTES UNIDAD CANTIDAD V/UNITARIO V/PARCIAL
1 TRANSPORTE DE MATERIALES GLB 10% $ 2,787,630.00 $ 278,763.00
SUBTOTAL TRANSPORTE $ 278,763.00
#REF!
ITEM: PROTECCIONES DE TRANSFORMADOR MONOFASICO
MEDIDA: UND
A. MATERIALES UNIDAD CANTIDAD V/UNITARIO V/PARCIAL
1 CRUCETA METALICA DE 2,4 M AUTOSOPORTADA UND 1.00 $ 186,500.00 $ 186,500.00
2 CABLE DE COBRE DESNUDO O FORRADO No. 2 ML 30.00 $ 11,750.00 $ 352,500.00
3 PARARRAYOS SINTETICO DE 12KV-10KAMP. UND 2.00 $ 134,500.00 $ 269,000.00
4 PERNO DE 5/8X12" UND 2.00 $ 3,500.00 $ 7,000.00
5 CORTACIRCUITOS DE 100 AMP-15KV TIPO COSTA UND 2.00 $ 161,350.00 $ 322,700.00
6 FUSIBLE DE SOGA DE 2 AMP. UND 3.00 $ 6,500.00 $ 19,500.00
7 TUBO GALVANIZADO DE 1/2"X3M UND 1.00 $ 31,500.00 $ 31,500.00
8 CONECTOR CON ESTRIBO DE COBRE UND 2.00 $ 35,000.00 $ 70,000.00
9 CONECTOR AMOVIBLE DE COBRE UND 2.00 $ 23,500.00 $ 47,000.00
10 CINTA BANDIT DE 3/4" ML 6.00 $ 3,500.00 $ 21,000.00
11 HEBILLAS PARA CINTA BANDIT DE 3/4" UND 3.00 $ 1,200.00 $ 3,600.00
12 ABRAZADERA DE UNA SALIDA DE 6-8" UND 2.00 $ 18,500.00 $ 37,000.00
13 VARILLA DE COBRE SOLIDO CON CONECTOR UND 1.00 $ 125,600.00 $ 125,600.00
SUBTOTAL MATERIALES $ 1,492,900.00
#REF!
ITEM: RED DE MEDIA TENSION BIFASICA EN CABLE ACSR 1/0
MEDIDA: ML
A. MATERIALES UNIDAD CANTIDAD V/UNITARIO V/PARCIAL
1 CABLE DE ALUMINIO TIPO ACSR No. 1/0 ML 3.10 $ 2,850.00 $ 8,835.00
#REF!
ITEM: TEMPLETE DE MEDIA TENSION DIRECTO A TIERRA
MEDIDA: UND
A. MATERIALES UNIDAD CANTIDAD V/UNITARIO V/PARCIAL
1 AISLADOR DE PORCELANA TIPO TENSOR DE 4-1/2" UND 1.00 $ 18,000.00 $ 18,000.00
2 GRAPAS PRENSAHILO DE 1 1/2 X 1/4" X 6" 3 PERNOS UND 4.00 $ 12,500.00 $ 50,000.00
3 GUARDACABO EN ACERO GALVANIZADO PARA CABLE DE 1/2" UND 1.00 $ 2,500.00 $ 2,500.00
4 ARANDELA CUADRADA DE 4 X 4 X 5/8" X 1/8" PARA ANCLAJE UND 1.00 $ 4,000.00 $ 4,000.00
5 VARILLA DE ANCLAJE DE 5/8" X 1,8 MTS UND 1.00 $ 30,000.00 $ 30,000.00
6 VIGUETA DE CONCRETO PARA ANCLAJE DE 24X15X18,5 CMS UND 1.00 $ 12,500.00 $ 12,500.00
7 CABLE DE ACERO PARA RETENIDA EXTRA ALTA RESISTENCIA DE 1/4" ML 12.00 $ 2,350.00 $ 28,200.00
8 ALAMBRE GALVANIZADO No. 10 KG 2.00 $ 3,620.00 $ 7,240.00
9 PLETINA DE SUJECION UND 1.00 $ 45,000.00 $ 45,000.00
10 PERNO DE 5/8X10" UND 2.00 $ 3,500.00 $ 7,000.00
SUBTOTAL MATERIALES $ 204,440.00
#REF!
ITEM: SISTEMA DE PUESTA A TIERRA PLANTA DE TRATAMIENTO
MEDIDA: UND
A. MATERIALES UNIDAD CANTIDAD V/UNITARIO V/PARCIAL
1 VARILLA DE COBRE SOLIDO DE 5/8"X2.4M UND 3.00 $ 125,600.00 $ 376,800.00
2 CABLE DE COBRE DESNUDO No. 1/0 ML 18.00 $ 18,500.00 $ 333,000.00
3 HIDROSOLTA UND 4.00 $ 95,000.00 $ 380,000.00
4 SOLDADURA CADWELD DE 90 GRAMOS UND 4.00 $ 35,000.00 $ 140,000.00
5 PLATINA DE CORE DE 5/8X1/4"X60 CMS UND 1.00 $ 380,000.00 $ 380,000.00
6 AISLADORES DE BARRAJE Y TRORNILLOS UND 2.00 $ 6,500.00 $ 13,000.00
7 ELEMENTOS DE SUJECION Y MONTAJE GL 1.00 $ 35,003.00 $ 35,003.00
SUBTOTAL MATERIALES $ 1,657,803.00
#REF!
