Method Statement for Installation of Roller Coaster of Morocco

ZHEJIANG JUMA AMUSEMENT EQUIPMENT CO., LTD

Method Statement for Installation of Boomerang Roller Coaster of Morocco

Basic tools for Installation

Mobile crane 80 t 1 set

Mobile crane 50 t 2 sets

Mobile crane 25 t 1 set

shackles 32t 4 sets

shackles 10t 8 sets

Wire rope clam Ø13-/ Ø19.5 20 ea


/Ø26/ Ø36
per
Chain block 5t 4 sets

Chain block 3t 4 sets

Chain block 2t 4 sets

hemp rope 100 米(Ø14) 2 rolls

Steel wire rope Ø26 1850mpa 200 m

Steel wire rope Ø13 1850mpa 300 m

Torque wrench 500-1000Nm 1 set With sockets


100-500 Nm

Jack 32t 4 pcs

Jack 16t 4 pcs

1
Method Statement for Installation of Roller Coaster of Morocco
ZHEJIANG JUMA AMUSEMENT EQUIPMENT CO., LTD

Jack 10t 2 pcs

Electrical tensio 300-500 Nm 1 set With sockets


ner 500-1000Nm

Adjustable spa 12”/24” 2 pcs


nner
Box spanner Each type 2 sets

Crowbar big 2 pcs

Crowbar small 4 pcs φ

Big hammer 12 pound 1 pc

Small hammer 4 pound/2.5 po 2 ea


und
Pipe pliers Big/small 1 ea

Hacksaw frame 1 set With saw blade

Theodolite laser 1 set With tripod

Dumpy level 1 set

tag line 200m

Fire extinguishe 10 pcs


r
Safety harness 8 sets

Safety helmet 10 pcs

2
Method Statement for Installation of Roller Coaster of Morocco
ZHEJIANG JUMA AMUSEMENT EQUIPMENT CO., LTD

Walkie talkie 5 pcs With charger

3
Method Statement for Installation of Roller Coaster of Morocco
ZHEJIANG JUMA AMUSEMENT EQUIPMENT CO., LTD

Steel wire 8#、14# 1 bundle e


ach
Paint brush Roller, handle Several

scaffolding Several With horizontal and om


ni-direction clamper
Scaffold plate thickness 50m 10 pcs
m
Angle steel 5×50 300m For installation of tempo
rary platorm
Secondary big 1 set With power meter
power
distribution box
(cabinet)
Tertiary power 2 sets Electrician's Tools
distribution box (Electrician bring along)
(cabinet)
Carbon
Welding machi 2 sets With accessories
dioxide(400
ne above)

Arc welding ma small(315) 1 set Portable, with accessori


chine es
Oxygen, acetyl 2 pcs With meter, hose,
ene connector, cutter

Electrode dryer 1 sets (506/507)2 box

4
Method Statement for Installation of Roller Coaster of Morocco
ZHEJIANG JUMA AMUSEMENT EQUIPMENT CO., LTD

Electrode incub 2 sets


ator
Welding wire Flux core several Purchase 60 rolls as pe
r usage in drawing

100/150 With grinding disk,cutti


Angle grinder 2 sets
ng disk, wire mesh

5
Method Statement for Installation of Roller Coaster of Morocco
ZHEJIANG JUMA AMUSEMENT EQUIPMENT CO., LTD

Goggles 10 pcs

Face shield, gla several


ss
Head grinder 2 sets With grinding heads

Power cable several

Steel ruler 1m 2 pcs

tape 5m 3 pcs

tape 50 m 2 pcs

Triangle ruler 2 pcs

marker, ink (bucket) line, spirit level,


puncher, shovel, Ø16-20 nylon rope

Installation key points


All data (column/track) must be measured and determined
based on the foundation 000 (coordinate benchmark)!

6
Method Statement for Installation of Roller Coaster of Morocco
ZHEJIANG JUMA AMUSEMENT EQUIPMENT CO., LTD

Work deployment
1:Wash the bolts on the steel foundation plate first to ensure cleanliness and convenience
for installation.

2:Measure whether each foundation position meets the requirements of the drawing!
GSC(HXS-I).00.TJ

3:First install column set 1 and diagonal column set 2/ of lifting section. Those are column
sets that need primary and secondary concreting.

