You are on page 1of 8

Calculating Cement Sand And Aggregate In Concrete

Volume Of Concrete 1 M3
Dry Volume 1.54 M3

S.No Item Quantity Units Rate Amount


1 Cement 12 Bags 250 3000
2 Sand 13.59 Cuft. 17 231.10395
3 Aggregate 27.19 Cuft. 22 598.1514
4 Mason 0.37 Day/M3 350 129.5
5 Labour 3.5 Day/M3 250 875
6 Bhisti 0.2 Day/M3 200 40
Total Amount 4873.76
Add 1.5% Of Equipment Charge 73.11
Total 4946.86
Add 10% Contractor Profit 494.7
Grand Total 5441.5

Note Only Input the Data In the Red cell


egate In Concrete

Mix Ratio
Cement 1
Sand 1
Aggregate 2
Sum 4
Calculating Of Brick Work With Rate Analysis

1 M3 Material Ratio
Volume Of Brick Work
Cement 1
Sand 4
Volume Of Brick 0.001539 M3 Sum 5
Without Mortar

Volume Of Brick With 0.002 M3


Mortar

S.No Items Quantities Units Rate Amount


1 Cement 2 bags 250 500
2 Sand 8.660 cuft 17 147.217418
3 Brick 500 pcs 5 2500
5 Mason 0.94 day 350 329
6 Labour 1.8 day 250 450
7 Bhisti 0.2 day 200 40
Total Amount 3966.217
ADD 1.5% OF EQUIPMENT CHARGE 59.493
Total 4025.711
ADD 10% CONTRACTOR PROFIT 402.571
Grand Total 4428.282
Note Only Input the Data In the Red cell
h Rate Analysis

Volume Of Mortar
0.231 M3
(Wet)

Volume Of Mortar
0.307 M3
(Dry)

Brick Size With


0.2 0.1 0.1
Mortar
Brick Size Without
0.19 0.09 0.09
Mortar
Calculate Cement Sand In Pla

AREA OF PLASTER 100 M3


THICKNESS OF PLASTER 0.006 M

NOTE- 6MM THICKNESS PLASTER SHEET


S.NO ITEMS QNATITY 6MM UNITS RATE AMOUNT

1 Cement 6 bags 250 1500


2 Sand 21.13 cuft 17 359.261595
3 Mason 7.4 day/m2 350 2590
4 Labour 9.2 day/m2 250 2300
5 Bhisti 9.2 day/m2 200 1840
TOTAL AMOUNT 8589.26
ADD 1.5% EQUIPMENT CHARGE 128.84
TOTAL AMOUNT 8718.10
ADD 10% CONTRACTOR PROFIT 871.81
GRAND TOTAL 9589.91

NOTE - 12MM & 15MM PLASTER THICKNESS SHEET


AREA OF PLASTER ONE SIDE
THICKNESS OF PLASTER
THICKNESS OF PLASTER

S.NO ITEMS 12MM THICKNESS 15MM THICKNESS UNITS RATE AMOUNT


1 CEMENT 7 9 bags 250 4000
2 SAND 48.30 60.38 cuft 17 1847.63
3 MASON 7.4 7.4 day/m2 350 5180
4 LABOUR 9.2 9.2 day/m2 250 4600
5 BHISTI 9.2 9.2 day/m2 200 3680
TOTAL AMOUNT 19307.63
ADD 1.5% EQUIPMENT CHARGE 289.61
TOTAL AMOUNT 19597.25
ADD 10% CONTRACTOR PROFIT 1959.72
GRAND TOTAL 21556.97

Note Only Input the Data In the Red cell


ment Sand In Plaster

FOR 6MM THICKNESS PLASTER RATIO 1:3

Ratio 1:03
Cement 1
Sand 3
Total Ratio 4

FOR 12MM & 15MM THICKNESS PLASTER RATIO 1

100 M2 Ratio 1:06


0.012 M Cement 1
0.015 M Sand 6
Total Ratio 7
Calculation White Wash Putty Paint Q

AREA TO BE PAINTED 1000 SQFT

S.NO. ITEMS QUANTITY UNIT RATE AMOUNT FOR MATERIALS


1 WHITE WASH 33.33 KG 45 1500 ITEMS
2 PUTTY 40 KG 200 8000 WHITE WASH
3 PAINT 18.16 LITRE 300 5447.6121 PUTTY
4 MASON FOR WW 1.43 DAY 300 428.57143 PAINT
5 MASON FOR PUTTY 3.3 DAY 300 1000
6 MASON FOR PAINT 4 DAY 300 1200 FOR LABOUR
TOTAL AMOUNT 17576.18 ITEMS
ADD 2.5% EQUIPMENT CHARGE 439.40 WHITE WASH
TOTAL AMOUNT 18015.59 PUTTY
ADD 10% CONTRACTOR PROFIT 1801.56 PAINT
GRAND TOTAL 19817.15

Note Only Input the Data In the Red cell


Wash Putty Paint Quantity

1 gallon (U.K) 4.54 litter


1 gallon (u.S) 3.85 litter
FOR MATERIALS
MATERIALS UNIT
30 SQFT/kg
25 SQFT/kg
55.07 SQFT/ltr

FOR LABOUR
work effici coat unit
700 one coat sqft/day
300 two coat sqft/day
250 one coat sqft/day

You might also like