Professional Documents
Culture Documents
Satya CV
Satya CV
L
Mobile: 9004499000
Email : drmmmct@gmail.com
Grew freight revenues of freight by over 80% to Rs 110 Cr in FY 2020; achieved the highest
Non-Fare revenue on Indian Railways of Rs 85 Cr in FY 2020; completed crucial capex
projects like 15 car works; and achieved a capex growth of over Rs 650 cr (+30% y-o-y) in
FY 2020 and held the #1 position in KPI ranking for Divisions with workload above 300 in FY
2020-21.
Implemented two AI based predictive maintenance projects – for loco brake block inspection
at Mumbai Central and another a comprehensive loco external inspection system at Bandra
Loco shed
Formulated a strategy paper on “Manpower Strategy for New Infrastructure” in June 2019
and issued to all Railways.
Coordination with RITES for development of a National Rail Plan – work completed in FY
2019-20.
Responsible for monitoring at Railway Board for all aspects of the Dedicated Freight
Corridor Projects –construction, operational and financial aspects.
Formulated a highly data-driven and case study based, “AS-IS” report on DFC to CRB and
suggested a time-bound Turn-Round Plan and the Way Forward.
Formulated a “Blue Print” for Indian Railway on the way forward after Commissioning of the
DFCs.
Intense monitoring of the DFCs and escalation of issues to the highest level in a “truthful”
manner led to considerable action, especially on the RUB front on NCR. From a level of
ZERO the number of RUBs has gone upto 26 in one year.
Headed a Committee to evaluate the “Three New DFCs” and submitted the report to the
Board in three months.
Reducing unit cost of operation and up gradation of water depths and handling capabilities;
providing seamless connectivity by road and rail were thus imperative.
Modernization of the 80 year old Port was thus inevitable for its survival.
As Vice-Chairman of the Port was the project leader for the Project Monitoring Unit for
Infrastructure projects – 3 projects of Deepening of Channels (Dredging) – Rs 478 Cr;
5 Projects for development of New Berths with mechanization – Rs 1456 Cr; 3
projects of Upgradation/Mechanization of existing berths – Rs 1506 Cr; 5 projects of
other capacity enhancement works – Rs 325 Cr; 3 Road and Rail Connectivity
projects of Rs 460 Cr. 8 of these projects were taken up on PPP mode. 7 of these PPP
projects were started from RFQ stage and all LOAs had been issued, through a mechanism
perfected through a rapidly pro-active, learning curve.
DBFOT Model was followed in the PPP projects, with structures of Independent
Engineer/PMC being followed. However Internal monitoring mechanisms through
encouragement of timely escalation of issues and resolution of the issues, by balancing
immediate growth with long-term sustainability, no issue went unresolved on the same day.
Strict timelines were adhered to and have the proud distinction of the Port having had a
Brownfield transformation of its Prime General Cargo Berth, which underwent
mechanization on a PPP mode being commissioned by April 2013, complete with Cape
Handling, 4500 TPH discharge on ship side and rapid-loading silo system for rail, with RFP
issued in Feb 2010.
The capacity of the Port rose from 63 MTPA in 2009 to 111 MTPA by 2014, through
implementation of crucial projects.
Apart from the above capacity augmentation works of over Rs 4300 Cr, during the period
we undertook paradigm shifts in wet- leasing 2 Nos of 50T Tugs, 4 numbers of diesel
locomotives; revising the manning scales, datums and incentives of the employees
involved in shipping and railway activities. Led the talks with the Unions and the trade. Were
the only Port to have developed and implemented a Special Voluntary Retirement
scheme for its employees.
Undertook Rs 25 Cr. ERP project in 2010 on a QCBS (70:30) mode and infused technology
of GPSs on locomotives, tugs for better monitoring and 34 CCTVs spanning the entire Port.
Set up a Unified Command and Control Centre (UC 3) for synergizing the various facets of
Port Operations – shipping, railway, environment, road movements, security, etc. Facilitated
NID, Ahmedabad to conduct a three day workshop for design of the UC 3.. The facility was
inaugurated in December 2013.
Continual customization of Marketing policies on Priority Berthing; Volume Discount
Schemes; Berthing Policies and Plot allocation policies in a dynamically changing
environment was a daily routine.
Also developed three models of MMLP – one on a JV model with Balmer Lawrie;; the other
on a land-lease model with CONCOR and another as an embedded component in the
PPPs. Phase –I of COCNOR MMLP was commissioned in 2014.
Applied principles of costing and driven by market surveys, was the first Railway to invoke
Section 32 of Indian Railway Act to propose for station to station rates for Cement traffic
originating in Southern Railway. Approved after Finance Concurrence by GM, Southern
Railway.