Measure columns by
total station and see
whether they meet
requirements of the
drawing. And nut shall
be tightened to rated
torque. A secondary
grouting is required in
the drawing

M1/M4 Anchor connection form

7
Method Statement for Installation of Roller Coaster of Morocco
ZHEJIANG JUMA AMUSEMENT EQUIPMENT CO., LTD

All columns have No. marks on it. Flange connected by bolts.


M24*120 bolt for big pipe flange, M24*80 bolt for others, all of which
are double-nut and double washer.

Note: When installing bolts above M12 on


the equipment, use a torque wrench to
achieve the pre-tightening torque in the
drawing, and make a mark for preventing
loosening.

8
Method Statement for Installation of Roller Coaster of Morocco
ZHEJIANG JUMA AMUSEMENT EQUIPMENT CO., LTD

lift 1# and 9# track.

1# is primary lifting section, total 3 parts.

Refer to GSC(HXS-I).02.01 for details

M24*110 bolt for big pipe flange, M24*100 bolt for others, all of which are double-nut
and double washer.

7
Method Statement for Installation of Roller Coaster of Morocco
ZHEJIANG JUMA AMUSEMENT EQUIPMENT CO., LTD

8
Method Statement for Installation of Roller Coaster of Morocco
ZHEJIANG JUMA AMUSEMENT EQUIPMENT CO., LTD

Hook mechanism GSC(HXS-I).02.01.01.04

GSC(HXS-I).02.01

Tractor brake

Roller/frame GSC (HXS-


I).02.01.01.05

9
Method Statement for Installation of Roller Coaster of Morocco
ZHEJIANG JUMA AMUSEMENT EQUIPMENT CO., LTD

When lifting column 1 and track 1/track 9, use one 80t mobile crane and one 50t crane.
Connections between column and track are welded at site, cutting and beveling as per the position of column and track.

10
Method Statement for Installation of Roller Coaster of Morocco
ZHEJIANG JUMA AMUSEMENT EQUIPMENT CO., LTD

11
Method Statement for Installation of Roller Coaster of Morocco
ZHEJIANG JUMA AMUSEMENT EQUIPMENT CO., LTD

现场焊接!

12
Method Statement for Installation of Roller Coaster of Morocco
ZHEJIANG JUMA AMUSEMENT EQUIPMENT CO., LTD

After installation of 1#-2# primary lifting track 1 and track 2


8#_9# secondary lifting track 2 and track 8
First install drawing No.7 (vertical ring 360),

According to the welding number of the track, all the sections are assembled and connected on the g
M20*100 bolt for track connection.
At the track junction, use auxiliary materials to strengthen the connection.

Red auxiliary structure installed to strength the connection for the safety of lifting

On the foundation plate,assemble H24A-H24B, H23A-H23BR 2-in-


1 column and H21, H22, H25, H26 single column

13
Method Statement for Installation of Roller Coaster of Morocco
ZHEJIANG JUMA AMUSEMENT EQUIPMENT CO., LTD

For measurement of important data of drawing, use 00


original coordinates as benchmark for total station!

14
Method Statement for Installation of Roller Coaster of Morocco
ZHEJIANG JUMA AMUSEMENT EQUIPMENT CO., LTD

Weld at site!

Weld at site!

Weld at site!

Smooth joint transi


tion
Weld at site!

15
Method Statement for Installation of Roller Coaster of Morocco
ZHEJIANG JUMA AMUSEMENT EQUIPMENT CO., LTD

Use 2 cranes to lift vertical ring. Slowly move to the


connection point of column, and measure until it’s in correct
position. All of 8 joints between column and tracks are welded
at site

One example of installation

16
Method Statement for Installation of Roller Coaster of Morocco
ZHEJIANG JUMA AMUSEMENT EQUIPMENT CO., LTD

Install column
H6/ H7/ H8/ H9/ are single column
H10A/ H10B are double column

H11(A/B/C) triple column

H12(A/B)double column

H13(A/B)double column

H14(A/B/C)triple column

H15A/ H15B double column


H16/ H17/ H18/ H19/ are single column

17
Method Statement for Installation of Roller Coaster of Morocco
ZHEJIANG JUMA AMUSEMENT EQUIPMENT CO., LTD

Use total station to measure the coordinates of top point of


each column and make sure they reach the requirement
of drawing.

