You are on page 1of 6

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/239818010

Jubarte Field-Development Strategy

Article · April 2007


DOI: 10.4043/19088-MS

CITATIONS READS

2 1,704

7 authors, including:

Iubatan Pinto Roberto Adelar Bonora Vieira


Wirtschaftsuniversität Wien Petróleo Brasileiro S.A.
5 PUBLICATIONS   16 CITATIONS    2 PUBLICATIONS   3 CITATIONS   

SEE PROFILE SEE PROFILE

All content following this page was uploaded by Iubatan Pinto on 06 March 2017.

The user has requested enhancement of the downloaded file.


OTC 19088-PP

JUBARTE FIELD – DEVELOPMENT STRATEGY


Bento Daher Junior, Cezar Augusto Monteiro Siqueira, Ivan do Nascimento, Iubatan Antonino Pinto, Jackson Burjack
Farias, Roberto Adelar Bonora Vieira / PETROBRAS E&P, Roberto de Oliveira Goulart / PETROBRAS R&D Center.
Copyright 2007, Offshore Technology Conference
The technological solution for assure the oil quality is
This paper was prepared for presentation at the 2007 Offshore Technology Conference held in discussed.
Houston, Texas, U.S.A., 30 April–3 May 2007.
This paper describes in details the technology gaps
This paper was selected for presentation by an OTC Program Committee following review of
information contained in an abstract submitted by the author(s). Contents of the paper, as
identified and the solutions on the works for making this
presented, have not been reviewed by the Offshore Technology Conference and are subject to heavy oil production system, in deep to ultra-deep water, a
correction by the author(s). The material, as presented, does not necessarily reflect any
position of the Offshore Technology Conference, its officers, or members. Papers presented at successful business.
OTC are subject to publication review by Sponsor Society Committees of the Offshore
Technology Conference. Electronic reproduction, distribution, or storage of any part of this
paper for commercial purposes without the written consent of the Offshore Technology Introduction
Conference is prohibited. Permission to reproduce in print is restricted to an abstract of not
more than 300 words; illustrations may not be copied. The abstract must contain conspicuous
acknowledgment of where and by whom the paper was presented. Write Librarian, OTC, P.O.
Box 833836, Richardson, TX 75083-3836, U.S.A., fax 01-972-952-9435.
The Jubarte Oil Field, discovered in January 2001, is
approximately located 80 km off the Espírito Santo State
coast, southeastern Brazil (Figure 1), under water depths
Abstract
between 1,000 and 1,500 m.
The Jubarte Field, off the Espirito Santo State coast, Brazil, is
an offshore heavy oil deepwater field that poses several
challenges. It was discovered in January, 2001 in about 1,300
m (4,400 ft) water depths and its reserves mount to 700
million barrels of 17 API oil.
Before its commercial production, several questions were
not answered yet such as the well productivity, the best
artificial lift method and the recommended production
strategy. In order to fully understand and implement a solid
definitive production system, Petrobras has decided to develop
the field step-wise, starting from a two-month extended well
test, then a Pilot Production phase, followed by two
development phases, named Phase I and Phase II.
The Phase I system includes the FPSO P-34, which plant
was adapted to produce 60,000 bpd of heavy oil in deep
waters, and four horizontal production wells. In this phase,
PETROBRAS is piloting several new technologies, regarding
artificial lift, to be used in the final Phase II development and
other PETROBRAS demands. High power downhole ESP
installed through horizontal wet X-tree and seabed installed
ESP systems are among the major innovations.
The FPSO P-34 has a site where the PETROBRAS
Research Center – CENPES - will test new technologies of
heavy oil and water separation.
Phase I started production in 2006 4th quarter and it is Figure 1 – Jubarte Oil Field location map.
expected to provide rich information regarding aquifer
strength that will optimize the water injection system of Phase The Jubarte field contains 17.1° API oil, which dead oil
II. viscosity at 20°C is about 3,000 cP, being the most viscous oil
For Phase II, in addition to the technologies tested in Phase at surface conditions ever produced in Brazil through a wet
I, other innovations are anticipated, for the processing plant of completion system. Such fluid characteristics and the
the 180,000 bopd FPSO, specifically designed for heavy oil expressive discovered volumes in this area were considered as
production. Phase II first oil is expected in 2011. a big challenge and an opportunity to develop knowledge to
The process plant solution is presented considering free exploit heavy offshore oil reservoirs in deep waters under
water knockout separator, oil stabilization on the oil economical basis. Thus, several questions should be addressed
dehydrator, the FPSO arrangement and main utilized facilities. such as the well productivity, the best artificial lift method and
2 OTC 18708

