sewage line chamber fixing 500mmX500mmX1000mm

Sl No Description Unit Quantity Rate


sewage line chamber fixing
SEWAGE LINE CHAMBER FIXING
NO's
A EARTH WORK cum 0.70 250.00
B pcc cum 0.036 5,200.00
C LABOUR NO's 1 112.5
D HYDRA NO's 1 1,250.00
E COLLER NO's 6 136.00
Total

G [Total A+B+C+D+E)

I TOTAL

CONTRACTOR PROOFIT 15% 0.15


J TOTAL
X1000mm
Amount Remarks

176.00
187.20
112.50
1,250.00
816.00
2,541.70

2,541.70

2,541.70

381.26
2,922.96
Inspection chamber 500 x 500 mm depth upto
Sl No Description Unit No Length
Inspection chamber
A EARTH WORK cum 1.00 0.80
B PCC cum 1.00 0.60
C Bricks cum 2.00 0.50
Bricks cum 2.00 0.96
E Concrete benching Cum 1.00 0.50
F External plastering Sqmt 4.00 0.96
G Top plastering Sqmt 4.00 0.73
H Internal plastering Sqmt 1.00 2.00
I Medium duty perforated cover (Material cost) NO's 1.00
J Frame & Cover fixing NO's 1.00

material cost

Tools and tackles

Sub Total

CONTRACTOR PROOFIT 15%


J TOTAL
er 500 x 500 mm depth upto 900 mm
Bredth Depth Quantity Rate Amount Remarks

0.80 1.00 0.64 280.00 179.20


0.60 0.075 0.03 5,200.00 140.40
0.23 0.9 0.21 7,000.00 1,449.00
0.23 0.9 0.40 7,000.00 2,782.08
0.50 0.10 0.03 6,000.00 150.00
1.00 3.84 600.00 2,304.00
0.23 0.67 600.00 402.96
1.00 2.00 600.00 1,200.00
1.00 2400 2,400.00
1.00 500.00 500.00

11,507.64 14550

0.10 1,150.76

12,658.40

0.15 1,898.76
14,557.16
Enclosed
the rate
analysis
for your
reference.

SI No Item Description UOM Qty Rate Amount

supply and fixing HDPE fitting with


1
electrofusion joint all complete works.

a 110 mm coupler (supply) Nos 18

Installation Nos 18

b 110 mm elbow (supply) Nos 6

Installation Nos 6

c 110 mm 45*bend (supply) Nos 2

Installation Nos 2

110 mm flange (supply) Nos 10

Installation Nos 10

d 110 mm tee (supply) Nos 2

Installation Nos 2

e L.N 110mm Long Bush Nos 8

Installation Nos 8

supply and fixing Hdpe cutting,fitting


2 and jointing pipe pe-100 all complete
work.

a 110 mm dia (supply) Mtr 30

Installation Mtr 30
Sewage line cleaning Feet 140
Sub Total

14,998

Installation
Nos
6
800
4,800

-
c
110 mm 45*bend (supply)
Nos
2
2,499.64
4,999

Installation
Nos
2
800
1,600

110 mm flange (supply)


Nos
10
2,499.64
24,996

Installation
Nos
10
800
8,000
-
d
110 mm tee (supply)
Nos
2
2,499.64
4,999

Installation
Nos
2
800
1,600

-
e
L.N 110mm Long Bush
Nos
8
2,499.64
19,997

Installation
Nos
8
800
6,400
2
supply and fixing Hdpe cutting,fitting and jointing pipe pe-100 all complete work.
-
a
110 mm dia (supply)
Mtr
30
771.42
23,143

Installation
Mtr
30
200
6,000

Sewage line cleaning


Feet
140
600
84,000

Sub Total
264,926
Existing DG shifting
Sl No Description Unit Quantity Rate
sewage line chamber fixing
SEWAGE LINE CHAMBER FIXING
NO's
A REMOVING OF CABLES FOR DG AND PANELS LS 1.00 5,000
B FOUNDATION BREAKING AND SHIFTING NO's 1 10,000
C BARICATTION SHEETS REMOVING AND SHIFTING NO's 60 100
D MS ANGLES/SUPPORTS REMOVING AND SHIFTING LS 1 5,000
E HYDRA FOR DG AND PANEL SHIFTING DAY 1 12,000
Total

I TOTAL

CONTRACTOR PROOFIT 15% 0.15


J TOTAL
Amount Remarks

5,000.00
10,000.00
6,000.00
5,000.00
12,000.00
38,000.00

38,000.00

5,700.00
43,700.00
LT Cable joint kits 3c x 25 sqmm, Supply
Sl No Description Unit Quantity Rate Amount
sewage line chamber fixing
SEWAGE LINE CHAMBER FIXING
NO's
A 3.5 Core*25sqmm XLPE joint kit nos 1.00 2,956.00 2,956.00

B 2,956.00

TOTAL 2,956.00

CONTRACTOR PROOFIT 15% 0.15 443.40


C TOTAL 3,399.40
Remarks
LT Cable joint kits 3c x 75 sqmm, Supply
Sl No Description Unit Quantity Rate Amount
sewage line chamber fixing
SEWAGE LINE CHAMBER FIXING
NO's
A 3.5 Core*75sqmm XLPE joint kit nos 1.00 3,868.00 3,868.00

B 3,868.00

TOTAL 3,868.00

CONTRACTOR PROOFIT 15% 0.15 580.20


C TOTAL 4,448.20
Remarks
12 way SPN Double door DB
Sl No Description Unit Quantity Rate Amount
sewage line chamber fixing
SEWAGE LINE CHAMBER FIXING
NO's
A Supply nos 1.00 5,718.00 5,718.00
b Instalation nos 1.00 2,110.00 2,110.00

7,828.00

TOTAL 7,828.00

CONTRACTOR PROOFIT 15% 0.15 1,174.20


C TOTAL 9,002.20
Remarks
Supply, intallation, tetsting and comissioning of spreders for feeder pillar panels.
Sl No Description Unit Quantity Rate Amount
sewage line chamber fixing
SEWAGE LINE CHAMBER FIXING
NO's
A Supply nos 1.00 236.25 236.25
b Instalation nos 1.00 25.00 25.00

261.25

TOTAL 261.25

CONTRACTOR PROOFIT 15% 0.15 39.19


C TOTAL 300.44