Latihan Sequence FW

Diketahui : Data Dibawah


siklus Cor Pier (1 Stage) : 6 days
siklus Cor Pier (2 Stage) : 6 days Bila Ada
Sikus Cor Pier Head : 26 days
Ketinggian Fomrmwork Pier : 3.6 M
Waktu Penyelesaian : 150 days
Harga Rental Pier : 125.000/m2/month
Harga Rental Pier head : 435.000/m2/month
Jika Productivitas Pekerja : 4m2/man/Days (Fabrication)
: 2.5 m2/man/Days (Seeting & Dismantling)
Ditanya
Discription Type Sistem Qty (set) M2 N x Pindah Cost FW / Scaffold
1. Formwok Pier
2. Formwok Pier Head (side Form)
3. Shoring Pier Head (Bottom Form)
4. Jumlah Pekerja yang dibutuhkan dalam waktu Konstruksi Tersebut diatas

Ramp 5_Kelompok 3
Description Dimensi A1 P1 P2 P3 P4 P5 P6 A2
High Pier (cm) 5,000 12,000 14,000 14,000 14,000 12,000 9,000 5,000
Unit Pier (Pcs) 3.5 m x 3.5 m 1 1 1 1 1 1 1 1
Unit Pier Head (Pcs) 6 m x 2.5 m x 1m 1 1 1 1 1 1