Professional Documents
Culture Documents
Procurement of Works
This SBD is intended as a model for admeasurement (unit prices or unit rates in a bill
of quantities) types of Contract, which are the most common in Works contracting.
Care should be taken to check the relevance of the provisions of the standard
documents against the requirements of the specific Works to be procured. The
following directions should be observed when using the documents:
(a) All the documents listed in the Table of Contents are normally required for
the procurement of Works. However, they should be adapted as necessary
to the circumstances of the particular Project.
(c) This SBD is intended to serve on a repetitive basis in the Philippines, once
agreement between the Philippines and the Funding Source has been
reached. Modifications for specific Project or Contract needs should be
provided only in the SCC as amendments to Conditions of Contract. If
modifications must be made to bidding procedures, they can be presented
in the BDS.
1 Except in the case of International Competitive Bidding (ICB) funded by either ADB, JBIC or WB in
which case the use of the respective SBD for ICB is mandatory
1
(d) The notes inside boxes with single borders are not part of the text, but
rather contain instructions for the user, as do the Preface and this
Introduction section. They should not be incorporated in the Bidding
Documents. The cover should be modified as required to identify the
Bidding Documents as to the names of the Project, Contract, and
PROCURING ENTITY, in addition to date of issue.
(e) The notes inside boxes with double borders should be retained in the
issued Bidding Documents, since these notes provide important guidance
to Bidders.
(f) The SBD have been prepared for bidding where post-qualification applies
with or without an eligibility check. The process of pre-qualification of
Bidders is not covered in this SBD.
2
Table of Contents
3
Section I. Invitation to Apply for Eligibility
and to Bid
(a) Advertised at least twice within a maximum period of fourteen (14) calendar days,
with a minimum period of six (6) calendar days between publications, in a
newspaper of general nationwide circulation which has been regularly published for
at least two (2) years before the date of issue of the advertisement;
(c) Posted at any conspicuous place reserved for this purpose in the premises of the
PROCURING ENTITY concerned, as certified by the head of the Bids and Awards
Committee (BAC) Secretariat of the PROCURING ENTITY during the maximum
period of fourteen (14) calendar days stated above;
(d) In the case of ADB, WB and JBIC funding, sent to all who have expressed an
interest in undertaking the works as a result of any General Procurement Notice
issued; and
(e) In addition, sent to all heads of associations of contractors within the area.
The Invitation provides information that enables interested Bidders to decide whether to
participate. Apart from the essential items listed in the Bidding Documents, the Invitation
should also indicate the following:
(a) The Bidding Documents shall be issued within thirty (30) calendar days from the
last day of the period of advertising and/or posting of the Invitation to Apply for
Eligibility and to Bid; In the case of the ADB, JBIC and WB, the Bidding
Documents must be available for purchase for a minimum of thirty (30) days;
(b) The following deadline for submission for Bids from the last day of the period for
advertising and/or posting of the Invitation: [Estimated Contract Cost (in pesos);
period]
1 For Projects funded by ADB, JBIC or WB, replace all instances of the term "Invitation to Apply for
Eligibility and to Bid" with "Invitation for Bids", except when the term is used in a provision solely for
GOP funded projects.
4
i. Up to twenty five (25) million Pesos, 15 to 30 calendar days;
ii. Above twenty five (25) million up to fifty (50) million Pesos, 15 to 45
calendar days;
iii. Above fifty (50) million up to two hundred (200) million Pesos, 30 to 60
calendar days; and
iv. Above two hundred (200) million Pesos, 60 to 90 calendar days;
(c) Any important Bid evaluation criteria (for example, the application of a margin of
preference in Bid evaluation) or qualification requirement (for example, a
requirement for a minimum level of experience in constructing similar works for
which the Invitation is issued).
The Invitation to Apply for Eligibility and to Bid should be incorporated into the Bidding
Documents. The information contained in the Invitation must conform to the Bidding
Documents and in particular to the relevant information in the BDS.
5
Invitation to Apply for Eligibility and to Bid
1. If the Funding Source is ADB, JBIC or WB, state the following (If the
Funding Source is wholly GOP, delete this provision):
This Invitation for Bids follows the general procurement notice for this project
that appeared in Development Business, issue no. [insert number] of [insert
date]
2. Select one of the two following paragraphs deleting the other depending on
the Funding Source:
2In the case of National Government Agencies, the General Appropriations Act and/or continuing
appropriations; in the case of Government Owned or Controlled Corporations (GOCCs), Government
Financial Institutions (GFIs), and State Universities and Colleges (SUCs), the Corporate Budget for
the contract approved by the governing Boards; in the case of Local Government Units (LGUs), the
Budget for the contract approved by the respective Sanggunian. (Section 5(a), R.A. 9184)
6
3. Select one of the following two paragraphs, depending on the funding Source:
The [insert name of PROCURING ENTITY] now invites sealed Bids from
eligible Bidders for [insert brief description of works to be procured]1.
Completion of the works is required by [insert the required delivery date or
expected contract duration].
The [insert name of the PROCURING ENTITY] now invites potential Bidders
to apply for eligibility for [insert brief description of works to be procured].
Bidders should possess a valid PCAB license applicable to the above type and
cost of the contract, have completed a similar contract with a value of at least
50% of the ABC, and meet the other minimum eligibility requirements stated in
the eligibility forms. Applications for eligibility will be evaluated on a
“pass/fail” basis. The deadline for submission of eligibility documents shall be
on or before [insert date]. Only those Bidders passing the eligibility check will
be entitled to purchase the Bidding Document. Completion of the works is
required by [insert the required delivery date or expected contract duration].
4. Select one of the following four paragraphs, deleting the other three
depending on the Funding Source:
1 A brief description of the type(s) of works should be provided, including scope, location of project,
and other information necessary to enable potential bidders to decide whether or not to respond to the
invitation.
7
Bidding will be conducted in accordance with Asian Development Bank’s
procurement procedures and is open to all Bidders from eligible source
countries as defined in “Guidelines for Procurement by the Asian
Development Bank and its Borrowers”
5. Interested Bidders shall secure the Eligibility documents from the BAC
Secretariat at the address stated below, on or before [insert time and date]. They
shall submit the accomplished Eligibility documents, in order for these to be
received by the BAC Secretariat in the same address, on or before [insert time
and date].
6. Interested eligible Bidders may obtain further information from [insert name of
the PROCURING ENTITY] and inspect the Bidding Documents at the address
given below from [insert start of office hours] to [insert end of office hours] on
[insert dates].
8
A complete set of Bidding Documents may be purchased by Bidders that passed
the eligibility check upon the presentation of the Notice of Eligibility to the
BAC Secretariat, at the address below [state address at the end of document]
and upon payment of a nonrefundable fee [insert amount in Pesos]. The
Bidding Documents shall be received personally by the bidder or his authorized
representative on or before [insert time and date].
8. The [insert name of the PROCURING ENTITY] will hold a Pre-Bid Conference
open to all Eligible Bidders on [insert time and date] at the following address
[insert address]
9. Eligible Bidders must submit their Bids at the address below at or before [insert
time and date]. All Bids must be accompanied by a Bid security in the form of
[state the form of security] and in an amount of [insert amount in Pesos] or an
equivalent amount in a freely convertible currency. Late Bids shall not be
accepted. Bid opening shall be on [insert date, time and place]. Bids will be
opened in the presence of the Bidders’ representatives who choose to attend at
the address below at [insert time and date].
10. [Insert such other relevant documents deemed necessary by the PROCURING
ENTITY]
11. The [insert name of the PROCURING ENTITY] reserves the right to accept or
reject any Bid, and to annul the bidding process and reject all Bids at any time
prior to contract award, without thereby incurring any liability to the affected
Bidder or Bidders.
9
Section II. Instructions to Bidders
Section II contains provisions that are to be used unchanged. Section III consists of
provisions that supplement, amend, or specify in detail information or requirements
included in Section II and which are specific to each procurement.
Matters governing the performance of the Contractor, payments under the contract, or
matters affecting the risks, rights, and obligations of the parties under the contract are not
normally included in this section, but rather under Section IV. General Conditions of
Contract (GCC), and/or Section V. Special Conditions of Contract (SCC). If duplication
of a subject is inevitable in the other sections of the document prepared by the
PROCURING ENTITY, care must be exercised to avoid contradictions between clauses
dealing with the same matter.
10
Table of Contents
11
1. Scope of Bid
1.1. The PROCURING ENTITY as defined in the Bid Data Sheet (BDS)
and SCC, invites Bids for the construction of Works, as described in
the SCC and BDS. The name and identification number of the
Contract is provided in the BDS and SCC.
1.2. The successful Bidder will be expected to complete the Works by the
intended completion date specified in the SCC.
