TO,
Dear sir,
This has been reference to the discussions we had with you regarding your requirement of
complete TWO STAGE PARBOILING & PADDY DRIER 24T/BATCH made of (Stainless STEEL)
3) consumable items like gas for cutting sheets to be provided to complete the work. HYDRA OR
. CRANE required for unloading or erection of the plant is to be provided by the costumer.
4) Main stem header on plant & valves to be provided by customer
6) any additional structure required in case of deviation in plant by the customer has to be
provided by him.
7) water condensate line & its valve from heater to boiler is to be provided by costomer
8) water line from pump to inlet & waste line is to be done by customer
SANJAY AND COMPANY
Address. NICHLAUL, DIST- MAHARAJGANJ
UTTAR PRADESH-273304
Mob... 9648122946, 9415280705
EMAIL ID-SANJAYANDC@gmail.com
INSTALLATION SCOPE
1) INSTALLATION will begin when 70% of the material is reached at the site
2) Our scope is only limited to send labour for erection & the supervision all the tools ,
gases, & welding rod etc & HYDRA or CRANE required to erect the plant to be provided
by customer
3) Customer will have to make arrangement for the labour to stay at site & provide them
the basic amenities & food
1) All the prices are EX- works NICHLAUL (UP) & freight, insurance & taxes etc.
2) Payment terms 50% advance & rest before delivery.
3) All the material is covered except consumables ( sprockets , bearing, belts, rotors etc)
for the period of 1 year
4) All the unloading of the material is in customer scope & to be kept in his custody
5) All steel used is of PRIME Jindal/sail
6) Part shipment should be allowed