the aquifer strength. In order to answer the main questions, energy flows close to source areas or long-distance confined
PETROBRAS has decided to start an Extended Well Test, gravity flows with high capacity of sediment transportation.
beginning in October 2002. The excellent well productivity Based in composition, texture, sedimentary structure and
results, 16,500 bpd by natural flow, made PETROBRAS issue geometry, the flows have been interpreted as high-density
the declaration of commerciality of Jubarte Field in December hiperpicnal flows, whereby texturally and compositionally
2002 and the phased-approach Field Development Plan as immature sediments were transferred from shallow water into
follows: deep-water settings by high-density, highly concentrated and
• Production Pilot - DP FPSO Seillean; tractive gravity flows (quasisteady currents). Catastrophic
• Phase I - Early Production System - FPSO P-34; floods probably triggered major gravity flow events allowing
• Phase II – Definitive Production System - FPSO P-57. highland rivers to deliver large amounts of sediments directly
The Pilot phase started in December 2002 and finished 3 to coastal areas. A general overview of the Jubarte reservoir
years later, while the Phase I started in December 2006 and is showing exploratory wells is presented on Figure 3.
predicted to finish in 2011.
The Phase II is planned to start production in 2011. More
details can be obtained from Table 1 below.

Table 1 - Production phases of the Jubarte Field


EWT Pilot Phase I Phase II
Production Unit FPSO FPSO
P-34 P-57
Seillean Seillean
Oil/Liquid
18.5 / 180 /
Processing 22 / 22 60 / 60
18.5 300
Capacity (kbpd)
Gas Compression
3 - - - 3
(MM m /d)
Water Injection
- - - 310 Figure 3 - General overview of the Jubarte reservoir.
(kbpd)
Producers 1 1 4 15
Pilot Phase
Production Peak 16.5 22.7 51 180
(kbpd) (2002) (2003) (2007) (2012)
At the beginning of this phase (December 2002) the ESP was
Gas Production
0.14 0.14 0.34 1.7
turned on and the well rate raised from 16,500 bpd to 20,000
3
Peak (MM m /d) bpd, limited by the plant processing capacity. In April 2003
some adjustments were made in the processing plant, reaching
Reservoir characterization and modeling the oil rate peak of 22,700 bpd.
Table 2 shows the main information gathered from
Jubarte reservoir is constituted by arkosic sandstones and EWT/Pilot and Table 3 the information gathered and with
conglomerates deposited in the Maastrichtian age and later future updates expected during Phase I.
inverted due to the role of halokinesis (Fig. 2). They are
constituted of poorly sorted and loosely packed sediments Table 2 – Information gathered from EWT/Pilot
presenting angular to sub-angular grains.
Information How

Vertical permeability DST and EWT (re)interpretations

Oil/Water contact confirmation Apparaisal and Pilot wells drilling

GOR evaluation Production data

Reservoir temperature PDG/TPT data

Oil/water separation and oil


Laboratory tests
treatment
Figure 2 – E-W cross section showing geometry of the Jubarte
Maastrichtian reservoirs.

As interpreted from cores, these reservoirs depict


amalgamated cycles with scoured bases suggesting either high
OTC 18708 3

Table 3 – Information gathered from EWT/Pilot with future updates Table 4 – Expected information from Phase I
expected
Information How
Information How
Pressure and production data
Aquifer Strength
History Match
Vertical permeability History Match

PI evolution and skin values Pressure and production data


Oil - Water relative permeability Water cut history match along the production History Match

Original Oil in place Material balance Oil/water separation and oil


FPSO plant tests
treatment

Pressure and production data


Faults characteristics High power ESP Performance and Production data
History Match

Pressure and production data


Flow vertical barriers
Seismic interpretation
In Phase I, PDG pressure was measured before production
Emulsion multiphase flow Production data start up. This information is very important to match the
performance Flow correlations matching
aquifer volume modeled in 3D geological model and its action
during the production stop the end of the Pilot Phase and the
ESP above Xtree performance Production data beginning of Phase I (almost 1 year time). The conclusion is
that the aquifer strength has a very similar behavior as was
predicted by simulation model (Figure 4). Another conclusion
Regarding reservoir aspects, it is possible to conclude that, is that the forecasted Productivity Index (PI) was confirmed by
in these production test period, the amount of information the Phase I first well.
gathered is very important for the field development History Match - Phase 1 well start up
optimization.
285 200
One of these important information is the aquifer strength. 270 Static Pressure 180
EWT/Pilot production data showed a big water volume 160