1.3. The PROCURING ENTITY has received funds from the Funding
Source named in the BDS, and in the amount indicated in the BDS. It
intends to apply part of the funds received towards the cost of the
Project, as defined in the BDS, to cover eligible payments under the
Contract for the Works. Unless otherwise indicated in the BDS,
payments by the Foreign Funding Source will be made only at the
request of the PROCURING ENTITY and upon approval by the
Funding Source in accordance with the terms and conditions of the
Financing Agreement between the GOP/PROCURING ENTITY and
the Funding Source (hereinafter called the "Financing Agreement").
The payments will be subject in all respects to the terms and conditions
of that Financing Agreement and the applicable law. No party other
than the PROCURING ENTITY shall derive any rights from the
Financing Agreement or have any claim to the funds.
(a) defines, for the purposes of this provision, the terms set forth below
as follows:
(i) "corrupt practice" means behavior on the part of
officials in the public or private sectors by which they
improperly and unlawfully enrich themselves and/or
others, or induce others to do so, by misusing the
position in which they are placed, and it includes the
offering, giving, receiving, or soliciting of anything of
value to influence the action of any such official in the
procurement process or in contract execution; entering,
12
on behalf of the Government, into any contract or
transaction manifestly and grossly disadvantageous to
the same, whether or not the public officer profited or
will profit thereby; and
(ii) "fraudulent practice" means a misrepresentation of facts
in order to influence a procurement process or the
execution of a contract to the detriment of the
PROCURING ENTITY, and includes collusive
practices among Bidders (prior to or after Bid
submission) designed to establish Bid prices at artificial,
non-competitive levels and to deprive the PROCURING
ENTITY of the benefits of free and open competition.
(iii) “collusive practices” means a scheme or arrangement
between two or more Bidders, with or without the knowledge
of the PROCURING ENTITY, designed to establish Bid prices
at artificial, non-competitive levels;
(iv) “coercive practices” means harming or threatening to
harm, directly or indirectly, persons, or their property to
influence their participation in a procurement process,
or affect the execution of a contract.
(b) will reject a proposal for award if it determines that the Bidder
recommended for award has engaged in corrupt or fraudulent
practices in competing for the Contract; and
(c) will declare a firm ineligible, either indefinitely or for a stated
period of time, to be awarded Contract funded by the Funding
Source if it at any time determines that the firm has engaged in
corrupt or fraudulent practices in competing or, or in executing,
a Contract funded by the Funding Source.
2.2. Further, the GOP will seek to impose the maximum penalties for civil
and criminal liability available under the applicable law on individuals
and organizations deemed to be involved with corrupt or fraudulent
practices.
2.3. Furthermore, the Funding Source reserves the right to inspect and audit
records and accounts of a contractor in the Bidding for and
performance of a contract themselves or through independent auditors
as reflected in the GCC Clause 31..
3. Eligible Bidders
3.1. A Bidder, and all parties constituting the Bidder, shall have the
nationality of an eligible country as defined by the Funding Source
indicated in the BDS.
3.4. Subject to the provisions in the BDS, a Bidder (including all members
of a JV and subcontractors) shall not be presently associated, or shall
not have been associated in the past, directly or indirectly, with the
consultant or any other entity that has prepared the design,
specifications, and other documents for the Project or being proposed
as Engineer of the PROCURING ENTITY for the Contract.
3.5. A Bidder shall not have a conflict of interest. All Bidders found to
have a conflict of interest shall be disqualified. A Bidder may be
considered to have conflicting interests with another Bidder in any of
the events described in paragraphs (i) through (iii) below and a general
conflict of interest in any of the circumstances set out in paragraphs
(iv) through (viii) below:
14
Bidder, or influence the decisions of the PROCURING
ENTITY regarding this bidding process;
(v) submit more than one Bid in this bidding process. However,
this does not limit the participation of subcontractors (if
indicated in the BDS) in more than one Bid, or as Bidders and
subcontractors simultaneously;
(vi) participated as a consultant in the preparation of the design or
technical specifications of the goods and related services that
are the subject of the Bid; or
(vii) a firm or an organization who lends, or temporarily seconds, its
personnel to firms or organizations which are engaged in
consulting services for the preparation related to procurement
for or implementation of the project, if the personnel would be
involved in any capacity on the same project.
3.6. Bidders shall not be under a declaration of ineligibility for corrupt and
fraudulent practices issued by any of the Funding Agencies in
accordance with ITB Clause 2..
d) If the Bidder is a JV, the provisions of items (a), (b) or (c) of this
Clause shall correspondingly apply to each of the members of the
said JV, as may be appropriate.
15
3.8. Unless otherwise indicated in the BDS, majority publicly-owned
enterprises from the GOP shall be eligible only if, in addition to
conformance with all of the above requirements, they are also:
5. Eligibility/Qualification of Bidder
5.1. Prospective Bidders shall submit the following Eligibility
Requirements, unless otherwise stated in the BDS:
17
(k) Prospective Bidder’s computation of its Net Financial Contracting
Capacity (NFCC) as described in the BDS, or at the Bidder’s
option a commitment from a licensed bank to extend a credit
line, in the event of an award in the Bidder’s favor, or at the
Bidder’s option a cash deposit certificate, of not less than the
amount shown in the BDS;
Class "B" Documents
(l) A valid Joint Venture Agreement (JVA);
(m) A letter authorizing the BAC or its duly authorized
representative/s to verify all of the documents submitted; and
(n) Any other document described in the BDS.
5.4 To be considered eligible and qualified for contract award a Bidder must
meet the minimum qualifying criteria stated in the BDS.
5.5 5.5 The Bidder’s authorized signatory must certify all copy documents
as true and correct copies of the original document(s). Bidders must
follow the format and sequence set out above. Should a Bidder fail to do
so the PROCURING ENTITY will accept no liability for the rejection of
a Bidders Bid in accordance with ITB Clause 18.3..
5.6 Unless otherwise indicated in the BDS, only Bids from eligible Bidders
shall be opened and considered for award of Contract. These eligible
Bidders, whether single entities or JVs, should submit with their Bids,
information updating their original eligibility applications or,
alternatively, confirm in their Bids that the originally-submitted
information remains correct as of the date of Bid submission. The
update or confirmation should be provided in Section IX Forms and
Qualification Information.
6. Pre-Bid Conference
18
6.1. The Bidder by the act of submitting its Bid, shall be deemed to have
inspected the site and determined the general characteristics of the
contract works and the conditions of the contract to bid. The BAC shall
require an affidavit of such site inspection from eligible Bidder.
6.4. The Pre-Bid Conference shall be held at least twelve (12) calendar
days before the deadline for the submission and receipt of Bids.
However, attendance of the Bidders shall not be mandatory.
6.5. The Pre-Bid Conference shall discuss among other things, the technical
and financial components of the contract to be Bid. The minutes of the
Pre-Bid Conference shall be recorded and made available to all
participants not later than three (3) calendar days after the Pre-Bid
conference.
7.1. The set of Bidding Documents comprises the documents listed in the
table below and addenda issued in accordance with ITB Clause 8:
7.2. Bidders should note that the PROCURING ENTITY will only accept
Bids from Bidders that have purchased the Bidding Documents from
the office indicated in the Invitation to Apply for Eligibility and to Bid.
8.3 The Supplemental/Bid Bulletin shall be posted in the G-EPS and the
PROCURING ENTITY’s website, if any.
9.1 The Bidder shall bear all costs associated with the preparation and
submission of his Bid, and the PROCURING ENTITY will in no case
be responsible or liable for those costs.
9. Language of Bid
10.1 The Bid prepared by the Bidder, as well as all correspondence and
documents relating to the Bid exchanged by the Bidder and the
PROCURING ENTITY, shall be written in English. Supporting
documents and printed literature furnished by the Bidder may be in
another language provided they are accompanied by an accurate
translation of the relevant passages in English, in which case, for
purposes of interpretation of the Bid, the English translation shall
govern.
20
Documents Comprising the Bid, Technical and Financial Proposals
21
d) Any other document described in the BDS.
11.3 If indicated in the BDS, all Financial Proposals that exceed the ABC as
in the BDS, shall be rejected.
12.2. The Bidder shall fill in rates and prices for all items of the Works
described in the Bill of Quantities. Bids not addressing or providing
all of the required items in the Bidding Documents including, where
applicable, bill of quantities, shall be considered non-responsive and,
thus, automatically disqualified. In this regard, where a required item is
provided, but no price is indicated, the same shall be considered "0"
(zero) for the said item would mean that it is being offered for free to
the Government.
12.3. All duties, taxes, and other levies payable by the Contractor under the
Contract, or for any other cause, prior to the deadline for submission of
Bids, shall be included in the rates, prices, and total Bid price
submitted by the Bidder.
