You are on page 1of 2

Atlas Copco Underground drill rigs

Boom positioning
BUT 35 and BUT 45 Boltec with control system RCS

Preparations
Diesel engine must be running.
See Driving instruction Hydraulic pressure lever must be in position ON.

Start control system (1) Right lever

Left lever 2 Activate boom with button


on operator’s panel (2)
1
1 1 RCS
0 1 Activate screen handling
0 +
T

-
0
or service platform (3)
3

Positioning

Left lever Left lever + push button

1250 0207 23
Atlas Copco Underground drill rigs
Boom positioning
BUT 35 and BUT 45 Boltec with control system RCS

Positioning

Right lever Right lever + upper push button

Right lever + lower push button


1250 0207 24

After positioning
CAUTION! Turn off the hydraulic pressure lever after boom positioning.
9852 2005 01

Atlas Copco Rock Drills AB


ÖREBRO, Sweden
© Atlas Copco Rock Drills AB, 2008. All rights reserved