You are on page 1of 7

SHIKARAM ELEVATORS

H.No. 13-174/1C, Near St. Pauls School, Sai Nagar Colony, JADCHERLA.
H No. 12-1-154/7, Kushi Nagar, Bandlaguda X Road, Nagole Hyd.

TO, Date:24-06 -2022

Mr.

Site: BANDLAGUDA

Dear Sir,

Sub: Supply, Installation, Testing and Commissioning of 1no.Passenger Elevator

For your proposed site at BANDLAGUDA

We are pleased to submit our competitive offer for the above subjected job. Please find
enclosed the following for your kind reference:-

a. Technical specifications to your lift.


b. Terms and Conditions of our offer.
c. Price Schedule with Terms of Payment.
d. Conclusion of Contract.

Thanking you,

For M/s. Shikaram Elevators


Narsimha. K
9515746507.
7386589129.
Proprietor

1
SHIKARAM ELEVATORS
List Specifications
S.NO DESCRPTION SPECIFICATION
1 Type/Capacity Passenger/ 6 persons
2 Load / Speed 408 kg’s/ 0.60 M/sc
3 Motor Sharp Hp 5
4 Travel Height(Approximately) ...0 Meters (approx)
5 Type of Controller Microprocessor down collective V3F
Controller
6 Floors/ Openings G+ 3 ,Floor / 4 Openings/ 4 Landings
7 Type of Landing Doors
S.S DOOR FRAMES , 304 ,1.2

8 Type of Car Door Collapsible Gate


9 Car Right S.S Panel
Left S.S Panel
Back S.S Mirror Finishing
10 Display LED in All Landing & Inside the Car
11 Flooring & Illuminations PVC Vinyl Flooring, LED Light
Fittings, Fan and Fall Ceiling.
12 Pit Depth 910 mm
13 Over Head Management 4200 mm
14 Power Machine Room 3 Phase,420 Volts, 50 Cycles A.C
Supply Lift Well 1 Phase,230 Volts, 50 Cycles A.C
15 Landing & Car Fixtures S.S Mat Finish With Micro Push
Buttons
16 Additional Fixtures Emergency Alarm With Battery
17 Warranty After Running Date One and Half Year
18 Location of Machine Unit Above the lift Shaft
19 Motor RPM 960

2
SHIKARAM ELEVATORS
MATERIAL SPECIFICATIONS
S.NO MATERIAL COMPANY
1 MOTOR SHARP 5 HP C Core
Motonary
2 RAILS MAHARAJ COMPANY
10MM(m/f) 6 MM
3 DOOR FRAMES
S.S DOOR FRAMES 304, 1.2
4 GATES HAVEY COLLAPSIBLE
GATE 52 KG
5 ROPE USHA MARTINS ROPES
13MM
6 CABIN JINDAL SIEEL S.S 304

7 TYPE OF CAR FRAME OTC CAR FRAME

8 V3F (DRIVE) Toshiba &Yasikawa

9 PANEL BOARD RESIED AND ARISHITHA

10 ARD RESIED ARD

11 WIRING JOHNSON WIRING ,


MIRCO THARAM
12 LOP & COP TOUCH SS MANVEL DJTAL
BUTTONS
13 Governor Safety OSG Safety

14 NUT,BOLT TVS

3
SHIKARAM ELEVATORS
PRICE SCHEDULE AND TERMS OF PAYMENT:
I.PRICE SCHEDULE
Company’s Contract Price for supply, Installation and Testing Commissioning of your proposed
passenger lift as per the specifications attached shall be as below

Specification Reference No. Of Unit Price Total Price


Lifts
1) 6 persons passenger Lift
with S.S Car Body &
M.S COLLAPSIBLE
GATE and down 1 No. 4,80,000 /- 4,80,000 /-
collective V3F
Final
Controller.
Amount
2) INCLUDING ARD
(automatic rescue
device)

NOTE : EXCLUDING TAXES


II.TERMS OF PAYMENT:-

1) 50% Advance Along with Order.


2) 50% of contract value delivery of Material of site.

III.DELIVERY SCHEDULE:

 2 weeks from the date of advance payment along with order

IV.INSTALLATION & COMLETION SCHEDULE:-

 Installation shall be started within one week from the date of delivery at the site.
 The installation & commissioning work of the lift shall be completed within 3weeks from the
date of materials delivery at the site

4
SHIKARAM ELEVATORS
CONCLUSION OF CONTRACT
This Contract or Offer is Valid for 30 days from the date of offer for
acceptance by Customer. The Contract however shall be deemed concluded
and to have come into force only or confirmation by the Authorized
Signatory of Company.

Offer made and confirmed BY:


SIGNATURE
For M/S. NARSIMHA.K
9515746507
7386589129

Proprietor

Offer Accepted By:

SHIKARAM ELEVATORS

Customer signature

5
SHIKARAM ELEVATORS
WORKS IN YOUR SCOPE
CIVIL WORK
1. Completion of Three sides wall with plastering and coat white wash.
2. Scaffolding as per our requirements to be done by you.
3. Pocket hole chipping grouting or any other alternation work (Machinery) shall
be in your scope.
4. Machine room shall be completely finished as per our drawing with …’x … ”
door, two no’s of 3’x2’ lower type ventilators with steps/steel ladder for
commencing erection.
5. Wooden Template for Shaft Plumbing.

ELECTRICAL WORK
1. 3 phase supply to machine room along with 2 no’s 8 copper wiring from your
mains. Single phase supply in lift well form machine room shall be provide.
2. 2 no’s of 40 wt. tube light and bulk-head fittings in lift well for maintenance
along with 15A 3 pin sockets, as suggested by us.
3. 1no 4 pole MCB of suitable capacity & 2no’s of 6A MCB’s along with fixing
board shall be provide in Machine room as suggested in our GAD.

UNLOADING
1. Unloading the lift material from truck to the site will in your scope.
2. LOCKABEL store room shall be provided for delivery of Materials ,
Otherwise the responsibility for any loss of material supplied shall be to your
account.

MAINTENANCE:

6
SHIKARAM ELEVATORS
a) To provide free maintenance service for TWELVE months from the date of
commissioning of the lift as certified by company. Service shall consist of
regular examination, making any necessary adjustments, cleaning and
lubrication of all parts where such service is necessary to maintain the lift
equipment in proper and safe working Condition. The required supplies and
parts shall be furnished by company necessitated due to negligence, misuse or
accident or other abnormal conditions due directly or indirectly to
circumstances beyond company’s control. Company shall however not be held
responsible for the following items and these shall not be replaced buy company
free of cost;Viz.Car enclosure(including removable panels, door panels, hung
ceilings, hand rails,mirror,flooring, light fittings, fans, intercoms and
batteries),lift shaft enclosures, landing gates,door-closers,sills,indicator lamps
and light fittings.

b) To send trained personnel to the lift site as quickly as possible during working
hours on regular working days on receipt of information from a responsible
person in case of irregularities in working of the lift. Company shall not assume
possession or control of any part of the equipment but the same shall remain the
customer’s(or lessee’s) property exclusively. The Parts which are replaced shall
be Company’s Property.
c) Company shall not be liable for any loss, damage or delay due to any cause
Beyond its reasonable control including but not limited to acts of government,
strike,fire,explosion flood,theft,riot,civil commotion, war, malicious mischief or
act of God if the lift and its parts or the machine room are interfered with by
persons not authorized by company, Under no Circumstances shall company be
liable for consequential damages.