12.4. For the given scope of work in the contract as awarded, all Bid prices
shall be considered as fixed prices, and therefore not subject to price
escalation during contract implementation, except under extraordinary
circumstances as indicated in the BDS and specified in GCC Clause
49. and the SCC.
14.3. In the case of contracts in which the Contract Price is fixed (not subject
to price adjustment), if the period of Bid validity is extended beyond
sixty (60) days after the original Bid validity period, the Bid prices,
may be adjusted by applying the factors specified in the BDS or in the
request for extension, for the period of delay beyond sixty (60) days
after the expiry of the initial Bid validity, up to the notification of
award. Bid evaluation will be based on the Bid prices without taking
the above correction into consideration
(a) cash;
(b) a cashier's or certified check;
(c) an irrevocable letter of credit;
(d) a bank guarantee;
(e) surety bond;
(f) foreign government guarantee; or
(g) other such form indicated in the BDS.
15.3 In case of a bank guarantee, the Bid Security shall be submitted using
the Bid Security Form included in Section IX Forms and Qualification
Information, or another form acceptable to the PROCURING
ENTITY. The form must include the complete name of the Bidder.
The Bid Security should be valid for the period specified in the BDS.
23
15.5 No Bid Securities shall be returned to bidders after the opening of bids
and before contract signing, except to those that failed to comply with
any of the requirements to be submitted in the first bid envelope of the
bid, as provided in this IRR-A. Without prejudice to the provisions the
Act and this IRR-A on the forfeiture of Bid Securities, Bid Securities
shall be returned only after the bidder with the Lowest Calculated
Responsive Bid has signed the contract and furnished the Performance
Security, but in no case later than the expiration of the Bid Security
validity period indicated in the BDS.
The Bid Security of the successful Bidder will be discharged when the Bidder
has signed the Agreement and furnished the required Performance Security,
but in no case later than the expiration of the Bid Security validity period as
indicated in the BDS.
(a) if the Bidder withdraws the Bid after Bid opening during the period
of Bid validity;
(b) if the Bidder does not accept the correction of the Bid price,
pursuant to ITB Clause 25; or
(c) in the case of a successful Bidder, if the Bidder fails within the
specified time limit to
i. sign the Agreement;
ii. furnish the required Performance Security; or
iii. enter into a JV agreement if it has undertaken to do so.
(d) any other reasons stated in the BDS.
17.2. The original and the two (2) copies of the Bid shall be typed or written
in indelible ink and shall be signed by the Bidder or a person or
persons duly authorized to bind the Bidder to the contract. All pages
of the Bid where entries or amendments have been made shall be
initialed by the person or persons signing the Bid.
17.4. Unless otherwise provided in the BDS, the Bidder shall furnish
information as described in the Form of Bid on commissions or
gratuities, if any, paid or to be paid to agents relating to this Bid, and to
contract execution if the Bidder is awarded the contract.
18.2. Each copy of the Technical Proposal and Financial Proposal, shall be
similarly sealed duly marked as “COPY NO… - TECHNICAL
PROPOSAL” and “COPY NO…. – FINANCIAL PROPOSAL”
respectively and the outer envelope as “COPY NO”. These envelopes
containing the original and the copies shall then be enclosed in one
single envelope that shall:
18.3. If all envelopes are not sealed and marked as required, the
PROCURING ENTITY will assume no responsibility for the
misplacement or premature opening of the Bid.
25
18. Deadline for Submission of Bids
19.1. Bids must be received by the BAC of the PROCURING ENTITY at
the address on or before the date and time indicated in the BDS.
20.1 Any Bid submitted after the deadline for submission and receipt of
Bids prescribed by the PROCURING ENTITY, pursuant ITB Clause
19.1., shall be declared “Late”, and shall not be accepted by the
PROCURING ENTITY.
21.1 The Bidder may modify its Bid after it has been submitted; provided
that the modification is received by the PROCURING ENTITY prior
to the deadline prescribed for submission and receipt of Bids. The
Bidder shall not be allowed to retrieve its original bid, but shall be
allowed to submit another bid equally sealed, properly identified,
linked to its original bid marked as “TECHNICAL MODIFICATION”
or “FINANCIAL MODIFICATION” and stamped “received” by the
BAC. Bid modifications received after the applicable deadline shall not
be considered and shall be returned to the Bidder unopened.
21.3 No Bid may be modified after the deadline for submission of Bids. No
Bid may be withdrawn in the interval between the deadline for
submission of Bids and the expiration of the period of Bid validity
specified by the Bidder on the Bid Form. Withdrawal of a Bid during
this interval may result in the forfeiture of the Bidder’s Bid Security,
pursuant to the ITB Clause 15.7, and the imposition of administrative,
civil and criminal sanctions as prescribed in the IRR-A of R.A. 9184.
26
22.1. The BAC of the PROCURING ENTITY shall open Bid envelopes in
the presence of Bidders’ representatives who choose to attend, at the
time, on the date, and at the place specified in the BDS.
Representatives of the Bidders who are present shall sign a register
evidencing their attendance.
22.2 Letters of withdrawal shall be read out and recorded, and the envelope
containing the corresponding withdrawn Bid shall be returned to the
Bidder unopened. If the withdrawing Bidder’s representative is in
attendance the original Bid and all copies thereof shall be returned to
the representative during the Bid opening. If the representative is not in
attendance, the Bid shall be returned unopened by registered mail. The
Bidder may withdraw its Bid prior to the deadline for submission and
receipt of Bids, provided that the corresponding letter of withdrawal
contains a valid justification requesting for such withdrawal, subject to
appropriate administrative sanctions.
22.6 The BAC of the PROCURING ENTITY shall determine each Bidder’s
compliance with the documents required to be submitted for the
Technical Proposal of the Bid, as prescribed in ITB Clause 10.. For
this purpose, the BAC of the PROCURING ENTITY shall check the
submitted documents of each Bidder against a checklist of required
documents to ascertain if they are all present in the first (Technical)
envelope, using a non-discretionary “pass/fail” criteria, as stated in the
Invitation to Apply for Eligibility and to Bid and this ITB. If a Bidder
submits all required documents, it shall be rated “passed” for that
particular requirement. In this regard, failure to submit a requirement,
27
or an incomplete or patently insufficient submission, shall be
considered “failed” for the particular requirement concerned. In case
one or more of the above required documents in the first envelope of a
particular Bid is missing, incomplete, or patently insufficient, the BAC
of the PROCURING ENTITY shall rate the Bid concerned as “failed”
and immediately return to the Bidder concerned its second (Financial)
Bid envelope unopened.
28
24. Detailed Evaluation and Comparison of Bids
24.1. The PROCURING ENTITY will evaluate and compare, in detail, only
the Bids that are rated "passed" for both Technical and Financial
Proposals.
24.2 In evaluating the Bids to get the Lowest Calculated Bid,, the
PROCURING ENTITY shall undertake the following:
(b) The ranking of the total bid prices as so calculated from the lowest
to highest. The bid with the lowest price shall be identified as the
Lowest Calculated Bid.
24.3 To determine the Lowest Calculated Bid, the BAC shall use non-
discretionary criteria, as stated in the Invitation, which shall include a
consideration of the following:
(a) The bid must be complete. Bids not addressing or providing all of
the required items in the Bidding Documents including, where
applicable, bill of quantities, shall be considered non-responsive
and, thus, automatically disqualified. In this regard, where a
required item is provided, but no price is indicated, the same shall
be considered as non-responsive, but specifying a “0” (zero) for the
said item would mean that it is being offered for free to the
Government; and
24.4 The BAC shall evaluate all bids on an equal footing to ensure fair and
competitive bid evaluation. For this purpose, all bidders shall be
required to include the cost of all taxes, such as, but not limited to,
value added tax (VAT), income tax, local taxes, and other fiscal levies
and duties which shall be itemized in the bid form and reflected in the
detailed estimates. Such bids, including said taxes, shall be the basis
for bid evaluation and comparison.
(a) bid prices in figures and in words, the latter shall prevail;
(b) the unit rate and the line item total resulting from multiplying the
unit rate by the quantity, the unit rate as quoted will govern, unless
in the opinion of the PROCURING ENTITY there is an obviously
29
gross misplacement of the decimal point in the unit rate, in which
case the line item total as quoted will govern, and the unit rate will
be corrected.;
(c) the total Bid amount and the sum of total costs per item, the sum of
the total costs per item shall prevail and the total Bid amount will
be corrected;
(d) unit cost in the detailed estimate and unit cost in the bill of
quantities, the latter shall prevail.
24.6 Based on the detailed evaluation of bids, those that comply with the
above-mentioned requirements shall be ranked in the ascending order
of their total calculated bid prices, as evaluated and corrected for
computational errors, discounts and other modifications, to identify the
Lowest Calculated Bid. Total calculated bid prices, as evaluated and
corrected for computational errors, discounts and other modifications,
which exceed the approved budget for the contract shall not be
considered.