ITEM: PUESTA A TIERRA DE ESTRUCTURAS METALICAS
MEDIDA: UND
A. MATERIALES UNIDAD CANTIDAD V/UNITARIO V/PARCIAL
1 VARILLA DE COBRE SOLIDO DE 5/8"X2.4M UND 1.00 $ 125,600.00 $ 125,600.00
2 CABLE DE COBRE DESNUDO No. 2 ML 12.00 $ 10,750.00 $ 129,000.00
3 CONECTOR DE COMPRESION PARA VARILA DE 5/8" UND 1.00 $ 8,750.00 $ 8,750.00
4
5
SUBTOTAL MATERIALES $ 263,350.00
#REF!
ITEM: REGISTRO DE BAJA TENSION DE 80X80X60 CMS
MEDIDA: UND
A. MATERIALES UNIDAD CANTIDAD V/UNITARIO V/PARCIAL
1 CONCRETO DE 2500 PSI M3 0.19 $ 402,924.00 $ 77,361.41
2 HIERRO KGR 18.00 $ 5,937.00 $ 106,866.00
SUBTOTAL MATERIALES $ 184,227.41
#REF!
ITEM: REGISTRO DE BAJA TENSION DE 30X30X60 CMS
MEDIDA: UND
A. MATERIALES UNIDAD CANTIDAD V/UNITARIO V/PARCIAL
1 CONCRETO DE 2500 PSI M3 0.14 $ 402,924.00 $ 58,021.06
2 HIERRO KGR 12.00 $ 5,937.00 $ 71,244.00
SUBTOTAL MATERIALES $ 129,265.06
#REF!
ITEM: SALIDA Y LAMPARA FLUORESCENTE
MEDIDA: UND
A. MATERIALES UNIDAD CANTIDAD V/UNITARIO V/PARCIAL
1 TUBERIA PVC CONDUIT DE 1/2" ML 6.00 $ 1,186.00 $ 7,116.00
2 ADAPTADOR TERMINAL PVC 1/2" UND 4.00 $ 227.00 $ 908.00
3 UNION PVC CONDUIT 1/2" UND 2.00 $ 135.00 $ 270.00
4 CURVA PVC CONDUIT DE 1/2" UND 1.00 $ 390.00 $ 390.00
5 CABLE DE COBRE THW No. 12 ML 18.00 $ 1,460.00 $ 26,280.00
6 LAMPARA FLUORESCENTE DE 2X32W CON BALASTO ELECTRONICO UND 1.00 $ 78,500.00 $ 78,500.00
7 INTERRUPTOR SENCILLO UND 0.50 $ 5,250.00 $ 2,625.00
8 CAJA OCTAGONAL GALVANIZADA UND 1.00 $ 1,200.00 $ 1,200.00
9 CAJA RECTANGULAR 2X4" GALVAN. UND 1.00 $ 1,000.00 $ 1,000.00
10 PEGANTE, CINTA, OTROS GLB 1.00 $ 500.00 $ 500.00
SUBTOTAL MATERIALES $ 118,789.00
#REF!
ITEM: SALIDA PARA TOMA MONOFASICA DOBLE DE 120 VOLTIOS - 15 AMPERIOS
MEDIDA: UND
A. MATERIALES UNIDAD CANTIDAD V/UNITARIO V/PARCIAL
1 TUBERIA PVC CONDUIT DE 1/2" ML 6.00 $ 1,186.00 $ 7,116.00
2 ADAPTADOR TERMINAL PVC 1/2" UND 2.00 $ 227.00 $ 454.00
3 UNION PVC CONDUIT 1/2" UND 1.00 $ 135.00 $ 135.00
4 CURVA PVC CONDUIT DE 1/2" UND 2.00 $ 390.00 $ 780.00
5 CABLE DE COBRE THW No. 12 ML 19.00 $ 1,460.00 $ 27,740.00
6 TOMA DOBLE MONOFASICA CON POLO A TIERRA UND 1.00 $ 4,850.00 $ 4,850.00
7 CAJA RECTANGULAR 2X4" GALVAN. UND 1.00 $ 1,500.00 $ 1,500.00
8 PEGANTE, CINTA, OTROS GLB 1.00 $ 500.00 $ 500.00
SUBTOTAL MATERIALES $ 43,075.00
#REF!