PI [m3/d/kgf/cm2]
255
Pwf [kgf/cm2]

140
connected to the oil zone but it was not possible to model the 240
120
225
aquifer strength itself, what should be known during Phase I. 210
100
Forecasted PI 80
195 60
Jubarte Phase I 180 40
165 20
150 0
In order to answer remaining questions from EWT/Pilot
/1 0 6

/1 0 6

/2 0 6

/2 0 6

/2 0 6

/2 0 6

/2 0 6

/2 06

/2 06

/2 06

/2 06

/2 0 6

/3 0 6

/3 0 6

1/ 006

1/ 007

1/ 007
07
Phase, Phase I was implemented, with production starting in
12 /20
12 /20

12 /20

12 /20

12 /20

12 /20

12 /20

12 20

12 /20

12 /20

12 /20

12 /20

12 20
12 /20

20
2

2
4/

9/

1/

1/

2/

3/
17

0
/
12

December 2006.
Time [day]
The FPSO P-34, which has been used by PETROBRAS as P PDG Simulated P PDG Measuerd PI [m3/d/kgf/cm2]
a pilot unit in several fields, was fully modified to process Figure 4 –Production x Simulated data
60,000 bpd of 17° API oil during Phase I. It was also modified
to operate at a 1,350 m water depth. The main impact of this result is the water injection design
The expected information from Phase I regarding in Phase II. It is important to state that the design of P-57 has
reservoir, artificial lift method and production operation are already been concluded, considering information from
presented in Table 4. EWT/Pilot Phase, regarding water injection flow rate. In case
of new information arises from Phase I, it will be used in order
to optimize the Phase II water injection system, mainly the
number of injection wells.
Phase I considers no injection wells and four production
wells, with different artificial lift methods and well layouts, as
shown in Figure 5.
4 OTC 18708

running ESP. The electric cable was designed to address the


requirements of high power ESP and long tieback wells.
Regarding flow assurance, transient numerical simulations
showed that thermal insulation of the flowlines is enough to
avoid wax deposition and blockage for hydrate due to the
characteristics of the Jubarte oil.
During EWT, it was observed a high degree of barium and
strontium sulfate precipitation in the ESP impellers. In Phase
I, different inhibitors will be tested to reduce this problem,
especially in the wells with ESP.

Figure 5 – Phase I Schematics

Free area was saved and tie-ins were installed on the P-34
process plant to allow the test of compact 3-phase separators
from different manufactures through R&D projects
coordinated by PETROBRAS Research Center (CENPES).
This phase is expected to last four years, with a very important
task: to gather valuable information for developing the Phase
Figure 6 – Satellite well and the pumping module installed on the
II. sea bed.

Well Engineering Challenges Phase II – Definitive Development


Well engineers faced two main challenges in order to drill A comprehensive technical and economical feasibility study
Phase I wells, one of them related to drill and install the 1200 was conducted by the project team from mid 2003 to early
HP ESP inside the wellbore. The other refers to install the 2005 in order to pick the best development concept for Phase
sand control system in a horizontal extended well, in a low II. A broad range of technical alternatives were analyzed,
fracture gradient formation. covering the various disciplines: type and size of floating
production unit (FPSO, TLP, TLWP), wet or dry completion,
Flow Assurance and Artificial Lift Devices artificial lift method, rigid or flexible flowlines and risers etc.
The low API and high viscosity oil (which, combined with
One of the most important technologies tested in Phase I is the low temperatures, imposes huge challenges to flow assurance),
use of ESP located on the sea bed. the high water production rates and the lack of pre-existing
For this project, PETROBRAS worked with service infrastructure (both on and offshore) were the main drivers
companies to design and build basically a submarine module taken into account during the concept selection study.
(capsule) and base which is installed in an auxiliary well in the The selected development concept (Figure 7) was a
Jubarte field, at 1,400 m water depth. It was designed to work 180,000 bopd FPSO, named P-57, with large liquid handling
with a 33 m long ESP. This pumping module, applied for one capacity (300,000 blpd) and gas compression capacity up to 3
of the production wells, allows to by-pass the ESP when using million std m³/d. It will be connected to 15 horizontal
gas-lift as the artificial lift method in case of ESP failure. The production wells and 7 horizontal water injection wells
ESP is located 200 m from the production well (Figure 6). through 6" flexible risers and flowlines. The average length of
This distance was adopted considering safety aspects. The the horizontal section will be 1,000 m for producer and
next step of this concept, which will be used in Phase II, injector wells, completed with open hole gravel packing.
considers the ESP replacement and installation performed by
special boat instead of by rig.
For another well, the pump will be located inside the
wellbore. Both pumps power is 1,200 HP and 4.5 KV motors
will be used to drive them. The other two wells use gas lift as
the artificial lift method.
A new umbilical system was also developed and qualified,
integrating the power cable and the electro-hydraulic functions
to reduce installation costs. This new cable is used in the wells
OTC 18708 5