Use 2 cranes to lift track. And another crane or scaffolding


for workers to access to height for connection of tracks.

18
Method Statement for Installation of Roller Coaster of Morocco
ZHEJIANG JUMA AMUSEMENT EQUIPMENT CO., LTD

use 3 cranes in the same time to asse


mble track 5#

19
Method Statement for Installation of Roller Coaster of Morocco
ZHEJIANG JUMA AMUSEMENT EQUIPMENT CO., LTD

assemble track 4#

20
Method Statement for Installation of Roller Coaster of Morocco
ZHEJIANG JUMA AMUSEMENT EQUIPMENT CO., LTD

Smooth transition for each joint

21
Method Statement for Installation of Roller Coaster of Morocco
ZHEJIANG JUMA AMUSEMENT EQUIPMENT CO., LTD

Assemble track for station platform.

22
Method Statement for Installation of Roller Coaster of Morocco
ZHEJIANG JUMA AMUSEMENT EQUIPMENT CO., LTD

23
Method Statement for Installation of Roller Coaster of Morocco
ZHEJIANG JUMA AMUSEMENT EQUIPMENT CO., LTD

There are 9 sets of brakes at the station platform. The


installation height of brake shall be according to the
dimension in the drawing. It’s preferred to put car on the
track and install brake with reference to it.

24
Method Statement for Installation of Roller Coaster of Morocco
ZHEJIANG JUMA AMUSEMENT EQUIPMENT CO., LTD

Traction steel cable transition trolley

tractor

25
Method Statement for Installation of Roller Coaster of Morocco
ZHEJIANG JUMA AMUSEMENT EQUIPMENT CO., LTD

when lift hook

the principle of primary and secondary lifting is same

26
Method Statement for Installation of Roller Coaster of Morocco
ZHEJIANG JUMA AMUSEMENT EQUIPMENT CO., LTD

transition trolley transition wheel at top of


lifting track

tractor

winch

27
Method Statement for Installation of Roller Coaster of Morocco
ZHEJIANG JUMA AMUSEMENT EQUIPMENT CO., LTD

afte tractor is inst


alled, install verifi
cation system of
hook and de-hoo
k

28
Method Statement for Installation of Roller Coaster of Morocco
ZHEJIANG JUMA AMUSEMENT EQUIPMENT CO., LTD

29
Method Statement for Installation of Roller Coaster of Morocco
ZHEJIANG JUMA AMUSEMENT EQUIPMENT CO., LTD

Hook verification sy
stem

30
Method Statement for Installation of Roller Coaster of Morocco
ZHEJIANG JUMA AMUSEMENT EQUIPMENT CO., LTD

Cabin press bar mechanism. Electrical control push cylinder upward, push the small wheel under cabin to
open press bar of seat.

31
Method Statement for Installation of Roller Coaster of Morocco
ZHEJIANG JUMA AMUSEMENT EQUIPMENT CO., LTD

Small wheel go upward, push


sling, open press bar of seat

32
Method Statement for Installation of Roller Coaster of Morocco
ZHEJIANG JUMA AMUSEMENT EQUIPMENT CO., LTD

periodically
check
connection bolts
between cars to
see if there is
any loosening

periodic check point


prevent loosening!

33
Method Statement for Installation of Roller Coaster of Morocco
ZHEJIANG JUMA AMUSEMENT EQUIPMENT CO., LTD

Connection points bet


ween cars

34
Method Statement for Installation of Roller Coaster of Morocco
ZHEJIANG JUMA AMUSEMENT EQUIPMENT CO., LTD

35
Method Statement for Installation of Roller Coaster of Morocco
ZHEJIANG JUMA AMUSEMENT EQUIPMENT CO., LTD

all mechanism of primary and


secondary lift are same. Install
tractor and hook mechanism as
per drawing of primary lift.
Platform roof and
electrical
equipment/circuit
installation. Mechanical
installation work is
basically done, wait for
electrical equipment
commissioning. Meet
requirement of general
drawing!

Juma Tech
nical Dept.
2020.9.29