ITEM: TABLERO BIFASICO DE 16 CIRCUITOS CON ESPACIO PARA TOTALIZADOR (INCLUYE TEMPORIZADORES)
MEDIDA: UND
A. MATERIALES UNIDAD CANTIDAD V/UNITARIO V/PARCIAL
1 TABLERO BIFASICO DE 16 CIRCUITOS CON ESPACIO PARA TOTALIZADOR
2 CON BARRAJE DE NEUTRO Y TIERRA UND 1.00 $ 326,400.00 $ 326,400.00
3 BREAKERS ENCHUFABLE 1X20 AMP. UND 2.00 $ 9,850.00 $ 19,700.00
4 BREAKERS ENCHUFABLE 2X20 AMP. UND 7.00 $ 26,000.00 $ 182,000.00
5 BREAKER INDUSTRIAL GRADUABLE DE 56 A 80 AMP. 25 KAMPERIOS UND 1.00 $ 228,760.00 $ 228,760.00
6 ACCESORIOS MENORES UND 1.00 $ 15,600.00 $ 15,600.00
7 TEMPORIZADORES UND 4.00 $ 145,000.00 $ 580,000.00
SUBTOTAL MATERIALES $ 1,352,460.00
1 TRAMITES ANTE ELECTRICARIBE PARA ENERGIZACION, REVISION DE GLOB 1.00 $ 4,320,000.00 $ 4,320,000.00
SUBTOTAL MATERIALES $ 4,320,000.00
1. PRELIMINARES $ 15,920,814.00
Localización, Replanteo, nivelación de tubería, incluye comision topografica permanente.
1.1 ML $ 6,729.00 $ 2,366.00 $ 15,920,814.00
Relleno con material seleccionado de cantera, compactado al 95% del proctor modificado: incluye la
5.2 explotación, cargue y transporte del material, herramientas menores, equipos de compactación y mano de M3 $ 5,676.00 $ 71,192.00 $ 404,085,792.00
obra.
Retiro de material sobrante de la excavación y escombros y limpieza general de obra, incluye: cargue,
5.3 M3 $ 4,916.00 $ 21,932.00 $ 107,817,712.00
transporte, herramientas menores y mano de obra.
17.3 Conformacion de dique perimetral con material de excavación M3 $ 3,036.00 $ 18,066.00 $ 54,848,376.00
Suministro, colocación y compactación de material granular, e = 0.20 m, en la corona de los diques de la
17.4 M3 $ 180.00 $ 71,142.00 $ 12,805,560.00
PTAR.
PROPUESTA ECONOMICA
Entidad: ALCALDÍA MUNICIPAL DE CHIRIGUANÁ
22.13 Muro en Ladrillo a la vista - E=0.15m, Ladrillo 0.07x0.12x0.24m - Mortero de pega a la vista y ranurado. M2 $ 12.50 $ 126,245.00 $ 1,578,062.50
PROPUESTA ECONOMICA
Entidad: ALCALDÍA MUNICIPAL DE CHIRIGUANÁ
Suministro de tuberia de PVC con sistema de unión mecanica, campana espigo con hidrosello, de pared
25.1 ML $ 3,958.00 $ 42,359.00 $ 167,656,922.00
interior lisa y exterior corrugada, de diametro 8" (200mm).
Suministro de tuberia de PVC con sistema de unión mecanica, campana espigo con hidrosello, de pared
25.2 ML $ 1,053.00 $ 61,867.00 $ 65,145,951.00
interior lisa y exterior corrugada, de diametro 10" (250mm).
Suministro de tuberia de PVC con sistema de unión mecanica, campana espigo con hidrosello, de pared
25.3 ML $ 402.00 $ 91,472.00 $ 36,771,744.00
interior lisa y exterior corrugada, de diametro 12" (315mm).
Suministro de tuberia de PVC con sistema de unión mecanica, campana espigo con hidrosello, de pared
25.4 ML $ 1,316.00 $ 160,314.00 $ 210,973,224.00
interior lisa y exterior corrugada, de diametro 16" (400mm).
Suministro de tuberia de PVC con sistema de unión mecanica, campana espigo con hidrosello, de pared
25.5 ML $ 2,952.00 $ 31,016.00 $ 91,559,232.00
interior lisa y exterior corrugada, de diametro 6" (160mm).
Suministro Silla Yee de 8"x6" (200 x160 mm)
25.6 UN $ 392.00 $ 118,644.00 $ 46,508,448.00
Suministro Silla Yee de 10"x6" (250 x160 mm)
25.7 UN $ 33.00 $ 134,126.00 $ 4,426,158.00
Suministro Sillas Yee de 12" x 6" (315 mm x 160 mm)
25.8 UN $ 47.00 $ 201,674.00 $ 9,478,678.00
SISTEMA DE TRATAMIENTO DE AGUAS RESIDUALES $ 179,263,908.98
Suministro de tuberia de PVC con sistema de unión mecanica, campana espigo con hidrosello, de pared
25.9 ML $ 88.06 $ 31,016.00 $ 2,731,268.96
interior lisa y exterior corrugada, de diametro 6" (160 mm).
Suministro de tuberia de PVC con sistema de unión mecanica, campana espigo con hidrosello, de pared
25.10 ML $ 32.93 $ 160,314.00 $ 5,279,140.02
interior lisa y exterior corrugada, de diametro 16" (400 mm).