Jubarte’s pipeline end manifold (PLEM) are Cachalote, Baleia


Franca and Baleia Anã.
Most Phase II systems are currently under final front end
engineering and design or tender. Major contracts are expected
to be awarded by mid 2007 and its first oil is planned for 2011.

Conclusions

Jubarte Field presents one of the largest PETROBRAS


reserves, but the oil characteristics, the water depths and the
lack of local infrastructure require a special approach to
reduce technical and economical risks on both execution and
operation phases of the Definitive Production System.
The strategy was to split the Field Development Plan into
three production phases, the Production Pilot, Phase I, the
Early Production System, and Phase II, the Definitive
Figure 7 – Jubarte Field Phase II Project Schematics.
Production System. The first two phases gathered important
information to Phase II optimization.
Artificial lift will be provided by high power 1,500 hp ESP During EWT and Pilot Phase, results confirmed the high
installed on the sea bed, 200 m from the X-tree. This design well Productivity Index, the problems related to foam, the
concept allows lower workover costs in case of ESP failure, calibration of multiphase flow correlation and the possibility
since all the job is performed without well intervention, saving of using the ESP outside the well.
rig time. As mentioned before, it is being studied the Phase I is now under operation and brings important
possibility of using special boats for ESP replacement, instead information to the next phase like the aquifer strength, the
of the usual expensive drilling rigs. This technology will be reservoir data that could not be obtained during the EWT and
extensively tested during Phase I. Gas lift will be used as Pilot Phase and the test of new technologies to be applied in
contingency. For this purpose, all production wells will be Phase II.
equipped with gas lift valve, but the compression capacity at Another important result of Phase I is the revenue
the FPSO is designed to supply lift-gas to 5 wells operating anticipation, improving the project NPV using an existing
simultaneously in the beginning of Phase II. Extra lift-gas production unit from the PETROBRAS fleet, the P-34.
capacity will be obtained when exported gas volumes
decrease. Acknowledgments
The oil will be offloaded from the FPSO to shuttle tankers.
The gas will be used as the main energy source for equipments The authors would like to thank PETROBRAS for the
and the exceeding volumes will be exported to the onshore permission to publish this paper. Special thanks to our
treatment facility (a dew point adjustment and condensate colleagues from Petrobras E&P Headquarters (E&P-ENGP),
separation plant) through a 80 km, 12" rigid pipeline. Petrobras Research & Development Center (CENPES),
The spread moored FPSO P-57 will have the largest liquid Petrobras E&P Espírito Santo Business Unit (UN-ES) and
handling capacity in PETROBRAS fleet. Its process plant will Petrobras E&P Services Unit (E&P-SERV).
handle 300,000 blpd and 180,000 bopd, split into 2 separation
trains, using free water knockout separators. This large water
handling capacity is one of the key features to improve the References
production profile of this deep water heavy oil project. The
free water knockout separators will allow energy savings since Bezerra, M. F. C. et al: The Appraisal and Development
free water is separated before entering the heating system. Oil Plan for the Heavy Oil Jubarte Field, Deepwater Campos
will be stabilized on the dehydrator unit. The FPSO oil storage Basin, Brazil, OTC (2004).
capacity is 1,800,000 barrels. Goulart, R O. et al: Jubarte Field Development
The project concept considers the reservoir pressure will Architecture, Brazil, DOT (2004).
be maintained by water injection. Produced water will be
treated and then re-injected. In case re-injection is temporally
not possible, up to 3 storage tanks can be used to help treating
the produced water prior to its discharge in the sea. Sea water
will also be used for injection, after sulphate removal. If Phase
I results confirm the aquifer strength, the injection system will
be optimized by evaluating the reduction of the number of
injection wells and the flow rate of sea water.
Phase II gas export pipeline and onshore facility capacities
were designed to be shared with other fields in the Campos
Basin northern area, improving their economical
attractiveness. Among the fields that will be connected to the

View publication stats

You might also like