30
26. Post Qualification of the Lowest Calculated Bid
27.2 The PROCURING ENTITY reserves the right to reject any and all
bids, declare a failure of bidding, or not award the contract in the
following situations:
c) For any justifiable and reasonable ground where the award of the
contract will not redound to the benefit of the Government as
follows: (i) if the physical and economic conditions have
31
significantly changed so as to render the project no longer
economically, financially or technically feasible as determined by
the head of the procuring entity; (ii) if the project is no longer
necessary as determined by the head of the procuring entity; and
(iii) if the source of funds for the project has been withheld or
reduced through no fault of the PROCURING ENTITY.
32
30.1 Within ten (10) calendar days upon receipt of the Award, the successful
Bidder shall submit to the PROCURING ENTITY:
30.2 Within twenty (20) calendar days upon receipt from the successful
Bidder of the signed confirmation of the Award, the signed contract,
the required Performance security and all other documentary
requirements, the PROCURING ENTITY shall sign and approve the
contract.
(a) cash;
(b) a cashier’s or certified check;
(c) an irrevocable letter of credit;
(d) a bank guarantee;
(e) surety bond;
(f) foreign government guarantee; or
(g) other such form indicated in the BDS.
33
correspondent bank located in the country of the PROCURING ENTITY,
or (b) with the agreement of the PROCURING ENTITY directly by a
foreign bank acceptable to the PROCURING ENTITY.
34
Section III Bid Data Sheet
ITB Clause
Or
The Funding Source is the GOP, the GOP limits eligibility to the
following:
Or
Or
Or
36
described on Asian Development Bank’s web page www.adb.org
Or
3.4 If the Funding Source is ADB, JBIC or WB, all bidders shall
submit a written statement of compliance with this provision.
37
Or
5.1. If the Funding Source is the GOP and an eligibility check will take
place in advance of Bid opening state the following, amending the
BDS text at ITB Clause 10. accordingly:
If the funding source is not the GOP delete the above paragraph
and state the following, again amending the BDS text at ITB
Clause 10. accordingly:
38
5.1. State either, if the funding is GOP:
Or, if the funding is WB, ADB or JBIC, delete the above text and
state:
39
“passed” for all the eligibility requirements, it shall be considered
eligible and subject to further evaluation, and the BAC shall mark
the set of eligibility documents of the Bidder concerned as
“eligible.” If a Bidder is rated “failed” in any of the eligibility
requirements, it shall be considered ineligible to participate in the
bidding, and the BAC shall mark the set of eligibility documents
of the prospective Bidder concerned as “ineligible.” In either case,
the markings shall be countersigned by the BAC chairperson or
duly designated authority
The BAC shall inform an eligible Bidder that it has been found
eligible to participate in the bidding. The BAC shall inform an
ineligible Bidder that it has been found ineligible to participate in
the bidding, and the grounds for its ineligibility. Those found
ineligible have seven (7) calendar days upon written notice within
which to file a request for a reconsideration including supporting
information as necessary, with the BAC: The BAC shall decide on
the request for reconsideration within seven (7) calendar days
from receipt thereof. The BAC may request a Bidder to clarify its
eligibility documents if necessary.
In the event that a Bidder, at its own option, does not provide
either a credit line or cash deposit certificate in the amount of
40
[insert 10% of the ABC], the Bidder must provide a statement of
its NFCC. The NFCC is as follows:
If the funding is JBIC delete the above and retain the following:
In the event that a Bidder, at its own option, does not provide
either a credit line or cash deposit certificate in the amount of
[insert 10% of the ABC] the Bidder must provide a statement of its
NFCC. The NFCC is as follows:
41
successful experience as prime contractor in the construction of at
least one (1) work of a nature and complexity equivalent to the
Works in the last five (5) years (to comply with this requirement,
single works cited should be at least eighty percent (80%) of
value of estimated contract cost of Works under bid), such being
verifiable from completion certificates, and
Have an annual turnover from all works averaged over the last
three (3) years equal to one hundred percent (100%) of the
estimated value of the contract to be bid.
Note: If the ABC is less than 1 million pesos state that there will
be no Pre-Bid Conference.
42
11.1 (k) Technical Documents, Line of Credit
Or
None.
Or
None.
11.3 Select one, delete the other.
Or
Note: In a case to case basis, the World Bank may accept or reject
Financial Proposals in excess of the ABC provided that the
following conditions are met:
12.4. If the funding is GOP or in the case of non-GOP and of less than
one year’s duration state the following:
If the funding is not the GOP and the contract is of over one year’s
duration, insert the appropriate special condition of contract and
state the following:
For goods and services that will be supplied from outside of the
Philippines Bid prices for goods and services supplied from
outside of the Philippines shall be quoted in Philippine Pesos.
For goods and services that will be supplied from outside of the
Philippines Bid prices for goods and services supplied from
outside of the Philippines shall be quoted in United States Dollars.
44
Bids will be valid until [insert date].
If the Funding Source is the GOP, state nil for both categories. If
the Funding Source is not the GOP, propose and agree the rate
with the relevant Funding Source.
Select one of the following, deleting the others, note that the Bid
Security amount should always be fixed at 2.5% of the ABC other
than for the GOP:
The Funding Source is the GOP, the Bid Security shall be in the
following forms and amount:
Or
The Funding Source is the World Bank, the Bid security shall be
in the following amount [Insert 2.5% of ABC].
Or
Or
Insert date between sixty (60) and ninety (90) days from the date
set for Bid opening
15.7 (d) If the Funding Source is the GOP, leave clause unchanged and the
following shall be the additional grounds for forfeiture of the Bid
Security:
7. All other acts that tend to defeat the purpose of the competitive
bidding, such as an eligible contractor not buying bid documents,
and contractors habitually withdrawing from bidding or submitting
letters of non-participation for at least three (3) times within a
year, except for valid reasons.
46
If the funding source is the ADB, JBIC and WB, commissions or
gratuitous maybe allowed.
Insert identification/reference
Insert address
Insert address
If the Funding Source is the GOP retain the following deleting the
above:
Or
48
The Funding Source is the ADB, JBIC or WB. The Performance
Security shall be in the following amount [Insert amount].
49
Section IV. General Conditions of Contract
50
Table of Contents
1. Definitions...........................................................................51
2. Interpretation.......................................................................53
3. Language and Law.............................................................53
4. Communications.................................................................54
5. Possession of Site..............................................................54
6. The Contractors Obligations.............................................54
7. Performance Security........................................................55
8. Sub-Contracting..................................................................55
9. Liquidated Damages..........................................................56
10. Site Investigation Reports.................................................56
11. The PROCURING ENTITY, Licenses and Permits...........57
12. Contractor’s Risk................................................................57
13. PROCURING ENTITY’s Risk..............................................57
14. Insurance.............................................................................58
15. Default by Contractor.........................................................59
16. Default by PROCURING ENTITY.......................................59
17. Termination.........................................................................59
18. Force Majeure, Release From Performance....................61
19. Resolution of Disputes......................................................62
20. Suspension of Loan, Credit or Appropriation.................62
21. PROCURING ENTITY’s Engineer’s Decisions.................63
22. Queries About Special Conditions of Contract...............63
23. Approval of Drawings and Works by the PROCURING
ENTITY’s Engineer..............................................................63
24. Acceleration and Delays Ordered by the PROCURING
ENTITY’s Engineer..............................................................63
25. Extension of the Intended Completion Date....................64
26. Right to Vary.......................................................................64
27. Contractors Right to Claim................................................64
28. Dayworks.............................................................................64
29. Early Warning......................................................................65
30. Program...............................................................................65
31. Management Conferences.................................................66
32. Bill of Quantities.................................................................66
33. Changes in Quantities........................................................67
34. Instructions, Inspections and Audits...............................67
35. Identifying Defects.............................................................67
36. Cost of Repairs...................................................................68
37. Correction of Defects.........................................................68
38. Uncorrected Defects..........................................................68
51
39. Advance Payment...............................................................68
40. Progress Payments............................................................69
41. Payment Certificates..........................................................69
42. Retention.............................................................................70
43. Payments for Variations....................................................71
44. Compensation Events........................................................72
45. Contract Completion..........................................................72
46. Suspension of Work...........................................................73
47. Payment on Termination....................................................74
48. Extension of Contract Time...............................................74
49. Price Adjustment................................................................75
50. Completion..........................................................................76
51. Taking Over.........................................................................76
52. Operating and Maintenance Manuals...............................76
52
13.1
1. Definitions
1.1 Boldface type is used to identify defined terms.
1.3 Bill of Quantities means the priced and completed Bill of Quantities
forming part of the Bid.
1.4 The Contract is the Contract between the PROCURING ENTITY and
the Contractor to execute, complete, and maintain the Works. It
consists of the documents listed in GCC Sub-Clause 2..3 below.