25.11 Suministro Geomembrana 40 ml M2 $ 5,335.00 $ 22,200.00 $ 118,437,000.00
25.12 Suministro Geotextil NT 2000 M2 $ 5,335.00 $ 9,900.00 $ 52,816,500.00
PROPONENTE
Entidad: ALCALDÍA MUNICIPAL DE CHIRIGUANÁ
CONSTRUCCIÓN DE LOS SISTEMAS DE ALCANTARILLADO SANITARIO Y TRATAMIENTO DE LAS AGUAS RESIDUALES DEL CORREGIMIENTO DE POPONTE MUNICIPIO
Proyecto:
DE CHIRIGUANA DEPARTAMENTO DEL CESAR
1. PRELIMINARES $ 15,920,814.00
ESTRUCTURAS DE LA LAGUNA: CONCRETOS Y MORTEROS, ACEROS Y ESTRUCTURAS METALICAS, JUNTAS, CINTA PVC, INSTALACION DE
16. TUBERIA DE ALCANTARILLADO SANITARIO, TUBERIAS INTERNAS, RELLENOS Y DIQUES, POZOS DE INSPECCION, INSTALACION $ 247,746,122.31
GEOMEMBRANA, CABEZAL DE ENTREGA
COSTO
DESCRIPCIÓN UNIDAD CANT. TIEMPO VALOR PARCIAL
MENSUAL
OTROS COSTOS DIRECTOS
Alquiler de equipo de topografia Mes 500,000.00 0.50 8.00 2,000,000.00
COSTO
DESCRIPCIÓN UNIDAD CANT. TIEMPO VALOR PARCIAL
MENSUAL
COSTOS INDIRECTOS
Arriendo de Oficina MES 500,000.00 1.00 8.00 4,000,000.00
Comunicaciones (incluye celulares, fax, servico de
MES 400,000.00 1.00 8.00 3,200,000.00
internet, etc.)
PRESTACIONES BASE
Cesantias E 10.00% 1,041,894 10.98%
Intereses Cesantias 12.00% 125,027 1.32%
Vacaciones 15 Dias A 50.00% 390,621 4.11%
Primas 30 Dias C 100.00% 869,453 9.20%
OTROS COSTOS
Botas y Overol 82,500 3.00 247,500 4.09%
Seguro Colectivo D 0.50% 47,526 0.50%
SEGURIDAD SOCIAL
Pensiones D 12.00% 1,140,613 12.00%
Medicina Familiar D 8.50% 807,934 8.50%
Riesgos Profesionales D 5.60% 532,286 5.60%
APORTES SENA
Aporte Ordinario D 2.00% 190,102 2.00%
F.I.C Nota 4 18.00% 190,536 1.80%
OTROS APORTES
I.C.B.F D 3.00% 285,153 3.00%
Subsidio Familiar D 4.00% 380,204 4.00%
NOTAS:
1.- Subsidio de transporte solo se paga hasta sueldos de 2 salarios minimos mensules legales vigentes.
2.- Subsidio de transporte anual = Subsidio mensual / 30 x (365 dias-18 fiestas - 3 permisos- 15 dias vacaciones).
3.- Porcentajes solo son validos para actividades de construccion. Para otros empleados se debe utilizar 30 dias de cesantia y 2.2%
(promedio para empresas de bajo riesgo).
4.- Un salario minimo por cada 40 trabajadores. El valor se obtiene asi: (Salario minimo x 12 / 40) / Salario annual estudiado.
2- CALCULO DE SOBRECOSTO POR HORAS EFECTIVAS TRABAJADAS-OBREROS CON UN
SALARIO MINIMO TRABAJADO
A- Anual con Subsidio de Transporte 16,812,493
B- Horas Calendario Anuales 365 x 8 Hhr 2,920
C- Horas Laborales Anuales (52 Sem x 48 Hr)+8Hr 2,504
D- Horas Habiles Anuales 2920 Hr-((52 Dom + 18 2344
Fiestas + 3 Permisos) x 8
E- Valor Hora Calendario Hr) A/B 5,758 100.00%
F- Valor Hora Laboral A/C 6,714 116.61%
G- Valor Hora Efectiva A/D 7,173 124.57%
NOTAS:
Los factores de sobrecostos se utilizan para valorizar el tiempo efectivo que un obrero dedica a su labor y refleja el costo del tiempo
durante el cual no esta trabajando pero si esta devengando.
Si se toma como base la hora calendario, se incrementa 24.57% para obtener la hora efectiva.
Si se toma como base la hora laboral, se incrementa 6.83% para obtener la hora efectiva.
CALCULO DE CUADRILLAS
CUADRILLA (Topografia)
Jornal Ayudante 1.2 Minimos 43,150
Valor Real del Jornal 214.77% 92,674
Valor Total Hr Ayudante 11,584
NOTAS:
Jornal = sueldo mensual x 12 meses / 365 dias.