Conceived, coordinated and developed Common User “Walajabad Auto Hub” in Chennai.
Conducted intensive safety drives and cleared arrears and made them current
Modified tender condition, with the permitted ambit, to maximize leasing potential of Parcel
Vans on the Railway
Managed the Brownfield works of the 3rd and 4th lines between Kottavalasa-Vizianagaram
and Kottavalasa-Simhachalam North with high density freight operations.
Streamlined Crew Management System in Waltair area and simplified operating principles to
the field level implementation : e,g mandating simple rules that a freight train shall not be
stabled at a particular station unless the level is escalated, etc.
Developed stretch targets and created an enabling environment for execution at field level.
Conceived the first ever “Route-Planning” Initiative on Indian Railway and within three
months of joining produced the High Density Network (HDN) Blue Print.
Segmenting Indian Railway into 7 major HDN routes along with associated feeders, the
current and future constraints were mapped in a logically sequenced manner and a route-
wise Rs 15043 Cr. Capex was projected. This pioneering work, which won acclaim is
attached as Annexure.
Director, Finance Directorate, Railway Board Indian Railway, New Delhi, India
April 2006 -May 2007
Collated the revenue, expenditure and operations databases of Indian Railway and
attempted to build a unified IT system complete with Marketing information.
Gained insights into the expenditure classification systems and the costing mechanisms of
the Railway.
Conducted a detailed Cost-Benefit Analysis of the two DFC Projects, complete with traffic
analysis, simulation with different scenarios of rolling stock parameters; financing options,
etc. Presented the same in a CTRAM conference in 2007.
Presented a Freight Business Plan for Indian Railway to the Financial Commissioner.
Chief Freight Marketing Manager(i/c) Southern Zone Indian Railway, Chennai, India
April 2003 – Jan 2004
Responsible for developing the $200 million freight segment, through liaising with industry;
planning the investment budget of $60 million; and for delivering marketing programs
through a team of 18 officers and 26 inspectors.
Improved overall revenues of zone by 36% (+$72 million) in the period 2002 – 2003 by
setting up focused marketing and sales teams and through innovative pricing.
Conceived, designed and implemented India’s first “refrigerated rail van” service.
Conceived and implemented a cost based pricing mechanism, which increased the
“automotive” transport by rail from a market share of ten percentage points during the
period.
Responsible for developing and implementing the EDI network across 16 functional
departments and for transforming the legacy systems into state-of-art technologies.
Senior Divisional Operations Manager, Palghat Division Indian Railway, Palghat, India
August 1997 – Aug 2000
March 2001- April 2003
May 2005 – March
2006
Responsible for optimal utilization of $180 million assets and for planning an investment
budget of $12 million.
Direct administrative responsibility for 1600 staff and responsible for ensuring safe, efficient
and punctual freight and passenger train operations over 1200 route kilometers.
Grew revenues to $35 million (+150%), improved asset utilization by 63%, saving $9 million
(+270%) over the period through focused operating strategies, developing high-level service
teams and instituting effective team based monitoring mechanisms.
Conducted frequent workshops with staff, supervisors and employees to expose them to
latest developments.
Conceived, developed and implemented Indian Railway’s first “Computerised train control
charting system”, with full-fledged capabilities of a FOIS. The system ran from 2001 –
2006, before being replaced by an all-India initiative by CRIS.
Awarded the Rail Minister’s National Award in 1999 for individual efficiency
During the above six year period in three spells, oversaw the entire 330 km doubling project
from Shoranur-Mangalore, as well as electrification of the double line from Erode to
Shoranur. Maintaining punctuality, in sensitive high-density sections of Kerala with doubling
works in progress was a great challenge. Cancellation, Diversion of trains, dealing with
commuter agitations and keeping open a formal and informal channel of communication with
the public was an art, perfected through a culture of openness and sharing.
Planned for port based rail-traffic of Sterlite industries, SPIC and the cement cluster around
Tuticorin by suitable infrastructure.
Managed the rail traffic control centre with 90 personnel and was responsible for safe,
punctual and efficient train operations over 1200 route kilometers.
Strived for mastering the art of train operations through extensive travel along the centres of
Salem, Erode, Karur, Trichy, Coimbatore, Shoranur, Calicut, Cannanore, Mangalore and
through interactions with Controllers, Drivers, Station Masters, Guards, Train Examiners,
Shunting staff, etc
Managed the rail traffic control centre with 90 personnel and was responsible for safe,
punctual and efficient train operations over 600 route kilometers