1.5 The Contract Price is the price stated in the Letter of Acceptance and
thereafter as adjusted in accordance with the provisions of the
Contract.
1.6 Dayworks are varied work inputs subject to payment on a time basis
for the Contractor’s employees and Equipment, in addition to
payments for associated Materials and Plant.
1.10 The Contractor is a person or corporate body whose Bid to carry out
the Works has been accepted by the PROCURING ENTITY.
1.11 The PROCURING ENTITY is the party who employs the Contractor
to carry out the Works stated in the SCC.
1.13 The Procuring Entity’s Engineer is the person named in the SCC (or
any other competent person appointed by the PROCURING ENTITY
and notified to the Contractor, to act in replacement of the
53
PROCURING ENTITY’s Engineer) who is responsible for supervising
the execution of the Works and administering the Contract.
1.14 The Start Date is given in the SCC. It is the latest date when the
Contractor shall commence execution of the Works. It does not
necessarily coincide with any of the Site Possession Dates.
1.15 The Intended Completion Date is the date on which it is intended that
the Contractor shall complete the Works. The Intended Completion
Date is specified in the SCC. The Intended Completion Date may be
revised only by the PROCURING ENTITY’s Engineer by issuing an
extension of time or an acceleration order.
1.17 The Defects Liability Period is the period named in the SCC and
calculated from the Completion Date.
1.20 The Contract Price is the price stated in the Letter of Acceptance and
thereafter as adjusted in accordance with the provisions of the
Contract.
1.23 A Defect is any part of the Works not completed in accordance with
the Contract.
1.25 Plant is any integral part of the Works that shall have a mechanical,
electrical, chemical, or biological function.
1.27 Site Investigation Reports are those that were included in the Bidding
Documents and are factual and interpretative reports about the surface
and subsurface conditions at the Site.
54
1.28 Temporary Works are works designed, constructed, installed, and
removed by the Contractor that are needed for construction or
installation of the Works.
1.30 The Works are what the Contract requires the Contractor to construct,
install, and turn over to the PROCURING ENTITY, as defined in the
SCC.
2. Interpretation
2.1 In interpreting these Conditions of Contract, singular also means
plural, male also means female or neuter, and the other way around.
Headings have no significance. Words have their normal meaning
under the language of the Contract unless specifically defined. The
PROCURING ENTITY’s Engineer will provide instructions clarifying
queries about these Conditions of Contract.
(a) Agreement,
(b) Letter of Acceptance,
(c) Contractor’s Bid,
(d) Special Conditions of Contract,
(e) Conditions of Contract,
(f) Specifications,
(g) Drawings,
(h) Bill of Quantities, and
(i) Any other document listed in the SCC as forming part of the
Contract.
55
4. Communications
4.1 Communications between parties that are referred to in the Conditions
shall be effective only when in writing. A notice shall be effective
only when it is received by the concerned party.
5. Possession of Site
5.1 The PROCURING ENTITY shall give possession of all parts of the
Site to the Contractor. If possession of a part is not given by the date
stated in the SCC, the PROCURING ENTITY will be deemed to have
delayed the start of the relevant activities, and this will be a
Compensation Event.
5.2 The Contractor shall allow the PROCURING ENTITY’s Engineer and
any person authorized by the PROCURING ENTITY’s Engineer
access to the Site and to any place where work in connection with the
Contract is being carried out or is intended to be carried out.
6.2 The Contractor shall commence execution of the Works on the Start
Date and shall carry out the Works in accordance with the Program
submitted by the Contractor, as updated with the approval of the
PROCURING ENTITY’s Engineer, and complete them by the
Intended Completion Date.
6.3 The Contractor shall be responsible for the safety of all activities on
the Site.
6.4 The Contractor shall carry out all instructions of the PROCURING
ENTITY’s Engineer that comply with the applicable laws where the
Site is located.
6.5 The Contractor shall employ the key personnel named in the Schedule
of Key Personnel, as referred to in the SCC, to carry out the supervision
of the Works. The PROCURING ENTITY will approve any proposed
replacement of key personnel only if their relevant qualifications and
abilities are equal to or better than those of the personnel listed in the
Schedule.
56
6.6 If the PROCURING ENTITY’s Engineer asks the Contractor to
remove a person who is a member of the Contractor’s staff or work
force, stating the reasons, the Contractor shall ensure that the person
leaves the Site within seven days and has no further connection with
the work in the Contract.
6.8 The Contractor shall submit to the PROCURING ENTITY for consent
the name and particulars of the person authorized to receive instructions
on behalf of the Contractor.
6.9 The Contractor shall cooperate and share the Site with other
contractors, public authorities, utilities, and the PROCURING
ENTITY between the dates given in the Schedule of Other
Contractors, as referred to in the SCC. The Contractor shall also
provide facilities and services for them as described in the Schedule.
The PROCURING ENTITY may modify the Schedule of Other
Contractors, and shall notify the Contractor of any such modification.
7. Performance Security
7.1 The Performance Security shall be submitted to the PROCURING
ENTITY not later than the date specified in the Letter of Acceptance
and shall be issued in an amount and form as specified in the SCC, and
denominated in the currency in which the Contract Price is payable. The
Performance Security shall be valid for the period specified in the SCC.
7.2 The Contractor, by entering into the Contract with the PROCURING
ENTITY, acknowledges the right of the PROCURING ENTITY to
institute action pursuant to Republic Act 3688 against any subcontractor
be they an individual, firm, partnership, corporation or association
supplying the Contractor with labor, materials and/or equipment for the
performance of the Contract.
8. Sub-Contracting
8.1 The contractor cannot subcontract more than fifty percent (50%) of the
value of the works, unless otherwise indicated in the SCC. Moreover,
57
except if otherwise provided by the contract, it cannot subcontract any
part of the works without the prior consent of the head of the
PROCURING ENTITY. However, this consent does not relieve the
contractor of any liability or obligation under the contract. It will be
responsible for the acts, defaults and neglects of any subcontractor, his
agents, servants or workmen as fully as if these were its own acts,
defaults or neglects of the contractor, or those of its agents, servants or
workmen.
9. Liquidated Damages
9.1 The Contractor shall pay liquidated damages to the PROCURING
ENTITY at the rate per day stated in the SCC for each day that the
Completion Date is later than the Intended Completion Date. The total
amount of liquidated damages shall not exceed the amount defined in
the SCC. The PROCURING ENTITY may deduct liquidated damages
from payments due to the Contractor. Payment of liquidated damages
shall not affect the Contractor. Once the cumulative amount of
liquidated damages reaches ten percent (10%) of the amount of the
contract, the PROCURING ENTITY shall rescind the contract, without
prejudice to other courses of action and remedies open to it.
58
11. The PROCURING ENTITY, Licenses and Permits
11.1 The PROCURING ENTITY shall, if requested by the Contractor, assist
him in applying for permits, licenses or approvals, which are required for
the Works.
Form of Warranty
Minimum Amount in % of Total Contract Price
13.1 From the Start Date until the Certificate of Final Acceptance has been
issued, the following are risks of the PROCURING ENTITY:
59
(ii) negligence, breach of statutory duty, or interference
with any legal right by the PROCURING ENTITY or
by any person employed by or contracted to him except
the Contractor.
13.2 Insurance
14.1 The Contractor shall provide, in the joint names of the PROCURING
ENTITY and the Contractor, insurance cover from the Start Date to the
end of the Defects Liability Period, in the amounts and deductibles
stated in the SCC for the following events which are due to the
Contractor’s risks:
14.3 Alterations to the terms of an insurance shall not be made without the
approval of the PROCURING ENTITY’s Engineer.
14.4 Both parties shall comply with any conditions of the insurance
policies.
14.5 If the Contractor does not provide any of the policies and certificates
required, the PROCURING ENTITY may effect the insurance which
the Contractor should have provided and recover the premiums the
PROCURING ENTITY has paid from payments otherwise due to the
Contractor or, if no payment is due, the payment of the premiums shall
be a debt due.
60
13. Default by Contractor
15.1 If the Contractor abandons the Works, refuses or fails to comply with a
valid instruction of the PROCURING ENTITY or fails to proceed
expeditiously and without delay or is, despite a written complaint, in
breach of the Contract, the PROCURING ENTITY may give notice
referring to this Clause and stating the default.
15.2 If the Contractor has not taken all practicable steps to remedy the default
within fourteen (14) days after the Contractor's receipt of the
PROCURING ENTITY's notice, the PROCURING ENTITY may, by a
second notice given within a further twenty one (21) days, rescind the
Contract. The Contractor shall then demobilize from the Site leaving
behind Materials and Plant
15.3 All Materials on the Site, Plant, Equipment, Temporary Works, and
Works shall be deemed to be the property of the PROCURING ENTITY
if the Contract is rescinded because of the Contractor’s default.