LISTA DE PRECIOS ELÉCTRICOS
ITEM DESCRIPCION UNIDAD VALOR
1 TUBERIA GALVANIZADA DE 2" ML $ 39,450.0
2 ADAPTADOR TERMINAL PVC 2" UND $ 3,360.0
3 UNION PVC CONDUIT 2" UND $ 1,450.0
4 CURVA PVC CONDUIT DE 2" UND $ 4,164.0
5 CABLE COBRE THNN No. 1/0 ML $ 20,735.0
6 CINTA BANDIT DE 3/4" ML $ 4,300.0
7 HEBILLAS PARA CINTA BANDIT DE 3/4" UND $ 1,450.0
8 CAPACETE DE 2" UND $ 7,350.0
9 CONECTOR PONCHABLE CABLE 1/0 UND $ 8,650.0
10 TUBERIA PVC CONDUIT DE 2" ML $ 6,750.0
11 ADAPTADOR TERMINAL PVC 2" UND $ 3,360.0
12 UNION PVC CONDUIT 2" UND $ 1,450.0
13 CURVA PVC CONDUIT DE 2" UND $ 4,164.0
14 CABLE COBRE THNN No. 1/0 ML $ 20,735.0
15 PEGANTE, CINTA, OTROS GLB $ 450.0
16 TUBERIA PVC CONDUIT DE 3/4" ML $ 1,565.0
17 ADAPTADOR TERMINAL PVC 3/4" UND $ 302.0
18 UNION PVC CONDUIT 3/4" UND $ 350.0
19 CURVA PVC CONDUIT DE 3/4" UND $ 530.0
20 CABLE COBRE THNN No. 10 ML $ 2,145.0
21 CABLE COBRE THNN No. 12 ML $ 1,502.0
22 PEGANTE, CINTA, OTROS GLB $ 450.0
23 TUBERIA PVC CONDUIT DE 1" ML $ 2,195.0
24 ADAPTADOR TERMINAL PVC 1" UND $ 530.0
25 UNION PVC CONDUIT 1" UND $ 450.0
26 CURVA PVC CONDUIT DE 1" UND $ 910.0
27 CABLE COBRE THNN No. 8 ML $ 3,220.0
28 CABLE COBRE THNN No. 10 ML $ 2,145.0
29 PEGANTE, CINTA, OTROS GLB $ 450.0
30 TUBERIA PVC CONDUIT DE 1" ML $ 2,195.0
31 ADAPTADOR TERMINAL PVC 1" UND $ 530.0
32 UNION PVC CONDUIT 1" UND $ 450.0
33 CURVA PVC CONDUIT DE 1" UND $ 910.0
34 CABLE COBRE THNN No. 6 ML $ 4,935.0
35 CABLE COBRE THNN No. 10 ML $ 2,145.0
36 PEGANTE, CINTA, OTROS GLB $ 450.0
37 TUBERIA PVC CONDUIT DE 1" ML $ 2,195.0
38 ADAPTADOR TERMINAL PVC 1" UND $ 530.0
39 UNION PVC CONDUIT 1" UND $ 450.0
40 CURVA PVC CONDUIT DE 1" UND $ 910.0
41 CABLE COBRE THNN No. 6 ML $ 4,935.0
42 CABLE COBRE THNN No. 10 ML $ 2,145.0
43 PEGANTE, CINTA, OTROS GLB $ 450.0
44 TUBERIA PVC CONDUIT DE 3/4" ML $ 1,565.0
45 ADAPTADOR TERMINAL PVC 3/4" UND $ 302.0
46 UNION PVC CONDUIT 3/4" UND $ 350.0
47 CURVA PVC CONDUIT DE 3/4" UND $ 530.0
48 PEGANTE, CINTA, OTROS GLB $ 450.0
49 TUBERIA PVC CONDUIT DE 1" ML $ 2,195.0
50 ADAPTADOR TERMINAL PVC 1" UND $ 530.0
51 UNION PVC CONDUIT 1" UND $ 450.0
52 CURVA PVC CONDUIT DE 1" UND $ 910.0
53 PEGANTE, CINTA, OTROS GLB $ 450.0
LISTA DE PRECIOS ELÉCTRICOS
ITEM DESCRIPCION UNIDAD VALOR
54 LAMPARA CERRADA DE ALUMBRADO TIPO ORION DE SYLVANIA 60W TIPO LED UND $ 599,277.0
55 BRAZO CON ABRAZADERAS DE 1.5MX1-1/2" UND $ 48,600.0
56 BASE Y FOTOCELDA DE 1000W UND $ 26,400.0
57 CABLE DE COBRE THNN No. 12 ML $ 1,750.0
58 CONECTOR DE RED TRENZADA 2-12 UND $ 13,600.0
59 ACCESORIOS MENORES DE MONTAJE GLB $ 300.0
60 POSTE DE CONCRETO DE 12 MTS X 750 KGR UND $ 870,500.0
61 POSTE DE CONCRETO DE 10 MTS X 510 KGR UND $ 596,500.0
62 CRUCETA METALICA DE 2,4 M AUTOSOPORTADA UND $ 186,500.0
63 ESPARRAGO DE 5/8X12" UND $ 8,500.0
64 PERNO DE 5/8X12" UND $ 3,500.0
65 ABRAZADERA DOBLE DE 7-8" UND $ 21,350.0
66 AISLADOR SINTETICO DE 15 KV UND $ 45,000.0
67 TUERCA DE OJO ALARGADO DE 5/8" UND $ 8,500.0
68 GRAPA TIPO PISTOLA DE 2 UES UND $ 21,450.0
69 AISLADOR DE PIN DE 15 KV UND $ 32,560.0
70 PIN PARA CRUCETA METALICA UND $ 8,650.0
71 ACCESORIOS MENORES GLB $ 4,500.0
72 CRUCETA METALICA DE 2,4 M AUTOSOPORTADA UND $ 186,500.0
73 ESPARRAGO DE 5/8X12" UND $ 8,500.0
74 PERNO DE 5/8X12" UND $ 3,500.0
75 AISLADOR SINTETICO DE 15 KV UND $ 45,000.0
76 TUERCA DE OJO ALARGADO DE 5/8" UND $ 8,500.0
77 GRAPA TIPO PISTOLA DE 2 UES UND $ 21,450.0
78 ACCESORIOS MENORES GLB $ 4,500.0
79 CRUCETA METALICA DE 2,4 M AUTOSOPORTADA UND $ 186,500.0
80 PERNO DE 5/8X12" UND $ 3,500.0
81 AISLADOR DE PIN DE 15 KV UND $ 32,560.0
82 PIN PARA CRUCETA METALICA UND $ 8,650.0
83 ACCESORIOS MENORES GLB $ 2,500.0
84 CRUCETA METALICA DE 2,4 M AUTOSOPORTADA UND $ 186,500.0
85 ESPARRAGO DE 5/8X12" UND $ 8,500.0
86 PERNO DE 5/8X12" UND $ 3,500.0
87 AISLADOR DE PIN DE 15 KV UND $ 32,560.0
88 PIN PARA CRUCETA METALICA UND $ 8,650.0
89 ACCESORIOS MENORES GLB $ 4,500.0
90 TRANSFORMADOR TRIFASICO DE 45 KVA -13200/220/127 VOLTIOS UND $ 6,480,500.0
91 COLLARIN PARA TRANSFORMADOR DE 15 CMS UND $ 28,500.0
92 CRUCETA METALICA DE 2,4 M AUTOSOPORTADA UND $ 186,500.0
93 CABLE DE COBRE DESNUDO O FORRADO No. 2 ML $ 11,750.0
94 PARARRAYOS SINTETICO DE 12KV-10KAMP. UND $ 125,000.0
95 PERNO DE 5/8X12" UND $ 3,500.0
96 CORTACIRCUITOS DE 100 AMP-15KV TIPO COSTA UND $ 164,505.0
97 FUSIBLE DE SOGA DE 2 AMP. UND $ 6,500.0
98 TUBO GALVANIZADO DE 1/2"X3M UND $ 31,500.0
99 CONECTOR CON ESTRIBO DE COBRE UND $ 35,000.0
100 CONECTOR AMOVIBLE DE COBRE UND $ 23,500.0
101 CINTA BANDIT DE 3/4" ML $ 3,500.0
102 HEBILLAS PARA CINTA BANDIT DE 3/4" UND $ 1,200.0
103 ABRAZADERA DE UNA SALIDA DE 6-8" UND $ 18,500.0
104 VARILLA DE COBRE SOLIDO CON CONECTOR UND $ 125,600.0
105 CABLE DE ALUMINIO TIPO ACSR No. 1/0 ML $ 2,850.0
106 AISLADOR DE PORCELANA TIPO TENSOR DE 7" UND $ 18,000.0
LISTA DE PRECIOS ELÉCTRICOS
ITEM DESCRIPCION UNIDAD VALOR
107 GRAPAS PRENSAHILO DE 1 1/2 X 1/4" X 6" 3 PERNOS UND $ 12,500.0
108 GUARDACABO EN ACERO GALVANIZADO PARA CABLE DE 1/2" UND $ 2,500.0
109 ARANDELA CUADRADA DE 4 X 4 X 5/8" X 1/8" PARA ANCLAJE UND $ 4,000.0
110 VARILLA DE ANCLAJE DE 5/8" X 1,8 MTS UND $ 30,000.0
111 VIGUETA DE CONCRETO PARA ANCLAJE DE 24X15X18,5 CMS UND $ 12,500.0
112 CABLE DE ACERO PARA RETENIDA EXTRA ALTA RESISTENCIA DE 1/4" ML $ 2,350.0
113 ALAMBRE GALVANIZADO No. 10 KG $ 3,620.0
114 PLETINA DE SUJECION UND $ 45,000.0
115 PERNO DE 5/8X10" UND $ 3,500.0
116 VARILLA DE COBRE SOLIDO DE 5/8"X2.4M UND $ 125,600.0
117 CABLE DE COBRE DESNUDO No. 1/0 ML $ 18,500.0
118 HIDROSOLTA UND $ 95,000.0
119 SOLDADURA CADWELD DE 90 GRAMOS UND $ 35,000.0
120 PLATINA DE CORE DE 5/8X1/4"X60 CMS UND $ 380,000.0
121 AISLADORES DE BARRAJE Y TRORNILLOS UND $ 6,500.0
122 ELEMENTOS DE SUJECION Y MONTAJE GL $ 35,003.0
123 VARILLA DE COBRE SOLIDO DE 5/8"X2.4M UND $ 125,600.0
124 CABLE DE COBRE DESNUDO No. 2 ML $ 10,750.0
125 CONECTOR DE COMPRESION PARA VARILA DE 5/8" UND $ 8,750.0
126 TUBERIA PVC CONDUIT DE 1/2" ML $ 1,186.0
127 ADAPTADOR TERMINAL PVC 1/2" UND $ 227.0
128 UNION PVC CONDUIT 1/2" UND $ 135.0
129 CURVA PVC CONDUIT DE 1/2" UND $ 390.0
130 CABLE DE COBRE THW No. 12 ML $ 1,460.0
131 LAMPARA FLUORESCENTE DE 2X32W CON BALASTO ELECTRONICO UND $ 78,500.0
132 INTERRUPTOR SENCILLO UND $ 5,250.0
133 CAJA OCTAGONAL GALVANIZADA UND $ 1,200.0