16.2 If the default is not remedied within twenty eight (28) days after the
PROCURING ENTITY's receipt of the Contractor's notice, the
Contractor may, by a second notice given within a further twenty one
(21) days, terminate the Contract. The Contractor shall then demobilize
from the Site.
15. Termination
17.1 The PROCURING ENTITY or the Contractor may terminate the
Contract if the other party causes a fundamental breach of the Contract.
61
(b) the PROCURING ENTITY’s Engineer instructs the Contractor
to delay the progress of the Works, and the instruction is not
withdrawn within twenty eight (28) days;
(c) the PROCURING ENTITY or the Contractor is made bankrupt
or goes into liquidation other than for a reconstruction or
amalgamation. In the case of the Contractor's insolvency, any
Contractor's Equipment which the PROCURING ENTITY
instructs in the notice is to be used until the completion of the
Works.;
(d) a payment certified by the PROCURING ENTITY’s Engineer
is not paid by the PROCURING ENTITY to the Contractor
within eighty four (84) days from the date of the PROCURING
ENTITY’s Engineer’s certificate;
(e) the PROCURING ENTITY’s Engineer gives Notice that failure
to correct a particular Defect is a fundamental breach of
Contract and the Contractor fails to correct it within a
reasonable period of time determined by the PROCURING
ENTITY’s Engineer;
(f) the Contractor does not maintain a Security, which is required;
(g) the Contractor has delayed the completion of the Works by the
number of days for which the maximum amount of liquidated
damages can be paid, as defined in the SCC; and
(h) if the Contractor, in the judgment of the PROCURING
ENTITY has engaged in corrupt , coercive, collusive or
fraudulent practices in competing for or in executing the
Contract.
17.3 For the purpose of GCC Clause 17.2(h) corrupt and fraudulent
practices are defined as follows:
62
competitive levels and to deprive the borrower of the benefits
of free and open competition.
17.5 When either party to the Contract gives notice of a breach of Contract
to the PROCURING ENTITY’s Engineer for a cause other than those
listed under Clause 17.2 above, the PROCURING ENTITY’s Engineer
shall decide whether the breach is fundamental or not.
18.2 If the event continues for a period of eighty four (84) days, either Party
may then give notice of termination, which shall take effect twenty eight
(28) days after the giving of the notice.
63
(a) any sums to which the Contractor is entitled under GCC Clause
27.1.;
(b) the Cost of his suspension and demobilization;
(c) any sums to which the PROCURING ENTITY is entitled.
18.4 The net balance due shall be paid or repaid within twenty eight (28) days
of the notice of termination.
19.2 Any and all disputes arising from the implementation of a contract
covered by the Act and this IRR-A shall be submitted to arbitration in
the Philippines according to the provisions of Republic Act No. 876,
otherwise known as the "Arbitration Law": Provided, however, That,
disputes that are within the competence of the Construction Industry
Arbitration Commission to resolve shall be referred thereto. The
process of arbitration shall be incorporated as a provision in the
contract that will be executed pursuant to the provisions of the Act and
this IRR-A: Provided, further, That, by mutual agreement, the parties
may agree in writing to resort to other alternative modes of dispute
resolution.
20.1. In the event that the Funding Source suspends the Loan, Credit or
Appropriation to the PROCURING ENTITY, from which part of the
payments to the Contractor are being made:
64
18. PROCURING ENTITY’s Engineer’s Decisions
21.1 Except where otherwise specifically stated, the PROCURING
ENTITY’s Engineer will decide contractual matters between the
PROCURING ENTITY and the Contractor in the role representing the
PROCURING ENTITY.
21.2 The PROCURING ENTITY’s Engineer may delegate any of his duties
and responsibilities to other people, except to the Arbiter, after
notifying the Contractor, and may cancel any delegation after notifying
the Contractor.
23.3 The PROCURING ENTITY’s Engineer’s approval shall not alter the
Contractor’s responsibility for design of the Temporary Works.
23.4 The Contractor shall obtain approval of third parties to the design of
the Temporary Works, when required by the PROCURING ENTITY.
25. Dayworks
28.1 If applicable as indicated in the SCC, the Dayworks rates in the
Contractor’s Bid shall be used for small additional amounts of work
66
only when the PROCURING ENTITY’s Engineer has given written
instructions in advance for additional work to be paid for in that way.
28.3 The Contractor shall be paid for Dayworks subject to obtaining signed
Dayworks forms.
27. Program
30.1 Within the time stated in the SCC, the Contractor shall submit to the
PROCURING ENTITY’s Engineer for approval a Program showing
the general methods, arrangements, order, and timing for all the
activities in the Works.
67
certificate and continue to withhold this amount until the next payment
after the date on which the overdue Program has been submitted.
30.5 When the Program is updated, the Contractor shall provide the
PROCURING ENTITY’s Engineer with an updated cash flow
forecast. The cash flow forecast shall include different currencies, as
defined in the Contract, converted as necessary using the Contract
exchange rates.
32.2 The Bill of Quantities is used to calculate the Contract Price. The
Contractor is paid for the quantity of the work done at the rate in the
Bill of Quantities for each item.
68
30. Changes in Quantities
33.1 If the final quantity of the work done differs from the quantity in the
Bill of Quantities for the particular item by more than twenty five
percent (25%), provided the change exceeds one percent (1%) of the
Initial Contract Price, the PROCURING ENTITY’s Engineer shall
adjust the rate to allow for the change.
33.2 The PROCURING ENTITY’s Engineer shall not adjust rates from
changes in quantities if thereby the Initial Contract Price is exceeded
by more than fifteen percent (15%), except with the prior approval of
the PROCURING ENTITY.
34.3 The Contractor shall permit the Funding Source named in the SCC to
inspect the Contractor’s accounts and records relating to the
performance of the Contractor and to have them audited by auditors
appointed by the Funding Source, if so required by the Funding
Source.
69
33. Cost of Repairs
36.1. Loss or damage to the Works or Materials to be incorporated in the
Works between the Start Date and the end of the Defects Liability
Periods shall be remedied by the Contractor at the Contractor’s cost if
the loss or damage arises from the Contractor’s acts or omissions.
37.2 Every time notice of a Defect is given, the Contractor shall correct the
notified Defect within the length of time specified in the PROCURING
ENTITY’s Engineer’s notice.
37.3 The Contractor shall correct the Defects which he notices himself
before the end of the Defects Liability Period.
37.4 The PROCURING ENTITY shall certify that all Defects have been
corrected. If the PROCURING ENTITY considers that correction of a
Defect is not essential, he can request the Contractor to submit a
quotation for the corresponding reduction in the Contract Price. If the
PROCURING ENTITY accepts the quotation, the corresponding
change in the SCC is a Variation.
38.2 The use of a third party to correct defects that are uncorrected by the
Contractor will in no way relieve the Contractor of its liabilities and
warranties under the Contract.
70
advance payment to the contractor in an amount equal to fifteen
percent (15%) of the total contract price, to be made in lump sum or, at
the most two, installments according to a schedule specified in the
SCC.
39.2 The advance payment shall be made only upon the submission to and
acceptance by the PROCURING ENTITY of an irrevocable standby
letter of credit of equivalent value from a commercial bank, a bank
guarantee or a surety bond callable upon demand, issued by a surety or
insurance company duly licensed by the Insurance Commission and
confirmed by the PROCURING ENTITY.
39.4 The contractor may reduce his standby letter of credit or guarantee
instrument by the amounts refunded by the Monthly Certificates in the
advance payment.
40.3 Unless otherwise stated, all payments and deductions will be paid or
charged in the proportions of currencies comprising the Contract Price.
40.4 Items of the Works for which no rate or price has been entered in will
not be paid for by the PROCURING ENTITY and shall be deemed
covered by other rates and prices in the Contract.
71
38. Payment Certificates
41.1 The Contractor shall submit to the PROCURING ENTITY’s Engineer
monthly statements of the estimated value of the work executed less
the cumulative amount certified previously.
41.4 The value of work executed shall comprise the value of the quantities
of the items in the Bill of Quantities completed.
41.5 The value of work executed shall include the valuations of approved
Variations.
39. Retention
42.1 The PROCURING ENTITY shall retain from each payment due to the
Contractor the proportion and time period stated in the SCC.
The total "retention money" shall be due for release upon final
acceptance of the works. The contractor may, however, request the
substitution of the retention money for each progress billing with
irrevocable standby letters of credit of from a commercial bank, bank
guarantees or surety bonds callable on demand, of amounts equivalent
to the retention money substituted for and acceptable to Government,
provided that the project is on schedule and is satisfactorily
undertaken. Otherwise, the ten percent (10%) retention shall be made.
Said irrevocable standby letters of credit, bank guarantees and/or
surety bonds, to be posted in favor of the Government shall be valid for
a duration to be determined by the concerned implementing
office/agency or procuring entity and will answer for the purpose for
72
which the ten percent (10%) retention is intended, i.e., to cover
uncorrected discovered defects and third party liabilities.
43.4 Any cumulative Variation Order beyond ten percent (10%) shall be
subject of another contract to be bid out if the works are separable
from the original contract. In exceptional cases where it is urgently
necessary to complete the original scope of work, the head of the
procuring entity may authorize the variation order beyond ten percent
(10%) but not more than twenty percent (20%) subject to the
guidelines to be determined by the GPPB: Provided, however, That
appropriate sanctions shall be imposed on the designer, consultant or
official responsible for the original detailed engineering design which
failed to consider the Variation Order beyond ten percent (10%).
73
43.5 In claiming for any Variation Order, the contractor shall, within seven
(7) calendar days after such work has been commenced or after the
circumstances leading to such condition(s) leading to the extra cost,
and within twenty-eight (28) calendar days deliver a written
communication giving full and detailed particulars of any extra cost in
order that it may be investigated at that time. Failure to provide either
of such notices in the time stipulated shall constitute a waiver by the
contractor for any claim. The preparation and submission of Variation
Orders are as follows:
d. If, after review of the plans, quantities and estimated unit cost of the
items of work involved, the proper office of the procuring entity
empowered to review and evaluate Change Orders or Extra Work
Orders recommends approval thereof, the head of the procuring
entity or his duly authorized representative, believing the Change
Order or Extra Work Order to be in order, shall approve the same.
46.2 The contractor or its duly authorized representative shall have the right
to suspend work operation on any or all projects/activities along the
critical path of activities after fifteen (15) calendar days from date of
receipt of written notice from the contractor to the district
engineer/regional director/consultant or equivalent official, as the case
may be, due to the following:
75
d. There is failure on the part of the procuring entity to deliver
government-furnished materials and equipment as stipulated in the
contract.
47.3. The net balance due shall be paid or repaid within twenty eight (28) days
from the notice of termination.
47.4. If the Contractor has terminated the Contract under GCC Clauses 16.2,
17.5, or 18.1, the PROCURING ENTITY shall promptly return the
Performance Security to the Contractor.
48.2 No extension of contract time shall be granted the contractor due to (a)
ordinary unfavorable weather conditions and (b) inexcusable failure or
negligence of contractor to provide the required equipment, supplies or
materials.
48.3 Extension of contract time may be granted only when the affected
activities fall within the critical path of the PERT/CPM network.
48.4 No extension of contract time shall be granted when the reason given
to support the request for extension was already considered in the
determination of the original contract time during the conduct of
detailed engineering and in the preparation of the contract documents
as agreed upon by the parties before contract perfection.
77
and submitted to the procuring entity for consideration and the validity
of the performance security shall be correspondingly extended.
50. Completion
50.1 The Contractor shall request the PROCURING ENTITY’s Engineer to
issue a certificate of Completion of the Works, and the PROCURING
ENTITY’s Engineer will do so upon deciding that the work is
completed.
52.2. If the Contractor does not supply the Drawings and/or manuals by the
dates stated in the SCC, or they do not receive the PROCURING
ENTITY’s Engineer’s approval, the PROCURING ENTITY’s
Engineer shall withhold the amount stated in the SCC from payments
due to the Contractor.
78
Section V. Special Conditions of Contract
Similar to the BDS in Section III, the clauses in this Section V are intended to assist the
PROCURING ENTITY in providing contract-specific information in relation to
corresponding clauses in the GCC.
The provisions of Section V complement the GCC included in Section IV, specifying
contractual requirements linked to the special circumstances of the PROCURING
ENTITY, the PROCURING ENTITY’S country, the sector, and the Works procured. In
preparing Section V, the following aspects should be checked:
However, no special condition which defeats or negates the general intent and purpose of
the provisions of Section IV should be incorporated herein.
79
Special Conditions of Contract
GCC Clause
2.3(i) The other documents forming part of the Contract are list
documents or state “none”
= 1 + C + ( i x n)
WHERE:
82
specified contract time plus any time extension duly granted
to the contractor, the procuring entity concerned may rescind
the contract, forfeit the contractor's performance security and
takeover the prosecution of the project or award the same to
a qualified contractor through negotiated contract.
Or
10.1 The site investigation reports are: list here or state none
84
The allowable reimbursable expenditures are:
Or
85
39.1 The amount of the advance payment is [insert amount as
percentage of the Contract Price and schedule of payment]
86
(i) The advance payment is delayed.
(j) The effects on the Contractor of any of the
PROCURING ENTITY’s Risks.
(k) The PROCURING ENTITY’s Engineer unreasonably
delays issuing a Certificate of Completion.
(l) Other Compensation Events described in the Contract
or determined by the Procuring Entity’s Engineer shall
apply.
87
(coefficient B).
(b) For currency [type of currency]:
(i) [percent] percent non-adjustable element
(coefficient A).
(ii) [percent] percent adjustable element (coefficient B).
Contract prices are fixed prices and are not subject to price
adjustment except for extraordinary circumstances as
determined by NEDA and approved by GPPB.
88
Section VI Specifications
Notes on Specifications
Samples of specifications from previous similar projects are useful in this respect. The
use of metric units is mandatory. Most specifications are normally written specially by
the PROCURING ENTITY or its Engineer to suit the Contract Works at hand. There is
no standard set of Specifications for universal application in all sectors in all regions, but
there are established principles and practices, which are reflected in these SBD.
Care must be taken in drafting specifications to ensure that they are not restrictive. In the
specification of standards for goods, materials, and workmanship, recognized
international standards should be used as much as possible. Where other particular
standards are used, whether national standards or other standards, the specifications
should state that goods, materials, and workmanship that meet other authoritative
standards, and which ensure substantially equal or higher quality than the standards
mentioned, will also be acceptable. The following clause may be inserted in the Special
Conditions or Specifications.
Wherever reference is made in the Contract to specific standards and codes to be met by
the goods and materials to be furnished, and work performed or tested, the provisions of
the latest current edition or revision of the relevant standards and codes in effect shall
apply, unless otherwise expressly stated in the Contract. Where such standards and codes
89
are national, or relate to a particular country or region, other authoritative standards that
ensure a substantially equal or higher quality than the standards and codes specified will
be accepted subject to the PROCURING ENTITY’s Engineer’s prior review and written
consent. Differences between the standards specified and the proposed alternative
standards shall be fully described in writing by the Contractor and submitted to the
PROCURING ENTITY’s Engineer at least twenty eight (28) days prior to the date when
the Contractor desires the PROCURING ENTITY’s Engineer’s consent. In the event the
PROCURING ENTITY’s Engineer determines that such proposed deviations do not
ensure substantially equal or higher quality, the Contractor shall comply with the
standards specified in the documents.
These Notes for Preparing Specifications are intended only as information for the PROCURING ENTITY
or the person drafting the Bidding Documents. They should not be included in the final documents.
90
Section VII Drawings
Insert here a list of Drawings. The actual Drawings, including site plans, should be
attached to this section or annexed in a separate folder.
91
Section VIII Bill of Quantities
Objectives
The objectives of the Bill of Quantities are
In order to attain these objectives, Works should be itemized in the Bill of Quantities in
sufficient detail to distinguish between the different classes of Works, or between Works
of the same nature carried out in different locations or in other circumstances which may
give rise to different considerations of cost. Consistent with these requirements, the
layout and content of the Bill of Quantities should be as simple and brief as possible.
Daywork Schedule
A Daywork Schedule should be included only if the probability of unforeseen work,
outside the items included in the Bill of Quantities, is high. To facilitate checking by the
Entity of the realism of rates quoted by the Bidders, the Daywork Schedule should
normally comprise the following:
(a) A list of the various classes of labor, materials, and Constructional Plant for
which basic daywork rates or prices are to be inserted by the Bidder, together
with a statement of the conditions under which the Contractor will be paid for
work executed on a daywork basis.
(b) Nominal quantities for each item of Daywork, to be priced by each Bidder at
Daywork rates as Bid. The rate to be entered by the Bidder against each basic
Daywork item should include the Contractor’s profit, overheads, supervision,
and other charges.
Provisional Sums
A general provision for physical contingencies (quantity overruns) may be made by
including a provisional sum in the Summary Bill of Quantities. Similarly, a contingency
allowance for possible price increases should be provided as a provisional sum in the
Summary Bill of Quantities. The inclusion of such provisional sums often facilitates
budgetary approval by avoiding the need to request periodic supplementary approvals as
the future need arises. Where such provisional sums or contingency allowances are used,
the SCC should state the manner in which they will be used, and under whose authority
(usually the PROCURING ENTITY’s Engineer’s).