134 CAJA RECTANGULAR 2X4" GALVAN. UND $ 1,000.0
135 PEGANTE, CINTA, OTROS GLB $ 500.0
136 TUBERIA PVC CONDUIT DE 1/2" ML $ 1,186.0
137 ADAPTADOR TERMINAL PVC 1/2" UND $ 227.0
138 UNION PVC CONDUIT 1/2" UND $ 135.0
139 CURVA PVC CONDUIT DE 1/2" UND $ 390.0
140 CABLE DE COBRE THW No. 12 ML $ 1,460.0
141 TOMA DOBLE MONOFASICA CON POLO A TIERRA UND $ 4,850.0
142 CAJA RECTANGULAR 2X4" GALVAN. UND $ 1,500.0
143 PEGANTE, CINTA, OTROS GLB $ 500.0
TABLERO TRIFASICO DE 36 CIRCUITOS CON ESPACIO PARA TOTALIZADOR, CON
144 UND $ 590,000.0
BARRAJE DE NEUTRO Y TIERRA
145 BREAKERS ENCHUFABLE 1X20 AMP. UND $ 9,850.0
146 BREAKERS ENCHUFABLE 2X20 AMP. UND $ 26,000.0
147 BREAKER INDUSTRIAL DE 3X125 AMPERIOS UND $ 462,150.0
148 ACCESORIOS MENORES UND $ 15,600.0
CÁLCULO DETALLADO DEL VALOR PORCENTUAL DEL A.I.U
PERSONAL ADMINISTRATIVO
Secretaria de la Oficina Ppal Mes 2.00 $ 1,809,817 $ 3,619,634 0.13%
Mensajero de Obra Mes 4.00 $ 1,809,817 $ 7,239,267 0.26%
Elementos de Seguridad Personal en Obra Frente 10.00 $ 1,790,627 $ 17,906,269 0.63%
Almacenista de la Obra Mes 6.00 $ 1,103,126 $ 6,618,758 0.23%
Celador de la Obra Mes 10.00 $ 1,206,545 $ 12,065,445 0.43%
PERSONAL TÉCNICO
Ingeniero Director (Con Prestac. Sociales) Mes 2.00 $ 5,942,280 $ 11,884,560 0.42%
Ingeniero Residente (Con Prestac. Sociales) Mes 10.00 $ 4,129,140 $ 41,291,400 1.46%
Ingeniero Auxiliar (Con Prestac. Sociales) Mes 10.00 $ 4,129,140 $ 41,291,400 1.46%
Plan de Gestion Social Mes 4.00 $ 3,571,770 $ 14,287,080 0.50%
Valor y porcentaje total de los Costos de Legalización y Administración $ 679,603,071 24.00%
Valor porcentual de los Imprevistos $ 28,316,795 1.00%
Condiciones climáticas $ 14,158,397 0.50%
Modificaciones menores $ 14,158,397 0.50%
Valor porcentual de la Utilidad estimada $ 141,583,973 5.00%
XXXXXXXXXXXXXXXXXXXXXXXXXX
CÁLCULO DETALLADO DEL VALOR PORCENTUAL DEL A.I.U
PERSONAL ADMINISTRATIVO
Secretaria de la Oficina Ppal Mes 0.50 $ 1,809,817 $ 904,908 0.11%
Mensajero de Obra Mes 0.50 $ 1,809,817 $ 904,908 0.11%
Elementos de Seguridad Personal en Obra Frente 0.50 $ 1,790,627 $ 895,313 0.11%
Almacenista de la Obra Mes 0.50 $ 1,103,126 $ 551,563 0.07%
Celador de la Obra Mes 0.50 $ 1,206,545 $ 603,272 0.07%
PERSONAL TÉCNICO
Ingeniero Director (Con Prestac. Sociales) Mes 0.25 $ 8,372,000 $ 2,093,000 0.26%
Ingeniero Residente (Con Prestac. Sociales) Mes 0.30 $ 6,045,000 $ 1,813,500 0.22%
Ingeniero Auxiliar (Con Prestac. Sociales) Mes 0.30 $ 5,577,000 $ 1,673,100 0.21%
Plan de Gestion Social Mes $ 5,447,000 $ - 0.00%
Valor y porcentaje total de los Costos de Legalización y Administración $ 146,121,167.88 18.00%
XXXXXXXXXXXXXXXXXXXXXXXXXXXX
PROPUESTA ECONOMICA
Entidad: ALCALDÍA MUNICIPAL DE CHIRIGUANÁ
CONSTRUCCIÓN DE LOS SISTEMAS DE ALCANTARILLADO SANITARIO Y TRATAMIENTO DE LAS AGUAS RESIDUALES DEL CORREGIMIENTO DE POPONTE MUNICIPIO
Proyecto:
DE CHIRIGUANA DEPARTAMENTO DEL CESAR
Relleno con material seleccionado de cantera, compactado al 95% del proctor modificado: incluye la
5.2 explotación, cargue y transporte del material, herramientas menores, equipos de compactación y mano de M3 $ 5,676.00 $ 71,192.00 $ 404,085,792.00 8.71%
obra.
Retiro de material sobrante de la excavación y escombros y limpieza general de obra, incluye: cargue,
5.3 M3 $ 4,916.00 $ 21,932.00 $ 107,817,712.00 2.32%
transporte, herramientas menores y mano de obra.
0.00%
6. INSTALACION DE TUBERIA Y ACCESORIOS PARA CONEXIONES DOMI $ 59,690,876.00 1.29%
Instalación de tubería de PVC con sistema de unión mecánica, campana espigo con hidrosello, de pared
6.1 ML $ 2,952.00 $ 13,608.00 $ 40,170,816.00 0.87%
interior lisa y exterior corrugada, de diámetro 6" (160 mm).
Instalación Silla Yee de 8"x6" (200 x160 mm)
6.2 UN $ 392.00 $ 38,620.00 $ 15,139,040.00 0.33%
Instalación Silla Yee de 10"x6" (250 x160 mm)
6.3 UN $ 33.00 $ 45,774.00 $ 1,510,542.00 0.03%
Instalación Sillas Yee de 12" x 6" (315 mm x 160 mm)
6.4 UN $ 47.00 $ 61,074.00 $ 2,870,478.00 0.06%
0.00%
7. POZOS DE INSPECCION $ 157,267,504.62 3.39%
Construcción de pozos de inspección de diámetro interno 1.20 mts, muros y placa de fondo de e = 0.20 m.
en concreto de 4000 psi, impermeabilizado. los pozos con profundidad menor a 1.80 m terminaran en placa
de espesor 0.25 m. en concreto reforzado de 4000 psi y 20 Kg de hierro. La tapa será en ferroconcreto y
7.1 0.00%
arotapas en platina, con manija pasante, se colocaran escalones en varillas de 3/4" cada 0.40 m. pintados
con anticorrosivos; incluye: materiales, herramientas, equipos, formaletas y mano de obras. el cemento para
los concretos debe ser tipo V.
Construcción de pozo con altura menor de 1.80 m. Hprm. 1.38 m.
7.1.1 UN $ 31.00 $ 2,108,805.02 $ 65,372,955.62 1.41%
Construcción de pozo con altura mayor de 1.80 m. Hprm. 2.35 m.
7.1.2 UN $ 35.00 $ 2,455,987.00 $ 85,959,545.00 1.85%
Construcción de pozo con altura mayor de 2.35 m. Hprm. 3.21 m.
7.1.3 UN $ 2.00 $ 2,967,502.00 $ 5,935,004.00 0.13%
0.00%
PROPUESTA ECONOMICA
Entidad: ALCALDÍA MUNICIPAL DE CHIRIGUANÁ
CONSTRUCCIÓN DE LOS SISTEMAS DE ALCANTARILLADO SANITARIO Y TRATAMIENTO DE LAS AGUAS RESIDUALES DEL CORREGIMIENTO DE POPONTE MUNICIPIO
Proyecto:
DE CHIRIGUANA DEPARTAMENTO DEL CESAR
22.13 Muro en Ladrillo a la vista - E=0.15m, Ladrillo 0.07x0.12x0.24m - Mortero de pega a la vista y ranurado. M2 $ 12.50 $ 126,245.00 $ 1,578,062.50 0.03%
0.00%
23. ASEO GENERAL, EMPRADIZACIÓN Y ADECUACIÓN VÍA $ 210,239,069.92 4.53%
23.1 Aseo general M2 $ 367.27 $ 1,616.44 $ 593,669.92 0.01%
23.2 Empradización dique perimetral M2 $ 3,000.00 $ 45,343.00 $ 136,029,000.00 2.93%
23.3 Adecuación vía de acceso, espesor promedio 0.20 m. M2 $ 3,120.00 $ 23,595.00 $ 73,616,400.00 1.59%
0.00%
TOTAL COSTO DIRECTO - OBRA CIVIL $ 2,831,679,463.51 61.04%
COSTOS INDIRECTOS - A.I.U. $ 849,503,839.05 18.31%
ADMINISTRACIÓN 25.00% $ 707,919,865.88 15.26%
IMPREVISTOS 1.00% $ 28,316,794.64 0.61%
UTILIDAD 4.00% $ 113,267,178.54 2.44%
TOTAL OBRA CIVIL $ 3,681,183,303.00 79.35%
0.00%
PROPUESTA ECONOMICA
Entidad: ALCALDÍA MUNICIPAL DE CHIRIGUANÁ
CONSTRUCCIÓN DE LOS SISTEMAS DE ALCANTARILLADO SANITARIO Y TRATAMIENTO DE LAS AGUAS RESIDUALES DEL CORREGIMIENTO DE POPONTE MUNICIPIO
Proyecto:
DE CHIRIGUANA DEPARTAMENTO DEL CESAR
PROPONENTE