92
The estimated cost of specialized work to be carried out, or of special goods to be
supplied, by other contractors (refer to Clause 8. of the Conditions of Contract) should be
indicated in the relevant part of the Bill of Quantities as a particular provisional sum with
an appropriate brief description. A separate procurement procedure is normally carried
out by the PROCURING ENTITY to select such specialized contractors. To provide an
element of competition among the Bidders in respect of any facilities, amenities,
attendance, etc., to be provided by the successful Bidder as prime Contractor for the use
and convenience of the specialist contractors, each related provisional sum should be
followed by an item in the Bill of Quantities inviting the Bidder to quote a sum for such
amenities, facilities, attendance, etc.
These Notes for Preparing a Bill of Quantities are intended only as information for the PROCURING
ENTITY or the person drafting the Bidding Documents. They should not be included in the final
documents.
93
Section IX Forms and Qualification
Information
Table of Forms
Bid Form....................................................................................................93
Bid Security...............................................................................................95
Qualification Information.........................................................................97
Letter of Acceptance..............................................................................100
Form of Agreement................................................................................101
Performance Security (Bank Guarantee).............................................102
Bank Guarantee for Advance Payment................................................103
Affidavit of Disclosure of Relations.....................................................104
94
Bid Form
To:
Address:
(a) We have examined and have no reservation to the Bidding Documents, including
Addenda, for the Contract ___________(Name of
Contract)______________________;
(b) We offer to execute the Works for this Contract in accordance with the Bid and
Bid Data Sheet, General and Special Conditions of Contract accompanying this
Bid;
(c) The total price of our Bid, excluding any discounts offered in item (d) below is:
;
(d) The discounts offered and the methodology for their application are:
(f) If our Bid is accepted, we commit to obtain a Performance Security in the amount
of _______percent of the Contract Price for the due performance of the Contract;
(g) Our firm, including any subcontractors or suppliers for any part of the Contract,
have nationalities from the following eligible countries
__________________________;
(h) We are not participating, as Bidders, in more than one Bid in this bidding process,
other than alternative offers in accordance with the Bidding Documents;
(i) Our firm, its affiliates or subsidiaries, including any subcontractors or suppliers
for any part of the Contract, has not been declared ineligible by the Funding
Source;
(j) We understand that this Bid, together with your written acceptance thereof
included in your notification of award, shall constitute a binding contract between
us, until a formal Contract is prepared and executed; and
95
(k) We understand that you are not bound to accept the Lowest Evaluated Bid or any
other Bid that you may receive.
Name
In the capacity of
Signed
Date
96
Bid Security
Date: ________________________
Contract No.: _____________________
To: _____________________________________________________________________
Whereas
___________________________________________________________________
(hereinafter “the Bidder”) has submitted its Bid dated _____________________ for
the construction of _________(Name of
Contract)_____________________________________
__________________________________________________________________her
einafter called “the Bid.”
1. If the Bidder withdraws its Bid during the period of Bid validity specified by
the Bidder in the Bid Form; or
2. If the Bidder, having been notified of the acceptance of its Bid by the Entity,
during the period of Bid validity, fails or refuses to:
(a) execute the Contract; or
(b) furnish the Performance Security, in accordance with the ITB Clause 31;
or
(c) accept the correction of its Bid by the Entity.
We undertake to pay the Entity up to the above amount upon receipt of its first written
demand, without the Entity having to substantiate its demand, provided that in its
97
demand the Entity states that the amount claimed by it is due to it, owing to the
occurrence of one or more of the above conditions, specifying the occurred
conditions.
This security shall remain in force up to and including twenty-eight (28) days after the
period of Bid validity, and any demand in respect thereof should be received by the
Bank not later than the above date.
Name
In the capacity of
Signed
Date
98
Qualification Information
Notes:
The information to be filled in by Bidders in the following pages will be used for purposes
of qualification as provided for in Clause 5 of the Instructions to Bidders. This information
will not be incorporated in the Contract. Attach additional pages as necessary.
1.2* Total annual volume of construction work performed in the past five years, in
the currency specified in the Bid and Contract Data Sheet.
1.3 Work performed as prime contractor on works of a similar nature and volume
over the last ten years. Proof of completion, e.g. Certificate of Completion
signed by the Employer or Owner, shall be submitted. Also list details of work
under way or committed, including expected completion date.
99
1.4 Major items of contractor’s Equipment proposed for carrying out the Works.
List all information requested below.
1.
2.
1.6* Financial statements for the last five years. Attach audited financial statements.
1.
2.
3.
1.8 ..Name, address, and telephone, and facsimile numbers of banks that may provide
references if contacted by the Entity.
1.9 Proposed Program (work method and schedule). Attach descriptions, drawings
and charts, as necessary, to comply with the requirements of the Bidding
Documents.
100
Section of the Value of subcontract Subcontractor Experience in
Works (Name and address) similar work
2. Joint Ventures*
2.1 The information listed in 1.1 - 1.9 above shall be provided for each partner of
the joint venture.
2.2 Attach the power of attorney of the signatory(ies) of the Bid authorizing
signature of the Bid on behalf of the joint venture.
2.3 Attach the Agreement among all partners of the joint venture (and which is
legally binding on all partners), which shows that:
(a) all partners shall be jointly and severally liable for the execution of the
Contract in accordance with the Contract terms;
(c) the execution of the entire Contract, including payment, shall be done
exclusively with the partner in charge.
101
Letter of Acceptance
[Letterhead of the Entity]
Date: ____________
This is to notify you that your Bid dated for execution of the ___[name
of Contract and identification number as given in the Instructions to Bidders]] ___ for
the Contract Price of [insert amount in specified currency]_____ , as corrected
and or modified1 if applicable, in accordance with the Instructions to Bidders is hereby
accepted by our Agency.
You are hereby instructed to come to our office ____[Office address]____ to sign the
formal agreement on __[date]___ at __[time]__.
Authorized Signature:
Name:
Designation:
Whereas, the Entity is desirous that the Contractor execute [name and identification
number of contract] (hereinafter called “the Works”) and the Entity has accepted the
Bid for _ [insert the amount in specified currency in numbers and words] by the
contractor for the execution and completion of such Works and the remedying of any
defects therein.
1. In this Agreement, words and expressions shall have the same meanings as are
respectively assigned to them in the Conditions of Contract hereinafter referred
to, and they shall be deemed to form and be read and construed as part of this
Agreement.
In Witness whereof the parties thereto have caused this Agreement to be executed the
day and year first before written.
[Addendum showing the corrections, if any, made during the Bid evaluation should be
attached with this agreement]
103
Performance Security (Bank Guarantee)
Whereas [name and address of contractor] (hereinafter called “the contractor”) has
undertaken, in pursuance of Contract No. [number] dated [date] to execute [name of
Contract and brief description of Works] (hereinafter called “the Contract”);
And whereas it has been stipulated by you in the said Contract that the contractor
shall furnish you with a Bank Guarantee by a recognized bank for the sum specified
therein as security for compliance with his obligations in accordance with the
Contract;
And whereas we have agreed to give the contractor such a Bank Guarantee;
Now therefore we hereby affirm that we are the Guarantor and responsible to you, on
behalf of the contractor, up to a total of [amount of Guarantee] [amount in words]1
such sum being payable in the types and proportions of currencies in which the
Contract Price is payable, and we undertake to pay you, upon your first written
demand and without cavil or argument, any sum or sums within the limits of [amount
of Guarantee] as aforesaid without your needing to prove or to show grounds or
reasons for your demand for the sum specified therein.
We hereby waive the necessity of demand of the said debt from the contractor before
presenting us with the demand.
This Guarantee shall be valid until a date twenty eight (28) days from the date of issue
of the Certificate of Completion.
1 An amount is to be inserted by the Guarantor, representing the percentage of the Contract Price
specified in the Contract, and denominated in the specified currency.
104
Bank Guarantee for Advance Payment
Gentlemen:
This Guarantee shall remain valid and in full effect from the date of the advance
payment under the Contract until [name of PROCURING ENTITY] receives full
repayment of the same amount from the contractor.
Yours truly,
Address:
1 An amount is to be inserted by the Bank or Financial Institution representing the amount of the
Advance Payment, and denominated in the specified currency of the Advance Payment as specified in
the Contract.
2 An amount is to be inserted by the Bank or Financial Institution representing the amount of the
Advance Payment, and denominated in the specified currency of the Advance Payment as specified in
the Contract.
105
Date
WHEREAS [name of the Bidder] is an established and reputable Contractor for [name
and/or description of the works] do hereby solemnly swear that:
We understand and accept that any false statement in this respect will render [name of
the Bidder], and its authorized officers liable for prosecution to the full extent of the
law.
Signed by
________________________________
As authorized official of the Bidder
Witnessed by my hand and Notarial Seal on the date and place first mentioned.
106